iv.m.2 wastewater (3rd screencheck) - los...
TRANSCRIPT
CityofLosAngeles IV.M.2‐1 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
IV.M.2 WASTEWATER
1. INTRODUCTION
Thissectiondiscusses thewastewatersystemfortheproposedProjectsiteandsurroundingarea
and evaluates potential Project impacts on the existing wastewater system maintained by the
BureauofSanitation (BoS)of theCityofLosAngelesDepartmentofPublicWorks(LADPW).The
analysisbelowisbased,inpart,onthetechnicalreportpreparedbyKPFFConsultingEngineersfor
theproposedProject, entitledBarlowReplacementHospitalandMasterPlan:Wastewater (2010).
ThatreportisincludedasAppendixIV.M.2ofthisDraftEIR.
2. REGULATORY FRAMEWORK
a. City of Los Angeles General Plan Framework
The City of Los Angeles General Plan Framework Element is a plan for long‐term growth that
establishes a City‐wide context for guiding the update of Community Plans and General Plan
elements. The Framework Element characterizes the reuse of gray water as an opportunity to
reducewastewater generation, although it notes that systems should be designed to ensure that
graywater does not enter the stormdrain system. Goal 9AwithinChapter 9, Infrastructure and
PublicServices,oftheGeneralPlanFramework,andtherelatedobjectivesandpoliciesaddressthe
needforadequatewastewatercollectionandtreatmentcapacityfortheCityandinbasinstributary
toCity‐ownedwastewatertreatmentfacilities.1
b. City of Los Angeles Integrated Resources Plan (IRP)
TheIntegratedResourcesPlan(IRP)isaplanningdocumentpreparedundertheleadershipofthe
BoSandtheDepartmentofWaterandPower(DWP)tocomprehensivelyaddresstheCity’swastewater,
stormwatermanagement,andrecycledwaterneeds.
PhaseIoftheIRPprojecttookplacebetween1999and2001andaddressedtheinterrelationshipsoftheLos
Angelesbasin‐widewater,wastewater,andstormwatersystemsand theneedsof theseprograms toserve
thepopulationofLosAngeles through theyear2020(the IntegratedPlan for theWastewaterProgram,or
IPWP). The IPWP addressed the complex interrelationships of the water, wastewater and stormwater
systemsandtheanticipatedneedsoftheCityintheyear2020.PhaseIstudiesfocusedongapsintheability
of the City’s currentwater resources systems to serve future populations and focused onways to bridge
1 City of Los Angeles, General Plan Framework Element, Chapter 9: Infrastructure and Public Services,
http://cityplanning.lacity.org/cwd/framwk/chapters/09/09.htm#Wastewater.2001.
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐2 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
those gaps throughplanning of future facilities, resourcemanagement, and demandmanagement. Phase I
also resulted in the development of a set of performance‐based guiding principles for future planning of
waterresourcesmanagement.Theguidingprinciplepertainingtowastewaterisasfollows:
• Build new wastewater facilities “upstream” in the system. New or expanded wastewater
facilities will be needed. Placing these facilities upstream in the system offers greater operating
flexibility systemwide, increases opportunities to beneficially reuse treated effluent, and reduces
dependencyonimportedwaterforusessuchasirrigation,industrialprocessingandcooling,etc.
PhaseIIof theIRP,undertakenbetween2002and2006,encompassedthepreparationoftechnicalstudies
andtheidentificationandcomparisonofdifferentalternativeapproachestomanagementoftheCity’swater
resources.Fourfinalalternativesweredeveloped,basedonthestudiesundertakeninPhaseI,todefinethe
appropriateinfrastructure,policies,andprogramsforimplementationby2020.
The Los Angeles City Council certified the Final EIR in November 2006 and adopted a final
alternative,theApprovedAlternative(Alternative4).Alternative4isintendedtoincreasewastewater
collection and treatment capacity, water reclamation storage and beneficial use, water conservation, and
runoffmanagementopportunities.
The IRP is documented in a collection of reports that address facilities planning, financial planning, and
environmentaldocumentation.2
c. Planned Capital Improvements
Wastewater initiallyfirst flowsthroughsmall‐diametersewerscalledlaterals,orlateralpipelines,
thatconveywastewater fromresidencesorbusinesses into larger‐diametersewermainsbeneath
streets, alleys, and other rights‐of‐way. Mains in turn connect to collectors and trunk lines that
dischargeintointerceptorsewers.Interceptorsewers,whichmaybeeightfeetormoreindiameter,
conveywastewatertotheCity’streatmentandwaterreclamationplants.
i. Wastewater Capital Improvement Program
Every 10 years, the Bureau of Sanitation of the City of LosAngelesDepartment of PublicWorks
updatesthe10‐YearCapitalImprovementProgramtoaddressplannedreplacement,rehabilitation,
andexpansionofthemajorwastewatercollectionsystemandtreatmentfacilitieswithintheCity’s
service area. Many of these improvements are necessary for compliancewith State and Federal
2 CityofLosAngeles,IntegratedResourcesPlan(IRP),http://www.lacitysan.org/irp/facilitiesplan.htm.2006.
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐3 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
CleanWater Act regulations; improvements are then carried out by various divisionswithin the
Bureaus of Sanitation and Engineering. The most recent update, the Wastewater Capital
Improvement Program: Fiscal Year 2006/2007–2015/2016, defines improvements scheduled
through2016tothecollectionsystem,pumpingplants,andthefourtreatmentplantsthatservethe
area.3Improvementsplannedforthecollectionsystemincludeprimarysewerprojects(i.e.,mains,
ormunicipally‐ownedpipes18ormoreinchesindiameter),secondarysewersystemprojects(i.e.,
pipeslessthan18inchesindiameter,servingresidentialandcommercialproperties),reliefsewers,
andemergencyprojects.
ii. Collection System Settlement Agreement
In 2004, the City of Los Angeles reached a settlement agreement with local governments and
environmental organizations to replace aging and substandard secondary wastewater system
infrastructure, or pipes less than 16 inches in diameter serving residential and commercial
properties, over the course of 10 years.4 TheAgreement identified agingwastewater systems in
needofrehabilitationorreplacementthroughouttheCity’sservicearea.Approximately2.46miles
ofwastewaterpipelinesthroughouttheSilverLake—EchoPark,CentralCityNorth,andCentralCity
areasboundedbyAcademyRoadonthenorth,TempleStreetonthesouth,theLosAngelesRiveron
theeastandGlendaleBoulevardonthewestwereacknowledgedtobemorethan70yearsoldand
tohavereachedtheendoftheiruseful life.ThisareaincludestheProjectsite,andimprovements
are planned for portions of the system in one of the City projects planned under the settlement
agreement (e.g., Secondary Sewer Renewal Program (SSRP) N13). Wastewater infrastructure
improvements under that City project commenced in February 2011, and are expected to be
completedbyJune2012.5
iii. Wastewater System Design Criteria
The City of Los Angeles Bureau of Engineering Sewer DesignManual: Part F establishes design
criteriaforpipeswithintheCity’swastewatersystem.TheSewerDesignManualrecommendsthat
pipesbedesignedforpeakdryweatherflowdepthsoflessthan50percentofpipedepthforpipes
18inchesor less indiameter, to accommodate fluctuations in flowwhile stillmaintainingdesign
3 CityofLosAngeles,DepartmentofPublicWorks,BureauofSanitation,WastewaterCapital ImprovementProgram,
FiscalYears2006/07–2015/16.http://www.lacitysan.org/fmd/WCIP/WCIPBook06‐07.pdf.2006.4 City of Los Angeles, Department of Public Works, Collection System Settlement Agreement,
http://www.lasewers.org/sewers/about/index.htm.2004.5 KPFFConsultingEngineers,pers.com.,February28,2012(basedonlatestCityofLosAngelesProjectInformation
ReportforSSRPN13)
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐4 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
velocities.6 In addition, for purposes of analyzing remaining capacity, wastewater pipes are
consideredconstrained(i.e.,atcapacity)whenflowssurpass75percentofpipedepth,sinceflows
inexcessofthiscancauseinternalpressureandsurchargesinupstreamportionsofthesystem.7
BureauofEngineeringSpecialOrderNo.06‐0691,whichalsosets forthdesigncriteria forgravity
sewers, further states that trunk, interceptor,outfall, and relief sewers (i.e.,wastewaterpipes18
inchesindiameterandgreater)shouldhaveatleasta60‐to100‐yeardesignlife,andsewerlaterals
(i.e.,pipeslessthan18inchesindiameter)shouldhaveatleasta100‐yeardesignlife.8
d. City of Los Angeles Municipal Code
Sections64.11and64.12of theLosAngelesMunicipalCode (LAMC)requireapprovalofasewer
permit,alsocalledanSPermit,priortoconnectiontothewastewatersystem.Newconnectionsare
assessed a Sewerage Facilities Charge based on wastewater flow volume and strength. The
determinationofwastewaterstrengthforeachapplicableprojectisbasedonCityguidelinesforthe
averagewastewater concentrationsof twoparameters,biologicaloxygendemandandsuspended
solids, foreach typeof landuse.Feespaid to theSewerageFacilitiesChargearedeposited in the
City’s Sewer Construction andMaintenance Fund forwastewater‐related purposes including but
notlimitedtoindustrialwastecontrolandwaterreclamationpurposes.
Section64.15oftheLAMCrequiresthataSewerCapacityAvailabilityRequest(SCAR)beperformed
bytheDepartmentofBuildingandSafetywhenasewerpermit issoughtforanewconnectionto
the City's wastewater system, or in the event of a proposed increase in discharge to a public
wastewaterlineorproposedfuturedevelopmentanticipatedtogenerate10,000gallonsormoreof
wastewater per day. A SCAR evaluates the existing wastewater collection system to determine
whether adequate capacity exists to convey project‐generated wastewater to the appropriate
treatmentplant.Ifcapacityisavailable,theDepartmentofBuildingandSafetyacceptsprojectplans
and specifications for plan check; otherwise, projects are placed on a waiting list to receive an
allocation of forthcoming capacity, or applicants are required to construct a connection to the
nearest wastewater line with available capacity. The Department of Building and Safety accepts
project plans and specifications for plan check if the project is on the waiting list, although the
6 KPFFConsultingEngineers,BarlowMasterPlanandReplacementHospital:Wastewater,(2010)4.7 City of LosAngeles, Department of PublicWorks, Bureau of Sanitation,HyperionSewerSystemManagementPlan,
(2009),58.8 CityofLosAngeles,DepartmentofPublicWorks,BureauofEngineering,SpecialOrder006‐0691:PlanningPeriod,
Flow,andDesignCriteriaforGravitySanitarySewersandPumpingPlants, http://eng.lacity.org/docs/sporders/1991/so00691.pdf.1991.
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐5 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
projectmay not connect to the City’swastewater system until capacity is available and a sewer
permithasbeenissued.
3. EXISTING CONDITIONS
a. City of Los Angeles Wastewater Collection and Conveyance
The City of Los Angeles Department of Public Works, Bureau of Sanitation, is responsible for
wastewatercollectionandtreatmentintheCityofLosAngeles,includingtheProjectsite.
The Bureau of Sanitation’s Wastewater Collection Systems Division operates and maintains the
largest wastewater collection system in the nation, serving over 4 million people within
approximatelya600‐square‐mileserviceareaandcomprisingmorethan6,700milesofwastewater
pipes,140,000maintenancestructures,100diversionstructures,and44sewagepumpingplants.
TheCitysystemalsoprovideswastewaterconveyanceandtreatmentservicesto29agenciesunder
contractual agreements. City wastewater pipes range from six to 150 inches in diameter, with
approximatelyfiftypercentofthesystemmorethan50yearsold.9TheBureauofSanitationisalso
responsibleforsystemmaintenance.
The municipal wastewater main beneath Stadium Way adjacent to the Project site is the most
upstreammain for this tributaryareaand therefore initiallyonly serves theProject site (i.e., the
Projectsiteisthefirstconnection).Thereare15availablepointsofconnection/discharge(laterals)
between the Project site and the wastewater main beneath Stadium Way, including 10 for the
eastern Project site and five for thewestern Project site. Six active laterals exist on the eastern
ProjectsiteandtwoactivelateralsexistonthewesternProjectsite;theremainingfourlateralson
theeasternProjectsiteandthreelateralsonthewesternProjectsitedonotcurrentlyappeartobe
inuse.
The wastewater main beneath StadiumWay was constructed at different times in segments of
varying diameters. The oldest remaining portions of the main were constructed in 1917, with
upgraded,largersegmentsintheProjectvicinitydatingtothe1930s,1940s,and1960s.Themost
upstreamsegmentsof thewastewatermain,beneathStadiumWayatScottStreetnear thenorth
end of the Project site, are 8 inches in diameter, increasing to 15 inches in diameter near the
midpoint of the Project site, and then decreasing in size downstream, with 8‐, 10‐, and 12‐inch
segmentssouthoftheProjectsite.Wastewatersystemsarenormallydesignedtosteadilyincrease
9 LosAngelesDepartmentofPublicWorks,AbouttheCity’sSewerSystem,
http://www.lasewers.org/sewers/about/index.htm.2009.
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐6 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
in size downstream, to accommodate a larger number of connections and increasing volume of
discharge.ThevariablesizeofthesystemintheProjectvicinitythereforeconstrainsthesystem’s
capacity,whichisnecessarilylimitedbythesmallestdiametersegments.FigureIV.M.2‐1,Project
VicinityWastewaterCollectionSystem,showstheagesanddiametersofmunicipalwastewatermain
segments adjacent to and downstream of the Project site. From the Project site, wastewater is
conveyedsouthbeneathStadiumWaytoa10‐inchlineinBernardStreetbeforesplittingintoa18‐
inchlineinAlamedaStreetanda15‐inch‐linebeneathCollegeStreet,bothofwhichthendischarge
intoa30‐inchlineinLosAngelesStreet.
b. Project Site Wastewater Collection and Conveyance
AsdiscussedinSectionII,ProjectDescription,ofthisDraftEIR,the25‐acreProjectsiteisdivided
into eastern and western parcels by StadiumWay. The eastern Project site, approximately 10.6
acres, is currently occupied by 29 buildings, including the existing hospital. The hospital and
majorityoftheexistingbuildingsontheeasternProjectsitearelocatedwithintherelativelyflator
gentlyslopedportionsof thesiteclosest toStadiumWay.Mostof thebuildingswereconstructed
before1930aspatientcottages,administrativeoffices,ormaintenance facilities for thehospital’s
predecessor, Barlow Sanatorium. The currently operational 49‐bed Barlow Respiratory Hospital
occupiesabuildingwithportionsconstructedbetween1927—1978.Fifteenoftheotherbuildings
on the easternProject site areused for additional office or storage space.The remainderof the
buildingsontheeasternProjectsitearenolongerinuseanddonotgeneratewastewater
ThewesternProjectsite,approximately14.2acres,slopessteeplyupfromStadiumWaytoElysian
ParkDriveonitseasternboundary.ThewesternProjectsitecontains10buildings, includingtwo
currentlyoccupiedsingle‐familyresidencesbuilt in1936and1940,respectively,atthetopofthe
slopeonElysianParkDrive.Eight formerpatientcottagesconstructedbefore1930arelocatedat
thebottomoftheslopealongStadiumWay.Oneformercottageiscurrentlyusedforstoragebythe
hospital;theremainingcottagesarenolongerinuseanddonotgeneratewastewater.
The existingwastewater collection system on the Project sitewas constructed in the 1930s and
consistsofanundergroundnetworkofvitrifiedclaypipes(VCP)andpolyesterresinconcrete(PRC)
pipes.Figure IV.M.2‐2,ProjectSiteWastewaterCollectionSystem,shows the locationsof existing
buildingsandtheon‐sitewastewaterpipes.Wastewaterpipes,includingthoseontheProjectsite,
are typically designed to operate via “gravity loading”, where upstream (upslope) pipes convey
wastewater flows downstream (downslope) to a point of discharge, relying only on gravity (not
pumps or other mechanical aids) for conveyance. The use of gravity systems imposes some
Figure IV.M.2-1Project Site Wastewater Collection System
Source: KPFF Consulting Engineers, 12/21/2010.
LEGEND
0 100 200
Scale (Feet)
N
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐8 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
Figure IV.M.2-2Project Vicinity Wastewater Collection System
Source: KPFF Consulting Engineers, 12/21/2010.
Not to Scale
N
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐10 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐11 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
constraints on system design; pipes must have enough relative difference in elevation between
points of building connection and discharge to ensure adequate slope, flow, and capacity for the
buildingsserved.
As previously noted, the eastern Project’s site, which contains the existing hospital, is currently
servedbysixactivesewerlateralsofvaryinglength,size,andslope.Thelongestlateral,servingthe
majority of the eastern Project site, begins at BuildingNo. 10, east of the hospital, travels south
approximately700feetthroughthecenterofthesite,andturnswestthroughtheexistingparking
lot, terminating in the municipal wastewater main beneath Stadium Way. This 8‐inch lateral
receivesdischargesfromannetworkoffour‐,six‐andeight‐inchlinesthatservethebuildingsinthe
centeroftheeasternProjectsiteaswellasBuildingNos.6,11,12,21,and25.Theremainingfour
activelateralsontheeasternProjectsiteconsistof8‐inchVCPlinesthatprovidedirectconnections
betweenbuildingsthatfrontonStadiumWayandthewastewatermainbeneathStadiumWay.
ThewesternProjectsitehastwoactiveVCPlateralsofeightinchesand15inchesindiameterthat
connectdirectlytothewastewatermainbeneathStadiumWay.Theselateralsservethebuildings
frontingonStadiumWayandarealsobelievedtoservethetwosingle‐familyresidencesatthetop
oftheslopeonElysianParkDrive.
c. Wastewater Treatment
theCityofLosAngelesDepartmentofPublicWorks,BureauofSanitation,ownsandoperatesfour
wastewater treatmentandwater reclamation facilities:. theHyperionTreatmentPlant, located in
Playa del Rey; two partial treatment/reclamation plants located inland (the Tillman Water
ReclamationPlantinVanNuysandtheLosAngeles‐GlendaleWaterReclamationPlantnearGriffith
Park); and theTerminal IslandWaterReclamation Plant. TheBureau of Sanitation also operates
two ocean outfalls; 48 pumping plants in low‐lying communities; and an array of wastewater
system connections and major interceptors. These facilities collect and treat sewage generated
throughouttheCityofLosAngelesaswellascitiesthatcontractfortheseservices.TheLosAngeles
areaisdividedintotwomajorserviceareas,theHyperionTreatmentAreaandtheTerminalIsland
Servicearea;theProjectsiteislocatedwithintheHyperionTreatmentArea.
WastewatergeneratedontheProjectsiteisconveyedapproximately21milesto,andistreatedat,
Hyperion Treatment Plant, the largest of the three treatment plants in the Hyperion Treatment
System.TheHyperionTreatmentPlantservesthecentralLosAngelesarea,treatsexcessflowsfrom
the Los Angeles‐GlendaleWater Reclamation Plant, and processes solids generated by the City’s
other treatment/reclamation plants. Opened in 1950, Hyperion Treatment Plant can now
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐12 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
accommodate a total average flow of 450 million gallons per day (mgd) under dry weather
conditions andup to onebillion gallons per dayduringpeakwet‐weather flow conditions. As of
2010,HyperionTreatmentPlanttreatedanaverageof300mgd,foraremainingcapacityofupto
150mgd.10
Basedonthelatestdataavailable,theaveragedryweatherflowfortheentireCityserviceareais
approximately380mgd,or180mgdbelowthedesigncapacityof560mgd forall threeplants.11
Thisexcesscapacity isdue, inpart, towaterconservationmeasuresnowrequiredpertheCityof
Los Angeles Uniform Building Code, since wastewater flows are directly proportional to water
usage.
With theapprovalof the2006 IntegratedResourcePlan, the capacityatHyperion in conjunction
with other relief wastewater treatment facilities is expected to provide sufficient wastewater
treatmentcapacityfortheserviceareathroughtheyear2020.
d. Wastewater Generation and Conveyance Capacity
i. Project Site
The total sewage generation of existing uses on theProject site, based on the generation factors
defined by the City of Los Angeles in the Los Angeles CEQA Thresholds Guide, is approximately
16,067 gallons per day (gpd) (.016mgd). Refer toTable IV.M.2‐1, ExistingBarlowMaster Plan
Sewer Load Summary, for a detailed breakdown of wastewater generation under existing
conditions.Asshowninthetable,anumberoftheexistingon‐sitebuildingsarenotcurrentlyinuse
anddonotgeneratewastewater.
ii. Project Area
As previously stated, the wastewater main beneath Stadium Way adjacent to and south of the
Projectsitevaries indiameter,withsegmentsof8 inches,12 inches,and15 inches.Basedonthe
City’s established design capacity requirements forwastewaterpipes, limitingpeak flows to less
than fifty percent of pipe depth, the maximum allowable design capacity of the 15‐inch pipe is
approximately2.19mgd.However,sincethesmallest‐diametersegmentofthewastewatermainin
10 CityofLosAngeles,DepartmentofPublicWorks,BureauofSanitation,Five‐YearStrategicPlan,FiscalYears2010/11‐
2014/15,14.http://www.ci.la.ca.us/san/general_info/pdfs/Strategic_Plan_10‐11_Final.pdf.2010.11 City of Los Angeles, Department of PublicWorks, Bureau of Sanitation,WastewaterEngineering ServicesDivision,
SewageTreatmentPlantFlowData,2005–2006,(2006).
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐13 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
Table IV.M.2‐1
Existing Barlow Master Plan Sewer Load Summary
Buildings TypeDescription Amounts UnitsGenerationFactor(gal/day/perunit)
DailyGeneration(gal/day)
1 Office 2,559 gsf 150gpd/1000gsf 3842 Hospital/Medical
Building47,014 gsf 250gpd/1000gsf. 11,754
2A MedicalBuilding 1,804 gsf 250gpd/1000gsf 4513 Office 2,072 gsf 150gpd/1000gsf 3114 Office 1,392 gsf 150gpd/1000gsf 2095 Office 4,537 gsf 150gpd/1000gsf 6806 Maintenance 1,696 gsf 80gpd/1000gsf 1367 a ‐ ‐ 8 Office 1,505 gsf 150gpd/1000gsf 2269 Office 5,841 gsf 150gpd/1000gsf 87610 Storage 575 gsf 20gpd/1000gsf 1111 a ‐ ‐ 12 Office 808 gsf 150gpd/1000gsf. 12113 a ‐ ‐ 14 ‐ ‐ ‐ 15 Office 648 gsf 150gpd/1000gsf 9716 Office 783 gsf 150gpd/1000gsf 11817 a ‐ ‐ 18 a ‐ ‐ 19 a ‐ ‐ 20 a ‐ ‐ 21 a ‐ ‐ 22 a ‐ ‐ 23 a ‐ ‐ 24 a ‐ ‐ 25 a ‐ ‐ 26 Storage 685 gsf 20gpd/1000gsf 1427 Maintenance 773 gsf 80gpd/1000gsf 6228 Maintenance 2,164 gsf 80gpd/1000gsf 17329 a ‐ ‐ 30 a ‐ ‐ 31 a ‐ ‐ 32 a ‐ ‐ 33 a ‐ ‐ 34 a ‐ ‐ 35 a ‐ ‐ 36 Office 824 gsf 150gpd/1000gsf 12437 Residential 1 du 160gpd/du 16038 Residential 1 du 160gpd/du 160
Total 16,067 aNotinuse.Notes:gal–gallons;gsf=grosssquarefeet;du=dwellingunits.Source:CityofLosAngeles,LosAngelesCEQAThresholdsGuide,2006WastewaterGenerationFactors.
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐14 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
the Project vicinity is only 8 inches in diameter, this segment necessarily constrainswastewater
systemcapacityupstream.Themaximumallowable(i.e.,fiftypercent)designcapacityofthe8‐inch
pipeisapproximately363,000gpd,andasofNovember2009approximatelyflowlevelsinthepipe
weregaugedatapproximately22percentofpipedepth.12
4 IMPACT ANALYSIS
a. Methodology
The analysis in this section is based, in part, on the technical report prepared for theProject by
KPFF Consulting Engineers. Information regarding existing publicwastewater pipe location, age,
andcapacitywasprovidedbytheBureausofEngineeringandSanitationoftheCityofLosAngeles
DepartmentofPublicWorksbasedontheSCAR,publishedreports,as‐builtplansandothersources.
This analysis compares wastewater generation projected for the proposed Project to existing
wastewater generation on the Project site, based on established City of Los Angeleswastewater
generation factors, and determines the capacity of the existing public wastewater conveyance
systemtoaccommodateProjectincreasesinwastewatergeneration.
b. Significance Thresholds
AppendixGof theStateCEQAGuidelinesprovides sample checklistquestions foruse inan Initial
Study to determine a project’s potential for environmental impacts. According to the applicable
questions13 contained in Appendix G under Section XVII, Utilities and Service Systems, a project
wouldhaveapotentiallysignificantimpactifitwould:
XVII.a) Exceedwastewater treatment requirementsof theapplicableRegionalWaterQuality
ControlBoard;
XVII.b) Require or result in the construction of new wastewater treatment facilities or
expansion of existing facilities, the construction of which could cause significant
environmentaleffects;or14
12 Correspondence fromBrent Lorscheider,DivisionManager, City of LosAngeles,WastewaterEngineering Services
DivisionoftheBureauofSanitation,DepartmentofPublicWorks,November10,2009.13 Appendix G Utilities and Service Systems sample questions (XVI.b (in part), and –d through ‐g) pertain towater
supplyandsolidwasteandareaddressedinSectionsIV.L.1,WaterSupply,andIV.L.3,SolidWaste.SamplequestionXVI.cpertainstohydrologyandisaddressedinSectionIV.G,SurfaceWaterHydrologyandWaterQuality.
14 Sample question XVI.b addresses the construction of new water and wastewater treatment facilities and theexpansionof existing facilities. Assuch, this samplechecklistquestion isalsodiscussed inSection IV.L‐1,WaterSupplyofthisDraftEIR.
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐15 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
XVII.e) Result in a determination by thewastewater treatment provider that serves ormay
serve the project that it has inadequate capacity to serve the project’s projected
demandinadditiontotheprovider’sexistingcommitments.
The factors used in the City of Los Angeles CEQA Thresholds Guide to determine significant
wastewater impacts incorporate themoregeneralchecklistquestionscontainedinAppendixGof
theStateCEQAGuidelines.Therefore,basedonthemorespecificCityofLosAngelesCEQAThresholds
Guide,theproposedProjectwouldhaveasignificantwastewaterimpactif:
WW‐1 TheProjectwouldcausemeasurableincreaseinwastewaterflowsatapointwhere,
andatatimewhen,asewer’scapacityisalreadyconstrainedorthatwouldcausea
sewer’scapacitytobecomeconstrained;
WW‐2 The Project’s additional wastewater flows would substantially or incrementally
exceedthefuturescheduledcapacityofanyonetreatmentplantbygeneratingflows
greaterthanthoseanticipatedintheWastewaterFacilitiesPlanorGeneralPlanand
itselements;or
WW‐3 The Projectwould result in exceedance ofwastewater treatment requirements of
theapplicableRegionalWaterQualityControlBoard.
c. Project Design Features
Barlow Hospital has committed to the following water conservationmeasures for the proposed
Project,bythedateofProjectbuildout:
• Bathroom faucets: 1.5 gallons per minute (GPM) (residential/private); 0.5 GPM
(hospital/public)
• Kitchenfaucets:1.5GPM
• Low‐flowshowerheads:2.0GPM,nomorethan1showerheadperstall
• High‐efficiencyclotheswashers(residential):watersavingsfactorof5.0orless
• High‐efficiencytoilets:1.28gallonsperflushorless,ordualflush
• High‐efficiency/ultra‐lowwaterurinals:0.125to0.5gallonsperflush
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐16 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
• Energystardishwashers
• High‐efficiencyclotheswashers(commercial):watersavingsfactoror7.5orless
• Pre‐rinsekitchensprayhead
• Publicrestroomself‐closingfaucets
• Domesticwaterheatingsystemincloseproximitytopoint(s)ofuse
• Tanklessandon‐demandwaterheaters
• Rotatingsprinklernozzlesforlandscapeirrigation:0.5GPM
• Weather‐basedirrigationcontroller
• Micro‐spray
• Bubblerirrigation
• Properhydro‐zoning(i.e.,groupplantswithsimilarwaterrequirementstogether)
• Zonedirrigation
• Landscapecontouringtominimizeprecipitationrunoff
• Drought‐tolerantplants:75percentoftotalnewlandscapeplantings
• CoolingtowerconductivitycontrollersorcoolingtowerpHconductivitycontrollers(cooling
towerstooperateataminimumof5.5cyclesofconcentration)
• Water‐savingpoolfilter
• Reclaimedwatersystemforirrigation
• Convertcoolingtowersto100percentreclaimedwateruse,aspermittedbylaw
TheproposedProjectalsowouldcomplywiththerequiredStandardUrbanStormWaterMitigation
Plan(SUSMP)andwouldimplementBestManagementPracticesthathavestormwaterrechargeor
reusebenefits.
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐17 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
d. Project Impacts
WW‐1 WouldtheproposedProjectcausemeasurableincreaseinwastewaterflows
at a point where, and at a time when, a sewer’s capacity is already
constrainedorthatwouldcauseasewer’scapacitytobecomeconstrained?
WW‐2 Would theproposedProject’s additionalwastewater flowssubstantiallyor
incrementally exceed the future scheduled capacity of any one treatment
plantbygeneratingflowsgreaterthanthoseanticipatedintheWastewater
FacilitiesPlanorGeneralPlananditselements?
i. Construction Impacts
Project implementation would involve the construction of a new on‐site wastewater system to
service the proposed replacement hospital, skilled nursing facility, 868 condominium units, 20
residential townhomes, commercialuses, andadaptive reuseof existingbuildings.Newbuildings
wouldbeconstructedonboththeeasternandwesternProjectsites.Projectimplementationwould
necessitateupgradingProjectsiteexistingconnections(laterals)totheexistingpublicwastewater
mainbeneathStadiumWay,and/oranincreaseinthevolumeofwastewatercurrentlydischarged
to the public water system by on‐site uses. Additionally, during construction of the proposed
Project, it is anticipated that construction contractorswould provide portable, on‐site sanitation
facilities that would be regularly serviced at approved disposal facilities located off‐site.
Constructionactivitieswould,therefore,havenoimpactontheProjectsite’swastewatercollection
system.
New and/or upgraded lateral connections to the StadiumWay sewer main associated with the
proposedprojectwould require construction activities that could affect themain. However, any
sucheffectswouldbetemporaryandwouldoccurinaccordancewithallapplicableregulationsas
enforced under required LADPW construction permits. Because these requirements have been
formulated to avoid significant impacts, suchasdisruptionsof sewer service to existingadjacent
usesand/or sewagespillsduring the constructionperiod,project construction impactswouldbe
lessthansignificant
ii. Operational Impacts
Wastewater generation associated with the proposed Project was calculated using the sewer
generation factors contained in the City of Los Angeles CEQA Thresholds Guide. Project
implementationwould increase thenumberofwastewatergenerationsourceson theProjectsite
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐18 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
throughan increase inhospitalbeds, the introductionofa24‐bedskillednursingfacility,andthe
construction of residential units, including kitchen, bathroom, and laundry facilities, and
commercial uses. As a result, Project implementation would increase the volume of wastewater
generated on the Project site and discharged to the public system. Table IM.M.2‐2, Projected
Wastewater Discharges, shows the projected wastewater discharge volumes. The Project is
projected to generate approximately 157,236 gpd of wastewater, for a net increase of
approximately 141,169 gpd over existing conditions. This represents approximately 5 percent of
themaximumallowabledesigncapacityofthe15‐inchwastewatermainbeneathStadiumWayand
approximately 43 percent of the maximum allowable design capacity of the 8‐inch wastewater
main, and both wastewater pipes would therefore continue to operate below the maximum
allowable design capacity. The Bureau of Sanitation has also indicated that there is sufficient
capacity inthewastewatersystemtoaccommodatetheanticipatedProjectwastewaterflows.15,16
Therefore, although the Project would result in an increase in wastewater flows into the
wastewater system, the system isnotpresently constrainedand theProjectwouldnot cause the
systemtobecomeconstrained. Therefore,projectimpactsonwastewaterpipecapacitywouldbe
lessthansignificant.
WW‐3 Would the Project result in exceedance of wastewater treatment
requirementsoftheapplicableRegionalWaterQualityControlBoard
As stated previously, wastewater from the Project site is currently, and would continue to be,
conveyedby thepublicwastewater system to theHyperionTreatmentPlant.Theplantcurrently
processed average daily flows of 300 mgd and has the capacity to treat up to 450 mgd. The
proposed Project would represent a minor incremental increase in the volume of wastewater
treatedatHyperion,andtheBureauofEngineeringhasconcurredthatsufficientcapacityexistsat
Hyperion to treat Project‐generated wastewater flows. Since the Project would not exceed the
capacityofHyperionorgenerateflowsgreaterthanthoseanticipatedintheWastewaterFacilities
PlanorGeneralPlan,impactswouldbelessthansignificant.
e. Mitigation Measures
The proposed Project would result in less than significant impacts with respect to wastewater
collectionorconveyancesystemsortreatmentcapacityandnomitigationisrequired.
15 Correspondence fromBrent Lorscheider,DivisionManager, City of LosAngeles,WastewaterEngineering Services
DivisionoftheBureauofSanitation,DepartmentofPublicWorks,November10,2009.16 CityofLosAngeles,BureauofEngineering,DepartmentofPublicWorks,SewerCapacityAvailabilityRequest(SCAR)
no.21‐1369‐0510(resubmitted5/13/10as18‐1201‐0509),approvedJune4,2010.
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐19 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
Table IV.M.2‐2
Projected Wastewater Discharges
Type Amounts Units General Factor
(gal/day/per unit) Daily Generation
(gal/day) Existing
ExistingBuildingstobeDemolished ‐ ‐ ‐ 14,771
ExistingBuildingstoRemain(HistoricCore):2A,3,15,16,17,18,20,37,and38
‐ ‐ ‐ 1,296
Total(Existing) 16,067
Proposed
Hospital(56Beds)/SkilledNursingFacility(24Beds)/AdministrationandSupportFacility
120,000 gsf 250gpd/1000sq.ft. 30,000
Condos(2‐Bedroom) 435 du 160gpd/du 69,600
Condos(1‐Bedroom) 435 du 120gpd/du 52,200
Townhomes 18 du 230/du 4,140
ExistingBuildingstoRemain
Total(Proposed) 155,940
1,296
Total(ExistingtoRemain+Proposed) 157,236
NetIncrease 141,169 Source:KPFFConsultingEngineers;WastewaterAssessmentprepared for theProjectbyTheBureauof Sanitationof theDepartmentofPublicWorks,CityofLosAngeles,October2010. Notes:gsf=grosssquarefeet;du=dwellingunits..
f. Level of Significance After Mitigation
Projectimpactswithrespecttowastewatersystemcapacitywouldbelessthansignificantandno
mitigationisrequired.
g. Cumulative Impacts
As stated in Section2.c.,PlannedCapital Improvements, every 10 years, the City of Los Angeles
updatesits10‐YearCapitalImprovementProgramtoaddressplannedreplacementandexpansion
ofthewastewatercollectionsystemandtreatmentfacilitieswithinitsservicearea;improvements
arethencarriedoutbytheBureausofSanitationandEngineering.Themostrecentupdatedefines
improvementsscheduledthrough2016.Moreover,theSecondarySewerRenewalProgram,which
identifiessubstandardsecondarysewers, includesplannedupgradestothewastewatersystemin
IV.M.2 Wastewater
CityofLosAngeles IV.M.2‐20 BarlowHospitalReplacementandMasterPlanProjectENV2009‐2519‐EIR DraftEIR. April2012
theProjectarea(e.g.,CityprojectSSRPN13).These improvementscommencedinFebruary2011
andareexpectedtobecompletebyJune2012,andareintendedtoensurethewastewatersystemin
theProjectareaisabletoaccommodatepresentandfuturewastewaterflows.17Finally,theProject
siteisthemostupstreampointofconnectiontothepublicsewerbeneathStadiumWaythatserves
the site, and no other properties discharge wastewater to this sewer. All the related projects
definedinSectionII,EnvironmentalSetting,ofthisDraftEIRarelocateddownstreamoftheProject
site.
According to the technical studies prepared for this analysis by the Project civil engineer and
correspondencefromtheCityofLosAngeles,theexistingsewersystemandwastewatertreatment
plantservingtheProjectsitehaveadequatecapacitytoaccommodateProject‐generatedincreases
inwastewaterflowsunderexistingconditions,andwillcontinuetodosofollowingplannedsewer
improvements in the Project area. The downstream trunk and interceptor mains that convey
Projectwastewater flows toHyperion Treatment Plant likewise have adequate capacity, as does
Hyperion.Forthesereasons,theproposedProject,consideredtogetherwithrelatedprojects,would
notresultinacumulativelyconsiderablecontributiontocumulativelysignificantimpactsrelatedto
thesewersystemcapacityorwastewatertreatmentcapacity.
17 KPFFConsultingEngineers,pers.com.,February28,2012(basedonlatestCityofLosAngelesProjectInformation
ReportforSSRPN13)