improving efficiency & reliability of steam turbine through r & m by: amitabh srivastava...
TRANSCRIPT
Improving Efficiency & Reliability
of
STEAM TURBINEThrough R & M
BY:AMITABH SRIVASTAVA
SR.DGM, BHEL HARDWAR
IN THE PRESENT POWER SECTOR SCENARIO
FOCUS IS ON
• ENHANCING EFFICIENCY• RELIABILITY• STRICTER POLLUTION NORMS• COST REDUCTION
RESULTING TO ENHANCED EMPHASIS ON
=> REDUCTION IN GENERATION COST
HIGH EFFICIENCY OF TG CYCLE LOWER EQUIPMENT COST SHORTER GESTATION PERIOD REDUCED MAINTENANCE TIME
=> INCREASED RELIABILITY
=> MINIMIZING ENVIRONMENTAL HAZARDS
IMPROVEMENT IN STEAM TURBINE IMPROVEMENT IN STEAM TURBINE PERFORMANCEPERFORMANCE
POSSIBLE BY1. IMPROVED BLADE PROFILE• REDUCTION IN THE AERODYNAMIC
FLOW LOSSES e.g.PROFILE LOSSSECONDARY FLOW LOSSTIP LEAKAGE LOSS
•MORE UNIFORM FLOW DISTRIBUTIONCONTD……..
IMPROVEMENT IN STEAM TURBINE IMPROVEMENT IN STEAM TURBINE PERFORMANCEPERFORMANCE
POSSIBLE BY ….contd...
2. OPTIMISED FLOWPATH
3. IMPROVEMENT IN SHAFT SEALING SYSTEM
4. REDUCTION IN PRESSURE DROPS
5. REDUCED FRICTION LOSSES
6. OPTIMISATION OF INLET & EXHAUST SECTION
7. OPTIMISED EXHAUST LOSS
DEVELOPMENT OF PROFILES FOR DEVELOPMENT OF PROFILES FOR
CYLINDRICAL TURBINE BLADESCYLINDRICAL TURBINE BLADES
T4 PROFILE HAS 1% LOWER PROFILE LOSSES COMPARED TO T2 PROFILE.
NEWLY DEVELOPED TX HAS 0.2% LOWER PROFILE LOSSES COMPARED TO T4 PROFILE.
CONSIDERATIONS IN RETROFITTING & CONSIDERATIONS IN RETROFITTING & UPGRADATION OF OLDER SETSUPGRADATION OF OLDER SETS
• COST EFFECTIVENESS• MODIFICATIONS IN TURBINE INTERNALS ONLY• INCREASE IN POWER OUTPUT WITH MINIMUM CHANGES• OUTER CASING, PIPINGS, VALVES, PEDESTAL FIXING ARRANGEMENT , STEAM PARAMETERS & FOUNDATION DETAILS REMAIN UNALTERED• SHORTEST POSSIBLE OUTAGE TIME
RETROFITTING & UPGRADATION OF OLDER RETROFITTING & UPGRADATION OF OLDER SETSSETS
PRE-REQUISITE
•IDENTIFY THE UNIT
•PRESENT LEVEL OF PERFORMANCE
•RESIDUAL LIFE ASSESSMENT STUDY OF CRITICAL COMPONENTS
•ANALYSIS OF HISTORY & OPERATING DETAILS
RETROFITTING & UPGRADATION OF OLDER RETROFITTING & UPGRADATION OF OLDER SETSSETS
MAJOR MODIFICATIONS INMAJOR MODIFICATIONS IN GUIDE & MOVING BLADEGUIDE & MOVING BLADE
(LATEST STATE OF ART (LATEST STATE OF ART PROFILE)PROFILE)
STEAM FLOWPATHSTEAM FLOWPATH ROTORS & INNER CASINGS ROTORS & INNER CASINGS
OF TURBINEOF TURBINE SHAFT SEALINGSSHAFT SEALINGS [ADVANTAGE IN HEATRATE [ADVANTAGE IN HEATRATE
/ OUTPUT CAN BE WORKED / OUTPUT CAN BE WORKED OUT ON CASE TO CASE OUT ON CASE TO CASE BASIS]BASIS]
3 DS BLADE
(HPT/IPT)
TWISTED PROFILE
BLADE (HP/IPT)
BANANA TYPE
BLADE (LPT)
EXISTING 210 MW HP TURBINE EXISTING 210 MW HP TURBINE WITH IMPULSE BLADINGWITH IMPULSE BLADING
PROPOSED NEW DESIGN WITH PROPOSED NEW DESIGN WITH LATEST STATE OF ART BLADINGLATEST STATE OF ART BLADING
210 MW STEAM TURBINE (IMPULSE DESIGN SET) HP TURBINE
EXISTINGEXISTING IMPULSE BLADING ( PRESSURE DROP
ONLY IN STATIONARY BLADES)
EFFICIENCY : 83.6 % (FOR NEW MACHINE) EFFICIENCY FOR
EXISTING CONDITION : ~ 80%
NEWNEW REACTION BLADING
( PRESSURE DROP IN STATIONARY AS WELL AS MOVING BLADES
EFFICIENCY : 86.5 %
HP TURBINE
ACTIVITIES INVOLVED
REMOVAL OF EXISTING HP ROTOR, LINERS AND DIAPHRAGMS
INSTALLATION OF NEW LINERS FITTED WITH STATIONARY BLADES AND NEW HP ROTOR
FITTING DIMENSIONS ARE TO BE MEASURED DURING PREVIOUS OVERHAUL AND LINERS ARE MACHINED ACCORDINGLY.
REMOVED HP ROTOR AND DIAPHRAGMS CAN BE USED AS SPARE FOR OTHER SETS
THE RETROFIT CAN BE DONE WITHIN NORMAL OVERHAUL PERIOD.
PAY BACK PERIOD IS LESS THAN 3 YEARS
ACTIVITIES INVOLVEDACTIVITIES INVOLVED
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1
Rated parameters
Main steam Flow 662 T/h
Main Steam Pressure 130 ata
Main Steam Temperature 535 Deg C
Hot reheat Temperature 535 Deg C
Condenser Vacuum 0.1042 ata
TG Heatrate 2062 kCal/kWh
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1
Rated parameters
Main steam Flow 662 T/h
Main Steam Pressure 130 ata
Main Steam Temperature 535 Deg C
Hot reheat Temperature 535 Deg C
Condenser Vacuum 0.1042 ata
TG Heatrate 2062 kCal/kWh
B. Expected present performance level (210 MW Original rating)
Considering deterioration due to ageingdeterioration due to ageing as per ASME-PTC-6Report 1985•Expected Power output
with 662 T/h main steam flow
and rated parameters 202.4 MW
•Expected TG Heatrate with 662 T/h main steam flow
and rated parameters 2164 kCal/kWh
B. Expected present performance level (210 MW Original rating)
Considering deterioration due to ageingdeterioration due to ageing as per ASME-PTC-6Report 1985•Expected Power output
with 662 T/h main steam flow
and rated parameters 202.4 MW
•Expected TG Heatrate with 662 T/h main steam flow
and rated parameters 2164 kCal/kWh
EXPECTED PERFORMANCE IMPROVEMENT EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING IMPULSE DESIGN SET DUE IN THE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE REFURBISHMENTTO HP TURBINE REFURBISHMENT
INCREASE IN POWER OUTPUT : 8.6 MW
IMPROVEMENT IN HEATRATE : 4% (FROM EXISTING PERFORMANCE LEVEL OF
THE SET WITH RATED STEAM PARAMETERS & THROTTLE STEAM FLOW)
BRAND NEW SET
EXPECTED PRESENT
DETERIORATED CONDITION
UPGRADED HPT
OUTPUT (MW)
210 202.4 (3.6% DECREASE)
211 (4.2% INCREASE)
HEAT RATE (KCAL/ KWh)
2062 2164 (4.9% INCREASE)
2077 (4.02% IMPROVEMENT)
EXPECTED PERFORMANCE IMPROVEMENT IN THE EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE
REFURBISHMENTREFURBISHMENT
COMPARISONCOMPARISON
GAIN WITH UPRATED HPT:
ADDITIONAL GEN. OF MU = MW X1000 X HRS.X PLF
= 8.6 X 1000 X 8000 X 0.80 = 55.04 MU
ADDITIONAL GEN. OF REVENUE @ RS 2/= PER UNIT
= 55.04 X 2 = RS 11 CR
WORK INVOLVED IN RETROFIT OF LP WORK INVOLVED IN RETROFIT OF LP TURBINETURBINE
WORK TO BE DONE AT SITE:
•CUTTING OF DEFLECTORS / RIBS & BLANKING THE SPACE IN LP CASING TO FACILITATE REMOVAL OF BAUMEN STAGE.•MODIFICATION OF STRUCTURE AT THE EXHAUST END OF LPC TO FACILITATE INSTALLATION OF DIFFUSOR.
CONTD….
• MODIFICATION OF STRUCTURE AT THE STEAM INLET END OF LPC TO FACILITATE INSTALLATION OF 1ST STAGE OF GUIDE BLADES.
WORK INVOLVED IN RETROFIT OF LP WORK INVOLVED IN RETROFIT OF LP TURBINETURBINE
WORK TO BE DONE AT SITE:
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1
Rated parameters
Main steam Flow 662 T/h
Main Steam Pressure 130 ata
Main Steam Temperature 535 Deg C
Hot reheat Temperature 535 Deg C
Condenser Vacuum 0.1042 ata
TG Heatrate 2062 kCal/kWh
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1
Rated parameters
Main steam Flow 662 T/h
Main Steam Pressure 130 ata
Main Steam Temperature 535 Deg C
Hot reheat Temperature 535 Deg C
Condenser Vacuum 0.1042 ata
TG Heatrate 2062 kCal/kWh
B. Expected present performance level (210 MW Original rating)
Considering deterioration due to ageingdeterioration due to ageing as per ASME-PTC-6Report 1985•Expected Power output
with 662 T/h main steam flow
and rated parameters 202.4 MW
•Expected TG Heatrate with 662 T/h main steam flow
and rated parameters 2164 kCal/kWh
B. Expected present performance level (210 MW Original rating)
Considering deterioration due to ageingdeterioration due to ageing as per ASME-PTC-6Report 1985•Expected Power output
with 662 T/h main steam flow
and rated parameters 202.4 MW
•Expected TG Heatrate with 662 T/h main steam flow
and rated parameters 2164 kCal/kWh
EXPECTED PERFORMANCE EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING SET IMPROVEMENT IN THE EXISTING SET
DUE TO LP TURBINE REFURBISHMENTDUE TO LP TURBINE REFURBISHMENT
INCREASE IN POWER OUTPUT : 10.1 MW
IMPROVEMENT IN HEATRATE : 102 KCAL / KWH
(FROM EXISTING PERFORMANCE LEVEL OF THE
SET WITH RATED STEAM PARAMETERS & THROTTLE STEAM FLOW)
BRAND NEW ST
EXPECTED PRESENT DETERIORATED CONDITION
UPGRADED LPT
OUTPUT (MW)
210 202.4 212.5HEAT RATE (KCAL / KWH)
2062 2164 2066
ADDITIOAL GEN (MU)
NA NA 64.64
COMPARISONCOMPARISON
COMPARISONCOMPARISON
GAIN WITH UPRATED LPT:
ADDITIONAL GEN. OF MU = MW X1000 X HRS.X PLF
= 10.1 X 1000 X 8000 X 0.80 = 64.64 MU
ADDITIONAL GEN. OF REVENUE @ RS 2/= PER UNIT
= 64.64 X 2 = RS 12.93 CR
BRAND NEW ST
EXPECTED PRESENT DETERIORATED CONDITION
UPGRADED HPT
UPGRADED LPT
UPGRADED HPT & LPT
OUTPUT (MW)
210 202.4 211 212.5 214HEAT RATE (KCAL / KWH)
2062 2164 2077 2066 2047
ADDITIOAL GEN (MU)
NA NA 55.04 64.64 74.24
COMPARISONCOMPARISON
COMPARISONCOMPARISON
GAIN WITH UPRATED HPT & LPT:
ADDITIONAL GEN. OF MU = MW X1000 X HRS.X PLF
= 11.6 X 1000 X 8000 X 0.80 = 74.74 MU
ADDITIONAL GEN. OF REVENUE @ RS 2/= PER UNIT
= 74.74 X 2 = RS 14.848 CR
EXISTING DESIGN:
HP Turbine:•HP ROTOR : WITH MOVING BLADES OF T2 PROFILE
•INNER CASING: WITH STATIONARY BLADES OF T2 PROFILE
•INLET INSERTS: WITH 580X9 MM BUTTRESS THREADS
•EXHAUST ELBOWS: WITH SERRATED GASKET.
210 MW STEAM TURBINE (REACTION DESIGN SET-KWU)
HP TURBINE
RETROFITTING 210 MW REACTION TURBINE WITH IMPROVED BLADING
IMPROVEMENTS IN PROPOSED DESIGN:
HP MODULE:
•INNER CASING & HP ROTOR WITH OPTIMISED HIGHLY EFFICIENT T4 PROFILE BLADING.
ADVANTAGE:INCREASED EFFICIENCY
IMPROVEMENTS IN PROPOSED DESIGN: (CONTD.)
HP MODULE (CONTD.):
• MODIFIED HPT INLET INSERTS WITH BUTTRESS THREADS OF SIZE 580X20 MM IN HP OUTER CASING & BREECH NUTS.
ADVANTAGE:EASE IN ASSEMBLY & DISMANTLING.
IMPROVEMENTS IN PROPOSED DESIGN: (CONTD.)
HP MODULE (CONTD.):
MODIFIED HP EXHAUST ELBOWS WHICH HAVE U-RING IN PLACE OF SERRATED GASKET.
ADVANTAGE:ENHANCED RELIABILITY.
SCOPE OF SUPPLY
FOR HP TURBINE:
•COMPLETELY ASSEMBLED HP MODULE WITH T4 PROFILE BLADING ALONGWITH MODIFIED HP INLET ASSEMBLY & HP EXHAUST ELBOWS.
210 MW STEAM TURBINE
(REACTION DESIGN SET-KWU)
IP TURBINE
RETROFITTING 210 MW REACTION TURBINE WITH IMPROVED T4 PROFILE BLADING
ADVANTAGE:IMPROVED PERFORMANCE.
SCOPE OF SUPPLY (CONTD.)
FOR IP TURBINE:
•IP INNER CASING & IP ROTOR WITH T4 PROFILE BLADING.•A SET OF HPR-IPR & IPR-LPR COUPLING BOLTS.•NECESSARY KEYS ETC.
WORK REQUIRED TO BE DONE AT SITE:
[NOT INCLUDED IN THE SCOPE OF THIS TECHNICAL OFFER]
•PERFORMANCE TESTING PRIOR & AFTER R & M.•OVERHAULING.•RLA STUDY.•COMPONENTS IDENTIFIED DURING OVERHAULING/ RLA STUDY WHICH NEED REPLACEMENT
WORK REQUIRED TO BE DONE AT SITE: (FOR HP Turbine)
•REMOVAL OF OLD HP MODULE FROM ITS
POSITION AFTER DISMANTLING OF HP
INLET INSERTS AND HP EXHAUST ELBOWS.
•OLD HP INLET ASSEMBLY (INLET INSERTS
WITH BREECH NUTS) & HP EXHAUST
ELBOWS ARE TO BE CUT FROM MS PIPES &
CRH PIPES RESPECTIVELY.
WORK REQUIRED TO BE DONE AT SITE:(CONTD.)
•INSTALLATION OF NEW IMPROVISED
HPT MODULE IN POSITION, CENTERING
& ALIGNMENT.
•WELDING OF HP INLET ASSEMBLY OF
NEW MODULE WITH MAIN STEAM PIPES.
WORK REQUIRED TO BE DONE AT SITE:(CONTD.)
•HP EXHAUST ELBOWS ARE TO BE WELDED WITH CRH STEAM PIPES.
•ASSEMBLY OF HP INLET INSERTS & HP EXHAUST ELBOWS TO BE COMPLETED.
WORK REQUIRED TO BE DONE AT SITE:FOR IP Turbine
•REMOVAL OF OLD IP ROTOR & IP INNER CASING.•INSTALLATION OF NEW IP INNER CASING & IP ROTOR WITH T4 PROFILE BLADING, ITS CENTERING & ALIGNMENT.•COMPLETION OF BOX UP OF IP Turbine.
CONDITION AFTER R & M OF HPT & IPT (UNDER RATED CONDITION):
RATED PARAMETERS:At 100% MCR condition
•MAIN STEAM FLOW : 641.3 T/HR•MS/ HRH STEAM TEMP:535/535 DEG C•MAIN STEAM PR: 150 ATA•BACK PR: 0.121 ATA
EXPECTED PRESENT PERFORMANCE:
CONSIDERING DETERIORATION DUE TO AGING AS PER ASME-PTC-6 REPORT 1985 FOR AVERAGE LIFE OF 20 YEARS, FOLLOWING WILL BE EXPECTED PERFORMANCE AT 641.3 T/HR MAIN STEAM FLOW AND RATED PARAMETERS OUTPUT: 202.3 MW HEAT RATE: 2067 KCAL/KWH
PAY BACK PERIOD
1) REDUCTION IN OH PERIOD: 25 DAYSRESULTING TO
ADDITIONAL POWER GENERATION FOR 25 DAYS
YIELDING TO
GUAREENTED MINIMUM ADDITIONAL REVENUE:= 209MW x 1000 x 25DAYS x 24HRS x 0.80PLF x 2.00RS
=RS 20.06 CRORES
PAY BACK PERIOD
2) ADDITIONAL ANNUAL REVENUE GENERATION DUE TO INCREASE IN OUTPUT & IMPROVED HEAT RATE:
= 6.7 MW x 1000 x 8000 HRS x 0.80 PLF x RS 2.00
= RS 8.576 CRORES PER YEAR
HENCE, PAY BACK PERIOD < 3 YEARS