landslide current availability and methodology for natural risk map production armonia project...
TRANSCRIPT
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-1
B.III Landslides
Authors: Giuseppe Delmonaco, Daniele Spizzichino, T6
1 Definition of Landslide..................................................... 4
2 Landslides classification .................................................. 4
2.1 Material type ............................................................................5
2.2 Landslide activity ......................................................................6
2.2.1 State of activity.........................................................................6
2.2.2 Distribution of activity ................................................................8
2.2.3 Style of activity .........................................................................8
2.3 Landslide causes .......................................................................9
3 Intensity or Magnitude (I)............................................. 10
3.1 Velocity.................................................................................. 10
3.2 Dimension.............................................................................. 12
3.3 Energy................................................................................... 13
3.4 Consequences......................................................................... 13
3.5 Hybrid ................................................................................... 14
4 Return period of landslides............................................ 15
4.1 Geomorphological criteria or qualitative analysis......................... 15
4.2 Analysis of temporal series related to effects.............................. 15
4.3 Analysis of temporal series related to causes ............................. 16
4.3.1 Precipitation............................................................................16
4.3.2 Earthquakes............................................................................17
4.4 Monitoring.............................................................................. 18
4.4.1 Mechanical approach ................................................................18
4.4.2 Kinematics approach ................................................................18
5 Hazard assessment (H) ................................................. 19
5.1 Basic concepts ........................................................................ 19
5.2 Prediction of landslide types ..................................................... 20
5.3 Prediction of landslide intensity................................................. 20
5.4 Prediction on landslide affected area ......................................... 21
5.4.1 Methods of relative hazard analysis ............................................21
5.4.1.1 Qualitative methodologies...................................................21
5.4.1.1.1 Field geomorphologic analysis .........................................21
5.4.1.1.2 Combination of index maps or heuristic approach...............22
5.4.1.2 Quantitative methodologies.................................................23
5.4.1.2.1 Statistical analysis .........................................................23
5.4.1.2.2 Geotechnical models ......................................................25
5.5 Temporal prediction ................................................................ 27
5.5.1 Analysis of return time .............................................................27
5.5.2 Analysis of intensity/magnitude .................................................29
5.6 Prediction of evolution ............................................................. 29
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-2
5.6.1 Prediction of run-out ................................................................30
5.6.2 Prediction of retrogression limits ................................................30
5.6.3 Prediction of lateral expansion ...................................................30
6 Landslide hazard mapping............................................. 30
6.1 Introduction ........................................................................... 30
6.2 Susceptibility and hazard mapping............................................ 31
6.3 Hazard zoning scales ............................................................... 33
6.4 Landslide Hazard map types..................................................... 33
6.5 Approaches to landslide mapping.............................................. 34
6.5.1 The Inferential Approach...........................................................34
6.5.2 The Statistical Approach ...........................................................34
6.5.3 The Process-Based Approach.....................................................35
6.6 The mapping unit for GIS Technique ......................................... 35
7 Element at Risk (E) or exposure .................................... 36
7.1 Definition ............................................................................... 36
7.2 Cartography related to the element at risk - Map of Exposure -.... 37
7.3 Economic value of element at risk............................................. 37
7.3.1 Human life Value .....................................................................38
7.3.2 Goods and activities value.........................................................38
7.3.3 Global Value ...........................................................................39
8 Vulnerability (V) ............................................................ 39
8.1 Vulnerability: some web definitions ........................................... 40
8.2 Conceptual approach: vulnerability assessment.......................... 40
8.2.1 Definition ...............................................................................40
8.2.2 Vulnerability components..........................................................41
8.3 Human life vulnerability ........................................................... 42
8.4 Vulnerability of good and activities............................................ 42
9 Analysis of Risk (R) ....................................................... 45
9.1 Definition ............................................................................... 45
9.2 Qualitative analysis ................................................................. 45
9.2.1 Damage propensity..................................................................45
9.3 Quantitative analysis ............................................................... 46
9.3.1 Total risk................................................................................46
9.3.2 Potential damage (WL)..............................................................47
9.3.2.1 Rigorous assessment .........................................................48
9.3.2.2 Simplified assessment. .......................................................49
9.3.3 Specific Risk (Rs) .....................................................................50
9.4 Probability of acceptable rupture............................................... 50
10 Risk management.......................................................... 52
10.1 Introduction ........................................................................... 52
10.2 Framework for landslide risk management ................................ 53
10.2.1 General framework ..................................................................53
10.2.2 Increasing of social acceptable threshold risk...............................54
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-3
10.3 Acceptable and tolerable risk from landsliding............................ 55
10.3.1 General issues.........................................................................55
10.4 Treatment.............................................................................. 57
10.4.1 Risk mitigation through structural action and measures.................58
10.4.2 Risk mitigation with non-structural action and measures ...............58
10.5 Public Awareness, Education and Capacity Building .................... 59
10.6 Emergency Preparedness Plan.................................................. 59
10.6.1 Before the Landslide ................................................................59
10.6.2 When it Rains..........................................................................60
10.6.3 Key Considerations ..................................................................61
10.6.4 What Can You Do If You Live Near Steep Hills ..............................61
10.6.4.1 Prior to Intense Storms: .....................................................61
10.6.4.2 During Intense Storms:......................................................61
10.6.5 After the Disaster ....................................................................62
10.7 The Phases of emergency Plan (planning, response, recovery) .... 62
10.7.1 Emergency Phases...................................................................62
10.7.2 Planning Phase........................................................................62
10.7.3 Response Phase ......................................................................63
10.7.3.1 Initial Response.................................................................63
10.7.3.2 Extended Response............................................................64
10.8 Recovery Phase ...................................................................... 64
11 Glossary of all keywords................................................ 64
12 Bibliography .................................................................. 70
13 Appendix: Operational Standards for Risk Assessment
aimed at Spatial Planning................................................... 92
13.1 Minimum standard (simplified model) for hazard mapping
aimed at a legal directive................................................................. 92
13.1.1 Various methodologies related to the 3 assumed scales of analysis
in the light of a potential harmonisation of hazard maps, based on a multi-
hazard perspective...............................................................................92
13.2 Minimum standard (simplified model) for risk mapping aimed at
spatial planning .............................................................................. 98
13.2.1 Multi-risk assessment perspective as element of the Strategic
Environmental Assessment....................................................................98
13.2.2 Methodologies, functions and outputs .........................................99
13.2.2.1 ........................................................................................ 101
13.3 Minimum Standard for Landslide Risk Maps ............................. 106
13.3.1 Local Scale mapping ( 1: 10.000) .......................................... 106
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-4
1 Definition of LandslideThe term "landslide" describes a wide variety of processes that result in the
downward and outward movement of slope-forming materials including
rock, soil, artificial fill, or a combination of these (UNESCO, 1984).
A landslide event is defined as "the movement of a mass of rock, debris or
earth down a slope" (Cruden 1991). The word 'landslide' also refers to the
geomorphic feature that results from the event. Other terms used to refer
to landslide events include 'mass movements', 'slope failures', 'slope
instability' and 'terrain instability'.
Limits and uncertainties
There is a conceptual confusion in the term landslide since it is referred
both to landslide deposit (displaced mass) and the movement of material
along a slope.
2 Landslides classificationIn spite of the simple definition, landslide events are complex
geological/geomorphological processes and are therefore difficult to classify.
An adequate classification system should be based on parameters and/or
features that can be measured and observed in the field. At the same time,
a classification system should satisfy requisites of uniqueness, rationality,
homogeneity and readiness of application, though the detection of classes
mutually exclusive.
The classification system, most commonly used worldwide, and proposed
for this report, is modified from Varnes (1978). The classification is based
upon material type and type of movement, and is similar to the updated
classification of slope movements suggested by Cruden and Varnes(1996).
This is based on the movement, with a special attention to the spatial
distribution of displacements and their velocity as well as to the shape of
the failure and landslide body.
The Cruden & Varnes classification can be resumed in the following landslide
types:
1. Falls: take place rapidly by free-fall, bouncing, or rolling, and may
develop into either slides or flows.
2. Topples: consist of the rapid rotation of a unit of rock or soil about
some pivot point. Toppling may not lead to either falls, slides or flows.
3. Slides: involve the movement along one or more distinct surfaces.
Slides are subdivided into 'rotational slides' and 'translational slides',
depending upon the shape of the failure plane.
a . Rotational slides: also referred to as slumps, involve movement
along a curved failure plane. Often the failure plane did not exist
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-5
before movement occurred. Rotational slides usually involve relatively
few distinct rock or soil units.
b. Translational slides: involve the movement of many rock or soil
units along a plane. If few distinct units are involved, the movement
is referred to as a 'translational block slide'. Often the failure plane
existed before movement occurred.
4. Lateral spreads: are dominated by lateral extension of the ground,
accompanied by shear or tensile forces, and a general subsidence of the
ground surface. They generally occur relatively slowly.
5. Flows describe movement that resembles a viscous fluid. Some flows
occur slowly, others occur rapidly. Velocity within the flowing mass is
usually decreases with depth and laterally. In most cases, water is an
integral component. Creep is a type of flow that occurs very slowly.
6. Complex landslides involve the combination of two or more types of
movement. Commonly one type of movement starts the material
moving, such as a debris slide, and once underway the material takes on
the character of another type of movement, such as a debris flow. The
name of the complex movement is a combination of the types of
movement, in order of occurrence, such as a debris slide-debris flow.
The rate of movement depends on the types of movements and material
types involved.
According to WP/WPLI (1990-1994), complex landslides should be classified
following the types of movement involved related to the genetical and
temporal sequence of the single types that compose the phenomenon.
2.1 Material type
The material involved in a landslide should be classified according to its
state before the initiation of the movement or, if the movement changes in
the time, according to the state that characterizes the material before the
movement where such a change occurs
The material involved in a landslide is classified into two groups, 'bedrock'
and 'soil'. Soil, which is generally unconsolidated superficial material, is
further subdivided into 'debris' and 'earth' depending upon its texture.
Rock refers to earth materials that have lithified by some rock-forming
process. Its strength depends not only on the rock type but also on the
degree of weathering and the density and orientation of the discontinuities,
which are generally the planes of weakness in the rock mass.
Debris is composed of predominantly coarse grained soil, or as mentioned
above, can also include highly fractured bedrock. The strength of coarse
grained soil is generally derived from friction between the grains.
Earth refers to predominantly fine grained soil (primarily of silt and clay
sized materials). The strength of fine grained soil is generally derived from
cohesion, the chemical and electrical bonding between the small particles.
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-6
2.2 Landslide activity
The activity defines the temporal evolution of a landslide, through the
analysis of movement, displaced materials and areas involved. The activity
can be regrouped under three headings:
1. State of activity, that is related to the timing of a landslide
2. Distribution of activity, that describes the area where a landslide is
moving
3. Stile of activity, that indicates the contribution of single movements to
the landslide
2.2.1 State of activity
The state of activity is defined as follows Cruden & Varnes, 1996):
active: landslide currently moving; suspended: landslide moved within the last annual cycle of seasons, but
not presently moving;
reactivated: landslide that is again active after being inactive; inactive: landslide that moved more than one annual cycle of seasons
ago.
Inactive landslides can be subsequently divided in:
dormant: if the causes of movement remain apparent; naturally stabilised: inactive landslide protected by its original causes
without human interventions;
artificially stabilised: inactive landslide protected by its original causeswith artificial remedial measures;
relict: inactive landslides developed under geomorphologic and climaticsetting, considerably different from present conditions.
The geomorphological information of the state of activity are generally
related to the type and state of preservation of some diagnostic elements,
as reported in Table 2.1.
Active Inactive
Scarps, terraces and crevasses with sharp bordersScarps, terraces and crevasses with roundedborders
Crevasses and depressions without secondaryfilling
Crevasses and depressions with secondary filling
Secondary mass movements on scarpsAbsence of secondary mass movements onscarps
Fresh striae over the failure surface and marginalshear planes
Absent or weathered striae over the failuresurface and marginal shear planes
Fresh crack surfaces on blocks Weathered crack surfaces on blocks
Irregular drainage system, diffuse ponding anddepressions with internal drainage
Well preserved drainage system
Pressure crests at the contact with sliding margins Abandoned marginal cracks and banks
Absence of soil on the exposed portion of the failuresurface
Growth of soil on the exposed portion of thefailure surface
Presence of rapid-growing vegetation Presence of slow-growing vegetation
Different vegetation between internal and externallandslide areas
No difference of vegetation between internal andexternal landslide areas
Tilting trees without vertical growthTilting trees with vertical growth in the portions
succeeding the tilted part
Table 2.1. Geomorphic criteria for field survey of landslide state of
activity (Crozier, 1984, modified)
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-7
The state of activity of a landslide and its geomorphologic characteristics
are strictly depending on climate conditions, as reported in Figure 1.
Fig. 1. Block diagrams of morphologic changes with time of idealized
landslide (a) in humid climate: A, active or recently active (dormant
historic) landslide features are sharply defined and distinct; B,
dormant young landslide features remains clear but are not
sharply defined owing to slope wash and shallow mass movements
on steep scarps; C, dormant mature landslide feature are
modified by surface drainage, internal erosion and deposition, and
vegetation; D, dormant old landslide features are weak and often
subtle. (Turner & Schuster, 1996).
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-8
2.2.2 Distribution of activity
The distribution of activity describes where the landslide is moving and
permits to predict the type of landslide evolution in the space. Following the
distribution of activity a landslide is:
advancing: if the surface of rupture is extending in the direction ofmovement;
retrogressive: if the surface of rupture is extending in the directionopposite the movement of the displaced material;
progressive or multi-directional: if the surface of rupture is enlargingin two or mode directions;
diminishing: if the volume of displaced material is decreasing withtime;
confined: landslide with a scarp but no visible surface of rupture inthe foot of the displaced mass;
constant: if the displaced mass continues to move withoutconsiderable change of the rupture surface and volume of the
displaced mass;
enlarging: if the rupture surface is developed on one or both lateralmargins of the landslide.
2.2.3 Style of activity
The style of activity is the way in which different movements contribute to
the landslide. Following the style of activity a landslide can be defined as:
complex: characterised by the combination, with time, of at least twotypes of movement (fall, topple, slide, expansion, flow);
composite: characterised by the combination, with time, of at leasttwo types of movement (fall, topple, slide, expansion, flow)
simultaneously in different areas of the displaced mass;
successive: characterised by a movement of the same type to anearlier and adjacent landslide, where displaced masses and rupture
surfaces are clearly distinct;
single: characterised by a single movement of the displaced mass; multiple: characterised by repeated movements of the same type,
often following enlargement of the failure surface.
In order to characterise the type of evolution of a landslide it can be very
useful to refer to the frequency of reactivations instead of the state of
activity detected during field survey. On this subject the distinction
proposed by Del Prete et al. (1992) among continuous, seasonal and
intermittent (pluriannual or pluridecennial return time) landslides or what
proposed by Bisci & Dramis (1991) and Flageollet (1994) reported in Table
2.2.
State of activity Recurrence Return time Last activation
ACTIVE Continuous - Presently moving
Seasonal > 1 year Recent
Short-term recurrence 1 - 10 years Recent history
QUIESCENT Medium-term recurrence 10 - 100 years Recent history
Long-term recurrence 100 - 1000 years Recent or ancient history
STABILISED Very long-term recurrence > 1000 years Ancient history and prehistory
Tab. 2.2 Landslide activity (BISCI & DRAMIS, 1991 and
FLAGEOLLET, 1994, modified).
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-9
2.3 Landslide causes
Landslide causes analysis consists in examining the various factors that
contribute to slope instability, in their parameterisation and subdivision in
classes and, finally, in their representation as thematic maps.
A list of major predisposing factors, derived by literature (Terzaghi, 1950;
Carrara & Merenda, 1974; Cotecchia, 1978; Varnes, 1978; Hansen, 1984;
Esu, 1984; Crozier, 1986; Canuti et al., 1992; Amanti et al., 1992; Cruden
& Varnes, 1994; Hutchinson, 1995) is reported in the following table:
LITHO-STRATIGRAPHYa) lithological characteristics (i.e. weak materials, presence of clayey
particles);b) stratigraphical characteristics (i.e. rheological contrast: rigid
material over ductile material;c) textural characteristics (i.e. porosity, materials with metastable
texture);d) primary structures (layers, schistosity, fissility);e) mineralogical, petrographical, geochemical characteristics (i.e.
typology of clayey minerals, weathering).
TECTONICa) secondary structures (joints, faults, folds, shear bands, bending);b) tectonic setting of the area;c) neo-tectonic uplift and/or e/o tilting;
QUATERNARY GEOLOGYa) weathering (physical and/or chemical);b) depth of soil, regolith and degradation covers;c) climatic fluctuations;d) eustatic fluctuations;e) melting of glaciers (i.e. unloading of pressures);f) melting of permafrost;g) glacio-eustasy and glacio-isostasy;h) ancient or relict landslides.
HYDROGEOLOGYa) hydrography and springs;b) permeability, contrast of permeability;c) drainage conditions;d) characteristics of groundwater (i.e. free, suspended, confined,
semi-confined aquifers);e) pore pressure in soils and discontinuities;f) filtration;g) capillarity and negative pore pressures;h) evapotranspiration, runoff and infiltration;i) groundwater geochemistry;
GEOTECHNICS AND GEOMECHANICSa) granulometry;b) index properties (i.e. Atterberg limits, point load);c) cementation (i.e. content of CaCO3);d) density (with natural water content, dry, saturated);e) shear strength of material (peak, critical condition, residual;
drained or undrained);f) tensile strength;g) geometrical characteristics of discontinuities (i.e. orientation,
spacing, persistence, roughness);h) mechanical characteristics of discontinuities (i.e. shear strength);i) presence of pre-existing shear surfaces;j) presence of organic matter;k) sensitivity (change in strength with remoulding);l) fragility and progressive rupture;m) cracking and softening;n) swelling and consolidation;o) stress history (i.e. pressure and overconsolidation ratio);p) in situ tensional state;
SEISMICITYa) neotectonics, regional geodynamic model;b) historical and instrumental seismicity, seismotectonic model;c) characteristics of the source (recurrence, maximum expected
magnitude, hypocentral depth, geometry of the source);d) attenuation law;e) seismic macrozoning: ground shaking (i.e. intensity, peak
acceleration, response spectrum)f) seismic microzoning: local seismic response (i.e. amplification),
dynamical effects on terrain properties (liquefaction; dynamicaleffects on pore pressure and shear strength).
VOLCANIC ACTIVITYa) steam emission and subsequent condensation;b) tephra accumulation;c) hydrothermal alteration;d) ice and snow melting;e) volcanic uplift;f) diversion of hydrographic network.
GEOMORFOLOGYa) slope morphometry (i.e. slope angle, height, length, shape,
orientation);b) morphometry of catchments and channels;c) relief energy;d) erosion (i.e. fluvial, marine, glacial) on the foot of the slope;e) superficial erosion (diffuse or concentrated runoff);f) underground erosion (i.e. solution, karst, piping);g) slope loading;h) deforestation (natural causes);
CLIMATOLOGY, METEOROLOGY E HYDROLOGYa) rainfall pattern;b) frequency, intensity and duration of extreme events (i.e. intense
rainfall, extremely prolonged rainfall);c) thermal pattern (ice/snow melting, freezing of spring waters);d) fluctuation of hydrographical level (lakes or rivers);e) fluctuation of sea level;f) thermal excursion (freeze-thaw cycles);g) fluctuation of soil humidity (imbibition / desiccation).h) pre-existing mass movements and frequency of reactivations.
VEGETATION AND LAND USEa) pedologic characteristics (i.e. soil type, texture, structure, depth,
organic matter, content in carbonates);b) agricultural land use (i.e. crop, tree crop, specialised cultures,
grassland, bush, forest)c) type and state of vegetation (i.e. leave cover, depth and strength
of roots, weight of vegetation);d) agricultural techniques (i.e. superficial tillage, strip, terrace).
HUMAN FACTORSa) excavation on the slope or slope toe;b) overloading on slope or crest;c) fluctuation of piezometric levels of artificial basins (i.e. critical
height; rapid emptying);d) deforestation and forestation;e) irrigation;f) mining activity;g) artificial vibrations;h) water leakage (reservoirs, aqueducts, sewage systems).
Tab.2.3 Causative factors of landslides.
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-10
3 Intensity or Magnitude (I)Geometrical and mechanical severity of a landslide. It may be expressed as
a relative scale or as one or more landslide parameters (i.e. velocity,
volume, energy).
A conceptual distinction between magnitude and intensity is reported in
Hungr (2001) in the dynamic analysis of fast-moving landslides (flows and
slides). The magnitude is a parameter that describes the scale of an event.
As a general rule, the volume of the involved material can express the
magnitude of a landslide. The initial volume (i.e. the volume of a rock mass
before the detachment) should be distinguished from the volume of a
landslide deposit, that can be larger due to swelling or erosion phenomena,
or smaller due to partial deposition or diversion of material during the
travel.
Therefore, the magnitude defines the total volume of the displaced mass, as
a sequence of connected episodes, considered as a single event. The
intensity, as for earthquakes, is not a single parameter but a spatial
distribution of different characteristics that describe, qualitatively or
quantitatively, the impact of a landslide in different sites. Velocity, duration
of movement, height of displaced mass, depth of deposits are some of
quantitative parameters of intensity. These parameters are a function of the
areas involved by a landslide and tend to annul at lateral and distal margins
of the path, defining in such a way the extension of the impact zone. With
respect to other field such as seismicity and flood where the intensity may
be clearly defined (i.e. magnitude of an earthquake, height or discharge of
water flow) the definition of the severity of a landslide (in terms of intensity
or magnitude) is a very difficult task for experts due to the objective
difficulty in the assessment of the various parameters. In addition, the
expression of intensity related to potential damage or losses should be
avoided being depending on vulnerability of potential exposed element.
3.1 Velocity
Hungr (1981) proposed a scale of landslide intensity based on classes of
velocity related to a scale of damage. This scale has been partially modified
by Cruden & Varnes (1996) as shown in Table 3.1.
Class Description Potential damage Velocity (mm/s)
7 Extremely rapidCatastrophe of major violence; buildings destroyed by impact ofdisplaced material; many deaths; escape unlikely.
5 m/s 5 x 103
6 Very rapidSome lives lost; velocity too great to permit all persons toescape
3m/min 5 x 101
5 RapidEscape evacuation possible; structures, possessions andequipment destroyed
1.8 m/h 5 x 10-1
4 ModerateSome temporary and insensitive structures can be temporarilymaintained
13m/month
5 x 10-3
3 Slow
Remedial construction can be undertaken during movement;insensitive structures can be maintained with frequentmaintenance work if total movement is not large during aparticular acceleration phase
1.6m/year
5 x 10-5
2 Very slow Some permanent structures undamaged by movement15
mm/year5 x 10
-7
1 Extremely slowImperceptible without instruments; construction possible withprecautions
Table 3.1. Scale of landslide intensity based on velocity and induced
damage (Cruden & Varnes, 1996)
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-11
The assessment of velocity of a landslide is generally a difficult task; it may
be assessed approximately considering the typology and activity of a
landslide (Varnes, 1978) (Tab 3.2).
CLASSES OF VELOCITY
1 2 3 4 5 6 7
Fall
Topple
Rock slide (F)
Rock slide (R)
Debris slide
Earth slide (F)
Earth slide (R)
Lateral expansion of rock mass
Lateral expansion of rock mass overlaying clay bedrock
Lateral expansion due to liquefaction
Rock flow
Debris flow
Cohesive earth flow (F)
Cohesive earth flow (R)
Tab. 3.2 - Landslide velocity (referred to the classes proposed by
Cruden & Varnes, 1996) based on typology, material and state of
activity; F =first-triggered landslide; R = reactivation
A similar approach has been proposed by Canuti & Casagli (1996), based on
landslide typology, involved material and state of activity (first-triggered or
reactivated landslides) (Tab. 3.3).
Typology Fall Slide Flow
Material Rock Rock Debris Earth Rock Debris Earth
State of activity - F R - F R - - -
Class of velocity 6-7 5-6 1-5 1-6 5-6 1-5 1-2 1-7 1-4
Table 3.3. Landslide velocity proposed by Canuti & Casagli (1996)
based on typology, material and state of activity. F =first-triggered
landslide; R = reactivation
The relationship between movement and velocity is quite evident: a debris
flow or a rock fall are generally very rapid or extremely rapid, while an
earth flow is usually slow or very slow. Generally a first-triggered landslide
exhibits a higher velocity than a reactivation, except for some cases
discussed by Hutchinson (1987). The former is characterised by a fragile
rupture mechanism while the latter by a ductile rupture mechanism where
the shear strength is proximate or equal to residual values.
Another way to assess landslide intensity, based on velocity, can be done
comparing the surface area of present or potential landslides with their
estimated velocity (Tab.3.4 and 3.5). The potential unstable areas are
assessed taking into account landslide phenomena that are developing over
slopes with similar geological and morphological setting.
VELOCITY
Class V0 V1 V2 V3
Values - < 10-6 m/s
(< m/month)10
-6 - 10
-4m/s
(m/month - m/h)> 10
-4 m/s
(>m/h)
Class Values Description NEGLIGIBLE SLOW MODERATE RAPID
A0 - NEGLIGIBLE I0 I0 I0 I0
A1 < 103 m
2SMALL I0 I1 I2 I3
A2 103 - 10
5 m
2MEDIUM I0 I1 I2 I3
AREA A3 > 10
5 m
2LARGE I0 I2 I3 I3
Tab. 3.4 Diagram for simplified assessment of intensity
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-12
Intensity Description
I0 NEGLIGIBLE Stable or potentially stable areas
I1 SMALL Areas with small or potentially small landslides
I2 MEDIUM Areas with intermediate or potentially intermediate landslides
I3 LARGE Areas with large or potentially large landslides
Tab. 3.5 Classes of intensity referring table 3.4
3.2 Dimension
Landslide intensity can be also estimated through the dimension of the
displaced mass (Fell, 1994) (Tab. 3.6).
Intensity (I) Description Volume (m3)
7 Extremely large > 5 x 106
6 Very large 1 x 106 5 x 10
6
5 Large 2.5 x 105 1 x 10
6
4 Medium 5 x 104 2.5 x 10
5
3 Small 5 x 103 5 x 10
4
2.5 Very small 5 x 102 5 x 10
3
2 Extremely small < 5 x 102
Table 3.6 - Scale of intensity of landslides based on the volume of
the displaced mass (Fell, 1994)
The estimation of the displaced mass is often difficult to calculate;
therefore, the intensity may be preferably expressed as landslide area.
The assessment of intensity, based on dimension, should take into account
the different landslide typologies. DRM (1990) has proposed to associate
the volume of displaced mass following landslide types (Tab. 3.7) compared
with intensity levels and consequent damage on human life and economy.
The intensity of slides is evaluated through the depth of phenomena since
the estimation of volumes, for this type of landslides, is rather difficult.
FALLS AND TOPPLES
Volume (m3) Description
H1 E1 < 102
Fall of isolated blocks
H2 E2 102 - 10
4Fall, topple or sliding of blocks
H3 E3 104 - 10
6Large fall of blocks
H3 E4 > 106
Catastrophic fall or sliding
FLOWS
Volume (m3) Description
H1 E1 < 5 x 102
Mud flow or mud slide
H2 E2 5 x 102 - 10
4Mud or debris flow
H3 E3 104 - 10
6Rapid debris flow
H3 E4 > 106
Exceptional mass movement
SLIDES
Depth (m) Description
H0 E1 < 2 Superficial slide or solifluxion
H0 E2 2 10 Localised slide
H0 E3 10 50 Slide of a slope
H0 E4 > 50 Exceptional slide
Table 3.7 - Relationship between intensity and physical
characteristics of landslides (DRM, 1990)
In the table 10 the distinction between intensity and consequences on
human setting (H0 H3) and economic setting (E1 E4) has been kept. With
respect to the velocity of movements, the scales of intensity referred to falls
and slides (rapid movements) are the same; as regarding slides, that are
generally slow movements, the intensity, referred to human setting, is
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-13
equal to zero (H0) independently from landslide dimension. This definition
includes an analysis of social and economic vulnerability. Finally, the
symbols H and E are referred to the French terminology humaine and
conomique (human and economic respectively) and not to the UNESCO
terminology H (Hazard) and E (Element at risk).
3.3 Energy
As reported by Morgenstern (1985) and Cruden & Varnes (1996), small and
very rapid landslides may be more disastrous than large slow-moving
landslides due to their high kinetic energy.
Intensity may be considered as equal, or proportional, to the kinetic energy
developed by landslides. The energy is variable with the time: equal to zero
at the initial conditions, increasing up to the highest value after the
landslide triggering, then decreasing up to zero again. Landslide intensity
can be measures as the maximum kinetic energy or the average value
developed by a landslide.
An assessment of the energy balance may be done following the sled
model, proposed by Heim (1932) and after by Scheidegger (1973), Hs
(1975) and Sassa (1988), based on the assumption that all the energy of
the movement is lost for friction.
3.4 Consequences
Another way of assessing landslide intensity is to relate the event with the
potential damage. This approach has been proposed by the French project
PER (Plan dExposition aux Risques) (DRM, 1988, 1990) where the intensity
levels are defined with respect to the potential damage for human lives
(Tab. 3.8) and economy (Tab. 3.9).
Degree Intensity Potential consequences Landslide types
H0 Very lowImprobable damage (except induceddamage)
Slow-moving landslides
H1 Medium Isolated damage Isolated falls
H2 High Some victims Falls, slides or mud flows
H3 Very high Catastrophe (some tens victims)Catastrophic falls and slides,rapid mud/debris flows
Table 3.8 - Scale of landslide intensity with respect to potential
consequences on human life (DRM, 1990)
Degree Intensity Potential consequences Example
E0 Low10% of worth of an individual singlehouse
Detachment of unstable blocks
E1 MediumTechnical intervention on few houses orsmall lots
Rock detachment or fallingrock barriers; drainage ofsmall unstable areas
E2 HighHigh qualified technical intervention of alarge area, with relevant costs
Stabilisation of a largelandslide; consolidation of arock slope
E3 Very highAny technica l intervention hasunacceptable costs for populations
Catastrophic fall or slide
Table 3.9 - Scale of landslide intensity with respect to potential
economic losses (DRM, 1990)
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-14
3.5 Hybrid
Landslide intensity can be assessed using different parameters as velocity,
kinetic energy, depths and heights of landslide deposits, applied, following
their suitability, for different landslide types. This approach is adopted in the
guidelines for landslide hazard and risk assessment in Switzerland (Raetzo
et al., 2002). Indicative values of these parameters are used to subdivide
potential unstable areas or risk areas in three different intensity classes:
high, medium, low (Tab. 3.10). The criterion for assessing landslide
intensity is applied on the most diffuse landslide types, distinguishing for
each one those parameters that properly characterise the intensity.
Landslide types Low intensity Average intensity High intensity
Rock falls E < 30 kj 30 < E < 300 kj E > 300 kj
Rock avalanches E > 300 kj
Slides v 2 cm/year v: dm/year (> 2 cm/year) Large differential movements: v >0.1 m/day for superficial slides;displacement > 1 m per event
Earth/debris flow
Potential e < 0.5 m 0.5 m < e < 2 m e > 2 m
Real - h < 1 m h > 1 m
Table 3.10 - Criteria for intensity assessment. E = kinetic energy; v
= long-term average velocity; e = depth of unstable mass; h =
height of deposit (Raetzo et al., 2002)
The BUWAL method (1998), used for the assessment of hazard in
Switzerland, provides an intensity analysis by defining the magnitude as
product of velocity vs. geometrical severity. The velocity is compared with
velocity classes provided by Cruden & Varnes (1996) (see table 3.11).
Class Description Velocity Potential damage for peopleVelocityBUWAL
7 Extremely rapid 5 m/s
6 Very rapid 3m/minSevere injury and/or death 3
5 Rapid 1.8 m/h
4 Moderate 13m/monthModerate injury 2
3 Slow 1.6 m/year
2 Very slow 16 mm/year
1 Extremely slow
Minor/no injury 1
Table 3.11 - Landslide intensity scale following BUWAL (1998)
compared with intensity scale from Cruden & Varnes, 1996
The geometrical severity is defined through the following table.
Falls Slides and flows Geometrical severity
Diameter of blocks > 2 m Depth > 10 m 3
Diameter of blocks 0.5 - 2 m Depth 2 - 10 m 2
Diameter of blocks < 0.5 m Depth < 2 m 1
Table 3.12 - Landslide intensity scale following BUWAL (1998) based
on geometrical severity compared with different landslide types
The magnitude is the product of geometrical severity by velocity (Tab 3.13)
Potential damage to structures Magnitude
Severe (disruption) 6-9
Functional 3-4
Minor 1-2
Table 3.13 - Landslide intensity expressed as total magnitude
(BUWAL, 1998)
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-15
4 Return period of landslidesThe most common criteria for the assessment of landslide return times are
the following:
a) Geomorphological criteria or qualitative analysis;
b) Analysis of temporal series related to effects: the analysis of temporal
series of mass movements enables to define directly the return times of
landslides;
c) Analysis of temporal series related to causes: the correlation between
landslides and long-time records of possible triggering elements (i.e.
rainfall, seismicity) permits to define critical thresholds and associated
return times;
d) Monitoring: the instrumental observation of piezometric levels or slope
displacement for single landslides allows the prediction of slope
movements through the comparison with thresholds or models calibrated
on the observed unstable or potentially unstable areas.
4.1 Geomorphological criteria or qualitative analysis
The recurrence of landslides can be assessed subjectively from general or
qualitative information such as historical, geomorphological and
geotechnical analyses. The direct analysis, using geomorphological and
geotechnical information, in case of lack of historical data, can provide a
probabilistic estimation on landslide occurrence. This approach, although
subjective, is an effective way for assigning relative probability of return
times of landslides in a given area. For instance, a lower probability of
landslide occur in slope that exhibit rounded and vegetated crown areas
while higher probability can be associated to steep slopes with tension
cracks.
4.2 Analysis of temporal series related to effects
Historical analysis is the main source for assessing landslide return times.
The main sources are:
a) Multi-temporal analysis of maps (i.e. geomorphological maps, landslide
inventory maps);
b) Multi-temporal analysis of aerial photos or satellite images;
c) Newspapers;
d) Direct observations;
e) Scientific publications;
f) Technical reports.
Long-term activity of landslides can be analysed with datation methods,
commonly used in Earths Sciences, such as radiocarbon, lichenometry and
dendrocronology methods (Starkel, 1966; Schoeneich, 1991; Corominas et
al., 1994).
The annual frequency f(N) of landslides in a period of N years, is the ratio
between the number of events n and the number N of observed years. If N
is quite long, f(N) is an estimation of the annual probability of occurrence P.
Landslide hazard can be calculated as follows:
H(N) = 1 - (1 - P)N = 1 - (1 - 1/T)N (4.1)
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-16
When landslide events are very low compared to the time under analysis,
namely N
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-17
movements is analysed without implementing physical laws that rule the
transformation rainfall-infiltration-piezometric response;
b) deterministic models: where hydrological models are use for analysis of
various parameters (rainfall, run-off, effective infiltration) and
hydrogeological models for analysis of piezometric height and aquifer
recharge;
c) hybrid models: where the above approaches are usually coupled (e.g.
aquifer recharge through a hydrological model and piezometric response
by means of a statistical analysis).
4.3.2 Earthquakes
The influence of earthquakes on slope stability is still quite controversial
and, often, overestimated.
The effects of an earthquake on a slope can be direct or indirect. The former
may cause slope movements during the seismic event; the former may
occur from some hours to some days after an earthquake (Hutchinson,
1993).
The main effect results in increasing of destabilizing stresses through the
application of a transient horizontal inertial stress (F = KW), where W is the
weight of the potential unstable mass and K is the coefficient of seismic
acceleration. Such a stress is generally assumed in the calculation of limit
equilibrium for the assessment of the safety factor under pseudo-static
conditions. Since the wavelengths of strong earthquakes, in most of
terrains, are some tens meters, the effects of direct destabilization may
occur only along short slopes, with length generally < 30m (Ambraseys,
1977; Hutchinson, 1987). For longer slopes, in fact, the destabilizing
acceleration produced toward the external part of slopes is balanced by a
stabilizing acceleration, with opposite direction, caused by the succeeding
waves. The highest synchronous acceleration, associated to the maximum
peak of K, results for landslides that have a dimension equal to half
wavelength.
Rock falls, debris flows and earth flows are the most common landslide
types triggered by earthquakes, especially under saturated conditions of
terrains. Re-activation of slides and flows may occur also in cohesive
materials (Hutchinson & Bhandari, 1971).
Another important effect of earthquakes, affecting saturated loose granular
soils, is the dynamic liquefaction (Seed & Idriss, 1967; Seed, 1968; Valera
& Donovan, 1977; Crespellani et al., 1988). An earthquake can cause a
consolidation of soils due to a structural collapse and, consequently,
promote critical pore pressure values that result in liquefaction. In this case,
the shear strength of soils can decrease abruptly causing sliding also along
gentle slopes. Many landslide-induced earthquakes are generally associated
to liquefaction (Seed, 1975). Moreover, since ground failure is fragile,
landslides generated by liquefaction are characterised by high velocity and
long run-out, constituting very hazardous phenomena. The assessment of
potential liquefaction of a soil is based on seismic parameters (e.g.
magnitude, duration, number of cycles, distance from epicentre, maximum
site acceleration) as well as on geotechnical parameters (e.g. grain-size
distribution, uniformity, relative density, SPT test, initial stress state).
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-18
The indirect effects, generally, cause the re-activation of pre-existing
landslides, also large landslides in cohesive soils, due to the cyclic load on
pore pressure regime. Some investigations (Lemos et al., 1985; Sassa,
1992) have shown that the application of rapid cyclic loads in special shear
ring apparatus can cause, in some cohesive materials, a progressive
decreasing of residual shear strength after an initial peak. Such a behaviour
can explain the delay between the seismic shake and landslide trigger.
The triggering thresholds of landslides can be assessed as local seismic
response parameters (i.e. intensity, peak acceleration) or as earthquake
source parameters (i.e. magnitude). A common adopted methodology is to
implement a deterministic analysis (i.e. pseudo-static slope stability
analysis) to calculate the critical acceleration that produce a safety factor
equal to 1. Another method is to compare empirically landslides occurrence
with site intensity of magnitude at the source.
4.4 Monitoring
The assessment of landslides occurrence based on monitoring provides the
most detailed and reliable information, especially in landslide hazard and
risk analysis at local/site scale.
Two distinct approaches can be adopted in landslide hazard analysis
through monitoring: mechanical and kinematical approaches.
4.4.1 Mechanical approach
Theoretically, the prediction of landslide movements or potentially unstable
slopes can be done through the monitoring of all parameters, variable in
time, that define the safety factors such as pore pressure, slope
morphology, geotechnical parameters of terrains, loads.
In practical terms, pore pressure is the parameter that exhibits a large
uncertainty as well as a wide variability in time. Therefore, the mechanical
approach is essentially based on piezometric measures.
Generally, 1-2 years of piezometric observations are used to deduce a
possible correlation between rainfall and groundwater fluctuation. The
prediction of hazard can be done through a statistical analysis of
precipitation. Estimated pore pressures can be used as input in slope
stability models for assessing the safety factor; in addition, their
probabilistic assessment through the analysis of annual extremes enables to
associate a return time to each safety factor value (hazard analysis).
A wide scientific literature is available on the prediction of piezometric
fluctuation related with rainfall and other meteorological parameters, based
on empirical, deterministic and hybrid approaches applied to slope stability
assessment.
4.4.2 Kinematics approach
A direct approach for predicting the time of failure of a slope is based on
displacement monitoring, through topographic, extensometric or
inclinometric measures.
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-19
5 Hazard assessment (H)Hazard is defined as the probability that a landslide with a given intensity
may occur in a specific time and area. It can be expressed as annual
probability or return time of a landslide. Landslide hazard is to be referred
to a well defined intensity:
H = H (I)
5.1 Basic concepts
As a basis for landslide hazard assessment and zoning any methodology
should be referred to the following four fundamental assumptions, widely
accepted by landslide experts (Varnes et al., 1984; Carrara et al., 1991;
Hutchinson & Chandler, 1991; Hutchinson, 1995; Turner & Schuster, 1995):
Landslides will always occur in the same geological, geomorphological,
hydrogeological and climatic conditions as in the past;
The main conditions that cause landsliding are controlled by identifiable
physical factors and laws that can be empirically, statistically and
deterministically defined;
The degree of hazard can be evaluated;
All types of slope failures can be identified and classified.
On this basis a complete assessment of landslide considers prediction of the
following parameters (Hartln & Viberg, 1988):
Typology: prediction of the landslide type that may occur in the
considered area;
Affected area: prediction of where a landslide may occur;
Return time: prediction of when a landslide may occur;
Intensity: prediction of dimension (area and/or volume), velocity or
energy of a landslide;
Evolution: prediction of run-out, retrogression limits and/or lateral
expansion of a landslide.
Limits and uncertainties
A rigorous landslide hazard assessment needs a large amount of
information on the various parameters. In addition, considering that reliable
scenarios should be done at local/site scale, this implies a time and money-
consuming activities for analysis and mapping.
The basic principle for which past and present unstable areas will be
affected by landslides in the future can be valid for factors that are constant
in time, such as geological, structural and geotechnical setting. A correct
landslide hazard assessment should take into account the variability of
those factors that may play a role in slope stability like climate and land use
modifications.
Due to the objective conceptual and operational limits, most of landslide
hazard maps should be defined as landslide susceptibility maps.
Limitations of landslide hazard analysis mainly include:
o Spatial and temporal discontinuity of landslides,
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-20
o Objective difficulty in the prediction of causes, triggering
factors and cause-effect relations,
o Long-term and exhaustive historical records on landslides and
potential triggering factors (i.e. long-term climatic records).
5.2 Prediction of landslide types
The prediction of landslide types that may occur in an area can be done
starting from an accurate landslide inventory map. In this case, the spatial
and temporal prediction of landslides can be differentiated according to
Cruden & Varnes classification.
As concerning potentially unstable areas, the expected landslide type can be
assessed on the basis of the typologies occurring in areas with similar
geological, geomorphological, geotechnical and land use characteristics.
5.3 Prediction of landslide intensity
The prediction of the landslide intensity is mainly depending on the amount
and quality of information from landslide inventory. Landslide hazard, or the
probability of occurrence, should be differentiated according to the
intensity, in order to have an estimation of consequences (risk analysis).
On this issue, some authors (i.e. Fell, 1994) provide a different definition of
landslide hazard that can be expressed as the product of intensity (I) and
probability of occurrence (P).
The methodology proposed by Fell (1994) considers the product of an index
of intensity by an index of probability associated to intensity and hazard
classes (Tab. 5.1).
INTENSITY PROBABILITY HAZARD
I Description Volume (m3) P Description P (annual) H = I P Description
7 Extremely high > 5 x 106
12 Extremely high 1 30 Extremely high6 Very high
1 x 106 5 x
106
8Very high 0.2
20-29Very high
5 High2.5 x 10
5 1 x
106
5High 0.05
10-19High
4 Medium5 x 10
4 2.5 x
105
3Medium 0.01
7-9Medium
3 Small5 x 10
3 5 x
104
2Small 0.001
3-6Small
2.5 Very small5 x 10
2 5 x
103
1Very small 0.0001
2Very small
2Extremely
small< 5 x 10
2
Table 5.1 - Assessment of landslide hazard with prediction of
intensity (Fell, 1994)
The approach proposed by DRM (1990) for PER implementation is more
correct since it provides the definition of the probability of occurrence
depending on different levels of intensities. Anyway, in the implementation
of PER sometimes the local authorities have used operational criteria where
landslide hazard is not properly expressed as combination of probability by
intensity (Perrot, 1988).
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-21
Limits and uncertainties
The expression of hazard as I x P is not coherent with the UNESCO
terminology and can present some problems. In fact, an event of small
dimensions and very frequent can have the same hazard of a very large and
less frequent landslide event. In addition, the vulnerability is already related
to landslide intensity. This implies that intensity is taken into account two
times in the risk assessment. To overcome this problem Fell defines the
specific risk as the product of probability by vulnerability.
5.4 Prediction on landslide affected area
The spatial prediction of hazard consists in the assessment of relative
hazard. This is the degree of hazard of a slope compared with other slopes,
without indicating the probability of occurrence of landslides (temporal
occurrence), generally based on historical and present instability.
5.4.1 Methods of relative hazard analysis
The methods for the assignment of the different hazard levels can be
qualitative or quantitative, direct or indirect:
Qualitative methods are subjective and describe the hazard zoning in
terms substantially descriptive;
Quantitative methods provide numerical estimations, in terms of
probability, on landslide occurrences for each hazard class;
Direct methods produce essentially geomorphological mapping of
landslide hazard (Verstappen, 1983);
Indirect methods are essentially carried out through distinct stages. First
of all, these require a field analysis and a landslide inventory map in the
study area or in a subset area (training area). The second step is the
detection and mapping of a set of physical factors that are directly or
indirectly related to slope instability (predisposing factors). Finally, an
assessment of the relative contribution of the various predisposing
factors for landsliding and a hierarchisation of landslide hazard in areas
with distinct hazard degree (hazard zoning).
5.4.1.1 Qualitative methodologies
In general qualitative approaches are based entirely on expert judgement.
The input data are usually derived from assessment during field trips,
possibly integrated by aerial photo interpretation. These methodologies can
be divided into two types: field geomorphological analysis and combination
or overlaying of index maps (heuristic approach).
5.4.1.1.1 Field geomorphologic analysis
This approach is a direct and qualitative method based on the experience of
the earth scientist in assessing present and potential landsliding without any
specific indication of rules that have led to the assessment and/or zoning. In
this case the stability maps are directly evolved from detailed
geomorphological maps. The assessment of slope stability takes into
consideration a very large number of factors. They can be used successfully
at any scale and adapted to specific local requirements. The field
geomorphological analysis does not require the use of a Geographical
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-22
Information System which, in this case, is simply a drawing tool. Examples
of geomorphological-based hazard analysis are very frequent in scientific
literature of the 70s and 80s.
Perhaps one of the most comprehensive projects reported in the literature is
the French ZERMOS (Zones Exposes des Risques aux MOuvements du
Sol et du sou-sol) procedure which involves two main phases: analysis and
extrapolation. In the first phase, all the predisposing factors are examined,
both permanent (e.g. topography, geology, hydrogeology) and temporary
(e.g. climate, land use and other man-made factors). Active and/or inactive
landslides may be analysed. In the following phase all the factors are
extrapolated by the author to areas with similar physical conditions, thus
enabling zoantion of the area into three sections with varying degrees of
hazard (defined as risque):
null or low hazard, areas in which no instability should occur;
potential or uncertain hazard, areas with potential instability of uncertain
nature and extent;
ascertained hazard, areas with declared instability and certain threat of
failure.
The hazard calculated is of a relative nature and the authors acknowledge
that the various hazard categories cannot be compared from one area to
another. The choice of three classes is inspired to the necessity to let the
hazard maps comprehensive by stakeholders and end users (Public
Administration)
Limits and uncertainties
The main disadvantages of such approaches are:
The subjectivity in the selection of both the data and the rules that
govern the stability of slopes or the hazard of instability; this fact makes
it difficult to compare landslide hazard maps produced by different
investigators or experts;
Use of implicit rather than explicit rules hinders the critical analysis of
results and makes it difficult to update the assessment as new data
become available;
Lengthy field surveys are required.
5.4.1.1.2 Combination of index maps or heuristic approach
In this approach, the expert selects and maps the factors that affect the
slope stability and, based on personal experience, assigns to each a
weighted value that is proportionate to its expected relative contribution in
generating failure. The following operations should be carried out:
subdivision of each parameter into a number of relevant classes;
attribution of a weighted value to each class;
attribution of a weighted value to each of the parameters;
overlay mapping of the weighted maps;
development of the final map showing hazard classes.
The advantages of such a methodological approach are that it considerably
reduces the problem of the hidden rules and enables total automation of the
operations listed above through appropriate use of a GIS. Furthermore, it
enables the standardisation of data management techniques, from
acquisition through final analysis. This technique can be applied at any
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-23
scale. In order to provide a better coherence to physical processes, the
attribution of weights can be supported by statistical analysis on the
assessment of the contribution of single predisposing parameters to slope
instability.
Limits and uncertainties
The major disadvantage is the lengthy operations involved, especially where
large areas are concerned. In addition, the reliability of heuristic methods
depends largely on how well and how much the investigator understands
the geomorphological processes acting upon the terrain. Since this
knowledge can be formalised into rules, the method could take into account
local geomorphological variability or specific conditions leading to slope
failures. Major limitations refer to the fact that in most cases the available
knowledge on the causal relations between environmental factors and
landslides is inadequate and, most importantly, is essentially dependent on
the experience of the investigator. At present, maps obtained by this
method cannot be readily evaluated in terms of reliability or certainty.
Additionally, landslide hazard is not directly expressed in terms of
probability, limiting the use for risk evaluation and economic estimates.
5.4.1.2 Quantitative methodologies
5.4.1.2.1 Statistical analysis
The attribution of weighted values on a subjective basis to the numerous
factors governing slope stability represents the main limitation in all the
methods described above. The solution to this problem could be to adopt a
statistical approach that compares the spatial distribution of landslides with
the parameters that are being considered. The results could then be applied
to areas currently free of landslides but where conditions may exist for
susceptibility to future instability. The major difficulty consists in
establishing the slope failure processes and in systematically identifying and
assessing the different factors related to landsliding. One of the principal
advantages is that the investigator can validate the importance of each
factor can validate the importance of each factor and decide on the final
input maps in an interactive manner. The use of GIS makes these
operations much easier and to a large extent explains the increasing
adoption of the statistical approach which closely parallels the ever-
increasing application of GIS techniques.
Statistical analyses can be either bivariate or multivariate.
Bivariate statistical analysis
In bivariate statistical analysis each individual factor is compared to the
landslide map. The weighted value of the classes used to categorise every
parameter is determined on the basis of landslide density in each individual
class. The following operations are required:
selection and mapping of significant parameters and their categorisation
into a number of relevant classes;
landslide mapping;
overlay mapping of the landslide map with each parameter map;
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-24
determination of density of landslides in each parameter class and
definition of weighted values;
assignment of weighting values to the various parameter maps;
final overlay mapping and calculation of the final hazard or susceptibility
value of each identified land unit.
The simplest models consider the determination of threshold value of slope
angle, for each lithological type, that may cause potential slope instability.
The models are based on a series of empirical functions that relate two or
more significant parameters, such as slope height or slope angle of
landslide areas.
The bivariate statistical approach is widely employed by the earth scientists
and numerous parameters may be taken into consideration: lithology, slope
angle, slope height, land use, distance from major structures, drainage
density, relief morphology, closeness of the facet to a river, attitude of
lithotypes. This approach has been successfully employed by researchers
mapping hazard of superficial failures that affect prevalently weathered and
soil covers, triggered by heavy rainfall.
Multivariate statistical analysis
Although the multivariate statistical approach had already been successfully
applied in several areas of applied geology, such as petroleum exploration,
the application of this technique to landslide hazard assessment began since
the second half of 70s. The so-called black-box statistical approaches are
based on the analysis of functional links among the various predisposing
factors and present and past landslide distribution.
The procedure involves several preliminary steps which are undertaken in a
test area. Once the results achieved have been verified, they are extended
to the entire area under examination. The following steps are required.
1. Classification of the study area into land units.
2. Identification of significant factors and creation of input maps.
The input variables include information concerning the landslides (i.e.
typology, degree of activity) and geo-referencing. Several attributes are
automatically derived from statistical operations performed on the basic
parameters (mean, standard deviation, maximum or minimum values). An
important aspect is the conversion of various parameters from nominal to
numeric, such as geological composition or vegetation cover. This can be
done through the creation of dummy variables or by coding and ranking the
classes based on the relative percentage of the area affected by landsliding.
The two methods are similar but the latter is to be preferred.
3. Construction of a landslide map.
4. Identification of the percentage of landslide-affected areas in every land
unit and their classification into unstable and stable units.
The threshold value of this classification is fixed every time on the basis of
two requirements: a) in areas with high landslide density, the threshold
should be based on relatively high percentages in order to achieve two
statistically representative groups; b) however, even a relatively low
landslide density must be taken into consideration as it could represent a
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-25
risk for human activities. In general, the decision to carry out the analysis
on two groups only (unstable and stable land units) simplifies the problem
from a statistical point of view but hinders the identification of various
combinations of factors related to different hazard types.
5. Combination of the parameter maps with the land unit map and creation
of an absence/presence matrix of a given class of a given parameter within
each land unit.
6. Multivariate statistical analysis.
The statistical analysis most frequently used are discriminant analysis or
regressive multiple analysis which are often employed in parallel within the
same project. It is preferable to apply discriminant analysis (stepwise or
canonical discriminant analysis) with continuous variables, while the
regressive analysis can be used even with nominal variables.
7. Reclassification of land units based on the results achieved in the
previous phase and their classification into susceptibility classes.
In the discriminant analysis for example, the inspection of the standardised
discriminant coefficient allows the contribution of various parameters in
causing slope instability to be quantified and, as a result, enables objective
reclassification of the study area. By transforming the classification function
scores into probabilities, the susceptibility map can then be converted into a
hazard map.
Limits and uncertainties
Black-box are conceptually simple but, due to the great complexity in
identifying the slope failure processes and the difficulty in systematically
collecting the different factors related to landsliding, the task of creating
a geomorphological predictive model enabling actual/potential unstable
slopes to be identified over large areas, is difficult operationally.
Errors in mapping past and present landslides will exert a large and not
readily predictable influence on statistical models, particularly if errors
are systematic in not recognizing specific landslide types.
Additionally, being data-driven, a statistical model built up for one region
cannot readily be extrapolated to the neighbouring areas.
5.4.1.2.2 Geotechnical models
Deterministic analysis
This type of approach involves analysing specific sites or slopes in
engineering terms. The main physical properties are quantified and applied
to specific mathematical models and the safety factor is calculated. These
models (mono, bi- and tri-dimensional) are commonly used in soil
engineering for slope-specific stability studies. The approach is widely
employed in civil engineering and engineering geology and has been applied
to landslide hazard assessment and mapping, especially after the
introduction of GIS. Accuracy and reliability is improved as detailed
knowledge of the area of application increases. A deterministic approach
was traditionally considered to be sufficient for both homogenous and non-
homogenous slopes. The index of stability is the well known safety factor,
based on the appropriate geotechnical model. The calculation of the safety
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-26
factor, F, requires geometrical data, shear strength parameters and
information on pore water pressure. Moreover, decisions must be made on
whether to use peak shear strength values or residual shear strength values
(or values in between) for specific parts of the slip surface. For these
reasons such methods are normally applied only in small areas and at
detailed scales. Calculations of the safety factor must be made for each
individual slope or area before a hazard map can be prepared.
The safety factor enables the evaluation on the slope stability degree and
an objective comparison among different slopes. Usually the probability of
occurrence of a landslide is not calculated unless the safety factor is related
to the temporal occurrence of the possible triggering factor (i.e. critical
precipitation return time). A reference for assessing the relative hazard
based on F has been proposed by Ward (1996).
Tab.5.2 - Hazard classes related to safety factor F (Ward, 1976).
Probabilistic analysis
For decades, geotechnical modelling and analysis within a deterministic
framework has facilitated the quantification of safety or reliability. However,
performance indicators such as the factor of safety, F, do not take into
account the variability of geotechnical parameters of terrains such as
cohesion c, angle of internal friction and the undrained shear strength susome of which may also vary in magnitude with time. The spatial and
temporal variability of pore water pressure is again very important but is
not reflected in the calculated values of the conventional factor of safety.
The probability of failure is defined as the probability that the performance
function has a value below the threshold value. Considering the factor of
safety, F, as the performance function, the threshold value is 1 and
probability of failure pf may, therefore, defined as:
pf = P[F 1.7
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-27
The numerator gives the extent to which the average value is above the
threshold value and the denominator reflects the dispersion from this
average value.
Three commonly used methods of probability calculation are:
First Order Second Moment Method (FOSM);
Point Estimate Method;
Monte Carlo Simulation Method.
The availability of GIS can facilitate the use of a deterministic or a
probabilistic geotechnical approach as part of a methodology of landslide
hazard assessment. For example, after subdivision of an area or region into
elements or small areas, the factor of safety of individual sloping areas may
be computed and then mapped. Alternatively, using a probabilistic
framework, the probability of failure of individual slopes could be computed
and then mapped. Depending on the adopted hazard assessment approach,
this information could be used on its own or combined with other factors or
factor maps to produce susceptibility maps and/or hazard maps.
Limits and uncertainties
The deterministic models that provide safety factor calculation usually do
not provide return time of landslide phenomena.
Systematical uncertainties derive from the following considerations:
o a soil mass can only be investigated at a finite number of points;
o the number of field and laboratory tests conducted to determine soil
parameters is limited by financial and time constraints;
o the testing equipment and methods are not perfect.
Other uncertainties are associated with geotechnical models, landslide
mechanisms, their occurrence and impact.
A deterministic analysis of landslide hazard can be done only for single
slopes or limited areas where a large and detailed geotechnical data are
available.
Reliable mechanical models are not yet available for several types of
structurally complex rock units.
5.5 Temporal prediction
The temporal prediction of landslide hazard is essentially based on definition
of the probability of occurrence of landslides. While spatial prediction
provides a relative hazard of different slopes, the temporal prediction
provides an absolute hazard.
For some authors the term absolute hazard is not referred to the probability
of occurrence, but to the definition of the safety factor (F) that, as already
discussed, indicates only a relative zoning of a slope-failure propensity and
not a probabilistic estimate of occurrence.
5.5.1 Analysis of return time
If P is the annual probability of occurrence of a landslide, the return time T
of the event is given by 1/P.
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-28
The probability of occurrence of m events in a period of N years is given by:
P m NN
m N mP Pm N m( , )
!
!( )!( )=
1
In case of rare events compared with the available temporal scale (for
N>30 or P
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-29
5.5.2 Analysis of intensity/magnitude
The BUWAL method (1998) is used for the analysis of landslide hazard. This
is calculated through a matrix between intensity, expressed as velocity
(Tab. 5.5) and magnitude (Tab. 5.6), vs. return times of potential
landslides.
Velocity Return time (years) Probability (annual) Hazard1 < 1 (active) 1 11 1-30 0.03 31 30-100 0.01 2
1 100-1000 0.001 2
2 < 1 (active) 1 32 1-30 0.03 42 30-100 0.01 32 100-1000 0.001 22 > 1000 0.0001 1
3 < 1 (active) 1 4
3 1-30 0.03 43 30-100 0.01 43 100-1000 0.001 33 > 1000 0.0001 2
Table 5.5 - Potential landslide hazard related to velocity and return
time (BUWAL, 1998)
Magnitude Return time (years) Probability (annual) Hazard1-2 < 1 (active) 1 2
1-2 1-30 0.03 31-2 30-100 0.01 2-31-2 100-1000 0.001 2
3-4 < 1 (active) 1 33-4 1-30 0.03 3-43-4 30-100 0.01 33-4 100-1000 0.001 2-3
3-4 > 1000 0.0001 1
6-9 < 1 (active) 1 46-9 1-30 0.03 46-9 30-100 0.01 46-9 100-1000 0.001 36-9 > 1000 0.0001 1-2
Table 5.6 - Potential landslide hazard related to magnitude and
return time (BUWAL, 1998)
Since vulnerability is proportional to landslide phenomena, the levels of
landslide hazard, when associated to the elements at risk, correspond to
specific risk (Cruden & Varnes, 1996).
5.6 Prediction of evolution
The prediction of landslide evolution consists in the detection of the area
that can be directly or indirectly affected by a landslide, through the
analysis of:
o prediction of run-out;
o prediction of retrogression limits;
o prediction of lateral expansion.
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-30
5.6.1 Prediction of run-out
Current an past research into the run-out calculation of a fast-moving
landslide (i.e. rock falls, debris flows, rock avalanches) can generally be
grouped into three categories. The first includes empirical models aimed at
providing practical tools for predicting the run-out distance and distribution
of landslide accumulation. The second category includes simplified analytical
models that describes the physical behaviour of mass movement, based on
lumped mass approaches in which the mass is assumed as a single point.
The third includes numerical simulations of conservation equations of mass,
momentum and energy that describe the dynamic motion of landslide mass,
and/or a rheological model to describe the material behaviour of sliding
mass.
5.6.2 Prediction of retrogression limits
The prediction of retrogression limits is essentially based on the analysis of
geomorphologic evidences on the field that define the distribution of activity
(i.e. tension cracks, counter slopes). Some landslide typologies are
generally characterised by a retrogressive evolution such as rotational and
translational slides, rock topples/falls affecting jointed rocks. In most cases,
the ultimate limit is represented by the catchments divide so that the
analysis, although conservative, can be carried out simply by using
topographical information.
5.6.3 Prediction of lateral expansion
The prediction of lateral expansion is important in the analysis of earth
flows or liquefaction phenomena, when the displaced mass is very fluid and
may expand to the slope toe. The prediction is very complex and mostly
depends on slope morphology, grain-size and water content of soils, shear
strength of materials, pore pressure and lateral stress coefficient.
6 Landslide hazard mapping
6.1 Introduction
The identification and map portrayal of areas highly susceptible to
damaging landslides are first and necessary steps toward loss-reduction
(Zeizel, 1988). There are four general categories of potential users of
landslide hazard information (Wold and Jochim, 1989):
o scientists and engineers who use the information directly;
o planners and decision makers who consider landslide hazards among
other land-use and development criteria;
o developers, builders, and financial and insuring organizations;
o interested citizens, educators, and others with little or no technical
experience.
Members of these groups differ widely in the kinds of information they need
and in their ability to use that information (Wold and Jochim, 1989).
Most local governments do not have landslide hazard maps and do not have
funding available for mapping activities, and such communities usually look
to a higher level of government for mapping. The U.S. Geological Survey
(USGS) has provided maps in some areas (e.g., demonstration
-
ARMONIA PROJECT (Contract n 511208) Deliverable 2.1
B.III-31
mapping of San Mateo County, California; Brabb et al., 1972), but in
general, landslide hazard mapping by the USGS has had limited geo-
graphic coverage. Although most local communities look to their state as
the primary source of maps, few states have undertaken significant
landslide hazard mapping programs. However, there are important
exceptions. California and Oregon, for example, have undertaken landslide
hazard mapping at standard USGS mapping scales. These maps provide an
excellent starting point for local communities and, importantly, form the
basis for state laws that require a certain level of compliance with the
information they provide.
The considerable variability among state geological agencies, particularly in
terms of their existing mapping capabilities and projected funding
environments, makes it difficult to provide detailed commentary and
suggestions regarding the partnerships between the USGS and states for
landslide hazard mapping and assessment. Historically, there have been
strong ties between the USGS and state geological surveys in the realm of
mapping (e.g., Ellen et al., 1993; Coe et al., 2000b) and, to a lesser extent,
for the identification and mitigation of natural hazards. The suggestion in
the national strategy proposal (Spiker and Gori, 2000) of mapping
partnerships, using a model based on competitive grants and matching
funds (as with the existing National Geologic Cooperative Mapping
Program), would undoubtedly provide resources for a considerable amount
of much-needed mapping. However, such a model raises the possibility that
hazard ma