islamic republic of pakistan of abbreviations adb asian development bank ap affected persons discos...
TRANSCRIPT
Islamic Republic of Pakistan
In Association with
Asian Development Bank (ADB)
Pakistan Power Distribution Enhancement MFF Project
Tranche III (Saving Component)
Loan No.2972-PAK
Laying of 132 kV D/C Copper Cable b/w 220 kV Shalamar – 132 kV
Shalamar - II Grid Stations
Due Diligence Report
September 2016
Lahore Electric Supply Company
(LESCO)
Table of Contents
List of Abbreviations
A. Project Overview
B. Background
C. The Subproject
D. Potential Social and Resettlement Impacts
E. Due Diligence
F. Community Consultations
List of Abbreviations
ADB Asian Development Bank
AP Affected Persons
DISCOs Distribution Companies
D/C Double Circuit
EA Executing Agency
LESCO Lahore Electric Supply Company
MFF Multi-tranche Financing Facility
MoWP Ministry of Water & Power
PEPCO Pakistan Electric Power Company
ROW Right of Way
TEPA Traffic Engineering Planning Agency
LDA Lahore Development Authority
WAPDA Water and power Development Authority
WASA Water and Sanitation Agency
Due Diligence Report
Laying of 132 kV D/C Copper Cable b/w Shalamar 220 kV – 132 kV
Shalamar - II Grid Stations
A. PROJECT OVERVIEW
1. The Government of Pakistan (the Government) has requested the Asian Development
Bank (ADB) to support the Power Distribution Enhancement Investment Program (the
Investment Program) and provide financing through a multi-tranche financing facility
(MFF) for $810 million over 10 years. The Investment Program is designed to provide
grid-connected customers with adequate and reliable supply of electricity. The
rehabilitation, augmentation, and expansion of the eight power Distribution Companies
(DISCOs) will increase the reliability of supply to residential, agricultural, commercial,
and industrial customers in Pakistan. A reliable electricity supply will lead to social and
economic benefits and improved conditions for schools, hospitals, and other social
services.
2. This Investment Program will (i) improve power distribution infrastructure through
system rehabilitation, augmentation, and expansion; and relieve the power system from
distribution bottlenecks and constraints; (ii) enable continued operation and maintenance
in accordance with best international practices; and (iii) commercialize DISCO
operations. Specifically, (i) DISCOs will adhere to regulatory requirements and comply
with regulated security standards; (ii) about 12,000 gigawatt-hours (GWh) of additional
energy is forecast to be supplied through the national grid annually; (iii) the system will
be upgraded to meet peak demand, with electricity outages significantly reduced; and (iv)
30 million additional people will have access to electricity from the national grid by 2018
3. Pakistan Electric Power Company (PEPCO) has been nominated by Ministry of Water
and Power (MOWP) to act as the Executing Agency (EA) with each DISCO being the
Implementing Agency (IA) for work in its own area. PEPCO’s role in the processing and
implementation of the investment program is that of a coordinator.
4. Lahore Electric Supply Company (LESCO) implemented the Tranche-III program which
included construction of 04 new grid stations, four (4) extensions and thirteen (13)
augmentation sub-projects, at overloaded substations. Now in order to utilize the savings
of approximately US$2.0 Million from T-III Loan No.2972-Pak, LESCO has included
this subproject in the scope of work as Saving Component (T-III) for ADB’s financing.
5. The said subproject comprises of Laying of 132 kV D/C Power Cable (Copper) b/w
220kV Shalamar – 132 kV Shalamar II Grid Stations. Shalamar and is feeding important
densely populated areas of old Lahore including Bhagwanpura,Singhpura,Shalamar Link
Road, Darogawal etc.
B. Background
6. In order to strengthen 132 kV system and dispersal of power from 220 kV Shalamar GIS
grid station LESCO has proposed interconnection between 220 kV Shalamar – 132 kV
Shalamar II grid station through 132 kV D/C underground Power Cable (Copper) of
approximately 300 m length. Moreover, it will be a feeding source for 132 kV UET
substation under construction for providing uninterrupted power supply for Orange Line
Train Project which is a mega project in the city.
7. Therefore, laying of 132 kV copper cable b/w 220 kV Shalamar -132 kV Shalamar is
essential and unavoidable in order to ensure continuous electricity supply for Orange
Line Train and to give relief and strengthen the distribution system.
C. The Subproject
8. The SP covers only the laying of 132 kV D/C underground power cable (copper cable)
between 220 kV Shalamar GIS – 132 kV Shalamar II Grid station. The route for laying of
new underground cable will be followed starting from Shalamar –II Grid station, passing
through the premises of grid station, adjacent WAPDA Base Workshop for automobiles
and will end in yard of 220 kV GIS Grid Station. The whole route exists within boundary
walls of 132 kV Shalamar G/Station,Base workshop WAPDA and 220 kV Shalamr Grid
station so no external people or community will be affected. Length of route will be
approximately 300 m.A trench for laying of cable has already been constructed. Map is
given in Annexure A.
9. This route is a tentative route and will be finalized once the contractor will be mobilized
to conduct survey and finalize the design. Photographs are given in Annexure B.
D. Potential Social and Resettlement Impacts
10. No purchase of land and dislocation of people is involved for this subproject as
underground cable will be laid down within the boundary wall of LESCO, NTDC and
WAPDA premises.
11. There are no directly or indirectly affected persons (APs) and no compensation payment
is involved.
E. Due Diligence
12. As there are no directly/indirectly affected persons (APs) and no compensation payment
is involved, the preparation of a LARP for this SP is not required and hence this brief due
diligence report has been prepared to documentary requirements of both the LESCO and
ADB.
F. Community Consultations
13. Consultation with the staff of 220 kV Shalamar Grid Station,132 kV Shalamar Grid
Station and WAPDA Base Workshop for automobiles was carried out on site. Detail
regarding consultation is given in Annexure A. All the relevant staff and officers showed
their consent for this project as already 220 kV grid station is connected to Shalamr II
grid station and underground power cable will provide another feeding source to
Shalamar grid station for further dispersal of electricity. However, all the relevant staff of
LESCO and WAPDA Base workshop showed their concern regarding design of the
project and urged for direct laying of cable underground instead of using of already
constructed trench for better safety and maintenance of cable.
Annexure A Consultation held on September 23, 2016
List of Participants in Consultation Sessions
Sr.No. Name of participants Address
1 Mr.Akhter Riaz
AET Shalamar
Shalamar-II Grid Station
2 Mr.Afzaal Shalamar-II Grid Station 3 Tariq Masood Malik
Manager
WAPDA Base Workshop
4 Tahir Javid Asstt.Manager WAPDA Base Workshop 5 Farooq Hassan
Asstt.Manager (O&M)
NTDC
220 kV GIS Shalamar Grid
Station
6 Javaid Bhullar Foreman 220 kV GIS Shalamar Grid
Station
Annexure B
Photographs of Route of 132 kV Underground Power Cable b/w 220 kV Shalamar-132 kV
Shalamar II Grid Station
Behind Control Room of Shalamar II Grid station where Route starts for U/G Cable
Base Workshop where cable route will enter into Base workshop premises
The wall of 220 kV Grid Station shown at far end where route will enter into 220 kV
Shalamar G/Station
Wall on other side where Route from Base workshop will enter into 220 kV GIS Shalamar
Yard of 220 KV Grid Station where u/g cable will end