industry briefing | 29 november 2016 · 29-11-2016 · planned outcomes a safe reliable and...
TRANSCRIPT
• Project Overview• Target Programme• Designation and resource consent conditions• Ground investigations• Mana Whenua• Design Status• Tunnels• Stations• Sustainability• Design Management and Interfaces• Questions - followed by afternoon tea
Agenda
Planned Outcomes
A safe reliable and attractive railway• 24 trains per hour in each direction ultimate track capacity• 18,000 passengers per hour in each direction as the ultimate
patronage capacity through two new stations and two modified stations
• Future proofing oversite development opportunities at each station
• Sustainability IS project target rating 'excellent'• Operating in 2023/24
C3/C7 Interface• Trackwork
• Signalling
• Overhead line
• Communications
• Fire engineering
• Tunnel ventilation
• Controls
• Integration
• Testing
• Commissioning
• C1,C2, DSC complete in 2019
• C3 2019-2023/24
• C5 2019-2022
• C6 2018-2019
• C7 2019-2023/24
• C8 TBA
• C9 2023/24
Target Construction Programme
• Surface and subsurface designations • 3 resource consent packages• Noise and vibration • Traffic impacts• Business disruption• Settlement impacts
Designation and Resource Consent Conditions
Ground Investigations • Approx. 130 BHs and CPTs carried out (excluding non-CRL BHs)
• Extensive network of groundwater monitoring installations and core sample storage
• Geotechnical Baseline Report (GBR) and Geotechnical Data Report (GDR) will be available to tenderers
Utilities Investigations
• Utility surveys undertaken in Albert Street and Beresford Square
• Further utility potholing to be carried out in open cut sections
• Anticipated completion end of 1st quarter 2017
• Potential early utilities diversions and/or removal of canopies
CRL's Mana Whenua forum
The eight Mana Whenua who self-identified their interest in CRL, and who are part of the forum :
• Ngāi Tai Ki Tāmaki• Ngāti Maru• Ngāti Paoa• Ngāti Tamaoho• Ngāti Te Ata Waiohua• Ngāti Whātua o Ōrākei• Te Ᾱkitai Waiohua• Te Kawerau a Maki
• Modification of existing platforms, tracks and signals• Addition and alteration works of operation support entities i.e.
offices, gates, stairs etc
C9 Britomart East
Aotea Station - Utilities & Stormwater Diversion
• Albert Street stormwater pipe jack
• Orakei Main Sewer
• Existing subsurface utilities to be diverted/protected
Aotea Station - Connection to Structure
• Connect to C2 cut and cover tunnel south of Wyndham Street
• C2 expected completion 3rd
quarter 2019
• Potential future integration with NDG’s development at Albert Street/Victoria Street junction
• Potential future connection to SkyCity
Aotea Station Construction Site - Bledisloe Carpark
• Available as site support area during construction
• Carpark side entrance along Wellesley to be maintained
Aotea Station - Future Oversite Development
• Feasibility and space proofing carried out
• Resource Consent granted
• Structural enabling works within station structure
• Mercury Plaza site
• Available as construction support area
• Building possibly demolished as advanced work
Karangahape Station - Construction Support Area
Karangahape Station - Existing Structures
Beresford SquareMercury Theatre
(Former) George Courts BuildingMethodist Church
N
Existing Structures - Verandahs
• Existing verandahs may obstruct construction of station
• Potentially advanced work
• Verandahs to be removed and reinstated/ replaced
C6 Mt Eden Stormwater Diversion
• Diversion of 1950mm SW pipe
• 3 shaft locations
• Approximately 450m length
• Pipe jack launch at Mt Eden Rd shaft
• Tunnelling largely below basalt layer
• Western Line Metro and freight services maintained• Limited full blocks of line• Staged testing and commissioning • Civil, structural, trackwork, railway systems scope
Western Line
• Decision making that considers social, environmental and cultural impacts, risks and opportunities
• Truly integrated design
• Understanding and considering whole of life costs
• Collaboration around interfaces
Delivering CRL Sustainably
• Reducing resource consumption - measuring CRL’s carbon footprint- energy, water, materials
• Zero waste to landfill - aspirational goal - designing out waste- avoiding construction waste
• Social outcomes- workforce development, employment, social enterprises
• Mana Whenua outcomes - kaitiakitanga
• Reporting - qualitative and quantitative
Focus areas
• 'Excellent' Design and As-built rating for whole project
• Each contract package will be contributing their own rating- C1, C2, C3, C5, C7 and C9 - (not C6 and C8)
• New Zealand pilot - CRL version:- NZ criteria- incorporates Mana Whenua cultural
values
Infrastructure Sustainably Infrastructure
Sustainability
Council of Australia
Kaitiakitanga includes:• protecting, restoring, enhancing the mauri of te Ao Māori;• fulfilling spiritual, emotional and inherited responsibilities to
the environment;• maintaining mana over te taiao; and • ensuring the welfare of the people. In Tamaki Makaurau it is Mana Whenua who are Kaitiaki.
In meeting their sustainability commitments the CRL
project is supporting kaitiakitanga and Mana Whenua as
kaitiaki.
Kaitiakitanga, Sustainability & CRL
Social Outcomes for Auckland
• There are eight local boards with higher than average numbers of people Not in Employment Education or Training (NEET)
• There is a significant skills shortage in construction and infrastructure
• Creating positive social value through the delivery of CRL
Work undertaken:
• Materiality assessment for the scope of each contract package
• Reference design level footprints - for operations only
• Principal’s evidence
Infrastructure Sustainably
Process
• Particular requirements• Planning conditions• Mandated design elements• Interface management and control• DOORS Database• Multi-discipline Gateway Reviews• Systems Assurance
Design Management
• Progressive information co-ordination and delivery- Intermediate gate in interactive pre-award period- Gates through detailed design- Final gate at completion of detail design
• On line real time demonstration of the co-ordinated information delivery and compliance with requirements
Gateway Reviews
• Interface boundary mapping and ownership- DOORS- C3-C6, C3-C2, C3-C7, C3-C5, C3-C9- C7-C1, C7-C2, C7-C3, C7-C5, C7-C9
• Interface control documents- Geographical co-ordination- Cross boundary co-ordination
• Collaborative development - cross contract resolution
• Collective responsibility
Interfaces
• Fully co-ordinated 3D model required• Single source of truth required throughout delivery• Cross contract co-ordination into one federated model generation• BIM 200 at start, BIM 400 on completion of the works
BIM
• Not to hurt anybody• Maintain design quality and cultural narratives• Improve delivery programme - working smarter• 20% cost reduction • Meeting all RMA designation conditions• Key specialist resources in place at start of contract and
maintained through delivery• Draft OPW’s in place prior to contract award and lodge within four
weeks of award• Exceed sustainability targets to ‘leading’ status• To leave behind a more skilled workforce
The Challenge
• For Procurement questions please email
Technical Questions