lean_construction_principles_may_2011.pptx
TRANSCRIPT
-
7/28/2019 lean_construction_principles_may_2011.pptx
1/75
LEAN CONSTRUCTION PRINCIPLES
Dick Bayer May 16, 2011
-
7/28/2019 lean_construction_principles_may_2011.pptx
2/75
BACKGROUND
Use the contractto influence how
we do work on
the project
Try partnering toinfluence how
we do work on
the project
-
7/28/2019 lean_construction_principles_may_2011.pptx
3/75
BACKGROUND
O A R
Change the observer
Cha
nge the
operatingsystem
-
7/28/2019 lean_construction_principles_may_2011.pptx
4/75
HOW DO WE MANAGE PROJECTS NOW?
Determine client requirements including quality,time and budget limits. Design to meet them.
ProgramDesign toProgram
PriceRedesignto Match
Price
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
5/75
HOW DO WE MANAGE PROJECTS NOW?
Break project into activities, estimating durationand resource requirements for each activity and
placing them in a logical order with CPM
Demolition
Grade & Fill
Foundations
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
6/75
HOW DO WE MANAGE PROJECTS NOW?
Assign or contract each activity, give start notice
and monitor safety, quality, time and cost
standards. Act on negative variance from
standards
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
7/75
HOW DO WE MANAGE PROJECTS NOW?
Coordinate with master schedule and weekly
meetings
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
8/75
HOW DO WE MANAGE PROJECTS NOW?
Reduce cost by productivity improvement
Reduce duration by speeding each piece or
changing logic
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
9/75
HOW DO WE MANAGE PROJECTS NOW?
Improve quality and safety with inspection
and enforcement
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
10/75
TRADITIONAL PROJECT MANAGEMENT:
A COHERENT COMMON SENSE
Activity Centered
(CPM)
Command &
Control
Organization
Transactional
OperatingSystem
Commercial
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
11/75
LEAN PROJECT MANAGEMENT:
A MORE COHERENT COMMON SENSE
2011 Lean Construction Institute
Flow CenteredCollaborative
Organization
Relational
OperatingSystem
Commercial
-
7/28/2019 lean_construction_principles_may_2011.pptx
12/75
LEAN TECHNIQUES AND PROCESSES
Three opportunities of lean
construction and design:
Impeccable coordination
The project as a production
system
The project as collective
enterprise
-
7/28/2019 lean_construction_principles_may_2011.pptx
13/75
LEAN TECHNIQUES AND PROCESSES
Impeccable coordination
Understanding the work
Collaborative planning
Reliable promising
-
7/28/2019 lean_construction_principles_may_2011.pptx
14/75
LEAN TECHNIQUES AND PROCESSES
Understanding the Work: Traditional Process
Common
Un
derstanding
CM/GC Hired
Major Trades Hired
Pre-Construction Services
Architect Hired
Engineers Hired
100%
SD DD CD
ConstructionOwner
-
7/28/2019 lean_construction_principles_may_2011.pptx
15/75
LEAN TECHNIQUES AND PROCESSES
Understanding the Work: Lean Project
Time
Common
U
nderstanding
CM/GC Hired
Concept Design Implementatio
n
Construction
Architect Hired
Engineers Hired
100%
Major Trades Hired
Pre-Construction Services
Valid.
Owner
-
7/28/2019 lean_construction_principles_may_2011.pptx
16/75
LEAN TECHNIQUES AND PROCESSES
-
7/28/2019 lean_construction_principles_may_2011.pptx
17/75
-
7/28/2019 lean_construction_principles_may_2011.pptx
18/75
PARADE OF TRADES: ASSUMPTIONS
1. The project is complete when 35 units have been processed
by each of seven trades in sequence.2. The trades come onto the project a week apart. Work is
completed and available to the next trade once a week.
3. The trades work in sequence, with each following trade able
to work only on what was produced in the previous week bythe prior trade.
4. Work is done by rolling a die (singular of dice) and passing
the number of units rolledup to the number of units the
trade has to work on.
5. The number rolled represents the amount of work
accomplished each week by the crew. On average each crew is
able to produce one unit of work in the week.
2009 Lean Construction Institute18
-
7/28/2019 lean_construction_principles_may_2011.pptx
19/75
Move 35 units of work through 7 trades.
Work is completed at the end of the week and passed to nexttrade. Place materials on table as shown.
Chips (the units of
work) & Score
SheetDie
Concrete
Mason
Facade
Paint
Electrical
Plumber
Carpenter 19 2009 Lean Construction Institute
PARADE OF TRADES
-
7/28/2019 lean_construction_principles_may_2011.pptx
20/75
1. Distribute score
sheets as directed
2. Chips on the left of
Concrete
3. Establish queue
spaces betweeneach trade and cup
at end.
4. Give die to Painter
5. FUNDAMENTALRULE: Chips move
right, dice move left
2009 Lean Construction Institute20
PARADE OF TRADES
-
7/28/2019 lean_construction_principles_may_2011.pptx
21/75
21
Mason rolls 2,
moves 2, leaving 1 in
inventory.
Hands the die to
Concrete.Records the result.
2011 Lean Construction Institute
PARADE OF TRADES
-
7/28/2019 lean_construction_principles_may_2011.pptx
22/75
Concrete rolls 3 and moves 3 chips.
Hands the die to the painter!
Records the result.
22
End of Week 1
Painter says,
Beginning week 2
Die passes left all the way
around the circle to the
Mason.
2011 Lean Construction Institute
PARADE OF TRADES
-
7/28/2019 lean_construction_principles_may_2011.pptx
23/75
23
Concrete rolls 2, passes 2,records.
Hands die to Painter.
Painter says, Beginning
week 3.
Week 2: Mason rolls 2; passes 2, 1 ininventory. Mason records 2, hands die to
Concrete.
2011 Lean Construction Institute
PARADE OF TRADES
-
7/28/2019 lean_construction_principles_may_2011.pptx
24/75
Week 3: Facade rolls, passes & records.
Hands die to Mason. Mason rolls, recordsand hands die to Concrete. And so it goes.
2011 Lean Construction Institute
PARADE OF TRADES
-
7/28/2019 lean_construction_principles_may_2011.pptx
25/75
Concrete
Carpenter
Mason
Facade
Electrical
Paint
35
Plumber
Chips
Keep
passing
the dieto the
left!
25 2009 Lean Construction Institute
PARADE OF TRADES
-
7/28/2019 lean_construction_principles_may_2011.pptx
26/75
PARADE OF TRADES
Record the week
each Trade finishes.Sum and record the
Available Capacity
for all Trades. Sum
and record the totalRemaining
Inventory for all
Trades except
Concrete. Note the
highest amount of
Inventory in any
week for each
trade. Call out
scores when asked. 26
Craft Week CompleteTotal Capacity
(Sum "Column 1")
Total Inventory
(Column 3)
Highest inventory
in any week forthis trade
Concrete
Mason
Faade
Carpenter
Plumber
Electrical
Paint
Sum ofColumn
Circle Color of Dots on Die Blue Black Red
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
27/75
27 2011 Lean Construction Institute
PARADE OF TRADES
Scheduling:
How many weeks will
it take you to move 35
pieces of workthrough 7 trade
stations?
Profitability:
Whats the number of
resources you will use
to move 35 pieces ofwork through 7 trade
stations?
-
7/28/2019 lean_construction_principles_may_2011.pptx
28/75
RESULTS
1.2.2.5.5.6 1.2.3.4.5.6 2.2.3.4.5.5 2.3.3.4.4.5 3.3.3.4.4.41.1.1.6.6.6
Average
Worst
Best
28 2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
29/75
LEAN TECHNIQUES AND PROCESSES
Collaborative Planning
Delay decisions to last responsible
moment
Use Pull Planning to Create Schedules
Reliability of work flow
Only do work to release downstream crews(important also in design)
-
7/28/2019 lean_construction_principles_may_2011.pptx
30/75
LEAN TECHNIQUES AND PROCESSES
Collaborative
Planning
Chilled WaterPlant
3-D BIM model,
located the
equipment on the pad,connected the piping and
identified the hangers . . .
-
7/28/2019 lean_construction_principles_may_2011.pptx
31/75
LEAN TECHNIQUES AND PROCESSES
Collaborativ
e
Planning:
. . .then
designed the
structure to
carry the
building
components
-
7/28/2019 lean_construction_principles_may_2011.pptx
32/75
LEAN TECHNIQUES AND PROCESSES
Collaborative
Planning
Short loopdesign iterations
using budget as a
design criteria
-
7/28/2019 lean_construction_principles_may_2011.pptx
33/75
LEAN TECHNIQUES AND PROCESSES
Collaborative Planning: Set Based Design
Create Analyze Converge Decide
-
7/28/2019 lean_construction_principles_may_2011.pptx
34/75
LEAN TECHNIQUES AND PROCESSES
Reliable Promising:
in Design and
Construction
Pull planning for
design efforts
-
7/28/2019 lean_construction_principles_may_2011.pptx
35/75
LEAN TECHNIQUES AND PROCESSES
Reliable Promising:
in Design and
Construction
-
7/28/2019 lean_construction_principles_may_2011.pptx
36/75
LEAN TECHNIQUES AND PROCESSES
Reliable Promising: in Design and
Construction
-
7/28/2019 lean_construction_principles_may_2011.pptx
37/75
IMPECCABLE COORDINATION & PRODUCTIONSYSTEM DESIGN
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
38/75
Begin with blank card
Goal is to produce a card that looks like this . . .
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
39/75
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
40/75
Station 1 performs any necessary layout
for installation
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
41/75
Station 2 is responsible for assuring batch
size
Batches of 5 must be punched and
secured with a paper clip
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
42/75
Station 3 is responsible for
installing the green dot
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
43/75
Station 4 is responsible for installing 3
red dots
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
44/75
Station 5 is responsible for installing the
yellow dot
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
45/75
Station 6 is responsible for installing
star on yellow dot
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
46/75
PHASE 1 LOGISTICS
Workstations in work flow sequence
Materials located at workstation
Workstations 2-7 have an incoming queue
space
Completed Batches of 5 placed in queue
space of next station
Batches remain together until final
inspection
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
47/75
PHASE 1 POLICIES
Workers perform only their assigned tasks - NO
THINKING
Maintain Batch integrity - BUILD IT IF YOU CAN
and PASS IT ON IF YOU CANT.
QC Problems only detected by Inspector - NOFEEDBACK - NO TALKING
All QC problems set aside by inspector as rework -
TURN UPSIDE DOWN
QC Inspector announces first good product.
Assemblers are paid by the piece, period.
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
48/75
PERFORMANCE METRICS
Production: the number of good cards
produced in each 6 minute phase.
Time: the time it takes the first good card
to get through the system.
Rework: the number of cards set aside to
indicate defects in configuration or fit.
Work-in-Progress Inventory (WIP): the
number of subassemblies on the table at
the end of the 6 minute phase.
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
49/75
YOUR HYPOTHESES
How many good cards will your team producein Phase I?
How long will it take for you to produce the
first good card? How much rework will you generate (cards set
aside)?
How much WIP will you generate(subassemblies left on the table)?
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
50/75
HOW COULD THIS SYSTEM BE
REDESIGNED FOR BETTER
PERFORMANCE?
2011 Lean Construction Institute
PHASE 2 LOGISTICS
-
7/28/2019 lean_construction_principles_may_2011.pptx
51/75
PHASE 2 LOGISTICS
Workers may have only one assembly at their
workstation
Only 1 assembly allowed in queue space
between stations (Batch size of 1)
Assembly can only be placed in queue when it isempty (pull mechanism).
Workstations in Work Flow Sequence
Materials located at station
Stations 2-7 have an incoming queue space
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
52/75
PHASE 2 POLICIES
QC Problems may be verbalized by any worker SOME THINKING and TALKING ALLOWED
All QC problems set aside as rework at stationdiscovered.
TURN UPSIDE DOWN
Everyone is paid hourly wages plus a bonus forteam performance.
Workers perform only their assigned tasks Workers cannot fix QC problems from upstream
Inspector announces first good card.
2011 Lean Construction Institute
PHASE 3 LOGISTICS
-
7/28/2019 lean_construction_principles_may_2011.pptx
53/75
PHASE 3 LOGISTICS
Workload may be re-sequenced and/or
rebalanced by the team Workers may have only one assembly at their
workstation
Only 1 assembly allowed in queue space betweenstations (Batch size of 1)
Components can only be placed in queue when itis empty (pull mechanism).
Workstations in Work Flow Sequence Materials located at station
Stations 2-7 have an incoming queue space
2011 Lean Construction Institute
PHASE 3 POLICIES
-
7/28/2019 lean_construction_principles_may_2011.pptx
54/75
PHASE 3 POLICIES
Workers perform ANY step in theproduction process.
QC problems can be fixed by any worker -Fix it when you find it.
No restrictions on talking. Everyone is paid hourly wages plus a bonus
for team performance.
Inspector announces first good card.
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
55/75
YOUR HYPOTHESES
How many good cards will your teamproduce in Phase III?
How long will it take for you to produce the
first good card?How much rework will you generate (cards
turned upside down)?
How much WIP will you generate(subassemblies left on the table)?
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
56/75
THE DOT GAME
1. What are the key points or lessons for you?
2. How might these apply to designing and
building? How could you use what you have
learned on your project?
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
57/75
GOALS FOR PRODUCTION SYSTEM DESIGN
Match throughput rate to demand rate Minimize cycle time
Reduce WIP to the minimum needed tomaintain throughput
Minimize resources required
2011 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
58/75
LEAN TECHNIQUES AND PROCESSES
Reliable Promising: in Design andConst.
0
0.1
0.2
0.3
0.4
0.50.6
0.7
0.8
0.9
1
0
0.1
0.2
0.3
0.4
0.50.6
0.7
0.8
0.9
1
33308333163332333330333373334433351333783338533393334063342733432 33439
PPC
4 Week Moving Average
Planning System Measurement
-
7/28/2019 lean_construction_principles_may_2011.pptx
59/75
LEAN TECHNIQUES AND PROCESSES
Production System Design
C Q S OC SS S
-
7/28/2019 lean_construction_principles_may_2011.pptx
60/75
LEAN TECHNIQUES AND PROCESSES
Production System Design:
Target Value Design
Pull planning
Built in Quality Plan Safety Plan
First Run Studies
Metrics
LEAN TECHNIQUES AND PROCESSES
-
7/28/2019 lean_construction_principles_may_2011.pptx
61/75
LEAN TECHNIQUES AND PROCESSES
Collective Enterprise: Maximize the whole, not
the pieces
LEAN TECHNIQUES AND PROCESSES
-
7/28/2019 lean_construction_principles_may_2011.pptx
62/75
LEAN TECHNIQUES AND PROCESSES
Collective Enterprise: Maximize the whole, not
the pieces
Contingency
CM/GC
Architect
Mechanical
Electrical
Engineering
Steel
Drywall
Conc. Civil
Glazing
Profit
-
7/28/2019 lean_construction_principles_may_2011.pptx
63/75
BUILDINGS LEAK AT THE
INTERSECTION OF CONTRACTS
Waterproofing
Structural steel
Roofing
Window
Caulking
Masonry
Concrete
Excavation
Foundation
Wall stud
Todd Zabelle
2010 Lean Construction Institute
-
7/28/2019 lean_construction_principles_may_2011.pptx
64/75
KEY LEARNINGS
The larger system is the focus of managementattention, not local optimization
Stakeholder interests are aligned through
shared risk and reward Product life cycle stages are considered in the
development of the value equation
Product and process are designed together;indeed, all design criteria are considered when
generating and selecting from design options
-
7/28/2019 lean_construction_principles_may_2011.pptx
65/75
KEY LEARNINGS
Downstream players are involved in upstreamwork, and vice-versa
Continuous learning and innovation is the real
end game Variation is attacked and reduced variation in
work load, in process durations, in product
quality, in plan reliability,
-
7/28/2019 lean_construction_principles_may_2011.pptx
66/75
KEY LEARNINGS
Inventory, capacity, schedule and financialbuffers are sized and located to perform their
function of absorbing variability that cannot yet
be eliminated
The rule followed for release of work between
connected specialists is: Flow where you can, Pull
where you cant, Push where you must
Activities are performed at the last responsible
moment
-
7/28/2019 lean_construction_principles_may_2011.pptx
67/75
WHOS DOING LEAN?
Healthcare Projects (IPD or IPD-ish):
Sutter Health, Northern California
Camino Medical Center (DPR)
Castro Valley (Turner)
Cathedral Hill (Herrero/Boldt)
Palo Alto Medical Center (Skanska)
Sacramento General (renovation/new: Boldt)
-
7/28/2019 lean_construction_principles_may_2011.pptx
68/75
WHOS DOING LEAN?
Healthcare Projects:
UHS, company-wide
Texhoma
Temecula: Reducing sqft costs to $900/
SSM,
Cardinal Glennon, St. Louis
St. Claire, Fenton, Mo.
-
7/28/2019 lean_construction_principles_may_2011.pptx
69/75
WHOS DOING LEAN?
Healthcare Projects:
Affinity Healthcare, Appleton, Wis.
Augusta General, Maine
Martin Memorial, Stuart, Fla.
Seattle Childrens
Theda Care, Wisconsin
-
7/28/2019 lean_construction_principles_may_2011.pptx
70/75
WHOS DOING LEAN?
Public Projects:
School Projects:
Middle School, Dallas
Middle & High Schools, Los
Angeles
Community College, San Diego
St. Olaf College, Minnesota
Community College, Cleveland
-
7/28/2019 lean_construction_principles_may_2011.pptx
71/75
WHOS DOING LEAN? DESIGN FIRMS
-
7/28/2019 lean_construction_principles_may_2011.pptx
72/75
WHOS DOING LEAN? CONSTRUCTION FIRMS
-
7/28/2019 lean_construction_principles_may_2011.pptx
73/75
WHOS DOING LEAN? CONSTRUCTION FIRMS
-
7/28/2019 lean_construction_principles_may_2011.pptx
74/75
WHOS DOING LEAN? TRADES
Visit www.leanconstruction.org for all of our Corporate
members
http://www.leanconstruction.org/http://www.leanconstruction.org/ -
7/28/2019 lean_construction_principles_may_2011.pptx
75/75
THANKS!
Dick Bayer
Interim Executive Director
858-373-8449
mailto:[email protected]:[email protected]