introduction to computer integrated manufacturing (cim)

57
4/3/2014 1 Hareesha N G, Dept of Aero Engg, DSCE, Blore

Upload: hareesha-n-gowda-dayananda-sagar-college-of-engg-bangalore

Post on 06-May-2015

1.901 views

Category:

Education


5 download

DESCRIPTION

This presentation gives an introduction to computer integrated manufacturing (first chapter as per VTU Syllabus, 10ME61).

TRANSCRIPT

Page 1: Introduction to computer Integrated Manufacturing (CIM)

4/3/2014 1 Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 2: Introduction to computer Integrated Manufacturing (CIM)

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 2

Page 3: Introduction to computer Integrated Manufacturing (CIM)

Production System

A collection of people, equipment, and procedures organized to accomplish the manufacturing operations of a company

Two categories: • Facilities – the factory and equipment in the facility

and the way the facility is organized (plant layout)

• Manufacturing support systems – the set of procedures used by a company to manage production and to solve technical and logistics problems in ordering materials, moving work through the factory, and ensuring that products meet quality standards

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 3

Page 4: Introduction to computer Integrated Manufacturing (CIM)

4

Types of Manufacturing Systems

1. Continuous-flow processes. Continuous dedicated production of large

amount of bulk product. Continuous manufacturing is represented by

chemicals, plastics, petroleum, and food industries.

2. Mass production of discrete products. Dedicated production of large

quantities of one product (with perhaps limited model variations).

Examples include automobiles, appliances and engine blocks.

3. Batch production. Production of medium lot sizes of the same product.

The lot may be produced once or repeated periodically. Examples: books,

clothing and certain industrial machinery.

4. Job-shop production. Production of low quantities, often one of a kind, of

specialized products. The products are often customized and

technologically complex. Examples: prototypes, aircraft, machine tools

and other equipment.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 5: Introduction to computer Integrated Manufacturing (CIM)

Production

quantity

Continuous-

flow production

Mass

production

Batch

production

Job shop

production

Product variety

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 5

Page 6: Introduction to computer Integrated Manufacturing (CIM)

Category Automation achievements

Continuous-flow process

•Flow process from beginning to end

•Sensors technology available to measure

important process variables

•Use of sophisticated control and optimization

strategies

•Fully computer automated lines

Mass production of discrete products

•Automated transfer machines

•Dial indexing machines

•Partially and fully automated assembly lines

•Industrial robots for spot welding, part handling,

machine loading, spray painting, etc.

•Automated material handling systems

•Computer production monitoring

Batch production

•Numerical control (NC), direct numerical

control (DNC), computer numerical control

(CNC).

•Adaptive control machining

•Robots for arc welding, parts handling, etc.

•CIM systems.

Job shop production •Numerical control, computer numerical control

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 6

Page 7: Introduction to computer Integrated Manufacturing (CIM)

The Production System

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 7

Page 8: Introduction to computer Integrated Manufacturing (CIM)

Production System Facilities

Facilities include the factory, production machines and tooling, material handling equipment, inspection equipment, and computer systems that control the manufacturing operations

• Plant layout – the way the equipment is physically arranged in the factory

• Manufacturing systems – logical groupings of equipment and workers in the factory – Production line – Stand-alone workstation and worker

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 8

Page 9: Introduction to computer Integrated Manufacturing (CIM)

Manufacturing Support Systems

Involves a cycle of information-processing activities that consists of four functions: 1. Business functions - sales and marketing, order

entry, cost accounting, customer billing

2. Product design - research and development, design engineering, prototype shop

3. Manufacturing planning - process planning, production planning, MRP, capacity planning

4. Manufacturing control - shop floor control, inventory control, quality control

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 9

Page 10: Introduction to computer Integrated Manufacturing (CIM)

Information Processing Cycle in Manufacturing Support Systems

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 10

Page 11: Introduction to computer Integrated Manufacturing (CIM)

Automation in Production Systems

Two categories of automation in the production system:

1. Automation of manufacturing systems in the factory

2. Computerization of the manufacturing support systems

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 11

Page 12: Introduction to computer Integrated Manufacturing (CIM)

Computer Integrated Manufacturing

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 12

Page 13: Introduction to computer Integrated Manufacturing (CIM)

Mechanization

• Mechanization is providing human operators with machinery that assist them with the muscular requirements of work.

• It can also refer to the use of machines to replace manual labor or animals.

• A step beyond mechanization is automation.

• The use of hand powered tools is not an example of mechanization.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 13

Page 14: Introduction to computer Integrated Manufacturing (CIM)

Automation

• What is automation?

• Why automation is required?

• Which are the operations can be automated in production system?

• Can automation be implemented suddenly?

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 14

Page 15: Introduction to computer Integrated Manufacturing (CIM)

Automation

• Automation can be defined as the technology concerned with the application of complex mechanical, electronic, and computer-based systems in the operation and control of manufacturing systems.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 15

Page 16: Introduction to computer Integrated Manufacturing (CIM)

Automation

Automation is the use of control systems

(such as numerical control, programmable logic control, and other industrial control systems),

in concert with other applications of information technology

(such as computer-aided technologies [CAD, CAM,]),

to control industrial machinery and processes, reducing the need for human intervention.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 16

Page 17: Introduction to computer Integrated Manufacturing (CIM)

Automation • In the scope of industrialization, automation

is a step beyond mechanization.

• Where as mechanization provided human operators with machinery to assist them with the muscular requirements of work.

• Automation greatly reduces the need for human and mental requirements as well.

• Processes and systems can also be automated.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 17

Page 18: Introduction to computer Integrated Manufacturing (CIM)

Automated Manufacturing Systems

Examples:

• Automated machine tools

• Transfer lines

• Automated assembly systems

• Industrial robots that perform processing or assembly operations

• Automated material handling and storage systems to integrate manufacturing operations

• Automatic inspection systems for quality control

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 18

Page 19: Introduction to computer Integrated Manufacturing (CIM)

Automated Manufacturing Systems

Three basic types:

1. Fixed automation

2. Programmable automation

3. Flexible automation

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 19

Page 20: Introduction to computer Integrated Manufacturing (CIM)

Fixed Automation

A manufacturing system in which the sequence of processing (or assembly) operations is fixed by the equipment configuration.

Typical features: • Suited to high production quantities • High initial investment for custom-engineered

equipment • High production rates • Relatively inflexible in accommodating product

variety

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 20

Page 21: Introduction to computer Integrated Manufacturing (CIM)

Programmable Automation

A manufacturing system designed with the capability to change the sequence of operations to accommodate different product configurations

Typical features: • High investment in general purpose equipment • Lower production rates than fixed automation • Flexibility to deal with variations and changes in

product configuration • Most suitable for batch production • Physical setup and part program must be changed

between jobs (batches)

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 21

Page 22: Introduction to computer Integrated Manufacturing (CIM)

Flexible Automation

An extension of programmable automation in which the system is capable of changing over from one job to the next with no lost time between jobs

Typical features:

• High investment for custom-engineered system

• Continuous production of variable mixes of products

• Medium production rates

• Flexibility to deal with soft product variety

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 22

Page 23: Introduction to computer Integrated Manufacturing (CIM)

Product Variety and Production Quantity for Three Automation Types

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 23

Page 24: Introduction to computer Integrated Manufacturing (CIM)

Reasons for Automating

1. To increase labor productivity 2. To reduce labor cost 3. To mitigate the effects of labor shortages 4. To reduce or remove routine manual and clerical

tasks 5. To improve worker safety 6. To improve product quality 7. To reduce manufacturing lead time 8. To accomplish what cannot be done manually 9. To avoid the high cost of not automating

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 24

Page 25: Introduction to computer Integrated Manufacturing (CIM)

Production Concepts and Mathematical Models

• Production rate Rp

• Production capacity PC

• Utilization U

• Availability A

• Manufacturing lead time MLT

• Work-in-progress WIP

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 25

Page 26: Introduction to computer Integrated Manufacturing (CIM)

Production rate Rp • Hourly production rate

• Work units completed/Hr

• Cycle time: Time that one work unit spends being processed or assembled. It is the time between when one work unit begins processing and next unit begins.

• Not all time is productive.

• Cycle time consists of i) actual machining operation time ii) workpart handling time

iii) tool handling time per workpiece

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 26

Page 27: Introduction to computer Integrated Manufacturing (CIM)

Operation Cycle Time

Typical cycle time for a production operation: Tc = To + Th + Tth -------------------1 where Tc = cycle time, min/pc To = processing time for the operation, min/pc Th = handling time (e.g., loading and unloading

the production machine), min/pc and Tth = tool handling time (e.g., time to change

tools), min/pc

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 27

Page 28: Introduction to computer Integrated Manufacturing (CIM)

Tool handling time

• Time spent changing tools when worn out

• Time required for changing one tool to the next.

• Tool indexing time for indexable inserts or for tools on a turret lathe

• Tool positioning for next pass etc..

– These activities do not occur every cycle

– They must be spread over the number of parts

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 28

Page 29: Introduction to computer Integrated Manufacturing (CIM)

Production rate for batch production

Time to process one batch(Q units) = Setup time + processing time, i.e., Tb = Tsu + QTc------------------2

where

Tb = Batch processing time in min

Tsu = Setup time required for one batch in min

Q = Batch quantity, pc

Tc = cycle time per workunit in min/cycle

Tp = Tb / Q ,------------------------3

whereTp= Avg prod. Time/workunit , min/pc

Rp = 60 / Tb ,----------------------4

Where Rp = Hourly prod rate, pc/Hr 4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 29

Page 30: Introduction to computer Integrated Manufacturing (CIM)

Production rate for job shop production

Time to process one batch(Q units) = Setup time + processing time, i.e., Tb = Tsu + QTc

For job shop production, Q = 1

So, Tb = Tsu + Tc = Tp How??

Tp = Tb / Q , whereTp= Avg prod. Time/workunit , min/pc

Rp = 60 / Tb , Where Rp = Hourly prod rate, pc/Hr

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 30

Page 31: Introduction to computer Integrated Manufacturing (CIM)

Production rate for mass production

Production rate = cycle rate of the machine

Tb = Tsu + QTc

For mass production, Q = very large

Tp = Tb/Q = (Tsu + QTc ) / Q = Tsu /Q + QTc/Q

Tp = Tsu/Q +Tc

As Q becomes very large, Tsu/Q 0

So, Tp = Tc

WKT, Production rate is reciprocal of production time

Rp = Rc = 60/Tc 4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 31

Page 32: Introduction to computer Integrated Manufacturing (CIM)

Production rate for flow line mass production

• Production rate = cycle rate of the production line

• Workstations are interdependent in the line

• Impossible to divide total work equally among all workstations on the line.

• So, one station ends up with the longest operation time ( Bottle neck station).

• Bottle neck station sets the pace to other workstation.

• Work units should be moved from one workstation to next (Tr ) 4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 32

Page 33: Introduction to computer Integrated Manufacturing (CIM)

Production rate for flow line mass production

• Cycle time = transfer time + longest processing time

Tc = Tr + Max To -----------------5

• Where Max To = operation time at the bottle neck station i.e., The maximum of operation times for all stations on the line

• Tr = Transfer time

Rc = 60/Tc ----------------6

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 33

Page 34: Introduction to computer Integrated Manufacturing (CIM)

Production capacity

• maximum rate of output that a production facility (or production line, work center, or group of work centers) is able to produce under a given set of assumed operating conditions

• Operating conditions refer to the number of shifts per day, number of days in the week (or month) that the plant operates, employment levels, and so forth.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 34

Page 35: Introduction to computer Integrated Manufacturing (CIM)

Production capacity Let PCw = the production capacity of a given facility under

consideration.

Let the measure of capacity = the number of units produced per week.

Let n = the number of machines or work centers in the facility.

A work center is a manufacturing system in the plant typically consisting of one worker and one machine. It might also be one automated machine with no worker, or multiple workers working together on a production line.

It is capable of producing at a rate RP unit/hr. Each work center operates for Hs hr/shift.

Let Sw denote the number of shifts per week.

PCw = n Sw Hs Rp --------------------7

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 35

Page 36: Introduction to computer Integrated Manufacturing (CIM)

Production capacity

• If we include the possibility that each work unit is routed through no operations, with each operation requiring a new setup on either the same or a different machine,

• where no = number of operations in the routing

o

psw

n

RHnSPC ---------8

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 36

Page 37: Introduction to computer Integrated Manufacturing (CIM)

Production Capacity

Plant capacity for facility in which parts are made in one operation (no = 1):

PCw = n Sw Hs Rp

where PCw = weekly plant capacity, units/wk Plant capacity for facility in which parts require multiple operations (no > 1):

where no = number of operations in the routing

o

psw

n

RHnSPC

Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 38: Introduction to computer Integrated Manufacturing (CIM)

Production Capacity

Equation indicates the operating parameters that

affect plant capacity. Changes that can be made to increase or decrease

plant capacity over the short term are:

1. Change the number of shifts per week (S). For example, Saturday shifts might be authorized to temporarily increase capacity.

2. Change the number of hours worked per shift (H). For example, overtime on each regular shift might be authorized to increase capacity.

o

psw

n

RHnSPC

Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 39: Introduction to computer Integrated Manufacturing (CIM)

Over the intermediate or longer term, the following changes can be made to increase plant capacity:

3. Increase the number of work centers, n, in the shop. This might be done by using equipment that was formerly not in use and hiring new workers.

4. Increase the production rate, Rp by making improvements in methods or process technology.

5. Reduce the number of operations no required per work unit by using combined operations, simultaneous operations, or integration of operations.

Production Capacity

Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 40: Introduction to computer Integrated Manufacturing (CIM)

Utilization • Utilization refers to the amount of output of a

production facility relative to its capacity. Expressing

U=Q/PC------------9 Where U = utilization of the facility,

Q = actual quantity produced by the facility during a given time period (i.e., pc/wk), and

PC = production capacity for the same period (pc/wk).

It is often defined as the proportion of time that the facility is operating relative to the time available under the definition of capacity.

Utilization is usually expressed as a percentage.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 40

Page 41: Introduction to computer Integrated Manufacturing (CIM)

Availability • Availability is defined using two other reliability

terms, mean time between failure (MTBF) and mean time to repair (MTTR).

• The MTBF indicates the average length of time the piece of equipment runs between breakdowns.

• The MTTR indicates the average time required to service the equipment and put it back into operation when a breakdown occurs.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 41

Page 42: Introduction to computer Integrated Manufacturing (CIM)

Availability

Availability is defined as follows:

Availability: A =

where MTBF = mean time between failures, and

MTTR = mean time to repair

Availability is typically expressed as a percentage

MTBF

MTTRMTBF -----------10

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 42

Page 43: Introduction to computer Integrated Manufacturing (CIM)

Availability - MTBF and MTTR Defined

Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 44: Introduction to computer Integrated Manufacturing (CIM)

1) A production machine operates at 2 shifts/day and 5 days a week at full capacity. Its production rate is 20 unit/hr. During a certain week, the machine produced 1000 parts and was idle in the remaining time, (a) Determine the production capacity of the machine, (b) What was the utilization of the machine during the week under consideration?

if the availability of the machine is 90%, and the utilization of the machines is 80%. Compute the expected plant output.

Solution:

(a) The capacity of the machine can be determined using the assumed 80-hr week as follows:

PC = 80(20) = 1600 unit/wk

(b) Utilization can be determined as the ratio of the number of parts made by the machine relative to its capacity.

U = 1000/1600 = 0.625 (62.5%)

(c) U=Q/PC or

Q= UxPCxA or UAxnSHRp

Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 45: Introduction to computer Integrated Manufacturing (CIM)

2) The mean time between failures for a certain production machine is 250 hours, and the mean time to repair is 6 hours. Determine the availability of the machine.

Availability: A =

3) One million units of a certain product are to be manufactured annually on dedicated production machines that run 24 hours per day. 5 days per week, 50 weeks per year, (a) If the cycle time of a machine to produce one part is 1.0 minute, how many of the dedicated machines will be required to keep up with demand? Assume that availability, utilization, and worker efficiency = 100%, and that no setup time will be lost, (b) Solve part (a) except that availability = 0.90.

Solution: Tc= 1 min

Tb = Tsu+QTc = 0+QTc

Tp= Tb/Q = Tc

Rp=60/Tp = 60 Parts/Hr

n= PC/SHRp

= 1000000/(50x5x24x60)

= 2.77 = 3 machines

MTBF

MTTRMTBF

Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 46: Introduction to computer Integrated Manufacturing (CIM)

Manufacturing Lead Time

Manufacturing lead time (MLT) is the total time required to process a given part or product through the plant, including any lost time due to delays, time spent in storage, reliability problems, and so on.

Production consists of a sequence of individual processing and assembly operations. Between the operations are material handling, storage, inspections, and other non productive activities.

Divide these activities as operation and non operation elements.

Non operation elements are Handling, temporary storage, inspection and other sources of delay when work unit is not in machine.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 46

Page 47: Introduction to computer Integrated Manufacturing (CIM)

Let Tc = the operation cycle time at a given machine or workstation,

Tno = the nonoperation time associated with the same machine.

no = the number of separate operations through which the work unit must be routed

Tsu = Setup time required to prepare each production machine for the particular product. If we assume batch production, then there are Q work units in the batch.,

Given these terms, we can define manufacturing lead time as

MLTj = where

MLTj = manufacturing lead time for part or product j (min).

Tsuji = setup time for operation i (min) for the product j,

Qj = quantity of part or product in the batch (pc),

Tcji = operation cycle time for operation i (min/pc),

Tnoji = nonoperation time associated with operation i (min), and

i indicates the operation sequence in the processing; i = I, 2,... noj

ojn

i

nojicjijsuji TTQT1

)( -----------11

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 47

Page 48: Introduction to computer Integrated Manufacturing (CIM)

To simplify and generalize the model,

let us assume that all setup times, operation cycle times, and non operation times are equal for the noj machines.

Further, let us suppose that the batch quantities of all parts or products processed through the plant are equal and that they are all processed through the same number of machines, so that noj = no , With these simplifications, Eq. becomes:

MLT = no (Tsu + QTc + Tno)

where

MLT = manufacturing lead time,

no = number of operations,

Tsu = setup time,

Q = batch quantity,

Tc = cycle time per part, and

Tno = non-operation time

-----------12

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 48

Page 49: Introduction to computer Integrated Manufacturing (CIM)

• For a job shop in which the batch size is one (Q = 1), Eq. (1.12) becomes

MLT=no(Tsu+TC+Tno)------------ (1.13)

For mass production, the Q term in Eq. (1.12) is very large and dominates the other terms.

In the case of quantity type mass production in which a large number of units are made on a single machine (no =1). The MLT simply becomes the operation cycle time for the machine after the setup has been completed and production begins.

MLT = QxTc ------------1.14 4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 49

Page 50: Introduction to computer Integrated Manufacturing (CIM)

For flow line mass production, the entire production line is set up in advance. Also, the non operation time between processing steps is simply the transfer time Tr

to move the part or product from one workstation to the next. The station with the longest operation time sets the pace for all stations:

MLT =no(Tr +Max To) = noTc --------------1.15

Since , (Tr +Max To) = Tc (1.5)

Since the number of stations is equal to the number of operations (n = no) Eq. (1.15) can also be stated as

MLT =n(Tr +Max To) = nTc --------------1.16

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 50

Page 51: Introduction to computer Integrated Manufacturing (CIM)

A certain part is produced in a batch size of 100 units. The batch must be routed through five operations to complete the processing of the parts. Average setup time is 3 hr/operation, and average operation time is 6 min . Average non operation time due to handling, delays, inspections, etc., is 7 hours for each operation. Determine how many days it will take to complete the batch, assuming the plant runs one 8-hr shift/day.

Solution: Given:

Q = 100 units

no = 5

Tsu = 3hr/operation

Tc = 6 min

Tno = 7 hr/operation

The manufacturing lead time is computed from Fq

MLT = no (Tsu + QTc + Tno)

MLT = 5(3 + 100 X 0.1 + 7) = 100 hours

At 8 hr/day. this amounts to L00/8 = 12.5 days.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 51

Page 52: Introduction to computer Integrated Manufacturing (CIM)

A certain part is routed through six machines in a batch production plant. The setup and operation times for each machine are given in the table below. The batch size is 100 and the average non operation time per machine is 12 hours. Determine (a) manufacturing lead time and (b) production rate for operation 3.

Solution: Given:

Q = 100 units

no = 5

Tsu = 3hr/operation

Tno = 12hr/machine

The manufacturing lead time is computed from Fq

MLT =

ojn

i

nojicjijsuji TTQT1

)(

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 52

Page 53: Introduction to computer Integrated Manufacturing (CIM)

A certain part is routed through six machines in a production plant. The operation times for each machine are given in the table below. Suppose the part is made in very large quantities on a production line in which an automated work handling system is used to transfer parts between machines. Transfer time between stations = 15 s. The total time required to set up the entire line is 150 hours. Assume that the operation times at the individual machines remain the same. Determine (a) manufacturing lead time for a part coming off the line.(b) production rate for operation 3. and (c) theoretical production rate for the entire production line.

Solution: Given:

a) MLT = no(Tr+MaxTo)

b) Rp3 = 60/Tp ; But Tp = Tc = To

c) Rp = 60/Tp; But Tp = Tc ; But Tc = Tr+Max To

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 53

Page 54: Introduction to computer Integrated Manufacturing (CIM)

Work-In-Process

Work-in-process (WIP) is the quantity of parts or products currently located in the factory that either are being processed or are between processing operations.

WIP is inventory that is in the state of being transformed from raw material to finished product.

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 54

Page 55: Introduction to computer Integrated Manufacturing (CIM)

Work-In-Process An approximate measure of work-in-process can be obtained from the following, using terms previously defined:

WIP =

where WIP = work-in-process, pc; A = availability, U = utilization, PC = plant capacity, pc/wk; MLT = manufacturing lead time, hr; Sw = shifts per week, Hsh = hours per shift, hr/shift

w sh

AU PC MLT

S H

Hareesha N G, Dept of Aero Engg, DSCE, Blore

Page 56: Introduction to computer Integrated Manufacturing (CIM)

TIP Ratio

The TIP ratio measures the time that the product spends in the plant relative to its actual processing time.

It is computed as the total MLT for a part divided by the sum of individual operation time for the plant.

oT

MLTTIP

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 56

Page 57: Introduction to computer Integrated Manufacturing (CIM)

The average part produced in a certain batch manufacturing plant must be processed sequentially through six machines on average. Twenty (20) new batches of parts are launched each week. Average operation time = 6 minutes, average setup time = 5 hours, average batch size= 25 parts, and average non operation time per batch = 10 hr/machine. There are 18 machines in the plant working in parallel. Each of the machines can be set up for any type of job processed in the plant. The plant operates an average of 70 production hours per week. Scrap rate is negligible. Determine (a) manufacturing lead time for an average part, (b) plant capacity, and (c) plant utilization, (d) Determine the average level of work-in-process in the plant.

a) MLT = no( Tsu + QxTc + Tno )

b) PC = A.U. n.SwHs.Rp/no

c) U = Q/PC

d) WIP = A.U.PC.MLT/SwHs

4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 57