ITB 2021-07 Smith Creek Volunteer Fire Department Building Addendum No. 1 1 Addendum No. 1 to ITB 2021-07 SMITH CREEK VOLUNTEER FIRE DEPARTMENT BUILDING August 20, 2021 SECTION 1.0 SCHEDULE OF EVENTS – Please see dates adjusted in RED below Failure to comply with this or any other paragraph of this ITB shall be sufficient reason for rejection of the bid. All times listed in the Schedule of Events are Eastern Standard Time (EST). Event Date/Time Bid Advertisement Date July 29, 2021 Release of Invitation to Bid July 29, 2021 Mandatory Pre-Bid Conference August 9, 2021 @ 10:00 A.M. Bid Questions Due from Prospective Bidder August 13, 2021 Responses to bid questions due August 20, 2021 BIDS DUE TO BOCC August 31, 2021 @ 3:00 P.M. Posting of Intended Award September 13, 2021 Board Consideration of Intended Award October 4, 2021 Posting of Notice of Award October 5, 2021 This addendum is being posted to provide answers (A) to questions (Q) regarding ITB 2021-07

Upload: others

Post on 07-Jun-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ITB 2021-07 Addendum Number 1

ITB 2021-07 Smith Creek Volunteer Fire Department Building Addendum No. 1

1

Addendum No. 1 to ITB 2021-07 SMITH CREEK VOLUNTEER FIRE DEPARTMENT BUILDING

August 20, 2021

SECTION 1.0 SCHEDULE OF EVENTS – Please see dates adjusted in RED below Failure to comply with this or any other paragraph of this ITB shall be sufficient reason for

rejection of the bid. All times listed in the Schedule of Events are Eastern Standard Time (EST).

Event Date/Time Bid Advertisement Date July 29, 2021

Release of Invitation to Bid July 29, 2021 Mandatory Pre-Bid Conference August 9, 2021 @ 10:00 A.M.

Bid Questions Due from Prospective Bidder August 13, 2021 Responses to bid questions due August 20, 2021

BIDS DUE TO BOCC August 31, 2021 @ 3:00 P.M. Posting of Intended Award September 13, 2021

Board Consideration of Intended Award October 4, 2021 Posting of Notice of Award October 5, 2021

This addendum is being posted to provide answers (A) to questions (Q) regarding ITB 2021-07

Page 2: ITB 2021-07 Addendum Number 1

ITB 2021-07 Smith Creek Volunteer Fire Department Building Addendum No. 1

2

Q.1 Will there be an addendum for the septic system? Need to know whether the

relocation will be by the county or by the contractor. A.1 The County is working to have the design, permitting and construction of this

work done independently from the awarded building contract. The building contractor would be responsible for coordinating with the septic contractor for installation of system.

Q.2 Are there any issues with using the existing water tanks? A.2 No Q.3 Where is the potable water coming from? A.3 Existing 4” well Q.4 Where will the material staging area be locate do site? A.4 SE corner, Refer to Red-line Attachment A0.01

Q.5 Who pays for permits? Who pays for the septic tank permit?

A.5 Contractor is responsible for securing the permits associated with the Building Construction

Q.6 When was the existing building built?

A.6 Property Appraiser Data indicates the structure was built in 1940

Q.7 Has there been a hazardous material survey?

A.7 Not at this time but the County has authorized one to be performed and will issue an addendum if the results are available prior to bid.

Q.8 Is there any septic tank work to be done or are we to use existing?

A.8 The County is working to have the design, permitting and construction of this work done independently from the awarded building contract. The building contractor would be responsible for coordinating with the septic contractor for installation of system.

Page 3: ITB 2021-07 Addendum Number 1

ITB 2021-07 Smith Creek Volunteer Fire Department Building Addendum No. 1

3

Q.9 “R” panel color for roof and wall panels?

A.9 To be selected from the full range of MFG color options

Q.10 What "R" Value Insulation in roof & walls?

A.10 Walls R11 Refer to input Data Report

Roof R19 Refer to input Data Report

Q.11 The plans do not provide any information concerning a new septic system. What

is your intent for a system and the inlet elevations. A.11 The County is working to have the design, permitting and construction of this

work done independently from the awarded building contract. The building contractor would be responsible for coordinating with the septic contractor for installation of system.

Q.12. Please provide the floor elevation to insure fall for the building sewer drain. A.12 F.F.E 69.0, Refer to Civil Sheet C4 Q.13 The water tank gets its power from the building to be demolished. Will the

county resolve this, if not please provide the amperage, voltage and location to supply power.

A.13 The County is in the process of moving the power supply prior to this work beginning.

Q.14 There is a indication the red iron is to be painted. Please provide clarification

and specification to provide this? A.14 Please refer to Specification Section 99123, page 5, 3.2 Preparation, 99123, page

9, 3.6 Interior Painting, D., 5 Water Based Light Industrial Coatings Q.15 The volatility of the market has the Metal building manufacture in a position

they cannot insure the building cost for more than five days. Will the county provide a measure to renegotiate the building cost after the time period.

A.15 Bid Bond requires that the Contractor hold their pricing for 14 days. We assume

the MFG’s will hold pricing for the 14 days the bidders who submit. Refer to Question 16 below.

Page 4: ITB 2021-07 Addendum Number 1

ITB 2021-07 Smith Creek Volunteer Fire Department Building Addendum No. 1

4

Q.16 Metal building manufactures require a 10 to 20 % deposit to put the building in production. The balance due when delivered. The county will provide these funds when requested or will the county purchase directly, also saving the taxes?

A.16 The County acknowledges current volatility of construction materials.

Contractor will submit with their bid the minimum cost required, by the Pre-engineered Metal Building (PEMB) Manufacturer, the price for putting the building in production and the required percentage, on PMB Letterhead. The County will make all efforts to provide the selected bidder that ‘Up Front Cost’ to secure the building production and secure the building pricing submitted. Efforts will be made to provide this payment within 14 to 21 days for selection.

Q.17 Has there been a asbestos and or lead presence survey for demolition? A.17 Not at this time but the County has authorized one to be performed and will

issue an addendum if the results are available prior to bid. Q.18. There is no available cell phone service for this area. Can the county provide a

phone land line for the contractor use? A.18 There is a land line on-site that the contractors may use during construction for

emergencies and general use.

Q.19 Please provide calcification to the following: Framing

Sheet A4.02 indicates 5/8' drywall to the back of exterior framed wall Sheet S2.1 note A/S2.1 indicates 1/2" plywood sheathing at exterior framed wall. Sheet S2.3 note J/S-2.3 indicates 1/2" plywood sheathing @ exterior framed wall.

A. 19 Refer to Red-Line sheets A4.02 & S-2.3

Q.20 Please provide calcification to the following:

Foundation/ slab Sheet S1.3 refers to detail D/S2. Detail D/S2.1 is for a interior wall foundation please provide the detail desired.

A.20 Refer to Red-Lined Sheet S-1.3

Page 5: ITB 2021-07 Addendum Number 1

ITB 2021-07 Smith Creek Volunteer Fire Department Building Addendum No. 1

5

Q21. Looking through the documents we do not find a reference to Builders Risk,

Insurance. Will the county provide this coverage. A.21 Contractor is expected to Provide: Builder Risk Bid Bond Performance Bond Q.22 There are several discrepancies as to warranties. We will as stated provide for all

products and performance, industry standard, a one year warranty, unless otherwise advised.

A.22 Contractor is responsible for providing the standard 12-month Warrantee on their work and any standard MFG Warrantees on products and materials. Contractor Warrantees and MFG Warrantees should be provided at the completion of the project prior to final payment. Documents should be bound in a 3-ring binder for submission to the County.

Q.23 Electrical questions asked of the Electrical Engineer. A.23 Refer to Attachment

Page 6: ITB 2021-07 Addendum Number 1
Page 7: ITB 2021-07 Addendum Number 1
Page 8: ITB 2021-07 Addendum Number 1
Page 9: ITB 2021-07 Addendum Number 1
Page 10: ITB 2021-07 Addendum Number 1

TO:

FROM:

DATE:

Applied R esearch and Design, Inc. 2623 S. Blairstone Road Tallahassee, FL 32301

Tel: (850) 668-6324

Bret Hammond / Hammond Design Group

James M. Lamb, PE

August 17, 2021

SUBJECT: Smith Creek Fire Station - Addendum

ARD # 0073

Please include the following as an addendum to the bid documents.

Item I: Reference sheet E0.0 I; In response to inquiry and equipment data submitted by bidder, the following equipment is approved for use on this project: • Generac #SD040 Generator, configured with options and accessories per !ans (enclosure,

base tank, battery charger, block heater, etc.) • Generac #TX301 Series Transfer Switch (configured per plans)

Item 2: Reference sheet El.01; Contractor is to provide generator remote annunciator, t I

be installed adjacent to fire alarm remote annunciator at room "Entry 01." Provide all cabling, raceways, etc. for a complete and operational system.

Please let me know if you have any questions.