industrial power systems topic 1
TRANSCRIPT
PLANT PLANNING
AND
POWER DEMAND
Industrial Power Systems
Topic 1
BEF 44903
BEF 44903 – Industrial Power Systems – Topic 1
2
Outlines
1.1 Plant Distribution Systems
1.2 Voltage and Frequency Considerations
1.3 Types of Plant Distribution Networks
1.4 Power Demand and Load Estimation
1.5 Transformer Sizing
BEF 44903 – Industrial Power Systems – Topic 1
3
1.1 Overview of Electric Power Systems
Distribution System
11 kV – 66 kV
Transmission System
132 kV – 500 kV
Generation System
13.8 kV – 15.6 kV
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Example of Plant Distribution System
4
Panelboard Feeding
240/415V
Harmonic Loads
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Planning Distribution Systems
Power system concept:
– Analysis
– Selection of the network
configuration
– Type of connection to ground
– Technical features
Network calculation:
– Load flow
– Short-circuit calculation
– Energy balance
Rating:
– Transformers
– Cables
– Protective/ switching devices
– Provisions for redundant supply
5
Power system planning
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Planning Distribution Systems
6
Source: Siemens
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Planning Distribution Systems
An optimum network configuration should
particularly meet the following requirements:
7
1
Simple structure
2
High reliability of supply
3
Low losses
4
Favorable and flexible expansion
options
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Planning Distribution Systems
8
BEF 44903 – Industrial Power Systems – Topic 1
9
1.1 Planning Distribution Systems
A distribution system deals with the distribution of electrical energy to its specific loads.
The main purposes of planning are:
• To make the system economical (cost effective).
• To minimise power losses and maintain regulation within permissible limits.
Load survey and load forecasting of the area are necessary.
BEF 44903 – Industrial Power Systems – Topic 1
10
1.1 Planning Distribution Systems
For the purpose of forecasting load, the prospective consumers may be categorised as follows:
• Domestic consumers, i.e. residential houses.
• Commercial consumers, i.e. shops, schools, hospitals, hotels, and other commercial establishments.
• Industrial consumers:
• Small industries
• Medium industries
• Large industries
• Municipal consumers (i.e. street lighting, water works, parks, etc.)
• Agricultural consumers
• Mining industries
BEF 44903 – Industrial Power Systems – Topic 1
11
1.1 Layout of Distribution Systems
132kV/66kV 66kV/11kV
11kV Feeder
11kV Feeder
11kV/415V
Industrial
Consumer
3 Phase
Consumers
(415V)
Single Phase
Consumers
(240V)
Secondary
Substation
Distribution
SubstationPrimary
Substation
66kV Feeder
Sub-transmission Line
(66kV or 33kV)
BEF 44903 – Industrial Power Systems – Topic 1
12
1.1 Layout of Distribution Systems
The high voltage from transmission line (132 kV) is step-down at the “Primary Substation” to 66 kV or 33 kV.
From this primary substation, power at 66 kV or 33kV is carried through sub-transmission lines to different load centres. The length of a sub-transmission line is about 50 km and they carry about 50 MW of power.
It has been found that sending power through sub-transmission lines at 33 kV or 66 kV is economical in terms of losses (i.e. I2R) and the capital cost (i.e. cost of conductor, insulators and supports).
Most domestic, commercial and small-scale industrialconsumers receive power at low voltage, i.e. 240V or 415V. Large-scale consumers having load in excess of 100 kW buy bulk power at 11 kV and above.
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Planning for Connection
Supplies at Low Voltages of 240V and 415V
Maximum power requirements in kVA
Types and number of equipment and its
corresponding connected capacity in kVA
Shunt connected reactors and capacitors in kVAr
For single-phase 240V motors with rating of greater
than 6kVA and/or three-phase 415V motors with
rating greater than 75kVA:
(i) Rating in HP or KVA, (ii) Types of control equipment, (iii)
Methods of starting and starting current, (iv) Frequency of
starting (number/hour), and (v) Rated power factor;
Voltage sensitive loads (indicating sensitivity)
13
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Planning for Connection
Supplies at 275kV, 132kV, 33kV, 22 kV, 11kV
and 6.6kV
For all types of loads:
Maximum Active Power consumption in kW;
Maximum Reactive Power consumption in kVAR.
For motor loads:
Types of control equipment;
Methods of starting;
Magnitude and duration of the starting current;
Frequency of starting (number/hour);
Under voltage setting and time;
Negative phase sequence protection;
Sub-transient and/or locked rotor reactance of the motor.
14
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Planning for Connection
For nonlinear loads with harmonic current injections:
Harmonic current spectrum including harmonic number and
the corresponding maximum current.
For fluctuating loads:
The rates of change of Active Power and Reactive Power
consumption in kW/minute and kVAR/minute ,respectively,
both increasing and decreasing;
The shortest repetitive time interval between fluctuations for
Active Power and Reactive Power in minutes; and
The magnitude of the largest step changes in Active Power
and Reactive Power in kW and kVAR respectively, both
increasing and decreasing.
15
BEF 44903 – Industrial Power Systems – Topic 1
1.1 Planning for Connection
For voltage sensitive loads:
steady-state voltage tolerance limits of the equipment in
percentage of the nominal voltage;
intrinsic immunity limits to short duration voltage variation;
transient voltage tolerance limits of the equipment in
percentage of the nominal voltage and the corresponding
duration;
harmonic current emission limit for equipment.
For Shunt Connected Reactors and Capacitors:
configuration and sizes of individual banks;
types of switching and control equipment; and
types of harmonic filtering reactors.
16
BEF 44903 – Industrial Power Systems – Topic 1
1.2 World Voltage and Frequencies Standards
17
BEF 44903 – Industrial Power Systems – Topic 1
1.2 IEC Voltage Standards (IEC 60038 Edition 7.0 2009-06)
18
BEF 44903 – Industrial Power Systems – Topic 1
1.2 Voltage and Frequency Considerations
Voltage Criteria
Steady-State Voltage Fluctuation (Normal Condition):
Steady-State Voltage Fluctuation (Contingency Condition)
19
Voltage level % variation
415 V and 240 V -10% & +5%
6.6 kV, 11 kV, 22 kV,33 kV +/- 5%
132 kV and 275 kV -5% & +10
Voltage level % variation
415 V and 240 V +/- 10%
6.6 kV, 11 kV, 22 kV,33 kV +10 & -10%
132 kV and 275 kV +/- 10%
BEF 44903 – Industrial Power Systems – Topic 1
1.2 Supply Voltage Options
Low Voltage:
Single-phase, two-wire, 240V, up to 12 kVA maximum
demand
Three-phase, four-wire, 415V, up to 45 kVA maximum
demand
Three-phase, four-wire, C.T. metered, 415V, up to
1,000 kVA maximum demand
20
BEF 44903 – Industrial Power Systems – Topic 1
1.2 Supply Voltage Options
Medium and High Voltages:
Three-phase, three-wire and 11 kV for load of 1,000
kVA maximum demand and above
Three-phase, three-wire, 22 kV or 33 kV for load of
5,000 kVA maximum demand and above
Three-phase, three-wire, 66 kV, 132 kV and 275 kV
for exceptionally large load of above 25 MVA
maximum demand
21
BEF 44903 – Industrial Power Systems – Topic 1
1.2 Voltage and Frequency Considerations
Frequency Criteria
The variation of the supply frequency is 50 Hz ± 1%
(European Standard) and 60 Hz ± 1% (US Standard)
22
BEF 44903 – Industrial Power Systems – Topic 1
23
1.3 Classification of Distribution Systems
The distribution systems may be classified in
the following ways:1. According to nature of construction
a. Overhead distribution system (cheaper)
b. Underground distribution system (in crowded area)
2. According to nature of current
a. DC distribution system
b. AC distribution system
3. According to number of wires
2-wire DC system, 3-wire DC system, 1-phase 2-wire AC system,
3-phase 3-wire AC system, 3-phase 4-wire AC system
4. According to the scheme of connections
(a) Radial system
(b) Ring system
(c) Inter-connected system
BEF 44903 – Industrial Power Systems – Topic 1
24
1.3 Primary Distribution Lines (Feeders)
The 33/11 kV secondary substation is established where
the load requirement is approximately 5 MVA. Since
normally a primary distribution line is designed to carry a
load of 1-2 MVA, the number of primary distribution lines
emanating from a 33/11 kV secondary substation is
about 4.
When the load requirement increases and crosses about
8 MVA, the losses in the 33 kV sub-transmission line
become large. Thus, power must fed from a 66 kV sub-
transmission line. The number of primary distribution
lines emanating from a 66/11 kV secondary substation is
six to ten.
BEF 44903 – Industrial Power Systems – Topic 1
25
1.3 Primary Distribution Lines (Feeders)
There are 3 different ways in which the primary
distribution lines can be laid:
1. The radial primary circuit
2. The loop primary circuit
3. The ring main system (or primary network)
BEF 44903 – Industrial Power Systems – Topic 1
26
1.3 Primary Distribution Lines (Feeders)
Radial Primary Circuits
When each circuit coming out of a substation is separate
from the other circuits and has no inter-connection with
any other circuit, it is called a radial circuit.
Secondary
Substation
Factory having load
of 1 MW at 11 kV
Circuit 1 for Factory
Circuit 2 feeding Substation in the city
Circuit 3 for Rural Areas
BEF 44903 – Industrial Power Systems – Topic 1
27
1.3 Primary Distribution Lines (Feeders)
Advantages of Radial Feeders:
i. A heavy load very near the secondary substation.
ii. Isolated loads.
iii. An area of low load density such as a village.
Limitations of Radial Feeders:
i. When the load demand on the radial feeder increases, the
length of the feeder has to be extended. This results in a greater
voltage drop which may cause the voltage towards the tail-end
to reach a value below the permissible limit.
ii. When a fault occurs at any point along the length of the feeder,
supply to all the consumers beyond this point towards the tail-
end gets interrupted.
BEF 44903 – Industrial Power Systems – Topic 1
28
1.3 Primary Distribution Lines (Feeders)
Loop Primary Circuits
To overcome the limitations of the radial feeders, the
loop primary circuit is taken to use.
Secondary
Substation
Distribution
Substation 1
Distribution
Substation 2
Distribution
Substation 3
CB1CB2
CB3
CB4
CB6
CB5
A
11 kV 11 kV
BEF 44903 – Industrial Power Systems – Topic 1
29
1.3 Primary Distribution Lines (Feeders)
Two 11 kV feeders emanate from the secondary
substation.
In this system, every distribution substation receives
supply from two sides.
In case of fault, say at point A, the circuit breaker 1 at
distribution substation 1 and circuit breaker 6 at
distribution substation 3 will open, thus isolating the
faulty section. The supply to the substation 1 and 3 is still
uninterrupted and continues to be received from another
side.
This system is generally used in towns and cities.
BEF 44903 – Industrial Power Systems – Topic 1
30
1.3 Primary Distribution Lines (Feeders)
The reliability of supply in this system has improved in
comparison with that in the radial system as it has an
alternative supply, in case one side fails.
However, it must be realised that the source of supply for
the whole loop system is a single secondary substation.
If a fault occur in the secondary substation causing a
failure of the 11 kV supply source, the whole of the
system will suffer power interruption.
BEF 44903 – Industrial Power Systems – Topic 1
31
1.3 Primary Distribution Lines (Feeders)
Ring Main or Network System
A more reliable system is the ring main system.
Secondary
Substation A
Distribution
Substation 1
Distribution
Substation 2
Distribution
Substation 3
CB1CB2
CB3
CB4
CB6
CB5
11 kV 11 kV
Secondary
Substation B
CB7 CB8 CB9 CB10
BEF 44903 – Industrial Power Systems – Topic 1
32
1.3 Primary Distribution Lines (Feeders)
In the ring main system, there are two different sources
of supply which are indicated as secondary substation A
and B.
The ring system has the added advantage from loop
system is that should one of the sources of supply fail,
say A, the whole system continues to get supply from the
other source B.
The ring main system is by far the most reliable for
continuity of supply. It gives a better voltage regulation
and less feeder losses.
Circuit breakers are used instead of fuses for protecting
the transformer in ring main system due to heavier loads.
BEF 44903 – Industrial Power Systems – Topic 1
33
1.3 Secondary Distribution Lines (Distributors)
Distribution substations are a link between
feeders and distributors.
The standard voltage transformation at a
distribution substation is 11 kV/415V. The
declared consumer voltage as per Malaysian
Nasional Grid is 415 V between phases and 240
V between phase and neutral with a permissible
voltage variation of 5%.
Distribution
Substations11 kV Feeders 415 V Distributors
BEF 44903 – Industrial Power Systems – Topic 1
34
1.3 Secondary Distribution Lines (Distributors)
A consumer at the near-end of the distribution
substation may have a voltage as high as 436 V
(3-phase) and 252 V (single-phase) during light
load hours whereas a consumer at the far-end
may have a voltage as low as 395 kV (3-phase)
and 228 V (single-phase) at peak load hours.
The circuits for the secondary distribution
system are essentially the same as those for
primary distribution except that they are on a
smaller scale.
BEF 44903 – Industrial Power Systems – Topic 1
35
1.3 Secondary Distribution Lines (Distributors)
When power is supplied to the consumers
through the secondary distribution system, one
of the following arrangements is used:
1. Radial system
2. Looped system
3. Network system (Banked secondary system)
BEF 44903 – Industrial Power Systems – Topic 1
36
1.3 Secondary Distribution Lines (Distributors)
Radial System
In this system, the LV distribution lines radiate out from
the distribution substation.
In this system, the supply is from a single 11 kV feeder.
A fault in the feeder will cause the interruption of supply
to all consumers. Circuit breaker and switch-cum fuse
units are used for protection purpose.
11 kV Line220 kVA 11
kV/415V
LV CBRadial Line 1
Radial Line 2
Switch-cum
Fuse Units
BEF 44903 – Industrial Power Systems – Topic 1
1.3 Expanded Radial Scheme
37
BEF 44903 – Industrial Power Systems – Topic 1
38
1.3 Secondary Distribution Lines (Distributors)
Looped System
In this case, the reliability of supply is better than in the
radial system. In the case of fault on one line, the load
can be fed from the other by connecting switch S.
However, a fault in the 11 kV feeder will cause the
interruption of supply to all consumers. Circuit breaker
and the fuse unit provide a protection for the transformer
and line respectively.
11 kV Line220 kVA 11
kV/415V
CB
S
415/240 V
415/240 V
BEF 44903 – Industrial Power Systems – Topic 1
Primary Selective Scheme
39
BEF 44903 – Industrial Power Systems – Topic 1
40
1.3 Secondary Distribution Lines (Distributors)
Banked Secondary System
When radial secondary circuits are supplied by a single
transformer, high starting currents of motors may cause
objectionable voltage drops. One of the most effective
and economical means of controlling such a voltage drop
is the banking of distribution transformers.
11 kV Primary Distribution Line
415/240 V Secondary Distribution Line
T1 T2 T3 Fuse
BEF 44903 – Industrial Power Systems – Topic 1
41
1.3 Secondary Distribution Lines (Distributors)
Transformers are said to be banked when two or more
supplied from the same primary circuit are paralleled to
feed into the same secondary mains.
By this arrangement more than one path is provided
over which high currents can flow. This results in
lowering the extent to which the voltage fluctuates on
the line.
Further advantages of this system:i. More reliable, have alternative supply from other transformer.
ii. Better load distribution on each transformer.
iii. The voltage drop in the system is reduced.
BEF 44903 – Industrial Power Systems – Topic 1
42
1.3 Secondary Distribution Lines (Distributors)
This system is mostly used in areas of low load
densities, where a multiple primary and secondary
network is not justified.
If a fault occurs within one of the transformers, it will be
automatically disconnected from the line by blowing the
two secondary line fuses and the primary transformer
fuse without interrupting service to any consumer.
BEF 44903 – Industrial Power Systems – Topic 1
1.3 Secondary Selective Scheme
43
BEF 44903 – Industrial Power Systems – Topic 1
1.3 Sparing Transformer Scheme
44
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Load Data
Typical range of Industrial Loads:
Light Industry – 50 kVA to 7000 kVA
Heavy Industry – 1,000 kVA to 200,000 kVA
Typical Industrial Loads:
HVAC
Process equipment, pumps, compressors and fans
Industrial services such as boiler, water treatment…
Workshop and laboratory equipment
Motor control centre
45
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Initial Maximum Demand Estimation
2 methods to estimate the maximum power
demand in feasibility/ conceptual design stage:
VA/m2 or W/ ft2 – This is normally apply to commercial
building where the typical loads are lighting, general
power, and HVAC. Example: 50 – 100 VA/m2 for
non-retail buildings, 60 – 150 VA/m2 for retail
buildings. 0.9 W/ft2 for lighting and 4.7 W/ft2 for Air
Condition.
Maximum demand of a similar building/ industry –
Applicable for residential, commercial, and industrial
buildings. Example: Plant A having maximum
demand of 2 MVA then this figure can be used for a
plant of similar capacity.
46
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Initial Maximum Demand Estimation
When some or all of the load characteristics are
not known, the values shown below may be
used to give a very approximate estimate of VA
demands (Electrical Installation Guide 2016 – Schneider).
47
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Detailed Load Estimation
It can be calculated either in kVA or amperes. If
the output is given in kW, the kVA can be
obtained using following formula:
Future load should be considered as given in
spare circuits for future use.
For better load estimation, a proper utilisation
factor (ku) and diversity factor (ks) should be
considered as not all equipment/ load operate
simultaneously.
48
)( PFkWkVA
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Utilisation Factor (ku)
In normal operating conditions, the power
consumption of a load is sometimes less than
that indicated as its nominal power rating, a fairly
common occurrence that justifies the application
of an utilisation factor (ku) in the estimation of
realistic values.
This factor must be applied to each individual
load, with particular attention to electric motors,
which are very rarely operated at full load.
In an industrial installation this factor may be
estimated on an average at 0.75 for motors.
49
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Diversity Factor (ks)
Definition of diversity factor (IEC defined as coincidence factor)
Typical diversity factor values:
50
Load ConnectedDemand Max.k s
Types of load/ circuit Recommended DF
Lighting load 100%
General purpose power circuit (SSO) 40% - 50% (for industrial installation)
Main switchboard 80% - 90%
Intermittent duty loads ≤ 50%
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Example: Max. Loading for MCC (SB)
Load
description
3ø
/
1ø
Duty
N or
S
Motor
rating
(kW)
Ope-
rating
motor
power
(kW)
PF x η
= K
Motor
input
power
Heater 3ø
load
(kVA)
1ø
load –
R
phase
(kVA)
1ø
load –
Y
phase
(kVA)
1ø
load –
B
phase
(kVA)
Cooling
tower 1 fan3 N 15 12 0.7 17.1 17.1
Cooling
tower 2 fan3 S 15 12 0.7 17.1 -
Heater 3 N 5 - - - 5 5
Fan coil 1 N 1.5 1.3 0.6 2.2 2.2
Water pump 3 N 11 9 0.68 13.2 13.2
Extract fan 1 N 1 0.8 0.6 1.3 1.3
Compressor 1 N 1.5 1 0.6 1.6 1.6
Future pump 3 N 5.5 4 0.6 6.7 6.7
Total load 42.0 2.2 1.3 1.6
51
Total load on the MCC = 47.1 kVA
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Example: Max. Loading for LV Switchboard
Load
description
Duty (N/ S) Connected
(kW)
Operating
load (kW)
K kVA
DB 1 - - - - 30
DB 2 - - - - 78
MCC 1 - - - - 47.1
MCC 2 - - - - 50
Packaging
machine- 37 31 0.7 44.3
CO2
compressorN 75 68 0.765 88.9
Water pump 1 N 30 25 0.68 36.8
Water pump 2 S 30 25 0.68 -
Welder N 18 - 0.5 36
Future 50
52
Total load on LV Switchboard = 461.1 kVA
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Diversity Factor (ks)
Rated Diversity Factor for distribution
switchboards: the assumed loading of the
outgoing circuits of the assembly or group of
outgoing circuits may be based on the values:
53
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Diversity Factor (ks)
Diversity factor according to circuit function:
54
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Example of application of factors ku and ks
55
BEF 44903 – Industrial Power Systems – Topic 1
1.4 Old Supply Schemes for various M.D
56
BEF 44903 – Industrial Power Systems – Topic 1
1.4 New Supply Schemes for various M.D
57
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Common Connection for Transformer
58
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Why Delta – Grounded Star
Delta at primary
Free of 3rd harmonics of the magnetising currents and
any possible homopolar current are free to circulate
through the sides of the delta, without flowing into the
network; thus, the magnetic fluxes remain sinusoidal
at the secondary.
In case of unbalanced loads at the secondary
winding, the reaction current absorbed by the primary
flows only through the corresponding winding (as
shown in the figure) without affecting the other two.
59
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Why Delta – Grounded Star
Grounded Star at secondary
To make line and phase voltages easily available.
For safety reasons, since in the event of a fault
between the MV and LV sides, the voltage at the
secondary remains close to the phase value, thus
guaranteeing higher safety for people and maintaining
the insulation.
60
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Basic Installation of Industrial Plant
61
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Methods of Transformer Installation
Method 1 – Substation with a single transformer
62
• In the case where the protection device also carries out switching and isolation functions, an interlock must be provided which allows access to the transformer only when the power supply line of the substation has been isolated.
• Installation of the “SMV” switching and isolation device positioned immediately to the supply side of the transformer.
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Methods of Transformer Installation
Method 2 – Substation with two transformers
with one as a spare for the other
63
• The circuit-breakers on the LV side must be connected with an “I” interlock whose function is to prevent the transformers from operating in parallel.
• Apart from the switching and isolation device on the incoming MV line (IGMV), it is advisable to provide a switching, isolation and protection device on the individual MV risers of the two transformers (IMV1 and IMV2) as well.
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Methods of Transformer Installation
Method 3 – Substation with two transformers
which operate in parallel on the same busbar
64
• Possible to use two transformers with lower rated power.
• Operation in parallel of the transformers could cause greater problems in management of the network.
• When coordinating the protections, the fact that the overcurrent on the LV side is divided between the two transformers must be taken into consideration.
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Methods of Transformer Installation
Method 4 – Substation with two transformers
which operate simultaneously on two separate
half-busbars
65
• Providing a “CLV” bus-tie and an “I” interlock which prevents the bus-tie from being closed when both the incoming circuit-breakers from the transformer are closed.
• This management method allows a lower value of the short-circuit current on the busbar.
BEF 44903 – Industrial Power Systems – Topic 1
1.5 Transformer Sizing
• Total max. demand of individual/ group consumer
• Installed voltage level (kV)
• Method of installation or arrangement
• Short circuit capacity
Transformer sizing is generally based on:
• Voltage drop at secondary (TR) must less than 10%
• Motor full load current ≤ 65% of transformer full load current
• If motor start more than once/ hour, transformer size should be increased additional 20%
Criteria to be met:
66