indiana’s newest filtration facility; east chicago...indiana’s newest filtration facility; east...
TRANSCRIPT
Innovation and Value-Added Benefits Behind East Chicago’s Membrane Treatment Facility
August 1, 2012
Indiana’s Newest Filtration Facility; East Chicago
Eric Horvath, PE and Kara M. Boyles, PhD, PE
Presentation Overview
• Project Drivers
• Value Engineering
• Membrane Procurement
• Membrane Design
• New WTP Overview
• Start-Up Challenges
• Lessons Learned
Project Drivers • Marquette Plan for
Redevelopment
– Indiana Lakefront Communities
– Project to Reclaim the Lakeshore
• Age and Condition of Existing Plant
Existing Water Treatment Plant
Existing Water Treatment Plant
• WTP Built in 1964 • 24 MGD • Conventional Sand
Filtration • Aluminum Sulfate
Coagulation • 6 MG Finished Water
Storage • Located near Lakefront
Existing & Future WTP Sites
Existing Water Plant
New WTP Site Existing
Brownfield
Project Considerations • Time is of the Essence
– No Further Investment at Existing WTP
– Move Redevelopment Forward
• Clear Site for Redevelopment
– Relocation of Raw Water Pump Station
• Constrained Budget
• Flow 20 MGD Initial & 30 MGD Future
• Meet LT2ESWTR Bin 2
• Minimize Flow to Sanitary Sewers
• Investigate Zebra Mussel Treatment
• No Gaseous Chlorine at Proposed
WTP
Value Engineering • City Unhappy with $70M Price Tag
– Fresh Look at Design – Potential Cost Savings – Increased Functional Ability
• Team Reviewed Collected Data • 294 Creative Concepts Developed • 24 Concepts Further Developed • Optimal Combinations of Concepts to
Form 4 Alternatives Pressure Membrane
Submerged Membrane Traditional Gravity Filters
Treatment Alternatives
• Low Cost Alternative • Pressure Membrane • Submerged Membrane • Conventional Filtration
Treatment Alternatives Process Flow Diagram
RESIDUALS EQUALIZATION (Required by All)
A. Concrete Equalization Basin – Gravity Filters
B. Concrete Equalization Basin – Membranes
RESIDUALS DISCHARGE A. Inclined Plate Settler with
Recycle to Head of Plant B. Inclined Plate Settler with
Discharge to Sanitary Sewer. C. Discharge to Sanitary Sewer
Solids to Sanitary Sewer
RAW WATER SOURCE A. Indirect Withdrawal B. Zebra Mussel Control in Existing Intake C. Existing Intake With No Zebra Mussel Control
RAW WATER PUMP STATION
(Not Required for Indirect Withdrawal)
A. Vertical Turbine Pumps B. Submersible Pumps
FLOCCULATION & CLARIFICATION
A. Rapid Mix & Flocculation (Filtration C & D) B. Rapid Mix, Flocculation & Inclined Plate Settlers (Filtration A & B) C. Ballasted Clarification
FILTRATION (Required by All)
A. Concrete Gravity Filter B. Rectangular Steel Gravity Filter C. Pressure Membranes D. Submerged Membranes
DISINFECTION (Required by All)
A. UV Disinfection / Sod. Hypo B. Sodium Hypochlorite
TRANSFER PUMP STATION
(Required for Pre-stressed Concrete Ground
Storage)
GROUND STORAGE (Required by All)
A. Pre-stressed Concrete Ground Storage B. Below-grade Concrete Storage
HIGH SERVICE PUMPING (Required by All)
Preferred Alternative Process Flow Diagram
RESIDUALS EQUALIZATION
Concrete Equalization Basin
for Membranes
RESIDUALS DISCHARGE
Inclined Plate Settler with Recycle to Head of Plant
Recycle Water to Head of Plant
Solids to Sanitary Sewer
RAW WATER SOURCE
Existing Intake With No Zebra Mussel
Control
RAW WATER PUMP STATION
Vertical Turbine Pumps
FLOCCULATION & CLARIFICATION
In-Line Flocculation
FILTRATION
Pressure Membranes
DISINFECTION
Sodium Hypochlorite
GROUND STORAGE Pre-stressed Concrete Ground Storage
HIGH SERVICE PUMPING To Distribution System
Membrane Procurement
• Request for Proposals • Financial Criteria – Total Present
Worth – Membrane Equipment Capital Cost – Non-Equipment Capital Cost – Present Worth of Operating Cost – PW Cost of Membrane Replacement –
20 yr • Non-Financial Criteria
– Layout and Assembly for Ease of O&M – Technical and Performance Information
Membrane Procurement • Competitive Membrane
Proposals – Option for Vendor to Propose One
Submerged System and One Pressure System
– Pressure Proposals from Pall and Siemens
– Submerged Proposals from GE and Siemens
Membrane Procurement
Schedule Item GE/Zenon Submerged
Pall Encased
Siemens Submerged
Siemens Encased
Membrane Equipment Capital Cost
$4,469,572 $4,485,704 $4,876,897 $4,515,812
Non-Equipment Capital Cost $1,189,026 $1,217,622 $1,379,756 $1,271,505
Present Worth of Operating Cost
$1,585,596 $1,671,308 $1,578,835 $1,465,405
Present Worth of Membrane Replacement Cost
$1,040,439 $1,018,134 $1,035,538 $ 985,240
Total Present Worth $8,284,633 $8,392,768 $8,871,026 $8,237,963
Membrane Filtration
• Definition
– Semi-permeable thin layer of material
– Slow rate of transfer across the membrane and high pressure drops
– Very effective
RO, NF, UF and MF MEMBRANE
DESIGNATION
PRESSURE GRADIENT
PORE DIAMETER REMOVAL
EFFICIENCY
Mechanisms of Filtration
• Mechanical Screening • Adsorption • Cake Filtration
Principles of Membrane Filtration
Osmosis Osmotic Pressure
Membrane Filtration Theory • Water flux:
Where: – J = volumetric flux of water – Q = volumetric flow rate of pure water, gal/day – A = surface area of clean membrane, ft2 – ∆P = transmembrane pressure – µ = dynamic viscosity of water – Rm = membrane resistance coefficient
))(( mRP
AQJ
µ∆
==
Membrane Filtration Theory • Fouling
Flow (85-90%)
Product Water
Fouling Layer
Permselective Barrier
Flux (10-15%) Adsorption
Biofouling
• Biofouling is referred as the undesired development of microbial layers on the surface.
• Biofilm organisms are embedded in a matrix of microbial origin, consisting of extracellular polymeric substances (EPS).
Membrane Surface
Microbial Attachment
Microbial Colonization
EPS & Microbial Growth
Membrane System Components
• Membranes • Modules • Racks • Piping
Hollow Fiber Flow Path
• Inside-Out • Outside-In
Membrane Processes: Operation
Pretreatment
• Coagulation, flocculation, and sedimentation for high raw water turbidity and/or high NOM
• Where iron and/or manganese are prevalent, oxidation is performed to form precipitate prior to filtration
• Pre-filtration of particulates – To remove large particle fraction, a strainer or bag
filter rated at 50 to 500 µm is used for all water sources
Cleaning
• Backwashing with either air or permeate water at preset intervals of 30 to 90 min.
• Addition of chlorine to backwash water aids in reducing biofouling. Oxidant tolerant membrane material must be selected to employ this technique.
• Chemical cleaning in place or with modules removed will be required periodically
Post-treatment
• Concentrate – High solids concentration – High concentration of pathogens – Disposal: municipal sewer, ocean discharge,
deep well injection
Final Plant Design Elements
• Siemens Pressure Membrane Pilot Testing – Test Plan & Protocol – Complete Membrane System
• Includes all ancillary equipment – Specific Parameters for Backwash and
Maintenance Wash – Cold Water and Warm Water Piloting – Run at 1.1 times full scale flux
Final Plant Design Elements • Design Flow Changed to 16 MGD • Utilize Existing Intake • Zebra Mussel Control using Divers
for Cleaning • Extension of Raw Water Intake
using Jack & Bore / Slurry Micro- tunneling
• New Raw Water Pumping Station – Vertical Turbine Raw Water Pumps – Automatic Self Cleaning Strainers – PAC Feed System
Final Plant Design Elements • New Operations Building
– Bulk Chemical Storage and Feed Systems
– Siemens “CP Wing” Pressure Membranes
– Mechanical, Electrical, Office and Lab
Rooms – High Service Pumping Station – Future Ultra-Violet Treatment Area
Added – Package Plate Settlers
• Membrane Backwash EQ Tank • Back Up Power Supply • 4 MG Finished Water Storage (w/
Space for Additional 3 MG Tank) – Construction Under USACE 219 Grant
The New WTP Aerial View
Start-up Challenges • Finished Water Storage
Reservoir – Timing of Reservoir Completion
• Raw and High Service Pumps – Motor Vibration Issues
• Chemical Feed Systems – Chemical Compatibility of
Materials Utilized – Calibration of Pumps
• Strainers – V-notched Openings Plugging
Lessons Learned
• Value Engineering Pays • Coordination and Communication are Key • One General Contractor • Assignment of Owner-Procured
Equipment • Project Risk Managed • Thorough Set of Plans and Specifications • Design Staff Active During Construction
Thank You
Eric Horvath, PE [email protected] American Structurepoint 211 W. Washington St., Suite 2410 South Bend, IN 46601 574.287.2231
Kara Boyles, PhD, PE [email protected] American Structurepoint 211 W. Washington St., Suite 2410 South Bend, IN 46601 574.287.2231