leaflet no.3

Upload: sabra-as

Post on 05-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Leaflet No.3

    1/8

    XYZ Engineering ServicesDesign & Construction of Dynamic Superstructures REF: SAB-035/2003

    REV: 00

    PAGE 1 of 1

    [email protected]

    SUBJECT: RECOMMENDATIONFORCONVERSIONOFBULK/TANKSFUELSROADTANKERSTOBOTTOMLOADINGANDINSTALLATIONOFVAPOURRECOVERYSYSTEM

    ONE LEAFLETMinimum Requirements for road tank vehicles

    Draft Requirements

    DOC. NUMBER SAS- 03/ 2010

    RELEASE DATE 01, MAY, 2010

    RELEASE STATUS DRAFT - One fleet team

    The purpose of this leaflet is to give instructions on the conversion of road tankers to BOTTOMLOADING and the installation of the VAPOUR RECOVERY SYSTEM (VRS) in compliance with theEC directive regarding the vapour recovery at installations, distribution and gas stations (STAGE 1 a &b, COM 93 422 FINAUSYN 425).The specifications mentioned below are derived from IP standards (Edition May 1995), API standards,the EC directive, JPRC regulations.

    A. PARTS AND EQUIPMENT NEEDED

    The necessary parts and equipment needed for the conversion of road tankers toBOTTOM LOADING & VAPOUR RECOVERY are:

    1. Foot valves2. Fuel couplings3. Vapour coupling4. Pressure/Vacuum valve (vents)5. Manhole system

    6. Overfill protection system7. Vapour Recovery; overfill protection and earthing detection system.8. Interlock system9. Vapour recovery line piping10. Dip stick assembly11. Pneumatic system

    B. DESCRIPTION AND POSITIONING OF THE EQUIPMENT

    The general layouts of the installed equipment are identified by SABRA design.The dimensions on the drawing derive from API standards. Actually for some of those dimensions, asdescribed below, some deviations of the above standards are necessary. More specifically thespecifications of the above equipment are:

  • 7/31/2019 Leaflet No.3

    2/8

    XYZ Engineering ServicesDesign & Construction of Dynamic Superstructures REF: SAB-035/2003

    REV: 00

    PAGE 1 of 1

    [email protected]

    1. Pneumatic 4 inch footvalves

    The footvalves preferable to be pneumatic rather than mechanical, non-pressure balanced, 4inch, according to API standards. With the installation of the footvalves all the components andpipe lines comprising the system between the couplings and the footvalves should bedesigned for an operating pressure of 500 kPa (75 psi) and will not allow any leak for pressure1.5 times higher of the operating pressure. Any component that does not meet theserequirements should not be used in a bottom loading road tanker.

    The footvalves can be normal, low profile or extra low profile according to the needs of the

    conversion but should always meet the API standards.

    2. Fuel Couplings

    It is male 4 inch API standard as defined in the following publication:API RECOMMENDED PRACTICE 10047th EDITION, NOV. 1988"Bottom Loading and Vapour Recovery for MC-306 Tank Motor Vehicles"

    I. SPECIFICA TIONThe fuel coupling should have the basic configuration, in the open position; thecoupling should have a clear unobstructed opening 2 inch depth from the outer face orclosure of the valve and an opening of 4 inch diameter. The mating action should bedesigned to limit the entrapment of liquid to not more than 2 ml thus dry-breakcouplings should be used.The coupling may be opened by manual or automatic means for loading and it shouldbe capable of being opened by the hydraulic force of the liquid being loaded. Pressureloss must be minimal.Two - way flow should be provided. This can be achieved with the appropriatelydesigned coupling with an external means for opening and closing the valve.

    Coupling liquid seals and sealing surfaces should be protected from mechanicaldamage. The mating liquid seals should be part of the loading hose coupling forloading and the discharge hose connection for unloading.The non-metallic for all of the seals should be suitable for liquids high in aromatics,olefins and oxygenates as appropriate.

    A drip cap with a liquid-tight seal should be provided to prevent leakage and to protectthe coupling. The drip cap should be permanently attached to the coupling with achain or strap.

    II. POSITIONING OF THE COUPLINGS

    The bottom loading couplings (as well as all the other controls of the vapour recoveryand bottom loading system) should be installed on the right hand side of the lorry andeffectively protected against side collision of the vehicle, to prevent damage andleakage, by means of a locking bar.The overall size of the coupling, including any handles or controls, should permit easyoperation with gloved hands. The distance between the centers of adjacent couplingsshould be 300 mm. However in reality this distance should be slightly longer for theconvenience of the driver (330 mm ), especially when the overall number of thecompartments is such that the space between the couplings is not enough and wouldcreate a problem during connection for loading (the loading arm is not long enough)The distance from the face of the couplings to the maximum width of the vehicle in thearea of the couplings should not be more than 150 mm.

  • 7/31/2019 Leaflet No.3

    3/8

    XYZ Engineering ServicesDesign & Construction of Dynamic Superstructures REF: SAB-035/2003

    REV: 00

    PAGE 1 of 1

    [email protected]

    The overall length of the couplings envelope should not exceed the 2 m. Also the

    couplings must be installed not higher than 1 m (unlaoded) and not lower than 0.7 mwhen the vehicle is fully loaded.When, due to the number of the compartments, the overall length of the couplingsenvelope exceeds the planned, the arrangement of the couplings in two levels isallowed in the way that is provided by SABRA design.

    III. HOSE COUPLING

    The mating action should be if possible of the push type with provision for loadingwithout rotating the loading hose coupling. The coupling should permit mating in anyposition in a range of 360 degrees, without any coupling operating lever interferingwith an adjacent coupling.A safety interlock with two-stage action should be provided on the coupling to preventany liquid flow whilst coupling or uncoupling the loading hose.

    A typical loading hose coupling together with a simple description of its interlocksystem will be detailed on offer.

    3. Vapour Recovery Coupling

    It is male 4 inch API standard as defined in the following publication:API RECOMMENDED PRACTICE 10047th EDITION, NOV. 1988"Bottom Loading and Vapour Recovery for MC-306 Tank Motor Vehicles"

    I. SPECIFICATIONTo avoid connection of the vapour recovery line to the fuel line the coupling ofthe Vapour Recovery System (VRS) should be 4 inch cam and groove quickcoupling self-sealing type.It is essential that the connection of the vapour recovery line is detected andthe signal should be send to the Vapour Recovery, overfill protection andearthing detection plug.

    II. POSITION

    The distance between the VRS coupling and the fuel couplings must not begreater than 2.2 m. However the distance between the vapour coupling andthe nearest fuel coupling must be at least 400mm to allow handling. Also theVRS coupling must not be installed higher than 1 m in unladen condition and

    not lower than 0.7 m when the vehicle is fully loaded.

    4. P/V valves and vapour vents

    The vapour vents should open simultaneously with the footvalves and from the same control.They should be positioned either on the manhole system or on the top of the compartment.The connection should be with a flange.The P/V valves that will be installed must be designed to open at an internal tank pressure 20-50 mbar (vacuum) and 70-120 mbar (pressure).The actual calibration should take place after a test with the existing loading rates.

    In the event of overturning of the vehicle they should be closed automatically to avoid leakage.

    5. Manhole system

  • 7/31/2019 Leaflet No.3

    4/8

    XYZ Engineering ServicesDesign & Construction of Dynamic Superstructures REF: SAB-035/2003

    REV: 00

    PAGE 1 of 1

    [email protected]

    It should be API compliant, light, low profiled and it will be connected to the tank with a flange.The system must have a dual opening system and a special opening key. The manhole bodyshould have (preferably) on it all the provision (holes) for the connection of P/V valve, VRSconnection, overfill detection equipment and the dip stick I conductor tube connection.

    6. Overfill protection system

    The overfilled protection system that will be used should be five (5) wire optical. The probemust be placed and adjusted in such a position that a volume of 120 It. or 5% of thecompartment (when the compartment is bigger than 2400 It.) is left as an empty space in eachcompartment. The probe can be installed either in a special place in the manhole system orpermanently attached in the top of the compartment. The signal of the probe end in thedetection system plug.

    The overfill protection system must be installed in every compartment of the vehicle andshould be designed to perform self checks before loading and its operation should be fail safe.The system is not activated under normal operation and therefore regular system checks arenecessary to ensure reliable operation.

    It is noted that the replacement of the dip sticks is required after the conversion of the roadtanker to bottom loading so that the volume of the piping after the footvalve and up to thecoupling is included in the compartment volume.

    7. Vapour Recovery; overfill protection and earthing detection socket

    API standard three "J" slot socket according to API 1004

    This socket receives the signals of the optic sensor of the overfill protection system, earthingand VR coupling sensor. The whole detection system is installed so as to prevent loading ifone of the above connections has not been made correctly.

    8. Interlock systemTo avoid leakage and other hazards adequate measures will be taken to prevent the movingof the vehicle until the footvalves and the vents are closed, the earthing and the plug has beendisconnected and all the loading and vapour recover couplings have been disengaged fromthe vehicle.

    This is done with the installation of the following interlock system:A hinged faucet guard bar is installed, that its position can be identified with a pneumaticswitch, that prevents any movement of the vehicle, with the engagement of the vehicle brakes,until it is in the down position (which means that all the above have been disconnected). The

    overfill plug and the vapour coupling are protected in the same way.

    The guard bar must have at least at three arms (one at every end and in the middle) andadequately supported in the up and down position by elastic clips.

    The pneumatic interlock system must include an override switch that will be located in thecontrol box and will be sealed by the company and will be used only in cases of interlocksystem failure in order to prevent immobilization of the road tanker. After the repair of thedamage, the override switch must be sealed again to ensure the proper function of theinterlock system.

    9. Vapour recovery line piping

  • 7/31/2019 Leaflet No.3

    5/8

    XYZ Engineering ServicesDesign & Construction of Dynamic Superstructures REF: SAB-035/2003

    REV: 00

    PAGE 1 of 1

    [email protected]

    The vapour recovery manifold must be of adequate capacity to avoid stressing the tank from

    the vapour pressure at maximum loading rate. The fuel piping must be 4 inch. The vapourrecovery line must have a minimum area equivalent in cross section to a 4 inch pipe.The designing of the VRS must allow the complete drainage of the line by gravity of any liquidthat might accumulate therefore a slight inclination of the vapour recovery line is essential inthe horizontal parts of the piping; therefore an inclination of the pipe is necessary. Also thedesign must allow easy gas freeing of the tank for repair. There should also be an inclinationof at least 3 degrees to the fuel line between the footvalve and the coupling.To avoid confusion the vapour recovery line must be painted ORANGE. The vapour line,provided that it ends in a coupling with a distance not greater than 2.2 m from the fuelcouplings, can be passed either from the front side of the tank or through a centralcompartment, according to construction needs.The fuel piping must end in a pipe segment with a side glass attached to it just before the fuelcoupling.

    10. Dip stick assembly

    The flow of the fuel (2500 It. /min through 4 inch pipe) is high enough to create static electricityso the installation of earth bonding between the higher and the lower part of each ompartmentis essential to avoid the generation of a spark.

    Special consideration must be given to the type of metal used in earth bonding so as to avoidthe effect of electrochemical corrosion due to the existence of bimetallic surface in the joiningarea. Therefore the earth bonding must be a conductor of the same metal as the tankapproximately 8 to 10 mm diameter.

    Iso-dynamic connection is achieved by the dip stick assembly that is electrically connected tothe bottom of the tank by flexible conductors. The flexible conductors must ensure theconstant electrical continuity between the top and bottom of the compartment and should notstress the tank because of its dimensional tolerances.

    After the conversion of the road tanker to bottom loading the replacement of the dip sticks isessential to include the volume between the footvalve and the fuel coupling and the possiblechanges in tank compartment.

    11. Pneumatic system

    It comprises of the manual controls (located near the fuel couplings) all the equipment andpiping that end in the footvalves, vapours vents, locking bar switch and emergency switch. Thepneumatic controls must be located in a control cabinet with a door opening at a wide angle.The pneumatic circuit connection must be such so as the manual control/switch that isrespective to each compartment opens / closes at the same time both the footvalve and the

    vapour vent. The emergency switch closes the footvalves and vapour vents of ALL thecompartments and it is located close to the drivers side. There is also another switch with thesame function in the control box.

    The pneumatic system lines are placed in a metallic pipe or frame for protection.

    C. ELECTRICAL SYSTEM

    The response time of the electrical overfill protection system should be as short as possible and at anycase not bigger than 0.5 sec. The socket pin connection as well as the coloring of the electrical systemwires should be with accordance to the IP standards (Edition May 1995).

    The vehicle high level cut-off control circuits should be both physically and electrically isolated from thevehicle circuits by using dedicated conduits and junction boxes with round corners to avoid damage to

  • 7/31/2019 Leaflet No.3

    6/8

    XYZ Engineering ServicesDesign & Construction of Dynamic Superstructures REF: SAB-035/2003

    REV: 00

    PAGE 1 of 1

    [email protected]

    the wires. All the wires should be insulated and inside a PVC tube. The PVC pipe must be placed

    inside a iron pipe or other metallic frame. There should be special care so as to simplify futuremaintenance and repair of the system. That can be achieved by placing the PVC pipe inside a metallicconduit that will comprise of pipe segments not permanently connected. The wires within the pipesmust be continuous without any brakes or junctions.

    SABRA shall be in accordance with the CENELEC Standard EN 50014 to EN 50020 and EN 50039 asappropriate.Any electrical subsystem that will be used for the control of the overfill protection should be certifiedintrinsically safe Eex-ia suitable for operation in zone 0, standard class BS 5501 part 7.

    D. GENERAL DIRECTIONS

    i. All welds on the tank barrel and under-structure are to be left in the as-welded condition.

    ii. All gaskets should be of conductive material.iii. All authorized road tankers designed for bottom loading must have a sign on the same side of

    the couplings stating, with letters at least 10 mm high, the maximum number of compartmentsthat can be loaded simultaneously, the type of the installed optic overfill protection probes, thatnon-pressured balanced footvalves are installed, the capacity of each compartment and thatall measurements in the compartments should be made with the respective footvalve open.

    iv. Every three (3) months the road tankers must be checked regarding their water tightness.v. All the VRS components to be installed on the top of the tank must be protected against

    damage in the event of overturning. This can be achieved by confining them within the limits ofthe tank shell contour. The shell contour must be at least 20 mm higher of the highest point ofthe equipment installed.

    vi. There should be a cut-off switch placed inside the cabin that isolates the electric circuit of thevehicle from the battery. The position of this switch is identified by a special led in the cabin.

    vii. The couplings must be adequately fastened, with screws, to an appropriate metal face that is

    welded to the chassis of the road tanker so as to avoid their oscillation during movement of thevehicle.

    viii. The vehicles' guard bars must be, with regard to their support, totally isolated from the supportstructure of the couplings.

    E. MATERIALS

    1. Manhole System with two or three accessory holes.The manhole cover must be self latching, two stage opening, lockable (including key) andopen 180. The system must include:

    (a) P/VN valve with rollover seal appropriate for loading rates up to 2500 It. /min

    (b) Emergency venting in case of fire engulfment. The manhole system must be made ofaluminum or aluminum alloy, the vent and base seals of viton and designed and constructed inaccordance with petroleum spirit regulations (S.1. 1059) or equivalent.

    2. Foot valve 4" (100 mm nominal bore) pneumatically operated non pressure balanced.

    It can be normal, low or very low profile. It should be made or aluminum or aluminum alloy andhave viton seals. It must be appropriate for loading rates up to 2500 It. /min and allow the fuelto enter the tank compartment sideways through a strainer. It should be of such design as toallow easy maintenance and have a mechanism for manual opening / closing in case of airsystem failure.

  • 7/31/2019 Leaflet No.3

    7/8

    XYZ Engineering ServicesDesign & Construction of Dynamic Superstructures REF: SAB-035/2003

    REV: 00

    PAGE 1 of 1

    [email protected]

    3. Vapour Recovery vent pneumatically operated.

    3" or 4" (please specify) made of aluminum or aluminum alloy and have viton seals. Thevapour recovery vent must include hood flame arrester hose (not less than 300 mm in length)and connecting flange. The mechanism must allow the poppet to open into the tank to preventsurge pressure leakage and spillage via the vent in case of tank rollover.

    4. Dip tube assembly

    Compatible with above described manhole system. Must be of lightweight construction withquick release cup. Its length must be about 2000 mm.

    5. API standard 4" tank truck adaptor

    Openable or non openable with or without side glass. It must be of lightweight aluminum oraluminum alloy construction, including metallic or plastic dust cap.

    5.1. Gravity coupler4" API to 3" (hose) with no actuator and with actuator appropriate for the adaptorsdescribed above.

    5.2. Gravity coupler4" API to 3" Cam-lock coupler on hose connection with no actuator and with actuatorfor the adaptors described above.

    6. Vapour Recovery API4" adaptor

    With sight glass and metallic or plastic cap or with no sight glass, with drilledmounting pad for air interlock valve.

    6.1 Air interlock valve for item 6

    7. Pneumatic interlock valve/mechanism for locking bar

    Part of the pneumatic system acts on the vehicles brakes.

    8. Pneumatic system control panel

    It must be with control valves for at least 3 compartments tank truck, light weight with visualindicators (mechanical or electrical) and valve numbering. It must also have a master switch(pneumatic) with visual indicator.

    Options:(a) Pressure Gauge(b) Housing weather proof (metallic or GRP) with locking mechanism.

    The pneumatic system must have all accessories required for air filtering, pressure regulation(throttle) 3/2 way valves (for operating the foot valve and the vapour vent, simultaneously).Control valve for allowing the vehicles air brakes to operate while by-passing the otherpneumatic mechanism when air pressure is low. The system must include a pneumaticmaster/emergency switch away from the control panel which would override all the pneumaticsystem, shut all foot valves and vapour vents but allow the vehicle to move (in case of lockingbar failure).

    The system must include all appropriate push-in connectors and at least 80m UN proof tubingfor the air tube plumbing.

  • 7/31/2019 Leaflet No.3

    8/8

    XYZ Engineering ServicesDesign & Construction of Dynamic Superstructures REF: SAB-035/2003

    REV: 00

    PAGE 1 of 1

    [email protected]

    9. Overfill protection system.

    It must have a 5 wire optic sensor. The optic probe must be stainless steel at least 250 mmlong and have a 2" housing with BSP thread and viton seal. The housing allows the lengthadjustment of the sensor probe. The system must include the 5 wire connectors and 5 wireconductor with color coded jacketed cables and strain relief fittings.

    9.1 Female socket with J-slots together with plastic cap

    It must be min. 2 pin - 5 wire (to service up to 3 compartments min.) for 5 wire optic sensingoverfill protection system, earth connection and vapour connection line interlock.The socket must have stainless steel contact pins must be durable and corrosion resistant andallow secure fixing on to the vehicle.

    Options:

    (a) Break interlock: pneumatic - electrical(b) Socket testing equipment