Instruction Manual for inserting the CMS ZDCs using the crane. ZDC REMOVAL PROCEDURE STEP 1 : Set up Test control system above ground 3 Moving Materials 4 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Instruction Manual for inserting the CMS  ZDCs  using the crane

Instruction Manual for inserting the CMS ZDCs using the crane

Page 2: Instruction Manual for inserting the CMS  ZDCs  using the crane

2

Summary TableZDC REMOVAL PROCEDURE

STEP 1: Set up1. Test control system above ground 32. Moving Materials 43. Cables connections 5-6 4. Laying of Cables. 75. Test crane movement without payload 86. Bring sarcophagus to TAN 97. Install rotation servo motor 10-128. Control System Activation 13-159. Crane rotation (to SARCO) 16-1710.Install elevator servo motor 18

STEP 2: Extraction of ZDC11.Rotate crane to TAN and lower elevator to ZDC 1912.Aline elevator to ZDC 2013.Fasten vertical elevator to ZDC 2114.Extract the ZDC 2215.Rotate crane and insert ZDC in SARCO 2316.Unfasten ZDC 2417.Store ZDC in bunker 25

Continued on next page

Page 3: Instruction Manual for inserting the CMS  ZDCs  using the crane

3

Summary TableZDC REMOVAL PROCEDURE

STEP 3 : Insertion of steel bars 1. Raise crane to make space for steel bars 262. Bring steel bars to TAN using transpallet 273. Lower elevator to steel bars 284. Fasten elevator to steel bars 295. Extraction of bars and rotation over TAN 306. Insertion of bars in TAN 317. Disconnect elevator from bars 32

STEP 4: Clean up8. Move empty crane over sacro 339. Disconnect servo motor from vertical elevator 3410.Move empty crane back over TAN 3511.Take empty sarco back to bunker 3612.Remove rotation servo motor 3713.Pull up control cables 3814.Disconnect Cables from control system Connections 39-4015.Bring materials back 41

Page 4: Instruction Manual for inserting the CMS  ZDCs  using the crane

4

STEP 1Op. 1: Test control system above ground.1. B90 power cable2. B90_RES cable3. B63 power cable4. B63_RES cable5. Fake switch cable, shown in insert. 6. SPARE 7. Handset cable8. 220v 15A ___________________Time : 5 minOperators : A and B

8

1 2 37

5

4

6

Page 5: Instruction Manual for inserting the CMS  ZDCs  using the crane

5

STEP 1Op. 2: Moving MaterialsBring downstairs control cabinet , remote control, motors, cables

Reference List : 1. Control Cabinet2. Remote Command

Handset3. Baldor BSM90

Servo motor (Rotation)

4. Baldor BSM63 Servo motor(vertical axis)

5. Cables

____________________

Time : 15 minOperators : A and B

1

34

25

Page 6: Instruction Manual for inserting the CMS  ZDCs  using the crane

6

STEP 1Op.3: Cable Connections (A)Control System Installation(with cables connections)

____________________

Time : 10 minOperators : A and B

Page 7: Instruction Manual for inserting the CMS  ZDCs  using the crane

7

STEP 1Op.3: Cable Connections (B)Control System Installation(cables connections)

Reference List :

1. B90_PWR cable2. B90_RES cable3. B63_PWR cable4. B63_RES cable5. Limit_Switch cable6. SPARE 7. Handset cable8. 220v 15A

____________________

Time : 5 minOperators : A and B

8

1 2 37

5

4

6

Page 8: Instruction Manual for inserting the CMS  ZDCs  using the crane

8

STEP 1 Op.4: Laying of CablesFrom the Control System to the ZDC Crane.

____________________

Time : 5 minOperators : A and B

20meters

15meters

Page 9: Instruction Manual for inserting the CMS  ZDCs  using the crane

9

STEP 1 Op.5: Test crane movement without payloadRun the crane forward and backward through its entire range of motion without a payload.____________________

Time : 10 minOperators : A and BOne near TAN the other at the staging area

Page 10: Instruction Manual for inserting the CMS  ZDCs  using the crane

10

STEP 1 Op.6: Bring sarcophagus to TAN.Using the transpallet bring and empty Sarcophagus to the TAN. ____________________

Time : 5 minOperators : A

Page 11: Instruction Manual for inserting the CMS  ZDCs  using the crane

11

STEP 1Op.7: Install rotation servo motor (A)1) Connect the Baldor BSM90 Servo motor to crane2) Connect cables to motor

____________________

Time : 10 minOperators : A and B

1

2

Page 12: Instruction Manual for inserting the CMS  ZDCs  using the crane

12

STEP 1 Op.7: Install rotation servo motor (B)Baldor BSM90 Servo motor (Rotation) : Assembly to the crane

____________________

Page 13: Instruction Manual for inserting the CMS  ZDCs  using the crane

13

STEP 1Op.7: Install rotation servo motor (C)Baldor BSM90 Servo motor (Rotation) : Fastening

________________

Page 14: Instruction Manual for inserting the CMS  ZDCs  using the crane

14

STEP 1Op.9: Control System Activation(A) 1.Power-ON(LV)2.Emergency Stop&Key enabling system for HV 3. Switch control of HV motor power

____________________

Time : 2 minOperators : B

1

Page 15: Instruction Manual for inserting the CMS  ZDCs  using the crane

15

STEP 1Op.9: Control System Activation(B) 1.Power-ON(LV)2.Emergency Stop&Key enabling system for HV 3. Switch control of HV motor power

____________________

2

Page 16: Instruction Manual for inserting the CMS  ZDCs  using the crane

16

STEP 1Op.9: Control System Activation(C) 1.Power-ON (LV)2.Emergency Stop&Key enabling system for HV 3. Switch control of HV motor power

____________________

3

Page 17: Instruction Manual for inserting the CMS  ZDCs  using the crane

17

command button (rotate to TAN)

command button (rotate to SARCO)

command button (move UP)

command button (move DOWN)

Indicator light (move UP)

Indicator light (move DOWN)

Indicator light (rotate to TAN)

Indicator light (rotate to SARCO)

STEP 1Op.10: Crane rotation to SARCO (A) Push the command button and keep it pushed to rotate the crane to SARCO

____________________

Time : 5 minOperators : B

Page 18: Instruction Manual for inserting the CMS  ZDCs  using the crane

18

STEP 1Op.10: Crane rotation to SARCO (B) Wait until the crane is completely extended over the SARCO

____________________

Page 19: Instruction Manual for inserting the CMS  ZDCs  using the crane

19

STEP 1Op.8: Install elevator servo motor 1) Connect cables to Baldor BSM63 servo motor

2) Connect motor to the crane.

____________________

Time : 4 minOperators : A and B

Page 20: Instruction Manual for inserting the CMS  ZDCs  using the crane

20

STEP 2Op.1: Rotate crane to TAN and lower elevator to ZDC 1. Bring back the

crane in the starting position over the TAN.

2. Then lower the Overhead Beam of the Vertical Elevator close to the ZDC Module

____________________

Time : 5 minOperators : B

b

a

Page 21: Instruction Manual for inserting the CMS  ZDCs  using the crane

21

A

View « A »

STEP 2Op.2: Aline elevator to ZDC Lower the Overhead Beam of the Vertical Elevator until the holes on Lifting Bridge shoe (1) are Alined with the holes on the ZDC supports (2)____________________

Time : 2 minOperators : A and B

1

2

Page 22: Instruction Manual for inserting the CMS  ZDCs  using the crane

22

STEP 2Op.3: Fasten vertical elevator to ZDC Fastening of the Lifting Bridge shoe to the ZDC supports with screws and nuts

Reference List :

1. M12 screw (4)2. M12 Nut (4)____________________

Time : 3 minOperators : A and B

1

2

Page 23: Instruction Manual for inserting the CMS  ZDCs  using the crane

23

STEP 2Op.4: Extract the ZDC Lift the ZDC calorimeter out of the TAN ____________________

Time : 2 minOperators : B

Page 24: Instruction Manual for inserting the CMS  ZDCs  using the crane

24

STEP 2Op.5: Rotate crane and insert ZDC in SARCO

1. Rotate the crane until completely extended over the SARCO

2. Insert the ZDC calorimeter into the SARCO

____________________

Time : 4 minOperators : B

Page 25: Instruction Manual for inserting the CMS  ZDCs  using the crane

25

STEP 2Op.6: Unfasten ZDC

Remove the 4 screws and the 4 nuts from the ZDC supports

____________________

Time : 1 minOperators : A

Page 26: Instruction Manual for inserting the CMS  ZDCs  using the crane

26

STEP 2Op.7: Store ZDC in bunker

Bring the sarcophaguscontaining the ZDC tothe bunker

____________________

Time : 4 minutesOperators : A

Page 27: Instruction Manual for inserting the CMS  ZDCs  using the crane

27

STEP 3Op.1: Raise crane to make space for steel bars. Raise the Overhead

Beamof the Vertical Elevator10cm____________________

Time : 2 minOperators : B

a

Page 28: Instruction Manual for inserting the CMS  ZDCs  using the crane

28

STEP 3Op.2: Bring steel bars to TAN using transpallet____________________

Time : 5 minutesOperators : A

Page 29: Instruction Manual for inserting the CMS  ZDCs  using the crane

29

A

View « A »

STEP 3Op.3:Lower elevator to steel bars Lower the Overhead Beam of the Vertical Elevator until the holes on Lifting Bridge shoe (1) are Alined with the holes on the supports of the steel bars (2)____________________

Time : 1 minOperators : B

1

2

Page 30: Instruction Manual for inserting the CMS  ZDCs  using the crane

30

STEP 3Op.4: Fasten elevator to steel bars Fastening of the Lifting Bridge shoe to the steel bar supports with screws and nuts

Reference List :

1. M12 screw (4)2. M12 Nut (4)____________________

Time : 4’Operators : A and B

1

2

Page 31: Instruction Manual for inserting the CMS  ZDCs  using the crane

31

STEP 3Op.5: Extraction of bars and rotation over TAN

a) Extract the bars from the SARCO

b) Rotate the crane until the bars are over the TAN.

____________________

Time : 5 minOperators : B

Page 32: Instruction Manual for inserting the CMS  ZDCs  using the crane

32

STEP 3Op.6: Insertion of bars in TAN Lower the steel bars into the TAN ____________________

Time : 3 minOperators : B

Page 33: Instruction Manual for inserting the CMS  ZDCs  using the crane

33

STEP 3Op.7: Disconnect elevator from bars Unscrew nuts that link bridge shoe to the bars and then remove screws.

Reference List :

1. M12 screw (4)2. M12 Nut (4)____________________

Time : 1 minOperators : A and B

1

2

Page 34: Instruction Manual for inserting the CMS  ZDCs  using the crane

34

STEP 4Op.1: Move empty crane over sarco Lift the elevator bar and rotate crane over empty sarco____________________

Time : 4 minOperators : B

Page 35: Instruction Manual for inserting the CMS  ZDCs  using the crane

35

STEP 4Op.2: Disconnect servo motor from vertical elevator 1) Unbolt Baldor

BSM63 Servo motor

2) 2 disconnect cables

____________________

Time : 2 minOperators : A and B 2

1

Page 36: Instruction Manual for inserting the CMS  ZDCs  using the crane

36

STEP 4Op.3: Move empty crane back over TAN Rotate crane over empty sarco____________________

Time : 3 minOperators : B

Page 37: Instruction Manual for inserting the CMS  ZDCs  using the crane

37

STEP 4Op.4: Take empty sarco back to bunker

____________________

Time : 4 minutesOperators : A

Page 38: Instruction Manual for inserting the CMS  ZDCs  using the crane

38

STEP 4Op.5: Remove rotation servo motor1) Uncable Baldor

BSM90 servo motor

2) Loosen and remove bolts

3) Take off motor

________________

Time : 4 minOperators : A and B

3

2

1

Page 39: Instruction Manual for inserting the CMS  ZDCs  using the crane

39

STEP 4 Op.6: Pull up contol cablesGather up the cables from the Control System to the Crane.

____________________

Time : 2Operators : A and B

20meters

Page 40: Instruction Manual for inserting the CMS  ZDCs  using the crane

40

STEP 4Op.7: Disconnect Cables from control system Connections (A)

____________________

Time : 4Operators : A and B

Page 41: Instruction Manual for inserting the CMS  ZDCs  using the crane

41

STEP 1Op.7: Disconnect cable from contorl system (B)

Reference List :

1. B90_PWR cable2. B90_RES cable3. B63_PWR cable4. B63_RES cable5. Limit_Switch cable6. SPARE 7. Handset cable8. 220v 15A

____________________

Time : 3 minOperators : A and B

8

1 2 37

5

4

6

Page 42: Instruction Manual for inserting the CMS  ZDCs  using the crane

42

STEP 4Op. 8: Bring materials backBring control cabinet , remote control, motors, and cables upstairs.

Reference List : 1. Control Cabinet2. Remote Command

Handset3. Baldor BSM90

Servo motor (Rotation)

4. Baldor BSM63 Servo motor(vertical axis)

5. Cables

____________________

Time : 15 minOperators : A and B

1

34

25