itc transmission company - michigan and limited capacity surpluses. • itc is not able to achieve...
TRANSCRIPT
Energy Business SolutionsConfidential/Proprietary
ITC Transmission CompanyTransmission Tie Analysis DRAFT
August 2006
Presentation to Michigan CNF Workgroup 8/8/2006
Energy Business SolutionsConfidential/Proprietary
2
PURPOSE OF THE ANALYSIS
• Examine ITC Area Relationship between:• Required Internal Reserves v.• Transmission Capability• At Constant Supply System Loss of Load Probability (LOLP)
• Examine trade-off between Transmission and Internal Reserves
• Produce, for further economic analysis, Three Scenarios of ITC transmission/capacity expansion with Consistent Reliability.
Energy Business SolutionsConfidential/Proprietary
3
LOLP PERSPECTIVE
• LOLP is defined in this study as the cumulative loss of load hours based on an analysis that examines the probability of a supply system deficiency during the peak hour of each day of the year.
• Most of the probability of load loss due to supply deficiencies accumulates during the peak hours.
• LOLP is valuable as a relative measure of the adequacy of and changes in system reliability due to changes in system conditions.
• LOLP targets should include consideration of historical system performance, reserve levels and transmission support for reliability.
• The LOLP target that we are using is 1 day in 10 years.
Energy Business SolutionsConfidential/Proprietary
4
FOR CONSISTANCY, THE STARTING POINT WAS THE MOST RECENT MISO MARELI ANAYSIS FOR The Capacity Needs Forum (CNF)
MPSC-CNF Integration Group Meeting LOLP Analysis Update July 25, 2005
This Study
Area Isolated (2009)
Area with transmission
capability
Area Isolated
30.1 days/yr
.39 days/yr
Area with transmission
capability
ITC
32.3 days/yr 1.03 days/yr(simultaneous
TTC is 2800MW)
1.03 days/yr
METC
.38 days/yr 0 days/yr(simultaneous
TTC is 3500MW)
Not tested
NOTE: MPSC-CNF data from Integration Group presentation revised 8/12/2005
Energy Business SolutionsConfidential/Proprietary
5
MISO MARELI v. ITC ANAYSIS COMPARISON CONTINUED
Benchmark to MPSC-CNF “With Support”system Summary - 2009 LOLP RESULT
Sink From Import Value LOLP MPSC-CNF
ITC MAIN 3000 .69 .69ITC TVA 2800 1.03 1.03
ITC MAAC 2500 1.76 1.77
ITC VACAR 2700 1.24 1.24
This Study benchmark
NOTE: MPSC-CNF data from Integration Group presentation revised 8/12/2005
Energy Business SolutionsConfidential/Proprietary
6
Study Parameter Comparison (“This Study” includes ITC data refinements)
MPSC-CNF This Study
ITC Load 13,648 13,648Internal Capacity * 12,110 12,500
Reserve -11% - 8%
Consumers Load 11,212 10,950Internal Capacity 13,450 13,483
Reserve 20% 23%
Wolverine Load 494 494Internal Capacity 386 372
Reserve - 22% - 25%
Lansing Board Load 526 526Internal Capacity 532 539
Reserve 1% 2%
* ITC Internal Capacity Reconciled in Appendix 1NOTE: MPSC-CNF data from Integration Group presentation revised 8/12/2005
Energy Business SolutionsConfidential/Proprietary
7
ITC ANALYSIS TRANSMISSION STRUCTURE
• Two separate analysis
AEP
500
METC ITC
Variable
2500
METC ITC
Variable
1) ITC-METC only 2) ITC-METC-SOUTH
Energy Business SolutionsConfidential/Proprietary
8
KEY DEFINITIONS
• See Appendix 3 for additional details.• Chart Keys
• Single Area Isolated – LOLP for an area with no ties.• Single Area Full Import – LOLP assuming tie accesses its full
capability worth of generation reserves.• 2009 – LOLP assuming studied internal and external reserves and
modeled transmission capability, with “no loss sharing.”• No Loss Sharing – External areas supply emergency assistance only
from surpluses on their system
• Capacity Benefit – Transmission Benefit to reliability measured in MW• Internal Reserves – Generation reserve capacity accessable on internal
transmission only• CBM – Transmission Set-Aside for Capacity Benefit Margin• TRM – Transmission Set-Aside for uncertainties
Energy Business SolutionsConfidential/Proprietary
9
ITC – METC ONLY STRUCTURE RESULTS
• ITC-METC only areas modeled• ITC LOLP
• Single Area• Effect of Transmission Ties
• Points (a system reliability view):• Transmission is a key element of reliability• This model clearly shows saturation effects of both limited
transmission and limited capacity surpluses.• ITC is Not able to achieve reliability standard (1:10) without
assistance from outside Michigan• ITC Tie Capacity Benefit (another view)• Point: (A transmission benefit view of the same system)
• Transmission benefits saturate
Energy Business SolutionsConfidential/Proprietary
10
ITC-METC ONLY STRUCTURE
ITC Base Reserve LOLP
0
5
10
15
20
25
30
35
500 1000 1500 2000 2500 3000 3500 4000 4500 5000 10000
TIE CAPACITY
DA
. / Y
R.
SINGLE AREA ISOLATED SINGLE AREA FULL IMPORT 2009
Energy Business SolutionsConfidential/Proprietary
11
ITC-METC ONLY STRUCTURE
METC Base Reserve LOLP(tie capacity is bidirectional - prior to ITC capacity updates)
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
500 1000 1500 2000 2500 3000 3500 4000 4500 5000 10000
TIE CAPACITY
DA
. / Y
R.
SINGLE AREA ISOLATED SINGLE AREA FULL IMPORT 2009
Energy Business SolutionsConfidential/Proprietary
12
ITC-METC ONLY STRUCTURE
ITC BASE RESERVE CAPACITY BENEFIT
0
200
400
600
800
1000
1200
1400
1600
1800
2000
500 1000 1500 2000 2500 3000 3500 4000 4500 5000 10000
TIE CAPACITY
MW
CAPACITY BENEFIT
Energy Business SolutionsConfidential/Proprietary
13
ITC ANALYSIS TRANSMISSION STRUCTURE
ITC-METC-South Analysis
AEP
500
METC ITCVariable
2500
Energy Business SolutionsConfidential/Proprietary
14
ITC – METC- SOUTH STRUCTURE RESULTS
• ITC-METC JOINED BY LINK TO AREAS SOUTH OF MI• ITC LOLP
• A big assumption – Transmission is reserved as CBM (TRM?)• Points (a system reliability view):
• Ties to South provide significant reliability benefits• Reserves and/or Transmission improve reliability• “No Transmission” requires > 20% reserves (500 MW to South
remains)• “No Reserves” requires approx. 2700 MW METC tie benefit plus
500 MW to South (3200 MW total)• Counting just METC and AEP generation surpluses support
transmission benefits up to approximately 3500 MW.
Energy Business SolutionsConfidential/Proprietary
15
ITC-METC-SOUTH STRUCTURE RESULTS –(zoomed view of previous slide)
2009 Full System LOLP v. ITC-METC Tie Capability(for varying internal reserve levels)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 1500 3000 4000
ITC-METC Tie Capability
LOLP
-8% Internal Reserve
0% Internal Reserves
10% Internal Reserves
20% Internal Reserves
30% Internal Reserves
Energy Business SolutionsConfidential/Proprietary
16
ITC-METC-SOUTH STRUCTURE RESULTS– ITC LOLP FOR ESTIMATED 2009 RESERVES
• This 1:10 result requires Tie Capability:• about 3200 MW to ITC from METC, plus• 2500 MW METC from South, plus• 500 MW ITC from South.
• Assumes transmission is set aside for firm reliability purposes.
Energy Business SolutionsConfidential/Proprietary
17
ITC-METC-SOUTH STRUCTURE RESULTS
ITC LOLP FOR BASE RESERVE
ITC Base Reserve LOLP
15.02
8.91
4.87
2.29
0.960.36 0.020.020.020.040.12
0
2
4
6
8
10
12
14
16
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000ITC-METC TIE CAPABILITY
DA
. / Y
R.
2009 LOLP: - 8% RESERVE
Loop Flow and Firm Reservations andRTO allocations?
Current assumption fortransmission
Energy Business SolutionsConfidential/Proprietary
18
ITC-METC-SOUTH STRUCTURE RESULTS
• ITC Capacity Benefit of Ties (for base level reserves)• Longer linear portion due to access to greater reserves to the South
(compare to slide 12.)• Rapid saturation above 3500 MW due to combined effects of 3000
MW bottleneck to the South and total available capacity reserve.
• “Capacity Benefit” is “ideal” capacity• “Ideal” capacity is capacity that is fully available to cover shortages
when they occur.• The “benefit” limited by pool of available generation.• On the linear portion of the curve 1 MW of tie always can access 1MW
of generation.
• “Ideal” capacity – not to be confused with internal reserves (slides 22, 23.)
Energy Business SolutionsConfidential/Proprietary
19
ITC-METC-SOUTH STRUCTURE RESULTS
ITC BASE RESERVE TOTAL TIE CAPACITY BENEFIT
0
500
1000
1500
2000
2500
3000
3500
4000
4500
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000METC-ITC TIE CAPACITY (MW)
MWCAPACITY BENEFIT(res -8)
Energy Business SolutionsConfidential/Proprietary
20
ITC – METC- SOUTH STRUCTURE RESULTS
• Question:
• Transmission Capability = Generation Capacity• What decides the proper balance?
• Equivalance is not 1:1 and limited in magnitude• Coordinated Sharing• Policy
• Equitable “Tie Benefit” requires everyone to do their share
• i.e. no “leaning” (If Area A and Area B do independent studies and each relies on the other’s assumed reserve levels, both may underplan for system reliability.)
• What is the Internal Reserve v. Transmission trade-off?
Energy Business SolutionsConfidential/Proprietary
21
ITC-METC-SOUTH STRUCTURE RESULTS
MW Reserves for 1:10(base reserve is -1148 MW)
(2009 load is 13,648 MW)
3,071
1,092
-887
-1,500
-1,000
-500
0
500
1,000
1,500
2,000
2,500
3,000
3,500
0 1500 3000
ITC - METC Tie Capability
MW
Res
erve
s
(8%)
(22.5%)
(- 6.5%)
Energy Business SolutionsConfidential/Proprietary
22
ITC – METC- SOUTH STRUCTURE RESULTS
(Values in first 3 columns read from previous graph)
METC Tie capability
1:10 Reserve %
1:10 Reserve MW
Added Tie
Saved Reserve
Reserve Value per MW of Tie
Benefit (MW)
0 22.5 3,071
1500 8 1,092 1,500 1,979 1.32
3000 -6.5 -887 1,500 1,979 1.32
Energy Business SolutionsConfidential/Proprietary
23
ITC-METC-SOUTH STRUCTURE RESULTS
• 1500 MW of additional tie capability can substitute for nearly 2000 MW of internal reserves.
• 1 MW Tie Capacity = 1.32 MW Internal Reserves• 1 MW Internal Reserves replaces .76 MW Tie Capacity
• The value of Internal Reserve depends on Unit characteristics relative to the area load profile.
• Unit size relative to load• Unit availability characteristics
Energy Business SolutionsConfidential/Proprietary
24
ITC – AEP only TRANSMISSION STRUCTURE(Sensitivity to test tie saturation drivers)
ITC-AEP only Analysis
AEP
Variable3,000 – 10,000 MW
ITC
Energy Business SolutionsConfidential/Proprietary
25
COMPARE TIE BENEFITS OF TWO STRUCTURES
ITC BASE (-8%) INTERNAL RESERVE TIE CAPACITY BENEFIT
3000
3500
4000
4500
5000
5500
6000
6500
7000
3000
3200
3400
3600
3800
4000
4200
4400
4600
4800
5000
5200
5400
5600
5800
6000
6200
6400
6600
ITC Simultaneous Tie Capability (MW)
MW
Capacity Benefit AEP OnlyStructure
Vary ITC-METC Tie (tiesouth is 500 MW)
Linear (Capacity Benefit AEP OnlyStructure)
Energy Business SolutionsConfidential/Proprietary
26
CONCLUSIONS FROM ITC-AEP only STRUCTURE
• Tie Benefit for the 3-area structure saturates about 3500 MW• METC-area Capacity and Ties to South are Limits
• Tie Benefit for the 2-area ITC/AEP structure saturates above 6700 MW• AEP has more surplus capacity of which to take advantage
• The results point to transmission limit issues as more distant capacity is relied upon for reliability
• More distant areas’ own use of transmission may take priority
Energy Business SolutionsConfidential/Proprietary
27
KEY OBSERVATIONS
• Firm transmission reservations that diminish CBM will limit transmission reliability benefits to the ITC area.
• CBM is the set aside of transmission capacity for use during generation deficiency situations. This margin will limit “firm” uses of the transmission system. However, the capacity is available for non-firm use when CBM is not needed (which may be most of the time).
• Currently, there are is no margin for CBM (TRM?) subtracted from METC to ITC flowgates. Many flowgates interconnecting METC and ITC to the south have little or no CBM set aside. This issue is under investigation with MISO.
Energy Business SolutionsConfidential/Proprietary
28
KEY OBSERVATIONS
• The amount of reserves required for a 1 day in 10 year LOLP is not a fixed number but depends on assumptions of transmission available for reliability.
• For ITC forecast load (CNF base forecast) and capacity for 2009, 2000 MW simultaneous CBM 8% reserves achieves 1 in 10 LOLP
• For 3500 MW ITC simultaneous CBM, -6.5% is required.
• For - 8% internal reserve, the ITC area needs about 3700 MW of simultaneous import capability that is incremental to other firm uses (such as firm transactions or allocations of flowgate capacity to other RTOs) for 1 in 10 reliability.
Energy Business SolutionsConfidential/Proprietary
29
KEY OBSERVATIONS
• If 1500 MW of the simultaneous import capability is used up because of other firm uses, it would imply a LOLE higher than 1 day in 10 years. Restoring LOLE to 1 day in ten years could be accomplished by increasing simultaneous import capability to 5200 MW.
• Procurement of reliability reserve obligations from “off-system” sources uses firm transmission. System reliability depends upon restoring the CBM assumptions built into the reserve requirement determination.
• Increasing tie CBM capacity reduces the total required internal reserves.
Energy Business SolutionsConfidential/Proprietary
30
KEY OBSERVATIONS
• Internal transmission limits are assumed to not limit “on-system” load access to internal resources or external resources delivered across the ties.
• Disparities in ITC/METC system reliability (recall base LOLP comparison) shows Michigan transmission does not support comparable reliability for all points on the system.
• Additional Transmission is required to share Michigan reserve benefits.
Energy Business SolutionsConfidential/Proprietary
32
ITC Area Capacity Changes for ITC Analysis(total +390 MW in 2009)
DETED Interruptible:1 245.00Fermi:2 137.00River Rouge:1 28.00St. Clair:7 15.00St. Clair:3 8.00Sumpter Energy Assoc.:GTGS10 4.00Carleton Farms Generating Project:1 2.40Ann Arbor Generating Station:1 0.80Lyon Generating Facility:GTGS7 -2.00St. Clair:4 -4.00St. Clair:1 -10.00Mistersky:5 -10.00Mistersky:6 -11.00Mistersky:7 -13.00
Energy Business SolutionsConfidential/Proprietary
33
Appendix 2
3-Area StructureVarious ITC/METC transmission capabilities
ITC -8% starting internal reserve500 MW ITC/South transmission capability
Additional Firm Tie or Internal reserve needed for 1:10 LOLP
Energy Business SolutionsConfidential/Proprietary
34
APPENDIX 2 - Additional Firm Tie or Internal reserve needed for 1:10 LOLP
METC/ITC import (Res -8%) (add'l firm copied from next worksheet)
MW METC / ITC Import 1000 1500 2000 2500 3000 3500 4000 4500 5000
add'l firm capacity for 1:10 2071 1574 1070 583 104 -313 -523 -576 -585
ITC INTERNAL CAPACITY 12500 12500 12500 12500 12500 12500 12500 12500 12500
ITC INTERNAL LOAD 13648 13648 13648 13648 13648 13648 13648 13648 13648
INTERNAL RESERVE (MW) -1148 -1148 -1148 -1148 -1148 -1148 -1148 -1148 -1148
INTERNAL RESERVE (%) -8% -8% -8% -8% -8% -8% -8% -8% -8%
Assumed Internal Availability 0.76 0.76 0.76 0.76 0.76 0.76 0.76 0.76 0.76
INTERNAL MW RESERVE for 1:10 1,576 923 260 -381 -1,012 -1,560 -1,836 -1,906 -1,917
INTERNAL % RESERVE for 1:10 11.6% 6.8% 1.9% -2.8% -7.4% -11.4% -13.4% -14.0% -14.0%
Capacity Benefit of Ties (MW) 1499.4 2000.1 2499.9 2997.2 3481.1 3887.6 4107.6 4155 4161.7
INTERNAL Reserve plus TIE BENEFIT needed for 1:10 3,076 2,923 2,760 2,616 2,469 2,328 2,272 2,249 2,245
TOTAL RESERVE % for 1:10 22.5% 21.4% 20.2% 19.2% 18.1% 17.1% 16.6% 16.5% 16.4%
Energy Business SolutionsConfidential/Proprietary
35
Appendix 3Terms and Definitions applicable to this analysis
Energy Business SolutionsConfidential/Proprietary
36
APPENDIX 3
LOLP – Loss of Load Probability – Cumulative probability that the peak daily load will be greater than available capacity plus support available over the transmissioin ties. Calculated for the peak hour of each day for a year this metric can be compared to the “1 day in 10 year” standard (LOLP=.1) LOLH – Loss of load Hours. The LOLP accumulated over a number of analyzed hours.INTERNAL CAPACITY or RESERVES – Total Generation Capacity or
Capacity in excess of an Area’s annual peak load and located within the Area’s local transmission system.MPSC-CNF – Michigan Public Service Commission Capacity Needs ForumTTC – Total Transmission Capability. The total ability of the transmissiointies to support transfers, including currently reserved firm transmission service (base transfers).
Energy Business SolutionsConfidential/Proprietary
37
APPENDIX 3
SIMULTANEOUS/ NON-SIMULTANEOUS – Referring to a measure of transmission capability from multiple areas, simultaneous means the maximum total transfer capability from all the areas together. Non-simultaneous means the maximum transfer capability from each area take one at a time.TIE CAPABILITY – Transmission capability available for emergency support. TIE CAPACITY BENEFIT or CAPACITY BENEFIT – The fully available firm generation support available to an area from all available transmission interfaces.SINGLE AREA ISOLATED – The LOLP for an Area assuming zero transmission tie capability.SINGLE AREA FULL IMPORT – The LOLP for an Area assuming it can receive emergency generation support up to the full capability of its transmission ties (external capacity is always available when needed.)
Energy Business SolutionsConfidential/Proprietary
38
APPENDIX 3
2009 Full System LOLP – Also abbreviated “2009” – Calculated LOLP based on studied internal and external capacity and transmission limits, with all their limitations active. External capacity is only available up to the transmission limit and if the external system is not itself short of supply. CBM – Capacity Benefit Margin – An amount of firm transmissioincapability reserved for access to energency supplies of generation during times when an area is short of internal supplies. TRM – TRANSMISSION RESERVE MARGIN – An amount of firm transmission capability reserved to account for uncertainties in the calculation of the Available Transmission Capability (for example, loop flows and load forecast error.)MARELI – New Energy’s Multi-Area Reliability softwareNO LOSS SHARING – A MARELI option that limits emergency assistance between areas to times when they have generation surpluses. LossSharing would enable “short areas” to share their load loss within the larger system.