kensal ecoquarter - overview report
DESCRIPTION
overview report, the final report in a sequence of four reportsTRANSCRIPT
Kensal Canalside Pre-Feasibility Studyo v e r v i e w r e p o r t
D e c e m b e r 2 0 0 8
Kensal Canalside Pre-Feasibility Study o v e r v i e w r e p o r t
D e c e m b e r 2 0 0 8
Willie Miller Urban Design
Colliers CRE
Battle McCarthy
Alan Baxter Associates
Gardiner & Theobald
Kevin Murray Associates
20 Southbrae Drive
Glasgow G13 1PY
Royal Borough of Kensington and Chelsea
contents
Kensal Canalside Pre-Feasibility Study o v e r v i e w r e p o r t
D e c e m b e r 2 0 0 8
Summary 1
1 Introduction 5
2 Approach 7
3 Outcomes 13
4 Next steps 17
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 1
summary
This is the Overview Report of a ‘pre-feasibility study’ into
the creation of a potential EcoQuarter at North Kensal.
Commissioned by the Royal Borough of Kensington
and Chelsea in April 2008. It aims to explore whether
the Council’s current vision for the site – comprising
placemaking, regeneration, sustainability and transport
infrastructure aspirations – has the potential to be viable and
deliverable in the longer term as a major transformational
project.
The study considered constraints and physical parameters,
a range of diverse future scenarios and opportunities, as
well as costs, risks and other deliverability issues. These are
provided in the full compendium of documents including:
• OverviewReport–thisdocument.
• BaselineReport–settingoutexistingconditions
and parameters.
• OptionsReport–exploringtheimplicationsof
alternative scenarios and options.
• RiskReport–identifyingthevarioustypesofrisk
which could affect implementation of the various
options.
During the commission, the global credit crunch and
economic crisis increasingly undermined the team’s ability
to consider future situations with any degree of reliability.
Nevertheless, we consider that there are some key findings.
Positive strategic role
There is definite potential to undertake significant
development on the study area – and to influence
regeneration in the surrounding areas in the northern part
of the Borough and in adjoining boroughs, and possibly
even at a London level and beyond. The full scope and scale
of transformation is dependent on a number of factors,
including the ability to capitalise upon opportunities and
address some very real constraints.
Constraints
There are a number of key constraints affecting development
of the site:
• Therailandcanalcorridorsformbarrierstonorth-
south movement within and beyond the site.
Whilst development could possibly be built over the
railway, this is unlikely to be viable for the canal.
• Safetyconcernsaroundthegasholdersarelikelyto
prevent residential development on portions of the
site as long as the gasholders are in place (until at
least 2016).
• Thesinglevehicularconnectiontothesitemakes
it isolated, both in terms of public and private
transport. It also places significant physical
constraints on the quantum of development.
• TheexistingSainsbury’sstoremayormaynotwish
to move from its current site - it could possibly be
redeveloped as part of a larger, denser development.
• WeunderstandthatCrossrailareseekingtousepart
of the southern portion of the site as a temporary
bus garage during construction works, to 2017.
Scenarios and development choices
The scale of future scenarios considered range from modest
housing to large scale mixed use destinations, with greater
developments requiring much more infrastructure, including
a Crossrail station. These were indicative scenarios rather
2
than specific physical options, but they did indicate
variability in delivery and impact across both time and space.
Economic viability
None of the scenarios is considered viable in the immediate
future because of market circumstances. However, the lower
scale residentially-oriented developments (shown by options
A and B) would probably secure landowner developer support
in time, because they are of a more modest scale and are less
dependent on costly infrastructure.
The more significant developments, exemplified in options
D, E and F, have more market risk at present. This is because
they are so dependent on substantial infrastructure such as a
Crossrail station and one or more bridge crossings.
Risks and benefits
Whilst exploring the viability of different development
options for the site, the study also considered benefits that
could accrue for the local area. If the potential to provide
direct connections from the site to a wider London is
realised, whether through Crossrail or some other means, the
site could potentially fulfil a role of much wider significance
than the purely local.
Indeed the scenarios indicated a potential to contribute to
London’s international role as a world gateway city, whilst
also contributing to the regeneration of North Kensington,
responding positively to climate change, and intensifying
development in an accessible locations. However, this would
see the less intensive development of the site as a missed
opportunities (options A, B and even C), and options D, E
and F as more aspirational and potentially bringing greater
economic and social benefit.
In terms of sustainability, there are benefits in an approach
that brings improved access to a wider range of community
facilities and employment in an area of social deprivation,
as well as new development biased towards low car usage,
public transport, and low carbon energy efficient buildings.
Important risk factors include:
• Roleandwillingnessofthefourkeylandownersto
participate in such a large scale project.
• Timingofthegasholderdecommissioning,andthe
spatial extent of its safety buffer.
• Costsandvaluesofdifferentdevelopmentand
infrastructure components.
• ImplicationsofsecuringaCrossrailstation–ornot.
Recommendation
The recommendation is to pursue as ambitious an option
as possible in partnership with the key landowners, and
to continue to build up the parallel case for a station. We
see this option being represented as a composite of C and
D at this stage, beginning in the eastern part of the site,
and extending westwards over time as the gas holders are
decommissioned. This composite is more ambitious than
options A and B, but is more feasible than option E. It could
also provide a basis for including part of option F if the
opportunity presents itself.
Next steps
Assuming the Borough remains keen to pursue the concept
further, the next steps would be to:
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 3
Allocate the area as a Special Development 1.
Opportunity in any relevant policy framework.
Undertake detailed, phased masterplan design and 2.
feasibility testing.
Identify the impacts/benefits upon the wider area, 3.
as part of the case for transformational change.
Work closely with all the current landowners.4.
Work towards making a Crossrail station viable. 5.
At the appropriate time – engage with the local community.
4
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 5
1 introduction
In April 2008 a team of consultants was appointed by the
Royal Borough of Kensington and Chelsea to undertake a
preliminary feasibility study for a major redevelopment at
Kensal in the north of the borough. The team was led by Kevin
Murray Associates and comprised:
Kevin Murray Associates lead consultant
Willie Miller Urban Design spatial design
Alan Baxter Associates transport
Battle McCarthy sustainability
Gardner & Theobald costing
Colliers CRE property
The brief was initially termed an ‘ecotown’ or ‘eco-
neighbourhood’. Although this terminology has been
dropped to avoid confusion with a specific government
programme, many of the ideas have continued in the
evolution and testing of the concept.
The brief, and subsequent review, is focused around the
opportunity to deliver radical and transformational development
on a 19 hectare site lying between the main Great Western
railway line and Grand Union Canal in the north of the Borough.
As key sites within the area come forward for redevelopment,
there is potential to transform not only those sites but also
to make physical, social and economic linkages that could
regenerate the area as a whole, making it a more sustainable
neighbourhood from a number of perspectives. If delivered,
a visionary project if this type could deliver scale, critical
mass, diversity, connectivity, and a vibrant urban hub, all
in the context of a 21st century low carbon scenario. This,
however, depends on a radically different approach from the
‘do-minimum’ – which is becoming increasingly challenging
in the current investment context.
Context
In response to the brief, a vision of what this opportunity
could deliver was identified. It embraced:
• Agoodfunctionalpieceofcity,withwellintegrated
development that is permeable and of human scale.
• Developmentofahighlyaccessible‘centre’witha
range of public transport services, and retail and
leisure functions.
• Anenhancedresidentialcatchmentthattransforms
its existing nature and weaknesses and is high
enough to support good bus or Crossrail services,
and community services.
• Aboveall,creationofazeroorlowenergy
development that is also modest in use of other
resources.
As the project review progressed, it became apparent that
these aspirations could apply in different ways at a variety of
scales – from a very localised transformation, to a Borough-
wide and West London transformation, up to a London-wide
and potentially international scale.
aerial view of site + site boundary
6
The purpose of this pre-feasibility study was to assess how
practical and realistic such an overall vision could be. The
brief asked us to:
• Undertakeaninitialpre-feasibilityofthepotential
for an ‘EcoTown’ approach using key sites at Kensal.
• Identifyeitherthattheconcepthasnopotentialor
– if it does – to scope out the next stage of work in a
vision concept and brief.
The commission took place against a backdrop of
ongoing progress with the Local Development Framework
(LDF). Following the Council’s initial stage of LDF public
consultation, an Issues and Options consultation on the
Core Strategy in 2005, the Council held two further public
consultations which coincided with this commission:
• Immediatelybeforethecommissionbegan,in
February to April 2008, the Council held a further
Issues and Options public consultation on its Core
Strategy and North Kensington Area Action Plan.
The Kensal site was specifically included within this
Area Action Plan.
• BetweenJulyandOctober2008,theCouncil
undertook public consultation on a combined
document “Towards Preferred Options” which
included both the Core Strategy and the North
Kensington Area Action Plan. This focussed
particularly on strategic policy directions and
alternative visions for the Borough, together with a
focus on spatial areas in south of the Borough.
We understand that this commission will inform the LDF
process as it moves forward.
This Overview Report sets out the approach and key findings
of our commission. It should be emphasised that all of the
core work was undertaken before the full impacts of the
credit crunch had worked through.
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 7
2 approach
To navigate through the complex issues presented by the
site and brief, the approach to the commission involved a
progressive sequence of stages:
• Baselineinformation–assemblingrelevant
information about the site and its context.
• Optiongenerationandtesting–generationof
options as alternative scenarios, a review and
testing workshop, then a refinement of these
scenarios as conceptual options.
• Discussionswithkeystakeholders,including
landowners and politicians.
• Analysisofkeyconstraintsandotherdimensionsof
risk to the project, or to elements of it.
These various stages have been reported on in a sequence of
separate Reports.
Baseline analysis
To ensure that the options stage was informed and realistic,
a thorough baseline assessment was undertaken. The
main points are captured in the Baseline Report under the
following headings:
• Sitelocation-inarelativelyisolatedpositionat
the northern extremity of the Borough, the site is
currently only accessed from Ladbroke Grove. It
is split by rail tracks carrying the Great Western
main line and the Heathrow Express. Existing uses
include Sainsburys and two gasholders, as well as
derelict land. The Grand Union Canal and Kensal
Green Cemetery define the northern edge of the site.
• Policycontext–asummaryofkeypointersfrom
the statutory planning framework, which contains
important clues as to the potential long term role of
the site both locally and strategically.
• Areaanalysis–ananalysisofthephysicalformand
character of the site, dividing it into a number of
characterzonesforanalyticalpurposes.
• Ownership–therearefourkeylandholdingswhich
canbedividedintodistinctzones,eachofwhich
offers varying levels of potential for more intensive
use.
• Transport–accessibilityisakeyissue.This
section of the Baseline Report looks at existing
vehicular and pedestrian networks, public transport
accessibility, and examines the potential for
securing a new Crossrail station.
• Sustainability–thebriefplacessustainable
development at the heart of the project. We took
a broad view of sustainability, encompassing
economic, social and environmental issues. This
section places the site in context using indicators
for each of three types of issue.
• Propertymarket–anintroductiontofactors
which will affect the future use of the site from the
property market’s perspective.
• Infrastructureandcontamination–asummary
of key factors, focussing on remediation and the
impact of the gasholders on future development.
• Costs–anoverviewofcost-relatedfactorsthatwill
impact on how the site can be developed.
Significant physical constraints identified at this early stage
included:
• Therailandcanalcorridorsformbarrierstonorth-
south movement within and beyond the site. Whilst
8
development could possibly extend over the railway,
this is unlikely to be viable for the canal.
• Safetyconcernsaroundthegasholdersarelikely
to prevent residential development on significant
portions of the site as long as the gasholders are in
place (until at least 2016) – although there is a view
that these safety requirements are excessive.
• Thesinglevehicularconnectiontothesitemakes
it isolated, both in terms of public and private
transport.
• Sainsburysareunlikelytowanttomovetheirstore
from its current site, although it could possibly be
redeveloped as part of a larger, denser development.
The Baseline Report contains more details of this stage of the
process.
Options generation and testing
The options stage was pivotal in the overall process. It was
a progressive learning and testing approach to unearth the
relationships between the various issues, identify a number
of possible scenarios, and crystallise both the client’s and the
consultants’ thinking about practical ways of developing the
site in response to the study brief.
A client workshop was used to test different development
scenarios for the site, based on a set of alternative scenarios
of progressive scales and intensity of development.
The process of generating and testing options was designed
to be creative and open, with the aim of avoiding closing
down ideas and choices before they had been explored.
This open approach resulted in consideration of a wide
range of possibilities. It enabled a variety of futures and
outcomes to be constructed, explored and developed, then
further reviewed and tested for feasibility, desirability
and plausibility. This method enabled exploration of
scenarios that were acknowledged as being, to varying
extents, desirable and plausible – not simply a wish list of
workshop images - 13 May 2008
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 9
A
Amax
D F1
B
C
E F2
a few idealised end-states. The scenarios explored a future
situation (2025) well beyond the limits of current policy, and
also without community involvement at this early stage.
Importantly, it generated a wide range of relevant issues for
further testing, review and, where appropriate, policy action
and dialogue with landowners and statutory bodies.
The development of the range of scenarios involved initial
construction using two key variables – one relating to an
increasing scale and quantum of development, the other
to an increasingly diverse range of uses and activities. The
absence or presence of a Crossrail station was included in the
range. Using the knowledge gained from the initial stages of
baseline research, the options were developed and reviewed
in a collaborative workshop with the client, following which
the consultant team updated and modified the options in
response to further baseline information that subsequently
emerged.
The final options are shown on the accompanying table and
plans. Further detail is available in the Options Report,
which also describes the options generation and testing
approach in more detail.
10
option gross area
storeys residential units commercial floorspace
description Crossrail station
north south total
A 6.7 ha 4 1256 920 1256 7,000m2 Residential, 3 and 4 storey [average 3.5 for calculating number of homes], some
higher, Sainsbury retained as is, canal extensions through site, no development south
of railway, no station.
no
A max 12.8 ha 5 2435 920 1992 7,000m2 Same as A but includes development south of the railway no
B 15.2 ha 6 2922 1104 3355 12,000m2 Residential,5and6storey,somehigher,Sainsburyincludedinreconfiguredbuilding,
canal extensions through site, residential development south of railway, Crossrail
station.
yes
C 15.2 ha 7+ 3896 1288 5184 20,000m2 Residential,6and7storey,communityandretail,Sainsburyincludedinreconfigured
building, canal extensions through site, residential south of railway, Crossrail station.
yes
D 15.7 ha 6-12 1260 920 2180 164,201m2 Business, leisure, retail and residential, 11 and 12 storey, residential south of railway,
Crossrail station. A London destination rather than a residential dormitory.
yes
E 16.7 ha 13+ 1989 404 2393 480,000m2 Business, leisure, retail and residential, 13+ storeys, megastructure around Crossrail
station, underground parking. A London destination rather than a residential
dormitory.
yes
F1 16.7 ha various 0 920 920 580,000m2 Large single user on megastructure around Crossrail station, underground parking.
An international centre of excellence – for example in health or education.
yes
F2 15,2 ha various 0 404 404 500,000m2 Same as F1 but without a crossrail station nor construction over the railway (unless
viable)
no
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 1 1
Stakeholder discussions
In the latter part of the study, discussions took place with
two key stakeholder groups - landowners and key local
politicians to present the issues surrounding redevelopment
of the site and understand their aspirations.
These discussions highlighted a divergence between the
aspirations of these two key groups of stakeholders. This in
summary was as follows:
• Thekeylandowners viewed major redevelopment
proposals cautiously. Generally, they favour lower
intervention options without new rail bridges
and stations –unsurprisingly given the inherent
additional cost and risk in the more interventionist
options. Put very simply, the optimal commercial
scenario could be described as achieving maximum
possible development capacity of high value
development (likely to be residential) with minimal
strategic interventions such as a rail bridge or
station.
• Key politicians took a rather more proactive stance.
They aspired to see the site developed for more than
just housing, instead setting their sights on mixed
use with employment and community benefits or
the single-user campus type scenario. They were
keen to move forward with the process of securing
appropriate redevelopment of the site.
It is important to note that local communities are also a
key stakeholder. Whilst it was – with good reason - beyond
the scope of this pre-feasibility study to engage with
communities, it is important that early, genuine community
engagement takes place if regeneration of the site is
progressed. We discuss this in more detail in the Risk Report.
Risk assessment
Identifying the risks that might derail this project has
always been a critical part of this commission. As we have
explained above, our initial proposal recognised that there
are a number of potential risks that could prevent this project
either from being delivered or fulfilling its potential – in
other words, failing to meet the high aspirations that have
been set for the project.
Our analysis identified a number of key barriers to
implementation and risks to the project, each of which is
explained in more detail in the Risk Report:
• Property market – the main property market risks
focus around creating a distinctive location that the
market will be persuaded to invest in, particularly
in the way that would be required to meet the
ambitious ‘ecoquarter’ aspirations.
• Landowners – the main risks relate to failing to
ensure that key landowners act in concert to provide
an outcome that is more substantial and beneficial
than the sum of their individual aspirations.
• Placemaking and liveability – the key risk is in
delivering the substantial scale of development
envisaged but without distinctive character,
comfortable human scale, user-friendly sense of
space or integration, and linkage with surrounding
areas. In other words, the scheme might ‘tick the
boxes’ but not deliver a sustainable neighbourhood
of enduring quality.
12
• Sustainability – the main sustainability risks relate
to providing a basic development that does not meet
the higher aspirations of an ecoquarter. This is as
much about aspiration and eventual user lifestyles
as it is about the initial development.
• Local infrastructure and carrying capacity – there
are some risks around the carrying capacity of the
area to take the scale of development anticipated.
Improvements are required before major scale
development can be successfully progressed and
integrated.
• Delivery of a Crossrail station – risks are presented
by uncertainly over Crossrail: firstly, whether and
when any station might be delivered, and secondly
how much development can be progressed before
hitting any trip generation thresholds.
• Political support – because of the boldness and
scale of any Kensal ‘ecoquarter’ scheme, there will
always be a risk of political fragmentation and
changes in vision and direction throughout the
duration of such a major project. This could also
have property market confidence implications.
• Community support – any major scheme will
generate community concerns – and likely
opposition. The greater the scheme, the greater the
potential for opposition unless clearly identified
community benefits can be communicated.
• Regulatory requirements – regulatory
requirements could have a significant bearing
on what may be possible. Of these, the safety
zonearoundthegasholdersiscurrentlythemost
prominent uncertainty.
To supplement these generic risks, the Risk Report also
summarised specific risks for each of development option.
This demonstrates a clear relationship between risk and
reward: option A offers the least risk, yet is also the least
aspirational and ambitious in terms of regeneration benefits,
Crossrail and other public benefits. The more ambitious
development options contain greater risks, but also the
promise of greater rewards.
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 1 3
3 outcomes Decision areas
The process of generating and testing options produced a
range of development scenarios for the site. These varied in
terms of both use (encompassing residential, mixed use and
single institutional users) and scale (from developing only
the area to the north of the railway to a megastructure which
decks over the railway and takes in the entire site).
In the Options Report, we have identified three key decision
areas which need to be aligned to have any chance of
securing the more ambitious proposals of the area becoming
a major destination:
• Thelong term strategic aspiration for the role
of the location – whether to play a wider socio-
economic role in West London and beyond, or focus
on the more immediate neighbourhoods at the
Borough scale.
• WhetherthereisaprospectofsecuringaCrossrail
station in the medium term, which is closely
linked to the first decision area, but not necessarily
resolved immediately.
• Whetherthevariouslandowners are willing to act
in concert with the Council to promote the more
ambitious development options.
The Options Report also identified a number of associated
factors, none of which are small challenges – all require a bold
approach and committed follow-through:
• Securingtheoptimumsolutionintermsof
matrix for plotting scenarios
environmental sustainability.
• Achievingwider regeneration benefits beyond the
immediate locality.
• Ensuringthatthecarrying capacity of the
local area can accommodate the quantum
of development associated with each option
– particularly in terms of infrastructure and
community facilities.
• Producinganeconomically viable approach that
contributes to the public realm and well-being.
• Ensuringthatplacemaking and liveability are of
the highest order, particularly for the more intense
development options.
The original directional choices can be summarised as:
• A,AmaxandB:lowerintensityhousingdriven
options. Potentially deliverable – but not necessarily
fully transformational.
• C:highdensitycommunity,potentiallydeliverable,
but not fulfilling potential role.
• DandE:increasinglydensemixeduse,potentially
viable as destination, but raising questions over
14
delivery and may bring disbenefits in terms of
community value.
• F1andF2:‘centreofexcellence’campus.
Aspirational, highly transformational, but only
deliverable under certain circumstances.
Recommended approach
As a result of ongoing review, early dialogue with landowners
and members, and changing market circumstances, we
recommend proceeding with a cautiously optimistic
approach, anticipating a change in future circumstances.
This would allow for:
• Progressive,butlinked,implementationbydifferent
landowners/developers.
• Agreaterlevelofmixandscalethanthat
represented by options A and B, with potential to
bring Borough and London-wide benefits.
• Avoidingthehighestriskoptions–intermsofscale,
cost and complexity.
• Maintainingtheaspirationaltargetofsecuringa
station because of its wider benefits.
This approach is exemplified by a new Balanced Composite
taking elements of options C and D (see plan overleaf ). This
includes a reconfigured Sainsbury’s block with car parking
incorporated in the building and residential uses above.
This reconfigured Sainsbury’s store would lie within a new
street layout on the eastern part of the site. Development
would only occur on the western part of the site once the gas
holders have been decommissioned and then removed. This
aims to build up a critical mass of development over several
stages, including elements of key infrastructure.
This composite option responds to a number of particular
constraints:
Continued use of the gas holders until at least 2016, •
and related health and safety constraints.
The need to create a second access to the site south •
of the railway, connecting to Barlby Road at at least
two points and with a possible western connection
to Mitre Way if feasible.
An anticipated requirement for Sainsbury’s to retain •
visual prominence from Ladbroke Grove.
Avoiding prejudicing the potential for a future •
Crossrail station.
We would emphasise that this remains a conceptual
approach at this stage which needs further feasibility testing
and discussion with key stakeholders. It is not yet a fully
costed masterplan framework.
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 1 5
indicative framework
phase 2
phase 1
16
K E N S A L C A N A L S I D E P R E - F E A S I B I L I T Y S T U D Y
D E C E M B E R 2 0 0 8 | K E V I N M U R R A Y A S S O C I A T E S | 1 7
4 next steps
First and foremost, this commission has established that
there is potential for comprehensive redevelopment of the
site to contribute not only to the case for a Crossrail station
but other wider regeneration benefits in the north of the
Borough.
Further, more specific and detailed testing of a specific
approach is now required to underpin this approach in
policy terms. In addition, exploring the options by creatively
engaging with the local community and other stakeholders
is important to address one of the key components of the
project – as interested parties.
It is proposed the next steps would be to:
1. Allocate the area as a Special Development
Opportunity in any relevant LDF policy framework,
setting down key goals.
2. Undertake detailed phased masterplan framework,
socio-economic impact appraisal and feasibility
testing.
3. Identify the impacts/benefits upon the wider area,
as part of the case for transformational change.
4. Work closely with all the current landowners.
5. Work towards making a Crossrail station viable.
6. At the appropriate time, consult with the local
community about concept and content – within the
broad framework of the LDF programme.