JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION, DECEMBER 01 ST ABB Ability - Digital Substations FISE 7a Edición

Upload: vuongtuong

Post on 01-Dec-2018

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

—JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION, DECEMBER 01ST

ABB Ability - Digital SubstationsFISE 7a Edición

Page 2: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

—Current challenges and changes facing utilities

December 11, 2017 Slide 2

Aging infrastructureLegecy systems with static or

eletromechanical relays, and evenfirst microprocessor based relays

Workforce in transitionMaintenance and operationengineering groups memberselegible for retirement in next fewyears.

ReliabilityThere´s increasing pressure to

continually improve reliabilityand customer satisfaction.

Spending justificationRevenue challenges and regulatoryinspection will drive thecosts/expenditure.

Cyber segurançaAttacks on critical infrastructure areincreasing in terms of regularity andsophistication.

Disruptive technologiesDigitalization techniques for

substation automation via IEC61850, concerns about cyber security

and asset management demandsattention by the utilities part.

Changes in business modelNew players are entering in energy

market, and among them are investorswho are non-utilities companies. This

group will be responsible by 20% oftransmission and distribution around the

world until 2020.

TrainingNetwork computers and itsprotocols, topologies andcommunication redundancy.

CostsMinimizeàOptimize

PerformanceExceedàMeet or beat

RisksAvoidàManage

$

Page 3: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

Digital substations concepts

Protocols and Ethernet allocation

Communication network topologies

Cyber security approaches

Reference cases

Atlas Juazeiro: First full digital substation in South America

December 11, 2017 Slide 3

Iniciativa EletrobrasAgenda

Page 4: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

Intelligentsubstation

HMI

SDM600Data

manager

How the digitalization is understood by the utilitiesDigital substation concepts and scenarios

December 11, 2017 Slide 4

Station bus

Process bus

Mobile workforcemanagement

CALMPlatformSCADA NCCDisturbanc

e records

Operation

Network control center

Super PDCPMUs

SCADA Level 2

RTU Gateway Level2

Cyber security

Mergingunits

Ability

Primary apparatus sensing

Control room perimeter

Teleprotection overMPLS with FOX615

1

2

3

4

7

xOpportunities to explore with digital substations- Process bus- Cyber security- MPLS/TP teleprotection- PMUs- Asset management- MESH industrial Wifi communication- Primary apparatus sensing

“A digitalized substation (no digital substation) doesn´t considers thegray areas!”

Asset Management

PMU and PDCs

WiFi Industrial

6

5

Page 5: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

—A full Digital Substation

December 11, 2017 Slide 5

The resources available on an IEC 61850 station and process bus application with ABB Ability

AB

BA

bili

tyo

nd

igit

alsu

bst

atio

njo

urn

ey

• All the control copper cables from VTs, CTsand apparatus (circuit breaker anddisconnectors) to the control room arereplaced by optical fibers

• The SAM600 MUs converts the analog data from theswitchyard (voltage and current) in digital signalsprovided by the SMV protocol. The binaries inputsand output are, as well, encoded in GOOSE messagesover the Ethernet network and carried out togheterSMV data.

• The RELION protection and control IEDs offers 4redundant communication networks with zerolatency and switchover, avoiding loss ofinformation in this critical mission system incase of failures N-1

• The MicroSCADA supervisory system get data from theIEDs and show the real time status of the substationvia the single line diagrams, event and alarm lists. Thearchitecture of such system contains 2 GPS clocks tooffers a 1 microsecond synch time to the entirenetwork architecture

LEVEL 0The substationswichyard

LEVEL 0The SAM600 merging unitsIEC 61850-9-2 standard

LEVEL 1Control roomProtection and control IEDs

LEVEL 2Control roomMicroSCADA supervisorysystem

1

2

3

4

ABB AbilityTM

On Prem or Cloud

Page 6: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

—A full Digital Substation

December 11, 2017 Slide 6

The benefits overview

Sceneries: From conventional to digital What happen inside the control room? The direct impacts of a digital substation

Page 7: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

IEC 61850-8-1 and 9-2 togheterProtocols and Ethernet allocation

December 11, 2017 Sources: ABBSlide 7

The station and process bus togheter offers thefollowing services. using the 7 OSI layers:

Vertical communication over MMS: Data exchangeamong IEDs and supervisory system;Horizontal communication with GSE messages:Information between the IEDs;Process communication: GSE for binary signalsbetween the IEDs and the merging units, SMVmessages for analogs such as currents and voltages;IEEE 1588 (PTP) for devices synchronism, accuracyaround 1 µs;Network redundancy in IEC 62439-3 standard (PRPand HSR).

Protocols and services

1

2

3

GOOSE

SV,GOOSE

Bay 1

Processbus

Station bus

MergingUnit

Prot &CtrlDevices

StationComputer

Gateway

Bay n

SAM600SAM6004

Page 8: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

The sampled values in process busProtocols and Ethernet allocation

December 11, 2017 Sources: ABBSlide 8

Which signals are transmitted in a SMV frame?Four currents, four voltages and their qualityinformation.

Merging units and SMV according IEC 61850-9-2LE

1

984 bitsThis is the size of atypical SMV frame

4800It´s the numberof samples in onesecond in a 60Hzfrequency rate

5Mb/sIt´s the Ethernetnetworkbandwidthallocated for asingle SMV frame

SMV frame captured with the IEC61850 State of art testing toolITT600

Page 9: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

—Usage of PRP and HSE according IEC 62439-3Communication network topologies

December 11, 2017 Slide 9

PRP

HSR

Recommended to stationbus

Recommended toprocess bus

Page 10: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

Unauthorized access or attackCyber security approaches

December 11, 2017 Slide 10

Page 11: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

How to deal to cyber hazards & standardsCyber security approaches

December 11, 2017 Slide 11

IEC 62443*IEEE 1686 IEC62351* NERCCIP

There´s different standards to deal to sensitive data protection in a substation. These mechanisms are aligned to the digitalsubstation philosophy once the data and network communications were expanded with the introduction of process bus. Anyway, more

attention is requited from utilities regarding this issue

Page 12: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

ABB’s IEC 61850 digital substation experienceReference cases

December 11, 2017 Slide 12

Pilot installationBraemar, AUGIS NCIT,670series

Pilot installationLaufenburg, CHGIS NCIT,670series, REB500

Pilot installationSvK, SEDCB with FOCS,670series

Pilot installationCHGIS NCIT,670series, 3rd party

Pilotinstallation UKGIS NCIT,670 series

Pilot installationNehden, DE3rd party NCIT,REB500

Real installationLoganlea, AUGIS NCIT,670series, REB500

Real installationMillmerran, AUGIS NCIT,670series, REB500

Pilot installationTPC, TWSAM600670series, 3rd party

Real installationBulli Creek, AU*GIS NCIT,670series, REB500

2009 2010 2011 2012 2013 2014 2015 2016 2017

Real installationUKSAM600, FOCS670series, 3rd party

Pilot installationCN (several)DCB with FOCS3rd party

Pilot installationVattenfall, SEAIS 3rd party NCIT,670, 630, 615series

Pilot installationUSDTB with FOCS,SAM600, 670 series

* 3 more projects under commissioning by utilityPilot projects are installations to verify technology and compare to traditional systemsReal projects are installations without traditional backup

Pilot installationNLGIS NCITL+G revenue meter

Pilot installationTPC, TWSAM600670series, 3rd party

Pilot installationBRSAM600670series

Real installationINSAM600670, 615 series

Page 13: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

Stand-alone merging units pilot projects executed by ABB Brazil: ISA/Brazil and ICE/Costa RicaReference cases

December 11, 2017 Slide 13

Project description

- SAM600 installation in existing line transmission

Pilot experience

- Equipment installed and successfully commissioned inJune 2017

Stand-alone merging unit in Brazil

Project description

- SAM600 installation in existing capacitor bank 34,5kV

Pilot experience

- Equipment installed and successfully commissioned in July 2017

Stand-alone merging unit in CostaRica

Page 14: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB

First full digital substation in South AmericaAtlas Juazeiro

December 11, 2017 Slide 14

- A 230kV substation composed by 2 transmission lineand 1 power transformer;

- The solution applies all resources of IEC 61850-8-1 and9-2:

§ PRP network redundancy for station bus using Relion IEDsand MicroSCADA;

§ HSR network redundancy for process bus applying SAM600merging units;

§ PTP synchronization concerning about 1 us of accuracy;

§ Network traffic optimization for better performance;

§ SMV and GSE available in the process bus network;

§ Independent busbar voltages process bus network;

§ No switches (failure points) in process bus application, in amore robust solution including cyber security approach;

§ Flexible naming for Logical nodes and data objects;

§ Totally IEC 61850 Edition 2 compliant.

Atlas Juazeiro substation

Page 15: JULIO OLIVEIRA, ABB POWER GRIDS – GRID AUTOMATION ... Oliveira_ABB_SE... · IEC 61850-8-1 and 9-2 togheter Protocols and Ethernet allocation December 11, 2017 Slide 7 Sources: ABB