ims element 14 - permit to work (ptw) procedure

34
IMS PROCEDURE Document No. 000056567 Document Title IMS Element 14 - Permit to Work (PTW) Procedure Function Integrated Management System Issue Date 2 September 2021 Department Element 14: Systems of Work Version Number 20 Document Owner Manager - Safety, Radiation and Occupational Hygiene Olympic Dam Document No. 000056567 V. 20 Page 1 of 34 Uncontrolled when printed

Upload: others

Post on 24-Dec-2021

44 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: IMS Element 14 - Permit to Work (PTW) Procedure

IMS PROCEDURE Document No. 000056567

Document Title IMS Element 14 - Permit to Work (PTW) Procedure

Function Integrated Management System Issue Date 2 September 2021

Department Element 14: Systems of Work Version Number 20

Document Owner Manager - Safety, Radiation and Occupational Hygiene

Olympic Dam Document No. 000056567 V. 20 Page 1 of 34

Uncontrolled when printed

Page 2: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 2 of 34 Uncontrolled when printed

CONTENTS1 PURPOSE ....................................................................................................................................32 SCOPE .........................................................................................................................................33 TERMS AND DEFINITIONS.........................................................................................................34 PROCESS FLOW.........................................................................................................................55 PROCEDURE STEPS..................................................................................................................6

5.1 Review THA/WI ..................................................................................................................6

5.2 Clearance certificate required?...........................................................................................6

5.2.1 Authorise THA/WI.....................................................................................................6

5.3 Prepare relevant clearance certificates for execution of the work......................................7

5.4 Relevant clearance certificates and THA/WI authorised. (Handover) ................................7

5.4.1 Handover Accepted..................................................................................................8

5.5 Familiarise with required controls and sign onto THA/WI and commence work ................9

5.6 Emergency, or work changed?...........................................................................................9

5.6.1 Emergency Situation? ..............................................................................................9

5.6.2 Scope of Work change?.........................................................................................10

5.7 Follow emergency procedures .........................................................................................10

5.8 Review work pack requirements and re-authorise ...........................................................10

5.9 Work completed?..............................................................................................................11

5.10 Is a Job Owner Transfer Possible? ..................................................................................11

5.10.1Facilitate Job Owner Transfer ................................................................................11

5.10.2Suspend work.........................................................................................................12

5.11 Follow hand-back requirements .......................................................................................13

5.12 Accept Hand back ............................................................................................................13

5.12.1Record Keeping......................................................................................................13

5.12.2Failure to Hand back ..............................................................................................14

5.12.3Training, Competency & Authorisation Requirements ...........................................14

6 ROLES AND RESPONSIBILITIES ............................................................................................147 REFERENCES AND RELATED DOCUMENTS ........................................................................158 APPENDICES ............................................................................................................................17

8.1 Appendix A – Clearance Certificate .................................................................................17

8.2 Appendix B – Training and Competency & Authorisation Requirements .........................19

8.3 Appendix C – Temporary Transfer of Area Ownership ....................................................21

8.4 Appendix D – Area Ownership Map .................................................................................22

8.4.1 Map 1 - Overview Surface Processing Plant..........................................................22

8.4.2 Map 2 - Surface Processing Plant (West) ..............................................................24

8.4.3 Map 3 - Surface Processing Plant (East) ...............................................................28

8.4.4 Map 4 - Mine Surface.............................................................................................31

8.4.5 Map 5 - Olympic Village, Airport and Surrounds ....................................................34

Page 3: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 3 of 34 Uncontrolled when printed

1 PURPOSE

The Permit-to-Work (PTW) process ensures that appropriate steps are taken to identify and manage work with hazards and risks to people that have the potential for a fatality risk or a significant environmental or equipment event.

The PTW process requires that:

The boundaries and scope of work are identified and communicated.

The appropriate clearance certificates are identified and completed for the work activities that have the potential fatality risk, or significant environmental event to ensure that the controls have been implemented and are effective.

A formal process for facilitating the Hand-Over and Hand-Back of clearance certificates, facilities, plant and equipment is maintained.

Effective management and communication of Simultaneous Operations (SIMOPS), with the potential for fatality risk, occurs within areas and work groups.

Compliance with legislative requirements and procedural controls, e.g. BHP Our Requirements’ document and the Integrated Management System requirements are maintained.

Note: Work without SIMOPS and not requiring clearance certificates is to be managed using the Task Hazard Analysis (THA) Procedure Doc no. 000037634.This document supports IMS Element 14: Systems of Work Standard.

2 SCOPE

This document applies to Olympic Dam employees and contractors involved in planning, execution and supervision of field-based work.

To ensure accuracy of information, this document will only be amended once relevant stakeholders and subject matter experts have been identified and consulted i.e. risk owner, control owner/s, process owner/s, process implementer/s etc. These stakeholders and subject matter experts will also be included in the document control process.

3 TERMS AND DEFINITIONS

For the purposes of this document, the following terms and definitions apply:

Term/Acronym Definition

CC Clearance Certificate

HO/HB Handover / Hand back

ILB Isolation Lock Box

IMS Integrated Management System

LMS Learning Management System

MoC Management of Change

OD Olympic Dam

PTW Permit to Work

SIMOPS Simultaneous Operations

Page 4: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 4 of 34 Uncontrolled when printed

Term/Acronym Definition

THA Task Hazard Analysis

TTTC Take Time Take Charge

OR BHP Our Requirements (previously GLD)

WI Work Instruction

Page 5: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 5 of 34Uncontrolled when printed

4 PROCESS FLOW

Permit-To-Work Process

Are

a O

wne

rJo

b O

wne

rW

ork

Exe

cute

r

Work ClosureWork Preparation Work Execution

5.6 Emergency or scope change?

START

5.1.ValidateWI/THA

5.2Clearance Certificate required?

No 5.11Follow hand-back

requirements

5.3.Prepare relevant CC for execution

of work

5.5.Familiarise with required controls. Sign

onto THA/WI and commence work.

5.6.1.Emergency?

5.8.Review work

pack requirements

and Re-authorise.

5.9Work

completed?

Yes

No

No

Yes

Yes

END

5.7.Follow emergency

procedures

No

5.4.CC’s and THA/WI

Approved?

5.10.1Facilitate Job Owner

transfer

5.6.2.Work scope changed?

Yes

No

5.2.1ApproveTHA/WI

5.12Accept Hand back,

Update AO work register..

5.10Is a Direct Job Owner transfer

possible?

5.10.2Suspend work

Yes

Yes

No

5.4.1Accept

Handover

Page 6: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 6 of 34Uncontrolled when printed

5 PROCEDURE STEPS

Refer to the process flow chart when reading the procedure steps. Clearance certificates define the minimum controls to prevent incidents with potential for a fatality risk, or a significant environmental or equipment event, or as a result of a legislative requirement (e.g. Confined Space entry).

Clearance certificates are used in conjunction with either a THA or WI combined with an IMS Element 14 -Permit to Work Process WI Handover – Hand back Form, Doc No. 000119419, to constitute a permit to work.

The use of THA/WI is used within this document to represent work under the permit to work process – there is no separate permit to work form.Appendix A, to be used in the job planning stage or during work preparation, to identify the relevant clearance certificates required.

5.1 Review THA/WIJob Owner to complete or validate the THA/WI for the scope of work and identifies potential clearance certificates required for the scope of work.

Job Owner, preferably with the Work Executor(s), to inspect the job site prior to commencement of the task to ensure identified controls are detailed in the risk assessment (THA / contained in the WI) and will be effective.

Job Owner to identify any simultaneous work (SIMOPS) being conducted and to effectively manage the interactions between work groups and is responsible to ensure SIMOPS affecting their scope of work and/or persons or work crew have been identified and are effectively managed.

Notes:

The WI must be an approved WI, as per the OD Controlled Document Management process requirements, otherwise a Task Hazard Analysis (THA) is required.

The THA must meet the requirements of Task Hazard Analysis, Doc No. 000038526.

1. THA or WI reviewed for scope of work

2. Job site inspected to determine controls and clearance certificates required

OUTPUT:

3. Potential SIMOPS identified by Job Owner

5.2 Clearance certificate required?Job owner shall determine if any clearance certificates are required for the proposed scope of work using the list of clearance certificates in Appendix A as a reference.If it has been determined that clearance certificates are not required, proceed to Step 5.2.1

If it has been determined a clearance certificate is required, proceed to Step 5.3.

OUTPUT: 1. Determination made if clearance certificates are required for scope of work

5.2.1 Authorise THA/WIArea Owner together with the Job Owner shall confirm:

The specific equipment/ area being worked on

The scope of work is correct and can be conducted without SIMOP’s.

The boundaries of the task are discussed and understood by the Job Owner.

That the Job Owner has appropriately completed the relevant clearance certificates and understands the implementation requirements of the controls identified on the clearance certificate for the work to be performed safely.

Page 7: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 7 of 34Uncontrolled when printed

The relevant clearance certificate(s) have been authorised by a competent person/s.

Safe handover of the equipment/area has been made to the Job Owner.

Area Owner to retain the original THA/WI and any other relevant documents in the agreed permit management location (e.g. permit hut, confined space/mobile ILB etc.) This original document is where all sign on signatures and changes are captured.

Job Owner shall maintain a copy of the current THA/WI and clearly it as a copy which shall be kept at the job site to be used as a reference document if/when required.

Where SIMOPS have been confirmed the Area Owner shall update the Area Owner Work Register (scope of work title, status, location, Job Owners name and contact details).

Notes:

Should the Area Owner identify changes that are required to be made, the Job Owner will be expected to complete/facilitate completion of these changes before prior to the Area Owner authorising it.

Subsequent Re-Authorisation of the work to be recorded on the Re-Authorisation, Work Suspension & Job Owner Transfer sheet of the THA or WI HO/HB cover sheet.

Where an electronic Area Owner Work Register is not available or not functioning, then the Area Superintendent must determine an alternate but equal means of communicating active work information within the area. This may include (e.g. Whiteboard, paper log sheet etc.) that contains equivalent information.

Area Owner can give verbal authorisation to work team to go ahead on a daily basis if they are working under the remote area safety procedure.

Note: Should a clearance certificate not be required for the work, then after the THA/WI has been authorised, proceed to Step 5.5.

OUTPUT: 1. THA/WI for work not requiring clearance certificates is authorised

5.3 Prepare relevant clearance certificates for execution of the workJob Owner to facilitate the completion of all the relevant clearance certificates associated to the scope of work. These clearance certificates will outline the required controls and other associated documents that must be implemented to allow the safe execution of the task.

Job Owner shall establish the effective implementation of the required controls identified in the relevant clearance certificates.

Note: The specific details for completing and authorising each of the clearance certificates covered in Appendix A refer to the relevant procedure associated with the relevant clearance certificate.Job Owner shall establish a complete work pack consisting of THA or WI including a Handover/Hand back cover sheet, all relevant clearance certificates and any other relevant documents related to the scope and proceed to Step 5.4

1. Identified clearance certificates and associated supporting documentation assembled and prepared for authorisation

OUTPUT:

2. Appropriate documents/controls established to ensure the work will be executed safely

5.4 Relevant clearance certificates and THA/WI authorised. (Handover)The Area Owner in consultation with the Job Owner shall conduct an infield walk around to confirm:

The specific equipment/ area being worked on

The scope of work is correct and can be conducted without SIMOP’s conflicts.

Page 8: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 8 of 34Uncontrolled when printed

The boundaries of the task are discussed and understood by the Job Owner.

That the Job Owner has appropriately completed the relevant clearance certificates and understands the implementation requirements of the controls identified on the clearance certificate for the work to be performed safely.

The relevant clearance certificate(s) have been authorised by a competent person/s.

The Area Owner shall determine the frequency they will review the task based on the risk associated with the task and area the task is being conducted. Which shall be updated on the front page of the THA work sheet or WI Hand over/hand back cover sheet.

Area Owner to sign the Hand over section of the THA/WI coversheet.

Area Owner to apply a uniquely numbered hasp to the relevant ILB and record the hasp number along with the Isolation lock box number on the front page of the THA or the Hand over hand back cover page of the WI for jobs involving Level 2 isolations as a control

Safe handover of the equipment/area has been made to the Job Owner.

Area Owner to retain the original THA/WI and any other relevant documents in the agreed permit management location (e.g. permit hut, confined space/mobile ILB etc.) This original document is where all sign on signatures and changes are captured.

Job Owner shall maintain a copy of the current THA/WI and any other relevant documents and clearly mark them as a copy which shall be kept at the job site to be used as a reference document if/when required.

Area Owner to update the Area Owner Work Register (scope of work title, status, location, Job Owners name and contact details).

Notes:

Should the Area Owner identify any additional controls that require a clearance certificate, (Confined Space entry, hot work etc.) then the Job Owner will be expected to complete/facilitate completion of these before the Area Owner authorises the associated THA/WI.

Subsequent Re-Authorisation of the work to be recorded on the Re-Authorisation, Work Suspension & Job Owner Transfer sheet of the THA or WI HO/HB cover sheet.

Where an electronic Area Owner Work Register is not available or not functioning, then the Area Superintendent must determine an alternate but equal means of communicating active work information within the area. This may include (e.g. Whiteboard, paper log sheet etc.) that contains equivalent information.

5.4.1 Handover AcceptedThe Job Owner shall accept the conditions of the work pack by signing the Job Owner acceptance section of the THA/WI hand over hand back cover sheet.

NOTE: Area Owner and the Job Owner shall record their worksite checks where relevant by dating and signing the Area Owner/Job Owner checks column of sign-on sheet of the THA / WI HO/HB cover sheet, Doc No 000119419

1. Appropriate controls established to ensure the work will be executed safely

2. Area Owner and Job Owner agree on SIMOPS and required controls.

3. Plant/equipment handed over to Job Owner for work to be performed

OUTPUT:

4. Area Owner Work register updated

Page 9: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 9 of 34Uncontrolled when printed

5.5 Familiarise with required controls and sign onto THA/WI and commence work

Job Owner must review the THA/WI and associated clearance certificates and any other relevant task information with the Work Executor/s to ensure their full understanding.

Work Executor/s are to sign onto the ‘Work Executor sign-on section’ of the THA/WI hand over hand back cover sheet acknowledging:

They understand the scope of work and boundaries of the task

They understand the task steps and equipment required for the job.

The safety requirements including Hazards /DE and their controls for executing the work safely

They are trained and competent to conduct the work

Work Executor(s) to sign onto the work executor’s column of the THA work sheet/WI hand over hand back cover sheet acknowledging that they accept the conditions of all the associated task documentation.

Work Executor shall then complete a Take Time Take Charge (TTTC) form on the job before commencing the work and satisfy themselves that they understand the Work Scope, and that they have confidence in the effectiveness of the controls implemented in the execution of the job to prevent an unwanted event from occurring. Any concerns must be raised with the Job Owner to ensure any concerns raised can be managed in consultation with the Area Owner.

Safety requirements for executing the work safely, including application of personal locks and danger tags for jobs involving isolation of equipment (Refer IMS Element 14 - Management of Isolations Doc No. 000056428).

Job Owner to show Work Executors where to apply personal locks and danger tags, if applicable, and/or Work Executor(s) to proceed to execute the work in the field to completion, maintaining the copy of relevant documents in a protective device (e.g. folder/envelope) at the place of work, ensuring that all personnel affected by the work sign-on the original THA/WI before commencing work.

1. Work Executor/s understand the scope of work and required hazard controls (including any isolations) and have signed onto all relevant documentation and applied their personal lock and danger tag into the ILB hasp where applicable.

2. Work Executor(s) have been involved in the TTTC process and escalated any concerns to the Job Owner to manage.

OUTPUT:

3. The safe execution of the work has commenced.

5.6 Emergency, or work changed?It is imperative that Emergencies and/or Changes to the scope of work, or the area the work is being conducted is identified and appropriately managed to ensure the work can be executed safely.

5.6.1 Emergency Situation?An emergency is any Health, Safety and Environmental event which has resulted in or has the potential to harm people, the environment or equipment.

If there is an emergency, Proceed to Step 5.7

If there is not an Emergency, Proceed to Step 5.6.2

5.6.2 Scope of Work change?The scope of work is considered to change/have changed if:

New/additional hazards are introduced into the scope of work/work area (e.g. SIMOPS), and/or

The current Health, Safety and Environment controls have become ineffective, and/or

Page 10: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 10 of 34Uncontrolled when printed

The work boundaries change, (e.g. isolation requirements need to change)

If the job scope has changed, proceed to Step 5.1

If the job scope has not changed, Proceed to Step 5.9

1. If there has been an emergency, it is being effectively managed by the Job Owner at Step 5.9

OUTPUT:

2. If there has been a change to scope, it is being effectively managed by the Job Owner at Step 5.1

5.7 Follow emergency proceduresIn the case of an emergency, all personnel stop the task and, if safe, secure the area. Follow the evacuation requirements for the area and restrict access to the area as appropriate. If necessary, notify Emergency Services and immediately report the event to your Supervisor/Job Owner.

Follow the direction of the Evacuation Warden and await the “All Clear” instruction.

When the “All clear” instruction is given, Proceed to Step 5.10.2

OUTPUT: 1. Emergency procedures are followed, all personnel are accounted, Evacuation warden’s instructions are followed and the “All clear” instruction is given.

5.8 Review work pack requirements and re-authoriseThe re-authorisation process to continue work is as follows:

The Job Owner shall review the information on the Out-of-Service tag attached to the Isolation Lock Box hasp (where relevant) to understand the scope of work and the current status of the work.

The Job Owner in consultation with the Area Owner shall conduct an infield walk around and complete a TTTC card to review all hazards, controls (including isolations) and Simultaneous Operations for the task.

The Job Owner to then review the THA or Work Instruction to verify that all identified hazards and controls and SIMOPS are captured.

The Area Owner to then sign onto the Re-Authorisation Work Suspension Job Owner transfer sheet of the THA/WI HO/HB cover sheet before the Job Owner.

The Job Owner to then sign onto the Re-Authorisation Work Suspension job owner transfer sheet of the THA/WI HO/HB cover sheet, then where relevant remove the out of service tag from the relevant ILB hasp as directed by the Area Owner and attach their personnel red lock and a completed Job Owner tag.

If no changes are required to the work pack, Proceed to Step 5.5

If changes are required to the work pack, proceed to 5.1

Area Owner to retain the original THA/WI and any other relevant documents in the agreed permit management location (e.g. permit hut, confined space/mobile ILB etc.) This original document is where all sign on signatures and changes are captured.

Job Owner shall maintain a copy of the current THA/WI and any other relevant documents and clearly mark them as a copy which shall be kept at the job site to be used as a reference document if/when required.

Area Owner to update the Area Owner Work Register (scope of work title, status, location, Job Owners name and contact details).

Notes:

Where an electronic Area Owner Work Register is not available or not functioning, then the Area Superintendent must determine an alternate but equal means of communicating active

Page 11: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 11 of 34Uncontrolled when printed

work information within the area. This may include (e.g. Whiteboard, paper log sheet etc.) that contains equivalent information.

If the previous Job Owner has not Transferred and suspended work Proceed to Step 5.12.2

1. An Area Owner and Job Owner have conducted an infield TTTC to ensure understanding of the current area/task conditions.

OUTPUT:

2. The full work pack is reviewed to determine if changes are needed.

If no changes are required to the work pack, Proceed to Step 5.5If changes are required to the work pack, proceed to 5.1

5.9 Work completed?Task/Work is considered finished when:

The work scope has been completed as intended, and

The equipment/plant is in a safe return to service state ready for Hand-Back, and

All clearance certificates are ready to be handed back/closed, and

If the task/work is not complete proceed to Step 5.10If the Job Owner has deemed the task/work finished, the Job Owner shall proceed to Step 5.11

OUTPUT: 1. Job owner has determined if work is complete If the Job Owner has deemed the task/work finished, the Job Owner shall

proceed to Step 5.12 If the task/work is not complete proceed to Step 5.10

5.10 Is a Job Owner Transfer Possible? If Yes, Proceed to Step 5.10.1

If No, Proceed to Step 5.10.2

5.10.1 Facilitate Job Owner TransferIf the work is a continuation across shifts/work teams and the scope of the work has not changed, then an Area Owner can authorise the new Job Owner by following the below instructions:

Area Owner to confirm that the incoming Job Owner is trained and competent (minimum of carrying a JO card)

The incoming Job Owner in consultation with the outgoing Job Owner and an Area Owner shall conduct an infield walk around and complete a TTTC to assist in the review of all aspects of the task including:

Scope of work and the current status of the work

The location of the work and/or the equipment that is being worked on

Boundaries of the work are discussed and understood

All hazards, controls and Simultaneous Operations (SIMOPS) for the task

Clearance certificate requirements, to ensure they are completed to the required standard and attached to the work pack

The incoming Job Owner shall then review the THA/WI to verify that everything discussed/identified during the walk around is appropriately covered by the current THA/WI to reduce the risk to as low as reasonably practical. If not and changes are required, Proceed to Step 5.1

If no changes are needed, proceed as per below:

Page 12: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 12 of 34Uncontrolled when printed

Area Owner shall authorise the new JO by signing the Area Owner’s part of the re-authorisation page within the THA/WI HO/HB cover sheet.

The in-coming (new) Job Owner shall sign the Job Owner’s part of the re-authorisation page within the THA/WI HO/HB cover sheet and any relevant clearance certificates.

The in-coming (new) Job Owner shall hand Personal danger lock and completed Job Owner’s danger tag onto the relevant ILB hasp (where level 2 isolation are being used as a control for the task)

The outgoing JO shall sign in the Transferred column of the re-authorisation page of the THA/WI HO/HB cover sheet. (Where level 2 isolation are being used as a control for the task remove their Personal danger lock and completed Job Owner’s tag from the relevant ILB has)

Transfer complete, Proceed to Step 5.5

Notes:

Work executers can remain on the job during a Job Owner’s transfer if/when needed, this is why the AO authorises the new JO and the incoming JO must be signed on before the outgoing JO signs the transferred column of the re-authorisation section of the THA work sheet. (The incoming Job Owner shall determine if they will allow WE’s to remain on the job during the Job Owner transfer before the transfer begins)

The incoming JO must notify the WE’s before conducting a JO transfer.

1. The incoming Job Owner has determined if they will allow the current WE’s to remain on the job whilst they conduct their Job Owner transfer.

OUTPUT:

2. Safe and effective Job Owner transfer of work between Job Owners completed in consultation with an Area Owner, JO then Proceeds to step 5.5 and follows work flow to get new WE’s onto the job.

5.10.2 Suspend work.Where work is not complete and a transfer between Job Owners is not possible:

Job Owner and Area Owner must collaboratively determine the suitable safe state or condition for the equipment

Work Executors to stop work (Remove their personal lock and danger tag if applicable)

All clearance certificates must be managed, refer to the detailed clearance certificate procedures to determine the requirements

Job Owner to sign the Work Suspended column of the Re-Authorisation and Work Suspension Job Owner transfer sheet on the THA or WI HO/HB cover sheet and place all documents back into the permit management location for safekeeping.

Job Owner shall remove their Job Owner tag and personal danger lock from the Isolation Lock Box hasp and place an completed Out-of-Service tag on there (where Level 2 Isolations are associated with the task)

The Job Owner shall notify the Area Owner why they have suspended the task and when it is likely to continue

Area Owner shall update the Area Owner work register.

Work Suspension complete.

NOTE: New Job Owners to Proceed from Step 5.8

1. Work has been suspended, to be continued later from Step 5.8OUTPUT:

2. Work status communicated between Job Owner and Area Owner and the AO register is updated.

Page 13: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 13 of 34Uncontrolled when printed

5.11 Follow hand-back requirementsIn consultation with the Area Owner the Job Owner shall conduct an infield walk around to ensure that:

The scope of work is complete as intended

The Equipment/Area is in a safe operational state e.g. area clean, machine guarding back, parts and equipment used for task removed from area etc.

All Work Executor’s have removed their personal lock and danger tag from the relevant ILB Hasp (Where isolations where being used as a control)

All clearance certificates have been closed (refer to the detailed clearance certificate procedures to determine the requirements)

Job Owner “hands back” to the Area Owner by signing the ‘handback” section on the THA/WI HO/HB cover sheet.

Job Owner shall hand all associated documents for the task to the Area Owner for review and acceptance of the handback.

Note: If someone has lost their key and the forced removal of a personal lock is required, refer to Management of Isolation, Doc No. 000056428.

1. Area Owner and Job Owner have confirmed the work is complete. OUTPUT:

2. Job Over “hands back” to the Area Owner by signing the ‘handback” section of the THA WI.

5.12 Accept Hand backThe Area Owner shall ensure:

All associated documents for the task has been received from the Job Owner

Area Owner confirms the acceptance of the hand back by signing the Hand back acceptance section of the THA/ WI HO/HB cover sheet.

Area Owner updates the Area Owner work register.

Note: If someone has lost their key and the forced removal of a personal lock is required, refer to Management of Isolation, Doc No. 000056428.

1. All associated documents for the task has been received by the Area Owner for review and acceptance of the handback.

OUTPUT:

2. Area Owner has accepted the hand back.

5.12.1 Record KeepingThe Area Owner shall collate all documentation associated to the task and archive it the permit management location for a period of 3 months.

Disposal after this period shall be via the relevant OD disposal of records requirements.

NOTE: Any documentation involved in an incident shall be attached directly to the event notification in EMS.

OUTPUT: 1. All documentation associated to the task is archived to ensure it auditability if/when required.

5.12.2 Failure to Hand backIn the event that a Job Owner fails to facilitate a Job Owner transfer/Work suspension the Area Owner shall contact the Job Owner who has failed to facilitate a Job Owner transfer/Work suspension prior to leaving site and request that they return to work and do so.

Page 14: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 14 of 34Uncontrolled when printed

Where it is determined it’s either unsafe or it’s unrealistic that they can return to facilitate a Job Owner transfer/Work suspension within in a suitable time frame the Area Owner shall escalate to the Area Superintendent / Duty Manager.

The Area Superintendent / Duty Manager shall:

Confirm with the main gate that the individual is swiped “offsite”, and

Contact the Job Owner by phone to discuss the task/area and its current status to ensure full understanding of the task hand over information, and

Review the TTTC card that the new Job Owner and the Area Owner have completed (on the job) to ensure real time hazards including SIMOPS have been considered, and

Area Superintendent / Duty Manager can then allow an Area Owner to authorise a new Job Owner onto the task without the previous Job Owner having signed the Transferred or Suspended columns of the Re-Authorisation, Work Suspension & Job Owner Transfer section of the THA/WI HO/HB cover sheet.

The Area Owner with support from the Job Owner will then raise an Event Notification in EMS for follow up and data capture.

5.12.3 Training, Competency & Authorisation RequirementsFor all Training and Competency requirements: Refer to Appendix B, and IMS Element 3 - Olympic Dam Training Pathways Procedure, Doc No. 12275829.

6 ROLES AND RESPONSIBILITIES

Role Expectation

Work Executor A trained and competent person responsible for carrying out the work under the permitted conditions.

Responsible for the safe execution of the work as per the scope, including adherence to the requirements of the documented clearance certificates and Task Hazard Assessment (THA) or Work Instruction (WI).

Area Owner Nominated, trained and authorised person who are accountable for the coordination, safe execution and close-out of all work within a defined work area:

Responsible for confirming requirements of the documented clearance certificates and THA/WI are in place before authorising or re-authorising the relevant clearance certificates THA/WI for the Job Owner.

Manages SIMOPS, permitted work handover/hand back, closeout and tracking of permitted work within designated work area.

Performs periodic field verification checks of conformance of permitted conditions during the permit to work lifecycle.

Cannot also hold the role of Job Owner for a given permitted THA/WI.

Job Owner A nominated, trained work team supervisor who is the single point of accountability for the safe execution and close-out of assigned permitted work.

Responsible for developing and implementing the requirements of the documented clearance certificates and THA or WI

Gains authorisation from the Area Owner before commencing work. Communicates the work requirements to the work executors and ensures

effective management of controls during the permit to work process lifecycle including handover/hand back and closeout.

Ensures Work Executors are trained, qualified and competent to perform the work.

Cannot also hold the role of Area Owner on a single THA/WI.

Page 15: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 15 of 34Uncontrolled when printed

Role Expectation

A Job Owner who is also a Work Executor on a task, can’t be the Job Owner of any other scopes of work.

May be the Job Owner of up to a maximum of 5 jobs simultaneously, if in consultation with the AO they agree that they can effectively supervise each of the jobs.

Area Superintendent(Owner of the Area)

A trained and appointed individual responsible for the management and application of the permit to work process within their respective area of responsibility as the Owner of the Area (i.e. plant or area of operation).

Authorises personnel who fulfil the roles of the permit to work process with their area of responsibility.

Management of Area Owner coverage to ensure effective management of SIMOPs and the permit to work process.

Ensure all temporary transfer of Area Ownership is managed using the process described in Appendix C

Note: The Area Ownership Map (Appendix D) is used to indicate high level area ownership and supplements the OD Battery Limits (Doc No. 000099773)

Duty Manager Can act on behalf of the Area Superintendent outside of normal business hours (on call) or as directed if/when they are not available.

7 REFERENCES AND RELATED DOCUMENTS

Document Type Document Title and Number

Standard IMS Element 14 - Systems of Work Standard, Doc No 012350432

Other PTW and Isolation Training Pathways, Doc No. 012275829

Procedure Management of Isolations, Doc No. 000056428

Procedure Task Hazard Analysis (THA) Procedure, Doc No. 000037634

Form Permit to Work Process WI Handover – Hand back Form, Doc No. 000119419

Other Olympic Dam Battery Limits, Doc No. 000099773

Form PTW Temporary Area Transfer, Doc No. 011816978

Form Task Hazard Analysis (THA) Worksheet - 000038526

Page 16: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 16 of 34Uncontrolled when printed

8 APPENDICES

8.1 Appendix A – Clearance CertificateListed below are the clearance certificates required for management of the hazard controls associated with significant risks at OD.

Clearance Certificate (CC) Title

Doc No. Ref. Hazard/s as Energy

Purpose

Building Penetration clearance certificate

000106221 Electrical Issued for any work that requires excavation or ground/building penetration (apart from the working mine), identifying underground services and recording hazard controls associated to the ground disturbance.

Confined Space 000098483 Chemical Completed to ensure full understanding of the space(area)/task being conducted is fully understood taking into consideration all related documentation so all required controls and associated documentation is in place and the confined space has been prepared for safe entry for personnel.Used whenever a person’s breathing zone (300mm sphere around the mouth and nose) gets within the entry plane of a confined space.

CC for Conveyor Belt Clamps

000118483 Machine Safe clamping of conveyor belts.

Environmental disturbance clearance certificate

000116395 Environment Required for any disturbance to vegetation outside the boundaries of the exclusion zone shown on drawing ODE4000-0-0533 and any areas within the exclusion zone where plants, animals or environmental monitoring equipment may be affected.

Equipment Isolation Method (EIM) Template

000055945 Machine, Chemical, Electrical

Identify the isolation process required for completing a task or series of tasks safely without the potential for entanglement, electric shock, etc. The isolation requirements also consider any break in containment or testing/sanctioning requirements.

Emergency Excavation Certificate

000117640 Engulfment, Electrical, Chemical

Issued for any emergency excavation or ground penetration (apart from the working mine), identifying underground services and recording hazard controls associated to the ground disturbance.

Excavation Clearance Certificate

000119174 Engulfment, Electrical, Chemical

Issued for any work that requires excavation or ground penetration (apart from the working mine), identifying underground services and recording hazard controls associated to the ground disturbance.

Page 17: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 17 of 34Uncontrolled when printed

Clearance Certificate (CC) Title

Doc No. Ref. Hazard/s as Energy

Purpose

High Voltage Electrical Work: Electrical Working on equipment or infrastructure with more than 1000 volts alternating current.

High Voltage - Vicinity (VCC) 000053145 Electrical Issued when there is a requirement for personnel to work within the vicinity of live high voltage (HV) equipment.

High Voltage - Testing (TCC) 000053496 Electrical Issued when there is a requirement for a high voltage testing party to work on or within the minimum safe working distance of HV equipment that would normally be capable of being energised. Differs from HV Access clearance certificate in that it authorises the HV Permit Acceptor to remove or place operator earths for the purpose of testing, and to apply lethal voltages or currents for testing purposes.

High Voltage - Access (ACC) 000053201 Electrical HV equipment that would normally be capable of being energised.

Hot Work CC 000119931 Thermal Issued for all jobs involving any arc or gas welding, any gas, disc or oxy- cutting, any grinding or other procedure which involves the generation of sparks or other ignition sources that have the potential to create fire or explosion. To identify hazard and record risk controls for any hot work activity performed outside of an approved hot work area, e.g. workshop. Hot work undertaken outside of designated Hot Work area.

Radiation Clearance to Enter Areas of High Radiation

000063556 Radiation Issued for: 1) All radiography, e.g. x-raying welds, 2) Any work required to be performed within 1 metre of an isolated radiation source and 3) Any work required to be performed on non-isolated radiation sources.

Radiation Gauge Clearance 000071617 Radiation Issued for work on or around radiation density gauges.

Working at Height 000121159 Gravitational Issued to identify hazards and risk controls for any work where there is a chance of personnel or equipment being exposed to injury by work at heights.

Workbox clearance certificate

000040453 Gravitational Clearance certificate for workbox.

Page 18: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 18 of 34Uncontrolled when printed

8.2 Appendix B – Training and Competency & Authorisation RequirementsStructured competency-based training shall be given to all users of the Permit to Work process, for more detail on area or process specific Permit to Work training refer to Element 14 - PTW and Isolation Training Pathways, (Doc No. 012275829).

Role Pre-requisites Training, Assessment & Authorisation Who can train and assess?

Work Executor Nil Maintain the requirements of IMS Element 3 – Olympic Dam Training Pathways Procedure Document Number 012275829 such as:

Site Access Curricula Mandatory Inductions Mandatory Area Inductions Hold current tickets/licenses for all relevant

work being conducted Completed Safety Essential User training.

NOTE: for a full description of training needs refer to IMS Element 3 – Olympic Dam Training Pathways Procedure Document Number 012275829

Training Department approved BHP Facilitators

Job Owner Work Executor OD: THA Developer & Job Owner/Area Owner (8 hr classroom LMS #717001).Complete any other Job Owner training & certification requirements required for the relevant clearance certificate and/or related procedure, (e.g. Management of Isolations Doc No.000056428). Note: Job Owners will receive a Job Owners card.

Training Department approved BHP Facilitators.

Area Owner Job Owner 1. Complete the OD: PTW - Area Owner Practical Training record. (Doc No: 000110979) (LMS code ODURN05890OD)2. Pass the OD: PTW - Area Owner Competency assessment. (Doc No: 000058545) (LMS code ODQ50558686)

1. Competent Person2. Area approved in-field Trainers and Assessors3. Area Superintendent

Page 19: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 19 of 34Uncontrolled when printed

Role Pre-requisites Training, Assessment & Authorisation Who can train and assess?

3. Gain authorisation from the relevant Area Superintendent via area specific Authorisation sheet.

Area Superintendent

Job Owner No additional training requirements Area Inducted.

Page 20: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 20 of 34Uncontrolled when printed

8.3 Appendix C – Temporary Transfer of Area OwnershipOccasionally situations arise that may be suited to conduct a temporary transfer of Area Ownership, as defined by the Permit to Work process. A common example of this would be to Transfer Area Ownership of a small area to a Project lead for a certain period/phase of a long-term project.

This transfer of Area Ownership requires the new owner of the area e.g. Project Lead to take on the full accountabilities of the PTW process in that area for a specified duration of time. (e.g. the duration of the project period/phase) including the authorisation process for projects personnel to perform PTW roles within the defined area such as Area Owners.

To manage the risks involved in the temporary transfer of Area Ownership the following process shall be followed for each transfer of area ownership:

1. Incoming (new) Area Superintendent/Project lead and current Area Superintendent shall determine if the transfer of Area Ownership can be limited to non-operational plant areas, where clear demarcation of the area is possible.

2. Incoming Area Superintendent to initiate a temporary Management of Change (MOC) via the OD MOC Process.

3. Ensure a Risk Assessment (e.g. RRRA) is conducted to ensure the inherent risks of the area are known and managed by the incoming temporary Area Superintendent as Owner of the Area.

4. Identify the process to establish competent and authorised Area Owners and Authorised Isolators for the temporary change area.

5. Use the PTW Temporary Area Transfer Form (Document # 011816978) and attach to the MOC (include handback process).

6. Obtain authorisation for the transfer from the original Manager of the Area as a minimum.

Page 21: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 21 of 34Uncontrolled when printed

8.4 Appendix D – Area Ownership MapThe application and governance of the OD Permit to Work Doc No. 000056567 requires definition of ownership of all Permit to Work areas (and certain services) at the Superintendent level.

This Appendix visually demonstrates these physical areas and boundaries at Area Superintendent Level and supplements the information in the OD Battery Limits, Doc No. 000099773. The underground section of the Mine has not been included at this time.

Further to the maps and information provided below, the Element 14 - PTW and Isolation Training Pathways, Doc No. 012275829 has been cross-referenced to identify the current owners of the areas and the specific training and authorisation requirements.

Maps are high level and may have overlap; please contact the assigned Area Owner for more detailed information.

8.4.1 Map 1 - Overview Surface Processing Plant

Page 22: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 22 of 34Uncontrolled when printed

Area Number Sub Area Area Superintendent Area Manager

1TRS

Evaporation Ponds, Tailings, Resource Recovery Superintendent TRS Manager Production UGS

2Pilot Plant & Surrounds

Superintendent Concentrator Manager Production Copper

3Mine Production

Surface Quarry.Many subareas exist within this area owned by Mine Production. Map 4 provides details

Superintendent Mine Production Surface

Surface Manager Mine Production

4Desalination Plant

RO, Borefield Rd, Demin Plant, Water Storage Dams, Saline System, Plant Water, Effluent & Sewerage, Wheel Wash

Superintendent Onsite Facilities and Water Ops

Manager Asset Integrity Remediation

5Resource Recovery

Landfill, CWDF Manager Asset Integrity Remediation

Saline system and Assets - spread throughout the Surface and Mine (not depicted on map)

Superintendent Onsite Facilities and Water Ops

Manager Asset Integrity Remediation

Page 23: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 23 of 34Uncontrolled when printed

8.4.2 Map 2 - Surface Processing Plant (West)

Page 24: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 24 of 34Uncontrolled when printed

Area Number Sub Area Area Superintendent Area Manager

1 ER

CSM, APM, ASM, Crane, Slimes Collection Superintendent Production Electro Refinery

Manager Production Copper

2a EW

CSM, Crane Superintendent Production Labs EW & GR

Manager Production UGS

2b Gold Room

Cyanidation, Silver Room, Gold Cage, Zinc, Aciding, NOX Scrubber

Superintendent Production Labs EW & GR

Manager Production UGS

2c Laboratory

Final Products Lab, Metallurgical Lab, Analytical Lab

Superintendent Production Labs EW & GR

Manager Production UGS

3 Smelter 1, Hot metals maintenance work shop Superintendent Maintenance Smelter

Manager Maintenance Surface

4 LPG Yard, Broadspectrum yard, Superintendent Hot Metals Manager Smelter

5Supply

Yard 3, Warehouse Superintendent Warehouse and Transport

Head of Operations Australia

6Switch Yard 2

Instrument air isolations Refrigeration isolations, Instrumentation isolations, Plumbing isolations, Linesman isolations, Commercial Elect Equip, Industrial Elect Equip, Unrestricted HV, Restricted HV

Superintendent Electrical Manager Maintenance Surface

7 Superintendent Warehouse and Transport

Head of Operations Australia

8SCM Laydown

Superintendent SCM Planning Manager Maintenance Surface

Page 25: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 25 of 34Uncontrolled when printed

Area Number Sub Area Area Superintendent Area Manager

9Industrial Cleaning Yard

Superintendent TRS Manager Production UGS

10HSE

Main Gate, Medical Centre, Emergency Services, Radiation and Hygiene, Safety BP

Superintendent Safety, Environment and Radiation

Head of HSE OD

11Refinery Maint Workshop

Superintendent Refinery Maintenance

Manager Maintenance Surface

12Storm Water Pond

Superintendent Acid Plant Feed Prep

Manager Smelter

13Oxy Plant (BOC)

n/a Manager Smelter

14Cape Yard

n/a Manager Maintenance Surface

15 Superintendent TRS Manager Production UGS

16aCentral Control Building

Central Control Room, Technology, Primary Server Room

Superintendent OT Operations Maintenance

Manager OT Operations

16bDisaster Recovery Control Centre

Datapod, Backup Control Room, Secondary Server Room

Superintendent OT Operations Maintenance

Manager OT Operations

177th Ave Car Wash

Superintendent Acid Plant Feed Prep

Manager Smelter

Page 26: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 26 of 34Uncontrolled when printed

Area Number Sub Area Area Superintendent Area Manager

Broadway pipeline Superintendent Acid Plant Feed Prep

Manager Smelter

P1/P2 Car parks Superintendent Mine Production Surface

Manager Mine Production Surface

P1 and P2 Laundry Change rooms Superintendent Onsite Facilities and Water Ops

Manager Asset Integrity Remediation

Smelter Office Manager Smelter

PTS Office Manager Maintenance Surface

PPO Office Manager Modification & Small Projects

Admin Building General Manager Surface

Training Building Manager Training

PAT Centre Head of HSE

Project Offices Manager Studies (Projects)

Page 27: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 27 of 34Uncontrolled when printed

8.4.3 Map 3 - Surface Processing Plant (East)

Page 28: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 28 of 34Uncontrolled when printed

Area Number Sub Area Area Superintendent Area Manager

1Smelter and Casting

LPG, Anode Furnace off gas, Casting, Blister refining, Shaft Furnace, Flash Furnace/ Electric Furnace, Waste Heat Boiler

Superintendent Production Hot Metals Manager Smelter

2Acid Plant Feed Prep

AUX Boiler, Dry Gas, Strong Acid, Sulphur handling, concentrate drying & filtering, Conc storage & transport, Conc Ponds & reclaim, Conc Thickening, Flux Plant

Superintendent Production Acid Plant and Feed Prep

Manager Smelter

3Hydromet & Solvent Extraction

CCD, Clarification, Deslimes, Tails Disposal, Tails Leach, CUSX, USX, Precip, Calcination, UOC, Ammonia bullets, Scuttle Pond

Superintendent Hydro/SX Manager Production UGS

4Concentrator

Slag Mill, OSA, Floats, Grinding, Reagents, Cons Leach, Dust Leach

Superintendent Production Concentrator

Manager Production Copper

5Northern Switch Yard

Instrument air isolations Refrigeration isolations, Instrumentation isolations, Plumbing isolations, Linesman isolations, Commercial Elect Equip, Industrial Elect Equip, Unrestricted HV, Restricted HV

Superintendent Electrical Manager Maintenance Surface

6 Compressor House, Pot shed, Workshops n/a Manager Maintenance Surface

7Fixed Plant Maint Workshop

Plant Mechanical, Fixed Plant Electrical, Fixed Services, Underground Rail Fixed

Superintendent Fixed Plant Manager Maintenance Fixed Plant

8 Firewater Dam, Stormwater Pond, Process ire System, Demin Plant

Superintendent Onsite Facilities and Water Ops

Manager Asset Integrity Remediation

9 Superintendent Shutdown Execution Manager Maintenance Surface

Page 29: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 29 of 34Uncontrolled when printed

Area Number Sub Area Area Superintendent Area Manager

10 Superintendent Hydro/SX/TRS Maintenance

Manager Maintenance Surface

11Boom Yard

n/a Manager Maintenance Surface

12Cape Yard

n/a Manager Maintenance Surface

14Primary Sewer Lagoon, Evaporation Fill Lagoon, 170 ML Process Water Dam, 200 ML Process Water Dam, Redundant Sewerage Treatment Lagoon

Superintendent Onsite Facilities and Water Ops

Manager Asset Integrity Remediation

Mill/Hydro Off Manager Production UGS

Page 30: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 30 of 34Uncontrolled when printed

8.4.4 Map 4 - Mine Surface

Page 31: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 31 of 34Uncontrolled when printed

Area Number Sub Area Area Superintendent Area Manager

1 Superintendent Fixed Plant Manager Maintenance Fixed Plant

2 Mine Surface Workshop

Mobile Fleet Superintendent Maintenance Mobile Fleet Manager Mine Mobile Maintenance

3Fuel and Hydrocarbon Area, Air Compressor Facility, Whenan shed

Superintendent Fixed PlantManager Maintenance Fixed Plant

4Development

Superintendent Mine Development NMA/SMA Manager Mine Development Underground

5 n/a Manager Maintenance Fixed Plant

6Core Farm Diamond Drill

Superintendent Diamond Drilling Manager Mine Production Underground

7Mobile Maintenance Workshop

Drills & Light Vehicles Superintendent Maintenance Mobile Fleet Manager Mine Mobile Maintenance

8McMahon Yard

Superintendent Drill and Blast Manager Mine Production Underground

9Sandvic Yard

Superintendent Mine Production Underground Manager Mine Production Underground

10Shotcrete Plant

Superintendent Mine Development NMA/SMA Manager Mine Development Underground

11 Mobile Fleet Superintendent Mine Mobile Maintenance Manager Mine Mobile Maintenance

12 Project Yards n/a Manager Asset Integrity Remediation

Page 32: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 32 of 34Uncontrolled when printed

Area Number Sub Area Area Superintendent Area Manager

13 Superintendent Mine Development SMA Manager Mine Development Underground

14Goodline Yard

n/aManager Modifications and Small Projects

Raised Bores Superintendent Fixed Plant Manager Maintenance Fixed Plant

Car parks and roads (Mine End only) Superintendent Mine Production Surface Manager Mine Production Surface

Page 33: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 33 of 34Uncontrolled when printed

8.4.5 Map 5 - Olympic Village, Airport and Surrounds

Page 34: IMS Element 14 - Permit to Work (PTW) Procedure

IMS Element 14 - Permit to Work (PTW) Procedure Olympic Dam

Olympic Dam Document No. 000056567 V. 20 Page 34 of 34Uncontrolled when printed

Area Number Area Superintendent Area Manager

1OD Airport

Superintendent Offsite Facilities Manager Services

2OD Village

Superintendent Offsite Facilities Manager Services

3 Superintendent Onsite Facilities and Water Ops Manager Asset Integrity Remediation