john boon zut november 2010. procurement systems the organisation of the interaction between the...
TRANSCRIPT
Procurement Systems
The organisation of the interaction between the purchaser of a new building and the suppliers of goods and services that enable the new building to be created.
2 basic procurement systems:Separated systems: the design of the
building and its construction are procured separately
Integrated Systems: the design and construction are procured from a single company.
Separated system
user
owner
developer
design team
contractor
subcontractor
supplier
Procurement system
financiers
Integrated system
user
owner
developer
design team
contractor
subcontractor
supplier
Procurement system
financiers
In the west, the most common form of procurement system is the separated system.
Design firms are separated from construction firms
It is easier to run a competitive tender process for construction than for design and construction
Until about 1980 in most western countries the professional body (institute) for architects, engineers and quantity surveyors fixed the fees for their services
The most common way of selecting a contractor is for the design team to complete the design and then a bidding process is conducted and the contract awarded to the contractor offering the lowest price.
Design firms are also often selected by bidding
Conventional Design - bid - Build
Feasibility Design Construction
Appointment of design
team
Appointment of contractor
Concept design
Developed design
Constructiondrawings
Within the separated system there is:
Means of selection Price formula
Competitive process (bid) Negotiation
Lump sum fixed price Lump sum with provision for
adjustment for: Variations Cost escalation
Measure & value Formula for negotiating lump
sum Guaranteed maximum price Cost + overheads + profit
With or without gainshare / painshare
Separated system
Feasibility Design Construction
Appointment of design
team
Appointment of contractor
Selection of contractor• competitive tender (bid)• negotiation
Lump sum fixed price
The contractor undertakes to build the building as designed with no adjustment allowed to the price unless the client requests a change to the design.
Not normally used as the contractor has to price for risks they are unable to control
Lump sum with provision for adjustment of the price for:
1. Errors in the contract documents If errors are found in the drawings, specification or schedule of
quantities the price is adjusted for this.
2. Changes to the clients design requirements
3. Costs incurred by the contractor due to being delayed by the client / design team
4. Changes in the price of labour and materials By reference to a price index By comparing actual costs to those allowed in the bid price
Contracts involving 1 – 3 are common
4. is only used in contracts with a long time span or in an environment of high inflation
Measure and value (schedule of prices)
Prices for units of quantity of the work are agreed before the contract is signed (by bidding or negotiation)examples: $200 per m3 of concrete
$23 per m of 100 * 50mm timber framing$135 each per door.
As the work proceeds it is measured and the contractor is paid according to the amount of work done.
Common in civil engineering projects (roads, dams etc) unusual in building projects
Formula for agreeing lump sumTypical process Contractors price build up1. A bid process is run in which
the competing contractors submit their: Preliminary and general costs ($) Overhead % Profit %
2. The contractor with the lowest bid is selected
3. As the design is completed the contractor conducts bidding exercises for each sub-contract package – the lowest bidder is selected.
4. When the design is complete and all sub-contract packages bid a lump sum (with provision for adjustment) is agreed
Preliminary and general items Project managers and
supervisors Site accommodation Cranes and other large plant Insurance etc
Cost of work done by sub-contractors
Contractors overhead costs (%) Head office etc
Contractors profit (%)
Used to enable the contractor to be appointed before the design is complete
Formula for agreeing lump sum + guaranteed maximum price
Same as last but the contractor guarantees the maximum price the client will pay (GMP)
Often there is provision for the client and contractor to share the savings in cost below the GMP
Formula for agreeing lump sum + guaranteed maximum price
Feasibility Design Construction
Appointment of design
team
Contractor selected and GMP agreed
Cost + overheads + profitSimilar to the last:
Overheads and profit % are agreed in advance by bidding or negotiation.
All costs are reimbursed to the contractor + % as work proceeds
Sometimes a “target outturn cost” (TOC) is agreed and the contractor and client:share the saving below the TOC (gainshare)share the additional costs over the TOC
(painshare)