incentive structures · •generation based incentive (gbi) goi, with ireda as the nodal agency,...

27
1 Incentive Structures

Upload: others

Post on 11-Aug-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

1

Incentive Structures

Page 2: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Incentives – Growth Path

Need of Incentives – Till when?

Issues, Recommendations & Discussions

Regulatory

Financial and Fiscal/Tax

2

Coverage

Page 3: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Incentives– Growth Path

Incentives Prior to EA’03

Incentives Post EA’03

Wind Vision - 2030

3

Page 4: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

4

From Central Government From State Government

Income Tax Holiday Energy buyback, power wheeling and banking facilities

Accelerated Depreciation Sales tax concession benefits

Concessional Custom Duty / Duty Free Import

Electricity tax exemption

Capital/Interest Subsidy Capital Subsidy

Incentives – Prior to EA’03

325

725

895 935 985

1135

1315

1565

1908

0

500

1000

1500

2000

2500

1994-95 1995-96 1996-97 1997-98 1998-99 1999-20 2000-01 2001-02 2002-03

Policy Announcement

by Govt of India

Inst

alle

dC

apac

ity

(MW

)

Page 5: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Conducive Policy and Regulatory Framework ensured continued

development of Wind Sector.

Growth rate for the last 2 years has been sluggish due to uncertainty

over GBI post FY 2012-13 and withdrawl of AD.

With new GBI scheme being notified by MNRE, and restoration of

AD, the growth rate is again picking up.

5

Incentives – Post EA’03

Page 6: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

6

The CAGR for increase in capacity addition from 21.14 GW in FY

2013-14 to 202.89 GW in FY 2031-32, works out to 13.39%

Wind Vision – 2030

-

50.00

100.00

150.00

200.00

250.00

2013-14 (Installed)

2016-17 (Projected)

2021-22 (Projected)

206-27 (Projected)

2031-32 (Projected)

21.14

39.62

79.42

128.36

202.89

Wind Capacity in (GW)

Page 7: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Need of Financial Incentives: Till When?

7

Page 8: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Need of Financial Incentives

8

• Wind Vision – 2032 of 200 GW is an ambitious target

• Whether prevailing level of Incentives sustainable?

• Such huge capacity addition possible, if wind power

becomes competitive with minimal financial incentives

support

• An attempt has been made to ascertain the time by which

the Wind FiT would become comparable to the average

power purchase cost of the DISCOMs and thus, would no

longer require any financial incentive

Page 9: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

9

• A comparative analysis of forecast combined average power

procurement cost of major (Wind rich) States vis-à-vis Projected

FiT of Wind as per CERC Norms

Broad Assumptions

• State-wise Energy Demand Projection: As per 18th EPS of CEA

• Weighted Average Power Purchase Cost Projection: Based on 10

Year (Trend Line 1) and 5 Year (Trend Line 2) CAGR of average

Power Purchase Cost

• CERC Wind FiT: Rs. 5.07/kWh escalated by 2% per annum

• Storage Cost: Rs. 5.40/kWh (as per IEA)

• Storage Requirement: 25% of the Installed Capacity

Need of Financial Incentives

Page 10: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

CERC FiT vis-à-vis Average Power Purchase Cost

10

3.50

4.50

5.50

6.50

7.50

8.50

9.50

10.50

2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25

Trend 1 Trend 2 CERC FIT CERC FIT + Storage Cost

FY 2018-19 Trend 1 – Rs 5.55 kWh Trend 2 – Rs 5.70 kWh CERC FIT – Rs 5.38/kWh

FY 2021-22 Trend 1 – Rs 7.14 kWh Trend 2 – Rs 7.54 kWh CERC FIT – Rs 6.98/kWh

Till FY 2018-19

Requirement of

Financial Incentives

FY 18-19 to FY 21-22

Incentives to

Promote Storage

Technologies

Post FY 2022-23

Non-Financial Incentives

and Other Support

Mechanisms to continue

Page 11: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Discussion Point

11

• Should the Government continue

Financial/Fiscal Incentives only till Grid

Parity

• Whether Grid Parity would necessarily

indicate complete rollback of Incentives

having Financial implications for Govt

Page 12: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Regulatory Incentives:

Issues, Recommendation and

Discussion Points

12

Page 13: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

13

Regulatory Incentives

• Feed in Tariff (FiT)/Preferential Tariff

One of the main factor behind significant growth of RE sector

in general and Wind sector in particular

Nearly, all SERCs have determined their FITs

• Open Access, Banking & Wheeling Arrangement

Not per-se Incentives, but ‘special dispensation’ by Regulator

No direct financial impact on DISCOMs,

Financial burden is indirectly spread out to broader consumer

base.

Favourable Banking and Wheeling arrangement essential for

promotion of inter-state transaction of renewable power.

Page 14: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

14

Regulatory Incentives

• RPO Mechanism

Provision of certain % age of electricity consumption by eligible

entities through RE source

SERCs have issued RPO Orders/Regulations specifying % for

mandatory RE procurement obligations

• REC Mechanism

Separates the two components-Electricity & Green Component

Electricity Component meets energy demand and Green

Component is converted into tradable RECs

Electricity

Green Component

APPC

REC

Page 15: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

RE Policy and Regulatory Recommendations

Wind FiT Determination –CERC Vs SERCs

Zone wise tariff Vs Single Tariff

15

Issues Recommendations

Variation in Wind FiTs approved by SERCs and CERC

Uniform Tariff Regime

Variation in Indexation mechanism for capital cost

considered by SERCs & CERC Uniform mechanism for Indexation

Principle for computation of levellised tariff

Broad consensus across Regulators for developing a nation-wide

framework.

Issue Recommendation

Consideration of same CUF at all sites within the same State

Zone wise wind tariff determination to push capacity

additions in low wind zones

Page 16: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Rationalization of Open Access Regime

16

Issues Recommendations

Delays in granting connections in Open Access

Entire procedure should expedite

Accounting issues in lower than MW size transactions Appropriate M&V system should

be developed Management of UI charges -Provision of scheduling

RE Policy and Regulatory Recommendations

Need for building national level Consensus on OA

Regime for RE / Wind related Transactions – Captive and

Third party Sale

Promotion of Inter-State RE/Wind power sale through

introduction of national /regional level OA Framework.

Page 17: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

RE Policy and Regulatory Recommendations

RPO Compliance and REC Mechanism

17

Issues Recommendations

Lack of Penalties for non-compliance with the RPO by the

obligated entities Strict penalties for Non-compliance

Lack of a uniform mechanism for M&V of RPO

Appropriate guidelines for SNAs for M&V of compliance with RPOs.

Lack of clarity about the application of RPO to OA and

captive-power consumers

Enable SERCs to specify RPOs for OA and captive consumers in addition to

distribution licensees

RECs are treated as Regulatory instruments

RECs should be made a Statutory instrument

Page 18: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Discussion Points

18

FiT/Preferential Tariff

Standardisation of SERCs capital cost / financial

parameters in lines with CERC Regulations

Desirability of Zone-wise tariff within the State to push

capacity additions in lower wind zones

Open Access (OA) Regime

Need for building national level Consensus on OA

Regime for RE / Wind related Transactions – Captive and

Third party Sale

Promotion of Inter-State RE/Wind power sale through

introduction of national /regional level OA Framework.

Page 19: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Discussion Points

19

RPO Compliance

Whether ‘Incentivising Compliance & Penalising Default’

would motivate cash-strapped Discoms to comply?

Does Wind Vision 2032 – 200 GW require the impetus of

Separate Wind RPO, similar to Solar RPO?

REC Mechanism

Differentiation between APPC and Non-APPC based Projects –

Multiplier based RECs affecting capacity addition

Exploring possibility of Bilateral / Multilateral transactions of

RECs to improve bankability?

Visibility of Floor/Forbearance Price Mechanism for longer

tenure (10-20 years) with values to be fixed periodically

Page 20: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Financial and Tax Incentives:

Issues, Recommendation and

Discussion Points

20

Page 21: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

• Generation Based Incentive (GBI)

GOI, with IREDA as the nodal agency, introduced GBI scheme

for Grid-interactive wind power projects

The scheme was rolled back in 2012 but re-introduced in 2013

New scheme applicable on Wind projects commissioned on or

after April 2012, available for entire 12th FYP, with a target of

15,000 MW

Incentive of Rs 0.50 per unit, with a cap at Rs 10 million per

MW (not exceeding Rs 2.5 million per MW per year)

For a minimum of 4 years and a maximum of 10 years

Incentive will be over and above the applicable tariff

approved by respective SERCs.

21

Financial Incentives

Page 22: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

• Accelerated Depreciation (AD)

One of the most significant drivers aimed at capacity

additions

Mainly targets small/medium size captive consumers

Speeds up the depreciation in value of wind projects in the

FY after CoD and hence significantly reduces tax liability

Allows producers of RE Power to claim AD in first year on

written down value

Reduction in AD rate has affected wind capacity

installation

Restoration of AD in FY 2014-15 would again boost the

Wind Sector

22

Tax Incentives

Page 23: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

• Tax Holiday

Sec 80-IA provides exemption to wind project developers

from income tax on all earnings generated from the project

Applicable to a project for period of 10 consecutive

assessment years during the first 15 years of the project life

The book profit from such undertaking, however attracts

MAT @18.5% of book profits.

• Others

Concessional Custom Duty on Imports

Excise Duty exemptions

Exemption in CST

Exemption from ED, Stamp Duty, VAT in certain States

23

Tax Incentives

Page 24: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Recommendations on Tax Provisions Direct Tax Code (DTC)

Goods & Service Tax (GST)

24

Issues Recommendations

Large & complicated structure

Ensure that the DTC continues to provide the tax holiday as

provided under the current direct tax laws to some categories of

infrastructure projects

No Clarity on the proposed DTC – whether income tax holidays

currently enjoyed by various RE projects will be continued

Issues Recommendations

Cascading Tax Structure Simplification in the structure

No Excise Duty Exemption Extend the exemption

Negative list of Services Defining of Appropriate categories

Page 25: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Recommendations on Other Provisions RE Law in India

25

Issues Recommendations

Legislative support for RE development is inadequate

Few important amendments are to be done in RE policies

Inconsistent RE policies across states

Pass the RE Act enabling all necessary provisions

Inadequate empowerment to MNRE

RE Act to be administered by MNRE

Page 26: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

Discussion Points

26

• Policy clarity on GBI and AD with clear road map of

phasing out

• Extend Tax Benefit for Investment in Wind Sector to

individual Tax payers also

• Structures such as Real Estate Investment Trust

should be promoted in Wind Sector

• Incentivise Discoms and other Off-takers by weighted

higher deduction on expenses on Wind Power

Purchase

• Link Central Assistance/ Grants/ Low-cost Financing

to Discoms to Wind Power off-take and RPO

compliance

Page 27: Incentive Structures · •Generation Based Incentive (GBI) GOI, with IREDA as the nodal agency, introduced GBI scheme for Grid-interactive wind power projects The scheme was rolled

THANK YOU