© 2018 Aker Solutions
Johan Sverdrup
Hook-Up
Modifikasjonskonferansen, 2018
Kjetil Vågen, Senior Engineering Manger,
Aker Solutions
© 2018 Aker Solutions 09 March 2018 Slide 2
Johan Sverdrup Phase 1
Riser platform
22.000 ton
FC contract
Install: 2018
Process platform
26.000 ton
FC contract
Install: 2019
Drilling/WHP
21.500 ton
EPC contract
Install: 2018
LQ/Utility
19.000 ton
EPC contract
Install: 2019
EPC EPma EPma
Living Quarters (LQ) Process (P1) Drilling (DP) Riser (RP)
EPC
© 2018 Aker Solutions
Hook Up Preparations - Milestones and Improvement Strategies
09 March 2018 Slide 3
Define min/max req.
Base Scope defined on
Work orders
Base scope work orders
verified at site
Status on Base Scope
materials
Suggest COW priority
Base scope materials
available
Cable pulling and coiling
philosophy
Efficient handling of
insulation boxes
Front loading work order
production
Start Up strategy
Temporary systems
Continuity of resources
through all phases
Temp placement of
caissons on jacket
Prefab Process
Quality survey and laser
scanningSecure all interfaces with
Crane and Lift supplier
Digital NDT
Secure participation in
Site team with offshore
key resources
Secure strategy for
preservation
Improve HSE on work
close to live systems
Secure uninterrupted
power supply for
Construction
Implement strategy to
control carry over work
Establish Space
management plan
Secure
implementation of
HUC preparation
documents at site.
Logistic planning
process with all
vendors at Dusavik
MC
sta
tus a
t
sa
il a
way
Wo
rk
Pre
pa
rati
on
Infrastructure and interfaces
Efficient
Hook Up
offshore
Logistic
© 2018 Aker Solutions
Infrastructure and Interfaces- A Part of a Bigger Picture
09 March 2018 Slide 4
Commissioning
FC contractorHook-Up
Lifts
RP Jacket HUC DP
Pit-stop cranes
EPMAHeavy lift
Aker Solutions,
Kværner &
Beerenberg
© 2018 Aker Solutions 09 March 2018 Slide 5
Infrastructure and Interfaces
SM02
Ready For first
Access to
RP from Flotel
SM03
Ready For full
Access to
RP from Flotel
7/5 15/5 1/6
OM31
RP
Cranes
operative
Timeline
15/6
HM01
Infrastructure
in place
Installation of modules Access limited Limitation in infrastructure Full access
10 operators
2 Supervisors
75 operator
26 Management and foremen
Total POB 100
Full mobilization
150 operator
50 Management and foremen
Total POB 200
LIMITATIONS IN THIS PERIODE
IS OFFICES - TO BE MITIGATED
3/5
Mobilisation
Onshore at
Flotel
25/4
Mobilisation
At Thialf
© 2018 Aker Solutions
Work Preparation and Scope of Work
■ The Riser Platform (RP) is delivered in three
modules, therefore main offshore EIT scope
is cable installation.
■ 2700 Cables full pull / uncoil: 230 000
meters■ Full pull - 870 cables
■ Coiled - 1370 cables
■ Demolition 400 cables.
■ 1000+ piping spools
09 March 2018 Slide 6
© 2018 Aker Solutions
Work Preparation and Scope of Work
09 March 2018 Slide 7
© 2018 Aker Solutions
Mechanical Completion Status and Site Verification
09 March 2018 Slide 8
Mechanical trades
ISO trades
Cable Verification Status
© 2018 Aker Solutions
Mechanical Completion Status and Site Verification
09 March 2018 Slide 9
Construction
progress: 99,7 % (4 February)
© 2018 Aker Solutions
Main Logistics
Equipment, materials and tools need to be
loaded on board:
▪ Modules (Korea/Haugesund)
▪ Thialf (Rotterdam)
▪ Safe Zephyrus (Mekjarvik/Averøya)
▪ Supply vessels from Dusavika
09 March 2018 Slide 10
RQ0 and RM01 on
DW Mighty Servant 3
RC01 and RC02 on DW
White Marlin
Heerema Thiealf
Heerema Thiealf
© 2018 Aker Solutions
MTO and Logistics
09 March 2018 Slide 11
© 2018 Aker Solutions
Hook Up Preparations - Milestones and Improvement Strategies
09 March 2018 Slide 12
Define min/max req.
Base Scope defined on
Work orders
Base scope work orders
verified at site
Status on Base Scope
materials
Suggest COW priority
Base scope materials
available
Cable pulling and coiling
philosophy
Efficient handling of
insulation boxes
Front loading work order
production
Start Up strategy
Temporary systems
Continuity of resources
through all phases
Temp placement of
caissons on jacket
Prefab Process
Quality survey and laser
scanningSecure all interfaces with
Crane and Lift supplier
Digital NDT
Secure participation in
Site team with offshore
key resources
Secure strategy for
preservation
Improve HSE on work
close to live systems
Secure uninterrupted
power supply for
Construction
Implement strategy to
control carry over work
Establish Space
management plan
Secure
implementation of
HUC preparation
documents at site.
Logistic planning
process with all
vendors at Dusavik
MC
sta
tus a
t
sa
il a
way
Wo
rk
Pre
pa
rati
on
Infrastructure and interfaces
Efficient
Hook Up
offshore
Logistic
© 2018 Aker Solutions
CopyrightCopyright of all published material including photographs, drawings and images in this document remains vested in Aker Solutions and third party contributors as appropriate. Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor used in any manner without express prior permission and applicable acknowledgements. No trademark, copyright or other notice shall be altered or removed from any reproduction.
DisclaimerThis Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and uncertainties that could cause actual results to differ. These statements and this Presentation are based on current expectations, estimates and projections about global economic conditions, the economic conditions of the regions and industries that are major markets for Aker Solutions ASA and Aker Solutions ASA’s (including subsidiaries and affiliates) lines of business. These expectations, estimates and projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” or similar expressions. Important factors that could cause actual results to differ materially from those expectations include, among others, economic and market conditions in the geographic areas and industries that are or will be major markets for Aker Solutions’ businesses, oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency exchange rates and such other factors as may be discussed from time to time in the Presentation. Although Aker Solutions ASA believes that its expectations and the Presentation are based upon reasonable assumptions, it can give no assurance that those expectations will be achieved or that the actual results will be as set out in the Presentation. Aker Solutions ASA is making no representation or warranty, expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Aker Solutions ASA nor any of its directors, officers or employees will have any liability to you or any other persons resulting from your use.
Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as the common brand or trade mark for most of these entities. In this presentation we may sometimes use “Aker Solutions”, “we” or “us” when we refer to Aker Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutions company.
09 March 2018 Slide 13
Copyright and Disclaimer