United Nations Development Programme
Country: Philippines
PROJECT DOCUMENT
Project Title: PHILIPPINES: CLIMATE CHANGE CAPACITY BUILDING PROJECT IN THE
FRAMEWORK OF THE LOW-EMISSION CAPACITY BUILDING PROGRAMME
UNDAF Outcome(s): Area 4 – Resilience towards Disasters and Climate change
UNDP Strategic Plan Environment and Sustainable Development Primary Outcome:
Catalyzing environmental finance
UNDP Strategic Plan Secondary Outcome: Climate Change Adaptation
Expected CP Outcome(s): Adaptive capacities of vulnerable communities and ecosystems are
strengthened to be resilient to threats, shocks, disasters and climate change.
Expected CPAP Output (s): Increased capacities of key duty-bearers and claim-holders to lead
and support a sustainable national anticipatory climate change adaptation process.
Executing Partner: United Nations Development Programme - Philippines
Implementing Partner: Climate Change Commission – Philippines
3
Table of Contents
Subject Page
1. Situation Analysis 5
2. Strategy 6
3. Project Results Framework 9
4. Total Budget and Work Plan 12
5. Management Arrangements 15
6. Monitoring and Evaluation Framework 23
7. Legal Context 29
Appendix A: Technical components of the project proposal 31
Appendix B: Terms of Reference 39
Appendix C: Endorsement letter 51
4
Acronyms
ALU Agriculture and Land Use
AWP Annual Work Plan
ASoG Ateneo School of Government
BAS Bureau of Agricultural Statistics
BAR Bureau of Agriculture Research
CAI-Asia Clean Air Initiatives for Asian Cities
CCC Climate Change Commission
CDR Combined Delivery Report
CI Conservation International -Philippines
CPD Country Programme Document
DA Department of Agriculture
DOE Department of Energy
DENR - EMB Department of Environment and Natural Resources– Environment Management
Bureau
DILG Department of the Interior Local Government
DTI-BOI Department of Trade and Industry/Board of investments
DOTC Department of Transportation and Communication
EU European Union
FR Financial Report
FMB Forest Management Bureau
FACE Funding Authorization and Certificate of Expenditures
GSC Global Support Component
GoP Government of the Philippines
GHG Greenhouse gas
IP Implementing Partner
INC Initial National Communication
ICRAF – UPLB International Center for Research in Agroforestry / University of the Philippines –
Los Baños
LGUs Local government units
LEDS Low-emission development strategies
LULUCF Land Use, Land Use Change and Forestry
MO Manila Observatory
MRV Measurable, Reportable and Verifiable
MOU Memorandum of Understanding
M&E Monitoring and evaluation
NCCAP National Climate Change Action Plan
NCs National Communications
NEDA National Economic and Development Authority
NSWMC National Solid Waste Management Commission
NSC National Steering Committee
NAMAs Nationally Appropriate Mitigation Actions
NGO Non-governmental organization
PAGASA Philippine Atmospheric, Geophysical and Astronomical Services Administration
PBE Philippine Business for the Environment
PCCI Philippine Chamber of Commerce and Industry
PCAARRD –
DOST
Philippine Council for Agriculture, Aquatic and Natural Resources Research and
Development– Department of Science and Technology
PMCJ Philippine Movement for Climate Justice
PEI Preferred Energy Incorporated
5
PTFCC Presidential Task Force on Climate Change
PAC Project Advisory Committee
PCR Project Completion Report
PFP Project Focal Point
PMS Project Management and Secretariat
PM Project Manager
PRF Project Results Framework
QA/QC quality assurance/quality control
REAP Renewable Energy Association of the Philippines
SEA GHG Regional Capacity Building Project for Sustainable National GHG Inventory
Management Systems in Southeast Asia
SNC Second National Communication
SIBAT Sibol ng Agham at Teknolohiya– Wellspring of Science and Technology
TO Technical Officer
TWGs Technical Working Groups
CO The UNDP Country Office
UNDAF United Nations Development Assistance Framework
UNDP United Nations Development Programme
UNFCCC United Nations Framework on Climate Change Convention
USAID United States Agency for International Development
CTS UP National Center for Transport Studies
EC-LEDS USAID Programme on Enhancing Capacity for Low emission Development
Strategies
WWF World Wildlife Fund -Philippines
6
PHILIPPINES: CLIMATE CHANGE CAPACITY BUILDING PROJECT
IN THE FRAMEWORK OF THE LOW-EMISSION CAPACITY BUILDING PROGRAMME
1. SITUATION ANALYSIS
The Philippines has already been experiencing the ever-increasing impacts of climate change, which
have affected directly development strategies at the national and local levels. As in many affected
countries, the need to understand and manage a tremendous amount of related technical information
and at the same time to bring various stakeholders together to address climate change concerns
coherently becomes a big challenge in the midst of scarce resources.
In 2009, the Climate Change Commission (CCC) was established with the enactment of the Republic
Act 9729 known as the Climate Change Act. Among its powers and functions include recommendation
of legislations, policies and strategies on climate change adaptation and mitigation as well as oversee
the dissemination of information on climate change-related issues. Furthermore, the Commission is
also mandated to formulate strategies on mitigating greenhouse gases and other anthropogenic
causes of climate change.
As a Party to the United Nations Framework Convention on Climate Change (UNFCCC), the Philippines
has prepared two national communications, which included the GHG National Inventories. For the
Initial National Communication, submitted to the UNFCCC in 2000, the Philippines reported its national
GHG emissions, with 1994 as its base year. The Philippines is set to submit its Second National
Communication (SNC) containing the national GHG inventory for 2000. Despite the fact that the
Philippines is not a major emitter, it acknowledges the importance of accounting for its GHG emissions
as one possible strategy for achieving sustainable development. The SNC saw the need to
institutionalize the GHG inventory process in relevant government agencies. GHG inventory
institutionalization is a critical component to help the Philippines be in a position to conduct the
inventory on a regular basis. This activity would not just help the Philippines fulfill its obligations to
the UNFCCC but also enable the country to transition towards a more climate-friendly development
path by providing a good basis for formulating mitigation strategies. Initial attempt at mitigation
analysis was included in the SNC but data included was limited. There is therefore a need to come up
with a more comprehensive mitigation analysis.
The Philippine National Framework Strategy on Climate Change (2010 – 2022) articulates the national
commitment and highlights the clean development path for the country and the mutually beneficial
relationship between climate change mitigation and adaptation, where mitigation is seen as a function
of adaptation. A National Climate Change Action Plan has been issued by the Climate Change
Commission in compliance with Republic Act No. 9729 or the Climate Change Act of 2009 and its
Implementing Rules and Regulations and with international commitments. As stated in the UNDAF
2012 – 2018, the UN will collaborate with the Climate Change Commission (CCC), Local government
units (LGUs) and vulnerable communities in climate proofing (i.e. integrating climate change
adaptation activities) national, regional and local plans, planning and programming guidelines, and
regulatory processes; the development and testing of climate and impact monitoring systems at all
levels; the development and testing of competency development programs for agencies, communities
and other key stakeholders; and the development or strengthening of knowledge management and
technical support systems.
In the Philippines, there is an increasing awareness and resolve to take action and cooperation on the
parts of the Public Sector and Industry. However, the capacity for systematic reporting of greenhouse
gas (GHG) emissions needs further strengthening. Likewise, the country also faces some concerns in
defining Nationally Appropriate Mitigation Actions (NAMAs) and designing low-emission development
strategies (LEDS), as well as the associated Measurable, Reportable and Verifiable (MRV) systems.
7
Industry’s participation in adopting mitigation actions, particularly in carbon-intensive sectors, plays a
crucial role and is slowly gaining ground.
The Low Emission Capacity Building Project (or also referred herein as the LECB Project) will be
implemented under UNDP rules and procedures. The Philippines is among the 15 phase 1 countries to
be provided support for their national efforts to integrate climate change into strategies and plans and
ensure appropriate linkages between policy making and options for financing. UNDP works with
national governments while collaborating with other UN agencies in order to help UN Country Teams
and governments integrate climate risk into the formulation and implementation of key UN
cooperation frameworks such as the United Nations Development Assistance Framework (UNDAF).
The LECB Project will act as a liaison between Industry and the Public Sector to achieve this
cooperation.
Responding to climate change and achieving low-carbon growth and development will be a major
challenge for a developing country, requiring significant action and cooperation from both the public
and industrial sectors. Industry‘s enormous role in meeting this challenge consists of spearheading the
investment and technological innovation that will underpin low-carbon growth, of providing financing
for mitigation and adaptation, of adopting low-carbon production processes, and of encouraging and
facilitating more climate-conscious purchasing decisions by consumers. Nevertheless, reporting tools
and technical expertise must be made available.
As stated in the Country Programme Document (CPD) 2012-2016, the overall approach will be to
strengthen capacities of the local government and communities including climate change adaptation
(which includes mitigation as an adaptive approach) while ensuring that human rights and gender are
integrated into local policies, processes, programs and budgets.
The Climate Change Commission (CCC), by virtue of Climate Change Act of 2009 and the attendant
National Climate Change Action Plan (NCCAP) adopted by the GoP, provides the policy, institutional
and legal frameworks for the climate change agenda for the country. In the institutional mapping
exercise conducted, six sectors have been identified that need climate change capacity building as
described above, namely: energy, transport, agriculture, industry, forestry/land use, and waste
management. Currently, the CCC is engaged in proposing one (1) project and implementing two (2)
endeavors related to mitigation issues such as GHG inventory, LEDS and MRV. The proposed project is
the subject of this Proposal Document. The first ongoing project is the Regional Capacity Building
Project for Sustainable GHG Inventory Management Systems in Southeast Asia (SEA GHG) Phase II.
This project is in collaboration with the UNFCCC and the US Government where they provide only
technical assistance or advice in developing a sustainable inventory management system. Training for
the Agriculture and Land Use Greenhouse Gas Inventory (ALU) software is conducted focusing on the
Agriculture and Land Use, Land Use Change and Forestry (LULUCF) sectors. The second ongoing
endeavor is the Enhancing Capacity for Low Emission Development Strategies (EC-LEDS) Project. A
Memorandum of Understanding was signed between Climate Change Commission (CCC) and the
United States Agency for International Development (USAID). This activity focuses primarily on GHG
Inventory, among other topics.
As decided in the consultation meetings, the LECB Project will focus on four sectors: transport,
agriculture, waste, and industry, while the other two sectors (energy and forestry/land use) will be
given attention also through the United States Agency for International Development (USAID) program
on Enhancing Capacity for Low Emission Development Strategies (EC-LEDS). The SEA GHG Phase II
project will assist the CCC in completing a template for the institutional arrangements, QA/QC and
archiving as well as provide technical assistance in using the ALU software for the agriculture and
forestry/land use sectors. The CCC will oversee all the sectors under its national mandate and
program to ensure the complementation of projects. Under the LECB Project, the Philippines will focus
on Area 1: Public Sector capacity building on national GHG inventory systems, MRV, NAMAs and LEDS.
8
The Global Support Unit of the overarching LECB Programme will help the Philippines – among other
participating countries – build the needed capacities. The Philippine participation in the LECB
Programme therefore provides very important synergistic opportunities for the country with its other
related ongoing and planned initiatives in the environmental, political, and institutional aspects.
2. STRATEGY
The Philippine project rationale is consistent with the LECB Programme rationale that countries need
support in terms of providing technical expertise and assistance in developing capacity of the Public
Sector (since the Philippines is a participant to Area 1 of the LECB Programme). Capacity development
is central to the country’s efforts to tackle climate change. This includes increasing institutional
capacities to provide appropriate mechanisms of support and coordination when addressing climate
risks. It includes strengthening technical knowledge in order to better understand and make use of
climate information, and increasing relevant data and access to data for planning and decision-making.
In these areas, the LECB Programme can play an important role in helping the Philippines understand
how to take climate change into account more effectively when developing planning strategies and
designing and implementing policies.
The project strategy is also in line with the LECB Programme strategy to support the formulation and
implementation of smaller, more specific projects at the national level in each country through the
Programme’s Global Support Component (GSC). Thus, this Project Document includes details of the
expected outcomes and activities, which are planned to take place under the Philippine individual
national project according to the country’s needs and priorities, with technical support foreseen from
the overall programme.
As part of the Programme’s inception phase, and as guided by the GSC, the Philippines carried out
stocktaking exercise and stakeholder consultations for the design of its national project. This included
an assessment of needs as part of the stocktaking exercise, which included gap identification based on
desk research, stakeholders consultation and the experiences in the initial and second National
Communications as well as results from related complementary initiatives, actions and programs. The
stocktaking has identified the needed scope and nature of the country’s project proposal and the
potential synergies with ongoing projects and/or policy matters which is incorporated in this project
document that will have to be reviewed by the National Steering Committee. This process ensures that
this project complies with UNDP processes and is aligned with the interests and needs identified at the
country level considering the country’s available resources, capacities and interests. As appropriate,
this project shall include cross-cutting practices such as gender, poverty reduction and capacity
development and shall link with the UNDAF focus for the Philippines, as maybe appropriate.
The guiding strategy therefore is for UNDP to ensure the necessary linkages of this national project
with the UNDAF in close coordination with the GoP more specifically by:
• Understanding both the beneficial and detrimental linkages between climate change and
development;
• Using this knowledge to strengthen the national development framework and UNDAF
priorities;
• Addressing climate change related risks and opportunities as early as possible in UN-supported
programmes and projects; and
• Tracking progress towards achievement of UNDAF outcomes, including their contribution to
climate resilience and low-carbon development at the national level.
This Project Document includes the proposed activities within the Programme’s Area 1: Public Sector
capacity building on national inventory systems, and MRV, NAMAs and LEDS in four identified sectors
9
of the country: Transport, Agriculture, Waste and Industry, as a result of the stocktaking exercise and
context assessment for the Philippines. In the process of project development and a series of
stakeholder consultations, country ownership has been achieved to ensure that this project is aligned
with the political and institutional mandates in climate change. As such, the project’s activities and
outcomes have been designed to likewise ensure sustainability and replicability beyond the
programme’s four-year term.
The design of the Project Document is guided by existing policies of the government on mitigation.
The project is consistent with the goal of the Philippines’ National Climate Change Action Plan to “build
the adaptive capacities of women and men in their communities, increase the resilience of vulnerable
sectors and natural ecosystems to climate change, and optimize mitigation opportunities towards
gender-responsive and rights-based sustainable development”.
Furthermore, the project document builds on the identified gaps and needs of key undertakings such
as Second National Communications, among others. Initial work on the identification of key
institutions for the national GHG inventory was done and there is a need to review the institutional
structure and identify mechanisms to address sectoral needs. A more comprehensive study for
identifying and prioritizing mitigation options and design a system for reporting and archiving data are
also seen as important activities.
It will be important to have effective coordination mechanisms and synergistic approaches between
the LECB project and other similar and complementary initiatives, such as EC LEDS and SEA GHG
(Phase II), through regular meetings among the respective project working groups in the planned
dialogue platforms. Additionally, close coordination among the UNDP, USAID and other partners will
be undertaken particularly on the NAMA expectations in the course of project implementation. This
coordination will ensure that a coherence framework or methodological approach to develop the
NAMAs is used across the sectors covered under the two initiatives.
As part of Philippine participation in Area 1: Public Sector Capacity Building on GHG Inventory systems,
NAMAs, LEDS, and MRV in the designated four sectors composed of the Transport, Agriculture, Waste
and Industry sectors, the following are the expected outcomes from which the project objectives are
directed to and as described and outlined in Appendix A:
� Outcome 1: Robust national system for preparation of GHG emission inventories have been
established at a national level
� Outcome 2: NAMAs and 4 sectoral road maps have been formulated within the context of
national development priorities
� Outcome 3: MRV systems have been designed to support implementation and evaluation of
NAMAs and LEDS/sectoral road maps
3. It is very important to note that while this project focuses on the Public Sector in general, its
project activities and outputs will involve participation to some extent of the private sector as well.
To have a flexibility that will ensure that, where feasible, the country will have and can benefit
from this capacity-building support to the fullest extent. Furthermore, potential linkages and
synergies between the Public and Private sectors will identify opportunities for public-private
partnerships to address key climate change priorities under the project in a coordinated manner.
In this context, the country will be able to identify the most suitable options to engage the private
sector in the formulation and implementation of the project and its activities. For this project, and
consistent with Area 1 focus, the Public sector can play a key role in the design of policies,
regulations and incentives to facilitate the active engagement of the private sector in efforts to
address climate change concerns. On the other hand, the private sector can identify and
implement concrete actions on the ground, at the sectoral or industrial level, to reduce GHG
emissions while ensuring linkages with development needs and economic growth.
10
4. PROJECT RESULTS FRAMEWORK
This project will contribute to achieving the following Country Programme Outcome as defined in CPAP or CPD: Adaptive capacities of vulnerable communities and ecosystems are
strengthened to be resilient to threats, shocks, disasters and climate change
Country Programme Outcome Indicators: Number of mechanisms, tools, systems and procedures on Environment and natural Resources, sustainable energy development and use,
climate change adaptation and environment risk management
Primary applicable Key Environment and Sustainable Development Key Result Area: Catalyzing environmental finance
Indicator Baseline Targets
End of Project Source of verification
Project Objective1: Public
Sector Capacity Building
on GHG Inventory
systems, NAMAs,
LEDS/sectoral road maps,
and MRV
• Preparation and submission of
NAMAs and LEDS/sectoral road
maps to the Climate Change
Commission
• Mitigation measures limited to
general description under the Initial
(1994) and Second (2000) National
Communications.
• Limited strategies for low carbon
growth
• NAMAs prepared by 2014
• Sectoral road maps prepared by
2014
• Final reports and findings adopted
by the relevant institutions
• Reports on NAMAs/sectoral
road maps produced
• Reports on Systems and
processes established
Outcome 12
Robust national system for
preparation of GHG
emission inventories have
been established at a
national level
• Number of training and
seminar/workshops conducted in
developing and in introducing the
national GHG inventory system
and the participants role in its
implementation
• Number of participants applying
the training on the national GHG
inventory system in its actual
implementation
• Limited; only during the conduct of
NCs
• Archived/documented
systematically
• Based on the training needs
assessment done
• 85%
• Training reports
• Post-training evaluation and
assessment report by
Training Specialist
1 Objective (Atlas output) monitored quarterly ERBM 2 All outcomes monitored bimonthly and quarterly.
11
Indicator Baseline Targets
End of Project Source of verification
• Rules of procedure established
(e.g., for documentation,
archiving, and spreadsheet
management/data sharing)
• QA/QC and maintenance strategy
developed
• None or partial rules of procedure
documented
• No systematic QA/QC and
maintenance
• Rules of procedure detailed as
part of a GHG inventory manual
(incl. timelines, budget, system
sustainability, etc.) by end of Yr 1
• QA/QC strategy and maintenance
system documented and adopted
by Q3 Yr 3
• Manual of procedures
• Memorandum on the
adoption of the QA/QC
strategy and maintenance
system
• Key institutional collaboration
arrangements codified
• Institutional collaboration on ad hoc
basis
• MOUs prepared with key
institutional partners by Q4 Y3
• Signed MOUs
• Continuous data measurement
and analysis system established
• Inventory improvement strategy
prepared
• Data collected on an ad hoc basis
when the National Communications
were compiled
• No strategy in place
• Data measurement and analysis is
institutionalized by Q3 Yr 3 to
generate reports on periodic basis
• Strategy approved by end of Yr 3 ,
along with decision on yearly
periodic updates
• External expert review
• Project documentation
Outcome 2
NAMAs and 4 sectoral
road maps have been
formulated within the
context of national
development priorities
• Number of training and
seminar/workshops conducted
based on training needs
assessment done on the
understanding of the coordination,
planning, design, implementation,
and evaluation of NAMAs and
LEDS sectoral road maps and the
participants role in its
implementation starting Q2 Yr1
• Limited; only during the conduct of
NCs
• Based on the training needs
assessment done
• Training reports
• Percentage of participants
applying the training on the
understanding of the coordination,
planning, design, implementation,
and evaluation of NAMAs and
sectoral road maps
• No data • 85% • Post-training evaluation and
assessment report by
Training Specialist
• NAMAs and roadmaps formulated
for 4 sectors at the national level
• None • NAMAs and roadmaps formulated
for 4 sectors at the national level
by Q1 Year 2
• Project documentation on
roadmaps
• NAMA concepts
• Number of specific mitigation
options identified and prioritized
• None • Mitigation options identified and
prioritized specific for the
• Project documentation on
identification and
12
Indicator Baseline Targets
End of Project Source of verification
for the selected industry groups
(e.g. metals, cement, etc.)
industry groups prioritization of specific
mitigation options.
• NAMAs identified and prioritized
for the Transport, Agriculture,
Waste and Industry Sectors by Q1
Yr 3; 4 sectoral road maps
prepared
• Mitigation measures limited to
general description under the Initial
(1994) and Second (2000) National
Communications
• NAMAs identified and prioritized
for the Transport, Agriculture,
Waste and Industry Sectors by Q1
Yr 3; 4 sectoral road maps
prepared
• Project documentation on
NAMAs identified and
prioritized
• NAMAs and LEDS/sectoral policy
instruments, technology options,
and funding strategies Identified
and established
• Limited strategies for low carbon
growth
• NAMAs and LEDS/sectoral policy
instruments, technology options,
and funding strategies Identified
and established Q3 of Yr 3
• Project documentation on
NAMAs and LEDS/sectoral
policy instruments,
technology options, and
funding strategies
• Policy-ready and investment-
ready portfolio containing NAMAs
and sectoral road maps
• . None
• Policy-ready and investment-
ready portfolio containing NAMAs
and sectoral road maps that are
adopted by NSC and endorsed to
the financial sector for future
implementation by Q3 Yr 3.
Portfolio document on
NAMAs/sectoral road maps
produced and endorsed by
the NSC to the Banking and
financial Sector
Outcome 3
MRV systems have been
designed to support
implementation and
evaluation of NAMAs and
LEDS
• Number of training and
seminar/workshops conducted on
MRV tools for NAMAs and
LEDS/sectoral road maps
• Limited; only during the conduct of
NCs
• Based on the training needs
assessment done
• Training reports
• Number of government officials
and local personnel trained
• Percentage of participants
applying the training on MRV tools
for NAMAs and sectoral road maps
• No data • 85% • Post-training evaluation and
assessment report by
Training Specialist
• MRV system designed and
approved for plant level mitigation
measures prioritized for selected
industry groups (e.g. metals,
cement, etc.)
• None • MRV design approved by the NSC
and endorsed for consideration of
the CCC by Q2 Yr 2
• Design documentation
• MRV system designed and
approved by the NSC and
endorsed for consideration of the
CCC
• None or partially developed in the 4
selected sectors
• MRV design approved by the NSC
and endorsed for consideration of
the CCC by Q2 Yr 2
• Design documentation
13
Indicator Baseline Targets
End of Project Source of verification
• National technology system
developed and applied by CCC
• No information system that could
directly support NAMAs and LEDs
implementation
• National technology system
developed and applied by CCC by
Q1 Yr 3
• Project documentation and
manual of operation on
information systems,
databases and
inventory/data gathering
processes established
• Monitoring reports produced
14
5. TOTAL BUDGET AND WORK PLAN
Award ID: 00061970 Project ID: 00079132
Award Title:
Project Title: Low Emission Capacity Building Programme
Business Unit: PHL10
Project Title: LECB Programme Country Name: Philippines
PIMS No: 4807
Implementing Partner (Executing Agency): Climate Change Commission
Outcome/Atlas
Activity
Responsible
Party/
Implementing
Agent
Fund ID Donor
Name
Atlas
Budgetary
Account
Code
ATLAS Budget Description
Amount
Year 1
(USD)
Amount
Year 2
(USD)
Amount
Year 3
(USD)
Total (USD)
1. OUTCOME 1:
Robust national
systems for
preparation of GHG
emission
inventories have
been established at
a national level.
UNDP
Philippines/
Climate
Change
Commission
30079
EU,
German
Govt and
Australian
Govt
71300 Local Consultants 17,455 17,455 17,455 52,365
71400 Contractual services - Individual 17,727 17,727 17,727 53,181
71600 Travel 8,591 8,591 8,591 25,773
72100 Contractual services -
Companies - 8,500 - 8,500
72400 Communications 2,727 2,727 2,727 8,181
74500 Miscellaneous Expenses 1,364 1,364 1,364 4,092
75700 Learning Cost 25,455 25,455 25,455 76,365
Total Outcome 1 73,319 81,819 73,319 228,457
OUTCOME 2:
NAMAs and LEDS
have been
formulated in the
context of national
UNDP
Philippines/
Climate
Change
Commission
30079
EU,
German
Govt and
Australian
Govt
71400 Contractual services - Individual 18,818 18,818 18,818 56,454
71600 Travel 8,527 8,527 9,727 26,781
72100 Contractual services -
Companies 44,000 44,000 88,000
15
Outcome/Atlas
Activity
Responsible
Party/
Implementing
Agent
Fund ID Donor
Name
Atlas
Budgetary
Account
Code
ATLAS Budget Description
Amount
Year 1
(USD)
Amount
Year 2
(USD)
Amount
Year 3
(USD)
Total (USD)
development
priorities 72400 Communications 1,818 2,727 1,818 6,363
75700 Learning Cost 8,182 27,273 26,364 61,819
Total Outcome 2 81,345 101,345 56,727 239,417
OUTCOME 3: MRV
systems to support
implementation
and evaluation of
NAMAs and LEDS
have been
developed
UNDP
Philippines/
Climate
Change
Commission
30079
EU,
German
Govt and
Australian
Govt
71300 Local Consultants 21,455 21,455 21,455 64,365
71400 Contractual services - Individual 18,818 18,818 18,818 56,454
71600 Travel 9,346 9,618 4,945 23,909
72205 Information Technology
Equipment 9,000 - - 9,000
72400 Communications 1,818 1,818 1,818 5,454
75700 Learning Cost 3,635 3,635 3,636 10,906
Total Outcome 3 64,072 55,344 50,672 170,088
Project
Management,
including
Monitoring and
evaluation
UNDP
Philippines/
Climate
Change
Commission
30079
EU,
German
Govt and
Australian
Govt
71400 Contractual services - Individual 15,364 15,364 15,364 46,092
71600 Travel 1,160 1,136 1,136 3,432
72100 Contractual services -
Companies - 15,909 17,500 33,409
72200 Equipment and furniture 5,000 2,000 1,000 8,000
72205 Information Technology
Equipment 4,000 500 500 5,000
72505 Offices Supplies 2,854 2,364 2,364 7,582
72400 Communications 682 682 682 2,046
16
Outcome/Atlas
Activity
Responsible
Party/
Implementing
Agent
Fund ID Donor
Name
Atlas
Budgetary
Account
Code
ATLAS Budget Description
Amount
Year 1
(USD)
Amount
Year 2
(USD)
Amount
Year 3
(USD)
Total (USD)
75700 Learning Cost 4,205 1,136 1,136 6,477
Total Project Management 33,265 39,091 39,682 112,038
PROJECT TOTAL 252,001 277,599 220,400 750,000
UNDP General Management Support (GMS) 7% Fee 52,500
GRAND TOTAL 802,500
17
WORKPLAN
Year 1 (2012) Year 2 (2013) Year 3 (2014)
Outcomes/Activities Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Implementation arrangements and project inception
1. Finalization of the Project Document
2. Approval of the Project Document
3. Project Inception Workshop
4. Finalization of Project Implementation and Institutional Arrangements and M&E Plan
5. Project Staffing and Operational Procedures
Outcome 1: Robust national systems for preparation of GHG emission inventories have been established starting with the Transport, Agriculture, Waste and Industry Sectors
1.1 Build capacity for national systems for the preparation of GHG national inventory system
1.2 Design and establish national systems for the preparation of GHG inventories and necessary
sustained maintenance
1.3 Establish institutional frameworks and coordination mechanisms that ensure periodic GHG
inventory updates
1.4 Institutionalize mechanisms at the national and institutional levels to link GHG Inventories to
MRV-related activities for long term sustainability
Outcome 2: NAMAs and sectoral road maps have been formulated within the context of national development priorities as applied to the Transport, Agriculture, Waste and
Industry Sectors
2.1 Build capacity to coordinate, plan, design, and implement mitigation actions/sectoral road maps
2.2 Identify and prioritise mitigation actions in key sector
2.3 Identify policy, financing, and technology instruments to implement mitigation actions and
sectoral road maps
2.4 Establish and facilitate dialogue platforms for mitigation actions and sectoral road maps
Outcome 3: MRV systems have been designed to support implementation and evaluation of NAMAs and sectoral road maps as applied to the Transport, Agriculture, Waste and
Industry Sectors
3.1 Build capacity in MRV-related activities in order that high government officials can support
mitigation actions and sectoral road maps
3.2 Design a MRV system to support the implementation of mitigation actions and sectoral road
maps and revisit system
3.3 Develop national technology systems for information and monitoring
Project Management, including M&E
1.Establish the Project Management and Secretariat
2. Regular Implementation/Periodic Monitoring
18
6. MANAGEMENT ARRANGEMENTS
The National Project Management arrangement is characterized as a multilateral system, comprised
of the designated government institution at a lateral level with the UNDP Country Office on a
nationally-executed scheme. While this project focuses on the Agriculture, Transport, Waste, and
Industry sectors, it also primarily aligns itself with the National Climate Change Action Plan (NCCAP)
which covers all the sectors under all programs and projects of the Government of the Philippines
(GoP) on climate change through the Climate Change Commission. This project management
arrangement therefore pertains to this LECB Project only and the scope it has on climate change
mitigation.
The management/organizational structure that define the implementing arrangements among the
project participants through the Project Management and Secretariat and the Technical Working
Groups is shown in Fig. 1 below.
Figure 1: Management Arrangements for Implementing the Project
Implementing Partner
The designated government institution and lead implementing partner is the Climate Change
Commission (CCC). Being the Implementing Partner (IP), the CCC is fully responsible and accountable
for managing the project and ensuring the on-the-ground implementation of the project, the
achievement of the expected project outcomes and outputs and the effective use of the project
resources. The IP chairs the project National Steering Committee (NSC). Specifically, the IP shall
prepare the Annual Work Plan (AWP) for the approval of the National Steering Committee; review
and sign the Combined Delivery Report (CDR) at the end of the year; and sign the Financial Report
(FR) or the Funding Authorization and Certificate of Expenditures (FACE). The IP works closely with
Climate Change Commission
(Implementing Partner)
UNDP Philippines CO
National Steering Committee
Management Structure for Implementing the
Climate Change Capacity Building Project: Philippines
TWG 1 GHG Emission
Inventories
TWG 2 NAMAs and LEDS
TWG 3 MRV Systems
Project Management and Secretariat
19
the UNDP Country Office (CO) in defining, assessing and monitoring program outputs and
achievements towards desired development outcomes. The project relies on strong collaboration
among the participating Philippine government departments and agencies and other stakeholders
for which the CCC is at the vantage point as it is also administratively under the GoP Office of the
President. A high-level official of CCC is appointed as the Project Focal Point (PFP), thus ensuring
country ownership and the effective and efficient steering of the project towards outcomes and
outputs that are of relevance and interest to the Philippines.
UNDP Country Office
The UNDP CO (through the Country Director or designated UNDP staff) is responsible for the
successful execution of program outcomes and monitoring of interdependencies between projects
and managing changes within and among projects. At the same time, UNDP CO co-chairs the NSC.
While project assurance is the responsibility of each NSC member, the UNDP assumes the overall
project assurance role in support of the NSC by carrying out objective and independent project
oversight and monitoring functions, and ensures that appropriate project management milestones
are managed and completed.
National Steering Committee
The NSC acts as the Project Board and provides the overall guidance and direction in implementing
the project with the full cooperation of all the NSC members from relevant main government and
sectoral counterparts. It is responsible for making consensus management decisions for the project.
It is consulted by the Project Management and Secretariat (PMS) for decisions when project
management tolerances (normally in terms of time and budget) have been exceeded.
Based on the approved Annual Work Plan (AWP), the NSC will meet quarterly with one meeting
dedicated for an Annual Review to review and approve project annual and quarterly plans when
required and authorizes any major deviation from these agreed quarterly plans. It is the authority
that signs off the completion of each quarterly plan as well as authorizes the start of the next
quarterly plan. These meetings should take place in person and thorough minutes must be kept.
Follow-up actions will be identified and concrete recommendations made on how to address
specific issues that may arise during the implementation of the project.
The NSC is composed of the following members to be represented by designated key officials:
Chair: Climate Change Commission
Vice Chair: UNDP Philippine Country Office
Members:
- Department of Transportation and Communication (DOTC)
- Department of Energy (DOE)
- Department of Trade and Industry (DTI)
- Department of Agriculture (DA)
- Department of Environment and Natural Resources (DENR)
- National Economic and Development Authority (NEDA)
- National Solid Waste Management Commission (NSWMC).
- Representative from the Private Sector
- Representative from the Academe
- Representative from the Civil Society
- Relevant Bilateral Donors
20
Project Management and Secretariat
The Project Management and Secretariat (PMS) group is headed by the designated Project Focal
Point (PFP) from CCC who acts as the overall Project Manager (PM). The PM is assisted by a
Technical Officer, a Project Assistant and an Admin Officer to be hired by the project. The NSC
provides guidance whenever required by the PFP and the Technical Officer.
The PM has the authority to run the project on a day-to-day basis on behalf of the IP and the NSC
within the policies and guidelines set by the NSC. The PM will facilitate the hiring of a team of
consultants to help in delivering the Project Outputs. Experts on training and capacity development,
greenhouse gas (GHG) inventory, NAMAs/LEDS, MRV systems, information technology, promotion
and knowledge management, M&E and audit will comprise the team of consultants.
The PMS will provide technical coordination of the three technical working groups in their respective
areas and in the cross-cutting activities, operating concerns and secretariat services for the project.
Technical Working Groups
There will be three Technical Working Groups (TWGs) that will be organized to assist the IP firm up
the methodologies, framework and strategies to be delivered under the Project. The TWGs will be
the technical arms of the Project. They will be tapped to ensure technical soundness and logical
consistency of outputs with current policies and programs on climate change mitigation for the
country in the three key result areas of the project:
1. Technical Working Group 1: GHG Emission Inventories
2. Technical Working Group 2: NAMAs and LEDS
3. Technical Working Group 3: MRV Systems
The TWGs will be composed of technical experts from key institutions and stakeholders of the
project as identified during the project development to be assisted by the consultants to be hired
through the project.
Stakeholder Consultations
In the course of project development there were several stakeholder consultations conducted
including the following for the purpose of identifying relevant stakeholders for the project
development, and subsequently, for the project implementation:
− At the initiation of the stocktaking work, a meeting was held on October 4, 2011 among the
UNDP Country Office in Manila, Climate Change Commission and the Project Development
Consultant in order to plan for the conduct of the preparatory work for the Project
Document;
− A Focused Group Discussion was held on October 7, 2011 in order to organize a core group
of agencies who will be the possible main stakeholders of the proposed project:
o Philippine Council for Industry, Energy & Emerging Technology Research &
Development of the Department of Science & Technology (PCIEERD-DOST)
o Energy Policy and Planning Bureau, Department of energy
o Department of Industry/Investment Priorities Plan
o Road Transportation Planning Division, Department of Transportation and
Communications
21
o Forest Management Bureau, Department of Environment and Natural Resources
o Environmental Management Bureau, Department of Environment and Natural
Resources
o National Solid Waste Management Commission
− At the stage of identifying priorities for the project, national consultations with relevant
stakeholders and participants in the proposed project were done on October 21, 2012 and
January 12, 2012. Various government agencies and private and non-governmental
organizations participated comprising of sectoral groupings, as follows: Forestry and Land
Use, Energy, Industry, Agriculture, Transportation, and Waste Management.
Name of institutions /
stakeholders consulted
Reasons for inclusion (e.g. leading institution
of a given sector/area, relevant research,
data management, etc.)
Role in the context-
assessment process (e.g.
consultation, preparation
of draft report, data
provider)
Overall
Climate Change
Commission
Sole agency of the GoP in charge of policy
making, program implementation and
management regarding climate change; in
the process of revising the implementing
rules of R.A. 9729 or the Climate Change Act
of 2009. On the overall, CCC is now
responsible for climate change policy and
program implementation.
Main proponent;
preparation of the
reports and draft project
document of the
Climate Change Capacity
Building Project for
Philippines
Department of
Environment and Natural
Resources (DENR) –
Environment
Management Bureau
(EMB)
Leading institution on environmental
management and conservation of natural
resources with the EMB as lead agency.
DENR is also the Designated National
Authority (DNA) on CDM to facilitate the
development and approval of projects under
this program.
Consultation, data
provider
Department of Energy
(DOE)
Leading institution on energy development
and supply which serves other sectors
including agriculture, industry and
transportation; implements the Energy
Conservation Law, Renewable Energy Act
and the Biofuels Act which are closely
related to climate change mitigation.
Consultation, data
provider; (Energy Sector
was decided to be
covered in the USAID EC-
LEDS project)
National Economic and
Development Authority
(NEDA)
GoP, through NEDA, is taking efforts to
mainstream sustainable development
policies and the inclusion of climate-proofing
strategies in key development plans and
processes as a means to adapt to climate
change
Consultation, data
provider
Transportation Sector
Department of
Transportation and
Communication (DOTC)
Leading institution in the Transport Sector;
DOTC and other transport-related agencies
formulated a National Environmentally
Sustainable Transport Strategy (NESTS) for
the country
Consultation, data
provider
UP National Center for
Transport Studies (CTS)
Leading institution in transportation
research, capacity building and sustainable
transport systems
Consultation, data
provider
Agriculture Sector
22
Name of institutions /
stakeholders consulted
Reasons for inclusion (e.g. leading institution
of a given sector/area, relevant research,
data management, etc.)
Role in the context-
assessment process (e.g.
consultation, preparation
of draft report, data
provider)
Department of
Agriculture
Leading institution in the Agriculture Sector;
DA has issued its Framework Strategy and
Policy and the Implementation Program on
Climate Change including GHG emissions
reduction and strategies based on
sustainable development and treating
mitigation as a function of adaptation
Consultation, data
provider
Bureau of Agricultural
Statistics (BAS)
Leading institution that provides data and
information on agricultural indicators system
pertinent to climate change in agriculture
Consultation, data
provider
International Center for
Research in Agroforestry
(ICRAF) / University of the
Philippines – Los Baños
(UPLB)
Leading institution in agricultural research
and application of trees and in securing
environmental services in production and
related capacity building
Consultation, data
provider
Bureau of Agriculture
Research (BAR)
Leading institution on responding to climate
change through R&D in agriculture; BAR
spearheaded the formulation of the climate
change R&D program to provide guidance on
appropriate adaptation and mitigation
research and extension efforts to
strategically respond to climate change in
agriculture. SEARCA through its established
networks and linkages within and outside
Southeast Asia has provided assistance to
the DA-BAR in its capability-building program
related to climate change.
Consultation, data
provider
Industry Sector
Department of Trade and
Industry/
Board of investments
(DTI-BOI)
Leading institution in industry sector; DTI
also issued the MSMED Plan 2011-2016
which aims to develop MSMEs and serves as
the framework for the convergence of global
themes and cross-cutting issues including
climate change.
Consultation, data
provider
Other Sectors
Philippine Council for
Agriculture, Aquatic and
Natural Resources
Research and
Development (PCAARRD)
– Department of Science
and Technology (DOST)
Lead institution on the national S&T agenda
for agriculture, aquatic and other natural
resources R&D as a consolidated response to
related national issues in these sectors,
including climate change, in consultation
with national experts, the member agencies
of the National Agriculture and Resources
Research and Development System
(NARRDS), and key national stakeholders
Consultation, data
provider
Forest Management
Bureau (FMB)
Lead institution on the 25-year Philippine
Master Plan for Forestry Development
(MPFD) under the primary responsibility of
DENR
Consultation (Forest Sector
was decided to be covered
in the USAID EC-LEDS
project)
National Solid Waste
Management Commission
(NSWMC)
Lead institution to implement the Ecological
Solid Waste Management Act of 2000
Consultation, data
provider
23
Name of institutions /
stakeholders consulted
Reasons for inclusion (e.g. leading institution
of a given sector/area, relevant research,
data management, etc.)
Role in the context-
assessment process (e.g.
consultation, preparation
of draft report, data
provider)
General/NGOs
Department of the
Interior Local Government
(DILG)
Leading institution in the mainstreaming and
implementation of all local-based, including
climate-change related, projects and
programs through the local government
units in cooperation with the general public
Consultation
World Wildlife Fund
(WWF)-Philippines
Leading world organization in sustainable
development through its Climate Change
and Energy Program that focuses on
increasing the resiliency of vulnerable areas
through local stakeholder engagement,
capacity-building exercises, public-private
cooperation and policy-making consistent
with GoP policies and programs to ensure
that adaptation measures are implemented
on the ground.
Consultation
Sibol ng Agham at
Teknolohiya (SIBAT) –
Wellspring of Science and
Technology
Leading NGO in sustainable development by
enabling poor communities achieve self-
reliance through appropriate science and
technology; supportive of instituting and
strengthening climate change adaptation
and mitigation measures in its current
programs and projects in renewable energy
and sustainable agriculture.
Consultation
Clean Air Initiatives for
Asian Cities (CAI-Asia)
Leading multi-stakeholder initiative by the
World Bank, ADB and USAID to promote
better air quality and livable cities by
translating knowledge to policies and actions
that reduce air pollution and greenhouse gas
emissions from transport, energy and other
sectors.
Consultation
Manila Observatory (MO) Leading organization providing technical
services in emissions inventory, RE
resources, training courses on climate
change, project development and education
resources
Consultation
Philippine Atmospheric,
Geophysical and
Astronomical Services
Administration (PAGASA)
Main agency for providing climatological and
agrometeorological services and
information.
Consultation
Geosphere Technologies,
Inc.
Leading service provider in industrial and
environmental solutions
Consultation
Conservation
International (CI) -
Philippines
Leading movement in promoting healthy
ecosystems by engaging governments,
NGOs, and the private sector in a science-
driven process of designing and creating
networks of protected areas and on zero and
low carbon development initiatives focusing
on thematic responses, supported by field
demonstration in priority areas.
Consultation
Philippine Chamber of Leading business organization through its Consultation
24
Name of institutions /
stakeholders consulted
Reasons for inclusion (e.g. leading institution
of a given sector/area, relevant research,
data management, etc.)
Role in the context-
assessment process (e.g.
consultation, preparation
of draft report, data
provider)
Commerce and Industry
(PCCI)
Environment Committee promotes
environmental responsibility and sustainable
development in the Philippine business
sector by examining environmental policy
issues and advocates for environmental
protection in the context of sustainable
development with the end in view of
promoting business growth and bringing
better quality life for all.
Philippine Business for the
Environment (PBE)
Leading not-for-profit organization of
businesses focused on environmental issues
with agenda details, missions, training,
publications and project information
Consultation
Ateneo School of
Government (ASoG)
Leading academia-based program on policy
and governance capacity building; heavily
involved in addressing environmental issues
particularly climate change also at the
national level to address climate change
impacts; projects on capacity building for
local government units, technology and
innovations, social accountability, disaster
risk management, and climate change
adaptation and mitigation.
Consultation
Aksyon Klima Pilipinas Leading national network of more than 40
CSOs working on diverse climate- and
development-related issues
Consultation
Yellow Ribbon Movement Leading moral transformation drive on a
nationwide coverage to support the present
GoP leadership on various thematic areas,
including environmental protection and
climate change.
Consultation
Renewable Energy
Association of the
Philippines (REAP)
Leading non-stock, non-profit organization of
companies and private individuals committed
to the nationwide development, promotion,
utilization and commercialization of renewable
energy technologies/systems for sustainable
energy generation as a means of climate
change mitigation strategy.
Consultation
Preferred Energy
Incorporated (PEI)
Leading service provider with the goal of
creating a favorable market for renewable
energy and energy efficiency in the country.
Consultation
Philippine Movement for
Climate Justice (PMCJ)
Leading organization advocating people-
oriented support for climate-related issues.
Consultation
Private Sector
Representatives from
various private companies
(Tiger Carbon, San Miguel
Corporation, AGC Flat
Glass Phil Inc.,
FIS Inc./Amertech)
Various private companies and business
ventures with varied interests in climate
change related ideas and projects.
Consultation
25
Institutional support will also come from several government departments and agencies that are
also involved in the formulation of climate change-related policies and programs and for this
project, those that are involved in the Transport, Agriculture, Waste, and Industry sectors which
were selected as the four sectors to be included in the LECB Project.
The Climate Change Commission will be the main implementing partner for the project, in
coordination with relevant institutions in the said sectors included in the project.
Through the capacity building activities and measures of the project, all the stakeholders will be
strengthened in the areas where they are weak or need support as validated during the course of
project implementation.
The project cooperation agreements, Terms of Reference (TOR) for staff or major contracts, etc. are
included in Appendix B.
7. MONITORING AND EVALUATION FRAMEWORK
Project progress will be monitored according to UNDP rules and regulations by using quarterly and
annual reviews against a set of implementation milestones. Monitoring will be ongoing, involving
data collection and assessment of the project’s field implementation and will involve key project
staff meeting to review operations and field implementation periodically and to assess whether new
priorities require a shift in the project’s implementation approach.
Progressive indicators measuring processes, outputs, and outcomes have been included in the
Project Results Framework (PRF). Indicators are both qualitative and quantitative.
Monitoring Project Progress
Tools for monitoring the Project’s timely completion, quality of the outputs and the efficient use of
allotted resources (financial, human and physical) will include:
Within the annual cycle, on a quarterly basis
- On a quarterly basis, a quality assessment shall record progress towards the completion
of key results, based on quality criteria and methods captured in the Quality Management
table below.
- An Issue Log shall be activated in Atlas and updated by the Project Manager to facilitate
tracking and resolution of potential problems or requests for change.
- Based on the initial risk analysis submitted, a risk log shall be activated in Atlas and regularly
updated by reviewing the external environment that may affect the project implementation.
- Based on the above information recorded in Atlas, a Project Progress Reports (PPR) shall be
submitted by the Project Manager to the NSC through UNDP acting the role of Project
Assurance, using the standard report format available in the Executive Snapshot.
- A project Lesson-learned log shall be activated and regularly updated to ensure on-going
learning and adaptation within the organization, and to facilitate the preparation of the
Lessons-learned Report at the end of the project
- A Monitoring Schedule Plan shall be activated in Atlas and updated to track key
management actions/events.
26
Annually
- Field visits: Representatives from the UNDP and EU Offices in Manila should visit the project
at least once a year. Field visits serve the purpose of results validation, especially when
undertaken in the first half of the year. If undertaken in the latter part of the year, the field
visit should provide latest information on progress for annual reporting preparation. Field
visits should be documented through brief and action-oriented reports, submitted within
the week of return to the office.
- Annual Review Report: An Annual Review Report shall be prepared by the Project Manager
and shared with the NSC. As a self-assessment by the project management, it does not
require a cumbersome preparatory process. As minimum requirement, the Annual Review
Report shall consist of the Atlas standard format for the PPR covering the whole year with
updated information for each above element of the PPR as well as a summary of results
achieved against pre-defined annual targets at the output level. As such, it can be readily
used to spur dialogue with the NSC and partners.
- Annual Project Review: Based on the above report, an annual project review shall be
conducted during the fourth quarter of the year or soon after, to assess the performance of
the project and appraise the Annual Work Plan (AWP) for the following year. In the last year,
this review will be a final assessment. This review is driven by the NSC and may involve
other stakeholders as required. It shall focus on the extent to which progress is being made
towards outputs, and that these remain aligned to appropriate outcomes. Once cleared, key
elements of the reports shall feed directly into the annual reporting exercise on results at
the outcome level.
Audit and External Evaluation
- The project will also be subject to at least one external management audit in accordance
with established UNDP regulations.
- The project will also be subject to at least one independent evaluation, i.e. mid-term review,
to be conducted by an external team to assess progress on outputs/outcomes and identify
areas for strategic, budgetary, or programmatic adjustments if necessary.
- Apart from the external audit mentioned above, the project is also subject to internal UNDP
and EU Office spot checks/audits.
At project completion
- The project’s Terminal or Project Completion Report (PCR) that will sum up the level of the
project’s accomplishments in meeting its objectives, outcomes and outputs. The PCR will
also highlight the breakthroughs and innovative contributions of the project in the field of
coordination system development which are worth replicating in similar projects to be
undertaken in other countries. It will also set out the strategies to efficiently managing
resources.
- Results from the Project will be disseminated within and beyond the Project intervention
through information sharing networks and/or through publications. For publications,
proper acknowledgement to UNDP and programme donors for providing funding will be
ensured.
27
Adaptive Management and Project Revisions
- The monitoring framework and indicators will provide the project management with regular
information on the project status. In addition, regular feedback will come from the Project
Board. Collectively, this feedback will enable the project management to continuously learn
lessons and modify approaches and strategies, and to overcome challenges and exploit
opportunities.
- Budget revisions/amendments to the contract will be done through a formal exchange of
letters between UNDP and the Climate Change Commission along with a revised Work and
Financial Plan. Depending on the nature of the amendment, the proposed revision will be
subject to UNDP and EU processes and procedures.
Quality Management for Project Activity Results
Outcome 1: Robust national systems for preparation of GHG emission inventories have been established in
the Transport, Agriculture and Industry Sectors
Activity Result 1.1
(Atlas Activity ID)
Understanding of the requirements for GHG inventories
and National Communications (NCs) and a description of
institutional arrangements in the selected sectors
Start Date: Q2 Yr 1
End Date: Q2 Yr 2
Purpose
To take into account the potential requirement for reliable national system and more
frequent GHG inventory reporting
Description
Build capacity for national systems for the preparation of GHG inventories through
training and seminar/workshops for relevant government officials and staff involved in
the activity
Quality Criteria Quality Method Date of Assessment
Number of training and
seminar/workshops conducted on the
preparation of GHG inventory systems
On-training evaluation by
participants and training reports on
the on the preparation of GHG
inventory systems vis-a-vis the
training needs assessment done
During every training and
seminar/workshop
Number of government officials and
local personnel trained
Percentage of participants applying the
training on the national GHG inventory
system in its actual implementation
Post-training evaluation and
assessment report by Training
Specialist
Q1 Yr 3
Activity Result 1.2
(Atlas Activity ID)
Well designed and established national systems for the
preparation of GHG inventories as applied to the selected
sectors
Start Date: Q3 Yr 1
End Date: Q4 Yr 2
Purpose
To improve national system for GHG inventory
Description
Design and establish national systems for the preparation of GHG inventories and
necessary sustained maintenance
Quality Criteria Quality Method Date of Assessment
Rules of procedure detailed as part of a
GHG inventory manual (incl. timelines,
budget, system sustainability, etc.) by
end of Yr 1
Manual of procedures Q4 Yr 2
QA/QC strategy and maintenance
system documented and adopted by
Q3 Yr 3
Documentation and policy adoption Q4 Yr 3
Activity Result 1.3
(Atlas Activity ID)
Appropriate institutional frameworks and arrangements
established to ensure regular updates of GHG inventories
Start Date: Q2 Yr 2
End Date: Q2 Yr 3
Purpose To ensure that actual data required for GHG inventories is compiled on a regular basis
28
and in the required format by relevant institutions
Description
Establish institutional frameworks, organizational mandates and coordination
mechanisms that ensure periodic GHG inventory updates
Quality Criteria Quality Method Date of Assessment
MOUs prepared with key institutional
partners by Q4 Y3
Policy adoption and
institutionalization
Q3 Yr 3
Activity Result 1.4
(Atlas Activity ID)
Established linkages between the GHG inventory systems
and MRV system for NAMAs and LEDS
Start Date: Q2 Yr 3
End Date: Q4 Yr 3
Purpose
To institutionalize the linkage between the GHG inventory system and the MRV
schemes adopted to support decision making and program outcome monitoring and
evaluation
Description
Institutionalize mechanisms at the national and institutional levels to link GHG
Inventories to MRV-related activities for long term sustainability
Quality Method Date of Assessment
Data measurement and analysis is
institutionalized by Q3 Yr 3 to generate
reports on periodic basis
External expert review Q4 Yr 3
Strategy approved by end of Yr 3 ,
along with decision on yearly periodic
updates
Project documentation Q3 Yr 3
Outcome 2: NAMAs and sectoral road maps have been formulated within the context of national
development priorities as applied to the Transport, Agriculture, Waste and Industry Sectors
Activity Result 2.1
(Atlas Activity ID)
Understanding of the coordination, planning, design,
implementation, and evaluation of NAMAs and sectoral
road maps
Start Date: Q2 Yr 1
End Date: Q2 Yr 2
Purpose
To build synergies with national priorities, national policies that can be upgraded to
NAMAs
Description
Build capacity to coordinate, plan, design, and implement mitigation actions and
sectoral road maps
Quality Criteria Quality Method Date of Assessment
Number of training and
seminar/workshops conducted the
coordination, planning, design,
implementation, and evaluation of
NAMAs and sectoral road maps
On-training evaluation by participants
and training reports on the
coordination, planning, design,
implementation, and evaluation of
NAMAs and sectoral road maps vis-a-
vis the training needs assessment
done
During every training and
seminar/workshop
Number of government officials and
local personnel trained
Percentage of participants applying the
training on the understanding of the
coordination, planning, design,
implementation, and evaluation of
NAMAs and sectoral road maps
Post-training evaluation and
assessment report by Training
Specialist
Q1 Yr 3
Activity Result 2.2
(Atlas Activity ID)
Creation of NAMAs and sectoral
roadmaps at the national level
Start Date: Q1 Yr 2
End Date: Q1 Yr 3
Purpose
To align mitigation actions and sectoral road maps with the country’s short- and long-
term national development goals.
Description
Identify and prioritize mitigation actions in the key sectors
Quality Criteria Quality Method Date of Assessment
NAMAs and sectoral roadmaps
formulated at the national level Q1 Yr 2
NAMAs and sectoral roadmaps
approved by the NSC
Q2 Yr 2
29
NAMAs prioritized for the Transport,
Agriculture, Waste and Industry Sectors
by Q1 Yr 3, and sectoral road maps
prepared
NAMAs identified and sectoral
roadmaps approved by the NSC
Q2 Yr 3
Activity Result 2.3
(Atlas Activity ID)
Establishment of NAMAs and sectoral
policy instruments, technology
options, and funding strategies
Start Date: Q1 Yr 2
End Date: Q4 Yr 2
Purpose
To develop financing strategies to secure funding for short- to medium-term activities.
Description
Identify policy, financing, and technology instruments to implement mitigation actions
and low emissions strategies
Quality Criteria Quality Method Date of Assessment
NAMAs and sectoral policy
instruments, technology options, and
funding strategies Identified and
established Q3 Yr 3
Approval of NAMAs and sectoral
policy instruments, technology
options, and funding strategies by the
NSC
Q4 Yr 3
Policy-ready and investment-ready
portfolio containing NAMAs and
sectoral mitigation measures that are
adopted by NSC and endorsed to the
financial sector for future
implementation by Q3 Yr 3.
Consultation and endorsement Q4 Yr 3
Activity Result 2.4
(Atlas Activity ID)
Consensus reached in mitigation
actions and sectoral roadmaps among
stakeholders and interested actors
Start Date: Q3 Yr 1
End Date: Q4 Yr 3
Purpose
To provide the basis for continuous interaction with stakeholders for reaching
consensus and for monitoring of the project’s activities
Description
Establish and facilitate dialogue platforms for mitigation actions and low-emissions
strategies
Quality Criteria Quality Method Date of Assessment
Mitigation actions and sectoral road
maps approved for endorsement by
NSC to CCC by Q1 Yr 3
Series of consultation and consensus
building
Q2 Yr 3
Lessons learned report validated by Q3
Yr 3
Dialogue and project documentation Q4 Yr 3
Outcome 3: MRV systems have been designed to support implementation and evaluation of NAMAs and LEDS
as applied to the Transport, Agriculture, Waste and Industry Sectors
Activity Result 3.1
(Atlas Activity ID)
Training of government officials and local personnel in
MRV tools for NAMAs and LEDS
Start Date: Q2 Yr 1
End Date: Q2 Yr 2
Purpose
To develop capacity of the stakeholders in the relevant government institutions under
the selected sectors in connection with the design of the MRV systems
Description
Build capacity in MRV-related activities in order that government officials and ;local
personnel can support mitigation actions and low-emissions strategies
Quality Criteria Quality Method Date of Assessment
Number of training and
seminar/workshops conducted on MRV
tools for NAMAs and LEDS
On-training evaluation by participants
and training reports on MRV-related
activities in support mitigation actions
and low-emissions strategies vis-a-vis
the training needs assessment done
During every training and
seminar/workshop
Number of government officials and
local personnel trained
Percentage of participants applying the
training on MRV tools for NAMAs and
Post-training evaluation and
assessment report by Capacity
Q1 Yr 3
30
LEDS Building Specialist
Activity Result 3.2
(Atlas Activity ID)
MRV systems for NAMAs and LEDS
developed
Start Date: Q4 Yr 1
End Date: Q2 Yr 2
Purpose
To select and develop appropriate methodologies and monitoring protocols for
planned the MRV systems
Description
Design a MRV system to support the implementation of mitigation actions and low-
emissions strategies and revisit system for further improvement
Quality Criteria Quality Method Date of Assessment
MRV design approved by the NSC and
endorsed for consideration of the CCC
by Q2 Yr 2.
Design and review process Q1 Yr 3
Activity Result 3.3
(Atlas Activity ID)
Assessment of technology needs to
develop a national information
system
Start Date: Q2 Yr 2
End Date: Q1 Yr 3
Purpose
To determine the requirements and methodology for developing national technology
systems
Description
Develop national technology systems for information and monitoring according to the
country’s needs
Quality Criteria Quality Method Date of Assessment
National technology system developed
and applied by CCC by Q1 Yr 3
Independent evaluation based on the
assessment of technology needs
made by the project
Q3 Yr 3
Project Inception
A Project Inception Workshop will be held within the first 2 months of project start-up with those
with assigned roles in the project organization structure, the UNDP CO and, where
appropriate/feasible, regional technical policy and programme advisors, as well as other
stakeholders. The Inception Workshop is crucial for building ownership regarding the project results
and to prepare the Year 1 Annual Work Plan.
The Inception Workshop will address a number of key issues including:
a) Assist all partners to fully understand and take ownership of the project. Discuss the roles,
functions, and responsibilities within the project's decision-making structures, including
reporting and communication lines, and conflict resolution mechanisms. The Terms of
Reference for project staff can be discussed again as needed.
b) Based on the Project Results Framework (Section 3), finalize the Year 1 Annual Work Plan,
review and agree on the indicators, targets and their means of verification, and recheck
assumptions and risks.
c) Provide a detailed overview of reporting, monitoring and evaluation requirements. The
M&E work plan and budget should be agreed and scheduled.
d) Discuss financial reporting procedures and obligations.
e) Plan and schedule NSC meetings. Roles and responsibilities of all project organization
structures should be clarified and meetings planned. The first NSC meeting should be held
within the first 12 months following the Inception Workshop.
An Inception Workshop Report is a key reference document and will be prepared and shared with
participants to formalize various agreements and plans decided during the meeting. It should be
considered a key deliverable of the project.
31
Learning and Knowledge Sharing
As noted earlier, it will be important to have effective coordination mechanisms and synergistic
approaches between the LECB project and other similar and complementary initiatives, such as EC
LEDS and Third National Communication, through regular meetings among the respective project
working groups in the planned dialogue platforms. Additionally, close coordination among the
UNDP, USAID and other partners will be undertaken particularly on the NAMA expectations in the
course of project implementation. This coordination will ensure that a coherence framework or
methodological approach to develop the NAMAs is used across the sectors covered under the two
initiatives.
Furthermore, potential linkages and synergies between the Public and Private sectors will identify
opportunities for public-private partnerships to address key climate change priorities under the
project in a coordinated manner. In this context, the country will be able to identify the most
suitable options to engage the private sector in the formulation and implementation of the project
and its activities.
Results from the project will be disseminated within and beyond the project intervention zone
through existing information sharing networks and forums at the sub-national, national, regional,
and global levels. The national management unit will work closely with the Programme’s Global
Support Component in this context.
The project team will also identify and participate, as relevant and appropriate, in scientific, policy-
based and/or any other networks, which may be of benefit to project implementation through
lessons learned.
The project will identify, analyze, and share lessons learned that might be beneficial in the design
and implementation of similar future projects. There will be a two-way flow of information between
this project and other projects of a similar focus, supported by the Programme’s Global Support
Unit. Specific agreed activities for ensuring uptake of lessons learned and best practices are detailed
in Appendix D.
M&E Work Plan
Type of M&E activity Responsible Parties Time frame
Inception Workshop and Report � Project Manager
� UNDP CO, UNDP EEG
Within first two months of
project start up
Bimonthly report on output and
implementation
� Oversight by Project Manager
� Project team
Every two months
Quarterly report (Atlas and ERBM) � UNDP CO Quarterly
Periodic status/ progress reports � Project Manager and team Every six months
Project Terminal Report � Project Manager and team
� UNDP CO
At least three months before the
end of the project
Audit � UNDP CO
� Project Manager and team
End of project
8. LEGAL CONTEXT
This Project Document shall be the instrument referred to as such in Article I of the Standard Basic
Assistance Agreement between the Government of the Philippines and the United Nations
Development Programme, signed by the parties on 21 July 1977. The host country implementing
agency shall, for the purpose of the Standard Basic Assistance Agreement, refer to the government
co-operating agency described in that Agreement.
32
The UNDP Resident Representative in Philippines is authorized to effect in writing the
following types of revision to this Project Document, provided that he/she has verified the
agreement thereto by the European Union Office in the country and is assured that the other
signatories to the Project Document have no objection to the changes:
a) Revision of, or addition to, any of the annexes to the Project Document;
b) Revisions which do not involve significant changes in the immediate objectives, outputs or
activities of the project, but are caused by the rearrangement of the inputs already agreed
to or by cost increases due to inflation;
c) Mandatory annual revisions which re-phase the delivery of agreed project inputs or
increased expert or other costs due to inflation or take into account agency expenditure
flexibility; and
d) Inclusion of additional annexes and attachments only as set out here in this Project
Document
Consistent with the Article III of the Standard Basic Assistance Agreement, the responsibility for the
safety and security of the implementing partner and its personnel and property, and of UNDP’s
property in the implementing partner’s custody, rests with CCC as the Implementing Partner. CCC
shall:
a) put in place an appropriate security plan and maintain the security plan, taking into account the
security situation in the country where the project is being carried;
b) assume all risks and liabilities related to the implementing partner’s security, and the full
implementation of the security plan.
UNDP reserves the right to verify whether such a plan is in place, and to suggest modifications to the
plan when necessary. Failure to maintain and implement an appropriate security plan as required
hereunder shall be deemed a breach of this agreement.
The implementing partner agrees to undertake all reasonable efforts to ensure that none of the
UNDP funds received pursuant to the Project Document are used to provide support to individuals
or entities associated with terrorism and that the recipients of any amounts provided by UNDP
hereunder do not appear on the list maintained by the Security Council Committee established
pursuant to resolution 1267 (1999). The list can be accessed via
http://www.un.org/Docs/sc/committees/1267/1267ListEng.htm. This provision must be included in
all sub-contracts or sub-agreements entered into under this Project Document”.
This project forms part of an overall programmatic framework under which several separate
associated country level activities will be implemented. When assistance and support services are
provided from this Project to the associated country level activities, this document shall be the
“Project Document” instrument referred to in: (i) the respective signed SBAAs for the specific
countries; or (ii) in the Supplemental Provisions attached to the Project Document in cases where
the recipient country has not signed an SBAA with UNDP, attached hereto and forming an integral
part hereof.
This project will be implemented by the agency (name of agency) (“Implementing Partner”) in
accordance with its financial regulations, rules, practices and procedures only to the extent that they
do not contravene the principles of the Financial Regulations and Rules of UNDP. Where the
financial governance of an Implementing Partner does not provide the required guidance to ensure
33
best value for money, fairness, integrity, transparency, and effective international competition, the
financial governance of UNDP shall apply.
The responsibility for the safety and security of the Implementing Partner and its personnel and
property, and of UNDP’s property in the Implementing Partner’s custody, rests with the
Implementing Partner. The Implementing Partner shall: (a) put in place an appropriate security plan
and maintain the security plan, taking into account the security situation in the country where the
project is being carried; (b) assume all risks and liabilities related to the Implementing Partner’s
security, and the full implementation of the security plan. UNDP reserves the right to verify whether
such a plan is in place, and to suggest modifications to the plan when necessary. Failure to maintain
and implement an appropriate security plan as required hereunder shall be deemed a breach of this
agreement.
The Implementing Partner agrees to undertake all reasonable efforts to ensure that none of the
UNDP funds received pursuant to the Project Document are used to provide support to individuals
or entities associated with terrorism and that the recipients of any amounts provided by UNDP
hereunder do not appear on the list maintained by the Security Council Committee established
pursuant to resolution 1267 (1999). The list can be accessed via
http://www.un.org/Docs/sc/committees/1267/1267ListEng.htm. This provision must be included
in all sub-contracts or sub-agreements entered into under this Project Document.
34
9. APPENDICES
Appendix A
TECHNICAL COMPONENTS OF THE
PHILIPPINES: CLIMATE CHANGE CAPACITY BUILDING PROJECT
Introduction
The Low Emission Capacity Building Programme (or briefly referred herein as the LECB Programme
or the Overall Global Programme) will be carried out in fifteen phase 1 countries, including the
Philippines, over a four-year period. The national project for the country is referred to as the
“Philippines: Climate Change Capacity Building Project” or referred herein also as the Project.
The Overall Global Programme will strengthen national capacities to do the following: 1)
Develop/establish greenhouse gas inventory management systems; 2) Formulate Nationally
Appropriate Mitigation Actions (NAMAs) and/or low-emission development strategies (LEDS) in the
context of national development; 3) Design MRV systems to support implementation and evaluation
of NAMAs and LEDS; and, in a few select countries, 4) Facilitate the design and adoption of
mitigation actions by selected industries; and 5) Support the design of the associated MRV systems
for industrial mitigation measures. The Philippines will focus on outcomes 1 to 3.
A Global Support Unit is providing technical assistance to countries in the design and
implementation of project activities at the national level, in response to the need for capacity
development at the country level, as well as to opportunities that have been identified for engaging
Public Sector and Industry support and participation in addressing the issue of climate change. The
Programme will operate at the global and national levels and will seek to engage relevant
stakeholders at all levels to meet the objectives of the Project.
1. Description of project outcomes and key activities
As part of Philippine participation in Area 1: Public Sector Capacity Building on GHG Inventory
systems, NAMAs, LEDS, and MRV in the designated four sectors composed of the Transport,
Agriculture, Waste, and Industry sectors, the following are the expected outcomes from which the
Project objectives are directed to produce the desired outputs and results.
� Outcome 1: Robust national system for preparation of GHG emission inventories have been
established at a national level
� Outcome 2: NAMAs and sectoral road maps have been formulated within the context of
national development priorities
� Outcome 3: MRV systems have been designed to support implementation and evaluation of
NAMAs and LEDS/sectoral road maps.
It is very important to note that while this Project focuses on the Public Sector in general, its project
activities and outputs will involve participation to some extent of the Industry sector as well. To have
a flexibility that will ensure that, where feasible, the country will have and can benefit from this
capacity-building support to the fullest extent. In fact, the capacity building of the Industry sector
which will cover GHG-intensive manufacturing companies will be covered in the Area 1 focus.
Furthermore, potential linkages and synergies between the Public and Industry sectors will identify
opportunities for public-private partnerships to address key climate change priorities under the
project in a coordinated manner. In this context, the country will be able to identify the most
35
suitable options to engage the private sector in the formulation and implementation of the project
and its activities.
For this Project and consistent with Area 1 focus, the Public sector can play a key role in the design
of policies, regulations and incentives to facilitate the active engagement of the private sector in
efforts to address climate change concerns. On the other hand, the private sector can identify and
implement concrete actions on the ground, at the sectoral or industrial level, to reduce GHG
emissions while ensuring linkages with development needs and economic growth.
� Outcome 1: Robust national system for preparation of GHG emission inventories have been
established in the Transport, Agriculture, Waste, and Industry Sectors
The Project will support technical and institutional capacity development geared toward
improving GHG inventories, including for MRV-related activities. The technical advice should
facilitate the establishment and long-term sustainability of national technical teams for the
preparation of upcoming national communications, including GHG inventories, on a continuous
basis. The Project’s expected outputs under Outcome 1 are:
• Output 1.1: Understanding of the requirements for a GHG inventory system and a
description of institutional arrangements
Activity 1.1: Build capacity for national systems for the preparation of GHG inventories. This
must take into account the potential requirement for more frequent GHG inventory and NC
reporting. Work includes training in understanding requirements, analyzing key emitters,
and describing institutional arrangements.
The outputs of this activity will be produced through training and seminar/workshops for
relevant government officials and staff involved in the GHG inventory activity. The training
program will be based on a training needs analysis to be conducted by a Capacity Building
Specialist. The relevant government officials and staff will the participants in the training and
seminar/workshops conducted in developing and introducing the national GHG inventory
system. The participants’ role in GHG inventory system development and implementation
will be presented and discussed. On-training evaluation will be accomplished by participants
during every training and seminar/workshop conducted. The work will build on the results
and lessons learned from the GHG inventory prepared under the Second NC and will ensure
the necessary coordination with the Third NC project, as appropriate3. A post-evaluation of
the training program effectiveness and impact will be conducted by the Capacity Building
Specialist as participants apply the acquired learning in their actual duties and
responsibilities.
• Output 1.2: Well designed and established national systems for the preparation of GHG
inventories and NCs
Activity 1.2: Design and establish national systems for the preparation of GHG inventories
and NCs. This includes training in the use of tools, the use of enhanced documentation
formats, QA/QC, the use of archiving systems, and planning inventory improvement. The
IPCC Good Practice Guidelines will be used as the basis for the design of the inventory
systems that will be sustained and maintained in the long term.
3 The Philippines has not started its Third NC, but it is expected that the preparatory phase will be initiated later
in 2012. The LECB project team will work closely with the NC team to avoid any potential duplication and
identify areas of collaboration and complementarity.
36
A GHG inventory system manual containing the rules of procedure and other details as part
of a manual (incl. timelines, budget, system sustainability, etc.) shall be developed and
disseminated. In order to ensure that the system developed will effectively meet the sector
and country requirements a quality assurance/quality control (QA/QC) strategy and
maintenance system shall be documented and adopted by the NSC for endorsement to CCC
for the latter’s implementation.
• Output 1.3: Appropriate institutional frameworks established to ensure regular updates of
GHG inventories
Activity 1.3: Establish institutional frameworks and coordination mechanisms that ensure
periodic GHG inventory updates. This will entail the creation of the institutional structure
and appropriate mandates to ensure that actual data required for GHG inventories can be
compiled on a regular basis and in the required format. A coordinated structure will seek to
integrate GHG inventory work into the institutions responsible for the relevant sectors for
long term sustainability.
In order to ensure the official policy adoption and institutionalization of the GHG inventory
system as well as the budgetary, organizational and sustainability arrangements, a
Memorandum of Understanding (MOU) shall be prepared with key institutional partners.
• Output 1.4: Established linkages between the GHG inventory system and MRV system for
NAMAs and LEDS
Activity 1.4: Institutionalize mechanisms at the national and institutional levels to link GHG
Inventory system to MRV-related activities on a sustained basis. To institutionalize the
linkage between the GHG inventory system and the MRV schemes adopted to support
decision making and program outcome monitoring and evaluation.
Standards in data acquisition, measurement and analysis shall be established and
institutionalized in order to generate quality reports on regular periodic basis. These should
be part of the overall strategy that shall be adopted and approved at the project level by the
NSC for subsequent adoption by the CCC in cooperation with various stakeholders, along
with a decision for yearly periodic updates and maintenance. For purposes of continuing
improvement of the GHG inventory system, an external expert review shall be conducted
toward the end of the project.
� Outcome 2: NAMAs and sectoral roadmaps have been formulated within the context of
national development priorities as applied to the Transport, Agriculture, Waste, and Industry
Sectors
The Project will support the Philippines’ planning, design, implementation, and evaluation of
mitigation strategies and programs. Support will be provided in the areas of a) developing
methodologies and tools to carry out mitigation analysis, b) prioritizing mitigation measures in
accordance with development priorities, c) designing the institutional mechanisms to support
adoption of mitigation measures, and d) setting up the reporting structure for monitoring the
implementation of mitigation measures and evaluating their effectiveness, including the design
of indicators to measure progress. In order to build synergies with national priorities, national
policies that can be “upgraded” to NAMAs will be identified, taking into account different
37
potential sources of financing, such as domestic, international, or carbon market financing. The
choice of appropriate methodologies and/or tools will consider best practices that are known
and applicable to the Philippine situation.
Outcome 2 is expected to produce substantive lessons learned for replication in future activities
or as useful examples for other countries. These lessons learned will be related to a high-level
coordination framework for mitigation programs, a NAMA and LEDS roadmap toolkit, and NAMA
and sectoral roadmap case studies. The expected outputs and activities under Outcome 2 are:
• Output 2.1: Understanding of the coordination, planning, design, implementation, and
evaluation of NAMAs and sectoral roadmaps (as precursor to a LEDS)
Activity 2.1: Build capacity to coordinate, plan, design, and implement mitigation actions and
low-emissions strategies. This activity will build upon the results of the mitigation analysis
carried out previously under the NCs. It will include the definition of the business-as-usual
and mitigation scenarios for the selected sectors and involve the participation of key
stakeholders. This includes training courses and workshops in which mitigation measures are
formulated jointly and action plans are specified for implementation and monitoring.
Training activities will be carried out in close coordination with the initiatives supported by
USAID and GIZ.
Aside from the usual on-training evaluation by participants, a post-training evaluation by the
Capacity Building Specialist shall be conducted to assess if the participants are applying the
training and knowledge gained on the understanding of the coordination, planning, design,
implementation, and evaluation of NAMAs and LEDS.
• Output 2.2: Formulation of NAMAs and sectoral roadmaps at the national level
Activity 2.2: Identify and prioritize mitigation actions in the key sectors. This will include
alignment with the target country’s short- and long-term national development goals.
NAMAs and sectoral roadmaps will be formulated in four sectors using national level
workshops and related synthesis studies. This will involve public and private actors for both
autonomously implemented NAMAs as well as those requiring international support. The
work includes joint specification of clear indicators to identify priority actions for the
Transport, Agriculture, Waste, and Industry Sectors.
As a result of the activity, the sectoral roadmaps that are formulated at the national level
will aid in identifying and prioritizing NAMAs for the Transport, Agriculture, Waste, and
Industry Sectors.
• Output 2.3: Establishment of NAMAs and sectoral policy instruments, technology options,
and funding strategies
Activity 2.3: Identify policy, financing, and technology instruments to implement mitigation
actions and low emissions strategies. This will involve the development of financing
strategies, with priority given to efforts to secure funding for short- to medium-term
activities and related policy instruments. The goal is put forward a policy-ready and
investment-ready portfolio of activities that will be developed in the Project. Having done
sufficient consultations and adopted NAMAs and sectoral policy instruments, technology
options, and funding strategies at the NSC level, this could lead to adoption at the national
level through the CCC. Ultimately, the Project shall endeavor to introduce the portfolio to
38
the banking and financial sector for their future inclusion in their overall banking portfolio
and implementation.
• Output 2.4: Establishment of dialogue platforms for stakeholders and interested actors
Activity 2.4: Establish and facilitate dialogue platforms for mitigation actions and low-
emissions strategies. These platforms will provide the basis for continuous interaction with
stakeholders and for the monitoring of the project’s activities. The sharing of experiences
and documentation of progress in the adoption of mitigation actions and low emissions
strategies that are in line with the country’s developmental needs and priorities shall
generate lessons learned and best practices that can be shared in various fora in the country
and in international symposia. These will be done through sectoral dialogues, consultation
and consensus building in Transportation, Agriculture and Industry which can be integrated
in the final stages of the Project to have a national level platform of exchange and
documentation.
� Outcome 3: MRV systems have been designed to support implementation and evaluation of
NAMAs and LEDS/sectoral roadmaps
In the Philippines, among other selected countries where the focus is on formulation of effective
NAMAs and/or LEDS, attention will be paid to designing MRV systems. This will be done by
establishing appropriate indicators for monitoring mitigation actions, as well as by helping to
create conditions necessary to support future investment in mitigation measures. The focus will
be on establishing scopes, metrics/indicators, reporting mechanisms, verification mechanisms,
and time frames. An improved MRV system will take into account whether NAMAs and/or
LEDS/sectoral roadmaps are implemented autonomously, through support from developed
countries, or through an international crediting mechanism. Suggested criteria for the MRV
systems include: credibility, cost effectiveness, timeliness, and a simple and clear procedure
which provides enough flexibility for a wide range of mitigation actions.
Outcome 3 could also result in a set of publications, examples of which include: a MRV system
training toolkit and compilations of case studies of MRV Protocol, LEDS Protocol, and MRV
system work.
The Project’s expected outputs and activities under Outcome 3 are:
• Output 3.1: Training of local personnel in MRV tools for NAMAs and LEDS/sectoral roadmaps
Activity 3.1: Build capacity in MRV-related activities in order that high government officials
can support mitigation actions and low-emissions strategies. This includes the different
executive departments such as Department of Environment and Natural Resources,
Department of Finance, Department of Transportation and Communication, Department of
Agriculture, Department of Trade and Industry, etc. Activities will consist primarily of tailor-
made information sessions. At the outset, a training needs assessment shall be done by a
Capacity Building Specialist which shall form the basis of the implementation plan and the
evaluation to be conducted to assess the outcome of the activity.
• Output 3.2: MRV systems for NAMAs and LEDS/sectoral road maps developed
Activity 3.2: Design a MRV system to support the implementation of mitigation actions and
low-emissions strategies. Among other things, work here includes the selection of
39
appropriate methodologies and monitoring protocols, training for the use of protocols and
tools, establishment and organization of a reporting process, and selection of verification
bodies.
• Output 3.3: Develop a national technology information system
Activity 3.3: Develop national technology systems for information and monitoring. This
activity will be built on current initiatives with GEF funding to help the country conduct their
technology needs assessments in the four selected sectors under the project. At the
baseline, there is no formally established information system that could directly support
NAMAs and LEDS/sectoral roadmaps implementation. The activity will start with the
Transportation, Agriculture, Waste, and Industry Sectors.
The Global Support Component
UNDP will support national project teams through a Global Support Component (GSC) by providing
guidance and capacity-development support. In particular, the GSC will work with countries to
identify key capacity challenges and barriers to implementation; monitor progress at both the
output and outcome levels; disseminate relevant resources, tools and training materials countries to
support national project activities; and disseminate knowledge and best practices within the global
cohort in order to enhance south-south learning and exchange of experiences.
At the beginning of project implementation, the GSC will discuss specific technical assistance needs
with the Philippines in order to design a strategy for technical backstopping in different areas and
identify a possible schedule for any needed trainings. The GSC will also.
2. Strategy to link process and outcomes of the project to relevant planning and decision making
processes
The overall Work Plan is to build capacities for the GHG National Inventory System, NAMAs & LEDS,
and MRV systems in parallel, since the work areas are so closely linked to one another. For more
effective and productive implementation of related activities, the dialogue platforms for NAMAs and
LEDS will provide an opportunity for continuous engagement of the GHG and MRV teams and the
regular meeting and sharing of results among all the project working groups.
The Project will be implemented within a strong policy, legal and institutional infrastructure through
the Climate Change Commission operating under and overseen by the Office of the GoP President.
Its project development went through rigid stakeholder consultations to ensure that the climate
change capacity needs are well articulated and therefore ownership and sustainability of the
program are properly lodged at the national and institutional levels. The Project is aligned with and
supports directly the National Climate Change Action Plan of the country. A strategy has been
agreed upon by the stakeholders to replicate the project results from the selected sectors of
Transport, Agriculture and Industry to the other sectors under the management and supervision of
the CCC, while also considering results from other related CCC projects and initiatives.
The stakeholder meetings and the context assessment exercise point to the need to prepare the
participants to the climate change program in the light of emerging global conventions and
commitments. This should be balanced with the inherent requirements of the Philippines in
addressing its own national and local climate change-related concerns and sectoral priorities. Each
40
sector has its own unique technical and policy agenda in terms of addressing the key result areas of
the Project vis-à-vis the country’s National Climate Change Action Plan and institutional structures.
The observations and conclusions provided the basis for the formulation of this LECB Project in line
with the Overall LECB Programme.
While this Project focuses on four sectors only (viz., Transportation, Agriculture, Waste and Industry
Sectors), the outcomes will definitively be linked with the national development priorities, processes
and plans as the results of this Project are combined with those of the projects for the other sectors
that are being done in parallel with assistance by other international support arrangements, i.e.
USAID and GIZ. These will be consolidated under the overall management of the Climate Change
Commission in close coordination with the stakeholders. Therefore, the Project will address and
strengthen a number of policy priorities on sustainable management of the very broad area of
climate change while maintaining focus on mitigation measures consistent with the government
policy direction.
The National Framework Strategy on Climate Change, the Climate Change Act of 2009 and other
relevant government issuances that institutionalized the organization and mandate of the Climate
Change Commission will unify various approaches in cooperation with relevant government
agencies and institutions as they gain knowledge and build their capacities in the Project’s key result
areas. The Project’s National Steering Committee will be the venue in which various stakeholders
reach consensus, make decisions and create synergies.
Moreover, the UNDAF and the Country Program Document that also articulate how the UNDP
supports the country’s overall development agenda will serve as additional guide posts (to those
mentioned above) in ensuring the sustainability and replicability of the Project and its outcomes.
The Project has taken the results-based approach to work planning and the review of the work plan
regularly. This work plan serves as a mechanism to link inputs, budget, activities, outputs and
outcomes, which are monitored and evaluated periodically. As lessons are learned, a flexible
approach to implementing the project should accommodate constant adjustments to ensure that
the Project’s outputs and other interventions are credibly linked to the achievement of the desired
outcomes and outputs through the various forms of assistance provided by the Project.
41
Appendix B
Terms of Reference
A. Project Management
A.1 Project Manager
A.2. Technical Officer
A.3 Project Assistant
A.4 Administrative Officer
B. Consultants
B.1 IT Professional
B.2 GHG Inventory Expert
B.3 NAMAs/LEDS Consultant
B.4 MRV Consultant
B.5 Promotion and Knowledge Management
42
SAMPLE TERMS OF REFERENCE
A. Project Management
A.1 TOR: Project Manager
The Project Manager (PM) will serve as the overall GoP manager of the project. The PM has the
overall authority to oversee the Project on behalf of the IP and the NSC within the policies and
guidelines set by the NSC. He/She will be assisted by the Technical Officer, a Project Assistant and an
Administrative Officer (as described below) to be hired by the Project. He/She will facilitate the
hiring of a team of consultants to help in delivering the Project Outputs.
He/ She will be a senior serving member of the Climate Change Commission (CCC) and designated by
the CCC Secretary.
Key Responsibilities
• To provide overall leadership and supervision to the Project Management and Secretariat
(PMS)
• To serve as focal point for the Project interaction with relevant Government counterparts,
donor agencies, private sector, NGOs and other stakeholders
• To be responsible for provision of all project M&E reporting, including progress reports,
project accounts and budgets, project annual work plans, Terms of Reference, etc. as
required by the GoP, UNDP, and donors
• To ensure achievement of the overall objectives and specific outputs of the Project, by
utilizing the project financial resources in an efficient, effective and transparent manner
• To review and endorse the progress and terminal reports of the Project to the National
Steering Committee.
Qualifications
• A senior government officer at the Climate Change Commission
• Strong knowledge of government policies and strategies
• Strong understanding about global and national climate change and environmental issues
• Good interaction with participating line departments/bureaus and other stakeholders;
• Demonstrated strong leadership and partnership
• Demonstrated ability to liaise and foster cooperation between agencies, including
government, private sector participants, NGOs and other stakeholders.
.
A.2 TOR: Technical Officer
A Project Technical Officer (TO) will be recruited for the Project. He/She will be responsible for the
overall implementation of the project activities under the direction of the PM. The TO will be a full-
time staff member for the duration of the project and will be assisted by a full-time Project Assistant
and Administrative Officer. The TOC will lead the Project Management and Secretariat (PMS) and
will be a primary coordinator who will also provide support to the three Technical Working Groups
and the Project Consultants. He/She will coordinate cross-cutting activities for the four (4) sectors
through the TWGs and the Project Consultants, including the development of sectoral road maps;
identification of capacity building needs; design and conduct of seminar/training workshops;
43
development of training modules and manuals; and monitoring of the progress of the different
activities in producing the outputs towards desired outcomes.
Key Responsibilities
• Managing and coordinating the day-to-day project activities including activities of the PMS
and project consultants
• Supervise and coordinate the production of project outputs through the TWGs and the
Project Consultants
• Maintain good communication and coordination with Government counterparts, donor
agencies, private sector, NGOs and other stakeholders
• Review and update the overall project work plan and budget allocation, in coordination with
the CCC and UNDP-CO,
• Participate in the preparation of TORs and organize interviews for selection of candidates for
consultants and sub-contractors
• Provide necessary guidance and technical support to consultants and sub-contractors in
performing their functions
• Organize and facilitate the National Steering Committee and Technical Working Groups
meetings and any other meetings with Government counterparts, donor agencies, private
sector, NGOs and other stakeholders
• Keep regular monitoring of the progress of the project and take corrective actions to ensure
that the project is achieving expected outputs within the given timeframe and budget
• Prepare monthly progress updates, quarterly and annual reports as required by the GoP, EU
and UNDP
• Supervise project personnel in conducting administrative and logistical functions and ensure
timely and effective implementation of project activities
• Certify and monitor the delivery of financial and non-financial resources
• Ensure that project assets are properly recorded and used for implementation of the Project
• Draft a terminal report to the GoP, UNDP, and donors
• Perform any other functions as required by the Project.
Qualifications
• Filipino National with advanced degree or higher (Master’s or higher) in areas relevant to
climate change, environment and national development
• Good knowledge of global and national climate change issues
• A minimum of 3 years of professional experience in the area relevant to the Project and
demonstrating ability in project administration and managing donor’s funds
• Demonstrated strong leadership, effective management skills, good coordination ability and
team working spirit
• Good organizational skills, with strong experience in organizing and facilitating meetings,
workshops and writing reports
• Good interpersonal/communication skills
• Good oral and written communication skills in English
44
A.3 TOR: Project Assistant
A Project Assistant (PA) will be recruited to provide daily assistance to the TO and the Project
management and Secretariat. The PA will be hired as a full-time project staff member for the
duration of the project.
Key Responsibilities
• Assist the TO to establish and maintain good communication and coordination with
Government counterparts, donor agencies, private sector, NGOs and other stakeholders
• Assist the TO to review the overall project work plan and budget allocation
• Organize meetings, including NSC and TWG meetings and taking minutes of the meetings
• Provide administrative and logistical support such as drafting correspondence letters,
organize filing system and record/update project inventory list
• Assist the TO in preparing monthly progress updates, Quarterly and Annual reports to the
GoP, EU and UNDP
• Assist the TO in preparing the terminal report to the GoP, UNDP, and donors
• Perform any other functions as required by the Project.
Qualifications
• Filipino National with College degree with a minimum of 3 years professional experience in
Administration and project management or equivalent
• Extensive experience in organizing meetings, workshops and writing reports
• Good interpersonal and communication skills
• Good organizational skills
• Strong computer skills especially for presentations, Word Processing and Spreadsheets
• Good oral and written communication skills in English
A.4 TOR: Administrative Officer
An Administrative Officer (AO) will be recruited to provide daily assistance to the TO and the Project
Management and Secretariat. The AO will be hired as a full-time project staff member for the
duration of the project.
Key Responsibilities
• Process financial transactions such as payments to consultants, supplies and logistical
requirements as well as monitor project expenditures
• Maintain books of accounts
• Prepare and update financial reports
Qualifications
• Filipino National with College degree in Business Administration, Accountancy or other
relevant degrees.
• Minimum of 5 years professional experience in Administration and project management or
equivalent
45
• Good interpersonal and communication skills
• Good organizational skills
• Strong computer skills especially for Word Processing and Spreadsheets
• Good oral and written communication skills in English
• Knowledge of UNDP and other foreign-assisted project implementation procedures,
including procurement, disbursements and reporting and monitoring is highly preferable.
46
B. Consultants
B.1 TOR: IT Professional
The role of Information Technology (IT) Professional shall be to lead the development of a national
interlinked database of climate change-related information particularly pertaining to GHG inventory,
NAMAs/LEDS and MRV systems. Much of this information currently exists in national agencies and
stakeholders identified in previous stocktaking work and during the preparation of the National
Communications and other government initiatives.
The IT Professional will be part of the Project Management and Secretariat and will report to the
Project Manager in coordination with the NPA/C.
Other relevant data will be researched, analyzed and incorporated in the information system to be
designed by the IT Professional in connection with the objectives of the Project. The consultant will
be responsible for needs assessment and data consolidation capabilities to make important climate
change-related information readily accessible to users. Arrangements will be made for managing and
up-dating databases based on the needs and capabilities of the participating agencies. The ultimate
goal is to make information publicly web-accessible and this will be behind conceptual approaches to
database formatting and presentations. Parallel strategies for making data publicly available should
be developed recognizing that agencies will have differing capabilities in providing data
electronically. The IT Professional will work with the GHG Inventory Expert, NAMAs/LEDS Consultant
and MRV Consultant to develop a strategy for developing the databases and information exchange
system to make them useful for said project key result areas and accessible to relevant users.
Tasks
1. Identify data available, data gaps, data formats, and data readiness for electronic transfer,
organizational capacity needs assessment and other relevant information technology
applications useful to the Project activities
2. Assess information needs of climate change database users, implementation issues and
recommend priority actions on data requirements, data access points, electronic access
issues, etc.
3. Design a national Integrated Climate Change Database and Information Exchange System
among the Project stakeholders, linked through a website via the Internet
4. Implement database development and/or upgrade depending on the status of such in the
Project stakeholders and assist in the development of database management programs as
specified in the design
5. Assist in the implementation of sectoral Integrated Climate Change Information Exchange
Website, which can be expanded to a national level system.
Deliverables
• Sectoral (Transportation, Agriculture, Waste, and Industry) climate change database and
information exchange needs analysis applicable to GHG inventory system, NAMAs/LEDS and
MRV schemes
• Sectoral (with national integration capability) Climate Change Database and Information
Exchange development strategy
47
• A national Web-ready Climate Change Database network and Operations / training work
plan
• An operational Climate Change Website for the database and networking
• A national climate change database and information exchange promotion program.
Qualifications
• Extensive experience in the design and development of databases and information exchange
systems
• Proven track record of research work involving measurement and evaluation of data analysis
• Credible skills in field measurements, data collection, database development, website
development and modeling
• Knowledge of the use of methodologies for data documentation, abstracting of technology
articles, preparation of project profiles
• Professional staff fluent in the English language.
B.2 TOR: GHG Inventory Expert
Working under the direct supervision of the Project Manager, the GHG Inventory Expert will provide
technical knowhow for capacity assessment and for design of GHG inventory systems in the sectors
covered by the Project (viz., Transportation, Agriculture, Waste and Industry). Relevant project
activities that will involve the services of the GHG Inventory Expert are under Outcome 1: Robust
national systems for preparation of GHG emission inventories have been established in the
Transport, Agriculture, Waste and Industry Sectors which includes the following activities:
• Activity 1.1: Build capacity for national systems for the preparation of GHG inventories
• Activity 1.2: Design and establish national systems for the preparation of GHG
inventories
• Activity 1.3: Establish institutional frameworks and coordination mechanisms that
ensure periodic GHG inventory updates
• Activity 1.4: Institutionalize mechanisms at the national and institutional levels to link
GHG Inventory system to MRV-related activities on a sustained basis
Tasks
1. Provide technical inputs for needs and capacity assessment and for design of GHG inventory
systems in the sectors covered by the Project (viz., Transportation, Agriculture, Waste and
Industry)
2. Act as technical expert and resource person in the design and conduct of training
seminar/workshops in the development and implementation of the GHG inventory system
3. Design and assist in the establishment national systems for the preparation of GHG
inventories for the four sectors
4. Recommend institutional frameworks and coordination mechanisms that ensure periodic
GHG inventory and NC updates
5. Recommend mechanisms at the national and institutional levels to link GHG Inventory
system for MRV-related activities on a sustained basis
6. Other tasks that the NSC will identify as necessary to the success of the Project in attaining
its objectives.
Deliverables
48
• Report on needs and capacity assessment for the GHG inventory systems in the sectors
covered
• Technical inputs in the design of capacity building program on GHG inventory system
• Sectoral training needs analysis and program requirement report
• Proposed training program and design of training and seminar/workshops
• Sectoral training materials/manuals
• Training and seminar/workshop report with on-training assessment
• Report on the design and development plans of the GHG Inventory system applicable to the
three sectors
• Recommendations on the institutional frameworks and coordination mechanisms that
ensure periodic GHG inventory updates
• Recommendations on the linkage of GHG Inventory system with MRV-related activities
Qualifications
• Advanced degree or higher (Master’s or higher) in areas relevant to climate change,
environment and national development
• Good knowledge of global and national climate change issues
• A minimum of 5 years of professional experience in the area relevant to the Project and
demonstrating ability in development of computer-based inventory systems
• Demonstrated strong leadership, effective management skills, good coordination ability and
team working spirit
• Good organizational skills, with strong experience in organizing and facilitating meetings,
workshops and writing reports
• Good interpersonal/communication skills
• Good oral and written communication skills in English
B.3 TOR: NAMAs/LEDS Consultant
Working under the direct supervision of the Project Manager, the NAMAs/LEDS Consultant will
provide technical knowhow for capacity assessment and for design of GHG inventory systems in the
sectors covered by the Project (viz., Transportation, Agriculture, Waste and Industry). Relevant
project activities that will involve the services of the GHG Inventory Expert are under Outcome 1:
Robust national systems for preparation of GHG emission inventories have been established in the
Transport, Agriculture, Waste and Industry Sectors which includes the following activities:
• Activity 2.1: Build capacity to coordinate, plan, design, and implement mitigation
actions and low-emissions strategies.
• Activity 2.2: Identify and prioritize mitigation actions and sectoral strategies in the
key sectors under the Project.
• Activity 2.3: Identify policy, financing, and technology instruments to implement
mitigation actions and low emissions strategies
• Activity 2.4: Establish and facilitate dialogue platforms for mitigation actions and
low-emissions strategies
Support will be provided in the areas of a) developing methodologies and tools to carry out
mitigation analysis, b) prioritizing mitigation measures in accordance with development priorities, c)
designing the institutional mechanisms to support adoption of mitigation measures, and d) setting
49
up the reporting structure for monitoring the implementation of mitigation measures and evaluating
their effectiveness, including the design of indicators to measure progress. In order to build
synergies with national priorities, national policies that can be “upgraded” to NAMAs will be
identified, taking into account different potential sources of financing, such as domestic,
international, or carbon market financing. The choice of appropriate methodologies and/or tools
will consider best practices that are known and applicable to the Philippine situation.
Tasks
1. Provide technical inputs for NAMAs/roadmap development in the sectors covered by the
Project (viz., Transportation, Agriculture, Waste, and Industry)
2. Act as technical expert and resource person in the design and conduct of training and
seminar/workshops in the development and implementation of the NAMAS/sectoral road
maps
3. Design and assist in the establishment of NAMAs/roadmaps for the four sectors
4. Recommend institutional frameworks and coordination mechanisms that ensure successful
development and implementation of the NAMAS/roadmaps
5. Other tasks that the NSC will identify as necessary to the success of the Project in attaining
its objectives.
Deliverables
• Report on needs and capacity assessment for the development and implementation of the
NAMAS/roadmaps in the sectors covered
• Technical inputs in the design of capacity building program on NAMAs/roadmaps
• Sectoral training needs analysis and program requirement report
• Proposed training program and design of training and seminar/workshops
• Sectoral training materials/manuals
• Training and seminar/workshop report with on-training assessment
• Report on identification and prioritization of mitigation actions and low-emissions strategies
in the key sectors under the Project.
• Report on the identification of policy, financing, and technology instruments to implement
mitigation actions and low emissions strategies
• Report on design and conduct dialogue platforms for mitigation actions and low-emissions
strategies
Qualifications
• Advanced degree or higher (Master’s or higher) in areas relevant to climate change,
environment and national development
• Good knowledge of global and national climate change issues
• A minimum of 5 years of professional experience in the area relevant to the Project and
demonstrating ability in development of policy measures and implementation plans that can
also be applied to NAMAS/LEDS development
• Demonstrated strong leadership, effective management skills, good coordination ability and
team working spirit
• Good organizational skills, with strong experience in organizing and facilitating meetings,
workshops and writing reports
• Good interpersonal/communication skills
• Good oral and written communication skills in English
50
B.4 TOR: MRV Consultant
Working under the direct supervision of the Project Manager, the MRV Consultant will provide
technical knowhow for capacity assessment and for design of Measurable, Reportable, and
Verifiable (MRV) systems in the sectors covered by the Project (viz., Transportation, Agriculture,
Waste and Industry). Relevant project activities that will involve the services of the MRV Consultant
are under Outcome 3: MRV systems have been created to support implementation and evaluation of
NAMAs and/or LEDS which includes the following activities:
• Activity 3.1: Build capacity in MRV-related activities in order that high government
officials can support mitigation actions and low-emissions strategies
• Activity 3.2: Design a MRV system to support the implementation of mitigation
actions and low-emissions strategies
• Activity 3.3: Develop national technology systems for information and monitoring.
Tasks
1. Provide technical inputs for MRV system development in the sectors covered by the Project
(viz., Transportation, Agriculture, Waste and Industry)
2. Act as technical expert and resource person in the design and conduct of training and
seminar/workshops in the development and implementation of the MRV system
3. Design and assist in the establishment of MRV system for the four sectors
4. Recommend institutional frameworks and coordination mechanisms that ensure successful
development and implementation of the MRV system
5. Other tasks that the NSC will identify as necessary to the success of the Project in attaining
its objectives.
Deliverables
• Report on needs and capacity assessment for the development and implementation of the
MRV system in the four (4) sectors covered
• Technical inputs in the design of capacity building program on MRV system
• Report on design and implementation plan for the development and implementation of the
MRV system
• Report on the recommendations on institutional frameworks and coordination mechanisms
that ensure successful development and implementation of the MRV system
• Sectoral training needs analysis and program requirement report
• Proposed training program and design of training and seminar/workshops
• Sectoral training modules and materials/manuals
• Training and seminar/workshop report with on-training assessment
Qualifications
• Advanced degree or higher (Master’s or higher) in areas relevant to climate change,
environment and national development
51
• Good knowledge of global and national climate change issues
• A minimum of 5 years of professional experience in the area relevant to the Project and
demonstrating ability in development of results-based monitoring and evaluation systems
that can also be applied to NAMAS/LEDS development and implementation
• Demonstrated strong leadership, effective management skills, good coordination ability and
team working spirit
• Good organizational skills, with strong experience in organizing and facilitating meetings,
workshops and writing reports
• Good interpersonal/communication skills
• Good oral and written communication skills in English
B.5TOR: Promotion and Knowledge Management Consultant
Working under the direct supervision of the Project Manager, the Promotion and Knowledge
Management Consultant will provide technical knowhow for capacity assessment and for planning,
design and implementation of the learning and Knowledge Sharing aspect of the Project. Under
UNDP policy guideline, activities should be dedicated to capturing best practices and lessons
learned, and raising the visibility of the project – both internally and externally. This sub-contract will
be guided by the related policies of the project which is seen in Appendix D: Visibility and Outreach
under the LECB Project and other pertinent guidelines.
Results from the project will be disseminated within and beyond the project intervention zone
through existing information sharing networks and forums at the sub-national, national, regional,
and global levels. The Project Management and Secretariat will work closely with the Programme’s
Global Support Component in conducting this activity to be assisted by the Promotion and
Knowledge Management Consultant.
The project team will also identify and participate, as relevant and appropriate, in scientific, policy-
based and/or any other networks, which may be of benefit to project implementation through
lessons learned.
The project will identify, analyze, and share lessons learned that might be beneficial in the design
and implementation of similar future projects. There will be a two-way flow of information between
this project and other projects of a similar focus, supported by the Programme’s Global Support
Unit. The Promotion and Knowledge Management Consultant shall assist the Project Management
and Secretariat in establishing and facilitating dialogue platforms for mitigation actions and low-
emissions strategies.
Tasks
1. Provide inputs for development and implementation of a promotion and knowledge
management program for the Project on GHG Inventory, NAMAS/LEDS and MRV system in
the sectors covered by the Project (viz., Transportation, Agriculture, Waste, and Industry)
2. Act as technical expert and resource person in the conduct of training and
seminar/workshops related to promotion and knowledge management program for the
Project
3. Design and assist in the establishment of a promotion and knowledge management
program for the project
52
4. Recommend institutional frameworks and coordination mechanisms that ensure successful
development and implementation of the promotion and knowledge management program
in GHG Inventory, NAMAS/LEDS and MRV system
5. Prepare a report on lessons learned derived from the Project implementation on GHG
Inventory, NAMAS/LEDS and MRV system
5. Other tasks that the NSC will identify as necessary to the success of the Project in attaining
its objectives.
Deliverables
• Report on the promotion and knowledge management program for the Project
• Inputs for the conduct of training and seminar/workshops related to promotion and
knowledge management
• Report on lessons learned from the Project
• Report on the dialogue platform designs and conduct of related activities.
Qualifications
• Advanced degree or higher (Master’s or higher) in areas relevant to climate change,
environment and national development
• Good knowledge of global and national climate change issues
• A minimum of 5 years of professional experience in the area relevant to the Project and
demonstrating ability in development and implementation of promotion and knowledge
management plans
• Demonstrated strong leadership, effective management skills, good coordination ability and
team working spirit
• Good organizational skills, with strong experience in organizing and facilitating meetings,
workshops and writing reports
• Good interpersonal/communication skills
• Good oral and written communication skills in English
53
APPENDIX C: VISIBILITY AND OUTREACH UNDER THE LECB PROJECT
CONTEXT
The Low Emission Capacity Building Programme is considered by its donors as an innovative
pathfinder project – allowing national governments to build capacities to plan their own low-
emission development pathways within the context of national circumstances and national
development goals. National teams are in the best position to identify on-the-ground experiences
that can be collated and disseminated.
As such, national LECB project teams are encouraged to program approximately 5% of their budget
for learning, knowledge sharing, communication and outreach activities and materials4. Visibility is a
major criterion from donors for measuring success and national teams are encouraged to develop an
outreach strategy the beginning of the project that is regularly monitored. At times, national teams
may be called upon to provide updates on their project progress for featuring in donor publications.
Required Visibility Products
National Fact Sheet/Case Study
Each national team is expected to prepare a National Factsheet/Case study that can be used at the
national and global levels (via the LECB Programme’s global website, newsletter, and other outreach
tools) to promote national project results and activities.
Lesson Learned/Best Practices Documents
Each national team is expected to produce a lessons learned/best practices document at the
completion of each project component to showcase their results and impacts. The Global Support
Unit will provide guidance on how to develop these best-practice documents, which will also be used
as guidance for other developing countries embarking on a LEDS/NAMA process.
Contributions to LECB Programme newsletter
The Global Support Unit will prepare a quarterly newsletter. National teams are required to
contribute with at least one newsletter article during the life of the project.
Recommended Visibility Products
National web page
National teams are requested to develop a web page or, at minimum, post relevant project activities
on the most appropriate institutional website. The Global Support Unit will link to the national page
from the global programme site, www.lowemissiondevelopment.org, and encourages similar
linkages to the global site wherever programme promotion is featured.
National media reports
National teams are requested to liaise with the communications focal point in the UNDP Country
Office regarding any media produced by or about the project, and to share media reports with the
Global Support Unit for global promotional efforts, including featuring on the programme website,
www.lowemissiondevelopment.org.
4 It is noted that these funds may be embedded in other activities, such as producing a Lessons Learned
document at the end of a project component, or developing a joint webpage with the government ministry
implementing the project and need not appear as a separate budget line or activity.