Professional Consulting and Design Services County of Kenosha 4777 88 th Ave Kenosha, WI 53144 KCDC Piping Project Phase II Bid # 2101 Date: January 20, 2021 Issued for Bid Clark Dietz: Project No. K0450050 Clark Dietz, Inc. 625 57 th Street, 6 th Floor Kenosha, WI 53140 P - 262.650.1550 PROJECT MANUAL

Upload: others

Post on 24-Oct-2021

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: KCDC Piping Project Phase II Bid # 2101

Professional Consulting and Design Services

County of Kenosha4777 88th AveKenosha, WI 53144

KCDC Piping Project Phase II Bid # 2101Date: January 20, 2021

Issued for Bid

Clark Dietz: Project No. K0450050

Clark Dietz, Inc.625 57th Street, 6th FloorKenosha, WI 53140P - 262.650.1550

PROJECT MANUAL

Page 2: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Table of Contents

Clark Dietz, Inc. 00 00 10 - 1

SECTION 00 00 10

TABLE OF CONTENTS

COUNTY OF KENOSHAKCDC PIPING PROJECT PHASE II

KENOSHA, WI

DIVISION 00 – BIDDING AND CONTRACT REQUIREMENTS

00 10 00 Table of Contents 00 10 00-1

DIVISION 01 – GENERAL REQUIREMENTS

01 10 00 Summary 01 10 00-1-301 29 76 Payment Procedures 01 29 76-1-301 30 00 Administrative Requirements 01 30 00-1-401 33 00 Submittal Procedures 01 33 00-1-601 40 00 Quality Procedures 01 40 00-1-301 42 16 Definitions 01 42 16-1-201 42 19 Reference Standards 01 42 19-1-301 50 00 Temporary Facilities and Controls 01 50 00-1-301 60 00 Product Requirements 01 60 00-1-301 70 00 Execution and Closeout Procedures 01 70 00-1-6

DIVISION 02 – DEMOLITION

02 41 19 Selective Demolition 02 41 19-1-3

DIVISION 09 – ARCHITECTURAL

09 05 11 Acoustic Panel Ceiling 09 05 11-1-5

DIVISION 23 HVAC23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 29 1-523 05 53 Identification for HVAC Piping and Equipment 23 05 53 1-423 05 93 Testing, Adjusting and Balancing for HVAC 23 05 93 1-423 08 00 Commissioning of HVAC 23 08 00 1-823 07 00 HVAC Insulation 23 07 00 1-523 21 13 Hydronic Piping 23 21 13 1-423 21 16 Hydronic Piping Specialties 23 21 16 1-423 25 00 HVAC Water Treatment 23 25 00 1-4

END OF SECTION

Page 3: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Summary

Clark Dietz, Inc. 01 10 00 - 1

SECTION 01 10 00

SUMMARY

PART 1 GENERAL

1.1 SECTION INCLUDESA. Related Documents.B. Contract Description.C. Scheduling of Work.D. Construction Schedule.E. Construction Sequence.F. Contractor's Use of Site.G. Owner Occupancy.H. Specification Conventions.

1.2 RELATED DOCUMENTS

A. Documents related to the Work include: 1. Contract Drawings2. General Provisions of the Contract including General and Supplementary Conditions3. All other Sections included herein as part of the Project Manual 4. Addendum to the Drawings and Project Manual issued during Bidding

1.3 CONTRACT DESCRIPTION

A. Work of the Project includes the following:1. Selective demolition and disposal.2. Replace existing grooved fittings and couplings with welded connections.3. Add balancing valves at existing hot water boilers.4. Alternate #1: Replace existing grooved fittings and couplings with new grooved fittings and couplings. 5. Alternate #2: Add a glycol charging station and make connection to the hot water system.6. Alternate #3: Replace existing glycol solution with 35% propylene glycol solution.

B. The Contract Documents indicate the Work of the contract and related requirements and conditions that have an impact on the Work. Related requirements and conditions that are indicated on the Contract Documents include, but are not necessarily limited to the following:1. Existing site conditions and restrictions on use of the Site.

1.4 SCHEDULING OF WORK

A. Scheduling of Work1. With the exception of work listed in this Section, the Contractor may schedule his work in any manner

he deems appropriate to complete the contract within the time allowed. The Contractor is cautioned that some of the work may have to be performed during other than normal working hours and that the Owner may revise the schedule whenever the Owner finds it necessary to maintain work progression, or to protect the Owner’s facility, or to maintain continuous, satisfactory operation of existing facilities.

2. The Contractor shall submit a Construction Progress Schedule as required in Section 01 32 16. 3. Anticipated schedule dates are listed below:

a. Construction Period: April 1, 2021 through August 31, 2021. The contractor may elect to start work anytime during this period. Once construction is started, contractor must be substantially completed within 45 calendar days.

4. The Contractor is responsible for the means and methods necessary to accomplish the work in compliance with the specified criteria. Access must be maintained for personnel and equipment to enter and maintain the facility at all times. All shutdowns must be coordinated with the Owner a

Page 4: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Summary

Clark Dietz, Inc. 01 10 00 - 2

minimum of 72 hours prior. All shutdowns must occur during low flow periods as defined by the Owner.

5. The balancing valves associated with boilers must be installed during night hours to minimize disruptions of owner’s operation. Contractor shall perform shut down, drain, installation of new balancing valves and refill overnight.

B. Coordination with Others 1. The Owner will attempt to keep the Contractor informed of changes to existing contracts and award of

subsequent contracts that may affect the Contractor. Schedules of operations for other contractors working will be made available to the Contractor upon request.

1.5 CONSTRUCTION SCHEDULE

A. The work described in this Section shall be shown in the Construction Progress Schedule specified in Section 01 32 16. All construction steps, procedures and temporary facilities shall be approved by the Owner prior to implementation by the Contractor. The monthly updates of the Schedule of Construction shall show any changes in the proposed work, including proposed shutdown work.

B. The completion schedule for this contract requires timely transmittal of contract submittals for review by the Engineer. The identification and transmittal of all submittals required for completion of the phase of work described above is the Contractor’s responsibility.

C. The Contractor shall be held responsible for all direct and indirect delays resulting from the Contractor’s failure to identify and transmit the submittals required to successfully complete the contract work within the time specified.

D. The following early submittals shall be submitted within ten days after Notice to Proceed: 1. Construction Schedule2. Health and Safety Plan

1.6 CONSTRUCTION SEQUENCE

A. To be determined

1.7 CONTRACTOR'S USE OF SITE

A. Limit use of site and premises to allow Owner occupancy.

B. Construction Operations: Construction operations to be coordinated with the Owner.

C. Time Restrictions for Performing Work: Work hours are to be coordinated with the Owner.

D. Utility Outages and Shutdown are to be coordinated with the Owner.

1.8 OWNER OCCUPANCY

A. The Owner will occupy the premises during the entire period of construction for the conduct of normal operations.

B. Cooperate with Owner to minimize conflict, and to facilitate Owner's operations.

C. Schedule the Work to accommodate Owner occupancy.

Page 5: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Summary

Clark Dietz, Inc. 01 10 00 - 3

1.9 SPECIFICATION CONVENTIONS

A. These specifications are written in imperative mood and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise. The words “shall be” are included by inference where a colon (:) is used within sentences or phrases.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION - Not Used

END OF SECTION

Page 6: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Payment Procedures

Clark Dietz, Inc. 01 29 76 - 1

SECTION 01 29 76

PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Related documents

B. Payment requests

1.2 PAYMENT REQUESTS

A. General: Except as otherwise indicated, the progress payment cycle is to be regular. Each application must be consistent with previous applications and payments. Certain applications for payment, such as the initial application, the application at substantial completion, and the final payment application involve additional requirements.1. Waivers of Lien: For each payment application, submit waivers of lien from every entity

(including Contractor) who could lawfully and possibly file a lien in excess of $1,000 arising out of the Contract, and related to work covered by the payment. Submit partial waivers for the amount requested, prior to deduction or retainage, on each item. When the application shows completion of an item, submit final or full waivers. The Owner reserves the right to designate which entities involved in the work must submit waivers.

2. Waiver Delays: Each progress payment must be submitted with Contractor's waiver for the period of construction covered by the application. At the Contractor's option, each progress payment may be submitted with waivers from the subcontractors or sub-subcontractors and suppliers for the previous period of construction covered by the previous application. The final payment application must be submitted together with or preceded by final or complete waivers from every entity involved with performance of the work covered by the payment request.

3. Waiver Forms: Submit waivers on forms, and executed in a manner, acceptable to Owner.4. Sworn Statement: Each progress payment must be submitted with a sworn statement

showing subcontractors and material suppliers and the payment status of each. Form of the sworn statement shall be subject to approval of the Owner.

B. Payment Application Times: The "date" for each progress "payment" is as indicated in Owner-Contractor Agreement or, if none is indicated therein, it is the 15th day of each month. The period of construction work covered by each payment request is period indicated in Owner-Contractor Agreement or, if none is indicated therein, it is period ending 15 days prior to date for each progress payment, and starting day following end of preceding period. Dates shall be confirmed at the preconstruction meeting.

C. Application Preparation: Except as otherwise indicated, complete every entry provided for on the form, including notarization and execution by authorized persons. Incomplete applications will be returned by Owner without action. Listing must include amounts of change orders issued prior to last day of the "period of construction" covered by application.

D. Initial Payment Application: The principal administrative actions and submittals which must precede or coincide with submittal of contractor's first payment application can be summarized as follows, but not necessarily by way of limitation:1. Schedule of Values2. Schedule of Submittals (Section 01 33 00).3. Listing of Contractor's staff assignments.4. Waiver of Lien and Sworn Statement.

Page 7: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Payment Procedures

Clark Dietz, Inc. 01 29 76 - 2

E. Monthly Payment Application: The principal administrative actions and submittals which must precede or coincide with submittal of contractor's first payment application can be summarized as follows, but not necessarily by way of limitation:1. Updated Network Diagram Schedule (Section 01 32 16).2. Revised Schedule of Submittals (Section 01 33 00), if applicable.3. Updated listing of Contractor's staff assignments, if applicable.4. Waiver of Lien, Including Subcontractor Lien Waivers, and Sworn Statement.

F. Application at Time of Final Completion: Following issuance of Owner's final "certificate of substantial completion", and also in part as applicable to prior certificates on portions of completed work as designated, a "special" payment application may be prepared and submitted by Contractor. The principal administrative actions and submittals which must proceed or coincide with such special applications can be summarized as follows, but not necessarily by way of limitation:1. Warranties (guarantees), maintenance agreements and similar provisions of contract

documents.2. Test records, maintenance instructions, start-up performance reports, and similar

change-over information germane to Owner's occupancy, use, operation and maintenance of completed work.

3. Final cleaning of the work.4. Application for reduction (if any) of retainage, and consent of surety.5. Advice to Owner on coordination of shifting insurance coverages, including proof of

extended coverages as required.6. Listing of Contractor's incomplete work, recognized as exceptions to Engineer's

certificate of substantial completion.7. Compact disc with project photos.

G. Final Payment Application: The administrative actions and submittals which must precede or coincide with submittal of contractor's final payment application can be summarized as follows, but not necessarily by way of limitation:1. Completion of project closeout requirements.2. Completion of items specified for completion beyond time of substantial completion

(regardless of whether special payment application was previously made).3. Assurance, satisfactory to Owner, that unsettled claims will be settled and that work

not actually completed and accepted will be completed without undue delay.4. Transmittal of required project construction records to Owner.5. Proof, satisfactory to Owner, taxes, fees and similar obligations of Contractor have

been paid.6. Removal of temporary facilities, services, surplus materials, rubbish and similar

elements.7. Consent of surety for final payment.

H. Application Transmittal: Submit 3 executed copies of each payment application, one copy of which is completed with waivers of lien, sworn statement and similar attachments. Transmit each copy with a transmittal form listing those attachments, and recording appropriate information related to application in a manner acceptable to Owner. Transmit to Owner by means ensuring receipt within 24 hours.

PART 2 PRODUCTS – Not Used

PART 3 EXECUTION – Not Used

END OF SECTION

Page 8: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Administrative Requirements

Clark Dietz, Inc. 01 30 00 - 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Coordinating interruptions in Owner’s operations.

B. Coordination and project conditions.

C. Special reports.

D. Preconstruction meeting.

E. Progress meetings.

F. Weekly report.

G. Cutting and patching.

H. Special procedures.

I. Cleaning and protection.

J. Conservation.

1.2 COORDINATING INTERRUPTIONS IN OWNER’S OPERATIONS

A. Show all anticipated operational interruptions of the Owner’s facilities on the progress schedule.

B. Coordinate all operational interruptions with the Owner at least 48 hours prior to commencing with the work. The Owner may require that the Contractor reschedule work as required to maintain the operation of their facilities.

C. Except as specified herein, all operations must be maintained during construction. The Contractor is responsible for all, temporary electrical, and temporary communications that are necessary to continue the Owner’s operation of their facilities.

1.3 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of various sections of Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Verify utility requirements and characteristics of operating equipment are compatible with utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, operating equipment.

C. Coordinate space requirements, supports, and installation of mechanical and electrical Work indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

Page 9: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Administrative Requirements

Clark Dietz, Inc. 01 30 00 - 2

D. In finished areas except as otherwise indicated conceal pipes within construction.

E. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion and for portions of Work designated for Owner's occupancy.

F. During Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

G. Limitations on construction area usage as well as specific requirements that impact utilization are indicated by Contract Documents. Schedule deliveries so as to minimize space and time requirements for storage of materials and equipment on construction area.

1.4 SPECIAL REPORTS

A. Accident Reports: Prepare and submit reports of significant accidents, at site and anywhere else work is in progress. Record and document data and actions. For this purpose, a significant accident is defined to include events where personal injury is sustained, or property loss of substance is sustained, or where the event posed a significant threat of loss or personal injury.

1.5 PRECONSTRUCTION MEETING

A. Engineer will schedule an initial progress meeting with the Contractor and Owner, recognized as the preconstruction meeting, after Notice of Award.

B. The preconstruction meeting will be an organizational meeting. Agenda items may include:1. Execution of Owner-Contractor Agreement.2. Submission of executed bonds and insurance certificates.3. Distribution of Contract Documents.4. Submission of list of Subcontractors, list of products, schedule of values, and progress schedule.5. Designation of personnel representing parties in Contract and Engineer.6. Procedures and processing of field decisions, submittals, substitutions, applications for payments,

proposal request, Change Orders, and Contract closeout procedures.7. Scheduling.8. Use of premises by Owner and Contractor.9. Owner's requirements.10. Survey and layout.11. Security and housekeeping procedures.12. Application for payment procedures.13. Procedures for testing.14. Procedures for maintaining record documents.15. Requirements for start-up of equipment.16. Inspection and acceptance of equipment put into service during construction period.

1.6 PROGRESS MEETINGS

A. In addition to other project meetings held for other purposes, hold a general progress meeting with the Engineer and Owner throughout progress of the Work at monthly intervals.

B. The schedule of the progress meetings will be determined during the preconstruction meeting. In general, progress meetings will be coordinated with preparation of the payment request.

C. Review each entity's present and future needs including interface requirements, time, sequences, deliveries, access, site utilization, temporary facilities and services, hours of work, hazards and risks, housekeeping, change orders, and documentation of information for payment requests. Discuss whether each element of current work is ahead of schedule, on time, or behind schedule in relation with updated progress schedule. Determine how behind-schedule work will be expedited, and secure commitments from

Page 10: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Administrative Requirements

Clark Dietz, Inc. 01 30 00 - 3

entities involved in doing so. Discuss whether schedule revisions are required to ensure that current work and subsequent work will be completed within Contract Time. Review everything of significance which could affect progress of the work.

D. Updating Schedules: Immediately following each progress meeting, where revisions to progress schedule have been made or recognized, revise and reissue progress schedule as described in Section 01 33 00.

E. Attendance Required: Job superintendent, major subcontractors and suppliers, and others as appropriate to agenda topics for each meeting.

F. Agenda:1. Review minutes of previous meetings, if applicable.2. Review of Work progress.3. Field observations, problems, and decisions.4. Identification of problems impeding planned progress.5. Review of submittals schedule and status of submittals.6. Review of off-site fabrication and delivery schedules.7. Maintenance of progress schedule.8. Corrective measures to regain projected schedules.9. Planned progress during succeeding work period.10. Coordination of projected progress.11. Maintenance of quality and work standards.12. Effect of proposed changes on progress schedule and coordination.13. Other business relating to Work.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION

3.1 SPECIAL PROCEDURES

A. Materials: As specified in product sections, match existing with new products for patching and extending work.

B. Employ skilled and experienced installers to perform work.

C. Cut, move, or remove items as necessary for access to alterations and renovation Work. Replace and restore at completion.

D. Remove unsuitable material not marked for salvage. Replace materials as specified for finished Work.

E. Remove debris and abandoned items from area and from concealed spaces.

F. Prepare surface and remove surface finishes to permit installation of new work and finishes.

G. Remove, cut, and patch Work in manner to minimize damage and to permit restoring products and finishes to original or specified condition.

H. Refinish existing visible surfaces to remain in renovated rooms and spaces, to specified condition for each material, with neat transition to adjacent finishes.

I. Patch or replace portions of existing surfaces which are damaged, lifted, discolored, or showing other imperfections.

Page 11: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Administrative Requirements

Clark Dietz, Inc. 01 30 00 - 4

J. Finish surfaces as specified in individual product sections.

3.2 CLEANING AND PROTECTION

A. General: During handling and installation of work at the project site, clean and protect work in progress and adjoining work on the basis of continuous maintenance.

B. Limiting Exposures of Work: To the extent possible through reasonable control and protection methods, supervise performance of the work in such a manner and by such means which will ensure that none of the work, whether completed or in progress, will be subjected to harmful, dangerous, damaging or otherwise deleterious exposure during the construction period. Such exposures include, where applicable, but not by way of limitation the following:1. Water or ice.2. Solvents.3. Chemicals.4. Light.5. Puncture.6. Abrasion.7. Heavy traffic.8. Misalignment.9. Excessive weathering.10. Unprotected storage.11. Improper shipping or handling.12. Theft.13. Vandalism.

3.3 CONSERVATION

A. It is a requirement for supervision and administration of the work that construction operations be carried out with the maximum possible consideration given to conservation of energy, water and materials.

END OF SECTION

Page 12: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Submittal Procedures

Clark Dietz, Inc. 01 33 00 - 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Submittal procedures.

B. Owner’s/Engineer’s Action.

C. Proposed products list.

D. Product data.

E. Shop drawings.

F. Design data.

G. Test reports.

H. Certificates.

I. Manufacturer's instructions.

J. Operation and Maintenance manuals.

K. Manufacturer's field reports.

L. Construction photographs.

1.2 SUBMITTAL PROCEDURES

A. Transmit each submittal with Engineer accepted form.

B. Sequentially number transmittal forms. Mark revised submittals with original number and sequential alphabetic suffix.

C. Identify Project, Contractor, subcontractor and supplier; pertinent drawing and detail number, and specification section number, appropriate to submittal.

D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with requirements of the Work and Contract Documents.

E. Schedule submittals to expedite Project and deliver to Engineer as directed below for electronic submittals. Coordinate submission of related items.

F. For each submittal review, allow 15 days excluding delivery time to and from Contractor. Where the submittal must be held for coordination, the Engineer will so advise the Contractor.

G. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of completed Work.

Page 13: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Submittal Procedures

Clark Dietz, Inc. 01 33 00 - 2

H. Allow space on submittals for Contractor and Engineer review stamps.

I. When revised for resubmission, identify changes made since previous submission.

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with requirements.

K. Submittals not requested will not be recognized or processed.

L. Except for samples, electronic submittals are required.

M. Electronic submittals are required to conform to all of the submittal requirements listed above.

N. Email electronic submittals to the Engineer.

O. Submit electronic documents as a single portable electronic file (.pdf). Contractor should request an exception for documents that are not sent in pdf format or are sent as multiple files. Electronic files will be rejected if they are not clearly legible.

P. Submittals delivered electronically will be returned to the Contractor as electronic files. Engineer will return: 1. Engineer’s review form and comments2. Contractor’s transmittal form3. Submittal materials only if comments on the materials are required.

1.3 OWNER’S/ENGINEER’S ACTION

A. Unless otherwise noted, the Owner/Engineer will review each submittal and mark with appropriate "Action".

B. Action Stamp: The Owner/Engineer will stamp each submittal to be returned with a uniform, self-explanatory action stamp, appropriately marked and executed to indicate whether the submittal returned is for unrestricted use, final-but-restricted use (as marked), must be revised and resubmitted (use not permitted) or without action (as explained on the transmittal form).

C. Final Unrestricted Release: Where the submittals are marked as follows, the work covered by the submittal may proceed provided it complies with the requirements of the contract documents; acceptance of the work will depend upon that compliance.1. Marking: "No Exception Taken".

D. Final-But-Restricted Release: When the submittals are marked as follows, the work covered by the submittal may proceed provided it complies with the Owner/Engineer's notations, corrections marked on the submittal, and with the requirements of the contract documents; acceptance of the work will depend on that compliance.1. Marking: "Make Corrections Noted".

E. Returned to Resubmittal: When the submittal is marked as follows, do not proceed with the work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise the submittal or prepare a new submittal in accordance with the Owner/Engineer's notations stating the reasons for returning the submittal. Repeat if necessary to obtain a different action marking. Do not permit submittals with the following marking to be used at the project site, or elsewhere where work is in progress.1. Marking:

a. "Rejected".b. "Revise and Resubmit".c. "Submit Specified Item."

Page 14: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Submittal Procedures

Clark Dietz, Inc. 01 33 00 - 3

1.4 PROPOSED PRODUCTS LIST

A. Within 15 days after date of Notice to Proceed, submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.

B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.

1.5 PRODUCT DATA

A. Information required specifically as product date includes manufacturer's standard printed recommendations for application and use, compliance with recognized standards of trade associations and testing agencies, and the application of their labels and seals (if any), special notation of dimensions which have been verified by way of field measurement, and special coordination requirements for interfacing the material, product or system with other work.

B. Collect required product data into a single submittal for each unit of work or system. Mark each copy to show which choices and options are applicable to the project. Where product data has been printed to include information on several similar products, some of which are not required for use on the project, or are not included in this submittal, mark the copies to show clearly that such information is not applicable.

C. Submit to Engineer for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents. Product data submittal is required for information and record and to determine that the products, materials and systems comply with the provisions of the contract documents. Therefore, the initial submittal is also the final submittal, except where the Engineer observes that there is non-compliance with the provisions of the contract documents and returns the submittal to the Contractor marked with the appropriate "Action".

D. Unless submitted electronically, submit number of copies Contractor requires, plus three copies Engineer will retain.

E. Identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.

F. Where product data must be specially prepared for required products, materials or systems, because standard printed data is not suitable for use, submit data as "shop drawings" and not as "product data".

G. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

H. After review, produce copies and distribute in accordance with SUBMITTAL PROCEDURES article and for record documents described in Section 01 70 00 - Execution and Closeout Requirements.

1.6 SHOP DRAWINGS

A. Shop Drawings: Submit to Engineer for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents.

B. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

C. When required by individual specification sections, provide shop drawings signed and sealed by professional engineer responsible for designing components shown on shop drawings.1. Include signed and sealed calculations to support design.2. Submit drawings and calculations in form suitable for submission to and approval by authorities

having jurisdiction.

Page 15: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Submittal Procedures

Clark Dietz, Inc. 01 33 00 - 4

D. Make revisions and provide additional information when required by authorities having jurisdiction.

E. Information required on shop drawings includes, dimensions, identification of specific products and materials which are included in the work, compliance with specified standards and notations of coordination requirements with other work. Provide special notation of dimensions that have been established by field measurement. Highlight, encircle or otherwise indicate deviations from the contract documents on the shop drawings.

F. Do not permit shop drawing copies without an appropriate final "Action" marking by the Engineer to be used in connection with the work.

G. Unless submitted electronically, submit number of opaque reproductions Contractor requires, plus three copies Engineer will retain.

H. After review, produce copies and distribute in accordance with SUBMITTAL PROCEDURES article and for record documents described in Section 01 70 00 - Execution and Closeout Requirements.

1.7 DESIGN DATA

A. Submit for Engineer's knowledge as contract administrator or for Owner.

B. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.

C. Unless submitted electronically, submit number of opaque reproductions Contractor requires, plus three copies Engineer will retain.

1.8 TEST REPORTS

A. Submit for Engineer's knowledge as contract administrator or for Owner.

B. Submit test reports for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.

C. Unless submitted electronically, submit number of opaque reproductions Contractor requires, plus three copies Engineer will retain.

1.9 CERTIFICATES

A. When specified in individual specification sections, submit certification by manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.

B. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.

D. Unless submitted electronically, submit number of opaque reproductions Contractor requires, plus three copies Engineer will retain.

1.10 MANUFACTURER'S INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Engineer for delivery to Owner in quantities specified for Product Data.

Page 16: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Submittal Procedures

Clark Dietz, Inc. 01 33 00 - 5

B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

1.11 MANUFACTURER’S OPERATION AND MAINTENANCE MANUALS

A. Obtain installation, operation, and maintenance manuals from manufacturers and suppliers for each item of equipment furnished under the Contract. Submit three copies of each complete manual to the Owner within 90 days after approval of shop drawings, product data, and samples and not later than the date of shipment of each item of equipment to the project site.

B. Manuals shall be provided for each piece of equipment including individual components and subsystems of complete assemblies. The section of the manual on operation shall describe the function of each component and its relationship to the system of which it is a part. Where several models, options, or styles are described, the manual shall identify the items actually provided.

C. The manual shall contain the following:1. An 8-1/2 x 11 inch typewritten sheet listing the manufacturer's identification, including order number,

model, and serial number and location of parts and service centers.2. A separate 8-1/2 x 11 inch typewritten list of recommended stock of parts, including part number and

quantity.3. Complete replacement parts list and drawings.4. Performance data and rating tables.5. Specific instructions for installation, operation, adjustment, and maintenance.

D. Each manual shall be bound in a folder and labeled to identify the contents and project to which it applies.

E. Operation and maintenance manuals specified herein are in addition to any operation, maintenance, or installation instructions required by the Contractor to install, test, and start up equipment.

1.12 MANUFACTURER'S FIELD REPORTS

A. Submit reports for Engineer's benefit as contract administrator or for Owner.

B. Unless submitted electronically, submit two copies of the report within 5 days of observation to Engineer for information.

C. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.

1.13 CONSTRUCTION PHOTOGRAPHS

A. Take pre-construction digital photos as evidence of existing project. The photos shall be submitted prior to working in each room.

B. With the application at time of Final Completion: Deliver compact discs with .jpg files to Owner with project record documents. Catalog and index files by room number.

1.14 SUBMITTAL SCHDULE

A. A proposed preliminary submittal schedule is attached to this Section.

B. Contractor shall submit his own Schedule of Submittals with the Initial Payment Application.

Page 17: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Submittal Procedures

Clark Dietz, Inc. 01 33 00 - 6

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION - Not Used

END OF SECTION

Page 18: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Quality Procedures

Clark Dietz, Inc. 01 40 00 - 1

SECTION 01 40 00

QUALITY REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDESA. Quality control and control of installation.B. Tolerances.C. References.D. Labeling.E. Source and quality of materials and equipment.F. Examination.G. Preparation.

1.2 QUALITY CONTROL AND CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. When manufacturers' instructions conflict with Contract Documents, request clarification from Engineer before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify field measurements are as indicated on Shop Drawings or as instructed by manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

1.3 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. When manufacturers' tolerances conflict with Contract Documents, request clarification from Engineer before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

1.4 REFERENCES

A. For products or workmanship specified by association, trade, or other consensus standards, complies with requirements of standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date for receiving bids, except where specific date is established by code.

Page 19: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Quality Procedures

Clark Dietz, Inc. 01 40 00 - 2

C. Obtain copies of standards where required by product specification sections.

D. When specified reference standards conflict with Contract Documents, request clarification from Engineer before proceeding.

E. Neither contractual relationships, duties, responsibilities of parties in Contract, nor those of Engineer shall be altered from Contract Documents by mention or inference otherwise in reference documents.

1.5 LABELING

A. Attach label from agency approved by authority having jurisdiction for products, assemblies, and systems required to be labeled by applicable code.

B. Label Information: Include manufacturer's or fabricator's identification, approved agency identification, and the following information, as applicable, on each label.1. Model number.2. Serial number.3. Performance characteristics.

1.6 SOURCE AND QUALITY OF MATERIALS AND EQUIPMENT

A. The source of materials to be used shall be in accordance with the Contract Documents and as approved by the Engineer before delivery. The approval of the source of any material shall continue as long as the material conforms to the Specifications.

B. All material not conforming to the requirements of the Specifications shall be considered as defective and shall be removed from the Work. If in place, faulty materials shall be removed by the Contractor at his expense and replaced with acceptable material unless permitted otherwise by the Owner. No defective materials which have been subsequently corrected shall be reused until approval has been given.

C. Upon failure of the Contractor to comply immediately with any order of the Engineer to remove and replace defective material, the Owner shall have authority to remove and replace defective materials, and to deduct the cost of removal and replacement from any monies due or to become due to the Contractor. Failure to reject any defective materials or work at the time of installation shall in no way prevent later rejection when such defects are discovered, nor obligate the Owner to final acceptance.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify utility services are available, of correct characteristics, and in correct locations.

Page 20: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Quality Procedures

Clark Dietz, Inc. 01 40 00 - 3

END OF SECTION

Page 21: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Definitions

Clark Dietz, Inc. 01 42 16 - 1

SECTION 01 42 16

DEFINITIONS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Description of requirements.B. Definitions.

1.2 DESCRIPTION OF REQUIREMENTS

A. This section specifies procedural and administrative requirements for compliance with governing regulations and codes and standards imposed upon the Work. These requirements include obtaining permits, licenses, inspections, releases and similar documentation, as well as payments, statements and similar requirements associated with regulations, codes and standards.1. The term "Regulations" is defined to include laws, statutes, ordinances and lawful orders issued by

governing authorities, as well as those rules, conventions and agreements within the construction industry which effectively control the performance of the Work regardless of whether they are lawfully imposed by governing authority or not.

B. Governing Regulations: Refer to General and Supplementary Conditions for requirements related to compliance with governing regulations.

1.3 DEFINITIONS

A. General Explanation: Certain terms used in contract documents are defined in this article. Definitions and explanations contained in this section are not necessarily complete but are general for the Work to the extent that they are not stated more explicitly in another element of the contract documents.

B. General Requirements: Provisions and requirements of other Division 01 sections apply to the entire work of the Contract and, where so indicated, to other elements which are included in the project.

C. Indicated: The term "indicated" is a cross-reference to graphic representations, notes or schedules on the drawings, to other paragraphs or schedules in the specifications, and to similar means of recording requirements in contract documents. Where terms such as "shown", "noted", "scheduled", and "specified" are used in lieu of "indicated", it is for the purpose of helping the reader locate the cross-reference, and no limitation of location is intended except as specifically noted.

D. Directed, Requested, etc.: Terms such as "directed", "requested", "authorized", "selected", "approved", "required", "accepted", and "permitted" mean "directed by the Owner", "requested by the Owner", and similar phrases. However, no such implied meaning will be interpreted to extend the Owner's responsibility into the Contractor's area of construction supervision.

E. Approve: Where used in conjunction with the Engineer's response to submittals, requests, applications, inquiries, reports and claims by the Contractor, the term "approved" will be held to limitations of the Engineer's responsibilities and duties as specified in General and Supplementary Conditions. In no case will the Engineer's approval be interpreted as a release of the Contractor from responsibilities to fulfill requirements of contract documents or acceptance of the Work, unless otherwise provided by requirements of the contract documents.

F. Project Site: The term "project site" means the space available to the Contractor for performance of the Work, either exclusively or in conjunction with others performing other construction as part of the project or

Page 22: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Definitions

Clark Dietz, Inc. 01 42 16 - 2

other projects. The extent of the project site is shown on the drawings and may or may not be identical with the description of the land upon which the project is to be built.

G. Furnish: The term "furnish" is used to mean "supply and deliver to the project site, ready for unloading, unpacking, assembly, installation, and similar operations."

H. Install: The term "install" is used to describe operations at project site including the actual "unloading, unpacking, assembly, erection, placing, applying, working to dimension, protecting, cleaning and similar operations."

I. Provide: The term "provide" means "to furnish and install, complete and ready for the intended use."

J. Installer: The "installer" is "the entity" (person or firm) engaged by the Contractor, its subcontractor or sub-subcontractor for performance of a particular element of construction at the project site, including installation, erection, application and similar required operations. It is a requirement that installers are experienced in the operations they are engaged to perform.

K. Testing Laboratories: A "testing laboratory" is an independent entity engaged to perform specific inspections or tests of the Work, either at the project site or elsewhere, and to report, and (if required) interpret results of those inspections or tests.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION - Not Used

END OF SECTION

Page 23: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Reference Standards

Clark Dietz, Inc. 01 42 19 - 1

SECTION 01 42 19

REFERENCE STANDARDS

PART 1 GENERAL

1.1 SECTION INCLUDESA. Description of requirements.B. Specification format and content explanation.C. Drawing symbols.D. Industry standards.E. Governing regulations/authorities.

1.2 DESCRIPTION OF REQUIREMENTS

A. This section specifies procedural and administrative requirements for compliance with governing regulations and codes and standards imposed upon the Work. These requirements include obtaining permits, licenses, inspections, releases and similar documentation, as well as payments, statements and similar requirements associated with regulations, codes and standards.1. The term "Regulations" is defined to include laws, statutes, ordinances and lawful orders issued by

governing authorities, as well as those rules, conventions and agreements within the construction industry which effectively control the performance of the Work regardless of whether they are lawfully imposed by governing authority or not.

B. Governing Regulations: Refer to General and Supplementary Conditions for requirements related to compliance with governing regulations.

1.3 SPECIFICATION FORMAT AND CONTENT EXPLANATION

A. General: This article is provided to help the user of these specifications more readily understand the format, language, implied requirements and similar conventions of content. None of the following explanations shall be interpreted to modify the substance of contract requirements.1. Production Methods: Portions of these specifications have been produced by editing master

specifications and the standard specifications covenants applicable to construction; they may contain minor deviations from traditional writing formats. Such deviations are a natural result of this production technique, and no other meaning shall be implied.

B. Specification Format: These specifications are organized based upon the Construction Specifications Institute's 48-Division format. The organization of these specifications into Divisions, Sections or Trade Headings conforms generally to recognized industry practice.

C. Specification Content: This project specification has been produced employing certain conventions in the use of language as well as conventions regarding the intended meaning of certain terms, words, and phrases when used in particular situations or circumstances. These conventions are explained as follows:1. In certain circumstances, language used in specifications and other contract documents is of the

abbreviated type. Implied words and meanings will be appropriately interpreted. Singular words will be interpreted as plural and plural words will be interpreted as singular where applicable and where the full context of the contract documents so indicates.

2. Imperative Language is used generally in the specifications. Requirements expressed imperatively are to be performed by the Contractor. At certain locations in the text, for clarity, contrasting subjective language is used to describe responsibilities which must be fulfilled indirectly by the Contractor, or by others when so noted.

D. Methods of Specifying: Techniques or methods of specifying requirements vary throughout the text. The method used for specifying one element of the Work has no bearing on requirements for another element of the Work.

Page 24: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Reference Standards

Clark Dietz, Inc. 01 42 19 - 2

E. Assignment of Specialists: In certain circumstances, the specification requires or implies that specific elements of the Work are to be assigned to specialists who must be engaged to perform that element of the Work. Such assignments are special requirements over which the Contractor has no choice or option. They are intended to establish which party or entity involved in a specific element of the Work is considered as being sufficiently experienced in the indicated construction processes or operations to be recognized as "expert" in those processes or operations. Nevertheless, the ultimate responsibility for fulfilling all contract requirements remains with the Contractor.1. These requirements should not be interpreted to conflict with the enforcement of building codes and

similar regulations governing the Work. They are also not intended to interfere with local trade union jurisdictional settlements and similar conventions.

F. Trades: The use of certain titles such as "carpentry" in the specification, is not intended to imply that the Work must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter". It also is not intended to imply that the requirements specified apply exclusively to tradespersons of that corresponding generic name.

1.4 DRAWING SYMBOLS

A. General: Except as otherwise indicated, graphic symbols used on the drawings are those symbols recognized in the construction industry for purposes indicated. Where not otherwise noted, symbols are defined by "Architectural Graphic Standards", published by John Wiley & Sons, Inc., seventh edition.

1.5 INDUSTRY STANDARDS

A. Applicability of Standards: Except where more explicit or stringent requirements are written into the contract documents, applicable construction industry standards have the same force and effect as if bound into or copied directly into the contract documents. Such industry standards are made a part of the contract documents by reference. Individual specification sections indicate which codes and standards the Contractor must keep available at the project site for reference.1. Referenced standards (standards referenced directly in the contract documents) take precedence

over standards that are not referenced but generally recognized in the industry for applicability to the Work.

2. Unreferenced Standards: Except as otherwise limited by the contract documents, standards not referenced but recognized in the construction industry as having direct applicability will be enforced for performance of the Work. The decision as to whether an industry code or standard is applicable, or as to which of several standards are applicable, is the sole responsibility of the Engineer.

B. Publication Dates: Except as otherwise indicated, where compliance with an industry standard is required, comply with standard in effect as of date of contract documents.1. Updated Standards: At the request of the Engineer, Contractor or governing authority, submit a

change order proposal where an applicable industry code or standard has been revised and reissued after the date of the contract documents and before the performance of the Work affected. The Engineer will decide whether to issue a change order to proceed with the updated standard.

C. Conflicting Requirements: Where compliance with two or more standards is specified, and where these standards establish different or conflicting requirements for minimum quantities or quality levels, the most stringent requirement will be enforced, unless the contract documents specifically indicate otherwise. Refer requirements that are different, but apparently equal, and uncertainties as to which quality level is more stringent to the Engineer for a decision before proceeding.1. Minimum Quantities or Quality Levels: In every instance the quantity or quality level shown or

specified is intended to be the minimum to be provided or performed. Unless otherwise indicated, the actual Work may either comply exactly, within specified tolerances, with the minimum quantity or quality specified, or may exceed that minimum within reasonable limits. In complying with these requirements, the indicated numeric values are minimum or maximum values, as noted, or as appropriate for the context of the requirements. Refer instances of uncertainty to the Engineer for decision before proceeding.

D. Copies of Standards: The contract documents require that each entity performing work be experienced in that part of the Work being performed. Each entity is also required to be familiar with industry standards

Page 25: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Reference Standards

Clark Dietz, Inc. 01 42 19 - 3

applicable to that part of the Work. Copies of applicable standards are not bound with the contract documents.1. Where copies of standards are needed for proper performance of the Work, the Contractor is

required to obtain such copies directly from the publication source.2. Although copies of standards needed for enforcement of requirements may be required submittals,

the Engineer reserves the right to require the Contractor to submit additional copies as necessary for enforcement of requirements.

E. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. The following acronyms or abbreviations as referenced in contract documents are defined to mean the associated names. Both names and addresses are subject to change, and are believed to be, but are not assured to be, accurate and up-to-date as of date of contract documents:1. ANSI - American National Standards Institute, 1430 Broadway, New York, NY 10018, (212)

354-33002. ASTM - ASTM, 655 Fifteenth Street NW, Washington, DC 20005, (202) 639-40253. AWS - American Welding Society, P.O. Box 351040, 550 Le Jeune Road NW, Miami, FL 33135,

(305) 443-9353

F. Federal Government Agencies: Names and titles of federal government standard or specification producing agencies are frequently abbreviated. The following acronyms or abbreviations as referenced in the contract documents indicate names of standard or specification producing agencies of the federal government. Names and addresses are subject to change but are believed to be, but are not assured to be, accurate and up-to-date as of the date of the contract documents.1. EPA - Environmental Protection Agency, 401 M Street SW, Washington, DC 20460, (202) 829-35352. OSHA - Occupational Safety and Health Administration (U.S. Department of Labor), Government

Printing Office, Washington, DC 20402, (202) 783-3238

1.6 GOVERNING REGULATIONS/AUTHORITIES

A. General: The procedure followed has been to contact governing authorities where necessary to obtain information needed for the purpose of preparing contract documents; recognizing that such information may or may not be of significance in relation to the Contractor's responsibilities for performing the Work. Contact governing authorities directly for necessary information and decisions having a bearing on performance of the Work.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION - Not Used

END OF SECTION

Page 26: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Temporary Facilities and Controls

Clark Dietz, Inc. 01 50 00 - 1

SECTION 01 50 00

TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.1 SECTION INCLUDESA. Temporary Utilities:

1. Temporary electricity.B. Construction Facilities:

1. Vehicular access, Parking, and Paved Area Use.2. Progress cleaning and waste removal.

C. Temporary Controls:1. Barriers.2. Security.

D. Construction Aids:1. Temporary runways, scaffolding, and ladders.2. Welding

E. Removal of utilities, facilities, and controls.

1.2 TEMPORARY ELECTRICITY

A. Owner will pay cost of energy used. Exercise measures to conserve energy. Utilize Owner’s existing power service.

B. Do not disrupt Owner's use of service.

C. Complement existing power service capacity and characteristics as required for construction operations.

D. If temporary wiring interferes with construction or the Owner’s operation of the facility, it shall be relocated.

E. Permanent convenience receptacles may be utilized during construction.

F. When temporary service is no longer needed, remove all temporary electrical facilities from the site.

1.3 TEMPORARY SANITARY FACILITIES

A. Specific existing restroom facilities shall be designated for Contractor use. If the owner deems that this privilege has been abused, the Contractor shall provide enough chemical toilets to conveniently serve the needs of all Contractor personnel.

B. Chemical toilets and their maintenance shall meet the requirements of State and local health regulations and ordinances. Any facilities or maintenance methods failing to meet these requirements shall be corrected immediately.

C. At end of construction, return existing facilities used for construction operations to same or better condition as original condition.

1.4 VEHICULAR ACCESS, PARKING, AND PAVED AREA USE

A. Use designated existing on-site roads for construction traffic.

B. Use of designated existing on-site streets and driveways used for construction traffic and parking is permitted. Tracked vehicles not allowed on paved areas.

Page 27: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Temporary Facilities and Controls

Clark Dietz, Inc. 01 50 00 - 2

C. Do not allow heavy vehicles or construction equipment in parking areas.

D. Maintenance:1. Maintain traffic and parking areas in sound condition free of excavated material, construction

equipment, products, mud, snow, and ice.

1.5 PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing spaces.

C. Broom and vacuum clean interior areas prior to start of surface finishing and continue cleaning to eliminate dust.

D. Collect and remove waste materials, debris, and rubbish from site as needed and dispose off-site.

1.6 SECURITY

A. Security Program:1. Protect Work from theft, vandalism, and unauthorized entry.2. Initiate program in coordination with Owner's existing security system at project mobilization.3. Maintain program throughout construction period until Owner acceptance precludes need for

Contractor security.4. Contractor shall be responsible for providing background checks and/or any other initial personnel

processing to perform work at KCDC.5. Contractor shall comply with all personnel ingress/egress requirements, as well as all equipment/tool

tracking requirements. Extra time and effort associated with complying with these requirements shall be included in the Contractor’s bid.

1.7 TEMPORARY RUNWAYS, SCAFFOLDING, AND LADDERS

A. Provide temporary ladders, ramps, and runways as required for performance and inspection of the work. The above facilities shall be constructed and maintained in accordance with the applicable Federal, State, and Municipal regulations and codes.

B. Furnish, erect, and maintain all scaffolding required for this work. Scaffolding shall be constructed and maintained in accordance with applicable State and Federal laws and local ordinances. Scaffolding shall be promptly removed after serving its purpose.

C. The structural strength and safety of scaffolding, runways, covers, railings, ladders, stairs, etc., and compliance with law shall be the sole responsibility of the Contractor.

1.8 WELDING

A. Provide all welding equipment and welding provisions needed to complete work.

B. Contractor shall provide electrician to support welding work.

1.9 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Substantial Completion or as soon as the Engineer deems permissible.

B. Clean and repair damage caused by installation or use of temporary work.

Page 28: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Temporary Facilities and Controls

Clark Dietz, Inc. 01 50 00 - 3

C. Restore existing and permanent facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

D. Surfacing and sub-base material used for temporary road and parking areas shall be removed, unless otherwise directed by the Engineer.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION - Not Used

END OF SECTION

Page 29: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Product Requirements

Clark Dietz, Inc. 01 60 00 - 1

SECTION 01 60 00

PRODUCT REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDESA. Products.B. Product delivery requirements.C. Product storage and handling requirements.D. Product options.E. Product substitution procedures.F. Equipment electrical characteristics and components.

1.2 PRODUCTS

A. Furnish products of qualified manufacturers suitable for intended use. Furnish products of each type by single manufacturer unless specified otherwise.

B. Do not use materials and equipment removed from existing premises, except as specifically permitted by Contract Documents.

C. Furnish interchangeable components from same manufacturer for components being replaced.

1.3 PRODUCT DELIVERY REQUIREMENTS

A. Manufactured materials and products shall be delivered as needed for installation.

B. Transport and handle products in accordance with manufacturer's instructions.

C. Promptly inspect shipments to ensure products comply with requirements, quantities are correct, and products are undamaged, in original packages, containers, or bundles, as packaged by the manufacturer with manufacturer's name, brand, seals, and labels intact.

D. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage.

E. Materials other than those designated within the Specifications or approved by the Owner shall not be delivered to the project site.

1.4 PRODUCT STORAGE AND HANDLING REQUIREMENTS

A. Store, protect, and preserve products in accordance with manufacturers' instructions. Store all materials in a manner to facilitate inspection and to prevent damage, contamination, or intermixing.

B. Repair any damage resulting from improper storage procedures, including damage caused by condensation or the elements. If products cannot be repaired to the specified condition as determined by the Engineer, Contractor shall replace them at no additional cost.

C. Contractor shall properly coordinate delivery of equipment/materials to limit to the maximum extent possible storage time on site.

D. Store with seals and labels intact and legible.

Page 30: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Product Requirements

Clark Dietz, Inc. 01 60 00 - 2

E. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to product.

F. For exterior storage of fabricated products, place on sloped supports above ground.

G. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

H. Store loose granular materials on solid flat surfaces in well-drained area. Prevent mixing with foreign matter.

I. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

J. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.

1.5 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description, subject to the review of product data and concurrence by the Owner as specified in Section 01 33 00.

B. Products Specified by Naming One or More Manufacturers: Products of one of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with Provision for Substitutions: Submit request for substitution for any manufacturer not named in accordance with the following article. Substitutions are subject to concurrence by the Owner as specified in Section 01 33 00.

1.6 PRODUCT SUBSTITUTION PROCEDURES

A. Engineer will consider requests for Substitutions only within 15 days after date of Owner-Contractor Agreement.

B. Substitutions may be considered when a product becomes unavailable through no fault of Contractor.

C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.

D. A request constitutes a representation that Contractor:1. Has investigated proposed product and determined that it meets or exceeds quality level of specified

product.2. Will provide same warranty for Substitution as for specified product.3. Will coordinate installation and make changes to other Work which may be required for the Work to be

complete with no additional cost to Owner.4. Waives claims for additional costs or time extension which may subsequently become apparent.5. Will reimburse Owner for review or redesign services associated with re-approval by authorities having

jurisdiction.

E. Substitutions will not be considered when they are indicated or implied on Shop Drawing or Product Data submittals, without separate written request, or when acceptance will require revision to Contract Documents.

F. Substitution Submittal Procedure:

Page 31: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Product Requirements

Clark Dietz, Inc. 01 60 00 - 3

1. Submit request for Substitution for consideration in accordance with the requirements of Section 01 33 00. Limit each request to one proposed Substitution.

2. Submit Shop Drawings, Product Data, and certified test results attesting to proposed product equivalence. Burden of proof is on proposer.

3. Engineer will notify Contractor in writing of decision to accept or reject request.

PART 2 PRODUCTS – Not Used

PART 3 EXECUTION - Not Used

END OF SECTION

Page 32: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Execution and Closeout Requirements

Clark Dietz, Inc. 01 70 00 - 1

SECTION 01 70 00

EXECUTION AND CLOSEOUT REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Description of requirements.

B. Prerequisites to substantial completion.

C. Prerequisites to final completion.

D. Final cleaning.

E. Starting of systems.

F. Protecting installed construction.

G. Project record documents.

H. Operation and maintenance data.

I. Manual for equipment and systems.

J. Spare parts and maintenance products.

1.2 DESCRIPTION OF REQUIREMENTS

A. Project closeout is the term used to describe certain collective project requirements, indicating completion of the Work that is to be fulfilled near the end of the Contract time in preparation for final acceptance and occupancy of the Work by the Owner, as well as final payment to the Contractor and the normal termination of the Contract.

B. Specific requirements for individual units of work are included in the appropriate sections.

C. Time of closeout is directly related to "Final Completion"; therefore, the time of closeout may be either a single time period for the entire Work or a series of time periods for individual elements of the Work that have been certified as substantially complete at different dates. This time variation, if any, shall be applicable to the other provisions of this section.

1.3 PREREQUISITES TO SUBSTANTIAL COMPLETION

A. General: Complete the following before requesting the Engineer's inspection for certification of substantial completion, either for the entire Work or for portions of the Work. List known exceptions in the request.1. In the progress payment request that coincides with, or is the first request following, the date

substantial completion is claimed, show either 100% completion for the portion of the Work claimed as "substantially complete", or list incomplete items, the value of incomplete work, and reasons for the Work being incomplete. Include supporting documentation for completion as indicated in these contract documents.

2. Submit a statement showing an accounting of changes to the Contract Sum.3. Submit specific warranties, workmanship/maintenance bonds, final certifications and similar

documents.

Page 33: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Execution and Closeout Requirements

Clark Dietz, Inc. 01 70 00 - 2

4. Obtain and submit releases enabling the Owner's full, unrestricted use of the Work.5. Submit record drawings, maintenance manuals, damage or settlement survey, and similar final record

information.6. Discontinue and remove temporary facilities and services from the project site, along with construction

tools and facilities.

B. Inspection Procedures: Upon receipt of the Contractor's Request for Substantial Completion, the Engineer will either proceed with inspection or advise the Contractor of unfilled prerequisites.1. Following the initial inspection, the Engineer will either prepare the certificate of substantial

completion or will advise the Contractor of work which must be performed before the certificate will be issued. The Engineer will repeat the inspection when requested and when assured that the Work has been substantially completed.

2. Results of the completed inspection will form the initial "punch-list" for final acceptance.

1.4 PREREQUISITES TO FINAL ACCEPTANCE

A. General: After the “punch-list” items have been completed the Contractor may request the Engineer's final inspection (Request for Final Completion) for certification of final completion, and final payment as required by the General Conditions. List known exceptions, if any, in the request.1. Submit executed Request for Final Completion with executed “punch-list”.2. Submit the final payment request with final releases and supporting documentation not previously

submitted and accepted. Include certificates of insurance for products and completed operations where required.

3. Submit an updated final statement, accounting for final additional changes to the Contract Sum.4. Submit a certified copy of the Engineer's final punch-list of itemized work to be completed or

corrected, stating that each item has been completed or otherwise resolved for acceptance and has been endorsed and dated by the Engineer.

5. Submit consent of surety.6. Submit a final liquidated damages settlement statement, acceptable to the Owner.

B. Re-inspection Procedure: The Engineer will re-inspect the Work upon receipt of the Contractor's notice that the work, including punch-list items resulting from earlier inspections, has been completed, except for these items whose completion has been delayed because of circumstances that are acceptable to the Engineer.1. Upon completion of re-inspection, the Engineer will either prepare a certificate of final completion or

will advise the Contractor of work that is incomplete or of obligations that have not been fulfilled but are required for final acceptance.

2. If necessary, the re-inspection procedure will be repeated.

1.5 FINAL CLEANING

A. Execute final cleaning prior to final project assessment.

B. Except as otherwise indicated or requested by the Engineer, remove temporary protection devices and facilities which were installed during the course of the Work to protect previously completed Work during the remainder of the construction period.

C. Clean equipment and fixtures to sanitary condition with cleaning materials appropriate to surface and material being cleaned.

D. Clean filters of operating equipment.

E. Clean site; sweep paved areas, rake clean landscaped surfaces.

F. Remove waste and surplus materials, rubbish, and construction facilities from site. Comply with safety standards and governing regulations for cleaning operations. Do not burn waste materials at the site. Do

Page 34: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Execution and Closeout Requirements

Clark Dietz, Inc. 01 70 00 - 3

not bury debris or excess materials on the Owner's property. Remove waste materials from the site and dispose of in a lawful manner.

1.6 STARTING OF SYSTEMS

A. Coordinate schedule for start-up of various equipment and systems with Manufacture’s Representative.

B. Notify Engineer seven days prior to start-up of each item.

C. Verify each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage.

D. Verify tests, meter readings, and specified electrical characteristics agree with those required by equipment or system manufacturer.

E. Verify wiring and support components for equipment are complete and tested.

F. Execute start-up under supervision of applicable manufacturer's representative and Contractors' personnel in accordance with manufacturers' instructions.

G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.

H. Submit a written report in accordance with Section 01 33 00 - Submittal Procedures that equipment or system has been properly installed and is functioning correctly.

1.7 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.

F. Prohibit traffic from landscaped areas.

1.8 PROJECT RECORD DOCUMENTS

A. Maintain on site one set of the following record documents; record actual revisions to the Work:1. Drawings.2. Specifications.3. Addenda.4. Change Orders and other modifications to the Contract.5. Reviewed Shop Drawings, Product Data, and Samples.6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

Page 35: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Execution and Closeout Requirements

Clark Dietz, Inc. 01 70 00 - 4

C. Store record documents separate from documents used for construction. Protect from deterioration and loss in a secure, fire-resistive location.

D. Provide access to record documents for Owner and Engineer reference during normal working hours.

E. Record information concurrent with construction progress, not less than weekly. All record documents must be kept up to date on a continuous basis by all contractors and subcontractors. Failure to do so will result in withholding additional money from monthly payment requests.

F. Record Specifications: 1. Maintain one complete copy of the Project Manual, including specifications and addenda, and one

copy of other written construction documents such as change orders and similar modifications issued in printed form during construction.

2. Legibly mark and record at each product section description of actual products installed, including the following:a. Manufacturer's name and product model and number.b. Product substitutions or alternates utilized.c. Changes made by Addenda and modifications.

G. Record Drawings and Shop Drawings: 1. Legibly mark each item to record actual construction including:

a. Measured depths of foundations in relation to finish [first] [main] floor datum.b. Measured horizontal and vertical locations of underground utilities and appurtenances,

referenced to permanent surface improvements.c. Measured locations of internal utilities and appurtenances concealed in construction, referenced

to visible and accessible features of the Work.d. Field changes of dimension and detail.e. Details not on original Contract drawings.

2. Mark whichever drawing is most capable of showing the actual "field" condition fully and accurately; however, where shop drawings are used for mark-up, record a cross-reference at the corresponding location on the working drawings.a. Mark record sets with red erasable pencil and, where feasible, use other colors to distinguish

between variations in separate categories of work.b. Mark-up new information which is known to be important to the Owner and Engineer but was not

shown on either contract drawings or shop drawings.c. Note related change-order numbers where applicable.d. Organize record drawing sheets into manageable sets, bind with durable paper cover sheets, and

print suitable titles, dates and other identification on the cover of each set.e. For buried piping, electrical, conduits, etc. measure distance to permanent exposed

improvements that will enable locations to be determined after backfilling. Provide two measurements for all bends, fittings, etc.

H. Record Product Data: Maintain one copy of each product data submittal. Mark these documents to show significant variations in the actual Work performed in comparison with the submitted information. Include both variations in the products as delivered to the site, and variations from the manufacturer's instructions and recommendations for installation. Give particular attention to concealed products and portions of the Work which cannot otherwise be readily discerned at a later date by direct observation. Note related change orders and mark-up of record drawings and specifications.1. Upon Completion of mark-up, submit complete set of record product data to the Engineer for the

Owner's records.

I. Miscellaneous Record Submittals: Refer to other sections of these specifications for requirements of miscellaneous record-keeping and submittals in connection with the actual performance of the Work. Immediately prior to the date or dates of substantial completion, complete miscellaneous records and place in good order, properly identified and bound or filed, ready for continued use and reference. Submit to the Engineer for the Owner's records.

Page 36: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Execution and Closeout Requirements

Clark Dietz, Inc. 01 70 00 - 5

J. Submit documents to Engineer with claim for final Application for Payment.

1.9 OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8-1/2 x 11-inch text pages, three D side ring binders with durable covers.

B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.

C. Internally subdivide binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.

D. Submit two sets of revised final volumes in final form within 10 days after final inspection.

E. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages.

F. Contents: Prepare Table of Contents for each volume, with each product or system description identified, typed on white paper, in three parts as follows:1. Part 1: Directory, listing names, addresses, and telephone numbers of Engineer, Contractor,

Subcontractors, and major equipment suppliers.2. Part 2: Operation and maintenance instructions, arranged by system and subdivided by specification

section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following:a. Significant design criteria.b. List of equipment.c. Parts list for each component.d. Operating instructions.e. Maintenance instructions for equipment and systems.f. Maintenance instructions for [special] finishes, including recommended cleaning methods and

materials, and special precautions identifying detrimental agents.3. Part 3: Project documents and certificates, including the following:

a. Shop drawings and product data.b. Certificates.c. Originals of warranties and bonds.

1.10 MANUAL FOR EQUIPMENT AND SYSTEMS

A. For equipment, or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance.

B. Submit one copy of completed volume15 days prior to final inspection. Draft copy be reviewed and returned, with Engineer comments. Revise content of document sets as required prior to final submission.

C. Submit two sets of revised final volumes in final form within 10 days after final inspection.

D. Each Item of Equipment and Each System: Include description of unit or system, and component parts. Identify function, normal operating characteristics, and limiting conditions. Include performance curves, with engineering data and tests, and complete nomenclature and model number of replaceable parts.

E. Include manufacturer's printed operation and maintenance instructions.

F. Additional Requirements: As specified in individual product specification sections.

G. Include listing in Table of Contents for design data, with tabbed dividers and space for insertion of data.

Page 37: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Execution and Closeout Requirements

Clark Dietz, Inc. 01 70 00 - 6

1.11 SPARE PARTS AND MAINTENANCE PRODUCTS

A. Furnish spare parts, maintenance, and extra products in quantities specified in individual specification sections.

B. Deliver to Project site and place in location as directed by Owner; obtain receipt prior to final payment.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION - Not Used

END OF SECTION

Page 38: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Selective Demolition

Clark Dietz, Inc. 02 41 19 - 1

SECTION 024119

SELECTIVE DEMOLITION

PART 1 GENERAL

1.1 SECTION INCLUDESA. Preparation.B. Examination.C. Equipment Removal.D. Salvage Requirements.E. Demolition.

1.2 CLOSEOUT SUBMITTALS

A. Project Record Documents: Accurately record actual locations of capped utilities, concealed utilities discovered during demolition, and subsurface obstructions.

1.3 QUALITY ASSURANCE

A. Conform to applicable code for demolition work, dust control, products requiring electrical disconnection and re-connection.

B. Conform to applicable code for procedures when hazardous or contaminated materials are discovered.

C. Obtain required permits from authorities having jurisdiction.

1.4 SCHEDULING

A. Cooperate with Owner in scheduling noisy operations and waste removal that may impact Owners operation and adjoining spaces.

B. Coordinate with the Owner any building service interruptions.

1. Do not disable or disrupt building fire or life safety systems without three calendar days prior written notice to Owner.

2. Schedule tie-ins to existing systems to minimize disruption.3. Coordinate Work to ensure fire alarms, smoke detectors, emergency lighting, exit

signs and other life safety systems remain in full operation in occupied areas.

1.5 PROJECT CONDITIONS

A. Conduct demolition to minimize interference with adjacent building areas.

B. Cease operations immediately if structure appears to be in danger and notify Engineer. Do not resume operations until directed.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 PREPARATION

Page 39: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Selective Demolition

Clark Dietz, Inc. 02 41 19 - 2

A. Mark location and termination of utilities.

B. Erect, and maintain temporary barriers and security devices at locations indicated, including warning signs and lights, and similar measures, for protection of the Owner and existing improvements indicated to remain.

C. Erect and maintain temporary partitions to prevent spread of dust, odors, and noise to permit continued Owner occupancy, where necessary.

D. Prevent movement of structure; provide temporary bracing and shoring as required to ensure safety of existing structure.

E. Provide appropriate temporary signage including signage for exit or building egress.

F. Do not close or obstruct building egress path.

3.2 EXAMINATION

A. Examine existing equipment and structures indicated to be demolished before demolition.

B. Determine where removals may result in structural deficiency or unplanned building collapse during demolition. Coordinate demolition sequence and procedures to prevent structures from becoming unstable.

C. Determine where demolition may affect structural integrity or weather resistance of adjacent buildings or structures indicated to remain.

1. Identify measures required to protect adjacent buildings and structures from damage.

2. Identify remedial work including patching, repairing, bracing, and other work required to leave buildings and structures indicated to remain in structurally sound and weathertight and watertight condition.

3.3 EQUIPMENT REMOVAL

A. Piping, fittings, and accessories to be replaced as shown on the Contract Drawings shall be removed by the Contractor.

B. The piping, fittings, and accessories shall be removed from the site by the Contractor at his own expense. The equipment shall be removed from the site within seven (7) days of removing it from the building.

3.4 SALVAGE REQUIREMENTS

A. Coordinate with Owner/Engineer to identify equipment required to be removed and delivered to Owner.

B. Tag components and equipment Owner designates for salvage. Identification tags shall remain intact on all removed equipment and identify the date and location from which the salvaged item was removed.

C. Protect designated salvage items from demolition operations until items can be removed.

D. Remove materials to be re-installed or retained in manner to prevent damage. Store and protect in accordance with requirements of Section 01 60 00.

Page 40: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Selective Demolition

Clark Dietz, Inc. 02 41 19 - 3

E. Carefully remove building components and equipment indicated to be salvaged.

F. Package small and loose parts to avoid loss.

G. Mark equipment and packaged parts to permit identification and consolidation of components of each salvaged item.

H. Prepare assembly instructions consistent with disassembled parts. Package assembly instructions in protective envelope and securely attach to each salvaged item.

3.5 DEMOLITION

A. Contractor is not allowed to bring a dumpster to the site. At the end of working day, all removed items shall be hauled away and disposed of at the contractor expense.

B. Maintain protected egress from and access to adjacent existing buildings at all times.

C. Do not close or obstruct roadways or sidewalks without Owner approval.

D. Cease operations immediately if structure appears to be in danger and notify Engineer.

E. Disconnect and remove designated utilities within demolition areas.

F. Cap and identify abandoned utilities at termination points when utility is not completely removed. Annotate Record Drawings indicating location and type of service for capped utilities remaining after demolition.

G. Demolish in orderly and careful manner. Protect existing improvements and supporting structural members.

H. Remove demolished materials from site except where specifically noted otherwise. Do not burn or bury materials on site.

I. Remove materials as Work progresses. Upon completion of Work, leave areas in clean condition.

J. The owner may choose to allow storage of removed materials in mechanical room if space is available.

K. Conduct demolition to minimize interference with adjacent building areas.

L. Project site does not allow contractor to bring a dumpster onsite.

M. At the end of working day, contractor must haul away and dispose all removed materials at the contractor expense. The owner may choose to allow storage of removed materials in mechanical room if space is available.

END OF SECTION

Page 41: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Acoustic Panel Ceiling

Clark Dietz, Inc. 09 05 11 - 1

SECTION 09 05 11

ACOUSTICAL PANEL CEILING

PART 1 - GENERAL

1.01 SUMMARY

A. This Section includes replacement of acoustical ceiling panels and exposed suspension system, as necessitated by removal of existing ceilings and installation of new HVAC and electrical.

1.02 SUBMITTALS

A. Product Data: For each type of product specified.

B. Product Test Reports: Indicate compliance of acoustical panel ceilings and components with requirements based on comprehensive testing of current products.

1.03 QUALITY ASSURANCE

A. Installer Qualifications: Engage an experienced installer who has completed acoustical panel ceilings similar in material, design, and extent to that indicated for this Project and with a record of successful in-service performance.

B. Source Limitations for Ceiling Units: Obtain each acoustical ceiling panel from one source with resources to provide products of consistent quality in appearance and physical properties without delaying the Work.

C. Fire-Test-Response Characteristics: Provide acoustical panel ceilings that comply with the following requirements:

1. Surface-burning characteristics of acoustical panels comply with ASTM E 1264 for Class A materials as determined by testing identical products per ASTM E 84.

2. Fire-resistance-rated assemblies, which are indicated by design designations from UL's "Fire Resistance Directory," from ITS/Warnock Hersey's "Directory of Listed Products," or from the listings of another testing and inspecting agency, are identical in materials and construction to those tested per ASTM E 119.

3. Products are identified with appropriate markings of applicable testing and inspecting agency.

1.04 DELIVERY, STORAGE, AND HANDLING

A. Deliver acoustical panels to Project site in original, unopened packages and store them in a fully enclosed space where they will be protected against damage from moisture, direct sunlight, surface contamination, and other causes.

B. Before installing acoustical panels, permit them to reach room temperature and a stabilized moisture content.

C. Handle acoustical panels carefully to avoid chipping edges or damaging units in any way.

1.05 PROJECT CONDITIONS

A. Environmental Limitations: Do not install acoustical panel ceilings until spaces are enclosed and weatherproof, wet-work in spaces is complete and dry, work above ceilings is complete, and ambient temperature and humidity conditions are maintained at the levels indicated for Project when occupied for its intended use.

1.06 COORDINATION

A. Coordinate installation of acoustical panels and any necessary suspension system with other construction that adjoins or penetrates ceiling.

1.07 EXTRA MATERIALS

Page 42: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Acoustic Panel Ceiling

Clark Dietz, Inc. 09 05 11 - 2

A. Furnish extra materials described below that match products installed, are packaged with protective covering for storage, and are identified with labels describing contents.

1. Acoustical Ceiling Units: Full-size units equal to 2.0 percent of amount installed.

PART 2 - PRODUCTS

2.01 ACOUSTICAL PANELS, GENERAL

A. Acoustical Panel Standard: Provide manufacturer's standard panels of configuration indicated that comply with ASTM E 1264 classifications as designated by types, patterns, acoustical ratings, and light reflectances, unless otherwise indicated.

B. Acoustical Panel Colors and Patterns: Match existing acoustic panels (Contractor shall confirm).

2.02 METAL SUSPENSION SYSTEMS, GENERAL

A. Metal Suspension System Standard: Provide manufacturer's standard direct-hung metal suspension system together with any edge suspension or support hardware and components to match existing suspension system.

B. Finishes and Colors, General: Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes. Provide manufacturer's standard factory-applied finish for type of system indicated.

C. Attachment Devices: Size for five times design load indicated in ASTM C 635, Table 1, Direct Hung, unless otherwise indicated.

D. Wire Hangers, Braces, and Ties: Provide wires complying with the following requirements:

1. Zinc-Coated Carbon-Steel Wire: ASTM A 641/A 641M, Class 1 zinc coating, soft temper.

2. Size: Select wire diameter so its stress at three times hanger design load (ASTM C 635, Table 1, Direct Hung) will be less than yield stress of wire, but provide not less than 0.106-inch- (2.69-mm-) diameter wire.

E. Sheet-Metal Edge Moldings and Trim: Manufacturer's standard moldings for edges and penetrations that fit acoustical panel edge details and suspension systems indicated; formed from sheet metal of same material and finish as that used for exposed flanges of suspension system runners.

1. Extruded-Aluminum Edge Moldings and Trim: Where indicated, provide manufacturer's Retain one finish requirement above or below, or delete and insert others.

2. Baked-Enamel Finish: AA-C12C42R1x (Chemical Finish: cleaned with inhibited chemicals; Chemical Finish: acid-chromate-fluoride-phosphate conversion coating; Organic Coating: as specified below). Comply with paint manufacturer's written instructions for applying and baking and for minimum dry film thickness.

a. Organic Coating: Manufacturer's standard thermosetting coating system with a minimum dry film thickness of 0.8 to 1.2 mils (0.02 to 0.03 mm).

b. Color: White.

3. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Armstrong World Industries, Inc.

b. Chicago Metallic Corporation.

c. USG Interiors, Inc.

F. Hold-Down Clips for Non-Fire-Resistance-Rated Ceilings: For interior ceilings consisting of acoustical panels weighing less than 1 lb/sq. ft. (4.88 kg/sq. m), provide hold-down clips spaced 24 inches (610 mm) o.c. on all cross tees.

PART 3 - EXECUTION

Page 43: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Acoustic Panel Ceiling

Clark Dietz, Inc. 09 05 11 - 3

3.01 EXAMINATION

A. Examine substrates and structural framing to which acoustical panel ceilings attach or abut, with Installer present, for compliance with requirements specified in this and other Sections that affect ceiling installation and anchorage, and other conditions affecting performance of acoustical panel ceilings.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

3.02 PREPARATION

A. Measure each ceiling area and establish sizes and layout of new or replacement acoustical panels. Avoid using less-than-half-width panels at borders, and comply with layout shown on reflected ceiling plans.

3.03 INSTALLATION

A. General: Install acoustical panel ceilings to comply with publications referenced below per manufacturer's written instructions and CISCA's "Ceiling Systems Handbook."

1. Standard for Ceiling Suspension System Installations: Comply with ASTM C 636.

B. Suspend ceiling hangers from building's structural members and as follows:

1. Install hangers plumb and free from contact with insulation or other objects within ceiling plenum that are not part of supporting structure or of ceiling suspension system.

2. Where width of ducts and other construction within ceiling plenum produces hanger spacings that interfere with location of hangers at spacings required to support standard suspension system members, install supplemental suspension members and hangers in form of trapezes or equivalent devices. Size supplemental suspension members and hangers to support ceiling loads within performance limits established by referenced standards and publications.

3. Secure wire hangers to ceiling suspension members and to supports above with a minimum of three tight turns. Connect hangers directly either to structures or to inserts, eye screws, or other devices that are secure; that are appropriate for substrate; and that will not deteriorate or otherwise fail due to age, corrosion, or elevated temperatures.

4. Space hangers not more than 48 inches (1200 mm) o.c. along each member supported directly from hangers, unless otherwise indicated; and provide hangers not more than 8 inches (200 mm) from ends of each member.

C. Install edge moldings, hangers and trim at required electrical panel soffit at Gymnasium entry in coordination with surface mounted electrical junction box and access panel at ceiling. Set soffit below panel and provide minimum of 6 inches clear at sides of electrical box. Coordinate installation of soffit with new gypsum drywall installation over existing metal louvers above adjacent doorway and Coordinate height of bottom of soffit to provide sufficient clearance to permit removal of acoustic panel at bottom face of soffit without damage to panel. Butt trim at wall and new transom and provide moldings at all corners of soffit.

D. Install edge moldings and trim of type indicated at perimeter of acoustical ceiling area and where necessary to conceal edges of acoustical panels.

1. Screw attach moldings to substrate at intervals not more than 16 inches (400 mm) o.c. and not more than 3 inches (75 mm) from ends, leveling with ceiling suspension system to a tolerance of 1/8 inch in 12 feet (3 mm in 3.6 m). Miter corners accurately and connect securely.

2. Do not use exposed fasteners, including pop rivets, on moldings and trim.

E. Install suspension system runners so they are square and securely interlocked with one another. Remove and replace dented, bent, or kinked members.

F. Install acoustical panels with undamaged edges and fitted accurately into suspension system runners and edge moldings. Scribe and cut panels at borders and penetrations to provide a neat, precise fit.

1. Arrange directionally patterned acoustical panels in alternating pattern:

a. To match existing pattern.

Page 44: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Acoustic Panel Ceiling

Clark Dietz, Inc. 09 05 11 - 4

2. For square-edged panels, install panels with edges fully hidden from view by flanges of suspension system runners and moldings.

3. Paint cut panel edges remaining exposed after installation; match color of exposed panel surfaces using coating recommended in writing for this purpose by acoustical panel manufacturer.

4. Protect lighting fixtures and air ducts to comply with requirements indicated for fire-resistance-rated assembly.

3.04 CLEANING

1. Clean exposed surfaces of acoustical panel ceilings. Comply with manufacturer's written instructions for cleaning and touchup of minor finish damage.

2. Remove and replace ceiling components that cannot be successfully cleaned and repaired to permanently eliminate evidence of damage.

END OF SECTION

Page 45: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hangers and Supports for HVAC Piping and Equipment

Clark Dietz, Inc. 23 05 29 - 1

SECTION 23 05 29

HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes: 1. Pipe hangers and supports.2. Hanger rods.3. Inserts.4. Formed steel channel.5. Equipment bases and supports.

1.2 REFERENCES

A. American Society of Mechanical Engineers: 1. ASME B31.1 - Power Piping.2. ASME B31.5 - Refrigeration Piping.3. ASME B31.9 - Building Services Piping.

B. ASTM International: 1. ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe Hangers.2. ASTM E1966 - Standard Test Method for Fire-Resistive Joint Systems.

C. American Welding Society: 1. AWS D1.1 - Structural Welding Code - Steel.

D. FM Global: 1. FM - Approval Guide, A Guide to Equipment, Materials & Services Approved By Factory

Mutual Research For Property Conservation.

1.3 SUBMITTALS

A. Shop Drawings: Indicate system layout with location including critical dimensions, sizes, and pipe hanger and support locations and detail of trapeze hangers.

B. Product Data: 1. Hangers and Supports: Submit manufacturers catalog data including load capacity.

C. Manufacturer's Installation Instructions: 1. Hangers and Supports: Submit special procedures and assembly of components.

1.4 QUALITY ASSURANCE

A. Perform Work in accordance with the Wisconsin Administrative code and AWS D1.1 for welding hanger and support attachments to building structure.

Page 46: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hangers and Supports for HVAC Piping and Equipment

Clark Dietz, Inc. 23 05 29 - 2

1.5 DELIVERY, STORAGE, AND HANDLING

A. Accept materials on site in original factory packaging, labeled with manufacturer's identification.

B. Protect from weather and construction traffic, dirt, water, chemical, and damage, by storing in original packaging.

PART 2 PRODUCTS

2.1 PIPE HANGERS AND SUPPORTS

A. Manufacturers: 1. Carpenter & Paterson Inc. 2. Creative Systems Inc. 3. Flex-Weld, Inc. 4. Glope Pipe Hanger Products Inc. 5. Michigan Hanger Co. 6. Superior Valve Co.

B. Hydronic Piping: 1. Conform to ASME B31.92. Hangers for Hot Pipe Sizes 2 to 4 inches: Carbon steel, adjustable, clevis.3. Hangers for Hot Pipe Sizes 5 inches and Larger: Adjustable steel yoke, cast iron roll, double

hanger.4. Multiple or Trapeze Hangers: Steel channels with welded spacers and hanger rods.5. Multiple or Trapeze Hangers for Hot Pipe Sizes 5inches and Larger: Steel channels with

welded spacers and hanger rods, cast iron roll.6. Wall Support for Pipe Sizes 3 inches and Smaller: Cast iron hooks.7. Wall Support for Pipe Sizes 4 inches and Larger: Welded steel bracket and wrought steel

clamp.8. Wall Support for Hot Pipe Sizes 5 inches and Larger: Welded steel bracket and wrought steel

clamp with adjustable steel yoke and cast iron roll.9. Vertical Support: Steel riser clamp.10. Floor Support for Hot Pipe Sizes 4 Inches and Smaller: Cast iron adjustable pipe saddle, lock

nut, nipple, floor flange, and concrete pier or steel support.11. Floor Support for Hot Pipe Sizes 5 inches and Larger: Adjustable cast iron roll and stand,

steel screws, and concrete pier or steel support.12. Copper Pipe Support: Copper-plated, carbon steel ring.

2.2 ACCESSORIES

A. Hanger Rods: Mild steel threaded both ends, threaded on one end, or continuous threaded.

2.3 INSERTS

A. Inserts: Malleable iron case of galvanized steel shell and expander plug for threaded connection with lateral adjustment, top slot for reinforcing rods, lugs for attaching to forms; size inserts to

2.4 FORMED STEEL CHANNEL

A. Manufacturers:

Page 47: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hangers and Supports for HVAC Piping and Equipment

Clark Dietz, Inc. 23 05 29 - 3

1. Allied Tube & Conduit Corp. B-Line Systems Midland Ross Corporation, Electrical Products Division Unistrut Corp.

B. Product Description: Galvanized 12 gage thick steel. With holes 1-1/2 inches on center.

PART 3 EXECUTION

3.1 PREPARATION

A. Remove incompatible materials affecting bond.

B. Install backing and damming materials to arrest liquid material leakage.

C. Obtain permission from Architect/Engineer before using powder-actuated anchors.

D. Do not drill or cut structural members.

3.2 INSTALLATION - INSERTS

A. Install inserts for placement in concrete forms.

B. Install inserts for suspending hangers from reinforced concrete slabs and sides of reinforced concrete beams.

C. Provide hooked rod to concrete reinforcement section for inserts carrying pipe 4 inches and larger.

D. Where concrete slabs form finished ceiling, locate inserts flush with slab surface.

3.3 INSTALLATION - PIPE HANGERS AND SUPPORTS

A. Install in accordance with ASME B31.1, ASME B31.5, and ASME 31.9

B. Support horizontal piping as scheduled.

C. Install hangers with minimum 1/2 inch space between finished covering and adjacent work.

D. Place hangers within 12 inches of each horizontal elbow.

E. Use hangers with 1-1/2 inch minimum vertical adjustment.

F. Where piping is installed in parallel and at same elevation, provide multiple pipe or trapeze hangers.

G. Provide copper plated hangers and supports for copper piping.

H. Design hangers for pipe movement without disengagement of supported pipe.

I. Prime coat exposed steel hangers and supports. Hangers and supports located in crawl spaces, pipe shafts, and suspended ceiling spaces are not considered exposed.

Page 48: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hangers and Supports for HVAC Piping and Equipment

Clark Dietz, Inc. 23 05 29 - 4

J. Provide clearance in hangers and from structure and other equipment for installation of insulation.

3.4 INSTALLATION - EQUIPMENT BASES AND SUPPORTS

A. Provide housekeeping pads of concrete, minimum 3-1/2 inches thick and extending 6 inches beyond supported equipment.

B. Using templates furnished with equipment, install anchor bolts, and accessories for mounting and anchoring equipment.

C. Construct supports of steel members or formed steel channel or steel pipe and fittings. Brace and fasten with flanges bolted to structure.

D. Provide rigid anchors for pipes after vibration isolation components are installed.

3.5 PROTECTION OF FINISHED WORK

A. Protect adjacent surfaces from damage by material installation.

3.6 SCHEDULES

A. Copper and Steel Pipe Hanger Spacing:

PIPE SIZE

Inches

COPPER TUBING

MAXIMUM

HANGER SPACING

Feet

STEEL PIPE

MAXIMUM

HANGER SPACING

Feet

COPPER TUBING

HANGER ROD

DIAMETER

Inches

STEEL PIPE

HANGER ROD

DIAMETER

Inches

1/2 5 7 3/8 3/8

3/4 5 7 3/8 3/8

2 8 10 3/8 3/8

2-1/2 (Note 2) 9 11 1/2 1/2

3 10 12 1/2 1/2

4 12 14 1/2 5/8

5 13 16 1/2 5/8

6 14 17 5/8 3/4

B. Note 1: Refer to manufacturer’s recommendations for grooved end piping systems.

C. Note 2: 20 feet maximum spacing, minimum of one hanger for each pipe section close to joint behind bell. Provide hanger at each change of direction and each branch connection. For pipe sizes 6 inches and smaller, subjected to loadings other than weight of pipe and contents, limit span to maximum spacing for water service steel pipe.

END OF SECTION

Page 49: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Identification for HVAC Piping and Equipment

Clark Dietz, Inc. 23 05 53 - 1

SECTION 23 05 53

IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:1. Nameplates.2. Tags.3. Pipe markers.4. Ceiling tacks.5. Labels.

1.2 REFERENCES

A. American Society of Mechanical Engineers:1. ASME A13.1 - Scheme for the Identification of Piping Systems.

1.3 SUBMITTALS

A. Product Data: Submit manufacturers catalog literature for each product required.

B. Shop Drawings: Submit list of wording, symbols, letter size, and color coding for mechanical identification and valve chart and schedule, including valve tag number, location, function, and valve manufacturer's name and model number.

C. Samples: Submit two tags, labels, and pipe markers, size used on project.

D. Manufacturer's Installation Instructions: Indicate installation instructions, special procedures, and installation.

1.4 CLOSEOUT SUBMITTALS

A. Project Record Documents: Record actual locations of tagged valves; include valve tag numbers.

1.5 QUALITY ASSURANCE

A. Conform to ASME A13.1 for color scheme for identification of piping systems and accessories.

PART 2 PRODUCTS

2.1 NAMEPLATES

A. Furnish materials in accordance with Kenosha County standards.

B. Product Description: Laminated three-layer plastic with engraved black letters on light contrasting background color.

2.2 TAGS

A. Plastic Tags

Page 50: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Identification for HVAC Piping and Equipment

Clark Dietz, Inc. 23 05 53 - 2

1. Laminated three-layer plastic with engraved black letters on light contrasting background color. Tag size minimum 1-1/2 inches diameter.

B. Metal Tags:1. Aluminum with stamped letters; tag size minimum 1-1/2 inches diameter with finished edges.

C. Information Tags:1. Clear plastic with printed "Danger," "Caution," or "Warning" and message; size 3-1/4 x 5-5/8 inches

with grommet and self-locking nylon ties.

D. Tag Chart: Typewritten letter size list of applied tags and location in anodized aluminum frame].

2.3 PIPE MARKERS

A. Color and Lettering: Conform to ASME A13.1.

B. Plastic Pipe Markers:

1. Factory fabricated, flexible, semi-rigid plastic, preformed to fit around pipe or pipe covering. Larger sizes may have maximum sheet size with spring fastener.

2. Flexible, vinyl film tape with pressure sensitive adhesive backing and printed markings.

C. Plastic Underground Pipe Markers:

1. Bright colored continuously printed plastic ribbon tape, minimum 6 inches wide by 4 mil thick, manufactured for direct burial service.

2.4 CEILING TACKS

A. Description: Steel with 3/4 inch diameter color-coded head.

B. Color code as follows:1. Heating/cooling valves: Blue.

2.5 LABELS

A. Description: Laminated Mylar, size 1.9 x 0.75 inches, adhesive backed with printed identification.

PART 3 EXECUTION

3.1 PREPARATION

A. Degrease and clean surfaces to receive adhesive for identification materials.

3.2 INSTALLATION

A. Install identifying devices after completion of coverings and painting.

B. Install plastic nameplates with corrosive-resistant mechanical fasteners, or adhesive.

C. Install labels with sufficient adhesive for permanent adhesion and seal with clear lacquer. For unfinished canvas covering, apply paint primer before applying labels.

Page 51: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Identification for HVAC Piping and Equipment

Clark Dietz, Inc. 23 05 53 - 3

D. Install tags using corrosion resistant chain. Number tags consecutively by location.

E. Identify water treatment device with plastic nameplate.

F. Identify valves in main and branch piping with tags.

G. Identify piping, concealed or exposed, with plastic pipe markers. Identify service, flow direction, and pressure. Install in clear view and align with axis of piping. Locate identification not to exceed 20 feet on straight runs including risers and drops, adjacent to each valve and tee, at each side of penetration of structure or enclosure, and at each obstruction.

H. Provide ceiling tacks to locate valves or dampers above T-bar type panel ceilings. Locate in corner of panel closest to equipment.

END OF SECTION

Page 52: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Testing, Adjusting, and Balancing for HVAC

Clark Dietz, Inc. 23 05 93 - 1

SECTION 23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:1. Testing, adjusting, and balancing of hydronic systems.2. Measurement of final operating condition of HVAC systems.

1.2 REFERENCES

A. Associated Air Balance Council:1. AABC MN-1 - National Standards for Testing and Balancing Heating, Ventilating, and Air Conditioning

Systems.

B. American Society of Heating, Refrigerating and Air-Conditioning Engineers:1. ASHRAE 111 - Practices for Measurement, Testing, Adjusting and Balancing of Building Heating,

Ventilation, Air-Conditioning and Refrigeration Systems.

C. Natural Environmental Balancing Bureau:1. NEBB - Procedural Standards for Testing, Adjusting, and Balancing of Environmental Systems.

1.3 SUBMITTALS

A. Test Reports: Indicate data on AABC MN-1 National Standards for Total System Balance forms, forms prepared following ASHRAE 111, or NEBB Report forms.

B. Field Reports: Indicate deficiencies preventing proper testing, adjusting, and balancing of systems and equipment to achieve specified performance.

C. Prior to commencing Work, submit report forms or outlines indicating adjusting, balancing, and equipment data required. Include detailed procedures, agenda, sample report forms.

D. Submit draft copies of report for review prior to final acceptance of Project.

E. Furnish reports in soft cover, letter size, 3-ring binder manuals, complete with table of contents page and indexing tabs, with cover identification at front and side. Include set of reduced drawings with equipment identified to correspond with data sheets.

1.4 CLOSEOUT SUBMITTALS

A. Project Record Documents: Record actual locations of balancing valves and rough setting.

B. Operation and Maintenance Data: Furnish final copy of testing, adjusting, and balancing report inclusion in operating and maintenance manuals.

1.5 QUALITY ASSURANCE

A. Perform Work in accordance with AABC MN-1 National Standards for Field Measurement and Instrumentation, Total System Balance, ASHRAE 111 or NEBB Procedural Standards for Testing, Balancing and Adjusting of Environmental Systems.

Page 53: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Testing, Adjusting, and Balancing for HVAC

Clark Dietz, Inc. 23 05 93 - 2

B. Prior to commencing Work, calibrate each instrument to be used. Upon completing Work, recalibrate each instrument to assure reliability.

1.6 QUALIFICATIONS

A. Agency: Company specializing in testing, adjusting, and balancing of systems specified in this section with minimum three years documented experience and certified by AABC or Certified by NEBB.

B. Perform Work under supervision of AABC Certified Test and Balance Engineer or NEBB Certified Testing, Balancing and Adjusting Supervisor.

1.7 PRE-INSTALLATION MEETINGS

A. Convene minimum one week prior to commencing work of this section.

1.8 SEQUENCING

A. Sequence balancing between completion of systems tested and Date of Substantial Completion.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify systems are complete and operable before commencing work. Verify the following:1. Systems are started and operating in safe and normal condition.2. Hydronic systems are flushed, filled, and vented.3. Pumps are rotating correctly.4. Proper strainer baskets are clean and in place or in normal position.5. Service and balancing valves are open.

3.2 PREPARATION

A. Furnish instruments required for testing, adjusting, and balancing operations.

B. Make instruments available to Architect/Engineer to facilitate spot checks during testing.

3.3 INSTALLATION TOLERANCES

A. Hydronic Systems: Adjust to within plus or minus 10 percent of design.

3.4 ADJUSTING

A. Verify recorded data represents actual measured or observed conditions.

B. Permanently mark settings of valves, dampers, and other adjustment devices allowing settings to be restored. Set and lock memory stops.

C. After adjustment, take measurements to verify balance has not been disrupted. If disrupted, verify correcting adjustments have been made.

Page 54: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Testing, Adjusting, and Balancing for HVAC

Clark Dietz, Inc. 23 05 93 - 3

D. Report defects and deficiencies noted during performance of services, preventing system balance.

E. Leave systems in proper working order.

F. At final inspection, recheck random selections of data recorded in report. Recheck points or areas as selected and witnessed by Owner.

G. Check and adjust systems approximately six months after final acceptance and submit report.

3.5 WATER SYSTEM PROCEDURE

A. Adjust water systems to obtain design quantities.

B. Effect adjustment of water distribution systems by means of balancing cocks, valves, and fittings. Do not use service or shut-off valves for balancing unless indexed for balance point.

C. Where available pump capacity is less than total flow requirements or individual system parts, simulate full flow in one part by temporary restriction of flow to other parts.

3.6 SCHEDULES

A. Equipment Requiring Testing, Adjusting, and Balancing:1. Packaged Steel Fire Tube Boilers.2. Packaged Roof Top Heating/Cooling Units (System balancing valves).

B. Report Forms1. Title Page:

a. Name of Testing, Adjusting, and Balancing Agencyb. Address of Testing, Adjusting, and Balancing Agencyc. Telephone and facsimile numbers of Testing, Adjusting, and Balancing Agencyd. Project namee. Project locationf. Project Architectg. Project Engineerh. Project Contractori. Project altitudej. Report date

2. Summary Comments:a. Design versus final performanceb. Notable characteristics of systemc. Description of systems operation sequenced. Nomenclature used throughout reporte. Test conditions

3. Instrument List:a. Instrumentb. Manufacturerc. Model numberd. Serial numbere. Rangef. Calibration date

4. Balancing Valves:a. Identification/numberb. Locationc. Sized. Manufacturere. Model number

Page 55: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Testing, Adjusting, and Balancing for HVAC

Clark Dietz, Inc. 23 05 93 - 4

f. Serial numberg. Design Flow rateh. Design pressure dropi. Actual/final pressure dropj. Actual/final flow rate

END OF SECTION

Page 56: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II HVAC Insulation

Clark Dietz, Inc. 23 07 00 - 1

SECTION 23 07 00

HVAC INSULATION

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes: 1. HVAC piping insulation, jackets and accessories.

1.2 REFERENCES

A. ASTM International: 1. ASTM C450 - Standard Practice for Fabrication of Thermal Insulating Fitting Covers for

NPS Piping, and Vessel Lagging.2. ASTM C585 - Standard Practice for Inner and Outer Diameters of Rigid Thermal

Insulation for Nominal Sizes of Pipe and Tubing (NPS System).3. ASTM C1071 - Standard Specification for Thermal and Acoustical Insulation (Glass Fiber,

Duct Lining Material).4. ASTM C1136 - Standard Specification for Flexible, Low Permeance Vapor Retarders for

Thermal Insulation.5. ASTM D1785 - Standard Specification for Rigid Poly (Vinyl Chloride) (PVC) Compounds

and Chlorinated Poly (Vinyl Chloride) (CPVC) Compounds.6. ASTM E96/E96M - Standard Test Methods for Water Vapor Transmission of Materials.7. ASTM E162 - Standard Test Method for Surface Flammability of Materials Using a

Radiant Heat Energy Source.

1.3 SUBMITTALS

A. Product Data: Submit product description, thermal characteristics and list of materials and thickness for each service, and location.

B. Manufacturer's Installation Instructions: Submit manufacturers published literature indicating proper installation procedures.

1.4 QUALITY ASSURANCE

A. Test pipe insulation for maximum flame spread index of 25 and maximum smoke developed index of not exceeding 50 in accordance with ASTM E84.

B. Pipe insulation manufactured in accordance with ASTM C585 for inner and outer diameters.

C. Factory fabricated fitting covers manufactured in accordance with ASTM C450.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Accept materials on site in original factory packaging, labeled with manufacturer's identification, including product density and thickness.

B. Protect insulation from weather and construction traffic, dirt, water, chemical, and damage, by storing in original wrapping.

Page 57: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II HVAC Insulation

Clark Dietz, Inc. 23 07 00 - 2

1.6 ENVIRONMENTAL REQUIREMENTS

A. Install insulation only when ambient temperature and humidity conditions are within range recommended by manufacturer.

B. Maintain temperature before, during, and after installation for minimum period of 24 hours.

PART 2 PRODUCTS

2.1 PIPE INSULATION

A. TYPE P-1: ASTM C547, molded glass fiber pipe insulation. [Conform to ASTM C795 for application on Austenitic stainless steel.]1. Thermal Conductivity: 0.23 at 75 degrees F.2. Operating Temperature Range: 0 to 850 degrees F.3. Vapor Barrier Jacket: ASTM C1136, Type I, factory applied reinforced foil kraft with self-

sealing adhesive joints.4. Jacket Temperature Limit: minus 20 to 150 degrees F.

2.2 PIPE INSULATION JACKETS

A. PVC Plastic Pipe Jacket: 1. Product Description: ASTM D1785, One piece molded type fitting covers and sheet

material, off-white color.2. Thickness: 30 mil.3. Connections: Brush on welding adhesive.

B. Aluminum Pipe Jacket: 1. ASTM B209.2. Thickness: 0.016 inch thick sheet.3. Finish: Smooth.4. Joining: Longitudinal slip joints and 2 inch laps.5. Fittings: 0.016 inch thick die shaped fitting covers with factory attached protective liner.6. Metal Jacket Bands: 3/8 inch wide; 0.015 inch thick aluminum.

2.3 PIPE INSULATION ACCESSORIES

A. Vapor Retarder Lap Adhesive: Compatible with insulation.

B. Covering Adhesive Mastic: Compatible with insulation.

C. Piping 1-1/2 inches diameter and smaller: Galvanized steel insulation protection shield. MSS SP-69, Type 40. Length: Based on pipe size and insulation thickness.

D. Piping 2 inches diameter and larger: Wood insulation saddle, hard maple. Inserts length: not less than 6 inches long, matching thickness and contour of adjoining insulation.

E. Tie Wire: 0.048 inch stainless steel with twisted ends on maximum 12 inch centers.

F. Mineral Fiber Hydraulic-Setting Thermal Insulating and Finishing Cement: ASTM C449/C449M.

Page 58: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II HVAC Insulation

Clark Dietz, Inc. 23 07 00 - 3

G. Insulating Cement: ASTM C195; hydraulic setting on mineral wool.

H. Adhesives: Compatible with insulation.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify piping, and equipment has been tested before applying insulation materials.

B. Verify surfaces are clean and dry, with foreign material removed.

3.2 INSTALLATION - PIPING SYSTEMS

A. Piping Exposed to View in Finished Spaces: Locate insulation and cover seams in least visible locations.

B. Hot Piping Systems greater than 140 degrees F: 1. Furnish factory-applied or field-applied standard jackets. Secure with outward clinch

expanding staples or pressure sensitive adhesive system on standard factory-applied jacket and butt strips or both.

2. Insulate fittings, joints, and valves with insulation of like material and thickness as adjoining pipe. Finish with glass cloth and adhesive or PVC fitting covers.

3. Insulate flanges and unions at equipment.

C. Inserts and Shields: 1. Piping 2 inches Diameter and Larger: Install insert between support shield and piping

and under finish jacket.a. Insert Configuration: Minimum 6 inches long, of thickness and contour

matching adjoining insulation; may be factory fabricated.b. Insert Material: Compression resistant insulating material suitable for

planned temperature range and service.2. Piping Supported by Roller Type Pipe Hangers: Install galvanized steel shield between

roller and inserts.

D. Pipe Exposed in Mechanical Equipment Rooms or Finished Spaces (less than 8 feet above finished floor): Finish with PVC jacket and fitting covers.

3.3 SCHEDULES

A. Heating Services Piping Insulation Schedule:

PIPING SYSTEM INSULATION

TYPE

PIPE SIZE

INSULATION

THICKNESS

inches

Heating Water Supply and Return P-1 1-1/2” and smaller

1-1/2” and larger

1.5

2.0

Page 59: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II HVAC Insulation

Clark Dietz, Inc. 23 07 00 - 4

END OF SECTION

Page 60: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Commissioning of HVAC

Clark Dietz, Inc. 23 08 00 - 1

SECTION 23 08 00

COMMISSIONING OF HVAC

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:1. HVAC commissioning description.2. HVAC commissioning responsibilities.

1.2 REFERENCES

A. American Society of Heating, Refrigerating and Air-Conditioning Engineers:1. ASHRAE Guideline 1 - The HVAC Commissioning Process.

B. National Environmental Balancing Bureau:1. NEBB - Procedural Standards for Building Systems Commissioning.

1.3 COMMISSIONING DESCRIPTION

A. HVAC commissioning process includes the following tasks:1. Testing and startup of HVAC equipment and systems.2. Equipment and system verification checks.3. Assistance in functional performance testing to verify testing and balancing, and equipment and

system performance.4. Provide qualified personnel to assist in commissioning tests, including seasonal testing.5. Complete and endorse functional performance test checklists provided by Commissioning Authority to

assure equipment and systems are fully operational and ready for functional performance testing.6. Provide equipment, materials, and labor necessary to correct deficiencies found during commissioning

process to fulfill contract and warranty requirements.7. Provide operation and maintenance information and record drawings to Commissioning Authority for

review verification and organization, prior to distribution.8. Provide assistance to Commissioning Authority to develop, edit, and document system operation

descriptions.9. Provide training for systems specified in this Section with coordination by Commissioning Authority.

B. Equipment and Systems to Be Commissioned:1. Piping systems.2. Testing, Adjusting and Balancing work.

1.4 COMMISSIONING SUBMITTALS

A. Draft Forms: Submit draft of [system verification form and functional performance test checklist.

B. Test Reports: Indicate data on system verification form for each piece of equipment and system as specified.

C. Field Reports: Indicate deficiencies preventing completion of system verification checks to achieve specified performance.

Page 61: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Commissioning of HVAC

Clark Dietz, Inc. 23 08 00 - 2

1.5 CLOSEOUT SUBMITTALS

A. Project Record Documents: Record revisions to equipment and system documentation necessitated by commissioning.

B. Operation and Maintenance Data: Submit revisions to operation and maintenance manuals when necessary revisions are discovered during commissioning.

1.6 QUALITY ASSURANCE

A. Perform Work in accordance with ASHRAE Guideline 1.

1.7 COMMISSIONING RESPONSIBILITIES

A. Equipment or System Installer Commissioning Responsibilities:1. Attend commissioning meetings.2. Ensure testing, adjusting, and balancing agency performs assigned commissioning responsibilities as

specified.3. Provide instructions and demonstrations for Owner's personnel.4. Ensure subcontractors perform assigned commissioning responsibilities.5. Ensure participation of equipment manufacturers in appropriate startup, testing, and training activities

when required by individual equipment specifications.6. Develop startup and initial checkout plan using manufacturer’s startup procedures and functional

performance checklists for equipment and systems to be commissioned.7. During verification check and startup process, execute HVAC related portions of checklists for

equipment and systems to be commissioned.8. Perform and document completed startup and system operational checkout procedures, providing

copy to Commissioning Authority.9. Provide manufacturer’s representatives to execute starting of equipment. Ensure representatives are

available and present during agreed upon schedules and are in attendance for duration to complete tests, adjustments and problem-solving.

10. Coordinate with equipment manufacturers to determine specific requirements to maintain validity of warranties.

11. Provide personnel to assist Commissioning Authority during equipment or system verification checks and functional performance tests.

12. Prior to functional performance tests, review test procedures to ensure feasibility, safety and equipment protection and provide necessary written alarm limits to be used during tests.

13. Prior to startup, inspect, check, and verify correct and complete installation of equipment and system components for verification checks included in commissioning plan. When deficient or incomplete work is discovered, ensure corrective action is taken and re-check until equipment or system is ready for startup.

14. Provide factory supervised startup services for equipment and systems specified. Coordinate work with manufacturer and Commissioning Authority.

15. Perform verification checks and startup on equipment and systems as specified.16. Assist Commissioning Authority in performing functional performance tests on equipment and systems

as specified.17. Perform operation and maintenance training sessions scheduled by Commissioning Authority.18. Conduct HVAC system orientation and inspection.

B. Testing, Adjusting, and Balancing Agency Commissioning Responsibilities:1. Attend commissioning meetings.2. Participate in verification of testing, adjusting, and balancing report for verification or diagnostic

purposes. Repeat sample of 10 percent of measurements contained in testing, adjusting, and balancing report as selected by Commissioning Authority.

3. Assist in performing operation and maintenance training sessions scheduled by Commissioning Authority.

Page 62: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Commissioning of HVAC

Clark Dietz, Inc. 23 08 00 - 3

1.8 COMMISSIONING MEETINGS

A. Attend initial commissioning meeting and progress commissioning meetings as required by Commissioning Authority.

1.9 SCHEDULING

A. Prepare schedule indicating anticipated start dates for the following:1. Piping system pressure testing.2. Piping system flushing and cleaning.3. Equipment and system startups.4. Testing, adjusting, and balancing.5. HVAC system orientation and inspections.6. Operation and maintenance manual submittals.7. Training sessions.

B. Schedule seasonal tests of equipment and systems during peak weather conditions to observe full-load performance.

1.10 COORDINATION

A. Notify Commissioning Authority minimum of four weeks in advance of the following:1. Scheduled equipment and system startups.2. Scheduled start of testing, adjusting, and balancing work.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 INSTALLATION

A. Place HVAC systems and equipment into full operation and continue operation during each working day of commissioning.

3.2 COMMISSIONING

A. Seasonal Sensitive Functional Performance Tests:1. Test heating equipment at winter design temperatures.

B. Be responsible to participate in initial and alternate peak season test of systems required to demonstrate performance.

END OF SECTION

Page 63: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Piping

Clark Dietz, Inc. 23 21 13 - 1

SECTION 23 21 13

HYDRONIC PIPING

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes: 1. Glycol piping, above ground.2. Unions and flanges.3. Pipe hangers and supports.4. Valves.

1.2 REFERENCES

A. American Society of Mechanical Engineers: 1. ASME B31.9 - Building Services Piping.2. ASME Section IX - Boiler and Pressure Vessel Code - Welding and Brazing Qualifications.

B. ASTM International: 1. ASTM A53/A53M - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded

and Seamless.2. ASTM A234/A234M - Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy

Steel for Moderate and High Temperature Service.3. ASTM A395/A395M - Standard Specification for Ferritic Ductile Iron Pressure-Retaining Castings for

Use at Elevated Temperatures.4. ASTM B32 - Standard Specification for Solder Metal.5. ASTM B88 - Standard Specification for Seamless Copper Water Tube.6. ASTM B584 - Standard Specification for Copper Alloy Sand Castings for General Applications.7. ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe Hangers.8. ASTM F1476 - Standard Specification for Performance of Gasketed Mechanical Couplings for Use in

Piping Applications.

C. American Welding Society: 1. AWS A5.8 - Specification for Filler Metals for Brazing and Braze Welding.2. AWS D1.1 - Structural Welding Code - Steel.

1.3 SYSTEM DESCRIPTION

A. Where more than one piping system material is specified, provide compatible system components and joints. Use non-conducting dielectric connections whenever jointing dissimilar metals in open systems.

B. Provide flanges, union, and couplings at locations requiring servicing. Use unions, flanges, and couplings downstream of valves and at equipment or apparatus connections. Do not use direct welded or threaded connections to valves, equipment or other apparatus.

C. Provide pipe hangers and supports in accordance with ASME B31.9.

D. Use butterfly valves for shut-off and to isolate equipment, part of systems, or vertical risers.

1.4 SUBMITTALS

A. Shop Drawings: Indicate schematic layout of piping system, including equipment, critical dimensions, and sizes.

Page 64: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Piping

Clark Dietz, Inc. 23 21 13 - 2

B. Product Data: 1. Piping: Submit data on pipe materials, fittings, and accessories. Submit manufacturers catalog

information.2. Valves: Submit manufacturers catalog information with valve data and ratings for each service.

C. Test Reports: Indicate results of piping system pressure test.

D. Manufacturer's Installation Instructions: Submit hanging and support methods, joining procedures and isolation.

E. Welders’ Certificate: Include welders’ certification of compliance with AWS D1.1.

1.5 CLOSEOUT SUBMITTALS

A. Project Record Documents: Record actual locations of valves, equipment, and accessories.

B. Operation and Maintenance Data: Submit instructions for installation and changing components, spare parts lists, exploded assembly views.

1.6 QUALITY ASSURANCE

A. Perform Work in accordance with ASME B31.9 code for installation of piping systems and ASME Section IX for welding materials and procedures.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Accept valves on site in shipping containers with labeling in place. Inspect for damage.

B. Provide temporary end caps and closures on piping and fittings. Maintain in place until installation.

C. Protect piping systems from entry of foreign materials by temporary covers, completing sections of the Work, and isolating parts of completed system.

PART 2 PRODUCTS

2.1 HEATING WATER (GLYCOL) PIPING, ABOVE GROUND

A. Steel Pipe: ASTM A53/A53M, Schedule 40, black.1. Fittings: ASME B16.3, malleable iron or ASTM A234/A234M, forged steel welding type.2. Joints: Threaded for pipe 2 inch and smaller; welded for pipe 2-1/2 inches and larger.

B. (ALTERNATE #1 ONLY) Steel Pipe: ASTM A53/A53M, Schedule 40, black, grooved ends.1. Fittings

a. Manufacturer: Victaulicb. ASTM A234/A234M carbon steel, grooved ends.c. Basis of Design: Grooved Elbow – No. 10, Grooved Tee – No 20, Grooved Reducing

Tee – No 252. Joints: Grooved mechanical couplings meeting ASTM A536. The couplings and fittings must be

capable of withstanding the following minimum working pressure and temperature of Glycol-Water solution.

a. Manufacturer: Victaulicb. Basis of Design: Rigid Coupling -107Nc. Hot-Water Heating Piping: 150 psig, 250F.

Page 65: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Piping

Clark Dietz, Inc. 23 21 13 - 3

d. Housing Clamps: ASTM A395/A395M and ASTM A536 ductile iron compatible with steel piping sizes, rigid type.

e. Gasket: Elastomer composition for operating temperature range from 40 degrees F to 250 degrees F.

f. Accessories: Steel bolts, nuts, and washers.g. Contractor must obtain all grooved joint couplings, fittings, valves and specialties

from single source. Obtain grooving tools from same source as grooved components.

C. Copper Tubing: ASTM B88, Type L, drawn.1. Fittings: ASME B16.18, cast brass, or ASME B16.22 solder wrought copper.

2. Joints: Braze, AWS A5.8 BCuP silver/phosphorus/copper alloy with melting range 1190 to 1480 degrees F.

2.2 UNIONS AND FLANGES

A. Unions for Pipe 2 inches and Smaller: 1. Ferrous Piping: Class 150, malleable iron, threaded.2. Copper Piping: Class 150, bronze unions with brazed joints.3. Dielectric Connections: Union with galvanized or plated steel threaded end, copper solder end, water

impervious isolation barrier.

B. Flanges for Pipe 2-1/2 inches and Larger: 1. Ferrous Piping: Class 150, forged steel, slip-on flanges.2. Gaskets: 1/16 inch thick preformed neoprene gaskets.

2.3 BALANCING VALVES

A. 2 inches and Smaller: Class 150 brass construction, female thread, Y-pattern globe style, minimum 5 turn, concealed locking balance point, flow measurement ports.

B. 2-1/2 inches and Larger: Class 150 cast iron construction, flanged, Y-pattern globe style, minimum 5 turn, concealed locking balance point, flow measurement ports.

2.4 BUTTERFLY VALVES

A. 2-1/2 inches and Larger: MSS SP 67, Class 150.1. Body: Cast or ductile iron, lug ends, stainless steel stem, extended neck.2. Disc: Aluminum bronze3. Seat: Resilient replaceable EPDM4. Handle and Operator: 10 position lever handle.

PART 3 EXECUTION

3.1 EXAMINATION

A. ALTERNATE #1 ONLY: Where grooved couplings are to be replaced, verify existing grooves in piping are acceptable as determined by coupling manufacturer’s test.

3.2 PREPARATION

A. Ream pipe and tube ends. Remove burrs. Bevel plain end ferrous pipe.

B. Remove scale and dirt on inside and outside before assembly.

Page 66: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Piping

Clark Dietz, Inc. 23 21 13 - 4

C. Prepare piping connections to equipment with flanges or unions.

D. Keep open ends of pipe free from scale and dirt. Protect open ends with temporary plugs or caps.

E. After completion, fill, clean, and treat systems. Refer to Section 23 25 00.

3.3 INSTALLATION - ABOVE GROUND PIPING SYSTEMS

A. ALTERNATE #1 ONLY: If grooved end fails examination per coupling manufacturer’s test, replace pipe spool. Groove ends and verify grooves pass test prior to installation.

B. ALTERNATE #1 ONLY: Contractor shall coordinate site visit during construction with manufacturer’s representative. Manufacturer’s representative shall review contractor’s installation of all fittings and ensure manufacturer’s requirements are met. Manufacturer’s material warranty must be applied to all work completed by the contractor.

C. Install glycol piping in accordance with ASME B31.9.

D. Install piping to conserve building space, and not interfere with use of space.

E. Group piping whenever practical at common elevations.

F. Slope hydronic piping and arrange systems to drain at low points. Use eccentric reducers to maintain top of pipe aligned.

G. Where pipe support members are welded to structural building framing, scrape, brush clean, and apply one coat of zinc rich primer to welds.

H. Prepare unfinished pipe, fittings, supports, and accessories, ready for finish painting.

I. Install valves with stems upright or horizontal, not inverted.

3.4 FIELD QUALITY CONTROL

A. Test glycol piping system in accordance with ASME B31.9.

END OF SECTION

Page 67: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Piping Specialties

Clark Dietz, Inc. 23 21 16 - 1

SECTION 23 21 16

HYDRONIC PIPING SPECIALTIES

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:1. Glycol charging equipment.2. Glycol solution.

1.2 REFERENCES

None.

1.3 SUBMITTALS

A. Product Data: Submit for manufactured products and assemblies used in this Project.1. Manufacturer’s data and list indicating use, operating range, and connection location requirement.2. Submit product description, model, dimensions, component sizes, rough-in requirements, service

sizes, and finishes.3. Submit schedule indicating manufacturer, model number, size, location, rated capacity, load served,

and features for each piping specialty.4. Submit electrical characteristics and connection requirements.

B. Manufacturer's Installation Instructions: Submit hanging and support methods, joining procedures, application, selection, and hookup configuration. Include pipe and accessory elevations.

C. Manufacturer's Certificate: Certify products meet or exceed specified requirements.

1.4 CLOSEOUT SUBMITTALS

A. Project Record Documents: Record actual locations of equipment.

B. Operation and Maintenance Data: Submit instructions for calibrating instruments, installation instructions, assembly views, servicing requirements, lubrication instruction, and replacement parts list.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Accept piping specialties on site in shipping containers with labeling in place. Inspect for damage.

B. Provide temporary protective coating on cast iron and steel valves.

C. Protect systems from entry of foreign materials by temporary covers, caps and closures, completing sections of the work, and isolating parts of completed system until installation.

PART 2 PRODUCTS

2.1 PACKAGED GLYCOL CHARGER

A. Mixing Tank: 55 gallon polyethylene tank with removable lid.

B. Charging pump: 3.75 gpm at 100 psi, ½ hp

Page 68: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Piping Specialties

Clark Dietz, Inc. 23 21 16 - 2

2.2 GLYCOL SOLUTION

A. Inhibited propylene glycol and water solution mixed 35 percent glycol - 65 percent water, suitable for operating temperatures from 0 degrees F to 210 degrees F.

PART 3 EXECUTION

3.1 INSTALLATION - HYDRONIC PIPING SPECIALTIES

A. Install manual air vents if new system high points are created as part of installation.

B. For automatic air vents in ceiling spaces or other concealed locations, install vent tubing to nearest drain.

C. Feed glycol solution to system through make-up line with pressure regulator, venting system high points. Set to fill at 12 psig.

D. The balancing valves associated with boilers must be installed during night hours to minimize disruptions of owner’s operation. Contractor shall perform shut down, drain, installation of new balancing valves and refill overnight.

3.2 FIELD QUALITY CONTROL

A. Test for strength of glycol and water solution and submit written test results.

3.3 CLEANING

A. Clean and flush glycol system before adding glycol solution.

END OF SECTION

Page 69: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Water Treatment

Clark Dietz, Inc. 23 25 00 - 1

SECTION 23 25 00

HVAC WATER TREATMENT

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:1. System cleaner.2. Closed system treatment (water-Glycol solution).3. Test equipment.

1.2 REFERENCES

A. National Electrical Manufacturers Association:1. NEMA 250 - Enclosures for Electrical Equipment (1000 Volts Maximum).

1.3 SUBMITTALS

A. Shop Drawings: Indicate system schematic, equipment locations, and controls schematics, electrical characteristics and connection requirements.

B. Product Data: Submit chemical treatment materials, chemicals, and equipment including electrical characteristics and connection requirements.

C. Manufacturer's Installation Instructions: Submit placement of equipment in systems, piping configuration, and connection requirements.

D. Manufacturers Field Reports: Indicate start-up of treatment systems when completed and operating properly. Indicate analysis of system water after cleaning and after treatment.

1.4 CLOSEOUT SUBMITTALS

A. Project Record Documents: Record actual locations of equipment and piping, including sampling points and location of chemical injectors.

B. Operation and Maintenance Data: Submit data on glycol chargers including spare parts lists, procedures, and treatment programs. Include step by step instructions on test procedures including target concentrations.

PART 2 PRODUCTS

2.1 SYSTEM CLEANER

A. Product Description: Liquid alkaline compound with emulsifying agents and detergents to remove grease and petroleum products; sodium tri-Poly phosphate and sodium molybdate.

B. Biocide; chlorine release agents including sodium hypochlorite or calcium hypochlorite, or microbicides including quaternary ammonia compounds, tributyl tin oxide, methylene bis (thiocyanate), or isothiazolones.

Page 70: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Water Treatment

Clark Dietz, Inc. 23 25 00 - 2

2.2 CLOSED SYSTEM TREATMENT (WATER-GLYCOL SOLUTION)

A. Sequestering agent to reduce deposits and adjust pH; polyphosphate.

B. Corrosion inhibitors; liquid boron-nitrite, sodium nitrite and borax, sodium totyltriazole, low molecular weight polymers, phosphonates, sodium molybdate, or sulfites.

C. Conductivity enhancers [; phosphates or phosphonates].

2.3 TEST EQUIPMENT

A. Furnish white enamel test cabinet with local and fluorescent light, capable of accommodating 4 - 10 ml zeroing titration burettes and associated reagents.

B. Furnish following test kits:1. Alkalinity titration test kit.2. Chloride titration test kit.3. Sulphite titration test kit.4. Total hardness titration test kit.5. Low phosphate test kit.6. Conductivity bridge, range 0 - 10,000 micro-ohms.7. Creosol red pH slide, complete with reagent.8. Portable electronic conductivity meter.9. High nitrite test kit.

PART 3 EXECUTION

3.1 PREPARATION

A. Operate, fill, start and vent systems prior to cleaning. Use water meter to record capacity in each system. Place terminal control valves in open position during cleaning.

3.2 CLEANING

A. Concentration:1. As recommended by manufacturer.2. One pound per 100 gallons of solution contained in the system.3. One pound per 100 gallons of solution for hot water systems.

B. Hot Water Heating Systems:1. Apply heat while circulating, slowly raising temperature to 160 degrees F and maintain for 12 hours

minimum.2. Remove heat and circulate to 100 degrees F or less; drain systems as quickly as possible and refill

with clean water.3. Circulate for 6 hours at design temperatures, then drain.4. Refill with clean water and repeat until system cleaner is removed.

C. Use neutralizer agents on recommendation of system cleaner supplier and acceptance of Architect/Engineer.

D. Flush glycol filled closed system with clean water for one hour minimum. Drain completely and refill.

E. Remove, clean, and replace strainer screens.

Page 71: KCDC Piping Project Phase II Bid # 2101

County of Kenosha – KCDC PIPING PROJECT PHASE II Hydronic Water Treatment

Clark Dietz, Inc. 23 25 00 - 3

F. Inspect, remove sludge, and flush low points with clean water after cleaning process is completed. Include disassembly of components as required.

END OF SECTION