introduction to mfg tooling

51
Tech 3113 Manufacturing Tooling Nageswara Rao Posinasetti

Upload: ramjirao

Post on 18-Feb-2016

280 views

Category:

Documents


7 download

DESCRIPTION

Gives an over view of need to study manufacturing tooling design.

TRANSCRIPT

Page 1: Introduction to Mfg Tooling

Tech 3113 Manufacturing Tooling

Nageswara Rao Posinasetti

Page 2: Introduction to Mfg Tooling

1. Introduction

April 22, 2023Nageswara Rao Posinasetti 2

Page 3: Introduction to Mfg Tooling

Reduce the overall cost of manufacturing a product by producing acceptable parts at lowest cost.

Increase the production rate by designing tools that will produce parts as quickly as possible.

Maintain quality by designing tools which will consistently produce parts with the required precision.

Reduce the cost of special tooling by making every design as cost effective and efficient as possible.

Design tools that will be safe and easy to operate.April 22, 2023Nageswara Rao Posinasetti 3

Objectives of tool design

Page 4: Introduction to Mfg Tooling

Cutting tools, tool holders and cutting fluids

Machine tools Jigs and fixtures Gages and measuring instruments Dies for sheet metal cutting and forming Dies for forging, cold finishing and

extrusion Fixtures for welding, riveting and other

mechanical fasteningApril 22, 2023Nageswara Rao Posinasetti 4

Responsibilities of tool designer

Page 5: Introduction to Mfg Tooling

Statement and analysis of the problem

Analysis of the requirements Development of initial ideas Development of design alternatives Finalization of design ideas

April 22, 2023Nageswara Rao Posinasetti 5

The Tool Design Process

Page 6: Introduction to Mfg Tooling

Problem without tooling What the tool is supposed to do?

Drill four holes Bottleneck in assembly

Low productivity with out tooling

April 22, 2023Nageswara Rao Posinasetti 6

Statement of the problem

Page 7: Introduction to Mfg Tooling

Must perform certain functions Must meet certain minimum precision

requirements Must keep the cost to a minimum Must be available when the production

schedule requires it Must be operated safely Must meet other requirements such as

adaptability to the machine tool, etc.

April 22, 2023Nageswara Rao Posinasetti 7

Analysis of the requirements

Page 8: Introduction to Mfg Tooling

Estimating cost of tooling

April 22, 2023Nageswara Rao Posinasetti 8

Page 9: Introduction to Mfg Tooling

Cost of material Cost of manufacturing Cost of assembling Cost of standard parts Cost of tryout

April 22, 2023Nageswara Rao Posinasetti 9

What is tool cost?

Page 10: Introduction to Mfg Tooling

Estimate the volume and mass - CAD Steel – 7.843 g/cm3

April 22, 2023Nageswara Rao Posinasetti 10

Cost of material

Page 11: Introduction to Mfg Tooling

It includes Cost of machining Cost of heat treatment

April 22, 2023Nageswara Rao Posinasetti 11

Cost of manufacturing

Page 12: Introduction to Mfg Tooling

April 22, 2023 Nageswara Rao Posinasetti12

Making a Cost Estimate This ability comes by experience Cost estimating procedures depends

on the source Purchase finished component Have a vendor produce the component In house manufacture

Page 13: Introduction to Mfg Tooling

April 22, 2023 Nageswara Rao Posinasetti13

The Cost of Machined Components

Control factors that determine the cost of machined components are:

From what material is the component produced? Cost of material Cost of scrap Ease with which the material can be

removed (machined)

Page 14: Introduction to Mfg Tooling

April 22, 2023 Nageswara Rao Posinasetti14

The Cost of Machined Components

What type of machine is used to manufacture the component? Lathe, horizontal mill, vertical mill, and so on. Cost of machine tool, tools and fixtures used

What are the major dimensions of the component? Size of the machine required That determines the machine overhead cost

Page 15: Introduction to Mfg Tooling

April 22, 2023 Nageswara Rao Posinasetti15

The Cost of Machined Components

How many machined surfaces are there, and how much material is to be removed? Gives a good estimate of time required

for machining How many components are made?

Fixturing requirements Setting times and costs

Page 16: Introduction to Mfg Tooling

April 22, 2023 Nageswara Rao Posinasetti16

The Cost of Machined Components

What tolerance and surface finishes are required? Tighter tolerances are more expensive

What is the labor rate for machinists?

Page 17: Introduction to Mfg Tooling

April 22, 2023 Nageswara Rao Posinasetti17

Courtesy: David Ullman – Mechanical Design Process, McGraw Hill, 2010

Page 18: Introduction to Mfg Tooling

April 22, 2023Nageswara Rao Posinasetti 18

Thumb rules for estimation

Page 19: Introduction to Mfg Tooling

This is relatively easier part. Check with vendor.

April 22, 2023Nageswara Rao Posinasetti 19

Cost of standard parts

Page 20: Introduction to Mfg Tooling

Drilling and fitting time and costs Depends on

Number of parts Complexity Precision required Skill of the operator and judgment

Prefers a rule of thumb rather than sophisticated analysis

April 22, 2023Nageswara Rao Posinasetti 20

Cost of Assembling and Tryout

Page 21: Introduction to Mfg Tooling

Using the listed alternatives, prepare a comparative analysis for the following tooling problem: A total of 950 flange plates require four holes accurately drilled 90 degrees apart to mate with a connector valve. Which of the listed alternatives is the most economically desirable?

A. Have a machinist who earns $30.00 per hour lay out and drill each part at a rate of 2 minutes per part.

B. Use a template jig, capable of producing 50 parts per hour and costing $50.00, in the production department, where an operator earns $15.00 per hour.

C. Use a duplex jig, which costs $500.00 and can produce a part every 26 seconds, in the production department, where an operator earns $15.00 per hour.

April 22, 2023Nageswara Rao Posinasetti 21

Tooling Economics

Page 22: Introduction to Mfg Tooling

Option a: Cost per piece = 30/30 = $1.00

Option b: Production rate = 60/1.2 = 50 per hour Cost per piece = 50/950 + 15/50 = 0.05 + 0.30 = $0.35

Option c: Production rate = 3600/26 = 138 per hour Cost per piece = 500/950 + 15/138 = 0.53 + 0.11 = $0.64 Cost per piece = 500/2500 + 15/138 = 0.20 + 0.11 =

$0.31 (If 2500 pieces are to be produced)

April 22, 2023Nageswara Rao Posinasetti 22

Tooling Economics

Page 23: Introduction to Mfg Tooling

C = Initial cost of the fixture I = interest rate on investment, say 6% M = maintenance cost of fixture, say 10% T = tax requirement on fixture investment,

say 4% D = depreciation of fixture, say 50% Make depreciation 100% if the cost is to be

recovered in one year. S = setup cost per year = setup cost per

batch * setup costApril 22, 2023Nageswara Rao Posinasetti 23

Tooling Economics

Page 24: Introduction to Mfg Tooling

t = time saved because of the fixture, hours a = Labor hourly cost A=Cost of saving due to fixture = a * t Y=Yearly cost of fixture = S + C*(I+M+T+D) n = Annual production rate N = Pieces to be made per year to justify fixture = It is necessary n > N

April 22, 2023Nageswara Rao Posinasetti 24

Tooling Economics

AY

Page 25: Introduction to Mfg Tooling

Economical cost of fixture,

Number of years for fixture to pay itself

April 22, 2023Nageswara Rao Posinasetti 25

Tooling Economics

DTMIS-taN

C

T)M(IC-S-taNC

Years

Page 26: Introduction to Mfg Tooling

April 22, 2023Nageswara Rao Posinasetti 26

Q5 Q6 Q7 Q8C = Initial cost of the fixture ₹

25,000.00 ₹ 35,000.00

₹ 45,000.00

₹ 35,000.00

I = interest rate on investment 6% 6% 6% 6%M = maintenance cost of fixture 10% 10% 8% 8%T = tax requirement on fixture investment 4% 4% 4% 4%D = depreciation of fixture 50% 50% 60% 50%S = setup cost ₹

500.00 ₹ 600.00

₹ 1,200.00

₹ 800.00

₹ 18,000.00

₹ 25,100.00

₹ 36,300.00

₹ 24,600.00

t = time saved because of the fixture, hours 0.03

0.04

0.03

0.03

a = Labour hourly cost ₹ 100.00

₹ 100.00

₹ 200.00

₹ 200.00

₹ 3.00

₹ 4.00

₹ 6.00

₹ 6.00

Number of pieces to be made per year 6,000

6,275

6,050

4,100

Make depreciation 100% if the cost is to be recovered in one year. 100% 100% 100% 100%Yearly cost of the fixture if the cost is to be recovered in one year.

₹ 30,500.00

₹ 42,600.00

₹ 54,300.00

₹ 42,100.00

Number of pieces to be produced if the cost is to be recovered in one year.

10,167

10,650

9,050

7,017

Economical batch size of manufacture 1000 1500 2000 1500Number of batches 6 5 4 3

Setup cost per year = setup cost per batch * setup cost ₹ 3,000.00

₹ 3,000.00

₹ 4,800.00

₹ 2,400.00

₹ 20,500.00

₹ 27,500.00

₹ 39,900.00

₹ 26,200.00

Number of pieces to be made per year 6,833

6,875

6,650

4,367

Page 27: Introduction to Mfg Tooling

Design alternativesCreate Analyze in terms of these criteria

Alternatives Function Quality Cost Date Auxiliary

AB..

April 22, 2023Nageswara Rao Posinasetti 27

Page 28: Introduction to Mfg Tooling

Temporary tooling Permanent tooling

April 22, 2023Nageswara Rao Posinasetti 28

Economics of Design

Page 29: Introduction to Mfg Tooling

Break-even charts are perhaps most widely used to determine profits based on anticipated sales.

They have other uses, however, such as for selecting equipment or for measuring the advisability of increased automation.

April 22, 2023Nageswara Rao Posinasetti 29

Break-Even Charts

Page 30: Introduction to Mfg Tooling

To determine which of two machines is most economical, the fixed cost and variable cost of each machine are plotted

The total cost is composed of the sum of the fixed and variable costs.

April 22, 2023Nageswara Rao Posinasetti 30

Break-Even Charts

Page 31: Introduction to Mfg Tooling

Fixed cost, which relates to the initial investment on the equipment and tools required for the process.

Variable cost on the other hand varies with the actual number of objects made.

The total cost is the sum of both fixed and variable cost.

April 22, 2023Nageswara Rao Posinasetti 31

Break Even Analysis

Page 32: Introduction to Mfg Tooling

TC = total cost FC = fixed cost VC = variable cost per piece N = production quantity

April 22, 2023Nageswara Rao Posinasetti 32

N VC + FC = TC

Page 33: Introduction to Mfg Tooling

April 22, 2023Nageswara Rao Posinasetti 33

N C V + C F = N C V + C F 2211

C V - C VC F - C F = N

21

12

N = Break even quantity

Page 34: Introduction to Mfg Tooling

Permanent mould casting, ($)

Die casting($)

Tooling 3600 7000Setup cost 6.8 17.0Labor cost 0.50 0.33Material cost 0.50 0.25

April 22, 2023Nageswara Rao Posinasetti 34

An aluminum canopy can be obtained by either permanent mould casting or die casting process. The costs in dollars in either case are

Find out the break-even quantity of production from 1000 to 15 000 pieces.

Page 35: Introduction to Mfg Tooling

April 22, 2023Nageswara Rao Posinasetti 35

Permanent mould casting($)

Die casting($)

Tooling 3600 7000

Setup cost 6.8 17.0

Fixed cost 3606.80 7017.00

Page 36: Introduction to Mfg Tooling

April 22, 2023Nageswara Rao Posinasetti 36

Permanent mould casting($)

Die casting($)

Tooling 3600 7000

Setup cost 6.8 17.0

Fixed cost 3606.80 7017.00Labor cost 0.50 0.33

Material cost 0.50 0.25

Variable cost 1.00 0.58

Page 37: Introduction to Mfg Tooling

April 22, 2023Nageswara Rao Posinasetti 37

Prod quantity

Permanent mould casting, ($)

Die casting($)

1000 4606.80 7580.005000 8606.80 9917.0010,000 13,606.80 12,800.0015,000 18606.80 15717.00

Break even quantity =

= 8119.52

58.000.180.36067017

Page 38: Introduction to Mfg Tooling

Draw and dimension with due consideration for someone using the drawing to make the item in the tool room. Do not crowd views or dimensions. Analyze each cut to be sure it can be done with

standard tools. Use only as many views as necessary to

show all required detail.

April 22, 2023Nageswara Rao Posinasetti 38

Tool Drawings

Page 39: Introduction to Mfg Tooling

Surface roughness must be specified. Tolerances and fits peculiar to tools need

special consideration. It is not economical as a rule to tolerance both

details of a pair of mating parts as is required on production part detailing.

In cases where a hole and a plug are on different details to be made and mated, the fit tolerance should be put on the male piece and the hole should carry a nominal size.

April 22, 2023Nageswara Rao Posinasetti 39

Tool Drawings

Page 40: Introduction to Mfg Tooling

The stock list of any tool drawings should indicate all sizes required to obtain the right amount for each detail. As far as possible, stock sizes known to

be on hand should be used, but in all cases, available sizes should be specified. A proper, finished detail is dependent upon starting with the right material.

April 22, 2023Nageswara Rao Posinasetti 40

Tool Drawings

Page 41: Introduction to Mfg Tooling

Use notes to convey ideas that cannot be communicated by conventional drawing. Heat treatments and finishes are usually identified as specification references rather than being spelled out on each drawing.

April 22, 2023Nageswara Rao Posinasetti 41

Tool Drawings

Page 42: Introduction to Mfg Tooling

Secondary operations such as surface grinding, machining of edges, polishing, heat treating, or similar specifications should be kept to a minimum. Only employ these operations when

they are important to the overall function of the tool; otherwise these operations will only add cost, not quality to the tool.

April 22, 2023Nageswara Rao Posinasetti 42

Tool Drawings

Page 43: Introduction to Mfg Tooling

Apply tolerances realistically. Overly tight tolerances can add a great deal of additional cost with little or no added value to the tool.

The function of the detail should determine the specific tolerance, not a standard title block tolerance value.

April 22, 2023Nageswara Rao Posinasetti 43

Tool Drawings

Page 44: Introduction to Mfg Tooling

Layout the part in an identifying color (red is suggested).

Layout any cutting tools. Possible interference or other confining items should be indicated in another identifying color (blue suggested). Use of the cutting tool should not damage the machine or the fixture.

April 22, 2023Nageswara Rao Posinasetti 44

Tooling Layout

Page 45: Introduction to Mfg Tooling

Indicate all locating requirements for the part. There are three locating planes: use three points in one, two points in the second, and only one point in the third plane. This is called the 3-2-1 locate system.

Do not locate on the parting line of castings or forgings. All locators must be accessible for simple cleaning of chips and dirt.

April 22, 2023Nageswara Rao Posinasetti 45

Tooling Layout

Page 46: Introduction to Mfg Tooling

Indicate all clamping requirements for the part.

Be careful to avoid marking or deforming finished or delicate surfaces.

Consider the clamping movements of the operator so injury to the hands or unsafe situations are eliminated.

Be sure it is possible to load and unload the part.

April 22, 2023Nageswara Rao Posinasetti 46

Tooling Layout

Page 47: Introduction to Mfg Tooling

Layout the details with due considerations to stock sizes, so as to minimize machining requirements.

Use full scale in the layout if possible. Indicate the use of standard fixture

parts (shelf items) whenever possible.

April 22, 2023Nageswara Rao Posinasetti 47

Tooling Layout

Page 48: Introduction to Mfg Tooling

Identify each different item or detail of any design by the use of balloons with leaders and arrows pointing to the detail in the view that best shows the outline of the item. These should not go to a line that is common to other details.

April 22, 2023Nageswara Rao Posinasetti 48

Tooling Layout

Page 49: Introduction to Mfg Tooling

Safety should be designed into the tooling. Cutting should never be performed against

a clamp, because of vibration and tool chatter. Instead, parts should be nested against pins in order to take the cutter load.

Rigidity and fool proofing should always be built into the tooling.

April 22, 2023Nageswara Rao Posinasetti 49

Safety as Related to Tool Design

Page 50: Introduction to Mfg Tooling

Make drill jigs large enough to hold without the danger of spinning.

Small drill jigs should always be clamped in a vise or against a bar or backstop.

Install plexiglass guards around all milling and fIycutting operations where chips endanger workers or work areas.

April 22, 2023Nageswara Rao Posinasetti 50

Safety as Related to Tool Design

Page 51: Introduction to Mfg Tooling

Questions?

April 22, 2023Nageswara Rao Posinasetti 51