j im-1003| 49mid.aar.com/pdfs/chapter_7_forms_msrp-j_14.final.pdfm-1003 aar manual of standards and...
TRANSCRIPT
M-1003
AAR Manual of Standards and Recommended Practices Specification for Quality Assurance
C H A P T E R 7
Rev. Xtn* QA-7.1
ASSOCIATION OF AMERICAN RAILROADS QUALITY ASSURANCE NONCONFORMANCE REPORT
7.3.4.1 Senal No.
7.34 2.1 Date
7 34.2.1 Reporting
Company 73.4.2 1 Reporting
Company Location
7.3.4.2.2 Contractor 7.3.4.2.2 Contractor Plant Location
7 3.4 2.3 item Description 7 3.4.2 3 AAR Spec. Code or Standard No.
7.3.4.2.4 Contractor's pari number, pattern numbers, drawing numbers, RMA tt, P0#, and/or other identifying infomiation.
7.3.4.27
New O
Reconditioned •
Requalified •
7.3.4.2.5 Quantity Received 7.3.4.2 5 Quantity Inspected
7.3.4 2.5 Quantity Rejected 7.3.4.2.6 Matena! inspected by Contractor'
Yes No If Yes. date of inspection
7.3 4 2 8 Senal Number. Identification Mark, or Car No.
7 3 4 2 9 Nonconformance Descnplion 7 3 4 2 10 Disposition of Item (Returned. Repaired. Scrapped Other)
7 3.4 3 Venfy copy sent to Contractor Infofmation. contractor
Name and Title
Comoanv Name
Street
Citv. State, ZIP
Person initiating daim Name
Signature Address
Title City. Slate ZIP
Email Phone
When not using the on-line system, send to AAR QA Program Coordinator, TTCI. 55500 DOT Road. Pueblo. CO 81001 or qa@aar com.
08/2014
Fig. 7.1 Quality Assurance Nonconformance Report (NCR)
J iM-1003| 49
C H A P T E R 7
AAR Manual of Standards and Recommended Practices Specification for Quality Assurance
M-1003
QA-7.2
ASSOCIATION OF AMERICAN RAILROADS QUALITY ASSURANCE NONCONFORMANCE RESPONSE REPORT
7.6 2 1 Serial No.
76.2 2 Date
7.6.2.3 Contractor 7 6.2 4 Reporting Company
7.6.2.3 Location 7 6 24 Location
7.6.2.5 Date QA-7.1 was filed 7.6.2.6 Quantity Rejected
7.6 2.7 Descnption of nonconfomance (from QA-7.1)
Action Required Description of Action Taken Date
7.6.2.8 Clearly define the nonconfor
mance that led to the rejection
7.6.2.9 Clearly define Ihe actions taken for disposition.
7.6.210 Clearly define the root
cause(s) that resulted in the noncon
formance.
7.6 2.11 Clearly define the corrective action(s) taken that will eliminate the root cause(s)
7 6.212 Clearly define the follow-up plan(s) that will ensure the effectiveness of Ihe corrective action(s) taken in Its/their permanence cause(s).
Note Contractor is not confined to using only the spaces above and is encouraged to use attachments.
7.6.2 13 Ensure that the QA-7.1 report initiator has been sent a copy of the completed QA-7.2. Including a copy of the original QA-7.1 report. Also
ensure that the customer's Purchasing and Mechanical Department managers have been sent a copy of the QA-7.1 and completed QA-7.2.
Signed by Management Representative Title
When nol uang the on-line system, send onginal to AAR QA Program Coordinator, TTCI. obSOO DOT Road. Pueblo. CO 81001 or [email protected]. Include a copy
of the onginal QA-7 1 report.
Fig. 7.2 Quality Assurance Nonconformance Response Report
J IM-10031 50 08/2014
\ A R Manual of Standards and Recommended Practices Specification for Quality Assurance
M-1003 ' C H A P T E R ?
QA-7.3
ASSOCIATION OF AMERICAN RAILROADS QUALITY ASSURANCE EVALUATION RESPONSE FORM
Date Q A 7 1 / Q A 7 . 2
Senal No.
Reporting company Contractor
Location Location
Person performing review
QA 7 2 received per 7.61 requireinents? n YES D NO
If no. response was received after fiow many days?
[~| The above-listed QA 7 2 tias been reviewed and. in the opinion of the reviewer the proposed corrective action has been found to be proper and adequate As such, the QA 7 1 is considered closed
OR
The above-listed QA 7.2 has been reviewed and in the opinion of the reviewer, the proposed corrective action (check one)
r~| Does NOT adequately identify the root cause Comments;
Does NOT propose a corrective action that will eliminate the identified root cause. Comments
Venfy copy sent to Contractor Information: contractor
Name and Title
Contractor Email
Company Name
Street
Citv. State. ZIP
Person reviewing QA 7.2 Name
Signature Address
Trtte City, State ZIP
Phone
When not using the on-line system, send copy to AAR Program Coordinator, TTCI, 55500 DOT Road, Pueblo. CO 81001 or [email protected].
0tV2014
Fig. 7.3 Quality Assurance Nonconformance Response Evaluation Form
J IM-10031 51
A A R Manual of Standards and Recommended Practices Specification for Quality Assurance
C H A P T E R ? ' M-1003
Initiator Encounlers prematurely failed material or service from applicable component list as published quarterly in tfie 'Quality Assurance Certified Companies" Circular.
Initiator Completes NCR form (Fig. 7.1) at http:/7aariifx.netor mails a copy to Contractor and to AAR QA Program Coordinator
Initiator Discuss failure witfi contractor and determine disposition of material.
T Initiator
If material cannot be held or returned for Contractor investigation, document circumstances
1 Initiator
Monitor Contractor response and solicit action to ensure response is received as per paragraph 7.6.1
Initiator Evaluate response at hltp//iirx aar.net or, using Fig 7 3, ensure a copy of all completed forms is sent to the AAR Program Coordinator and the Contractor
T
Advise QA Program Coordinator
initiator File responses and retain copies as per paragraph 7 61 for auditor verification
T Contractor
Discuss failure with initiator and determine disposition of material
T
1 QA Program Coordinator
File NCR
Contractor Investigate failure and develop response as per paragraph 7.6 and document response on form Fig 7.2
Contractor Respond at http / aar iirx.net or send response on form Fig 7 2 with a copy of the Initiator's completed form Fig 7.1 to AAR QA Program Coordinator and to the Initiator
Contractor Monitor Initiator evaluation to ensure acceptability of response as per paragraph 7 7.3
QA Program Coordinator
Monitor Contractor response.
Contractor File responses and retain copies as per paragraph 7.6.1 for auditor venfication
QA Program Coordinator Advise QA Committee of NCR status.
Fig. 7.4 Process map for nonconformance reporting
J IM-10031 52 08/'2014