l natural gas pt thomson extension - petroleumnews.com · l natural gas vol. 23, ... noted that...
TRANSCRIPT
l E X P L O R A T I O N & P R O D U C T I O N
l P I P E L I N E S & D O W N S T R E A M
l N A T U R A L G A S
Vol. 23, No. 37 • www.PetroleumNews.com A weekly oil & gas newspaper based in Anchorage, Alaska Week of September 16, 2018 • $2.50
page2
Newfield looking at Alaska;Begich, Dunleavy weigh in;L48 shale boom tapering off
TEXAS-BASED INDEPENDENT
NEWFIELD EXPLORATION has people visit-
ing Alaska to look at the North Slope’s geo-
logic potential.
Headquartered in The Woodlands, Texas,
the visiting scientists are not handing out busi-
ness cards to everyone they meet, so the visit
is very hush-hush.
Per the big independent’s website,
Newfield is an oil company focused on profitably growing liq-
uids-rich unconventional resource plays in the Anadarko and
Arkoma basins of Oklahoma, the Williston basin (Bakken) of
State looks for RIK gas interest;includes Prudhoe, Point Thomson
The Alaska Department of Natural Resources, Division of Oil
and Gas, is soliciting interest in potential royalty in-kind natural
gas from the Prudhoe Bay and Point Thomson units.
The solicitation, dated Aug. 31, asks for expressions of interest
by letter within 30 days.
DNR said it is considering whether to take the state’s royalty
on future natural gas production from Prudhoe Bay and Point
Thomson in value or in kind.
“If DNR takes the royalty in kind, it is currently considering a
noncompetitive contract,” solicitation says. The department said
that to consider a noncompetitive contract it “first considers
whether there is a lack of competition and whether a noncompet-
GAO questions lack of preliminarydesign review for polar icebreakers
The U.S. Government Accountability Office has issued a
report raising questions over the reliability of the estimated
cost and schedule for developing new heavy polar icebreakers
for the U.S. Coast Guard. The Department of Homeland
Security, the agency that includes the Coast Guard, has
accepted the GAO’s findings.
Currently the Coast Guard only operates two polar capable
icebreakers: the Healy, a medium duty icebreaker, much used
as a base for polar research, and the Polar Star, which is a
heavy-duty icebreaker but is 41 years old. A third icebreaker,
the Polar Sea, sister ship to the Polar Star, is laid up in port and
has become a source of spare parts for the Polar Star.
Colville barges diesel to SlopeTransportation company Colville has transported 2 million
gallons of diesel fuel by barge to Prudhoe Bay on the North
Slope, the company has announced. This was the first bulk
delivery of fuel to the Slope by barge since the 1990s, and
possibly the largest shipment of its type ever, the company
said. The supply barge, owned and operated by Crowley
Marine, arrived at Deadhorse on Sept. 6. Because of the shal-
low water depths, the barge had to be moored 3 miles off-
shore, with the fuel being carried to shore in smaller vessels.
Onshore, the fuel was pumped into tanker trucks for transfer
to Colville’s tank farm in Deadhorse.
The U.S. Coast Guard and BP oversaw the operation, said
Dave Pfeifer, Colville president and chief executive officer.
More typically, fuel for use on the North Slope is delivered
to Deadhorse from a refinery in Valdez, using tanker trucks
see INSIDER page 10
see GAS INTEREST page 8
see POLAR ICEBREAKERS page 8
see DIESEL DELIVERY page 7
EIA: Brent averaged $73/barrel inAugust; US crude 10.9 million bpd
Pt Thomson extensionState stays 2019 date in 2012 settlement on Alaska LNG project progress
By KRISTEN NELSONPetroleum News
The state has stayed a deadline in its 2012 set-
tlement with Point Thomson operator
ExxonMobil Production Co.
The settlement required a plan for expansion of
Point Thomson production by the end of 2019 if a
major gas sale hadn’t been sanctioned by June
2016. Late last year the state and ExxonMobil
reached agreement on the company’s expansion
plan. The settlement required either increasing
production to 30,000 barrels per day of condensate
(the current facilities support 10,000 bpd, although
that rate has rarely been achieved) or moving nat-
ural gas to Prudhoe Bay for injection there (requir-
ing an agreement with the Prudhoe Bay working
interest owners and construction of a gas pipeline
between the fields).
Moving natural gas to Prudhoe was
ExxonMobil’s choice.
That work has now been deferred.
An optimistic outlookConocoPhillips ups GMT-2 forecast; moves ahead on Willow, further exploration
By ALAN BAILEYPetroleum News
In a highly upbeat presentation to a
joint meeting of the Alaska House and
Senate Resources committees on Sept.
10, Scott Jepsen, ConocoPhillips Alaska
vice president of external affairs and
transportation, overviewed his compa-
ny’s current exploration and develop-
ment plans in Alaska, and the resulting
major uptick in the company’s expectations for its
future Alaska oil production.
Increased production estimateJepsen said that his company has upped the esti-
mated peak production for its Greater
Mooses Tooth 2 development in the
northeastern National Petroleum
Reserve-Alaska from 30,000 barrels of
oil per day to 38,000 bpd. The federal
Bureau of Land Management has pub-
lished a final environmental impact state-
ment for the project, with a record of
decision anticipated in October. That
could lead to a final investment decision
for the project later this year, Jepsen said.
Meanwhile the Greater Mooses Tooth 1 devel-
opment is moving ahead, with first oil anticipated
by the end of the year. Peak production is expected
to run at about 30,000 bpd.
Trudeau treads carefullyAdministration examining options to salvage Trans Mountain, including an appeal
By GARY PARKFor Petroleum News
T he future of large-scale resource
projects in Canada depends heavily
on how his government responds to a
federal court ruling that has stalled
progress on the Trans Mountain pipeline
expansion, said Prime Minister Justin
Trudeau.
“What we need is not just this
pipeline. We need to be able to build resource proj-
ects of all different types with appropriate social
license,” he told reporters.
He said the objective is to ensure that Trans
Mountain and other projects do not get “bogged”
down in endless court battles.
Trudeau, firing back at his critics,
noted that TransCanada’s Keystone XL
project was long ago approved in
Canada, but has become entangled in the
United States over a failure to engage in
detailed consultations with communities
along the pipeline right of way.
“This is the way that the world is
going and if we can demonstrate clarity
and certainty for businesses through the
process to the investors we will be able
to get more built,” he said.
Decision impacts communitiesTrudeau called the court decision on Trans
Mountain “frustrating and devastating” for com-
see POINT THOMSON page 12
see CONOCO OUTLOOK page 11
see TRANS MOUNTAIN page 9
Also Sept. 10, the Alaska GaslineDevelopment Corp. announced that
ExxonMobil and AGDC had agreed towhat the corporation called “certain keyterms including price and a volume basisfor a Gas Sales Agreement,” captured in
a “Gas Sales Precedent Agreement”signed Sept. 10.
SCOTT JEPSEN
JUSTIN TRUDEAU
2 PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018
GOVERNMENT
FINANCE & ECONOMY
PIPELINES & DOWNSTREAM
EXPLORATION & PRODUCTION
ENVIRONMENT & SAFTEY
6 National rig count unchanged at 1,048
4 White requests Supreme Court rehearing
7 Hilcorp seeks rule change in NM gas basin
4 US accused of planning Keystone protest crackdown
6 Pipeline company found guilty in oil spill
6 Average gas price steady at $2.91/ gallon
3 BP’s Prudhoe power station OK’d for VPP
3 Northstar Kuparuk gas injection request
2 Brent averaged $73 per barrel in August
EIA projects $73 this year, $74 in ’19, up $3 from Augustforecast; US crude averaged 10.9 million bpd in August, up 120,000 from June
Pt Thomson extensionState stays 2019 date in settlement on Alaska LNG project progress
An optimistic outlookConoco ups GMT-2 forecast; moves ahead on Willow
Trudeau treads carefullyAdministration examining options to salvage Trans Mountain
ON THE COVER
Insider: Newfield looking at Alaska; Begich,Dunleavy weigh in; L48 shale boom tapering off
State looks for RIK gas interest;includes Prudhoe, Point ThomsonGAO questions lack of preliminarydesign review for polar icebreakersColville barges diesel to Slope
Petroleum News Alaska’s source for oil and gas newscontents
TELECOMMUNICATIONS AT
WORK IN ALASKA
Telecom Engineering
Project Management
Two-way Radio Systems
Microwave & Satellite Systems
Fiber Optics & Network Cabling
FCC Licensing
Tower Construction & Inspection
(907) 751-8200 www.nstiak.com
l F I N A N C E & E C O N O M Y
Brent averaged $73 per barrel in AugustEIA projects $73 this year, $74 in ’19, up $3 from August forecast; US crude averaged 10.9 million bpd in August, up 120,000 from June
By KRISTEN NELSONPetroleum News
The Brent crude oil spot price averaged $73 per barrel
in August, down almost $2 from July, the U.S.
Energy Information Administration said Sept. 11 in its
Short-Term Energy Outlook. The expected average for the
year is $73 per barrel, rising to $74 in 2019.
West Texas Intermediate is expected to average about
$6 per barrel lower than Brent in both years. EIA said both
the Brent and WTI forecasts for 2019, $74 and $67 per
barrel respectively, are $3 per barrel higher than in the
agency’s August STEO.
EIA Administrator Dr. Linda Capuano said in a Sept.
11 statement that rising upward expectations were “large-
ly due to lower expectations for
Canada’s crude oil production and
OPEC’s condensate production.”
The agency said production from
the United States was also expected
to be lower than projected in 2019.
But, Capuano said, the U.S.
“remains on pace to set new crude
oil production records in 2018 and
2019,” with an average of 10.7 mil-
lion barrels per day this year, up
almost 14 percent from last year.
U.S. crude oil production is estimated to have averaged
10.9 million bpd in August, EIA said, up 120,000 bpd
from June. The 2018 forecast is for an average of 10.7 mil-
lion bpd, up from 9.4 million bpd in 2017. In 2019 the
agency expects an average of 11.5 million bpd.
Globally, EIA is forecasting total global liquid fuels
inventories to drop by 400,000 bpd this year, compared
with 2017, and to increase by 100,000 bpd in 2019. “This
outlook of relatively stable inventory levels during the
forecast period contributes to a forecast of monthly aver-
age Brent crude oil prices remaining relatively stable,” the
agency said, between $72 and $76 per barrel from
September through the end of 2019.
Crude oil pricesEIA said that while crude oil prices were up for
DR. LINDA CAPUANO
see EIA OUTLOOK page 3
NOWHERE WE’DRATHER BE
www.foss.com
experienced and hardworking crews
custom-made for the far North, our
Arctic environments. With a fleet
transportation issues in extreme
been called on to solve complex
oss Maritime hasor decades, FF
experienced and hardworking crews
custom-made for the far North, our
Arctic environments. With a fleet
transportation issues in extreme
been called on to solve complex
oss Maritime has
feel right at home here.
experienced and hardworking crews
.foss.comwwww.
always safe. always ready.
feel right at home here.
experienced and hardworking crews
always safe. always ready.
PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018 3
Overhead Lifting & Rigging
Alaska Rubber& RIGGING SUPPLY
www.alaskarubber.com • Toll Free: 800-478-7600
Member of:
Associated Wire Rope Fabricators
ee
YHoW
yt our emploe thaxperiencey aining and industr, trIt is with pride
lingse Se RopirW
ou UpYYokoHoane CWWe
& AA
ailablevvaa
lintheticS
SSy
.tionsand configura, lengths widths
y ofarietV
lingsSyn
yiesesorcc& A
lingshain Sy ColloA
aa.l klasklaske in Ae in Ai Aherherht e and chain slings righ, wirtheticsyn
y e the highest qualitwners makoee yt our emploe thaxperience
ed uthorizs A’’salaskA
oristributD
Bombay DeluxeThe Spice of Life...
Serving the finest Indian Cuisine in AlaskaTraditional chicken, lamb, seafood dishes
& Indian naan bread cooked in our
Tandoor (clay oven).
Vegetarian Specialties
Delicious Appetizers — Samosas, Pakoras
Lunch Buffet
Monday — Friday, 11:00 am — 2:00 pm
Dinner
Monday — Friday, 4:30 pm — 9:00 pm
Saturday & Sunday, 12:30 pm — 9:00 pm
Ph: 907-277-1200Conveniently located in Midtown
(Valhalla Center)
555 W. Northern Lights
Anchorage, Alaska
www.BombayDeluxe.com
Order on-line for pick-up or delivery at www.FoodOnTheWay.com
August as a whole, crude oil prices and commodity
prices broadly fell early in the month. The agency noted
declines in some emerging market currencies as possibly
contributing to global economic growth concerns and the
potential impact on oil demand.
“However,” EIA said, “oil prices rose in the second
half of August following reports of reduced purchases of
Iranian crude oil ahead of the United States reinstituting
sanctions on Iran in November.” The agency noted other
supply developments which likely pulled on inventories,
contributing to higher prices.
“A restart to some Canadian production after July’s
oil sands outage is anticipated to be delayed until
September, and tropical storm activity in the U.S. Gulf of
Mexico led to the shutdown of some offshore crude oil
platforms,” EIA said.
Permian region crude oil production is estimated to
grow to 3.4 million bpd in September, with current esti-
mates of available regional refinery intake and pipeline
takeaway capacity at about 3.6 million bpd. EIA said
crude oil takeaway infrastructure constraints could con-
tribute to wide price discounts for Permian crude through
the third quarter of 2019, moderating production growth
compared to an unconstrained scenario.
“EIA still expects Permian crude oil production to
drive total U.S. production growth next year,” the agency
said, noting that many producers in the area say they can
operate profitably at prices in the mid-$50 per barrel
range, and might use higher cost transportation options
to move crude to the U.S. Gulf Coast or other regions.
“Some producers with a geographically diverse port-
folio of upstream properties could also redirect capital to
other areas or decide to reduce completion activity until
the transportation constraints ease,” the agency said.
Natural gas“EIA forecasts U.S. dry natural gas production to
increase by 10 percent in 2018 to a record high 81 billion
cubic feet per day with continued growth expected in
2019,” Capuano said.
Estimated U.S. dry natural gas production in August
was 82.2 bcf per day, up 0.7 bcf from August, the agency
said, and is projected to average 81 bcf per day this year,
up 7.4 bcf from 2017 and establishing a new record high.
EIA expects production to average 84.7 bcf per day in
2019.
The Henry Hub spot price averaged $2.96 per million
British thermal units in August, up 12 cents from July,
EIA said. The agency noted that cooling degree days in
the U.S. averaged 13 percent higher than the 10-year,
2008-17, average in August, contributing to high natural
gas demand for power presentation.
Henry Hub natural gas spot prices are expected to
average $2.99 per million Btu this year and $3.12 in
2019.
EIA said natural gas inventories have been low during
most of 2018 compared with the 2013-17 five-year aver-
age, reflecting “high residential and commercial con-
sumption in early 2018 and growth in both liquefied nat-
ural gas and pipeline exports over the past year.” l
continued from page 2
EIA OUTLOOK
ENVIRONMENT & SAFETYBP’s Prudhoe power station OK’d for VPP
The Alaska Department of Labor and Workforce Development said Sept. 5 that
BP Exploration Alaska’s Prudhoe Bay Central Power Station has been approved
for a renewal of the Alaska Occupational Safety and Health Voluntary Protection
Program at the “Star” or highest level.
The Central Power Station has been in the program since 1999, said BP
Exploration’s Beatrice Egbejimba.
“Recertification of VPP is evi-
dence of BP Exploration Alaska’s
exemplary occupational safety and
health program,” said Egbejimba, an
industrial hygienist with BP.
“The VPP program is an opportu-
nity to partner with AKOSH while
showcasing and enhancing our safe-
ty and health culture. VPP supports
BP Exploration Alaska’s culture of
caring and empowers employees to
share this culture with family and
friends outside of the workplace,” she said.
The department said VPP recognizes and promotes effective workplace safety
and health management through a cooperative program between a company’s
management, employees and AKOSH.
“Participating in the Voluntary Protection Program illustrates an employer’s
steadfast commitment to worker safety,” said Labor Commissioner Heidi Drygas.
“I applaud BP Exploration Alaska’s Central Power Station employees for their
efforts in managing and maintaining occupational safety and health.”
VPP Star recipients are not subject to random enforcement actions for five
years, the department said, although enforcement regulations remain in effect and
cases of employee complaints, accident investigations or other significant inci-
dents will result in an enforcement inspection.
Participants in the AKOSH VPP Star program, in addition to BP’s Central
Power Station, include: Alaska Clean Seas; Arctic Slope Regional Corp. Energy
Services Grind and Inject Plant & Oily Water Injection Facility; BP Central
Compression Plant & Gas Facility; ConocoPhillips Alaska Inc. Alpine field oper-
ations; ConocoPhillips Kuparuk area; Fairbanks Memorial Hospital; Insulfoam
Inc.; and UniSea Inc.
—PETROLEUM NEWS
VPP Star recipients are not subjectto random enforcement actions for
five years, the department said,although enforcement regulations
remain in effect and cases ofemployee complaints, accident
investigations or other significantincidents will result in anenforcement inspection.
l E X P L O R A T I O N & P R O D U C T I O N
Northstar Kuparukgas injection requestHilcorp officials explain to AOGCC why the company wants to startinjection into the A & C sands through converted production well
By ALAN BAILEYPetroleum News
Hilcorp Alaska anticipates a 4 million
to 5.5 million barrel boost in oil
recovery from Kuparuk sands in the
Northstar oilfield, if the company imple-
ments gas injection into the field’s
Kuparuk oil pool, company officials said
during an Alaska Oil and Gas
Conservation Commission hearing on
Sept. 6. As previously reported in
Petroleum News, Hilcorp has applied to
the commission for permission for the gas
injection. Without gas injection, ultimate
oil recovery from the pool would be lim-
ited to some 9 million barrels, the compa-
ny has said.
The field is operated from a gravel
island offshore in the Beaufort Sea, with
the unit straddling state nearshore waters
and waters of the federal outer continen-
tal shelf.
Jim Shine, Hilcorp land manager, told
the commission that the field has three
participating areas: the Northstar, Fido
and Hooligan participating areas. The
Northstar and Fido participating areas
have reservoirs in the Ivishak formation,
equivalent to the main reservoir of the
Prudhoe Bay field. The Hooligan has
reservoirs in the shallower Kuparuk A
and C sands.
Production historyProduction from the Ivishak began in
2001. Sustained production from the
Kuparuk C began in 2010 from a single
well, the NS-08 well. Production from
both the Kuparuk A and C began in 2016
through another well, the NS-18 well.
And the NS-15 well came on line from
the A and C sands in 2017, Hilcorp reser-
voir engineer Chris Kanyer told the com-
mission.
Gas from the Kuparuk, produced
along with oil and condensate, has been
injected into the Ivishak reservoir, for
So now, with more than enoughgas being produced to support
Ivishak production, there isadequate gas for injection into the
Kuparuk — Hilcorp wants toconvert the NS-18 into a gas
injection well for this purpose.
see INJECTION REQUEST page 4
4 PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018
ADDRESS
P.O. Box 231647
Anchorage, AK 99523-1647
NEWS
907.522.9469
CIRCULATION
907.522.9469
ADVERTISING
Susan Crane • 907.770.5592
FAX FOR ALL DEPARTMENTS
907.522.9583
OWNER: Petroleum Newspapers of Alaska LLC (PNA)Petroleum News (ISSN 1544-3612) • Vol. 23, No. 37 • Week of September 16, 2018
Published weekly. Address: 5441 Old Seward, #3, Anchorage, AK 99518(Please mail ALL correspondence to:
P.O. Box 231647 Anchorage, AK 99523-1647)Subscription prices in U.S. — $118.00 1 year, $216.00 2 years
Canada — $206.00 1 year, $375.00 2 years Overseas (sent air mail) — $240.00 1 year, $436.00 2 years“Periodicals postage paid at Anchorage, AK 99502-9986.”
POSTMASTER: Send address changes to Petroleum News, P.O. Box 231647 Anchorage, AK 99523-1647.
www.PetroleumNews.com
Petroleum News and its supple-ment, Petroleum Directory, are
owned by Petroleum Newspapers ofAlaska LLC. The newspaper is pub-
lished weekly. Several of the individ-uals listed above work for inde-
pendent companies that contractservices to Petroleum Newspapers
of Alaska LLC or are freelance writers.
Kay Cashman PUBLISHER & FOUNDER
Mary Mack CEO & GENERAL MANAGER
Kristen Nelson EDITOR-IN-CHIEF
Susan Crane ADVERTISING DIRECTOR
Heather Yates BOOKKEEPER
Marti Reeve SPECIAL PUBLICATIONS DIRECTOR
Steven Merritt PRODUCTION DIRECTOR
Alan Bailey SENIOR STAFF WRITER
Eric Lidji CONTRIBUTING WRITER
Gary Park CONTRIBUTING WRITER (CANADA)
Judy Patrick Photography CONTRACT PHOTOGRAPHER
Forrest Crane CONTRACT PHOTOGRAPHER
Renee Garbutt CIRCULATION MANAGER
enhanced oil recovery from that reservoir.
But increased gas production, especially
from the N-15 well, has enabled the reser-
voir pressure in the Ivishak to be restored
to somewhere close to its original level.
So now, with more than enough gas being
produced to support Ivishak production,
there is adequate gas for injection into the
Kuparuk — Hilcorp wants to convert the
NS-18 into a gas injection well for this
purpose.
Hilcorp geoscientist Daniel Yancey
told the commission that the Kuparuk
sands lie between confining shale layers
above and below: 2,000 feet of HRZ and
Colville shales above, and more than
1,500 feet of the Kingak below. Hilcorp
well integrity engineer Wyatt Rivard pre-
sented evidence, demonstrating that
anticipated downhole pressures resulting
from the planned gas injection would be
well below the fracture pressure for the
shales. l
continued from page 3
INJECTION REQUEST
GOVERNMENTWhite requests Supreme Court rehearing
Jim White, owner of Alaskan Crude Corp., has asked the Alaska Supreme Court to
reconsider its recent ruling, upholding an Alaska Department of Natural Resources
decision to cancel Alaskan Crude’s lease covering the Moose Point prospect on the
northwest coast of the Kenai Peninsula. As reported in the Sept. 9 issue of Petroleum
News, DNR had cancelled the lease after Alaskan Crude did not continue a drilling
project in the lease, to meet an April 27, 2009, deadline set by DNR for completing a
well. DNR also set a 90-day deadline for bringing a Moose Point well into production,
should a viable resource be discovered.
White had argued that the deadline imposed by DNR had been invalid because it
had not been part of the original lease stipulations. White also said that questions over
the length of the winter drilling season, and over Alaska Oil and Gas Conservation
Commission requirements for a hearing into correlative rights for subsurface
resources, rendered investment in the drilling in time for the April deadline too finan-
cially risky — White supplies all of the financing for Alaskan Crude operations.
The state Superior Court found in favor of White. But the Supreme Court over-
turned the Superior Court decision, saying that DNR’s April deadline had provided
White with ample time to conduct the drilling.
In the request for a rehearing James Gottstein, attorney for White, argues that the
Supreme Court had overlooked the impact of the AOGCC requirement on DNR’s
deadline for production from the well. The court had also overlooked a requirement
for a DNR plan of development, if the well were to go into production. Thus, a rea-
sonable time to bring a well into production would be six months, rather than the 90-
days allowed under DNR’s order. Apparently these issues had been raised before the
Supreme Court.
l P I P E L I N E S & D O W N S T R E A M
US government accused of planning Keystoneprotest crackdown
By MATTHEW BROWNAssociated Press
Civil liberties advocates sued the U.S.
government Sept. 4, alleging law
enforcement agencies have been making
preparations to crack down on anticipated
protests over the Keystone XL oil pipeline.
Attorneys for the American Civil
Liberties Union and its Montana affiliate
filed the lawsuit in U.S. District Court in
Missoula against the Defense, Homeland
Security, Interior and Justice departments.
They asked the court to order the release
of all documents about cooperation over the
pipeline between federal, state and local law
enforcement and private security compa-
nies.
The groups cited confrontations between
law enforcement and protesters, including
many Native Americans, which turned vio-
lent during construction of the Dakota
Access Pipeline through South Dakota.
The clash over Dakota Access included
surveillance and prosecution of protesters,
Montana ACLU Attorney Alex Rate said.
Planning appears to be underway for a sim-
ilar response to protesters against Keystone
XL, Rate said, citing documents obtained
through public records requests submitted
to state and local agencies.
“The big question is what level of atten-
tion the (federal) government is paying to
the issue,” Rate said. “If you’re an indige-
nous person in Montana planning to protest
peacefully against the construction of the
pipeline, you have to be nervous about how
the government is going to react.”
The pipeline would transport up to
830,000 barrels of crude oil daily from
Canada through Montana and South Dakota
to Nebraska. It was approved by President
Donald Trump in March 2017, a decision
that’s been challenged in court.
A judge in that case in August ordered
federal officials to conduct a more thorough
review of the project after the Nebraska
Public Service Commission approved an
alternative route for the line through
Nebraska.
Defense Department spokesman Johnny
Michael said the agency was reviewing the
lawsuit and takes seriously its obligations to
release public records.
Homeland Security spokeswoman Katie
Waldman said the agency does not com-
ment on litigation.
The Interior Department referred ques-
tions to the Justice Department, which did
not immediately respond to a request for
comment.
The lawsuit included emails in which
federal officials discussed the establishment
of an “interagency team” to coordinate
security of Keystone XL construction.
Also included was a Homeland Security
analysis from last year on attacks on
pipelines by “environmental rights extrem-
ists.” The document focused in part on
activists who sought to shut down five
pipelines along the U.S.-Canada border
by illegally closing valves on the lines.
The material was obtained by the
ACLU under public records requests sub-
mitted to state and local agencies, Rate
said. l
see WHITE REHEARING page 7
PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018 5
Source: Symantec Internet Security Threat Report, Volume 20
Because you run a business security is not an option.
communication and security paramount. At AT&T, it’s our
layers of security across applications, devices, networks and platforms, we help reduce your risk of exposure from malicious attacks, so that companies like yours can stay Connected & Secure. Discover the Power of & with AT&T.
Speak with an AT&T representative about Network Security solutions today.
907-264-73871-800-955-9556
By AMANDA LEE MYERS & ROBERT JABLON
Associated Press
A pipeline company was convicted of
nine criminal charges Sept. 7 for
causing the worst California coastal spill
in 25 years, a disaster that blackened pop-
ular beaches for miles, killed wildlife and
hurt tourism and fishing.
A Santa Barbara County jury found
Houston-based Plains All American
Pipeline guilty of a felony count of failing
to properly maintain its pipeline and eight
misdemeanor charges, including killing
marine mammals and protected sea birds.
California Attorney General Xavier
Becerra said in a statement that Plains’
actions were not only reckless and irre-
sponsible but also criminal.
“Today’s verdict should send a mes-
sage: if you endanger our environment
and wildlife, we will hold you account-
able,” he said.
Plains said in a statement that the jury
didn’t find any knowing misconduct by
the company and “accepts full responsi-
bility for the impact of the accident.”
“We are committed to doing the right
thing,” the company said.
Company says jury erredThe company said its operation of the
pipeline met or exceeded legal and indus-
try standards, and believes the jury erred
in its verdict on one count where
California law allowed a conviction
under a standard of negligence.
“We intend to fully evaluate and con-
sider all of our legal options with respect
to the trial and resulting jury decision,”
Plains said.
The company is set to be sentenced on
Dec. 13. Because it’s a company, and not
a person, Plains only faces fines, though
it’s unclear how steep the penalties could
be.
Plains had faced a total of 15 charges
for the rupture of a corroded pipeline that
sent at least 123,000 gallons of crude oil
gushing onto Refugio State Beach in
Santa Barbara County, northwest of Los
Angeles.
Plains pleaded not guilty to the
charges and accused prosecutors of crim-
inalizing an unfortunate accident.
Errors called preventableBut federal inspectors found that
Plains had made several preventable
errors, failed to quickly detect the
pipeline rupture and responded too slow-
ly as oil flowed toward the ocean.
Plains operators working from a Texas
control room more than 1,000 miles away
had turned off an alarm that would have
signaled a leak and, unaware a spill had
occurred, restarted the hemorrhaging line
after it had shut down, which only made
matters worse, inspectors found.
The spill, two weeks shy of Memorial
Day, closed beaches with popular camp-
grounds for two months and put a crimp
in the local tourist economy and fishing
industry.
It also crippled the local oil business
because the pipeline was used to transport
crude to refineries from seven offshore
rigs, including three owned by Exxon
Mobil, that have been idle since the spill.
Producers bankruptLast year, Denver-based Venoco,
declared bankruptcy, in part because it
wasn’t able to operate its platform. The
state is now responsible for plugging and
decommissioning Veneco’s wells at an
estimated cost of $58 million. That
doesn’t include the eventual cost to
remove the enormous structure.
Plains apologized for the spill and paid
for the cleanup. The company’s 2017
annual report estimated costs from the
spill at $335 million, not including lost
revenues.
It is seeking approval to repair or
rebuild its corroded pipelines.
The company still faces possible fines
from the U.S. government and also faces
a federal class-action lawsuit by owners
of beachfront properties, fishing boat
operators, the petroleum industry and oil
workers who lost jobs because of the
spill.
The pipeline that spilled has been shut-
tered but Plains has applied to build a new
one in the same location.
Kristen Monsell, oceans legal director
with the Center for Biological Diversity,
said in a statement that Plains can’t be
given “a second chance to spill again.”
“It’s time to get dirty, dangerous
drilling out of our oceans, out of our
coastal areas and out of our state,” she
said. l
—Associated Press writer BrianMelley contributed to this report.
6 PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018
(907) 562-5303 | akfrontier.com
Safety Health Environment Quality
THE TEAM THAT
DELIVERS
EXPLORATION & PRODUCITONNational rig count unchanged at 1,048
The number of rigs drilling for oil and natural gas in the U.S. was unchanged
the week ending Sept. 7 at 1,048.
At this time a year ago there were 944 active rigs.
Houston oilfield services company Baker Hughes reported that 860 rigs target-
ed oil (down two from the previous week) and 186 targeted gas (up two). Two
were listed as miscellaneous (no change).
Among major oil- and gas-producing states, Louisiana gained three, Wyoming
gained two and Alaska and North Dakota each gained one. Oklahoma was down
two. Colorado and Texas were unchanged.
Texas, with 528 rigs, accounts for the majority of the nation’s rig activity, fol-
lowed by Oklahoma at 137 and New Mexico at 100.
The Baker Hughes rotary rig count shows six rigs active in Alaska, up from
four a year ago.
The U.S. rig count peaked at 4,530 in 1981. It bottomed out in May 2016 at
404.
—PETROLEUM NEWS
Average gas price steady at $2.91/ gallonU.S. gas prices remained steady
over the past two weeks and an analyst
says the pump price may start to drop
later in September.
Trilby Lundberg says the average
price of regular-grade gas as of Sept. 7
was $2.91 per gallon.
In California, however, the average
was $3.63, per gallon up 3 cents from
two weeks ago.
The price in the San Francisco Bay
Area was even higher while the city
with the lowest average was Jackson, Mississippi at $2.51 per gallon.
Consumers may see prices fall 2 to 4 cents per gallon by the end of September.
Lundberg says gasoline supplies are plentiful, growth in demand is weak and
refiners are ending their production of summer blend gas that's designed to reduce
pollution but is costlier to produce.
—ASSOCIATED PRESS
PIPELINES & DOWNSTREAM
Consumers may see prices fall 2to 4 cents per gallon by the end of
September. Lundberg saysgasoline supplies are plentiful,growth in demand is weak and
refiners are ending theirproduction of summer blend gas
that's designed to reduce pollutionbut is costlier to produce.
l P I P E L I N E S & D O W N S T R E A M
Pipeline company
found guilty in oil spill
PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018 7
l G O V E R N M E N T
Hilcorp seeks rule change in NM gas basinBy SUSAN MONTOYA BRYAN
Associated Press
AHouston-based oil and gas company
wants New Mexico regulators to ease
restrictions on well locations in two coun-
ties within one of the oldest producing
basins in the U.S., saying the change will
result in the capture of more natural gas.
The request involving San Juan and Rio
Arriba counties comes as an oil and gas
boom has helped to refuel state coffers.
That includes a recent record-breaking
lease sale on the other end of the state near
the Texas state line that promises nearly a
half-billion dollars more in revenues.
But environmentalists and landowners
are concerned about increasing well densi-
ties in the northwest as developers look to
tap more reserves in the San Juan Basin.
The request by Hilcorp Energy Co. is set
to be considered Sept. 13 by the Oil
Conservation Commission.
Critics want regulators to put off a deci-
sion until a thorough environmental review
is done. They’re citing potential cumulative
effects of the boom, saying more public
scrutiny is needed before rules are changed.
Rancher Don Schreiber said the most
pressing environmental questions in New
Mexico is how many wells an energy com-
pany can drill. He has lived in the region for
decades and remembers hunting deer as a
boy across San Juan County’s high desert.
“I’ve watched it go in a fairly short life-
time from a place of incredible beauty to a
borderline industrial site and certainly dou-
bling the wells would put us over the edge,”
he said.
More than 5,300 wellsHilcorp in a statement Sept. 10 denied
that the application is one that seeks to drill
more wells or change the way new wells are
permitted.
According to its application, the compa-
ny currently operates more than 5,300 pro-
ducing wells in what is known as the
Blanco-Mesaverde gas pool in San Juan
Basin. It also has thousands of wells that are
producing from other formations in the
region.
Those additional wells are situated to
recover reserves within the Blanco-
Mesaverde formation that aren’t being
tapped due to current density limits, the
company said.
“This allows all operators to reinvest and
upgrade existing well sites and production
equipment,” the company said, arguing that
this will result in extending the life of the
San Juan Basin.
The company also argued that changing
well density wouldn’t eliminate the need to
meet regulatory standards and other envi-
ronmental, cultural and archaeological
requirements for drilling new wells or
working on existing wells.
Since the beginning of 2018, the oil
commission has granted Hilcorp dozens of
exceptions to the density rules. The compa-
ny contends that updating the rules to allow
for eight wells — up from the current four
— on 320 acres would prevent waste and
boost the capture of natural gas.
Well spacing issueHilcorp’s request follows a previous pro-
posal to seek a change that would have
allowed Oil Conservation Division staff to
make decisions about well spacing rather
than go through a public hearing process.
The proposal piqued the interest of the state
attorney general’s office and it was ulti-
mately withdrawn.
Environmentalists on Sept. 10 asked the
attorney general’s office to weigh in this
time, citing concerns over public notice as
the announcement of the latest proposal and
the deadline for intervening spanned only a
week over the Labor Day holiday.
They argued that wasn’t enough time,
given the importance of the proposed
change.
Schreiber said granting the request
would amount to a parting gift to industry
as leadership at the state Energy, Minerals
and Natural Resources Department and the
oil commission is expected to change when
a new governor takes office in January.
State Energy Secretary Ken McQueen
and Oil Conservation Division director
Heather Riley both used to work for WPX
Energy, which operated in San Juan Basin
for years before shifting its focus to places
along the Texas-New Mexico border and
elsewhere. l
Safer. Smarter.
Our CDR2-AC rig reflects the latest innovations in Arctic drilling to provide our customers with incident free performance and operational and technical excellence.
CDR2-AC is the first Arctic rig designed and built by Nabors specifically for Coil Tubing Drilling operations. The rig was built to optimize CTD managed pressure drilling to provide precise control
of wellbore pressures for improved safety, decreased costs, and increased wellbore lengths.
Combining safety and environmental excellence with greater efficiency means CDR2-AC can deliver the high value results customers have come to expect from Alaska’s premier drilling contractor.
Learn more about Nabors’ new drilling technologies at Nabors.com.
nabors.com
Better.
A rehearing is justified, because, by
overlooking those AOGCC and DNR
requirements, the Supreme Court had not
considered the entirety of the contract
involved and of the material facts in the
case, as is required by law, Gottstein wrote.
Moreover, those two requirements, in
effect, meant that “Mr. White was doomed
from the beginning” in any effort to bring
the well into production within the DNR
deadline, even if White had continued with
the drilling in early 2009, Gottstein com-
mented.
—ALAN BAILEY
continued from page 4
WHITE REHEARING
that ply the Haul Road to the Slope.
Colville’s trucks make around 2,000 of
these trips each year, carrying about
10,000 gallons of fuel on each trip. The
delivery of fuel by barge, in effect,
replaces 200 tanker trips, Colville said.
Colville attributes its ability to con-
duct the barge operation to improving sea
ice conditions off northern Alaska and the
construction of Colville’s 5 million-gal-
lon fuel storage facility at Deadhorse.
Without the tank farm, there would be
insufficient fuel storage capacity at
Deadhorse to support the receipt of such
a large fuel shipment, the company said.
“This was a milestone for Colville and
the fuel transport industry and was
prompted by increased demand because
of all the new activity in the North Slope
oil fields. While we will consider future
barge deliveries, they will not replace our
trucking operation,” Pfeifer said.
—ALAN BAILEY
continued from page 1
DIESEL DELIVERY
The agency wants to build three new
heavy-duty icebreakers and three medium
icebreakers, in support of U.S. activities
in polar regions. The GAO report focuses
on the heavy icebreaker requirement.
Timing of the transitionAccording to the GAO report, the Polar
Star is currently expected to reach the end
of its operational life somewhere between
2020 and 2023. Since, however, the first of
the planned new icebreakers is not expect-
ed to be completed until 2024, the Coast
Guard anticipates renovating the Polar
Star’s systems, starting in 2020, to extend
the life of the vessel until the first of the
new vessels becomes available. But that
2024 schedule for the new vessel seems
unreliable, the GAO report says.
The construction schedule for the new
icebreakers appears to have been driven by
the timing of the predicted gap in icebreak-
er availability, rather than by a realistic
assessment of shipbuilding activities, the
report says. Although the Coast Guard has
followed standard DHS acquisition poli-
cies, the agency established design, cost
and schedule baselines without first con-
ducting a preliminary design review. Nor
did the agency conduct an assessment of
the maturity of the technologies planned to
be used in the icebreakers, the report says.
From the perspective of program costs,
the Coast Guard has not quantified the full
range of potential costs over the entire life
of the program. Thus, the cost estimate for
the entire program may be underestimated,
the GAO report says.
Cost and fundingThe Coast Guard has in the past indicat-
ed that each icebreaker may cost some $1
billion to construct. However, the agency
has suggested that efficiencies arising from
the use of a standardized design could
reduce that cost to $900 million. The
agency has requested $750 million in
funding, which, together with existing ice-
breaker funds, the agency has said, could
pay for the acquisition of the first icebreak-
er.
Congress recently passed a national
defense authorization act, authorizing the
construction of six polar class icebreakers.
However, although the Senate has passed a
funding bill that includes $750 million for
icebreaker funding, the House of
Representatives has not included the same
level of funding in its equivalent bill.
Integrated program officeMeanwhile, the Coast Guard and the
U.S. Navy have been operating an inte-
grated program office for the icebreaker
project. That office includes a ship design
team; a cost engineering and industrial
analysis group; and a directorate for deal-
ing with contracts. The office has already
completed an analysis and selection of the
best option for addressing the icebreaker
issue and has conducted an evaluation of
this option. Construction of the lead ship is
expected to start no later than June 2021,
with delivery of the vessel possible in the
fourth quarter of 2023. The Coast Guard
estimates the total full-lifecycle cost of the
three-heavy-icebreaker program to be in
the range of $8.5 billion to $9.8 billion, the
GAO report says.
The DHS has been seeking technical
proposals for the project, with price pro-
posals anticipated in October.
Conceptual designWork on a conceptual design began
back in 2016 and ultimately resulted in a
design concept involving an integrated
power plant providing electrical power for
rotatable propulsion pods under the ves-
sel’s stern. And, despite not having con-
ducted a preliminary review for the design
concept, the Coast Guard has used the con-
cept as the basis for a cost estimate, the
GAO report says. The predicted construc-
tion schedule is also based on this prelimi-
nary concept, rather than on a more mature
design, the GAO report says.
The Coast Guard views the preliminary
design as using proven technologies — the
type of power plant and thruster system
envisaged are already available commer-
cially. But the agency has not assessed the
readiness of the proposed technologies for
achieving the icebreaker program objec-
tives — it is necessary to evaluate the
effectiveness of the technologies in sup-
port of a different program or a different
operating environment from what has
already been demonstrated, the GAO
report says.
Thus, although the icebreaker project
team has thoroughly and accurately esti-
mated the cost of the icebreaker project,
within the parameters used for the estimat-
ing, there are remaining issues relating to
the credibility of the estimates. The devel-
opment schedule also appears optimistic.
In addition, the Coast Guard and the Navy
do not have a clear strategy for addressing
any cost growth in the program, the GAO
report says.
A number of recommendationsThe report makes a number of recom-
mendations, including a recommendation
that the icebreaker project team should
conduct a technology readiness assessment
of the conceptual icebreaker design. The
team should revisit the cost and schedule
estimates, taking full account of risks and
uncertainties in the program, and address-
ing how to deal with any cost growth. DHS
has agreed with the GAO recommendation
and has identified actions for addressing
the issues raised, the GAO report says.
—ALAN BAILEY
continued from page 1
POLAR ICEBREAKERS
8 PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018
907.277.7555 | 1120 E. 5th Ave. Anchorage, AK arcticcontrols.com
∙ Pinch Valves
∙ Tideflex Check Valves
∙ Pressure Sensors
∙ Expansion Joints
itive process is in the State’s best inter-
est.”
DNR said the current solicitation for
interest in future gas sales will allow the
state “to better understand competition
for its gas,” adding that it is not commit-
ting to take its royalty gas in kind or to
sell any volume of gas to any party.
“A public process, including legisla-
tive approval, is necessary before DNR
can enter into an agreement to sell royalty
in kind gas,” the department said.
DNR working issuesThe DNR commissioner has statutory
authority to negotiate commercial agree-
ments, market the state’s royalty in kind
and tax as gas volumes, and modify cer-
tain oil and gas lease terms.
Under Senate Bill 138, enacted in
2014, DNR would elect to receive Alaska
LNG royalty gas in kind, unless the DNR
commissioner finds that taking gas in
value would be in the best interest of the
state. Other than crude oil sold to in-state
refineries, the state takes its royalties on
crude oil production in value, with the
crude oil sold by producers and the state
taking payment for its royalty share.
DNR Commissioner Andy Mack told
legislators in a March update on the
Alaska LNG project that before entering
a contract to take gas as royalty in kind,
the department would issue a preliminary
best interest finding, take comments from
the public and the Royalty Oil and Gas
Development Advisory Board, and then
obtain legislature approval.
A final best interest finding would
then be issued.
Mack said any royalty in kind finding
has to come to the Legislature to be rati-
fied.
In a July update to legislators, DNR
Deputy Commissioner Mark Wiggin said
the department is working on royalty in
kind vs. royalty in value issues, including
eliminating switching between RIK and
RIV, a right the state now enjoys. He said
if RIK is selected, with the state taking
royalties (and probably also taxes) in gas
molecules, DNR would need a gas sale
agreement with the Alaska Gasline
Development Corp.
JDAThe joint development agreement for
Alaska LNG, signed in Beijing in early
November by the state, AGDC, China
Petrochemical Corp. (Sinopec), CIC
Capital Corp. and the Bank of China,
envisions that 75 percent of LNG from
the Alaska project will go to China, leav-
ing the state 25 percent to market to other
buyers and for in-state use. Those vol-
umes would include the state’s royalty
share.
The JDA says the parties will work
together on a scope of work defined in the
agreement, including the opportunity for
delivering 75 percent of the LNG pro-
duced from Alaska to China “at a cost-
based and stable price utilizing the bene-
fits of strategic financing and invest-
ment,” strategic financing opportunities
and a transparent investment model.
The JDA expires Dec. 31, 2018, unless
extended by mutual written agreement of
the parties.
—KRISTEN NELSON
continued from page 1
GAS INTEREST
Colville Transport enables fuel distribution services across the North Slope. With a fleet of more than
40 tractors and 40 tankers, we continuously move product from Fairbanks, Anchorage, and the Port of
Valdez to the Colville tank farm at Prudhoe Bay.
When you need a dependable fuel source on the North Slope, we’re there where you need us.
WE’RE THERE WHERE YOU NEED US
colvilleinc.com
tinuously moone c w,, erskorand the P,,agenchorA,,e Budhort Pm ale tank far
e on the cendable fuel sourpou need use ye where therr
e vtinuously mot of
.yae B
e on the .ou need us
om.colvilleincc
The construction schedule for thenew icebreakers appears to havebeen driven by the timing of the
predicted gap in icebreakeravailability, rather than by a
realistic assessment of shipbuildingactivities, the report says.
PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018 9
Oil Patch Bits
ADVERTISER PAGE AD APPEARS ADVERTISER PAGE AD APPEARS ADVERTISER PAGE AD APPEARS
Companies involved in Alaska’s oil and gas industry
All of the companies listed above advertise on a regular basis with Petroleum News
New ocean shipping options to Hawaii and GuamLynden International said Sept. 5 that it
has served the Hawaiian Islands for morethan 30 years and provided service toGuam for more than 20 years. For 2018,Lynden has enhanced its customer offer-ings in both locations by adding less-than-container-load ocean service between LosAngeles and Guam and LCL barge servicebetween Seattle and Honolulu via AlohaMarine Lines.
“The new service provides a lower-cost alternative to traditional steamship line serv-ice,” said Western Regional Sales Manager Charlie Ogle. “We offer twice monthly sailingsto Oahu with connections to the neighboring islands, “he added.
With this added service Lynden continues to offer its full menu of value-added capabili-ties like EZ commerce, multimodal shipping options, dynamic routing, time-specific deliver-ies, and warehousing. For more information visit www.lynden.com/LINT or [email protected].
COOEC-Fluor completes module fabrication projectFluor Corp. said Sept. 4 that its joint venture COOEC-Fluor Heavy Industries Co. Ltd.
fabrication yard has safely completed fabrication of the topsides, living quarters anddrilling modules for the CNOOC HZ32-5/33-1 Oilfield Joint Development Project. The mod-ules sailed away on schedule in July, destined for the Huizhou 32-5 oilfield development
approximately 105 miles south-east of Hong Kong in the PearlRiver Mouth basin of the SouthChina Sea.
“Both the COOEC-Fluor andCNOOC project managementteams successfully overcamenumerous challenges to com-plete the onshore constructionas scheduled, with zero punchlist items for onshore fabricationwork,” said Lianfeng Yang,CNOOC’s engineering, procure-ment and construction project manager. “We look forward to the COOEC-Fluor team suc-cessfully completing the close-out activities and sea fastening work.”
The fabrication yard delivered to the aggressive schedule and fabricated the 4,000-ton,four-deck topsides in less than 12 months with no follow-on work. Safety, a core value ofthe COOEC-Fluor yard, was at the forefront of all activities and the team achieved 1.5 mil-lion work hours without a lost-time incident.
“The project team optimized the fabrication methods and onshore commissioningscope, which minimized the schedule-intensive offshore installation requirements to main-tain schedule,” said Chris Vertanness, vice president of Fluor and director of operations atthe COOEC-Fluor fabrication yard. “The team’s planning, productivity and execution excel-lence enabled the delivery of the modules with the safety and schedule certainty ourclients expect.”
The platform is expected to continue to produce oil until after 2030.
AAfognak Leasing LLCAir LiquideAlaska Energy Services, LLCAlaska DreamsAlaska Frac Consulting LLCAlaska Frontier Constructors (AFC) . . . . . . . . . . . . . . . . . . . .6Alaska Marine LinesAlaska MaterialsAlaska RailroadAlaska Rubber & Rigging Supply Inc. . . . . . . . . . . . . . . . . . .3Alaska Steel Co.Alaska Textiles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4Alaska West ExpressAlpha Seismic CompressorsAmerican MarineArctic Catering & Support ServicesArctic Controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8Arctic Fox EnvironmentalArctic Wire Rope & SupplyARCTOS Alaska, Division of NORTECHArmstrongASRC Energy ServicesAT&T . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5Avalon DevelopmentAviator Hotel
B-FBombay Deluxe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3BPBrandSafway ServicesBrooks Range SupplyCalista Corp.Chosen Construction
Colville Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8Computing AlternativesCONAM ConstructionCruz ConstructionDowland-Bach Corp.Doyon AnvilDoyon AssociatedDoyon DrillingDoyon, Limitedexp Energy ServicesF. R. Bell & Associates, Inc.FairweatherFlowline AlaskaFluorFoss Maritime . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2Fugro
G-MGeotempsGMW Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11Greer Tank & WeldingGuess & Rudd, PCInspirations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10Judy Patrick PhotographyKuukpik Arctic ServicesLast Frontier Air VenturesLittle Red Services, Inc. (LRS)Lounsbury & AssociatesLynden Air CargoLynden Air FreightLynden Inc.Lynden InternationalLynden LogisticsLynden Transport
Mapmakers of AlaskaMAPPA TestlabMaritime HelicoptersMotion & Flow Control Products
N-PNabors Alaska Drilling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7Nalco ChampionNANA WorleyParsonsNature Conservancy, TheNEI Fluid TechnologyNordic CalistaNorth Slope Telecom . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2Northern Air Cargo . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10NRC AlaskaOpti StaffingPENCO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11Petro Star LubricantsPetroleum Equipment & Services, Inc.PRA (Petrotechnical Resources of Alaska)Price Gregory International
Q-ZResource Development CouncilSAExplorationSecurity AviationSourdough ExpressTanks-A-LotThe Local PagesUnique MachineVolant ProductsWaste ManagementWeston Solutions
CO
URT
ESY
LYN
DEN
CO
URT
ESY
FLU
OR
munities that were counting on the employment that
would come with the C$9.3 billion Trans Mountain
expansion. The prime minister said his administration is
examining a wide range of legislative and other options to
salvage Trans Mountain, including an appeal to the
Supreme Court of Canada.
However, he would not go as far as using a “legislative
trick,” such as an emergency measure in the guise of the
“national interest” to bypass the federal court ruling.
Trudeau said that might “be satisfying in the short term,”
but it would set up fights and uncertainty for investors over
the coming years on any other project because you can’t
have a government that keeps invoking those sorts of
things.
“We would like to see shovels in the ground as quickly
as possible. This is a priority for Alberta and Canada. We
must make sure it’s done right,” he said.
While Trudeau mulls his next move, patience is wearing
thin in Calgary, the heads office city of Canada’s petroleum
industry, where unemployment rose to 8.2 percent in
August from 7.9 percent in July in a metropolitan popula-
tion of 1.4 million, compared with 6.7 percent for all of
Alberta, 6.4 percent in the provincial capital of Edmonton
and 6 percent across Canada.
As hundreds of laid off residents with no hope of finding
a new job start packing their bags and heading for the exit
door, the real estate market is swamped with more than
5,000 listings.
“Oil companies are still very reluctant to hire heads
office workers (where Calgary’s economic strength lies),”
said Court Ellingson, vice president of Calgary Economic
Development.
Even so, he is confident that a recovery will occur based
on signs of a return to upstream exploration and develop-
ment.
In the meantime, patience in the industry is fast
approaching breaking point as Alberta Premier Rachel
Notley discovered during a “tense” late-August meeting
with industry executives.
Those from the larger companies unburdened them-
selves, speaking about the chilling impact of the Trans
Mountain court ruling on their investment climate and
Canada’s inability to get major infrastructure built that has
prompted oil sands giant Suncor Energy to shelve all plans
to grow production until pipeline capacity out of Alberta is
increased.
Chris Bloomer, chief executive officer of the Canadian
Energy Pipeline Association, told the Calgary Herald his
sector is moving towards a “pretty desperate” situation.
Tamarack Valley Energy Chief Executive Officer Brian
Schmidt, who also attended the Notley session, said he is
“just watching people leave” the Western Canada
Sedimentary Basin. “No one is able to raise money here
right now,” he said. l
continued from page 1
TRANS MOUNTAIN
North Dakota and the Uinta basin of Utah.
Newfield also has oil developments off-
shore China, but approximately 98 percent
of the company’s proved reserves are
onshore U.S.
According to www.newfield.com,
“Newfield has a clear vision — to be rec-
ognized as the premier independent E&P
company delivering operational excel-
lence, top tier business results and value to
our shareholders, employees and the com-
munities in which we live and work.”
—KAY CASHMAN
Begich, Dunleavy weighin on Pt. Thomson,Walker’s LNG deal
THE DEMOCRATIC AND
REPUBLICAN CANDIDATES in the
Alaska governor’s race have weighed in on
incumbent Bill Walker’s latest announce-
ment on his $43 billion-plus proposal to
build a natural gas pipeline from the North
Slope to Nikiski on the Kenai Peninsula,
where the gas will be liquefied, with 75
percent of the LNG going to China. The
Chinese, represented by China
Petrochemical Corp. or Sinopec, CIC
Capital Corp. and the Bank of China, will
play a role in construction. In April, Alaska
Gasline Development Corp. President
Keith Meyer said Sinopec has a very capa-
ble construction company and has built
longer pipelines than this project, in higher
places and with larger plants. He said the
ability of Alaska companies is something
AGDC is promoting to the Chinese.
On Sept. 10 the governor’s office said
Alaska has agreed to extend a key deadline
in a 2012 lawsuit settlement with
ExxonMobil and BP over development of
the Point Thomson unit gas and conden-
sate field 60 miles east of Prudhoe Bay on
Alaska’s North Slope.
State Commissioner of Natural
Resources Andy Mack said the deal was
reached to facilitate PTU operator
ExxonMobil’s agreement to supply its
North Slope gas, both at Point Thomson
and in the BP-operated Prudhoe Bay unit,
to the proposed Alaska LNG Project. The
PTU holds an estimated 8 trillion cubic
feet of natural gas and is an important part
of the gas supply needed for the Alaska
LNG Project. The Prudhoe Bay unit holds
22 tcf of gas.
A letter of agreement entered into by
the state, ExxonMobil and BP extends a
December 2019 deadline for the compa-
nies to expand PTU development beyond a
pilot program now underway to produce
condensate from the Thomson sands,
although currently shutdown by Exxon
because of technical problems.
The stay will end when there is a final
investment decision on an Alaska LNG
Project or work on the Alaska LNG Project
is no longer progressing.
In a separate statement AGDC, backed
by gubernatorial incumbent Walker, said it
has reached an (unbinding) agreement with
Exxon on certain key terms including price
and volume for a gas sales agreement. It
was signed Sept. 10, AGDC said, for terms
for the purchase of Exxon’s share of
Prudhoe Bay and PTU natural gas.
Begich wants Alaska workers on gas line, concerned about China
Gubernatorial candidate Mark Begich
told Petroleum News Sept. 12 he was
always concerned about what the governor
gave up in gas proj-
ect-related negotia-
tions, noting there
are too many unan-
swered questions:
“We want to be sure
Alaska got a good
deal, not just a fair
one … or worse.”
“We want Alaska
workers working on
that pipeline if it
comes to fruition,” he said, which is some-
thing that cannot be legally mandated by
the state, although the state can insist
unionized labor be used.
Begich was also concerned about the
economics of the gas project, questioning
whether it made sense or whether it would
lay a heavy burden of debt on the state.
The former U.S. senator from Alaska
also referred to China’s controversial
involvement in South Africa, which has
U.S. security advisers worried in both
Congress and the executive branch.
“Look at what China is doing in South
Africa. The Chinese are extracting every-
thing they can, controlling resources. The
U.S. government, I believe, would not
allow China to control Alaska North Slope
gas. … In my opinion, if we can make a
North Slope LNG project economic and
not a burden on Alaska, then we should
market our gas to other Asian markets, so
China does not own the majority of our
gas and have any involvement in its con-
struction.”
Dunleavy said LNG project must make economic sense
Gubernatorial candidate Mike Dunleavy
released the following statement in
response to the Walker administration’s
“letter of understanding” with the Point
Thomson working interest owners on the
Alaska LNG Project.
“We all support
monetizing our vast
natural gas resources
for the benefit of all
Alaskans. But for
Alaskans to benefit,
the project must
make economic
sense, and today’s
announcement does-
n’t change that
underlying fact.
Without further information, and with too
many unanswered questions, we don’t
know if today’s news represents a positive
step forward for the project. What we do
know is that press releases don’t build
pipelines.”
“Our campaign remains committed to a
project that maximizes the benefit to all
Alaskans without jeopardizing our finan-
cial future, one driven by the private sec-
tor, not politics,” Dunleavy said.
—KAY CASHMAN
Financial Times: US shaleboom begins to cool
PER A SEPT. 7 ARTICLE in the
Financial Times, the U.S. shale oil industry
is “slowing as logistical challenges includ-
ing labor costs and a lack of adequate
pipeline capacity pile up.”
FT reporter Ed Crooks summarized
what the chief executives of oilfield serv-
ice firms Halliburton and Schlumberger
and major shale producer EOG Resources
10 PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018
229-6000
Real Alaskans. Real cargo.
USITH ONNECT WC
ouer yyovveeevWhatail guns. Air comN
www/411.277.72800./US
.err.e delivveu need, wweessors. Geneprreail guns. Air com
/o.nac.aerrowwww.
ors.aterra
continued from page 1
INSIDER
see INSIDER page 12
MARK BEGICH
MIKE DUNLEAVY
The GMT-1 development is expected
to cost a little under $1 billion. GMT-2,
with more wells required but with higher
expected production rates, will likely cost
about $1.5 billion.
The environmental impact statement
scoping process is underway for
ConocoPhillips’ proposed major Willow
development, in the Bear Tooth unit, to
the west of Greater Mooses Tooth. That
development could result in peak produc-
tion of some 100,000 bpd, with first oil
around 2024 to 2025, ConocoPhillips has
indicated. Initial development of Willow
will likely cost $2 billion to $3 billion,
with a further $2 billion to $3 billion
required for full field development.
Exploration and appraisal this winterJepsen said that, following a particu-
larly successful exploration drilling pro-
gram last winter, ConocoPhillips plans an
aggressive two-rig exploration and
appraisal drilling program for the coming
winter. The company has used seismic
surveying to identify a patchwork of
exploration targets in its western North
Slope leases, including in the northeast-
ern NPR-A. Currently 75 percent of those
targets remain untested.
The coming winter’s plan involves the
drilling of six to eight wells.
Two of those wells would be drilled by
the end of the year, testing prospects
reachable from existing oil field well
pads. One of these is the Cairn prospect in
the southwestern corner of the Kuparuk
River unit. The other involves the Putu
prospect, near the village of Nuiqsut, in
what ConocoPhillips terms the Narwhal
trend, to the east of the Colville River.
This is the same trend as the
Pikka/Horseshoe trend, where Oil Search
and its partners are planning the develop-
ment of a major oil field primarily involv-
ing a reservoir in the Nanushuk forma-
tion.
Third Putu wellDuring last winter’s exploration
drilling season, ConocoPhillips drilled
two wells, the Putu 2 and 2A wells, in the
Putu prospect. Those wells, which tested
successfully for oil, targeted two distinc-
tive seismic amplitude anomalies, Jepsen
explained. But there is a third anomaly,
immediately west of the two tested anom-
alies — the plan for later this year is to
drill into this third anomaly from the CD-
4 pad in the Colville Delta unit, Jepsen
said.
The focus of the remainder of the com-
ing winter’s drilling will be Willow —
ConocoPhillips wants to drill some hori-
zontal wells, to better understand the
potential productivity from the field, and
some vertical wells to test inter-well com-
munication, Jepsen said. The company
wants to further delineate the field and to
conduct further well tests. Exactly how
much will be done during the winter sea-
son will depend on how fast the drilling
projects proceed and on the weather con-
ditions, Jepsen said.
In the Narwhal trend, ConocoPhillips
experienced success last winter in finding
oil in two zones at its Stony Hill well, in
addition to the Putu discoveries. But the
Stony Hill and Putu discoveries require
additional appraisal drilling and addition-
al analysis, Jepsen said. Putu has the
advantage of being situated inside the
Colville River unit, somewhat closer to
existing facilities than Stony Hill, Jepsen
remarked.
Looking further ahead, from 2020
onwards, ConocoPhillips anticipates
drilling into that remaining 75 percent of
its North Slope prospects that have not
yet been tested, Jepsen said.
Dramatic change in outlookJepsen’s comments about
ConocoPhillips’ upcoming plans came
within the context of a dramatic change in
the company’s outlook for its future
Alaska oil production. As recently as
2013 the company was forecasting a con-
tinuing decline rate of 6 to 8 percent per
year in its oil output from its North Slope
operations. But now the company antici-
pates a complete reversal of that situation,
with production in 2028 expected to be
some 100,000 bpd above where it is now,
Jepsen said.
And that comes within a context of
new oil production from other companies
operating on the North Slope, in what
Jepsen characterized as a North Slope
renaissance. For example, Oil Search and
its partners are planning a major develop-
ment in the Pikka prospect, Hilcorp is
planning the Liberty development in the
Beaufort Sea, and Brooks Range
Petroleum has been moving ahead with
its Mustang development. All told, there
is the potential for a total of 400,000 bpd
of new oil, although that new production
would not all start at the same time.
There is also the continuing health of
the core North Slope fields: Prudhoe Bay,
Kuparuk and Alpine. These fields provide
the economies of scale in oil output that
make the new developments viable,
Jepsen commented.
Jepsen divided ConocoPhillips’ pre-
dicted future oil production into four
tranches: base production from existing
fields; additional production from new
developments in those fields; further
developments from new field projects;
and potential future production resulting
from exploration.
Impact of new technologiesBase production in the Prudhoe Bay,
Kuparuk and Alpine fields has benefited
from exciting new technologies, in partic-
ular new drilling technologies.
“We have really advanced drilling
technology to the point where it’s making
a significant difference in terms of what
we can develop and how much we can
develop,” Jepsen said.
For example, earlier this year
ConocoPhillips drilled a 21,000-foot hor-
izontal lateral from a CD-5 well in the
Colville River unit, the longest lateral
ever drilled in North America, Jensen
said. It is now possible to steer a well
more than 4 miles through a 10- to 15-
foot thick reservoir sand, enabling a more
than 4-mile exposure to oil bearing rock.
By contrast, in the early years of Prudhoe
Bay drilling, a directional well might pen-
etrate a reservoir sand at a 45-degree
angle, enabling perhaps an exposure to
just 21 to 22 feet of oil-bearing rock in a
15-foot thick sand body.
Highly deviated drilling can also
reduce the surface footprint of an oilfield
development. ConocoPhillips has com-
missioned a new Doyon Drilling ultra-
extended reach rig that can drill out to a
distance of more than 37,000 feet, allow-
ing access to 154 square miles of subsur-
face from a 14-acre drilling pad. The
company plans to use this rig to develop
its Fiord West prospect, in the northwest
corner of the Colville River unit, from the
existing CD-2 well pad. Fiord West has
presented a development challenge
because of its environmentally sensitive
location on the Beaufort Sea coast.
Other new developmentsOther new ConocoPhillips develop-
ments include expansion of operations at
the CD-5 pad in the Colville Delta unit,
GMT-1, GMT-2, and NE West Sak or
NEWS in the Kuparuk River unit. The
company is also considering extending its
West Sak development into an area it
refers to as Eastern NEWS, Jepsen said.
Also, in terms of oil from new devel-
opment, there is the Willow project. As
previously reported in Petroleum News,
ConocoPhillips has prepared a master
plan for that project, involving the devel-
opment of up to five drill sites hooked
into a central processing facility for the
field. Modules for the development
would be delivered by sealift via an artifi-
cial island in the nearshore waters of the
Beaufort Sea.
Another new technology,
ConocoPhillips’ compressed seismic
imaging technique, has enabled the com-
pany to increase its resource estimate for
Willow from 400 million to 750 million
barrels of oil. The new seismic technique
enables seismic data to be gathered four
times faster than previously and enables
the production of better seismic images,
Jepsen said.
Jepsen said ConocoPhillips anticipates
Willow production involving a technique
referred to as MWAG, the alternating
injection of water and miscible injectant
into the reservoir. The injection of water
would require seawater from the Kuparuk
seawater treatment plant, probably deliv-
ered by pipeline from Kuparuk Central
Processing Facility 2, Jepsen said.
Oil from a discovery in the West
Willow No. 1 exploration well, also
drilled last winter, could tie into the
Willow facilities at some stage in the
future. But that discovery requires further
testing and delineation, Jepsen said.
A combination of factorsJepsen attributed the transformation of
ConocoPhillips’ outlook for its North
Slope oil production to a combination of
technical innovation, a reduced cost of
supply, and a competitive tax environ-
ment under the provisions of tax legisla-
tion, Senate Bill 21.
Technical innovation, including the
advances in drilling techniques, has
helped the company target more
resources in existing fields, as well as
improving the viability of new develop-
ments. To manage costs, following the oil
price crash of 2014, the company has
taken a hard look at how to do things bet-
ter, bringing its Alaska cost profile down
to be competitive with other components
of the company’s portfolio, Jepsen said.
Jepsen particularly cautioned that
Alaska’s fiscal environment needs to
remain competitive with other oil produc-
ing regions — the current fiscal frame-
work under SB 21 keeps Alaska in the
game, he said. He also expressed concern
about the upcoming ballot on a proposed
new anadromous fish habitat protection
law. Uncertainty and potential litigation
associated with this measure could
become a big drag on development, he
said. l
PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018 11
GMW Provides the Following Services
GMW has 17 years of experience working in Deadhorse supporting oil field activities on the North Slope of Alaska.
GMW Fire Protection has offices in Anchorage and Deadhorse
Fire Protection Specialists
(907) 336-5000gmwfireprotection.com
• Fire Sprinkler Design and Installation• Fire Sprinkler Inspections and Maintenance• Fire Alarm Design and Installation• Fire Alarm Inspections and Maintenance• Special Hazards Design and Installation
including FM-200 and water mistsuppression systems
• Fire Extinguisher Inspection and Service including hydro-testing and re-charge
• Fire pump certification and inspections• Portable gas monitors and systems
installation and calibration • Kitchen hood service and maintenance• CO2 system maintenance and recharge
Anchorage Honolulu Los Angeles
• Commercial Diving• Marine Construction Services• Platform Installation, Maintenance and Repair• Pipeline Installation, Maintenance and Repair• Underwater Certified Welding• NDT Services• Salvage Operations• Vessel Support and Operations
• Environmental Services• Oil-Spill Response, Containment and Clean-Up• Hazardous Wastes and Contaminated Site Clean-
Up and Remediation• Petroleum Vessel Services, e.g. Fuel Transfer• Bulk Fuel Oil Facility and Storage Tank
Maintenance, Management, and Operations
American MarineServices Group
6000 A Street, Anchorage, AK 99518
907-562-5420Deadhorse, AK
907-659-9010www.amarinecorp.com • www.penco.org
continued from page 1
CONOCO OUTLOOKAs recently as 2013 the company
was forecasting a continuingdecline rate of 6 to 8 percent per
year in its oil output from itsNorth Slope operations. But now
the company anticipates acomplete reversal of that situation,with production in 2028 expected
to be some 100,000 bpd abovewhere it is now, Jepsen said.
12 PETROLEUM NEWS • WEEK OF SEPTEMBER 16, 2018
By terms of a letter agreement dated Sept. 10, the
Alaska Department of Natural Resources, ExxonMobil
and BP (a major Point Thomson working interest owner)
agree that the year-end 2019 deadline has been stayed for
as long as the Alaska LNG Project is progressing. The
extension ends when the Alaska LNG Project reaches
final investment decision or when DNR notifies the par-
ties that the project is no longer progressing.
At the end of the extension the Point Thomson owners
will have 30 months to reach a final investment decision
on either of the expansion projects or lose acreage in the
field.
“The agreement continues to demand that our
resources at Point Thomson are developed to the maxi-
mum benefit of all Alaskans, and also aligns the state and
industry in a new way as the Alaska LNG Project
advances,” DNR Commissioner Andy Mack said in a
statement. “We are committed to development of this
critical resource, and this agreement keeps us on track.”
Gas sales agreementAlso Sept. 10, the Alaska Gasline Development Corp.
announced that ExxonMobil and AGDC had agreed to what
the corporation called “certain key terms including price
and a volume basis for a Gas Sales Agreement,” captured in
a “Gas Sales Precedent Agreement” signed Sept. 10.
AGDC and BP agreed to key terms of a gas sales agree-
ment, including price and volume, on May 4.
AGDC has not reached agreement with ConocoPhillips
— the other major North Slope leaseholder, a company
with natural gas interests at both Prudhoe Bay and Point
Thomson.
In a Sept. 10 statement on the ExxonMobil agreement
AGDC said the parties anticipated finalizing long-term gas
sales agreements for ExxonMobil’s share of both Prudhoe
Bay and Point Thomson gas. ExxonMobil has a 62.75 per-
cent share of Point Thomson and a 36.4 percent share of
Prudhoe Bay.
“This precedent agreement is good for Alaska and
ExxonMobil and represents a significant milestone to help
advance the state-led gasline project,” said ExxonMobil
Alaska President Darlene Gates. “As the largest holder of
discovered gas resources on the North Slope, ExxonMobil
has been working for decades to tackle the challenges of
bringing Alaska’s gas to market,” she said.
“The Alaska LNG project has made meaningful progress
over the past year,” said AGDC President Keith Meyer.
“We have secured the customers, we have advanced the
project with regulators, and now we have ExxonMobil’s
Gas Sales Precedent Agreement executed.”
Alaska Gov. Bill Walker said: “This agreement means
Alaska is one step closer to monetizing the North Slope’s
vast and proven natural gas resources. I am pleased with the
engagement and alignment from ExxonMobil for the
Alaska LNG project.”
Alaska’s congressional delegation welcomed the
announcement of the gas sales precedent agreement.
“This is a positive step in our state’s efforts to build a
new pipeline that will allow us to commercialize the North
Slope’s prolific natural gas resources,” the delegation said
in a Sept. 12 statement. “While we recognize that much
work remains to be done, we’re pleased to see the state
using its authority and leverage under the Point Thomson
settlement of 2012 to help move forward on this major
infrastructure project.”
The delegation, all Republicans, includes Congressman
Don Young and Sens. Lisa Murkowski and Dan Sullivan.
Agreement detailsThe Point Thomson Unit Letter Agreement said that for
purposes of the settlement agreement an Alaska LNG
Project means a fully integrated natural gas project produc-
ing LNG for export and natural gas for in-state delivery
being advanced by the state, a state-owned entity such as
AGDC “or an entity in which a State owned entity holds a
controlling equity share.”
The letter agreement says the June 30, 2017, plan of
development for Point Thomson, as supplemented in
October of that year and approved in August and December
2017, will remain in effect until the effective date of a major
gas sale POD, an expansion project POD or Dec. 31, 2019,
“if an MGS POD or Expansion Project POD has not been
submitted.”
The agreement calls for submittal of Point Thomson
PODs on a biennial basis beginning with the 2020-21 peri-
od. Those PODs would address initial production system
work or other exploration or development, including activ-
ities in support of the Alaska LNG Project.
On the extension period, a final investment decision is
defined as “a decision by the Alaska LNG Project owners to
construct the Alaska LNG Project, following securing the
necessary financing arrangements to construct and operate
the Alaska LNG Project.”
The agreements notes that the Point Thomson unit
working interest owners “have invested about $4 billion
in Point Thomson — more than 70 percent of that in
Alaska.” l
continued from page 1
POINT THOMSON
www.petroleumnews.com
said in presentations at the early
September Barclays conference in New
York.
“Evidence is accumulating that the
boom in the industry that began two years
ago is cooling off, particularly in what has
been its incandescent center, the Permian
basin of western Texas and eastern New
Mexico,” Crooks wrote, adding that both
Halliburton’s Jeff Miller and
Schlumberger’s Paal Kibsgaard “high-
lighted a slowdown in the number of new
wells being brought into production.”
Kibsgaard said the North America mar-
ket for hydraulic fracturing had “already
softened significantly more than we
expected” in the third quarter. The
Permian basin in particular, he said, faced
challenges that he expected to “have a
dampening effect on production growth,
wellhead prices and investment levels in
the coming year.”
Bill Thomas said EOG’s expectation
for the Permian basin was “probably a lit-
tle bit more subdued on growth than most
people would have it. It’ll grow certainly
for the next few years, but it’ll grow at a
slower pace every year and won’t be the
thing that’s going to destroy oil prices
again because it’s going to grow so fast.”
—KAY CASHMAN
continued from page 10
INSIDER
From left, Attorney General Jahna Lindemuth, ExxonMobil Alaska Production Manager Darlene Gates, Gov. Bill Walker, BPVice President of Commercial Ventures Damian Bilbao and DNR Commissioner Andy Mack.
STA
TE O
F A
LASK
A