individual report bembridge _ vol 2
TRANSCRIPT
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
TABLE OF CONTENTS
1- SYNOPSIS_______________________________________________________5
2- INTRODUCTION_________________________________________________7
3- Project Development_______________________________________________8
3.1- Introduction_______________________________________________________8
3.2- Research__________________________________________________________83.2.1- Problem Areas and Solutions______________________________________________103.2.2- Health and Safety_______________________________________________________103.2.3- Aesthetics_____________________________________________________________103.2.4- Stability______________________________________________________________11
3.3- Conceptual Design_________________________________________________123.3.1- Conceptual Criteria_____________________________________________________123.3.2- Problem Areas_________________________________________________________13
3.4- Initial Design_____________________________________________________163.4.1- Alternative Solutions____________________________________________________17
i/ General arrangement:____________________________________________________18ii/ Corrosion and treatments_________________________________________________18iii/ Essential considerations__________________________________________________19iv/ Buildability____________________________________________________________19v/ Slipway:______________________________________________________________20vi/ Walkway______________________________________________________________21vii/ Slab structure._______________________________________________________21
3.4.2- Feedback from Group Conceptual Design Interview____________________________22
3.5- Initial Design_____________________________________________________233.5.1- Slab__________________________________________________________________233.5.2- Slipway_______________________________________________________________233.5.3- Walkway______________________________________________________________243.5.4- Feedback from Individual Design Interview__________________________________24
i/ Slab: Bison hollow composite flooring.______________________________________25ii/ Slipway: UB beams._____________________________________________________25iii/ Walkway: UB beams.____________________________________________________25
3.6- Detailed Design.___________________________________________________263.6.1- Introduction___________________________________________________________263.6.2- Planning and Site Access_________________________________________________263.6.3- Slab:_________________________________________________________________27
i/ Pre-cast concrete structure:_______________________________________________27ii/ Steel grid structure:_____________________________________________________28
3.6.4- Slipway:______________________________________________________________29i/ Steel framework:_______________________________________________________29ii/ Steel framework summary:_______________________________________________31
3.6.5- Walkway:_____________________________________________________________31i/ Steel framework:_______________________________________________________31
3.6.6- Feedback from Design Seminar____________________________________________323.6.7- Action Taken as a Result of the Detailed Design Interview______________________323.6.8- Feedback from Design Seminar____________________________________________33
3.7- The Final Design__________________________________________________34
4- Construction Management_________________________________________35
Page 1 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
4.1- Method statement_________________________________________________354.1.1- METHOD STATEMENT 1: SLAB FLOOR__________________________________354.1.2- METHOD STATEMENT 2: SLIPWAY_____________________________________394.1.3- METHOD STATEMENT 3: WALKWAY___________________________________43
4.2- Material Specifications_____________________________________________484.2.1- Material properties/ characteristics._________________________________________48
i/ Steel framework: Universal Beam – UB._____________________________________48ii/ Walkway and Slipway guardrails.__________________________________________50iii/ Walkway and Slipway open metal grid floor surfacing__________________________51iv/ Precast Hollow Composite Floor.__________________________________________53
4.2.2- Testing Procedures______________________________________________________60i/ Thickness test__________________________________________________________60ii/ Liquid penetrant inspection_______________________________________________60
4.2.3- Performance criteria_____________________________________________________62i/ Corrosion protection_____________________________________________________62ii/ Fire protection: intumescent coating________________________________________65
4.3- Risk Assessments__________________________________________________674.3.1- HEALTH AND SAFETY PRECAUTIONS__________________________________674.3.2- Cost of Risk___________________________________________________________684.3.3- Whole Life Costing_____________________________________________________684.3.4- Major Risk Mitigation___________________________________________________71
i/ Risk with highest impact = Working at Height (Fatality)________________________71ii/ Working over water_____________________________________________________77iii/ Lifting operations:______________________________________________________78iv/ Plant and vehicles:______________________________________________________80v/ Slips and trips:_________________________________________________________80vi/ Workforce:____________________________________________________________81
4.3.5- Health mitigation measures for construction processes (HSE, 2007):_______________81
5- Construction Processes____________________________________________83
5.1- Construction Programme___________________________________________83
5.2- Construction Processes_____________________________________________83
6- CDM Appraisal__________________________________________________87
6.1- Introduction______________________________________________________87
6.2- CDM Compliance:_________________________________________________88
6.3- Obligation of persons involved in the construction process________________906.3.1- The Client (HSE, 2007):__________________________________________________906.3.2- The Principal contractor (HSE, 2007):_______________________________________906.3.3- As part of Designers we have to (HSE, 2007):________________________________91
6.4- CDM during the whole life project: Health and Safety___________________916.4.1- Demolition____________________________________________________________926.4.2- Pre-construction________________________________________________________926.4.3- Construction___________________________________________________________946.4.4- Post-construction_______________________________________________________946.4.5- Maintenance___________________________________________________________95
7- Environmental Assessment_________________________________________96
7.1- General requirements______________________________________________967.1.1- Life Station duration:____________________________________________________967.1.2- Certification ISO 14001:_________________________________________________97
7.2- Environmental issues_______________________________________________987.2.1- Land Contamination_____________________________________________________99
Page 2 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
7.2.2- Environmental Land Areas________________________________________________997.2.3- Climate Change – Possible Sea Levels Rising________________________________1007.2.4- Durability____________________________________________________________1017.2.5- Corrosion of Marine Structures___________________________________________1027.2.6- Sediment Zone________________________________________________________1037.2.7- Immersion Zone_______________________________________________________1037.2.8- Inter-tidal Zone________________________________________________________1037.2.9- Splash Spray Zone_____________________________________________________1047.2.10- Marine Atmosphere Zone_____________________________________________1057.2.11- Techniques used for Corrosion Control__________________________________1057.2.12- Tides and Adverse Sea Conditions______________________________________1067.2.13- Safety for other sea users______________________________________________106
7.3- Life Cycle Analysis________________________________________________1087.3.1- Initiation_____________________________________________________________108
i/ Goal of the Study______________________________________________________108ii/ Scope of the study_____________________________________________________108iii/ System Boundaries_____________________________________________________108iv/ Data categories________________________________________________________110
7.3.2- Inventory Analysis_____________________________________________________110i/ Procurement__________________________________________________________110ii/ Construction__________________________________________________________111
7.4- Environmental Impacts____________________________________________1127.4.1- Data Categories_______________________________________________________1137.4.2- Procurement__________________________________________________________1141.1. Conclusion___________________________________________________________118
8- References_____________________________________________________119
Page 3 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
TABLE OF FIGURES
Figure 1: Solution 1 (Autocad, 2007)___________________________________________________14Figure 2: Solution 2 Station (Autocad, 2007)_____________________________________________15Figure 3: Solution 2 Boathouse (Autocad, 2007)__________________________________________15Figure 4: Bembridge Location (RNLI, 2007)______________________________________________16Figure 5: offshore handrail (kee Klamp, 2006)____________________________________________50Figure 6 a/b: tolartois, 2006. Open metal grating floor_____________________________________51Figure 7: Tolartois, 2006. Element chosen_______________________________________________52Figure 8: tolartois, 2006. resistance data-weight__________________________________________52Figure 9 a/b/c: Bison hollow composite floor (Bison, 2007)__________________________________53Figure 10. (Bison, 2007) Element chosen________________________________________________56Figure 11 a/b: Standard fire test (Corus constrcution, 2006)_________________________________65Figure 12: Fire steel resitance design. (Corus constrcution, 2006)____________________________66Figure 13: Collective mitigation measure. (the plateforme compagny, 2007)____________________75Figure 14. individual mitigation measure, hardness. (the plateforme compagny, 2006)____________76Figure 16: Environmental Land Areas. (SCOPAC, 2007)___________________________________100Figure 19: EN ISO 14713:1999. Protection of steel against corrosion._________________________114
Page 4 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
1- SYNOPSIS
The objective of this report is the design and planning of the Slipway, Slab
and Walkway for the proposed lifeboat station at Bembridge on the Isle of
Wight.
This is volume 2 of the report and should be read in conjunction with volumes
1 and 3 along with the Preliminary Engineering Report.
Volume 1 of the report covers the design of the piling; this includes
development from concept to detailed final design, recommendations for the
final design, calculations, drawings, method statement, risk assessments,
CDM appraisal, Gantt chart with resource aggregation, Bill of Quantities and
material specifications, including an environmental assessment
Volume 2 of the report covers the design of the Slipway, the boat house Slab
and the walkway; this includes development from concept to detailed final
design, recommendations for the final design, calculations, drawings, method
statement, risk assessments, CDM appraisal, Gantt chart with resource
Page 5 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
aggregation, Bill of Quantities and material specifications, including an
environmental assessment
Volume 3 of the report covers the design of the superstructure and cladding;
similarly to volumes 1 and 2 this includes development from concept to
detailed final design, recommendations for the final design, calculations,
drawings, method statement, risk assessments, CDM appraisal, Gantt chart
with resource aggregation, Bill of Quantities and material specifications,
including an environmental assessment.
Page 6 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
2- INTRODUCTION
This report shows the project development, from concept to detailed final
design. The design has been undertaken by combined computer software
analysis and hand calculations, construction drawings have been included. All
steelworks of this project have to be galvanised for protection against
corrosion as an offshore site.
This report also looks at construction resources for the slipway, slab and
walkway structural framework including; a cost appraisal in the form of a Bill
of Quantities giving a construction cost of £103,127.47 (slipway), 121,886.82
(slab), 127,876.32 (walkway) , risk assessments and mitigations giving a
financial contingency of £330,250, whole life costing giving a total life cost of
£725,202.11 (slipway), 749,011.12 (slab), 758,448.75 (walkway) , a Gantt
chart showing the piling activities and construction duration of 1.5 months
(slipway), 2.5 months (slab), 1.5 months (walkway), detailed method
statement for the main area of work, CDM appraisal and material
specifications including performance criteria, construction processes and
environmental assessment.
Page 7 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
3- Project Development
3.1- Introduction
This section of the report looks at the development of the design of the
Slipway, lifeboat station Slab and finally the walkway, from the conceptual
design to the final review. It builds upon a general overview of the group
research as detailed in the Preliminary Engineering Report, and explains the
individual research into types of construction for slab (type of concrete: in-situ
or pre-cast), for the walkway (type of floor), construction problems, loading,
design development and choice of construction method.
3.2- Research
During the completion of the Preliminary Engineering Report (PER) research
was carried out into all aspects of marine construction. In the initial stages the
research concentrated on selecting an appropriate location for a new lifeboat
station that would satisfy both the requirements of the Steel Construction
Institute (SCI) and of the Royal National Lifeboat Institution (RNLI) see PER
(J.V, H.R, V.P, 2007).
Page 8 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
After researching possible locations along the Solent between Brighton and
Bournemouth, the findings of the PER concluded that Bembridge on the Isle
of Wight would be the most suitable location for a new station. The new
station would replace the existing one which has been in service (although
not in its current form) since 1867 and, although it has been updated over the
years, is representative of a traditional ‘shed on legs’. In addition to
aesthetics, Bembridge is in fact an ideal location for a lifeboat station as it
gives excellent access to the Solent being some 15-20 minutes sailing away
from the docks at Portsmouth (another possible location), thus allowing faster
response times.
Further research in to marine construction procedures with guidance from
Bison (2007) and my own engineer knowledge led to a preferred choice of
section and construction method. According with Bison (2007) a pre-cast
construction process give a lot of advantages (see section 4.2.1.iv. pp.53) as
it is easier and faster to fix in a very harsh environment as an offshore one.
Design of the Slipway and the Walkway was the results of a personnel
research, not lead from any books for the general arrangement of the design.
SCI Brief was used to design element in accordance with and then Staad pro
and Design of structural elements (Arya.C, 2003) was used for calculations.
Page 9 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
3.2.1- Problem Areas and Solutions
The design and construction of any maritime structure throws up a vast
amount of problem areas and a lifeboat station is no exception to this. The
main problems encountered in the design of the Slipway, slab and walkway
are the health and safety implications of both working at height and working
over water. In addition to this the requirement of the brief that the overall
scheme should be aesthetically pleasing meant that careful consideration to
the design had to be made at the conceptual stage.
3.2.2- Health and Safety
It is the view of the designer that, so far as reasonably possible, the
requirement for persons to work at height, over water should be reduce at the
minimum and then all mitigation measures must supply to do it (net filet,
working platform on the jack-up barge and prefixed guard-rail on pre-cast
slab, add individual mitigation as Harness for specific hazardous work.
3.2.3- Aesthetics
The decision was made by the designer that the slipway are going to be
design with only Universal Beams to comply with the SCI (2007) brief and
Page 10 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
RNLI requirements (2007) and with a simple and good looking geometry in
accordance of different slopes and loads required by the SCI brief (2007).
Then the designer chooses to design a pre-cast composite floor using Bison
hollow composite floor because of the relative facility to build it. There is no
aesthetics influence for this choice, because at the end we couldn’t see what
was done as type of floor. The designer chooses to design the walkway as
nice as possible. Then it was thinking to use long universal beams spans of
10m to have a good and light looking on the walkway for visitors and the
crew. The choice of Metal open grid floor (Tolartois. 2006) has been done for
its relative very light self-weight (26kg/m²) and the good looking of this
surfacing.
3.2.4- Stability
Due to the location of the station, there is a high volume of marine ‘traffic’
which passes by. There is therefore the likelihood of the structure being
struck by any size of vessel. It is therefore the opinion of the designer that,
while it is not financially viable to design a structure to be indestructible, it
should have some resistance to being struck. Hence it seems reasonable that
the slipway, slab and walkway be designed so that if one is destroyed by
collision the structure can still stand.
Page 11 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
3.3- Conceptual Design
3.3.1- Conceptual Criteria
The choice of construction depended on different criteria as:
- Localisation (weather, type of coast, accessibility, type of rescue…)
(R.H, P.V, V.J, 2007)
- Buildability and daily life: to build the offices on shore and the boat
room offshore or build both offshore.
- Type of lifeboat (B class, Tyne, Tamar…) (Royal National Lifeboat
Institution, 2007).
- Type of station: All weather lifeboat station (ALB) or Inshore lifeboat
station. It depends on the type of boat (all weather station or
inshore station) and the location (type of launch). (R.H, P.V, V.J,
2007)
- Type of launch: Afloat station, slipway station, carriage station, Davit
station for ALB and trolley launch, dodo trailer launch, davit launch,
floating boathouses and cradles for inshore lifeboat station. (R.H,
P.V, V.J, 2007)
Page 12 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
3.3.2- Problem Areas
The main problem encountered for the slab and general arrangement of the
lifeboat station was to provide an aesthetic solution comply with different
requirements from Chapter 7 of the RNLI brief “Accommodation
requirements”. The first problem was to choice how to build the station: in two
parts, with the crew room on the land and the boat room offshore or with both
offshore. The development of the size and shape of the building was firstly
undertaken as part of the group and is detailed in the Preliminary Engineering
Report. It was decided that the new Station should be design to be really
useful and really aesthetic as it was a main criteria for the client.
Two conceptual designs were produced which were then analysed by looking
at the advantages and disadvantages of each and compiling a decision
matrix, as seen in the Preliminary Engineering Report.
Solution 1: (Entire Lifeboat Station over the sea)
By first appearances this solution seems to best satisfy the requirements of
both the RNLI & SCI briefs with respect to room sizes and positions. It allows
adequate space and allows a potential for architectural features to be added,
namely to the roof.
Page 13 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Figure 1: Solution 1 (Autocad, 2007)
Solution 2: (Boathouse on sea and Facilities on land)
This solution does not completely satisfy the RNLI & SCI briefs, as the
boathouse and station are separate structures, where the station is situated
on land and the boathouse in the sea. This is, however, what is currently to
be found at Bembridge and an arrangement that appears to work.
By doing a decision matrix and by looking at the advantages and
disadvantages of each scheme and the preliminary costing, scheme 1 was
chosen.
Page 14 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Figure 2: Solution 2 Station (Autocad, 2007)
Figure 3: Solution 2 Boathouse (Autocad, 2007)
Page 15 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Figure 4: Bembridge Location (RNLI, 2007)
3.4- Initial Design
Since the positions of each room were defined by the RNLI brief, different
aesthetic aspect were discussed.
Inspirited by drawings made by architect and existing Station and thanks to
the help of architectural software the final design was found and approved by
each members of the group: Entire station over the sea as the old one (see
picture 4 bellow)
The main problem encountered with regards to the structural slipway
framework is to provide a good quality of framework in compliance with
Page 16 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
RNLI’s Brief and SCI’s Brief to provide for example the transversal and the
longitudinal slope required on SCI Brief, 2007.
For the walkway the main problem encountered is to adopt the structure to a
10m span length and realise a light and good looking structure and surfacing
to give a good first impression to visitors but also an enough wide walkway to
allow easy carriage.
Buildability is also an issue, due to the hard environmental site to build: over
the sea, solutions should be providing to allow a good quality of
manufacturing and good quality of material properties.
The other major problem to be considered is the corrosion risk of all
steelwork. Outside steelwork have a very harsh maritime environment due to
the waves, the sea salt, zones on intermediate low and high tides.
3.4.1- Alternative Solutions
For further details on group conceptual ideas refer the Preliminary
Engineering Report.
Page 17 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
i/ General arrangement:
The main problem encountered for the slab and general arrangement of the
lifeboat station was to provide an aesthetic solution comply with different
requirements from Chapter 7 of the RNLI brief “Accommodation
requirements” gives the sizes of each room that is required in a lifeboat
station and which rooms need to be in contact with an other (RNLI, 1999):
boat room (21m length by 9m wide), crew room, 1.5 to 2m² per person for 18
persons (36m²); Galley (3 x 3m), manager’s office (8m²), changing room/wash
room/ drying room (30m²), workshop, 5m x 3m; storage (4m²). Then an
economic solution fair easy to build in an aggressive environment as building
over the sea and with compliance the SCI Brief.
ii/ Corrosion and treatments
The other major problem to be considered is the corrosion risk of all steelwork
in a maritime environment. (See section 4.2.3.i. pp.62) for corrosion and fire
protection. For wind consideration sees on roof calculation, volume 3. Outside
steelwork have a very harsh maritime environment due to the waves, the sea
salt, zones on intermediate low and high tides. Salted water cause corrosion
of metal, therefore consideration must be taken into protection measures.
(Coatings for, 2000)
Page 18 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
iii/ Essential considerations
Overall, the main framework should be designed with the following essential
considerations:
- Imposed and wind loading (for the roof calculation)
- Protection of the UB beams framework from corrosion (slipway, slab,
walkway)
- Fire protection for the all site and all framework done
- Safety for the all site and all tasks done (CDM Regulations, 2007).
iv/ Buildability
Lifeboat station is going to be build in accordance with Heath and safety
regulations, CDM regulations, and Environmental assessment. Buildability is
also an issue, due to the hard environmental site to build: over the sea, it will
be likely to build all in factory and then commute it to the site by boat.
Construction should be undertaken in accordance with the CDM Regulations
(See portfolio 378769).
Page 19 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
v/ Slipway:
Quality of steel framework comply with hot-rolled sections to BS EN
10025:2004 and the dimensions and tolerances comply with part 2: 1997(SCI
Brief, 2207). The predominant steel grade is S275.
Transversal slipway slope of 2.6% (one horizontal meter needed from each
side of the keelway and 260 vertical mm to the plates, SCI brief. 2007. pp.5)
is realised by using appropriate Universal Beams for the central keelway and
then for the plates and drawing 206.
Longitudinal slipway slope of 1/5 is realised by using triangular pre-welded
wedge and drawing 206, detail E.
Universal Beams (UB) or cellular beams were considered at the first stage of
the Slipway design because of the one hand the very common used of
universal beams and on the other hand because of the light selfweight of the
cellular beams, which should have been much easier to fix on site. The
maximum on the slipway structure is 4m span length.
Finally Universal beams were chosen because of the too great corrosion
surfacing of cellular beams, which could involve durability problem in the
future.
Page 20 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
vi/ Walkway
As for the slipway, there are very length span of 10m for the walkway steel
beams. Then Universal Beams (UB) or cellular beams were considered at the
first stage because of the on one hand the very common used of universal
beams and on the other hand because of the light selfweight of the cellular
beams, which should have been much easier to fix on site.
Then for the surfacing an open metal grating floor has been used for the
walkway floor to provide a resistant for carriage case and a pleasant surfacing
for visitors. Then a Staad pro simulation has been done to find the more
appropriate Universal beam for the walkway.
vii/ Slab structure.
To begin with, design of the lifeboat station slab was a main key of the design
because it is where the lifeboat is standing when it is not using for rescue. It
was a team work to design it because slab structure is going to influence piles
calculation or localisation.
At the first stage the designer had to choice between the two first solutions he
was thinking about as know:
- in-situ concrete floor or
- composite- floor as Ribdeck 70 (see Appendix 2),
Page 21 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
For the first submission: Group conceptual design interview, Ribdeck solution
was chosen by he designer of because of two composite floor advantages:
- light selfweight
- easy to build on the site because the metal composite floor are going
to be used as formwork to pour in situ-concrete after (offshore site).
3.4.2- Feedback from Group Conceptual Design Interview
Following the Group Conceptual Design Interview, the feedback
recommendations were:
- Preferred an other solution than Ribdek composite floor because of
the very aggressive and corrosive costal environment. But solution
was well argument.
- Initial slipway design was done and general material research, and
model as well.
- No further special recommendations.
These issues were addressed as an individual in both the portfolio of
evidence literature review and in Appendix 9 of this report.
Page 22 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
3.5- Initial Design
3.5.1- Slab
The most favourable arrangement find after the Group conceptual design
interview was to design the lifeboat slab with pre-cast units. Indeed the
Ribdeck composite floor was no appropriate at all with the environmental
conditions (salt environment, corrosion of steel structure). The designer was
chosen to build the slab of the lifeboat and of offices with pre-cast concrete
units. Designer was using this constructive solution according with Bison
data. Bison hollow composite floor are pre-cast concrete units with very
flexible span and depth units sizes. This material allow very long span as 15m
and with a wide range of unit depth, from 150 to 450mm. (Bison, 2007).
(Calculations can be found on Appendix 2)
3.5.2- Slipway
Then using Universal Beams instead of steel cellular beams was chosen
because of the very aggressive maritime environment. Also we need to be
sure that the steel section will not reduce with corrosion, and it is preferred
Universal beams to not have very thin steel thickness where hollow are.
Universal Beams- BS EN 10025: 2004 and BS 4 Part 1: 1993 (Roymech, 2006).
Page 23 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
(Calculations can be found on Appendix 2)
3.5.3- Walkway
Finally for the slipway designer had using Universal Beams instead of steel
cellular beams was chosen because of the very aggressive maritime
environment. Also we need to be sure that the steel section will not reduce
with corrosion, and it is preferred Universal beams to not have very thin steel
thickness where hollow are.
Guard-rails are going to be used for the walkway and the first two meters of
the slipway (Kee Klamp, marine solution. 2006):
– can be used with absolute confidence for safety walkways in
aggressive coastal environments. It provides advantage of a
quick assembly of offset railings, handrails and guardrails.
– hot dip galvanized
– Quantities:
• Slipway: 4ml
• Walkway: 220ml
3.5.4- Feedback from Individual Design Interview
Page 24 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
The conceptual design interview feedback from the 26th March 2007 states
that the brief was interpreted well, that problem solving areas appear to have
been addressed, the construction planning and site access was not really
tackled that it needs further development and the stability analysis was basic
and needed to be addressed in more detail. With respect to the preliminary
drawings the assessors highlighted:
i/ Slab: Bison hollow composite flooring.
- Good choice of pre-cast units to earn time during construction.
- Drawings scale to small. Have to modify it and improve quality of
general drawings.
ii/ Slipway : UB beams.
- Initial slipway design and drawings will have to be corrected and
adjusted.
iii/ Walkway : UB beams.
- No special recommendations about the Walkway.
Page 25 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
3.6- Detailed Design.
3.6.1- Introduction
This section of the report describes how the points raised in section 3.4 were
implemented into the detailed design. This section also gives the feedback
from the detailed design interviews, the results of the design seminar and
feedback from the Industrial Advisory Committee (IAC) interviews along with
details of how this affected the design afterwards.
3.6.2- Planning and Site Access
As a result of the Conceptual Design Interview greater thought was given to
the issues of planning and site access. With respect to site access; there is to
be a site compound at Bembridge harbour where materials are to be
delivered (if travelling by land). Once the materials have arrived at Bembridge
harbour they are to be craned onto a supply barge which will deliver them to
the site jack-up barge.
Access to the structure will be via the walkway (on completion) and access to
the jack-up will be via boat from Bembridge harbour.
Page 26 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
3.6.3- Slab :
i/ Pre-cast concrete structure:
The final design that was decided upon consists of pre-cast hollow composite
floor (Bison, 2007):
- 5500 x 1200 x 250mm 14nr
- 5500 x 600 x 250mm 2nr
- 5000 x 1200 x 250mm 14nr
- 5000 x 600 x 250mm 2nr
- 4000 x 1200 x 250mm 2nr
- 4000 x 600 x 250mm 1nr
- 3000 x 1200 x 250mm 25nr
- 3000 x 600 x 250mm 1nr
See material used on Appendix 3 and drawing 205
A system of two pivots is used to provide a 3% longitudinal slope in the boat
room to allow on one side to work for the maintenance on a plan slab and on
the other side to launch quickly the lifeboat in rescue case. Pivots are directly
supported and connected to piles S19 and S20 (See drawing 204 and
calculation volume 1)
Page 27 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
A winch is using to tow the lifeboat during the recovery after rescue. This
element is directly supported and connected to the pile S11 (See drawing 204
and calculation volume 1).
ii/ Steel grid structure:
The pre-cast Bison hollow composite concrete floor is supported by a UB
beams grid bearing by CHS 323.9 x 16 piles under them (see drawing 204,
volume 1).
The longest span is 5.50m for the Boat room:
- UB 406 x 178 x 54
See calculation sheets in Appendix 2
The longest span for Offices area is 9.00m span:
- UB 254 x 146 x 31
See calculation sheets in Appendix 2
A common granolithic finish treatment is provided on the floor.
Page 28 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
3.6.4- Slipway :
i/ Steel framework:
From the beginning conceptual design to the final design of the slipway it was
important to respect transversal and longitudinal slope required by the SCI
Brief (SCI Brief, 2007). Each unit of the slipway was designed on Staad pro to
provide the most efficient and optimised Universal beam size.
It was necessary to consider sometimes different load case for a unique
element. For example for the central keelway was calculated under a
simulation of:
- on one hand a UDL 35 kN/m Gy load applied on 11m length during
boat launching (SCI brief, 2007) which is given a UB 457 x 191 x 74
- on the other hand during the boat recovery a punctual force divided
on 250 kN Gy and 150 kN Gz load applied on the middle of 4m
span (SCI brief, 2007). This case is the worst case. It is due to
transversal effects on wind and waves, what is going to create an
important impact when the boat has the first contact with the
slipway, which will never happen exactly, be on the central axe on
the slipway considered wind and waves effects. This load case is
given a UB 610 x 305 x 149.
It will be this last load case that is going to dimension the Universal beam
support of the keelway.
Page 29 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Indeed the keelway channel 305 x 89 has not a structural needed but is only
used as a girder to drive the boat on the good way during the launch or the
recovery.
The plates located symmetrically on the right and left sides from the central
keelway at 1m are going to supported load divided as a vertical load of 100kN
Gy and a horizontal load of 25kN Gz (25% of the first load case) supplied by
the SCI Brief, 2007. These load cases are represented the effect on the
Slipway plates if the boat is going to topple over on the right or left side of the
central keelway due to wind or waves effect. This load is only applied on
staad pro on one side to design but as it is a symmetrical load case only
happened on one or on the other side on se same time, the same Universal
beam size is used for the two plates. See calculation sheets on Appendix 2
This is given:
- UB 375 x 171 x 67
But according with the SCI Brief, a transversal slope on 11° or 625mm vertical
distance is needed between the central keelway and plates. Then to be in
accordance with the SCI Brief a 762 x 267 x 147 UB is used (See drawing
206).
The transversal beam was designed on Staad pro as a 4m span beam which
is supported a central vertical point charge of 140kN Gy (lifeboat of 30kN
applied on 4m longitudinal beam span) and a vertical point charge of 100kN
Gy on one support, symbolising the plate effect. This simulation is given, See
calculation sheets on Appendix 2:
Page 30 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- UB 365 x 127 x 33
ii/ Steel framework summary:
- UB 762 x 267 x 147 4.00m
- UB 610 x 305 x 149 4.00m
- UB 356 x 127 x 33 4.00m
- UB 127 x 76 x 13 0.849m
- Channel 305 x 89 4.00m
- Plate 150 x 15 4.00m
3.6.5- Walkway :
i/ Steel framework:
A Staad pro calculation (See calculation sheets on Appendix 2) was done for
a 10m UB span, bearing an imposed load of 2.5kN/m² and the floor finishes
self-weight. This is given:
- UB 553 x 210 x 122 10.00m
- UB 553 x 210 x 122 1.80m
Page 31 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Then an open metal grating floor of 2 m span is used to allow carriage on the
wide walkway and pleasant walkway crossing from the station to the beach
for the crew or visitors. This material is a very aesthetic one and provides
easy daily life maintenance. (See Appendix 3: materials)
To ensure durability of the materials used in the construction of the structure
BS 7543: Guide to the Durability of Buildings, Building Elements and
components and BS 8210: Guide to Building Maintenance Management.
(M.N, E.J, H.G, V.D, 2006)
3.6.6- Feedback from Design Seminar
The detailed design interview results from the 25 th April 2007 advised that
greater consideration be given to the Construction and Design Management
Regulations (CDM) especially with reference to the risks associated with all
working tasks at height and over water as for fixing the slab.
3.6.7- Action Taken as a Result of the Detailed Design Interview
As a result of the detailed design interview, the decision was made by the
slipway designer that sections of the slipway and piles should be pre-
connected on land in sections consisting of four piles for 4m span of slipway
beams. Then, on completion of four boreholes the section can be lowered into
place from the jack-up (see volume 1). For further details see Method
Page 32 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Statement on section 4.1.2). Health and Safety and the in section 4.3.1.
pp.67).
3.6.8- Feedback from Design Seminar
The design seminar that greater consideration be given to the effect . This
advice was echoed by the IAC and also pointed out that there was no time
allocated on the programme for the jack-up barge to be brought to site and
tested.
Following the Design Seminar results from the 16th May 2007, advice
recommendations received by Peter CROSS and Rachel FOWLER were:
- Very challenging role on the Bembridge group, well explained. (Dr
Sangle)
- Very appropriate CDM regulations, Method statement and Heath
Safety & Environment considerations. (Dr Sangle)
- Within the scope of the project no further points need to be
addressed. (Dr Sangle)
- Supply buckling analysis. (Dr. Chen)
- Construction rates are generally light taking in consideration an
offshore site.
- No traffic problem has to take in account because materials are going
to be supply trough the sea, using boats, because there are any
frame metal factory on Isle of Wight.
Page 33 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- Construction programme is too short on taking account of an offshore
site. It will be extend on proportion from 18 months to 24 months.
3.7- The Final Design
For the final design according with Dr Reynlds any changes have been done,
because for the programme advice, they were waiting for a 24months
programme including all preliminary researches and concept design period
and the legal period to survey the site. Then about the cost bembridge group
designers have done their cost files according with SPON’S (2007) and with
engineering judgment. But the slipway, slab and walkway designer are taking
in account all those advice to be able to update the project data if real rates
from offshore builders are going to be given to designer to adjust slipway,
slab and walkway designer programme and cost. Designer are going to adopt
for the final design the access method, because as any steel factory is
existing on Isle of Wight, designer is going to transport and deliver materials
trough the sea. This modification is very relevant and delete traffic problem for
lorries deliver on land.(See cost on Appendix 7 and general programme on
Appendix 8)
Page 34 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
4- Construction Management
4.1- Method statement
- Scheme Description
4.1.1- METHOD STATEMENT 1: SLAB FLOOR
Scheme Description:
LIST Project Structural metalwork; including fabrication and
erection of members for frames
Plant Gang: 1 Barge crane (including operator),1 Mobile crane
(including operator),
2 Cherry pickers (including operators). (ICE, 1999)
Labour Gang: 1 Ganger, 2 Labourers, 1 Banks man. (ICE, 1999)
Method statement:
A-General requirements:
1- Provide supervision and administration. (ICE, 1999)
2- ” Ensure all ear and eye protection are considered to be taken to
reduce the noise and debris risk” (Charlett, 2006, p 231-233)
3- Provide water supply services for the duration of construction -
Quality risk of temperature days that are too hot or too cold
Page 35 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
4- Provide sufficient potable water, either from bottled sources or
track delivery.
- Access
- 5- Access to the site and working areas will be as follows:
- 6- Labour via foot (once walkway is complete). Jack-Up barge labour;
access via boat.
- 7- Large deliveries to be delivered to Bembridge Harbour. A supply
barge and loading facilities will be available at all times to move
plant and materials to the Jack-Up by sea, throughout the duration
of the contract. The drill rig will be assembled at this location, then
transported to the lifeboat station on the Jack-Up by sea.
- 8- Fuel to be delivered to the site compound (at existing lifeboat
station car park).
- 9- Bring Jack-Up Barge (with on board plant as specified) to site.
- 10- Test rig for operation.
- 11- Full PPE will be worn at all times – Life jacket when on barge over
water, hard hat, suitable gloves, high visibility, ear defenders, safety
goggles, fire retardant overalls and steel toe capped boots.
- B- Specific Material requirements:
- 1- Order members for frames and holding down bolts.
- 2- Fabricate all members for frames at factory.
Page 36 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- 3- Deliver steel frames to construction site. Environmental Risk-
Delivery to site. (Guidance for the Prevention of Pollution, 2003).
- 4- Check and sort delivery and store in previously prepared storage
area. Quality Risk- Quality assurance of fabrication yard. (CDM
Regulations, 2004)
- 5- Unload materials using site crane and use banks man to guide
plant into position. Workforce supplied with full PPE and leather
gloves. (Health and safety personal 101, 1999) (CDM Regulations,
D9-1 pp.129, 2004) (CIRIA, 19990, pp.90) H&S Risk – reversing
lorries.
- 6- Check out that the crane has been erected in accordance with
manufacturer’s specifications and safely regulations.
- 7- Position Barge crane and check load capacity certificate. ( CIRIA
special publication 131 crane stability on site, 1996)
- 8- Maintain Barge crane - Quality risk of competence of workforce.
(ICE, 1999)
- 9- Specify the competency required for a safe and effective operation.
- 10- Offload materials and maintain services gang by labour teams -
Environmental risk of wet weather working: slippery surface protect
by guard-rail, Health and Safety risk of Heavy Lifting.
- 11- Ensure that all equipment including back-up lighting, heater and
shelters, is appropriate for use in extreme weather conditions and
power failure.
- 12- Take material to tip.
Page 37 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- C- Beam Steel work:
- 13- Lift steel beams using Barge crane, install beams on preloaded
holding down bolts and fix bolts.
- 14- Lift and install trusses and beam to beam. Quality Risk-
Tolerances of frames. (Downey & Ericksen,2006,p. 47-49)
- 15- Weld and bolt all the connections of frames. Health and Safety
Risk - Working at height and over water. (Parliament, 2005) (CDM
Regulations, E6-1 pp.157, 2004) (CIRIA Special publication 118
Steel reinforcement, 1995)
- 16- Unload beams grid to worksite on piles and fix it using bolts and
frame welded. Quality Risk-Tolerances of frames. (Downey &
Ericksen,2006)
D- Bison Hollow Precast composite Floor:
- 1- Precast units including floors shall be given under appropriate
heading and shall unless otherwise required be enumerated (kind,
quality and size of each floor unit). (The royal institution of
chartered surveyors & the national federation of building trades
employers, 1984, pp.39)
- 2- Pre-cast units shall include cast-in connections for handling,
positioning, hand rails and running lines. (CDM Regulations, C3-1
pp.73, 2004) (CIRIA Report 166)
- 3- Have hollow precast concrete floor delivered to site. Using crane
guides by banks man with swing bar to stabilize precast concrete
floor unit to transport it from bank to worksite above the sea.
Page 38 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Workforce supplied with full PPE and leather gloves. (Health and
safety personal 101, 1999)
- 4- Using guard-rail systematically fixed on precast slab unit. (CDM
Regulations, C3-1 pp.73, 2004)
- 5- Place in situ concrete using crane concrete skip to 50mm thickness
finish flooring and to join both precast slab units. (CDM
Regulations, C1-1 pp.65, 2004)
- 6- Finishes on to concrete floor using appropriate material. (CDM
Regulations, C2 pp.71, 2004)
This method statement should be read in conjunction with the risk
assessment attached.
4.1.2- METHOD STATEMENT 2: SLIPWAY
Scheme Description:
LIST Project Structural metalwork; including fabrication and
erection of members for frames
Plant Gang: 1 Barge crane (including operator),1 Mobile crane
(including operator),
2 Cherry pickers (including operators). (ICE, 1999)
Labour Gang: 1 Ganger, 2 Labourers, 1 Banks man. (ICE, 1999)
Method statement:
Page 39 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
A-General requirements:
1- Provide supervision and administration. (ICE, 1999)
2- ” Ensure all ear and eye protection are considered to be taken to
reduce the noise and debris risk” (Charlett, 2006, p 231-233)
3- Provide water supply services for the duration of construction -
Quality risk of temperature days that are too hot or too cold
4- Provide sufficient potable water, either from bottled sources or
track delivery.
- Access
- 5- Access to the site and working areas will be as follows:
- 6- Labour via foot (once walkway is complete). Jack-Up barge labour;
access via boat.
- 7- Large deliveries to be delivered to Bembridge Harbour. A supply
barge and loading facilities will be available at all times to move
plant and materials to the Jack-Up by sea, throughout the duration
of the contract. The drill rig will be assembled at this location, then
transported to the lifeboat station on the Jack-Up by sea.
- 8- Fuel to be delivered to the site compound (at existing lifeboat
station car park).
- 9- Bring Jack-Up Barge (with on board plant as specified) to site.
- 10- Test rig for operation.
Page 40 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- 11- Full PPE will be worn at all times – Life jacket when on barge over
water, hard hat, suitable gloves, high visibility, ear defenders, safety
B- Specific Material requirements:
- 1- Order members for frames and holding down bolts.
- 2- Fabricate all members for frames at factory.
- 3- Deliver steel frames pre-connected to construction site on shore.
Environmental Risk- Delivery to site. (Guidance for the Prevention
of Pollution, 2003).
- 4- Check and sort delivery and store in previously prepared storage
area. Quality Risk- Quality assurance of fabrication yard. (CDM
Regulations, 2004)
- 5- Unload materials using site crane and use banks man to guide
plant into position. Workforce supplied with full PPE and leather
gloves. (Health and safety personal 101, 1999) (CDM Regulations,
D9-1 pp.129, 2004) (CIRIA, 19990, pp.90) H&S Risk – reversing
lorries.
- 6- Check out that the crane has been erected in accordance with
manufacturer’s specifications and safely regulations.
- 7- Position Barge crane and check load capacity certificate. ( CIRIA
special publication 131 crane stability on site, 1996)
- 8- Maintain Barge crane - Quality risk of competence of workforce.
(ICE, 1999)
Page 41 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- 9- Specify the competency required for a safe and effective operation.
- 10- Offload materials and maintain services gang by labour teams -
Environmental risk of wet weather working: slippery surface protect
by guard-rail, Health and Safety risk of Heavy Lifting.
- 11- Ensure that all equipment including back-up lighting, heater and
shelters, is appropriate for use in extreme weather conditions and
power failure.
- 12- Take material to tip.
- C- Beam Steel work:
- 1- Lift steel beams using Barge crane, install beams pre-connected
on preloaded holding down bolts and fix bolts.
- 2- Lift and install trusses and beam to beam. Quality Risk-Tolerances
of frames. (Downey & Ericksen,2006,p. 47-49)
- 3- Weld and bolt all the connections of two frame units. Health and
Safety Risk - Working at height and over water. (Parliament, 2005)
(CDM Regulations, E6-1 pp.157, 2004) (CIRIA Special publication
118 Steel reinforcement, 1995)
- 4- Use suspended working platform (PERI UP Rosett, 2006) to work
on low tide water for the final part.
- 5- Unload beams grid to worksite on piles and fix it using bolts and
frame welded. Quality Risk-Tolerances of frames. (Downey &
Ericksen,2006)
Page 42 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
D- Metal Grid Flooring and handrail :
- 1- Metal open grid flooring shall be given under appropriate heading
and shall unless otherwise required be enumerated (kind, quality
and size of each floor unit). (The royal institution of chartered
surveyors & the national federation of building trades employers,
1984)
- 2- Metal open grid flooring units shall include cast-in connections for
handling, positioning, hand rails and running lines. (CDM
Regulations, C3-1 pp.73, 2004) (CIRIA Report 166)
- 3- Have metal open grid floor delivered to site. Using crane guides by
banks man with swing bar to unload metal grid floor unit on
boatroom slab. Workforce supplied with full PPE and leather
gloves. (Health and safety personal 101, 1999)
- 4- Using guard-rail systematically fixed on Metal grid flooring unit for
external units. (CDM Regulations, 2004)
This method statement should be read in conjunction with the risk
assessment attached.
4.1.3- METHOD STATEMENT 3: WALKWAY
Scheme Description:
LIST Project Structural metalwork; including fabrication and
erection of members for frames
Plant Gang: 1 Barge crane (including operator),1 Mobile crane
Page 43 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
(including operator),
2 Cherry pickers (including operators). (ICE, 1999)
Labour Gang: 1 Ganger, 2 Labourers, 1 Banks man. (ICE, 1999)
Method statement:
A-General requirements:
1- Provide supervision and administration. (ICE, 1999)
2- ” Ensure all ear and eye protection are considered to be taken to
reduce the noise and debris risk” (Charlett, 2006, p 231-233)
3- Provide water supply services for the duration of construction -
Quality risk of temperature days that are too hot or too cold
4- Provide sufficient potable water, either from bottled sources or
track delivery.
- Access
- 5- Access to the site and working areas will be as follows:
- 6- Labour via foot (once walkway is complete). Jack-Up barge labour;
access via boat.
- 7- Large deliveries to be delivered to Bembridge Harbour. A supply
barge and loading facilities will be available at all times to move
plant and materials to the Jack-Up by sea, throughout the duration
of the contract. The drill rig will be assembled at this location, then
transported to the lifeboat station on the Jack-Up by sea.
Page 44 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- 8- Fuel to be delivered to the site compound (at existing lifeboat
station car park).
- 9- Bring Jack-Up Barge (with on board plant as specified) to site.
- 10- Test rig for operation.
- 11- Full PPE will be worn at all times – Life jacket when on barge over
water, hard hat, suitable gloves, high visibility, ear defenders, safety
B- Specific Material requirements:
- 1- Order members for frames and holding down bolts.
- 2- Fabricate all members for frames at factory.
- 3- Deliver steel frames pre-connected to construction site on shore.
Environmental Risk- Delivery to site. (Guidance for the Prevention
of Pollution, 2003).
- 4- Check and sort delivery and store in previously prepared storage
area. Quality Risk- Quality assurance of fabrication yard. (CDM
Regulations, 2004)
- 5- Unload materials using site crane and use banks man to guide
plant into position. Workforce supplied with full PPE and leather
gloves. (Health and safety personal 101, 1999) (CDM Regulations,
D9-1 pp.129, 2004) (CIRIA, 19990, pp.90) H&S Risk – reversing
lorries.
- 6- Check out that the crane has been erected in accordance with
manufacturer’s specifications and safely regulations.
Page 45 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- 7- Position Barge crane and check load capacity certificate. ( CIRIA
special publication 131 crane stability on site, 1996)
- 8- Maintain Barge crane - Quality risk of competence of workforce.
(ICE, 1999)
- 9- Specify the competency required for a safe and effective operation.
- 10- Offload materials and maintain services gang by labour teams -
Environmental risk of wet weather working: slippery surface protect
by guard-rail, Health and Safety risk of Heavy Lifting.
- 11- Ensure that all equipment including back-up lighting, heater and
shelters, is appropriate for use in extreme weather conditions and
power failure.
- 12- Take material to tip.
- C- Beam Steel work:
- 1- Lift steel beams using Barge crane, install beams pre-connected
on preloaded holding down bolts and fix bolts.
- 2- Lift and install trusses and beam to beam. Quality Risk-Tolerances
of frames. (Downey & Ericksen,2006,p. 47-49)
- 3- Weld and bolt all the connections of two frame units. Health and
Safety Risk - Working at height and over water. (Parliament, 2005)
(CDM Regulations, E6-1 pp.157, 2004) (CIRIA Special publication
118 Steel reinforcement, 1995)
Page 46 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- 4- Use suspended working platform (PERI UP Rosett, 2006) to work
on low tide water for the final part.
D- Metal Grid Flooring and handrail :
- 5- Metal open grid flooring shall be given under appropriate heading
and shall unless otherwise required be enumerated (kind, quality
and size of each floor unit). (The royal institution of chartered
surveyors & the national federation of building trades employers,
1984)
- 6- Metal open grid flooring units shall include cast-in connections for
handling, positioning, hand rails and running lines. (CDM
Regulations, C3-1 pp.73, 2004) (CIRIA Report 166)
- 7- Have metal open grid floor delivered to site. Using crane guides by
banks man with swing bar to unload metal grid floor unit on
boatroom slab. Workforce supplied with full PPE and leather
gloves. (Health and safety personal 101, 1999)
- 8- Using guard-rail systematically fixed on Metal grid flooring unit for
external units. (CDM Regulations, 2004)
This method statement should be read in conjunction with the risk
assessment attached.
Page 47 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
4.2- Material Specifications
4.2.1- Material properties/ characteristics.
i/ Steel framework: Universal Beam – UB.
Section designation
The standard method for specifying the dimensions of a standard hot rolled steel
section includes using initials to designate the type of section, for example:
457x191x67UB, is a Universal Beam of nominal dimensions 457mm deep, 191mm
wide, weighing 67Kg/m. The table below shows the new section designation system
Page 48 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
for Advance sections from Corus (2005).
Section designation system
Corus AdvanceTM sectionsOld designation system
UKB UK Beam UB Universal Beam
UKC UK Column UC Universal Column
UKPFC UK Parallel Flange Channel
PFC Parallel Flange Channel
UKA UK Angle RSA Rolled Steel Angle
UKBP UK Bearing Pile UBP Universal Bearing Pile
UKT UK Tee Figure 1. Section designation system. (Corus, 2005)
All the Advance structural steel sections are supplied in accordance with the
Standards indicated in the table below.
Standards applicable to AdvanceTM sections from Corus
Section type
AdvanceTM
designation Dimensions
Tolerances
UK Beam UB BS 4-1:2005 BS EN 10034:1993
UK Parallel Flange Channel
UKPFC BS 4-1:2005
BS EN 10279:2000
Figure 2. Standard application for universal beams. (Corus, 2005)
Universal Beams- BS EN 10025: 2004 and BS 4 Part 1: 1993 (Roymech, 2006).
Page 49 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
DesignationMassperm
DepthofSection
WidthofSection
Thickness of
Root Radius
DepthbetweenFillets
AreaofSection
Second Moment Area
Radius of Gyration
Section(Elastic)Modulus
PlasticModulus
Web FlangeAxis x-x
Axis y-y
Axis
x-x
Axis
y-y
Axis x-x
Axis y-y
Axis x-x
Axis
y-y
M h b s t r d A Ix Iy rx ry Zx Zy Sx Sy
kg/m mm mm mm mm mm mm cm2 cm4 cm4 cm cm cm3 cm3 cm3 cm3
762x267x147 146.9 754 265.2 12.8 17.5 16.5 686 187 168502 5455 30 5.4 4470 411 5156 647
610x305x149 149.2 612.4 304.8 11.8 19.7 16.5 540 190 125876 9308 25.7 7 4111 611 4594 937
533x210x122 122 544.5 211.9 12.7 21.3 12.7 476.5 155 76043 3388 22.1 4.67 2793 320 3196 500
406x178x54 54.1 402.6 177.7 7.7 10.9 10.2 360.4 69 18722 1021 16.5 3.85 930 115 1055 178
356x127x33 33.1 349 125.4 6 8.5 10.2 311.6 42.1 8249 280 14 2.58 473 44.7 543 70.3
254x146x31 31.1 251.4 146.1 6 8.6 7.6 219 39.7 4413 448 10.5 3.36 351 61.3 393 94.1
127x76x13 13 127 76 4 7.6 7.6 96.6 16.5 473 55.7 5.35 1.84 74.6 14.7 84.2 22.6
Figure 3. Niversal beams BSEN 10025. (Roymech, 2006)
Page 50 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
ii/ Walkway and Slipway guardrails.
Figure 5: offshore handrail (kee Klamp, 2006)
For a steel solution (Kee Klamp, marine solutions, 2006):
Kee railing solution can be used with absolute confidence for safety
walkways in aggressive coastal environments. It provides advantage of a
quick assembly of offset railings, handrails and guardrails.
Kee Klamp are hot dip galvanized cast iron fittings that are built to last. Each
fitting can support an axial load of 900 kgs, and includes a safety factor of 2:1.
Page 51 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
iii/ Walkway and Slipway open metal grid floor surfacing
(Tolartois Gratings, 2006)
Page 52 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Figure 6 a/b: tolartois, 2006. Open metal grating floor
Page 53 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Figure 7: Tolartois, 2006. Element chosen
Figure 8: tolartois, 2006. resistance data-weight
Page 54 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
iv/ Precast Hollow Composite Floor.
Figure 9 a/b/c: Bison hollow composite floor (Bison, 2007)
Pre-cast floor Advantages
- Speed of Erection
Time consuming activities such as propping, shuttering and concrete pouring
are virtually eliminated.
- No Propping
Propping is not required with hollow core floors. Compare this with the large
amount of propping required with insitu and semi-insitu floor systems. It is a
very interessant advantage considering a maritime construction scheme, as a
lifeboat station.
- Fire Resistance
Page 55 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Standard precast floors can be supplied with a fire resistance of up to 2
hours.Periods in excess of this can be provided with modified sections if
required.
- Minimum Insitu Concrete
Using a precast floor, a large volume of work is carried out off site and saves
what can be complex and time consuming site operation subject to the
vagaries of the climate.
- Immediate Unpropped Working Platform
Once a precast floor is erected, it is immediately available as a working
platform. We can save working time and then money..
Steel deck systems by comparison can present problems in achieving level
surfaces whilst concrete is poured and in providing access whilst in the
propped condition.
- Preformed Site Services
Precast floors can be provided with factory formed service holes thus
avoiding laborious setting out and shuttering on site.
- Extra Long Spans
Factory made prestressed units offer the maximum design advantages of
achieving long span units for given depths. This avoids the need for
intermediate supports and provides an economically light solution throughout
Page 56 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
the entire structure. The Bison long span 450 mm deep unit can span in
excess of 16 metres.
- A 5.50m span as a maximum for LIST Project.
- Finished Soffits
Precast floors are manufactured on high quality steel beds and are suitable in
appropriate cases for direct decoration.
- Flexibility of Design Approach
Precast floors are available with a variety of factory formed notches, slots and
reinforcement arrangements which offer various design approaches.
- A precast floor of 1.20m wide as a maximum is using in LIST Project,
because of a various design approaches allowed according with Bison hollow
composite floor, 2007.
- Elimination of Edge Shuttering
Edge shuttering to any building is inevitably a difficult and often dangerous
operation. This can be totally avoided by using a precast floor.
- Structural Efficiency
A hollow core slab offers the ideal structural section by reducing the
deadweight whilst providing the maximum structural efficiency within the slab
depth.
Page 57 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- Factory Produced to Rigorous Quality Standards
Because precast floors are factory produced, they are manufactured in an
environment which is more readily controlled than a building site. Quality
control systems are properly implemented and are independently examined
on a regular basis under the British Standards Institution Quality Assurance
Scheme.
- Cost of quality assurance fabrication yard is by the way reducing.
Figure 10. (Bison, 2007) Element chosen
Page 58 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
All steel is to be grade 43 with a unit weight of 7850kg/m³ and all bolted
connections to use either M24 HSFG bolts or M20 Lindapter Hollobolts.
Universal Beams used in L.I.S.T Project comply with- BS EN 10025: 2004
and BS 4 Part 1: 1993 (Roymech, 2006).
Slipway:
UB 762 x 267 x 147 4.00m
weight = 146.9kg/m 44nr
UB 610 x 305 x 149 4.00m
weight = 149.2kg/m 11nr
UB 356 x 127 x 33 4.00m
weight = 33kg/m 12nr
UB 127 x 76 x 13 0.849m
weight = 13kg/m 12nr
Page 59 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Channel 305 x 89 4.00m
weight = 41.69kg/m 11nr
Plate 150 x 15 4.00m
weight = 7850kg/m³ 22nr
Bolts M20, grade 8.8 664nr
Walkway:
UB 553 x 210 x 122 10.00m
weight = 122kg/m 42nr
UB 553 x 210 x 122 1.80m
weight = 122kg/m 22nr
Bolts M20, grade 8.8 176nr
Slab:
UB 406 x 178 x 122 5.50m
weight = 54.1kg/m 6nr
Page 60 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
UB 406 x 178 x 122 5.00m
weight = 54.1kg/m 6nr
UB 406 x 178 x 122 4.50m
weight = 54.1kg/m 12nr
UB 254 x 146 x 31 9.00m
weight = 31.1kg/m 2nr
UB 254 x 146 x 31 5.00m
weight = 31.1kg/m 3nr
UB 254 x 146 x 31 4.00m
weight = 31.1kg/m 1nr
UB 254 x 146 x 31 3.00m
weight = 31.1kg/m 12nr
Bolts M20, grade 8.8 288nr
Page 61 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
4.2.2- Testing Procedures
i/ Thickness test
Testing the thickness of the metallic coating on the steelwork should be
undertaken by a suitably qualified inspector with the use of an ultrasonic
thickness gauge. (Coatings for protection of structural steel work, 2000)
The ultrasonic thickness gauge must first be calibrated by placing the probe
on an un-treated steel section. The probe is then placed on the area to be
inspected, the instrument will display an accurate reading for the coating
thickness and steel thickness at the same time. (Ultrasonic thickness, n.d.)
ii/ Liquid penetrant inspection
This method should be used regularly to check that the thickness of the zinc
coating is at least 100 µm.
This method of testing is used on non absorbent materials to look for flaws
and cracks in the surface of the material. In this case it will be used to test the
large steel beams which the walkway. The test involves applying a
fluorescent liquid to the surface of the steel and allowing 10-20mins it to soak
in (Munns, 2004).
Page 62 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
After this time has elapsed the excess liquid is wiped from the top of the steel
and a ‘developer’ is applied to the steel, this draws the penetrant out of the
cracks (Munns, 2004).
The penetrant can then be seen under UV indicating any cracks in the
surface of the steel. A special area would have to be set up site so that the
indicators could be viewed in darkened conditions (Munns, 2004).
Page 63 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
4.2.3- Performance criteria
i/ Corrosion protection
- Techniques Used for Corrosion Control
All steelwork will be protected against corrosion in accordance with BS
5493:1977. For permanent installations, few commonly used construction
materials have sufficient inherent resistance to corrosion to perform
adequately without the use of some form of corrosion control. In order for the
selection of the most cost effective combination of materials and corrosion
control techniques, the efficiency of the corrosion control technique for
specific materials must be determined. This normally requires testing.
(Baboian, 1995).
- Protective Coatings
Protective coatings are widely used for controlling corrosion of marine
structures. For proper selection of coatings many factors must be considered
including the zone of exposure, degree of shelter, the substrate to be
protected and the potential for recoating. (Baboian, 1995).
- Cathodic Protection
Page 64 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Cathodic Protection is widely used for the protection of submerged steel in
water front structures. It can also provide considerable benefit in the inter-tidal
zone and can even reduce the usually high corrosion rate experienced at the
boundary between the inter-tidal and splash/spray zones. Cathodic protection
is also effective in the control of corrosion in reinforcing steel in concrete in all
exposure zones in waterfront structures. (Baboian, 1995).
From (M.N, E.J, H.G, V.D, 2006) All steelwork will be protected against
corrosion in accordance with BS 5493:1977.
For this level of protection from corrosion Table 2 of BS 5493:1977
recommends that a sealed or unsealed, zinc or aluminium sprayed coating,
with a minimum thickness of 100 µm. Zinc will be used as it is more resilient
to corrosion. (Coatings for protection of structural steel work, 2000)
The most common methods of metallic coating are
- hot-dip galvanizing, or
- thermal spraying.
Because of there is a limit of the size of member which can be hot-dip
galvanised, the method most likely to be used for the majority of the structural
metalwork of the Life boat Station is to be thermal spraying, which has no size
limit. However thermal spraying is usually more expensive than hot-dip
galvanising, therefore members that are small enough should be coated using
this process. (Coatings for protection of structural steel work, 2000)
Page 65 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
The advantages of the sprayed zinc coating are that it has a predictable life,
it’s a single application system with no drying time needed, it can be applied
off-site and on-site for touching up areas, it has no effect on the metallurgical
properties of the steel and structures of any size can be protected. (EN ISO
14713:1999)
Guidance for the application of metallic zinc coatings is given in EN ISO
14713:1999; it states that the steel is first to be grit-blast cleaned to achieve a
clean roughened surface with which the metallic coating can be applied.
It is important that the areas around where HSFG bolts are used in bolt
connections are not coated, as the coating would reduce the slip factor
required for the joint. These areas can be touched-up after construction of
the frame is complete. (Coatings for protection of structural steel work, 2000)
The sealing coat and additional paint, for aesthetics, or intumescent fire
protection coating will prolong the corrosion protection, and therefore the time
between maintenance periods. (Coatings for protection of structural steel
work, 2000) (M.N, E.J, H.G, V.D, 2006)
ii/ Fire protection: intumescent coating
From (Corus Construction, 2006) Fire resistance a measure of the time taken
before an element of construction exceeds specified limits for load carrying
Page 66 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
capacity, insulation and integrity. These limits are clearly defined in the
standard. The characteristics of the time-temperature relationship for the test
fire from BS476 are shown in Figure 30 shown below.
All materials become weaker when they get hot. The strength of steel at high
temperature has been defined in great detail and it is known that at a
temperature of 550ºC structural steel will retain 60% of its room temperature
strength, Figure shown below, before collapse.
Figure 11 a/b: Standard fire test (Corus constrcution, 2006)
In BS5950 Part 8, (see Code of Practice for Fire Resistant Design), load is
expressed in terms of the ‘Load Ratio’.
Recent international research has shown, however, that the limiting (failure)
temperature of a structural steel member is not fixed at 550ºC but varies
according to two factors, the temperature profile and the load.(Corus
Page 67 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
construction, 2006)
Figure 12: Fire steel resitance design. (Corus constrcution, 2006)
Application :
For the fire protection of the internal structural steel, an intumescent coating
such as the Nullifire System E will be used, which has 240 minutes fire and
blast protection (Nullifire, 2001).
When it reaches its maximum size - after about 10 seconds - the coating
hardens and solidifies to form ‘char’ which protects the steel from the heat of
the fire (Nullifire, 2001).
-
Page 68 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
4.3- Risk Assessments
4.3.1- HEALTH AND SAFETY PRECAUTIONS
Only personnel with experience will be utilised.
Briefings will be carried out prior to each shift which will include:
- Specialist PPE
- Programme of works
- Methodology
- Contingency and emergency plans
- Effect of adverse weather on site conditions
- Competency of operatives
THE MAIN CONTRACTOR IS TO BE RESPONSIBLE FOR ALL WELFARE
Page 69 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
4.3.2- Cost of Risk
Steel erection is risky due to the large, heavy components that must be lifted
into place and the instability of the structure in the part-erected condition.
(Steel the safe, n.d.)
Following pages list the most common risks relevant to structural steelwork
erection and working over water as for an offshore site, and preventative
control measures.
The total financial contingency from the Slipway, Slab and Walkway risks is
£330,250. This amount was approved in the Design Seminar by Peter
CROSS.
4.3.3- Whole Life Costing
Construction Costs of the lifeboat station (M.N, E.J, H.G, V.D, 2006).
From the Bill of Quantities, the total cost of the construction of the lifeboat
station:
Slipway: (excluding Class A and B items) = £103,127.47
Page 70 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Slab: (excluding Class A and B items) = £121,886.82
Walkway: (excluding Class A and B items) = £127,876.32
As this figure does not include Class A and B items, it does not include: plant,
labour, supervision, ground investigation, or site mobilisation.
The total financial contingency found from undertaking the Risk Assessment =
£330,250
Therefore this gives a total construction cost for the Slipway of £433,377.47
Therefore this gives a total construction cost for the Slab of £452,136.82
Therefore this gives a total construction cost for the Walkway of £458,126.32
Consultancy/ Design Costs
This value has been assumed to be 10% of the total cost of the structure:
Total Slipway = £43,377.75
Total Slab =£45,213.70
Page 71 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Total Walkway = £45,812.63
Maintenance Costs
Design life of structure = 50 years
Inspections
General = £200 every 2 years
Total = £4,800
Principle = £3000 every 5 years
Total = £27,000
Maintenance
Resurfacing of tiling every 15 years = £50,000
Total = £100,000
Demolition
This value is assumed to be 10% of the construction costs, adjusted for
inflation at 2% for 50 years.
£ 43,337.747x 1.02^50 = £116,647.361
Total Slipway = £725,202.11
Page 72 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
£ 45,213.682 x 1.02^50 = £121,696.605
Total Slab= £749,011.12
£ 45,812.632 x 1.02^50 = £123,308.732
Total Walkway= £758,448.75
4.3.4- Major Risk Mitigation
(See Risk assessment on Appendix 6)
i/ Risk with highest impact = Working at Height (Fatality)
(Staybills patented guardrail and trestle system, 2006).
New legislation (WAHR) has come into force since 6th April 2005. This
followed the HSE producing this document in consultation with the DTI
(Department of Trade and Industry) and BSI (British Standards Institution) to
control working at height following the European Temporary Work at Height
Directive (published December 2003).
Approximately 2.2 million people work in Britain’s construction industry,
making it the country’s biggest industry. However, it is also one of the most
dangerous. In the last 25 years, over 2,800 people have died from injuries
Page 73 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
they received as a result of construction work. Many more have been injured
or made ill. In 2006/2007 over 70 people died and nearly 4000 suffered a
serious injury as a result of a fall from height in the workplace.
Falls from height are the most common cause of fatal injury and the second
most common cause of major injury to employees, accounting for around
15% of all such injuries. All industry sectors but in particular Construction
workers are exposed to the risks presented by this hazard although the level
of incidence varies considerably.
As a result, Falls from Height are a key priority in the Health and Safety
Commission Injury Reduction Programme. The objective is to reduce injury
rates by 10% by 2010 against a 1999/00 baseline.
Experience shows that falls from height usually occur as a result of poor
management control rather than because of equipment failure.
Common factors include:
• Failure to recognise a problem.
• Failure to provide safe systems of work.
• Failure to ensure that safe systems of work are followed.
• Inadequate information, instruction, training or supervision provided.
Page 74 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
• Failure to use appropriate equipment;
• Failure to provide safe plant/equipment.
Key Measures include:
Regulations detailing control measures include (M.N, E.J, H.G, V.D, 2006)
Management of Health and Safety at Work Regulations 1999
Construction [Health, Safety and Welfare] Regulations 1996
Construction Safety Manual Sections 3 and 7
GE 700 Construction Site Safety Modules C2-9, D4
All work at height is a high risk activity. At the start of each project the site
manager will identify all activities which involve work at height and decide on
suitable prevention measures and detail them in the specific activity Method
Statements and Risk Assessments. These should be then briefed to all
operatives before works commence.
The Regulations require duty holders to ensure (Work at Height Regulations,
2005, part 6-3)
- all work at height is properly planned and organized.
Page 75 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- all work at height takes account of weather conditions that
could endanger health and safety:
You must ensure that the work is postponed while weather conditions
endanger health or safety (Regulation 4(3, 4)).
- those involved in work at height are trained and competent:
(Regulations 5 and 6(5)(b)). This includes involvement in organisation,
planning, supervision, and the supply and maintenance of equipment.
- The place where work at height is done is safe:
(Regulation 6(4)) You must ensure that the place where work is done at
height (including the means of access) is safe and has features to prevent a
fall, unless this would mean that it is not reasonably practicable for the worker
to carry out the work safely (taking into account the demands of the task,
equipment and working environment).
- The risks from falling objects are properly controlled.
Use safety fillet to collect falling objects, like work tools...
- Equipment for work at height is appropriately inspected:
(Regulations 6(4)(b), 6(5)(a, b), 7, 8 and 12) You must provide equipment for
preventing a fall occurring comply CDM: Use the most suitable equipment
and give collective protection measures (eg guard rails see picture 1) priority
over personal protection measures (eg safety harnesses, see picture 2
bellow):
Page 76 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Example of collective mitigation measure (Working platform):
Figure 13: Collective mitigation measure. (the plateforme compagny, 2007)
Example of individual mitigation measure (Harness):
Harnesses do not prevent falls. They merely prevent the wearer from falling
too far.
Page 77 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Figure 14. individual mitigation measure, hardness. (the plateforme compagny, 2006)
Full arrest
lanyard
Shock
absorbingBS EN:355
RestraintWork
positioningBS EN:358
Full body Harnesses BS EN:361
Karabiners Connectors BS EN:362
The following steps should be considered when designer are planning work at
height (.N, E.J, H.D, V.D, 2006)
- decide what particular equipment will be suitable for the job and the
conditions on site
- make sure work platforms and any edges from which people are likely
to fall have guard rails and toe boards or other barriers
- make sure that the equipment needed is delivered to site in good time
and that the site has been prepared for it
Page 78 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- check that the equipment is in good condition and make sure that
whoever puts the equipment together is trained, competent, and
knows what they are doing
- make sure those who use the equipment are trained in its uses and
supervised so that they use it properly. The more specialised the
equipment [for example, boatswain’s chairs and rope access
equipment], the greater the degree of training and supervision
required to ensure safety
- check any equipment provided by another company is safe on site
before using it
- make sure people know who to tell if any defects need to be
remedied or modifications need to be made
- when harnesses are used, ensure there is sufficient clearance from
the ground to allow the shock absorbing lanyard or inertia reel to
fully extend.
- harnesses must be connected to a properly designed anchorage
point. Whenever harnesses are used a method must be available to
enable people to be rescued should they fall and be left suspended
in their harness.
- Users of harnesses must be trained in their use, inspection and
maintenance.
ii/ Working over water
Stability of working platform and crane, Storage including waste materials,
Work at appropriate weather, and with safety jacket. Signs to warn deep
water use guardrail systems systematically fixed of material (example on
Page 79 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
precast elements), working platform, safety nets or fall arrest systems (Bob
Babin, (2006).
Because of slippery conditions in cold, windy, wet or icy weather, and
because of the tall working height (13 to 15 feet) atop these vehicles, many
companies now install a combination of fall prevention and fall arrest
systems. These systems include an access system guardrail, non-slip
staircase and platform, as well as a counterweighted drop down gangway to
ascend the vehicle, and a fall arrest system for use while atop the vehicle.
These systems provide both OSHA compliance and maximum worker safety
(Bob Babin, (2006).
iii/ Lifting operations:
The major risk with heavy lifting takes place in the safe erection of the
attached steel beams of the slipway.
Page 80 of 136
Figure 15 a/b/c/d/e/f: personnel falling into water (CDM regulations, 2004)
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
To combat the risk of injury from heavy lifting, lifting aids are needed to be
used to greater effectiveness.
The Lifting Operations and Lifting Equipment Regulations (LOLER, 1998)
need to be considered fully to ensure a safe working practice is reached. The
regulations aim to reduce risks to people’s health and safety from lifting
equipment provided for use at work.
The regulations require that the lifting equipment for use on site is:
Strong and stable enough for the particular use and marked to indicate
safe working loads;
Positioned and installed to minimise any risks;
Used safely, i.e. the work is planned, organised and performed by
competent people; and
Subject to ongoing thorough examination and, where appropriate,
inspection by competent people.
The employer does not have duties under LOLER but they do under the
Management of Health and Safety at Work Regulations (MHSWR, 1999).
To ensure that the LOLER regulations are met, the lifting equipment should
be strong and stable, be positioned and installed to minimise risks and should
be visibly marked with any appropriate information to be taken into account
for it’s safe use, e.g. safe working loads. Accessories should be similarly
marked.
Page 81 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Additionally, it must be ensured that:
Lifting operations are planned, supervised and carried out in a safe
manner by people who are competent;
Where equipment is used for lifting people it is marked accordingly,
and it should be safe for such a purpose, e.g. all necessary
precautions have been taken to eliminate or reduce any risk;
Following a thorough examination or inspection of any lifting
equipment, a report is submitted by the competent person to the
employer to take the appropriate action.
iv/ Plant and vehicles:
Use traffic management plan & ensure vehicle maintenance. Keep vehicles
and pedestrians apart, use competent drivers & most appropriate vehicle for
the task. Use reversing sirens.
After Design Seminar it was decided to not use Lorries for deliveries but
boats, because there is any steel or pre-cast factory on the Isle of Wight.
v/ Slips and trips:
Ensure tidy and well-organised site. Store materials properly & keep
walkways clear.
Page 82 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
vi/ Workforce:
Workers have a right to be consulted. Ensure their involvement in health &
safety issues.
4.3.5- Health mitigation measures for construction processes (HSE,
2007):
Managing health: Organise your work to ensure that no one’s health is
adversly affected by their job. Produce an occupational health policy &
identify who will manage that policy & how.
Manual handling: Avoid where possible. Assess all tasks & reduce the risk.
Use mechanical assistance for all kerb/block lifting >20kg. Where possible,
use mechanical tying methods for steel fixing.
Cement dermatitis: Prevent direct contact. Provide hot/cold-running water
for washing & regular checks of exposed skin. Use protection gloves.
Page 83 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Noise: Assess & control exposure eg select tools to measure noise exposure
during construction processes for public on the beach and neighbours.
Workforce: Workers have a right to be consulted. Ensure their involvement in
health & safety issues. Communicate risks to contractors and workers.
Page 84 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
5- Construction Processes
5.1- Construction Programme
See Appendix 8: GANTT Chart
5.2- Construction Processes
This section covers the detailed construction process of the slipway, slab and
walkway of the Bembridge Lifeboat station. Prior to the Slipway, slab and
Walkway works, the piles must be erected (see Volume 1).
All structural steel members are pre-fabricated in the fabrication yard factory
prior to being delivered by boat to the site. The members will be grit-blasted,
zinc coated by either hot-dip galvanising or thermal spraying, sealed and
coated with an extra layer of intumescent fire protection. Care must be taken
to leave the bolted connection areas free of the coatings.
On each site units are erected with pre-attached on land temporary guard rail
on pre-cast concrete units on slab. On each site units are erected pre-
attached on land definitive guard rail on open grid floor on walkway and
slipway.
Page 85 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
The walkway construction begins from the land, as soon as piles are on
place. Then Steel frame are erected using crane on jack-up barge, with a two
points attach for stability. 10m span beams are fixing and after that
transversal one all the 10m are erected using the same scheme. When metal
grid is in situ, then open grid flooring could be erected with pre-attached
definitive guard rail fixed on land on open grid floor on walkway. Is it a very
long and repetitive task.
For the slab, the main grid beams (5m by 4.5m as an average grid size) is the
first to be lifted with a 2 points attached to provide horizontal stability into
place by use of the jack-up barge crane driving by a banks man to guide for
the slab in first the principal transversal beams, then le longitudinal ones.
When all grid metal flooring is fixing with connection, bolts, then pre-cast
concrete units are going to be lift by the crane using a 4 points attached
(palonnier) to provide horizontal stability and work with safety measures.
Then each part of the bat room and the offices are going to be done on the
same way, according with safety measure mitigation shown under and the
CDM Appraisal below. Finally formwork is done to allow to pour in-situ
concrete (mass concrete) for only 5cm depth to provide a well finish surfacing
a granolithic surfacing is done when in-situ concrete is dry. (the same day for
5cm depth, depending of weather).
Page 86 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
For the slipway, the arched truss is to be fabricated into 4 separate sections
of the main span, so that each section can easily be transported to site on a
delivery boat. When the tide is low, the crane lifts this pre-fabricated unit with
piles and with a lot of precision from the banks man, putting in on place
(hollows already done for piles). The beams are actually to be transported to
site by boat because of their length but also because there is any metal
factory on Isle of Wight. All connections and fixing bolts for this units is done
on land and allow in this way a very good schedule for work and provide a
very good quality of work. When it is received on site, the sections of the first
span, on the West face, will be arranged and welded together at ground level.
The full arched truss will be lifted into position using two cranes
simultaneously. The chains of the crane will be supporting the truss at either
end so that it does not affect the structural integrity whilst lifting. Each time
than two pre-fabricated units are on place under piles, then workers have to
fix both with bolts and welded connection. Operatives will bolt the arched
truss to the main beams via access on cherry pickers. The cranes shall
remain supporting the truss until all bolted connections are secure. This
dangerous task has to be done on safe, using a working platform on a jack-up
barge as possible when tide is low, and using as well a individual protection
as hardness to protect against falling into water. The slipway construction has
to respect a very strictly measure to provide the good construction levels and
slipway transversal and longitudinal slope. An automatic level is use by a
surveyor in charge of it during all the slipway construction.
Page 87 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
When it is received on site, the full structure will be lifted into position using
the crane. The chains of the crane will be supporting the beam at either end
so that it does not affect the structural integrity whilst lifting. Operatives will
bolt the beam to piles. The crane shall remain supporting the structure until all
bolted connections are secure.
Once the frame is complete, operatives in a cherry picker will go over the
whole structure and touch-up all areas that need corrosion protection with the
sprayed zinc coating. (M.N, E.J, H.G, V.D, 2006).
Each time a task is done and a day over, workers has to leave a worksite tidy
and clean to avoid accident.
Page 88 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
6- CDM Appraisal
6.1- Introduction
For the purposes of the CDM Regulations, a project is notifiable if the
construction phase is likely to involve more than 30 working days; or 500
person days, of construction work for a client.
The construction (Design and Management) Regulations 1994, aim to reduce
the risk of accidents arising from construction work. It ensures all risks are
identified, mitigated and managed throughout every stage of the Life Cycle of
the structure. The regulations require that the client must:
“Make information available and make reasonable enquiries in this
request” (HSE, n.d)
“Appoint competent designers, a planning supervisor and a principle
contractor, and ensure they have adequate resource” (HSE, n.d)
“Ensure that work does not start on site until an adequate health and
safety plan (see below) is established” (HSE, n.d)
“Ensure that any health and safety file is made available to those who
may need to see it” (HSE, n.d)
Page 89 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
6.2- CDM Compliance:
- Eliminate, Reduce, Inform, Control (ERIC) hazards and risks from
concept to completion.
- Promote better occupational health management throughout
construction process.
- Consider buildability of roofs, access, edge protection and
subsequent maintenance.
- Design out the need for ladders during construction, cleaning and
maintenance operations.
- Manage transport risks. Design and plan for segregation,
maintenance, driver visibility, and competence.
- Avoid or reduce risk of manual handling eg better design, specify
lifting aids,
- specify lighter materials.
- ERIC: Design out the need, select low exposure tools, communicate
risks to contractors and workers.
- Plan storage and delivery of materials to ensure good order and
housekeeping.
- Keep walkways clear.
- Promote engagement/ consultation with workers to ensure their
involvement in
- Health and safety issues.
Page 90 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- Work at height
The Construction Design and Management (CDM Regulations 1994), has aim
to reduce the risk of accidents and occupational ill health arising from
construction work. It ensures that construction health and safety risks are
avoided, mitigated or managed throughout every stage of the project and
involving all parties, client, designer, contractor and sub-contractor.
(Gilbertson, 2004)
Quality Assurance Systems
A QA system is required in order to maintain the best standards of work. The
following are integral to a go quality assurance system.
All parties involved in the project should have a clear understanding of
their roles and their responsibilities and those of other parties.
Good communication between all parties must be maintained
throughout the whole life cycle of the project. This should mean that all
parties are kept up to date with any important matters that arise in any
of the life stages of the structure.
Accurate records of all communications between parties should be
kept and stored. This is in case a dispute should arise.
Page 91 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
6.3- Obligation of persons involved in the construction
process
According with Construction design and Management Regulation 2007, Part 2
(HSE, 2007) obligations of the different parts involved in construction project
are:
6.3.1- The Client (HSE, 2007):
- Check competence and resources of all appointees
- Ensure there are suitable management arrangements for the project
welfare facilities
- Allow sufficient time and resources for all stages Provide pre-
construction information to designers and contractors
6.3.2- The Principal contractor (HSE, 2007):
- Plan, manage and monitor construction phase in liaison with
contractor
- Prepare, develop and implement a written plan and site rules (Initial
plan completed before the construction phase begins)
- Give contractors relevant parts of the plan
- Make sure suitable welfare facilities are provided from the start and
maintained throughout the construction phase
- Check competence of all appointees
Page 92 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- Ensure all workers have site inductions and any further information
and training needed for the work
- Consult with the workers
- Liaise with CDM co-ordinator regarding ongoing design
- Secure the site
6.3.3- As part of Designers we have to (HSE, 2007):
- Eliminate hazards and reduce risks during design.
- Provide information about remaining risks.
6.4- CDM during the whole life project: Health and Safety
This CDM file will be present through the life cycle of the building from
conception, design, construction, maintenance and finally demolition. It is vital
that the file is kept up to date with any significant occurrences that may affect
the stability or future use of the building. (HSE, n.d)
One of the main requirements of the CDM Regulations 2007 is that health
and safety is to be considered in every part of the life cycle of the building:
Preconstruction
Construction
Page 93 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Maintenance
6.4.1- Demolition
The health and safety file compiled in a normal project would be exhaustive.
For the process of this project only the main risks are identified in the risk
assessment (See Appendix 6 Risk Assessment). These are detailed on the
following pages.
Much of hazards will be present during the dismantling of the steel and
concrete frame of the old Bembridge lifeboat station located just beside the
new one, the post-construction health and safety file should be consulted
before commencing demolition works to assess any inherent risks involved.
6.4.2- Pre-construction
The CDM regulations state that the following must be completed before
construction works begin. (CDM regulations, 2007)
Pre-contract health & safety plan is produced by the client that details
foreseen job information, site conditions and risks.
Designers risk assessment is produced by the designer of the job, listing
foreseen risks with the design and construction.
Contractors risk assessment is produced by the contractor or sub-
contractor listing foreseen risks with construction.
Page 94 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
The final health and safety plan is compiled by the planning supervisor, which
includes all the above and which must be followed on-site during construction.
This is to be completed before any arrangements are made by the contractor
to start works. (CDM regulations, 2007)
Prior to commencement of works a method statement is produced, which
includes the specific task risk assessment. Method statements are not
required by law, but have been proven to be an effective management tool,
the risk assessments are mandatory and must be presented and
acknowledged by the workforce before work starts.
A notification form (F10) must be given to and signed by the Health & Safety
Executive (HSE) so that they are aware of work and have the authority to
inspect site health & safety at any time.
For the structure of the slipway, slab and walkway, special consideration
should be made towards the planning of the stability of the frame during
construction, as the incomplete frame is likely to be unstable. Temporary
props and supports will be required on a jack up barge until a plan and safety
platform is built (stable end core). See construction processes in next point.
(Controlling the risk, n.d.)
Page 95 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
6.4.3- Construction
The general health and safety on-site will be managed by the site
supervisors, who will ensure that the health and safety file, compiled before
construction, all work practices are followed and correct PPE is worn. This
can be achieved by briefing all personnel on-site before any activity.
Before lifting steelwork, a permit to lift certificate will be issued by the lifting
coordinator to show that all lifting equipment, cranes, jack-up barge, strops
and straps are properly certificated and that all operatives are competent in
the work activity. (CDM regulations, 2007)
The lifting of beams will be carried out with the presence of a qualified banks
man to guide the crane the lifting on the barge so as to avoid any possible
injury.
Throughout the duration of each job a health & safety record folder is kept,
this includes all safety related documents that demonstrate compliance with
the health and safety plan. This includes; records of site personnel, first aid
register, accident register, weekly site safety inspections, equipment/ plant
inspections, risk assessments, COSHH assessments and manual handling/
noise/ vibration assessments. (CDM regulations, 2007)
6.4.4- Post-construction
At the end of the job, a health & safety file is required to be produced under
CDM regulations. This is the hand-over document that lists how we have
Page 96 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
fabricated the project, what we have used and any specific hazards that
anyone should be aware of for future reference. It includes as-built drawings,
material conformity, test certificates and hazard data sheets for permanent
materials. (CDM regulations, 2007)
6.4.5- Maintenance
During the operation of the building, an inspection of the steel frame and pre-
cast concrete units will be required to check connections and look for signs of
corrosion or damage to protective layering on the steel. A general inspection
will be required once every two years and a detailed inspection will be
required once every five years.
The nature of the maintenance work required for the structural framing is
likely to be the re-treatment of steelwork with the zinc coating to protect
corrosion, because of the very harsh maritime environment, especially on the
inter-tide areas.
The inspections and maintenance needs are likely to be undertaken from the
use of scaffold towers erected inside the building when required, in which
case a safe system of works should be implemented to avoid risks of falling
from height and exposure to the zinc coating, with consultation to the post-
construction health and safety file.
Page 97 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
7- Environmental Assessment
7.1- General requirements
7.1.1- Life Station duration:
ALB’s have a life of 20 years when lying afloat and 25 years when housed
ashore. Class replacement is planned well in advance as it takes 7 years from
drawing board to class production.
The RNLI is proud of its tradition in building to a high standard. Many existing
stations have withstood harsh marine environments for over 100 years and
still provide good service today. High quality construction with low
maintenance costs is considered to be essential to the good management of
charitable funds (RNLI, n.d).
All new marine structures, i.e. slipways, etc. should be designed to have a life
of 50 years with only minimum maintenance. Particular attention is required
to basic materials, their use, specification and detailing (RNLI, n.d).
BS6349 Code of Practice for Maritime Structures is to be applied as a
minimum requirement for any part of a structure exposed to direct sea action,
sea spray or to flooding by sea water. Other British Standards and Codes of
Practice that are considered as essential references are listed in section 11,
‘Standard Specifications’ (RNLI, n.d).
Page 98 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Safe, effective and efficient maintenance is an essential requirement.
Designers must be able to demonstrate that buildings and structures can be
safely constructed and maintained in accordance with the requirements of the
Construction Design and Management Regulations (RNLI, n.d).
Public access is available and encouraged to certain areas of lifeboat
stations, where practical, and safe full disabled access is to be provided
(RNLI, n.d).
Environmental quality and certification
The emphasis on quality is intended to achieve good value for money over
the long term. Designers are expected to take a balanced view and to be
able to justify their recommended designs in accordance with this principle
(RNLI, n.d).
Therefore we designed a project in accordance with the Certification ISO
14001, describe below:
7.1.2- Certification ISO 14001:
ISO 14001 is the internationally recognised standard for the environmental
management of businesses. It prescribes controls for those activities that
have an effect on the environment. These include the use of natural
resources, handling and treatment of waste and energy consumption.
Implementing an Environmental Management System is a systematic way to
Page 99 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
discover and control the effects your company has on the environment. Cost
savings can be made through improved efficiency and productivity. These are
achieved by detecting ways to minimise waste and dispose of it more
effectively and by learning how to use energy more efficiently. This
demonstrates that your organisation is committed to environmental issues
and is prepared to work towards improving the environment (ISOQAR, 2007).
7.2- Environmental issues
This section will provide an appraisal of the key problems such as access,
safety and the environment that may effect the construction of a new lifeboat
station. The lifeboat station that is to be built will be to provide an offshore
lifeboat that is capable of reacting to emergencies both inshore and further
out sea.
The lifeboat station being built will have to be a larger size compared to most
other lifeboat stations on the south coast due to the need for newer and
bigger lifeboats. Another factor is that many of the older lifeboat stations have
reached their lifespan and it is therefore important to replace these stations
with up to date technology and equipment capable improving the current
capabilities of existing lifeboat stations.
Page 100 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
7.2.1- Land Contamination
There is unlikely to be any problems with land contamination as the locations
that the proposed lifeboat stations will be built on will be more than likely be
green field sites. There is a small possibility of contamination through oil or
petrol spillage at sites where an older lifeboat station is being replaced by a
newer one.
A desk study to look at previous land uses and a brief ground investigation
with a few trail pits should take place to rule out any possible ground
contamination issues.
7.2.2- Environmental Land Areas
Along the Solent’s coastline there are many areas that are classed as areas
of outstanding natural beauty or sites of special scientific interest (SSSI’s).
These areas of natural beauty can be a hindrance when it comes to designing
and building structures within the areas. Local authorities will insist that there
will have to be none or very little damage to the surrounding area both during
and after the construction phase.
It will become important to carry out a full environmental assessment in the
area of the proposed lifeboat station this will identify any major environmental
impact that the construction may have on the surrounding area and its
ecology.
Page 101 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
The environmental assessment will also outline possible risks and methods of
reducing these risks. Once an environmental assessment is complete as
satisfactory for the relevant authorities then the project will achieve planning
permission.
The areas of outstanding natural beauty (AONBs) and the sites of special
scientific interest (SSSI’s) are shown below.
Figure 16: Environmental Land Areas. (SCOPAC, 2007)
7.2.3- Climate Change – Possible Sea Levels Rising
With the fear of climate change and global warming and the possible rises in
the sea level it may be wise to design to lifeboat station to withstand such
changes to the environment. SCOPAC are a group that manages and looks
at coastal problems in the Solent the map shows their predictions on flooding
Page 102 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
and increasing sea levels. The map shows a possibility of flooding in the
areas highlighted for a one in 20 year storm event in the year 2020.
Climate change is likely to result in changes to three key forcing agents that
could have significant implications for the physical condition of shorelines
rising sea-levels, changes in wave direction and increased rainfall with
concentration in winter and a tendency for more extreme events. (Halcrow,
2007)
This possible sea level was considered when the lifeboat station is designed
to make the structure a more sustainable one and will ensure that it will last
into the future without the need to be modified. An Environmental Assessment
should look at the possibility sea level rise and propose strategies to deal with
this problem.
7.2.4- Durability
Durability is definitely a problem that will need to be addressed when
designing this lifeboat station. The lifeboat station will be built in an extreme
maritime environment and will be exposed to the elements including strong
wind, waves and seawater environment. This environment will cause severe
erosion and corrosion of the materials like concrete and the steel that are
used to build the lifeboat station.
Page 103 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
To preserve the long term durability of the structure it is likely that specialised
materials will be needed in the lifeboat station. Higher grade concretes will
need to be used so to avoid erosion from the elements and the steel that is
used will have to have protection to prevent corrosion. The boathouse will
have to have adequate drainage to disperse any water that might collect. It is
also important to keep the boat as warm and dry with heaters and blowers as
possible to preserve the boat in pristine condition, as a lifeboat that is stored
out of water is expected to last at least 20 years.
7.2.5- Corrosion of Marine Structures
Waterfront structures are exposed to a variety of marine environments. The
resistance of materials to each of these environments may vary considerably,
as well as applicability of various forms of corrosion control.
In order to properly select materials for these applications, the environment
can be divided into five exposure zones: sediment, immersion, inter-tidal,
splash/spray and atmospheric. In most cases a single type of material will be
used for the sediment, immersion and inter-tidal zones. In some cases
another material may be used for the splash/spray and atmospheric zones of
the structure. (Baboian, 1995).
Page 104 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
7.2.6- Sediment Zone
The sediment zone consists of those portions of the structure that are
continuously of intermittently exposed to the bottom sediments. The depth of
this zone may vary due to natural sediment movement or to dredging.
Cathodic protection can be effective in controlling corrosion of many metals in
the sediment zone. Coatings are frequently used to control the corrosion of
steel in the sediment zone by application of the coating prior to construction of
the structure. In-situ maintenance coating in usually not practical. (Baboian,
1995).
7.2.7- Immersion Zone
In this zone the material is continuously exposed to sea water. Behaviour of
materials in this zone differs depending upon the geographical location of the
structure but is predominantly controlled by the salinity, oxygen content,
temperature and intensity of fouling. Cathodic protection can be effective in
controlling corrosion of many metals in the immersion zone. Coating prior to
placement is frequently used in the immersion zone, insitu maintenance is
usually not cost effective due to the high cost of underwater surface
preparation and coating application. (Baboian, 1995)
7.2.8- Inter-tidal Zone
Corrosion in the inter-tidal zone is affected by intermittent immersion
conditions. When exposed to the air, large amounts of oxygen are available.
This affects the corrosion of many materials.
Page 105 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
For steel exposed to both the immersion and inter-tidal zone, corrosion in the
inter-tidal zone may be reduced due to:
Galvanic coupling between the steel exposed to both the immersion and inter-
tidal zone. For reinforcing steel in concrete, this may be the zone of maximum
attack. Cathodic protection is effective in mitigating corrosion in this zone and
can also mitigate the accelerated attack caused by inter-zone interactions.
Protective coatings are frequently used to control corrosion in the inter-tidal
zone. Coatings can be maintained either by the use of rapidly curing coatings
applied at low tide, coatings that can cure under water or cofferdams that can
provide a dry environment for surface preparation, coating application and
curing. (Baboian, 1995).
7.2.9- Splash Spray Zone
The splash spray zone id often the most aggressive zone on marine
structures.
In this zone the high availability of oxygen is not offset by galvanic interaction
between zones. In many cases the most aggressive zone is just at the
boundary between the inter-tidal and the splash/spray zone. Conventional
cathodic protection of steel in this zone is not generally effective, but steel in
reinforced may be effectively protected in this zone using cathodic protection.
Coatings are frequently used for corrosion control in the splash spray zone.
(Baboian, 1995).
Page 106 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
7.2.10- Marine Atmosphere Zone
Above the splash/spray zone, the environment is characterised by the climatic
conditions such as temperature and humidity, but is still usually contaminated
by salt. (Baboian, 1995).
7.2.11- Techniques used for Corrosion Control
For permanent installations, few commonly used construction materials have
sufficient inherent resistance to corrosion to perform adequately without the
use of some form of corrosion control. In order for the selection of the most
cost effective combination of materials and corrosion control techniques, the
efficiency of the corrosion control technique for specific materials must be
determined. This normally requires testing. (Baboian, 1995).
- Protective Coatings
Protective coatings are widely used for controlling corrosion of marine
structures. For proper selection of coatings many factors must be considered
including the zone of exposure, degree of shelter, the substrate to be
protected and the potential for recoating. (Baboian, 1995).
- Cathodic Protection
Cathodic Protection is widely used for the protection of submerged steel in
water front structures. It can also provide considerable benefit in the inter-tidal
zone and can even reduce the usually high corrosion rate experienced at the
boundary between the inter-tidal and splash/spray zones. Cathodic protection
Page 107 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
is also effective in the control of corrosion in reinforcing steel in concrete in all
exposure zones in waterfront structures. (Baboian, 1995).
7.2.12- Tides and Adverse Sea Conditions
Tides and storms will have a major influence in the way that the lifeboat
station is built, it may be the case that the work has to be carried out to
coincide with low tides rather than the usual 7am-5pm working hours. This is
especially the case when it comes to building the substructure involved in
supporting the boathouse and the slipway as at high tide the excess water in
the ground conditions could cause certain instability problems.
Also it will become almost impossible to work during stormy conditions as
high winds and large waves will cause a significant health and safety risk
meaning that the site will have to be closed during storms.
It will be important to minimise the amount of days lost to stormy weather, as
this will affect the cost as well as the quality of the boathouse. The best way
to do this will be make sure that the majority of the work takes place during
the summer months when the tides are at their lowest and the storms are
minimal.
7.2.13- Safety for other sea users
There is a possibility that other sea users may cause problems to the launch
of the lifeboat. When the lifeboat slides down the slipway it will reach a
predicted pace of around 15-20 knots by the time that it reaches the bottom
Page 108 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
(RNLI, 2007). This could cause an accident to another boat or divers in the
area if they are not well clear of the launch. A simple solution to this problem
would be to provide simple warning signs both onshore and offshore and
aquatic buoys around the launch area to keep anyone from entering the
launch zone.
Maintenance of equipment and material during whole life of the project is a
very important part, because it could involve a determinate price per year and
otherwise if an accident is happening because of a maintenance failure it will
be very dangerous because it exactly the opposite of the maintenance aim.
To avoid any accident, four main steps should be used (The Plateform
Compagny, 2006):
Equipment Examination and Certification, as prescribed by LOLER
Regulation, 1998.
- Emergency Callout breakdown service.
- Routine Service Maintenance Agreements.
- Full refurbishment service - ground up rebuilds to OEM standards, or
better.
Page 109 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
7.3- Life Cycle Analysis
7.3.1- Initiation
i/ Goal of the Study
The goal of this Life Cycle Assessment (LCA) is to assess the environmental
impact of foundations over the lifeboat stations 50 year design life.
ii/ Scope of the study
This LCA will compare the following stages throughout the buildings life:
- Procurement of materials.
- Construction of building on site.
- Demolition at the end of its design life.
iii/ System Boundaries
The limitations of this Environmental Assessment are defined as the
following:
- The main elements of the foundations which include the Steel Piles
and pile capping plates.
Page 110 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
- Impacts of the material extraction at source, excluding transport to
site.
- Use of the materials and plant on-site during construction of the
foundations.
- Use of plant and machinery during demolition of the building.
Exclusions from the EA are as follows:
- Use of building throughout its 25 year life
- Human energy.
- Production of electricity, gas and water required for procurement of
materials, construction, maintenance and demolition.
- Waste arising from procurement, construction and maintenance
stages.
- Transport of plant and machinery to site.
- Manufacture and maintenance of plant and machinery.
- Transport of workforce to site.
- Fabrication of components of piles off-site.
- Transport of raw materials and assembled components to site.
Page 111 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
iv/ Data categories
This LCA report categorises the following for comparison over the life cycle of
the building:
Energy in giga-joules; includes embodied energy in materials, plant use,
production of electricity, gas and water, and transportation of waste.
Air emissions in tonnes CO2 equivalent; includes procurement of cement,
plant use, production of electricity, gas and water, transportation of waste and
waste disposal.
7.3.2- Inventory Analysis
i/ Procurement
Energy
Table 3 - Embodied energy in materials: ¹ - Source: Lawson, (1995).
Component MaterialMass
(kg)
Embodied
Energy ¹
(MJ/kg)
Total
Embodied
Energy
(GJ)
BeamsZinc Galvanized
Steel173,710 34.8 6.045
Bolts Zinc Galvanized 27 34.8 0.001
Page 112 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Steel
TOTAL: 1,866 GJ
Air Emissions
Production of steel:
Mass of steel = 173.737 tonnes
Emissions / unit = 1,866 kg CO2/tonne (Steel Houses, n.d.)
production of steel
Total emissions = 173.737 x 1,866
= 324,193 kg CO2
= 324 tonnes CO2
ii/ Construction
Energy
This includes the energy consumption from use of plant during construction.
The plant listed in table is assumed plant used in construction.
Table 4 – Energy consumption during construction
Machine Power
(kW)
Duration of Use
³
(hours)
Energy
Consumption
(GJ)
2x Cherry Picker ¹ 301 120 520
TOTAL: 780 GJ
Page 113 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Notes on table:
¹ - Source: Caterpillar Machines, (2004).
² - Source: JCB, (2007).
Air Emissions
Air emissions from plant use assumed to be negligible.
7.4- Environmental Impacts
From fig’s 9 and 10 above it can be seen that Bembridge is both a Ramsar
and Internationally Important site. English Nature (2007) states that “Ramsar
designations protect species that are listed in the Red Data Books. These
books provide information on wildlife that is rare, vulnerable, endangered,
endemic or out of danger in the United Kingdom”.
Page 114 of 136
Figure 17: (Solent Forum, 2007)Figure 18: (Solent Forum, 2007)
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
7.4.1- Data Categories
This LCA report categorises the following for comparison over the life cycle of
the building:
- Energy in giga-joules; includes embodied energy in materials, plant
use, production of electricity, gas and water, and transportation of
waste.
- Air emissions in tonnes CO2 equivalent; includes procurement of
cement, plant use, production of electricity, gas and water,
transportation of waste and waste disposal.
(Hunt. 2006)
Page 115 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
7.4.2- Procurement
Figure 19: EN ISO 14713:1999. Protection of steel against corrosion.
Page 116 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Table 5 - RDB interest Example of endangered species Information
RDB Interest Example of Endangered
Species
Information
InvertebratesParacymus aeneus (water
beetle).
The intertidal mudflats at
Bembridge are the only known
site in the UK.
by seawater all the time.
(English Nature. 2007)
In addition to this, Bembridge is both an Area of Outstanding Natural Beauty
and a Site of Special Scientific Interest (SSSI) as can be seen from figs 11
and 12 below:
Also to be found at the proposed site are Seagrass Beds, the Solent Coastal
Habitat Action Plan (2007) state that “these plants are an important source of
organic matter, and provide shelter and attachment sites for other plants and
animals, allowing interesting marine communities to develop. Infaunal
Page 117 of 136
Figure 20: (Solent Forum, 2007)
Figure 21: (Solent Forum, 2007)
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
communities within Seagrass beds include some species not found in
adjacent areas, with a number of sedentary species of plant and animal
typically found attached to the leaves and free- living species occurring within
the beds. Seagrass beds also support a large number of burrowing
invertebrates, provide an important nursery and feeding ground for many fish
species and a valuable food source for internationally important populations
of waterfowl, particularly Brent Geese and Wigeon”.
It is therefore fundamentally important that (so far as reasonably possible) the
design process mitigates against causing significant and lasting damage. The
Leopold matrix (below) assigns possible Environmental Impacts in order of
their importance:
Table 6 – Environmental Impact Assessment
The matrix identifies that the largest environmental impact will be on the
Seagrass and the worst project activity will be the Construction phase.
Mitigation
Page 118 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
To limit damage caused to the Seagrass the following construction procedure
will be required:
Limiting the movements of the Jack-Up Barge to a minimum (see method
statement). By limiting the number of times the legs are attached to the
limestone as little damage (so far as reasonably possible) to the seabed will
be caused.
Furthermore, biodegradable hydraulic and hammer oils are to be used.
As a result of the works some cement grout will enter the sea – at low tide it
will merely set. At high tides the current is sufficient for it to cause little if no
impact.
Page 119 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
1.1. Conclusion
The results of this life cycle assessment on the swimming pool structural
frame have shown that, by far the greatest environmental impacts occur
during the procurement of materials stage of the life cycle of the building.
This shows that whilst it must be ensured that consideration is taken to
economise on the quantities of materials used, the environmental damage
occurred during the construction, maintenance and demolition of the structure
are negligible in comparison.
For the overall Lifeboat Station Project, the designer of this report enjoyed to
work as a team and he think that it is a very helpfull experience to have done
this project with the University of Portsmouth staff and students.
Page 120 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
8- References
Adalberth, K. (1997). Energy Use during the Life Cycle of Buildings: A
Method. Building and Environment.
Autocad. (2007). Autocad 2002: Autodesk.
Butler D. (1978) Designing Public Swimming Pools: Detailed Design. The
Sports Council.
Caterpillar machines (2004) Product Line. Caterpillar Worldwide. Retrieved 1st
May 2006, from http://unitedkingdom.cat.com/cda/layout?m=65265&x=7
CDM Regulations. (2004). Work sector guidance for designers, Second
edition. London: CIRIA.
CIRIA. (1997). Handbook site safety (2nd edition). London: CIRIA.
CIRIA. (2004). CDM Regulations work sector guidance for designers (2dn
edition). London: CIRIA.
Coatings for the Protection of Structural Steelwork (2000) Guides To Good
Practice In Corrosion Control. Retrieved March 28, 2006, from:
www.npl.co.uk/lmm/docs/steelwork.pdf
Page 121 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Controlling the risk of steel-framed farm buildings collapsing during erection
(n.d.) HSE Information Sheet, Retrieved April 18, 2006, form:
http://www.hse.gov.uk/pubns/ais18.pdf
Designing Public Swimming Pools (1978) Part 4 – Detailed Design of Pool
Superstructure. London: The Sports Council
Downey,E. W. & Ericksen,J. (2006). Tolerances Illustrated. Modern Steel
Construction. Retrieved October,2006 from
http://www.aisc.org/Template.cfm?Section=Technical_Answers&template=/
ContentManagement/ContentDisplay.cfm&ContentID=32546
EN ISO 14713 (1999) Protection against corrosion of iron and steel in
structures – Zinc and aluminium coatings - Guidelines. British Standards
Institution: London.
English Nature. (2007). Retrieved from English Nature website on March 3,
2007 from
http://www.english-nature.org.uk/science/natural/profiles/naProfile108.pdf
European Agency for Safety and Health at Work.(2003).The practical
prevention of risks from dangerous substances at work.(European Agency for
Safety and Health at Work Issue 106).Retrieved November 27,2006 from
European Agency for Safety and Health at Work website :
http://osha.europa.eu/publications/reports/106/index_18.htm
Page 122 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Gilbertson, A. (2004) CDM Regulations – practical guide for client and clients’
agents. Retrieved April 20, 2006, from: http://www.ciria.org/acatalog/c602.pdf
Guidance for the Prevention of Pollution: GPP CU1 Construction &
Maintenance Works (2003).Retrieved November 27, 2006, from University of
Cambridge, Estate Management and Building Service website:
http://www.admin.cam.ac.uk/offices/environment/guidance/maintenance.html
#Heading4
Health and safety personal protective equipment.(1999). Retrieved November
27,2006 from The Manchester Metropolitan University website :
http://www.mmu.ac.uk/humanresources/health/policy/ppe1.pdf
ICE. (1999). CESMM3 Price Database 1999/2000. London: Thomas Telford
JCB. (2007). Retrieved May 5, 2007 from:
http://www.jcb.co.uk/products/MachineProduct.aspx?PID=16&RID=2
Langdon, D. (2006). SPONS Architects and Builders Price Book 2006 (131st
ed.). Oxon: Taylor and Francis.
Lawson B. (1995). Embodied energy of building materials. Environment
Design Guide. Royal Australian Institute of Architects. PRO 2, August, 3.
Page 123 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
M.N, E.J, H.G, V.D, (2006). MEng 4 Integrated Project Report, Vol 2, 3, 4, 5,
6. Portsmouth: University of Portsmouth.
Mayer, P. (n.d.) Structural Steel Fire Protection. Retrieved April 20, 2006,
from: http://www.greenspec.co.uk/html/design/materials/steelfire.html
Munns, I. (2004). Liquid Penetration Inspection. Retrieved May 15, 2007
from: http://www.twi.co.uk/j32k/protected/band_3/ksijm001.html
Nullifire. (2001). Intumescent Coating. Retrieved May 15, 2007 from
http://www.nullifire.com/intumescent_coating/index.htm
Parliament. (2005). The Work at Height Regulations 2005: Statutory
Instruments 2005, No. 735 [Electronic version].Stationery Office.
Potain Product Guides. (2005). Top Slewing Tower Cranes; MD 560-M40.
Manitowoc Crane Group. Retrieved 1st May 2006, from
http://www.manitowoccranegroup.com/MCG_Downloads/MCG_POT_AM/EN/
MD560-M40PG_4_05.pdf
Reynolds, J. (2006). MEng 4 Integrated Design Project. University Of
Portsmouth Handout Guidance notes.
Page 124 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
R.H, P.V, V.J, (2007). MEng 4 Preliminary Engineering Report. Portsmouth:
University of Portsmouth.
RNLI (n.d). Standard Shoreworks Facilities for Lifeboat Stations, Briefing
Document for Architects and Consulting Engineers.
RNLI. 2007. Lifeboat Station Selsey. Retrieved February 16, 2007 from:
http://www.rnli.org.uk/rnli_near_you/east/stations/LittlehamptonWestSussex/
RNLI. 2007. Lifeboat Station Bembridge. Retrieved February, 16 2007 from:
http://www.rnli.org.uk/rnli_near_you/east/stations/LittlehamptonWestSussex/
Royal National Lifeboat Institution. (2007). Retrieved February 14, 2007 from
http://www.rnli.org.uk/who_we_are/boats_and_stations
SCI. (1997). Section Properties and Member Resistances to Eurocode 3
(UB,UC and Hollow Sections). London: SCI.
SCI. (2006). Steel structure design brief 2006-2007, Retrieved from Corus
Construction website February 23, 2007 from:
http://www.corusconstruction.com/en/news_and_events/awards/ugda/press_r
eleases/press_release_1/
Page 125 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
SCOPAC. (2007). Maps. Retrieved 26th February, 2007 from
http://www.scopac.org.uk/maps.html
Solent. (2007). Solent map. Retrieved February 24, 2007 from:
www.solentforum.hants.org.uk
Spon’s. (2007). Spon’s civil engineering and highway works price book.
London: Spon.
Steel Houses & Sustainability (n.d.) Retrieved 2nd May, 2006, from
http://www.sustainability.ca/Docs/ASRC-9.pdf?CFID=19461386&CFTOKEN=
19170753
Steel the safe solution (n.d.) Retrieved April 18, 2006, from:
http://www.corusconstruction.com/file_source/StaticFiles/Construction/Steel
%20the%20safe%20solution%202.pdf
The Construction (Design and Management) Regulations (1994) Retrieved
April 20, 2006, from:
http://www.opsi.gov.uk/si/si1994/Uksi_19943140_en_2.htm#mdiv4
Types of Truss (n.d.). Retrieved March 29, 2006, from:
http://www.brantacan.co.uk/trusstypes.htm#Town
Page 126 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
Ultrasonic thickness gauges help avoid equipment failure (n.d.) Retrieved
April 20, 2006, from: http://www.engineerlive.com/asiapacific-engineer/health-
safety/2185/ultrasonic-thickness-gauges-help-avoid-equipment-failure.thtml
Winistorfer P. and Chen Z. (2004) Energy Consumption And Associated
Greenhouse Gas Emissions Related To Deconstruction And Demolition Of A
Residential Structure. CORRIM: Phase I Final Report
Wolfe, R (1987) Designing Facilities To Meet Future Needs. Retrieved March
13, 2006, from:
http://www.usaswimming.org/USASWeb/ViewMiscArticle.aspx?
TabId=655&Alias=Rainbow&Lang=en&mid=1408&ItemId=1345
Page 127 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 1
INITIAL SKETCKES
Page 128 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 2
CALCULATIONS
Page 129 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 3
MATERIALS
Page 130 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 4
METHOD STATEMENTS
Page 131 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 5
CDM REGULATIONS
Page 132 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 6
INDIVIDUAL COST OF RISK
a/ SLIPWAY
b/ SLAB
c/ WALKWAY
Page 133 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 7
TAKE OF SHEETS AND BILL
OF QUANTITIES
a/ SLIPWAY
b/ SLAB
c/ WALKWAY
d/ GROUP
Page 134 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 8
GANTT CHART PROGRAMM
(Microsoft Project)
Page 135 of 136
MEng 4 Integrated Design Project-2007 Final Report – Volume 2Bembridge Lifeboat Station Project- L.I.S.T Project 378769
Slipway- Slab- Walkway
APPENDIX 9
RECOMMENDATIONS
Page 136 of 136