investigation into the progressive collapse of a rack suppo
TRANSCRIPT
1
Investigation into the Progressive Collapse
of a Rack Supported Structure
Lomira, Wisconsin
July 12, 2002
(Photograph of completed structure taken by Quad Graphics)
2
EXECUTIVE SUMMARY
On July 12, 2002 at approximately 9:29 PM the Quad Graphics Automated Storage and Retrieval
System (ASRS) high bay rack structure in Lomira, Wisconsin collapsed resulting in the death of
a 22 year old male employee. The collapse of the structure resulted in a fire, which burned for
nearly two weeks. The Quad Graphics plant produces printed material such as catalogs and color
newspaper supplements. The ASRS structure was designed to store materials that had been
partially completed, along with materials ready for shipping or mailing. At the time of the
collapse the building was approximately 80% loaded with materials. The ASRS structure
construction is identified as a “rack supported structure.” Essentially, the rack structure is
installed and a roof and exterior skin are attached to the rack structure to form the building. The
rack structure provides the structural elements of the building. Within a historical perspective
this type of structure is relatively new in design and application.
This document is the culmination of the investigation originated by the Wisconsin Department of
Commerce, Division of Safety and Buildings and concluded after the Division closed the
investigation and issued a violation report. The Division of Safety and Buildings has regulatory
authority over the construction and use of public buildings and places of employment within the
state of Wisconsin. On July 15, 2002 the Division organized a team of investigators to:
1) Determine if any codes were violated in the construction of the facility.
2) Determine if the design of the building was done in accordance with the requirements
of the codes and applicable standards.
The investigation team consisted of an architect, a professional engineer with expertise in
structural requirements, a professional engineer with expertise in building code requirements,
and a management representative with expertise in fire protection engineering and investigation.
3
ANALYSIS OF COLLAPSE CAUSATION
In order to determine the effectiveness of the Wisconsin Commercial Building Code the cause or
causes that may have attributed to the collapse had to be investigated. This report examines
probable causes for the collapse. This report does not establish absolute certainty as to the cause
of the collapse.
METHOD OF ANALYSIS
The Lomira collapse is considered to be a unwitnessed collapse. The building is normally
unoccupied and robotic cranes conduct work activities. At the time of the event there were two
workers present at the south conveyor area, and one worker at the north conveyor area.
Eyewitness accounts of the collapse are limited to those areas, which are visible from the north
and south ends of the building in the low bay areas.
Photograph of the North Low Bay area at the approximate location of the witness.
(Photograph by Commerce investigator.)
Because the actual point of
origin was unwitnessed this
evaluation can only provide
probabilistic analysis of the
origin based on available
information. In most
catastrophic events a single
cause is rare, and in most
cases a multitude of causes
culminates to form the result.
In an effort to identify the
cause of the collapse the
investigation and this report
has been developed using the
probabilistic analysis method.
Probabilities are assessed for
each key element associated
with failure modes. The analysis begins with defining the four major categories associated with
building failure, which include the design of the structure, the construction of the structure, the
operation or use of the structure, and any other external forces such as weather, foreign object
damage, etc. Given that the building did collapse the total probability for failure was 100%.
The four major categories begin with an equivalent probability for failure of 25%. The
probabilities are then adjusted up or down based on data assessments. During the initial phase of
the investigations there no identified probabilities for external events such as weather, foreign
objects, missile impact, or explosion. Based upon the determination that the external category
had a small probability factor the remaining categories are adjusted. Probabilities were adjusted
to reflect that three primary categories (design, construction and operation) remained equivalent
4
pending additional information. These categories were then reassessed to greater than 30% with
the external category lowered to less than 10%. The initial assessment of probabilities is shown
in Table 1.
Table 1 – Initial Assessment of Probabilities
Category Predominant Issues
Building Design
>30 %
Defective or Inadequate Design
Building
Construction
>30%
Defective Fabrication or Construction
Building Operation
>30%
Internal Event (crane accident, excessive loads, etc.)
External
<10%
Event (wind, snow, tornado, missile, etc.)
As discussed previously, single causes rarely result in a catastrophic event. This analysis further
separates the event into an “incident precipitators” and “progressive collapse factors.” In
comparison to a house of cards, the collapse begins at a single point where structural integrity is
lost. The loads begin to shift and the collapse progresses through the structure until one of two
events occurs, a total collapse or a portion of the structure resists and results in a partial collapse.
The category of external events was developed using historic information. Items in the category
were then reduced as probabilities due to the lack of any evidence that these forces existed.
In this method of analysis there is an inherent difficulty in reaching absolute certainty, with
regard to the conclusions. Mathematical and scientific modeling for this specific type of
structural event was not available during the investigation. Scientific modeling was gathered
from similar or related types of events as noted in the report.
The evaluation of the causes begins with an understanding of the building type and method of
construction.
5
BUILDING TYPE AND METHOD OF CONSTRUCTION
RACK SUPPORTED STRUCTURES
(Photographs taken during construction by Quad Graphics)
The pictures above are of the Lomira rack supported structure under construction. Photos from
top left to bottom right – first rack modules; installation of roof modules; east side exterior wall
covering; west side wall covering and precast concrete installation. In this form of construction
the rack system forms the structural elements. The rack structure is installed in modules. Each
module is aligned, plumbed and squared. After a significant number of modules are installed the
roofing structure is installed to provide cross aisle support, a cross aisle support is known as a
“cross aisle tie” (CAT). Support along the length of the module is provided by down aisle
supports. This type of a support is known as a “down aisle tie” (DAT).
The Quad Graphics ASRS structure was 763 feet long, 88 feet wide and 103 feet tall to the top of
the rack frames. The total height including roof structure was 106 feet.
6
The ASRS structure was adjacent to a north low bay area, a south low bay area and a corridor
low bay area on the east side (depiction above). The ASRS structure high bay area was
constructed by the Rack Structures Incorporated, the rack manufacturer. A construction division
of Quad Graphics and their sub-contractors constructed the low bay areas. The low bays were
constructed using standard beam and column construction. The north low bay area included the
shipping docks and was used as the primary area for handling finished product.
Photograph of North Low Bay looking towards conveyors to cranes. (Photograph taken by Quad
Graphics.)
The south low bay area was
predominately used for
handling partially
completed materials. The
north and south ends of the
high bay had “run out”
areas for the cranes. The
run out areas were open to
the full height of the
structure. The run out areas
provided space for the
cranes to operate near the
conveyor areas. The south
run out area included a
catwalk for maintenance on
the cranes. The south run
out area was longer than the north run out area due to the catwalk maintenance platforms.
Six aisles divided the high bay; each aisle had a robotic crane. The cranes were designed to
move full distance of the aisle. On each side of the aisle the racks storage cells were single deep.
The exterior racks on the east and west side were single wide, the interior racks were double
wide. Along the north – south axis the rack structures were identified as rows and aisles. Along
the east – west axis the rack structures were known as bays. There were a total of 136 bays, with
Bay 1 located at the south end, and Bay 136 located at the north end. Each rack had 19 storage
cells from floor to roof line. Each crane had access to 5,168 cells. The total number of cells in
the structure was 31,008. Cells near the run out areas were left open to allow employees access
to the cranes, which slightly reduced the total number of cells available to the cranes.
7
Photograph of Crane “B” and Aisle 2. Cranes A, C and D also shown.
(Photograph taken by Quad Graphics.)
At the time of the collapse Quad Graphics personnel had been in the process of loading pallets
into the ASRS system. The final cell loading is indicated in the table below.
Final Cell Loads as of July 12, 2002
Aisle Full Cells Empty Cells Total Cells Percent Full
1 5103 63 5166 98.78
2 5023 143 5166 97.23
3 4336 826 5162 84.00
4 3983 1185 5168 77.07
5 3362 1803 5165 65.09
6 3172 1994 5166 61.40
Totals 24979 6014 30993 80.60
8
RACK FRAME STRUCTURE
The rack structure was composed of rack frames. Each frame had two upright sections of cold
rolled steel. The uprights were constructed using heavier gauge steel for the lower half, and
thinner gauge steel section for the upper half. The two sections were spliced using welded
plates. Two uprights were then connected by a “Z” brace welded into place forming the rack
frame. Shelf units composed of “load
arms” and “load rails” were welded to the
rack frame. The shelf units were designed
to cantilever from the rack frame to support
pallet loads.
Photograph of a north end rack module
suspended by a crane during installation.
Note the down aisle ties, lateral bracing and
run out area without cells. (Photograph
taken by Quad Graphics)
Rack frames connected together formed rack modules. On each side of a rack row there were
nine down aisle ties, for a total of eighteen for each rack row. Cross aisle ties were only present
at the roof structure.
With an understanding of the building type and construction the collapse of the building was
then evaluated.
9
EVALUATION OF THE COLLAPSE
COLLAPSE SCENARIO
Collapse scenarios for rack systems generally fall into two main categories, localized (confined)
and progressive. The Lomira collapse was a progressive collapse. The eyewitnesses identified
the movement of the collapse from the east exterior rack (Row A) to the west in a domino effect.
Photograph of southeast section of the building. Exterior rack structure, cross aisle roof
structure, some remaining exterior wall covering. (Photograph taken by Commerce staff on July
15, 2002.)
The movement of the rack structure and the nature of the amount of damage would indicate a
progressive collapse. The movement of a progressive collapse begins with an initiating event,
which causes shifting of loads and subsequent failures. Load shifting from one element to
another would have a tendency to accelerate due to the addition of loads as each structural
member fails. Load shifting from structural elements would occur in a 360 direction with the
exception of the exterior racks. The exterior racks along the east and west walls would have load
shifting in a 180 direction. Acceleration along the exterior wall would be greater than an
interior rack row due to the limitation of elements by direction to accept loads. The acceleration
10
along the exterior rack would also be impacted by the width to height relationship. Interior racks
were double deep and exterior racks were single deep.
This depiction is an elliptical model based on a progressive collapse with an acceleration rate,
which is greater along the exterior wall than through the interior rack structure. It should be
noted that observers located in relation to the dots saw the movement of the east exterior rack
prior to movement of the interior racks.
View from the west side of the North Low Bay. Left side of photograph is the east exterior wall.
View is from the general area of the witness at the north end.
(Photograph taken by Commerce investigator)
11
COLLAPSE PROGRESSION
To define the collapse progression, the status of the building is evaluated in a reverse
chronological order. The ASRS building was completely razed within 48 hours of the incident
initiation.
The image below, left is from the Milwaukee Journal Sentinel from the night of the July 12,
2002; the image below right was taken on July 17, 2002 at 8:11 AM, by the investigation team.
The area shown is in the south end of the ASRS adjacent to the low bay conveyor area. The
south end of the ASRS was an area of total collapse.
The south end of the building is defined as the area south of the underground pedestrian tunnel,
which was located ~288 feet north of the south exterior wall of the ASRS high bay. Initial
observations by responders to the site indicated that this area was completely collapsed.
Responders also noted the area north of the pedestrian tunnel was damaged but standing. The
individual killed by the collapse was a car parked near the pedestrian tunnel.
Fire department responders during the initial hours after the collapse reported that the structure
north of the pedestrian tunnel stood until sometime between 12:30 and 1:00 AM on the morning
of July 13, 2002. At approximately midnight the fire that had been burning in the south area
progressed into the north end and a flashover occurred. The fire further weakened the damaged
north end resulting in the total collapse of building except for an area on the west exterior wall.
The area that did not collapse extended from ~446 feet north of the south exterior high bay wall
to a point ~588 feet north along the wall. The free standing area extended into the building ~36
feet and probably included bays 78 – 106 along rows E, F, and G (aisles 4, 5 and 6). The
freestanding area was pulled down by cranes at the direction of the fire department to prevent
injury due to the possibility of further collapse. It should be noted that aisle 4 was 77% full, aisle
5 was 65% full and aisle 6 was 61% full. It is highly likely that this area of the building was
12
resistant to collapse due to the decreased loads. Rack structural elements would have been able
to carry loads shifted during the collapse. It should also be noted that there were additional
bracing posts along east – west axis just north and south of the freestanding area.
(The Milwaukee Journal Sentinel took the photograph below on July 13, 2002.)
23
1
In the photograph arrow #1 indicates the location of the south low bay, #2 indicates the location
of the freestanding area, and #3 indicates the north low bay.
The area north of the freestanding section along the west exterior wall was reported by witnesses
as being pushed out along the base of the concrete precast walls, and buckled near the top
northwest corner of the building. The east exterior wall in an area across and just north of the
freestanding area was described by witnesses as leaning towards the east, with some of the
exterior wall covering missing.
13
The collapse at the Lomira plant began as a partial collapse, and then due to the subsequent fire
resulted in a near total collapse. The total collapse of the structure did not occur within the first
few minutes of the event. The building had four areas, which are defined as the area of origin, an
area of total collapse, an area of partial collapse, and an area of resistance to collapse.
The area depicted in shaded gray is approximately the area of the building, which exhibited
internal collapse, and some external damage. This area of partial collapse was further weakened
by the fire and completely collapsed around 12:30 AM on July 13, 2002.
The “X” is the location of the Crane A, the “P” is the approximate location of the witness in the
north low bay. The “PP” is the approximate location of the two witnesses in the south low bay.
The two black dots indicate the approximate locations of the sprinkler system supply lines to the
rack structure.
During the collapse Crane A was toppled severing the electrical connection in the base of the
crane. The Crane Trace Report indicates loss of contact with Crane A at 21:30 hours (July 12,
2002). The cranes were polled by the computer system every 500 milliseconds. At 21:29 the
fire alarm system recorded a fire pump start. The fire pump started due to a decrease in water
pressure. Because water is essentially non-compressible the rapid drop in water pressure
(exceeding the capability of the jockey pump) was probably due to the severing of one or more
of the branch lines or one of the main supply lines. The time differences between the fire alarm
system and the trace report computer could not be verified. A lighting strike caused a outage and
reset of the fire alarm system at a time period after the collapse and prior to the collection of
data. Time sequencing based on information available would seem to indicate that the fire pump
started before Crane A was toppled. This sequencing would indicate that given the speed and
acceleration of the collapse a sprinkler line at some distance north of Crane A was the first
sprinkler line severed.
Interviews of the witnesses indicated that the individuals in the south end low bay reported a
loud noise followed by the sound of thunder moving towards them. Looking towards Crane “A”
the witnesses reported the movement of Row A1 (east exterior rack), progressing towards the
west. The witness at the north low bay reported banging sounds, or pinging, something like a
metal drum being hit. The banging increased to a roar. At that time the witness identified the
movement of Row A1 progressing towards the west. Witness statements were focused on Row
A1, with a progressing west. The noises heard by the witness in the north end of the building
could be related to welds or bolt connections breaking. The thundering sound is likely related to
an acceleration of cells collapsing in downward direction.
14
The information garnered from the witnesses’ lead the investigation team towards the probability
that the initial point of origin was along the east wall and closer to the north end than the south.
The pinging sound followed by an increase in noise at the north end would be more indicative of
the point of origin than the thundering sound heard at the south end. This theory may be
supported by the time sequencing between the fire pump alarm and the Crane Trace Report.
Photograph of area along the east side, south of the North Low Bay. This section of the rack had
indications of compressed buckling of uprights above the splice and just above the base plates.
Debris in this area slumped on to the East Low Bay and the adjoining roof. (Photograph by
Commerce investigator.)
Photograph of slumped
rack structure on eastside,
shows debris accumulation
on adjoining East Low Bay
roof.
15
EVALUATION OF PROBABLE COLLAPSE CAUSES
LOAD SHIFTING
Load shifting is the action that occurs when a structural member fails to support all or some of
the loads and the loads are completely or partially shifted to another structural member. The
most prominent examples of load shifting in recent history include the collapse of the World
Trade Center, and the Murray building in Oklahoma City. Load shifting can occur in macro or
micro scale. Micro shifts in loads can occur without obvious indicators, or a load shift can result
in deformations of the structural member.
The progression in the collapse of the Quad Graphics ASRS Building appears to be due in part to
load shifting.
In a paper by J. R. Gilmour and K S. Virdi the following description of load shifting was
presented:
1“Improvements in structural analysis and knowledge of materials over the last 100 years
have led engineers to build structures that are structurally more efficient than in the past.
This leads increasingly to stretching constituent materials to the limit of their operational
envelope. The result is that modern structures lack the strength reserve that was inherent
in older structures engineered by empirical knowledge and instinct, and hence thought
must be given as to how they will perform when subjected to abnormal loads. A
progressive collapse occurs when a structure has its loading pattern or boundary
conditions changed such that elements within the structure are loaded beyond their
capacity and fail. The residual structure is forced to seek alternative load paths in order
to redistribute the loads applied to it. As a result other elements may fail causing further
load redistribution. The process will continue until the structure can find equilibrium
either by shedding load as a by-product of elements failing or by finding stable
alternative load paths.”
The collapse progression and effect of load shifting in the World Trade Center were presented in
an article in the Member Journal of The Minerals, Metals & Materials Society by Thomas W.
Eagar, and Christopher Musso,
2“Nearly every large building has a redundant design that allows for loss of one primary
structural member, such as a column. However, when multiple members fail, the shifting
loads eventually overstress the adjacent members and the collapse occurs like a row of
dominoes falling down.”
16
A technical article published by Gross and Associates on micro-shifting states the following:
3“Over the past several years there has been a notable rise in the number of rack system
collapses, although seismic activity is rarely the cause of such structural failure. It is
much more likely that a series of pre-existing (man-made) conditions caused the rack
structure to be inherently unstable.
Forensic engineers conclude that lift truck damage, overloading, or inadequately
engineered systems account for nearly all rack failures. One or more of the above factors
can cause the center of gravity to shift away from the center of the rack column and
compromise structural integrity. As the center of gravity shifts further from the column
center (at the baseplate), this "offset" subjects the column to a bending moment, which
creates horizontal force on the column pushing it towards the load center. The column
deforms and the load center continues to shift further away from the column center,
creating an even greater moment. This cycle (called micro- shifting) continues until the
rack structure becomes so unstable that a relatively minor impact may trigger a major
collapse.”
In the 1994 edition of the Uniform Building Code, Table 16-B Special Loads, includes the
following note regarding rack storage.
“Vertical members of storage racks shall be protected from impact forces of operating
equipment, or racks shall be designed so that failure of one vertical member will not
cause collapse of more than the bay or bays directly supported by that member.”
HEIGHT AND WIDTH RELATIONSHIPS
In an article published by Rack Manufacturers Institute the following information was provided
on single row racks, height and width, and considerations with building interaction.
4“BUILDINGS USED TO BRACE RACKS
Wherever the racks have been tied to the building in any way, be absolutely certain the
building has been checked for its adequacy to resist these applied forces. I have seen
installations where a leaning rack was “braced” to the roof by welding an angle from the
top of the rack post to the bottom chord of the roof joist. This may be fine for the rack
except that when it snows, the roof tries to sag and the rack post ends up supporting the
roof as well as the pallet loads. Just because a rack is tied to a wall does not guarantee the
wall is capable of sustaining the applied loads.
Generally, single row racks create the major concern. Some specifications require
additional support for racks where the height to depth ration is greater than 6 to 1. The
height is the height to the top of the topmost load and the depth is the depth of the upright
frame. Stability requirements are a function of the imposed lateral loads. My own
judgment would be not to require additional support, including floor anchoring, for
17
Cross Aisle
Tie (CAT)
Down Aisle
Tie (DAT)
structures whose ratio is 6:1 when the height is to the topmost beam. From 6:1 to 8:1 is a
matter of judgment based upon the overall conditions and loads. Above 8:1 must be
either floor-anchored, wall-tied, or top-tied across the aisle. When racks are top-tied, post
must line up so that the tie runs from post to post. Otherwise the top assembly is too
flexible. “
Photograph of collapsed rack section showing top of rack frame to roof section. (Photograph by
Commerce investigator)
18
MECHANISMS OF COLLAPSE
In a study conducted by 5R.E. McConnel, Phd, CEng, MICE; and S.J. Kelly, Phd, the progressive
collapse of warehouse racks systems was evaluated by the use of computer models and half-scale
tests. The following report was presented and published in the periodical The Structural
Engineer, vol 61A, No. 11, Nov 1983 (figures are copied from the report):
“Mechanisms of Collapse
Taken together, the results of joint pull-out tests, computer program, and half-scale
collapse tests, lead to the following observations.
(i) After bottom leg failure (the most common
form of collapse initiation) a mechanism forms in
the two bays supported by the failed leg as
shown in Fig 5. This mechanism will hereafter
as the ‘joint rotation mechanism.’
(ii) The progress of the joint rotation mechanism
is partly retarded by the bracing connecting the
failed leg to the leg behind it.
(iii) The bracing in most racking systems is
incapable of transferring the load originally
carried by the failed leg to the rear leg; hence the
bracing fails.
(iv) The joint rotation mechanism can develop
only by drawing in the adjacent bays, and this
motion is resisted by the inertial damping and
structural resistance of the adjacent bays. Axial
forces are thus induced in the inclined beams.
Confined collapse
The pull out strength of the joints determines
whether the inclined beams in the joint rotation
mechanism separate from the ‘stationary’
adjacent bays. If separation occurs, a confined
collapse will result, as shown in Fig 6.
Progressive collapse
Alternately, if the beams do not separate, there
are two possible sequences of collapse. Which
of these is followed will depend on where the
initiation point is in relation to the ends of the
rack.
(1) If the initiation point is relatively close to a free end (within four or five bays),
and noting that significant inertial resistance of the adjacent bays occurs only in
19
the early stages of the sequence, the major resistance to the progress of the joint
rotation mechanism is the sway resistance of the bottom columns to the free end.
If the axial force in the bottom beam line is greater than the total sway resistance
of these bottom columns, a ‘bottom leg sway mechanism’ will result, as shown in
Fig 7.
(2) If collapse initiation is far from the free end, e.g. in the middle of a long rack,
the total sway resistance of all the columns either side of the failed leg is likely to
be high. Hence a bottom leg sway mechanism will not form.
An analysis of the forces in joint A in Fig 8 shows that the load lost by the
failed leg is transferred to the legs immediately adjacent to the joint rotation
mechanism. If the axial strength of these bottom columns is exceeded, the legs
must fail. Consequently, two ‘half’ joint rotation mechanisms are set up in
adjacent bays, as shown in Fig 9. Further bottom leg failures can be envisaged as
successive leg failures result from overloads, hence a ‘successive leg buckling
mechanism’ is set up.
Both the bottom leg sway and successive leg buckling mechanisms contain
several bottom leg failures in only the front frame, i.e. in the legs nearest the aisle.
An obvious consequence of this is rigid body rotation of the rack into the aisle, as
shown in Fig 10. A domino-type failure of the racks across the aisles of the
warehouse can then follow. This is the most likely mechanism of progressive
collapse that involves a complete racking installation.”
20
21
Compressed
buckling at
baseplate – aisle
side.
Photographs of rack frame uprights located in the north end of the building east side exterior
rack row. This rack row was a single deep rack structure.
(Photographs by
Commerce
Investigator)
Compression
buckling located
above splice on
aisle side upright.
Splice
Buckle of
upright
located above
splice
Failed
brace
22
The photograph below was taken of a rack frame upright, which was located along the east
exterior wall, single deep row rack. This upright was located nearer to the south end then
photographs shown previously.
(Photographs by Commerce investigator)
Compressed buckling
of non-aisle side
upright located above
splice - specific
distance undetermined.
23
STRUCTURAL WELDING
Documents reviewed by the investigators indicated that weld failures were known to have
existed from the construction of the first rack frame. The lack of weld quality was due in part to
the lack of certification of welders, the lack of procedures and quality assurance. Welding
problems existed in materials due to the inadequacy of seam welds in cold-formed steel tube
stock.
The design professionals including the supervisory design professional reviewed the welding
issues and provided updated engineering data to support continued construction of the facility.
Welding issue were never resolve throughout the construction process as evidenced by
communications between the parties. A weld failure during the loading phase of the project
resulted in visual examination, engineering evaluation and planning for weld replacement. The
loading of the racks did not cease, nor was product removed from the rack based on engineering
assessments of the extent of the problem.
SCOPE OF THE GENERAL CONTRACTOR
At the outset of the project the owner of the site and the contractors set up an unusual working
relationship. The owner contracted the company responsible for the automated cranes as the
general contractor, while retaining responsibility for elements of the building not specifically
associated with the rack structure such as the footing and foundation. This is an important
element of design considering that the site had to be elevated to meet the same floor level as the
rest of the graphics plant. Backfilling of the site and foundation work was accomplished by the
owner. The owner had a nationally renowned reputation for super level concrete design and
construction. The level of the concrete and shifting of the soils became a discussion during the
construction due to shifting of ceiling to rack elements and placement of upright spacers and the
floor level. During the investigation these issues were discussed as they related to load shifting
due differences rack height and roof leveling.
Another element that became an issue during load testing and as it related to the investigation
was the operation of the loading system between the forklifts and the automated racking system.
The conveyer system installed by the owner resulted in load shifting from the front of a rack cell
to the back of the rack cell. Analysis during this phase of the project by the engineering team
determined that a load shift to the back of the cell within the rack did not result in a load
problem. However, this condition was not thoroughly evaluated with respect to the single rack
rows located at the east and west walls. The rack structures at the east and west walls were
designed and evaluated to have the majority of the weight placed at the aisle side of the rack
rather than at the wall side (back of the cell) of the rack. This issue may have been a contributor
to the increase of load and resultant load shift.
24
The table indicates adjustments in the probability factors based on design issues in consideration
of the evaluation by the design professionals regarding construction defects.
Category Predominant Issues Incident Initiators Catastrophic Factors
Building Design
>60 %
Defective or Inadequate
Design
Code Compliance
Peer Documents –
Standards
Load Calculation
Safety Factors
Load Calculation –
Allowable Stress Design
with Impact Load of
10%; see RMI/ANSI
standard for load
calculations and 25%
load impact requirement.
Load Arm to Load Rail
weld correction analysis
and mechanical repair.
Load Rail deflection and
oscillation.
Single vs. double load
stops causing loads to be
skewed.
Calculation on load
stops in racks due to
conveyor system
placement of loads on
cranes.
Height to width ratio,
note in particular to
exterior rows.
Beam to column joints,
torsional and flexuaral
buckling of thin wall
cold formed steel
columns during load
impact moments.
Distortional buckling
and the formation of
Micro shifting of
loads and deflection
of frame posts.
Progressive collapse
analysis due to a
single column failure,
Cambridge Study,
also see UBC 1994
Table 16-B, storage
racks and note 12.
25
plastic hinges in steel
columns.
Soil capacity – Loading
Requirement due to soil
compaction.
Load shifting as a result
of placement of loads to
the back of the cell due
to the conveyor system.
Building
Construction
>30%
Defective Fabrication or
Construction
Welds
Mechanical
Connections
Plumb or Square
Base Material Defect
Load Arm to Load Rail
weld failures.
Load Arm to Rack
Frame weld failures.
Rack Frame post seam
failures.
Anchor Bolts –
Improper size and depth.
Shim – Improper height
of shims and subsequent
burning out shims.
Compression of rack
frames due to load
transfer through DAT
and CAT.
26
Bent posts in at least
three locations.
Roof frame alignment
problems due to post
height.
Use of welders without
certification on type of
weld or credential in
Wisconsin.
Building
Operation
>10%
Internal Event
Crane Operation
Rack Loading
Rack Damage
Rack load procedures –
Aisle A, B, and C were
loaded to greater degree
than D, E, and F.
Manual operation of
cranes and use of spider
crane.
In situ load test of
rack structures with
known weld failures.
External
0%
Event
Wind
Snow
Rain
Tornado
Flood
Foreign Object
Missile Damage
No items identified. No Items identified
27
Elevation view of slumped rack structure located on eastside near the East Low Bay.
28
Location of through-bolt
installed for sprinkler
system.
29
Poor quality weld from
upright to base.
30
Separation of rack structure at the point where the south run-out area was attached. Area on the
left (run-out area) folded towards the west. Area on the right indicates that the section pulled
down and away from the section on the left. Down aisle ties are all bent in a similar manner.
Mechanical repair installed
after load arm to load rail
weld failure.
31
South run-out area viewed from the south. Wall has folded over and the roof area is to the far
left.
32
Looking from the North Low Bay towards the south along the East Low Bay. Fire fighters
responding to this area stated that the area was blocked due to collapse debris. Debris was
present from the time of the initial partial collapse in this area. Further collapse occurred after
the fire degraded the remaining elements that were still standing. (Picture taken by Commerce
investigator)
33
Bowed uprights
Tear
Section of rack structure along the south end, exterior single-deep row. Uprights are bowed, note
the tear on upright at the approximate location of connection to the low bay.
Seam weld on upright.
34
Seam weld failures on
upright.
35
Seam weld failure
36
Load arm to upright weld failure
37
FINDINGS of THE DEPARTMENT OF COMMERCE:
The following findings are a result of the investigation. Following these findings the Department
issued Violation Orders, which are attached.
In accordance with Wisconsin State Statutes ch. 101.11 stats. the owner of a facility is
responsible for providing a safe workplace in conformance with the codes. The building was
not in conformance with the codes as identified by the violation orders.
The design of the structure did not include adequate safety factors to prevent the collapse of
the structure. The supervising professionals did not comply with requirements to submit a
compliance statement. The continued placement of loads in the rack structure resulted in an
uncontrolled in-situ load test. The loading of the rack structure was done with the approval
of the supervising engineer. The engineer signed the compliance statement with full
knowledge that welds had failed and needed to be repaired.
Ineffective welding techniques resulted in a reduction in the strength of the rack structure and
is a likely precipitator to the initial event. Welders working for two contractors did not have
the required credentials or certifications for the types of welding they performed.
A progressive collapse occurred in the ASRS building due to load shifting. Acceleration of
the collapse occurred in areas of the building, which were loaded to near capacity. Areas
within the building that were only partially loaded resisted collapse.
Further analysis may be necessary to determine if additional safety factors should be considered
to prevent a progressive collapse. Designs may need to include either a method to shed loads or
absorb loads during a load shifting progression.
DISCUSSION
The findings of the Department of Commerce were based only on those facts that could be
substantiated and did not expand into conjecture or theory due in part to the political and legal
nature of the Department. This purpose of this document is to expand into the probabilities and
discuss hypothetical causes based on probability.
The theory of initiation of the event begins with the welding failures. At the time of the collapse
the owner and contractors were investigating a failure of a weld that resulted in the load shifting
from an upper cell to a lower cell. This failure occurred in a double row rack in the south end of
the building. The report of the Nondestructive Testing Inspection NDI contractor indicated that
the probability of bad welds was more likely in the north end of the building. Inspection began
in the south end of the building and had not progressed to the north end at the time of the
collapse.
Based upon eyewitness accounts it is more likely the collapse began at the north end and
progressed to the south end. The witnessed also indicated that the motion moved from the east
wall to the west.
38
Based on the crane trace reports and the rack loading information the east wall, single row rack
was loaded to at least 98% of capacity. Again based on reports by the NDI contractor and the
eyewitness accounts the initiating event probably began in the single row rack along the east wall
at a point proximate to the north end. Although numerous investigators on site during the
investigation were focused on the south end of the ASRS, this location only seemed to provide
information relative to the collapse due to comments made by some of the individuals at the
plant. Investigative interviews with the eyewitnesses and with the first responders did not
support the theory that the collapse began at the south end.
The theory proposed in this report is that the collapse was initiated along the east wall at the
north end of the single row rack. The event may have been precipitated by a weld failure or and
in concert with the load placement of the load within the cell (at the back of the rack). Load
shifting in a micro scale was probably already present. Weld failure may have been the last
element necessary to begin a catastrophic load shift.
The progressive collapse was likely a result of design. The Down Aisle Ties were by design
bolted elements and would not have released without tearing metal elements of the rack uprights.
This was evident in examination of rack uprights during the investigation.
Imagine for a minute the playfull game of kids, each hold the others hands as they collapse to the
ground in a game called “ring around the rosey”. If there hands are grasped at the fingers, they
would lose grasp without much effort. If they grasp each other by wrists or forearms, then they
are more likely to hold on longer as they drop to the ground. Referring back to the testing done
on rack structure collapses in 1983, the stronger the down aisle tie, the greater the probability of
progressive collapse. Within the structural system designed for Quad Graphics, there was no
method of reliving or preventing a progressive collapse. In fact the design likely increased the
probability of a progressive collapse.
It is surprising that the requirement in the Uniform Building Code to prevent progressive
collapse has ceased to exist in codes developed from that document. If that code or the results
from the Cambridge study had been fully considered in the design of this building it is probable
that a progressive collapse could have been averted. Current building codes do not require
inherent safety factors to prevent a progressive collapse. The lack of this type of safety factor
was discussed within the State of Wisconsin Department of Commerce, Division of Safety and
Buildings, but was not addressed in the development of future projects or in the development of
future codes adopted by the Department.
It should be noted that after the economic downturn following September 11th
, the Wisconsin
Department of Commerce began a significant move away from state level enforcement and
began shifting enforcement duties to local communities and contractors. This was a primary
political platform of the election of the governor including the elimination of thousands of state
employees. The genesis of this report began within the Department of Commerce, but was
shelved due to cost, political and economic repercussions.
The importance of the release of this information has exceeded the need to maintain political and
economic viability for a few.
39
Hopefully, this report will generate renewed efforts to understand the probability of load shifting
and the need for designing elements to resist loads shifts that can result in catastrophic
progressive collapses.
40
1) ”NUMERICAL MODELLING OF THE PROGRESSIVE COLLAPSE OF FRAMED
STRUCTURES AS A RESULT OF IMPACT OR EXPLOSION.” J.R. Gilmour and K.S. Virdi;
Dept of Civil Engineering, City University, London, UK, EC1V OHB.
2nd
Int. Phd. Symposium in Civil Engineering 1998 Budepest.
2) “WHY DID THE WORLD TRADE CENTER COLLAPSE?, Science, Engineering, and
Speculation”
Thomas W. Eagar, the Thomas Lord Professor of Materials Engineering and Engineering
Systems, and Christopher Musso, graduate research student, are at the Massachusetts Institute of
Technology. MIT, 77 Massachusetts Avenue, Room 4-136, Cambridge, Massachusetts
JOM: The Member Journal of The Minerals, Metals & Materials Society
3) "PALLET RACK SYSTEMS DESIGN CRITERIA & SEISMIC CONSIDERATIONS"
Gross & Associates, Corporate Headquarters,167 Main St.,Woodbridge, NJ 07095
4)“DESIGN IT RIGHT AND IT WON’T GO WRONG”
William T. Guiher, V.P. Simulations & Material Handling, Inflection Point, Inc., 3045 Logan
Road, Greenbrier, TN 37073-4886
5) “STRUCTURAL ASPECTS OF THE PROGRESSIVE COLLAPSE OF WAREHOUSE
RACKING”; R.E. McConnel, Phd, CEng, MICE; and S.J. Kelly, Phd, University of Cambridge
Engineering Department; The Structural Engineer, vol 61A, No. 11, Nov 1983: