installation & maintenance foc
TRANSCRIPT
-
7/27/2019 Installation & Maintenance FOC
1/184
1
-
7/27/2019 Installation & Maintenance FOC
2/184
2
(FITL)
-
7/27/2019 Installation & Maintenance FOC
3/184
3
WHY FIBRE OPTICS
. DIGITALISATION OF LOCAL NETWORK
. MEETING FUTURE CUSTOMER NEEDS
(BOARD BANDWITH SERVICE)
. POTENCIAL COST-EFFECTIVENESS
. BETTER QUALITY, RELIABILITY AND
MAINTAINABILITY
. WIDER COVERAGE FOR EXCHANGES
. INFORMATION SECURITY
. REDUCE CONGESTION OF UNDERGROUND FACILITIES
-
7/27/2019 Installation & Maintenance FOC
4/184
4
DISADVANTAGES
. DELICATE TO HANDLE
. CRAFT SENSITIVE
- SPLICING
- EQUIPMENT
. GENERALLY STILL EXPENSIVE
- EQUIPMENT
- TOOLS AND TEST EQUIPMENT
. REQUIREMENT FOR FIELD EQUIPMENTS POWERING
-
7/27/2019 Installation & Maintenance FOC
5/184
5
SYSTEM AND FACILITIES
REQUIREMENTS
. CABLE AND ACCESSORIES
. TERMINAL EQUIPMENTS
. EQUIPMENT SPACE AND RACKING
. POWER SUPPLY
. SKILLED MANPOWER
-
7/27/2019 Installation & Maintenance FOC
6/184
6
TYPES OF APPLICATION
i) FIBRE TO THE OFFICE (FTTO)- FIBER IS TERMINATED DIRECT IN THE CUSTOMERS
PREMISES, CATERING TO DEMANDS OF COPPORATE
SECTOR.
ii) FIBRE TO THE STREET (FTTS)
- FIBER IS TERMINATED AT A POINT WHERE THERE IS A
CONCENTRATION OF DEMAND. THE DISTRIBUTION CABLE
WILL BE ON COPPER.
iii) FIBRE TO THE CURB (FTTC)
- SIMILAR TO THE FTTS BUT FIBRE IS BROUGHT NEARER TO
CUSTOMERS AND THE LAST APPROXIMATE 100M IS UNDERTAKEN BY
COPPER
-
7/27/2019 Installation & Maintenance FOC
7/184
7
TYPES OF APPLICATION
iv) FIBRE TO THE HOME (FTTH)- FIBER IS LAID DIRECT INTO INDIVIDUAL HOMES.
v) FIBRE TO THE ZONE (FTTZ)
- FIBER IS TERMINATED AT A POINT WHERE THEREIS A CENTRA .
-
7/27/2019 Installation & Maintenance FOC
8/184
8
MDF
PSTN
EXCHANGE
TUNNELMAINHOLE
DUCT
JOINT BOX
SHOP HSE OR
LOW-RISE
APARTMENT
RESIDENTIAL
HSES.
MULTI-STOREY
BLDG.
LOCAL
EXCHANGE A SDF
CABINET
AERIAL CABLE
DROP WIRE
DISTRIBUTIONPOINT
U/G COPPER
CABLE
TYPICAL SCHEMATIC DIAGRAM OF ACCESS NETWORK
LOCAL
EXCHANGE B
-
7/27/2019 Installation & Maintenance FOC
9/184
9
MDF
PSTN
EXCHANGE
TUNNELMAINHOLE
DUCT
JOINT BOX
SHOP HSE OR
LOW-RISE
APARTMENT
RESIDENTIAL
HSES.
MULTI-STOREY
BLDG.
LOCAL
EXCHANGE A SDF
FIBRE
CABINET
(FTTS)
AERIAL CABLE
DROP WIRE
DISTRIBUTIONPOINT
COT
RT
RT
(FTT0)
FIBRE
CABLE
TYPICAL SCHEMATIC DIAGRAM OF LOCAL NETWORK
LOCAL
EXCHANGE B
-
7/27/2019 Installation & Maintenance FOC
10/184
10
-
7/27/2019 Installation & Maintenance FOC
11/184
11
SYSTEM FOR OPTICAL TRANSMISSION
Optical transmission system are used fortransmission of electrical signal via anoptical fibre.
The component are:-(i) electro- optic transducer as the lighttransmitter at the beginning of the route.
(ii) The fibre optic transmission medium.(iii) Optic electric transducer as the lightreceiver at the end of the route.
-
7/27/2019 Installation & Maintenance FOC
12/184
12
Electrical signal from the Exchange is converted toOptical (using light as carrier) by Optical equipment
(DLC) at the COT. From the equipment, the light
signal is injected into the optical fibre. The light signalis guided by the fibre to its destination where it is
detected and converted back into electrical signal
again.
-
7/27/2019 Installation & Maintenance FOC
13/184
13
TRANSMISSION SYSTEM FOR DIGITALSIGNALS
Bit Rate (rounded Mbps)Number of 64 kbpschannel
2 30
8 120
34 480
140 1920
565 7680
PDH System with higher number of channels transmit bitrates of 8, 34, 140, 565 Mbps signals of the PCM 30
multiplexing unit.
-
7/27/2019 Installation & Maintenance FOC
14/184
14
SDH
SYSTEMMAX.2M MAX. CHANNEL.
STM1 63 1890 (63X30C)
STM4 252 7560 (252X30C)
STM16 63 X 2M X 16 30240 (1008X2M)
SDH (SYNCHRONOUS DIGITALHIERACHY)
TRANSMISSION SYSTEM FOR DIGITALSIGNALS
-
7/27/2019 Installation & Maintenance FOC
15/184
15
-
7/27/2019 Installation & Maintenance FOC
16/184
16
NETWORK TOPOLOGY
3 BASIC TYPES ARE:-
I) STAR
II) BUS
III) LOOP - STAR
TOPOLOGY ADOPTED BY TELEKOM
MALAYSIA BHD. :-
I) STAR
II) LOOP - STAR
-
7/27/2019 Installation & Maintenance FOC
17/184
17
NON-REDUCTIONAL LOOP + SWITCH-STAR WITH SHARED RESOURCE
Practical way to change the configuration
EXCHANGE EXCHANGE
-
7/27/2019 Installation & Maintenance FOC
18/184
18
-
7/27/2019 Installation & Maintenance FOC
19/184
19
STAR NETWORK CONFIGURATION
EXCHANGE
EXCHANGE
-
7/27/2019 Installation & Maintenance FOC
20/184
20
LOOP NETWORK
CONFIGURATION(1+1)
EXCHANGE
-
7/27/2019 Installation & Maintenance FOC
21/184
21
-
7/27/2019 Installation & Maintenance FOC
22/184
22
Basic Structure of an optical
fiber
-
7/27/2019 Installation & Maintenance FOC
23/184
23
THE CORE PERFORMS THE FUNCTION OF TRANSMITTING THE
LIGHT WAVES, WHILE THE CLADDING IS TO MINIMIZE SURFACE
LOSSES AND TO GUIDE THE LIGHT WAVES.
Basic Structure of an optical
fiber
-
7/27/2019 Installation & Maintenance FOC
24/184
24
OPTICAL FIBRE CONSTRUCTION
HIGH REFRACTIVE
INDEX
LOW REFRACTIVE
INDEX
-
7/27/2019 Installation & Maintenance FOC
25/184
25
Basic Structure of an optical fiber
Core 10 um
Cladding 125 um
Primary coating
250 umSecondary coating
-
7/27/2019 Installation & Maintenance FOC
26/184
26
TYPES OF OPTICAL FIBRE
TYPE
REFRACTIVE INDEX
PROFILE
LIGHT PROPAGATION
STEP - INDEX
MULTIMODE
GRADED -
INDEX
MULTIMODE
SINGLE -
MODE
100-200 50 - 100 LS
125 50 LS
125 LS
10
DIMENSION IN um LS = LIGHT
SOURCE
-
7/27/2019 Installation & Maintenance FOC
27/184
27
TYPE
INPUT PULSE LIGHT PROPAGATION
STEP - INDEX
MULTIMODE
GRADED -
INDEX
MULTIMODE
SINGLE -
MODE
LS
LS
LS
OUTPUT
PULSE
OPTICAL FIBRE PULSE DISTRORATION
PULSE DISTRORATION DETERMINE THE BANDWIDTH OF OPTICAL FIBRES.
-
7/27/2019 Installation & Maintenance FOC
28/184
28
CONSTRUCTION OF SLOTTED CORE OPTICAL
FIBER CABLE
-
7/27/2019 Installation & Maintenance FOC
29/184
29
125um 190um 250um
Ultra Violet Curable Acrylate Coated Fiber
Silica Fiber
SoftUV
Hard UV
CONSTRUCTION OF SLOTTED CORE OPTICAL FIBER
CABLE
-
7/27/2019 Installation & Maintenance FOC
30/184
30
CONSTRUCTION OF SLOTTED CORE OPTICAL FIBER CABLE
Nylon Coated Fiber
Silica Fiber
Silicon
Resin
Nylon
125um 400um 900um
-
7/27/2019 Installation & Maintenance FOC
31/184
31
FIBER
NO.4 FIBER 6 FIBER 8 FIBER 12 FIBER
1 BLUE BLUE BLUE BLUE
2 YELLOW YELLOW YELLOW YELLOW
3 GREEN GREEN GREEN GREEN
4 RED RED RED RED
5 VOILET VOILET VOILET
6 WHITE BROWN BROWN
7 WHITE WHITE
8 WHITE WHITE
9 WHITE
10 WHITE
11 WHITE12 WHITE
-
7/27/2019 Installation & Maintenance FOC
32/184
32
OPTICAL FIBRE
FILLING COMPOUND
SLOT
CENTRAL STRENGTH
MEMBER
WRAPPING
SHEATH
-
7/27/2019 Installation & Maintenance FOC
33/184
33
-
7/27/2019 Installation & Maintenance FOC
34/184
34
-
7/27/2019 Installation & Maintenance FOC
35/184
35
Cross-section of four (4)fiber Ribbon
Optical fiberPrimary coating Jacketing ( u v
cured material)
0.4mm
1.1mm
CROSS SECTION OF COMPLETED
-
7/27/2019 Installation & Maintenance FOC
36/184
36
4 - FIBRE RIBBON
FILLING COMPOUND
SLOT
CENTRAL STRENGTH
MEMBER
WRAPPING
SHEATH
RIB IDENTIFICATION
MARKING
CROSS-SECTION OF COMPLETED
CABLE 24 FIBER RIBBON
-
7/27/2019 Installation & Maintenance FOC
37/184
37
CROSS-SECTION OF
COMPLETED CABLE
48 FIBER RIBBON
CROSS SECTION OF 4 FIBER
-
7/27/2019 Installation & Maintenance FOC
38/184
38
CROSS-SECTION OF 4 FIBER
RIBBON IN A GROOVE OF SLOT
TAPE A
TAPE B
TAPE C
TAPE D
FOR CORE NO.1 - 24
FOR CORE NO.
25 - 48
FOR CORE NO.
49 - 72
FOR CORE NO.
73 - 96
-
7/27/2019 Installation & Maintenance FOC
39/184
39
LOOSE TUBE
FIBRE CABLE
AMOURED
FIBRE CABLE
CONSTRUCTION OF LOOSE BUFFERED TUBE OPTICAL FIBER CABLE
-
7/27/2019 Installation & Maintenance FOC
40/184
40
Petroleum Jelly
Two RipcordsFiller
Core wrapping
Strength member
Buffered Tube
Thixotropic Jelly
Fiber
Outer PE sheath
CONSTRUCTION OF LOOSE BUFFERED TUBE OPTICAL FIBER CABLE
6 core
CONSTRUCTION OF LOOSE BUFFERED TUBE OPTICAL FIBER CABLE
-
7/27/2019 Installation & Maintenance FOC
41/184
41
CONSTRUCTION OF LOOSE BUFFERED TUBE OPTICAL FIBER CABLE
Buffered Tube
PE CoatingStranded wire
PE web
36 core
CONSTRUCTION OF LOOSE BUFFERED TUBE OPTICAL FIBER CABLE
-
7/27/2019 Installation & Maintenance FOC
42/184
42
Petroleum Jelly
Two Ripcords
PE Coating
Core wrapping
Strength member
Buffered Tube
Thixotropic Jelly
Fiber
Outer PE sheath
96 core
-
7/27/2019 Installation & Maintenance FOC
43/184
43
FIBER
NO.
FIBER
COLOUR
TUBE
NO.
TUBE
COLOUR
FIBER
NO.
FIBER
COLOUR
TUBE
NO.
TUBE
COLOUR
1 BLUE 1 BLUE 19 BLUE 4 RED
2 YELLOW 20 YELLOW
3 GREEN 21 GREEN
4 RED 22 RED
5 VOILET 23 VOILET
6 BROWN 24 BROWN
7 BLUE 2 YELLOW 25 BLUE 5 VOILET
8 YELLOW 26 YELLOW
9 GREEN 27 GREEN
10 RED 28 RED
11 VOILET 29 VOILET
12 BROWN 30 BROWN
13 BLUE 3 GREEN 31 BLUE 6 BROWN
14 YELLOW 32 YELLOW15 GREEN 33 GREEN
16 RED 34 RED
17 VOILET 35 VOILET
18 BROWN 36 BROWN
-
7/27/2019 Installation & Maintenance FOC
44/184
44
FIBER
NO.
FIBER
COLOUR
TUBE
NO.
TUBE
COLOUR
FIBER
NO.
FIBER
COLOUR
TUBE
NO.
TUBE
COLOUR
1 BLUE 25 BLUE
2 YELLOW 26 YELLOW
3 GREEN 27 GREEN4 RED 28 RED
5 VOILET 29 VOILET
6 BROWN 30 BROWN
7 PINK 31 PINK
8 GREY 32 GREY
9 BLUE 33 BLUE
10 YELLOW 34 YELLOW
11 GREEN 35 GREEN12 RED 36 RED
13 VOILET 37 VOILET
14 BROWN 38 BROWN
15 PINK 39 PINK
16 GREY 40 GREY
17 BLUE 41 BLUE
18 YELLOW 42 YELLOW
19 GREEN 43 GREEN
20 RED 44 RED
21 VOILET 45 VOILET
22 BROWN 46 BROWN
23 PINK 47 PINK
24 GREY 48 GREY
RED
VOILET
BROWN
1
2
3
4
5
6
BLUE
YELLOW
GREEN
-
7/27/2019 Installation & Maintenance FOC
45/184
45
FIBER
NO.
FIBER
COLOUR
TUBE
NO.
TUBE
COLOUR
FIBER
NO.
FIBER
COLOUR
TUBE
NO.
TUBE
COLOUR
49 BLUE 73 BLUE
50 YELLOW 74 YELLOW
51 GREEN 75 GREEN52 RED 76 RED
53 VOILET 77 VOILET
54 BROWN 78 BROWN
55 PINK 79 PINK
56 GREY 80 GREY
57 BLUE 81 BLUE
58 YELLOW 82 YELLOW
59 GREEN 83 GREEN60 RED 84 RED
61 VOILET 85 VOILET
62 BROWN 86 BROWN
63 PINK 87 PINK
64 GREY 88 GREY
65 BLUE 89 BLUE
66 YELLOW 90 YELLOW
67 GREEN 91 GREEN
68 RED 92 RED
69 VOILET 93 VOILET
70 BROWN 94 BROWN
71 PINK 95 PINK
72 GREY 96 GREY
7
8
9
10
11
12
PINK
GREY
BLACK
IGHT BLU
WHITE
ORANGE
-
7/27/2019 Installation & Maintenance FOC
46/184
46
-
7/27/2019 Installation & Maintenance FOC
47/184
47
INSTALLATION OFSUB DUCTS
INSTALLATION OF SUB DUCT
-
7/27/2019 Installation & Maintenance FOC
48/184
48
INSTALLATION OF SUB-DUCT
Two types of sub-duct :-
i) PVC Sub-duct 32mm X 6M length, one end side with
spigot for jointing purpose.
ii) Corrugated sub-duct 32mm X 600M length per coil
complete with nylon string.
-
7/27/2019 Installation & Maintenance FOC
49/184
49
Existing copper duct route (Main duct) :-
New duct route for 100% optical fibre cable can goes up
to 300M to 500M per section C/W concrete encasement.
180220M
M/H M/H M/Hcopper duct route
SPECIAL CONDITIONS BEFORE INSTALLING A
-
7/27/2019 Installation & Maintenance FOC
50/184
50
SPECIAL CONDITIONS BEFORE INSTALLING A
CABLE INTO THE MAIN DUCT/SUB-DUCT
i) Cable must always be installed in an empty duct
ii) Under no circumstance may a second cable be
drawn into the duct later
iii) Max allowable only 60% of duct space use for cable
PURPOSED OF MAIN-DUCT
-
7/27/2019 Installation & Maintenance FOC
51/184
51
PVC Main - duct 100mm X 6M length, one end sidewith spigot for jointing purpose.
i) For pulling cable
ii) Easy for maintenance ( cable breakdown)
iii) For recovery of cable (easy drawing in/out cables
without opening the ground)
iv) Additional duct space allow future cabling to be
drawn in without opening ground for new duct
installation
v) Manholes and joint boxes at interval of duct route
enable easier maintenance
100mm
PURPOSED OF SUB - DUCT
-
7/27/2019 Installation & Maintenance FOC
52/184
52
i) To increase the capacity of the duct route system inside
the main-duct.
ii) To provide the fibre cable with protection/safety
iii) Also provide the fibre cable with additional protection
from the environment
iv) Ameans for fiture cable installation and removal
v) To allow additional cables to be place in the same routevi) Economical, to reduce the duct cost per cable
SELECTION OF MAIN DUCT FOR
-
7/27/2019 Installation & Maintenance FOC
53/184
53
i) Should be at least at the second layer of the main duct(to avoid possible damage due to cave in and etc.)
ii) For loop network configuration when using the same
duct route, chose the lowest and the second lowest
layer of the main duct routeiii) Can be installed in duct already occupied by existing
cables, only for short distance
-
7/27/2019 Installation & Maintenance FOC
54/184
54
Installation procedure
1. Preparation of duct
a. Cleared of obstruction
b. Roding- use rod sweep cane, pvc rod
c. Cleaning mandrel cutting,brushes and cleaning disc
best mandrel is 457 mm long x 83 mm diameter and
cylindrical brush 108 mm in diameter
2. Preparation of sub duct prior laying
a. Jointing of sub duct
b. Bunches of sub duct
c. Cutting of sub duct
3. Laying of sub duct
Manually as sesame as cable pulling
4 I t ll ti f t d b d t
-
7/27/2019 Installation & Maintenance FOC
55/184
55
4. Installation of corrugated sub duct
1. Preparation of sub duct bunch together with 3 layer
adhesive tape at every 1.5 meter interval long
2. Fit 1 meter pulling rod to every sub duct
3. Hold the end of sub duct, tightly together 800 mm
4. Pass the cable grip over + swivel
5. Laying of sub duct1. manually pulling
2. Max.Pulling force 80 KN(8160kg)
3. Max pulling speed is 15 meter/minute
4. Use swivel to avoid twittering during hauling
5. 3 sub duct (34 mm )to be installed simultaneously in107 mm duct
-
7/27/2019 Installation & Maintenance FOC
56/184
56
6. After pulling in
1. cut 60 mm from the sub duct mouth
2. Install O ring3. Install flange holder (B plate)
4. Install another O ring
5. Make I slit to secure the nylon rope
6. Fit end cap
7. Marking of sub duct.
1 st sub duct white
2 nd sub duct yellow
3 rd sub duct Green
-
7/27/2019 Installation & Maintenance FOC
57/184
57
8. Jointing sub duct
1. cut both sub duct perpendicularly
2. Remove all burr
3. Jointing sleeve 250 mm piece of sub duct
4. Wrap 10-12 turn
5. Pull one of the sub duct 50 mm out of the jointing sleeve6. Wrap another 12-15 turn
-
7/27/2019 Installation & Maintenance FOC
58/184
58
PULLING ROD TO BE INSERTED INTO SUB-
DUCT 1000mm
1000 mm pulling rod
-
7/27/2019 Installation & Maintenance FOC
59/184
59
Wrap the sub-duct with four turns of colour tape 100mm
from duct end.
1st Sub-duct colour white
2nd Sub-duct colour yellow
3rd Sub-duct colour green
-
7/27/2019 Installation & Maintenance FOC
60/184
60
Use of cable grip, swivel, D shackle and pulling rope
for pulling sub-duct into the main duct.
Bunching of three sub-ducts with adhesive tape
1.5m
Terminating corrugated sub-duct in manhole
-
7/27/2019 Installation & Maintenance FOC
61/184
61
Sub-duct inserted into the PVC Plate B
122mm X 122mm X 5mm
Bolt Expansion
(Iron Raw plug)
Rubber O ring
End Cap
Optic fibre cable 60mm
-
7/27/2019 Installation & Maintenance FOC
62/184
62
INSTALLATION OPTICAL
FIBER CABLESUB DUCTS
1. TOOLS AND MATERIAL
-
7/27/2019 Installation & Maintenance FOC
63/184
63
Tool name Usage
1. Safety cones
2. Barrier & barricades
3. Flashing Light
4. Flag
5. Canvas Tent &frame GI
6. Manhole key
7. Gas detector
8. Water pump
9. Portable generator
10. Exhaust fan/blower
11. Cable jack
Safety/traffic warning
Safety/traffic warning
Safety/traffic warning
Safety/traffic warning
Provide shade for workman
For opening the manhole cover
To detect dangerous gases
To remove water in manhole
To supply electrical power
To ventilate manhole
For cable drum jacking
-
7/27/2019 Installation & Maintenance FOC
64/184
64
Tool name Usage
12. roding tools (PVC Type)
13. Cable cutter
14. Cable grip
15. Shackle D
16. Swivel
17. Pulling rope
18. Cable roller
19. Cable guide
20. Dynamometer
21. PVC Sheeting
22. Cable winch
23. Pulley24. Cable trailer
For rodding or sub duct
To cut the cable
Grip cable for pulling
As a connector
To prevent cable twisting
For pulling the cable
To guide the cable into duct
To protect the cable against damage
To measure the pulling tension
Cable protection while forming F8
Pulling cable
To pull pulling rope out of manholeTo hold cable drum
2. MAXIMUM PULLING TENSION
-
7/27/2019 Installation & Maintenance FOC
65/184
65
Contract No of core
Max.pulling
force
TOMEN UP TO 48 CORE 1.7 KN(170kg)
MARCONI/HESFIBEL UP TO 96 CORE 1.1 KN(110kg)
OPCOM UP TO 96 CORE2KN(200kg)
PERWIRAERICSON
UP TO 96 CORE2.5KN(250kg)
-
7/27/2019 Installation & Maintenance FOC
66/184
66
3. LAYING SPEED : 15 meter / minute
4. BENDING RADIUS :10 D while setting20 D while pulling
4. LAYING MATHOD :
1. unidirectional pulling2. Bi-directional pulling3. Intermediate pulling
5. Diameter of figure 8 is min.1 meter
UNIDIRECTIONAL PULLING METHOD
-
7/27/2019 Installation & Maintenance FOC
67/184
67
Cable drum
Manhole
Pulled in a continuous operation in one direction only ( < 1 km)
In this case, the cable drum is placed at one of the manhole,and cable is pulled in a continuous operation in one direction
only.
-
7/27/2019 Installation & Maintenance FOC
68/184
68
In this case, the cable drum is placed at one of the manhole,
and cable is pulled in a continuous operation in one direction
only.
BI - DIRECTIONAL PULLING METHOD
-
7/27/2019 Installation & Maintenance FOC
69/184
69
When it is difficult to lay the whole cable length in one continuous
operation due to geographical configuration of cable route bi-
directional pulling is used. This method is mainly adopted for
complicated cable route having curves or level differences of ducts
at pull-through manholes.
Bi-directional Pulling Method
Bi-directional Pulling Method
-
7/27/2019 Installation & Maintenance FOC
70/184
70
This method is recommended for complicated cable routes having
curves or level differences of sub-duct at pull through
manholes and or cable lengths greater than 1km.
a) Place the cable drum at the midpoint of the section.
b) Pull the cable towards one directions until it reaches its
destination.
c) Uncoil the balance of the cable in the drum for the second
pull. A PVC sheet placed on the ground to protect the cable
while forming the Figure 8.
d) A suitable space measuring about 6m x 3m is necessary for
uncoiling the cable. This operation is shown in figure 8. Pull
the cable end of the uncoiled cable in the other direction.
-
7/27/2019 Installation & Maintenance FOC
71/184
71
As illustrated in figure 6. A cable is placed at the corner of the cable
route and the cable is laid in two steps. In the first pull, a longerlength is laid into duct in continuous operation. The remaining
shorter cable on the same cable drum is uncoiled for the second
pull. The cable should be coiled on the ground in the form of
figure 8. This will be enable the remaining cable to pull in the
other direction easily. The diameter of figure 8 should be greaterthan 1 meter. Fig 7 show the uncoiling of the remaining cable in the
drum.
-
7/27/2019 Installation & Maintenance FOC
72/184
72
Pulling a long cable with sharp bends.
Figure 8a and 8b shows how bi-directional pulling is used in route withsharp bends.
a) Place the cable drum at the chosen corner manhole.
b) First pull in the direction indicated as (1)-fig 8a
c) Uncoil the balance of the cable in the drum in the form of a
Figure 8 at the position (2)
d) The second pull is in the opposite direction that toward (3) (Fig 8b)
and (4)-(Fig 8b)
METHOD OF CABLE LAYING INTO SUBDUCTS
-
7/27/2019 Installation & Maintenance FOC
73/184
73
BI - DIRECTIONAL PULLING METHOD
Manhole
2) Making of Figure
8
1) Direction of first
pull
3) Direction of second
pull
O O C NG N O SU UC S
Intermediate Manual Pull
-
7/27/2019 Installation & Maintenance FOC
74/184
74
Intermediate Manual Pull
This method is recommended for pulling cable in straight routeand with distance greater than 1 km.
a. Place the cable drum at the end of the cable length.
b. Pull the cable towards one of the splice location.
c. After pulling the cable through four or five manhole say 1
km, take the cable out of the manhole and coil it on the
ground to form the figure 8. Continue this process until
the cable in the drum as completely uncoiled. Turn the coiled
figure 8 cable over to get the pulling end to continue withthe cable pulling process.
-
7/27/2019 Installation & Maintenance FOC
75/184
75
Here we have a number of pull-through manholes assistance is
needed in the intermediate manholes. A man is stationed in each
intermediate manholes. A manholes manually assisting in the cable
pulling process ( hand-over-hand) as it passes through. This reduce
the effective tail load at the manhole. As a result, the maximumpulling tension is substantially reduced. Figure 9 shows the
intermediate manual assisted cable pulling.
METHODs OF CABLE LAYING INTO SUBDUCTS
-
7/27/2019 Installation & Maintenance FOC
76/184
76
INTERMEDIATE PULLING METHOD
2) Making of
Figure 81) Direction of
first pull
3) Direction of second
pull
4) The next drum of
cable
Greater than 1 km
Colling Of Remaining Shorter Cable
Why figure 8..?
-
7/27/2019 Installation & Maintenance FOC
77/184
77
Manhole
Uncoil the balance of the cable in the
drum for the second pull. A PVC sheet
(6M X 3M) placed on the ground to
protect the cable while forming the
Figure 8.
Why figure 8..?To reduce pulling tension
CABLE FEEDING ENDARRANGEMENT OF MANPOWER FOR
CABLE PULLING
-
7/27/2019 Installation & Maintenance FOC
78/184
78
Cable rollerCable Jack
Cable Protecting Bend
ARRANGEMENT OF MANPOWER FOR
CABLE PULLINGCABLE FEEDING END
-
7/27/2019 Installation & Maintenance FOC
79/184
79
Cable feeder tube or
corrugated duct
Cable Jack
CABLE PULLING ENDARRANGEMENT OF MANPOWER FOR
CABLE PULLING
-
7/27/2019 Installation & Maintenance FOC
80/184
80The laying speed shall be less than 15 m/min.
Cable roller
Pulley Block
ChainsPulling rope
-
7/27/2019 Installation & Maintenance FOC
81/184
CABLE PULLING ENDARRANGEMENT OF MANPOWER FOR
CABLE PULLING
-
7/27/2019 Installation & Maintenance FOC
82/184
82
ARRANGEMENT OF MANPOWER FOR CABLE
PULLING AT INTERMIDIATE MANHOLE
-
7/27/2019 Installation & Maintenance FOC
83/184
83
Cable Protecting Bend Corrugated sub-duct to
replace the manpower.
ARRANGEMENT OF MANPOWER FOR CABLE
PULLING AT INTERMIDIATE MANHOLE
-
7/27/2019 Installation & Maintenance FOC
84/184
84
ARRANGEMENT OF MANPOWER FOR CABLE
PULLING AT INTERMIDIATE MANHOLE
-
7/27/2019 Installation & Maintenance FOC
85/184
85
STORING EXCESS CABLE
-
7/27/2019 Installation & Maintenance FOC
86/184
86
No Location Formula
1 Jointing manhole 3L+ 2w + H
2Pull throughmanhole 2H+ L
3Pull throughmanhole (potentialgrowth area
3L+ 2w + 2H
-
7/27/2019 Installation & Maintenance FOC
87/184
87
SETTING CABLE IN JOINTING MANHOLE
MIN. BENDING RADIUS 10 x
DAI. OF CABLE
-
7/27/2019 Installation & Maintenance FOC
88/184
88
SETTING CABLE IN PULL-THROUGH MANHOLE
MIN. BENDING RADIUS 10 x
DAI. OF CABLE
6. When bending the cable the following cable length
-
7/27/2019 Installation & Maintenance FOC
89/184
89
6 e be d g t e cab e t e o o g cab e e gtshould be kept straight :
- minimum 6 cm from duct inlet- minimum 6 cm from a cable joint end
7. All cable passing through manholes must be tiedto the cable bracket by using cable tie no.3
8. At jointing manhole, four additional cable bearerMust be installed at end wall to support cable ,
9. The space between the end of cable joint and theduct inlet 60 cm
-
7/27/2019 Installation & Maintenance FOC
90/184
90
10.The jointing closure is tight to to supporting
plate using cable tie no.6
11.To prevent the cable bearer bracket from floatinginstall anti floating device.
12. In manhole constructed at both end of bridge,
cable slack more than 100 cm to absorb cablecreep caused by expansion & contraction of cablelaid.
13. Important cable must be protected use helically
coiled protector.
LABELLING
-
7/27/2019 Installation & Maintenance FOC
91/184
91
1. Should be fitted 7 cm away from the cable joint.
2. Labeling information
a. Type and cable sizeb. Route name
c. Contract Numberd. Installation datee. Cable section code
3. Cable section comprises of :a. Network codeb. Cable section number
-
7/27/2019 Installation & Maintenance FOC
92/184
-
7/27/2019 Installation & Maintenance FOC
93/184
Minimum clearance :
-
7/27/2019 Installation & Maintenance FOC
94/184
94
LOCATION MINIMUM CLEARANCE
1 Along road 4.5 Meter
2 At road crossing 5,5 Meter
3 At railway crossing 6.7 Meter (not relevant)
4 From power cablesa. Less than 600
Volt
b. More than 600Volt
600 mm
2000 mm
-
7/27/2019 Installation & Maintenance FOC
95/184
95
2. The sag is 2% from span length(40 Meter-50 Meter = 1M)
MAX PULLING
3. MAXIMUM PULLING FORCE
-
7/27/2019 Installation & Maintenance FOC
96/184
96
CONTRACT NO.OF CORESMAX.PULLINGFORCE
TOMEN UP TO 36 8 KN(800kg)
MARCONI/HESFIBEL
UP TO 36 1.1 KN(110kg)
OPCOM UP TO 36 15KN(1500kg
PERWIRAERICSON UP TO 48 9KN(900kg)
4. Termination of IB OFC
-
7/27/2019 Installation & Maintenance FOC
97/184
97
a. Beginning and the end of route
b. Distribution pole
c. Angle pole deviation of the route isgreater than 400
d. All river and railway crossing
e. Poles where two cables are jointing.
f. Each end of isolated long span greaterthan 200 Meter.
1 Th i d di l ti
Integral Bearer wire earthling system
-
7/27/2019 Installation & Maintenance FOC
98/184
98
1. The required grounding location :
a. Dead end or terminal poles.b. Poles holding supporting wire for jointingclosures.c. At every interval of approximately 250 M
2. Type of openable jointing connector :a. HD 10 b.HD 12 A
3. The max.earth system is 1 ohm .
4. Earth wire size is 7/1.04 mm
Preformed gripBracket tubular pole
-
7/27/2019 Installation & Maintenance FOC
99/184
99
PVC tape
Thimble
Cable
Fig.1 Through Double Termination
-
7/27/2019 Installation & Maintenance FOC
100/184
100
L1 = Just sufficient to terminate bearer wire with correct size of
preformed grip + 200 mm
L2 = Just sufficient to terminate bearer wire with correct size of
preformed grip + 50 mm
-
7/27/2019 Installation & Maintenance FOC
101/184
-
7/27/2019 Installation & Maintenance FOC
102/184
-
7/27/2019 Installation & Maintenance FOC
103/184
NO TOOL NAME USE
-
7/27/2019 Installation & Maintenance FOC
104/184
104
1 Bolt cutter For cutting cable
2 Scissors For cutting wrapping
3 Optical Fibre Sheath Cutter For removal of cable sheath
4 Screw Driver Set For tightening screws
5 Tape Measuring For measurement
6 Allen Key For tightening nuts
7 Pliers Combination 8" For cutting tension member, etc
8 Knife Trimming Removing slot
9 Torque Wrench For tightening nuts
10 Adapter Spanner For tightening nuts
11 Fibre Cleaver For cutting glass fibre
12 Fibre Stripper To remove secondary coating
13 Buffer Tube Stripper
To remove PVC sheath of fibre
cord/buffer tube
14 SPLICING MACHINE For splicing fibre
-
7/27/2019 Installation & Maintenance FOC
105/184
-
7/27/2019 Installation & Maintenance FOC
106/184
-
7/27/2019 Installation & Maintenance FOC
107/184
-
7/27/2019 Installation & Maintenance FOC
108/184
PREPARING FIBER FOR SPICING
-
7/27/2019 Installation & Maintenance FOC
109/184
109
1. Removing secondary coating35 mm
2. Removing primary coatingpiece of gauge soaked
with alcohol.
3. Fiber cleaving16 mm
-
7/27/2019 Installation & Maintenance FOC
110/184
MAX. ESTIMATED SPLICING LOSS
Estimated splicing loss should be kept
-
7/27/2019 Installation & Maintenance FOC
111/184
111
p g p
low within the recommended valuesof:-
i) Fibre In The Loop (Local Cable) is 0.05
dB loss/splice.ii) Junction Cable is 0.05dB loss/splice.
iii)Trunk Cable is 0.03 dB loss/splice
CRACK
OBSERVATION OF SPLICE POINT
-
7/27/2019 Installation & Maintenance FOC
112/184
112
BUBBLE
SEPARATION
TOO THICK
TOO THIN
BUBBLE
Improper cleaving ofoptical fibre. Dust onf b d f
Cleave the fiberagain or change thel
TREATMENT OF DEFECTIVE SPLICE RESULTS
-
7/27/2019 Installation & Maintenance FOC
113/184
113
fibre end face. cleaver.
TOO THICK(Barrel)
Mulfunction of fusionsplice main body.
Adjust the spliceprogrammedparameter.
TOO THIN(Necking)
Abnormal discharge. Mulfunction of fusionsplice main body.
Adjust the spliceprogrammedparameter.(ARC POWER, etc.)
SEPARATIONImproper high rackingpower
Change the arcpower parameter
-
7/27/2019 Installation & Maintenance FOC
114/184
-
7/27/2019 Installation & Maintenance FOC
115/184
115
SPLICE CLOSURE KIT FOR OPTICAL FIBRE CABLEFUJIKURA TYPE
1. Sleeve halves
2 Centre band
11. Sealing tape
12. Sleeve gasket
SPLICE CLOSURE KIT FOR OPTICAL FIBRECABLE FUJIKURA TYPE
-
7/27/2019 Installation & Maintenance FOC
116/184
116
2. Centre band
3. Side clamp
4. Cable clamp
5. Tension member clamp
6. Slack tray
7. End seal block
8. Cable adapter
9. End cap
10. Tension member protector
12. Sleeve gasket
13. Fibre protection tube
14. Closure scal
-
7/27/2019 Installation & Maintenance FOC
117/184
-
7/27/2019 Installation & Maintenance FOC
118/184
RAYCHEM FOSC 400 TYPEFiber Optic Splice Closure
-
7/27/2019 Installation & Maintenance FOC
119/184
119
-
7/27/2019 Installation & Maintenance FOC
120/184
120
-
7/27/2019 Installation & Maintenance FOC
121/184
121
SETTING CABLE IN JOINTING MANHOLE
MIN. BENDING RADIUS 10 x
DAI. OF CABLE
-
7/27/2019 Installation & Maintenance FOC
122/184
-
7/27/2019 Installation & Maintenance FOC
123/184
INTERCONNECTION LOSS
-
7/27/2019 Installation & Maintenance FOC
124/184
124
Light Loss
Light Loss
Core diameter mismatch loss
( Core diameter of the TX Fibre is larger
than the core diameter of the RX Fibre)
INTERCONNECTION LOSS
-
7/27/2019 Installation & Maintenance FOC
125/184
125
Numerical Aperture Mismatch Loss
INTERCONNECTION LOSS
Core 2
Cladding
-
7/27/2019 Installation & Maintenance FOC
126/184
126
Core 1
Core 2
Concentricity and Ellipticity
( Alignment of the two cores connector loss)
ATTENUATION LOSS
Ray of light to
partially scatter
-
7/27/2019 Installation & Maintenance FOC
127/184
127
Light Loss
partially scatter
Rayleigh Scattering
Caused by microscopic non uniformities
in the optical fibre.
ATTENUATION LOSS
-
7/27/2019 Installation & Maintenance FOC
128/184
128
Obsorption
Caused by the molecular structure of the material,
impurities in the fibre, metal ions, OH ions (water)
and atomic defects (unwanted oxidized elements inglass composition).
MICROBENDING LOSS
ATTENUATION LOSS
-
7/27/2019 Installation & Maintenance FOC
129/184
129
CHANGES OF THE CORE DIAMETER, ROUGH
BOUNDARIES BETWEEN THE CORE AND
CLADDING, MECHANICAL STRESS, PRESSURE,
TENSION OR TWISTING.
-
7/27/2019 Installation & Maintenance FOC
130/184
-
7/27/2019 Installation & Maintenance FOC
131/184
-
7/27/2019 Installation & Maintenance FOC
132/184
132CHECK FOR MICROBENDING LOSS
MACROBENDING
LOSS
ATTENUATION LOSS
-
7/27/2019 Installation & Maintenance FOC
133/184
133
(i) Min. BENDING RADIUS OF CABLE10 X DIA. OF CABLE
(ii)Min. BENDING RADIUS OF FIBRE
40MM
50cm
-
7/27/2019 Installation & Maintenance FOC
134/184
134
CHECK FORMACROBENDING
LOSS
-
7/27/2019 Installation & Maintenance FOC
135/184
CHECK FOR MACROBENDING LOSS
-
7/27/2019 Installation & Maintenance FOC
136/184
136
SETTING CABLE IN JOINTING MANHOLE
MIN. BENDING RADIUS 10 x
DAI. OF CABLE
CHECK FOR MACROBENDING LOSS
-
7/27/2019 Installation & Maintenance FOC
137/184
137
SETTING CABLE IN PULL-THROUGH MANHOLE
MIN. BENDING RADIUS 10 x
DAI. OF CABLE
-
7/27/2019 Installation & Maintenance FOC
138/184
MATERIALS FOR FIBRE OPTIC CABLE
TEST
-
7/27/2019 Installation & Maintenance FOC
139/184
139
NO MATERIAL NAME USE REMARKS
1 COTTON BUD
For cleaning the
connectors and
optical detector.
2 ALCOHOLFor cleaning theconnectors and
optical detector.
Minimum
95% pure.
3 PACTH CORD
For pacthing at the
test eguipment and
Fibre DistributionFrame.
FC type
connector
TESTING AND COMMISSIONING OPTICAL
FIBRE SCHEME
-
7/27/2019 Installation & Maintenance FOC
140/184
140
1. Testing Optical Fibre Cable
The test to be conducted shall be as follows:
a. Cable End to End Loss
Maximum allowable loss between sending and receiving
stations
= aL +bN +C
a = Cable Loss dB/km, which is 0.40 or 1300 nm region
and 0.25 for 1550 nm region
where,
-
7/27/2019 Installation & Maintenance FOC
141/184
141
b = Average Loss per slice, which is 0.20 dB for RT and
0.1dB for Fokus and trunk lines.
C = Constant of 1 for Connector Loss (i.e 0.5 dB per
connector).
L = Cable Length (km).
N = Number of splice.
-
7/27/2019 Installation & Maintenance FOC
142/184
Splice loss
The maximum loss allowed shall be less than or equal to
0.20 dB for RT and 0.1dB for Fokus and Trunk lines. This
value shall be average value (measured from both sides of
the link using an OTDR)
-
7/27/2019 Installation & Maintenance FOC
143/184
143
the link using an OTDR).
The measured value at 1550 nm region shall not exceed that
measured at 1300 nm region by 0.15 db. The rationale of this
requirement is to ensure that the macro-bending and micro-
bending loses at 1550 nm is not excessive as a result of poor
installation practices at a jointing closures
http://www.gemini-inc.com/images/products/hp/8147big.htm -
7/27/2019 Installation & Maintenance FOC
144/184
144
installation practices at a jointing closures.
Any splices failing to meet the above criteria shall be respliced.
The acceptance test format used is as shown in App.1.
Core Reversal Test
This test is to ensure that the correct fibre cores ar
e
spliced together. It is to be tested at both sides of
the optical fibre link specifically at the FDF by
-
7/27/2019 Installation & Maintenance FOC
145/184
145
the optical fibre link specifically at the FDF by
using Fibre Identifier.
-
7/27/2019 Installation & Maintenance FOC
146/184
-
7/27/2019 Installation & Maintenance FOC
147/184
COMMISIONING
After testing have been successfully completed in the presence of
-
7/27/2019 Installation & Maintenance FOC
148/184
148
After testing have been successfully completed in the presence ofSuperintendent Officer (S.O) or his appointed representative, test
results shall be certified by both contractor and TMs S.O.
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE FROM
FDF TO FDF
CONTRACT NO: INDENT NO: STATE:
ROUTE: REGION: CORE:
ACTUAL DISTANCE: OTDR DISTANCE: NO. OF SPLICING: +(TB X 2)
WAVELENGHT: 1300nm / 1550nm
CABLE LOSS MEASUREMENT BY OTDR
CORE NO 1-2 LOSS (dB) REMARKS
1
-
7/27/2019 Installation & Maintenance FOC
149/184
149
2
3
4
5
6
PREPARED BY CONFIRMED BY TELEKOM MALAYSIANAME
SIGNATURE
DATE
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE
(EVERY SPLICING POINT)
CONTRACT NO: INDENT NO: STATE:
ROUTE: REGION: CORE:
ACTUAL DISTANCE: OTDR DISTANCE: NO. OF SPLICING: +(TB X 2)
WAVELENGHT: 1300nm / 1550nm
SPLICEP
OINT
CORE NO. TESTING
1 2 3 4 5 6 DATE BY
-
7/27/2019 Installation & Maintenance FOC
150/184
150
EQUIPMENT USED
PREPARED BY CONFIRMED BY TELEKOM MALAYSIAO.T.D.R.
SERIAL NO:
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE FROM FDF TO FDF
CONTRACT NO: INDENT NO: STATE:
ROUTE: REGION: CORE:
ACTUAL DISTANCE: OTDR DISTANCE: NO OF SPLICING:
CORE NO 1 2 LOSS (dB) REMARKS
CABLE LOSS MEASUREMENT BY OTDR
WAVELENGTH:
-
7/27/2019 Installation & Maintenance FOC
151/184
151
CORE NO. 1-2 LOSS (dB) REMARKS
1
2
3
4
5
6
78
9
10
11
12
PREPARED BYCONFIRMED BY TELEKOM
MALAYSIANAME
SIGNATURE
DATE
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE (EVERY SPLICING POINT)
CONTRACT NO:
ROUTE:
STATE:
CORE:
ACTUAL DISTANCE:
INDENT NO:
REGION:
OTDR DISTANCE:
TESTINGSPLICE
WAVELENGTH: 1300nm/1550nm
NO OF SPLICING: +(TBX2)
-
7/27/2019 Installation & Maintenance FOC
152/184
152
1 2 3 4 5 6 7 8 9 10 11 12 DATE BY
CONFIRMED BY TELEKOM
POINT
EQUIPMENT USED
OTDR:
SERIAL NO:
PREPARED BY
BASIC TERMS - OTDR
-
7/27/2019 Installation & Maintenance FOC
153/184
153
-
7/27/2019 Installation & Maintenance FOC
154/184
-
7/27/2019 Installation & Maintenance FOC
155/184
155
SPLICE LOSSCONNECTOR LOSSFAR-END FRESNAL
REFLECTION
NEAR-ENDFRESNAL
REFLECTION
-
7/27/2019 Installation & Maintenance FOC
156/184
156
OTDR
-
7/27/2019 Installation & Maintenance FOC
157/184
-
7/27/2019 Installation & Maintenance FOC
158/184
-
7/27/2019 Installation & Maintenance FOC
159/184
-
7/27/2019 Installation & Maintenance FOC
160/184
160
A reflection combined with a loss (as shown at the point of the bold
vertical bar labeled C) is usually either a mechanical splice or a
connector, but could also be acrackin the fibre. As the locations of
connectors and mechanical splices is normally known the
identification of the type of event should be easy.
-
7/27/2019 Installation & Maintenance FOC
161/184
Fibre Bend
-
7/27/2019 Installation & Maintenance FOC
162/184
162
Fusion Splice
AB
-
7/27/2019 Installation & Maintenance FOC
163/184
163
A point loss which has no reflection is usually either a fusion splice
or a bend. Again splice locations should be known so
differentiating between splices and bends is normally easy. Note
that if a good splice is testing really bad it can mean that their is a
bend nearby and the OTDR is not able to split the two close together
events.
The real splice loss isll
-
7/27/2019 Installation & Maintenance FOC
164/184
164
Backscatter coefficientFibre B > A
very small
A B
-
7/27/2019 Installation & Maintenance FOC
165/184
165
Here the level of backscatter before and after a fusion splice shows a
upwards trend, usually called a 'gainer splice' or simply a 'gain'. This isnot due to the splice having an actual gain but is instead a result of the
second fibre have a higher backscatter. If the OTDR was placed at the far
end of the fibre (so that we view from the higher backscatter fibre to the
lower one) then we would see a large loss through the same splice. The
actual splice loss is the average of the splice loss measured in bothdirections.
-
7/27/2019 Installation & Maintenance FOC
166/184
-
7/27/2019 Installation & Maintenance FOC
167/184
167
The end of this fibre shows a strong reflection as it is
terminated in a polished connector. If the end was
shattered or immersed in water (as can happen in a broken
cable situation) then there may be a smaller reflection or
no reflection at all.
-
7/27/2019 Installation & Maintenance FOC
168/184
Mismatch of Fibre Types
-
7/27/2019 Installation & Maintenance FOC
169/184
169
Single ModeFibre
Multi Mode
Fibre
You can use the OTDR to locate features or breaks
for a larger fibre core diameter, but not to measure
loss accurately.
Mismatch of Fibre Types
Position of features is
OK
-
7/27/2019 Installation & Maintenance FOC
170/184
170
Attenuation and loss iswrong!
Mismatch of Fibre Types
-
7/27/2019 Installation & Maintenance FOC
171/184
171
Single ModeFibre
Multi Mode
Fibre
You can use the OTDR to locate features or breaks
for a larger fibre core diameter, but not to measure
loss accurately.
SETTING LIGHT SOURCE & POWER METER
1. WARM UP THE METER SET AT LEAST 30 MIN.
2 SETTING LIGHT SOURCE:SET THE WAVE LENGTH
-
7/27/2019 Installation & Maintenance FOC
172/184
176
2. SETTING LIGHT SOURCE:SET THE WAVE LENGTH
ACCORDING TO THE TYPE OF FIBER LINK.
SETTING LIGHT SOURCE & POWER METER
P M d P h M dif l h
-
7/27/2019 Installation & Maintenance FOC
173/184
177
- Press Mode Param then Modify to select the
right wave length.
- Press Mode Param to set Attenuation to 0.00.
- Press Mode Param set to CW for complete
wave.
3. SETTING POWER METER:
- Set the wave length according to Light Source
setting.
- Press Param until you get T to set Average
-
7/27/2019 Installation & Maintenance FOC
174/184
178
Time , press Modify to set 200ms.
- Press Auto to set into Auto.
- Press dBm to set Unit into dBm
- Press N Dig to place decimal point XX.XX
CALIBRATION OF TWO POWER METERS :
-
7/27/2019 Installation & Maintenance FOC
175/184
179
To make the two power meters same reading.
- Press Mode Param until you get CAL ,then press Modify soft key to do calibration.
CONTRACT NO: INDENT NO: STATE:
ROUTE: REGION: CORE:
ACTUAL DISTANCE: OTDR DISTANCE: NO OF S PLICING:WAVE LENGTH:
1ST
2ND
3RD
DEVIATION V (E=MAX - MIN)
REP. CALIBRATION VALUE
E+ (P1-P2)/3
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE FROM FDF
(1) REPRESENTATIVE CALIBRATION VALUE OF THE POWER METER
P1 PP2 E=P1-P2
dBm dBm
REMARKSDESCRIPTION
dBm
-
7/27/2019 Installation & Maintenance FOC
176/184
180
1 2 3 4 5 6 7 8 9 10 11 12
INPUT LEVEL P IN: (1)
OUTPUT LEVEL P OUT: (2)
REP. CALIB. VALUE "E": (3)OPTICAL LOSS: (2)-(1)+(3)
(3) ALLOWANCE VALUE
NAME
SIGNATURE
DATE
Core No. (unit:dB)DESCRITION
ALLOWANCE VALUE (dB)
AVERAGE VALUE (dB)
MAXIMUM VALUE (dB)
OPTICAL POWER METER AT UPPER EXCH:
OPTICAL POW ER ME TER AT LOWER E XCH:
STABILIZED LIGHT SOURCE:
(2) OPTICAL LOSS OF END TO END
FORMULA(4) A LLOWANCE
VALUE IS CALCULATED BY THE
FOLLOWING FORMULA :
ALLOWANCE VALUE dB
0.4L+0.2N+1.0(const)
PREPARED BY CONFIRMED BY TELEKOM
CONTRACT NO: INDENT NO: STATE:
ROUTE: REGION: CORE:
ACTUAL DISTANCE: OTDR DISTANCE: NO OF SPLICING:
WAVE LENGTH:
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE FROM FDF
(1) REPRESENTATIVE CALIBRATION VALUE OF THE POWER METER
P1 P2 E=P1 P2
-
7/27/2019 Installation & Maintenance FOC
177/184
181
1ST
2ND
3RD
DEVIATION V (E=MAX - MIN)
REP. CALIBRATION VALUE
E+ (P1-P2)/3
P1 P2 E=P1-P2
dBm dBm
REMARKSDESCRIPTION
dBm
CONTRACT NO: INDENT NO: STATE:
ROUTE: REGION: CORE:
ACTUAL DISTANCE: OTDR DISTANCE: NO OF SPLICING:
WAVE LENGTH: * 1300nm / 1550nm
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE FROM FDF
(1) REPRESENTATIVE CALIBRATION VALUE OF THE POWER METER
P1 P2 E=P1-P2
-
7/27/2019 Installation & Maintenance FOC
178/184
182
1ST
2ND
3RD
DEVIATION V (E=MAX - MIN)
REP. CALIBRATION VALUE
E+ (P1-P2)/3
P1 P2 E=P1-P2
dBm dBm
REMARKSDESCRIPTION
dBm
CONTRACT NO: INDENT NO: STATE:
ROUTE: REGION: CORE:
ACTUAL DISTANCE: OTDR DISTANCE: NO OF SPLICING:
WAVE LENGTH: * 1300nm / 1550nm
(1) REPRESENTATIVE CALIBRATION VALUE OF THE POWER METER
P1 P2 E=P1-P2
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE FROM FDF
-
7/27/2019 Installation & Maintenance FOC
179/184
183
1ST
2ND
3RD
DEVIATION V (E=MAX - MIN)
REP. CALIBRATION VALUE
E= (P1-P2)/3
dBm dBm
REMARKSDESCRIPTION
dBm
20.48
61.3
20.34
60.51
P1 P2 E P1 P2
20.4 19.85 0.55
20.42 20.32 0.1
0.14
0.45
0.26
CONTRACT NO: INDENT NO: STATE:
ROUTE:WERE RD. - IPK REGION: CORE:6
ACTUAL DISTANCE: 4.623km OTDR DISTANCE:4.624km NO OF SPLICING: 3+(TBx2)
WAVE LENGTH: * 1300nm / 1550nm
(1) REPRESENTATIVE CALIBRATION VALUE OF THE POWER METER
P1 P2 E=P1-P2
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE FROM FDF
-
7/27/2019 Installation & Maintenance FOC
180/184
184
1ST
2ND
3RD
DEVIATION V (E=MAX - MIN)
REP. CALIBRATION VALUE
E= (P1-P2)/3
dBm dBm
REMARKSDESCRIPTION
dBm
20.3 20.27
P1 P2 E P1 P2
20.35 20.32
20.32 20.29
CONTRACT NO: INDENT NO: STATE:
ROUTE:WERE RD. - IPK REGION: CORE: 6
ACTUAL DISTANCE: 4.623km OTDR DISTANCE:4.624km NO OF SPLICING:3+(TBX2)
WAVE LENGTH: * 1300nm / 1550nm
THE LOSS DATA OF THE SINGLE MODE OPTICAL FIBRE CABLE FROM FDF
(1) REPRESENTATIVE CALIBRATION VALUE OF THE POWER METER
P1 P2 E=P1-P2
-
7/27/2019 Installation & Maintenance FOC
181/184
185
1ST
2ND
3RD
DEVIATION V (E=MAX - MIN)
REP. CALIBRATION VALUE
E= (P1-P2)/3
20.32 20.29 0.03
0.03
0
0.03
20.35 20.32 0.03
20.27
60.88
20.3
60.97
dBm dBm
REMARKSDESCRIPTION
dBm
1 2 3 4 5 6 7 8 9 10 11 12
INPUT LEVEL P IN: (1) 20.30 20.35 20.32 20.30 20.35 20.30
OUTPUT LEVEL P OUT: (2) 23.65 23.55 23.70 23.58 23.71 23.54
REP. CALIB. VALUE "E": (3)OPTICAL LOSS: (2)-(1)+(3)
(2) OPTICAL LOSS OF END TO END
Core No. (unit:dB)DESCRITION
-
7/27/2019 Installation & Maintenance FOC
182/184
186
(3) ALLOWANCE VALUE
NAME
SIGNATURE
DATE
FORMULA(4) ALLOWANCE
VALUE IS CALCULATED BY THE
FOLLOWING FORMULA :
aL+bN+C
ALLOWANCE VALUE dB
0.4L+0.2N+1.0(const)
Wlength 1300nm
AVERAGE VALUE (dB)
PREPARED BY CONFIRMED BY TELEKOM
MAXIMUM VALUE (dB)
OPTICAL POWER METER AT UPPER EXCH:
OPTICAL POWER METER AT LOWER EXCH:
STABILIZED LIGHT SOURCE:
ALLOWANCE VALUE (dB)
1 2 3 4 5 6 7 8 9 10 11 12
INPUT LEVEL P IN: (1) 20.30 20.35 20.32 20.30 20.35 20.30
OUTPUT LEVEL P OUT: (2) 23.65 23.55 23.70 23.58 23.71 23.54
REP. CALIB. VALUE "E": (3) 0.03 0.03 0.03 0.03 0.03 0.03OPTICAL LOSS: (2)-(1)+(3) 3.38 3.23 3.41 3.31 3.39 3.27
Core No. (unit:dB)DESCRITION
(2) OPTICAL LOSS OF END TO END
-
7/27/2019 Installation & Maintenance FOC
183/184
187
(3) ALLOWANCE VALUE
NAME
SIGNATURE
DATE
PREPARED BY CONFIRMED BY TELEKOM
MAXIMUM VALUE (dB) 3.41 coreno.3
OPTICAL POWER METER AT UPPER EXCH:
OPTICAL POWER METER AT LOWER EXCH:
STABILIZED LIGHT SOURCE:
ALLOWANCE VALUE (dB) 3.44dB
FORMULA(4) ALLOWANCE
VALUE IS CALCULATED BY THE
FOLLOWING FORMULA :
aL+bN+C
ALLOWANCE VALUE dB
0.4L+0.2N+1.0(const)
Wlength 1300nm
AVERAGE VALUE (dB) 3.33dB
1 2 3 4 5 6 7 8 9 10 11 12
INPUT LEVEL P IN: (1)
OUTPUT LEVEL P OUT: (2)
REP. CALIB. VALUE "E": (3)
OPTICAL LOSS: (2)-(1)+(3)
(3) ALLOWANCE VALUE
(2) OPTICAL LOSS OF END TO END
FORMULA(4) ALLOWANCE
Core No. (unit:dB)DESCRITION
-
7/27/2019 Installation & Maintenance FOC
184/184
188
(3) ALLOWANCE VALUE
NAME
SIGNATURE
DATE
FORMULA(4) ALLOWANCE
VALUE IS CALCULATED BY THE
FOLLOWING FORMULA :
aL+bN+C
ALLOWANCE VALUE dB
0.25L+0.1N+1.0(const)Wlength 1550nm
AVERAGE VALUE (dB)
PREPARED BY CONFIRMED BY TELEKOM
MAXIMUM VALUE (dB)
OPTICAL POWER METER AT UPPER EXCH:
OPTICAL POWER METER AT LOWER EXCH:STABILIZED LIGHT SOURCE:
ALLOWANCE VALUE (dB)