introduction to reliability centred maintenance · 2020-03-09 · introduction to reliability...

35
Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Upload: others

Post on 30-Jun-2020

18 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Introduction to Reliability Centred Maintenance

Keith Ashington

M.Eng CM.EngNZ C.Eng M.ICE

Page 2: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Summary

• Background

• What is RCM2?

• The RCM2 process

• Application to track assets

• Benefits

Page 3: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Background

Page 4: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Initial assumptions

• Every aircraft has a specific ‘life’

• Every major component has a specific ‘life’

• Servicing carried out just before ‘life’ reached

• Life can be predicted / defined

• Reducing service life increases reliability

Page 5: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Study findings

Page 6: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

What is RCM2?

“A process used to determine what must be done to ensure that any physical asset

continues to do what is users want it to do in its present operating context”

Page 7: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Further publications

Page 8: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

RCM2 in the UK rail network

• NR/L2/SIG/10662

• NR/L2/MTC/10662

Page 9: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

The RCM2 Process

FMECA+

Page 10: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Workshop

RCM2

Facilitator

Engineering Supervisor

Operative

External specialist

Operator

Operations Supervisor

Page 11: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Operating Context

Page 12: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 1 - Function

• “What are the functions and associated performance standards of the asset in its present operating context?”o “To…

o …Verb…

o …Noun…

o …Performance Standard”

• Primary Function

• Secondary function

Page 13: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 2 - Functional Failure

• In what ways does it fail to fulfil its functions?

Page 14: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 3 - Failure modes

• What causes each functional failure?

Page 15: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 3 - Failure modes

Page 16: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 4 - Failure effects

• What happens when each failure occurs?

• Identifies potential failure points

• Defect may not become observable

100% Capability

Starts to degrade

Defect becomes

observable

Further degradation

Failure

Page 17: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 5 - Failure Consequences

• Hidden Consequence • Safety / Environmental consequence

Page 19: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 6 - On-condition tasks

• Predictive / Preventative

• Defects lead to Faults

o P = potential for failure identified (Defect)

o F = failure identified (Fault)

o P-F = inspection interval + rectification period

Page 20: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Typical on-condition tasks

Page 21: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

KiwiRail example – track geometry

• Rectification periodso P4 = 13 weeks

o P3 = 2 weeks

o P2 = 3 days

o P1 = 1 days

o U1 = FAIL

• BUT P2 requires TSR, so failure.

• Very little time to plan rectification

• Inspection Intervalso Class A(M) = 17 weeks

o Class A(NM) = 26 weeks

o Class B = 35 weeks

o Class C = 52 weeks

Page 22: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

KiwiRail P-F Intervals

P4 P3 P2 P1 U1

Class A(M) 30 weeks 19 weeks 17.3 weeks 17.1 weeks 17.0 weeks

Class A(NM) 39 weeks 28 weeks 26.3 weeks 26.1 weeks 26 weeks

Class B 48 weeks 37 weeks 35.3 weeks 35.1 weeks 35 weeks

Class C 65 weeks 54 weeks 52.3 weeks 52.1 weeks 52 weeks

• P-F Interval = inspection interval + rectification period

• More time needed to rectify

o Reduce inspection interval

o Find P5

Page 23: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 7 - Scheduled tasks

• On-condition tasks not possible

• Still a risk of failure

• Discard

• Restoration

Page 24: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Stage 8 - Default Actions

• Hidden Consequenceso Failure finding tasks

• Safety / Environmental consequenceso Compulsory re-design

• Operational / Non-operationalo Desirable re-design

o Do nothing

Page 25: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Implementation

• Improved Maintenance Regime

o On-condition Tasks

o Scheduled Tasks

o Re-designs

o Failure finding tasks

Improved Maintenance

Regime

Professional Head Approval

Implementation

Review

Page 26: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

RCM2 analysis of track assets

• Exeter - Barnstaple

• Bristol - Exeter

• Euston – Rugby

• Bletchley – Bedford

• Paddington -Heathrow

• Etc

Page 27: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

RCM2 analysis - findings

• Consequences o Hidden – Low (Buffer stops, guard rails)

o Safety / environmental - high (Wrong side failures)

o Operational – low (Right side failure, IBJ)

o Non-operational – low (Wheel squeal)

• On-condition taskso Already in place

o Changes in frequency

o Changes in rectification periods

Page 28: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Changes to on-condition tasks

• All inspections intervals and periods justified

Inspection Change

Patrolling Removed

SM(T) Inspections Replaced with verifications

TME Inspections Maintained (Assurance)

Track Geometry recording

Non-mandated AL faults became mandated

Ultrasonic inspections Non-mandated faults became mandated, all suspects verified

Structure Gauging No change (ORR mandated)

Grinding No change

Lubrication No change

Page 29: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Impact on traditional track

• On condition taskso Small P-F

o Worth doing?

• scheduled restorationso Screw tightening

o Lubrication

o Joint adjustment

o Fastening maintenance

• Default actionso Redesign (Modern track)

• Operating context

o Low tonnage

o Low speed

o Low spend!

Page 30: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Impact on modern track

• On-condition taskso Automated

o Fewer visual inspections

• Scheduled Restorationso Grinding

o Rail lubrication

• Scheduled Discardso Re-padding

• Default actionso Turnout redesigns

Page 31: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Results of RCM2 analysis

• Greater reliance on automated systems

• Targeted track patrolling / verifications

• Maintenance backlog reduced

• Opex reduction

• Risk reduction

Page 32: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Do we need to patrol at all?

• Safety risk on site

• Safety risk travelling to site

• Age / fitness

Page 33: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

What can be achieved?

Page 34: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE
Page 35: Introduction to Reliability Centred Maintenance · 2020-03-09 · Introduction to Reliability Centred Maintenance Keith Ashington M.Eng CM.EngNZ C.Eng M.ICE

Thank you!

Questions?

Keith Ashington CM.EngNZ, C.Eng M.ICE