industry briefing | 29 november 2016 · 29-11-2016  · planned outcomes a safe reliable and...

83
Industry Briefing | 29 November 2016

Upload: others

Post on 27-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Industry Briefing | 29 November 2016

• Project Overview• Target Programme• Designation and resource consent conditions• Ground investigations• Mana Whenua• Design Status• Tunnels• Stations• Sustainability• Design Management and Interfaces• Questions - followed by afternoon tea

Agenda

Planned Outcomes

A safe reliable and attractive railway• 24 trains per hour in each direction ultimate track capacity• 18,000 passengers per hour in each direction as the ultimate

patronage capacity through two new stations and two modified stations

• Future proofing oversite development opportunities at each station

• Sustainability IS project target rating 'excellent'• Operating in 2023/24

Route Context

Climbing the Hill

Designation Boundaries

Contract Split

C3/C7 Interface• Trackwork

• Signalling

• Overhead line

• Communications

• Fire engineering

• Tunnel ventilation

• Controls

• Integration

• Testing

• Commissioning

Procurement Programme

• C1,C2, DSC complete in 2019

• C3 2019-2023/24

• C5 2019-2022

• C6 2018-2019

• C7 2019-2023/24

• C8 TBA

• C9 2023/24

Target Construction Programme

• Surface and subsurface designations • 3 resource consent packages• Noise and vibration • Traffic impacts• Business disruption• Settlement impacts

Designation and Resource Consent Conditions

Ground Investigations • Approx. 130 BHs and CPTs carried out (excluding non-CRL BHs)

• Extensive network of groundwater monitoring installations and core sample storage

• Geotechnical Baseline Report (GBR) and Geotechnical Data Report (GDR) will be available to tenderers

Geotechnical Longsection

Mt Eden Geology

Utilities Investigations

• Utility surveys undertaken in Albert Street and Beresford Square

• Further utility potholing to be carried out in open cut sections

• Anticipated completion end of 1st quarter 2017

• Potential early utilities diversions and/or removal of canopies

CRL's Mana Whenua forum

The eight Mana Whenua who self-identified their interest in CRL, and who are part of the forum :

• Ngāi Tai Ki Tāmaki• Ngāti Maru• Ngāti Paoa• Ngāti Tamaoho• Ngāti Te Ata Waiohua• Ngāti Whātua o Ōrākei• Te Ᾱkitai Waiohua• Te Kawerau a Maki

Cultural Narratives

Illustration Aotea station - indicative expression of narratives

Mandated Design

STEPS Modelling

Design Document Structure

BIM Model

Tunnels

Mined Tunnels

Cut and Cover Tunnels

Bored Tunnels

Tunnels & Alignment

Tunnels & Alignment - Aotea to Karangahape

Tunnels & Alignment Newton Junction

N

Tunnels & Alignment - East Connection

Tunnels & Alignment - West Connection

C1 and C2

N

• Modification of existing platforms, tracks and signals• Addition and alteration works of operation support entities i.e.

offices, gates, stairs etc

C9 Britomart East

Stations - Aotea

N

Aotea Station - Existing Structures

Bluestone Wall Crown Plaza Deck

Public Trust BuildingVerandahs

Aotea Station - Utilities & Stormwater Diversion

• Albert Street stormwater pipe jack

• Orakei Main Sewer

• Existing subsurface utilities to be diverted/protected

Aotea Station - Connection to Structure

• Connect to C2 cut and cover tunnel south of Wyndham Street

• C2 expected completion 3rd

quarter 2019

• Potential future integration with NDG’s development at Albert Street/Victoria Street junction

• Potential future connection to SkyCity

Aotea Station Construction Site - Bledisloe Carpark

• Available as site support area during construction

• Carpark side entrance along Wellesley to be maintained

Aotea Station Geology

Aotea Station - Plan (North)

Aotea Station - Plan (Middle)

Aotea Station - Plan (South)

Aotea Station - Typical Section (North)

Aotea Station - Typical Section (South)

Aotea Station

Architecture

Stations - Aotea

Aotea Station - Future Oversite Development

• Feasibility and space proofing carried out

• Resource Consent granted

• Structural enabling works within station structure

Virtual Station Tour

Karangahape Station Location Plan

N

Karangahape Station - General Arrangement

• Beresford Square

• Current carpark area

Karangahape Station - Construction Support Area

• Mercury Plaza site

• Available as construction support area

• Building possibly demolished as advanced work

Karangahape Station - Construction Support Area

Karangahape Station - Geology

Karangahape Station - Existing Structures

Beresford SquareMercury Theatre

(Former) George Courts BuildingMethodist Church

N

Existing Structures - Verandahs

• Existing verandahs may obstruct construction of station

• Potentially advanced work

• Verandahs to be removed and reinstated/ replaced

Stations - Karangahape

Stations - Karangahape

Stations - Karangahape

Stations - Karangahape

Mt Eden Plan

Structures - Cross Over Shaft

C6 Mt Eden Stormwater Diversion

• Diversion of 1950mm SW pipe

• 3 shaft locations

• Approximately 450m length

• Pipe jack launch at Mt Eden Rd shaft

• Tunnelling largely below basalt layer

Structures - Station Box

N

Construction Sites

Mt Eden

Geology

Stations - Mt Eden

Pedestrian Bridges - Western Line

Perspective of Normanby Road

• Western Line Metro and freight services maintained• Limited full blocks of line• Staged testing and commissioning • Civil, structural, trackwork, railway systems scope

Western Line

• Decision making that considers social, environmental and cultural impacts, risks and opportunities

• Truly integrated design

• Understanding and considering whole of life costs

• Collaboration around interfaces

Delivering CRL Sustainably

• Reducing resource consumption - measuring CRL’s carbon footprint- energy, water, materials

• Zero waste to landfill - aspirational goal - designing out waste- avoiding construction waste

• Social outcomes- workforce development, employment, social enterprises

• Mana Whenua outcomes - kaitiakitanga

• Reporting - qualitative and quantitative

Focus areas

Comparing three options for constructing 200m long, 7-9m deep platform trench

Carbon footprint

• 'Excellent' Design and As-built rating for whole project

• Each contract package will be contributing their own rating- C1, C2, C3, C5, C7 and C9 - (not C6 and C8)

• New Zealand pilot - CRL version:- NZ criteria- incorporates Mana Whenua cultural

values

Infrastructure Sustainably Infrastructure

Sustainability

Council of Australia

Kaitiakitanga includes:• protecting, restoring, enhancing the mauri of te Ao Māori;• fulfilling spiritual, emotional and inherited responsibilities to

the environment;• maintaining mana over te taiao; and • ensuring the welfare of the people. In Tamaki Makaurau it is Mana Whenua who are Kaitiaki.

In meeting their sustainability commitments the CRL

project is supporting kaitiakitanga and Mana Whenua as

kaitiaki.

Kaitiakitanga, Sustainability & CRL

Social Outcomes for Auckland

• There are eight local boards with higher than average numbers of people Not in Employment Education or Training (NEET)

• There is a significant skills shortage in construction and infrastructure

• Creating positive social value through the delivery of CRL

Journey so far

Contracts 1 & 2

Work undertaken:

• Materiality assessment for the scope of each contract package

• Reference design level footprints - for operations only

• Principal’s evidence

Infrastructure Sustainably

Process

• Particular requirements• Planning conditions• Mandated design elements• Interface management and control• DOORS Database• Multi-discipline Gateway Reviews• Systems Assurance

Design Management

• Progressive information co-ordination and delivery- Intermediate gate in interactive pre-award period- Gates through detailed design- Final gate at completion of detail design

• On line real time demonstration of the co-ordinated information delivery and compliance with requirements

Gateway Reviews

• Interface boundary mapping and ownership- DOORS- C3-C6, C3-C2, C3-C7, C3-C5, C3-C9- C7-C1, C7-C2, C7-C3, C7-C5, C7-C9

• Interface control documents- Geographical co-ordination- Cross boundary co-ordination

• Collaborative development - cross contract resolution

• Collective responsibility

Interfaces

• Fully co-ordinated 3D model required• Single source of truth required throughout delivery• Cross contract co-ordination into one federated model generation• BIM 200 at start, BIM 400 on completion of the works

BIM

• Not to hurt anybody• Maintain design quality and cultural narratives• Improve delivery programme - working smarter• 20% cost reduction • Meeting all RMA designation conditions• Key specialist resources in place at start of contract and

maintained through delivery• Draft OPW’s in place prior to contract award and lodge within four

weeks of award• Exceed sustainability targets to ‘leading’ status• To leave behind a more skilled workforce

The Challenge

• For Procurement questions please email

[email protected]

Technical Questions

Thank you.

The Project Route