inside knowledge may ‘16storage.googleapis.com/wzukusers/user-14594296... · improvement in...
TRANSCRIPT
Inside Knowledge May ‘16
Plan A Consultants Ltd. Registered in England No. 967002.
www. PlanAConsultants.comLinkedIn | Twitter
Plan A Consultants was founded by Gerard Daws and Nick Willars and specialises in Design Management. We work within Design Teams to manage the design process and ensure the design is developed and delivered efficiently to meet all project stakeholder requirements.
[email protected]@planaconsultants.com
Plan A Consultants are passionate about Design Management. Over the past twenty years, we have worked with some of the world’s most creative designers. The purpose of ‘Inside Knowledge’ is to share our experience and knowledge of Design Management, provide guidance to those interested in the subject, and to inspire debate and discussion amongst peers.
Every couple of months, our thoughts on different topics and themes related to Design Management will be shared in Inside Knowledge. We welcome feedback and your thoughts on the content contained within each release.
(44) 020 7258 [email protected]
Plan A Consultants Ltd. Registered in England No. 967002. Plan A Consultants Ltd. Registered in England No. 967002.
What makes a valuable Design Programme?
by Nick Willars and Gerard Daws
the correct level of attention despite the obvious benefits both to the Lead Designer and the project. It is too often seen as a non-essential chore and a deliverable that can be ticked off once issued to the Project Manager. The Design Programme then rarely sees the light of day once submitted. They can likewise be produced in isolation without any input from the other consultants which nearly always results in mismatches in terms of interpretations and expectations.
A Design Programme is an absolute necessity for any Lead Designer to ensure that they are able to successfully define, co-ordinate and manage the delivery of the design. However, we believe that this management tool is not currently being used in way that maximises the benefits. We map out in this article why Design Programmes are important, why we believe they are not being used effectively and finally some tips to facilitate their preparation.
Before going any further, it is worth clarifying that there are different kinds of programmes for different purposes. It is important to differentiate between a Master Programme, and a Design Programme.
Generally produced by a Project Manager or Client representative, a Master Programme covers the complete project lifecycle (including construction) and is typically more strategic to reflect the high level decisions required.
A Design Programme conversely relates to only the activities within the design periods generally prepared on a stage by stage basis. As outlined in the RIBA plan of work 2013 Guide to Project Leadership, it is the Lead Designer’s responsibility to prepare a Design Programme that supports and coordinates with the Master Programme. It will need to provide a greater level of detail to explain how the design team is to progress the design.
Why is a Design Programme an important Design Management tool? Ultimately, it provides benefits to the project, Client and Design Team:
1. It gives confidence to Client/ Project Manager that there is a ‘plan’ and the Design Team is organized.2. Improvement in efficiency through mapping out when decisions and sign-offs need to be made and sign-offs.3. It can help to justify whether insufficient time has been included in a Master Programme.4. Aids resource planning.5. Enhances a ‘single team’ ethos across the Design Team through a document that everyone has bought into.6. Assists in accurate progress reporting and as a tool to support any claims, prolongations etc.
Given the benefits, it is bewildering to us as Design Managers that the Design Programme is not given
So what are the necessary steps when putting a Design Programme together? Check out some of the points below:
1. The format of the Design Programme should reflect the design stage. From experience, we use a ‘Route Map’ style format for the early design stages. This is to reflect the more strategic approach during RIBA stages 2 and 3. A common mistake is using a Gantt chart in the early stages which is inappropriate to what is an iterative process that needs to remain flexible so as not to compromise the creative nature of design. Typically the more traditional gantt chart is utilised during stage 4. The process is less about design and more about production and is therefore more linear with a greater level of predictability and exchange content. 2. Make sure that you obtain appropriate input from all of the relevant design team members. All too often, the Design Programme is produced in isolation and does not reflect a ‘team’ mentality which goes against the role of the Lead Designer. We lead Design Programme workshops where design disciplines can interactively map out what they need and when with a focus on objectives, tasks, decisions and sign-offs
(44) 020 7258 [email protected]
Plan of Work style programme showing design progression.
Prog:
Date :
Ref :
STRATEGIC CONCEPTUAL
DESIGN PROGRAMMEEARLS COURT MASTERPLAN
DESIGN MANAGEMENT
TITLE : PROJECT :
Sheet 1 of 1
0 (FOR REVIEW)
28/02/2012
20120228 pro 001 CD Programme Overview for TFP
05
1111
12
2222
19
3333
26
4444
30
----5555
06
----4444
13
----3333
27
----1111
20
----2222
02
5555
16
7777
23
8888
09
6666
04
14141414
11
15151515
18
16161616
25
17171717
30
9999
07
10101010
14
11111111
21
12121212
28
13131313
06 13 20 2702
18181818
09
19191919
23
21212121
30
22222222
16
20202020
Conceptual Design (4 weeks)
Commence Preliminary Design
31 Jan 11
Instruction to
proceed 05 March 12
TFP/KPF Issue 02
06 Apr 12
Com
men
cem
ent (
17 w
eeks
)
FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST
PM : Drawn :NW NW
BW05/07
Mobilise
Consultant Issue 01
(Sketch) 21 Apr 12
Co-ord
Undercroft Studies
KPF Deliverables
BriefReview
Costcheck AREAS
Rev :/001
Costcheck
1
Development and Co-ordination (12 weeks)
Production 3 weeks)
1 TFP/KPF Issue 01 02 Apr 12
Client
Review
LEGEND• Workshop Review• Document Review• TFP Activities• KPF Activities• Design Report• Capco• SMEP• Sub-Consultants• Cost
30 June 2012
objectives
1. Be in a position to allow the
resolution of the Reserved Matters to
commence
2. To improve cost certainty
(especially to deck level) more
accurately
3. To more accurately identify and
quantify risks and opportunities
4. To improve certainty of Phase 1
value
5. To capture design development
since the Planning Application
6. To develop the key Phase 1
elements so that the overall design
can be validated.
7. To be able to commence (detailed)
Pre-application consultations.
8. To allow a delivery strategy and
structure to be developed
9. To facilitate funding and confidence
in delivery
10. To work out optimum phasing and
sequencing.
11. To facilitate the preparation of
Marketing material
WV02-06KPF Parcel Design
Challenge Density and Massing.
Develop Architectural language
Outline Design
report
Capco Review
TFP Parcel Design
TFP/KPF Interim Issue 26 Mar 12
Inte
rim
Str
ate
gy v
alid
atio
n
Design Report
MobiliseBrief
Review
Test Strategies
Deck Studies
Structure, Services
cores, parking, Energy Centre
Existing constraints & Surveys Review LUL/TfL liaisonExisting Site Team KPF
Master-PlanTeam TFP
Undercroft Team KPF
Ground Plane Team TFP
Management Team
InterimReport
2
Develop ProjectExecution Plan
Capco
Review
Surveys Procurement Complete surveys
Undercroft designdevelopment
Massing Studies/options
Deck design development
TFP/KPF Interim
cost Issue 04 May 12
Consultant Co-ord
Refine Strategies(5 weeks)
Open Space Review
Town Planning Support(8 weeks)
KPF Parceldevelopment
TFP Parceldevelopment
Consultant Co-ord
Capco
Review
TFP Deliverables
2
Cost Plan Capco
Review
Design team
Meetings
Review Master PlanInterfaces and Implications
Existing Elements integration
3
Deliverables
Undercroft /Parcel integration
Ground Plane/ Parcel integration
TFP/KPF Issue 03
29 Jun 12
Consultant Delievables
Consultant Issue 02
29 Jun 12
Ground Plane/ Undercroft integration
Access, landscape, services
penetrations, Security
Capacity, Density, Open space,
places, Ground floor uses
Railways, Existing Deck, 3rd
party consultations
Risk/Opp Risk/ Opp mitigation
VE & Report
WV02-06
BW05
BW07
Revise Strategies
TFP Town Planning Support, S106 ReviewConditions
Planning Conditions Resolution
3rd PartyEngagement strategy
PreferredMassing development
Plan A Consultants Ltd. Registered in England No. 967002.
A plan of work style programme illustrating information exchange milestones aligned with meeting strategy.
required rather than deliverables. Likewise, factor in enough time to prepare the document so that all relevant consultants can check drafts prior to final submittal to the Client/ Project Manager. Don’t forget though that the Lead Designer (usually the Architect) should have the final say – it is contractually his responsibility to define the process by which the design will be progressed.3. The first step in mapping out an actual design stage is to identify and agree the overarching objectives of the stage. We say this because despite the RIBA attempting to tie down activities and outputs aligned with every work-stage, there is still overlap in design stages and a lack of clear definition. Clients tend to have their own objectives that don’t necessarily follow the same pattern from project to project – so make sure there is only one interpretation of this.
4. We have found from experience it pays to break each design stage down into interim milestones so that there are clearly defined periods for draft submissions and an opportunity for the Client to review work in progress. This is also important if you want to identify a progressive sign-off process with the Client/Project Manager. Likewise, it pays to include for regular cost reviews to avoid surprises at the completion of the design stage.5. Behind each interim milestone you should include a set of clear objectives which should in turn act as a navigation tool to steer you to the end of the workstage knowing that each step helps you to get there – thus making it easier to understand progress relative to time. Behind each interim milestone objective you should agree with all consultants what deliverables are required to meet those objectives, including their dependencies and ultimately what design activities they’re intended to inform. 6. At this stage of the design process, simply meeting the objectives at each milestone should satisfy over-zealous project managers that you are in fact on track – more often than not using deliverables alone will end in tears as most architects will produce 2/3 of their deliverables during the last third of a design stage working period.
7. What content should be included in a Design Programme? Long parallel bars in a gantt chart labelled ‘1:100 dwgs, 1:200 dwgs etc’ don’t really help anyone. It is our experience that unnecessary over-population of a programme contributes to them being either misunderstood, superceded the day after they’re issued or completely ignored. The RIBA 2013 Guide to Project Leadership provides an overview of key elements that a design programme must contain:
a. Start and completion of each stage.b. Client stage approval and sign-off period.c. Client and consultant review periods.d. Stakeholder Engagemente. Interim Information Exchanges by discipline.f. Interim Information Exchanges objectives.g. Consultant inputs/responsesh. Design team and Client design review meetings.i. Cost management process.j. Visualisation/models deadlinesk. Statutory approvals process and key meetings.l. Stage report production and review process.
A Design Programme is therefore an essential tool, not a burden or a chore. Make sure as Lead Designer, you own the Design Programme. It’s generally a contractual obligation but more importantly, it’s your process. The key is to appropriately match the style of the programme with the right level of information, appropriate to each design stage.
A Gantt Chart Programme setting out a high level task path through a design phase.
(44) 020 7258 [email protected]