kenneth j. andrews emp-5179-5-1 manufacturing systems: emp-5179 module #5: value-stream mapping...
TRANSCRIPT
Kenneth J. Andrews EMP-5179-5-1
Manufacturing Systems: EMP-5179
Module #5: Value-Stream Mapping& Quick Set-Up
Dr. Ken AndrewsHigh Impact Facilitation
Fall 2010
Kenneth J. Andrews EMP-5179-5-2
Program Overview (Modules & Weeks)7. Quality at Source
8. Customer Ints.
9. QFD & DFM
10. Teams & Change
11. Term Papers
1. Intro. ToManuf. Systems
2. Lean & JIT
3. Push vs. PullProcess Impr.
4. TQ Tools & Techs.
5. Value Stream Maps
6. Manuf. Metrics 12. Final Exam (Dec 6)-new date
There IS Class on Nov 8
No Class on October 11
Kenneth J. Andrews EMP-5179-5-3
EMP-5179: Module #5
Gen-X Case Study
Value Stream Mapping(ref Gary Conner)
Quick Set-Up
Kenneth J. Andrews EMP-5179-5-5
Producing defective parts Passing on defective parts Not communicating
improvements Overproduction Inventories Motion High nonvalue ratio Transportation Waiting Counting Inspection after the fact
Facility layout Excessive setup times Incapable process Maintenance Work method Training (or lack of) Supervisory ability
(coaching) Production
planning/scheduling Lack of workplace
organization Supplier quality/reliability Lack of concern
Waste Opportunities
Kenneth J. Andrews EMP-5179-5-6
Two Approaches
Percent of Lead Time5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
VA
NVA
NVA
NVA
VA
VA
Kenneth J. Andrews EMP-5179-5-7
Define all activities required to design, order, and provide a specific product, from concept launch, from order to
delivery, from raw materials into the hands of the customer.
This includes:• Information flow• Material flow• Inventory (WIP) • Non value-added activities• Transportation flow
Mapping Value Streams
Kenneth J. Andrews EMP-5179-5-8
Value Stream Mapping
A visual tool for identifying all activities of the planning, and manufacturing process to identify waste
Provides a tool to visualize what is otherwise usually invisible
The leaders of each product family need to have a primary role in developing the maps for their own area
Develop a current state map before improvements are made so that the efforts and benefits can be quantified
On the shop floor, not from your office—you need the real information, not opinion or old data
What?
Why?
Who?
When?
Where?
Kenneth J. Andrews EMP-5179-5-9
Value Stream Map Symbols
Spot weld
ABCplating
C/T = 30 sec
C/O = 10 min
3 shifts
2% scrap rate
Process
Finishedgoods
Vendor Data box
3,000 units
= 1 day
Inventory
Push Supermarket Physical pull
Monand
Wed
Shipment
Kenneth J. Andrews EMP-5179-5-10
Approach to Value Stream Mapping
Step #1– Identify customer requirements
– Define method of delivery
– Define typical quantity requirements
– It is OK that more than one customer is served by this value stream, but make sure that the primary processes used are similar
– Use a pencil rather than computer
6 units/week
Recyclable tray
XYZ Corporation
18 units/day
9 lefts9 rights
Kenneth J. Andrews EMP-5179-5-11
Approach to Value Stream Mapping
Step #2– Perform an upstream walk through each
process step, observing and documenting as much of the following as possible:
• Cycle time (operator & machine cycle time)
• Changeover times• Average inventory queue• Average production batch size• Number of operators at each process• Package or container size• Available time (don’t count breaks) • Scrap rate• Machine up time (availability)• Number of product variations
180 units/week
Recyclable tray
XYZ Corporation
18 units/ day
9 lefts9 rights
Kenneth J. Andrews EMP-5179-5-12
Process Description
Crew size:
Output: per:
Waste %
Time available
C/T
C/O
Up time:
I The triangle symbol identifies inventory; this can be expressed in pieces or in time (how many hours, days, or weeks of inventory).
The arrow connects to the next process. A straight arrow can stand for a push, a curved arrow can symbolize a physical pull from a kanban location.
Step #3Record as much data as is pertinent in the process description box
Approach to Value Stream Mapping
Kenneth J. Andrews EMP-5179-5-13
Step #4• Dream about perfection• Think outside the box • Develop alternatives to the current state map—Muda
free• Focus on velocity• Test each idea against TOP— in other words, does it
support: One-piece flow Pull
Approach to Value Stream Mapping
Kenneth J. Andrews EMP-5179-5-14
Step #4• Dream about perfection• Think outside the box • Develop alternatives to the current state map—Muda
free• Focus on velocity• Test each idea against TOP— in other words, does it
support: One-piece flow Pull
• Develop a “future state” map that visually describes the goal
• Break down the future state map into manageable steps
• Develop a Gantt chart (time-phased project plan)• Identify the kaizen events that will need to take place
Approach to Value Stream Mapping
Kenneth J. Andrews EMP-5179-5-15
Fast Track Process Improvement
What process?
Customer +requirements
Map currentprocess
Identifyhot-spots
Root-causeanalysis
Improvements toa) fix root causes b) meet C requirements
Metrics (1-3 months)
Communicate plan
Implement,measure,fine-tune
Kenneth J. Andrews EMP-5179-5-16
Weekly shipments:700,000 lineal50,000 pieces
1,034 sec 280 sec
IMolder #4
Crew size: 4Run speed 300 ft/minOutput:1,285 pieces/hr
Waste = 1/2%
Sec available27,000
C/T= 2.8 sec
C/O= 5 - 45 min
% Crew:days= 100% swing = 0 %
% Reliability = 98%
Weekly hr = 38.9
IPrime
Crew size: 3Run speed: 3,15 l ft/minOutput: 1,350 pieces/hr
Waste = 3%
Sec available 27,000
C/T= 1.3 sec
C/O= 1 min - 1 hr
% Crew:days =100% swing =
% Reliability =73%
Weekly hr = 18.5
130 sec
Staging
5,350 finished pieces/day
ILam #1
Crew size: 4Run speed 58 ft/minOutput: 500 pieces/hr
Waste = 1/2%
Sec available 27,000
C/T= 7.2 sec
C/O= 5 - 25 min
% Crew:days= 100% swing = 0%
% Reliability = 98%
Weekly hr = 5
5 %
90 %
IResaw (4 saws)
Crew size: 1 1/3Run speed 184 ft/min.Output:1,584 pieces/hr
Waste =
Sec available 108,000
C/T= 2.3 sec
C/O= 7 - 30 min
% Crew Days =100%Swing =0%
% Reliability = 95%
Weekly hr = 31.6
5 %
10%
230 sec
90%
268 pieces
4,500 pieces
9000pcs
9,000pieces
.5 hr 48 hr48 hr48 hr
6-day lead time as shown
Current State Map (Simplified)
Kenneth J. Andrews EMP-5179-5-17
Process Time
Shear 10 blanks = 15 minPunch 10 blanks = 30 minDeburr 100 parts = 10 minForm 100 parts = 40 minHrdwr 100 parts = 15 minPack 100 parts = 10 minTotal = 120 min
Lead time
1.0 day1.0 day0.5 day1.0 day1.5 day0.5 day5.5 day (7,920
min)
120 is 1.5% of total lead time or a ratio of 1:66
Value-added Ratios VA:NVA
Kenneth J. Andrews EMP-5179-5-18
Production leadtime = 3.7 hr
Value-added time 1,233 sec
Weekly shipments:700,000 lineal50,000 pieces
1,034 sec
VA Ratio =1:12
Staging
5,350 finished pieces/day
ILam #1
Crew size: 4Run speed 58 ft/minOutput: 500 pieces/hr
Waste = 1/2%
Sec available 27,000
C/T= 7.2 sec
C/O= 5 -25 min% Crew:days= 100% swing = 0%
% Reliability = 98%
Weekly hr = 5
5%
IPrimed lineal cell
Crew size: 6Run speed 300 ft/minOutput: 1,285 pieces/hr
Waste = 1.2%
Sec available 27,000
C/T= 2.8 sec
C/O= 10 - 20 mins% Crew days =100%
% Reliability = 95 %
Weekly hr = 38.9
199 sec
268 pieces4,500pieces
.5 hr .2 hr3 hr
Ÿ Free up $50,625 inventoryŸ 96% improvement in lead timeŸ Instant quality feedback
1-day lead time as shown
95%
Future State Map
Kenneth J. Andrews EMP-5179-5-19
Before
5 forklift
movements
28,118 pieces in
WIP
144 hr lead time
273 labor hr/week
9,000 ft2 required
After
3 forklift
movements
10,118 pieces in
WIP
3.7 hr lead time
235 labor hr/week
2,760 ft2 required
Improvement
40% reduction
64% reduction
97% reduction
14% reduction
70% reduction
Improvement Data
Kenneth J. Andrews EMP-5179-5-20
Value Stream Mapping: Summary
Develop a current state map first
Clearly document the future state map so everyone can visualize it
Perform the improvements in manageable steps
Be good at finishing—use policy deployment
Don’t wait for the entire process to complete, celebrate the journey
Kenneth J. Andrews EMP-5179-5-21
EMP-5179: Module #5
Review Quiz #1
Gen-X Case Study
Value Stream Mapping
Quick Set-Up
Kenneth J. Andrews EMP-5179-5-22
JIT: Pull System
Benefits:– Eliminate waste.– Eliminate over production.
– Reduce inventory and warehousing costs.
Restrains.– Higher shipping costs per unit.– Needs extensive supplier and system integration.
Remember from Module #2?
Kenneth J. Andrews EMP-5179-5-23
Reducing Inventoriesthrough Setup Time Reduction
Central to JIT is the reduction of production lot sizes so that inventory levels are reduced.
Smaller lot sizes result in more machine setups
More machine setups, if they are lengthy, result in:
– Increased production costs
– Lost capacity (idle machines during setup)
The answer is: REDUCE MACHINE SETUP TIMES
Remember from Module #2?
Kenneth J. Andrews EMP-5179-5-24
Set-Up Reduction
Traditionally, we have left set-up operations to the workers. Even when employees are conscientious, they often lack the resources and authority to make significant improvements to the set-up process.
Outdated accounting practices still “drive” many organization’s thoughts regarding set-up. That is- large lot size runs in order to spread the cost of timely and costly set-up operations across many pieces, thereby reducing set-up cost per piece.
What this model of thinking results in is lengthy set-up operations that take hours or days, instead of minutes. Most set-ups can be reduced by 50-90% with a focused approach, using low-cost, no cost techniques.
The potential that reducing set-up has is difficult for most people to envision as a reality, because “that is the way we have always done it”, blinds us to the possibilities.
In order to achieve small lot production and thereby achieve significant reductions in inventory and WIP, set-up reductions must be done first.
Kenneth J. Andrews EMP-5179-5-25
Typical setup activities
– Prepare 30%
– Attach machine parts 5%
– Measure, center
15%
– Adjust 50%
Setup reduction
Kenneth J. Andrews EMP-5179-5-26
The SMED Approach
Observe (videotape) the setup– Time– Distance (spaghetti diagram)
Define internal/external elements
Separate external elements from setup
Shift as many internal elements to external as possible
Streamline internal elements
Streamline external elements
Kenneth J. Andrews EMP-5179-5-27
ElementClock Internal External 0.3 0.5 0.8 1 1.3 1.5 1.8 2 2.3 2.5 2.8 3 3.3 3.5 3.8 4 4.3 4.5 4.8 5 5.3 5.5 5.8 6 6.3 6.5 6.8
1 Find die and paperwork 7 72 Move to machine 5 123 Dissassemble 5 174 Stone rough cut 1 185 Mount angle blocks 2 206 Place die on grinder 1 217 Grind blocks 7 288 Turn die over 6 349 Indicate part 1 35
10 Clean die 1 3611 Measure pre-land 5.75 41.7512 Change wheel 1.25 4313 Look for wheel 1.25 44.2514 Load wheel 1.75 4615 Dress wheel 5.5 51.516 Position the wheel 1 52.517 Adjust stops 2.2 54.718 Position wheel 1.8 56.519 First spark 5 61.520 Stop 0.25 61.7521 Clean die 0.25 6222 Measure 1.25 63.2523 Start cutting 4.25 67.524 Measure 1 68.525 Adjust wheel travel 0.75 69.2526 Adjust stops 2 71.2527 First spark 4.75 7628 Dress wheel 1.25 77.2529 Position wheel 1.25 78.530 First spark 1 79.531 Stop and clean part 0.5 8032 Install lifting eyes 0.5 80.533 Find hoist 1.25 81.7534 Lift die 1 82.75
Time Observation Sheet
Kenneth J. Andrews EMP-5179-5-28
Set-Up Reduction
Internal Set-up- Defined as the elements or work that must be carried out while the machine or equipment is shut down or idle.
- Example of Internal Set-up Elements: - Removal and attachment of dies. - Tooling adjustments when tooling is on the machine.
External Set-Up
- Defined as set-up elements which can take place while the machine is in operation or after the operation is completed.
- Example of External Set-Up Elements: (1) Return of dies to storage. (2) Transporting of new dies to machine.
Kenneth J. Andrews EMP-5179-5-29
Set-Up Reduction: Internal External
Improving Transportation and removal of Dies and other Parts:Do as an External Activity and not when the machine is idle.
- Die storage should have a clearly marked and specific location, not simply a general shop area. Dies need to always be returned to the same location, in “production ready” condition.- Wherever possible, dies should be stored at or near the point of production use. Segregation by cell, product line or family are also possible location schemes.
Eliminate Small losses:
- Determine what preparations have to be made in advance.- Determine what tools need to be on hand- What type of work bench is required for proper organization of tools and other equipment.- Where the tools, jigs, dies, blades, cutters placed after each use
Kenneth J. Andrews EMP-5179-5-30
Pre-assemble. Do any assembly of parts attachment when the machine is running and adjust “pre-sets” also during External Time.
Eliminate “guess work” and repeated need to adjust to get correct settings of tooling, jigs, beds, etc.
Use standard and “One-Touch” Tools. “One-Touch” tools are quick fitting jigs, fixtures, that require minimal adjustment and are easily placed repeatedly and accurately for each set-up.
Simplify Clamping Mechanisms. – Reduce the number of bolts.– Use single thread bolts versus multiple thread bolts.– Replace bolts with hydraulic or cam-operated clamps.
Set-Up Reduction: Internal External
Kenneth J. Andrews EMP-5179-5-31
Set-Up Reduction: Internal External
Add parallel operations – Two people are more effective than one and the set-
up time can often be reduced by more than 50% with the same amount of labor.
Optimize the Number of Workers and the Division of Labor.– On lengthy set-ups, use more than two people.– Determine what the “optimum” number is through
analysis.– Determine how the work is to be divided to optimize
efficiency and avoid duplication of efforts. – Standardize the work and cross-train.
Kenneth J. Andrews EMP-5179-5-32
Three ways to spend money on Setup
Run large batch sizes, hold lots of inventory
Run small batch sizes with no change to the setup
Fix the setup
Kenneth J. Andrews EMP-5179-5-33
Set-Up Time & Lot Size
In a mass production environment, the most commonly recognized benefits of shorter set-up times are:– Greater machine utilization– Higher workstation efficiency– Overall factory efficiency ????
In a lean environment the greatest benefit of reduced set-up times is:– The ability to produce in smaller lots
Kenneth J. Andrews EMP-5179-5-34
Production Options with Quick Set-Up
Set-up
A
Set-up
B
Original
Set-up
A
Set-up
B
Improved
Set-up
A
Set-up
B
LargerLots
Set-upA
Set-upB
Set-upA
Set-upB
Smaller Lots
Kenneth J. Andrews EMP-5179-5-35
Impact of Small Lots on Total System Efficiency
Eliminates Over-Production
Reduces Cycle-Time
Reduces Congestion/Waiting at Machines
Supports Inventory/WIP Reduction
Less Floor-Space Requirements
Reduces Scrap
Improves Quality (“machine + man + dog”)
Improves Customer Response Time & Flexibility
Increases Worker Motivation