implications of a contractor failure. implications of contract failure costs –lost revenue –poor...

17
lications of a contractor Failure

Upload: florence-mckenzie

Post on 26-Dec-2015

219 views

Category:

Documents


0 download

TRANSCRIPT

Implications of a contractor Failure

Implications of Contract Failure

Costs

– Lost Revenue

– Poor Service Delivery

– Cost and effort of ongoing risk mitigation

– Remedial activity

– Contractual Disputes

– Contract Variations

Implications of Contract Failure

Costs

– Retendering Costs – Replacement or alternative suppliers/services

– Project Delays

– Legal costs

– Lost opportunity costs

– Sunk costs – starting over

Implications of Contract Failure

Other impacts

– Impact on stakeholders

– Political fallout,

– Bad publicity

– Warranty

– Mission Critical Operations – Continuity

– Flow-on effects

Case Studies

Contract Impact Background

Speed Cameras Contract value Under $5million

Impact on stakeholders

Political fallout

Lost revenue

The organisation involved routinely ran very large tenders, so a contract of this value “got under the radar” as far as doing an appropriate financial check was concerned.

It all came to head when the accuracy of the cameras was challenged. As a result they were withdrawn and sent back to the original supplier for recalibration. The company promptly went into liquidation. Result was over $30million in lost revenue in the first month that the cameras were out of operation.

Case Studies

Contract Impact Background

Portable Buildings $20million

Retendering Costs

Project Delays

Impact on stakeholders

The preferred tenderer was a small but solid company with a strong technical bid. It also had an existing contract with the client. However, to take on the contract, the contractor would have needed to increase its capacity by well over 300% in one year.

This raised concerns over its ability to maintain the required cashflow. Our analysts embarked on detailed assessment of the cashflow. As the financial implications of taking on the tender became apparent, the tenderer withdrew its bid. This avoided entering a contract that would have failed and ensured the existing contract remained intact.

Case Studies

Contract Impact Background

Solar Hot Water System

$20million

Impact on stakeholders

Political fallout

Bad publicity

Poor Service

We reviewed the financial position of its 3 preferred tenderers, based on price. There were concerns that there might be capacity issues. A review of the 3 showed that 2 were small local businesses with no capacity to upscale.

The third was an international company with undoubted capacity. However the parent company was facing litigation in relation to serious charge of fraud and an engagement with organisation had the potential to cause embarrassment. Financial assessments of the next ranked tenderers also flushed out companies with financial issues.

Case Studies

Contract Impact Background

Supply of Granite

Under $1million

Impact on stakeholders

Political fallout

Project Delays

With the busy Xmas shopping period coming up, there was a deadline to complete the project. A financial assessment showed the lowest bidder with serious cashflow problems having overinvested in capital equipment.

Because the deadlines were so important, a higher bid was selected. The importance of that decision was shown when the lowest bidder when into liquidation, just 2 weeks after the contract was awarded. If the bid had been accepted, the supply would have been seriously delayed and the project compromised.

Case Studies

Contract Impact Background

Road Construction

$20million

Retendering Costs

Project Delays

Legal costs

Political fallout

The client was aware of potential cashflow problems, with reports that subcontractors were not being paid. We identified that the contractor had liquidity problems caused by its first ever significant trading loss in 40 years. Further investigation identified the poor credit quality of moneys owed to the contractor from a related party.

The bank had offered a nominal loan, but analysis showed this was well short of the requirement. The client chose not to enter the contract. In the event, the contractor went into liquidation and the project, which was federally funded, was saved.

Case Studies

Contract Impact Background

Software Installation

$30million

Project Delays

Legal costs

Lost opportunity costs

Sunk costs

Impact on stakeholders

The provider was heavily dependent on its parent company overseas. The parent was shown to be very marginal with severe risk issues. An aggressive acquisition strategy had left it highly vulnerable. However, the contract was signed because of the unique functionality of the product. Risk mitigation was recommended, but not fully implemented. The supplier’s position, which was being monitored, continued to deteriorate and project implementation was delayed significantly.

After 3 years of implementation there was nothing to show for it except a substantial legal bill. This could have been avoided if more attention had been paid to the initial advice.

Case Studies

Contract Impact Background

Civil Engineering & Concreting works

$24 million

Project Delays

Remedial Action

Legal Action

A fairly basic check on a preferred tenderer, (lowest price bid), failed to raise serious questions relating to the tenderer’s capacity to take on the job. The job had to be completed within 40 weeks and the contract was several times larger than the contractor’s previous year’s revenue. If a proper analysis of the finances had been undertaken, it would have identified cashflow issues. The organisation decided to proceed with the contract, with the security of a $1miilion bank guarantee.

On completion of the job, an independent inspection showed serious faults in the work requiring remedial action. The cost was estimated at $5million plus. The likely success of legal action was not considered very high and was more likely to send the contractor into liquidation. We were belatedly asked to investigate, but by then it was too late.

When to Determine Contractor Risk

•Consider Size & Dollar Value

•Consider Risk Profile

When to Determine Contractor Risk

Risk Profile:

• Term,

• Complexity

• Scope of contract

• Tendering Costs

• Difficulty and costs of retendering or finding alternate suppliers

• Political Profile

• Implications of failure or poor service delivery

• Costs

• Other issues

When to Determine Contractor Risk

Risk Profile:

• Potential Sunk Costs, what will be written off if contractor fails

• Criticality of Service

• Commitment of Resources / infrastructure

• Level of funding

• Impact on key Stakeholders

• Impact on subcontractors

Assessing Contractor Viability

• Term,• Complexity• Scope of contract• Tendering Costs• Difficulty and costs of retendering• Potential Sunk Costs• Criticality of Service• Commitment of Resources /

infrastructure• Level of funding• Political Profile• Impact on key Stakeholders• Impact on subcontractors• Implications of failure or poor

service delivery• Costs• Other issues

• Size,

• Dollar Value

HighLow

High

Financial Assessments

What needs to be determined:• Risk of Failure over term of Contract and warranty period

• Capacity to take on Contract (Sustainable Growth, Other Contract Commitments)

• Cash flow during term of contract

• Counterparty Risks

• Contract Conditions – Risk mitigation strategies & covenants

• Past Performance issues

• Match the level of assessment with the contract risk

Implications of a contractor Failure