8/8/2019 KOSTT
1/14
KOSTT the Kosovan Independent
Transmission System and Market Operator
-
8/8/2019 KOSTT
2/14
KOSTT - Transmission, System and Market Operator
Planning, developing, maintaining and operating the Kosovan
Electricity Transmission System;
Providing non-discriminatory Third Party Access;
Operating the New Electricity market; Promoting efficiency in the implementation of Market Rules;
Efficient implementation and management of Balancing and
Settlement provided for by the Market Rules;
Providing conditions that promote competition within Kosova;
Working with neighboring TSOs for the benefit of Kosova and the
region;
-
8/8/2019 KOSTT
3/14
KOSTT - Transmission, System and Market Operator
KOSTT is the owner of the High Voltage Power Transmission System.
The High Voltage Power Transmission System consists of:
OVERHEAD POWER LINES 5 lines 400kV 181.4 km 15 lines 220kV - 361.8 km
38 lines 110kV 643.5 km
SUBSTATIONS 1 Substation 400/220 kV of transformer capacity 1200 MVA 3 Substation 220/110 kV of transformer capacity 1000 MVA 1 Switching substation 220kV 1 Substation 220/35/10 kV only 220kV bays
31 Substation 110/(35 or 10) kV only 110kV bays
-
8/8/2019 KOSTT
4/14
KOSTT - Transmission, System and Market Operator
Power
PlantUnit
Gross
Installed
Power
[MW]
Net
Power
[MW]
Net
Aviable
Power
[MW]
FuelStart of
operation
Kosova A
A1
A2
A3
A4
A5
65
125
200
200
210
58
113
182
182
187
30-40
0
130/150
120/145
135/150
L/N
L/N
L/N
L/N
L/N
1962
1964
1970
1971
1975
Kosova B
B1
B2
HPP Ujman (Gazivoda)
339
339
309
309
230/250
230/250
L/M
L/M
1983
1984
G1G2
17.517.5
17.517.5
17.517.5
19811981
Existing Power Generation Facilietis in Kosova
L/N= Lignite /diesel, L /M= Lignite /Mazout
The electricity in the Kosova PowerSystem is generated from: 96.8% Lignite Thermal Power Plants 3.2 % Hydro Power Plants
From To kV MW
1
2
34
Kosova
Kosova
KosovaKosova
Serbia
Montenegro
MacedoniaAlbania
400
400
400200
600
600
600200
Indicative Values for Net Transfer Capacities to and from Kosova
-
8/8/2019 KOSTT
5/14
Prizreni
Gjilani
Prishtina
Mitrovica
UjmaniValac
Deani
Leposavic
VushtrriaBurimi
Klina
Dragashi
Shtrpca
Vitia
Rahoveci
Lipjan
Shtimje
Ferizaji
Kamenica
Podjeva
2
Drenasi
1
3
A
B
1
3
4
Theranda
Sharri
1
2
2
MACEDONIA
ALBANIA
MONTE NEGRO
SERBIA
SERBIA
SERBIA
Peja
Sknderaji
Gjakova
Trepa
Berivojc
5
Feronikeli
Bardh
Legjenda
TC
HC
Linj 400kV
Linj 220kV
Linj 110kV
TS
POWER SYSTEM OF KOSOVA
400kV, 220kV and 110kV
2
1
12
Supply problems.
More transformation required.
Overloaded lines
New PEJA III 400kV Sub/Stn
New Sub/Stn at FERIZAJNew 400kV line before TPKOSOVA C
2100MW
KOSOVA CDistribution reinforcement
6
4 5
Malisheva
-
8/8/2019 KOSTT
6/14
Existing Interconnection Lines
600MW600MW
600MW600MW
600MW600MW
600MW600MW
MONTENEGROMONTENEGRO
ALBANIAALBANIA
SERBIASERBIA
SERBIASERBIA
FYR of MACEDONIAFYR of MACEDONIA
1
2
3
600MW600MW
The existing
interconnection linesenable power
exchange with
neighboring power
systems.
-
8/8/2019 KOSTT
7/14
Development of Interconnection Lines
600MW600MW
MONTENEGROMONTENEGRO
ALBANIAALBANIA
SERBIASERBIA
SERBIASERBIA
FYR of MACEDONIAFYR of MACEDONIA
1
2
3
600MW600MW
Existing and new
interconnection lines
that need to be build,
will create sufficient
transmission capacity
for export of
electricity generated
in the new TPP
Kosova C.
600MW600MW
600MW600MW
600MW600MW
600MW600MW
BiHCROATIA
BiHCROATIA
ITALY
-
8/8/2019 KOSTT
8/14
I
H
SI
A
I
SER
CG
RO
AL
MK
BG
TR
GR
KS
BiH
SK
CZ
CH
D
F
Strategic Zone
Base Energy
Peak Energy
Kosova Key Strategic Player in SEE Electricity Market
-
8/8/2019 KOSTT
9/14
Development of Kosova Power System
No investment between 1990 - 2000
Between 2002 2006 the ITSMO has initiated investment and
development plan for 5-10 years
0
1
2
3
1951 1956 1961 1966 1971 1976 1981 1986 1991 1996 2001 2006
-
8/8/2019 KOSTT
10/14
0
200
400
600
800
1000
1200
Generation
Full Operation
N-1 Operation
Daily Winter peak demandMWh
h
Existing Transmission Capacity
-
8/8/2019 KOSTT
11/14
Demand Growth
Kosova growth 7% Regional growth 4-5%
0
1000
2000
3000
4000
5000
6000
7000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
MWh
-
8/8/2019 KOSTT
12/14
2100 MW Power Station and KOSTT
Transmission investment opportunity to secure access
rights to other regions;
Local transmission investment also required to support
demand growth;
Early discussions with KOSTT necessary forconnection solution to TPP Kosova B switch yard.
-
8/8/2019 KOSTT
13/14
Electricity Market and Regulatory Environment
The market place is on the transmission network; The SO manages physical flows;
The MO manages it commercially these flows;
All necessary liberal market codes are in place (Grid Code, Market
Rules etc.);
KOSTT is in process of being recognised in the Region and is a
strong supporter of inter-regional trade;
KOSTT is actively being participating in all Athens Processes;
KOSTT is required to, and does, support competition in generation,
supply and regional trade;
KOSTT is strong supporter of new generation;
-
8/8/2019 KOSTT
14/14
Thank you for your attention!
Transmission, System and Market Operator
www.kostt.com