jpkenny subsea system model that worked 240310
TRANSCRIPT
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
1/19
A Model That Worked
Brian TaylorSnr Subsea Systems Engineer, J P Kenny
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
2/19
What is a System?
Definition
An (assembly or) combination of interrelated elements (orparts) working together toward a common objective.
rgo, ystem ng neer ng s
The (design and) implementation of (production) systems
that require the integration of diverse and complex tasks.
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
3/19
Project Drivers
Project
Development
System
Engineering
Process
Development
Phasing
Life Cycle
TheSystem
Design Basis
Team
Life CycleIntegration
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
4/19
System Definition
DesignIntent
System Drivers
Flow Assurance
Materials
DesignPhilosophies
Detailed Design
ontro Construction/Installation
Commissioning
Operations
IMR
Inspection
Maintenance
Repair
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
5/19
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
6/19
System Engineering Management
O erations &
The Traditional Approach
Requirements
Analysis
Concept
System Design
FEED
qu pmen
Engineering
Detail Design
es
Integration
Manufacture /Test &
Integration
ns a a on
Commissioning
Commissioning& Operation
Time
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
7/19
Breaking with Tradition...
RISER
QUICK CO NNECT /DISCONNECTTURRETSOFEC
INSTALL ATION ACTIVITIESCS O
SHUTTLE TANKERPETRO-CANADA
OFFL OADING
SBR /PCL
125,000bopd PROCESSSBR /PCL
SWIVELSOFEC STEEL VESSEL
SBR /SHIPYARD
TRANSOCE ANE XPLORERDRILL RIG
TERRA NOVA
RESE RVOIR E NGINEE RINGPC /HES
DOWN HOL E-WORKHES
XMAS TREE SF MC
'HOST'TE MPL ATE /MANIFOL DKOS
OPEN 'GL ORY HOLE 'CS O
MOORINGSSOFEC
PIL E D ANCHORS
FLEXIBLE FLOWLINESCS O
PC - PE TRO-CANADA
C SO - COFL EX IP STE NA OFFSHORE
SB R - SHAWMONT BROWN & ROOT
H E S - HAL L IBURTON ENER GY SE RVIC ES
PC L - P C L C O N ST R UC T O R S
F MC - FMC (SOFE C, K OS)
DC - DORIS CONPRO
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
8/19
The Jordan Wheel
Subsystems
Equipment Vendor Engineer
Lead Engineers:
Materials Controls
Commissioning Operations Communications Flow Assurance
Interface Engineers
Technical Integrity Group
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
9/19
What is the TIG?
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
10/19
Questions......
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
11/19
Workshop
Its discussion time........
We will spend the next 30 mins or so split into 2 groups
Grou 1 Grou 2
Suggested key words:- Responsibilities
Ownership
Deliverables (e.g. P&ID,
Philosophies, Design Basis etc) Input & Influence [on project
processes]
Gate / Peer Reviews
Suggested key words:- Integrated Team
System Manager
Current project s [examples of
use] Opportunity [to adopt as
industry approach]
Scaled [down for a smallproject]
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
12/19
Conclusions
We will record any outcomes from today's workshop
and present them to the SUT for their use
Thank you for your time and participation
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
13/19
Society for Underwater
Technology
13
Output fromWorkshop
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
14/19
Group 1
Frame how the systems engineers responsibilities progress through the projectlifecycle.
PHASE 1:
Definition of project design basis.
Engineering concept definition / functionality.
Take reservoir characteristics and provide to FA engineer FA design basis.
14
System manager frames the opportunity.
Develop a high level concept to prove commerciality of project.
Feed into overall value of project (NPV, R01, etc).
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
15/19
Group 1
PHASE 2:
Generate alternative layouts for subsea architecture.
Enhance project design basis, philosophies, P&IDs and strategies. Develop Subsea design and Pipeline design.
Constraints on project contracting strategy, scheduling drivers andgovernment issues etc.
ec n ca qua ca on program.
Screen options, both internally and externally. Select preferred option andprovide recommendation.
Conduct Pre-FEED surveys.
Define technical specifications that need to be developed in Phase 3(FEED ITT package).
System engineer ensures integrity of design.
15
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
16/19
Group 1
PHASE 3:
FEED
Driver to attain scope definition. Develop a schedule.
Integration of all disciplines:
Functional engineer.
O erations.
Flow assurance. Precommission / IMR.
Project Execution Plan Role &Responsibilities.
Prequals verification and assurance program.
ITT procurement packages.
Subsea Equipment Vendors, Umbilical Vendors, etc. Long Lead Items based on schedule constraints.
Class III established.
Final Investment Decision [FID].
16
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
17/19
Group 1
PHASE 4:
Execution.
Award and manage packages. Interface management.
Ensure project support is in place and processes are clearly defined.
System verification activities:
Design reviews.
Monitoring and assessing Fit for Purpose
SIT
Constructability and installability.
17
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
18/19
Group 2
Current Projects and how the system is managed:
Pluto
Systems manager Process and FA
Materials / integrity
Operations
Commissioning
I/F management
Gorgon
Engineering management
Standard guidelines
WEL SSF Integrity Team (TIAs) Centralise TIAs by project at the project base
Integrated team.
18
-
8/2/2019 JPKenny Subsea System Model That Worked 240310
19/19
Group 3
Does the TIG work?
There appear to be lots of chiefs is this extra responsibility over there normaldiscipline role?
There has to be a facilitator for the TIG. But with what level of responsibility?
The process needs to be well defined before project kick-off
Lessons learnt from various projects (see group 2) should be compiled to see if it
Pros of TIG type & of Traditional type Cons of TIG type & of Traditional type
Communication is key to the TIG
Project management systems must be coordinated across the differentdisciplines/contracts
Interfaces have to be filtered, meaningful and given prioritised accordingly
Empowerment people in the TIG must be given the authority to make a decisionand follow it through
Scaling does not appear to be an issue and the TIG would seem lend itselfparticularly well to projects with smaller client team
19