improving grid discipline through abt.pps

40
05/16/22 1 AVAILABILITY BASED TARIFF An Overview Dr. S. K. Agrawal, General Manager, POWERGRID Kathmandu : April 1, 2009 Energy Transmission Partnership on the Cross Border Exchange of Electricity

Upload: juben-bhaukajee

Post on 10-Dec-2015

7 views

Category:

Documents


1 download

TRANSCRIPT

  • *

    AVAILABILITY BASED TARIFF An Overview

    Dr. S. K. Agrawal, General Manager, POWERGRID

    Kathmandu : April 1, 2009

    Energy Transmission Partnership on the Cross Border Exchange of Electricity

  • SKA*Chronological Sequence of Implementation of ABT

    1990 : K. P. Rao Committee Proposed Two Part Tariff structure consisting of Fixed and Variable charges1993-94 : A structured study by M/s ECC, USA, funded by ADB, sponsored by WB as a covenant of loans to POWERGRID Availability Based Tariff (ABT)1995-98 : NTF / RTFs, formed for ABT implementation. 1999 : Matter transferred to CERC : Hearings etc.2000 : CERC Order, but stayed due to petitions2001-02 : Problems of regional grid operation continued : Many intractable commercial disputes also arose2002-03 :ABT implemented successfully.

    SKA

  • *Outline of the presentationNeed for ABTABT conceptHow UI pricing works?Amendments to UI ratesPayment of capacity & Energy ChargesMany dimensions of UI mechanismSettlement system and logisticsImpact of ABTLimitations and way ahead

  • *Conditions when ABT was conceivedGrid indiscipline No respect for schedule by generating stations as well as beneficiary SEBsPoor Frequency regime Low frequency during peak periods, high frequency during off-peak periodsReasonPerverted incentives in the tariff regime at that time Recover of capacity charges based on PLF and no differential payment for deviations from schedule

  • SKA*ABC of ABTFrequency actuated signalSignal transmitted at the speed of dynamics to be controlledQuasi-steady state assumption not validReal time pricing stretched to its physical limitsMerit orderEconomic load managementIncentives for helping the gridOpportunities for a diligent playerSimple, dispute-free weekly settlement system

    SKA

  • SKA*Deviations from Schedule - UI

    SKA

  • SKA*DECENTRALIZED SCHEDULINGAvailability Declaration (DC)EntitlementsSLDC

    Requisition & Bilateral AgreementsInjection ScheduleDrawal ScheduleRevision in DCRevision in RequisitionFinalInjection ScheduleFinalDrawal ScheduleRLDCISGSTimeRevisions duringCurrent dayRevisions duringCurrent day0 to 24 hours

    09:00 10:0015:0017:0022:0023:00

    SKA

  • SKA*

    SKA

    Chart1

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    10001000

    982982

    964964

    946946

    928928

    910910

    892892

    874874

    856856

    838838

    820820

    802802

    784784

    766766

    748748

    730730

    712712

    694694

    676676

    658658

    640640

    622622

    604604

    586586

    568568

    550550

    532532

    514514

    496496

    478478

    460460

    442442

    424424

    406406

    388388

    370370

    352352

    334334

    316316

    298298

    280280

    272272

    264264

    256256

    248248

    240240

    232232

    224224

    216216

    208208

    200200

    192192

    184184

    176176

    168168

    160160

    152152

    144144

    136136

    128128

    120120

    112112

    104104

    9696

    8888

    8080

    7272

    6464

    5656

    4848

    4040

    3232

    2424

    1616

    88

    00

    050.52

    050.54

    050.56

    050.58

    050.6

    050.62

    050.64

    050.66

    050.68

    050.7

    050.72

    050.74

    050.76

    050.78

    050.8

    050.82

    050.84

    050.86

    050.88

    050.9

    050.92

    050.94

    050.96

    050.98

    051

    Unscheduled Interchange (UI) Rate Applicable only for deviations from contract in real-time

    280

    Surplus condition in the Grid

    Deficit Condition in the Grid

    Signal to use all available generating resources else reduce energy consumption

    signal to serve more consumer if possible else save fuel by reducing generation

    UI Rate wef 07th Jan 2008

    UI Rate wef 07th January 2008

    Frequency (HZ)--->

    Rate(Paise/KWH)--->

    Balancing Market guiding Vector

    Sheet1

    48.51000

    48.521000

    48.541000

    48.561000

    48.581000

    48.61000

    48.621000

    48.641000

    48.661000

    48.681000

    48.71000

    48.721000

    48.741000

    48.761000

    48.781000

    48.81000

    48.821000

    48.841000

    48.861000

    48.881000

    48.91000

    48.921000

    48.941000

    48.961000

    48.981000

    491000

    49.02982

    49.04964

    49.06946

    49.08928

    49.1910

    49.12892

    49.14874

    49.16856

    49.18838

    49.2820

    49.22802

    49.24784

    49.26766

    49.28748

    49.3730

    49.32712

    49.34694

    49.36676

    49.38658

    49.4640

    49.42622

    49.44604

    49.46586

    49.48568

    49.5550

    49.52532

    49.54514

    49.56496

    49.58478

    49.6460

    49.62442

    49.64424

    49.66406

    49.68388

    49.7370

    49.72352

    49.74334

    49.76316

    49.78298

    49.8280

    49.82272

    49.84264

    49.86256

    49.88248

    49.9240

    49.92232

    49.94224

    49.96216

    49.98208

    50200

    50.02192

    50.04184

    50.06176

    50.08168

    50.1160

    50.12152

    50.14144

    50.16136

    50.18128

    50.2120

    50.22112

    50.24104

    50.2696

    50.2888

    50.380

    50.3272

    50.3464

    50.3656

    50.3848

    50.440

    50.4232

    50.4424

    50.4616

    50.488

    50.50

    50.520

    50.540

    50.560

    50.580

    50.60

    50.620

    50.640

    50.660

    50.680

    50.70

    50.720

    50.740

    50.760

    50.780

    50.80

    50.820

    50.840

    50.860

    50.880

    50.90

    50.920

    50.940

    50.960

    50.980

    510

    Sheet2

    Sheet3

  • *Concept of ABTCapacity (fixed) Charge recovery of generator linked to AvailabilityCapacity charges payable by beneficiary based on capacity allocatedEnergy (variable) charges based on scheduled energyA third component known as Unscheduled Interchange (UI) charge is levied for deviation from the schedulesRate of UI Charge is based on frequencySettlement period of 15 minutesApplicability - Central Generating Stations and drawal from the grid by beneficiaries

  • *Unscheduled Interchange (UI)For Generating StationUI = Actual generation - Scheduled generation

    For beneficiary (getting supply from grid)UI = Total actual drawal - Total scheduled drawal

  • *Kink at 49.8 HzNormal Operating Band specified in IEGC

  • *How UI pricing works -High FrequencyExample: Generating Stations

    Sheet1

    Generating Station

    AB

    Energy Charge (INR /Kwh) =1.040.88

    Frequency(Hz) =50.2

    UI Rate (INR /Kwh)=1.2

    Gain (Paise/ KWh) for generation below schedule =0.160.32

    Conclusion:

    Generating station A should srart reducing generation if frequency rises beyond the level at which UI rate is 1.04 INR/KWh i.e. 50.24 Hz

    Generating station B should start reducing generation if frequency rises beyond the level at which UI rate is 88 INR/KWh i.e. 50.28 Hz

    Frequency (Hz) =50.1

    UI Rate (Paise /Kwh)=112

    Variable cost of costliest operating generating station owned by the beneficairy (Paise /Kwh)=

    120

    Loss (Paise/ KWh) for each unit of own generation8

    Conclusion:

    Beneficiary should start reducing generation at the costliest operating station (and overdraw from the grid) if variable cost of this station exceed prevailing UI Rate..

    Frequency (Hz) =49.849.5

    UI Rate (Paise /Kwh)=196280

    Variable cost of the cheapest hot standby generating resorrce owned by the beneficairy (Paise /Kwh)=

    150

    Loss (Paise/ KWh) for each unit of own generation-46

    Conclusion:

    Beneficiary should start generation at the cheapest hot standby unit at a frequency dips to a value at which UI rate becomes equal to variable cost of this unit.

    Beneficiary should start loadshedding if UI rate is high and there is no standby generating resource.

    Frequency (Hz) =49.4

    UI Rate (Paise /Kwh)=308

    Variable cost of the generating station despatched below availability or having margins295

    Gain by generating over the schedule (Paise /KWh)13

    Conclusion:

    A generating station under ABT should, if feasible, start generating above schedule if frequency dips to a level at which UI Rate is equal to its variable cost.

    Sheet2

    Sheet3

  • *How UI pricing works -Low FrequencyExample: Generating Station

    Sheet1

    Generating Station

    AB

    Energy Charge (paise /Kwh) =9070

    Frequency(Hz) =50.250.28

    UI Rate (Paise /Kwh)=8461.6

    Earning (Paise / KWh) for over generation =-6-8.4

    Conclusion:

    Generating station A should not generate over schedule beyond the frequency at which UI rate is 90 aise/KWh i.e. 50.18 Hz

    Generating station B should not generate over schedule beyond the frequency at which UI rate is 70 aise/KWh i.e. 50.25 Hz

    Frequency (Hz) =50.1

    UI Rate (Paise /Kwh)=112

    Variable cost of costliest operating generating station owned by the beneficairy (Paise /Kwh)=

    120

    Loss (Paise/ KWh) for each unit of own generation8

    Conclusion:

    Beneficiary should start reducing generation at the costliest operating station (and overdraw from the grid) if variable cost of this station exceed prevailing UI Rate..

    Frequency (Hz) =49.849.5

    UI Rate (Paise /Kwh)=196280

    Variable cost of the cheapest hot standby generating resorrce owned by the beneficairy (Paise /Kwh)=

    150

    Loss (Paise/ KWh) for each unit of own generation-46

    Conclusion:

    Beneficiary should start generation at the cheapest hot standby unit at a frequency dips to a value at which UI rate becomes equal to variable cost of this unit.

    Beneficiary should start loadshedding if UI rate is high and there is no standby generating resource.

    Frequency (Hz) =49.8

    UI Rate (INR /Kwh)=2.8

    Energy charge of the generating station despatched below availability or having margins2.4

    Gain by generating over the schedule (INR /KWh)0.4

    Conclusion:

    This generating station should, if feasible, start generating above schedule if frequency dips below the level at which UI Rate is equal to its energy charge i.e. 49.9 Hz.

    Sheet2

    Sheet3

  • *How UI pricing works -High FrequencyExample: Beneficiary

    Sheet1

    Generating Station

    AB

    Energy Charge (paise /Kwh) =9070

    Frequency(Hz) =50.250.28

    UI Rate (Paise /Kwh)=8461.6

    Earning (Paise / KWh) for over generation =-6-8.4

    Conclusion:

    Generating station A should not generate over schedule beyond the frequency at which UI rate is 90 aise/KWh i.e. 50.18 Hz

    Generating station B should not generate over schedule beyond the frequency at which UI rate is 70 aise/KWh i.e. 50.25 Hz

    Frequency (Hz) =50.1

    UI Rate (INR /Kwh)=1.6

    Variable cost of costliest operating generating station owned by the beneficairy (INR /Kwh)=

    2.4

    Gain (INR/ KWh) for drawal above schedule (by reducing generation at own costiliest station)0.8

    Conclusion:

    Beneficiary should start reducing generation at the costliest operating station (and overdraw from the grid) if variable cost of this station exceed prevailing UI Rate.

    Frequency (Hz) =49.849.5

    UI Rate (Paise /Kwh)=196280

    Variable cost of the cheapest hot standby generating resorrce owned by the beneficairy (Paise /Kwh)=

    150

    Loss (Paise/ KWh) for each unit of own generation-46

    Conclusion:

    Beneficiary should start generation at the cheapest hot standby unit at a frequency dips to a value at which UI rate becomes equal to variable cost of this unit.

    Beneficiary should start loadshedding if UI rate is high and there is no standby generating resource.

    Frequency (Hz) =49.4

    UI Rate (Paise /Kwh)=308

    Variable cost of the generating station despatched below availability or having margins295

    Gain by generating over the schedule (Paise /KWh)13

    Conclusion:

    A generating station under ABT should, if feasible, start generating above schedule if frequency dips to a level at which UI Rate is equal to its variable cost.

    Sheet2

    Sheet3

  • *How UI pricing works -Low FrequencyExample: Beneficiary

    Sheet1

    Generating Station

    AB

    Energy Charge (paise /Kwh) =9070

    Frequency(Hz) =50.250.28

    UI Rate (Paise /Kwh)=8461.6

    Earning (Paise / KWh) for over generation =-6-8.4

    Conclusion:

    Generating station A should not generate over schedule beyond the frequency at which UI rate is 90 aise/KWh i.e. 50.18 Hz

    Generating station B should not generate over schedule beyond the frequency at which UI rate is 70 aise/KWh i.e. 50.25 Hz

    Frequency (Hz) =50.1

    UI Rate (Paise /Kwh)=112

    Variable cost of costliest operating generating station owned by the beneficairy (Paise /Kwh)=

    120

    Loss (Paise/ KWh) for each unit of own generation8

    Conclusion:

    Beneficiary should start reducing generation at the costliest operating station (and overdraw from the grid) if variable cost of this station exceed prevailing UI Rate..

    Frequency (Hz) =49.949.4

    UI Rate (INR /Kwh)=2.4390

    Variable cost of the cheapest standby generating resource owned by the beneficairy (INR /Kwh)=2

    Loss (Paise/ KWh) for each unit of drawal above schedule (and not harnessing own standby generation)0.4

    Conclusion:

    The distribution licensee should start generation at the cheapest standby unit if frequency dips below the value (50 Hz in this case) at which UI rate becomes equal to variable cost of this unit.

    The distribution licensee should start loadshedding if UI rate is beyond its means and there is no standby generating resource.

    Frequency (Hz) =49.4

    UI Rate (Paise /Kwh)=308

    Variable cost of the generating station despatched below availability or having margins295

    Gain by generating over the schedule (Paise /KWh)13

    Conclusion:

    A generating station under ABT should, if feasible, start generating above schedule if frequency dips to a level at which UI Rate is equal to its variable cost.

    Sheet2

    Sheet3

  • *Changing UI Rates

    Chart1

    4.265.77.4510

    2.8564.083.543.615.68

    2.0162.882.192.192.98

    0.0560.080.060.060.08

    upto 31.03.2004

    w.e.f. 01.04.2004

    w.e.f. 01.10.2004

    w.e.f. 01.04.2007

    w.e.f. 07.01.2008

    Frequency (Hz)

    INR/kWh

    Sheet1

    HZpaisa/unit

    upto 31.03.2004w.e.f. 01.04.2004w.e.f. 01.10.2004w.e.f. 01.04.2007w.e.f. 07.01.2008

    49.024.265.77.4510

    49.52.8564.083.543.615.68

    49.82.0162.882.192.192.98

    50.50.0560.080.060.060.08

    4.265.77.4510

    2.8564.083.543.615.68

    2.0162.882.192.192.98

    0.0560.080.060.060.08

    Sheet2

    Sheet3

  • *Determination of Availability : Thermal StationsAvailability means average of daily Declared Capacities expressed as % of Installed capacity minus Normative Auxiliary ConsumptionDeclaration of capacity taking into account fuel availabilityNormative Availability 80% (exception for some specified generating stations)Availability to be certified by Member Secretary of the RPC concerned.

  • *Determination of Availability : Hydro StationsCapacity Index (CI) as measure of availabilityDaily CI = (Declared Capacity/Max available capacity)*100Declared capacity over peaking hours of next day (not less than 3 hours each day) taking into account availability of water, optimum use of water and availability of machines. Max. available capacity is the max. capacity in MW the generating station can generate with all units running, under the prevailing conditions of water levels and inflows, over the peaking hours of next day .Normative CI: 90% for Purely Run-of-river (ROR) stations and 85% for Storage and ROR stations with pondageCI to be certified by Member Secretary of the RPC concerned.

  • *Energy ChargesBased on actually implemented scheduled energyRate for thermal stations based on norms of operationRate for hydro stations equal to lowest energy charge of Central Sector thermal station in the Region

  • *Mitigation of GamingThermal Stations: up to 105% of DC in time-block and 101% of average DC over the day allowed. Generation beyond these limits to be investigated by RLDC and UI to be made zero if gaming is foundHydro Stations: Schedule prepared for Day 4 (based on DC) is adjusted by deviation from the schedule on Day 1.RLDC may ask generating station to demonstrate DCPenalty for first mis-declaration equals 2 days fixed chargesPenalty to be doubled for 2nd mis-declaration and so on and so forth.

  • *Multi-dimensional ABTA commercial mechanism for settlement of deviations from the scheduleA commercial mechanism for improving grid discipline and frequency regimeA commercial mechanism to achieve near-merit order operation A default market mechanism for trading

  • *Settlement of DeviationsAny market liberalized or regulated, needs a mechanism for balancing to take care of imbalances arising out of deviations from contracted schedules.In some markets, there is separate market for balancing.In India, UI mechanism attempts real-time balancing.

  • *Grid discipline and frequency profilePayment of Capacity Charges based on capacity available rather than energy generated - Avoidance of unwanted generationUI Charges - Load shedding/ increased generation at low frequency and reduction in generation at high frequency

  • SKA*ABT encourages grid discipline leading to better frequency profile

    SKA

  • *Merit order operation

    Strict merit order operation - if generation scheduling is done for all the generating stations in the grid by single entity (Centralized scheduling)In Indian decentralized scheduling system UI Rate encourages: Backing down of generation in decreasing order of variable cost as frequency goes up Picking up of generation in increasing order of variable cost as frequency goes down

  • *Default market for tradingUnderdrawals with respect to schedule may be viewed as supply to the grid (at UI rate) and vice-versa Similarly, under generation with respect to schedule may be viewed as drawal from the grid (at UI rate)

    . UI rate serves as default rate for trading

  • SKA*Time Line For UI SettlementSettlement weekMonday 0000 Sunday 2400Tuesday2400Meter Data download & receipt at RLDC & preliminary checksThursday 1200Data validation, processing and computation at RLDC. Forwarded to Regional Power Committee SecretariatSaturday2400Data cross checking by Regional Power Committee Secretariat & Issue of Pool Account

    Unscheduled Interchange Account Reactive Energy AccountTuesday2400Payment by utilities to the pool account managed by System Operator (RLDC)Tuesday2400Friday 2400Disbursement to utilities from the pool accountThree day grace periodFor Bank processing0.04 % per day interest on defaultersAccount Settled within 21 days Monday 2400

    SKA

  • *Settlement SystemSettlement period- 15 minutesDeclaration, scheduling and UI accounting on 15 minute basisSpecial Energy Meters - for time differentiated measurement of energyEnergy Accounting (capacity and energy charges) - on monthly basisUI accounting on weekly basisUI payments are received in a pool and payments are made from the pool

  • *LogisticsSEMs installed by CTU (POWERGRID)Meter readings downloaded and sent to RLDCs every week by staff of generating stations, POWERGRID and beneficiariesRLDCs validate and submit data to RPC Secretariat by Thursday noon for the week ending midnight of previous SundayRPC Secretariat to carry out UI charge accounting (weekly basis) and energy accounting (monthly basis)

  • SKA*01.01.200301.07.200201.04.200301.11.200301.12.2002ABT implemented in All Five Regions.POWERGRID co-ordinated and provided all infrastructure for ABT implementation.

    Pool Accounts Operated by RLDCs.

    SKA

  • *Impact of ABT Comparison of frequency profile - Full year after and before ABT

    Sheet1

    Generating Station

    AB

    Energy Charge (paise /Kwh) =9070

    Frequency(Hz) =50.250.28

    UI Rate (Paise /Kwh)=8461.6

    Earning (Paise / KWh) for over generation =-6-8.4

    Conclusion:

    Generating station A should not generate over schedule beyond the frequency at which UI rate is 90 aise/KWh i.e. 50.18 Hz

    Generating station B should not generate over schedule beyond the frequency at which UI rate is 70 aise/KWh i.e. 50.25 Hz

    Frequency (Hz) =50.1

    UI Rate (Paise /Kwh)=112

    Variable cost of costliest operating generating station owned by the beneficairy (Paise /Kwh)=

    120

    Loss (Paise/ KWh) for each unit of own generation8

    Conclusion:

    Beneficiary should start reducing generation at the costliest operating station (and overdraw from the grid) if variable cost of this station exceed prevailing UI Rate..

    Frequency (Hz) =49.849.5

    UI Rate (Paise /Kwh)=196280

    Variable cost of the cheapest hot standby generating resorrce owned by the beneficairy (Paise /Kwh)=

    150

    Loss (Paise/ KWh) for each unit of own generation-46

    Conclusion:

    Beneficiary should start generation at the cheapest hot standby unit at a frequency dips to a value at which UI rate becomes equal to variable cost of this unit.

    Beneficiary should start loadshedding if UI rate is high and there is no standby generating resource.

    Frequency (Hz) =49.4

    UI Rate (Paise /Kwh)=308

    Variable cost of the generating station despatched below availability or having margins295

    Gain by generating over the schedule (Paise /KWh)13

    Conclusion:

    A generating station under ABT should, if feasible, start generating above schedule if frequency dips to a level at which UI Rate is equal to its variable cost.

    Sheet2

    YearFrequncy RangeRegion

    NorthernWesternEastern & North-Eastern RegionSouthern

    1994-95< 49.0 Hz32.718.913.969.6

    > 50.5 Hz #14.316.722.313.5

    # > 50.2 in case of Southern Region

    1999-00< 49.0 Hz43.826.98.074.4

    > 50.5 Hz *12.820.646.54.2

    * > 51.0 Hz in case of Eastern Region

    RegionPercentage of time when frequency was

    < 49.0 Hz49.0 - 50.5 Hz> 50.5

    2001-022003-042001-022003-042001-022003-04

    Northern11.24.876.289.412.65.8100100

    Western31.42.861.689.47.02.410094.6

    Southern78.02.317.997.34.10.4100100

    2002-032003-042002-032003-042002-032003-04

    Eastern13.02.955.795.931.31.2100100

    Sheet3

  • *Impact of ABT Merit order

  • *Limitations / ConstraintsShortage conditionsRegular and timely payments to UI poolExpectation of rational behabiour from utilities and operating personnelDemand forecastingControl over generation level and demand

  • SKA*ABC of ABTScientific settlement system for contracted sale & purchase of powerHas three componentsFixed Charges or capacity chargeLinked to day-ahead declared availability / subscriptionVariable Charges or fuel chargesLinked to before the fact energy schedulesCharges for deviation from commitments

    SKA

  • SKA*

    SKA

    Base UI Status 17-23Sept-ISGS

    All India UI Summary of ISGS - Payables (+) / Receivables (-)

    For the Period 17th September To 23rd September, 2007

    UI Payables (+) / Receivables (-) (in Rs.)UI Payables (+) / Receiables (-) (Rs. in Lakhs)

    S. No.RegionName of Org.Name of ISGS

    1ERNHPCRANGIT-294081-2.94

    2ERNTPCKAHALGAON STPP-2624059-26.24

    3ERNTPCTALCHER STPP246247124.62

    4ERNTPCFARAKKA STPP-5431810-54.32

    5NERNEEPCOKOPILI-II-112096-1.12

    6NERNEEPCODOYANG HEP-135880-1.36

    7NERNEEPCOKOPILI-504892-5.05

    8NERNEEPCOKHANDONG-269087-2.69

    9NERNHPCLOKTAK-497353-4.97

    10NERNEEPCORANGANADI HEP-1595517-15.96

    11NERNEEPCOAGARTALA GAS TPP-903566-9.04

    12NERNEEPCOASSAM GAS BPP9151509.15

    13NRNHPCTANAKPUR HEP-244102-2.44

    14NRNHPCDHAULIGANGA-2059850-20.60

    15NRNHPCBAIRASIUL HEP-343793-3.44

    16NRNHPCCHAMERA HEP-II-1170785-11.71

    17NRNTPCRIHAND STPS-2588468-25.88

    18NRNHPCURI HEP-1121943-11.22

    19NRNHPCSALAL HEP-2882880-28.83

    20NRNTPCUNCHAHAR-I TPS-704690-7.05

    21NRTHDCTEHRI HEP-4851745-48.52

    22NRNTPCRIHAND-II STPS-988864-9.89

    23NRNTPCDADRI GPP925250.93

    24NRSJVNLNATHPA JHAKRI-5964496-59.64

    25NRNHPCCHAMERA HEP-2241529-22.42

    26NRNTPCANTA GPP-4129276-41.29

    27NRNTPCUNCHAHAR-II TPS-1778983-17.79

    28NRNTPCSINGRAULI STPS-6578621-65.79

    29NRNTPCAURAIYA GPP-21430659-214.31

    30NRNTPCDADRI TPS-2510866-25.11

    31SRNTPCRAMAGUN. STPS STG-III-3834859-38.35

    32SRNLCNEYVELI TPS-I (EXPN.)-664290-6.64

    33SRNLCNEYVELI TPS-II STG-I-4920041-49.20

    34SRNTPCTALCHER STPS-II-30143798-301.44

    35SRNLCNEYVELI TPS-II STG-II-3645487-36.45

    36SRNTPCRAMAGUN. STPS STG-I & II-2581587-25.82

    37WRNTPCKAWAS GPP-2280770-22.81

    38WRNTPCVINDHYACHAL STPS # 3-4160533-41.61

    39WRNTPCVINDHYACHAL STPS # 1-3342585-33.43

    40WRNTPCGANDHAR GPP262430726.24

    41WRNTPCVINDHYACHAL STPS # 2-2638244-26.38

    42WRNTPCKORBA STPS-5967277-59.67

    UI Status 17-23 Sept - ISGS

    All India UI Summary of ISGS - Payables (+) / Receivables (-)

    For the Period 17th September To 23rd September, 2007

    UI Payables (+) / Receiables (-) (Rs. in Lakhs)

    S. No.Name of Org.Name of ISGS

    1NTPCGANDHAR GPP0.262430726.24

    2NTPCTALCHER STPP0.246247124.62

    3NEEPCOASSAM GAS BPP0.0915150139.15

    4NTPCDADRI GPP0.00925250.93

    5NEEPCOKOPILI-II-0.011209558-1.12

    6NEEPCODOYANG HEP-0.013587981-1.36

    7NHPCTANAKPUR HEP-0.0244102-2.44

    8NEEPCOKHANDONG-0.026908712-2.69

    9NHPCRANGIT-0.0294081-2.94

    10NHPCBAIRASIUL HEP-0.0343793-3.44

    11NHPCLOKTAK-0.049735321-4.97

    12NEEPCOKOPILI-0.050489156-5.05

    13NLCNEYVELI TPS-I (EXPN.)-0.066429-6.64

    14NTPCUNCHAHAR-I TPS-0.070469-7.05

    15NEEPCOAGARTALA GAS TPP-0.090356627-9.04

    16NTPCRIHAND-II STPS-0.0988864-9.89

    17NHPCURI HEP-0.1121943-11.22

    18NHPCCHAMERA HEP-II-0.1170785-11.71

    19NEEPCORANGANADI HEP-0.159551718-15.96

    20NTPCUNCHAHAR-II TPS-0.1778983-17.79

    21NHPCDHAULIGANGA-0.205985-20.60

    22NHPCCHAMERA HEP-0.2241529-22.42

    23NTPCKAWAS GPP-0.228077-22.81

    24NTPCDADRI TPS-0.2510866-25.11

    25NTPCRAMAGUN. STPS STG-I & II-0.2581587-25.82

    26NTPCRIHAND STPS-0.2588468-25.88

    27NTPCKAHALGAON STPP-0.2624059-26.24

    28NTPCVINDHYACHAL STPS # 2-0.2638244-26.38

    29NHPCSALAL HEP-0.288288-28.83

    30NTPCVINDHYACHAL STPS # 1-0.3342585-33.43

    31NLCNEYVELI TPS-II STG-II-0.3645487-36.45

    32NTPCRAMAGUN. STPS STG-III-0.3834859-38.35

    33NTPCANTA GPP-0.4129276-41.29

    34NTPCVINDHYACHAL STPS # 3-0.4160533-41.61

    35THDCTEHRI HEP-0.4851745-48.52

    36NLCNEYVELI TPS-II STG-I-0.4920041-49.20

    37NTPCFARAKKA STPP-0.543181-54.32

    38SJVNLNATHPA JHAKRI-0.5964496-59.64

    39NTPCKORBA STPS-0.5967277-59.67

    40NTPCSINGRAULI STPS-0.6578621-65.79

    41NTPCAURAIYA GPP-2.1430659-214.31

    42NTPCTALCHER STPS-II-3.0143798-301.44

    NET PAYABLES (+)60.9

    NET RECEIVABLES (-)-1381.4

    SUMMARY OF RECEIVABLES (-) BY ISGS

    NAME OF ORG.NET RECEIVABLES (-) (Rs. in Lakhs)

    NTPC-1037.15949

    NHPC-108.5631621

    NEEPCO-35.2103752

    NLC-92.29818

    SJVNL-59.64496

    THDC-48.51745

    UI Status 17-23 Sept - Const

    All India UI Summary of Constituents - Payables (+) / Receivables (-)

    For the Period 17th September To 23rd September, 2007

    UI Payables (+) / Receivables (-) (in Rs.)UI Payables (+) / Receiables (-) (Rs. in Lakhs)

    S. No.RegionState

    1NRUttar Pradesh3587518293587.5235.88358751829

    2NRHaryana2532197482532.2025.32253219748

    3NRPunjab2243703642243.7022.44224370364

    4SRTamilnadu1181941671181.9411.82118194167

    5ERBihar88768650887.698.8888768650

    6WRMadhya Pradesh58466687584.675.8558466687

    7WRDadra & NH47881754478.824.7947881754

    8WRMaharashtra41245451412.454.1241245451

    9NRChandigarh16473992164.741.6516473992

    10ERJharkhand10990562109.911.1010990562

    11WRDaman & Diu971280697.130.979712806

    12ERSikkim695770469.580.706957704

    13NERNagaland519918051.990.525199180

    14NERTripura366004236.600.373660042

    15SRPondicherry171710217.170.171717102

    16NRRajasthan168253616.830.171682536

    17SRGoa-SR127961412.800.131279614

    18NRJ & K-1602152-16.02-0.16-1602152

    19NRDelhi-4080439-40.80-0.41-4080439

    20NERAr. Pradesh-4182776-41.83-0.42-4182776

    21SRKerala-12051965-120.52-1.21-12051965

    22WRChattisgarh-14505602-145.06-1.45-14505602

    23NRUttaranchal-15431377-154.31-1.54-15431377

    24NERMizoram-18165430-181.65-1.82-18165430

    25NERManipur-19517218-195.17-1.95-19517218

    26NERMeghalaya-21760457-217.60-2.18-21760457

    27WRGoa - WR-22199217-221.99-2.22-22199217

    28SRKarnataka-48948907-489.49-4.89-48948907

    29NRHP-55613441-556.13-5.56-55613441

    30NERAssam-58464292-584.64-5.85-58464292

    31ERWest Bengal-64934533-649.35-6.49-64934533

    32SRAndhra Pradesh-74199638-742.00-7.42-74199638

    33WRGujarat-81680500-816.81-8.17-81680500

    34ERDVC-111890129-1118.90-11.19-111890129

    35EROrissa-349279831-3492.80-34.93-349279831

    NET PAYABLES (+)12485.72

    NET RECEIVABLES (-)-9785.08

    RE Status 17-23Spt - Const

    All India RE Summary of Constituents - Payables (+) / Receivables (-)

    For the Period 17th September To 23rd September, 2007

    RE Payables (+) / Receivables (-) (in Rs.)RE Payables (+) / Receiables (-) (Rs. in Lakhs)

    S. No.RegionState

    1NRUttar Pradesh239383723.94

    2NRJ & K185583318.56

    3NRPunjab126876312.69

    4NRHP553300.55

    5NERAr. Pradesh144980.14

    6NERMizoram97340.10

    7NERMeghalaya38820.04

    8NERNagaland24800.02

    9NERManipur14220.01

    10WRDadra & NH00.00

    11WRDaman & Diu00.00

    12SRGoa-SR00.00

    13SRPondicherry00.00

    14NRUttaranchal00.00

    15ERWest Bengal00.00

    16ERSikkim00.00

    17ERJharkhand00.00

    18ERDVC00.00

    19EROrissa00.00

    20ERBihar00.00

    21NERTripura-800-0.01

    22WRGujarat-33768-0.34

    23NRDelhi-34230-0.34

    24NRChandigarh-37117-0.37

    25NERAssam-108495-1.08

    26NRHaryana-151841-1.52

    27WRGoa - WR-294473-2.94

    28SRKerala-871447-8.71

    29NRRajasthan-877842-8.78

    30WRMadhya Pradesh-1478458-14.78

    31WRChattisgarh-1481886-14.82

    32WRMaharashtra-2797814-27.98

    33SRKarnataka-4080431-40.80

    34SRTamilnadu-4579029-45.79

    35SRAndhra Pradesh-4836248-48.36

    NET PAYABLES (+)56.06

    NET RECEIVABLES (-)-216.64

    Chart UI Status - ISGS

    0.2624307

    0.2462471

    0.091515013

    0.0092525

    -0.011209558

    -0.013587981

    -0.0244102

    -0.026908712

    -0.0294081

    -0.0343793

    -0.049735321

    -0.050489156

    -0.066429

    -0.070469

    -0.090356627

    -0.0988864

    -0.1121943

    -0.1170785

    -0.159551718

    -0.1778983

    -0.205985

    -0.2241529

    -0.228077

    -0.2510866

    -0.2581587

    -0.2588468

    -0.2624059

    -0.2638244

    -0.288288

    -0.3342585

    -0.3645487

    -0.3834859

    -0.4129276

    -0.4160533

    -0.4851745

    -0.4920041

    -0.543181

    -0.5964496

    -0.5967277

    -0.6578621

    -2.1430659

    -3.0143798

    UI Payables (+) / Receivables (-) (in Rs.)

    UI Billing (Rs. in Crores)

    A Typical Week UI Billing For ISGS ( UI Payables(-) / Receivables (+))

    Chart UI Status - Constituents

    35.8751829

    25.3219748

    22.4370364

    11.8194167

    8.876865

    5.8466687

    4.7881754

    4.1245451

    1.6473992

    1.0990562

    0.9712806

    0.6957704

    0.519917962

    0.36600417

    0.1717102

    0.1682536

    0.1279614

    -0.1602152

    -0.4080439

    -0.418277595

    -1.2051965

    -1.4505602

    -1.5431377

    -1.816543025

    -1.951721757

    -2.176045678

    -2.2199217

    -4.8948907

    -5.5613441

    -5.846429208

    -6.4934533

    -7.4199638

    -8.16805

    -11.1890129

    -34.9279831

    UI Payables (+) / Receivables (-) (in Rs.)

    UI Billing (Rs. in Crores)

    A Typical week UI Bill-Statewise Pattern

    Chart RE Status - Constituents

    23.93837

    18.55833

    12.68763

    0.5533

    0.1449788

    0.097335

    0.0388206

    0.0248031

    0.0142191

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    -0.0079979

    -0.33768

    -0.3423

    -0.37117

    -1.0849472

    -1.51841

    -2.94473

    -8.71447

    -8.77842

    -14.78458

    -14.81886

    -27.97814

    -40.80431

    -45.79029

    -48.36248

    RE Payables (+) / Receivables (-) (in Rs.)

    RE in Rs. in Lakhs

    Statewise pattern in terms of RE Payables (+) / Receivables (-) for the week 17 Sept To 23 Sept2007

  • SKA*

    SKA

    Base UI Status 17-23Sept-ISGS

    All India UI Summary of ISGS - Payables (+) / Receivables (-)

    For the Period 17th September To 23rd September, 2007

    UI Payables (+) / Receivables (-) (in Rs.)UI Payables (+) / Receiables (-) (Rs. in Lakhs)

    S. No.RegionName of Org.Name of ISGS

    1ERNHPCRANGIT-294081-2.94

    2ERNTPCKAHALGAON STPP-2624059-26.24

    3ERNTPCTALCHER STPP246247124.62

    4ERNTPCFARAKKA STPP-5431810-54.32

    5NERNEEPCOKOPILI-II-112096-1.12

    6NERNEEPCODOYANG HEP-135880-1.36

    7NERNEEPCOKOPILI-504892-5.05

    8NERNEEPCOKHANDONG-269087-2.69

    9NERNHPCLOKTAK-497353-4.97

    10NERNEEPCORANGANADI HEP-1595517-15.96

    11NERNEEPCOAGARTALA GAS TPP-903566-9.04

    12NERNEEPCOASSAM GAS BPP9151509.15

    13NRNHPCTANAKPUR HEP-244102-2.44

    14NRNHPCDHAULIGANGA-2059850-20.60

    15NRNHPCBAIRASIUL HEP-343793-3.44

    16NRNHPCCHAMERA HEP-II-1170785-11.71

    17NRNTPCRIHAND STPS-2588468-25.88

    18NRNHPCURI HEP-1121943-11.22

    19NRNHPCSALAL HEP-2882880-28.83

    20NRNTPCUNCHAHAR-I TPS-704690-7.05

    21NRTHDCTEHRI HEP-4851745-48.52

    22NRNTPCRIHAND-II STPS-988864-9.89

    23NRNTPCDADRI GPP925250.93

    24NRSJVNLNATHPA JHAKRI-5964496-59.64

    25NRNHPCCHAMERA HEP-2241529-22.42

    26NRNTPCANTA GPP-4129276-41.29

    27NRNTPCUNCHAHAR-II TPS-1778983-17.79

    28NRNTPCSINGRAULI STPS-6578621-65.79

    29NRNTPCAURAIYA GPP-21430659-214.31

    30NRNTPCDADRI TPS-2510866-25.11

    31SRNTPCRAMAGUN. STPS STG-III-3834859-38.35

    32SRNLCNEYVELI TPS-I (EXPN.)-664290-6.64

    33SRNLCNEYVELI TPS-II STG-I-4920041-49.20

    34SRNTPCTALCHER STPS-II-30143798-301.44

    35SRNLCNEYVELI TPS-II STG-II-3645487-36.45

    36SRNTPCRAMAGUN. STPS STG-I & II-2581587-25.82

    37WRNTPCKAWAS GPP-2280770-22.81

    38WRNTPCVINDHYACHAL STPS # 3-4160533-41.61

    39WRNTPCVINDHYACHAL STPS # 1-3342585-33.43

    40WRNTPCGANDHAR GPP262430726.24

    41WRNTPCVINDHYACHAL STPS # 2-2638244-26.38

    42WRNTPCKORBA STPS-5967277-59.67

    UI Status 17-23 Sept - ISGS

    All India UI Summary of ISGS - Payables (+) / Receivables (-)

    For the Period 17th September To 23rd September, 2007

    UI Payables (+) / Receiables (-) (Rs. in Lakhs)

    S. No.Name of Org.Name of ISGS

    1NTPCTALCHER STPS-II3.0143798301.44

    2NTPCAURAIYA GPP2.1430659214.31

    3NTPCSINGRAULI STPS0.657862165.79

    4NTPCKORBA STPS0.596727759.67

    5SJVNLNATHPA JHAKRI0.596449659.64

    6NTPCFARAKKA STPP0.54318154.32

    7NLCNEYVELI TPS-II STG-I0.492004149.20

    8THDCTEHRI HEP0.485174548.52

    9NTPCVINDHYACHAL STPS # 30.416053341.61

    10NTPCANTA GPP0.412927641.29

    11NTPCRAMAGUN. STPS STG-III0.383485938.35

    12NLCNEYVELI TPS-II STG-II0.364548736.45

    13NTPCVINDHYACHAL STPS # 10.334258533.43

    14NHPCSALAL HEP0.28828828.83

    15NTPCVINDHYACHAL STPS # 20.263824426.38

    16NTPCKAHALGAON STPP0.262405926.24

    17NTPCRIHAND STPS0.258846825.88

    18NTPCRAMAGUN. STPS STG-I & II0.258158725.82

    19NTPCDADRI TPS0.251086625.11

    20NTPCKAWAS GPP0.22807722.81

    21NHPCCHAMERA HEP0.224152922.42

    22NHPCDHAULIGANGA0.20598520.60

    23NTPCUNCHAHAR-II TPS0.177898317.79

    24NEEPCORANGANADI HEP0.15955171815.96

    25NHPCCHAMERA HEP-II0.117078511.71

    26NHPCURI HEP0.112194311.22

    27NTPCRIHAND-II STPS0.09888649.89

    28NEEPCOAGARTALA GAS TPP0.0903566279.04

    29NTPCUNCHAHAR-I TPS0.0704697.05

    30NLCNEYVELI TPS-I (EXPN.)0.0664296.64

    31NEEPCOKOPILI0.0504891565.05

    32NHPCLOKTAK0.0497353214.97

    33NHPCBAIRASIUL HEP0.03437933.44

    34NHPCRANGIT0.02940812.94

    35NEEPCOKHANDONG0.0269087122.69

    36NHPCTANAKPUR HEP0.02441022.44

    37NEEPCODOYANG HEP0.0135879811.36

    38NEEPCOKOPILI-II0.0112095581.12

    39NTPCDADRI GPP-0.0092525-0.93

    40NEEPCOASSAM GAS BPP-0.091515013-9.15

    41NTPCTALCHER STPP-0.2462471-24.62

    42NTPCGANDHAR GPP-0.2624307-26.24

    NET PAYABLES (+)641.2

    NET RECEIVABLES (-)679.2

    SUMMARY OF RECEIVABLES (-) BY ISGS

    NAME OF ORG.NET RECEIVABLES (-) (Rs. in Lakhs)

    NTPC344.16291

    NHPC108.5631621

    NEEPCO26.0588739

    NLC92.29818

    SJVNL59.64496

    THDC48.51745

    UI Status 17-23 Sept - Const

    All India UI Summary of Constituents - Payables (+) / Receivables (-)

    For the Period 17th September To 23rd September, 2007

    UI Payables (+) / Receivables (-) (in Rs.)UI Payables (+) / Receiables (-) (Rs. in Lakhs)

    S. No.RegionState

    1NRUttar Pradesh3587518293587.5235.88358751829

    2NRHaryana2532197482532.2025.32253219748

    3NRPunjab2243703642243.7022.44224370364

    4SRTamilnadu1181941671181.9411.82118194167

    5ERBihar88768650887.698.8888768650

    6WRMadhya Pradesh58466687584.675.8558466687

    7WRDadra & NH47881754478.824.7947881754

    8WRMaharashtra41245451412.454.1241245451

    9NRChandigarh16473992164.741.6516473992

    10ERJharkhand10990562109.911.1010990562

    11WRDaman & Diu971280697.130.979712806

    12ERSikkim695770469.580.706957704

    13NERNagaland519918051.990.525199180

    14NERTripura366004236.600.373660042

    15SRPondicherry171710217.170.171717102

    16NRRajasthan168253616.830.171682536

    17SRGoa-SR127961412.800.131279614

    18NRJ & K-1602152-16.02-0.16-1602152

    19NRDelhi-4080439-40.80-0.41-4080439

    20NERAr. Pradesh-4182776-41.83-0.42-4182776

    21SRKerala-12051965-120.52-1.21-12051965

    22WRChattisgarh-14505602-145.06-1.45-14505602

    23NRUttaranchal-15431377-154.31-1.54-15431377

    24NERMizoram-18165430-181.65-1.82-18165430

    25NERManipur-19517218-195.17-1.95-19517218

    26NERMeghalaya-21760457-217.60-2.18-21760457

    27WRGoa - WR-22199217-221.99-2.22-22199217

    28SRKarnataka-48948907-489.49-4.89-48948907

    29NRHP-55613441-556.13-5.56-55613441

    30NERAssam-58464292-584.64-5.85-58464292

    31ERWest Bengal-64934533-649.35-6.49-64934533

    32SRAndhra Pradesh-74199638-742.00-7.42-74199638

    33WRGujarat-81680500-816.81-8.17-81680500

    34ERDVC-111890129-1118.90-11.19-111890129

    35EROrissa-349279831-3492.80-34.93-349279831

    NET PAYABLES (+)12485.72

    NET RECEIVABLES (-)-9785.08

    RE Status 17-23Spt - Const

    All India RE Summary of Constituents - Payables (+) / Receivables (-)

    For the Period 17th September To 23rd September, 2007

    RE Payables (+) / Receivables (-) (in Rs.)RE Payables (+) / Receiables (-) (Rs. in Lakhs)

    S. No.RegionState

    1NRUttar Pradesh239383723.94

    2NRJ & K185583318.56

    3NRPunjab126876312.69

    4NRHP553300.55

    5NERAr. Pradesh144980.14

    6NERMizoram97340.10

    7NERMeghalaya38820.04

    8NERNagaland24800.02

    9NERManipur14220.01

    10WRDadra & NH00.00

    11WRDaman & Diu00.00

    12SRGoa-SR00.00

    13SRPondicherry00.00

    14NRUttaranchal00.00

    15ERWest Bengal00.00

    16ERSikkim00.00

    17ERJharkhand00.00

    18ERDVC00.00

    19EROrissa00.00

    20ERBihar00.00

    21NERTripura-800-0.01

    22WRGujarat-33768-0.34

    23NRDelhi-34230-0.34

    24NRChandigarh-37117-0.37

    25NERAssam-108495-1.08

    26NRHaryana-151841-1.52

    27WRGoa - WR-294473-2.94

    28SRKerala-871447-8.71

    29NRRajasthan-877842-8.78

    30WRMadhya Pradesh-1478458-14.78

    31WRChattisgarh-1481886-14.82

    32WRMaharashtra-2797814-27.98

    33SRKarnataka-4080431-40.80

    34SRTamilnadu-4579029-45.79

    35SRAndhra Pradesh-4836248-48.36

    NET PAYABLES (+)56.06

    NET RECEIVABLES (-)-216.64

    Chart UI Status - ISGS

    3.0143798

    2.1430659

    0.6578621

    0.5967277

    0.5964496

    0.543181

    0.4920041

    0.4851745

    0.4160533

    0.4129276

    0.3834859

    0.3645487

    0.3342585

    0.288288

    0.2638244

    0.2624059

    0.2588468

    0.2581587

    0.2510866

    0.228077

    0.2241529

    0.205985

    0.1778983

    0.159551718

    0.1170785

    0.1121943

    0.0988864

    0.090356627

    0.070469

    0.066429

    0.050489156

    0.049735321

    0.0343793

    0.0294081

    0.026908712

    0.0244102

    0.013587981

    0.011209558

    -0.0092525

    -0.091515013

    -0.2462471

    -0.2624307

    UI Payables (+) / Receivables (-) (in Rs.)

    UI Billing (Rs. in Crores)

    A Typical Week UI Billing For ISGS ( UI Payables(-) / Receivables (+))

    Chart UI Status - Constituents

    35.8751829

    25.3219748

    22.4370364

    11.8194167

    8.876865

    5.8466687

    4.7881754

    4.1245451

    1.6473992

    1.0990562

    0.9712806

    0.6957704

    0.519917962

    0.36600417

    0.1717102

    0.1682536

    0.1279614

    -0.1602152

    -0.4080439

    -0.418277595

    -1.2051965

    -1.4505602

    -1.5431377

    -1.816543025

    -1.951721757

    -2.176045678

    -2.2199217

    -4.8948907

    -5.5613441

    -5.846429208

    -6.4934533

    -7.4199638

    -8.16805

    -11.1890129

    -34.9279831

    UI Payables (+) / Receivables (-) (in Rs.)

    UI Billing (Rs. in Crores)

    A Typical week UI Bill-Statewise Pattern

    Chart RE Status - Constituents

    23.93837

    18.55833

    12.68763

    0.5533

    0.1449788

    0.097335

    0.0388206

    0.0248031

    0.0142191

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    -0.0079979

    -0.33768

    -0.3423

    -0.37117

    -1.0849472

    -1.51841

    -2.94473

    -8.71447

    -8.77842

    -14.78458

    -14.81886

    -27.97814

    -40.80431

    -45.79029

    -48.36248

    RE Payables (+) / Receivables (-) (in Rs.)

    RE in Rs. in Lakhs

    Statewise pattern in terms of RE Payables (+) / Receivables (-) for the week 17 Sept To 23 Sept2007

  • SKA*The End Result .Frequency is collectively controlleddemocratically stabilizedWholesale market is workably competitive allocative efficiencyproductive efficiencyEconomic signal available for optimum utilization of resource investments in generation capacitySettlement isstreamlined dispute-free

    SKA

  • *What lies ahead?Intra-State ABTModulating UI prices according to changing situations

  • Futuristic ScenarioAdopt operating practices and commercial mechanism for stricter frequency control (when shortages are eliminated?)

    SKA*

    SKA

  • SKA*

    THANK YOU

    SKA

    **************************NRLDC*************