Page 1: Landsat Data Continuity Mission (LDCM) USGS Project Status Report January 6, 2009 Dave Hair USGS LDCM Project Manager hair@usgs.gov

Landsat Data Continuity Mission (LDCM) Landsat Data Continuity Mission (LDCM) USGS Project Status ReportUSGS Project Status Report

January 6, 2009

Dave HairUSGS LDCM Project [email protected]

Page 2: Landsat Data Continuity Mission (LDCM) USGS Project Status Report January 6, 2009 Dave Hair USGS LDCM Project Manager hair@usgs.gov

U.S. Department of the Interior 2

TopicsTopics

USGS LDCM Project Team update Ground system development status Landsat L0R RFI Results Algorithm Delivery Status

Page 3: Landsat Data Continuity Mission (LDCM) USGS Project Status Report January 6, 2009 Dave Hair USGS LDCM Project Manager hair@usgs.gov

U.S. Department of the Interior

USGS LDCM Project Organization

Contactor Key * EROS TSSC (SGT) ** EROS LDCC (SAIC) *** The Aerospace Corp **** Flight Ops Team (TBD)

TSSC Chief SE - Jim Nelson*

Project Scientist - John DwyerScience Office – M Bouchard*Cal/Val Lead - Ron Morfitt*

Landsat Science Team Manager

Dr. Tom Loveland

Financial Analyst – Connie Hamann/Denny TolliverAdmin Assistant - Christine MadiganCM – Mike Wehde*

USGS SE – Grant MahLDCC – Joel Nelson**

USGS SE – Brian SauerTSSC – Todd Taylor*LDCC – Steve Zahn**

I&T Lead – Royce Reit*

Int’l Ground Station Network Manager

Steve Labahn

GS Support Lead - Kari Wulf*Scheduler – Jay Ugofsky*

Flight Operations Segment Manager

Steven Walters

Data Processing and Archive Segment Manager

Karen Zanter

Integration and Test Systems Engineer

Chris Torbert

FOT Lead - TBD****

USGS HQ LRS ProgramBruce Quirk / Tim Newman

NASA LDCM Project MgrBill Ochs

LDCM Project ManagerDave Hair (Acting)

Development ManagerRod Pater

Chief EngineerJim Lacasse

Technical Resource ManagerDave Hair

Flight Systems ManagerNicolaie Todirita

GS Integration LeadDoug Daniels***

3

Page 4: Landsat Data Continuity Mission (LDCM) USGS Project Status Report January 6, 2009 Dave Hair USGS LDCM Project Manager hair@usgs.gov

U.S. Department of the Interior

Ground System Development StatusGround System Development Status

Accomplishments and Highlights Preliminary design nearing completion and critical design initiated Worked with NASA to the award of the Mission Operations Element contract Evaluated responses to Request For Information (RFI) for demodulators Space to Ground Interface Technical Interchange Meeting Nov 19-21 Continued research on automated cloud cover assessment algorithm

• Algorithm approach has been streamlined, i.e. eliminated time-series and parallax techniques

Full-scene cloud and shadow masks have been developed for use in developing training statistics for decision-tree algorithms and for validating algorithm results

Evaluating trade study hardware required for the internal cache OLI Calibration/Validation Technical Interface Meeting Dec 2-3. The flow

for delivery of algorithms to the ground system was discussed, followed by in-depth technical discussions of algorithm-specific issues.

Page 5: Landsat Data Continuity Mission (LDCM) USGS Project Status Report January 6, 2009 Dave Hair USGS LDCM Project Manager hair@usgs.gov

U.S. Department of the Interior

Ground System Design Reviews

Critical Design Reviews DateCollection Activity Planning Element (CAPE)Data Processing and Archive Segment (DPAS)Ground Network Element (GNE)Ground System

Jan 2009Jul 2009

Sep 2009Dec 2009

Preliminary Design Reviews DateCollection Activity Planning Element (CAPE)Infrastructure Element (IE) - SpiralUser Portal Element (UPE)Storage and Archive Element (SAE)Image Processing Element (IPE)

Apr 2008 Jul 2008Jul 2008

Aug 2008Oct 2008

Ground Network Element (GNE)Mission Operations Element (MOE)Ground System

Apr 2009Apr 2009

May 2009

5

Page 6: Landsat Data Continuity Mission (LDCM) USGS Project Status Report January 6, 2009 Dave Hair USGS LDCM Project Manager hair@usgs.gov

U.S. Department of the Interior

Ground System ScheduleGround System Schedule

Spacecraft PDR CDR PSR

OLICDR PER

2008 2009 2010 2011 2012 2013J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J JA S O N D

Mission

CDR

LRD

SRR

Launch Site LRD

IIRR

KDP-D

10 Months Reserve

3.5 Months Reserve

2 Weeks Reserve

PSRPSR

PDR

KDP-C

4 Months Reserve

Critical Path

PDRTIRS

CDR PSRPERSCR PDR

3 Months Reserve

CPTs/MRTsw/ OLI & Bus

SRRSRR

LRR

LVFRR

MRR

S&MSR

ORRFORSIRCR

PERSRR

Ground SysPDR CDR

PDR CDRMOE

SRR PSR

GRTsComplete

GRTsBegin

4 Months Reserve

Spacecraft PDR CDR PSR

OLICDR PER

2008 2009 2010 2011 2012 2013J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J JA S O N D

Mission

CDR

LRD

SRR

Launch Site LRD

IIRR

KDP-D

10 Months Reserve

3.5 Months Reserve

2 Weeks Reserve

PSRPSR

PDR

KDP-C

4 Months Reserve

Critical Path

PDRTIRS

CDR PSRPERSCR PDR

3 Months Reserve

CPTs/MRTsw/ OLI & Bus

SRRSRR

LRRLRR

LVFRRLVFRR

MRRMRR

S&MSRS&MSR

ORRORRFORFORSIRSIRCR

PERSRR

Ground SysPDR CDR

PDR CDRMOE

SRR PSR

GRTsComplete

GRTsBegin

4 Months Reserve

Spacecraft PDR CDR PSR

OLICDR PER

2008 2009 2010 2011 2012 2013J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J JA S O N D

Mission

CDR

LRD

SRR

Launch Site LRD

IIRR

KDP-D

10 Months Reserve

3.5 Months Reserve

2 Weeks Reserve

PSRPSR

PDR

KDP-C

4 Months Reserve

Critical Path

PDRTIRS

CDR PSRPERSCR PDR

3 Months Reserve

CPTs/MRTsw/ OLI & Bus

SRRSRR

LRR

LVFRR

MRR

S&MSR

ORRFORSIRCR

PERSRR

Ground SysPDR CDR

PDR CDRMOE

SRR PSR

GRTsComplete

GRTsBegin

4 Months Reserve

Spacecraft PDR CDR PSR

OLICDR PER

2008 2009 2010 2011 2012 2013J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J JA S O N D

Mission

CDR

LRD

SRR

Launch Site LRD

IIRR

KDP-D

10 Months Reserve

3.5 Months Reserve

2 Weeks Reserve

PSRPSR

PDR

KDP-C

4 Months Reserve

Critical Path

PDRTIRS

CDR PSRPERSCR PDR

3 Months Reserve

CPTs/MRTsw/ OLI & Bus

SRRSRR

LRRLRR

LVFRRLVFRR

MRRMRR

S&MSRS&MSR

ORRORRFORFORSIRSIRCR

PERSRR

Ground SysPDR CDR

PDR CDRMOE

SRR PSR

GRTsComplete

GRTsBegin

4 Months Reserve

Page 7: Landsat Data Continuity Mission (LDCM) USGS Project Status Report January 6, 2009 Dave Hair USGS LDCM Project Manager hair@usgs.gov

U.S. Department of the Interior

Landsat L0R RFILandsat L0R RFI

Purpose Gage interest in historical Landsat L0R data (MSS, TM, ETM+)

Determine interest in processing L0R data for custom product generation as a service to others

Determine expectations of the USGS to provide the necessary processing software

Determine the potential frequency and volume of requests

Results Responses received from two commercial firms, both of which are

interested in providing custom processing services

Cost of L0R data will be a factor driving volume of requests

Potential confusion in client base, i.e. free L1T from USGS vs. commercially provided products

Page 8: Landsat Data Continuity Mission (LDCM) USGS Project Status Report January 6, 2009 Dave Hair USGS LDCM Project Manager hair@usgs.gov

U.S. Department of the Interior

Algorithm Delivery Status

Total of 45 algorithms to be delivered for implementation to support on-orbit initialization and verification Ingest Image Assessment Product Generation CalVal Toolkit

An additional 14 algorithms to be implemented by Initial Operations Algorithms are delivered in phases according to progression in the

design and development of OLI instrument and Ground System Image Processing Element (IPE) Phase 1 – completed for IPE PDR (Oct ’08) Phase 2 – to be completed by Data Processing & Archive Segment CDR

(Jul ’09) Phase 3 – to be completed by Ground Readiness Tests (GRTs) Phase 4 – delivered post-launch