landsat data continuity mission (ldcm) usgs project status report january 6, 2009 dave hair usgs...
Post on 18-Dec-2015
217 views
TRANSCRIPT
Landsat Data Continuity Mission (LDCM) Landsat Data Continuity Mission (LDCM) USGS Project Status ReportUSGS Project Status Report
January 6, 2009
Dave HairUSGS LDCM Project [email protected]
U.S. Department of the Interior 2
TopicsTopics
USGS LDCM Project Team update Ground system development status Landsat L0R RFI Results Algorithm Delivery Status
U.S. Department of the Interior
USGS LDCM Project Organization
Contactor Key * EROS TSSC (SGT) ** EROS LDCC (SAIC) *** The Aerospace Corp **** Flight Ops Team (TBD)
TSSC Chief SE - Jim Nelson*
Project Scientist - John DwyerScience Office – M Bouchard*Cal/Val Lead - Ron Morfitt*
Landsat Science Team Manager
Dr. Tom Loveland
Financial Analyst – Connie Hamann/Denny TolliverAdmin Assistant - Christine MadiganCM – Mike Wehde*
USGS SE – Grant MahLDCC – Joel Nelson**
USGS SE – Brian SauerTSSC – Todd Taylor*LDCC – Steve Zahn**
I&T Lead – Royce Reit*
Int’l Ground Station Network Manager
Steve Labahn
GS Support Lead - Kari Wulf*Scheduler – Jay Ugofsky*
Flight Operations Segment Manager
Steven Walters
Data Processing and Archive Segment Manager
Karen Zanter
Integration and Test Systems Engineer
Chris Torbert
FOT Lead - TBD****
USGS HQ LRS ProgramBruce Quirk / Tim Newman
NASA LDCM Project MgrBill Ochs
LDCM Project ManagerDave Hair (Acting)
Development ManagerRod Pater
Chief EngineerJim Lacasse
Technical Resource ManagerDave Hair
Flight Systems ManagerNicolaie Todirita
GS Integration LeadDoug Daniels***
3
U.S. Department of the Interior
Ground System Development StatusGround System Development Status
Accomplishments and Highlights Preliminary design nearing completion and critical design initiated Worked with NASA to the award of the Mission Operations Element contract Evaluated responses to Request For Information (RFI) for demodulators Space to Ground Interface Technical Interchange Meeting Nov 19-21 Continued research on automated cloud cover assessment algorithm
• Algorithm approach has been streamlined, i.e. eliminated time-series and parallax techniques
Full-scene cloud and shadow masks have been developed for use in developing training statistics for decision-tree algorithms and for validating algorithm results
Evaluating trade study hardware required for the internal cache OLI Calibration/Validation Technical Interface Meeting Dec 2-3. The flow
for delivery of algorithms to the ground system was discussed, followed by in-depth technical discussions of algorithm-specific issues.
U.S. Department of the Interior
Ground System Design Reviews
Critical Design Reviews DateCollection Activity Planning Element (CAPE)Data Processing and Archive Segment (DPAS)Ground Network Element (GNE)Ground System
Jan 2009Jul 2009
Sep 2009Dec 2009
Preliminary Design Reviews DateCollection Activity Planning Element (CAPE)Infrastructure Element (IE) - SpiralUser Portal Element (UPE)Storage and Archive Element (SAE)Image Processing Element (IPE)
Apr 2008 Jul 2008Jul 2008
Aug 2008Oct 2008
Ground Network Element (GNE)Mission Operations Element (MOE)Ground System
Apr 2009Apr 2009
May 2009
5
U.S. Department of the Interior
Ground System ScheduleGround System Schedule
Spacecraft PDR CDR PSR
OLICDR PER
2008 2009 2010 2011 2012 2013J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J JA S O N D
Mission
CDR
LRD
SRR
Launch Site LRD
IIRR
KDP-D
10 Months Reserve
3.5 Months Reserve
2 Weeks Reserve
PSRPSR
PDR
KDP-C
4 Months Reserve
Critical Path
PDRTIRS
CDR PSRPERSCR PDR
3 Months Reserve
CPTs/MRTsw/ OLI & Bus
SRRSRR
LRR
LVFRR
MRR
S&MSR
ORRFORSIRCR
PERSRR
Ground SysPDR CDR
PDR CDRMOE
SRR PSR
GRTsComplete
GRTsBegin
4 Months Reserve
Spacecraft PDR CDR PSR
OLICDR PER
2008 2009 2010 2011 2012 2013J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J JA S O N D
Mission
CDR
LRD
SRR
Launch Site LRD
IIRR
KDP-D
10 Months Reserve
3.5 Months Reserve
2 Weeks Reserve
PSRPSR
PDR
KDP-C
4 Months Reserve
Critical Path
PDRTIRS
CDR PSRPERSCR PDR
3 Months Reserve
CPTs/MRTsw/ OLI & Bus
SRRSRR
LRRLRR
LVFRRLVFRR
MRRMRR
S&MSRS&MSR
ORRORRFORFORSIRSIRCR
PERSRR
Ground SysPDR CDR
PDR CDRMOE
SRR PSR
GRTsComplete
GRTsBegin
4 Months Reserve
Spacecraft PDR CDR PSR
OLICDR PER
2008 2009 2010 2011 2012 2013J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J JA S O N D
Mission
CDR
LRD
SRR
Launch Site LRD
IIRR
KDP-D
10 Months Reserve
3.5 Months Reserve
2 Weeks Reserve
PSRPSR
PDR
KDP-C
4 Months Reserve
Critical Path
PDRTIRS
CDR PSRPERSCR PDR
3 Months Reserve
CPTs/MRTsw/ OLI & Bus
SRRSRR
LRR
LVFRR
MRR
S&MSR
ORRFORSIRCR
PERSRR
Ground SysPDR CDR
PDR CDRMOE
SRR PSR
GRTsComplete
GRTsBegin
4 Months Reserve
Spacecraft PDR CDR PSR
OLICDR PER
2008 2009 2010 2011 2012 2013J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J JA S O N D
Mission
CDR
LRD
SRR
Launch Site LRD
IIRR
KDP-D
10 Months Reserve
3.5 Months Reserve
2 Weeks Reserve
PSRPSR
PDR
KDP-C
4 Months Reserve
Critical Path
PDRTIRS
CDR PSRPERSCR PDR
3 Months Reserve
CPTs/MRTsw/ OLI & Bus
SRRSRR
LRRLRR
LVFRRLVFRR
MRRMRR
S&MSRS&MSR
ORRORRFORFORSIRSIRCR
PERSRR
Ground SysPDR CDR
PDR CDRMOE
SRR PSR
GRTsComplete
GRTsBegin
4 Months Reserve
U.S. Department of the Interior
Landsat L0R RFILandsat L0R RFI
Purpose Gage interest in historical Landsat L0R data (MSS, TM, ETM+)
Determine interest in processing L0R data for custom product generation as a service to others
Determine expectations of the USGS to provide the necessary processing software
Determine the potential frequency and volume of requests
Results Responses received from two commercial firms, both of which are
interested in providing custom processing services
Cost of L0R data will be a factor driving volume of requests
Potential confusion in client base, i.e. free L1T from USGS vs. commercially provided products
U.S. Department of the Interior
Algorithm Delivery Status
Total of 45 algorithms to be delivered for implementation to support on-orbit initialization and verification Ingest Image Assessment Product Generation CalVal Toolkit
An additional 14 algorithms to be implemented by Initial Operations Algorithms are delivered in phases according to progression in the
design and development of OLI instrument and Ground System Image Processing Element (IPE) Phase 1 – completed for IPE PDR (Oct ’08) Phase 2 – to be completed by Data Processing & Archive Segment CDR
(Jul ’09) Phase 3 – to be completed by Ground Readiness Tests (GRTs) Phase 4 – delivered post-launch