instructions to bidders city of richmond · instructions to bidders city of richmond contract 3055q...

83
2250090 INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA JUNE 2007

Upload: others

Post on 21-Apr-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

2250090

INSTRUCTIONS TO BIDDERS

CITY OF RICHMOND

CONTRACT 3055Q

SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA

JUNE 2007

Page 2: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond ii Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

TABLE OF CONTENTS

1. INTRODUCTION .................................................................................................................. 4

1.1 Introduction.................................................................................................................. 4 1.2 Definitions.................................................................................................................... 4 1.3 Availability Contract Documents.................................................................................. 5

2. INSTRUCTIONS ................................................................................................................... 5

2.1 Closing Time and Address for Delivery: ...................................................................... 5 2.2 Late Quotations ........................................................................................................... 5 2.3 Amendments/Withdrawals........................................................................................... 5 2.4 No Fax......................................................................................................................... 5 2.5 Enquiries ..................................................................................................................... 5 2.6 Errors or Omissions..................................................................................................... 6 2.7 Addenda...................................................................................................................... 6 2.8 Site Meeting ................................................................................................................ 6 2.9 Inspection of Work....................................................................................................... 6

3. SUBMISSION OF QUOTATIONS......................................................................................... 7

3.2 Form of Quotation ....................................................................................................... 7 3.3 Quotation Price............................................................................................................7 3.4 Execution of Form of Quotation................................................................................... 7 3.5 Submission Label ........................................................................................................ 8

4. DURATION OF QUOTATIONS ............................................................................................ 8

4.1 Duration....................................................................................................................... 8

5. AWARD ................................................................................................................................. 8

6. GENERAL............................................................................................................................. 9

6.1 Ownership of Documents ............................................................................................ 9 6.2 Freedom of Information Legislation............................................................................. 9 6.3 Expenses..................................................................................................................... 9 6.4 No Claims.................................................................................................................... 9 6.5 No Collusion ................................................................................................................ 9

Page 3: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond iii Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

7. FORM OF QUOTATION ................................................................................................10-17

QUOTATION ANNEXURES

APPENDIX A: LIST OF UNIT PRICES

APPENDIX B: LIST OF SUPERVISORY PERSONNEL

APPENDIX C: LIST OF SUBCONTRACTORS

APPENDIX D: LIST OF DETAILS

APPENDIX E: CONSTRUCTION SCHEDULE

APPENDIX F: UNDERTAKING OF LIABILITY INSURANCE

8. GENERAL SPECIFICATIONS ........................................................................................... 18

9. GENERAL CONDITIONS OF THE CONTRACT CCDC2 – 1994 NOT ATTACHED

10. SUPPLEMENTARY GENERAL CONDTIONS..............................................................19-26

11. SPECIFICATIONS – ATTACHED

Division 01

01010 Summary of Work 01100 General Requirements 01525 Scaffolding

Division 07

07210 Rigid Insulation 07275 Self Adhesive Membrane 07465 Preformed Metal Cladding 07535 Modified Bitumen Sheet Roofing 07600 Flashing & Sheet Metal 07900 Joint Sealants

Division 09

09900 Paint 12. DETAILS – Attached 13. NOTICE OF NO BID

Page 4: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 4 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

INSTRUCTIONS TO BIDDERS

1. INTRODUCTION

1.1 Introduction

These Instructions apply to the preparation of Quotations for the Contract, which is generally for the following:

Exterior retrofit of “East” Walls Roof Curbs Landscaping Protection Painting – Finish Schedule Clean-up Requirements

,located at 7551 Minoru Gate, Richmond, BC, Minoru Arena #1

1.2 Definitions

In these Instructions and the Form of Quotation the following definitions will apply:

“Closing Time” has the meaning set out in section 0 of these Instructions;

“Contact Person” has the meaning set out in section 0 of these Instructions;

“Contract” means the contract between the Owner and the Contractor for the performance of the Work as described in the Contract Documents;

"Contract Documents" means: (i) Agreement, Definitions and General Conditions of CCDC 2 – 1994 (ii) Supplementary General Conditions; (iii) Specifications; (iv) Drawings; and (v) Issued Addenda (if any); (vi) Instructions to Bidders; and (vii) Form of Quotation.

“Notice of Award” has the meaning set out in section of these Instructions;

"Owner" means the City of Richmond;

"Instructions" means these instructions to Bidders;

“Quotation” means a Quotation submitted in response to these Instructions;

“Bidder” means a person who submits a Quotation;

“Quotation Price” has the meaning set out in section 2.2 of the Form of Quotation;

Page 5: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 5 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

“Work” has the meaning set out in the Definitions of CCDC 2 – 1994.

1.3 Availability Contract Documents

Copies of the Contract Documents are available for review and pick-up at Front of House, Richmond City Hall, 6911 No. 3 Road, Richmond, B.C.

2.0 INSTRUCTIONS

2.1 Closing Time and Address for Delivery:

(a) Quotations must be received on or before the following date and time (the “Closing Time”)

3:00 pm Pacific Standard Time Wednesday, August 1, 2007

(b) Quotations must be delivered to the "Information Counter", Main Floor, Richmond City Hall at the following address:

The Office of the Manager - Purchasing & Risk City of Richmond 6911 No. 3 Road Richmond, B.C. V6Y 2C1

2.2 Late Quotations

Quotations received after the Closing Time will be returned to the Bidder unopened and will not be considered.

2.3 Amendments/Withdrawals

Quotations may be amended or withdrawn only by giving written notice delivered to the place for delivery of Quotations described in section 0 at any time prior to the Closing Time. Notices received after the Closing Time will be of no effect.

2.4 No Fax

Quotations, amendments or withdrawals sent by FAX will not be accepted.

2.5 Enquiries

All enquiries related to this Quotation should be submitted in writing to the person named below (the “Contract Person”):

Contract:

Sheryl Hrynyk, Supervisor Phone: 604-276-4135 Purchasing Email: [email protected]

Page 6: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 6 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

City of Richmond 6911 No. 3 Road Richmond, B. C. V6Y 2C1

Technical: Aqua-Coast Engineering Ltd. Phone: 604-542-5532 Email: [email protected] and Ricardo T. Soliven, AScT Phone: 604-244-1237 Project Coordinator Email: [email protected] Facilities Management

2.6 Errors or Omissions

Bidders finding inconsistencies, errors, or omissions in the Contract Documents, or having doubts as to the intent of any provision of this Quotation, should immediately notify the Contract Person. Bidders are responsible to check the Contract Documents for completeness, including checking the drawings and the specifications against the index.

2.7 Addenda

If the Owner determines that an amendment is required to these Instructions or to any of the Contract Documents, the Owner will issue a written addendum that will form part of the Contract Documents. No amendment to these Instructions or to any of the Contract Documents is effective unless contained in a written addendum. In no event may oral communications or information obtained from any source be relied upon to amend, supplement, add to or otherwise alter any of the Contract Documents. Any interpretation of, additions to, deletions from, or any other corrections to the Contract documents, will be issued as written addenda by the City of Richmond. It is the sole responsibility of the potential bidders to check with the City of Richmond’s and/or BC Bid to ensure that all available information has been received prior to submitted a Quotation.

2.8 Site Meeting

The Owner will host a site meeting on Wednesday, July 18th at 10:00 a.m. local time.. Bidders are strongly encouraged to attend the site meeting. By submitting a Quotation, all Bidders will be deemed to have received all of the information as would have been obtained by a contractor who attended the site meeting and who is qualified to undertake the Work as described in the Contract.

2.9 Inspection of Work

Bidders have the responsibility to conduct their own inspection of the place of the work and to determine all factors relating to the place of the work that will affect the performance of the work, including issues such as access to the place of Work, conditions such as weather and availability of labour and any and all matters which are referred to in the Bid Documents which

Page 7: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 7 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

are necessary for the full and proper completion of the work and the conditions under which is will be performed. By submitting a Quotation the Bidder will be deemed to have undertaken any such inspection required, and will be deemed to confirm that with respect to such matters it is in no way relying on any information or representative from the Owner, or any representative of the Owner.

3. SUBMISSION OF QUOTATIONS

3.1 Quotation Summary Sheet

Bidders should complete and include the Quotation Summary Sheet showing the Bidder’s name, address and telephone number.

3.2 Form of Quotation

Bidders must submit the following as part of a Quotation:

(a) a completed Form of Quotation, including the following completed Appendices:

(1) Appendix A: List of Unit Prices

(2) Appendix B: List of Supervisory Personnel;

(3) Appendix C: List of Subcontractors;

(4) Appendix D: List of Drawings;

(5) Appendix E: Proposed Construction Schedule;

(6) Appendix F: Undertaking of Insurer to provide Comprehensive Liability Insurance as described in Appendix F;

3.3 Quotation Price

The Quotation Price will represent the entire cost to the Owner of the completed Work, and will, subject to express provisions in the Contract Documents, include the cost of all labour, materials and equipment required to perform and complete the Work in accordance with the Contract Documents.

3.4 Execution of Form of Quotation

The Form of Quotation must be signed by an authorized signatory of the Bidder as follows:

(b) Signatures must be in original handwriting;

(c) If the Bidder is a partnership or joint venture then the name of the partnership or joint venture and the name of each partner or joint venturer must be included,

Page 8: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 8 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

and each partner or joint venturer must sign personally; if a partner or joint venturer is a corporation then such corporation must sign as indicated below; and

(d) if the Bidder is a corporation then the full name of the corporation must be included, together with the names and signatures of authorized signatories

3.5 Submission Label

Quotations should be delivered in a sealed envelope or package clearly marked with 3055Q, Supply and Installation of East Wall partial Retrofit – Minoru Arena and the name of the Bidder.

4. DURATION OF QUOTATIONS

4.1 Duration

After the Closing Time, Quotations will remain valid and irrevocable as set out in paragraph 5 of the Form of Quotation.

5. AWARD

5.1 Award

The Owner reserves the right to:

(a) accept any Quotation;

(b) reject any and all Quotations, including Quotations which are incomplete, illegible or obscure, or that contain additions not called for, erasures, alterations, errors or irregularities of any kind, or contain prices which appear to be unbalanced so as likely to adversely affect the Owner;

(c) waive any minor informalities or irregularities in a Quotation, including if it contains a defect or fails in some way to comply with the requirements of the Instructions, which in the sole discretion of the Owner is not material, and accept the Quotation;

(d) accept any Quotation which the Owner determines in its judgment to be most advantageous, including a Quotation that is not the lowest price Quotation, having regard for all the information as called for by the Contract Documents; and

(e) accept all or any part of a Quotation unless stated otherwise by the Bidder within its submitted Quotation.

Page 9: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 9 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

6. GENERAL

6.1 Ownership of Documents

All documents submitted to the Owner in response to these Instructions become the property of the Owner and will not be returned to Bidders.

6.2 Freedom of Information Legislation

Bidders are advised that Quotations are subject to the Freedom of Information and Privacy Act.

6.3 Expenses

Bidders are solely responsible for their own costs and expenses in preparing and submitting Quotation and participating in this Quotation process.

6.4 No Claims

The Owner and its representatives, agents, consultants and advisors will not be liable to any Bidder for any claims, whether for costs, expenses, losses or damages, or loss of anticipated profits, or for any other matter whatsoever, incurred by the Proponent in preparing and submitting a Quotation.

6.5 No Collusion

By submitting a Quotation, the Bidder, and each firm, corporation or individual member of the Bidder represents and confirms to the Owner that the Bidder has prepared its Quotation without any connection, knowledge, comparison of figures, or arrangement with any other person or persons submitting a Quotation for this Contract, and that this Quotation is in all respects fair and without collusion or fraud.

Page 10: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 10 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

FORM OF QUOTATION

RE: 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

Manager - Purchasing & Risk City of Richmond 6911 No. 3 Road Richmond, B.C. V6Y 2C1 1. I/We, the undersigned:

1.1 have carefully read and examined all of the Contract Documents, including the Instructions to Bidders, Form of Quotation (including all Appendices), the Agreement, General Conditions of the Contract, Supplemental Conditions of the Contract, Specifications, Drawings and Addenda #_____________(list);

1.2 have carefully examined all conditions at the place of the Work, including as appropriate and without limitation, the nature of the ground and sub-soil and the means of access;

1.3 have full knowledge of the Work required and of the materials to be furnished and used;

1.4 have complied with the Instructions to Bidders; and 2. Accordingly, I/we hereby offer:

2.1 to perform and complete the all of the Work as described in the Contract Documents and provide all necessary labour, plant, equipment, tools and materials, as set forth and in strict accordance with the Contract Documents, and on the terms set out in the Contract Documents;

2.2 for the price (the “Quotation Price”) of $____________ INCLUSIVE OF GST; and

2.3 to achieve substantial performance of the Work within ________________ (insert completion time in weeks following award of the Contract).

3. I/We confirm that the Quotation Price includes all cash allowances referred to on the Drawings and Specifications and listed in the Appendices, and all applicable duties, taxes, and handling charges incidental to the Work.

4. I/We confirm that the following appendices are attached to and form part of this Quotation:

(a) Appendix A: Schedule of Prices;

(b) Appendix B: List of Supervisory Personnel;

Page 11: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 11 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

(c) Appendix C: List of Subcontractors;

(d) Appendix D: List of Details;

(e) Appendix E: Proposed Construction Schedule;

(f) Appendix F: Undertaking Of Liability Insurance;

5. I/We confirm that this Quotation will be open for acceptance for a period of 60 calendar days from the day the day following the Closing Date. If within this period the Owner delivers a written notice by which the Owner accepts our Quotation (“Notice of Award”), I/we will, within 14 days of receipt of the Notice of Award deliver to the Owner:

(a) certified copies of all insurance policies and certificates required and specified in the Contract Documents; and

(b) a signed copy of the Contract Documents.

6. I/We agree that, if we receive a written Notice of Award and fail to deliver the documents as required by paragraph 5 of this Form of Quotation, then such failure shall be deemed to be a failure to enter into the Contract, and the Owner may award the Contract to another party. I/We further agree that, as full compensation on account of damages suffered by the Owner because of such failure or refusal, and not by way of penalty, the Quotation Security shall be forfeited to the Owner.

Dated this day of 20

Bidder: _____________________________________________ Full legal name of Corporation, Partnership or Individual _____________________________________________ Authorized Signatory

Page 12: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 12 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

APPENDIX A: LIST OF UNIT PRICES

The following are our Unit Prices for the units of work listed hereunder. The Unit Prices listed apply to performing the units of work only during the time scheduled for such work in the project schedule. These prices do NOT include Value Added Taxes.

Unit Price ($) Unit of Work Addition Deletion Supply and install timber and products (All Inclusive of Labour, material and markups): Supply and install new rigid insulation, board size and type as per Section -07210 – Rigid Insulation. Pressure Washing. Supply and install new Preformed Metal Cladding per Section -07465 – Preformed Metal Cladding. Supply and Install new 3x12 rough sawn fascia c/w fasteners. Labour Rates: Working Foreman (T.Q.) Carpenter (T.Q.) Carpenter (Non-T.Q.) Carpenter Helper Labourer (skilled) Caulking Applicator Roofer Flashing Installer Painter Markup, overhead and profit applicable to unallocated subcontractors. Note: All unit rates are to include all mark ups for overhead and profit.

$ /BOARD (40 SF) $ /100SF $ /SF $ /LF $ /HR $ /HR $ /HR $ /HR $ /HR $ /HR $ /HR $ /HR $ /HR %

(If Appendix “A” is not used, put “Not Applicable” and initial the bottom of the page)

Page 13: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 13 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

APPENDIX B: LIST OF SUPERVISORY PERSONNEL

The Bidder will carry out the work covered by this Contract under the direction of the following supervisory personnel employed by the Bidder:

NAME POSITION ON THIS CONTRACT

(If additional space is required, use reverse side of this page.)

Page 14: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 14 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

APPENDIX C: LIST OF SUBCONTRACTORS

The undersigned agrees that the subcontractors shown herein is the list of subcontractors that the undersigned proposes to use to carry out those parts of the work shown on the list and, subject to their approval by the Owner, the undersigned agrees to so employ the listed subcontractors and no others in their stead. This listing is not intended to be inclusive of all trades required to perform the Work.

ITEM OF WORK NAME OF SUB-CONTRACTOR VALUE OF WORK

(If additional space is required, use reverse side of this page.)

Page 15: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 15 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

APPENDIX D: LIST OF DETAILS

SHEET NO. TITLE IN1 Drawing Index

CA1 Construction Assemblies

1 East Wall Plans

2 Wall/Roof Interface – Type 1

3 Wall/Roof Interface – Type 2

4 Scupper

5 Base of Wall at Overhang

6 Base of Wall at Foundation

7 Base of Wall at Slab

8 Inside Corner

9 Inside Corner Termination

10 Outside Corner

11 Outside Corner Termination

12 Steel Door - Head

13 Steel Door - Jamb

Page 16: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 16 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

APPENDIX E: CONSTRUCTION SCHEDULE

Attach and submit a planned work schedule in a Bar Chart format by weeks of construction showing:

(a) the start and completion of each major element or phase of the Work;

(b) the activity of each major sub-trade; and

(c) the time to achieve Substantial Performance of the Work.

Page 17: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 17 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

APPENDIX F: UNDERTAKING OF LIABILITY INSURANCE

City of Richmond 6911 No. 3 Road Richmond, B.C. V6Y 2C1 Dear Sirs:

We, the undersigned

do hereby, undertake and agree to insure the Contractor in the amount of $5,000,000 Comprehensive Liability Insurance as outlined in the attached "Contract Documents" and agree to:

A. Name the City of Richmond, its officers, officials, agents and employees, and the projects developer and contractor as additional insured in connection with the work being proposed by the Contractor.

B. State that such policy applies to each insured in the same manner and to the same extent as if separate policy had been issued to each insured named on the policy.

C. State that the policy cannot be cancelled, lapsed, or materially changed without at least 30 days written notice of cancellation delivered to the City Clerk of the City of Richmond at 6911 No. 3 Road, Richmond, B.C. V6Y 2C1.

D. State that coverage provided by such insurance shall protect the Contractor and the City of Richmond during the performance of the works and services specified in the attached form of Quotation and specifically that the insurance required by such Quotation shall be consistent with the requirements therein

if the Contract is awarded to

EXCEPTIONS:

Dated at , British Columbia, this day of 20

BY: TITLE:

This form must be signed by the Insurance Company or an authorized Broker on behalf of the Insurance Company A SEPARATE FORM MUST BE SIGNED FOR EACH POLICY IF MORE THAN ONE POLICY.

Page 18: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 18 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

GENERAL SPECIFICATIONS

The scope of work generally includes the following:

Exterior retrofit of “East” Walls Roof Curbs Landscaping Protection Painting – Finish Schedule Clean-up Requirements

,located at 7551 Minoru Gate, Richmond, BC, Minoru Arena #1 The whole of the works must be completed no later than 5 weeks from the start of the project.

Page 19: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 19 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena

2250090

SUPPLEMENTARY GENERAL CONDITIONS

For use with CCDC2 1994 These Supplementary General Conditions modify and amend Standard Construction Document CCDC-2 - 1994 and form a part of this Contract. In the event of any conflict between the provisions of the Contract Documents and any provision of these Supplementary General Conditions, these Supplementary General Conditions shall govern.

DEFINITIONS

1. Immediately before the word “amendments” in the second line of paragraph 2, insert “written”.

GENERAL CONDITIONS OF THE CONTRACT

2. In GC 1.1.9.1:

(a) insert “• the Instructions to Bidders,” immediately after “• the Agreement between the Owner and the Contractor,” and immediately before “• the Definitions”; and

(b) insert “• Quotation Form, including all appendices,” immediately after “Supplementary Conditions” and immediately before “• the General Conditions”.

3. In GC 2.2.6, delete the words “, except with respect to GC 5.1 - FINANCING INFORMATION REQUIRED OF THE OWNER” from the second and third lines.

4. In GC 2.2.7, delete the words “, except for GC 5.1 - FINANCING INFORMATION REQUIRED OF THE OWNER,” from the second and third lines.

5. Add the following GC 3.5.2:

“The Contractor will perform the Work in compliance with the construction schedule. If, for any reason, the Work falls behind the schedule for the Work set forth in the construction schedule the Contractor shall as part of the Work either:

(a) if in accordance with the Contract Documents the delay entitles the Contractor to a time extension the Contractor shall forthwith prepare and deliver to the Consultant a revised construction schedule to the reasonable satisfaction of the Consultant indicating the revised dates for the remaining activities of the Work; or

(b) if in accordance with the Contract Documents the delay does not entitle the Contractor to a time extension then the Contractor shall take such steps as required to bring the Work back into conformity with the construction schedule.

Failure to comply with the requirements of this section shall be deemed to be a default under the Contract to which the provisions of GC 7.1.2 apply.”

Page 20: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 20 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena Supplementary General Conditions Con’t

2250090

20

6. Add the following at the end of GC 3.8.2:

“The Contractor shall not employ any Subcontractor, or change Subcontractor, without the written approval of the Owner, which approval will not be unreasonably withheld.”

7. Add the following GC 3.9.4:

“Immediately upon receiving from the Consultant a written notice stating the Consultant’s reasonable objection to the work conduct of any superintendent, foreman or worker on the Project site, the Contractor will remove such persons from the Project site.”

8. In GC 3.10, following the words “Contract Documents,” in the first line, insert “reviewed shop drawings,”.

9. Add the following at the end of GC 3.11.4:

“The shop drawings provided by the Contractor will be complete and show the entire extent of the relevant portion of the Work.”

10. Add the following GC 3.11.7:

“Upon Substantial Performance of the Work, the Contractor will submit all reviewed and revised shop drawings to the Owner as a permanent record of the Work. As of the date of issuance of a final certificate for payment, the shop drawings will be retained by the Owner as the Owner’s property.”

11. Add the following GC 3.11.8:

“The Contractor shall not proceed with the Work to which a shop drawing applies before the Consultant has reviewed and approved the shop drawing as provided by GC 3.11.5.”

12. Delete GC 5.1, including all of GC 5.1.1 and GC 5.1.2, in its entirety.

13. Add the following at the end of GC 5.2.2:

“The Contractor will identify separately, with reference to the applicable Change Order, any application for payment for Work performed pursuant to a Change Order. No payment for extras or changes will be made before the issuance of the applicable Change Order.”

14. Delete GC 5.2.6. in its entirety and insert:

“No claim shall be made for any Product which is delivered to the Place of the Work until it is incorporated into the Work and any claim for Products which are incorporated into the Work shall be supported by such evidence as the Consultant may reasonably require to estimate the value of such Products.”

15. Add the following GC 5.3.3:

Page 21: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 21 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena Supplementary General Conditions Con’t

2250090

21

“The Owner may set off from payments owing to the Contractor costs, expenses and damages the Owner incurs or suffers as a result of the Contractor’s wrongful or negligent act or omission, or which the Owner incurs on the Contractor’s behalf.”

16. Add the following GC 5.3.4:

“The Owner may, in addition to other holdbacks as provided by the Contract Documents, hold back an amount equal to any lien which has been filed with respect to the Work, plus 10% as security for costs. The Owner may, at its option, after five days written notice to the Contractor, pay such amount into court to discharge the lien. If the lien is discharged without payment of the holdback into court, then the Owner shall pay such holdback to the Contractor, without interest.”

17. Add the following GC 5.4.5:

“In addition to builders lien holdbacks, the Owner may retain holdbacks to cover deficiencies in the Work, in an amount equal to twice the amount the Consultant estimates as the total cost to complete the deficiencies.”

18. Add the following GC 5.4.6:

“The Contractor’s application for Substantial Performance of the Work will constitute a waiver by the Contractor of all claims except those previously made in writing to the Owner.”

19. Delete GC 5.5.3 in its entirety.

20. Add the following GC 5.7.5:

“The Consultant will not issue the final certificate for payment until the Contractor has submitted a release from the Workers Compensation Board covering work of the Contract to completion, plus inspections and approval certificates of all authorities with jurisdiction.”

21. Add the following GC 5.7.6:

“The issuance of a final certificate for payment in no way relieves the Contractor from correcting defects or deficiencies not apparent at the time the certificate is issued.”

22. Add the following GC 6.1.3:

“Whenever the Consultant delivers a written request to the Contractor for a quotation of a possible change, the Contractor will within 10 days after receiving such request provide to the Consultant in writing a quotation of the value of the contemplated change (increase or decrease) and a statement of the effect, if any, of the contemplated change on the construction schedule. The Contractor’s written quotation and statement will be interpreted to include all costs, including

Page 22: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 22 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena Supplementary General Conditions Con’t

2250090

22

any indirect or “impact” costs, and all effects on the construction schedule. The Contractor will not be entitled to claim on account of any cost or schedule effect not included specifically in the quotation and statement unless the quotation and statement specifically itemize and describe such cost or schedule effect.”

With respect to any change, the allowance for overhead shall be 10% and the allowance for profit shall be 5%, each applied to the cost of the change, (including indirect costs, if any) as described in the previous paragraph, as full payment owing for the change.

23. Add the following at the end of GC 6.5.4:

“No claim for additional payment arising from a delay will be payable to the Contractor unless the Contractor has prepared, or caused to be prepared, records of all Work and the costs of the Work, on a daily basis as the Work proceeds, and submits such records in support of the claim.”

24. Add the following GC 6.5.6:

“The Owner may, at any time, give written direction to the Contractor for the Contractor to accelerate the Work, in which event the Contractor shall use reasonable best efforts to proceed with the Work more quickly, which may include hiring additional labour and equipment and/or working additional hours or shifts. If at the time of such direction by the Owner the Contractor is behind the approved construction schedule due to a cause within the control of the Contractor, then the cost of such acceleration shall be borne by the Contractor. If at such time the Contractor is not behind the construction schedule, or is not behind due to a cause within the Contractor’s control, then the cost of such acceleration shall be for the account of the Owner.”

25. Add the following GC 6.5.7:

“If, for any reason, the Contractor deems it necessary to accelerate the Work, then the Contractor shall provide written notice of its intention to accelerate at least 24 hours prior to doing so.”

26. Add the following GC 6.5.8:

“In the event of a delay which results in a stoppage of the Work, the Contractor shall take all reasonable steps to protect the Work for the entire period of the delay. The cost of such protection shall be paid as follows:

(i) if under 6.5.1, or 6.5.2, the Owner will pay,

(ii) if under 6.5.3 the Contractor will pay.”

27. In GC 7.1.2, delete the words “and if the Consultant has given a written statement to the Owner and Contractor that sufficient cause exists to justify such action” from the second and third lines.

Page 23: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 23 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena Supplementary General Conditions Con’t

2250090

23

28. Delete GC 7.2.3.1.

29. In GC 9.2.4, following the word “costs,” in the second line, insert “and posting security in an amount and in a form reasonably satisfactory to the Owner,”.

30. Delete GC 9.3.2.

31. Delete GC 9.3.3.

32. Delete GC 9.3.4.

33. In GC 9.3.5, delete the words “which were not disclosed by the Owner, as required under paragraph 9.3.2, or which were disclosed but have not been dealt with as required under paragraph 9.3.4,”.

34. In GC 9.3.5.3, following the words “stopping the Work” in the first line, insert “if necessary”.

35. Add the following at the end of GC 10.2.1:

“This Contract shall be construed according to the laws of British Columbia. The Contractor will undertake all Work in full compliance with all applicable building, environmental and other laws, including without limitation building codes, regulations and bylaws applicable in the City of Richmond.”

36. In GC 10.2.5, delete the words “knowing it to be” from the second line.

37. Delete GC 10.4 in its entirety and substitute the following:

“The Contractor agrees that it shall at its own expense procure and carry or cause to be procured and carried and paid for, full Workers' Compensation Board coverage for itself and all workers, employees, servants and others engaged in or upon any work or service which is the subject of this Contract. The Contractor agrees that the Owner has the unfettered right to set off the amount of the unpaid premiums and assessments for such Workers' Compensation Board coverage against any monies owing by the Owner to the Contractor. The Owner shall have the right to withhold payment under this contract until the Workers' Compensation Board premiums, assessments or penalties in respect of work done or service performed in fulfilling this contract had been paid in full.

The Contractor agrees that it is the “prime contractor” for the purposes of the Workers Compensation Act (British Columbia). The Contractor shall have a safety program acceptable to the Workers' Compensation Board and shall ensure that all Workers' Compensation Board safety rules and regulations are observed during performance of this Contract by the Contractor and by all of its employees, workers, material men subcontractors, and others engaged in the performance of this Contract. Prior to commencement of construction, the Contractor shall complete and file a "notice of project" with the Workers' Compensation Board in accordance with the Occupational Health and Safety

Page 24: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 24 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena Supplementary General Conditions Con’t

2250090

24

Regulation and shall provide a copy of the same to the Owner confirming that the Contractor will be the prime contractor responsible for coordination of safety and health under the Workers Compensation Act (British Columbia).

The Contractor shall provide the Owner with the Contractor's Workers' Compensation Board registration number and a letter from the Workers' Compensation Board confirming that the Contractor is registered in good standing with the Workers' Compensation Board and that all assessments have been paid to the date thereof prior to the Owner having any obligation to pay the Contractor any monies under this Contract.

The Contractor shall indemnify the Owner and hold harmless the Owner from all manner of claims, demands, costs, losses, penalties and proceedings arising out of or in any way related to unpaid Workers' Compensation Board assessments owing from any person or corporation engaged in the performance of this Contract or arising out of or in any way related to the failure to observe safety rules, regulations and practices of the Workers' Compensation Board, including penalties levied by the Workers' Compensation Board.”

38. Delete GC 11.1.1 in its entirety and substitute the following:

“The Contractor shall, at his own expense, through the terms of the contract secure, maintain, and pay for the following coverage’s:

(a) Comprehensive General Liability Insurance with a limit of not less than $5,000,000 inclusive per occurrence for bodily injury and property damage and $5,000,000 for personal injury. The policy or policies shall cover all premises and operations necessary or incidental to the performance of this agreement and include but not necessarily be limited to the following coverages:

(1) contractual liability assumed under this Contract;

(2) contingent employer's liability with respect to operations of sub-contractors;

(3) owner's protective liability;

(4) cross liability;

(5) automobile liability (non-owned, hired);

(6) completed operations liability 24 months after completed operations; and

(7) voluntary medical payments.

(b) "Broad Form" Property Damage Insurance covering all risks of physical loss or damage on an occurrence basis, including loss of use of property, and including losses or damage from flood or earthquake. The coverage provided shall amount to no less than 80% of the total value of the work done and material

Page 25: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 25 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena Supplementary General Conditions Con’t

2250090

25

delivered to the site, payable to the Owner and Contractor as their interests may appear, and protecting each in such terms as will preclude subrogation claims by the insurer against anyone insured thereunder.

The Owner, its officers, officials, and employees shall be added as additional named insured on all such policies. All such insurance provided by these policies shall be primary regardless of any insurance or self insurance that may be enforced at the time of any loss or claim that insures the Owner, its officers, officials, and employees.

The policy or policies shall be underwritten by a responsible insurance company or companies licensed to do business in the Province of British Columbia and who meet with the reasonable approval of the Owner. Prior to the commencement of the work defined by this Contract, the Contractor shall furnish the Owner, through the Owner’s Office of the Manager - Purchasing and Insurance, a certified original copy of all such policies as evidence that such insurance is in force. The Contractor agrees that such insurance policies cannot be cancelled, lapsed, or materially changed without at least 30 days notice to the Owner.

Maintenance of such insurance and the performance of the Contractor of its obligations under this clause shall not relieve the Contractor of liability under the indemnification provisions here and above set forth. The foregoing insurance provisions shall not limit the insurance required by municipal, provincial, or federal law.

It shall be the full responsibility of the Contractor and the Owner respectively to determine what additional insurance coverage, if any, is necessary and advisable for its own protection and/or to fulfill its obligations under this Contract. Any such additional insurance shall be provided and maintained by the Contractor and/or the Owner at their own expense.

It is understood that this Contract is strictly between the Contractor and the Owner and in no way shall be interpreted as an employment relationship between the Owner, the employees of the Contractor and/or its agents and/or their employees, and/or its Contractors and/or their employees. Should any differences arise between the Contractor and any of its employees and/or its agents and/or their employees and/or their contractors and/or their employees, they shall be resolved directly between them and the Contractor in this connection.”

39. Delete GC 11.2.1 in its entirety and substitute the following:

“The Contractor will, prior to commencement of the Work, furnish

(1) a Performance Bond in the amount of 50% of the Contract Price covering the faithful performance of the Contract, including the corrections after completion, and the payment of all obligations arising under the Contract, on a form approved by the Insurance Bureau of Canada, and with such sureties as the Owner may approve.

(2) a Labour and Materials Payment Bond in the amount of 50% of the Contract Price, covering the prompt payment of all claimants and all

Page 26: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

City of Richmond 26 Contract 3055Q Supply and Installation of East Wall Partial Retrofit – Minoru Arena Supplementary General Conditions Con’t

2250090

26

labour and material used, or reasonably required for use, in the performance of the Contract, including all extra works and the corrections after completion, on a form approved by the Insurance Bureau of Canada, and with such sureties as the Owner may approve.”

40. Delete GC 12.1 in its entirety and substitute the following:

“The Contractor will indemnify, hold, and save harmless the Owner from and against all claims, losses, damages, costs, actions, and other proceedings, made, sustained, brought or prosecuted in manner, based upon, occasioned by, attributable to any injury, including death, property damage, infringement, or damage arising from any act or omission of the Contractor, his employees, officers, volunteers, servants, or agents or persons from whom the Contractor has assumed responsibility in the performance or purported performance of this agreement.”

41. In GC 12.2.1.4, delete the words “a period of 6 years from the date of Substantial Performance of the Work, as set out in the certificate of Substantial Performance of the Work, or within such shorter period” from the first and second lines and substitute “such periods”.

Page 27: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Summary of Work Section 01010 7551 Minoru Gate Page 1/4 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL The Contractor shall furnish all labour, materials and equipment to perform the partial retrofit work on the ‘east’ walls of the building located at Minoru Arena #1, 7551 Minoru Gate, Richmond, BC. The extent of the work is shown on the details and specifications prepared by the Consultant.

2 SCOPE OF WORK

Without limiting the generality of the foregoing, the following items are included in the scope of work of this Contract:

.1 Scope of Work - General

.1 Generally, retrofit work will be carried out at, but not limited to, the following locations: 1. Exterior of ‘East’ Walls 2. Roof Curbs 3. Landscaping Protection 4. Painting - Finish Schedule 5. Clean-up Requirements

.2 Exterior of ‘East’ Walls

.1 Remove and dispose of existing parapet cap flashing, misc. flashing, etc.

.2 Remove and dispose of existing scuppers and downspouts.

.3 Remove and dispose of existing fascias and miscellaneous wood trim on second level at downspouts.

.4 Remove existing steel doors. Prepare, paint and store in a secure location prior to reinstallation. Temporarily secure opening while door is removed.

.5 Prepare existing concrete block walls. Pressure wash to remove any debris, organic materials, moss, dirt, etc. Adjust the pressure for maximum cleaning without damage to the masonry. Start pressure washing at the top and work down to wash the debris down the walls and not onto previously cleaned areas. Angle the spray away from doors and other openings.

.6 Allow the wall to dry to maximum 12% moisture content. Inspect for any visible cracks in the concrete block or cracks in the mortar at joints.

.7 Repoint the joints with mortar and fill cracks with crack filler as required.

.8 Install new steel sub-girts to wall. Sub-girts and anchors to be as specified in section 07465 Preformed Metal Cladding.

.9 Install two layers of new rigid insulation - one base layer of 2”thick insulation board and a second layer of 1”thick insulation board. Refer to Section 07210 – Rigid Insulation for full description and installation method. Joints in insulation board are to be offset by 50% of board length. Glue the base layer of to the concrete block; then glue the second layer to the base layer. Glue is to be compatible with substrates and as recommended by the insulation manufacturer.

.10 Install required head and sill flashings, roof cap flashings and miscellaneous flashings, etc. in accordance with the details and the specifications.

Page 28: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Summary of Work Section 01010 7551 Minoru Gate Page 2/4 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

.11 Supply and install new preformed metal cladding to exterior walls. Install related flashings where detailed and where required. Refer to detail CA1 for wall assemblies and Section 07465 – Preformed Metal Cladding for fasteners, installation and further information.

.12 Reinstall existing steel doors into original opening. Refer to section 09900 Paint.

.13 Install urethane sealant at the door frame/cladding interfaces.

.14 Supply and install new rough sawn 3x12 fascia and plywood backing as per details. Paint or stain the new fascia. Fascia size is to match existing.

.15 Supply and install new preformed metal scuppers and downspouts at original locations. Size, shape and finish of new scuppers are to match existing. Scuppers are not to be added to any new locations unless directed by the Consultant. Fasten downspouts with stainless steel gasketted screws and washers. Install prefinished metal straps at maximum 10’ intervals. Strap colour is to match cladding. Connect new downspouts to existing downspouts located at the ground level.

.16 The Contractor is responsible for reinstallation of all items attached or fixed directly to the work areas.

.17 Caulk and seal at interfaces between dissimilar materials and where indicated on details.

.18 Paint fascias, miscellaneous trim, misc. metals, doors and frames, etc. Refer to Section 09900 - Paint.

.19 For clean-up requirements, refer to part 2.5 – Clean-up Requirements below.

.2 Roof Curbs .1 NOTE: Existing roofing is to remain in place and is not to be disturbed

except at scupper locations. .2 Remove and dispose of existing cap flashings and scuppers at roof curb only

in retrofit areas of east elevation. .3 Install new plywood backing as per details. Fasteners are to be non-corrosive. .4 Prime the existing substrates. Supply and install new 2 ply SBS 180 torch on

cap sheet membrane onto roof surfaces and over roof curbs and parapets as shown on the details. Approved Suppliers are IKO, Soprema and preapproved alternates.

.5 Install 26 gauge sloped metal roof cap and counter flashings over the new wood blocking and existing roof parapet framing as shown in details. New cap flashing segments to be joined by standing seams. Tie in new flashings to existing flashings with standing seams. Maintain watertight condition at joints and corners.

.6 Refer to part 2.2.14 for installation of new fascia.

.7 Supply and install new metal scuppers. Size, shape and finish to match existing scuppers.

.3 Landscaping Protection

Page 29: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Summary of Work Section 01010 7551 Minoru Gate Page 3/4 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

.1 Landscaping must be protected during construction. Damage to landscaping resulting from the performance of the Work will be paid for by the Contractor.

.2 Damaged shrubs and other plantings are to be replaced like for like.

.3 Where shrubs and other plantings have been damaged, and therefore require replacement, then it is the responsibility of the Contractor to provide for the necessary soil preparation and supply and installation of shrubs and other plantings.

.4 Construction debris must to be removed and cleaned from all landscaped areas on a daily basis.

.4 Painting – Finish Schedule (Refer to Section 09900)

.1 Paint the following surfaces: .1 Exterior:

Steel exit door and frame. Wood fascia, misc. trim boards, metal flashings, gutters and

downspouts, etc. .2 Interior:

Interior surfaces affected by removal/replacement of door. Touch-up finish to interior jambs, sills and heads and miscellaneous wall and/or ceiling surfaces.

.5 Clean-up Requirements:

.1 Disposal Requirements: .1 Conduct cleaning and disposal operations to comply with local and

provincial codes, ordinances, regulations and anti-pollution laws. .2 Dispose of rubbish, debris and waste materials at periodic intervals

away from the site in a legal manner. .3 Store volatile waste in covered, fireproof, metal containers and

remove from premises at the end of each working day. .4 Prevent accumulation of waste which creates hazardous conditions.

.2 During construction:

.1 Execute daily cleaning to keep the Work, the site and adjacent properties free from accumulations of waste materials, rubbish and wind blown debris.

.2 Provide on-site containers / bins for the collection of waste materials, debris and rubbish. Remove and dump as required to maintain an orderly, neat site. Do not allow overflow of debris onto adjacent property under any condition.

.3 Maintain the Work, including roof and building systems at least on a daily basis, free from accumulations of waste material and debris.

.4 Schedule cleaning operations so that the resulting dust and debris and other contaminants will not fall on wet, newly painted surfaces nor contaminate building systems.

.5 Clean exterior spaces prior to the start of finish painting and continue

Page 30: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Summary of Work Section 01010 7551 Minoru Gate Page 4/4 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

cleaning on an as-needed basis until painting is finished. .3 Final cleaning:

.1 Employ only skilled workers for the final cleaning.

.2 Remove all paint spots, stains, rubbish, debris, tools and equipment from all areas and broom clean.

.3 Remove grease, dust, dirt, stains, labels, fingerprints and other foreign materials from interior and exterior finished surfaces.

.4 Remove debris and surplus material from accessible concealed spaces.

- END OF SECTION -

Page 31: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 General Requirements Section 01100 7551 Minoru Gate Page 1/6 Richmond, BC Project No. 2331 May 1, 2007

Aqua-Coast Engineering Ltd.

1.0 Permits .1 The Contractor will apply for and obtain, on behalf of the Owner, the required

Building Permit. .2 Any additional permits required for the performance of the Work including but

not limited to rental of City property, street meter rental, hoarding permits, etc. will be the responsibility of the Contractor.

2.0 Regulatory Requirements

.1 All work shall be performed in accordance with the BC Building Code 2006

including all published revisions, addenda and bulletins. 3.0 Protection

.1 Construction Safety

The Contractor will: .1 Be responsible for all safety measures in connection with all construction

work particularly where workers are exposed to mould during the removal of decayed materials.

.2 Comply with all municipal, provincial and federal laws concerning construction safety.

.3 Provide, maintain and remove on completion, barriers, hoarding and warning signs for the protection of the workers and the public as approved by the Owner and in accordance with all applicable regulations.

.4 Maintain access to all exits, stairways and emergency exits for the building occupants.

.2 Hoarding

The Contractor will: .1 Provide suitable barricades or temporary fencing at ground level to the

perimeter of the work area to prevent public access to the work area. .2 Where working over a pedestrian pathway, emergency exit or roadway,

provide covered hoarding to prevent damage to property or injuries from falling objects.

.3 Maintain and remove on completion of the work.

.3 Protection of Off-Site and Public Property

.1 The Contractor will protect surrounding private and public property during the performance of the Work and be responsible for damage incurred.

.4 Protection of Building Finishes and Equipment

The Contractor will: .1 Protect existing pavements, landscaping, finished surfaces, equipment and

utilities during the performance of the work and make good any damage to the Owner’s approval at no cost to the Owners.

Page 32: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 General Requirements Section 01100 7551 Minoru Gate Page 2/6 Richmond, BC Project No. 2331 May 1, 2007

Aqua-Coast Engineering Ltd.

.2 Provide dust screens where required to localize dust generating work.

.3 Provide drop sheets and poly protection to all interior suite surfaces when working within suites.

.5 Fire Protection

The Contractor will: .1 Provide and maintain temporary fire protection equipment during the

performance of the work as required by insurance agencies or governing codes and regulations.

.2 Ensure all existing fire exits are maintained at all times.

.3 Where existing fire alarm wiring is damaged during the restoration work, arrange to have the wiring repaired immediately by the building’s fire alarm maintenance firm.

4.0 Environmental Controls

.1 Weather Enclosures

The Contractor will: .1 Provide protection against wind, rain and snow so as to maintain work,

materials, equipment and property free from injury or damage and as necessary to ensure work is performed expeditiously and in accordance with the agreed schedule.

.2 Provide scaffold mesh to vertical surfaces of scaffold. Provide tarps or shrink wrap to top of scaffolding to form a roof over the enclosure. Erect all materials in a neat and orderly manner, adequately restrained to minimize noise from wind.

.3 Maintain until the Work is complete. 5.0 Construction Aids

.1 Scaffolding

The Contractor will: .1 Provide and maintain scaffolding, ramps, ladders, platforms and

temporary stairs as required to perform the Work. All equipment must conform to WCB requirements including design and certification by a professional engineer.

.2 Scaffolding must be installed so as not to impede the cladding installation and such that the work can proceed in a continuous manner.

.3 Only use frame scaffolding. Attachment points to the building must be kept to the minimum allowable by the WCB and certifying engineer. If an alternate form of scaffolding is required to perform the work, the Contractor must review the situation with the Owner and receive written permission from him before proceeding.

.4 Locate all equipment so as not to impede access into and out of the building by its occupants.

Page 33: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 General Requirements Section 01100 7551 Minoru Gate Page 3/6 Richmond, BC Project No. 2331 May 1, 2007

Aqua-Coast Engineering Ltd.

.2 Hoisting .1 The Contractor will provide hoisting equipment as necessary to facilitate

the delivery and lifting of materials or equipment. 6.0 Temporary Facilities, Utilities

.1 The Contractor will provide and pay for a site trailer with power, telephone and

heat at a location approved by the Owner. Provide a plan table or desk and adequate space for the review of the plans and specifications by the contractor and Owner. Provide a separate room or separate trailer for use as a lunchroom and tool and equipment storage.

.2 The Contractor will make arrangements for sanitary facilities and disposal bins as required.

.3 The Owner will provide a source of potable temporary water and power. 7.0 Access & Storage

.1 Access to the site must be confirmed with the Owner through the Consultant. .2 No parking of the Contractor’s or workers’ vehicles will be permitted on site. .3 Areas for storage of materials must be coordinated with the Owner.

8.0 Working Periods

.1 The Contractor will attend the site during normal daytime working periods, as

permitted by the City regulations, and no restriction will be made on the general continuity of the work. If a major restriction on operation is required due to unforeseen circumstances, it shall be recorded and signed for by the Owner’s representative and subject to additional cost.

.2 No work permitted before 7:30 a.m. or after 6:00 pm on any workday. Saturday, Sunday and statutory holiday work is allowable ONLY by prior written permission of the Owner or the Owner’s representative.

9.0 Quality Control

.1 Inspections

.1 Inspections will be performed by the Consultant and all costs paid by the Owner.

.2 The Contractor will provide timely notice for items requiring the inspection of a Structural Engineer and by the Consultant.

.3 If the Contractor covers work before an inspection has been performed by the Consultant, the Consultant may order the work be uncovered for inspection at no cost to the Owner.

.4 If the Consultant suspects that any part of the work has not been completed in accordance with the Contract Documents, he may order the area to be uncovered for inspection. If any work is found that is not in accordance with the Contract Documents, the Contractor must repair the work and pay for the costs of inspection and correction.

Page 34: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 General Requirements Section 01100 7551 Minoru Gate Page 4/6 Richmond, BC Project No. 2331 May 1, 2007

Aqua-Coast Engineering Ltd.

.2 Rejected Work

.1 The Contractor will remove defective work, whether the result of poor workmanship, use of defective products or damage and has been rejected by the Consultant as failing to conform with the Contract Documents. Replace and re-execute the work in accordance with the Contract Documents at no cost to the Owners.

10.0 Clean up

The Contractor will: .1 Maintain the site in a clean condition to the satisfaction of the Owner. Debris

from the work area and surrounding areas must be removed daily. Contractor to provide a garbage bin for disposal of all waste. At no time may the building garbage bin be used. Location of the bin to be confirmed with the Consultant.

.2 Remove waste materials from the site on a regular basis.

.3 Failure by the Contractor to maintain a clean work site may result in cleaning and removal of waste materials removed at the Contractor’s expense.

11.0 Construction Sign

.1 Signage erected for any other purpose other than construction safety must receive prior approval of the Owner.

12.0 Subcontractors

.1 Subcontracting all or part of the Work will not be permitted without the prior

written consent of the Owner. .2 The Contractor will be held responsible for the work performed by any

subcontractor and will coordinate and supervise the work to ensure it is carried out in accordance with the Contract Documents.

13.0 Materials

.1 All materials will comply with the items specified in the various trade

specifications unless specific written approval has been obtained from the Consultant authorizing the use of alternate materials.

.2 All materials to be incorporated into the work will be new, not damaged or defective and of the best quality compatible with the specifications or purposes intended.

.3 Removal and reinstallation of existing materials is permitted only where identified in the specifications and scope of work.

.4 Conform to WHMIS requirements for the storage and handling of hazardous materials.

Page 35: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 General Requirements Section 01100 7551 Minoru Gate Page 5/6 Richmond, BC Project No. 2331 May 1, 2007

Aqua-Coast Engineering Ltd.

14.0 Workmanship .1 Workmanship must be of the best quality, executed by workers experienced and

skilled in the respective duties for which they are employed. The Contractor will notify the Consultant immediately if required work is impractical to produce required results.

.2 The Contractor must not employ any person unfit or unskilled to perform their required duties. The Consultant reserves the right to request dismissal from the site workers deemed incompetent, careless, insubordinate or otherwise objectionable.

.3 The Contractor must ensure cooperation of workers on site. Maintain efficient and continuous supervision.

15.0 Supervision and Coordination

The Contractor will: .1 Assign a foreman or superintendent to the project who will remain on site full

time and supervise all of the work until completion of the project. The supervisor may be a working foreman.

.2 Coordinate all work areas including storage and delivery of materials so as to produce as little disruption to the occupants of the buildings as possible and to minimize the spread of waste, debris and dust.

.3 Provide adequate supervision to ensure all work is performed in accordance with the Contract Documents and to best standards of workmanship.

.4 Maintain at the job site one copy of the contract drawings, details, specifications and addenda, shop drawings, change orders, change notices, field review reports, WCB safety program, building occupant safety program.

16.0 Schedule

The Contractor will: .1 Provide a schedule for the Owner’s review in bar chart form indicating each trade

or activity. Provide a separate line for each activity and a horizontal scale indicating the first work day in each week.

.2 Update the schedule monthly. 17.0 Final Clean Up

.1 The Contractor will ensure all work areas are adequately cleaned of all dirt and

debris and left in acceptable condition comparable to the condition prior to the start of the work.

.2 All new materials and existing materials are to be cleaned of all dirt, paint, handprints, etc.

Page 36: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 General Requirements Section 01100 7551 Minoru Gate Page 6/6 Richmond, BC Project No. 2331 May 1, 2007

Aqua-Coast Engineering Ltd.

18.0 Warranties, Record Drawings and Photographs .1 The Contractor must maintain one clean set of plans on site for the purpose of

recording all decay and deterioration, structural repairs and locations of any concealed services.

.2 The Contractor must record all observed defects and deterioration and provide a photographic record of all observations. Photos may be digital format. Provide one set of photographs or electronic media for the Owner.

.3 The Contractor must provide one set of record drawings to the Owner at the end of the project.

.4 The Contractor must provide one copy of each warranty required by the specifications to the Owner at the end of the project.

.5 The Owner may retain an additional hold back of $10,000 until all of the information listed above is provided.

- END OF SECTION -

Page 37: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Scaffolding Section 01525 7551 Minoru Gate Richmond, BC Page 1/3 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL 1. SCOPE OF WORK

1. The work in this section includes but is not limited to:

1. Designing supplying, erecting and maintaining scaffolding to facilitate restoration work including all bracing, tie backs, outriggers, guardrails, toe boards, platforms, access stairs and ladders.

2. Fabrication and installation of hoarding. 2. Performing daily safety inspections of the scaffolding throughout the progress of

the work, and maintaining the safety of the workmen and pedestrians. 3. Designing, supplying, erecting and maintaining hoarding to protect public,

workers, owners, tenants and private property from injury or damage. 4. When required, providing a weather tight enclosure for scaffolding and

maintaining required temperature with proper ventilation. 5. Obtain/provide appropriate permits, licenses, etc. as required.

2. RELATED WORK

1. Preformed Metal Cladding Section 07465 2. Flashing & Sheet Metal Section 07600

3. REFERENCE STANDARDS

1. CAN/CSA S269.2-M87, Access Scaffolding for Construction Purposes. 2. ANSI A10.8 – 1988, American National Standard for Construction and

Demolition Operations – Scaffolding – Safety Requirements. 3. British Columbia Building Code 2006 4. Workers Compensation Board of British Columbia. 5. Occupational Health and Safety Act of British Columbia.

4. SHOP DRAWINGS

1. A letter approving the erection of each section of scaffolding by a qualified registered Professional Engineer licensed to practice in the Province of British Columbia shall be on site prior to commencement of the Work.

2. If required by the Consultant, provide engineered stamped shop drawings of

scaffold design and erection prepared by a qualified registered Professional Engineer licensed to practice in the Province of British Columbia.

Page 38: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Scaffolding Section 01525 7551 Minoru Gate Richmond, BC Page 2/3 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

2 PRODUCTS

1. All scaffolding components to be free from defect and to be supplied by a qualified scaffolding supply company.

2. Scaffolding, netting, tarps, motion lights, and stairs.

3 EXECUTION 1. PROTECTION

1. Provide safety barriers and/or safety ribbon to protect passing pedestrians, owners, tenants and general public in and around the building(s) from all phases of the work.

2. Protect plants, vegetation and landscaping that might be unnecessarily damaged. 3. Provide adequate bearing pads at grade level. 4. Provide proper worker protection during scaffolding erection.

2. INSTALLATION OF SCAFFOLDING

1. Scaffold design to be adequate to accommodate imposed in-service loading, but not limited to: netting, tarpaulins, workers, tools, equipment, chutes and wind.

2. Verify that all tie-backs to existing building structure provide adequate support. 3. Verify that any areas of the existing structure used to support the scaffold can

accommodate the additional loading.

1. Provide design and installation of additional temporary shoring and support when required.

4. Do not overload the existing structure, soil, concrete slabs, patios or balconies. 5. Provide sufficient access points complete with ladders or stairs and required

railings. 6. Provide a minimum of one set of stairs and required railings. 7. Provide adequate guardrails to prevent persons from falling off the scaffolding. 8. Provide continuous, full width planking complete with cleats.

1. Clearly identify sections where planning is reduced or temporarily removed for material transportation.

Page 39: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Scaffolding Section 01525 7551 Minoru Gate Richmond, BC Page 3/3 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

9. Scaffolding netting, tarpaulins, chute and similar to be adequately secured to

scaffold. 10. Hoarding frame sections to be adequately secured in place to resist overturn and

uplift loads. 11. Hoarding covers to be adequately fastened to frames to resist scaffold dismantling. 12. Ensure that all accessories are removed from the building during scaffold

dismantling. 13. Finished cladding at anchor points to match adjacent areas.

3. FABRICATION AND INSTALLATION OF HOARDING

1. All hoarding is to be installed in accordance with the rules and regulations set forth in the referenced standards.

2. Install hoarding protection where shown on the site plan and in accordance with

approved shop drawings. 3. Provide posts, rafters, planking and plywood sheathing. 4. The roof structure of the hoarding is to be constructed of wood framing capable

of withstanding impact load from falling debris, materials or tools in order to provide overhead protection to public accessing the building during construction. The roof of all hoarding must also be waterproofed.

5. If necessary, provide sufficient lighting for evening entrance and exit of the

building throughout covered walkways to ensure safety and security to public. No dark corners are allowed.

6. Maintain hoarding in good condition at all times. 7. Repair any damaged hoarding to satisfaction of the Consultant and other

applicable authorities. 8. Keep hoarding clean at all times. 9. Remove hoarding from site only when authorized by the Consultant.

- END OF SECTION -

Page 40: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Rigid Insulation Section 07210 7551 Minoru Gate Page 1/2 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL 1.1 SCOPE

.1 Work will include: .1 Labour, materials, equipment and services necessary for installation of

two layers of rigid insulation - base layer of 2”thick insulation board and second layer of 1” thick insulation board.

1.2 RELATED WORK AND SECTIONS

.1 Summary of Work Section 01010

.2 Preformed Metal Cladding Section 07465 1.3 SUBMITTALS

.1 Product Data: .1 Provide data on material characteristics performance criteria limitations.

.2 Manufacturer’s Installation Instructions: .1 Indicate preparation installation requirements and techniques, product

storage and handling criteria. 1.4 REFERENCES

.1 ASTM C209 – (98) – Standard Test Methods for Cellulosic Fibre Insulating Board.

.2 ASTM C518-(04) – Standard Test Method for Steady-State Thermal Transmission Properties by Means of the Heat Flow Meter Apparatus.

.3 ASTM C1289-(05) – Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board.

.4 ASTM D1621-(04a) - Standard Test Method for Compressive Properties of Rigid Cellular Plastics.

.5 ASTM E96/E96M-(05) – Standard Test Method for Water Vapour `Transmission of Materials.

2 PRODUCTS 2.1 RIGID FOAM BOARD INSULATION

.1 A glass-fiber-reinforced polyisocyanurate foam core faced with nominal 1.25 mil embossed white acrylic-coated aluminum on one side and 1.25 mil embossed aluminum on the other side

2.2 PRODUCT AND MANUFACTURER NAME:

.1 Thermax ISO Light Duty Insulation Board by the Dow Chemical Company.

.2 Pre-approved Equivalent. 2.3 SIZES

.1 Thickness : 3”

.2 Sheet Size : 4’-0”x 10’-0”

.3 Edge Treatment : Shiplap Edges

Page 41: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Rigid Insulation Section 07210 7551 Minoru Gate Page 2/2 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

2.4 ACCESSORIES

.1 Adhesive: Single component, polyurethane adhesive UL 1897 and tested by factory mutual; Enerbond by the Dow Chemical Company.

.2 Joint Closure Strips: As per the manufacturer’s written instructions.

.3 Joint Tape: 2.0 mil. (0.051mm) thick aluminium tape, 3” wide.

.4 Sealant : One part, flexible polyurethane based elastomeric sealant ; moisture curing and non-sagging.

Approved Sealants: Vulkem 116, Sikaflex 201 and Dow Corning 790. 3 EXECUTION 3.1 PREPARATION

.1 Verify that surface and conditions are ready to accept work of this Section in accordance with the manufacturer’s recommendations.

3.2 EXAMINATION

.1 Verify that the insulation boards and adjacent materials are compatible.

.2 Verify that substrate is sound, clean, and free of oil, grease, irregularities, materials or substances that may impede adhesive bonds.

3.3 INSTALLATION

.1 Refer to manufacturer’s written installation instructions.

.2 Apply adhesive to concrete block wall and install first layer of insulation board. Second layer of insulation board to be glued to the first layer.

.3 Install boards with long axis parallel to supports. Ensure end joints are fully supported.

.4 Joints to be offset by 50 % of panel length. Butt edges and ends tight to adjacent boards and to protrusions.

.5 Fit insulation boards neatly around wall penetrations.

.6 Secure board insulation to wall using appropriate adhesives as specified and as recommended by the manufacturer.

.7 Cut and fit boards to suit project requirements.

.8 Apply continuous 3/8” beads of joint sealant along shiplapped edge of insulation board and press next insulation board into sealant bead.

.9 Ensure insulation boards are clean, free of dust and dry prior to applying joint tape. Apply joint tape over exposed board joints using a squeegee or bristle brush. Ensure tape adheres to embossed surface.

.10 Replace damaged insulation boards.

- END OF SECTION -

Page 42: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Self Adhesive Membrane Section 07275 7551 Minoru Gate Page 1/3 Richnond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL 1.1 REFERENCE

.1 ASTM D412 Vulcanized Rubber and Thermoplastic Rubbers and Thermoplastic Elastomers - Tension.

.2 CGSB 37-GP-9Ma-83 Primer, Asphalt, Unfilled, for Asphalt Roofing, Damp

Proofing and Waterproofing. .3 CGSB 37-GP-15M-76 Application of Asphalt Primer for Asphalt Roofing,

Damp Proofing and Waterproofing. .4 CGSB 37.29-M89 Rubber-Asphalt Sealing Compound. .5 CGSB 37-GP-56M-80 Membrane, Modified, Bituminous, Prefabricated, and

Reinforced for Roofing. 1.2 STORAGE & HANDLING

.1 Provide and maintain dry, off-ground weatherproof storage.

.2 Store rolls of membrane in upright position.

.3 Remove only in quantities for same day use. 1.3 ENVIRONMENTAL REQUIREMENTS

.1 Do not install membrane system when ambient temperatures are at or below 5°C for 24 hours before application, and only during dry conditions.

.2 Minimum temperature for installation of primer is 5°C. .3 Do not allow membrane to remain exposed longer than 6 weeks.

1.4 QUALITY ASSURANCE

.1 Applicator: Company specializing in performing the work of this section with minimum one year documented experience. Provide list of previous projects and references upon request by the Consultant.

2 PRODUCTS 2.1 MEMBRANE

Page 43: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Self Adhesive Membrane Section 07275 7551 Minoru Gate Page 2/3 Richnond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

.1 The rubberized asphalt self adhesive membrane to meet the following minimum criteria:

.1 Reinforced with a cross laminated polyethylene sheet 4 mils thick.

.2 Membrane is to be 40 mils thick (excluding release film) and must have a release film to protect the adhesive surface.

.3 The membrane system must not show any signs of softening, flow or deterioration

at temperatures 70° Celsius or below. .4 Acceptable products for application to walls behind cladding:

.1 Blueskin SA, manufactured by Monsey Bakor

.2 Perm-a-barrier, manufactured by W.R. Grace

.3 Pre-approved equivalent .5 Acceptable products for application below parapet flashings and profiled metal

roofing (high temperature resistant water and ice protection). .1 WIP 300 HT by MiraDRI. .2 Bakor Blueskin PE 200 HT by Monsey Bakor .3 Safseal 6634 by Safseal Innovations .4 Pre-approved equivalent

2.2 ACCESSORIES

.1 Primer: High tack SBS rubber based primer: to CGSB 37-GP-9Ma as recommended by manufacturer.

.2 Mastic sealant: As recommended by the manufacturer.

3 EXECUTION 3.1 PROTECTION

.1 Cover walls and adjacent work where material is to be hosted or used. .2 Clean off drips and smears of bituminous material and primers off adjacent

materials immediately. .3 At end of each day’s work, provide protection for completed work and materials

out of storage. 3.2 EXAMINATION OF SURFACES

.1 Examine surfaces to have membrane installed and immediately inform Consultant in writing of defects.

Page 44: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Self Adhesive Membrane Section 07275 7551 Minoru Gate Page 3/3 Richnond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

3.3 PREPARATION

.1 Protect adjacent surfaces not designated to receive membrane. .2 Clean and prepare surfaces to receive membrane in accordance with

manufacturer’s recommendations. Surfaces are to be clean, dry and free of foreign matter.

3.4 INSTALLATION

.1 Install membrane in accordance with manufacturer’s instructions. .2 Prime areas to receive membrane in accordance with manufacturer’s

recommendations. Primer must be dry prior to application of membrane. Membrane must be applied to primed area that same day.

.3 Roll out sheets. Discard wrinkled or bubbled membrane. .4 Remove release paper layer. Roll out on substrate with a mechanical roller to

encourage full contact bond. Use heat gun as required to achieve adequate continuous bond.

.5 Lap sides and ends in accordance with manufacturer’s instructions and with the

project details. .6 Apply membrane as indicated on the details in a shingle fashion lapping

horizontal joints (4") 100 mm and vertical joints (6") 150 mm. .7 Prestrip sheathing paper as required to ensure shingle fashion laps at tie-ins. .8 Patch deficient areas with membrane extending (6") 150 mm minimum in all

directions from affected area. Seal top and sides of patch with mastic. .9 Extend membrane onto items protruding to or penetrating assembly and seal

termination with mastic. .10 Ensure no membrane or membrane accessories extend to future exterior sealant

locations or on finished surfaces. Clean any affected areas as required. .11 Seal leading edge with mastic at the end of each day’s work.

- END OF SECTION -

Page 45: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Preformed Metal Cladding Section 07465 7551 Minoru Gate Richmond, BC Page 1/3 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL 1.1 SCOPE

1. Installation of metal wall cladding system where shown on drawings and as specified herein.

2. Coordinate this section with interfacing and adjoining work for proper sequence of installation.

1.2 RELATED WORK

.1 Summary of Work Section 01010

.2 Flashing & Sheet Metal Section 07600

.3 Joint Sealants Section 07900 1.3 QUALITY ASSURANCE

All fabrication and erection work shall be carried out by qualified personnel with a minimum of three years experience in this trade and in accordance with the manufacturer’s specifications, unless otherwise detailed or specified in the contract documents.

1.4 SUBMITTALS

Samples of materials to be used shall be submitted to the Consultant for approval. Colour selection of metal cladding. trims and accessories to be provided in writing from the Consultant prior to commencement of the work.

1.5 WARRANTY

Provide manufacturer’s 10 year warranty in addition to the warranty requirements under the General Contract.

2 PRODUCTS 2.1 MATERIALS

.1 Cladding shall be Grade 230 Steel with a minimum yield stress of 230 MPa. Base steel thickness shall be 24 Ga. (0.61 mm) for a nominal thickness Z275 coating of 0.5mm. Pre-finished colour coating shall be series 5000. Colours shall be as selected by the Owner from the manufacturer’s full range of STANDARD colours. .1 Acceptable Manufacturers/Materials/Colours:

.1 Vicwest / CL38 wall panel / VW6162 - Antique Linen

.2 Westform Metals / WF636 wall panel / QC8802 - Ivory

.3 Or Preapproved equivalent. .2 Supporting Sub-Girts (Z shaped – 76 mm x 48 mm (3” x 1 7/8”)) - Minimum 18

gauge thick preformed galvanized steel, ASTM A 653M Grade 230 with Z275 zinc coating and conforming to CSA S136-94.

.3 Sealant:

Page 46: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Preformed Metal Cladding Section 07465 7551 Minoru Gate Richmond, BC Page 2/3 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

.1 Concealed : Tape or compound , non-skinning, non-drying, butyl rubber.

.2 Exposed : (Acrylic co-polymer to CGSB 19 GP-5M) (One part silicone to CGSB CAN2-19.13).

.3 Provide resilient tape gaskets between side laps or spacers between metal components.

.4 Fasteners shall be cadmium plated # 14 self –tapping screws, c/w colour match

EPDM neo bond cap and washer. Side lap and flashing fasteners shall be stitch screws # 14 c/w colour match caps.

.5 Galvanized steel sheet: commercial grade to ASTM A526-80 with Z275 zinc

coating, 0.475mm thick.

.6 Anchors at fascia into masonry - 5/8" diameter Hilti HIT - A anchors @ 32" o.c. c/w screens & Hilti HY20 into void block OR Hilti Kwik Bolt threaded end @ 32" o.c. into existing grouted cores. ( N.B. grouting is to be verified) .7 Anchors at sub-girts into masonry - 3/8" diameter Hilti HIT - A anchors @ 32" o.c. c/w screens & Hilti HY20 into void block OR Hilti Kwik Bolt threaded end @ 32" o.c. into existing grouted cores (N.B. grouting is to be verified) .8 Anchors at sub-girts into solid concrete – 3/8” diameter Hilti Kwik Bolts @ 32” o.c.

.9 Flashings, trims and closures shall be of same thickness and colour as cladding. Provide all flashings, trims, closures, collars, capping, covers, end stops and filler pieces.

.10 Closure strips shall be of foamed plastic, profile to suit and not susceptible to

deterioration from weathering. 3 EXECUTION 3.1 EXAMINATION

Examine the condition of all existing surfaces and substrates to which the work of this section is to be applied and ensure that they are adequate for complete and satisfactory installation with true planes, vertical lines. Start of work will imply acceptance that all conditions are satisfactory.

3.2 INSTALLATION

.1 Install sub-girt framing. .2 Install cladding in accordance with manufacturer’s written instructions and per

BC Building Code 2006 requirements. End lap joints are not permitted. .3 Install starter flashing, exterior corners, drip caps, backer plates, fillers, closure

strips, flashings and other trims per manufacturer’s written instructions and per

Page 47: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Preformed Metal Cladding Section 07465 7551 Minoru Gate Richmond, BC Page 3/3 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

section 01010 and details. .4 The completed cladding installation shall provide protection against the

penetration of rain, snow, ice or environment elements. To be rigid and safely able to withstand all wind and environmental loads, not to deflect, buckle, twist or pull away from fastenings and substructures from base structures.

.5 Provide sealant at junctions with adjoining work. Refer to details. 3.3 PROTECTION

.1 Protect the work of this section against damage by others. .2 Protect the work of other sections against damage resulting from work of this

section. Repair and make good, at no extra cost, any damage to other sections caused by this work.

.3 All material which is stored on construction site is to be protected from the

weather so that the possibility of moisture entrapment on the siding is eliminated. Cleaning of the siding during erection or subsequent to it to ensure uniform appearance shall form part of the erection contract.

.4 Only minor touch-up will be allowed. Major scratches, dents, abrasions will be

rejected and any rejected panels shall be removed from the site and replaced with new panels at no extra cost to the Owner.

3.4 CLEAN UP

.1 Promptly as the work proceeds and upon completion, clean up and remove from the site all crating, rubbish and debris resulting from the work of this section. .2 Clean-up is required at the end of each days work. All debris must be in disposal bins or removed from the site at the end of each day.

- END OF SECTION -

Page 48: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Modified Bitumen Sheet Roofing Section 07535 7551 Minoru Gate Page 1/4 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL 1.01 SCOPE 1. Patching of existing SBS roofing system at roof parapets and scuppers on the

‘east’ walls with components of the 2-ply SBS roof system. Refer to the Summary of Work, section 01010 and details for further information.

1.02 RELATED WORK AND SECTIONS 1. Rough Carpentry Section 06100

2. Flashing and Sheet Metal Section 07600 1.03 QUALITY ASSURANCE 1. All applications shall be carried out by experienced personnel and in

accordance with the manufacturer's specifications, unless otherwise detailed or specified in the contract documents. The roofing applicator must be a manufacturer’s accepted installer and registered with the RCABC as an approved applicator.

1.04 GUARANTEE

1. No RCABC guarantee available for this Work, however all work must be carried out to meet the 5 year minimum RCABC requirements.

1.05 NOTE 1. This specification is based on the use of Soprema products. Other approved

manufacturers include: Siplast, IKO. 2 PRODUCTS 2.01 STANDARDS

1. Conform to the RCABC minimum standards for a 5-year warranty and to the appropriate CSA, CGSB and ASTM standards for the materials used in the roofing system specified. Materials to be listed in Section 2.2 of the RCABC manual.

2.02 MATERIALS 1. Base Overlay – Not required. 2. Base Sheet – Sopralene Flam 180 by Soprema or equal by IKO or Siplast. 3. Base Sheet Stripping – Not required.

4. Cap Sheet & Cap Sheet Stripping – Not required. 5. Lumber Pressure treated D.Fir or HemFir, No. 2 or better. 3/8” pressure treated

plywood to CSA 0121-M1978. 6. Sheet Metal Flashings – 26 gauge pre-finished baked enamel steel. Colour to be

pre-approved by the owners.

Page 49: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Modified Bitumen Sheet Roofing Section 07535 7551 Minoru Gate Page 2/4 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

7. Scuppers – To match existing sizes and shapes. Ship formed box ends, fully soldered seams. Replace existing scuppers with new.

3 EXECUTION 3.01 EXAMINATION & NOTIFICATION 1. Examine the condition of all existing surfaces and substrates to which the work

of this section is to be applied and ensure that they are adequate for complete and satisfactory installation with true planes, dry and clean. Consultant’s approval required that all conditions are satisfactory prior to commencing work.

2. Notify the Consultant 24 hours before the beginning roofing installation. 3.02 SUBSTRATE 1. Plywood and other substrates shall be dry, solid and smooth with no

depressions or splits. Decayed plywood and other substrates will be repaired by others under section 06100.

3.03 INSTALLATION

1. Base Overlay: 1. Not required.

2. Base Sheet: 1. Mechanically fasten the first layer of base sheet (Sopralene Flam

180) to all exposed wood surfaces on the existing roof parapet, over new plywood backing and new fascia. Refer to details for locations.

2. Torch apply a second layer of cap sheet over the first layer. 3. Degranulate the existing cap sheet adjacent to the areas of Work for

a minimum of 8” in all directions. Torch apply the second layer over the existing granulated cap sheet.

4. Torch apply the second layer of cap sheet over scupper bottoms and sides. Extend onto parapets and roof surfaces a minimum of 8”.

5. All base and cap sheets are to be fully adhered using the torch-on method of application.

6. Refer to details 1,3 & 4 for locations and extent of work.

3. Base Sheet Stripping: 1. Not required.

4. Cap Sheet: 1. Not required.

5. Cap Sheet Stripping:

1. Not required.

Page 50: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Modified Bitumen Sheet Roofing Section 07535 7551 Minoru Gate Page 3/4 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

6. Scuppers: 1. Install all new flanged scuppers to match existing sizes and shapes.

Horizontal and vertical flanges are to be set in a trowel coat of mastic and nailed in place prior to application of the base sheet.

7. Access to Roofs:

1. Access is by ladder only.

8. Material Storage and Disposal Bins: 1. Disposal bins and materials storage are not to block doorways or exits or roadways in the area. Materials storage and disposal bins locations must be coordinated with the City of Richmond Facilities Management department. Contact Ricardo Soliven, AScT.

3.04 FIRE PROTECTION 1. Provide one 10 lb full and operating ABC fire extinguisher for each person

torching. The fire extinguishers shall be on the roof surface within easy access to each person applying torch on membrane.

2. It is the roofing contractor’s responsibility to supply adequate fire protection at all times. No torch on applications will be allowed to proceed unless the appropriate fire extinguishers are in place. (Table 5.0.1 pages 1-6 RCABC Safety procedures).

3. Kettles or tankers are to be moved away from the building each night. Ladders are to be locked up or removed from the site.

3.05 WATER TEST

1. Conduct a 24-hour water test (minimum depth one inch) after completion of installation of membrane and scuppers.

2. Notify the Consultant in advance of performing the test in order to arrange for access to the inside of the arena to check for leakage.

3.06 CO-ORDINATION 1. Co-ordinate the work of this section with the work of other related trades. 3.07 PROTECTION 1. Protect the work of this section against damage by others.

2. Protect the work of other sections against damage resulting from work of this section. Repair and make good, at no extra cost, any damage to other sections caused by this work.

3. All material which is stored on construction site is to be protected from the weather.

Page 51: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Modified Bitumen Sheet Roofing Section 07535 7551 Minoru Gate Page 4/4 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

3.08 CLEAN UP 1. Promptly as the work proceeds and upon completion, clean up and remove

from the site all crating, rubbish, and debris resulting from the work of this section.

- END OF SECTION -

Page 52: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Flashing & Sheet Metal Section 07600 7551 Minoru Gate Page 1/2 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL 1.1 SCOPE

The removal and disposal of existing metal flashings and replacement with new flashings to building façade, roofs, etc. as indicated on the drawings.

1.2 RELATED WORK AND SECTIONS

1. Summary of Work Section 01010 2. Joint Sealants Section 07900

1.3 QUALITY ASSURANCE

1. All fabrication and erection work shall be carried out by experienced personnel and in accordance with the RCABC standards, unless otherwise detailed or specified in the contract documents.

1.4 SUBMITTALS

1. A sample of each flashing profile and colour to be used shall be submitted to the Owner for approval prior to fabrication.

2 PRODUCTS 2.1 MATERIALS

1. Hot-dipped galvanized sheet steel to be minimum 0.56 mm (26 gauge) thickness, on details unless noted otherwise pre-finished on both sides. Through-wall flashing and other flashings colour must be similar to cladding colour.

3 EXECUTION 3.1 EXAMINATION

1. Examine the condition of all existing surfaces and substrates to which the work of this section is to be applied and ensure that they are adequate for complete and satisfactory installation with true planes, vertical lines. Start of work will imply acceptance that all conditions are satisfactory.

3.2 FABRICATION GENERAL

1. Flashings to be fabricated to profiles indicated on the drawings, or when not shown, to the recommendations as indicated in the Installation Manual of ARCA to use "Drive-Lock" type joints at basically 8’-0” o.c. (Joints line up with any Architectural features where applicable.)

2. Metal flashings shall be provided to a minimum height of 8” above bottom of cant strips, and higher where indicated on drawings.

3. Provide flashing to sizes and shapes indicated or required for installation by other trades. Joints must be standing seam or S-lock, unless otherwise indicated. A safety edge must be installed on all cut flashing material. Apply caulking at the seams before fitting pieces together, so that the caulking is hidden (caulking not exposed to weathering).

Page 53: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Flashing & Sheet Metal Section 07600 7551 Minoru Gate Page 2/2 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

4. All arch shape or curved flashings over windows, arches or parapets must be formed using a Pittsburgh seam at all curved bends in the metal.

3.3 DOOR: HEAD AND SILL FLASHINGS

1. Provide metal head flashings for windows and doors. Provide sill flashings for windows only when required by detail. Head flashings are to be installed with end dams. End dams on sill flashings must be sealed.

3.4 INSTALLATION

1. Explosive or other impact actuated fasteners shall not be used to fasten metal flashings. The use of concealed in seam fasteners and concealed clip type fasteners is required. Fastening of metal flashings on the inside or outside face is permitted if no concealed fixing is possible. Caulk in the pilot hole before inserting fastener. Use appropriate screw fasteners in a colour matching the flashing complete with neoprene washers.

3.5 CLEAN-UP

1. Upon completion of all roofs, flashings, and sheet metal work, work shall be cleaned of all dirt and stains and left in perfect condition. As the work proceeds, remove from the site all debris resulting from the work of this section.

- END OF SECTION -

Page 54: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Joint Sealants Section 07900 7551 Minoru Gate Page 1/3 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL 1.1 RELATED WORK AND SECTION

1. Summary of Work Section 01010 2. Flashing & Sheet Metal Section 07600

1.2 SCOPE

This section covers the supply and installation of caulking sealants, back-up, and primers, as specified in this or other sections or cross referenced from other sections (where the work of caulking and sealants is the responsibility of another section), and as indicated on the drawings.

1.3 QUALIFICATIONS

Contractor for this Section of work to be an approved Sealant and Caulking contractor, with at least three years proven satisfactory experience in this trade. Applicators to be thoroughly trained mechanics fully competent in the application of sealants and caulking.

1.4 ENVIRONMENTAL

The performance of the work of this section shall only be carried out under climatic conditions in accordance with the manufacturer's instruction.

1.5 CURING AND PROTECTION

Cure compounds and sealants in accordance with manufacturer's instructions, to obtain maximum bond to surfaces, cohesive strength and durability at earliest possible time. Installer shall advise the Contractor of proper procedures for protection of compounds and sealants during construction period, so that they will be without any indication of deterioration or damage at time of acceptance by Owner.

2 PRODUCTS 2.1 MATERIALS

1. General 1. All materials to be pre-approved by Consultant. Colours as selected by

Consultant from standard range (generally to match surrounding surfaces). 2.2 CAULKING

Type 1 Exposed Exterior: Sonolastic NP 1 by Sonneborn, Dymonic or Dymonic FC by Tremco, or approved alternate. The colour of the caulking is to match the colour of the substrate.

Type 2 Sealant for Preformed Metal Cladding: Refer to Section 07465 – Preformed Metal Cladding, part 2.3 - Sealant. The colour of the caulking is to match the colour of the substrate.

Type 3 Sealant for Rigid Foam Board Insulation: Refer to Section 07210 – Rigid Insulation, part 2.03.4 - Sealant. The colour of the caulking is to match the colour of the substrate.

Page 55: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Joint Sealants Section 07900 7551 Minoru Gate Page 2/3 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

Primers: As approved by sealant manufacturer, and compatible with sealant. Joint Backing: Closed cell round polyethylene, 25% to 50% larger than opening. Shore hardness 20, tensile strength 20-30 psi. Solvents, Cleaners, and Bond Breakers: As recommended by approved sealant Manufacturers.

3 EXECUTION 3.1 SURFACE CONDITION

Examine all joints, spaces and surfaces to be sealed and caulked, including temperatures and conditions which may impair finished work, and report all unsatisfactory conditions in writing to Consultant. Consultant to approve surfaces before start of the work. Start of work implies acceptance of conditions and surfaces and this trade must assume responsibility and rectify, all unsatisfactory finish resulting.

3.2 PREPARATION

1. Joints and spaces must be clean, dry, frost free and free from dust, paint, loose mortar and other foreign materials.

2. Clean ferrous metals of all rust, mill scale and coatings by wire brush, grinding or sandblasting; remove oils and grease with xylol, toluol, or methylethyl ketone.

3. Remove protective and strippable coatings on metallic surfaces by a solvent leaving no residue. Apply solvent and wipe dry, using clean white cotton cloths, using fresh cloths for each process. Do not allow solvents to air dry before wiping.

4. Treat areas covered by masking tape (after removal) similarly to above. 5. Etch bond concrete and masonry surfaces with 5% solution of muriatic acid to

remove excess alkalinity, rinse thoroughly with water and dry prior to installation of sealants.

6. Joints and spaces to receive caulking: 1/4" deep and wide minimum, and 1" wide maximum, unless otherwise shown. Where these requirements are not met, obtain written permission from Consultant before proceeding with work.

7. Grind surface and edge at ceramic tile to obtain bond. 8. Fill joints where more than 1/2" deep, to within 1/2” of surface with a joint

backing. 9. Prime sides of joints in porous material immediately prior to caulking, in

accordance with manufacturer's instructions. Mask adjacent surfaces with tape prior to priming and caulking; remove tape after joint has been tooled.

3.3 APPLICATION

1. Apply sealant with a gun, with proper size nozzle, or knife as required. Use sufficient pressure to fill all voids and joints solid, superficial pointing with a skin bead will not be accepted.

2. Surface of sealant shall form a full continuous bead, smooth, free from ridges, wrinkles, sags, air pockets and embedded impurities. Neatly tool surface to a slight concave.

Page 56: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Joint Sealants Section 07900 7551 Minoru Gate Page 3/3 Richmond, BC Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

3. Clean adjacent surfaces immediately, and leave work neat and clean; remove excess and droppings using recommended cleaners as work progresses.

4. Do not apply when temperature below 4 C°. 5. Apply Sealant to Joint Location as follows:

1. Joints subject to air or water infiltration. 2. Exterior joints between and around grilles, and metal door frames,

expansion and control joints, and all dissimilar materials. 3. All areas noted or obviously required and to protect interior from exterior

water and air infiltration, and to complete air seal of building interior. 4. Caulk at all intersections between different materials (e.g. between

window frames and vinyl, at railing fasteners, at downpipe fasteners, etc.). 5. Always caulk in the pilot hole before inserting a fastener, and caulk

around the fastener after it is inserted. This applies particularly to balcony railings. Caulking should be installed before the finish coat of the stucco is applied. This sequence ensures that the joint surfaces are not contaminated with finish coat before caulking is installed.

3.4 SEALERS

Where liquid sealers are to be applied to concrete or other surfaces, do so only after application of sealant to joints.

3.5 CLEANUP

Remove excess compound promptly as the work progresses and upon completion using cleaners as recommended by the manufacturer.

- END OF SECTION -

Page 57: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 1/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

1 GENERAL 1.1 RELATED WORK

.1 Summary of Work Section 01010

.2 Flashing & Sheet Metal Section 07600

.3 Joint Sealants Section 07900 1.2 REFERENCE STANDARDS

.1 New surfaces - Master Painters Institute (MPI) Architectural Painting Specification Manual.

.2 Existing surfaces - Master Painters Institute (MPI) Maintenance Repainting

Manual. 1.3 SECTION INCLUDES

.1 All labour, materials, tools and other equipment, services and supervision required to complete all interior and exterior painting and decorating work as indicated on Finish Schedules and to the full extent of the drawings and specifications.

.2 Work under this contract shall also include, but not necessarily be limited to: 1. Surface preparation of substrates as required for acceptance of painting, including

cleaning, small crack repair, patching, caulking, and making good surfaces and areas to the limits defined under MPI preparation requirements.

2. Priming and back-priming of wood materials as noted herein or specified in the Master Painters Institute MPI Architectural Painting Specification Manual and/or the MPI Maintenance Repainting Manual.

.3 Refer to drawings and specifications (i.e. Painting-Finish Schedule, Sec. 01100,

General Requirements) for type, location and extent of finishes required, and include all touch-ups and field painting necessary to complete work shown, scheduled or specified.

.4 This Section, along with the drawings, forms part of the Contract documents and

is to be read, interpreted and coordinated with all other parts. .5 General Requirements, Section 01100 forms an integral part of this. Section of

Work. Painting contractor shall refer to these and all other related parts. 1.4 QUALITY ASSURANCE

.1 This Contractor shall have a minimum of five (5) years proven satisfactory experience and shall show poof before commencement of work that he will maintain a qualified crew of painters throughout the duration of work. When requested, Contractor shall provide a list of the last three comparable jobs including, name and location, specifying authority/ project manager, start and

Page 58: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 2/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

completion dates and cost amount of the painting work. .2 Only qualified journeymen who have a “Tradesman Qualification of Proficiency”

shall be engaged in painting and decorating work. Apprentices may be employed provided they work under the direct supervision of a qualified journeyman in accordance with trade regulations.

.3 Conform to the standards contained in the Master Painters Institute Architectural

Painting Specification Manual, latest edition (hereafter referred to as MPI Painting Specification Manual) and/or the Master Painters Institute Maintenance Repainting Manual latest edition (hereafter referred to as the MPI Maintenance Repainting Manual) for all painting products including preparation and application of materials. MPI Painting Specification Manual as issued by the local MPI Accredited Quality Assurance Association having jurisdiction.

.4 All paint manufacturers and products used shall be as listed under the “Approved

Products” section of the MPI Architectural Painting Specification Manual and/or the MPI Maintenance Repainting Manual..

.5 All surfaces requiring painting shall be inspected by the Consultant who shall

notify the General Contractor in writing of any defects or problems, prior to commencing painting work, or after the prime coat shows defects in the substrate.

1.5 REGULATORY REQUIREMENTS

.1 Conform to work place safety regulations for storage, mixing, application and disposal of all paint related materials to requirements of those authorities having jurisdiction.

.2 Conform to safety precautions in accordance with the latest requirements to

Industrial Health and Safety Regulations, latest edition, of authorities having jurisdiction.

.3 Fully cooperate at all times with the requirements of the Consultant in the

performance of their duties, including providing access and assistance as required to complete inspection work.

1.6 SUBMITTALS

.1 Submit list of all paints materials to the Consultant for review prior to ordering materials.

.2 Submit two sets of Material Safety Data Sheets (MSDS) prior to commencement

of work for review and for posting at job site as required. .3 Submit certification reports for ecologo paint products used. .4 When requested, submit invoice list of all paint materials ordered for project work

Page 59: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 3/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

to the Consultant indicating manufacturer, types and quantities for verification and compliance with specification and design requirements.

.5 When, requested or required by painting of occupied areas, submit work schedule

for various stages of work for the consultant’s review and Owner’s approval. .6 At project completion provide an itemized list complete with manufacturer, paint

type and color-coding for all colors used for Owner’s later use in maintenance. .7 At project completion provide properly packaged maintenance materials as noted

herein and obtain a signed receipt. 1.7 DELIVERY, STORAGE & HANDLING

.1 Deliver painting materials in sealed, original labeled containers bearing manufacturer’s name, brand name, type of paint or coating and color designation, standard compliance, materials content as well as mixing and/or reducing and application requirements. Only approved paint products as listed in the MPI Architectural Painting Specification Manual, latest edition and/or the MPI Maintenance Repainting Manual, latest edition, shall be delivered to the site.

.2 Store all paint materials in original labeled containers in a secure lockable, dry,

heated and well ventilated single designated area meeting the minimum requirements of both paint manufacturer and authorities having jurisdiction and at a minimum ambient temperature of 45ºF (7ºC). Only material used on this project to be stored on site.

.3 Where toxic and/or volatile/explosive/flammable materials are being used,

provide adequate fireproof storage lockers and take all necessary precautions and post adequate warnings as required. Take adequate measures to prevent the release of volatile organic compounds (VOC) into the atmosphere.

.4 Take all-necessary precautionary and safety measures to prevent fire hazards and

spontaneous combustion and to protect the environment from hazard spills. Materials that constitute a fire hazard (paints, solvents, drop clothes, etc.) shall be stored in suitable closed and rated containers and removed from the site on a daily basis.

.5 Comply with requirements of authorities having jurisdiction, in regard to the use,

handling, storage and disposal of hazardous materials. 1.8 PROJECT SITE REQUIREMENTS

.1 UNLESS specifically pre-approved by the specifying body, and the applied product manufacturer, perform no painting or decorating work when the ambient air and substrate temperatures are below 50ºF (10ºC) for both interior and exterior work.

Page 60: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 4/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

.2 Perform no painting or decorating work when the relative humidity is above 85% or when the dew point is less than 50ºF (10ºC) for both interior and exterior work.

.3 Perform no painting or decorating work when the maximum moisture content of

substrate exceeds: . 12% for concrete and masonry (clay and concrete brick/block) . 12% for wood . 12% for plaster and gypsum board . 12% for stucco

.4 Conduct all moisture tests using a properly calibrated electronic Moisture Meter,

except test concrete floor for moisture using simple “cover patch test”. .5 Test concrete, masonry and plaster surfaces for alkalinity as required. .6 Perform no painting or decorating work unless a minimum lighting level of 323

Lux (30 foot candles) is provided on surfaces to be painted or decorated. Adequate lighting facilities shall be provided by the General Contractor.

.7 Perform no painting or decorating work unless adequate continuous ventilation

and sufficient heating facilities are in place to maintain ambient air and substrate temperatures above 50ºF (10ºC) for 24 hours before, during and after paint application. Provide supplemental ventilating and heating equipment if ventilation and heating for existing system is inadequate to meet minimum requirements.

.8 Apply paint only to dry, clean, properly cured and adequately prepared surfaces in

areas where dust is no longer generated by construction activities such that airborne particles will not affect the quality of finished surfaces.

1.9 GUARANTEE

.1 Warranty for new paint: Upon completion of the Contract, Contractor shall provide a Five (5) Year Labour and Material Warranty for the full value of the contract stating that the paint will perform for a 5 year period, starting from the date of Final Inspection, and that all deficient paint will be replaced at no cost to the owner. This warranty is to be issued on company letterhead, signed and sealed or signed and notarized by all officers of the company. Any cost attached to this is to be included in the contract price.

.2 Provide five-year, labour, and material warranty under paint provider’s written

terms, conditions and limitations. 2 PRODUCTS 2.1 MATERIALS

Page 61: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 5/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

.1 All materials (primers, paints, coatings, varnishes, stains, lacquers, fillers, thinners, solvents, etc.) shall be in accordance with the MPI Architectural Painting Specification Manual and/or the MPI Maintenance Repainting Manual “Approved Product” listings and shall be from a single manufacturer for each system used.

.2 Other paint materials such as linseed oil, shellac, etc. shall be the highest quality

product of an approved manufacturer listed in the MPI Architectural Painting Specification Manual and/or the MPI Maintenance Repainting Manual and shall be compatible with other coating materials as required.

.3 All materials and paints shall be lead and mercury free and shall have low VOC content where possible.

.4 Where required, paint products shall meet the requirements of the Environmental

Choice Program, Department of the Environment. Water based paints to be certified to ECP-07-89, solvent based; to ECP-12-89.

.5 All paint materials shall have good flowing and brushing properties and shall dry

or cure free of blemishes or sage. .6 Where required, paints and coatings shall meet flame spread and smoke

developed ratings designated by local Code requirements and/or authorities having jurisdiction.

.7 Slip resistant additives (SRA) – rubber aggregate, clean/washed silica sand or

ground walnut chips (interior dry areas only) for use with or as a component part of paint on horizontal surfaces as required providing slip resistance. Where site applied, material to be either mixed into paint (and mixed constantly to keep material in suspension) or broadcast into first or prime coat as required.

2.2 EQUIPMENT

.1 Painting and decorating equipment – to best trade standards for type of product and application.

.2 Spray painting equipment – of ample capacity, suited to the type and consistency

of paint or coating being applied and kept clean in good working order at all times.

2.3 MIXING & TINTING

.1 Unless otherwise specified, paints shall be ready-mixed. Re-mix prior to application to ensure color and gloss uniformity.

.2 Paste, powder or catalyzed paint mixes shall be mixed in strict accordance with

manufacturer’s written instructions. .3 Perform all color tinting operations prior to delivery of paint to site.

Page 62: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 6/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

.4 Where thinner is used, addition shall not exceed paint manufacturer’s

recommendations. 2.4 GLOSS

.1 Paint gloss shall be defined as the sheen rating of applied paint, in accordance with the following values: . Flat or matte – 0 to 5 units at 60°F to a maximum of 10 units at 85°F . Low sheen - 0 to 10 units at 60°F and 10 to 30 units at 85°F . Eggshell or low luster – 10 to 25 units at 60°F and 10 to 30 units at 85°F . Satin – 20 to 35 units at 60°F and a minimum of 30 units at 85°F . Semi-gloss – 35 to 70 units at 60°F . Gloss – 70 units and greater

.2 Finish (i.e. gloss level) of all painted surfaces shall be as specified herein or as

noted on the Finish Schedule. 2.5 FINISHES

.1 Colours shall be as selected by the Owner from a manufacturer’s full range of colours.

3 EXECUTION 3.1 CONDITION OF SURFACES

.1 Prior to commencement of work of this section, thoroughly examine, and test as required, all conditions and surfaces scheduled to be painted and report in writing to the Contractor and Consultant any conditions or surfaces that will adversely affect work of this section.

.2 No painting work shall commence until all such adverse conditions and defects

have been corrected and surfaces and conditions are acceptable to the Consultant. .3 Commencement of work shall not be held to imply acceptance of surfaces except

as qualified herein. Such surfaces as concrete, masonry, structural steel and miscellaneous metal, wood, gypsum board and plaster, shall not be the responsibility of the Painting Subcontractor.

3.2 PREPARATION OF SURFACES

.1 Prepare all surfaces in accordance with MPI Architectural Painting Specification Manual and/or the MPI Maintenance Repainting Manual requirements. Refer to the MPI Manuals in regard to specific requirements for the following: - Environmental Conditions - PH testing - Acid etching

Page 63: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 7/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

- Rust stain removal - Asphalt surfaces - Vertical and horizontal concrete surfaces - Clay and concrete masonry units - Structural steel and miscellaneous metals - Steel exposed to high heat - Galvanized and zinc coated metal - Aluminum and cooper surfaces - Glue laminated beams and columns - Dimension and dressed lumber - Wood doors - Wood paneling and casework - Wood decks, floors, stairs and steps - Wood shingles and shakes - Stucco, plaster and gypsum board - Acoustical panels and tiles - Canvas and cotton coverings - Bituminous coated surfaces

.2 Protect all adjacent surfaces and areas from painting operations and damage by

drop cloths, shields, masking, templates, or other suitable protective means and make good any damage caused by failure to provide such protection.

.3 Substrate defects shall be made good and sanded ready for painting particularly

after first coat of paint. Finish painting of defective surfaces (e.g. gypsum board) shall indicate acceptance of substrate and any costs of making good defects shall be borne by the painter including re-painting of entire defective surface (no touch-up painting).

.4 Sand, clean, dry, etch, neutralize and/or test all surfaces under adequate

illumination, ventilation and temperature requirements. 3.3 APPLICATION

.1 Do not paint unless substrates are acceptable and/or until all environmental conditions (heating, ventilation, lighting and completion of other subtrade work) are acceptable for applications of products.

.2 Apply paint and decorating material in a workmanlike manner using skilled and

trade qualified applicators as noted under Quality Assurance. .3 Minimum painting standards shall be in accordance with MPI Architectural

Painting Specification Manual and/or the MPI Maintenance Repainting Manual Premium Grade finish requirements.

.4 Paint all surfaces requiring paint or stain finish to minimum MPI Architectural

Painting Specification Manual finish requirements with application methods in

Page 64: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 8/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

accordance with best trade practices for type and application of materials used. .5 Apply paint and coatings within an appropriate time frame after cleaning when

environmental conditions encourage flash-rusting, contamination or the manufacturer’s paint specifications require earlier applications.

.6 Painting coats specified are intended to cover surfaces satisfactorily when applied

at proper consistency and in accordance with manufacturer’s recommendations. .7 Tint each coat progressively lighter to enable confirmation of number of coats. .8 Apply a minimum of four coats of paint where deep or bright colors are used to

achieve satisfactory results. .9 Sand and dust between each coat to provide an anchor for next coat and to remove

defects visible from a distance up to 1000 mm (39”). .10 Do not apply finishes on surfaces that are not sufficiently dry. Unless

manufacturer’s directions state otherwise, each coat shall be sufficiently dry and hard before a following coat is applied.

.11 Prime coat of stain or vanish finishes may be reduced in accordance with

manufacturer’s directions. .12 Use aggregate coating or a slip resistant additive in paint for stair handrails, treads

and landings in accordance with the requirements of authorities having jurisdiction and where scheduled to be painted.

3.4 EXTERIOR SURFACES

Paint exterior surfaces in accordance with the following MPI Architectural Painting Specification Manual and/or MPI Maintenance Repainting Manual requirements: .1 Exterior Surfaces

.1 Concrete Vertical Surfaces: (including horizontal soffits) .1 New - EXT 3.1F Elastomeric .2 Repaint - REX 3.F Elastomeric

.2 Concrete Masonry Units: (smooth & split face block & brick)

.1 New - EXT 4.2D Elastomeric

.2 Repaint - REX 4.2D Elastomeric .3 Structural Steel and Metal Fabrications

.1 New - EXT 5.1C Alkyd metal primer/high performance acrylic (semi-gloss)

.2 Repaint - REX 5.1.C Alkyd metal primer/high performance acrylic (semi-gloss)

Page 65: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 9/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

.4 Galvanized Metal: (doors, frames, railings, misc., steel, pipes, overhead

decking, ducts, flashing, etc.) .1 New - EXT 5.3.G High performance acrylic (semi-gloss) .2 Repaint - REX 5.3G High performance acrylic (semi-gloss)

.5 Aluminum: (sash, sills and frames, flashing, posts and railings,

downpipes, etc.) .1 New - EXT 5.4B two component Aliphatic Polyurethane (gloss) .2 Repaint - REX 5.4B two component Aliphatic Polyurethane (gloss)

.6 Dimension Lumber: (columns, beams, exposed joists, underside of

decking, siding, fencing, etc.) .1 New - EXT 6.2A Latex (flat) .2 Repaint - REX 6.2A Latex (flat)

.7 Dressed Lumber: (including doors, door and window frames, casings,

battens, smooth fascias, etc. .1 New - EXT 6.3B Alkyd (semi-gloss) .2 Repaint - REX 6.3B Alkyd (semi-gloss)

3.5 FIELD QUALITY CONTROL

.1 All surfaces, preparation and paint applications shall be inspected. .2 Painted surfaces shall be considered to lack uniformity and soundness if any of

the following defects is apparent to the Consultant:

1. Runs, sags, hiding or shadowing by inefficient application methods. 2. Evidence of poor coverage at rivet heads, plate edges, lap joints, crevices,

pockets, corners and re-entrant angles. 3. Damage due to touching before paint is sufficiently dry or any other

contributory cause. 4. Damage due to application of moist surfaces or caused by inadequate

protection from the weather. 5. Damage and/or contamination of paint due to wind blown contaminants

(dust, sand blast materials, salt, spray, etc.). .3 Painted surfaces rejected by the inspector shall be made good at the expense of

the Contractor. Small affected areas may be touched up; large affected areas or areas without sufficient dry film thickness of paint shall be repainted. Runs, sags of damaged paint shall be removed by scraper or by sanding prior to application of paint.

3.6 PROTECTION

.1 Protect all newly painted exterior surfaces from rain and snow, condensation,

Page 66: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

Minoru Arena #1 Paint Section 09900 7551 Minoru Gate Richmond, BC Page 10/10 Project No. 2368 May 1, 2007

Aqua-Coast Engineering Ltd.

contamination, dust, salt spray and freezing temperatures until paint coatings are complete dry. Curing periods shall exceed the manufacturer’s recommended minimum time requirements.

.2 Erect barriers or screen and post signs to warn of or limit direct traffic away or

around work area as required. 3.7 CLEAN-UP

.1 Remove all paint where spilled, splashed, splattered or sprayed as work progresses using means and materials that are not detrimental to affected surfaces.

.2 Keep work area free from an unnecessary accumulation of tools, equipment,

surplus materials and debris. .3 Remove combustible rubbish materials and empty paint cans each day and safely

dispose of same in accordance with requirements of authorities having jurisdiction.

.4 Clean equipment and dispose of wash water/solvents as well as all other cleaning

and protective materials (e.g. rags, drop cloths, masking papers, etc.), paints, thinners, paint removers/strippers in accordance with the safety requirements of authorities having jurisdiction.

- END OF SECTION -

Page 67: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 68: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 69: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 70: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 71: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 72: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 73: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 74: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 75: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 76: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 77: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 78: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 79: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 80: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 81: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 82: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL
Page 83: INSTRUCTIONS TO BIDDERS CITY OF RICHMOND · INSTRUCTIONS TO BIDDERS CITY OF RICHMOND CONTRACT 3055Q SUPPLY AND INSTALLATION OF EAST WALL PARTIAL RETROFIT - MINORU ARENA ... GENERAL

141434 / 0745-01

CITY OF RICHMOND

Note: Receipt of this completed form will assist us in calling for future bids. Please complete and submit this form prior to the closing date and time as shown on the Request for Quotation/Proposal/Tender form. Please remember to include Quotation/Proposal/Tender No. at right.

Notice of No Bid Quotation/Proposal/Tender No.

A Quotation/Proposal/Tender is not being submitted for the following reason(s): We do not manufacture/supply the required

goods/services Cannot obtain raw materials/goods in time to meet

delivery requirements

We do not manufacture/supply to stated specifications Cannot meet delivery requirements

Specifications are not sufficiently defined

Cannot quote/tender a firm price at this time

Insufficient information to prepare quote/proposal/tender

Insufficient time to prepare quote/tender.

Quantity too small

We are unable to competitively quote/tender at this time.

Quantity too large

We do not have facilities to handle this requirement

Quantity beyond our production capacity

Licensing restrictions (please explain)

Cannot meet packaging requirements

Agreements with distributors/dealers do not permit us to sell directly.

Cannot handle due to present plant loading

Other reasons or additional comments (please explain below)

I / We wish to quote / tender on similar goods / services in future yes No

Authorized Company Official – Signature and Title Date

Firm Name Address City Province Postal Code

This space for City of Richmond Comments

Telephone Number