kendal at longwood cottages expansion project sustainable development & leed certification
TRANSCRIPT
(Leadership in Energy & Environmental
Design)
LEED is an internationally recognized green building certification system, providing third-party verification that a building or community was designed and built using strategies aimed at improving performance across the metrics that matter most: energy savings, water efficiency, CO2 emissions reduction, improved indoor environmental quality, and stewardship of resources and sensitivity to their impacts (www.USGBC.org).
What is LEED?
Leed Rating Systems
• New Construction • Existing Buildings: Operations and Maintenance
• Commercial Interiors
• Core and Shell
• Schools
• Retail
• Healthcare
• Homes
• Neighborhood Development
LEED points are awarded on a 100-point scale, and credits are weighted to reflect their potential environmental impacts
• Certified• Silver • Gold• Platinum
1. Lowering operating costs and increasing asset value. 2. Reducing waste sent to landfills. 3. Conserving energy and water. 4. Developing healthier and safer buildings for occupants. 5. Creating compact and walkable communities with good
access to neighborhood amenities and transit 6. Protecting natural resources and farmland by encouraging
growth to be located in areas with existing infrastructure. 7. Reducing greenhouse gas emissions. 8. Qualifying for tax rebates, zoning allowances, and other incentives. 9. Demonstrating an owner's commitment to environmental stewardship and social responsibility.
Environmental and Financial Benefits of LEED Certification
LEED for Homes
Anticipated Certification Summary
1 BR w/ Den (1250 sf) 79 points – GOLD
2 BR (1450 sf, 1395 sf*) 78 points – GOLD
2 BR w/ Den (1775 sf) 78.5 points – GOLD
2 BR w/ Den & Bsmt (3487 sf) 77 points – SILVER
* Small 2 BR recently added
LEED for Homes
Home Construction Costs
Typical Code Compliant Home $90 - $100 per SF
$12,378,800 Total Estimated Home Construction Cost
Kendal Cottages Project $100 - $110 per SF
$13,681,920 Total Estimated Home Construction Cost
$ 1,303,040 over a typical code compliant home
LEED for Homes
Home Construction Costs Per Unit
Typical Kendal Difference
1 BR Den $178,695 $197,505 $18,810
2 BR $215,840 $238,560 $22,720
2 BR Den $248,710 $274,890 $26,180
2 BR Den & Bsmt $431,110 $476,490 $45,380
LEED for Homes
LEED Certification Soft CostsLEED & Sustainability Consultant $96,000 $96,000
LEED Inspections & Administration Fees $62,400 $2,600 per duplex
USGBC Registration & Certification Fees $9,600 $375 per Duplex
Total LEED Certification Soft Costs $168,000
Soft Cost per cottage $3,500
LEED CATEGORY:
Energy and Atmosphere
30% Estimated Energy Reduction Strategies
Increased InsulationEnergy Star Rated Windows & AppliancesCFL & LED LightingPost Construction Performance TestingGeothermal Heat Pumps with Water Heating FeatureHigh Efficiency Water Heaters
LEED CATEGORY:
Energy and Atmosphere
HVAC System ROI Analysis (2 BR Unit)
Install Cost Operating Cost ReturnTypical Baseline Furnace $8,600 $3,630 baseline
Geothermal Heat Pump $20,656 $1,814 6.6 years
Water Heating System ROI Analysis (2 BR Unit) Install Cost Operating Cost Return
Standard Gas WH $500 $618 baselineGas WH w/ Desuperheater $750 $371 1.1 years
LEED CATEGORY:
Sustainable Sites
Site Design StrategiesNo Invasive Plants
100% Drought Tolerant Plants
Surface Water Management85% permeable surfaces2 retention & infiltration basins Multiple drainage areas seeded with native grasses & wildflowers
Nontoxic Pest ControlsPest Proof ScreensWood Protection
LEED CATEGORY:
Water Efficiency
Water Conservation
High-Efficiency Faucets, Showers, & Toilets Estimated 25% water savings (1,000 gallons per month per unit)
Showers 1.75 gallons per minuteFaucets 1.5 gallons per minuteToilets 1.20 gallons per flush
No Irrigation Required
LEED CATEGORY:
Materials and Resources
Sustainable Materials SelectionDetailed Framing Documentation
Lumber Waste Reduction
Construction Waste Reduction – 88% Diversion
Environmentally Preferable ProductsLinoleum Carpet ConcreteGypsum Board Insulation PEX PipePaint Low-VOC Materials
LEED CATEGORY:
Indoor Environmental Quality
Indoor Environmental Quality Strategies
No Combustion EquipmentHVAC System
High Performance Air FiltersDehumidification SystemKitchen Exhaust SystemPost Construction Performance Testing
Construction Features Garage Pollutant ProtectionRadon Resistant Construction
Pre-occupancy Building Flush-out
LEED CATEGORY:
Awarenessand Education
Optimizing Sustainable ElementsHomeowner EducationOperations & Maintenance Manual Operations Training
Building Manager TrainingOperations & Maintenance ManualOperations Training
LEED CATEGORY:
Innovation in Design Process
Project Strategies Beyond LEEDNative Habitat Restoration
On-Site Sewage Treatment
Green Cleaning & Housekeeping
Visitable Design (Full ADA Accessibility)
Waste Management and Recycling
Project Costs Unit CostsCredit Description Cost Notes
Innovation and Design Process (ID) 11 Points
1. Integrated Project Planning Preliminary Rating Required Soft Cost captured within consultant contracts - -
Integrated Project Team 1 Typical for projects of this size & scope. - -
Professional Credentialed with Respect to LEED for Homes 1
Design Charrette 1 Soft Cost captured within consultant contracts - -
Building Orientation for Solar Design 1
2. Durability Management Process Durability Planning Required Soft Cost captured within consultant contracts - -
Durability Management Required Soft Cost captured within Warfel scope. - -
Third-Party Durability Management Verification 3 Soft Cost captured within EAM contract. - -
3. Innovative or Regional Design 1 100k allowance for additional landscape work $100,000 $2,083
1 Existing Kendal system qualifies for credit. - -
1 Kendal - Establish any cost impact for green cleaning Kendal Kendal
1 Included in original project requirements - -
Location and Linkages (LL) 10 Points
1. LEED ND LEED for Neighborhood Development 10
2. Site Selection Site Selection 2 Parallels local regulations - -
3. Preferred Locations Edge Development 1 Credits automatically granted based on location. - -
Infill 1 - -
Previously Developed 1 - -
4. Infrastructure Existing Infrastructure 1 Credits automatically granted based on location. - -
5. Community Resources/Transit Basic Community Resources/Transit 1 Existing campus services meet requirements. - -
Extensive Community Resources/Transit 1 - -
Outstanding Community Resources/Transit 1
6. Access to Open Space Access to Open Space 1 Existing campus trails meet requirements. - -
Sustainable Sites (SS) 22 Points
1. Site Stewardship Erosion Controls During Construction Required Parallels local regulations. - -
Minimize Disturbed Area of Site 1
2. Landscaping No Invasive Plants Required Included in original project requirements - -
Basic Landscape Design 2
Limit Conventional Turf 1 to 3
Drought Tolerant Plants 1 to 2 Increase cost for meadow seed mixes vs standard $2,700 $56
Reduce Overall Irrigation Demand by at Least 20% 2 to 6
3. Local Heat Island Effects Reduce Local Heat Island Effects 1
4. Surface Water Management Permeable Lot 1 to 4 Parallels local regulations. - -
Permanent Erosion Controls 1 Parallels local regulations. - -
Management of Run-off from Roof 1 to 2 Local code requirement - -
5. Nontoxic Pest Control Pest Control Alternatives 1/2 to 2 Pest proof screens $5,100 $106
6. Compact Development Moderate Density 2
High Density 1
Very High Density 1
Construction Cost Impact
Construction Cost Impact
Innovation #1: Native Habitat Restoration/Soil Regeneration
Credit Category
Innovation #3: Green CleaningInnovation #4: Visitable Design
Innovation #2: On-Site Sewage Treatment
Water Efficiency (WE) 15
1. Water Reuse Rainwater Harvesting System 1 to 4
Graywater Reuse System 1
Use of Municipal Recycled Water System 3
2. Irrigation System High Efficiency Irrigation System 1 to 3
Third Party Inspection 1
Reduce Overall Irrigation Demand by at Least 45% 1 to 4
3. Indoor Water Use High-Efficiency Fixtures and Fittings 1 to 3
Very High-Efficiency Fixtures and Fittings 2 to 6
Energy and Atmosphere (EA) 38 Points
1. Optimize Energy Performance Performance of ENERGY STAR for Homes Required Soft cost for energy model included in EAM contract. - -
Exceptional Energy Performance 1 to 34
2. Insulation Basic Insulation Required Walls: R-13 code. R-19 installed. $15,000 $313
Enhanced Insulation 2
3. Air Infiltration Reduced Envelope Leakage Required
Greatly Reduced Envelope Leakage 2 Soft cost for testing included in EAM contract. - -
Minimal Envelope Leakage 3
4. Windows Good Windows Required
Enhanced Windows 2
Exceptional Windows 3 Installed U-factor 0.26 $48,774 $1,016
5. Heating and Cooling Distribution Reduced Distribution Losses Required Code required -
Greatly Reduced Distribution Losses 2 - -
Minimal Distribution Losses 3 -
6. Space Heating and Cooling Good HVAC Design and Installation Required Calculations covered in FX Bonnes contract. - -
High Efficiency HVAC 2 GSHP 15.8 EER, 3.9 COP $610,354 $12,716
Very High Efficiency HVAC 4
7. Water Heating Efficient Hot Water Distribution 2
Pipe Insulation 1 R-4 Insulation $54,912 $1,144
Efficient Domestic Hot Water Equipment 3 Bradford White Water Heater w/ 0.93 energy factor $5,000 $104
8. Lighting ENERGY STAR Lights Required
Improved Lighting 2 CFL Lighting package $144,000 $3,000
Advanced Lighting Package 3 LED Lighting package $71,392 $1,487
9. Appliances High Efficiency Appliances 2 Appliances - Kendal to price Kendal Kendal
Water Efficient Clothes Washer 1 Clothes Washer - Kendal to price Kendal Kendal
10. Renewable Energy Renewable Energy System 10
11. Refrigerant Charge Test Required Soft cost captured in consultant contracts. - -
Appropriate HVAC Refrigerants 1 Industry standard - -
No added cost. Credit achievement pending duct leakage testing.
Qualifying Energy Conservation Measures itemized below:
$33,000Toilets, sink faucets, and showerheads upgrades $688
Residential Refrigerant Management
Indoor Environmental Quality (EQ) 21 Points
1. ENERGY STAR with IAP ENERGY STAR with Indoor Air Package 13
Maximum Points: 13
2. Combustion Venting Basic Combustion Venting Measures Required Parallels code - -
Enhanced Combustion Venting Measures 1 to 2 No fireplaces. Granted automatically. - -3. Moisture Control Moisture Load Control 1 HVAC w/ Dehumidification $62,000 $1,292
4. Outdoor Air Ventilation Basic Outdoor Air Ventilation Required Calculations captured in FX Bonnes fee - -
Enhanced Outdoor Air Ventilation 2 Heat recovery ventilation units $96,000 $2,000
Third-Party Performance Testing 1 Soft cost built into EAM contract. - -
5. Local Exhaust Basic Local Exhaust Required Kitchen exhaust to exterior $7,400 $154
Enhanced Local Exhaust 1 Bathroom exhaust fan timer $5,000 $104
Third-Party Performance Testing 1 Soft cost built into EAM contract. - -
6. Distribution of Space Heating and Room-by-Room Load Calculations Required Calculations captured in FX Bonnes fee - -
and Cooling Return Air Flow / Room-by-Room Control 1 Calculations captured in FX Bonnes fee - -
Third-Party Performance Testing / Multiple Zones 2 Soft cost built into EAM contract. - -
7. Air Filtering Good Filters Required -
Better Filters 1 $80
Best Filters 1 MERV 16 filters $7,728 $161
8. Contaminant Control Indoor Contaminant Control during Construction 1 Captured in Warfel contracted fee - -
Indoor Contaminant Control 1 to 2 Included in original project design. - -
Preoccupancy Flush 1 Is it possible for Kendal to quantify this? Kendal Kendal
9. Radon Protection Radon-Resistant Construction in Moderate-Risk Areas Required Radon Resistant Construction $10,000 $208
Radon-Resistant Construction in High-Risk Areas 1
10. Garage Pollutant Protection No HVAC in Garage Required Mech room door system per LEED req's $48,000 $1,000
Minimize Pollutants from Garage 2 Caulk/seal all interior walls adjacent to garage. $5,000 $104
Exhaust Fan in Garage 1 Exhaust fan tied into CO sensor. $67,392 $1,404
Detached Garage or No Garage 3
Awareness and Education (AE) 3 Points
1. Education of the Homeowner or Basic Operations Training Required Soft cost built into TSP contract. - -
Tenant Enhanced Training 1 Soft cost built into TSP contract. - -
Public Awareness 1 Kendal - Is there a marketing budget number to use? - -
2. Education of Building Manager Education of Building Manager 1 Soft cost built into TSP contract. - -
MERV 10 filters $3,840