indonesia: neighborhood upgrading and shelter project ... - nusp2 social... · pdam perusahaan...
TRANSCRIPT
Social Monitoring Report
#Semestral Report (July – December 2017) December 2018
Indonesia: Neighborhood Upgrading and Shelter
Project – Phase 2
Prepared by the Directorate General of Human Settlements, Ministry of Public Works and Housing
for the Republic of Indonesia and the Asian Development Bank.
CURRENCY EQUIVALENTS (as of 30 November 2018)
Currency unit – rupiah currency name in lowercase (Rp)
Rp1.00 = $0.00007 $1.00 = Rp14,240
ADB – Asian Development Bank APBD – Anggaran Pendapatan and Belanja Daerah (Regional
Budget Income and Expenditure) DGHS – Directorate of Human Settlements
NOTE
(i) The fiscal year (FY) of the Government of Indonesia and its agencies ends on 31 December. “FY” before a calendar year denotes the year in which the fiscal year ends, e.g., FY2011 ends on 31 December 2011.
(ii) In this report, "$" refers to US dollars. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
2
Table of Contents
LIST OF TABLES ........................................................................................................................ 3
LIST OF FIGURE ........................................................................................................................ 3
LIST OF APPENDICES .............................................................................................................. 3
CHAPTER I. PROJECT BACKGROUND AND DESCRIPTION .................................................. 5
CHAPTER II. PROJECT IMPLEMENTATION PROGRESS ....................................................... 7
CHAPTER III. RESETTLEMENT................................................................................................ 8
CHAPTER IV. COMPENSATION AND INCOME RESTORATION PROGRAM .......................... 9
CHAPTER V. LAND DONATION ............................................................................................. 13
CHAPTER VI. DISCLOSURE, CONSULTATION AND PARTICIPATION ................................ 16
6.1. Disclosure ......................................................................................................................16
6.2. Public Consultation/Information Dissemination Meetings ...............................................16
CHAPTER VII. GRIEVANCE REDRESS MECHANISM (GRM) ............................................... 18
CHAPTER VIII. INSTITUTIONAL ARRANGEMENT AND CAPACITY BUILDING .................... 20
CHAPTER IX. CONCLUSION AND CORRRECTIVE ACTIONS ............................................... 21
9.1. Conclusion .....................................................................................................................21
9.2. Corrective Actions .........................................................................................................21
APPENDICES ........................................................................................................................... 22
3
LIST OF TABLES
Table 1. Livelihood Restoration Program offered to APs in Pekalongan ................................ 9
Table 2. Livelihood Restoration Program offered to APs in Kapuas ...................................... 9
Table 3. Program Participation ............................................................................................ 10
Table 4. Names of Affected Households (AHH) in NSD Palopo .......................................... 11
Table 5. APs and the Livelihood and Social Program .......................................................... 11
Table 6. Schedule of Recovery Programs ........................................................................... 11
Table 7. Consultation/Information Dissemination Meetings ................................................. 17
LIST OF FIGURE
Figure 1. Photo Documentation of Kelurahan Meeting (Muskel IV) in Kelurahan Selat Hilir,
Kapuas District .................................................................................................... 17
Figure 2. Work Flow of Grievance Redress Mechanism ...................................................... 19
LIST OF APPENDICES
Appendix 1. Letter of Bima Mayor to the Head of Bima District regarding the replacement
land for the Holding Ground and Animal Quarantine ....................................... 23
Appendix 2. Time Schedule of Offered Livelihood Recovery Program in Kapuas ................ 24
Appendix 3. Statement of Land Donation for NSD in Palopo ............................................... 25
Appendix 4. Minutes of meeting of Kelurahan Meeting (Muskel IV) in Kelurahan Selat Hilir,
Kapuas District ............................................................................................... 26
Appendix 5. List of attendees of of Kelurahan Meeting (Muskel IV) in Kelurahan Selat Hilir,
Kapuas District ............................................................................................... 28
Appendix 6. Community Land Contribution for Community Contracts at West Region FY
2017 ............................................................................................................... 30
Appendix 7. Community Land Contribution for Complex Civil Works at West Region FY 2017
....................................................................................................................... 34
Appendix 8. Community Land Contribution for Complex Civil Works at Central Region FY
2017 ............................................................................................................... 35
Appendix 9. Community Land Contribution for Community Contracts at East Region FY 2017
....................................................................................................................... 37
4
ABBREVIATION
ADB Asian Development Bank AH Affected Household AP Affected People APBD Anggaran Pembangunan dan Belanja Daerah (Regional Budget Planning) BPJS Kesehatan Badan Penyelenggara Jaminan Sosial Kesehatan (Social Security for
Health) BPN Badan Pertanahan Nasional (National Land Agency) BSPS Bantuan Stimulan Perumahan Swadaya (Self-help Housing Assistance) CA Community Adviser CC City Coordinator CIO Community Implementing Organization DED Detailed Engineered Design DDR Due Diligence Report DGHS Directorate General of Human Settlement EA Executing Agency EMP Environmental Management Plan FGD Focus Group Discussion FY Fiscal Year GAP Gender Action Plan GRM Grievance Redress Mechanism Ha Hectare HH Household IEE Initial Environmental Examination IP Indigenous People IPAL Instalasi Pengolahan Air Limbah (Wastewater treatment plant) LARP Land Acquisition and Resettlement Plan LCO Local Coordinating Office LG Local Government MDG Millennium Development Goals NMC National Management Consultant NSD New Site Development NPW Nilai Perkiraan Wajar (Reasonable Reimbursement Value) NUAP Neighborhood Upgrading Action Plan NUSP-2 Neighborhood Upgrading and Shelter Program Phase 2 PDAM Perusahaan Daerah Air Minum (local government owned clean water
provider) PIP Pengembangan Infrastructure Pemukiman (Settlement Infrastructure
Development) PIU Project Implementing Unit (Satker or Satuan Kerja) PMU Project Management Unit PPP Public Private Partnership PWH Public Works and Housing RAB Rencana Anggaran Belanja (Project Budget) RMC Regional Management Consultant RP Resettlement Plan RTRW Rencana Tata Ruang dan Wilayah (Spatial Plan) RT/RW Rukun Tetangga/Rukun Warga (Subdivision Institution under RW/
Subdivision Institution under Kelurahan) Satker PKPBM Satuan Kerja Peningkatan Kualitas Permukiman Berbasis Masyarakat
(National PIU of Settlement Quality Improvement) SIAP Slum Improvement Action Plan SPS Safeguard Policy Statement
5
CHAPTER I. PROJECT BACKGROUND AND DESCRIPTION
1. Approved on 31 March 2014, NUSP2 is aimed to upgrade basic public infrastructure
in slums, and contribute to meeting Millennium Development Goals (MDGs) targets for
achieving significant improvement in the lives of slum dwellers (MDG target 7D) and halving
the proportion of urban households without sustainable access to safe drinking water and
basic sanitation (MDG target 7C). The Project contributes to the implementation of the Cities
without Slums Program launched by the Government to address issues of the rapid
urbanization. The project covers 20 cities and improves basic infrastructure and living
conditions in selected slums.
2. NUSP Phase 2 assists 20 cities to develop and implement inclusive pro-poor city
development plans. The project improves living conditions in slum areas through (i) providing
resources to local governments and communities for upgrading basic infrastructure in slum
areas, (ii) strengthening planning and management capacities of local administrations for
inclusive pro-poor urban planning, (iii) establishing sustainable mechanisms to engage
communities in urban development planning processes, and (iv) launching public private
partnerships (PPPs) to establish affordable housing areas for poor families.
3. As stipulated in the Project Data Sheet, the NUSP-2 has a Safeguard Category B for
Involuntary Resettlement and Category C for Indigenous Peoples. The Category B means
the project will not include physical displacement and loss of more than 10 percent of
productive assets (income generating) of 200 or more persons due to involuntary land
acquisition. And the Category C for Indigenous Peoples means that the Project is not
expected to have any negative impacts on indigenous people. There are no indigenous
people reported in location nearby the project locations.
4. Since the project will adopt CDD approach, the specific intervention will be identified
by the community members only during project implementation, thus potential issues related
to land acquisition can be identified only at later stage. In the context of specific
neighborhood upgrading activities, i.e. construction of public sanitation facilities, small land
portions might be acquired from community members or donated voluntarily. Land required
for new settlement for poor families will be provided by participating districts/cities
government and resettlement issues are not expected or to be minor.
5. The expected impact of the NUSP-2 is improved living conditions in urban areas. The
outcome is improved infrastructure and access to service delivery in slum neighborhoods in
20 project cities. As for the outputs, the NUSP-2 has three outputs: (i) Institutional capacities
for managing pro-poor urban development strengthened; (ii) infrastructure in slum
neighborhoods upgraded; and (iii) new settlements for poor families established.
6. In efforts to improve infrastructure in slum neighborhoods effectively, the
infrastructure activities under NUSP-2 are grouped into three categories of work packages:
1). Community contracts (skala lingkungan);
2). Complex civil works (skala kawasan);
3). New Site Development.
7. The community contract activity is designated to infrastructure works which self-
managed by CIO (Community Implementing Organization) in a neighborhood (kelurahan)
where they live. This kind of construction works is commonly manageable using manual
6
labors. Some of these community contracts are conducted in two or three phases or cycles,
depending on the amount of the budget they manage. Whereas, the complex civil works
activity is designated to infrastructure works which implemented by contracted firm selected
through bidding process. This kind of complex construction works may have scope across
neighborhoods and usually requires advanced or heavy equipments.
8. The New Site Development (NSD) Construction Activity. The NSD plans to
construct the public facilities and infrastructures for the newly built neighborhood, such as
paving roads, drainage system, clean water supply, solid waste management system and
landscape for open green space. There are 4 (four) cities/districts participating in the NSD
projects, namely: Kendari City, Palopo City, Bima City and Kapuas District. The NSD activity
is also implemented by contracted firms selected through bidding process, and has many
types of infrastructure works in a new land including house construction which implemented
by the DGHP.
9. This Report is the Semi Annual Social Safeguard Monitoring Report prepared to
comply with the loan covenants, covering the period of second semester of July to
December 2017 in a cumulative manner. This report covers resettlement and social
safeguard monitoring results in complying with the ADB safeguard policy statement.
7
CHAPTER II. PROJECT IMPLEMENTATION PROGRESS
10. Community Contract Activity. During the second half of 2017, the NUSP-2 Project
has been continuing in 204 kelurahans (neighborhoods) within 20 cities. The Community
Implementing Organizations (CIO or BKM, Badan Keswadayaan Masyarakat) assisted by
Community Advisors (CA) have completed the whole cycles of 368 Community Action Plans
(CAPs or RKM, Rencana Kerja Masyarakat) in 204 kelurahans, and the land donation
required for the constructions have been complied to basic principle of land donation in
Resettlement Framework Paragraph 29, 30 and 31.
11. Complex Civil Works Construction Activity. In 16 cities/districts the 24 complex
civil work packages have been completed by contractor firms. The land donation for the
complex civil works have been complied to basic principle of land donation in Resettlement
Framework Paragraph 29, 30 and 31.
12. As the project implementation in complex civil works in Kapuas District and
Pekalongan City in 2016 have affected 149 peoples or 38 households and caused
resettlement, a Resettlement Due Diligence Report is still being prepared for each location.
However, the local government has been providing income recovery and livelihood programs
for the APs. The monitoring of the implementation of these programs is further elaborated in
Chapter IV Table 3 and 4.
13. The New Site Development (NSD). The current progress of Purirano NSD in
Kendari City is land preparation for housing construction. Later on, the NUSP-2 will provide
with public facilities and infrastructures on this site and the beneficiaries may occupy the
designated houses around mid 2018. There is no issue concerning land acquisition and
resettlement on this site, hence no further monitoring report of Kendari City NSD.
14. As for the NSD in Palopo City, there are two affected households who deserve the
income recovery and livelihood programs. The monitoring on implementation of these
programs is detailed in Chapter IV Table 4 of this report. The land acquisition reports for the
Palopo NSD are being prepared to complete the NSD technical proposals.
15. For the NSD in Bima, the government of Bima City has secured approval for land
donation from the government of Bima District in August 2017. Since the NSD needs
additional land, the government of Bima City requested more land, making the total land
asset to be transferred from the government of Bima District 3,91 Ha. The approval of
additional land transfer was granted in Septermber 2017. On this additional land requested,
4 dilapidated buildings formerly used as animal quarantine holding ground are considered as
affected structure and will be replaced and rebuilt on a new location as mentioned in the
Letter of Mayor of Bima City No.650/172a/V/2018 (Appendix 1).
16. In Kapuas District, the local government has secured approval for land utilization for
NSD from the local parliament in January 2017. The land title status is the property of the
government of Kendari City as shown in the Land Title Certificate issued in March 1996.
Since the land for NSD site is vacant and is the property of the local government of Kapuas
District, there is no issue on land acquisition and resettlement. The Due Diligence Report for
this NSD will be prepared around mid 2018.
17. The Land Acquisition Reports for the Kendari and Palopo are being prepared to
accompany the NSD’s Technical Proposals.
8
CHAPTER III. RESETTLEMENT
18. During this reporting period (June-December 2017), no involuntary resettlement or
loss more than 10% of productive assets were reported. The land acquisition requirement on
small land for project construction activities was fulfilled voluntarily, where all the affected
land owners did not demand any compensation in return. The National Management
Consultant (NMC) safeguard team has encouraged the Regional Management Consultants
(RMC) safeguard specialists to continue carefully identifying and inventory all land donations
and completed with safeguard documents. Land Donation will be discussed separately in
this report.
19. However, livelihood recovery programs were required in the affected area of Kapuas
District and Pekalongan City to provide adequate supports to the affected peoples (APs).
Both local government of Kapuas District and Pekalongan City have prepared the
comprehensive livelihood recovery program with coordination with related local agencies.
The implementation of these recovery programs will be further detailed in the next chapter.
9
CHAPTER IV. COMPENSATION AND INCOME RESTORATION PROGRAM
20. As of December 2017, during this reporting period, no construction activities or
schemes involved with any land acquisition and resettlement issues. However, for any
activities in the future which would involve with land acquisition and caused any resettlement
& rehabilitation, physical or economic displacement, the Resettlement Plan (RP) will be
prepared accordingly and subsequently with necessary monitoring of RP implementation.
Thus, the status of compensation payment to APs for their asset loss and mitigations of
different other social safeguard issues, if any, will be included in the next semi annual report.
21. As aforementioned in previous Chapter, the local governments of Kapuas District and
Pekalongan City have identified the suitable recovery programs to be offered to the affected
people. The process of program identification is carried out by considering educational
background, previous work experience and preference of the affected people. The livelihood
recovery or restoration programs provided by the local governments of Pekalongan and
Kapuas are presented in the following tables.
Table 1. Livelihood Restoration Program offered to APs in Pekalongan
No
Livelihood
Restoration Program Value Provider Financing
1. Kartu Indonesia Sehat 25,000/mo Dept of Health APBD
2. Kartu Indonesia Pintar 370,500/yr Dept of Education APBD
3. Program Keluarga
Harapan
200,000/mo Dept. of Social Affairs APBD
4. Pamsimas 240,000 Dept. of Public Works APBD
5. BSPS 15,000,000 Dept. of Housing and Settlement APBD
6. Posyandu Lansia 100,000/mo Dept of Health APBD
7. Sewing Training 1,875,000 Skill Training Center (BLK) of Kapuas District APBD
8. Carpentry Training 1,875,000 Subdepartmen of Construction Service (Jasa
Konstruksi/Jakon) of Kapuas District
APBD
9. Automotive Training
Course
1,875,000 Skill Training Center (BLK) of Kapuas District APBD
10. Agriculture & Fishery
Processing
1,875,000 Skill Training Center (BLK) of Kapuas District APBD
Table 2. Livelihood Restoration Program offered to APs in Kapuas
No
Livelihood Restoration
Program Value (IDR) Provider Financing
1. Kartu Indonesia Sehat 100,000/mo Dept of Health APBD
2. Kartu Indonesia Pintar 370,500/yr Dept of Education APBD
3. Program Bank Sampah - Div. of Waste Management APBD
4. Posyandu Lansia 100,000/mo Dept of Health APBD
10
No
Livelihood Restoration
Program Value (IDR) Provider Financing
5. Sewing Training 5.000.000,00 Skill Training Center (BLK) of Kapuas District APBD
6. Rattan Handicraft Training
Course
1,500,000 Department of Industry, Trading &
Cooperative of Kapuas District
APBD
7. Carpentry Training 4,500,000 Subdepartmen of Construction Service (Jasa
Konstruksi/Jakon) of Kapuas District
APBD
8. Credit for Small Business
(KUK)
70.000.000,00 Bank Rakyat Indonesia (BRI) APBD
9. Automotive Training
Course
5.000.000,00 Skill Training Center (BLK) of Kapuas District APBD
10. Welding Training Course 5.000.000,00 Skill Training Center (BLK) of Kapuas District APBD
11. Skill Certification Course 5.000.000,00 Subdepartment of Construction Service
(Jasa Konstruksi/Jakon) of Kapuas District APBD
22. The affected people in both sites were offered with the recovery programs, which
enthusiatically well accepted. The schedule for the offered livelihood recovery program in
Kapuas is shown in Appendix 2.
23. The participation of the AP’s in the recovery program presented in the following Table 3.
Table 3. Program Participation
Location No. of eligible
APs
Participation in Livelihood Restoration Activities by APs
Total AHs
Of which vulnerable
No. APs in
Sewing Training
No. APs in Rattan Handi craft
Training
No. APs in Carpen
try Trainin
g
No. APs in Credit
for Small Busine
ss
No. APs in
Welding Training
No. APs in
Automotiv
e Traini
ng
No. APs in
Skill Certification Cours
e
No. APs in Farming and
Fishery Proces
sing
Pekalongan
Pasir Keramat Keraton
32 5 - - - - 3 - 7 32 30
Kapuas
Selat Hulu
4 1 1 2 2 1 1 - - 4 4
Selat Tengah
2 - - 1 1 1 1 1 - 2 2
Total 38 6 1 3 3 2 5 1 7 38 38
24. In the Palopo NSD, a total of 20,000 m2 (2 hectares) acquired land for the
construction of NSD was owned by two households, the name presented in the following
table:
11
Table 4. Names of Affected Households (AHH) in NSD Palopo
No. N a m e of the head of
AHH
Male/ Female
Age Occupation Total Land
owned Lost Land
Severity (Yes/No)
01. Hatija Parakkasih
F 48 Enterpreneur 13.797 m² 10.797 m² Yes
02. Mustahir Ali M 50 Enterpreneur 19.203 m² 9.203 m² Yes
25. Since the land was unoccupied and non-productive, the land acquisition did not affect
the productive income. The two landowners live outside the NSD land. Hatija Parakkasih
lives outside of Palopo City, while Mustahir Ali lives in Palopo City. They are still in a
productive age, not disabled persons and are not considered vulnerable groups. An agreed
amount of the compensation money was used to buy car, renovating house, and meet other
needs. However, both households were provided with the agreed livelihood recovery
program as can be seen in Table 5 and Table 6 below.
Table 5. APs and the Livelihood and Social Program
No. Name of HH
member
Livelihood Training Social Program
Cellular Repair
Culinary Computer 12 Yrs Free
Education
National Health
Security
Local Rice-Aid
1 Mustahir Ali 2 Muhammad 3 Ratna 4 Puddin 5 Syafruddin, SE 6 Hatijah 7 Amiruddin
Table 6. Schedule of Recovery Programs
No
Name of Program
Beneficiaries (HH)
PIC Financed
by
Schedule of Implementation (month)
1 2 3 4 5 6 7 8 9 10 11 12
1 National Health Security
3 Local Health Agency
Regional Gov’
Budget
2 12 Yrs Free Education
1 Local
Education Agency
Regional Governm
ent Budget
3 Local Rice Aid
3 Local Social
Agency
Regional Governm
ent Budget
4 Trainings 3 Local Labor
Agency
Regional Governm
ent Budget
12
26. The continuing implementation livelihood recovery program in Kapuas, Pekalongan
and Palopo will be done in FY 2018. This will be monitored and reported in the next Semi
Annual Social Monitoring Report.
13
CHAPTER V. LAND DONATION
27. The relevant basic principles set forth in the Resettlement Framework document
(paragraph 29, point a, d, g and i) to be applied for the projects are as follows:
(i) Acquisition of land and other assets shall be avoided and minimized as much
as possible by exploring project and design alternatives and appropriate
social, economic, operational, and engineering solutions that have the least
impact on populations in the project area.
(ii) APs shall be fully consulted and informed on the project, their entitlement and
resettlement options. As well as the assistance measures. Ensure the APs
participation in planning, implementation, and monitoring and evaluation of
resettlements programs. Particular attention will be provided to the vulnerable
groups and ensure their participation in consultations.
(iii) There shall be an effective grievance redress mechanism to receive and
facilitate resolution of the affected persons’ concern during the preparation and implementation of LARPs.
(iv) Appropriate monitoring shall be carried out to assess land acquisition
objectives and their impacts on the standard of living of the APs. The M& E,
mechanisms shall be identified and set in place as part of the land acquisition
management system. Monitoring reports should be disclosed.
28. As the project of the NUSP-2 are specific neighborhood upgrading activities, only
small land portions acquired from community members or donated voluntarily. Land required
for the new settlement for poor families in NSD sites would be provided by participating
district or city governments. Hence, the resettlement issues are not expected to occur or just
minor.
29. Concerning the basic principles point (ii), prior to the commencement of construction
works in NUSP-2 subprojects, there are socialization or information dissemination meeting
for the potential affected people to be fully informed and consulted about the project, their
entitlement and resettlement option. More on this information disclosure will be discussed in
Chapter VI. Disclosure, consultation and Participation.
30. As for the basic principles point (iii), the NUSP-2 has developed grievance redress
mechanism to receive and facilitate the AP’s concerns, and will be further described in Chapter VII. The appropriate monitoring will be carried out and the monitoring report would
be disclosed.
31. When the project construction activities require a small land acquisition the project
communities or individuals may decide to make voluntary contribution of the affected land
and non-land assets. It occurs if the affected land owners did not demand any compensation
in return. The land donation shall not cause significant loss to the owner and the owner must
be a direct beneficiary of the project. According to the resettlement framework, this shall be
acceptable only if the following requirements are in place:
(i) Full consultations with the land owners and any non-titled displaced persons
on site selection;
14
(ii) Ensuring that voluntary donations do not severely affect the living standards
of the APs, and are linked directly to benefits for the APs, with community
sanctioned measures to replace any losses that are agreed to through verbal
and written record by the APs;
(iii) No any coercion to those who are opted for the contribution;
(iv) Any voluntary “donation” will be confirmed through verbal and written record and verified by an independent third party such as a designated non
government organization or legal authority;
(v) Having adequate grievance redress mechanism in place; and
(vi) Safeguards must be built into the community decision making process and
included in the project implementation guideline to be followed by project
consultants and facilitators and shared with the project community members.
32. As the NUSP-2 adopts the CDD approach, the specific intervention is identified by
the community members themselves during project implementation. So the land owners and
any non-titled displaced person are fully consulted through series of kelurahan meeting
(Muskel). However, as the process of land provision that may need land donation has been
done in an open and transparent manner through the Muskel II and III, the communities are
not aware or feel necessary to confirm this voluntary donation through verbal or written
record by an independent third party as required in point (iv) of paragraph 28 above
(paragraph 30 of RF document).
33. There is no documentation of verbal or written records as well, due to poor
documentation at the community level. The project is still considering recruiting an
independent individual as the third party to verify verbal or written records of voluntary land
donation process. All the process of these land donations have still been partially complied
with the RF procedure as set forth in paragraph 29-31 of RF document, and will be improved
in the FY 2018 land donation procedures.
34. Land donation by beneficiary households is acceptable where:
(i) the impacts are marginal (based on percentage of loss and minimum size of
remaining assets);
(ii) impacts do not results in displacement of households or cause loss of
household’s incomes and livelihood; (iii) the households making land donations are direct beneficiaries of the project;
(iv) donated land is free from any dispute on ownership or any other issues;
(v) consultations with the affected households are conducted in a free and
transparent manner;
(vi) land transactions are supported by transfer of titles; and
(vii) proper documentation of consultation meetings, grievances, and action taken
to address such grievances is maintained
35. In NUSP-2 Project, the land donation is based on Community Self-survey (Survey
Kampung Sendiri) from which the community identify the need for infrastructure mentioned
in the Neighborhood Upgrading Action Plan (NUAP) document. The need for piece of land
for infrastructure then being identified, discussed and assessed during the Kelurahan
Meeting II (Musyawarah Kelurahan/Muskel II) through meaningful consultation. Further, in
the Muskel III, the community finalizes and agrees upon the Community Action Plan (CAP),
including the land donation and proceed with signing the statement of land donation later on.
In fact, these land donations are voluntarily and are some forms of community contribution to
15
the project without any coercion. Since the land donation is less than 10%, the impact is also
marginal.
36. All lands donated in the community contracts and complex civil works in 2017 were
completed in the first semester 2017 and has been reported in the previous semi annual
report. No compensation demanded in return to benefits provided by the project. The land
donated were mostly unproductive and caused no physical relocation. The construction
activities caused no involuntary resettlement or losing of productive assets. The statement of
land donation is documented in a letter with some description of land situation, negotiation
process with minutes of meeting, list of attendance and photo documentation.
37. In the New Site Development (NSD) in Palopo, the total acquired land was 2,1
Hectares, of which the 2 Hectares were acquired through purchasing from 2 persons (Mrs.
Hatija Parakkasi and Mr. Mustahir Ali) living around the NSD location in 2016 using
negotiated land acquisition procedure set forth in the Law No.2/2012 on Land Acquisition for
Development of Public Interest and its implementing regulations. Later on, approximately
1000 sqm was donated in September 2017 by Mr. Mustahir Ali for additional area of Palopo
NSD. This land was unproductive land, thus would not bring severe impacts and cause
physical relocation. The donation process was documented in the statement of land donation
in Appendix 3.
16
CHAPTER VI. DISCLOSURE, CONSULTATION AND PARTICIPATION
6.1. Disclosure
38. The Due Diligence Report and regular monitoring report are subject to public
disclosure. Thereafter, these documents will be made available to public including the
affected people and related stakeholders. This Semi Annual Social Monitoring report will be
uploaded on the ADB and PWH Ministry websites, as well as on the local Satker’s website. Furthermore, the information about the due diligence report will be summarized in the form
of leaflet for dissemination to the affected households and peoples. These information
leaflets are being prepared for public dissemination.
SULTATION AND PARTICIPATION
6.2. Public Consultation/Information Dissemination Meetings
39. Public consultation is done to provide an opportunity for affected people including
landowners who sold their land assets as well as peoples who own land next to the planned
construction location. Specifically, the consultation is conducted to establish agreements
about land boundaries, land prices, and administrative processes of handover ownership.
The statement letter on the compensation payment release of the land right is signed by the
two parties (seller and buyer) and the explanation of the release of land rights is also carried
out and signed and by local authority (sub district head) and witnessed by at least two
persons.
40. Similar condition applies to land donation, full consultations with the land owners and
any non-titled displaced persons on site selection is required to make acceptable land
donation.The statement letter on release of land right is signed and acknowledge by local
authority and witnessed by at least two person. The public consultation/information
dissemination is documented in minutes of meeting, photos and list of attendance.
41. As an example and evidence of meaningful public consultation like in other locations,
here is a photo documentation of Kelurahan Meeting (Muskel) IV, held on 6 July 2017 in
Kelurahan Selat Hilir, Kapuas District, in which the community discussed and agreed on
implementation of infrastructure construction on designated site, the need for workers and
physical activity, and forming of procurement committee. There was no land donation
needed for the infrastructure being built. This meeting was attended by 32 participants (9
females and 23 males), shown in Figure 1 below, and the minutes of this meeting and the
list of attendees are provided in Appendix 4 and 5.
17
Figure 1. Photo Documentation of Kelurahan Meeting (Muskel IV) in Kelurahan Selat Hilir, Kapuas District
42. The Satker (PIUs) of Kapuas District and Pekalongan City have conducted
meaningful consultations with APs, their communities and other civil society members for
every project and subproject identified as having involuntary resettlement impacts. For the
livelihood and income recovery programs, the City Satker paid particular attention to the
need of disadvantaged or vulnerable groups, especially those below the poverty line, the
landless, the elderly, female headed households, women and children, and those without
legal title to land. Table 7 below shows some public consultation meetings in both sites.
Table 7. Consultation/Information Dissemination Meetings
Date Venue Participants Agenda/Topic Discussed Remarks
12-13 October 2017
Dept of Public Works Office, Kapuas District
NPIU, NMC, LCO, local PIU, CC and BKM.
Follow-up survey to APs, identification of livelihood restoration programs, DDR preparation.
No documentation and list of attendance recorded.
2 Nov 2017 Bappeda Office, Pekalongan
LCO, PIU, RMC Central, CC and CIO.
Identification of livelihood restoration programs.
No documentation and list of attendance recorded.
18
CHAPTER VII. GRIEVANCE REDRESS MECHANISM (GRM)
43. Grievance redress mechanism is used as an instrument to handle any complaints
and/or queries which emerge during land donation process and during construction process
of the NSD project. Any affected people/party will have the right to file complaints. It is
anticipated that all grievances related to benefits and other assistance will be expected to be
resolved at the subproject as the project upholds CDD (community-driven development) as
the overarching approach.
44. The procedure for filing complaints and/or grievance during construction is
established as follows:
(i) The complaint will be filed to the Badan Keswadayaan Masyarakat (BKM) or
Community Implementing Organization (CIO) members and local government at
the neighborhood level for an immediate solution when possible; and
(ii) If the problem cannot be solved, the BKM members and local government staff
will facilitate the APs (affected peoples) to submit their complaints to the
Project’s grievance redress committee (GRC) at the district level, and to the national level if needed. Community advisor then will record the complaint and
report it to the LCOs. The project will dedicate a staff at city/district and national
levels to be in charge of handling and following up on AP’s complaints.
45. The handling procedure by GRC on complaints and/or grievance is as follows:
(iii) The members of the GRC should involve the representatives of vulnerable
affected people (i.e. affected women, poor and minority groups) and other
affected people along with relevant government officials who have functional and
legal authority. The committee will then review grievances involving all land
acquisition benefits or issues, except for disputes related to ownership.
(iv) Grievances will be redressed within 2 to 4 weeks from the date of filing the
complaints at the district level and within 8 weeks at the national levels. If no
consensus can be reached, the dispute resolution will refer to the grievance
mechanisms based on Law No. 2/2012 on Land Acquisition for the Development
of Public Interest and Presidential Regulation No. 71/2012 on the Implementation
of Land Acquisition for the Development of Public Interest.
46. The project is preparing to establish a grievance redress mechanism, which basically
consists of three levels, i.e. at the kelurahan (neighborhood), the city/district and the national
level. This leveling system is expected to timely address any complaints during project
implementation. Affected people will have the right to file complaints and/or queries related
to adverse impacts due to project activities. Community complaints that will emerge later on,
will be handled with grievance redress mechanism in accordance with the complaint
handling guidelines which had been prepared by the DGHS in this reporting period.
19
47. At the neighborhood (kelurahan) level, the kelurahan office will register complaints
and subsequently resolve the complaints; the Kelurahan office will coordinate and provide
feedback to the contractor and City Satker in this matter. If the grievance cannot be resolved
at the kelurahan office, the complaint will be escalated to the city level. At the city level, the
complaints will be handled by the Local Coordinating Office (LCO) residing at the Bappeda
(District Planning Agency) and the complaints should be followed up and/or resolved within
15 workdays and the handling will be coordinated with the City Satker. If the grievance
cannot be resolved at the city level, it will be escalated to the PMU which representing the
DGHS, at the national government level.
Figure 2. Work Flow of Grievance Redress Mechanism
48. Once the Grievance Redress Mechanism is established and disseminated to all level
stakeholders and community, it shall be effectively implemented to receive complaints and
facilitate resolution of the affected people during the process of Land Acquisition and
Resettlement Plans (LARP) preparation and implementation. Regular report on the progress
of GRM implementation will be presented in the next semi annual report.
City Level
(LCO)
Kelurahan level
20
CHAPTER VIII. INSTITUTIONAL ARRANGEMENT AND CAPACITY BUILDING
49. To support the implementation of NUSP-2, there is a project management
organization that includes government, community and consultants, from the central,
district/city level, to the Kelurahan and the community.
50. The Directorate General of Human Settlements is the Executing Agency (EA) of
NUSP-2, at the central level the EA assisted by the Project Management Unit (PMU) and the
Satker PKPBM as the Project Implementation Unit (PIU). The national PIU is assisted by a
national management consultant (NMC). At the city level, there is a Local Coordinating
Office (LCO) of Kapuas District and City Satker of Kapuas District as a Project
Implementation Unit at the city level. At the city level, a Regional Management Consultant
(RMC) is assigned to assist the city satker. The Directorate General of Human Settlements
is responsible for the management of LARP compiled by the LCO and Satker with the
assistance of Technical Assistant (TA) on Safeguard at the RMC level. Consultants (RMC,
CC, and CA) along with Satker at the city level will continue to monitor and update LARP.
51. During this reporting period there was no official or special event for capacity building
being held, however the safeguard team at NMC and RMC continued to assist and mentor to
safeguard the NUSP-2 implementation at any level in regular practices.
21
CHAPTER IX. CONCLUSION AND CORRRECTIVE ACTIONS
9.1. Conclusion
52. Based on the monitoring, review and some analyses of social impacts on the local
community livelihoods and assets, within this reporting period the NUSP-2 projects and
subprojects did not include physical displacement and loss more than 10 percent of
productive assets and income generation. No land acquisition and involuntary resettlement
issues emerged during construction activities, except in Kapuas District and Pekalongan
City, for which the compensation and income restoration program are being provided for the
affected peoples (APs) of those two locations. The implementation of this income restoration
program will be further monitored and reported in the next Semi Annual Monitoring Report,
as well as the monitoring on the implementation of DDR or Land Acquisition Report for the
NSD in Palopo.
9.2. Corrective Actions
53. Some pending issues or gaps in implementing the requirements as set forth in the
Resettlement Framework are considered as partly compliance and need the corrective
actions to comply with those requirements and principles, as shown in Table 10 below.
These corrective or remedial actions will be monitored and also reported in the next Semi
Annual Monitoring Report.
Table 1. Pending Issues and the Corrective Actions
Pending Issues Corrective Actions need to be done
Responsible Institution/Party to complete Corrective Action
Timeline to complete Corrective Action
1. The form of donation should be uniformed and reflecting “severely impact” or percentage of loss and minimum size of remaining assets, as well as the socio-economic profile of land owner to indicate that the impacts are marginal.
- The improved template/form has been provided to be used consistently for any voluntary land donation in the remaining NUSP-2 projects and subprojects. - If possible, the current Land Donation Statements should be complimented with this new form/ template.
- The related Community Advisors (CAs) and City Coordinator (CCs) assist the land donors to fill-up the forms, supervised by safeguard specialists at the RMC and NMC
November 2018.
2. Any voluntary donation documents need to be verified by an independent third party.
- Recruit an independent third party or individual consultant through an open bidding process
The PMU December 2018
3. Screening of Involuntary Resettlement (IR) on every subprojects need to be done
- Will conduct IR screening in FY 2018 to be reported in the next Semi Annual Report
CAs and CCs supervised by Safeguard Specialists at the RMC and NMC
December 2018
23
Appendix 1. Letter of Bima Mayor to the Head of Bima District regarding the replacement land for the Holding Ground and Animal Quarantine
26
Appendix 4. Minutes of meeting of Kelurahan Meeting (Muskel IV) in Kelurahan Selat Hilir, Kapuas District
28
Appendix 5. List of attendees of of Kelurahan Meeting (Muskel IV) in Kelurahan Selat Hilir, Kapuas District
30
Appendix 6. Community Land Contribution for Community Contracts at West Region FY 2017
City/
District Kelurahan
Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contribution
Total
Land
Area
(m2)
Affected
Land
Area
(m2)
Remaining
Land Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Bandar
Lampung
Kota
Karang
Raya
Public Toilet &
Bayrsroom
(MCK)
Ali Amir using permit 250 18 232 9.000.000 house and
yard
own
property
using permit land <10% of
total land area, comply with
existing regulation
Karang
Maritim
Bore Well Idrus using permit,
20 yrs 150 4 146 800.000 yard
own
property
using permit land <10% of
total land area, comply with
existing regulation
Bore Well Sumardi using permit,
20 yrs 120 4 116 800.000 yard
own
property
using permit land <10% of
total land area, comply with
existing regulation
Pidada
Temporary
Waste Storage
(TPS) Murni using permit 500 12 488 2.400.000 yard
own
property
using permit land <10% of
total land area, comply with
existing regulation
Sukajawa
Baru Bore Well Mastur
using permit,
25 yrs 181 4 177 4.000.000 yard
own
property
using permit land <10% of
total land area, comply with
existing regulation
Bengkulu Sumber
Jaya
Drainage Sarpan land donation
150
9,00 141 2.340.000 yard
own
property
land donated <10% of total
land area, comply with
existing regulation
Drainage Nurhadi land donation
200
20,00 180 5.200.000 yard
own
property
land donated <10% of total
land area, comply with
existing regulation
31
City/
District Kelurahan
Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contribution
Total
Land
Area
(m2)
Affected
Land
Area
(m2)
Remaining
Land Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Drainage Sucia Hartina land
donation
150
12,00 138 3.120.000 yard
own
property
land donated <10% of total
land area, comply with
existing regulation
Sawah
Lebar Drainage
Agus
Supangat land donation
150
15,00 135 1.500.000
house and
yard
own
property
land donated <10% of total
land area, comply with
existing regulation
Fery
Martoni land donation
10.000
60,00 9.940 6.000.000 backyard
own
property
land donated <10% of total
land area, comply with
existing regulation
Saprudin land donation
150
6,00 144 600.000
house and
yard
own
property
land donated <10% of total
land area, comply with
existing regulation
Kampung
Kelawi
Drainage Edi Warman land donation
9.600
120,00 9.480 3.000.000
former
palm field
own
property
land donated <10% of total
land area, comply with
existing regulation
Drainage Meraya land donation
2.760
55,20 2.705 6.900.000
former
palm field
own
property
land donated <10% of total
land area, comply with
existing regulation
Concrete
Paving Road,
Drainage
H. Muktar
Yusuf land donation
400
15,00 385 1.500.000
vacant
land/pond
own
property
land donated <10% of total
land area, comply with
existing regulation
Concrete
Paving Road
and Staircase
Muskarudin land donation
1.242
69,00 1.173 6.900.000
vacant
land
own
property
land donated <10% of total
land area, comply with
existing regulation
Concrete
Paving Road
Samsir
Alam land donation
1.560
70,50 1.490 7.050.000
vacant
land
own
property
land donated <10% of total
land area, comply with
existing regulation
32
City/
District Kelurahan
Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contribution
Total
Land
Area
(m2)
Affected
Land
Area
(m2)
Remaining
Land Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Concrete
Paving Road
and Drainage
TM Jhoni land donation
2.100
165,00 1.935 16.500.000
vacant
land
own
property
land donated <10% of total
land area, comply with
existing regulation
Bajak
Drainage Fitri Ardi
Ningsih land donation
472,50
33,75 438,75 5.062.500 backyard
own
property
land donated <10% of total
land area, comply with
existing regulation
Bore Well Justia land donation
198,00
9,00 189,00 1.350.000 yard
own
property
land donated <10% of total
land area, comply with
existing regulation
Bore Well Suherman land donation
320,00
9,00 311,00 1.350.000 yard
own
property
land donated <10% of total
land area, comply with
existing regulation
Bore Well
Tery
Wijayanti
Putri
land donation
500,00
9,00 491,00 1.350.000 yard
own
property
land donated <10% of total
land area, comply with
existing regulation
Padang
Nangka Drainage Mawani land donation 200 9,20 190,80 1.380.000 yard
own
property
land donated <10% of total
land area, comply with
existing regulation
Palembang
Kemang
Agung
Concrete Alley Muhammad
Juliahapni
land
donation 1900 176 1724 35.200.000
vacant
land
own
property land donated <10% of total
land area, comply with
existing regulation Drainage own
property
2 Ulu Concrete
Alley
Ibrahim using permit 90 9.000.000 yard own
property
Maryadi using permit 55,2 5.520.000 yard own
property
33
City/
District Kelurahan
Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contribution
Total
Land
Area
(m2)
Affected
Land
Area
(m2)
Remaining
Land Area
(m2)
Value
(Rp)
Former
Function
Land
Status
A. fahruri using permit 15 5.000.000 yard own
property
Yanto using permit 60 12.000.000 yard own
property
Abdullah
Nandona using permit 21 11.000.000 yard
own
property
KMS Abdul
Hakim using permit 18 45.000.000 yard
own
property
Using Permit Land : 11 Donated Land : 18
34
Appendix 7. Community Land Contribution for Complex Civil Works at West Region FY 2017
City/District Kelurahan Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contribution
Total
Land
Area
(m2)
Affected
Land
Area
(m2)
Remaining
Land Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Batam City Sei Pelunggut
- Drainase U-
Ditch
- Concrete Paving
Road
N/A N/A N/A N/A N/A N/A N/A N/A N/A
Bandar
Lampung City Gunung Sulah
- Concrete
Drainage
- Asphalt Road
Suroso Using permit 50 ?
Adiyanto Using permit 150
Bengkulu City Panorama
- Concrete
Drainage & Stone
Masonry
- Asphalt Road
N/A N/A N/A N/A N/A N/A N/A N/A N/A
Tanjungbalai
City
Beting Kuala
Kapias
Sei Raja
- Asphalt Road
- Bridge N/A N/A N/A N/A N/A N/A N/A N/A N/A
Tanjung
Jabung Barat
District
Tungkal II
Tungkal III
- Concrete
Drainage N/A N/A N/A N/A N/A N/A N/A N/A N/A
Using Permit Land : 2 Donated Land : 0
35
Appendix 8. Community Land Contribution for Complex Civil Works at Central Region FY 2017
City/District Kelurahan Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contribution
Total
Land
Area
(m2)
Affected
Land Area
(m2)
Remaining
Land Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Sukabumi Kawasan Kel
SUKAKARYA
Water Supply
System N/A land donation 42,8 m
Semarang Meteseh
Achway, asphalt
road, drainage,
pedestrian
Arifin land donation 180 8,1 171,9 8.100 Yard own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Muhdlor land donation 240 10,8 229,2 10.800 Yard own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Sarno land donation 300 15 285 15.000 Yard own
property
land donated
<10% of total
land area,
comply with
existing
regulation
36
City/District Kelurahan Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contribution
Total
Land
Area
(m2)
Affected
Land Area
(m2)
Remaining
Land Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Kapuas Murung
keramat
Temporary Waste
Storage (TPS) N/A land donation 274 satker/PPK baru
Selat Hulu Temporary Waste
Storage (TPS) N/A using permit 6
using permit
land <10% of
total land area,
comply with
existing
regulation
Selat Tengah Temporary Waste
Storage (TPS)
Kelurahan
Government
of Selat
tengah
using permit 6 Vacant
frontyard
Kelurahan's
property N/A
Selat dalam TPS3R N/A land donation 274
Using Permit Land : 2 Donated Land : 6
37
Appendix 9. Community Land Contribution for Community Contracts at East Region FY 2017
City/District Kelurahan Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contributio
n
Total
Land
Area (m2)
Affected
Land
Area (m2)
Remainin
g Land
Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Bima
Jatiwangi
Concrete
Pavement
Road and
Drainage
Darwis
Ahmad
land
donation 200 19,2 180,8
180.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Yusuf H.
Akbar
land
donation 200 19,2 180,8
180.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Makassar
Paccerakkang
Concrete
Pavement
Road and
Drainage
Nurhaedah land
donation 10,5
10.500.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Abdul Rauf land
donation 30
30.000.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
H. Sinohadji land
donation 210
210.000.00
0
yard own
property
land donated
<10% of total
land area,
comply with
38
City/District Kelurahan Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contributio
n
Total
Land
Area (m2)
Affected
Land
Area (m2)
Remainin
g Land
Area
(m2)
Value
(Rp)
Former
Function
Land
Status
existing
regulation
Makassar Paccerakkang
M. Amir/
Ramli/
Jasmin
land
donation 31,5
31.500.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Lantih JB land
donation 67,2
67.200.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Nasruddin/
Kartika
Sumantri
land
donation 12
12.000.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
H. Sinohadji
(Dg Kalo dan
Usman)
land
donation 33
33.000.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
39
City/District Kelurahan Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contributio
n
Total
Land
Area (m2)
Affected
Land
Area (m2)
Remainin
g Land
Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Kendari
Korumba
Concrete
Pavement
Road and
Drainage, Bore
Well and
Streetlights
Iskandar
Zulkarnain
land
donation 266 5 261
3.250.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Wondudopi
Concrete
Pavement
Road and
Drainage,
Sumur Bor dan
PJU
Muhammad
Marcus
land
donation 5
8.000.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Lalolara
Concrete
Pavement
Road and
Drainage, Bore
Well and
Syamsuddin land
donation 5
1.750.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
40
City/District Kelurahan Type of
infrastructure
Affected Land
Remarks Name of
Owner
Type of
Contributio
n
Total
Land
Area (m2)
Affected
Land
Area (m2)
Remainin
g Land
Area
(m2)
Value
(Rp)
Former
Function
Land
Status
Kendari
Streetlights
Adolf Fina land
donation 5
1.750.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Lahundape
Concrete
Pavement
Road and
Drainage, Bore
Well and
Streetlights
Anna
Sukarna
land
donation 5
5.000.000 yard
own
property
land donated
<10% of total
land area,
comply with
existing
regulation
Using Permit Land : 0 Donated Land : 14