jpkenny subsea system model that worked 240310

Upload: zarean

Post on 06-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    1/19

    A Model That Worked

    Brian TaylorSnr Subsea Systems Engineer, J P Kenny

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    2/19

    What is a System?

    Definition

    An (assembly or) combination of interrelated elements (orparts) working together toward a common objective.

    rgo, ystem ng neer ng s

    The (design and) implementation of (production) systems

    that require the integration of diverse and complex tasks.

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    3/19

    Project Drivers

    Project

    Development

    System

    Engineering

    Process

    Development

    Phasing

    Life Cycle

    TheSystem

    Design Basis

    Team

    Life CycleIntegration

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    4/19

    System Definition

    DesignIntent

    System Drivers

    Flow Assurance

    Materials

    DesignPhilosophies

    Detailed Design

    ontro Construction/Installation

    Commissioning

    Operations

    IMR

    Inspection

    Maintenance

    Repair

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    5/19

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    6/19

    System Engineering Management

    O erations &

    The Traditional Approach

    Requirements

    Analysis

    Concept

    System Design

    FEED

    qu pmen

    Engineering

    Detail Design

    es

    Integration

    Manufacture /Test &

    Integration

    ns a a on

    Commissioning

    Commissioning& Operation

    Time

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    7/19

    Breaking with Tradition...

    RISER

    QUICK CO NNECT /DISCONNECTTURRETSOFEC

    INSTALL ATION ACTIVITIESCS O

    SHUTTLE TANKERPETRO-CANADA

    OFFL OADING

    SBR /PCL

    125,000bopd PROCESSSBR /PCL

    SWIVELSOFEC STEEL VESSEL

    SBR /SHIPYARD

    TRANSOCE ANE XPLORERDRILL RIG

    TERRA NOVA

    RESE RVOIR E NGINEE RINGPC /HES

    DOWN HOL E-WORKHES

    XMAS TREE SF MC

    'HOST'TE MPL ATE /MANIFOL DKOS

    OPEN 'GL ORY HOLE 'CS O

    MOORINGSSOFEC

    PIL E D ANCHORS

    FLEXIBLE FLOWLINESCS O

    PC - PE TRO-CANADA

    C SO - COFL EX IP STE NA OFFSHORE

    SB R - SHAWMONT BROWN & ROOT

    H E S - HAL L IBURTON ENER GY SE RVIC ES

    PC L - P C L C O N ST R UC T O R S

    F MC - FMC (SOFE C, K OS)

    DC - DORIS CONPRO

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    8/19

    The Jordan Wheel

    Subsystems

    Equipment Vendor Engineer

    Lead Engineers:

    Materials Controls

    Commissioning Operations Communications Flow Assurance

    Interface Engineers

    Technical Integrity Group

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    9/19

    What is the TIG?

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    10/19

    Questions......

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    11/19

    Workshop

    Its discussion time........

    We will spend the next 30 mins or so split into 2 groups

    Grou 1 Grou 2

    Suggested key words:- Responsibilities

    Ownership

    Deliverables (e.g. P&ID,

    Philosophies, Design Basis etc) Input & Influence [on project

    processes]

    Gate / Peer Reviews

    Suggested key words:- Integrated Team

    System Manager

    Current project s [examples of

    use] Opportunity [to adopt as

    industry approach]

    Scaled [down for a smallproject]

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    12/19

    Conclusions

    We will record any outcomes from today's workshop

    and present them to the SUT for their use

    Thank you for your time and participation

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    13/19

    Society for Underwater

    Technology

    13

    Output fromWorkshop

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    14/19

    Group 1

    Frame how the systems engineers responsibilities progress through the projectlifecycle.

    PHASE 1:

    Definition of project design basis.

    Engineering concept definition / functionality.

    Take reservoir characteristics and provide to FA engineer FA design basis.

    14

    System manager frames the opportunity.

    Develop a high level concept to prove commerciality of project.

    Feed into overall value of project (NPV, R01, etc).

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    15/19

    Group 1

    PHASE 2:

    Generate alternative layouts for subsea architecture.

    Enhance project design basis, philosophies, P&IDs and strategies. Develop Subsea design and Pipeline design.

    Constraints on project contracting strategy, scheduling drivers andgovernment issues etc.

    ec n ca qua ca on program.

    Screen options, both internally and externally. Select preferred option andprovide recommendation.

    Conduct Pre-FEED surveys.

    Define technical specifications that need to be developed in Phase 3(FEED ITT package).

    System engineer ensures integrity of design.

    15

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    16/19

    Group 1

    PHASE 3:

    FEED

    Driver to attain scope definition. Develop a schedule.

    Integration of all disciplines:

    Functional engineer.

    O erations.

    Flow assurance. Precommission / IMR.

    Project Execution Plan Role &Responsibilities.

    Prequals verification and assurance program.

    ITT procurement packages.

    Subsea Equipment Vendors, Umbilical Vendors, etc. Long Lead Items based on schedule constraints.

    Class III established.

    Final Investment Decision [FID].

    16

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    17/19

    Group 1

    PHASE 4:

    Execution.

    Award and manage packages. Interface management.

    Ensure project support is in place and processes are clearly defined.

    System verification activities:

    Design reviews.

    Monitoring and assessing Fit for Purpose

    SIT

    Constructability and installability.

    17

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    18/19

    Group 2

    Current Projects and how the system is managed:

    Pluto

    Systems manager Process and FA

    Materials / integrity

    Operations

    Commissioning

    I/F management

    Gorgon

    Engineering management

    Standard guidelines

    WEL SSF Integrity Team (TIAs) Centralise TIAs by project at the project base

    Integrated team.

    18

  • 8/2/2019 JPKenny Subsea System Model That Worked 240310

    19/19

    Group 3

    Does the TIG work?

    There appear to be lots of chiefs is this extra responsibility over there normaldiscipline role?

    There has to be a facilitator for the TIG. But with what level of responsibility?

    The process needs to be well defined before project kick-off

    Lessons learnt from various projects (see group 2) should be compiled to see if it

    Pros of TIG type & of Traditional type Cons of TIG type & of Traditional type

    Communication is key to the TIG

    Project management systems must be coordinated across the differentdisciplines/contracts

    Interfaces have to be filtered, meaningful and given prioritised accordingly

    Empowerment people in the TIG must be given the authority to make a decisionand follow it through

    Scaling does not appear to be an issue and the TIG would seem lend itselfparticularly well to projects with smaller client team

    19