inpact 1: how to avoid a failed project - slidecast 1: introducing the inpact assessment process
DESCRIPTION
Introduction to the principles behind The Change Equation, the INPACT assessment process and the project complexity modelTRANSCRIPT
© Imaginist 2009
Slidecast 1: Introducing the INPACT Assessment Process and the
Project Complexity model
ORGANISATI ONAL CAPABILITY
THE PROJ ECT
Culture Proce
ss
£
ORGANISATI ONAL CAPABILITY
THE PROJ ECT
Culture Proce
ss
£
The Change Equation
Or how to avoid a failed change project!
Peter DuschinskyManaging Director, The Imaginist Company
© Imaginist 2009
70% of change projects do not deliver the expected benefits
Is yours one of them?
What would it be worth if you could avoid that happening?
AND improve your project’s return on investment by 10%?
3
© Imaginist 2009
‘The Change Equation’ is based on three key contentions:
1. The success or failure of a change project is dependent on the complexity of the project being within the capability of the organisation
2. The management of change cannot be achieved within the lifecycle of the project – it has to start earlier and go on afterwards
3. Management typically:
• underestimates the complexity of the project, and
• Is unwilling to invest in change management early enough
The Change Equation
4
© Imaginist 2009
So the objective of running an INPACT assessment is to change mindsets
In order to do this we need to provide clear and simple top-level indicators that managers can understand quickly
We use a dashboard approach, including route-maps and RED / AMBER / GREEN traffic light indicators
V.HighV.HighV.High
V.HighV.HighHigh
V.HighHighHigh
HighHighHigh
HighHighHigh
HighHighMedMedMed
MedMedMedLow
MedLowLow
LowLow
5432Level 1
9. Pragmatic/Empowered
8. Systemist
7. Imaginist
6. Empiricist
5. Pragmatic/ Aligned
4. Aligned
3. Dialectic
2. Structuralist
1. Pragmatic/ Anarchic
Management Culture
Business Process Capability
V.HighV.HighV.High
V.HighV.HighHigh
V.HighHighHigh
HighHighHigh
HighHighHigh
HighHighMedMedMed
MedMedMedLow
MedLowLow
LowLow
5432Level 1
9. Pragmatic/Empowered
8. Systemist
7. Imaginist
6. Empiricist
5. Pragmatic/ Aligned
4. Aligned
3. Dialectic
2. Structuralist
1. Pragmatic/ Anarchic
Management Culture
Business Process Capability
V.HighV.HighV.High
V.HighV.HighHigh
V.HighHighHigh
HighHighHigh
HighHighHigh
HighHighMedMedMed
MedMedMedLow
MedLowLow
LowLow
5432Level 1
9. Pragmatic/Empowered
8. Systemist
7. Imaginist
6. Empiricist
5. Pragmatic/ Aligned
4. Aligned
3. Dialectic
2. Structuralist
1. Pragmatic/ Anarchic
Management Culture
9. Pragmatic/Empowered
8. Systemist
7. Imaginist
6. Empiricist
5. Pragmatic/ Aligned
4. Aligned
3. Dialectic
2. Structuralist
1. Pragmatic/ Anarchic
Management Culture
Business Process Capability
9 Pragmatist/Empowered9
8SystemistImaginist
7
6Empiricist
5
3Dialectic
INTERNALFOCUS
(Individual)
EXTERNALFOCUS
(Organisation)
Pragmatist1
3Rationalist
4Aligned
Structuralist2
5 Pragmatist/Aligned
9 Pragmatist/Empowered9
8SystemistImaginist
7
6Empiricist
5
3Dialectic
INTERNALFOCUS
(Individual)
EXTERNALFOCUS
(Organisation)
Pragmatist1
3Rationalist
4Aligned
Structuralist2
5 Pragmatist/Aligned
9 Pragmatist/Empowered9
8SystemistImaginist
7
6Empiricist
5
3Dialectic
INTERNALFOCUS
(Individual)
EXTERNALFOCUS
(Organisation)
Pragmatist1
3Rationalist
4Aligned
Structuralist2
5 Pragmatist/Aligned
9999
8SystemistImaginist
7Imaginist
7
6Empiricist
6Empiricist
6Empiricist
55555
3Dialectic
3Dialectic
INTERNALFOCUS
(Individual)
INTERNALFOCUS
(Individual)
INTERNALFOCUS
(Individual)
EXTERNALFOCUS
(Organisation)
EXTERNALFOCUS
(Organisation)
EXTERNALFOCUS
(Organisation)
Pragmatist1Pragmatist1
3Rationalist
3Rationalist
4Aligned
Structuralist2
Structuralist2
StructuralistStructuralist2
5 Pragmatist/Aligned
1.InitialAd hoc process
Chaotic
2.RepeatableStable process
Controlled environmentBasic
management control
3.DefinedStandard process
Consistent ExecutionProcess
definition
4.ManagedMeasured process
Quality and Productive Improvement
Process measurement
5.OptimisedEffective process
Continuing ImprovementProcess control
1.InitialAd hoc process
Chaotic
2.RepeatableStable process
Controlled environmentBasic
management control
3.DefinedStandard process
Consistent ExecutionProcess
definition
4.ManagedMeasured process
Quality and Productive Improvement
Process measurement
5.OptimisedEffective process
Continuing ImprovementProcess control
1.InitialAd hoc process
Chaotic1.InitialAd hoc process
Chaotic
2.RepeatableStable process
Controlled environmentBasic
management control
2.RepeatableStable process
Controlled environmentBasic
management control
3.DefinedStandard process
Consistent ExecutionProcess
definition
3.DefinedStandard process
Consistent ExecutionProcess
definition
4.ManagedMeasured process
Quality and Productive Improvement
Process measurement
4.ManagedMeasured process
Quality and Productive Improvement
Process measurement
5.OptimisedEffective process
Continuing ImprovementProcess control
5.OptimisedEffective process
Continuing ImprovementProcess control
75 4803600
10800
32400
72000
05000
1000015000
2000025000
3000035000
4000045000
5000055000
6000065000
7000075000
80000
1 2 3 4 5 6
Simple project
Not simple -needs some
project management
A complex project –needs an
experienced project
manager
Beyond this point your project is too complex –
break it down into separate projects
and employ a programme
manager
75 4803600
10800
32400
72000
05000
1000015000
2000025000
3000035000
4000045000
5000055000
6000065000
7000075000
80000
1 2 3 4 5 6
Simple projectSimple projectSimple project
Not simple -needs some
project management
Not simple -needs some
project management
A complex project –needs an
experienced project
manager
A complex project –needs an
experienced project
manager
Beyond this point your project is too complex –
break it down into separate projects
and employ a programme
manager
Beyond this point your project is too complex –
break it down into separate projects
and employ a programme
manager
- %Total potential impact on benefits
+ %Total potential impact on project timescales/costs
Other factors impact estimated at:
IT Solution9
Relationship with suppliers8
OTHER FACTORS
Delivery of Project Impact estimated at:
Benefits Realisation7
Distrust factor6
Visibility of process5
DELIVERY OF PROJECT
Project Impact estimated at:
Complexity of project4
Clarity of objectives3
PROJECT
Capability Impact estimated at:
Capability Maturity2
Management Culture1
ORGANISATION
Benefits-%
Time/Cost +%
Potential ImpactStatusComponent
- %Total potential impact on benefits
+ %Total potential impact on project timescales/costs
Other factors impact estimated at:
IT Solution9
Relationship with suppliers8
OTHER FACTORS
Delivery of Project Impact estimated at:
Benefits Realisation7
Distrust factor6
Visibility of process5
DELIVERY OF PROJECT
Project Impact estimated at:
Complexity of project4
Clarity of objectives3
PROJECT
Capability Impact estimated at:
Capability Maturity2
Management Culture1
ORGANISATION
Benefits-%
Time/Cost +%
Potential ImpactStatusComponent
Time & Cost
Distrust
(Trust % - 100)
People trust each other, relationships are good = Speedy change = Low cost = SUCCESS Levels of trust are poor, relationships
difficult = Slow or no change = Costs go up = FAILURE
Time & Cost
Distrust
(Trust % - 100)
People trust each other, relationships are good = Speedy change = Low cost = SUCCESS Levels of trust are poor, relationships
difficult = Slow or no change = Costs go up = FAILURE
Possible OutcomesAccountability?
Plan in place?
No
No
Yes
Yes
This project will not achieve its savings objectivesNo
Without formal framework, local managers will not be held accountable in practice – put one in place
Yes
Make local managers accountable for adopting the new processes and redeploying released resources to drive improved performance, or the benefits will not be realised
No
This project has a good chance of achieving the planned benefits
Yes
Possible OutcomesAccountability?
Plan in place?
No
No
Yes
Yes
This project will not achieve its savings objectivesNo
Without formal framework, local managers will not be held accountable in practice – put one in place
Yes
Make local managers accountable for adopting the new processes and redeploying released resources to drive improved performance, or the benefits will not be realised
No
This project has a good chance of achieving the planned benefits
Yes
Complexity
Too ComplexComplex
Not SimpleSimple
Low
Med
High
Capability
Complexity
Too ComplexComplex
Not SimpleSimple
Low
Med
High
Capability
The Change Equation
5
© Imaginist 2009
‘The Change Equation’ shows you how to take two models:
1. the Organisational Culture Evolution spiral
2. the Business Process Capability ladder
…and combine them to provide a baseline:the Organisational Capability Indicator
It then shows you how to assess the complexity and risks of a change project (3)
By analysing and quantifying the gap between Organisational Capability and Project Complexity, you can predict the likely success or failure of a change project
We can then add other tools to enrich the gap analysis
The Change Equation
ORGANI SATI ONAL CAPABI LI TY
THE PROJ ECT
Culture Proce
ss
£
ORGANI SATI ONAL CAPABI LI TY
THE PROJ ECT
Culture Proce
ss
£
£
1 2
3
© Imaginist 2009
Only 32% of change projects are successful
We claimed at the start that 70% of change projects do not deliver the expected benefits – that’s not our opinion, it comes from accredited sources:
Standish Group annual survey 2009 confirms that:• Only 32% of projects deliver the full benefits, on time and within
budget • 68% of projects are late, over budget and deliver less than the
expected benefits • 24% fail completely and are abandoned before they finish!
© Imaginist 2009
Change projects often fail to deliver
© Imaginist 2009
More evidence of the same trend
The Harvard Business School tracked the impact of change efforts among the Fortune 100 and they also found that only 30% produced a positive bottom-line improvement…
A recent survey of change programmes in <400 European organisations quoted by Prof. John Oakland, Emeritus Professor, Leeds University Business School found that:
• 90% of change programmes faced major implementation problems
• Only 30% delivered measurable business improvements
© Imaginist 2009
More evidence of the same trend -2
Management consultant PricewaterhouseCoopers (March 2007) claim that:
• 25% of IT projects succeed
• 25% fail and
• 50% are late or over budget
A CIPD survey of 800 executives found that reorganisations failed to deliver real improvement in performance in 40% of cases
Why do so many change projects fail to deliver?
25% FAIL 25% SUCCEED50% PARTIALLY SUCCEED
© Imaginist 2009
Why do change projects fail to deliver?
Here are some of the reasons we all know about:
• a focus on the technology instead of the business benefits
• poor specification of the system and lack of due diligence on supplier capability
• failure to gain senior management championship
• inadequate resources
• poor project management
• lack of user involvement
But if we all know about the reasons, why are change projects still going wrong so often?
© Imaginist 2009
“The Terminal 5 debacle is a national disgrace” Daily Mail, 14 April 2008
Some examples… Terminal 5
© Imaginist 2009
So what went wrong?
1. Shortage of staff car parking spaces
2. Only one employee security checkpoint operating
3. Some staff unable to log on to the computer system
4. Hand-held communication software running slow
5. No managers on the ground to re-allocate work
6. Shortage of bar-reading storage bins
Baggage handling staff late in arriving
60 staff queue to get into terminal
6am: 3 planes leave without bags
Bags pile up, unattended
By midday 20 flights cancelled
4pm: baggage conveyor belt grinds to a halt, BA suspends all baggage check-in
The result: Over 28,000 lost bags, 700 cancelled planes and more than 150,000 disrupted passengers
© Imaginist 2009
C-Nomis
2004: HM Prison Service commissions C-NOMIS to give prison and probation officers real-time access to offenders’ records
June 2005: the approved lifetime cost of the project is quoted as £234m
March 2007: Home Secretary John Reid: “the main C-NOMIS base release, encompassing full prison and probation functionality, will be available no later than July 2008"
July 2007: [just 4 months later!] £155m has been spent, C-NOMIS is two years behind schedule; estimated lifetime project costs are now £690m. The Ministry of Justice suspends the project
How can they have let a Minister do that? Surely someone knew…?
© Imaginist 2009
What went wrong?
National Audit Office report:• The project board accepted assurances that the project was “all
going well” and nobody knew what was being delivered for the money being spent
• There were insufficient resources and structures in place to deliver such a complex project
• Over time policy developed and stakeholder requirements changed, but there was no cumulative view of the impact of change requests on costs and timescales
• No resources were allocated to simplifying and standardising business processes across the 139 prisons and 42 probation areas, each of which had their own ways of working
The Commons Public Accounts Committee report verdict: “a spectacular failure – in a class of its own”
© Imaginist 2009
More examples…
Passport Office: • In 1999 delays in processing British passport applications,
following the introduction of the Passport Agency’s new system, cost £12 million
• £16,000 was allegedly spent on umbrellas to shelter those queuing in the rain to collect their passports!
MOD: • In 2002 a project to replace the British Army, Royal Navy and
Royal Air Force inventory systems with a single system (the Defence Stores Management Solution) was brought to a halt after £130 million had been spent
• Hardware worth a little over £12 million was able to be used elsewhere but the remaining £118 million was written off as a loss.
© Imaginist 2009
More examples…
The London Ambulance Service Computer-Aided Dispatch System
October 26, 1992: the London Ambulance Service CAD system goes live – and fails
A total of 46 people didn’t get an ambulance in time and DIED!
© Imaginist 2009
What went wrong?
The sequence of the collapse was:1. Poorly trained staff did not update system with location and
status of units
2. The increasingly out-of-date database meant units were being despatched non-optimally and multiple units were being sent to the same calls
3. A software bug generated a large number of exception messages– and un-responded exception messages generated repeat messages…
4. Lists scrolled off the top of the screens and were lost
5. The public repeated un-responded calls, adding to the chaos
© Imaginist 2009
What went wrong? cont…
6. The system grinds to a halt:• One ambulance arrived to find the patient dead and taken away by
undertakers• Another ambulance answered a ’stroke’ call after 11 hours, and 5 hours
after the patient had made their own way to hospital
7. CAD system partly disabled. Part-manual system seizes up completely
8. Operators now using tape recordings of calls, then reverting to a totally manual system
9. 29 October 2002: (3 days after confidently launching the system) Chief Executive resigns
The original estimate for the work was £1.25million. By the time the project was abandoned, £7.5million had been
spent. A total of 46 people didn’t get an ambulance in time and DIED!
© Imaginist 2009
Some conclusions
“The the small software error was the straw that broke the camel's back, but the responsibility for the LAS's CAD system failure does not lie solely on the single developer who made the error or even the developing organization to which he belonged. Rather, the attitudes of key LAS members toward the project and the unreasonable restraints they placed on the project allowed the failure to occur.” National Audit Office report
© Imaginist 2009
Projects don’t just fail in the public sector!
MFI• 2004/05: MFI’s new ERP system brought in - and crashes• Total loss of customer order data reported• 2005/06: UK retail division reports a ‘substantial loss’ following
the discovery of significant issues with the system which are affecting its ability to dispatch orders
• MFI said they needed to spend another £30 million on it• 26 Nov 2008 - MFI goes into administration with the loss of
1,500 jobs • Coincidence?
© Imaginist 2009
HP• In 2004, HP's project managers knew all of the things that could
go wrong with their ERP centralisation programme. But they just didn't plan for so many of them to happen at once.
• The project eventually cost HP $160 million in order backlogs and lost revenue—more than five times the project's estimated cost.
• Gilles Bouchard, then-CIO of HP's global operations, says: "We had a series of small problems, none of which individually would have been too much to handle. But together they created the
perfect storm." There’s a clue in there, somewhere…
Projects don’t just fail in the public sector!
© Imaginist 2009
Complexity is EXPONENTIAL!
Conclusion?
© Imaginist 2009
We’re surrounded by examples of exponential growth: For example, compound interest:
• "Scientists have developed a powerful new weapon that destroys people but leaves buildings standing – it's called the 17% interest rate.” Johnny Carson, The Tonight Show, 1980
• All that we had borrowed up to 1985 was around $5 billion, and we have paid about $16 billion; yet we are still being told that we owe about $28 billion. If you ask me what is the worst thing in the world, I will say it is compound interest.
President Obasanjo of Nigeria, 2000
Complexity is Exponential
© Imaginist 2009
Complexity is Exponential
The world population is growing at an exponential rate:
…and consumption of resources is following close behind -our energy usage is depleting the world’s natural resources exponentially
You are here!
(6,792,142,533)
© Imaginist 2009
Complexity is Exponential
And climate change is also following an exponential runaway profile
© Imaginist 2009
… but we don’t really understand it
We live in a world that can change exponentially – but we have brains that are hardwired to plot things out linearly - the software in our brains compels us to think about progressions as being simple arithmetic ones
"The greatest shortcoming of the human race is our inability to understand the exponential function." Prof Albert Bartlett, emeritus Professor of Physics at the University of Colorado
So as a species, and a society, we deal poorly with uncertainty in non-linear domains.
© Imaginist 2009
Managing Exponential Risk
Most risk management approaches work something like this:• Make a list of risks• Give them a weighting• Add up the scores• That is supposed to tell you something useful – it might be the
amount of contingency you need for the risk, or something like that
• When the risks you anticipated happen, they become issues• When the risks you didn’t anticipate happen, you become a
former project manager!
Source: David Christiansen
© Imaginist 2009
Managing Exponential Risk
So let’s draw up a table with all the risk factors, score them and then add them all together:
Risk Factors Weight Risk Potential Total
Scores
Low 1 2 3 4 5 High
ORGANISATIONAL
Urgency of need to change Little Vital
Culture Innovative, lively Closed, dead
Climate / Politics Open / Friendly Conflict / Bad feeling
Business Environment Static Rapid Change
Competition Low High
Growth / Stability Slow / Stable Rapid / Unstable
Management Style Inclusive Dictatorial
Management Experience Highly competent Naïve
Responsibilities and Leadership Clear Unclear
Perception of problems Shared Disagreed
Staff characteristics Willing and Able Unmotivated, inept
Adoption of IT Effective Ineffective
Quality Assurance procedures Well established Rough and ready
Available Finance High Low
© Imaginist 2009
Managing Exponential Risk
There’s more…
PROJECT
Definition of Aims and Objectives Clear Vague
Room for improvement Great Little
Project Plan Detailed Unprepared
Feasibility Certain Uncertain
Size Small Large
Budget < £10.000 > £1,000,000
Development Timescale < 3 months > 2 years
Operation / Delivery Date Flexible Tight / exact
Quality / Standards Minimal / Lax Strict / Rigorous
Monitoring and control mechanisms In place / Good Do not exist
Newness of project / Ambitiousness Familiar / Common Strange / Unique
Complexity Easy Difficult
Resource Availability Plenty Inadequate
Project Manager’s Experience Experienced Inexperienced
Project Team’s Competence Expert Naïve
Skills required Few Many, varied
Number of bosses / Owners One Many
No. of People / groups involved Few Many
No. of interfaces to other systems 1 > 10
Legacy equipment Integration None High / many
Need for Security Low High
Management Commitment Strong Weak
User demand Keen Hostile
Anticipated User involvement High throughout Minimal
Staff Capability High, adaptable Low, untrained
© Imaginist 2009
Managing Exponential Risk
And still more…
You think this is daunting? Have you looked at government’s Gateway Review?
OPTIONS
Operational Matches objectives Fits few of the needs
Financial Well within budget Over budget limit
Economic return Good investment Poor investment
Social upset / Staff happiness Improvement Anger & disruption
Achievability of Schedule Easily on Time May be late
Amount of change caused Highly beneficial Little difference
Potential User Impact / Retraining needs
Low High
Legal / Ethical problems Few Many
Number of Suppliers 1 > 5
Supplier support High, reliable Low, inadequate
Security Risk Low High
Newness of technology Tried and tested Frontier breaking
Build or Buy Modular package Bespoke software
© Imaginist 2009
Managing Exponential Risk
But if complexity is exponential, we actually only need 3 factors to build an exponential scale: X * Y * Z
That won’t represent all the risks, but if we select the right factors, it will give us a good indicator
So what are our 3 factors?
0
100000
200000
300000
400000
500000
600000
700000
800000
900000
1000000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
X
Y
Z
Complexity Factor
© Imaginist 2009
Managing Exponential Risk
The INPACT Exponential Complexity Tool uses the following 3 factors:
1. Number of people or Stakeholders involvedMore people = more complex = higher risk
2. Number of business activities or Processes affected More ambitious = more complex = higher risk
3. Elapsed Time to implement (in months) Longer to implement = more complex = higher risk
© Imaginist 2009
The INPACT Exponential Complexity Tool
Think about a project you are familiar with. Where do you think you are? Now do the numbers: Stakeholders x Processes x Time (in months) Where are you actually?
Co
mp
lexi
ty F
ac
tor
75 4803600
10800
32400
72000
0
5000
1000015000
20000
25000
30000
3500040000
45000
50000
55000
60000
6500070000
75000
80000
1 2 3 4 5 6
Not simple –needs
experienced project
management
A complex project –
needs dedicated
project team
Beyond this point your project is too complex – break it down into smaller
projects and employ a skilled programme
manager
Simple project – needs some
project management
Co
mp
lexi
ty F
ac
tor
75 4803600
10800
32400
72000
0
5000
1000015000
20000
25000
30000
3500040000
45000
50000
55000
60000
6500070000
75000
80000
1 2 3 4 5 6
Not simple –needs
experienced project
management
Not simple –needs
experienced project
management
Not simple –needs
experienced project
management
A complex project –
needs dedicated
project team
A complex project –
needs dedicated
project team
Beyond this point your project is too complex – break it down into smaller
projects and employ a skilled programme
manager
Beyond this point your project is too complex – break it down into smaller
projects and employ a skilled programme
manager
Simple project – needs some
project management
Simple project – needs some
project management
Simple project – needs some
project management
© Imaginist 2009
Why else do change projects fail?
So that’s complexity – we typically underestimate it, so we under-resource it and our expectations of outcomes are too optimistic
Our next slidecast focuses on the other half of the Change Equation – the capability of the organisation to cope with the changes needed to succeed.
© Imaginist 2009
Thank you for listening!
Peter Duschinsky
‘The Change Equation’ is now available from
Amazon.co.uk
© Imaginist 2009
Who are we?
The Imaginist Company is a change management consultancy We specialise in helping private and public sector clients identify
and overcome barriers to change and performance improvement Under our 'bethechange' brand, we work with non-profit
organizations across the world, advising them on strategic development and transformational fundraising programmes
Working with a team of associates and partners, Imaginist undertakes projects and programmes which require: • ‘Quantum’ thinking and the creation of new approaches
• Research, diagnostic assessment, analysis and evaluation
• Development of clearly articulated guidelines and policy documentation
• Dissemination, facilitation and mindset change
Contact us at: [email protected]