industrial rooftop solar · a fully government owned financial institution started operation in...
TRANSCRIPT
Overview of IDCOL A fully government owned financial institution
Started operation in 1997
Catalyzes private sector participation in infrastructure and renewable energy projects/programs
Market leader in renewable energy financing
Largest financier in private sector infrastructure projects in Bangladesh
Funded by the government and multiple development partners i.e. the World Bank, ADB, JICA, IDB, KfW, GIZ, USAID, UKAID etc.
Financed 2,200 MW Power Projects Financed 1st River port in private sector
Financed USD 147 million in Telecom Sector
Financed 1st Private Sector DrydockProject
Financed Refinery plant of PartexGroup
Financed 1st Central Effluent Treatment Plant
Infrastructure Projects Financed by IDCOL
Financed 4.13 Million SHS
Installed 49,000 Biogas Plants
27 Solar Mini grid Projects1,186 Solar Irrigation Pumps in operation
Installed 2 Rooftop Solar Projects with capacity of 1.82 MWp
Installed 1.65 million Improved Cook-stoves
Renewable Energy Initiatives
Why Rooftop Solar
Project Benefits
Financial Benefits
Environment friendly initiative
•Utilization of unused space
•Reduced use of grid electricity
•Minimum maintenance
•Easy to implement• Cheaper electricity than grid• Reduction in electricity bills• Sale of excess electricity to the national grid
• Reasonable payback period•Enhances green credentials
•Demonstrates environmental responsibility to stakeholders
Market ReadinessTechnical Standards
Pool of experts
Multiple project developers
Concessionary financing
Dedicated project unit
Net metering policy
IDCOL’s Investment Plan
Target to finance 300 MWp by 2022
Pipeline of 40 projects (30 MWp)
Secured soft financing from donors
Already approved 8 projects (4.50 MWp)
Approved loan of Tk. 28.38 crore
Approved Rooftop Solar Projects at a Glance
723.06 kWp project of Paragon Poultry Ltd.
1.1 MWp project of Far East Spinning
Industries Ltd.324 kWp project of
MegaRoofLtd.518 kWp project of Colour and Fashion
Ltd. (Textile)
322.5 kWp project of Egarosindur Cold Storage
Ltd.950.04 kWp project of
PUBL351 kWp project of Libas Textiles Ltd.
200 kWp project of Super Star Renewable
Energy Ltd.
Partnering with IDCOL
Technical supports
Long-term soft financing
Performance monitoring
Capacity development
supports
IDCOL’s Financing Scheme
• Term LoanFacility
• 80% of the project costLoan amount
• 10 yearsTenor
• 1 year (principal only)Grace period
• QuarterlyRepayment
• 6% p.a. (Fixed for Loan Tenor)Interest rate
11
Project Due Diligence & Approval Stages
Pre-approval
Approval
Post-approval
Submission of proposal to
IDCOL
NameClearance
Physical Inspection by
IDCOL
Technical Design & Evaluation of
Quotations
Project Appraisal
Disbursement of loan& Project
Implementation(milestone based)
Agreement SigningEquity Injection &
Security Completion by Borrower
Project COD
CRMC Approval Credit Committee Approval Board Approval
12
Required Documents• For Borrower:
• Constitutional documents copy (MoA, AoA, Certificate of Incorporation, Schedule X, Form XII, ETIN, VAT, Trade License etc.)
• Financial documents copy (Audited financials, Sanction letters, Bank statement, Credit rating report etc.)
• CIB documents• Shareholders documents copy (IT10B, ETIN, NID, Passport, Personal business profile
etc.)• Sister Concern:
• As mentioned above (if any)• Corporate Guarantor:
• As mentioned above (if any)• Technical Documents (Design, Equipment details, BoQ & BoM, Structural integrity analysis
etc.)• Others (standard formats as required by regulatory authorities)
Return on Industry Investment
Capacity 518 kWp
Capital investment Tk. 76.25/Wp
Loan amount 80% of project cost at 6% interest for 10 yrs
Assumptions:
Diesel genset use 2 hours
Grid tariff Tk. 8.56/kWh
Diesel rate Tk. 14/kWh
Operating expenses
Tk. 4,31,053 /year
Payback period 7.61 years
Equity IRR 17.61%
Electricity produced from solar/year 6,88,558 unit (kWh)
Cost of production Tk. 6.83/unit
Finding:
Diesel fuel Savings in a year (litre)
CO2 Emission Reduction in a year
(Tonnes)34,061 91.2
Project Performance: Paragon Poultry Ltd.
• Total generation from COD till date* : 747,138 kWh • Electricity cost savings total : BDT 63.95 lac
The generation dropped down in January 12, 2019 due to a fiber cut issue. Theissue was resolved from the following day.
*16 February, 2019
Project Performance: Far East Spinning Industries Ltd.
• Total generation from COD till date* : 420,282 kWh* • Electricity cost savings total : BDT 35.98 lac*
*16 February, 2019
Recommendation
• Technology should be selected considering weather conditions, electrical infrastructures, project site specific considerations.
• Study of building integrity should be conducted before technical design.
• Mounting options should be selected considering water leakage and roof life.
• Electrical safety equipment e.g. lightning arrester, string disconnects, etc. need to be installed in proper manner.