iraq oil refineries status of existing and proposed …

20
IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED REFINERIES

Upload: others

Post on 21-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

IRAQ OIL REFINERIES

STATUS OF EXISTING

AND PROPOSED

REFINERIES

Page 2: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

2

Content

1. Existing operation and potential page 3

2. Major oil refineries page 5

2.1. Basra oil refinery page 5

2.2. Baiji North and Salahedden refinery page 9

2.3. Daura refinery page 14

3. Proposed refineries page 19

4. Minor refineries page 2

Page 3: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

3

Iraqi Oil Refineries 1- Existing and proposed oil refineries in Iraq

Existing and potential

In summary Iraq has a 4 major and 8 minor oil refineries. The nameplate crude processing

capacities of each are listed in the table below:

Summary of Iraq`s nameplate oil refining capacity

Oil Refinery Nameplate crude refining capacity (Barrels

per Day)

Major: Basra

Baiji :

-North -Salaheddin Daura

170,000

150,000 140,000 100,000

Sub total 560,000

Minor: Kirkuk Nasiriyah Haditha Simawa Synaya

Meisan Najaf Qayarah

30,000 30,000 14,000 20,000 30,000 10,000 20,000

4,000

Sub total 158,000

Current Total 718,000

New capacity: Proposed Kerbala Meisan Nassyria

140,000

150,000

300,000

Subtotal 490,000

Potential Total 1,208,000

All Iraqi`s major refineries suffer through disrepair and war damage in not being able to refine

crude to their nameplate capacities nor by being able to produce products to specification that their

original design intended. All represent opportunities for refurbishment to alleviate the current state

of disrepair to achieve nameplate capacity. Following this modernization programs will be required

to meet current international standards for refined products and acceptable health, safety and

environmental standards. We have outlined each major refinery`s potential refurbishment and

modernization programs required for each in the body of the report.

It is also felt that Iraq will require in the medium term 1 new centrally located major

refinery of capacity (1x 140,000 +1 x 150,000 + 1 x 300,000) BPSD to satisfy projected

growth in domestic demand. The location of all refineries in Iraq is shown in the

illustration below.

Page 4: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

4

Locations of Iraq's Oil Refineries

It is difficult to assess the refurbishment and modification requirements of the minor

refineries. The Synaya (Baiji) Meisan, Kirkuk, Simawa and existing Nassyria units are in

fact topping plants, these are the first in a series of a total of 8 small refineries that Iraq

intends to locate at various points around the country to ensure that domestic demand for

refined products will always be met form locally sourced refined products.

A topping plant is a small (100 - 10,000 barrel per day) refinery, usually of modular

construction, for transportability, that can take a variety of crudes to produce straight run

gasoline, diesel and fuel oil. Actual product specification and mix depends on quality of

crude used to feed it.

In this section we describe the existing operation – that is the ownership, construction history,

capacity, unit operations, product specification and environmental concerns – associated with each

major refinery; along with the opportunity associated with each – this is refurbishment needs,

modernization requirements and their associate cost and timing

Opportunity

The business opportunity associated with Iraq`s refinery sector in summarized in the table below

Iraqi`s refinery sector – summary of business opportunity

Page 5: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

5

Name Work scope

Total Capital Investment Projected (Million $)

Time Frame (year)

Major Refineries: 1- Basra 2- Baiji 3- Daura 4- Proposed 5- Karbala,

Mesan Refinery 6- Nasria Refinery

Refurbishment and Modernization Refurbishment and Modernization Refurbishment and Modernization New – build

1000 1500 800 2000 2000

6000

2-5 2-5 2-5 2-5

Sub total 13300

Minor Refineries

New Topping Plants New – build 200 2-5

Sub total

Total 13500

Full Detail of these investments can be found in the body of this report. These represent the total

estimated investment contemplated for full modernization of Iraq`s refinery sector in order that it can

meet international products quality and health, safety and environmental standards.

2- Major Oil Refineries

Iraq has three major existing refineries and plans to build a new facilities in the central and southern

region of the country.

2-1 Basra Oil Refinery

Basra is Iraqi`s second oldest refinery and is located in the south.

Existing Operations

The operations of the Basra oil refinery are summarized in the table below.

Basra Oil Refinery Existing Operations Summery

Parameter Value

Page 6: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

6

Construction and Ownership Constructed Start – up year Current owner Original Owner Main Contractor

1970 1973

South Refineries Company

Techno Export (Czech)

Operations Overall Name Plate Capacity (barrels per day) Actual Capacity (Barrels Per day) Crude Feed Gravity (˚API)

170,000 BPSD (60,000 – 80,000) BPSD

Unit Operations Number Total Capacity

(Barrels Per day) Status

Large Crude Distillation Unit 2 140,000 Operating Near Capacity

Small Crude Distillation Unit 3 30,000 Operating Near Capacity

Hydro-Desulphurization 1 25,000 Out Of Action

Reformers 2 10,000 Operating Near Capacity

Lube Oil Blending 2 125,000 Ton/Year 1 unit Out of Action

Isomerization 1 10,000 Planned

Water treatment Plant 1 Only Partially Operational

Power plant - - Sourced from National Grid

The product capacities and qualities achieved in Basra refinery are provided in the table below.

Basra Oil Refinery Product Capacities and Quality

Products Design Capacity (Tones per

Year)

Quality

Parameter Design 1998305

Fuel Oil 2,770,000 Sulphur (%) 4 – 4.5 4.0

Gas Oil 1,230,000 Sulphur (%) 1 – 1.2 1.0

Kerosene and Jet Fuel 1,150,000 Sulphur (ppm wt) Smoke Point (mm) Freezing Point(˚C)

1 – 10 27 -55

0.21

Gasoline 770,000 Octane Number (RON) 81(84306) 78

Naphtha (Reformate) 386,000 Octane Number (RON) 88 and 91

Liquid Petroleum Gas 112,000 Sulphur (ppm wt) 100 – 200 72.5

Page 7: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

7

Lube Oils 100,000 Sulphur (%) VI Colour Pour Point

0.7 – 0.85 95 3.0(1.0308)

-6

The Basra refinery, which came on stream in 1973, house two identical crude distillation unit with

capacities of 70,000 barrel per day each, plus three small, 10,000 barrel per day crude distillers.

It thus has a nominal capacity of 170,000 barrel per day.

The plant was virtually destroyed in 1980 – 1981, at the start of war with Iran, and again during the

Gulf war, but was repaired and rehabilitated each time. It had to be repaired

again more recently, following an American air strike that destroyed its distribution manifold in

December 1998.

The refinery now operates at close to (60 – 80) thousand PSD (60 % of design capacity) despite

poor maintenance and a shortage of materials and spare parts.

The refinery was designed to produce fuel oil, gas oil, kerosene and jet fuel, gasoline, naphtha, LPG

and lube oils. Its unit operations include:

• Gas oil hydro – desulphurization unit: this is out of operation , because it was stripped of

essential equipment, as a result the refinery`s untreated gas oil product has a sulphur

content 0.9 – 1.0 %

• Reformers: two reformers are installed and are operating at the plant. One produces

reformate with an octane number of 82, the second produces reformate with an octane

number if 88 and 89.

• Lube oil blender: one of the refinery`s two lube oil blending units was brought back into

operation in 1996, and there are plans for rehabilitating the second.

• Isomerisation Unit: there are plans for installing an isomerisation unit for the treatment of

light naphtha to raise octane ratings and minimize TEL in the gasoline. (Project under

execution)

• Water treatment: only the first stage of waste water treatment plant and the mechanical oil

skimmers function properly, so water and oil pumps are in operation. Completion of stage

two and three of the water treatment plants has been held up by the failure of the necessary

materials and equipment to arrive, due to contracts being kept on hold at the UN.

Consequently, a lake of waste oil has accumulated close to refinery over the past four

years. In addition, the refinery has to burn a lot of gas and LPG due to lack of cooling

capacity to condense those components, which is also environmentally damaging.

• Power plant; the refinery does not have its own power plant, and operations are frequently

disrupted by the power shortages, especially during the winter.

Page 8: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

8

Opportunity

The Basra Refinery based on to its current status offers the potential for number of refurbishment

projects to rejuvenate its existing operation in order that it can meet the product qualities intended

in its original design along with minimum acceptable health, safety and environmental standards. In

addition there are a number of modernization projects that could be expected international products

quality requirement as well as international health, safety and international standards and to be

upgraded in its products specification to meet euro 3 and euro 4 standards.

The projects that would be required for the Basra Refinery along with their rationale, timeframe and

estimated cost are provided in the table below.

Basra Refinery Refurbishment and Modernization Projects

Projects Rationale

Time Frame (Years)

309

Cost Estimate

(Million $)

Refurbishment Hydro – Desulphurization Unit

Rebuild of existing plant order that

acceptable gas oil product specification can

be met

2 – 3 50

Water Treatment

Completion of Water Treatment Plant to

Achieve international standard for disposal

water 2 20

Power generation Unit

New – Build power generation plant to end

dependency on power from national grid in

order to improve overall plant reliability

and efficiency 2 – 3 40

Lube Oil Blender Rehabilitation of second oil blender 2 10

General Upgrade

Refurbishment if all existing unit, in

particular cooling units, to achieve

minimum acceptable HSE standards 2 – 3 90

Subtotal 210

Modernization Isomerisation Unit

New – build isomerisation Unit to improve

octane rating of gasoline produces by the

refinery

2 – 3 60

Boiler Feed Water Plant Plant to improve treated water for existing

on site boiler 2 10

Environmental Remediation

Recovery of waste oil discharged in the

refinery`s vicinity and associated cleanup.

in addition the acceptability residuum in to

disposal wells would be reviewed 3 – 5 30

Hydrocracker Unit

New – build hydrocracker to improve the

recovery of gasoline and other light

products 3 – 5 650

Alkylation Unit New – Build Alkylation unit designed to

take gaseous products from the

hydrocracker to improve gasoline yield 3 – 5 40

Subtotal 790

Total 1000

Page 9: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

9

A total investment of $ 1000 Million is anticipated as being required the Basra refinery up to

international product quality and health, safety and environmental standards and upgrade it to euro

3 and euro 4 standard

2-2 Baiji – North and Salahedden

The Baiji Refinery complex is Iraqi`s latest and is located in northern Iraq.

Existing Operation

the operation of the Baiji – North and Salahedden oil refinery complex are summarized in

the table below

Baiji – North and Salahedden Oil Refinery Complex Existing Operations Summery

Parameter Value

Construction and Ownership

constructed

Start – up year Current Owner Original Owner Main Contractor

North 1980 – 1984 Salahedden Lube Oil plant 1982 – 1986 North Refinery Company North: - Chiyoda (Japan) Salahedden: Techno export(Czech) Mont invest(Yugoslav) Lube

Oil plant: Technip (France) and Techno Export (Czech) and

GAMA group (Turkey)

Operation Overall Name Plate capacity (barrels per day) Actual Capacity (barrels per day) Crude Feed Gravity (˚API)

290,000 140,000

Bai Hassan (34) and Jambur (38)

Unit Operation Number Total Capacity

(barrel per day) Status

North Crude Distillation Unit 1 150,000 Out of Action

Salahedden Crude Distillation Unit 2 140,000 Operation Near Capacity

Vacuum Distillation Unit 1 Out of Action

Hydro cracker 1 75,000 Out of Action

Reformers (UOP Technology) 3 15,000 Operation Near Capacity

Lube Oil Blending 2 250,000 Ton/Year 1 unit out of action

Bitumen 1 Operational

Isomerisation 1 20,000 Planned

Water Treatment Plant 1 180,000311 Capacity Limited

Power Plant - Sourced From National Grid

Page 10: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

10

The product capacities and qualities achieved in Baiji – north and Salahedden oil refinery complex

are provided in the table below.

Baiji – North and Salahedden Oil Refinery complex product Capacities and Qualities

Products Design Capacity 312

(Tones per Year)

Quality

Parameter Design 1998

Fuel Oil 5,540,000 Sulphur (%) 5.0 4.0

Gas Oil 2,460,000 Sulphur (%) 1 – 1.2(0.1314) 1.0

Kerosene and Jet Fuel 2,300,000 Sulphur (ppm wt) Smoke Point (mm) Freezing Point (˚C)

1 – 10 26 -55

0.21

Capacities of hydrocracker, reformers, lube oil blending, isomerisation and water treatment

units are estimates. This is requirement for refinery complex operating at full capacity; current capacity is no more

than 60,000 barrels per day. Capacities are estimates and are for all units operational.

These are values actually being achieved in 1998. This would be after implementation of hydro-desulphurization project.

Products Design Capacity (Tones per Year)

Quality

Parameter Design 1998

Gasoline 1,310,000 Octane Number (RON) 81(84315) 78

Naphtha (Reformate) 772,000 Octane Number (RON) 75 and 76 91

Liquid Petroleum Gas 190,000 Sulphur (ppm wt) 4 – 10 725

Lube Oil 150,000 Sulphur (%) VI Colour Pour Point

0.7 – 085 95

3.0(1.0316) -

6

The Baiji - North and Salahedden oil refinery complex is Iraq's largest and newest refinery.

It came on stream in phases during the 1980s; the North refinery was completed in 1980 and

Salahedden in 1986.

In total it houses three crude distillation units, the North unit has a capacity of 150,000

barrel per day whilst Salahedden comprises 2 separate 70,000 barrel per day units. It thus has

a nominal capacity of 290,000 barrel per day. At present the North unit is out of action

restricting production to around half of installed capacity. The Baiji refinery complex was

originally designed to function as a sophisticated catalytic conversion complex. As a result

of spares shortages and war damage it has been converted in to a simple hydro-skimming

operation. It includes a vacuum distillation unit and hydro – cracking unit are currently out

of operation following cannibalization to maintain other refinery operations.

Page 11: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

11

The complex was attacked during the Gulf war by heavy allied air attacks. Iraqi officials

estimated that 80% of the refinery was either destroyed or incapacitated by the raid.

Subsequently the complex has been rebuilt to achieve today's production levels. The complex

covers a total of twelve square miles and includes 180 crude and product storage tanks, 70

of which are in a state of disrepair.

The complex is currently geared towards the production of middle distillates, such as diesel

and gas oil, only two residuum upgrading operations are included in its design: lube oil plant

and bitumen plant. The Sulphur content of the middle distillates is excessive, exceeding

normally accepted limits by a wide margin. This is due to the inefficiency of the current

hydro-skimming process; lack of spares for the hydrogen compressors is forcing restrictions.

The refinery was designed to produce fuel oil, gas oil, kerosene, jet fuel, gasoline, naphtha,

LPG and lube oils. Its unit operations include:

• Vacuum Distillation Unit: this was included in the Complex's original design to

improve recovery of light ends products such as gasoline. This is currently out of

action.

• Hydro Cracker: this 75,000 barrel per day unit was originally installed to crack

residuum from the Atmospheric distillation units in order to achieve a significant

improvement in light ends products recovery. The Unit is currently out of action.

• Reformers: three reformers - two use semi regenerative catalysts - are installed and

are operating at the plant. One produces semi regenerative unit

Produces reformats with an octane number of 90 and 91 RON, the second produces

reformate of 70 through 75 RON, and the third unit’s reformate specification is 90 and 91

RON .

• Lube Oil Blenders : one of the refinery’s two lube oil blending units is operational ,

and there are plans for rehabilitating the second .

• Isomerisatiom Unit : there are plans for installing an Isomerisation unit for the

treatment of light naphtha to raise octane ratings and minimize TEL in the gasoline

( project is under Construction ) .

• Bitumen plant: a repair programm has been proposed for this propane deasphalting

unit .

• Water Treatment : The waste water treatment plant is significantly capacity limited

through lack of spare parts and design constraints . It is currently able to process no

more than 60,000 barrel per day of waste water this compares with the requirement

to process 180,000 barrel per day should the refinery reach its full operating capacity

.

Page 12: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

12

As with the other refineries in Iraq waste oil has accumulated close to the refinery in

specially dug pits , this create problems not just through its hydrocarbon content but

also due to the fact that it tends to be highly sulphurous. The refinery contributes

significantly to the pollution of the Tigris through discharge of its sulphurous

wastewater via a specially constructed canal in to the river.

• Power Plant: the refinery does not have its own power plant, and operations are

frequently disrupted by power shortages, especially during the winter.

Opportunity

The Baiji – North and Salahedden oil refinery complex based on its current status offers

the potential for a number of refurbishment projects to rejuvenate its existing operations

in order that it can meet the product qualities intended in its original design along with

minimum acceptable health , safety and environmental standards, In addition there are a

number of modernization projects that could be executed international product quality

requirements as well as international health , safety and environmental standards .

The projects that would be required for the Baiji – North and Salahedden oil refinery

complex along with their rationale, timeframe and estimated cost are provided in the

table below.

Baiji – North and Salahedden Oil Refinery Complex Refurbishment and

Modernization Projects.

Project Rationale Time Frame

(Year)

Cost Estimate(Million$)

Refurbishment

Fluid catalytic

Rebuild of existing

plant, including the

Hydrocracker , in

order to improve

Project Tender for

feasibility study for

30,000 BPSD

F.C.C Unit has

been announced

2-3

600

Page 13: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

13

Water Treatment Completion and upgrade of water Treatment Plant to

achieve higher capacity and international standard

for disposal water.

2 25

Vacuum Distillation

Unit

Refurbishment of Vacuum Distillation unit to

improve the recovery of gasoline and other light

products.

2-3 45

Hydro- Desulphurisation

unit Rebuild of existing plant in order that acceptable

middle distillate Sulphur specification can be met. 2-3 65

Power Generation unit New –build power generation plant to end

dependency on power from the national grid in order

to improve overall plant reliability and efficiency.

2-3 80

Lube oil Blender Rehabilitation of second lube oil blender (Project

and Developments Limited (India ) claim to have a

contract to execute this )

2 50

Bitumen plants Implement refurbishment and repair of this propane

deasphalting unit . 2 10

Tankage Repairs Refurbishment of 70 storage Tanks or Demolition

were redundant . 2-3 30

General Upgrade Refurbishment of all existing units, in particular

cooling units, to achieve minimum acceptable HSE

standards.

2-3 100

Subtotal 850

Modernisation

Isomerisation Unit New-build Isomerisation Unit to improve octane

rating of gasoline produced by the refinery . (Czech

company Technoexport along with BHEL(India)are

thought to have conducted

2-3 75

preliminary work on this )

Boiler Feed Water plant

+Boilers for Salahedden

and north refinery

Plant to provide treated water for existing on site

boilers.

2 80

Page 14: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

14

Environmental

Remediation

Recovery of waste oil discharged in the refinery’s

vicinity and associated cleanup In addition the

acceptability of discharging residuum in to disposal

wells would be reviewed .

3-5 50

Alkylation Unit New-build Alkylation unit designed to take gaseous

products from the hydrocracker to improve gasoline

yield

3-5 50

Wax unit New-build wax plant designed to produce 20,000

tonnes per year 5-7 50

Used Lube oil unit New- build plant designed to recover 10,000 tonnes

per year of used lube oil 5-7 40

High Viscosity Lube oil

unit New-build plant designed to produce 150,000 tonnes

per year of high viscosity lube oil 9-10 150

Subtotal 495

Total 1500

A total investment of $ 1500 million is anticipated as required to bring the Baiji – North and

Salahedden oil refinery complex up to international product quality and health, safety and

environmental standards and upgraded to Euro 4 standards.

2-3 Daura

Daura is Iraq’s oldest refinery and is centrally located close to Baghdad.

Existing Operations

The operations of the Daura oil refinery are summarized in the table below.

Daura oil Refinery Existing Operations summary.

Page 15: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

15

Parameter Value

Construction and Ownership

Constructed 1954

Start –up Year

Current Owner Middle central Refineries company

Original Owner Iraqi Government

Main Contractor Kelloge US Company

Operations

Overall

Name Plate Capacity (barrels per day) 100,000

Actual Capacity (barrels per day) 70,000

Crude feed Gravity (°API , Wt% Sulphur) Kirkuk Fao (27,2.9) and south Rumaila(34,2.1)

Unit Operations Number Total Capacity (barrels

per day)

Status

Cude Distillation Unit 1 100,000 Operating

70%capacity

Reformers 1 5,000 Operating Near

capacity

Isomerisation Unit 1 7,000 Planned already

contracted with STP

Italy)

Desulphurisation Unit 1 15,000

Lube oil Blending 1 125,000 One unit Out of action

Bitumen 1 Operational

Water Treatment plant 1

Power plant 1 Sourced from

National grid

The product capacities and qualities achieved in the Daura oil refinery are provide in the

table below.

Capacities of reformers, blue oil blending desulphurization and isomerisation units are

estimates

Capacities are estimates and are for all units fully operational.

These are values actually being achieved.

Page 16: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

16

Daura oil Refinery product capacities and quality.

Products Design

Capacity

(Tonnes per

year)

Quality

Parameter Design 1998

Fuel Oil 1,800.000 Sulphur (%) 5.0 4.0

Gas Oil 820,000 Sulphur (%) 1-

1.2(0.1)

0.21

Kerosene and Jet

Fuel

750,000 Sulphur (ppm wt)

Smoke point (mm)

Freezing point (°C)

0.1-0.2

27

-55

0.21

Gasoline 436,000 Octane

Number(RON)

81(84) 78

Naphtha

(Reformate)

250,000 Octane Number

(RON)

81(84)

Liquied petroleum

Gas

60,000 Sulphur (ppm wt) 100-2-- 725

Lube oils 50,000 Sulphur (%)

VI

Colour

Pour point

1.0(0.6)

95

3.0(1.05)

-6

The Daura oil refinery is Iraq’s oldest and smallest. It came on stream in 1954 and by western

standards in a deplorable state and if operational in any other country would have probably

ben shutdown due to the high personnel safety risk caused by the state of much of its plant.

It design center on a single atmospheric distillatiom unit, which suffers considerable

downtime through failures and lack of spare parts for pumps and other key items of

equipment.

The complex was attacked during the Gulf war by allied air attacks but suffered spare

damage. Subsequently the complex has been rebuilt to achieve today ُ s production levels.

The refinery ُ s design is based on a simple hydro-skimming operation and is currently geared

towards the production of middle distillates, such as diesel and gas oil, only two residuum

upgrading operations are included in its design : lube oil plant and bitumen plant . The

Sulphur content of the middle distillations is exceeding normally accepted limits by a wide

margin. This is due to the inefficiency of the current hydro skimming process caused by a

general lack of spares.

Page 17: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

17

The refinery was designed to produce fuel oil, kerosene and jet fuel, gasoline, naphtha,

LPG and lube oils . Its unit operations include:

• Reformers: 1 reformer is in operation producing reformate with an octane number of

78 RON. This is low and gasoline marketed by the refinery has an octane number of

81 RON, indicating that additives are being used .

• Lube oil Blender , a single lube oil blending unit is operational .

• Isomerisation Unit : there are plans for installing an Isomerisation unit for the

treatment of light naphtha to raise octane ratings and minimize TEL . in the gasoline

( Project was signed lately with STP Italy ) .

• Bitumen plant: a single lube oil blending units is operational.

• Water Treatment : currently the refinery discharges an oil rich waste water stream in

to the Tigris . The waste water treatment plant is capacity limited and requires

refurbishment to be brought up to acceptable standards.

AS with the other refineries in Iraq waste oil has accumulated close to the refinery in

specially dug pits, this creates problem not just through its. Hydrocarbon content but also due

to the fact that it tends to be highly sulphurous.

• Power Plant: the refinery does not have its own power plant, and operations are

frequently disrupted by power shortages, especially during the winter.

Opportunity

The Daura oil refinery based on its-, current status offers the potential for a number of

refurbishment projects to rejuvenate its existing operations in order that it can meet the

product qualities intended in its original design along with minimum acceptable health, safety

and environmental standards. In addition there are a number of modernization projects that

could be executed in the longer term to allow the refinery's operations to meet normally

expected international product quality requirements as well as international health, safety and

environmental standards. The projects that would be required for the Daura oil refinery along

with their rationale, timeframe and estimated cost are provided in the table below.

Page 18: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

18

Daura Oil Refinery Refurbishment and Modernization Projects

Project Rationale

Time 325

Frame (Years)

Cost Estimate

(Million $)

Refurbishment Water Treatment

Completion and upgrade of Water

Treatment Plant to achieve higher

capacity and international standard for

disposal water

2 15

Hydro-Desulphurization Unit

Rebuild of existing plant in order that

acceptable middle distillate sulphur specification can be met

2 – 3 50

Power Generation Unit New-build power generation plant to end

dependency on power from the 2 – 3 25

national grid in order to improve overall

plant reliability and efficiency

Lube oil Blender

Rehabilitation of existing Lube Oil

Blender and construction of a

second New-build unit.

2 20

Bitumen Plant Implement refurbishment and repair of

this propane deasphalting unit

2 30

General Upgrade

Refurbishment of all existing units, in

particular cooling units and boilers, to

achieve minimum acceptable HSE

standards

2 – 3 30

Subtotal 128

Modernization

Isomerisation Unit

New-build Isomerisation Unit to improve

octane rating of gasoline produced by the

refinery.

2 – 3 75

Boiler Feed Water Plant /Boiler Plant to provide treated water for

existing on site boilers + New Boiler

2 40

Environmental Remediation

Recovery of waste oil discharged in

the refinery's vicinity and associated

cleanup. In addition the acceptability

of discharging residuum in to disposal

wells would he reviewed

3 – 5 57

Hydrocracker Unit New-build Hydrocracker to improve the

recovery of gasoline and other light end

products 3 – 5 450

Alkylation Unit New-build Alkylation unit designed to

take gaseous products from the

hydrocracker to improve gasoline yield 2-1 5 45

Subtotal 672

Total 800

Page 19: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

19

A total investment of $800 Million is anticipated as required to bring the Daura refinery

complex up to international product quality and health, safety and environmental standards

and upgraded to euro 3 and euro 4 standard .

3- Proposed Refineries

The Proposed Refineries are :

a. Karbala Refinery of 140,000 BPSD

b. Meisan Refinery of 150,000 BPSD

c. Nassyria Refinery of 300,000 BPSD

These proposed refineries are to have the following operation units

1. Atmospheric Crude Distillation Unit

2. Vacuum Distillation Unit

3. Fluid Catalytic Cracker

4. Hydrocracker

5. Hydro-Desulphurisation Unit

6. Reformers

7. Lube Oil Blending

8. Bitumen

9. Isomerisation

10. Alkylation Unit

11. Water Treatment Plant

12 .Power Plant

These will be Iraq's newest refineries. The product and unit operations mix we have

proposed above is somewhat speculative but it does tie in with the expectation that heavy

East Baghdad Crude is to be processed. We would also expect the refineries to meet

international standards once it is built so we have selected a products slate that ties in with

that the standards are as per euro 3 or euro 4.

We would expect the refineries to make the best use of modern technology to achieve a

higher light ends product mix than other refineries an Iraq consistent with best

international practice. As such we would expect it to include fluid catalytic cracking,

isomerisation, alkylation, reforming and water treatment that meets acceptable standard

from the start of operations; along with an integrated power system more usual in modem

refinery complexes, elsewhere.

Page 20: IRAQ OIL REFINERIES STATUS OF EXISTING AND PROPOSED …

20

Opportunity

The proposed Refineries complex, based on our assessment, represents a considerable

modernization project in its own right. The projects that would be required to construct the

proposed refineries complex are as per attached tender requirement for Meissan refinery

complex as an example.

A total investment of 8,000 million is anticipated on the proposed refineries complex

configuration and capacity selected.

4- Minor Oil Refineries

Iraq has a total of 9 small refineries designed to process up to 27,000 barrel per day of crude.

Existing Operations

As can no doubt be appreciated the visibility of the minor refineries is somewhat less than

that of the Major units: we have summarized what we currently know of their function and

status in the table below.

Minor Refineries operations and Status Summary

Refinery name Capacity (barrels

per day Type and Process Status

Kirkuk 30,000 Topping Partially Operated

Nasoriyah 30,000 Topping Partially Operated

Haditha 14,000 Topping Partially Operated

Baiji 1 (Synia) 30,000 Topping Partially Operated

Meisan 10,000 Topping Partially Operated

Qayarah 4,000 Topping Partially Operated

Samawa 30,000 Topping Partially Operated

Najaf 20,000 Topping Partially Operated

Total 168,000

Opportunity

In terms of an opportunity Iraq has stated that it intends to purchase a further 7 topping

plants and distribute them around the country in order to ensure domestic supply security.

We estimate that the installed cost of such a system could be $20 - 30 Million per unit

requiring a total investment of the order of $140 -210 Million. Our expectation is that work

on the existing major refineries would take precedence over adding these topping units so

they represent a long term opportunity.

Downstream- Refineries – Opportunity

In June 2005 Iran and Iraq agreed to build a 40-Km pipeline to carry Iraqi crude oil from

Iraqi oil fields in the south-west of Basra to a refinery in Abadan in Iran. The refined

products will be then sent back to Iraq to cover local shortages.