investigation of instances of low or negative pressures in...
TRANSCRIPT
Defra Ref: WT1243/DWI 70/2/245 WRc Ref: DEFRA8356
October 2011
Investigation of Instances of Low or Negative
Pressures in UK Drinking Water Systems -
Final Report
RESTRICTION: This report has the following limited distribution:
External: DEFRA
© WRc plc 2011 The contents of this document are subject to copyright and all rights are reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted, in any form or by any means electronic, mechanical, photocopying, recording or otherwise, without the prior written consent of WRc plc.
This document has been produced by WRc plc.
Any enquiries relating to this report should be referred to the Project Manager at the following address:
WRc plc,
Frankland Road, Blagrove,
Swindon, Wiltshire, SN5 8YF
Telephone: + 44 (0) 1793 865000
Fax: + 44 (0) 1793 865001
Website: www.wrcplc.co.uk
Investigation of Instances of Low or Negative
Pressures in UK Drinking Water Systems -
Final Report
Report No.: DEFRA8356
Date: October 2011
Authors: John Creasey, David Garrow
Project Manager: Joanne Hulance
Project No.: 15340-0
Client: DEFRA
Client Manager: Annabelle May
The research was funded by the Department for Environment, Food & Rural Affairs (Defra) under
project DWI 70/2/245. The views expressed here are those of the authors and not necessarily those of
the Department or DWI.
Contents
Summary .................................................................................................................................. 1
1. Introduction .................................................................................................................. 5
1.1 Background ................................................................................................................. 5
1.2 Objectives .................................................................................................................... 5
2. Methodology for Surge Sites ....................................................................................... 9
2.1 Surge in distribution .................................................................................................... 9
2.2 Approach to logging .................................................................................................. 10
2.3 Choice of sites and locations .................................................................................... 10
2.4 Requirements for logging equipment ........................................................................ 11
2.5 Description of equipment .......................................................................................... 11
3. Methodology for Exceptional Demand Sites ............................................................. 15
3.1 The hydraulic effect of exceptional demands ............................................................ 15
3.2 Approach to logging .................................................................................................. 16
3.3 Choice of sites and locations .................................................................................... 16
3.4 Requirements for logging equipment ........................................................................ 18
3.5 Description of equipment .......................................................................................... 18
4. Surge Site A .............................................................................................................. 19
4.1 Choice of site and locations ...................................................................................... 19
4.2 Logging Results ......................................................................................................... 21
4.3 Example events ......................................................................................................... 23
4.4 Discussion and conclusions ...................................................................................... 29
5. Surge Site B .............................................................................................................. 31
5.1 Choice of site and locations ...................................................................................... 31
5.2 Logging results .......................................................................................................... 33
5.3 Mechanism of pressure surge in Site B .................................................................... 35
5.4 Example events ......................................................................................................... 36
5.5 Summary results ....................................................................................................... 39
5.6 Discussion and conclusion ........................................................................................ 39
6. Surge Site C .............................................................................................................. 41
6.1 Choice of site and locations ...................................................................................... 41
6.2 Logging Results ......................................................................................................... 42
6.3 Example events ......................................................................................................... 43
6.4 Summary results ....................................................................................................... 46
6.5 Discussion and conclusions ...................................................................................... 46
7. Exceptional Demand Site D ...................................................................................... 47
7.1 Choice of site and locations ...................................................................................... 47
7.2 Logging results .......................................................................................................... 47
7.3 Example events ......................................................................................................... 50
7.4 Summary results ....................................................................................................... 54
7.5 Discussion and conclusion ........................................................................................ 55
8. Exceptional Demand Site E ...................................................................................... 57
8.1 Choice of site and locations ...................................................................................... 57
8.2 Logging results .......................................................................................................... 57
8.3 Example events ......................................................................................................... 59
8.4 Summary results ....................................................................................................... 65
8.5 Discussion and conclusion ........................................................................................ 66
9. Exceptional Demand Site F ....................................................................................... 67
9.1 Choice of site and locations ...................................................................................... 67
9.2 Logging results .......................................................................................................... 69
9.3 Example events ......................................................................................................... 70
9.4 Summary results ....................................................................................................... 78
9.5 Discussion and conclusion ........................................................................................ 78
10. Discussion ................................................................................................................. 79
10.1 Surge ......................................................................................................................... 79
10.2 Exceptional demand .................................................................................................. 80
10.3 Health risk ................................................................................................................. 82
10.4 Operational practice .................................................................................................. 82
10.5 Practical aspects of pressure monitoring .................................................................. 82
11. Conclusions and Recommendations......................................................................... 85
References ............................................................................................................................. 87
List of Tables
Table 4.1 Summary of low pressures in Site A ....................................................... 22
Table 5.1 Summary of low pressures in Site B ....................................................... 33
Table 6.1 Summary of low pressures in Site C ....................................................... 43
Table 7.1 Summary of low pressures in Site D ....................................................... 49
Table 7.2 Minimum pressures recorded at each location during low pressure event on 6
th January 2011, Site D ............................................ 54
Table 8.1 Summary of low pressures in Site E ....................................................... 59
Table 9.1 Summary of low pressures in Site F ........................................................ 70
List of Figures
Figure 3.1 The effect of high demand ....................................................................... 15
Figure 4.1 Location of loggers in relation to pumping station, Site A ....................... 20
Figure 4.2 Location of the loggers within the network, Site A .................................. 21
Figure 4.3 Burst event on 23rd
June 2010, Site A ..................................................... 23
Figure 4.4 Location of major burst on 23rd
June, Site A ........................................... 25
Figure 4.5 Area adjacent to ferrule blow out ............................................................. 26
Figure 4.6 Pressure at logger 5 following ferrule blow-out ....................................... 27
Figure 4.7 Pressure at the booster station on September 29th 2010 ........................ 28
Figure 5.1 DMA and large customer flows ............................................................... 31
Figure 5.2 Location of the loggers within the network, Site B .................................. 32
Figure 5.3 Flow to large user on August 23rd
2010 .................................................. 35
Figure 5.4 Surge event on August 23rd
..................................................................... 37
Figure 5.5 Surge event on August 18th ..................................................................... 38
Figure 6.1 Location of loggers in relation to pumping station, Site C ....................... 41
Figure 6.2 Location of loggers within the DMA, Site C ............................................. 42
Figure 6.3 Surge event on 8th February 2011 ........................................................... 44
Figure 6.4 Effect of hydrant flushing at location 4 on 29th March 2011 .................... 45
Figure 7.1 Location of loggers at Site D ................................................................... 48
Figure 7.2 Pressure trace on 29th November 2010 in DMA1, Site D ........................ 50
Figure 7.3 Location of local booster pumps for location 1, Site D ............................ 51
Figure 7.4 Pressure trace on 6th January 2011 in DMA 1, Site D ............................ 52
Figure 7.5 Pressure trace on 6th January 2011 in DMA 2, Site D ............................ 52
Figure 7.6 Location of loggers in DMA 1, Site D ...................................................... 53
Figure 8.1 Location of loggers at Site E ................................................................... 58
Figure 8.2 Pressure trace on 19th July 2010 in DMA 3, Site E ................................. 60
Figure 8.3 Pressure trace on 19th July 2010 in DMA 4, Site E ................................. 61
Figure 8.4 Pressure trace on 19th July 2010 in DMA 2, Site E ................................. 62
Figure 8.5 Pressure trace on 24th August 2010 in DMA 5, Site E ............................ 63
Figure 8.6 Location of loggers in DMA 5, Site E ....................................................... 63
Figure 8.7 Pressure trace on 24th August in DMA 4 in Site E .................................. 64
Figure 8.8 Pressure trace on 19th September 2010 in DMA 3 in Site E ................... 65
Figure 9.1 Location of loggers at Site F .................................................................... 68
Figure 9.2 Location of flushing on 2nd
August, Site F ............................................... 71
Figure 9.3 Flushing on 2nd
August 2010, Site F........................................................ 72
Figure 9.4 PRV event on 17th August 2010, Site F ................................................... 73
Figure 9.5 Burst on 3rd
December 2010, Site F ........................................................ 74
Figure 9.6 Mains repair on 8th December 2010, Site F............................................. 75
Figure 9.7 Event on 19th July 2010, Site F ............................................................... 76
Figure 9.8 Location of affected loggers on 19th July event, Site F ........................... 77
List of Photographs
Photograph 2.1 Installed kiosk for pressure logging – surge equipment .......................... 12
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 1
Summary
i Background
In a number of papers, concern had been raised that low pressures may occur in water
distribution systems such that dirty water could be drawn into the pipe with a consequent risk
to health. It was suggested that this could be the result of exceptional demands or unusual
operational events. A review was carried out for Defra by WRc. The review concluded that the
most valuable next step would be to carry out long-term pressure monitoring in distribution
systems. This project was the result of following up this conclusion.
ii Objectives
1. Identify three distribution systems that are likely to be subject to surge effects.
2. Identify three distribution systems that are likely to be subject to longer term
depressurisation caused by exceptional demand including bursts.
3. Within each distribution system identify appropriate vulnerable points for pressure
monitoring.
4. Install appropriate high speed pressure monitoring equipment and recording
instrumentation at the locations identified.
5. Maintain the pressure monitors throughout the study.
6. Download and review data from the pressure monitors at regular periods, gathering
other relevant data to help interpret the results.
7. Carry out final analysis and investigation, draw conclusions and report the findings.
iii Approach
Detailed pressure monitoring was carried out in 6 separate distribution networks for a
combined period of 56 months. The data was reviewed regularly and low pressure events
were investigated. The investigation included reference to the knowledge of water company
staff. Hydraulics theory, low pressure statistics from the fieldwork and detail from example
events were used to draw conclusions.
iv Conclusions
1. Some low and negative pressures were observed during the study.
2. The probability of very low (surge) pressures as a result of a sudden demand is very
low.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 2
3. The probability of very low pressures as a result of exceptional high demands is very
low.
4. A system is most at risk from low surge pressures if:
a. Pipe junctions are widely spaced
b. Property density is low (low number of service pipe connections)
c. There are very rapid increases in demand.
5. A system is most at risk from exceptional demands if:
a. There is a fall in ground level from the source followed by a substantial rise
b. There is a significant area at low level
c. There is a significant area at high level
d. Normal pressures in the high level area are low.
6. Pressures low enough to cause ingress are more likely as a result of the following than
they are from a demand-driven event:
a. Isolating mains for repair
b. Mains draining down during valving operations
c. Pump failure or rapid pump switching
d. PRV failure or maintenance.
7. To pose a health risk a source of contaminant around the low pressure point and a
pathway to the pipe flow are also necessary.
8. Thorough planning is required to ensure the successful completion of such an
extensive monitoring exercise.
v Recommendations
1. Additional proactive measures are not required to minimise an already low probability of
very low pressures occurring.
2. The practice of designing distribution systems with alternative routes to most customers
(i.e. with loops) should continue.
3. Good practice should be followed with respect to:
a. Opening and closing valves and hydrants slowly
b. Running hydrants at the lowest necessary flow
c. Returning mains to service (disinfection)
d. Disinfecting local mains which have drained as a consequence of work on other
mains
e. Implementing soft start and stop for pumps
f. Maintaining PRVs and maintaining pressures during maintenance.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 3
4. When carrying out research of this nature:
a. A thorough survey should be carried out of all potential locations for any monitoring
equipment
b. Sufficient alternative locations should be identified.
vi Résumé of Contents
The report gives underlying theory, describes the choice of sites and logging equipment, gives
a summary of all low pressure events and includes example events from each site.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 4
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 5
1. Introduction
1.1 Background
In a number of papers, concern had been raised that low pressures may occur in water
distribution systems such that dirty water could be drawn into the pipe with a consequent risk
to health. It was suggested that this could be the result of exceptional demands or unusual
operational events.
A review was carried out for Defra by WRc (WRc, 2008). It was chiefly concerned with the
circumstances under which low pressure could occur and the probability of such an
occurrence. Clearly, the risk to health depends on the integrity of the pipe, the nature of the
surrounding material, the quantity of water drawn into the pipe and the number of customers
downstream of the low-pressure point. However, the study investigated the hydraulic aspects
of this issue.
The review concluded that:
1. There are two different possible mechanisms: surge caused (for example) by pump
switching and longer-term fluctuations caused by exceptional demands.
2. The probability of ingress is low but the consequences may be significant.
3. The most valuable next step would be to carry out long-term pressure monitoring in
distribution systems.
This project was the result of following up conclusion (3).
1.2 Objectives
It was intended to monitor pressure in six systems. In three cases, the investigation was to be
concerned with the effects of exceptional demand and, in the others, with the surge
mechanism. Pressure was to be logged at a number of locations in each system for up to a
year. When pressure events occurred, background information would be collected in order to
identify a cause. Examples of such possible causes were thought to be pumps stopping or a
large burst at the time of the low-pressure event. The events were to be investigated to
determine if there had been a causal link, why the low pressure occurred at a particular
location and, what the effect would be of a change in the severity of the initiating event.
Sites were provided by a number of water companies, following discussions with WRc. The
participating water companies provided details on possible sites, allowing WRc to select those
sites most vulnerable to very low pressures and most appropriate for a study of this nature.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 6
The water companies also provided information on activities that might explain the low
pressure events witnessed within the sites.
All water companies, sites and locations within this report are anonymous. However, WRc are
very grateful to the four water companies who provided assistance.
The objectives of the project were:
1. Identify three distribution systems (“sites”) that are likely to be subject to surge effects
based on the factors previously reported.
2. Identify three distribution systems (“sites”) that are likely to be subject to longer term
depressurisation caused by exceptional demand including bursts.
3. Within each distribution system identify appropriate vulnerable points (“locations”) for
pressure monitoring.
4. Install appropriate high speed pressure monitoring equipment and recording
instrumentation at the locations identified.
5. Maintain the pressure monitors throughout the study including periodic calibration and
zeroing and ensure any spurious reading are promptly identified and steps taken to
correct performance.
6. Download and review data from the pressure monitors at regular periods, gathering
other relevant data to help interpret the results including data from the water company‟s
own monitoring and modelling outputs and the water company‟s own knowledge of
events in the network.
7. Carry out final analysis and investigation and draw conclusions.
8. Report the findings.
The final report was to include the following items:
1. Results of the monitoring surveys, identifying low and negative pressure events.
2. Conclusions on the spatial extent of surge pressures.
3. Identification of possible causes by linking low pressure occurrences to network events.
4. Extrapolation of results to demonstrate the possibility of more extreme pressure
excursions.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 7
5. An estimation of the frequency of these events throughout England and Wales.
6. Suggested improvements in operational practices.
This report contains the results of the monitoring work undertaken at all six selected sites.
The remainder of this report is split into sections. Sections 2 and 3 detail the monitoring
methodology used for the surge and exceptional demand sites, Sections 4 to 9 present
locational details and the results of monitoring pressures at each individual site, Section 10
provides a discussion of these results and the insights gained, and Section 11 presents the
conclusions and recommendations arising from this work.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 8
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 9
2. Methodology for Surge Sites
2.1 Surge in distribution
Whenever the rate of flow of water in a pipe changes there is a related change in pressure.
This change can be very much larger than the normal operating pressure, resulting in very
high or very low (surge) pressure. If a rapid increase in demand takes place, pressure at that
point will fall. This low pressure will travel through the system at high speed (the
“wavespeed”). A useful rule of thumb which gives the potential pressure change is given by
the Joukowski relationship (Wylie and Streeter, 1978):
v.a.p
where Δp change in pressure (N/m2)
ρ density of water (kg/m3)
a wavespeed (m/s)
Δv change in velocity (m/s)
The wavespeed depends (inter alia) on the pipe material. Wavespeeds in metal pipes are
greater than 1000 m/s, whereas wavespeeds in plastic pipes are usually in the range 400 to
500 m/s. As a consequence, the pressure change in a metal pipe for a given velocity change
is greater than that in a plastic pipe. Surge pressure changes can be very large. If the velocity
in a metal pipe changes by 1 m/s, the pressure may change by more than 100 m.
An example is provided by valve closure in a long simple trunk main. As the valve closes, the
pressure rises on the upstream side and falls on the downstream. These changes travel away
from the valve, travelling at the wavespeed.
There are a number of reasons why the change in pressure may be less than the value
predicted by the Joukowski equation. In the context of distribution systems, the important
issue is reflection from pipe junctions. When the surge event reaches a junction, only some of
the change is transmitted along the other pipes from the junction. A reflection of a lesser
magnitude and opposite sign returns along the incident pipe.
This has two effects. The impact of the pressure change decreases with distance from the
initiating event and the reflection modifies the pressure change at the source making it smaller
than the potential would suggest. The first consequence in a distribution system is that, at no
point, is the change as large as might be expected. The second is that the impact reduces
with each junction as the event moves away from the starting point. This latter effect limits the
spatial extent of any low pressure risk.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 10
Timescale is an important issue. If the nearest junction to the initiating point is distant by
100 m of iron pipe, the first reflection will return in approximately 0.2 seconds (= 2*100/1000).
As a consequence, any pressure change which takes longer than 0.2 seconds will be
modified (i.e. reduced). In this context, a rapid event (surge) is one which takes less than
0.2 seconds.
The pipe pressure at which ingress would be possible depends on the depth of the pipe. It is,
therefore, unlikely to be greater than 0.1 bars since the pipe would have to be more than 1 m
below water for ingress to occur at that pressure.
2.2 Approach to logging
The main concern is with intermittent and (possibly) unusual events. It was not known, in
advance of the logging, when or where (or even if) such an event would occur. This had a
marked effect on the approach taken. In order to increase the likelihood of securing data
during a surge event, it was planned to leave the loggers in situ for up to one year.
For this type of site, the location of the possible event is likely to be known (e.g. power failure
at a specific pumping station). This removes one of the unknowns discussed for exceptional
demands (see Section 3.2). As a result, far fewer loggers were to be deployed (five). One
would be at the event site (e.g. downstream of the non-return valve at the pumping station).
The others would be deployed at increasing distances into the distribution system. (More
accurately, with increasing numbers of junctions between event location and logger location.)
The rapidity of surge events (see Section 2.1) demands that pressures are logged frequently.
It is easy to miss maximum and minimum values of pressure if the logging interval is too
large. In this case, it was necessary to log at 0.1-second intervals. This is the time taken for a
surge pressure to travel 50 to 60 m in an iron pipe and return to the initiating point. It is
therefore short enough to capture the details produced by reflections in a distribution system.
Plastic pipes do not require such a short logging interval.
2.3 Choice of sites and locations
2.3.1 How the choice was made
It is known that maximum surge pressure change can develop in a long un-branched main. It
was argued that the best chance of recording an event with very low pressures would be in a
distribution system fed by a long pumping main. On pump failure, pressure would drop
significantly in the main because sufficient time would be available for the surge to develop.
By deploying loggers within the system, the progress of the low pressure could be tracked.
For these sites, the main parameters of interest are number and spacing of junctions and pipe
material. Ground level is only a secondary consideration, as opposed to being of primary
consideration for exceptional-demand driven low pressures. The plan was, therefore, to site
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 11
one logger at the pumping station, one at the feed to the distribution system and three more at
increasing distances from the pumping main. These three locations would be hydrants chosen
with increasing number of junctions between each and the pumping main. In each case, it
was possible to select alternative logger locations when practical difficulties were found with
the initial choice.
Sites A-C were selected as examples of surge scenarios and are described in Sections 4 to 6
below.
2.3.2 The lessons learnt
In addition to the preferred locations, a number of alternative hydrants were selected for each
site. This was done in order to accommodate the practical issues that may arise which would
prevent a location from being used. These issues can include a leaking or damaged hydrant,
lack of appropriate position for the kiosk housing the logger, or inability to obtain permission
from the land owner/highways authority to install the logger and kiosk.
2.4 Requirements for logging equipment
The logging equipment was required to generate readings at a sufficient frequency to detect
pressure changes of the duration anticipated. The lowest pressure generated in a kilometre of
iron main would be expected within the first two seconds after the initiating event (a pump
stopping). In this case, it would be necessary to log at intervals of 0.1 seconds to capture the
low pressure value. Standard loggers, of a type similar to those used in the exceptional
demand sites, were unable to provide the granularity of logging required.
The selected specialised loggers could log at such intervals and were programmed to monitor
pressures continuously but were only triggered to record data when the pressure fell below a
set low value (dependent on the location). By using a rolling buffer, the logger captured data
from 100 seconds prior to the trigger threshold being surpassed, until the end of the low
pressure event. When the pressure remained below the trigger level for a short period only,
the logger records data until an end point of 400 seconds after the pressure dropped below
the level. It was necessary for the loggers to be capable of being downloaded weekly via a
remote connection. This was needed to allow any events to be investigated with the water
company while they were still recent.
2.5 Description of equipment
The loggers used for surge monitoring were Campbell CR800 loggers complete with modem,
battery and photocell. The pressure sensors were 0-10 bar gauge, 0.25% accuracy and gave
un-calibrated negative readings at negative pressures. The loggers were connected to
pressure sensors which were attached to the hydrants using a hydrant cap via a quick action
coupling. The sensors also had a sealed electrical connection, to protect them in the event of
the hydrant pit flooding. Throughout the monitoring operation the hydrants remained slightly
opened.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 12
The size of the Campbell CR800 loggers prevented them from being installed in the hydrant
chambers, as was the case with the exceptional demand sites. Each logger was, therefore,
mounted inside a roadside kiosk, with a slot drilled into the road and pavement from the kiosk
to the hydrant to protect the sensor cable inside a 12 mm airline. This kiosk also provided
sufficient storage space for the batteries. A solar panel was mounted upon a pole above the
kiosk to keep the batteries charged.
Where the kiosk was to be installed on a natural surface, such as grass, the kiosk was either
attached to paving slabs first or dug directly into the ground, depending upon the specifics of
the location. Each kiosk measures 1750 mm (height) x 900 mm (width) x 545 mm (depth).
Permission to install these kiosks was obtained from the land owner and highways authorities
for each location and effort was taken to site the kiosks in the least obtrusive way at each
location.
Photograph 2.1 Installed kiosk for pressure logging – surge equipment
An example of an installed kiosk is shown in Photograph 2.1. The slot for the cable can be
seen in the bottom left of the picture.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 13
Data were downloaded weekly from each site. Downloads were performed remotely, using a
mobile telecommunications link. This link also allowed the loggers‟ performance and status to
be monitored, trigger points to be altered and new programs to be downloaded without the
added expense of sending out personnel. Initially, the communications facility was available
constantly, but could be limited to a period of only (for example) eight hours once a week to
limit the drain on the battery should the solar panel fail to provide enough power to keep the
battery running. This was necessary for one logger, where the solar panel became unable to
provide sufficient power to the batteries for constant communication.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 14
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 15
3. Methodology for Exceptional Demand Sites
3.1 The hydraulic effect of exceptional demands
The mechanism being investigated in these cases is illustrated in Figure 3.1 and is as follows:
1. An unusual high demand occurs at point
2. The resulting high flowrate increases the friction loss between the source (S) and P
3. This reduces the available pressure at P and at other points in the system.
Pressure at points downstream of P (D, E and F) will fall by the same amount as the reduction
at P. Pressure at points upstream of P and on route to P (B) will fall by a smaller amount (the
proportion of extra friction loss which occurs between S and B). Similarly, points fed from
branches on route to point P will suffer only a smaller drop (for example, pressure at C will fall
by the same amount as the pressure at B). There will be no effect on pressure at point A.
Figure 3.1 The effect of high demand
These low pressures will be maintained for as long as the exceptional demand persists.
Although the pressure at point P will drop significantly, it will necessarily remain positive to
drive the large demand at that point. Points vulnerable to low pressure will, therefore, need to
be at markedly higher ground level than point P. A point will also be vulnerable if the pressure
S
C
A
B
P
D
E
F
E
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 16
is normally low and if there is inadequate pipework between S and P. This aspect is
developed further in Section 3.3 on the choice of sites.
The pipe pressure at which ingress would be possible depends on the depth of the pipe. It is,
therefore, unlikely to be greater than 0.1 bars since the pipe would have to be more than 1 m
below water for ingress to occur at that pressure.
3.2 Approach to logging
As with the surge sites, these investigations are concerned with unusual, unpredictable
events. It was not known, in advance of the logging, when or where (or even if) such an event
would occur. This had a marked effect on the approach taken. In order to increase the
likelihood of securing data during an exceptional demand event, it was planned to leave the
loggers in situ for up to one year. This estimate was based on results from a previous
investigation (WRc, 2008).
The loggers need to be sited at vulnerable points in order to record the most useful data. The
position of these points would depend on the position of the demand event (as in Figure 3.1).
Since the position of the event (e.g. burst or fire flow) is not predictable, it is necessary to log
over a wide area. It was planned to install up to 20 loggers on each site, provided that a
sufficient number of appropriate locations could be identified.
In the case of these “exceptional demand” sites, it is envisaged that the high flow will continue
for at least a few minutes and that the defining hydraulics will be “quasi-steady-state” without
any transient pressure effects. This leads to the argument put forward in Section 3.1 and
should be compared with the discussion of “surge” in Section 2.1. As a result it was decided
that an instantaneous value logged every 10 seconds would provide sufficient detail.
Inevitably it is unlikely that the detail of any transient events that occurred in these systems
would be detected.
3.3 Choice of sites and locations
3.3.1 How the choice was made
Three sites needed to be found for this aspect of the work. To maximise the probability of
logging at locations of interest, and to obtain maximum benefit from the data, sites were
chosen bearing in mind the arguments of Section 2.1.
A significant variation in ground level is needed. Potential low-pressure points will be much
higher than the location of the exceptional demand. Normal operating pressures will be at
least 15 m (about 1.5 bars head). To give a possibility of sub-atmospheric pressures at a high
point, and still maintain a driving head at the demand point, a difference in ground level of at
least 20 m is necessary. Sites with at least this variation in ground level were sought.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 17
Section 3.1 shows that it is possible for a location, vulnerable to low pressure, to lie between
the demand point and the source of supply. However, a further requirement is that significant
head loss will be developed between the source and this location. It is the nature of
distribution networks that pipework close to the source is of larger diameter than that further
into the system. The effect of a given demand on friction in these pipes will usually be small.
Therefore, it is most likely that the vulnerable points will be downstream of the demand point.
Sites were, therefore, sought where a low-lying area lies between the supply source
(e.g. reservoir) and an area which is 20 m or more above this low point. The bigger the low-
lying area, the greater the chance of an exceptional demand in a position to cause low
pressures elsewhere. The bigger the area of high ground, the more positions are suitable for
logging and the greater the chance of insight into this mechanism.
Mains maps with contours and hydrant positions were used to find hydrants at which to site
the loggers. Contours sufficiently high compared to the system low point were highlighted.
Hydrant positions to cover the high ground were chosen. Hydrants in close proximity to each
other were avoided on the grounds that no extra information would be gained by logging at
both. This did, however, leave some alternative locations should any of the first choices be
unusable for practical reasons. A few locations at hydrants unlikely to be significantly affected
by pressure events were chosen for comparison purposes.
Sites D-F were selected as examples of exceptional demand scenarios and are described in
Sections 7 to 9 below.
3.3.2 The lessons learnt
It proved difficult to find distribution systems with the necessary topography to give a risk of
sub-atmospheric pressures. (Sites were sought in four companies. They cover large areas of
Southern England and the Midlands including significant areas of hilly terrain.) This, in itself,
gives an indication that the risk at a national level may be quite low.
Additionally, some sites which fulfilled the topographical requirements had only short pipe
lengths within the low-lying area and/or within the high area. The former issue reduces the
risk of a demand in a critical area; the latter reduces the area where ingress may occur. The
probability that other environmental conditions are such that ingress occurs and that there are
health implications is reduced if the area is small. However, ingress in this small area may still
put at risk downstream customers. The consequences could potentially be large if there are a
large number of these downstream customers.
To obtain maximum value from the logging exercise, systems with a substantial area of high
ground were chosen. This also allows for a number of alternative logging locations to be
identified in order to use when practical issues regarding the installation and maintenance of
loggers prevent the preferred location being used. Issues that can prevent loggers being
installed upon hydrants include a leaking or damaged hydrant, lack of access to the hydrant
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 18
chamber (e.g. cars parked over the cover or the hydrant being located in a busy road), too
shallow a hydrant chamber to allow the logger to be installed, or a buried hydrant. A number
of these issues were encountered during installation, requiring the alternative locations to be
utilised on occasion.
3.4 Requirements for logging equipment
Exceptional demand pressure events are relatively slow events, thus the logging equipment
for the exceptional demand sites did not need to log at the very short interval required for
surge monitoring (Section 2.4). The loggers were required to log at ten-second intervals and
to store sufficient data to allow for monthly downloads without data loss.
3.5 Description of equipment
The loggers used were Primayer Primelog 10 bar loggers, with additional memory provided to
ensure sufficient storage.
The locations of all loggers were agreed with the water company and details of final locations
provided for their operational records. The pressure loggers were attached to selected
hydrants throughout the distribution system. The loggers were connected to pressure sensors
attached to a hydrant cap via a quick action coupling, and the logger placed within the hydrant
pit.
Data were collected from the loggers on a monthly basis from each site. Data from each
logger was manually downloaded onto a laptop using bespoke software provided by
Primayer. All installation and data downloading was undertaken by trained WRc personal with
the appropriate “National Hygiene Scheme” accreditation.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 19
4. Surge Site A
4.1 Choice of site and locations
Site A was identified through discussions with water company representatives. This site has
experienced low pressure problems in the past. However, the implementation of a new soft
start/stop system at the pumping station prior to the logging period was expected to reduce
these problems. Despite this, it was decided that this site was of interest for the purposes of
this project, as the potential existed for low pressures, should there be a fault at the pumping
station.
The system at Site A is fed from a number of boreholes via a pumping station. This pumping
station pumps water along two mains (16” PVC and 12” cast iron (CI)) to a reservoir at the
other end of the system. One of the pressure loggers was installed at this pumping station, to
observe any low pressures that may originate here (location 1, Figure 4.1).
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 20
Figure 4.1 Location of loggers in relation to pumping station, Site A
123123123123123123123123123
999999999999999999
129129129129129129129129129
878787878787878787
848484848484848484
138138138138138138138138138117117117117117117117117117
939393939393939393
909090909090909090
102102102102102102102102102
13
213
213
213
213
213
213
213
213
2
105105105105105105105105105
96969696
9696
969696
120120120120120120120120120135135135135135135135135135
11
411
411
411
411
411
411
411
411
411
111
111
111
111
111
111
111
111
112
612
612
612
612
612
612
612
612
6
108108108108108108108108108
141
141
141
141
141
141
141
141
141
818181
8181
818181
81
787878787878787878
144144144144144144144144144
52
3
Trunk Mains
Water mains
3m contours
Hydrants
Meters
Logger locations
Pumps
1
16"
12"
4
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 21
The other four loggers were located in a village supplied from the 12” pumping main
(Figure 4.2). A booster station draws water from the pumping main and supplies it to the
village. One of the pressure loggers was installed on the outflow from the booster pumps, to
observe the impact of any low pressure events at the boosters (location 2). The remaining
three pressure loggers were installed at selected locations throughout the village, chosen to
reflect an increasing level of complexity in the system, with a greater number of junctions
reducing the magnitude of any pressure waves as they travel from location 3 to 4 and then to
5.
Figure 4.2 Location of the loggers within the network, Site A
4.2 Logging Results
Pressure loggers and kiosks were installed at the pumping station and booster pumps
(locations 1 and 2) on 17th February 2010, with the remaining three loggers installed later, on
9th June 2010. The loggers and kiosks were removed on 9
th March 2011.
Table 4.1 gives a summary of the low pressures recorded at these locations. It should be
noted that a number of individual low pressure events may have occurred but could have
been overwritten by subsequent low pressure events, before the weekly download took place.
This would only happen if long-term (non-surge) low pressure events lasted long enough to
exceed the memory size. This would only occur in the event of either many pressure drops or
117
117
117
117
117
117
117
117
117
135
135
135
135
135
135
135
135
135
132
132
132
132
132
132
132
132
132
126
126
126
126
126
126
126
126
126
141141141141141141141141141
138
138
138
138
138
138
138
138
138
111111111111111111111111111108
108
108
108
108
108
108
108
108
120120120120120120120120120
123123123123123123123123123
129
129
129
129
129
129
129
129
129
114114114114114114114114114
102102102102102102102102102
999999999999999999
969696969696969696
93
93
93
9393
93
93
93
93
52
3
4
Trunk mains
Water mains
3m contours
Hydrants
Meters
Logger locations
Pumps
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 22
a prolonged drop occurring. This occurred at all five loggers during an event on 26th July,
which is discussed in more detail below.
Table 4.1 Summary of low pressures in Site A
Location Trigger
(bar)
No of
events
< 1 bar
No of
events
< 0.1 bar
Min Observed Pressure
Pressure
(bars) Date
Duration
below 0.1 bar
1 4.40 1 1 -0.10 26th Jul n/a
2 1.3 84 1 0.06 23rd
June 56 sec
3 1.6 3 1 -0.03 26th Jul n/a
4 1.7 4 1 -0.01 26th Jul n/a
5 2.75 2 1† -0.47 21
st Sept 17.5 min
† Pressure fell below zero three times during this one event.
At four of the locations, there were very few occasions where the pressure fell below one bar.
At location 2, there appears to be a minor pump control problem which frequently causes the
pressure immediately downstream to fall briefly below one bar. The pressure as a result of
this control issue was never observed to fall to negative pressures and, therefore, is of no
consequence from an ingress point of view.
There were only four sub-zero pressures recorded in the nine-month logging period. A major
burst occurred on the 16” main on 26th July. However, on the same day pressures fell below
zero at locations 3 and 4. This was due to the fact that the supply to the village was cut off to
protect the reservoir, which is a critical supply to a nearby military establishment. The
pressure observed at location 2 was very close to zero but did not fall below it, as a result of
the village being cut-off. The pressure stayed low for a prolonged period of time and the data
recording the initial impact of the burst was overwritten at all five locations. This event has not
been included as an example (Section 4.3) due to the fact that the period of logged data
containing the initiating event (burst of 16” main) was overwritten due to the volume of data
recorded during the period when the reservoir supply was isolated. Note that, although the
logger was triggered at location 5 when the village was isolated, pressures below 1.5 bars
were not recorded.
The very low pressure observed at location 5 occurred on 21st September when the actions
taken by the water company to repair a burst main resulted in the temporary isolation of the
small part of the network where the logger was located.
There was also another major burst on the 16” main on 23rd
June, which produced very low
pressures at location 2, but not at the other locations.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 23
There were other minor pressure excursions which were noted during the logging. These
were of no consequence with respect to low pressure. However they did demonstrate the way
in which rapid pressure transients decay across the network.
4.3 Example events
4.3.1 Mains burst on June 23rd 2010
As discussed above, there were two occasions when there was a severe event (a major
burst) on the 16” pumping main which caused a large pressure fluctuation at the pumping
station (location 1). The location of the burst on 23rd
June 2010 is marked “B” in Figure 4.4.
This fluctuation at the pumping station resulted in lesser fluctuations being observed at the
logger locations within the distribution system (locations 2, 3 4 and 5). The pressure variation
at each location is shown in Figure 4.3.
Figure 4.3 Burst event on 23rd
June 2010, Site A
Figure 4.3 shows a pressure range of 8 bars at the pumping station but the range is only 3
bars at the other locations. The pumping mains are long enough to allow the high and low
pressures to develop as a result of the surge event. However, interactions within the
distribution system, where pipe junctions are much closer together, modify the transient. This
mechanism is explained in Section 2.1.
A further example of this aspect is shown by the positive pressure spike initiated at the
booster station (location 2) after about 280 seconds, as shown in Figure 4.3. This is a very
rapid change which is alleviated as the event crosses the system until it is much reduced at
location 5, which is the logger most distant from the booster station.
0
2
4
6
8
10
12
0 100 200 300 400 500 600
Pre
ssu
re (
bar
s)
Time (seconds)
1 2 3 4 5
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 24
Although the large pressure swing at location 1 is not reproduced in the distribution network, it
should be noted that the pressure falls close to zero at location 2 (booster station) with some
small possibility of ingress occurring. Pressure remains below 0.1 bars for 56 seconds.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 25
Figure 4.4 Location of major burst on 23rd
June, Site A
96969696
9696969696
999999999999999999
105105105105105105105105105
909090909090909090
114114114114114114114114114
117
117
117
117
117
117
117
117
117
14
714
714
714
714
714
714
714
714
713
513
513
513
513
513
513
513
513
5
111111111111111111111111111
848484848484848484
138138138138138138138138138
120120120120120120120120120
10
810
810
810
810
810
810
810
810
810
210
210
210
210
210
210
210
210
2
13
213
213
213
213
213
213
213
213
2
126126126126126126126126126
144
144
144
144
144
144
144
144
144
141141141141141141141141141
878787878787878787
129129129129129129129129129
939393939393939393
123123123123123123123123123
153153153153153153153153153
81
81
81
8181
81
81
81
81
787878787878787878
52
34
Trunk mains
Water mains
3m contours
Hydrants
Meters
Logger locations
Pumps
1
2B
16"
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 26
4.3.2 Mains burst on September 21st 2010
In the early afternoon of 21st September 2010, there was a burst (caused by a ferrule blow-
out) on the 3” main at the position marked “B” on Figure 4.5 resulting in “water shooting into
the air”, as observed by local residents. This is the type of sudden, high-flow-rate burst event
that might be expected to produce low pressures. However, in reality the pressure did not fall
low enough to trigger the loggers. It is clear from the values of normal pressure and of the set
trigger pressures that any resulting pressure drop was less than 1 bar.
Figure 4.5 Area adjacent to ferrule blow out
The explanation lies with the pipe junctions between the burst site and the upstream loggers
at locations 3 and 4 (see Section 2.1). Each of these reflects the pressure change back
towards the burst site as a rise in pressure and reduces the transmitted drop away from the
burst site. As can be seen from Figure 4.2, there are a large number of junctions on the path
through the network.
It is possible that low pressures were generated immediately upstream of the burst but there
were no loggers located in that area. However, this is unlikely since there is a „T‟ junction very
close to where the burst occurred and others within 100 m.
Water company staff proceeded to close valves on each side of the burst to isolate this
section for repair. There are cross-connected twin mains (3” and 6”) in this area and so a
number of valves needed to be closed. Logger 5 position is marked on Figure 4.5 as “5”. The
effect of valve closures at this point is shown in Figure 4.6.
5
102102102102102102102102102
108108108108108108108108108
117117117117117117117117117
12
612
612
612
612
612
612
612
612
6
120120120120120120120120120
114114114114114114114114114
Water mains
3m contours
Valve
Hydrant
Logger location
B6"
3"
3"
6"
3"
3"
6"
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 27
Figure 4.6 Pressure at logger 5 following ferrule blow-out
When a valve on the 6” main upstream of the burst was closed, the area where logger 5 was
situated was supplied via the 3” main and a cross connect, with the 3” main also supplying
flow to the burst. This will induce a large headloss in the mains. This valve closure produced
the major fall in pressure seen at approximately 100 seconds, marked as „A‟ on Figure 4.6.
The pressure fell below zero and then recovered to a small positive value. Oscillations caused
by further valve closures caused the pressure at this point to dip below zero again after
300 seconds, marked „B‟. Logger 5 was located on a dead end at a ground level higher than
the valves that were closed. When the final valve was closed (550 seconds, marked „C‟),
pressure fell below zero for a third time and remained there until the main was recharged
following repair.
Although negative pressures occur at this point, it is important to remember that this was not
caused by the catastrophic burst but by the valve closures necessary to deal with the burst.
The point where the negative pressures were seen is some metres higher than the burst site
and therefore translates the zero pressure at the burst to a negative pressure. The burst itself
did not trigger any of the loggers and very low pressures were not measured at any logger
other than number 5.
4.3.3 Pressure events at the booster station
On September 29th
2010, a rapid drop in pressure was observed at the booster station
(location 2). The recorded pressure data from location 2 is shown in Figure 4.7. This was a
frequent event in the months that followed.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 28
Figure 4.7 Pressure at the booster station on September 29th
2010
This was probably caused by the pump control and not by a sudden demand change. It is
certainly not a cause for concern from an ingress point of view. What it does do is provide
more insight into the behaviour of surge pressures in a distribution system. If the total drop in
pressure seen at around 100 seconds in Figure 4.7 had been transferred to the other logging
locations, it is certain that recording would have been triggered. This has not happened at any
of the loggers on any of the days that the transient was seen at the booster station.
Reflections and interactions at pipe junctions have reduced the pressure change
considerably. The most rapid fall in Figure 4.7 is 1.1 bars in 0.1 seconds: a genuine pressure
transient.
4.3.4 Summary results
1. In the nine-month logging period, pressure below zero was recorded on only four
occasions. There was one other instance when pressure was observed to fall below
0.1 bars.
2. On only one of these occasions (26th July) was the pressure the direct result of high
flow (see Section 4.2). This was recorded at the source pumps (pumping station) rather
than in distribution. It is not known whether pressures at the other locations fell
immediately to very low values because these records (if any) would have been
overwritten by the subsequent valving event. The other low pressure events resulted
from valving operations.
3. The catastrophic burst on 23rd
June on the trunk mains led to large pressure transients
in those mains. These pressure drops were considerably modified in the distribution
0
0.5
1
1.5
2
2.5
3
3.5
4
0 50 100 150
Ba
r
Secs
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 29
system so that only at one location (logger 2) did the pressure fall close to a value
which might cause ingress.
4. A similar transient occurred in the trunk mains following the burst on 26th July.
However, data from the four loggers in distribution were not available to confirm the
immediate effect on the network.
5. A catastrophic burst (21 September) within the distribution system did not trigger
recording at any location (see Section 4.3.2).
6. Negative pressures were recorded on 21st September at one location because a
section of the network was isolated for repair.
7. Other evidence of pressure transients being alleviated within the system was found.
4.4 Discussion and conclusions
During 9 months logging at 5 locations, there were just 5 occasions when pressures fell to a
point where the possibility of ingress was increased. On one occasion this was caused as a
direct result of high flow. The other low pressures were caused in isolated mains by closing
valves. Some data were overwritten during one long timescale event
One incident, due to a sudden flow change causing low pressure, occurred just downstream
of the source pumps. There was a possibility of ingress occurring at this point. It is significant
that this point is on a long simple pumping main which allowed time for the pressure surge to
develop.
During this incident, pressure drops within the distribution system were very much less due to
the ameliorating effect of reflections from pipe junctions within this dense network. Other
evidence was found of rapid pressure transients being beneficially modified within the
network.
A catastrophic burst within the system did not trigger the pressure loggers. There are a large
number of pipe junctions between the site of the burst and the loggers. These would severely
reduce the potential pressure drop caused by the burst.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 30
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 31
5. Surge Site B
5.1 Choice of site and locations
Site B was not a typical surge site as the focus was not upon potential failure or issues arising
from a pumping station. Instead, discussions with the water company identified this site as
one in which a large commercial user draws large amounts of water several times a day by
rapidly opening a valve. This was considered to have the potential to cause pressure
problems elsewhere in the distribution system. Since the event of interest was, unlike other
surge sites, frequent and regular, it was agreed that an extended period of pressure logging
was not necessary. Instead, pressure loggers were installed for a period of 14 days to
observe any pressure impacts of the large flow to the commercial user. As with Site A, the
locations of the pressure loggers were selected to represent an increasing level of complexity
across the distribution system. As there was no pumping station related to this site, there was
no requirement to locate a logger at such a location. Therefore, four loggers were considered
sufficient to observe pressures at this site.
The site chosen for the pressure logging has one large commercial user. Several times on
each working day, the commercial demand is large compared with the rest of the site. Figure
5.1 shows the flow for the whole site (DMA, in green) superimposed on the flow excluding the
large user (red).
Figure 5.1 DMA and large customer flows
-2
0
2
4
6
8
10
12
14
16
18
20
17/08/2010 00:00 21/08/2010 00:00 25/08/2010 00:00 29/08/2010 00:00 02/09/2010 00:00
Flo
w (
l/s)
Date_Time
DMA DMA minus major user
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 32
This shows a diurnal pattern to the rest of the site which is similar on each day and a number
of very large short-term additional flows. This system was chosen for investigation because of
these “exceptional demands”.
The commercial flow can be as high as 13 l/s expressed as a 15-minute average and as low
as zero. This compares with an average flow to the rest of the site of 3.4 l/s. Therefore, the
commercial flow often imposes a load on the system greater than the combined demand of
other customers within the site.
Pressure was logged at four sites for a period of 14 days. The location of the loggers is shown
in Figure 5.2.
Figure 5.2 Location of the loggers within the network, Site B
Location 1 was chosen because it was the nearest hydrant to the offtake of the major user
(marked as “U” in Figure 5.2). The others were chosen such that the pipework between
offtake and loggers was of different complexity. Location 2 was separated from the offtake by
just one „T‟ junction and 100 m of pipe. Location 3 was at the distant end of a residential area.
12
5
13
0
130
1
2
80
120
115
110
105
100
95
95
100
105
110
120
12
5
125130
110
95
100
105
110
115 120
130
100
105
115
120
130
130
90
4
3
5m contours
Water mains
Hydrants
Logger locations
U
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 33
5.2 Logging results
Pressure loggers and kiosks were installed at the four locations on 17th August 2010. The
data were downloaded daily until the loggers were removed on 1st September 2010.
At each location the logger was set to record when the pressure fell below a “trigger
pressure”. These trigger pressures were set at an initial level and were altered over the first
few days to record an acceptable level of data and prevent real low pressure events being
overwritten. The trigger pressures and number of events logged at each site are given in
Table 5.1.
Table 5.1 Summary of low pressures in Site B
Location
(see
Figure
5.2)
Typical
Normal
Pressure
(bar)
Date Number
of
events
Trigger
level
(bar)
Notes
1 3.3
17/08/2010 0 2.1 Check
telecommunications link
18/08/2010 3 2.1
19/08/2010 0 2.1
20/08/2010 3 2.1
23/08/2010 13 2.1
24/08/2010 6 2.1
25/08/2010 2 2.1
26/08/2010 1 2.1 Trigger dropped to 1.9
bar – no events
subsequently triggered
2 3.2
17/08/2010 0 1.8 Check
telecommunications link
18/08/2010 0 1.8 Trigger raised to 2.0 bar
19/08/2010 5 2.0
20/08/2010 11 2.0
23/08/2010 32 2.0
24/08/2010 7 2.0
25/08/2010 6 2.0
26/08/2010 20 2.0 Trigger dropped to 1.8
bar
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 34
Location
(see
Figure
5.2)
Typical
Normal
Pressure
(bar)
Date Number
of
events
Trigger
level
(bar)
Notes
3 3.5
17/08/2010 0 2.4 Check
telecommunications link
18/08/2010 22 2.4 Trig dropped to 2.25 bar
19/08/2010 1 2.25
20/08/2010 3 2.25
23/08/2010 17 2.25
24/08/2010 2 2.25
25/08/2010 2 2.25
26/08/2010 2 2.25 Trig dropped to 2.0 bar –
no events subsequently
triggered
4 3.2
17/08/2010 0 1.9 Check
telecommunications link
18/08/2010 0 1.9 Trigger raised to 2.1 bar
19/08/2010 12 2.1 Trigger dropped to 2.0
bar
20/08/2010 8 2.0
23/08/2010 31 2.0
24/08/2010 9 2.0
25/08/2010 6 2.0
26/08/2010 18 2.0 Trigger dropped to 1.8
bar – no events
subsequently triggered
As can be seen from Table 5.1, the loggers at all four locations were triggered on numerous
occasions over the 14-day logging period. This provided details of the pressure changes in
the distribution system as a result of the exceptional demand of the large commercial user.
However, at no point was a sub-zero pressure recorded at any of the locations. The minimum
observed pressure was 1.691 bars (recorded at location 2).
The pipe pressure at which ingress would be possible depends on the depth of the pipe. It is
therefore unlikely to be greater than 0.1 bars (see Section 2.1). The minimum observed
pressure was far above a value at which ingress would be likely. This is in spite of the fact
that there were many, frequent changes in flow at this site.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 35
5.3 Mechanism of pressure surge in Site B
5.3.1 Potential pressure change
As an example of the flow variation to the commercial premises, consider the period between
10 am and 11 am on August 23rd
(Figure 5.3).
Figure 5.3 Flow to large user on August 23rd
2010
There is an increase of 5.77 l/s between two successive flow readings. However, this is
probably an underestimate of the change because 15-minute averages are used, and these
will smooth out any sudden changes in flow. This customer is supplied from a 5” cast-iron
main in such a location that the increased flow can reasonably be assumed to be supplied
equally from both directions. If the supply had been through a single main, the velocity change
would have been double and the pressure surge more severe.
The velocity change in each main is given by:
--------------------- A
where ΔV velocity change in m/s
ΔQ flow change in l/s
0
2
4
6
8
10
12
14
00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00
Flo
w (
l/s)
Time
Major User Events_Site 1 Events_Site 2 Events_Site 3 Events_Site 4
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 36
In this case:
ΔV = 0.235 m/s
The potential pressure change in a 5-inch cast-iron main is given by:
ΔP = 13 x ΔV ---------------------- B
where ΔP pressure change in bars
As the flow is increasing, the pressure upstream of the inlet valve to the major user will fall.
The drop, in this case, is potentially 3.06 bars. If this were to be realised, sub-atmospheric
pressures could be achieved at all four sites. Such drops do not occur because of the
complexity of the system (see Section 2.1).
5.3.2 Speed of pressure change
Because pressure was logged at 0.1-second intervals, it is possible to calculate accurate
short-term rates of change. The rate of change of pressure close to the large user in the
period from 10:00 to 11:00 (considered in Section 5.3) peaked at 0.67 bars per second.
Equation B can be used to calculate that this is caused by a velocity increase of 0.046 m/s in
one second. Equation A gives the increase in flow to the customer over one second as
1.11 l/s, a total change in average velocity of 0.045 m/s over 15 minutes (i.e. considerably
less than the changes that are possible).
If this rate of pressure change had persisted for six seconds or longer, then sub-atmospheric
pressure would have been produced. This does not occur because of reflections of the
pressure wave from pipe junctions which moderate the change. Large diameter pipe junctions
are some 100 m away from the customer off-take in each direction. Since the wavespeed in
these pipes is 1300 m/s the return waves will arrive back at the off-take about 0.15 seconds
after initiation. Well within the first second, the surge is beginning to be alleviated. Further
moderating effects come successively from more distant junctions and changes in diameter.
5.4 Example events
5.4.1 Demand Event on August 23rd 2010
Some of the features of pressure surge in this system are demonstrated by an event
observed on August 23rd
. Pressures at three of the locations are shown in Figure 5.4. The
event was not recorded at location 3. It is assumed that the lowest pressure at that site was
just above the trigger and was, therefore, insufficient to cause the logger to start recording.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 37
Figure 5.4 Surge event on August 23rd
There are a number of interesting features:
1. There is an underlying oscillation with a period of 40 seconds. Using pressure results
from a single day of constant logging from location 1, it is noted that this is observed
throughout the day. The period is remarkably constant and the oscillation is persistent.
This strongly suggests a variation which is imposed on the system from outside the
distribution network. As this oscillation does not seem capable of producing very low
pressures, this is not of any direct concern to this project.
2. The pressure drop at around 100 seconds in Figure 5.4 is almost 2 bars and would
certainly be noticed by customers. However, as with all of the events recorded in this
site, it is much less severe than would be predicted by the flow change (see Section
5.3).
3. The pressure variations from the different locations were very similar both in shape and
magnitude. They vary in absolute value because of ground-level differences and friction
losses between logger locations.
It might be assumed that, as the pressure wave travels away from the source of the event, the
magnitude would decrease due to interactions at junctions and fluid friction. Indeed, this is the
case in a simple main with widely spaced offtakes. However, in a distribution system, where
fittings, changes of material and changes in diameter are close together, the moderating
influences travel rapidly to all locations, including the one closest to the initiating event. Flow
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
0 50 100 150 200 250 300 350 400 450 500
Bars
Time (s)
1 2 4
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 38
changes need to be extremely rapid to produce pressure changes similar to the maximum
potential change (see Section 5.3.1).
4. There is a small difference in the timing of the corresponding peaks and troughs at the
different locations. For example, the timing of the low pressure on Figure 5.4 varies by
less than one second across the three locations which are similar to the travelling time
between locations. It is indicative of the rapid communication through the pipes
between locations.
5.4.2 Demand Event on August 18th 2010
Figure 5.5 shows pressures observed at two locations on August 18th. This includes location
3, which was absent from the previous example.
Figure 5.5 Surge event on August 18th
This shows the four features noted for the other event:
1. The underlying oscillation.
2. The significant drop at both loggers which is less than the surge potential.
3. The similarity of the oscillation at the two locations.
4. The small difference in timing between locations.
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
0 50 100 150 200 250 300 350 400 450 500
Bars
Time (s)
1 3
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 39
In addition:
5. The general pattern is (1) an oscillation about a high pressure, (2) a sharp drop, (3) an
oscillation about a lower value, (4) a sharp rise. This is consistent with an increase in
demand (at 100 seconds) which is fast enough to cause a pressure surge followed by
the sudden fall in demand (at 270 seconds) (i.e. the opening and closing of the valve).
6. The average pressures at the two locations in period (1) (oscillation about a high
pressure) are similar. In period (3) (oscillation about a lower pressure), location 3 has a
markedly higher pressure. This is consistent with the large user being the source of the
demand. The pressure drop en-route from DMA entry to location 1 has increased
because of the increased flow. Location 4 shares only a short stretch of this route and,
therefore, suffers only part of the enhanced pressure drop.
5.5 Summary results
1. The flow to one commercial user is large compared to the flow to the rest of the DMA.
2. These large flows occurred frequently on dozens of occasions during the logging
period.
3. Surge pressures developed at the inlet to the commercial user were transmitted to the
logging locations.
4. On no occasion was the pressure close to gauge zero. The minimum pressure
observed at any location was 1.7 bars.
5.6 Discussion and conclusion
The potential pressure drop caused by the exceptional demand can be calculated from the
flow change. In theory, the demand by this large user is frequently large enough to produce
sub-atmospheric pressures in the main. This does not happen. The reason is that, when the
pressure wave reaches a pipe junction, a reflection is returned to the initiation point which
reduces the pressure change. There are junctions with substantial mains within 100 m of the
inlet to the large user. Therefore, the flow change would have to occur in less than
0.2 seconds for the whole of the potential drop to be realised (see Section 2.1). If the flow
change is rapid enough, the potential pressure will be developed before the reflection arrives.
It can be seen from the pressures logged at the nearest point (location 1) that the flow change
is indeed rapid. However, it is not fast enough to reduce pressures to a value near to gauge
zero.
In this (typical) distribution system with cast iron mains, the flow change must be very rapid
(i.e. of the order of 0.1 seconds) to produce very low pressures.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 40
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 41
6. Surge Site C
6.1 Choice of site and locations
Site C was identified through discussions with water company representatives. This site
consists of a DMA which is fed from a pumping station where the pumps are switched daily to
reduce energy use. The length of the main between the pumping station and the DMA is
considered to be sufficient for surge conditions to develop.
One of the pressure loggers was installed at the pumping station, to observe any low
pressures that may originate here (Figure 6.1, location 1). The direction of flow from the
pumping station to the DMA is shown by the blue arrows.
Figure 6.1 Location of loggers in relation to pumping station, Site C
125125125125125125125125125
959595959595959595
105105105105105105105105105
100
100
100
100
100
100
100
100
100
10
010
010
010
010
010
010
010
010
0959595959595959595
909090909090909090
909090909090909090 808080
8080
808080
80
105
105
105
105
105
105
105
105
105
10
010
010
010
010
010
010
010
010
0
80
80
8080
8080
80
8080
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
85
85
8585
8585
85
8585
80808080
8080
808080
808080
8080
808080
80
105105105105105105105105105
105105105105105105105105105
959595959595959595
757575
7575
757575
75
959595959595959595
80808080
8080
808080
757575757575757575
90
90
9090
9090
90
9090
757575757575757575
707070707070707070
75
75
7575
7575
75
7575
959595959595959595
10
510
510
510
510
510
510
510
510
5
70
70
7070
7070
70
7070
110110110110110110110110110
115115115115115115115115115
105105105105105105105105105
959595959595959595
909090909090909090
858585858585858585
105105105105105105105105105
100
100
100
100
100
100
100
100
100
80808080
8080
808080
80
80
8080
8080
80
8080
959595959595959595
100100100100100100100100100
707070707070707070
100
100
100
100
100
100
100
100
100
75
75
7575
7575
75
7575
100100100100100100100100100
909090909090909090
11
011
011
011
011
011
011
011
011
0
100100100100100100100100100
757575
7575
757575
75
110
110
110
110
110
110
110
110
110
959595959595959595
105105105105105105105105105
10010010010010010010010010011
011
011
011
011
011
011
011
011
0
110110110110110110110110110
120120120120120120120120120
115115115115115115115115115
160160160160160160160160160105105105105105105105105105
11
511
511
511
511
511
511
511
511
5
110110110110110110110110110
12
512
512
512
512
512
512
512
512
5
100
100
100
100
100
100
100
100
100
120120120120120120120120120
125125125125125125125125125
135135135135135135135135135 1
45
145
145
145
145
145
145
145
145
909090
9090
909090
90
959595959595959595
10
010
010
010
010
010
010
010
010
0
95
95
9595
9595
95
9595
909090909090909090
105105105105105105105105105
125125125125125125125125125
130
130
130
130
130
130
130
130
130
145145145145145145145145145
140
140
140
140
140
140
140
140
140
14
514
514
514
514
514
514
514
514
5
140
140
140
140
140
140
140
140
140
135135135135135135135135135
135135135135135135135135135 115115115115115115115115115
120120120120120120120120120
140
140
140
140
140
140
140
140
140
125125125125125125125125125
13
013
013
013
013
013
013
013
013
0
11
511
511
511
511
511
511
511
511
5
135
135
135
135
135
135
135
135
135
115115115115115115115115115
105105105105105105105105105
105
105
105
105
105
105
105
105
105
110
110
110
110
110
110
110
110
110
10
010
010
010
010
010
010
010
010
0
115115115115115115115115115
4
5
3
2
5m contours
Water mains
Bulk Meters
Hydrants
Pumps
Logger locations
1
500mm
500mm
500mm
18"
150mm
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 42
The other four loggers were located in one of the DMAs fed from the pumping main (Figure
6.2, locations 2 to 5). As with the other surge sites, the locations of these loggers were
chosen to reflect an increasing level of complexity in the system.
There are two junctions part-way along the trunk main which would be expected to modify the
pressure event as it travels towards the distribution system.
Figure 6.2 Location of loggers within the DMA, Site C
6.2 Logging Results
Pressure loggers and kiosks were installed in the network (locations 2 to 5) on 16th November
2010 and at the pumping station a day later, on 17th November 2010. The loggers were
removed on 8th April 2011.
Table 6.1 gives a summary of the low pressures recorded in Site C.
12
012
012
012
012
012
012
012
012
0
110110110110110110110110110
115
115
115
115
115
115
115
115
115
130130130130130130130130130
125
125
125
125
125
125
125
125
125
120
120
120
120
120
120
120
120
120
130
130
130
130
130
130
130
130
130
10
510
510
510
510
510
510
510
510
5
145145145145145145145145145
13
513
513
513
513
513
513
513
513
5
12
512
512
512
512
512
512
512
512
5
5
4
3
2
5m contours
Water mains
Bulk Meters
Hydrants
Pumps
Logger locations
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 43
Table 6.1 Summary of low pressures in Site C
Location Trigger
(bar)
Pressures
< 1 bar
Pressures
< 0.1 bar
Minimum
pressure
(bars)
Date of
< 0.1 bar
event
1 1.0 43 0 0.146 5th Feb
2 3.5 0 0 3.132 -
3 1.5 0 0 1.301 -
4 1.5 1 0 0.552 29th Mar
5 1.1 7 0 0.846 5th Dec
In the five-month logging period, the pressure never dropped below 0.1 bars. Indeed, at the
locations within distribution, there were only eight occasions when the pressure dropped
below 1 bar. Seven of these were at the same location.
6.3 Example events
6.3.1 Pump switching event on 8th February 2011
A pump switching event was recorded a number of times during the logging period. It is
probable that this is a frequent event which only triggers the loggers on some occasions
depending on the flow and pressure conditions in the network at the time. However, the ones
that were recorded are all essentially the same.
The pressure results, shown in Figure 6.3, are for one typical example of this pump switching
event.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 44
Figure 6.3 Surge event on 8th
February 2011
The trace for location 1 (the pumping station) shows a dramatic drop in pressure of some nine
bars. This is transmitted along the cast iron pumping main and is reflected from the
distribution networks. Subsequent reflections from the pumping station and network produce
the decayed oscillation which is typical of simple mains. A number of DMAs are supplied by
this station. They are fed from the main at a range of distances from the station. Taking 5 km
as typical and noting that the ferrous main has a wavespeed of around 1100 m/sec, the pipe
period is between nine and ten seconds (See Section 2.1). This is the time taken for the
reflection to return to the station. The time taken for the pressure at the pumps to fall to the
trough is about eight seconds (Figure 6.3). The pipe period is sufficient for the considerable
surge to develop.
If this low pressure had been transmitted to the distribution network, severe negative
pressures would have been developed because of the difference in ground levels. However,
reflections from the large number of pipe junctions modify the pressure change and at no
logging point does the pressure fall below one bar. The pipe lengths are of the order of 10
metres rather than kilometres. The timescales are of the order of 0.01 seconds leaving little
time for surge pressures to develop. Figure 6.3 shows a clear delay in the drop between
location 1 and the others but none between locations 2 to 5. The shape of these four pressure
traces is remarkably similar because of their close proximity to each other (see Section 5.3 for
a discussion of the impact of distribution system features on surge pressures).
0
2
4
6
8
10
12
0 100 200 300 400 500 600
Pre
ssu
re (
bar
s)
Time (seconds)
1 2 3 4 5
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 45
The initiating event would have to be completed in the order of 1/100 of a second for the full
effect to be seen at the loggers in the distribution system.
6.3.2 Hydrant testing on 29th March 2011
The Fire Brigade carried out hydrant flow tests in this area. This was apparent because they
temporarily disconnected the pressure logger at location 2. During the 20 minutes that the
logger was disconnected, the Brigade carried out two tests at location 2 which triggered the
logger at location 4. The pressure trace which resulted from the second hydrant flow event is
shown in Figure 6.4.
Figure 6.4 Effect of hydrant flushing at location 4 on 29th
March 2011
The figure shows (at 100 seconds) the pressure drop as a result of opening the hydrant
followed by a minor oscillation as the event is reflected within the system. At 170 seconds, the
pressure rise resulting from closing the hydrant is seen. This is followed by a more dramatic
oscillation. In fact, the minimum pressure is lower than that for the opening transient.
No other logger was triggered by this event. It is clear that the major part of the valve closure
took place in 1 second. In spite of this rapid closure, there was no risk of ingress as a result of
the hydrant testing.
0
1
2
3
4
5
0 100 200 300 400 500 600
Pre
ss
ure
(b
ars
)
Time (seconds)
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 46
There had also been hydrant testing in this area on 17th and 18
th March. However, none of the
loggers were triggered by this exercise.
6.4 Summary results
1. In the five-month logging period at five locations, the pressure never dropped below 0.1
bars.
2. Significant drops in pressure were observed frequently at the pumping station. These
were the result of pump-switching, which is undertaken in order to reduce power usage
during winter (see Section 6.3.1).
3. These pressure drops were considerably modified in the distribution system such that
pressures of less than 1 bar were only observed eight times, and all but one of these
were at a single location. These pressures never fell low enough to result in any risk of
ingress.
4. Hydrant tests in the area caused a low pressure to be registered on one occasion
(March 29th) at one of the logging locations (see Section 6.3.2). There was no risk of
ingress.
6.5 Discussion and conclusions
During five month‟s logging, pressure never fell below 0.1 bars.
One type of event caused pressures to fall below one bar at the pumping station and at one of
the distribution sites. This was a routine pump switching operation which caused a pressure
drop at the station of about nine bars. The pumping main is long enough to allow this pressure
surge to develop. If this had been transmitted to the distribution system, severe sub-
atmospheric pressures would have resulted. Reflections within the system prevented this. It is
the relationship between pump switching time and density of the distribution system that
determines the impact of the pressure surge on the distribution pressures. If the pump stop is
rapid compared with surge transit times in the system, a large impact is to be expected.
In some systems it will be advisable to implement pump controls such that pumps stop more
slowly (a “soft stop”).
Hydrant testing was carried out on several days and caused a low pressure at one location on
one occasion. This pressure was not low enough to cause ingress. The lowest pressure was
caused by closing the valve very quickly. Rapid opening and closing should be avoided.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 47
7. Exceptional Demand Site D
7.1 Choice of site and locations
The water company provided a number of potential sites where their pressure models had
identified areas which were expected to be at risk of lower pressures. WRc discussed these
sites with the water company and selected Site D as an area which could potentially
experience very low pressures driven by exceptional demands.
Site D is composed of four DMAs fed through a booster station to the east of the area and
also from the north (see Figure 7.1). The booster station and northern feed are located at
lower altitudes than much of the site. The highest areas are to be found to the south, west and
north of the site, with a more isolated hill in the vicinity of locations 10, 11, 11A and 12.
Location 11, for example, is some 50 m higher than the booster station. Pressure loggers
were placed at sixteen locations throughout these DMAs. These locations were selected to
provide a good spatial representation of pressure changes in the DMAs, with particular
attention paid to the areas where it was decided that very low or negative pressures were
most likely to occur.
One location (location 11) was abandoned during the logging period when the hydrant began
to leak when the valve was opened. An alternative location was identified (location 11A), and
a logger was installed at this location the following month.
7.2 Logging results
Fourteen pressure loggers were installed on 23rd
/24th February 2010, with a further two
installed during the first download on 12th/13
th April. Location 11A was identified as an
alternative to location 11, and a pressure logger was installed at the new location during the
scheduled data download on 25th/26
th August 2010. All the loggers were removed on 14
th
February 2011, although a number of loggers stopped working due to frost damage, caused
by the extreme cold during December 2010.
Table 7.1 provides a summary of the low pressure events recorded at all sixteen locations.
The loggers were in situ for almost one year at these locations. Table 7.1 shows that during
that period pressure fell below one bar gauge on only 11 occasions. These were only
observed at six of the sixteen locations (11A is a replacement location close to 11, which it
replaced). At three of these locations only one such low pressure event was observed, where
the pressure was low but positive. For each of these events the minimum recorded pressure
was above 0.1 bar (0.21, 0.26 and 0.20 bar) and, ingress is very unlikely. The pipe would
have to be some 2 or 3 m below water for ingress to occur.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 48
Figure 7.1 Location of loggers at Site D
6
1
25
4
3
10
11A
11
12
16
1514
13
9
8
7
225
235
250
260
265
19
0
18
5
180
175
195
200
210
220
205
215
230
240
255
270
275170
245
28
0
285
DMA 1
DMA 2
DMA 3
DMA 4
Other mains
5m contours
Hydrants
Bulk meters
Pumps
Logger locations
Booster
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 49
As can be seen from Table 7.1, pressure fell to zero on one occasion at location 6. This was
due to a brief isolated incident symptomatic of local valve closure to isolate the main in the
vicinity of the logger (i.e. a rapid fall to zero or near zero at one logger, with no measurable
effect or minor effect at other loggers). All the negative pressures (three in total, two events)
were recorded at locations 4 and 11/11A. On the 6th/7
th January 2011 a system-wide event
(failure at the works) caused negative pressures at these points (see Section 7.3.2). Loggers
4 and 11/11A were situated at the highest points in the site, and it is unsurprising that they are
the most vulnerable (see Section 3.3). The third instance of negative pressure (recorded at
location 11 on 28th May) was again symptomatic of local valve closure.
Table 7.1 Summary of low pressures in Site D
Location No of events
< 1 bar
No of events
< 0.1 bar
Min Observed Pressure
Pressure
(bars) Date
Duration
below
0.1 bar
1 0 0 2.09 - -
2 1 0 0.21 - -
3 1 0 0.26 - -
4 3 1 -0.30 6th Jan 58 mins
5 0 0 1.92 - -
6 1 1 0.00 22nd
Oct 4 mins
7 0 0 1.49 - -
8 1 0 0.20 - -
9 0 0 2.07 - -
10 0 0 1.25 - -
11 3 1 -0.05 28th May 3 mins
11A 1 1† -0.72 6
th Jan 1 hr 5 min
12 0 0 1.68 - -
13 0 0 1.44 - -
14 0 0 2.28 - -
15 0 0 1.22 - -
16 0 0 1.93 - -
†Pressure fell below zero twice during this one event.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 50
7.3 Example events
7.3.1 Pump failure event on 29th November 2010
On 29th November, a pressure drop was recorded throughout Site D. The effect was most
marked in DMA 1, and the results for this DMA are shown in Figure 7.2.
Figure 7.2 Pressure trace on 29th
November 2010 in DMA1, Site D
The behaviour of the pressure at each of these locations is essentially the same and that is
consistent with a pump failure at the treatment works (i.e. a pressure change imposed on the
whole system). Each logger records a large pressure transient (a drop of between 2 and
3 bars) followed by a new steady state (approximately 1 bar below normal pumping pressure).
This new pressure is maintained until the problem is resolved about 17 minutes later,
probably as a result of the pump being restored. The lowest pressure (1.1 bars) is recorded at
location 11 (the highest logger in the DMA).
It must be remembered that logging in this case was at 10-second intervals. This time
discrimination is usually inadequate to capture the detail of surge events in distribution (see
Section 2.2). It is possible that there was a brief pressure excursion lower than those logged.
The large surge drop is transferred to DMA 2 but is rather less at location 1 which is the most
remote from the works and where pressures are enhanced by a local booster pump (see
Figure 7.3). The lowest pressure (0.70 bars) is at location 4 (the highest logger in this DMA
0
1
2
3
4
5
6
7
14:45:00 15:00:00 15:15:00 15:30:00 15:45:00 16:00:00 16:15:00 16:30:00 16:45:00
Bars
Date_Time
10 11 12 13 14 15 16
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 51
without a local booster pump). The phenomenon is recorded in DMAs 3 and 4 but is much
reduced because these loggers are hydraulically more remote from the initiating event
(multiple pipe junctions cause reflections which ameliorate the surge).
The temporary steady pressure is significantly lower than normal in DMA 2 except at logger 1
where pressure is maintained by a local booster pump (marked „BP‟ on Figure 7.3). There is
very little impact on steady state pressure in DMA 3 (because supply is solely through the
booster to the east of the DMA) or in DMA 4 (because pressure is controlled by a Pressure
Reducing Valve (PRV)). It is worth noting that a significant surge pressure is recorded in both
of these DMAs (see previous paragraph). The PRV and booster do not react quickly enough
to entirely suppress the surge.
Figure 7.3 Location of local booster pumps for location 1, Site D
7.3.2 Power failure event on 6th and 7th January 2011
On the night of 6th January 2011, the major water treatment works that supplies Site D
experienced a power failure with a subsequent failure of all pumps. This produced pressure
drops across all four monitored DMAs, with the absolute drop in pressure being similar across
the locations. This drop was large enough to produce low pressures at some locations and
negative pressures at locations 4 (DMA 2) and 11A (DMA 1) (see Figure 7.4 and Figure 7.5).
5
6
2
1
4
10
7
3
225
235
240
250
255
260
265
19
0
18
5200195
245
270
275
280
175
18
0
DMA 1
DMA 2
DMA 3
DMA 4
Other mains
5m contours
Hydrants
Bulk meters
Pumps
Logger locations
BP
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 52
Figure 7.4 Pressure trace on 6th
January 2011 in DMA 1, Site D
Figure 7.5 Pressure trace on 6th
January 2011 in DMA 2, Site D
-2
-1
0
1
2
3
4
5
6
7
22:00:00 22:30:00 23:00:00 23:30:00 00:00:00 00:30:00 01:00:00 01:30:00
Bars
Time
10 11A 12 13 14 15 16
-1
0
1
2
3
4
5
6
22:00:00 22:30:00 23:00:00 23:30:00 00:00:00 00:30:00 01:00:00 01:30:00
Bars
Time
01 04
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 53
Figure 7.4 shows that the pressure drops in DMA 1 at locations 10, 11A, 12 and 15. The
loggers at locations 13 and 16 were damaged at this time, as a result of freezing during the
cold weather in December 2010 and January 2011. Therefore, there are no data for these
locations. The logger at location 14 does not record the drop in pressure, the only working
logger across all four DMAs not to do so. There is no clear reason why this location should
behave differently. The four locations exhibiting a drop in pressure in DMA 1 all show a similar
pattern and magnitude to the drop and subsequent recovery. Pressures are already lower at
location 11A than at other locations, due to this location being at a higher ground level than
the others (see Figure 7.6). This results in a negative pressure being recorded at this location.
The network at this location is subject to negative pressure for roughly one hour, before
pressures recover briefly. A second pressure drop results in negative pressures for about
30 minutes. Negative pressures are also recorded for the first pressure drop at location 4 in
DMA 2 (Figure 7.5), for a period of roughly one hour. Location 1 shows a lesser effect on
pressures, which is likely due to a separate booster pump serving this location that dampens
the pressure drop (see Figure 7.3).
Figure 7.6 Location of loggers in DMA 1, Site D
A summary of the minimum pressures witnessed at each location during this event is shown
in Table 7.2.
16
11
10
11A9
1213
15
14
19
0
18
5
180
195
20
0
210
220
205
215
225
235
230
DMA 1
DMA 2
DMA 3
DMA 4
Other mains
5m contours
Hydrants
Bulk meters
Pumps
Logger locations
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 54
Table 7.2 Minimum pressures recorded at each location during low pressure event
on 6th
January 2011, Site D
Location Minimum pressure (bars)
1 3.388
3 0.255
4 -0.297
6 2.912
8 0.198
10 1.247
11A -0.718
12 1.682
14 3.687
15 1.221
2 No data
5 No data
7 No data
9 No data
13 No data
16 No data
Although the cause of this low pressure event was identified by the contributing water
company as a power failure at a water treatment works, rather than an exceptional demand
event, it is clear that ingress could have occurred at locations 4 and 11A, where pressures
were negative for at least an hour.
7.4 Summary results
1. 16 loggers were deployed for one year.
2. On only 11 occasions did any pressure fall below 1 bar.
3. On only four occasions did pressure fall below 0.1 bars (negative on three occasions).
4. One failure at the works on January 6th caused negative pressures at two high points
(see Section 7.3.2).
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 55
5. There were two occasions (October 22nd
and May 28th) where zero or negative
pressure results were symptomatic of mains isolation by local valve closure to isolate
the main in the vicinity of the logger.
6. A PRV and local booster pump each provide some protection against low steady state
pressures in their vicinity.
7.5 Discussion and conclusion
There were only three occasions when pressure fell to or below zero. It is believed that none
of these were due to exceptional demand events. The system is robust in that it has large
diameter mains which provide alternative supply routes to many areas. Those lower-lying
areas where a large flow would be possible are linked to the higher ground by large diameter
mains. Even a large outflow would have a modest effect on headloss in these large mains and
hence is unlikely to lower pressures to very low values.
Some additional protection against low pressures is provided at some locations by PRVs and
local booster pumps.
Although no negative or very low pressures were observed as the result of exceptional
demand events (e.g. bursts) in this site, a failure at the treatment works did produce negative
pressures at two locations for over an hour.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 56
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 57
8. Exceptional Demand Site E
8.1 Choice of site and locations
Discussions with the water company identified areas which had characteristics that might
result in low pressures occurring. Some of the areas at risk were considered too small to be
worth investigating, as the low-lying areas where any exceptional demand event leading to
low pressures at the higher areas would have to occur were relatively small. This reduces the
probability of any events being observed during the study period. WRc discussed all the
potential sites with the water company and selected Site E as an area worth investigating
because it had the desirable variation in ground level.
Site E is composed of five DMAs fed from the same supply. Pressure loggers were placed at
sixteen locations throughout these DMAs (Figure 8.1). These locations were selected to
provide a good spatial representation of pressure changes in the DMAs, with particular
attention paid to the highest areas within the site, where it was decided that very low or
negative pressures were most likely to occur. The blue arrows in Figure 8.1 indicate the
direction of flow through the trunk mains that feed the site.
One location (location 8) was abandoned during the logging period when the hydrant began to
leak when the valve was opened. An alternative location was identified (location 8A), and a
logger was installed at this location the following month.
8.2 Logging results
Fifteen pressure loggers were installed on 15th/16
th March 2010, with one more logger
installed during the first download on 22nd
/23rd
May 2010. Location 8A was identified as an
alternative to location 8, and a pressure logger was installed at the new location during the
scheduled data download on 23rd
/24th August 2010. All the loggers were removed on 21
st
February 2011, although a number of loggers had stopped working during December 2010,
due to frost damage arising from the extreme cold weather.
Table 8.1 provides a summary of the low pressure events recorded at the sixteen locations.
Loggers were in situ for approximately 11 months. Table 8.1 shows that pressures below one
bar were recorded on just 17 occasions. Pressures below 0.1 bars were rarer – ten events
observed at seven locations. Nine of these events were symptomatic of local valve closure to
isolate the main to which the logger was connected (i.e. a rapid fall to zero or near zero at one
logger with no measureable effect or minor effect at other local loggers). Just one low
pressure event is believed to be the result of an exceptional demand event. In this case, the
water was taken from a hydrant with a pressure logger which would need to be removed for
the purpose. The zero value is therefore not good data. The impact on other local loggers was
minor.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 58
Figure 8.1 Location of loggers at Site E
1
163
13
1412
7
9
8
8A
6
1011
2
4
5
15
162
165144
168
147
138
11
1
105
141
132
120
135
150
108
114
12
6
123
171 174
177
15
3
117
159
129
99 102
96
DMA 1
DMA 2
DMA 3
DMA 4
DMA 5
All other mains
Trunk mains
3m contours
Hydrants
Meters
Logger locations
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 59
Table 8.1 Summary of low pressures in Site E
Location No of events
< 1 bar
No of events
< 0.1 bar
Min Observed Pressure
Pressure
(bars) Date
Duration
below
0.1 bar
1 2 1 -0.05 26th Apr 4 hrs
1
2 0 0 1.71 - -
3 3 1 -0.40 15th Sept 8 min
4 1 1 0.00 24th Aug 7 min
5 0 0 2.76 - -
6 1 1 0.05 14th Sept 3 min
7 1 1 0.00 4th Oct 25 min
8 0 0 2.90 - -
8A 0 0 2.89 - -
9 1 0 0.46 - -
10 0 0 4.02 - -
11 0 0 1.12 - -
12 0 0 1.37 - -
13 0 0 2.64 - -
14 5 4
-0.26 4th May 12 min
0.00 5th May 1 hr 8 min
2
0.00 24th Nov 18 min
0.00 25th Nov 12 min
15 2 0 0.32 - -
16 1 1 0.00 2nd
Feb 11 12 min
1. Pressure went negative for a few seconds. Pressure recorded at zero for the remainder of the event.
2. Pressure went to zero for a few minutes.
8.3 Example events
8.3.1 Event on 19th July 2010
The pressure was seen to fall on a number of the loggers at Site E just after 04:40 am on 19th
July 2010. The pressure remains at this lower level for about 1 hour and 21 minutes before
recovering to normal levels.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 60
The magnitude of the impact of this demand event on pressures varies across the three
affected DMAs. The greatest impact is observed at location 16, in DMA 3, where the pressure
drops by 3.48 bars (Figure 8.2). However, this location exhibits a higher starting pressure, so
the large drop can be accommodated without any significant probability of sub-atmospheric
pressure. All three loggers in this DMA (DMA 3) show a significant pressure drop, suggesting
the causal demand event is likely to have been in this DMA. A burst in the vicinity of location
16 would increase the pressure drop in the smaller diameter mains feeding that location. The
routes from source to locations 1 and 3 have some small diameter mains in common with the
route to 16. There was a major effect at these points but less than that at 16.
The lowest pressure observed during this event was at location 1, where the minimum was
0.788 bars, following a drop of 3.04 bars from the starting pressure. Although the minimum
pressure is not very low or negative, it is noted that there are points at higher altitudes within
this DMA that might be expected to exhibit lower pressures than the minimum observed. The
hydrants at the higher locations are located within a busy main road, and the installation of
loggers at these hydrants would have caused significant planning and traffic disruption on a
monthly basis. Therefore, no loggers were located here. As the difference in the altitude
between location 1 and the highest point in the DMA is about 7.5 m, it is possible that very low
pressures were observed at and around the highest point, but only over a very small area.
Figure 8.2 Pressure trace on 19th
July 2010 in DMA 3, Site E
The loggers located in DMAs 1 and 5 were unaffected by this event. Both of these DMAs are
fed from large diameter mains. The flow in these mains would have been affected by the
suspected burst, but the resultant pressure drop would have been small. There was some
impact on loggers in DMA 4 (Figure 8.3) because of shared pipework. This DMA is fed from
0
1
2
3
4
5
6
7
04:00:00 04:30:00 05:00:00 05:30:00 06:00:00 06:30:00 07:00:00
Bars
Time
01 03 16
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 61
two large mains, originating from the same source. The lack of any impact at location 5 is
because this location is fed by a large diameter main which is not impacted by flows in DMA 3
(where the burst occurred).
Figure 8.3 Pressure trace on 19th
July 2010 in DMA 4, Site E
The impact of the demand event varies across DMA 2, with only a small impact observed at
two of the locations (13 and 14), whilst location 12 observed a large pressure drop, although
still remaining above one bar (Figure 8.4). This is also a multi-feed DMA with the flow to the
three logging locations being via different district meters. The flow route to location 12 shares
more common pipework with DMA 3 than 13 or 14.
0
1
2
3
4
5
6
04:00:00 04:30:00 05:00:00 05:30:00 06:00:00 06:30:00 07:00:00
Bars
Time
05 06 07 08 09 10
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 62
Figure 8.4 Pressure trace on 19th
July 2010 in DMA 2, Site E
8.3.2 Hydrant flushing event on 24th August 2010
For some 7 minutes just after 8 o‟clock in the morning, water was drawn from a hydrant in the
study area. It is almost certain that this involved disconnecting and then reconnecting the
logger at location 4. This resulted in the string of zero values seen in Figure 8.5. (It is not
possible for these to be genuine pressure values when the coincident results at the nearby
logger 2 are around 3.5 bars.) Loggers 2 and 11 are in the same DMA (See Figure 8.6). The
increased friction head induced by the imposed high flow is modest (2 to 5 m) and is of no
consequence at these points where the normal pressure is in the 3 to 4 bar range.
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
04:00:00 04:30:00 05:00:00 05:30:00 06:00:00 06:30:00 07:00:00
Bars
Time
12 13 14
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 63
Figure 8.5 Pressure trace on 24th
August 2010 in DMA 5, Site E
Figure 8.6 Location of loggers in DMA 5, Site E
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
07:00:00 07:15:00 07:30:00 07:45:00 08:00:00 08:15:00 08:30:00 08:45:00
Ba
rs
Date_Time
02 04 11
4
2
6
11
5
123
126
120
114
111
105
108
DMA 1DMA 2DMA 3DMA 4DMA 5All other mains
Trunk mains
3m contours
Hydrants
Meters
Logger locations
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 64
DMA 5 is fed from DMA 4 and so the hydrant flow affects the pressures in this latter DMA
(Figure 8.7). The effect is barely detectable because of the large diameter mains crossing
DMA 4. The effect is not detectable at location 5 which is fed from the largest (10”) main. The
other DMAs are not affected because they are fed directly from a large diameter main.
Figure 8.7 Pressure trace on 24th
August in DMA 4 in Site E
8.3.3 Burst event on 19th September 2010
A significant mains burst occurred on a short length of 8” main which itself is fed from a 10”
main. The 10” main feeds DMAs 2, 3 and 4. However, the impact on pressures in these DMAs
was minor. The results for the loggers in DMA 3 are shown in Figure 8.8. A small fall was
registered at each location and remained until the burst was repaired. A similar result was
observed by the loggers in DMAs 2 and 4.
The pressure drop is the result of increased headloss in the 10” main from supply source to
the burst. Even a large burst has only a small effect on a main of this size.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 65
Figure 8.8 Pressure trace on 19th
September 2010 in DMA 3 in Site E
8.4 Summary results
1. Sixteen loggers were deployed for eleven months.
2. Pressure fell below one bar on seventeen occasions.
3. Seven locations observed pressures below 0.1 bars. These values were recorded on
ten occasions. Three of these were negative pressures. The effect at other locations
was usually negligible and sometimes minor.
4. Nine low pressure events were probably due to local valve closure; the remaining low
pressure event (see Figure 8.5) was in all probability a spurious result where the logger
was removed from the hydrant.
5. A possible burst on July 19th had a major impact locally without pressures falling to very
low values (see Section 8.3.1). Impact on other DMAs was small because of the large
diameter spine mains which feed the DMAs.
6. Flow from a hydrant on August 24th had a small effect on logged pressures (see
Section 8.3.2).
0
1
2
3
4
5
6
7
21:00:00 22:00:00 23:00:00 00:00:00 01:00:00 02:00:00 03:00:00 04:00:00
Ba
rs
Date_Time
01 03 16
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 66
7. A burst which was reported as “large” had a very small effect on logged pressures
because it was close to a large diameter main which feeds 3 of the 5 DMAs (see
Section 8.3.3).
8.5 Discussion and conclusion
Sixteen loggers were installed for eleven months. Although ten very low pressures were
recorded in that time, none were caused by large flow events. Most were probably caused by
the valving off of sections of main containing the pressure loggers.
Three high flow events were examined. A reported burst registered on several loggers but the
pressure change was very small. An event which was probably a burst had a marked effect
on local pressures but not, by any means, enough to cause a low pressure problem at any
logger site. It is possible that a small area at higher ground level suffered very low pressure.
Flow from a hydrant had a minor effect at local loggers. In this system, relatively large
diameter mains can supply an exceptional demand with only a small increase in headloss
and, therefore, a small fall in pressure at downstream locations. In particular, the DMAs in this
group are supplied by large mains from the source, so a demand on one DMA has little
impact in some of the others.
A burst is a major demand event and is relatively common in older cast iron systems. This
monitoring has shown that this type of event appears to have very limited impact on the
pressures in this site. Pressure does not fall to very low values and pressure falls do not
extend across the whole system.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 67
9. Exceptional Demand Site F
9.1 Choice of site and locations
Discussions with the water company identified areas which had characteristics that might
result in low pressures occurring. WRc discussed these sites with the water company and
selected Site F. This is an area in which pressure problems were known to have previously
occurred, and where the main feeding the site is lower-lying than the site.
Site F is composed of two DMAs fed from the same supply. Pressure loggers were placed at
sixteen locations throughout these DMAs (Figure 9.1). These locations were selected to
provide a good spatial representation of pressure changes in the DMAs, with particular
attention paid to the high areas where it was decided that very low or negative pressures were
most likely to occur. The blue arrows in Figure 9.1 indicate the main direction of flow.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 68
Figure 9.1 Location of loggers at Site F
757575757575757575
656565656565656565
65
65
6565
6565
65
6565
60
60
60 60
60 60
60
6060
606060606060606060
55555555
5555
555555
606060606060606060
606060606060606060
55555555
5555555555
606060606060606060
55555555
5555555555
606060606060606060
2
5
3
8
97
14
4
15
613
12
10A10
1611
1
595959595959595959
626262626262626262
626262626262626262
636363636363636363
656565656565656565
585858585858585858
484848484848484848
565656565656565656 686868686868686868666666666666666666
838383838383838383
868686868686868686
777777777777777777
575757575757575757
646464646464646464595959595959595959
717171717171717171
848484848484848484
646464646464646464
585858585858585858
545454545454545454
606060606060606060
50.950.950.950.950.950.950.950.950.9
57.957.957.957.957.957.957.957.957.9
54.354.354.354.354.354.354.354.354.3
494949494949494949
31.331.331.331.331.331.331.331.331.3
46.946.946.946.946.946.946.946.946.9
37.837.837.837.837.837.837.837.837.8
49.749.749.749.749.749.749.749.749.7
48.248.248.248.248.248.248.248.248.2
38.438.438.438.438.438.438.438.438.4
41.841.841.841.841.841.841.841.841.8
646464646464646464
424242424242424242
535353535353535353
424242424242424242
575757575757575757
515151515151515151
525252525252525252
414141414141414141
787878787878787878
565656565656565656
595959595959595959
565656565656565656
858585858585858585
565656565656565656
686868686868686868
707070707070707070
595959595959595959
59.759.759.759.759.759.759.759.759.7
82.382.382.382.382.382.382.382.382.369.869.869.869.869.869.869.869.869.8
67.767.767.767.767.767.767.767.767.7
646464646464646464
69.269.269.269.269.269.269.269.269.2
72.172.172.172.172.172.172.172.172.1
68.368.368.368.368.368.368.368.368.3
515151515151515151
656565656565656565
474747474747474747
41.841.841.841.841.841.841.841.841.8
49.449.449.449.449.449.449.449.449.4
60.760.760.760.760.760.760.760.760.7
616161616161616161
46.346.346.346.346.346.346.346.346.3
51.551.551.551.551.551.551.551.551.5
51.251.251.251.251.251.251.251.251.2
606060606060606060
707070707070707070
75757575
7575
757575
656565656565656565
656565656565656565
80
80
8080
8080
80
8080
555555555555555555
606060606060606060
656565656565656565
606060606060606060
65656565
6565656565
606060606060606060
656565656565656565
505050505050505050
555555555555555555
55555555
5555
555555 50
50
5050
5050
50
5050
50505050
5050505050
505050505050505050
45
45
45 45
45 45
45
4545
505050505050505050
555555555555555555
606060606060606060
454545454545454545
404040404040404040
45454545
4545
454545
404040404040404040
404040404040404040
454545454545454545
505050
5050
505050
50
555555555555555555
606060606060606060
808080808080808080
35353535
3535
353535
404040404040404040454545454545454545
555555
5555
555555
55
555555555555555555
50505050
5050
505050
70
70
70 70
70 70
70
7070
454545454545454545
505050505050505050 555555555555555555
656565656565656565
555555555555555555
55
55
55 55
55 55
55
5555
606060606060606060
454545454545454545
505050505050505050555555555555555555
555555555555555555
707070707070707070
808080808080808080
757575757575757575
707070707070707070
707070707070707070
707070707070707070
606060606060606060
808080808080808080
757575757575757575
656565656565656565
555555555555555555
505050505050505050
505050505050505050
454545454545454545
454545454545454545
353535353535353535
35353535
3535
353535
353535353535353535
454545454545454545
505050505050505050
50
50
5050
5050
50
5050
505050505050505050
40404040
4040404040
454545454545454545
454545454545454545
454545
4545
454545
45
45454545
4545
454545
50
50
5050
5050
50
5050
50
50
50 50
50 50
50
5050
65656565656565656545454545
4545
454545
50505050
5050
505050
656565656565656565
454545454545454545
454545454545454545
50505050
5050
505050
45
45
4545
4545
45
4545
454545
4545
454545
45
40404040
4040
404040
40404040
4040404040
555555555555555555
656565656565656565
656565
6565
656565
65
65
65
65 65
65 65
65
6565555555
555555555555
555555555555555555
55555555
5555
555555
50505050
5050505050
60606060
6060
606060
65656565
6565
656565
606060606060606060
606060
6060
606060
60
555555555555555555
50505050
5050
505050 505050
505050505050
555555555555555555
55555555
5555
555555
606060
6060
606060
60
656565
6565
656565
65
707070
7070
707070
70
757575
7575
757575
75
707070707070707070
606060
6060
606060
60
70707070
7070
707070
707070707070707070
65656565
6565
656565
70707070
7070
707070
75757575
7575
757575 8
080
8080
8080
80
8080
80808080
8080
808080
80808080
8080
808080
757575757575757575 707070707070707070
555555555555555555
50505050
5050
505050
50505050
5050
505050
50
50
5050
5050
50
5050
50505050
5050
505050
55555555
5555
555555
454545454545454545
60
60
6060
6060
60
6060
60606060
6060
606060
707070
7070
707070
70
505050505050505050
454545454545454545404040404040404040
454545454545454545
454545454545454545
404040404040404040
454545454545454545
45454545
4545
454545
DMA 1DMA 2All Other Mains
Spot heights
5m contours
Hydrants
Logger locations
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 69
One location (location 10) was abandoned soon after installation when it became apparent
the hydrant had a leak. An alternative location was identified (location 10A), and a logger was
installed at this location the following month.
9.2 Logging results
Nine pressure loggers were installed on 29th June 2010, with the remaining seven loggers
installed the next week on 6th July 2010. Location 10A was identified as an alternative to
location 10, and a pressure logger was installed at the new location during the first data
download on 10th/11
th August 2010. All the loggers were removed on 28
th February 2011,
although two of the loggers had stopped working during December 2010 due to frost damage
caused by the extreme cold weather.
On 17th August 2010, the Pressure Reducing Valve (PRV) controlling the pressure of water
reaching locations 10, 10A, 11, 12, 13 and 16 (DMA 2) underwent maintenance. This
maintenance, along with the alteration of this PRV from a flow-modulation to a two-point
controller on 4th September 2010, resulted in frequent, regular drops in pressure observed at
locations 10A, 11, 12, 13 and 16. As these drops were the result of the new type of controller
used for the PRV and, as they did not reach below 0.1 bar, they are not of interest to this
study. On 12th October 2010, the PRV was changed to a flow-modulation controller once
again. This resulted in the pressure pattern stabilising, and the regular low pressures were no
longer observed.
Table 9.1 provides a summary of the low pressure events observed at the logger locations.
Loggers were deployed at sixteen locations for eight months. Table 9.1 shows that pressures
fell below 1 bar on a large number of occasions. However most of these were in a pressure-
reduced area as a result of problems, modifications and maintenance on the PRV. Excluding
these, 27 low pressures (below 1 bars) were recorded. Very low pressures (below 0.1 bars)
occurred at 5 locations on a total of 6 occasions. On 4 of these occasions, either the water
company reported that a mains repair had taken place or the effect was symptomatic of local
valving to affect a repair. On the other two occasions, hydrant use was either reported or
suspected by the water company. There was a smaller impact on pressure at one other local
logger.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 70
Table 9.1 Summary of low pressures in Site F
Location
No. of
events
<1bar, inc.
PRV
events
No. of
events
<1bar, exc.
PRV events
No. of
events
< 0.1 bar,
exc. PRV
events
Minimum Observed Pressure
Pressure
(bar) Date
Duration
below
0.1 bar
1 3 3 1 -0.05 26th Aug 23 min
2 0 0 0 2.86 - -
3 0 0 0 1.60 - -
4 0 0 0 3.06 - -
5 0 0 0 1.04 - -
6 0 0 0 1.78 - -
7 4 4 2 0.00 19
th Jul 1 sec
0.05 22nd
Oct 1 sec
8 0 0 0 1.90 - -
9 4 4 1 -0.05 8th Dec 17 min
10 1 1 1 -0.05 29th Jul 2 min
10A 57 5 0 0.57 - -
11 61 5 1 0.05 15th Aug 2 min
12 1 0 0 0.99 - -
13 0 0 0 2.37 - -
14 0 0 0 1.15 - -
15 2 2 0 0.53 - -
16 59 3 0 0.31 - -
9.3 Example events
9.3.1 Hydrant flushing event on 2nd August 2010
Flushing took place in the early afternoon at one of the dead ends downstream of location 9
(Figure 9.2). Although it is not known exactly at which hydrant flushing occurred, it is known to
be one of the hydrants circled and marked “F” in Figure 9.2.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 71
Figure 9.2 Location of flushing on 2nd
August, Site F
This had an effect on the loggers at three locations, as shown in Figure 9.3.
60
60
60 60
60 60
60
6060
606060606060606060
606060606060606060
606060606060606060
55555555
5555555555
9
5
3
8
7
15 14
787878787878787878
67.767.767.767.767.767.767.767.767.7
656565656565656565
65656565
6565656565
656565656565656565
757575757575757575
DMA 1DMA 2All Other Mains
Spot heights
5m contours
Hydrants
Logger locations
F
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 72
Figure 9.3 Flushing on 2nd
August 2010, Site F
The largest effect was at location 9 where the pressure fell to 0.4 bars. Since the downstream
ends of the sections being flushed are higher than this point, the pressure could not fall
further. The pressure drop was caused by the increased headloss in the 3” main which feeds
this area which, in turn, is caused by the exceptional flow from the flushing.
Location 3 can be fed from two directions. One of the routes from the supply source was
directly affected by the flushing flow. The extra flexibility in the system at this point resulted in
a considerably lower pressure drop. In addition, this location is some 5 m lower than location
9, so the observed pressure was roughly 0.5 bars higher before the hydrant flushing.
Location 5 is more distant. The flushing had a small effect on pressure at this point because
there are other flow routes to this location. No other logger registered a pressure fall at this
time. A location will only be affected if the supply to that location has a pipe in common with
the supply to the exceptional demand. If those common pipes are large, the effect may be
negligible. This is the case for many logger locations for this event on this site.
9.3.2 PRV maintenance
There were a number of instances where pressures were at low levels for a short period
during Pressure Reducing Valve (PRV) maintenance. An example from 17th August 2010 is
shown in Figure 9.4.
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
11:57:00 12:12:00 12:27:00 12:42:00 12:57:00 13:12:00 13:27:00 13:42:00
Ba
rs
Time
03 05 09
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 73
Figure 9.4 PRV event on 17th
August 2010, Site F
Pressure fell at two locations (11 and 16) to 0.3 bars. These were the highest of the loggers. It
is possible that lower pressures were suffered at other points in the mains which had a higher
ground level, though this area of higher ground is very small. A logger could not be installed in
this area because a water company logger was already present upon the hydrant.
The clue that this is not a demand driven event is provided by the fact that all five loggers in
this pressure controlled area recorded the same pressure fall with the same shape. No low
pressure event was registered outside the PRV area as a result of this maintenance.
9.3.3 Burst event on 3rd December 2010
A burst occurred in the evening of 3rd
December 2010 near logger location 9. It reduced
pressure at that location by approximately 1 bar. A small effect was seen at locations 3 and 5.
(Figure 9.5)
0
1
2
3
4
5
6
7
10:15:00 10:30:00
Bars
Date_Time
10A 11 12 13 16
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 74
Figure 9.5 Burst on 3rd
December 2010, Site F
This makes an interesting comparison with the results of a flushing exercise which took place
in the same road (Section 9.3.1). Clearly, the burst was a much smaller “exceptional demand”
than the flushing.
The lower pressures produced by the burst persisted for 5 days until the main was isolated for
repair. This also isolated the logger at location 9 which recorded zero or near-zero pressure
for over half an hour (Figure 9.6). In fact, pressure falls just below zero on a number of
occasions during this event. It is likely that this is as a result of attempts by customers situated
at points lower than the logger, to draw water.
The pressures at other local loggers (locations 2, 3 and 5) rose slightly when the burst was
isolated.
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
20:30 21:30 22:30 23:30
Ba
rs
Date_Time
02 03 05 08 09
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 75
Figure 9.6 Mains repair on 8th
December 2010, Site F
A further feature of Figure 9.6 is the fall in pressure at these locations as the main is flushed
prior to reinstatement. This is a potential problem if the main being reinstated had been lower
than the surrounding network.
9.3.4 Demand event on 19th July 2010
A significant fall in pressure was observed at two loggers on this date. Pressure fell to zero at
location 7 and to 0.84 bars at location 15 (see Figure 9.7). There was no noticeable effect at
any other logger.
-0.5
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
12:45:00 13:15:00 13:45:00 14:15:00 14:45:00 15:15:00 15:45:00
Ba
rs
Date_Time
02 03 05 08 09
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 76
Figure 9.7 Event on 19th
July 2010, Site F
The water company reports that there was an increase in flow to this DMA at the time of the
event with the possibility that this was illegal usage.
Figure 9.8 shows the pipework and the contours in the vicinity of locations 7 and 15, with the
blue arrows indicating the direction of flow.
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
16:19:12 16:48:00 17:16:48 17:45:36 18:14:24 18:43:12 19:12:00 19:40:48
Ba
rs
Date_Time
08 09 10 14 07 15
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 77
Figure 9.8 Location of affected loggers on 19th
July event, Site F
The site of the exceptional demand must have been close to the junctions where the flow to
these two loggers diverged (marked „J‟ on Figure 9.8) since:
1. They each measure the same drop in pressure;
2. There are no loggers downstream of 7 and 15; and,
3. There is no effect at other loggers suggesting that the enhanced headloss is only in the
feed common to 7 and 15.
It is worth noting that location 7 is almost 10 m higher than location 15, and this explains the
difference in minimum pressure that was observed. The point which has been suggested as
the demand location is almost 15 m below location 7. Therefore, during the event, pressure at
that point would have been more than 1 bar which is sufficient to drive a large flow through an
open hydrant.
A similar pressure event took place in this area on 22nd
October 2010. In that case, the
pressure at location 7 fell to 0.1 bars and at location 15 to 0.6 bars suggesting that the
demand was closer to location 15 on this occasion.
60
60
60 60
60 60
60
6060
55555555
5555
555555
606060606060606060
606060606060606060
606060606060606060
55555555
5555555555
606060606060606060
4
3
8
7
1415
646464646464646464
67.767.767.767.767.767.767.767.767.7
50505050
5050
505050
656565656565656565
45454545
4545
454545
50
50
5050
5050
50
5050
656565656565656565
454545454545454545
404040
4040
404040
40
65656565
6565
656565
707070707070707070
DMA 1DMA 2All Other Mains
Spot heights
5m contours
Hydrants
Logger locations
J
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 78
9.4 Summary results
1. Sixteen loggers were deployed for eight months.
2. Pressure fell below 1 bar on 27 occasions.
3. Five locations suffered very low pressures (less than 0.1 bars). Six such values were
recorded. Three were negative.
4. Most of these low pressure events were because the local main had been isolated. Two
hydrant uses had a localised effect.
5. Work on a PRV caused a large number of low pressures in the study area (see Section
9.3.2).
6. A mains flushing event caused a large drop in pressure locally without the possibility of
ingress (see Section 9.3.1). The effect on pressure at other locations was much smaller
because of the robustness of the system.
7. On another occasion (December 3rd
), a burst close to the locations of the flushing
discussed in point 6 (above) had a much smaller effect (see Section 9.3.3).
8. An exceptional demand on July 19th caused zero pressure at one local logger and a low
pressure at another (see Section 9.3.4). It is believed that the demand was at a much
lower ground level than the loggers and caused enhanced headloss only in the main
feeding this small area.
9.5 Discussion and conclusion
On only two occasions were very low pressures thought to be caused by an exceptional
demand. Some effect was recorded on two other loggers. Other lesser events also had only a
localised effect because of the robustness of the system.
On one occasion, an exceptional demand was thought to be at a much lower ground level
than two of the logger points but such that an enhanced headloss was induced in the main
feeding those two points. These two conditions are needed to cause a very low pressure.
However, upstream of this main, the exceptional flow was carried by a larger main. The effect
on other sites was therefore negligible.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 79
10. Discussion
10.1 Surge
10.1.1 The mechanism
When flow in a pipe changes, there is a resulting change in pressure. This change can be
very much larger than the normal operating pressure resulting in very high or very low (surge)
pressures. If a rapid increase in demand takes place, pressure at that point will fall. This low
pressure will travel through the system at high speed (the “wavespeed”). Wavespeed in metal
pipes is more than 1000 m/s and in plastic pipes typically between 300 and 600 m/s.
In a simple pumping main, the event will travel to the end of the main where it will be
reflected. Multiple reflections lead to the familiar pressure oscillation. In a distribution network,
the event will travel to the nearest junctions where some of the change will be transmitted and
some will be reflected. Because the distance between junctions are short, the reflection
returns to the demand point whilst the flow is still increasing and the pressure still decreasing.
The reflection will have a beneficial effect on the pressure change, limiting this change to less
than it would otherwise be.
Networks have a large number of closely-spaced junctions providing multiple reflections which
restrict the pressure change until fluid friction causes pressures to return to their steady-state
values.
It is possible to develop very low pressures in distribution networks by this mechanism but the
demand change would need to be very rapid. As an example, consider an iron main where a
junction is 100m away from the sudden change in demand. The total time taken for the
pressure event to travel to the junction and for the reflection to return is approximately
0.2 seconds. Only if the demand change is complete within 0.2 seconds will the full pressure
change develop. In addition there is a small reflection and a small reduction in the transmitted
pressure change when the wave reaches a service pipe. Although this effect is small, it can
be shown that the combined effect of all the service connections in an urban street is
substantial.
The pressure logging carried out during this project provided some striking examples of the
difference between pressure surge in a pumping main and in a distribution network. Large
pressure changes developed in the long mains were clearly sufficient to cause low pressures
in the network. However, the interactions within the network ensured that the changes there
were very modest.
The most important effect is the one described above which limits the fall in pressure at the
initiating point. In addition, the pressure change reduces as it travels away from this point. For
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 80
a particularly fast transient, the change can be seen to reduce rapidly with distance. An
example of this was seen during the logging for this project.
10.1.2 The probability of low pressure
Five loggers were deployed at each of two sites for nine and five months respectively. In
addition four 4 loggers were installed for two weeks at a third site where it was known that a
large commercial demand occurred frequently. There were just five occasions when pressure
fell below 0.1 bars and on some of these negative pressures were observed. These were all
in the same system (site A).
On just one of these occasions was the pressure the direct result of high flow. This was
recorded at the source pumps rather than in distribution but remains a possible source of
ingress which could contaminate the water supplied to all the customers. It is not known
whether pressures at the other locations fell to very low values because these records (if any)
would have been overwritten by the subsequent isolation of the distribution system.
Catastrophic bursts occurred on a trunk main and within a distribution system. Severe
pressure drop occurred at a pumping station. None of these caused very low pressures within
distribution.
Based on the results of this study, there is a very low probability of very low pressure as a
result of surge flows. Valving operations to isolate mains can cause low pressures and
sometimes negative pressures.
10.2 Exceptional demand
10.2.1 The mechanism
An unusually large flow in a main will increase the headloss in that main. While this flow is
maintained, the pressure throughout the part of the system fed through this main will be
lowered. However, if this is a large diameter main, it will accommodate a large additional flow
with only a small increase in headloss. (Since distribution networks are usually designed to
provide 15 m available pressure throughout the system at normal maximum demand, this
increase in headloss must be at least 15 m in order to cause a problem.)
Pressure at the location of the exceptional demand (customer demand, hydrant flow or burst)
must remain positive to drive the outflow of water. Indeed, it may need to be significantly
positive depending on the size of the orifice or service pipe. There is a balance between
pressure in the pipe and outflow. If the pressure is low, the outflow will be low. The ground
level of areas with a higher likelihood of negative pressures due to this mechanism will have
to be higher than the exceptional demand location.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 81
These two aspects together lead to the following conclusions about an “at risk” system. It
must contain an area of low-lying land and an area of high ground. If an exceptional demand
event occurs in the low-lying area, the pressure may remain high enough to supply this
demand. If the demand is high with respect to the capacity of the pipes feeding it, it will induce
a high headloss in those mains. This will reduce pressure in these mains and in mains
downstream of the demand. The only points where there is a likelihood of very low pressure
are those which are markedly higher than the demand. Although it is feasible for the “at risk”
area to be upstream of the demand, it is unlikely because only part of the enhanced headloss
will apply to upstream points. As the supply source is approached, the mains diameters
typically increase and the increase in headloss will be smaller.
A typical “at-risk” system therefore has a fall in ground level from the source followed by a
substantial rise. The probability is lower if a small part of the network is at low level because
there are now fewer potential locations for a high flow event. The area at risk is also smaller if
the high level area is small. It can be seen that the conditions necessary for a demand to
produce widespread very low pressures by this mechanism are very restrictive.
There are additional distribution features which reduce the probability of low pressure.
Systems are rarely designed as tree structures. Most of the system will have loops providing
alternative routes to most of the customers. This will limit the increase in headloss even to
those areas which would normally be supplied by the pipe with the extra demand. PRVs and
pressure-controlled booster pumps will also limit the effect on controlled areas.
10.2.2 The probability of low pressure
Sixteen loggers were deployed in each of three systems for one year, eleven months and
eight months respectively. There were only 20 instances of pressure falling below 0.1 bars. Of
these, only two were caused by exceptional demands (hydrant flows). The very low pressure
in these two cases was confined to the mains in a few residential streets. As they were dead
ends, the risk (if any) of receiving contaminated water was confined to these few customers.
This suggests that the probability of low pressure caused by exceptional demand is very
small. It should also be noted that the three systems were chosen because they had
substantial variation in ground level which is a pre-requisite for achieving low pressures by
this mechanism.
Many more instances of lower pressure were recorded. These suggested that other issues
are of more concern than exceptional demand. The most common was the result of valve
closure to isolate a main for repair. This accentuates the need for good disinfection practice
when returning the main to service. Other problems are: mains draining down during valving
operations, pump failure and, PRV failure or maintenance
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 82
10.3 Health risk
It should also be noted that other features are needed before the risk of low pressure
becomes a health risk. These are:
1. There must be a source of contamination at points where low pressure occurs,
2. There must be a pathway between the contaminant and the pipe flow.
10.4 Operational practice
Although the probability of very low pressure as a result of either mechanism is low, it can be
lowered further by opening and closing valves and hydrants slowly, and running hydrants at
the lowest necessary rate. There is clearly no action that can be taken to prevent sudden
and/or large bursts, though mains replacement programmes and good operational practice
will minimise risks.
Very low pressures were observed due to operational practices and other events, i.e. valving
off mains for repair, pump start and stop, pump failure, maintenance or failure of PRVs. Action
can be taken to limit low pressures because of operational practice. Pump control (“soft start
and stop”) to avoid rapid start-up and run-down is beneficial as is maintenance of PRVs. Care
should be taken to maintain pressures whilst PRVs are being maintained.
Following good disinfection practice when returning mains to service and paying similar
attention to related mains which may have drained as a consequence of the valving will
minimise potential health effects resulting from low pressures in these instances. The ability to
recognise that local mains have been drained requires a thorough understanding of the mains
layout.
10.5 Practical aspects of pressure monitoring
This study had a number of technical objectives which dictated the choice of equipment
needed to monitor pressure. The main constraints on the choice of equipment were the time
interval of data recording and power requirements. The Primayer loggers used in the
exceptional demand sites (Sites D, E & F) allowed pressure to be recorded at 10 sec intervals
and had a battery life of approximately 40 days. Consequently the loggers were compact
enough to be readily installed within a hydrant chamber. The compromise for the use of such
compact equipment was the necessity for manual retrieval of the data on a monthly basis.
All the installations and monthly data retrievals were carried out by WRc personnel, but
permission was obtained from each water company to allow the connection of the Primayer
loggers to their networks. To safeguard the quality of the water in these sites, the WRc
personnel that undertook the monitoring exercise were fully trained in the operation of the
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 83
loggers and hydrants. Procedures for disinfection of the equipment were agreed and all WRc
personnel were accredited under the National Water Hygiene Scheme.
As discussed in Sections 2.3.2 and 3.3.2, it was important to ensure that alternative hydrants
could be identified in each site, should it prove difficult to install the pressure loggers. These
practical issues included difficult access to the hydrant (parked cars, busy roads), leaking
hydrants or shallow/ buried hydrants.
The Campbell loggers used in the surge sites (A, B & C) allowed pressure to be recorded at
0.1 sec intervals and required significant storage capacity for this data. Data retrieval was
carried out remotely requiring radio communication equipment. The resulting monitoring
assembly was too large to be installed within a hydrant chamber and therefore had to be
placed within a purpose-built kiosk. The installation of the surge equipment therefore required
much greater planning and resources to implement.
There were a number of practical issues that had to be taken into consideration during the
selection of the locations for the surge equipment, in addition to those that relate to the
condition and position of the hydrant. The ideal location had suitable space to house the
kiosk, without causing an obstruction or hazard to the general public. It was also necessary to
identify the owner of the potential site and obtain their permission to install the kiosk. In the
majority of cases the kiosks were installed on adopted highway and permissions were granted
by the local highways authority. Other land owners included a commercial business, a church,
a sheltered accommodation organisation and a district authority. Each of these organisations
responded differently to requests to install the kiosks, ranging from verbal agreement to
requesting the signing of legal agreements.
To ensure that the installations were carried out at efficiently as possible a thorough survey
was undertaken of each potential location. This included measurement of the available space,
testing the hydrant and also obtaining contact details of the possible land owners. A number
of alternative locations were also surveyed in each of the three sites.
The main obstacle that had to be overcome for the installation of the surge loggers was
dealing with the data cable connecting the pressure sensor on the hydrant to the logging
equipment. These cables needed to be buried to avoid causing a trip hazard. As a result, the
cables were classed as “apparatus” under the New Roads and Streetworks Act (NRSWA) and
were therefore subject to the requirements of this act. In practice this meant that licences had
to be obtained from the local highways authority to install them and the appropriate notices
had to be served to allow the highway to be excavated and reinstated. This installation had to
be carried out by personnel qualified to work in the highway, as stipulated in the Specification
for Reinstatement of Openings in Highways.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 84
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 85
11. Conclusions and Recommendations
Detailed pressure monitoring was carried out in 6 separate distribution networks for a combined period
of 56 months. Some low and negative pressures were observed during the study. The following
conclusions can be drawn from this study.
1. The probability of very low (surge) pressures as a result of a sudden demand is very low.
2. The probability of very low pressures as a result of exceptional high demands is very low.
3. A system is most at risk from low surge pressures if:
a. Pipe junctions are widely spaced
b. Property density is low (low number of service pipe connections)
c. There are very rapid increases in demand.
4. A system is most at risk from exceptional demands if:
a. There is a fall in ground level from the source followed by a substantial rise
b. There is a significant area at low level
c. There is a significant area at high level
d. Normal pressures in the high level area are low.
5. Pressures low enough to cause ingress are more likely as a result of the following than they are
from a demand-driven event:
a. Isolating mains for repair
b. Mains draining down during valving operations
c. Pump failure or rapid pump switching
d. PRV failure or maintenance.
6. To pose a health risk a source of contaminant around the low pressure point and a pathway to the
pipe flow are also necessary.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 86
7. Thorough planning is required to ensure the successful completion of such an extensive monitoring
exercise.
The recommendations from this study are as follows:
1. Additional proactive measures are not required to minimise an already low probability of very low
pressures occurring.
2. The practice of designing distribution systems with alternative routes to most customers (i.e. with
loops) should continue.
3. Good practice should be followed with respect to:
a. Opening and closing valves and hydrants slowly
b. Running hydrants at the lowest necessary flow
c. Returning mains to service (disinfection)
d. Disinfecting local mains which have drained as a consequence of work on other mains
e. Implementing soft start and stop for pumps
f. Maintaining PRVs and maintaining pressures during maintenance.
4. When carrying out research of this nature:
a. A thorough survey should be carried out of all potential locations for any monitoring equipment
b. Sufficient alternative locations should be identified.
DEFRA
WRc Ref: DEFRA8356/15340-0 October 2011
© WRc plc 2011 87
References
WRc, 2008, A review of research on pressure fluctuations in drinking water distribution systems and
consideration and identification of potential risks of such events occurring in UK distribution systems
(WT1205/DWI 70/2/220), Report No: DEFRA7555.01
Wylie, E.B. and Streeter, V.L. Fluid Transients, McGraw-Hill Inc., p3