implementation of quality management system ...m.s., department of civil engineering supervisor :...

132
IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM IN AN IRRIGATION PROJECT: A CASE STUDY A THESIS SUBMITTED TO THE GRADUATE SCHOOL OF NATURAL AND APPLIED SCIENCES OF MIDDLE EAST TECHNICAL UNIVERSITY BY N. BRKAN DEDEKL IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE IN CIVIL ENGINEERING JANUARY 2005

Upload: others

Post on 15-Aug-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM IN AN IRRIGATION PROJECT: A CASE STUDY

A THESIS SUBMITTED TO THE GRADUATE SCHOOL OF NATURAL AND APPLIED SCIENCES

OF MIDDLE EAST TECHNICAL UNIVERSITY

BY

N. B�RKAN DEDEKL�

IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR

THE DEGREE OF MASTER OF SCIENCE IN

CIVIL ENGINEERING

JANUARY 2005

Page 2: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Approval of the Graduate School of Natural and Applied Science

Prof. Dr. Canan Özgen

Director

I certify that this thesis satisfies all the requirements as a thesis for the degree of Master of Science.

Prof. Dr. Erdal Çokça Head of Department

This is to certify that we have read this thesis and that in our opinion it is fully adequate, in scope and quality, as a thesis for the degree of Master of Science.

Prof. Dr. A. Melih Yanmaz Supervisor

Examining Committee Members Prof. Dr. Talat Birgönül (METU, CE)

Prof. Dr. Melih Yanmaz (METU, CE)

Assoc. Prof. Dr. Nuri Merzi (METU, CE)

Assist. Prof. Dr. �ahnaz Ti�rek (METU, CE)

Engin Günindi, M.S. (DOLSAR)

Page 3: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

iii

I hereby declare that all information in this document has been obtained and presented in accordance with academic rules and ethical conduct. I also declare that, as required by these rules and conduct, I have fully cited and referenced all material and results that are not original to this work. Name, Last name : N. Birkan DEDEKL�

Signature :

Page 4: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

iv

ABSTRACT

IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM IN AN IRRIGATION PROJECT: A CASE STUDY

Dedekli, N. Birkan

M.S., Department of Civil Engineering

Supervisor : Prof. Dr. A.Melih Yanmaz

January 2005, 119 Pages

There is a growing tendency in the application of the quality management system to

the construction industry. Within this perspective, some quality management

standards, like ISO 9001, are utilized to assure the quality in projects. Application of

this system to water resources projects is also of importance since they are very

large systems having various components for which quality management would

improve the overall efficiency. The aim of this thesis is to examine the

implementation of the quality management in the design and construction processes

of a sample irrigation network in order to evaluate its benefits by the cost of quality,

which is assumed to be the most effective performance measure. To this end, the

prevention and appraisal costs and failure costs, which constitute the cost of quality,

are identified separately and their interactions are investigated on a case study in

which the causes of these failures are analyzed and quantified in the form of graphs.

Keywords: Quality, Quality Management, ISO 9001, Cost of Quality

Page 5: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

v

ÖZ

KAL�TE YÖNET�M S�STEM�N�N B�R SULAMA PROJES�NDE UYGULANMASI: ÖRNEK OLAY �NCELEMES�

Dedekli, N. Birkan

Yüksek Lisans, �n�aat Mühendisli�i Bölümü

Tez Yöneticisi : Prof. Dr. A. Melih Yanmaz

Ocak 2005, 119 Sayfa

Kalite yönetim sisteminin in�aat sanayinde uygulanması üzerine artan bir e�ilim

görülmektedir. Bunun neticesinde, projelerde kaliteyi temin edebilmek için ISO 9001

gibi bir takım kalite yönetim standartlarından faydalanılmaktadır. Çe�itli bile�enleri ile

çok büyük sistemlere sahip su kaynakları projelerinde bu sistemin uygulanması ise

elde edilecek verimi arttırma olana�ı sa�layaca�ından ayrı bir önem ta�ımaktadır.

Bu tezin amacı kalite yönetiminin örnek bir sulama �ebekesinin tasarım ve in�aat

a�amalarında uygulanmasını inceleyerek, getirilerini en etkili kalite ölçüm aracı

olarak kabul gören kalite maliyeti ile de�erlendirebilmektir. Bunun için kalite

maliyetini olu�turan hatayı önleme ve tesbit maliyetleri ile hatanın maliyetleri ayrı

ayrı tanımlanmı� ve bunların birbirleriyle olan ili�kileri, bu hataların analiz edildi�i ve

grafiksel olarak nicelendi�i bir örnek uygulama ile ara�tırılmı�tır.

Anahtar Kelimeler: Kalite, Kalite Yönetimi, ISO 9001, Kalite Maliyeti

Page 6: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

vi

ACKNOWLEDGEMENTS

The author wishes to express his deepest gratitude to his supervisor Prof. Dr.

A. Melih Yanmaz for his guidance, advice, criticism, encouragements and insight

througout this study.

The encouragement and comments of Mr.Gürkan Dedekli and Ms.Ye�im Ökmen are

gratefully acknowledged. Special thanks go to the parents of the author for their

encouragements.

Page 7: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

vii

TABLE OF CONTENTS

PLAGIARISM……………......................................................................................iii

ABSTRACT……………........................................................................................iv

ÖZ.……………......................................................................................................v

ACKNOWLEDGEMENTS……………...................................................................vi

TABLE OF CONTENTS.......................................................................................vii

LIST OF TABLES..................................................................................................x

LIST OF FIGURES..............................................................................................xii

LIST OF SYMBOLS AND ABBREVIATIONS…....…………………………..……xiii

CHAPTER

1 INTRODUCTION………...…………………………………….......……………..1

2 QUALITY MANAGEMENT IN CONSTRUCTION…...…………………..........4

2.1 HISTORY OF QUALITY……………………………………...……..........4

2.2 DEFINITIONS RELATED TO QUALITY…...…………………...……....5

2.3 WHY QUALITY MANAGEMENT?.......................................................8

2.4 THE STANDARD OF ISO FOR THE QUALITY MANAGEMENT……9

2.4.1 General Requirements……..……….……………………………….9

2.4.2 Developments of Quality Management Standard………...….…12

Page 8: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

viii

2.5 QUALITY CONTROL SYSTEM IN CONSTRUCTION PROJECTS..15

2.5.1 Quality System Procedure………...………………….…………...15

2.5.2 Contract Review Procedure…………………………………….....15

2.5.3 Design Control Procedure………………….……………...………16

2.5.4 Documet and Data Control Procedure………………………...…20

2.5.5 Purchasing Procedure……………………………………..………20

2.5.6 Control of Employer Supplied Product Procedure…………..….20

2.5.7 Process Control Procedure…………………………………..…...21

2.5.8 Inspection and Testing Procedure……………………...………...21

2.5.9 Control of Nonconforming Product Procedure……………..…...21

2.5.10 Corrective and Preventive Actions Procedure………...……….22

2.5.11 Handling, Storage, and Delivery Procedure……………….......22

2.5.12 Quality Records Procedure……………………………………...22

2.5.13 Internal Quality Audits Procedure……………………………….23

2.5.14 Training Procedure……………………..………………………...23

2.5.15 Calibration Procedure………………………………………...…..24

2.5.16 Maintenance Procedure…………………………………...……..24

2.5.17 Communication Procedure…………………………………...….25

2.5.18 Assessment of Supplier Procedure…………………………......25

3 COST OF QUALITY…………………………………………………………26

3.1 THE CONCEPT OF COST OF QUALITY…………..………………...26

3.2 CATEGORIES OF COST OF QUALITY……………………...……….27

3.2.1 Prevention Costs………………………………………………..….27

Page 9: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

ix

3.2.2 Appraisal Costs………………………………………..…………...28

3.2.3 Internal Failure Costs………………………...…………………….28

3.2.4 External Failure Costs……………………..………………………29

3.3 THE STUDY FOR COST OF QUALITY………………………...……..29

3.3.1 Obtaining The Cost Data……………………………………..…...31

3.3.2 Economic Model of Quality of Conformance…………..………..32

4 DESCRIPTION OF THE IRRIGATION PROJECT…………………..…….34

4.1 GENERAL CONDITIONS…………………………………………...…..34

4.2 DESIGN CRITERIA OF THE PROJECT……………………......…….38

4.3 ORGANIZATION………………………………………………………....41

5 CASE STUDY…………………………………………………………...……..43

5.1 FAILURE COSTS ANALYSIS…………………..……………………...43

5.1.1 Nonconformances at Design Activities…………..………………44

5.1.2 Nonconformances at Construction Activities……………..……..50

5.2 PREVENTION AND APPRAISAL COSTS ANALYSIS……………..63

5.3 DISCUSSION OF RESULTS…………………………………...………69

6 CONCLUSIONS……………………………………………………...………..73

REFERENCES…………………...………………………………………………75

APPENDICES: TABLES OF COST CALCULATIONS…...…………..….….77

Page 10: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

x

LIST OF TABLES

TABLES Table 4.1 Distribution of the Canalet Types ............................................................36 Table 4.2 Supplied Discharges according to the Main Canalets..............................41 Table A.1 Calculations of Monthly/ Daily Overheads in the Construction Site .........78 Table A.2 Calculations of Monthly/ Daily Overheads in the Design Office...............79 Table A.3 Cost Calculations for Design Non-Conformance 1 - (DNC-1)..................80 Table A.4 Cost Calculations of Replacing Canalets for Design Non-Conformance 2 - (DNC-2) ...............................................................................................81 Table A.5 Cost Calculations of Redesign & Delays for Design Non-Conformance 2 - (DNC-2) ...............................................................................................82 Table A.6 Cost Calculations for Design Non-Conformance 3 - (DNC-3)..................83 Table A.7 Cost Calculations for Design Non-Conformance 4 - (DNC-4)..................84 Table A.8 Cost Calculations for Design Non-Conformance 5 - (DNC-5)..................85 Table A.9 Cost Calculations for Design Non-Conformance 6 - (DNC-6)..................86 Table A.10 Cost Calculations for Design Non-Conformance 7 - (DNC-7)................87 Table A.11 Cost Calculations for Design Non-Conformance 8 - (DNC-8)................89 Table A.12 Cost Calculations for Material Non-Conformance 1 - (MNC-1)..............90 Table A.13 Cost Calculations for Material Non-Conformance 2 - (MNC-2)..............91 Table A.14 Cost Calculations for Material Non-Conformance 3 - (MNC-3)..............92 Table A.15 Cost Calculations for Material Non-Conformance 4 - (MNC-4)..............93 Table A.16 Cost Calculations for Material Non-Conformance 5 - (MNC-5)..............94 Table A.17 Cost Calculations for Material Non-Conformance 6 - (MNC-6)..............96

Table A.18 Cost Calculations of Reworks for Civil Works Non-Conformance 1 - (CNC-1) ..............................................................................................97

Page 11: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

xi

Table A.19 Cost Calculations of Delays for Civil Works Non-Conformance 1 - (CNC-1) ..............................................................................................99 Table A.20 Quantity Calculations for Civil Works Non-Conformance 2 - (CNC-2) .100 Table A.21 Cost Calculations for Civil Works Non-Conformance 2 - (CNC-2) .......101 Table A.22 Quantity Calculations for Civil Works Non-Conformance 4 - (CNC-4) .102 Table A.23 Cost Calculations for Civil Works Non-Conformance 4 - (CNC-4) .......103 Table A.24 Quantity Calculations for Civil Works Non-Conformance 5 - (CNC-5) .104 Table A.25 Cost Calculations for Civil Works Non-Conformance 5 - (CNC-5) .......105 Table A.26 Quantity Calculations for Civil Works Non-Conformance 6 - (CNC-6) .106 Table A.27 Cost Calculations for Civil Works Non-Conformance 6 - (CNC-6) .......107 Table A.28 Cost Calculations for Civil Works Non-Conformance 7 - (CNC-7) .......108 Table A.29 Cost Calculations for Civil Works Non-Conformance 8 - (CNC-8) .......109 Table A.30 Cost Calculations for Civil Works Non-Conformance 9 - (CNC-9) .......110 Table A.31 Summary of the Failure Costs ($) .......................................................112 Table A.32 Cost Calculations for Preventive Training ...........................................113 Table A.33 Cost Calculations for Preventive Maintenance....................................114 Table A.34 Cost Calculations for Calibration.........................................................115 Table A.35 Cost Calculations for Preventive Communication................................115 Table A.36 Cost Calculations for Supplier Quality Evaluation ...............................116 Table A.37 Cost Calculations for Internal Quality Audits .......................................117 Table A.38 Summary of the Prevention and Appraisal Costs ($)...........................118 Table A.39 Total Quality Costs ($) ........................................................................119

Page 12: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

xii

LIST OF FIGURES

FIGURES Figure 2.1 Plan–Do–Check–Act Methodology..........................................................6 Figure 2.2 Quality Management System Model .......................................................9 Figure 2.3 Process-based Management System to Control Quality .......................13 Figure 3.1 Cost of Quality Decision Flowchart ........................................................30 Figure 3.2 Model for Quality Costs..........................................................................32 Figure 4.1 General Layout of The Irrigation Network...............................................35 Figure 5.1 P2-Y14-1 Dividing Structure...................................................................56 Figure 5.2 Outlet Structure of The Siphon on P2-Y3 ...............................................59 Figure 5.3 Siphon on P2 Main Canalet ...................................................................60 Figure 5.4 Inlet Structure of The Chute on P2-Y5 ...................................................62 Figure 5.5 Cost versus Quality................................................................................70 Figure 5.6 Design and Construction Failure Cost versus Quality ............................71 Figure 5.7 Internal and External Failure Cost versus Quality ..................................72

Page 13: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

xiii

LIST OF SYMBOLS AND ABBREVIATIONS

Q : Canalet Capacity (lt/s)

A : Irrigable Land (ha)

F : Flexibility Coefficient

qmax : Irrigation Modulus

L : Length

Ø : Diameter

USD/ $ : United States dollar

ISO : International Organization for Standardization

n : Yearly Work Time of the Construction Equipment (hours)

N : Purchasing Price of the New Equipment

DNC : Design Non-Conformance

MNC : Material Non-Conformance

CNC : Civil Works Non-Conformance

HDPE : High Density Polyethylene

PDCA : Plan-Do-Check-Act

TQC : Total Quality Costs

QCC : Quality Control Costs

FC : Failure Costs

IFC : Internal Failure Costs

EFC : External Failure Costs

PC : Prevention Costs

AC : Appraisal Costs

Page 14: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

1

CHAPTER 1

INTRODUCTION

A survey conducted on quality of construction by the International Federation of

Consulting Engineers (FIDIC, 2004) within member associations confirmed that

failure to achieve appropriate quality of construction is a problem worldwide. The

pressure to reduce the initial costs of construction and supervision were found to

have an adverse effect on quality. The problem is serious and is evident in both

developed and developing countries. For example, Construction Industry Institute

(CII, 1989) stated that deficiency in maintaining quality costed the U.S. construction

industry over $15 billion annually in rework expenses alone. Additional costs for

other quality failures may bring the total cost to more than twice that amount.

Lack of quality in construction is manifested in poor or non-sustainable

workmanship, unsafe structures, delays in construction, cost overruns, and disputes

in construction contracts.

It is believed that construction should be sustainable, and each organization in the

construction process should satisfy the obligations in respect to achieving quality of

construction. Therefore, adopting a quality management approach towards projects

and construction is of importance for the construction industry and its parties.

According to the Executive Committee of FIDIC (2004), the necessary actions to be

taken by these parties are:

• to recognise the importance of quality of construction;

• to adopt quality management systems;

• to provide procedures for corrective action when quality control and /or acceptance criteria are not met;

• to provide feedback to the other parties (consultants, contractors, designers, clients, etc.) for improvement of quality of construction;

• to recruit, train, and assign a skilled work force;

• to take measures to ensure that subcontractors are qualified, and/or licensed as required.

Page 15: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

2

To solve the problem, the construction industry embraced the ISO 9001 (ISO, 2000),

Quality Management Standard of the International Organization for Standardization.

The Quality Management Standard has become the benchmark for successful

construction companies. The discipline and systematic approach helped many

companies to structure their management and processes to consistently meet the

client’s requirements.

After the related literature on the quality management implementation over an

irrigation project was reviewed, it became evident that the contractor had net

benefits as cost and time dependent and improved its performance for the further

construction projects. Thus, the major objectives of this study are to investigate the

effects of quality management over a sample irrigation project and to obtain a

relationship for quality costs.

In Chapter 2, the quality concept and related definitions to quality are examined in

the view of quality management standard. As a quality management standard, the

world’s most popular standard of International Organization for Standardization, ISO

9001, is utilized. The general principles are explained by giving application aspects

in construction industry.

The concept of quality cost is introduced in Chapter 3. The categories and examples

of typical subcategories of quality cost are discussed. The distribution of quality

costs over the major categories is further explored using a model, developed by the

primary authorities of quality management, such as Juran and Gryna (1988) and

Besterfield (2004). The main elements of the model are given by defining the

nonconformance and conformance items to the requirements. The approaches,

used for collecting data in the cost study, are presented for the construction of the

model.

Chapter 4 describes the characteristics and scope of the irrigation project used in

the case study. The general conditions of the project and the contract, made

between the contractor and the employer, are summarized. The constructional

details and the design criteria of the project used in the hydraulic calculations are

demonstrated to give the reader a view over the project. The organization

Page 16: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

3

undertaking the design and construction activities is introduced with the

assignments of responsibilities in the quality management system.

The quality cost concept in the irrigation project is studied as a case study in

Chapter 5. Being a design-and-construct project, the nonconformances are

examined in both processes. The costs and expenses of these nonconformances

are calculated and evaluated as failure costs of the model. The preventive and

appraisal activities are mentioned to carry out the requirements of quality

management system, supported by the related procedures of the standard. The

costs of these activities are also evaluated to complete the model. By getting the

total quality costs, the model is obtained to demonstrate the benefits of the quality

management, including the economic conformance level.

Chapter 6 presents the conclusions and recommendations for future studies. In this

chapter, quality management is indicated one of the most important parts of the

construction industry. The idea of “construction costs increase as activities related to

quality assurance increase” is pointed at a common misleading evaluation. The

importance of the quality improvement in the quality control activities is highlighted

and a methodology, developed by Deming (1986) called as PDCA, is proposed to

improve the quality in the construction industry.

Page 17: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

4

CHAPTER 2

QUALITY MANAGEMENT IN CONSTRUCTION

2.1 HISTORY OF QUALITY

The concept of quality of goods or services is not new for human being. Throughout

the history, society has demanded that providers of goods or services should meet

their obligations. Dated back to 1780 BC, King Hammurabi of Babylon introduced

the concept of product quality and liability into the building industry of the time by

declaring (Horne, 1998):

“………if a builder build a house for some one, and does not construct it properly,

and the house which he built fall in and kill its owner, then that builder shall be put to

death. If it kill the son of the owner the son of that builder shall be put to death.“

During the middle ages many of the guilds of craftsmen were established to

guarantee the quality of workmanship and to define the standards to be expected by

the purchaser. During the industrial revolution, many of the technological advances,

such as development of the steam engine, were made possible through

developments in metrology and the standardization of engineering components,

such as screw threads.

The advent of mass production during the twentieth century increased the demands

on the control of product quality. During the 1940s and 1950s, the techniques of

quality control became an increasingly important aspect of business management

as organizations sought to gain competitive advantage and reduced costs through

the inspection of product quality. The success of Japanese manufacturers during the

1960s and 1970s changed the emphasis from a quality control approach to a quality

assurance approach requiring more of the business functions to be involved in the

management of quality and requiring longer implementation timescales. Finally the

fierce international competition for goods and services during the 1980s and 1990s

has led to a “total” approach to quality management whereby everyone in

Page 18: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

5

organization is involved in developing an improvement and prevention orientation

which focuses upon the employer through teamwork.

2.2 DEFINITIONS RELATED TO QUALITY

Quality can be defined as the totality of features and characteristic of a service or

material that bear on its ability to meet the stated or implied needs and expectations

of a product and/or project at the right time and at the first time. A brief definition for

quality can be given also as conformance to requirements.

Quality management is the process required to ensure a project that will satisfy the

needs and objectives for which it was undertaken, consisting of planning,

assurance, control, and improvement of quality. It uses a systematic set of activities

to ensure that processes create products with maximum quality at minimum cost.

Quality control is the managerial process during which actual process performance

is evaluated and actions are taken on unusual performance. It is a process to

ensure whether a product meets predefined standards and requisite action taken if

the standards are not met. Quality control measures both products and processes

for conformance to quality requirements (including both the specific requirements

prescribed by the product specification, and the more general requirements

prescribed by quality assurance); identifies acceptable limits for significant quality

attributes; identifies whether products and processes fall within those limits (conform

to requirements) or fall outside them (exhibit defects); and reports accordingly.

Quality assurance is a planned and systematic set of activities to ensure that

variances in processes are clearly identified, assessed and improving defined

processes for fullfilling the requirements of employers and product or service

makers.

Quality improvement is a systematic and continuous activity to improve all

processes and systems in the organization to achieve optimal level of performance.

The Deming Cycle (Deming, 1986) is especially useful in improving the quality. This

cycle denotes continuous improvement by repeating the basic cycle of planning,

Page 19: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

6

doing, checking, and acting and is also known as Plan-Do-Check-Act (PDCA)

Methodology.

The methodology as illustrated in Figure 2.1 proposes that first, one has to plan the

process improvement approach, then perform planned work, check whether the

improvements are working, and then act to modify the process based on the lessons

learned. These steps are repeated until the desired results are achieved. PDCA is a

part of the overall quality management system and also the ISO 9001 (2000)

Standard refers to the PDCA methodology as the means for implementing all

required processes from the high-level strategic processes to the product realization

and other quality management system processes.

Mutafelija and Stromberg (2003) give the four major steps of the PDCA as follows:

Plan: Identify the failure by:

• selecting failures to be analyzed and establishing a precise failure statement;

• setting measurable goals for the problem solving effort.

Analyzing the failure by:

• identifying the processes that impact the failure and select one;

• identifying potential cause of the failure;

• collecting and analyzing data related to the failure;

• identifying root cause of the problem.

ACT PLAN

DO CHECK

Figure 2.1 - Plan–Do–Check–Act Methodology (Deming, 1986)

Page 20: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

7

Do: Develop solutions by:

• establishing criteria for selecting a solution;

• generating potential solutions that address the root cause of the failure;

• selecting a solution and planning the solution implementation.

Implementing a solution by:

• implementing the chosen solution on a trial or pilot basis.

Check: Evaluate the results by:

• gathering data on the solution;

• analyzing data on the solution.

Act: Determine next steps by:

• repeating the PDCA Cycle, if the desired goal was not achieved;

• identifying systematic changes needed for full implementation, if the goal was

achieved;

• adopting the solution and monitoring the results;

• looking for the next improvement opportunity.

Quality system is the organizational structure, responsibilities, procedures,

processes, and resources for implementing quality management. Beecroft (2001)

indicates that the emergence of the quality system-based approach to the

management of quality led to the need for a generalized standard for assessing

such quality systems which provided:

• a general framework for assessing an organization’s quality system

• a structure that is applicable to all organizations, from production to service, from

large to small

• an independently verifiable, internationally accepted systems checklist.

The process mentioned herein means one event or succession of events in which

people, tools, material, and/or enviroment act in concert to perform an operation.

The processes can be grouped as main processes and subprocesses. For example,

design stage is a main process whereas surveying activities are subprocesses. In

this study, the word of process is used for each of the activities, like surveying,

Page 21: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

8

concreting, installation of structural units, incoming material verification, delivery,

etc.

2.3 WHY QUALITY MANAGEMENT?

In many companies the top priority before 1980’s was not on quality, but it was on

cost, benefits or other parameters. Then, the emerging forces required raising the

priority given to quality, which are global competition, technological change, social

forces, and work ethic. So, managerial decisions must give equal considerations to

quality as well as to aspects of others.

Assuming these companies are looking for the basic ability to meet the employer

demands and the global world requirements, the quality management seems to fit

the need for qualification of companies.

Quality management seems to be based on the idea of inspecting the production

processes and the workers, instead of the product itself.

The most important benefit of quality management is driving continuous

improvement and contributes to improvement in profit through better efficiency and

waste reduction. Also, there are other considerable benefits of the quality

management given by CIF (2004), Construction Industry Federation, like;

• consistent and effective control of key processes and project management • promotion and standardisation of good working practices • provision of a vehicle for training new employees • effective management of risk and reducing crisis management • more effective data analysis, generation of key performance metrics and

continual improvement objectives • greater emphasis on communication, leadership, change management and

adequacy of training • a planning and review process which will ensure that the system in place

remains suitable , effective and capable of identifying new opportunities • effective remote site management, accountability and contractual control

Page 22: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

9

• promoting control of suppliers and subcontractors and the development of effective supply chain management

• world-wide recognition.

2.4 THE STANDARD OF ISO FOR THE QUALITY MANAGEMENT (ISO 9001)

2.4.1 General Requirements

In the following sections, five essential parts of ISO 9001 Standard are presented. In

December 2000, a revised version of the ISO 9001 Standard was issued after

several years of worldwide rewrites, ballots, and approvals. The standard is based

on a set of quality management principles, like employer focus, involvement of

people, process approach, and continual improvement. No single principle will

ensure the success. On the basis of these principles, the standard covers the

minimum requirements in five parts to implement the quality management, which are

presented and discussed in the following sections. These requirements must all be

satisified in a cooperation to get the benefits of the standard as shown in Figure 2.2.

The figure also reveals the importance of the employer focus for an effective quality

management (Pereda, 2000).

Figure 2.2- Quality Management System Model (Pereda, 2000)

Voice of the

Employer

Product Realization

Management responsibility

Resource Management

Measurement, analysis and improvement

Requirements Product

Employer Satisfaction

Page 23: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

10

Quality Management System (QMS): ISO defines the QMS as a set of interrelated

and interacting processes. Section 4 of the Standard contains the essential

requirements for establishing, documenting, implementing, maintaining and

continually improving (revising) the QMS. The QMS is documented by the following

means:

• publishing a quality manual;

• specifying a quality policy and quality objectives;

• developing and documenting the procedures required by the standard;

• developing and controlling the documentation necessary to plan, check, and

manage the organization processes;

• collecting records required by the Standard.

The extent of the QMS documentation depends on the size of the organization,

complexity and interactions of the processes, which must be also documented. After

the processes are defined and documented, they must be implemented. In some

cases, a process already exists in the organization has to be captured and

documented. Invariably, however, some aspects of some processes will not yet

have been implemented, such as measurement, collection, and analysis. For such

processes to be effective, staff will require training to understand what is needed to

develop and implement the missing steps, to collect records, and to make necessary

corrections upon analysis of the data.

Management Responsibility: Section 5 of the standard addresses management

responsibility, particularly the responsibility of top management. The publication and

implementation of the QMS is an important strategic decision. The commitment to

the issue and following this document is the responsibility of top management.

According to Mutafelija and Stromberg (2003), the top management is required to

show evidence of its commitment by:

• communicating the importance of meeting employer requirements;

• establishing the quality policy and quality objectives;

• conducting reviews;

• ensuring availability of resources.

Page 24: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

11

In addition, top management is expected to accomplish the following goals:

• provide employer focus;

• plan the QMS, based on the quality policy and objectives;

• ensure that responsibilities and authorities are defined and communicated

through the organization;

• name a quality manager as representative with the responsibility for

establishing, implementing and maintaining the QMS.

Resource Management: Section 6 of the ISO 9001 addresses resource

management. Without resources, organizational goals and objectives cannot be

achieved. Resources can be identified in several forms, such as materials,

equipment, supplies, staff or financial. Projects then use the resources, as required,

to develop their products.

Product Realization: Product realization is the largest and seventh section of the

standard, ISO 9001 (2000), requiring the specification of processes that transform

employer requirements into products. The section includes the following

subsections:

• Planning of product realization

• Determination and review of requirements related to the product

• Employer communication

• The planning, inputs, outputs, review, verification, and validation of design and

development

• Control of design and development changes

• Purchasing process and information

• Verification of purchased product

• Control of production and service provision

• Validation of processes for production and service provision

• Identification and traceability

• Preservation of product

• Control of monitoring and measuring devices

Page 25: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

12

Measurement, Analysis, and Improvement: Measurement is a key element of

successful management in every well-established engineering discipline. ISO 9001

has requirements for planning and implementing measurement, analysis, and

improvement processes throughout the QMS. Through measurement and analysis,

one can quantitatively determine the status of a process, detect changes in its

performance, and then implement corrective actions as necessary. Although the

standard does not prescribe the analysis techniques, statistical methods provide

effective tools.

2.4.2 Developments of Quality Management Standard

For structuring, construction, implementation, and monitoring the quality

management system, the organization shall form the following documents:

1- Quality Manual

2- Procedures

3- Job Instructions

4- Quality Records (like plans, checklists, reports, tables, etc.)

Quality Manual: Quality manual covers the extent of the quality management system

and includes the items of the quality standard. It refers to the content of the

procedures. It is a more general document and defines also the concept of quality

and its elements. However, one of the most important features of the manual is to

cover the organization scheme. So, to build an effective organization is very

important to get performance at a construction site.

Procedures: Procedures are the formal plans, which include the way of processing

and controling a working order. Procedures define the general requirements of the

quality management system to work in coordination and cooperation between the

organizational functions as shown in Figure 2.3. In a process-based management

system, these efforts will satisfy the control of quality. They facilitate also a good

overview of the quality system’s compatibility with the standard. However, a clear

understanding of the main processes of the company is required, since this will not

be evident from the element-oriented structure of the system.

Page 26: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

13

Figure 2.3- Process-based Management System to Control Quality (Tropp, 2004)

In common, the fundamental procedures are established based on the 20 quality

elements of the ISO 9001, which are as follows (Kehoe, 1996):

1- Management Responsibility

2- Quality System

3- Contract Review

4- Design Control

5- Document and Data Control

6- Purchasing

7- Control of Employer Supplied Product

8- Product Identification and Traceability

9- Process Control

10- Inspection and Testing

11- Control of Inspection, Measuring and Test Equipment

12- Inspection and Test Status

13- Control of Non-Conforming Product

14- Corrective and Preventive Actions

15- Handling, Storage, Packaging, and Delivery

16- Quality Records

Process Control

Training Quality Audits

Management Responsibility

Corrective and Prevention

Actions

Quality Management

System Design and Production

Employer Feedback

Strategic Direction

Quality Policies

ISO 9001 Requirements

Page 27: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

14

17- Internal Quality Audits

18- Training

19- Servicing

20- Statistical Techniques

Any of the elements not relevant to the individual organization should be left out.

Each of the elements might have standard sub-elements, utilized as a supporting

procedure. Some of the supporting procedures are suggested as below:

1- Calibration

2- Maintenance

3- Communication

4- Assessment of Supplier (including Sub-Contractor)

5- Health and Safety

The purposes of all the procedures are to increase the productivity, and hence to

reduce the costs by providing the quality control. All of the procedures have

interaction in between. This study also demonstrates this interaction and discusses

the benefits over an irrigation project.

Job Instructions: The job instructions direct the staff in a single activity and are

subordinate documents to procedures. They are required for specific tasks,

processes or operations, test and/or inspection activities. In such cases the job

instructions become an extension of the technical specification. They clarify “what,

who, how, when and in which frequency” to fulfill and/or control a task or process.

They are written in imperative mood.

Quality Records: The quality records include plans, forms, checklists, reports,

tables, technical, statutory and legal documents, specifications, codes of practice

and all other documents which will demonstrate the achievement of the quality

system requirements. Records provide the factual information needed for internal

audits, statistical quality control, fixing the nonconformances, planning and following

the preventive and corrective actions, like maintenance, calibration, training, etc.

Page 28: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

15

2.5 QUALITY CONTROL SYSTEM IN CONSTRUCTION PROJECTS

The methods developed for control of work in the construction industry are uniquely

correlated with the types of work and construction materials involved. As compared

with the control of the production of products in the mass-production industry, when

some hundreds to many tens of thousands of a product item are to be

manufactured, there is need to control work when only one item is to be constructed.

When only one or a few items of a given type are to be designed and constructed,

like in the construction industry, there is need for a uniquely different assembly of

control methods. So, the project-type management control of work is complex in the

construction industry when major capital works, such as dams, tunnels, power-

generating stations, irrigation networks, bridges and harbors must be designed,

constructed and commissioned.

In construction works control must emanate from the senior manager to whom the

designer, supplier and quality assurance people report, with the designer providing

technical guidance throughout. It is the duty of the quality activity to provide the

quality systems by which the project work can be successfully completed. The

procedure sets given below forth the areas of control needed in projects.

2.5.1 Quality System Procedure

This element basically requires that the quality system should be documented in

terms of policies, procedures, and instructions. Emphasis is placed on problem

prevention, rather than detection, in all activities from purchasing through installation

and servicing after delivery. For an effective quality system, written job instructions

are required. The instructions also describe where the results of the control should

be recorded.

2.5.2 Contract Review Procedure

A review of the contracts or purchase orders is required by the standard. The

contractor shall be sure that the requirements of the employer are clearly

understood before a design, civil work or a construction material will be supplied. If

there is any doubt about the requirements, clarification should be made before the

Page 29: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

16

processes begin. Also, the organization shall be reviewed of the contract for the

capability to meet the requirements. Capability to meet the requirements means not

only having the material and equipment to perform the necessary operations but

also the technology, qualified employees, and the ability to deliver on time.

2.5.3 Design Control Procedure

The control of design requires that the design process should be documented and

correctly planned and both the design inputs (employer specifications, contract,

standards, enviromental conditions, etc.) and the design outputs (drawings, details,

type of the materials, instructions, tables, etc.) should be formally documented by

the design organization. The outputs are the technical documents that will be used

throughout the production and installation processes. The organization shall review

the designs to ensure that the outputs meet the input requirements and that any

changes to the designs are properly controlled. All design changes require written

employer approval. Also there should be a periodic reevaluation of the constructed

structure in order to ensure that the design is still valid.

The critical aspects in the design of a civil work are described below for the main

three stage of the design process as design input, design and design output stages.

Design Input Stage: The design input stage is to refine the employer requirements

into design specifications and create the documentation needed for the later stages.

It should be noted first that while the employer requirements may be qualitative and

macroscopic in a contract, the design specification must include these requirements

as quantitative and microscopic. For instance, while the employer needs

compressing a flow from one pressure to another pressure, design engineer

determines to create a ruled surface centrifugal impeller with an optimum diameter

and rotational speed and resulting stresses. The degree of details and length of the

design specification varies widely between organizations and requirements.

The design input stage is essential for attaining quality in design. In spite of the

effort spent in achieving a stable design input document, revisions may be required

and must be controlled.

Page 30: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

17

In particular, the quality standard states that the design input documentation is to

identify and evaluate applicable statutory and regulatory requirements, e.g.

expropriation. Depending on the kind of construction, there could be a checklist of

possible standards and government regulations. Also, the standard states that the

design input documentation must be reviewed for adequacy. Thus, an approval

signature is added to the document by a person given the responsibility for

reviewing the documentation.

To approve the design specification documentation, Schoonmaker (1997) proposes

a number of questions which should be covered. The following are sample

questions:

1. Is the schedule realistic?

2. Are adequate resources available?

3. Are the design specifications complete and are they unambiguous?

After all the questions posed above been adequately addressed, there would be an

Input Review Meeting according to communication procedure. At this meeting, all

the management personnel responsible for approving the design specification would

meet and review the design specification and decide if the design specificaiton is

acceptable. If problems are determined at this point, corrective action should be

initiated like explained in the corrective action procedure.

As a conclusion, the documents of design input stage translate the employer’s

requirements into specific design parameters. This stage needs to be given proper

attention, since changes in the design specification at the design stage will bring

negative effect, e.g. loss of time, additional cost due to rework.

Design Stage: The design stage is where the product is actually designed or

invented. The standard emphasizes that if the design stage fails, all other processes

are going to fail, and employer needs simply cannot be fulfilled.

In a practical sense, the design activity almost always involves a trial-and-error

activity. The designer proposes a real solution to the problem posed by the design

input documentation. This proposed solution is generally to be based on the

Page 31: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

18

designer’s previous experiences. The proposed solution is then tested in a variety of

ways, like by making theoretical calculations, empirical calculations, field experience

or laboratory works. In each of these cases, the designer is searching for a reason

the design is feasible or not feasible. If the proposed solution withstands the reviews

and the tests, then it may be taken to a prototype stage.

Each of the trials, solutions, and also difficulties present an opportunity to learn and

expand the knowledge base of the organization. If these investigations are properly

documented, then they can be referenced for future efforts. Also, for the quality

standard, this documentation can be used to demonstrate an appropriate level of

control over the design stage. There are a number of sample documents for

containing this knowledge, such as design files, engineering standards, verification

studies and engineering test reports. The quality standard gives high attention these

types of documents during developments.

The balance between control and innovation may be assisted by the use of

engineering standards. These design standards are developed standards for guiding

the design process. Engineering standards are certainly valuable in the context of

the quality standard. The organization must keep a catalog of all the engineering

standards and they must take care to show that they are controlled documents. An

engineering standard should include the revision level of the standard, the date of

issue of the standard, and the name of the person and/or organization who issued

the latest revision. However, a signed approval form for an engineering standard

does not necessarily mean that the methods and formulas it employs are any more

likely to be valid models of the physical universe. At this point, design stage shifts to

a design verification, which is a part of design stage for an ISO 9001 process. In a

verificaiton study of an engineering standard, there should be oppurtunities to make

alternative calculations for the methods in the standard. There are often a variety of

methods for calculating the same parameters. The sets of results should then be

compared and discussed. In some cases, statistical methods would be applied to

consider the results.

Assuming the verification study is controlled and considered a quality record

according to quality records procedure, the engineering and design organization

should have no difficulty with demonstrated proper use of the design verification

Page 32: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

19

activity. Also, there are some other means to be discussed for design verification,

like comparison with existing works, used the same standards, undertaking tests in

laboratory, etc.

The ISO 9001 design process also required a design review activity, must be

included in the design stage. For the specific project being designed, this design

review needs to compare the design input documentation with the current state of

the design. The design review activity can take place at a meeting of the

organization. Some of the participants of this meeting to consider are the design

engineers, engineers responsible for testing, and safety engineers. The basic task of

this review meeting is to verify that the design meets the requirements of the design

specification.

For safety requirements, for example, the representatives at the design review must

be proactive. They need to imagine “what if” scenarios with the design. Then they

should consider the effects of these scenarios, and whether the design needs to be

changed to prevent injury or damage loss by the help of Health and Safety

Procedure. Minimizing the injury and damage loos means fewer stops during the

construction works and brings productivity. Theoretically it should be much easier to

alter the basic design at this design stage than to wait for the end of the design

output stage.

As a conclusion, design stage is going to determine the characteristics of the

project. The concept, materials, geometry, and dimensions of the project are critical

to the success of the project or its ability to satisfy the employer.

Design Output Stage: In an ISO 9001 design process, a separate Design Output

Stage is considered to handle the development and creation of the drawings and

other documents for construction. It is focused on preparing all the documentation

for release to the construction enviroment with all necesarry details.

If the final documentation is being prepared in the design stage where the basic

design can be still changing, then there may be a great deal of rework and time loss.

So, one of the necessity of the design output stage is to eliminate this lost effort for

revisions and reapproving the changes.

Page 33: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

20

2.5.4 Document and Data Control Procedure

The documents, which form part of the quality system (procedures, drawings,

specifications, instructions, etc.) should be controlled and approved. Therefore, the

system documents should include who has approved the document, the date of

approval, and the current level of revision, if any. The purpose of document control

is to ensure that current issues of documents are supplied to everyone in the

organization who needs to use it. Likewise, changes to documents must be

reviewed and approved by the same method.

2.5.5 Purchasing Procedure

Purchasing activities cover two categories of work done under contract. These

include the purchase of the construction materials from the suppliers and the

subcontracting of the work by the service supplier, which may or may not include the

supply of the materials.

In both case, the supplier shall review and approve purchase order documents or

contract for adequacy of specified requirements prior to release. These documents

shall contain, for the materials or services, the applicable specifications, drawings,

quality levels required, inspection or test methods to be used, characteristics to be

supplied and limits to be met, quantity to be supplied, and all other pertinent data

needed to assure the quality of incoming materials or services.

The supplier contracts shall clearly communicate all requirements for labeling,

packing, shipping, delivering, installing, and the name of the standard to be applied

to the material. Expecting use of a quality program by the supplier will strengthen

and facilitate the condition of the organization in quality control.

2.5.6 Control of Employer Supplied Product

The procedure is used where the employer supplies construction materials for use

on the project and those items can not be satisfactorily inspected to assure their

quality as delivered to the contractor. Thus, the organization of the contractor shall

(Taylor, 1989):

Page 34: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

21

• examine all such materials upon receipt for completeness, proper type, and any

evidence of transit damage;

• control all employer-supplied items, preserve them from damage, and use them

in accordance with the contract and the needs of the project;

• on a timely basis, report to the employer any evidence of damage or

nonconformity.

2.5.7 Process Control Procedure

The organization shall identify and plan the works for construction and, where

applicable, installation processes which directly affect the quality and shall ensure

that these processes are caried out under controlled conditions. Stebbing (1993)

describes the controlled conditions which include the followings:

• Documented job instructions, which define the tasks at the installation. The

instructions shall explain the appropriate way of the jobs, type of the installation

equipment, suitable working environment, and reference standards/codes.

• Monitoring and control of the conformance of the process and material

characteristics during construction.

• Implement controls to prevent the use of items of an unknown quality until the

items have been inspected or tested and the results are known.

• Use only fully qualified and experienced personnel to carry them out by which to

assure that the processes are yielding satisfactory conformance.

2.5.8 Inspection and Testing Procedure

The organization shall ensure that incoming material is not used or processed until it

has been inspected or verified as conforming to the requirements. It is required also

to define the responsibility, authority and the interrelation of all personnel, who

manage, perform, and verify the works affecting quality.

2.5.9 Control of Nonconforming Product Procedure

Material or service, which does not conform to requirements, shall be identified and

controlled to prevent its unintended use or delivery. Control shall provide for

Page 35: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

22

recording, evaluation, segregation, and disposition of nonconforming material.

Records of the nature of nonconformities and any subsequent actions taken shall be

maintained. The nonconforming material or the service shall be corrected and

reverified by taking the appropriate actions, such as reworking to meet the specified

requirements, accepting with or without repair by concession, regrading for

alternative applications and rejecting and/or scrapping.

2.5.10 Corrective and Preventive Actions Procedure

The organization shall take corrective actions appropriate to the effects of the

nonconformances in order to eliminate the cause of the nonconformances and

prevent reoccurrence. For this purpose, the organization shall review

nonconfomances (including employer complaints), determine their causes,

determine and implement needed actions and record the results of actions taken.

The same procedure shall be applied for the potential nonconformances as

preventive actions relating to the job conditions. The potential nonconformances can

be found by brainstorming, “what if” scenarios or experiences. Preventive action is

taken to prevent occurence while corrective action is taken to prevent reoccurence.

2.5.11 Handling, Storage, and Delivery Procedure

The organization shall prepare documents and establish a program for handling,

transporting, stacking, storing, preserving, and segregating all construction materials

as necessary to safeguard quality characteristics and prevent the commingling of

nonconforming materials with conforming materials. It should also be provided

secure storage areas or stock rooms to prevent damage or deterioration of the

material and inspections of the materials held in stock for condition and shelf life

expiry. The supplier shall arrange for the protection of the quality of the material until

the final inspection and test and this protection shall be extended to include delivery

to destination.

2.5.12 Quality Records Procedure

The company shall maintain records that objectively demonstrate that the quality

system is effective. To this effect the results of measurements, which objectively

Page 36: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

23

show conformance with requirements of materials or services, shall be retained and

each such record should include the date of the inspection or test, the identity of the

inspector, evidence of any nonconformance, and evidence of the resulted corrective

action from discovery of nonconformances. Quality records shall be available to the

quality auditor and the employer for analysis and review.

2.5.13 Internal Quality Audits Procedure

After the policies, procedures and job instructions have been developed and

implemented, checks must be made to ensure that the system is being followed and

the expected results are being obtained. All elements should be audited at least

once per year and some more frequently, depending on need. Besterfield (2004)

provides five objectives of the internal audit which are:

• to determine that actual performance conforms to the documented quality

management system;

• to initiate corrective action activities in response to deficiencies;

• to follow up noncompliance items from previous audits;

• to provide continued improvement in the system through feedback to

management;

• to cause the auditee to think about the process, thereby encouraging possible

improvements.

Audits shall, as a minimum, include an evaluation of:

• work areas, activities and processes

• products and services being produced

• quality control practices being used

• documented quality program procedures, instructions, reports, and records

2.5.14 Training Procedure

The organization shall identify the training needs and provide training for all

personnel, who are in an activity affecting quality during design, production, and

installation. Personnel assigned for specific tasks should be qualified on the basis of

appropriate education, training, and experience as required. So, management

Page 37: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

24

should establish, by review, examination, or other means, whether personnel

carrying out such functions require training. Management should also establish how

competence in a given function is determined, by examination, testing, certification,

and so on.

Training in certain functions requires regular updating and the necessary evidence

that such retraining or maintenance of qualifications has been carried out should be

documented. For example, welders and weld inspectors require retesting at regular

intervals to retain qualification.

2.5.15 Calibration Procedure

Where necessary to ensure valid results, measuring equipment shall (Stebbing,

1993):

• be calibrated or verified at specified intervals against measurement standards;

where no such standards exist, the basis used for calibration or verification shall

be recorded;

• be adjusted or re-adjusted as necessary;

• be identified to enable calibration status to be determined;

• be safeguarded from adjustments that would invalidate the measurement result;

• be protected from damage and deterioration during handling, maintenance and

storage.

In addition, when the equipment is found not to conform to requirements the

organization shall check and record the validity of the previous measuring results.

2.5.16 Maintenance Procedure

Maintenance of the unit shall be periodically necessary if the unit is to continue to

perform satisfactorily during its anticipated service life. So, a programme of

preventive maintenance shall be established to ensure continuing process

capability. The construction equipment and machinery should be appropriately

stored and adequately protected between uses.

Page 38: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

25

2.5.17 Communication Procedure

Communication activities are divided in two, as internal and external communication.

For the internal communication, the organization shall ensure that appropriate

communication channels are established within the organization and that

communication takes place regarding the effectiveness of the quality management

system. Typical communication techniques are meetings, briefings, bulletin boards,

and other communication tools.

The organization shall determine and implement effective arrangements for

communicating with the employer in relation to product or service information;

inquiries and documentation; employer feedback. Such an external communication

should be provided also for the third parties in the work enviroment, concerning the

construction activities.

The requirements for communication should have been established during the

design stage.

2.5.18 Assessment of Supplier Procedure

The organization shall select his suppliers on the basis of their ability to meet

subcontract requirements. The selection of the supplier and the type and extent of

control exercised by the organization shall be dependent upon the type of material

or service. The supplier shall be periodically evaluted within the organization for his

satisfaction of the contract and quality requirements. Founded as not sufficiently

qualified, an alternative supplier shall be assigned for further bussiness.

Page 39: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

26

CHAPTER 3

THE COST OF QUALITY

3.1 THE CONCEPT OF COST OF QUALITY

The Cost of Quality (CoQ) concept has been around for many years. In 1951, Dr.

Joseph M. Juran included a section on CoQ in his Quality Control Handbook (see

Juran, 1988). The Quality Cost Committee under the Quality Management Division

was established by the American Society for Quality (ASQ) in 1961. Such several

quality system standards other than ISO 9001 as QS 9000, and AS-9000, which are

presently accepted, reference the use of CoQ for quality improvement.

According to Juran (1988), the term cost of quality should be construed as the cost

of poor quality, namely the costs associated with the detection and rectification of

defective work. Besterfield (2004) defines cost of quality as the costs associated

with the non-achievement of product or service quality as defined by the

requirements established by the organization and its contractual liabilities between

the employer and the society. The cost of poor quality is used by the management

team in its pursuit of quality improvement, employer satisfaction, market share, and

profit maximization.

The CoQ concept is based on a detailed analysis of the processes and activities

within a project. It reduces the cost of production by means of decreasing the

number of defects and reworks. Further cost reduction is possible through the

incorporation of appropriate techniques which enable lower inventory and ongoing

work costs, and reduce the need for supervision and maintenance.

For a quality cost analysis, data involved in the processes need to be converted into

financial information in order to provide comparable measures across processes,

and to facilitate the improvement of effectiveness and efficiency throughout the

organization. These financial measures consist of prevention and appraisal costs,

and internal and external failure costs.

Page 40: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

27

3.2 CATEGORIES OF COST OF QUALITY

Costs of quality are traditionally divided into four categories:

1- Prevention costs

2- Appraisal costs

3- Internal failure costs

4- External failure costs

Containing elements and sub-elements, each category is discussed below.

Regarding the cost of quality concept, the following equations are defined:

TQC = QCC + FC (3.1)

QCC = PC + AC (3.2)

FC = IFC + EFC (3.3)

where TQC is the total quality costs, QCC is the quality control costs, FC is the

failure costs, PC is the prevention costs, AC is the appraisal costs, IFC is the

internal failure costs, and EFC is the external failure costs.

3.2.1 Prevention Costs

Prevention costs are those costs associated with the planning and implementation

of a quality management system aiming at the prevention of poor quality. Typical

prevention costs incurred by an organization include (Juran, 1988):

• costs of quality assurance activities such as quality system design,

implementation, auditing, communication and reviewing, and the cost of

consumables used in these activities;

• costs related to supplier quality assessment and supplier product inspection,

including development programmes, and the establishment of specifications for

supplier assessment;

• costs of education and training, including both quality system specific training

programmes and the more general staff development activities. Part of this work

Page 41: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

28

may be executed by personnel who are not on the payroll of the Quality

Department;

• costs that are incurred within the context of reliability engineering and other

quality-related activities associated with design reviews and checks;

• costs of process control, including in-process inspection and tests for

determining the current status of the process;

• costs of preventive maintenance

3.2.2 Appraisal Costs

Appraisal costs are the costs associated with verification activities to ensure

conformance to requirements although they exclude the costs associated with re-

inspection following the failure of a product or design. Typical appraisal costs

include (Juran, 1988):

• costs of incoming materials and services verification activities, including the

inspection of pre-contract trials;

• costs of in-process verification, including all checking of the required parameters

to ensure product or design conformance;

• costs of development of inspection and testing equipment in terms of the

specification of such items or services and the calibration costs, but excluding

the capital costs;

• costs of evaluation of stocks, including costs of testing products in stock to

evaluate degradation;

• costs of analysing, reviewing, reporting, and storing the appraisal data.

3.2.3 Internal Failure Costs

Internal failure costs are the costs associated with the non-conformance of the

product or design prior to the transfer to the employer. Typical internal failure costs

include (Juran, 1988):

• costs of scrap of defective product which cannot be reworked, including the

material and direct/indirect labour costs associated with the rejected item;

Page 42: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

29

• rework, retest or replacement costs for product or design which does not

conform to the specified requirements, including the costs associated with the

identification of the remedial action and root causes;

• costs of scrap and rework due to nonconforming product received from

suppliers;

• avoidable process losses, including cost of losses that occur even with

conforming product. For example, using more cement than required in preparing

concrete.

• costs of modification, downgrading and concessions, including the effort

involved in obtaining agreement to reduce the specification;

• re-inspection costs associated with product having previously failed to meet

requirements and having to be reworked.

3.2.4 External Failure Costs

External failure costs are the costs associated with non-conformance of the product

or design and which are detected after the product is shipped of to the employer.

Typical external failure costs include (Juran, 1988):

• costs of rejected / returned product, including the cost of repairing or replacing

the product and the associated handling costs;

• costs of warranty claims and product liability, which may represent costs

significantly in excess of the actual value of the product or design supplied;

• employer dissatisfaction, including the investigation of complaints, the

commercial downgrading of the product or service and the potential loss of

future bussiness.

3.3 THE STUDY FOR COST OF QUALITY

The study for quality cost requires two main components, which will be divided

further into categories given above. They are cost of conformance and cost of

nonconformance.

Cost of conformance is a component of the cost of quality for a work product. Cost

of conformance is the total cost of ensuring that a product is of good quality. It

Page 43: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

30

includes prevention and appraisal costs, such as documentation, using standards,

training, process control, reviews, audits, inspections, and testing. Cost of

nonconformance is the element of the cost of quality representing the total cost to

the organisation of failure by not having quality systems or a quality product. Cost of

nonconformance includes both of the failure costs generated by quality failures,

particularly the costs of scrap and rework, replacement of lost work, possible loss of

business and other potential costs.

For a successful cost of quality study, it is important to categorize the costs related

to quality accurately. The cost of quality decision flowchart, given in Figure 3.1, will

be helpful in this categorization.

Yes

No

Yes

No

Yes Yes

No

No

Not a quality cost!

Figure 3.1 – Cost of Quality Decision Flowchart (Schoonmaker, 1997)

Is cost related to prevention of non conformance?

Prevention Cost

Is cost related to evaluating the conformance?

Appraisal Cost

Is cost related to non conformance?

Is nonconformance found prior the transfer of the product to employer?

Internal Failure Cost

External Failure Cost

Page 44: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

31

3.3.1 Obtaining the Cost Data

Juran (1988) gives two main approaches by composing the cost data used in the

cost analysis. These are:

By Estimate: This is the practical approach which involves only a modest amount of

effort. Several methods may be useful in estimating. The following are sample

methods:

a) Temporary records: For example, some production workers spend part of

their time replacing defective product. It may be feasible to arrange with their

supervisor to create a temporary record so as to evaluate the time of

replacement and thereby the replacement cost. This cost can then be

extrapolated for the time period to be covered by the study.

b) Work sampling: In this method, random observations of activities are taken

and the percent of time spent in each of a number of predefined categories

can then be estimated.

c) Allocation: For example, in an engineering deparment, some of the

engineers are engaged in making product failure analysis. However, the

department makes no provision for charging engineering time to multiple

accounts. It could be asked each engineer to make an estimate of time spent

on product failure analysis.

d) Standard costs data: Examples include scrap, rework, and replacement of

field samples. Such data may be based on unit prices used in the contract or

published by the public sector. They can be get also from the purchasing

department of the organization.

e) Other methods: Opinions of the specialist persons or institutions, like trade or

industry chambers.

By the Accounting System: This is a more elaborate approach. It requires a lot of

effort from various departments, especially accounting and quality. The established

accounts of the activities for quality, such as inspection, training, communication,

maintenance, payroll data, etc., are secured to quantify the quality costs.

Page 45: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

32

3.3.2 Economic Model of Quality of Conformance

The study of the distribution of quality costs over the major categories in section 3.2

can be further explored using the model as shown in Figure 3.2, given by Besterfield

(2004). The vertical scale of the figure illustrates the cost of quality monetary, where

the horizontal scale is the percent quality of conformance. The aim of the model is to

determine the relationship among the cost categories. The model shows three

curves:

1. The failure costs: As the quality of conformance improves and approaches

100%, failure costs, total of internal and external, are reduced until they

approach zero. In other words, if the product or service is perfect, there are

no failure costs.

2. The costs of prevention plus appraisal: These costs are zero at 100 percent

defective, and rise as perfection is approached. It is necessary to increase

appraisal and prevention costs to achieve a reduction in failure costs.

3. The sum of curves 1 and 2: This third curve is marked “total”, and represents

the total costs of quality.

To construct the model, summaries of cost data by calendar periods may be utilized.

These periods provide information on trends and progress in quality improvement

efforts.

0 100Quality of Conformance-%

Qua

lity

Cos

ts-$

Figure 3.2 - Model for Quality Costs (Besterfield, 2004)

Prevention and Appraisal Costs

Internal and External Failure Costs Total Quality Costs

Page 46: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

33

The distribution of quality costs over the major categories can be investigated using

the relationship shown in Figure 3.2, which reveals that the cost of poor quality

decreases as quality increases. However, it is uneconomical to achieve 100%

conformance since the prevention and appraisal costs increase in a geometric

manner. However, perfection is being economically achieved as the inspection

process is automated and where the employer is willing to pay for perfect quality.

Also, perfection is the goal where quality has a critical impact on safety, such as in

the nuclear power field, or where losses can lead to bankruptcy.

As a conclusion, the target should be the reduction of the cost of failure. Increase in

the cost of prevention will have an accelerated effect on the reduction of these

failure costs and contribute to profit without increase in turnover. This is contrary to

the belief that higher quality results in higher costs.

Appraisal costs activities should also be minimized, as they are non-valued added.

They are defined as non-value added as they do not change the quality of the

product or service being evaluated. The more inspections or verifications conducted

the less likely poor quality will be shipped to the employer; however, these activites

do not prevent the poor quality from being produced. By spending more money on

prevention activities, appraisal activities can be reduced and this should also lead to

lower failure costs.

Page 47: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

34

CHAPTER 4

DESCRIPTION OF THE IRRIGATION PROJECT

4.1 GENERAL CONDITIONS

In the case study, a large-scaled irrigation network construction project is examined.

The project was performed in Antalya, a southern coastal province in Turkey. The

aim of the project is to divert flows of the Aksu River, into an existing main channel

by a diversion weir to irrigate a land of 2200 ha. Construction of two pumping

stations, penstocks, and irrigation networks are involved in the project. The flow is

taken into the pumping stations and distributed to irrigable lands in Gebiz Plain

through penstocks, canalet networks, and high-density polyethylene (HDPE) pipes.

Some information about the elements of the project is as follows:

One of the pumping stations, which is named as P2, was constructed with its own

basin in the vicinity of the main channel, and it takes water through an engine. Other

pumping station, which is named as P1, draws the water from the main channel by

means of a suction pipe in 900 mm diameter and 35 m long. The station P1 is

consisting of a building having 8.15 m width and 39.45 m length, whereas the station

P2 has 37.80 m width and 21.50 m length. Both of these buildings have the same

height which is 7.25 m. To each station five pumps were installed in order to serve

group “P1” and “P2” canalets. The pump powers, which are serving “P1” and “P2”

canalets, are 315 KW, and 160 KW, respectively. Besides these pumps, the station

“P1” has three more pumps in order to supply water to the “K” group canalets and

these additional pumps have powers of 55 KW. The general layout of the whole

irrigation network with the corresponding codes is given in Figure 4.1.

Penstocks with large diameters were constructed between the stations and the main

canalets. The station P1 has two penstocks. One of these penstocks has 500 mm

diameter and 575 m length. It provides water for group “K” canalets. The other

penstock has 900 mm diameter and 885 m length. This penstock is joined to P1

Page 48: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

35

Figure 4.1- General Layout of the Irrigation Network

Page 49: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

36

canalets. The station P2 has only a single penstock which has 900 mm diameter

and 94 m length. This single penstock supplies water for group “P2” canalets.

The project has four groups of main canalets, which are K1, K2, P1, and P2. These

are the canalets in semi-elliptical shape and between the commercial types of

280-1000. Considering the main canalets, secondaries and the tertiaries the design

group gave codes for the canalet routes. The secondaries are denoted with “Y” and

the sequence numbers after the code of the concerned main canalet. For the

tertiaries only the sequence numbers of the tertiary on a specified secondary is

used. For example; the first tertiary which is separated from the fifth secondary on

the route of P2 main canalet, is denoted as P2-Y5-1. The secondaries are in the

range of type 100 and type 800, whereas the tertiaries are in general with types

100,180, and 280. The numbers in the canalet types indicates the inner sectional

semi-elliptical area of the corresponding members. For example, canalet type 280

has an inner sectional area of 0,280 m², which is also equal to the discharge in that

canalet for 1.0 m/s velocity. The canalets type 100, 180, 280, 400, 600, 800, and

1000 are used in the project. Besides these types, actually, there are 21 commercial

types of canalets (Terenzio, 1964), like 120, 135, 315, 520, 700, etc. The concrete

thicknesses of the canalets are in the range of 40 mm and 100 mm. The project

involves the construction of the canalet routes for a total length of 116.485 km. The

distribution of the total length with respect to the canalet types is given in Table 4.1.

All of the canalet members used in this project are in the standardized length of 5 m.

Table 4.1 – Distribution of the Canalet Types

Type of the Canalet Total Length (m)

Type 100 67275

Type 180 16465

Type 280 8915

Type 400 8740

Type 600 8875

Type 800 3610

Type 1000 2605

Page 50: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

37

In order to complete the networks, in addition to the canalets, siphons and HDPE

100 pipes with different diameters were constructed. They were used in general to

cross the roads. The total length of the siphons and the HDPE 100 pipes is 3075 m

and 7093 m, respectively. So, the total length of the whole network is 126.653 km.

In different shapes and sizes, totally 2735 reinforced concrete structures were also

constructed as appurtenances, like dividing structures, outlet and inlet structures for

siphons, chutes, elbows, etc.

At the installation of the canalets, concrete saddles and footings were utilized. The

saddles are prefabricated concrete units, and they are used at the joining points of

the canalet members. They are similar in the shape of the canalets and their lengths

changes between 16 cm and 29 cm (Terenzio, 1964). The concrete thicknesses of

the saddles are in the range of 80 mm and 245 mm. The type of the saddle is the

same as the type of the canalet installed over that portion. For example, for the

junction of two canalets in Type 400, Type 400 saddle is used.

The concrete footings in different heights are built in order to provide the slope

adjustments for the canalets with respect to the existing land conditions. Using the

proper forms, the footings are constructed in-situ by pouring concrete. The footings

are in general trapezoidal section and the maximum height of them is 200 cm.

U-shaped sections are used for the footings that are less than 50 cm in height. For

21 types of canalet members, 9 types of footings are produced by grouping the

canalets in similar dimensions (Terenzio, 1964). The standardized heights of the

footings were 20, 30, 40, 50, 70, 90, 110, 130, 150, 170, and 200 cm. In order to

transfer the weight of the canalets and the load of the carried water to the ground,

concrete footing blocks in different sizes were built under the footings. During the

project footings with a total height of 16200 m were constructed.

The total cost of the irrigation project is estimated to be $ 4,820,000. The

permissible time period for the total construction works was 763 days according to

the contract and the delaying penalty after the end of this period was 0,03% of the

contract price for each delayed day. Thus, the daily delaying penalty can be

calculated by multiplying the contract price with this rate and it is found as 1446

$/day.

Page 51: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

38

When the contractor decided to implement the quality management system in the

project, the constructions of the pumping stations, the penstocks, the routes for

group “K” canalets and approximately 85% of the routes for group “P1” canalets

have been completed. Therefore, this study covers mainly the design and

construction processes of the group “P2” canalets, which are approximately 48% of

the total project works. Using this percentage, the project cost of the completed

parts before quality management system can be calculated as $ 2,506,400.

4.2 DESIGN CRITERIA OF THE PROJECT

The project which is used as a case study is a typical irrigation project with canalet

networks, which are very popular in Turkey. An irrigation project is designed

considering the operation, network, and the farm application of the system.

Therefore, the design criteria of a project includes the classification of land, physical

properties of soil, cropping pattern, climatic conditions, irrigation efficiencies, and

type of irrigation network.

The classification of the land for irrigation is an assessment of the physical and

chemical factors of land features that affect the irrigation potential. The standards

should be used in order to classify a land as "irrigable" or “not irrigable”. According

to field and laboratory tests with reference to the USBR Standards, the land in the

project was classified as Class 2. It means that the soil is loamy sand to very

permeable clay and the land has smooth slopes up to 4%, or rough slopes up to 8%.

Moreover, the land also requires a moderate leveling.

The physical properties of soil include infiltration rate, porosity, field capacity, and

permanent wilting point. Infiltration rate is the rate at which water is infiltrated by the

soil when the conditions are limited only by soil factors. Infiltrability of a soil

decreases as the pressure difference, or hydraulic gradient of the infiltration surface

decreases. For a sandy loam soil the average infiltration rate is 2.5 cm/hr.

Porosity is the ratio of volume of voids to the total volume of soil including water and

air. Porosity of irrigated soils varies between 35-55% (Hansen et al., 1980).

The average porosity of the soil in the project site was 48%.

Page 52: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

39

Field capacity is an estimation of maximum volume of water that may be temporarily

stored in the soil profile to be used by plants. The field capacity cannot be decided

accurately since there is no discontinuity in the moisture content versus soil

moisture tension relation. The field capacity of the soil is considered as 33%.

Permanent wilting point is the soil moisture content at which plants permanently wilt.

The permanent wilting point is influenced by the type of soil. The average

permanent wilting point of the sandy loam soil in the Gebiz Plain is 15%.

The water demand is basically determined by the expected cropping pattern and

irrigation efficiencies. The difficulty in determining the expected cropping pattern on

an irrigation scheme varies according to the degree of freedom allowed to farmers in

their choice of crops and the timing of their cultivation activities. Considering the

farmers habits the expected crop types for cultivation were wheat, cotton, barley,

and sesame. The weighted consumptive use of the project area is determined by

the Blaney-Criddle (1950) method. The climatic factors are also essential to

determine the water demand. As well as in the other countries having a semi-arid

climate, in Turkey the Blaney-Criddle (1950) formula is commonly used to determine

the consumptive use. The climatic factor in the formula is calculated by knowing the

ratio of monthly day time hours to annual day time hours and average monthly

temperatures. The average monthly temperatures were obtained from the local

meteorology stations having data for more than five years.

In order to complete the evaluation of demand, the irrigation efficiency of water

distribution system and efficiency of application must be known. This is usually the

weakest point in estimation of the demand, because such evaluations are rarely

made in the field because of the fact that they are time-consuming. In the absence

of reliable field data on efficiencies, empirical data from the abundant literature on

the subject are used.

In order to determine the irrigation network type, economical analyses are

performed for each type of network taking in the account the available technology,

labor, materials, and the operational requirements. The alternative, which gives the

greatest net benefit to the employer at this project, was the canalet network. The

main reasons for this are listed as follows:

1- The employer has an existing prefabricated canalet plant in the vicinity of the

land planned for irrigation.

Page 53: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

40

2- The routes for networks pass usually through the farmers’ land, which leads

to pay expropriation costs. In addition, these second class lands are valuable

for irrigation. Since the width of the construction band is less than the open

channel, the canalet network was chosen to reduce the amount of the land

for construction.

3- Since most of the productions are prefabricated, the construction can be

completed in less time period.

4- There is almost no seepage at the canalet systems, which is important in the

region where the evaporation rate is high.

5- By changing the height of the footings, the water level can be adjusted easily

according to the local conditions.

6- Maintenance and repair of canalet systems are very easy and operation after

construction is simple, which is an important economical factor.

For the design of the canalet networks, two kinds of methods are used. These

methods are the demand method and the unit area - unit water method. Due to the

easy operation and due to the constraints for getting water by the farmers in the unit

area, the demand method was chosen by the design group and approved by the

employer.

Demand method aims to give water to project area continuously according to the

demand. Although this condition is hypothetical and uneconomical, the designs of

the main canalets, secondaries, and tertiaries are based on continuous watering.

However, in the operation of the system only the desired amount is given to the

field. In the demand method, the required parameters for calculations are the

irrigation modulus, qmax (lt/s/ha), irrigable area, A (ha) and flexibility coefficient, F.

Using the parameters the demand and the canalet capacity, Q (lt/s), for the given

area can be calculated by the formula as follows:

Q= qmax.A.F (4.1)

The flexibility coefficient shows the probability of supplying the demand in the field

which is a function of the number of turnouts operating at the same time. Its value

depends upon the area, A, and maximum water requirement, qmax, and it can be

obtained from the table of Kızılkaya (1988). For this reason, the design should be

Page 54: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

41

checked for the month, when the maximum water demand occurs. The irrigation

modulus, qmax , was calculated for the entire project as 1.40 lt/s/ha for 2700 ha. The

supplied discharges over the corresponding areas by each canalet group are given

in Table 4.2.

Table 4.2 – Supplied Discharges according to the Main Canalets

Main Canalet Total Length

(m)

Total Discharge

(lt/s)

Irrigable Area

(ha)

P1 50845 1979 1198

P2 60650 2221 1370

K1-K2 4990 282 132

TOTAL 116485 4482 2700

It should be noted that ineffective design of an irrigation project due to wrong

selection of method creates serious problems and irreversible deficiencies in the

project area. Selection of irrigation practices, networks, and operation methods are

very important tasks of the design engineers.

Since the groundwater level is low in the region, there was no need to design a

drainage system. However, discharging of the wastewater in the network, especially

in the main canalets, was an important task for the design group, so channels and/or

pipes were designed to drain water towards the existing creeks.

4.3 ORGANIZATION

The contractor of the studied project has established an organization, which is

capable of performing both quality and project management. Project management

encompasses the planning, designing, managing, directing, and controlling the

construction, and quality assurance activities. Moreover, it effectively uses

resources to achieve the project goals and set objectives to complete the work on

schedule within the budget. This process was executed by the Project Manager and

the teams which contains qualified technical and administrative personnel. These

Page 55: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

42

personnel might be divided into two main groups as design group and construction

group.

The technical staffs of the design works were named as the “Design Group”. It

includes project manager, design engineers, surveying engineers, topographers,

and technicians. The technical staffs of the construction works were named as the

“Construction Group”. It includes project manager, senior manager, site engineers,

topographers, and technicians.

In order to control and to satisfy the requirements of the quality management system

“Quality Group” was assigned by the contractor. It included quality (assurance)

manager, quality control engineers, and technician. The group is mainly responsible

for checking whether or not, the system requirements were being followed, all

procedural nonconformances are resolved, all procedures and instructions are

prepared. Moreover, it regularly reviews these procedures and instructions and

makes updates if necessary; determines and reports the principal causes of quality

losses and nonconformances. It works with the other groups, and examines where

improvements are required, and it recommends the preventive and corrective

actions.

Page 56: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

43

CHAPTER 5

CASE STUDY

The contractor who undertakes the irrigation project, about which the general and

technical properties are given in Chapter 4, decided to implement the quality

management system in his construction sites. In that manner, taking this irrigation

project as a base, the required studies were started in February 2002. During the 12

months between the time periods March 2002 and February 2003, quality

improvements were aimed and the requirements of the system were set. During this

period, studies were carried out on the determination of the deficiencies in the

design and construction processes, and on the elimination of the effects of these

failures by means of quality management. The aim of this study is to examine the

effects of these studies on the cost of quality. The Cost of Quality Concept, which is

mentioned in Chapter 3, and the cases about its categories faced with while

performing the project and quality system are explained in the following sections.

In the cost of quality calculations, the costs related to these cases are given in

tabular form and in these tables the months between March 2002 and February

2003 are ranked as 1 to 12. (See Tables A.1 - A.39)

5.1 FAILURE COSTS ANALYSIS During the irrigation construction, several nonconformances were observed. The

causes of these nonconformances varied from material defects to workmanship

errors. Several nonconformances occurred also in the design stage. In order to

convert the data of the nonconformances to monetary units, technical analysis,

quantity calculations, unit prices of the public sector, accounting records and

estimates are performed. Since the calculations in this study aim to identify the own

costs of the contractor, the utilized unit prices are profitless.

Also, the costs coming from the delays in the work schedule due to the failures are

considered in the calculations. These are calculated by considering the daily

Page 57: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

44

overheads of the construction site and the design office and the penalty for each

delayed day after the end of the permissible construction period. According to the

contract, daily delaying penalty is identified as 0.03% of the contract price. The

calculations of the overheads are carried out on the basis of bookkeeping.

Overheads for construction and for the design office are treated and evaluated

separately. As it can be seen in Table A.1 and Table A.2, the overheads involve the

costs for the personnel, nourishment, energy, communication, etc., even if no work

is done. These overheads are shown in the related tables firstly for month to month,

and then the daily overheads are found by dividing the total monthly overhead to the

corresponding numbers of calendar days in the considered month. Thus, the cost for

each delayed day is determined by considering both the delaying penalty and the

overheads for the construction site and for the office. The daily delaying penalty of

0.03% of the contract price for each delayed day corresponding to a contract price

of 4,820,000 $ is found as 1446 $/day as calculated in Chapter 4.

For the calculations in USD, exchange rates of selling for one USD announced at

the beginning of the years 2002 and 2003 by the Central Bank of Turkey were

utilized, which were 1,447,714.-TL and 1,656,389.-TL respectively.

5.1.1 Nonconformances at Design Activities

As a main process, the design works can be divided into three subprocesses, as

surveying, mapping, and designing.

Before every design in the office is going to be made, the topographers measure the

necessary coordinates and elevations on the field. Upon getting the data, mapping

works are generated by the survey engineers of the design group. The next process,

designing, starts by the aid of those maps.

For this project, the design engineers completed 708 drawings and according to the

contract, the total cost of them to the contractor is approximately $ 155,000. Also the

contract states that the expenses for the surveying and mapping activities are

$ 82,500. For simplicity, in the cost calculations all of the design, mapping and

surveying activities for each final drawing are evaluated as equal in price.

Consequently, the cost for each drawing is calculated as follows:

Page 58: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

45

Total Surveying and Mapping Cost for 708 Drawings = $ 82,500

Surveying and Mapping Cost For 1 Drawing = $ 82,500 / 708 = $ 117

Total Designing Cost for 708 Drawings = $ 155,000

Designing Cost for 1 Drawing = $ 155,000 / 708 = $ 219

8 Nonconformance Reports were issued by the quality group for the design works.

The costs of design nonconformances (DNCs) are classified as internal and external

failure costs according to the quality cost concept and the conditions are listed as

follows:

DNC – 1: In the design of the project, some of the canalet routes passed through

private areas, which created expropriation problems. Therefore, the drawings of

some routes in the network were revised, which are P2-Y3, P2-Y5-9, P2-Y10, P2-

Y3-6, and P2-Y3-4-1. Besides these revisions, two of the routes, which are P2-Y9

and P2-Y15, have cancelled due to the disagreement with the farmers. As a result,

22 drawings were revised and 12 drawings were scrapped. For the revisions, the

design group spent 13 days and some of the delays affected the schedule of the

construction works, which generated overheads and penalties. The cost of the

nonconformance can be classified in internal failure costs as scrap and rework.

However, if the expectations of the farmers have been asked throuh meetings at the

beginning of the design stage according to the Communication Procedure, there

have not been such problems and time losses.

For calculations, the months at which these failures were occurred are shown in

Table A.3 indicating the routes. In this table, numbers of revised and scrapped

drawings for each of the routes are also given. Using the unit cost for one drawing

calculated above, daily delaying penalty, and the daily overheads corresponding to

the related month given in the Table A.1, the monthly costs for this nonconformance

are calculated.

DNC – 2: In the construction region, there are several creeks and the biggest is the

Gebiz Creek. When the canalet routes were designed, one of the lines, P2-Y5-1,

passed nearby the Gebiz Creek. Especially at the beginning of the spring season,

melting of the snows and the excess rainfalls caused flooding problems in the area.

Page 59: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

46

In March 2002, just after the construction of the line P2-Y5-1 along the creek, the

flood took place and lots of canalet members were damaged. Although the design

group had being aware of the flooding possibility of the creek, they did not get the

existing statistical data for the area. In fact, employer specified in his contract

documents that the designer of the contractor should evaluate the general

geological and environmental conditions and should take the necessary precautions

according to the Contract Review Procedure. By ignoring the contract conditions,

and not checking the design for the existing conditions specified in the Design

Control Procedure, input stage of the design failed and the design needed to be

revised. As a remedy, the design group proposed to construct stone fills in some

parts instead of changing the route.

In Table A.4, the cost calculations are given for this nonconformance and the cost is

considered in the internal failure costs as rework. In these calculations, the number

of the damaged canalets and the damaged footing types on the route of P2-Y5-1 are

indicated and the lengths of these members are shown. Using these total lengths,

costs for the damaged products and reworks are obtained by using the profitless

unit prices about the production and installation for each type of members given by

the Turkish State of Hydraulic Works in 2002. The costs required for surveying,

mapping, and design facilities in order to determine new routes and the delaying

costs are added to the costs for the damaged products and reworks shown in Table

A.5. The construction site overheads corresponding to the months at which the

failures occurred are taken from the Table A.1.

DNC- 3: 16 nonconformances were reported for the surveying processes, which are

mentioning about the deficiencies for the survey parameters. The surveying

members of the design group ignored to measure some coordinates which are

required for the design. It was observed that the topographers did not know exactly

what they should measure for an irrigation project. The problem was solved by

organizing two meetings and providing more communication between the surveying

technical staff and design engineers according to the Communication Procedure.

The meetings also included educational parts, as described in the Training

Procedure. At these meetings the design engineers explained exactly what they wait

from the surveying technical staff. Delaying in the design activities caused

overheads for the design group as an internal failure cost for reinspection, and it is

Page 60: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

47

calculated in Table A.6. Since the delays did not occur over the long periods, their

effects on the construction work schedule were neglected. In the related calculation

table, the deficiencies and the caused delays are given with the related months. As

the result of the multiplication of these delays given in the form of days and the daily

design office overheads with respect to the months given in Table A.2, the total

monthly failure costs are obtained.

DNC – 4: Completion of the design on scheduled program is crucial for optimum

timing of the project. In the first eight months, the final drawings were not ready on

time several times. This caused delays in submission and approval of the employer

who requested minor changes in the format of the drawings. So, the construction

group was forced to commence as soon as they received the drawings. This

condition had impacts on the material and workforce logistics, which affected the

quality on negative sense. Moreover, it had impacts on the quality control and

assurance activities directly. Improvements were observed for the nonconformance

in time by utilizing the Design Control Procedure. The construction works were left

over the schedule, and it caused to an increase in the overheads. The cost of this

nonconformance is calculated in Table A.7 and it is evaluated in the external failure

costs as employer dissatisfaction. In this calculation table, the distribution of the

delays with respect to the months is given. Each of the delays is also shown in the

form of days. The monthly failure costs are obtained by using the daily delaying

penalty calculated before and the daily construction site overheads on the basis of

the months given in Table A.1.

DNC – 5: Although the specifications for the canalet networks notify to put tertiaries

at left and right sides of the secondaries for every 500 m, the design group ignored

this specification and some of the routes have been constructed not based on this

information. Due to the shortage in the time for the submission of the drawings to

the employer, the design group submitted the drawings without checking this detail

and they were submitted. Actually, after the submissions, the design engineers

could check the critical control points immediately related to the Design Control

Procedure, which they may ignore and could revise as required before being applied

in the site. This led to remobilization costs as rework for internal failure costs which

include allocation of a truck, an excavator, and a crane. Hence, the construction

group was forced to turn back to reconstruct the completed parts after the deficiency

Page 61: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

48

was observed. To eliminate the occurrence of further possible problems, an

educational meeting was arranged between the design and construction groups

according to the Communication Procedure.

The costs of remobilization are calculated in Table A.8 as rework in internal failure

costs. In the remobilization cost calculations, the formula for the hourly

remobilization cost of the equipments, given by the Turkish Ministry of Public Works

and Settlement is used. The formula is as follows:

Hourly remobilization cost of the equipment = 0.02 x N / n (5.1)

where N is the purchasing price of the new equipment and n is the work time for the

construction equipment in one year in terms of hours. The value of “n” is accepted

as 2000 hours for the cranes, excavators, and trucks by the ministry. “N” values are

obtained from the unit prices for these equipments given by the same ministry in

2002. These unit prices for crane, excavator, and truck are $ 128,670, $ 71,879, and

$ 12,866, respectively. Thus, putting these values into Equation (5.1) the hourly

remobilization costs are calculated and given in Table A.8. Moreover, the total

worked time in days for a route for both of the two remobilizations are also given in

this table. Multiplying these worked time by 8.5, which is the daily working hours, the

total worked time in hours are obtained. Multiplying the hourly remobilization costs of

the equipments and these total worked time in hours the total failure costs with

respect to the months are obtained.

DNC – 6: A calibration error made in one of the total stations was observed as a

nonconformance after the calibration reports have been developed. The accuracy of

the measurements for the drawings is in the responsibility of the design group. In

order to adjust the given drawing data on site for the applications, the construction

group had lost time, which caused delays in the work schedule. The cost of these

delays are calculated in Table A.9 for the first two months and listed in Table A.31 in

the internal failure costs as a retest because of the deficiency in the calibration. In

the cost calculations of the calibration deficiency of the total station, the average

daily delay in the schedule due to adjusting drawing data on the site is estimated as

0.5 hour. By taking the daily work as 8.5 hours, estimated average daily delay in the

work schedule in days is found as 0.059 day. By using the estimated average daily

delay, the estimated average monthly delay can be found in terms of days as 1.8

Page 62: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

49

days. Using the daily overheads in Table A.1 and the daily delaying penalty, given in

the contract, the cost of the calibration deficiency is obtained.

Putting Calibration Procedure into practice in the mid of the third month, all of the

surveying equipment were calibrated. Yearly calibration plans were prepared for two

calibrations in a year. In the plans weekly periods in a year were indicated for each

of the alienable equipment, and the equipments were taken from the site and sent to

calibration according to this plan.

DNC – 7: The drawings, prepared according to specifications, have included chutes

for the head differences. If a canalet member enters in a structure, there is no

requirement for constructing a footing. The design group was responsible to give the

number of the footings which will be constructed at each canalet route. The

drawings were submitted to the construction group and the decrease in number of

footings, because of presence of a number of chutes, was not taken into

consideration. As a result, the construction group arranged the required materials

and the work power according to these amounts. However, during the process

control in the field, the quality management group observed the excess amounts of

footings. A nonconformance report was prepared and forwarded to the design group

according to Corrective and Preventive Actions Procedure. The design group then

prepared a checklist for further implementations according to the Quality Records

Procedure.

The unnecessary loading and transporting works can be evaluated as a scrap, the

cost of which is calculated in Table A.10 in internal failure costs. In this calculation

table, numbers and types of the excess footings are given with respect to months.

Moreover, the saddle types transported to the site to be used on the footings are

also given. The numbers of saddles are equal to the numbers of excess footings.

The weights in terms of tons for each type of the footings and saddles are given in

the table. The unit prices per tons of loading, unloading and transporting the footings

and saddles given by the Turkish Ministry of Public Works and Settlement in 2002-

2003 are also presented in this table. The failure costs during the months are

calculated by using the total weights and the unit prices.

Page 63: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

50

DNC – 8: After some of the drawings were completed and submitted for approval,

the drawings of routes P2-Y12 and P2-Y13-1 were sent back by the employer who

requested an economical comparison between canalet network and pipeline for

these routes since the topography of these routes are very inclined. The employer

proposed to use HDPE type pipes as alternative to canalet network. After the design

group carried out an economic analysis, it was observed that a network composed

of HDPE 100 pipes would be more convenient. Calculations for the pipeline system

were fulfilled, all the drawings were revised and new drawings for the pipeline were

prepared. However, if the design group asked the advises and expectations of the

employer before each design part of the network according to the Design Control

and Communication Procedure, and these reworks would not occur. The design

group worked on the new drawings for 8 days and construction group was delayed

for these revisions 2 days in the work schedule. The costs of these redesigns and

the overheads because of these delays are handled as external failure costs of

complaint adjustments and they are calculated in Table A.11 by using the given

overheads in Table A.1. The cost of redesigns is calculated by multiplying the

number of redesigned drawings, given in Table A.11, by the cost of one drawing.

The failure costs in the design activities are summarized in Table A.31 indicating the

internal and external costs. In this table, the total monthly failure costs for each of

the nonconformances are involved.

5.1.2 Nonconformances at Construction Activities

The construction activities include two kinds of main processes; supplying the

construction materials and the civil works. These nonconformances can be divided

into two groups as Material Nonconformances (MNCs) and Civil Works

Nonconformances (CNCs) as follows:

Material nonconformances have been observed in 6 cases. These cases are

explained as follows:

MNC – 1: Cracks, deformations, and dimensional nonconformances were observed

on wooden elements used for formworks of footings and system structures. At the

beginning, the purchased materials were not checked for the construction

Page 64: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

51

conformance. Only one employee was responsible for counting the coming

materials and he did not have the sufficient knowledge on the construction

materials. By the means of the Training Procedure and according to the Control of

Non-conforming Product Procedure, the employee was trained for the critical checks

when the construction materials were brought to the site. The employee learned the

typical dimensions of the necessary formwork elements for the construction of the

footings and the system structures. After the training, the cost of the defective

products received by the contractor decreased considerably. In the 11th month, the

supplier of the wooden elements was changed according to supplier evaluation

report of the Assessment of Supplier Procedure. The cost calculations of these

nonconformances are given in Table A.12 and the cost is defined as internal failure

cost of scrap. In the related table, the defective wooden elements and their amounts

are given in terms of m3. The costs of the defective wooden elements with respect to

the months are calculated by using the unit rates for timber given by the Turkish

Ministry of Public Works and Settlement in 2002 and 2003.

MNC – 2: For a routine daily work, insufficiency of the concrete aggregates and

cement in the stocks were reported three times. In each of the cases, the concrete

works were delayed for half a day. This situation affected the work schedule directly.

Failures with respect to their occurrence months are shown in Table A.13. The

problem was solved upon preparing a chart showing the minimum stocking levels of

the materials according to the Handling, Storage, and Delivery Procedure. A quality

control engineer was assigned to control these levels. The cost of these delays is

handled as retest of the internal failure costs and calculated in Table A.13. In these

calculations, the daily delaying penalty in the contract and the overhead costs in

Table A.1 were utilized.

MNC – 3: Because of the inconvenient storage of cement, reinforcement steel and

canalet members, three non-conformances were detected. It was observed that

some bags of cement, canalet members, and reinforcement steel were

inconveniently stored because of insufficient protection from the external

environmental conditions. The occurrence months of these nonconformances are

given in Table A.14. According to Handling, Storage, and Delivery Procedure, the

list of stock conditions of such kind of materials were formed by considering their

characteristics. The stocking and stacking conditions were checked regularly by the

Page 65: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

52

quality control engineer according to Inspection and Testing Procedure besides

being checked by the quality manager during the controls according to Internal

Quality Audits Procedure. The cost of the scrap of the materials is calculated in

Table A.14 as an internal failure cost. In the calculations, the unit rates and unit

prices for cement, for reinforcement steel and for the canalet Type 280, given by the

Turkish Ministry of Public Works and Settlement, were utilized.

MNC – 4: The bituminous cords, which are used between two successive canalets

in order to provide leakage proofness, were produced in the bituminous cord

workshop by the construction group. The specifications notify that the bitumen of the

cord shall not flow in hot weathers and shall be rigid enough to resist the weight of

the joined canalets for protecting the hydraulic continuity between the adjacent

canalets. However, in the controls and audits, deficiencies were observed in the

bituminous cords, both in the stocks and over the canalets due to the high

temperature at the region. 65 cords were found as defective in the stocks, and 11

defective cords over the canalets were replaced including the reworks of the canalet

installation. These defective cords are given in Table A.15 according to months at

which they were realized. The cords, which were taken out from the completed

canalets, were also given separately. Besides these, the canalet types which were

subjected to reworks and the types of the defective cords are given.

A technical standard was developed to inspect the production quality of the cords

according to the Corrective and Preventive Actions Procedure. Subsequently, the

production works were carried out with respect to this standardized analysis and

controlled by the quality control engineer. Improvements were observed in the

production process.

The costs of the scrap, reworks and corresponding delays are evaluated as internal

failure and they are calculated in Table A.15. In the calculations of the canalet

installation and cord production costs, the unit prices per unit length in m given by

the Turkish State of Hydraulic Works in 2002 are used. Multiplying the lengths

according to the types of the materials by these unit prices, the failure costs for this

nonconformance are obtained. The delaying costs due to the effect of this

nonconformance over the working schedule is added to the failure costs from month

to month. In the determination of the delayed time, the required time for installing a

Page 66: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

53

canalet member given in the contract is used. In order to do this, the permissible

construction period given in the contract, which is 763 days, is divided by the total

numbers of the canalet members in the project, which is found by dividing 116485 m

by 5 m to obtain 0.03 day/member. This value is multiplied by the number of the

canalet members which are replaced in the considered month and the result is

multiplied by the daily overheads for that month and the delaying penalty.

MNC – 5: The control engineers of the employer checked regularly the installed

canalet members. The results of these controls are as follows:

• capillary cracks inside and outside of the members in 14 canalet members;

• separation of the reinforcement steel from the concrete in 6 canalet members;

• production deficiencies in 2 canalet members, which influence the roughness of

the member and constraint the flow of water.

In Table A.16, the number of the defective canalets is given according to the months

at which they were realized and according to the types of the canalets. It was

obvious that most of these damages were generated in the production stage in the

canalet plant. However, the construction group neglected to control the canalet

members when they were receivied from the plant. The defective members were

replaced with the sound ones and appraised as scrap. Actually, at the beginning if a

quality control technician had been assigned to check the canalets at the delivery,

there would not be scraps in such amounts. The assigned technician was trained at

first in respect of the Training and Inspection and Testing Procedures about the

project, construction methods, used materials, types of canalets and critical control

points to be checked before using or receiving a canalet member. He has given a

check list to be followed for every delivery according to Quality Records Procedure.

The reworks required for the defective canalets which must be replaced caused

delays in the working schedule. For the cost calculations of these delays, the same

value of 0.03 day/member, which is calculated and used in MNC-4, is used. By the

mean time, besides the overheads and penalties due to these delays, for the

calculations of the rework costs of the defective canalets, the amounts of the

damages which were realized throughout the year are indicated monthly by giving

the types of the canalets and the unit prices for producing and installing given by the

Page 67: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

54

Turkish State of Hydraulic Works are used. The costs of these reworks and delays

were found after the products had been shipped to the employer. Hence it is an

external failure cost in the subcategory of warranty charges. These costs are

calculated in Table A.16.

MNC – 6: According to the Assessment of Supplier Procedure, the subcontractors,

who are responsible for the transport of the construction materials, should follow

Handling, Storage, and Delivery Procedure. The construction materials are

inspected regularly by the site engineers whether or not they are delivered properly

at the right time. It is obvious that the problems in the deliveries will affect the

subsequent steps directly. In one year period, three nonconformances were

observed in the transport of the construction materials. In two of them, the

reinforcement steel and HDPE 100 pipes arrived late to the construction site one

day and two days, respectively. In the third one, some of the HDPE 100 pipes were

scuffed and scratched outside during loading and transporting. Inspecting and

evaluating the condition according to the existing specifications through the

Inspection and Testing Procedure, the quality group concluded that these damages

do not affect the serviceability of the pipes unless severe gouging or cutting takes

place. In general, specifications notify to repair or remove the pipes which are

gouged to depths greater than 10% of the wall thickness.

Late deliveries created delays in the work schedule, which is included in the

category of internal failure costs as avoidable process losses. According to

Assessment of Supplier Procedure, the common evaluation of the quality group and

the construction group was to change the transport subcontractor who is responsible

for transporting the HDPE 100 Pipes. The cost calculations of this nonconformance

are given in Table A.17. In the calculations, delays in terms of the days and daily

delaying penalty and the daily overheads corresponding to the related month taken

from the Table A.1 are multiplied.

Civil works nonconformances were observed in 9 cases. These cases are explained

as follows;

CNC – 1: In one year period, 17 stability failures took place in the installation of the

footings. The problem was observed mostly after the installation of the canalets over

Page 68: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

55

the footings, which caused the elevation differences between the adjacent canalets

or demolitions during placing. Including the item of checking the stability of the

footings before the installation of the canalets in the control instructions into the

Process Control Procedure, number of occurrences of these failures was

decreased. Consequently 6 failures were found before the installation of the

canalets and the footings were strengthened. However, in the remaining 11 failure,

there were 5 canalets and 4 footings damaged. Replacing the members and

improving the elevation differences brought about scrap, reworks and delays in the

work schedule, costs of which are calculated as internal failure in Tables A.18 and

A.19. In the calculations, it is clarified that either reinstallation or replacing is

involved by the reworks and to which and to what types of the members rework was

applied in that month.

Rework costs are calculated using the unit prices for producing and installing of

different types of members given by Turkish State of Hydraulic Works in 2002 and

2003. In order to find the total failure costs in the months, the delaying costs caused

by these reworks are calculated same as the calculation in MNC-4 and they are

added to the rework costs. In the calculations, the delays coming from the

strengthening works are negligible.

In the construction process of the system structures, 8 nonconformances were

reported in 3 cases for the concrete works. These cases are as follows:

CNC – 2: Some segregation events were observed because of inappropriate

vibration and delayed pouring of the concrete from the mixer. One of the

segregation was so important that a concrete wall of the dividing structure of P2-

Y14-1, located at 0+239,02 km on the route of P2-Y14, was demolished and

reconstructed by the request of the employer. The other failures were accepted as

harmless and the concrete surfaces were repaired by mortar works. Since the

mortar works are partial and in low quantities, they are neglected in the cost

calculations. The reconstruction of the wall delayed the site works for a half a day.

The failure cost of the reworks and delay are accepted as external in returned

material category and it is calculated in Table A.21. For the computations of reworks

in respect to the drawing of the demolished wall given in Figure 5.1, the quantity

calculations are made for reinforcement steel works, formworks and concrete works

Page 69: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the
Page 70: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

57

in Table A.20 and the total amount found is multiplied by the unit prices for related

productions given by the Ministry of Public Works and Settlement. Thus, the total

costs are obtained and given in the calculation table of costs. Daily delaying

penalties and daily overheads are used for the delay costs which are added to the

total costs.

CNC – 3: Inappropriate slump values in the checklists of the concrete pouring works

for the slump test were recorded 3 times. This belongs to the concept of the

Inspection and Testing Procedure. Due to the high temperature observed at the

region, especially in the summer season, the slump value should be between 12

and 15. However, the results of the test indicated that the consistency of the

concrete was quite dry at two times and watery at one time. At the first

nonconfarmance to the consistency as dry, the concrete was poured by adding

water by the instruction of the quality control technician. This caused to reduce the

strength of the concrete. Observing the fault in the internal audit, an instruction

paper was prepared by the quality manager as the conditions to conform at the

slump tests and a training program was given on the concrete works to the site

engineers, quality control engineer and technicians. Evaluating the condition and

concrete test results, the quality manager and the site manager concluded that there

was no need to reconstruct the poured members. Therefore, there was not any

additional cost for these nonconformances.

CNC – 4: In the reports of the cubical strength test, one deficiency was observed for

the compressive strength of concrete in one of the siphon outlets. The structure was

not accepted by the quality manager and the required construction works were

repeated. The reason for the failure can be said as the negligence in the control for

the dosage of the cement or water/cement ratio. In the training program on the

concrete works, the importance of the concrete strength was taken up and handouts

were distributed. These handouts included the 28-day compressive strength and the

required minimum cement dosage for each type of the system structures. Also, it

was remembered to control the dosages and water contents and to record in the

concrete checklists as instructed in Process Control, Inspection and Testing and

Quality Records Procedures. The reconstruction of the structure was delayed the

site works for a day and the costs of rework and delay are calculated in Table A.23.

The calculations are made same as described in CNC-2. The quantity calculations

Page 71: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

58

required for the structure given in Figure 5.2 are performed in Table A.22. The

calculated costs are treated as rework costs of internal failures.

In the construction of the system structures, like chutes, elbows, siphons, etc., 4

nonconformances in 2 cases were reported for the formworks. The cases are as

follows:

CNC – 5: The technical specifications notify that stripping time is 14 days for chutes

and elbows and 7 days for inner form and 2 days for outer form of siphons. In the

internal audits, 3 nonconformances for the stripping times were observed. In two

cases the forms of two elbows were stripped in 9 days and 12 days, respectively,

and in the other case, the inner forms of a siphon were stripped in 4 days. By

inspection, the detrimental effects of stripping in the cases of elbows were not found

as critical to require a demolition for the structures, but for the case of the siphon,

located at 1+028, 62 km on the route of P2 Main Canalet, the project manager

requested the reconstruction of the siphon to get rid of the effects of early stripping

on the roughness. By the aid of the concrete works checklists of Quality Record

Procedure, this kind of nonconformances can be eliminated for possible future

occurrences. In the first weekly site meeting, the technical staffs were warned to

check systematically the stripping times through these quality records. The

reconstruction of the siphon caused rework costs as internal failure and delayed the

site works for a day. The calculations of these failure costs are given in Table A.25

by considering these reworks and delays. The calculations are made same as

described in CNC-2. The quantity calculations required for siphon given in Figure

5.3 are performed in Table A.24.

CNC – 6: The formwork instructions notify that the technical staff should check the

dimensions of the installed concrete forms before the concrete is poured. Quality

control engineer and the employer detected 3 nonconformances in the dimensions

of the formworks. Two of these nonconformances were neglected after taking the

opinions of the control engineers. However, the third one which is about the wall

formworks of the inlet structure for the chute with pipe, located at the 0+073, 57 km

on the route of P2-Y5, was decided as inappropriate for concreting. The pouring

process was not allowed to begin till making the wall forms fit for it, where the

longitudinal dimensions of the forms were measured 12 cm less than the one

Page 72: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the
Page 73: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the
Page 74: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

61

required in the related drawings. The Process Control Procedure made it possible to

perceive and correct the fault and to prevent the possible failure before the

subsequent processes.

The reform works, cost of which is calculated in Table A.27 in the internal failure

category, were started and completed in the same day by over-hour working and did

not cause any delay in the schedule. The drawing which belongs to the reformed

structure is also given for the cost calculations in Figure 5.4. Using this figure, the

required quantity calculations are performed in Table A.26, and the calculated

amount is multiplied by the unit prices for the formwork given by the Ministry of

Public Works and Settlement.

CNC – 7: Use of HDPE pipes in the network oriented the quality management team

designating the required instructions and the checklists as defined in the Process

Control and Inspection and Testing Procedures. Since the most critical subprocess

of HDPE Piping is the butt welding, the instructions include mainly the critical check

points at the butt welding and the checklists were get filled according to these

instructions for every job of welding. Although the controls by the quality control

engineer and the site engineers reduced the welding failures in considerable

amounts, some deficiencies were observed in the process after the tests because of

nonconforming the cooling and heating times in the given pressures at joining the

butts. The 14 defective weldings generated cost of correction and accepted as

rework in the internal failure costs. Being independent work in the schedule, the

reworks for the piping did not cause any delay. The cost of the nonconformance is

calculated in Table A.28. For calculations, numbers of defects in butt welding are

shown in the related table with according to the months at which they occurred.

Moreover, the table contains also the diameters of the butt-welded pipes. Total

failure costs are calculated by using the unit prices for different diameters of pipes

given by Turkish Bank of Provinces in 2002 and 2003.

CNC – 8: The nonconformances in the excavation and backfilling works were

reported almost as the failures of the machinery, which was only sent to the

maintenance if they had any failure at work at the beginning of the quality

management system. These failures brought about stops in the works and delays in

the work schedule. These delays are given in Table A.29 in terms of days.

Page 75: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the
Page 76: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

63

By using the Maintenance Procedure, preventive maintenance plans were prepared

for every machine in site and the failures and corresponding delays were reduced.

These machines are one excavator, three loaders, one grader, one roller, and three

trucks for the earthworks. One employee, who is well-informed about the machines,

was assigned to follow these maintenance activities. According to the planned

periods the machines were taken from the site and sent to the maintenance

services. The operators were trained for the basic maintenance techniques and they

were given basic rules to use their machines more productive. Also, instructions and

checklists were prepared and distributed to the operators. Attention should be paid

to these checklists and they should be filled for every week while controlling the

machines about their conditions. 13 failures were observed in the machine failure

reports, caused avoidable process losses as internal failure cost, which are

calculated in Table A.29. For the calculations, the daily delaying penalties

concerning the delays occurred and the daily overheads corresponding to the month

at which the delay occurs are used.

CNC – 9: The technical specifications clarify the joint spaces between two

successive canalet members as minimum 0.5 cm and maximum 1.5 cm. According

to this criterion the installation works were checked as defined in the instructions of

the Inspection and Testing Procedure, and some faults were detected. The amount

of the faults decreased in time by the aid of the process control, but it is never

possible to get zero defects, which is also supported by the cost of quality concept.

The internal failure costs of these nonconformances are calculated in Table A.30. In

the calculation table, the types and the number of the reinstalled canalets are

shown. In order to calculate the costs of these reinstallations the unit prices given by

the Turkish State of Hydraulic Works are used.

The failure costs in the construction activities indicating the internal and external

costs are summarized in Table A.31. In this table, the total monthly failure costs for

each of the nonconformances are involved.

5.2 PREVENTION AND APPRAISAL COSTS ANALYSIS The decision of implementing the quality management given by the top

management of the company was an absolute requirement of the management

Page 77: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

64

responsibility principle. The reasons behind this decision were to serve in better

quality and to improve productivity in the construction industry, to improve market

position in the current global competition and to reduce the quality costs, which are

also the quality objectives of the company.

The next step was to decide on the selection of a quality management consultant,

who will assist in defining the quality policies and putting the quality management

system into practice by considering the conditions peculiar to the project. The

consultants consider in general a four – month period training as enough to form a

quality management system and to follow the implementations. The organization

paid to the consultant for four-month assistance $ 2500, including only the training of

the quality manager about the quality management system and implementations

and one training program for each of the design and construction groups about the

system requirements. This payment is handled in a separate row in Table A.38 as

the quality system design and implementation costs of preventions.

The formation of the quality management system is divided into two phases,

documentation and practice. The documentation phase includes mainly the

preparations of the quality handbook, the required procedures and instructions and

the formats of the corresponding quality records, like checklists, forms, plans, tables,

etc., considering the characteristics of the project. The top management has

assigned a quality manager, who is a civil engineer, to follow and control the

documental and practical activities at full authority according to the management

responsibility principle. The quality manager has worked together with the consultant

and was trained by him about the structure and the conceptual requirements of the

system. In the mid of March 2002, writing of the quality system documents were

started and they formed the quality handbook, which includes the quality policies,

missions, the brief contents of the project and the procedures, definitions, services,

processes, general formats of the documents, and the quality objectives. The quality

manager, who is the only responsible person for preparation of the quality handbook

and the first responsible for the procedures, instructions, and the quality records,

assigned a quality control engineer, also a civil engineer, for his assistance to

prepare, revise and control the documental part of the quality system in respect of

the Document and Data Control and Quality Records Procedures.

Page 78: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

65

The control engineer began his works in April 2002 and he was the second

responsible for the preparation of the procedures, instructions, and the quality

records. For simplicity, the monthly personnel expenses, salaries, insurance, etc., of

the quality manager, quality control engineer and technician are inserted in a row in

the prevention costs throughout one year in Table A.38. The other costs are the

costs of consumables associated with the documentation phase, like writing and

saving materials, copying, etc. Although the preparation part of the documentation

was completely finalized in August 2002 with the quality records, the revisions had

been continued intensively over the documents, especially about the job instructions

and the quality records, by perceiving the deficiencies in the practice. The monthly

distribution of the consumables costs for the documentation according to the

accounting records are given in a summary table (Table A.38).

During the preparation of the quality management system documents, the practice

phase of the system was started at the end of March 2002 with training programs.

The first training program was for the design group about the quality management

system by the consultant, including the requirements of the quality management

system. The program was also repeated for the construction group. The second

training program, given to the design group by the quality manager, was given in

June 2002. The program was intensed over the Design Control and Contract

Review Procedures. This program was required particularly in order to eliminate the

nonconformances, like DNC-2 and DNC-5. The last program for the design group

was carried out by the consultant in July 2002 considering the Document and Data

Control and Quality Records Procedures. The training provided to the design group

to earn an approach for preventing the nonconformaces, like DNC-4 and DNC-7.

For a total training period of 5 days, the expenses can be listed as the overheads in

the design office, given in Table A.2 as daily for each month, and the extra training

charge of the consultant. The cost calculations are given in Table A.32.

The construction group was also in need of training for the quality management

system. The first training, in April 2002, was about the requirements of the quality

management system. The second training program was fulfilled in May 2002 by the

quality manager to reduce the number of nonconformances in canalet installation

works and formworks, like CNC-1, CNC-5 and CNC-8. In this training the inspection,

testing, process control and design review activities of the quality management

Page 79: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

66

system were explained in detail and examples were given from the existing failures

of the canalet installation works and formworks and also from the possible ones,

related to concrete works. However, after the nonconformances on the concrete and

formworks, CNC-2, CNC-3, and CNC-4, a more effective training was applied to the

quality control engineer, site engineers, and the technicians in June 2002 by the

quality manager, including mainly the concrete works. The workers have included

only into the first training and the other trainings were given to the technical staff.

Therefore, the works were stopped due to the first training only one day. The

expenses, calculated in Table A.32, can be considered as the overheads of the

construction site and the delaying penalty for one day.

The training procedure requires also individual trainings, which were subjected to

the quality control engineer, technician and the employee who is responsible for the

storage. Other than the training programs given by the consultant and the quality

manager to groups, the quality control engineer was trained in the fifth month by the

quality manager particularly for the inspection and testing, process control and

quality records procedures and the stock conditions including the minimum stock

levels, in respect of the Handling, Storage, and Delivery Procedure. In the fifth

month training, which was held by the quality manager, was desired to get the

employee responsible for the storage to comprehend the conditions for the delivery

and the storage, appropriate for the Handling, Storage, and Delivery Procedure.

These two additional training programs caused not an important overhead to

consider in the prevention costs calculation.

The necessity for inspection of the incoming materials for the canalet members has

directed the quality manager to assign a quality control technician in July 2002. The

technician, who was unfamiliar with the quality management system, was trained by

the consultant about the implementation of the system and by the quality manager

about the project, construction methods, used materials, types of canalets, and the

critical control points to be checked before using or receiving a canalet member. The

charge of the consultant for the training is considered in the training cost

calculations in Table A.32.

According to the Maintenance Procedure, preventive maintenance activities

including a training program for operators were generated as described in CNC-8.

The preventive maintenance plans were prepared in the fourth month as to take the

Page 80: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

67

machines to the maintenance two times a year, firstly in the sixth and seventh

months and secondly in the eleventh and twelfth months. Also, a training program

was given by the technical person of the maintenance subcontractor without a

charge on the request of the quality manager. The costs of the maintenance

activities for the months are given in Table A.33 on the basis of the accounting

records.

The Calibration Procedure, which discuss to plan and act for the calibration activities

of the measuring devices, was implemented in the second month by taking the

necessary preventive measures as explained in DNC–6. The devices were planned

for calibration in the third and ninth months and the activities were held by a certified

calibration company in the planned periods. The calibration costs are given in Table

A.34 on the basis of the accounting records for the months of calibration.

According to the Communication Procedure, meetings are accepted to be the most

effective tools for communication. Therefore, meetings were organized for

prevention and correction of the nonconformances between different internal groups

throughout the year. The first meeting, required for the design activities, was

organized by the design group on the request of the quality manager in the third

month. The design engineers and the technical staffs of surveying came together in

the construction site to prevent further deficiencies in surveying activities, which will

influence the design activities directly. This meeting was repeated for the same

purpose in the seventh month between the same groups. In addition to these

meetings, the design group organized meetings with the local farmers in the fifth and

tenth months and with the construction group in the fifth month. All of these

meetings were carried out in the construction site and organized in order to prevent

the possible nonconformances, explained in the design part as DNC -1, DNC-3,

DNC-5, and DNC -8.

To learn the expectations of the employer, the design group also organized

meetings with the employer, especially after the sixth month. These meetings

continued orderly till the twelfth month and they were useful to designate the

essentials of the drawings before the action and to prevent the reworks.

Page 81: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

68

The overheads of these meetings were mainly due to the transportation costs of the

design group between the construction site and the employer’s office. These costs

are given in Table A.35 and accepted as prevention costs.

In respect of the Assessment of Supplier Procedure, supplier quality evaluations

were performed by the construction and quality groups as planned in the procedure.

These evaluations helped to determine the existing quality conditions of the

suppliers. After the common evaluation of the concerning staff, the transport

subcontractor and supplier of wooden formwork materials were evaluated as

insufficient in quality activities and eliminated from further business at least for a six

month. The replaced suppliers, which have ISO 9001 certification, began their

services at the seventh month for the transport and at the eleventh month for the

supplying of the wooden materials. However, the purchasing price differences in

their services can be considered as prevention cost and they are calculated in Table

A.36. In the calculation table, the total amounts and the costs of transportation and

purchasing of wooden elements in the months are given. Using the unit price

differences for the unit prices obtained from the accounting records, the total costs

of supplier quality evaluation for each month is obtained.

One of the most important procedures of the quality management system is the

Internal Quality Audits Procedure. According to this procedure, the organization

should conduct internal audits to determine if the quality management system

conforms to the requirements as well as documented procedures and if it is

implemented or maintained effectively. The quality manager has planned the time of

the audits as in every four months for the technical staff and ones in a year for the

whole of the organization. Since the system is to be implemented over the whole

organization in a long period of time, the audit overheads also increase with respect

to time. The first and third audits were applied only to the technical staff, whereas

the second audit was executed including the workers. The main overheads, given in

Table A.37, are considered as the costs of consumables, transportation cost of the

auditors and the overheads of the construction site and delay penalty for a half a

day in the second audit. Costs of consumables and transportation costs of the

auditors are taken from the organization’s accounting records, and the overheads of

the construction site is taken from the daily overheads with respect to the months

given in Table A.1.

Page 82: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

69

As emphasized in the Inspection and Testing Procedure, the design and

construction processes and the coming materials were inspected by using the

checklists, visual inspection, in-process inspection according to the instructions and

recording the conditions on the checklists, applying slump tests and strength tests at

concrete works, and water test for the canalets and HDPE pipes. The cost of the

inspection and testing activities were evaluated in the concept of appraisal costs,

which include the overheads of testing, costs of saving materials required to analyze

reports and store the appraisal data. These costs are given in Table A.38 by the

heading of cost of consumables used in inspections, which are obtained by the

accounting records.

In the prevention and appraisal costs analysis, it should be stressed that the given

personnel expenses for the quality staff in Table A.38 may be equally distributed on

the concerning quality system activities; such as incoming material and in-process

verifications, evaluation of stocks, process control, quality system design,

implementation and quality audits. For simplicity, they are added to the analysis as

the assignment costs of the staff.

5.3 DISCUSSION OF RESULTS

As a result of the cost analysis, the total monthly costs of quality are obtained by

summing the failure costs, prevention costs and appraisal costs as shown in Table

A.39. Having these three elements of the model, demonstrated in Section 3.3.2, the

curves which have the quality costs in vertical and quality progress in respect of the

months in horizontal scale were obtained. The data of the quality costs, shown in

Figure 5.5, are put for trendline application.

As can be seen from this figure, as the cost of quality related activities increases in

time, the cost of failures decreases, which is in agreement with Figure 3.2. The

reason for this increment may originate from the development and the activation in

the preventive and appraisal functions in time.

Page 83: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

70

0

5000

10000

15000

20000

25000

30000

35000

1 2 3 4 5 6 7 8 9 10 11 12

Quality Progress in Time (months)

Qua

lity

Cos

ts ($

)Failure Costs

Prevention and Appraisal Costs

Total Quality Costs

Total Quality Costs

Failure Costs

Prevention and Appraisal Costs

Figure 5.5- Cost versus Quality

Besterfield (2004) defines also the target of reduction as failure costs. The

decreasing trend of the failure costs, which are much higher than the increasing

trend of the prevention and appraisal costs, dominate also the tendency of the total

quality costs as in a reduction. Thus, it will be beneficial to demonstrate the

tendency of the failure costs separately.

The curves in Figure 5.6 show the costs of failures in the design and construction

activities monthly. Analyzing both curves, it can be concluded that the failure costs

reduce when a progress is obtained upon implementation of the quality

management. However, the distinction between the design and construction failure

Page 84: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

71

costs is a critical point to discuss. The design failure cost, approximately twice the

construction failure cost in the first month, dominates the tendency of the failure

costs especially for the first six months. At the end of one year, the total failure cost

in the design process is still higher than the total cost of construction activities,

which covers the incoming material verification and civil works. So, it can be

concluded that the design control is more critical to implement an effective quality

management system because the other activities start with the design.

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

1 2 3 4 5 6 7 8 9 10 11 12

Quality Progress in Time (months)

Qua

lity

Cos

ts ($

)

Design Failure Costs

Construction Failure Costs

Design Failure Costs

Construction Failure Costs

Figure 5.6- Design and Construction Failure Cost versus Quality

Differentiating the external and internal failure costs can be another tool to guide the

reasons of the poor quality. It is easily noticed in Figure 5.7 that the costs of internal

failures are much higher than the external failures for a long period of time. They

Page 85: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

72

can be taken down to the level of external failure costs in ten months through high

efforts of quality improvement. On the contrary of the industrial production in

factories, the construction industry is more susceptible to have internal failure costs,

where robotics and other forms of automation are almost not used during

production. Also, the construction activities are exposed to the natural conditions

more than the production in closed areas. So, the auto-control activities, such as

process control, inspection, and testing gain more importance in such an industry.

As a result, the target of reduction of failure costs should mainly cover preventing

the internal failures in the construction industry, which will also regulate the external

failures.

0

4000

8000

12000

16000

20000

24000

1 2 3 4 5 6 7 8 9 10 11 12

Quality Progress in Time (months)

Qua

lity

Cos

ts ($

)

Internal Failure Costs

External Failure Costs

Internal Failure Costs

External Failure Costs

Figure 5.7- Internal and External Failure Cost versus Quality

Page 86: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

73

CHAPTER 6

CONCLUSIONS

Quality management, in which interests have seen increased world-wide in the last

decade, causes discussions on the effects of its implementation and the quality

concept. Concerning the effects of the quality management implementation, different

researchers have different opinions. A number of them concluded that quality

management implementation reduces the cost of poor quality in a project and has

effects on business performance of organization, whereas others stated that project

costs increase as activities related to quality assurance increase.

In order to achieve the objectives of the current study, the procedures of the world-

wide quality standard, ISO 9001, were utilized and the study started with an

extensive review of the concept and requirements of this standard. The cost of

quality literature has been adopted to construct the quality costs model. The sample

irrigation project covers the irrigation near the Aksu River in Antalya with canalet

networks, was taken into account for the case study. Upon implementation of the

quality management over the irrigation project, it became evident that the

organization had net benefits as cost and time saving and improved its performance

for the further construction projects. The methods of measuring the quality

management implementation are found flexible enough to evaluate the effects of the

quality management implementation over the other water resources projects.

Implementation of the quality management system was observed to have positive

effects on the employee and employer satisfaction, product quality and business

performance by controlling the processes, education and training of the employee,

evaluating the supplier, spreading the external and internal communication on the

employee and controlling the measuring devices and the machinery. The case study

revealed that the model for quality costs developed in this study is applicable also in

the construction industry. This model can be used by the contractors and/or the

employers of the construction industry to inspect the cost of poor quality and to

improve their quality management implementation efforts. The case study further

shows that this model can be used to self-assess the quality improvement efforts of

the organization and measure their progress over time. By using the model in

Page 87: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

74

different areas of the project, the organization can rapidly determine the areas that

need urgent improvement.

Cost of quality data, useful as a measurement tool, can be used very effectively to

identify and prioritize improvement opportunities. First, it should be determined the

problem area using the cost analysis technique. Then, a team can be established,

composed of the quality manager, quality control engineer, site engineer, design

engineer, maintenance supervisor, and other appropriate personnel such as internal

supplier. Usually the team has sufficient authority and resources to enact corrective

or preventive action without approval of their superiors. Most of the quality

improvement projects will be directed toward reducing failure costs. Once the cause

of the problem has been determined, the team can concentrate on developing the

corrective action to control or, preferably, eliminate the problem. Follow-up activities

are conducted to ensure that the corrective action was effective in solving the

problem.

Further cost reductions are achieved by less inventory and work-in-progress costs

and reduced supervision and maintenance. The Deming cycle is used as the means

to systematically improve the methods, by focusing on the prevention and correction

of defects. This management loop given in Section 2.2 as attributed to Deming

(1986), advocates a Plan – Do – Check – Act (PDCA) Methodology for narrowing

the gap between the organization’s current performance and employer needs.

Page 88: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

75

REFERENCES

1- Beecroft D., “Cost Of Quality, Quality Planning and The Bottom Line”, Ancaster: Beecroft Inc, 2001 2- Besterfield Dale H., “Quality Control”, New Jersey: Prentice Hall, 2004 3- Blaney H.F., Criddle W.D., “Determining Water Requirements in Irrigated Areas from Climatological and Irrigation Data”, USDA-SCS Techical Paper No.96, 1950 4- CIF, “ISO 9000:2000–Quality Management Systems Standard for the Construction Industry”, Retrieved September 12, 2004, from the Construction Industry Federation (CIF) Web Site, http://www.cif.ie, 2004 5- CII, “Cost of Quality in Design and Construction”, Austin: Construction Industry Institute Publication 10-2, May 1989 6- Deming W.E., “Out Of The Crisis”, Cambridge: MIT CAES, 1986 7- FIDIC, “About FIDIC –Policies: Quality Of Construction”, Geneva: Executive Committee of International Federation of Consulting Engineers, January 2004 8- Hansen V.E., Israelsen O.W., and Stringham G.E., “Irrigation Principles and Practices”, New York: John Wiley and Sons, 1980 9- Horne C.F., “Internet Ancient History Sourcebook”, Retrieved September 12, 2004, from the Web Site of Paul Halsall, http://www.fordham.edu/ halsall/ancient/ hamcode.html, 1998 10- ISO, ISO 9001 Standard, Geneva: International Organization for Standardization, 2000 11- Juran J.M., Dr. Frank M. Gryna, “Quality Control Handbook”, New York: Mc Graw Hill, 1988 12- Kehoe Dennis F., “The Fundamentals Of Quality Management”, New York: Chapman & Hall, 1996 13- Kızılkaya T., “Irrigation and Drainage”, (in Turkish) Ankara: Publications of the Turkish State of Hydraulic Works, 1988 14- Mutafelija B.,Stromberg H., “Systematic Process Improvement Using ISO 9001:2000”, Boston: Artech House, 2003 15- Pereda H.F., “Quality Norm ISO 9001”, Retrieved January 11, 2005, from the Web Site of Information Service of Buscadores Professionals, http://www. buscarportal.com, 2000

Page 89: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

76

16- Schoonmaker Stephen J., “ ISO 9001 For Engineers and Designers”, New York: Mc Graw Hill, 1997 17- Stebbing L., “Quality Assurance”, New York: Ellis Horwood, 1993 18- Taylor J.R., “Quality Control Systems”, New York: McGraw-Hill, 1989 19- Terenzio U., Sbraccia A., “Types of the Prefabricated Flumes for Irrigation”, (in Turkish) Ankara: Publications of the Turkish State of Hydraulic Works, 1964 20- Tropp L., “Quality at Systime”, Retrieved January 11, 2005, from the Web Site of Systime Company, http://www.systime.net/systime-quality.asp, 2004

Page 90: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

77

APPENDICES

Page 91: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Personnel ($)

Nourishment ($)

Energy ($)

Communication ($)

Total Monthly Overheads

($)

Daily Overhead ($)

1 March 2002 15300 3630 325 490 19745 6372 April 17550 4200 350 550 22650 7553 May 17550 4300 355 570 22775 7354 June 19800 4900 405 550 25655 8555 July 19800 5000 400 600 25800 8326 August 20250 5600 400 610 26860 8667 September 20250 5400 395 630 26675 8898 October 19800 4850 415 800 25865 8349 November 10425 2100 700 350 13575 45310 December 10425 2150 900 200 13675 44111 January 2003 10425 2150 825 300 13700 44212 February 14700 3500 550 390 19140 684

Table A.1 - Calculations of Monthly/ Daily Overheads in the Construction Site

78

Months

Page 92: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Personnel ($)

Total Monthly Overheads

($)

1 March 2002 6750 69802 April 6750 69803 May 6750 69604 June 6750 69605 July 6750 69606 August 5625 57957 September 5625 58058 October 5625 58059 November 5625 582510 December 3375 352511 January 2003 3375 351512 February 5625 5845

194187194114

220

Daily Overhead ($)

225233225232225187

113209

180200150140

210210170180

Table A.2 - Calculations of Monthly/ Daily Overheads in the Design Office

79

Months Communication and Energy ($)

230230210

Page 93: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day Loss

Number of the Revised

Drawings

Number of the Scrap

Drawings

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1 3 4 13442 2 4 755 1446 57462 6 201634 3 6 20164 2 4 855 1446 594656 3 4 1344789 6 2016101112

20428TOTAL

Table A.3 - Cost Calculations for Design Non-Conformance 1 - (DNC-1)

80 117 219117 219

117 219

Description

117 219

Revision in route of P2-Y3-4-1

Revision in route of P2-Y3Revision in route of P2-Y5-9Cancellation of P2-Y9

Revision in route of P2-Y3-6

Revision in route of P2-Y10

Cancellation of P2-Y15

Surveying and Mapping

Cost ($)

Designing Cost ($)

117 219

117 219

117 219

Page 94: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Length of the

Damaged Canalets

(m)

Number of the

Damaged Footings

Height of the

Footings (cm)

Total Height of

the Footings

(cm)

Production Cost of the

Canalet $/m *1

Installation Cost of the

Canalet $/m *2

Production Cost of the

Footing $/cm *3

Installation Cost of the

Footing $/cm *4

Total Cost ($)

20 3 30 90 10.22 4.36 0.111 0.057 30755 10 40 400 10.22 4.36 0.111 0.057 86915 3 60 180 10.22 4.36 0.111 0.057 24915 2 50 100 10.22 4.36 0.111 0.057 236

1660

*1 - 2002 Profitless Unit Cost of the State of Hydraulic Works by job number 38.030

*2 - 2002 Profitless Unit Cost of the State of Hydraulic Works by job number 38.051

*3 - 2002 Profitless Unit Cost of the State of Hydraulic Works by job number 38.094*4 - 2002 Profitless Unit Cost of the State of Hydraulic Works by job number 38.104

Table A.4 - Cost Calculations of Replacing Canalets for Design Non-Conformance 2 - (DNC-2)

Replacing of Type 280 canalets and Type 4 footings

1

81

Description

TOTAL

Page 95: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day LossNumber of Revised Drawings

Surveying and

Mapping Cost ($)

Designing Cost ($)

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1 2 2 117 219 672

1 3 637 1446 6249

6921

82

TOTAL

Table A.5 - Cost Calculations of Redesign & Delay for Design Non-Conformance 2 - (DNC-2)

Description

Revision in Route of P2-Y5-1

Delay by getting rid of the demolition and reworks

Page 96: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Number of Deficiencies

Delays in Design (days)

Overheads of the Design Office

($)

Total Cost ($)

1 5 3 225 6753 2 233 4662 2 233 466

3 1 1 225 2252 1 232 2321 1 232 232

56 2 1 187 187789101112

2483

83

Description

Deficiency for elevationsDeficiency for coordinatesDeficiency for coordinatesDeficiency for elevations

Deficiency for coordinates

Table A.6 - Cost Calculations for Design Non-Conformance 3 - (DNC-3)

TOTAL

Deficiency for coordinatesDeficiency for coordinates

2

4

Page 97: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day LossNumber of

the Drawings

Daily Overhead Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1

2 2 1 755 1446 4402

3 1 1 735 1446 2181

3 - 1

4

5 1 1 832 1446 2278

6 2 1 866 1446 4624

7

8 1 1 834 1446 2280

8 - 1

910

11

1215765

Delay in the submission of the drawingsDelay in the approval of the drawings

TOTAL

Table A.7 - Cost Calculations for Design Non-Conformance 4 - (DNC-4)

84

Delay in the approval of the drawings

Delay in the approval of the drawings

Delay in the approval of the drawings

Description

Delay in the approval of the drawings

Delay in the submission of the drawings

Page 98: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months QuantityTotal Work

Time (days)

Total Work Time

(hours)

Re-Mobilization Cost of the

Crane ($/hour)*1

Re-Mobilization Cost of the Excavator ($/hour)*2

Re-Mobilization Cost of the

Truck ($/hour)*3

Estimated Re-Mobilization

Cost of the Workers and

Other Equipments

($/hour)

Total Cost ($)

1

2 1 8 68 1.29 0.72 0.13 0.10 152

3

4 1 6 51 1.29 0.72 0.13 0.10 114

56789101112

267

*1- Value of "N" is published by Turkish Ministry of Public Works and Settlement with equipment number 03.138*2- Value of "N" is published by Turkish Ministry of Public Works and Settlement with equipment number 03.005/2*3- Value of "N" is published by Turkish Ministry of Public Works and Settlement with equipment number 03.038/2

Description

Re -Mobilization for P2-Y11-1-3

Re -Mobilization for P2-Y3-1-585

Table A.8 - Cost Calculations for Design Non-Conformance 5 - (DNC-5)

TOTAL

Page 99: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

MonthsEstimated Avarage

Daily Delay (days)

Estimated Avarage Monthly Delay

(days)

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1 0.059 1.8 637 1446 3810

2 0.059 1.8 755 1446 3896

3456789101112

7706

Table A.9 - Cost Calculations for Design Non-Conformance 6 - (DNC-6)

86

Description

Cost of adjusting surveying parameter on site

Cost of adjusting surveying parameter on site

TOTAL

Page 100: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

MonthsNumber

of Excess Footings

Type of the

Footing

Height of the Footing

(cm)

Weight of the Footing

(ton)

Type of the

Saddle

Weight of the Saddle

(ton)

Loading and Unloading

Cost of one Footing/ Saddle $/ton * 1

Transporting Cost of one

Footing/ Saddle to the Stock Area

$/ton * 2

Total Cost ($)

1 2 1 70 0.071 100 0.031 3.06 2.10 1.051 1 1 80 0.078 100 0.031 3.06 2.10 0.561 1 3 100 0.153 180 0.056 3.06 2.10 1.081 2 3 120 0.208 180 0.056 3.06 2.10 2.721 2 3 150 0.258 180 0.056 3.06 2.10 3.242 1 1 80 0.078 100 0.031 3.06 2.10 0.562 1 1 100 0.092 100 0.031 3.06 2.10 0.632 1 3 90 0.142 180 0.056 3.06 2.10 1.022 3 4 90 0.179 280 0.096 3.06 2.10 4.262 2 5 120 0.268 400 0.126 3.06 2.10 4.073 1 4 90 0.179 280 0.096 3.06 2.10 1.424 2 3 60 0.110 180 0.056 3.06 2.10 1.714 1 4 70 0.154 280 0.096 3.06 2.10 1.295 2 4 90 0.179 280 0.096 3.06 2.10 2.846 2 4 150 0.303 280 0.096 3.06 2.10 4.127 1 4 140 0.288 280 0.096 3.06 2.10 1.988 1 3 90 0.142 180 0.056 3.06 2.10 1.028 1 4 90 0.179 280 0.096 3.06 2.10 1.429 1 3 80 0.132 180 0.056 3.06 2.10 0.97

87

Table A.10 - Cost Calculations for Design Non-Conformance 7 - (DNC-7)

Description

" "" "

" "

Loading and Transport" "

" "

" "

" "" "" "

" "

" "

" "" "" "

" "" "

" "

" "

Page 101: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

MonthsNumber

of Excess Footings

Type of the

Footing

Height of the Footing

(cm)

Weight of the Footing

(ton)

Type of the

Saddle

Weight of the Saddle

(ton)

Loading and Unloading

Cost of one Footing/ Saddle $/ton * 1

Transporting Cost of one

Footing/ Saddle to the Stock Area

$/ton * 2

Total Cost ($)

9 1 4 90 0.179 280 0.096 3.06 2.10 1.4210 1 1 70 0.071 100 0.031 3.06 2.10 0.5310 1 4 120 0.257 280 0.096 3.06 2.10 1.8211 1 4 100 0.191 280 0.096 3.68 2.73 1.8411 2 4 120 0.257 280 0.096 3.68 2.73 4.5312 2 4 150 0.303 280 0.096 3.68 2.73 5.12

50

*1 - 2002-2003 Profitless Unit Price Of The Turkish Ministry Of Public Works and Settlement by job number 09.019/1 *2 - 2002-2003 Profitless Unit Price Of The Turkish Ministry Of Public Works and Settlement by job number 07.006

Loading and Transport

Table A.10- (Continued)

Description

88

" "

" "

" "

" "

" "

Page 102: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day Loss Number of Drawings

Daily Overhead Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1234

5 2 10 832 1446 6746

6789101112

6746TOTAL

89

Table A.11 - Cost Calculations for Design Non-Conformance 8 - (DNC-8)

Designing Cost ($)

219

Description

Redesign for routes P2-Y12, P2-Y13-1

Page 103: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

MonthsDefective Material

(m3)

Unit Price of theTimber ($/m3)

* 1

Total Cost ($)

1 9 207 18631 3 207 62123 8 207 16564 6 207 124256 6 207 12426 3 207 621789 4 207 8281011 2 226 45212 1 226 226

8751TOTAL

Defect in the formwork scaffoldingDefect in the formwork scaffolding

Defect in the formwork scaffolding

Defect in the formwork scaffolding

Defect in the form material

*1 - 2002 - 2003 Unit Rates of Turkish Ministry of Public Works and Settlement for timber by material number 04.152

Table A.12 - Cost Calculations for Material Non-Conformance 1 - (MNC-1)

90

Description

Defect in the formwork scaffolding

Defect in the formwork scaffoldingDefect in the form material

Defect in the formwork scaffoldingDefect in the formwork scaffolding

Page 104: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day LossDaily

Overhead Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

123 0.5 735 1446 1091

4 0.5 855 1446 1151

56 0.5 866 1446 1156789101112

3397

91

Description

Insufficiency of fine aggregates and cement

Insufficiency of fine aggregates

Table A.13 - Cost Calculations for Material Non-Conformance 2 - (MNC-2)

Insufficiency of coarse aggregates

TOTAL

Page 105: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

MonthsAmount of the

Defective Materials

Unit Unit Price of The Material ($) Total Cost ($)

12 17 Bag 2 34

2 6 No 51.1 307

34 1.5 tn 190 28556789101112

626

*1 - 2002 Unit Rate of Turkish Ministry of Public Works and Settlement for bagged cement by material number 04.008*2 - 2002 Profitless Unit Price of the State of Hydraulic Works by job number 38.030 ,adjusted for 5 m long canalet*3 - 2002 Unit Rate of Turkish Ministry Of Public Works and Settlement for reinforcement steel by material number 04.253

92

Table A.14 - Cost Calculations for Material Non-Conformance 3 - (MNC-3)

Unconvenient storage of canalets Type 280 *2

Unconvenient storage of cement *1

Description

Unconvenient storage of reinforcement steel *3

TOTAL

Page 106: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day Loss

Number of the

Defective Cords

Type of the

Cord

Type of the

Canalet

Length of the

Canalet (m)

Length of the Cord (m)

Production Cost of the

Cord ($/m)

Installation Cost of the

Canalet ($/m) *1

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

123 17 180 1.45 0.85 213 13 280 1.70 0.85 193 9 400 1.95 0.85 15

3 0.03 5 280 280 5.0 1.70 4.36 735 1446 436

4 9 280 1.70 0.85 135 7 100 1.20 0.85 7

6 0.03 3 180 180 5.0 1.45 3.80 866 1446 265

6 0.03 3 100 100 5.0 1.20 3.04 866 1446 254

7 3 100 1.20 0.85 38 7 100 1.20 0.85 79101112

1040

*1 - 2002 Profitless Unit Price of the State of Hydraulic Works by job number 38.043, 38.047, 38.051

TOTAL

Defective cords Defective cords

Defective cords (over canalets)Defective cords (over canalets)

Defective cords

93

Table A.15 - Cost Calculations for Material Non-Conformance 4 - (MNC-4)

Description

Defective cords Defective cords

Defective cords

Defective cords (over canalets)

Defective cords

Page 107: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Number of the

Damaged Canalets

Day Loss

Type of the

Canalet

Length of the

Canalet (m)

Production Cost of the

Canalet ($/m) *1

Installation Cost of the Canalet

($/m) *2

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1 1 0.03 600 5 17.10 7.11 637 1446 1841 2 0.03 400 5 12.60 5.42 637 1446 3051 2 0.03 100 5 6.94 3.04 637 1446 2251 1 0.03 280 5 10.22 4.36 637 1446 1351 1 0.03 280 5 10.22 4.36 637 1446 1352 2 0.03 280 5 10.22 4.36 755 1446 2782 1 0.03 400 5 15.75 6.78 755 1446 1792 1 0.03 100 5 6.94 3.04 755 1446 1163 1 0.03 180 5 8.44 3.80 735 1446 1274 1 0.03 180 5 8.44 3.80 855 1446 1304 1 0.03 100 5 6.94 3.04 855 1446 1195 0.036 1 0.03 280 5 10.22 4.36 866 1446 1427 1 0.03 100 5 6.94 3.04 889 1446 1207 1 0.03 400 5 15.75 6.78 889 1446 1838 1 0.03 100 5 6.94 3.04 834 1446 1188 1 0.03 180 5 8.44 3.80 834 1446 13091011 1 0.03 280 5 12.06 5.19 442 1446 143

94

Capillary cracks

Defects in roughness

Table A.16 - Cost Calculations for Material Non-Conformance 5 - (MNC-5)

Capillary cracks

Seperation of the steel Seperation of the steel

Description

Capillary cracks

Seperation of the steel

Capillary cracks

Defects in roughness

Capillary cracksCapillary cracks

Seperation of the steel

Seperation of the steel

Capillary cracks

Seperation of the steel

Capillary cracks

Capillary cracks

Page 108: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Numbers of the

Damaged Canalets

Day Loss

Type of the

Canalet

Length of the

Canalet (m)

Production Cost of the

Canalet ($/m) *1

Installation Cost of the Canalet

($/m) *2

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

11 1 0.03 100 5 8.20 3.63 442 1446 11612 1 0.03 280 5 12.06 5.19 684 1446 150

3034

*1 - 2002-2003 Profitless Unit Price Of The State Of Hydraulic Works by job number 38.022, 38.026 , 38.030,38.033,38.036*2 - 2002-2003 Profitless Unit Cost Of The State Of Hydraulic Works by job number 38.043, 38.047, 38.051, 38.054,38.057

95

Capillary cracks

TOTALCapillary cracks

Table A.16- (Continued)

Description

Page 109: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day LossDaily

Overhead Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

12345 1 832 1446 227867 2 889 1446 467089101112

6948

96

Table A.17 - Cost Calculations for Material Non-Conformance 6 - (MNC-6)

Late delivery of the reinforcement steel

Late deliveries of the HDPE pipes

TOTAL

Description

Page 110: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Type of the

Canalet/ Footing

Length of the

Reinstalled Canalet

Length of the

Damaged Canalet

Number of the

Reinstalled Footings

Number of the

Damaged Footings

Height of the

Footing (cm)

Production Cost of the

Canalet $/m *1

Installation Cost of

the Canalet $/m *2

Production Cost of the

Footing $/cm *3

Installation Cost of

the Footing $/cm *4

Total Cost ($)

1 280/4 10 1 80 4.36 0.057 48

1 280/4 10 5 1 1 100 10.22 4.36 0.111 0.057 112

1 280/4 10 1 150 4.36 0.057 52

1 400/5 10 1 140 5.42 0.060 63

1 400/5 10 5 1 150 12.60 5.42 0.060 126

2

3 280/4 10 1 110 4.36 0.057 50

4 280/4 10 1 100 4.36 0.057 49

5 180/3 10 10 1 1 100 8.44 3.80 0.093 0.046 136

5 180/3 10 1 1 90 3.80 0.093 0.046 51

6

7

8 280/4 1 110 0.057 6

8 280/4 1 130 0.057 7

9

10 100/1 1 80 0.027 2

Replacing

Strengthening

Strengthening

Reinstallation

Replacing

Reinstallation

Replacing

Reinstallation

Strengthening

97

Reinstallation

Reinstallation

Table A.18 - Cost Calculations of Reworks for Civil Works Non-Conformance 1 - (CNC-1)

Description

Reinstallation

Page 111: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Type of the

Canalet/ Footing

Length of the

Reinstalled Canalet

Length of the

Damaged Canalet

Number of the

Reinstalled Footings

Number of the

Damaged Footings

Height of the

Footing (cm)

Production Cost of the

Canalet $/m *1

Installation Cost of

the Canalet $/m *2

Production Cost of the

Footing $/cm *3

Installation Cost of

the Footing $/cm *4

Total Cost ($)

11 100/1 1 100 0.032 3

11 280/4 1 70 0.068 5

11 280/4 10 5 1 90 12.06 5.19 0.068 118

12 180/3 1 100 0.055 6

12 280/4 10 1 1 150 5.19 0.133 0.068 82

916

*1 - 2002-2003 Profitless Unit Price of the State of Hydraulic Works by job number 38.026 , 38.030,38.033*2 - 2002-2003 Profitless Unit Priceof the State of Hydraulic Works by job number 38.047, 38.051,38.054*3 - 2002-2003 Profitless Unit Price of the State of Hydraulic Works by job number 38.093, 38.094,38.095*4 - 2002-2003 Profitless Unit Price of the State of Hydraulic Works by job number 38.101,38.103, 38.104,38.105

Replacing

Strengthening

Description

Replacing

Strengthening

98

Table A.18- (Continued)

Strengthening

TOTAL

Page 112: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Total Length of the

Reinstalled Canalets

(m)

Number of the Reinstalled

Canalet Members

Day Loss for one Member

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1 50 10 0.03 637 1446 62523 10 2 0.03 735 1446 1314 10 2 0.03 855 1446 1385 20 4 0.03 832 1446 27367891011 10 2 0.03 442 1446 11312 10 2 0.03 684 1446 128

1408

Delay due to reworks

Delay due to reworks

Delay due to reworksDelay due to reworks

Table A.19 - Cost Calculations of Delays for Civil Works Non-Conformance 1 - (CNC-1)

99

Description

TOTALDelay due to reworksDelay due to reworks

Page 113: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

# NosDiameter

(mm)Length

(m)Width

(m)Height

(m)Weight

(kg)Amount

155 / 20 = 3 3*2 = 6 6 12 3.63 0.888 19.34180 / 20 = 9 9*2 = 18 18 12 3.63 0.888 58.02(165+30) / 20 =10 10*2 = 20 20 12 3.63 0.888 64.4755 / 20 = 3 3*2 = 6 6 12 3.63 0.888 19.34(55 + 2*9) -5 = 68 2* 332 / 20 = 34 34 12 0.68 0.888 20.53(25+165+180 +2*9 = 388 2* 332 / 20 = 34 34 12 3.88 0.888 117.14(55 + 2*9) -5 = 68 2* 332 / 20 = 34 34 12 0.68 0.888 20.53

319.382

Outer 2 0.55 3.32 3.65(165 + 30 = 195) 1 1.95 3.32 6.47

1 1.80 3.32 5.98Inner (55-30 = 25) 2 0.25 3.32 1.66

1 1.65 3.32 5.48(180-30 = 150) 1 1.50 3.32 4.98

28.223

(2*55 + 180 + 165 + 30) = 485 1 4.85 0.30 3.32 4.834.83

Table A.20 - Quantity Calculations for Civil Works Non-Conformance 2 - (CNC-2)

100

Formworks

Total Amount (m2)Concrete Works (C25)

Total Amount (m3)

Reinforcement Steel Works

Job Type

Total Amount (kg)

Page 114: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

MonthsAmount of the Job

Day Loss

Unit Price of the R.C

Steel Works ($/ton) * 1

Unit Price of the

Formworks ($/m2) * 2

Unit Price of the Concrete

Works ($/m3) * 3

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

123 0.32 310.00 993 28.22 6.19 1753 4.83 33.38 1613 0.50 735 1446 1091456789101112

1526

*1 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 23.014*2 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 21.013*3 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 16.045

101

Delay due to reconstruction

TOTAL

Table A.21 - Cost Calculations for Civil Works Non-Conformance 2 - (CNC-2)

Cost of formworksCost of concrete works

Cost of reinforcement steel works

Description

Page 115: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

# NosDiameter

(mm)Length

(m)Width

(m)Height

(m)Weight

(kg)Amount

155 / 20 = 3 3*2*2 = 12 12 10 6.61 0.617 48.94100 / 20 = 5 5 * 2= 10 10 10 5.88 0.617 36.28220/20 = 11 11*2*2 = 44 44 10 6.61 0.617 179.45210/20 = 11 11*2 = 22 22 10 6.61 0.617 89.72(55 + 2*9) -5 = 68 73/20=4, 4*2*2=16 16 10 0.68 0.617 6.71(210+ 2*9) -5 = 223 557/20=28, 28*2=56 56 10 2.23 0.617 77.05(220+ 2*9) -5 = 233 630/20=32, 32*2=64 64 10 2.33 0.617 92.01(210+ 2*9) -5 = 223 630/20=32, 32*2=64 64 10 2.23 0.617 88.06Minus Siphon Ø 100 100/20=5, 5*2=10 -10 10 1.00 0.617 -6.17(220+ 2*9) -5 = 233 630/20=32, 32*2=64 64 10 2.33 0.617 92.01

704.062

Outer 2 0.55 6.30 6.931 1.00 5.57 5.572 2.20 6.30 27.721 2.10 6.30 13.23

Inner 2 0.25 6.30 3.151 1.00 5.57 5.572 1.60 6.30 20.161 1.50 6.30 9.45

Minus Siphon Ø 100 � /4 = 0,79 -0.79 1.00 1.00 -0.7990.99

3(210 + 220) *2 = 860 1 8.60 0.30 6.30 16.25Minus Siphon Ø 100 � /4 = 0,79 -0.79 1.00 0.30 1.00 -0.24Minus Canalet -1 1.00 0.30 0.73 -0.22

15.80

Table A.22 - Quantity Calculations for Civil Works Non-Conformance 4 - (CNC-4)

102

Reinforcement Steel Works

Job Type

Total Amount (kg)Formworks

Total Amount (m2)Concrete Works (C20)

Total Amount (m3)

Page 116: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Amount of the Job

Day Loss

Unit Price of the R.C Steel

Works ($/ton) * 1

Unit Price of the

Formworks ($/m2) * 2

Unit Price of the Concrete Works

($/m3) * 3

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

123 0.70 310.00 2173 90.99 6.19 5633 15.80 33.38 5273 1 735 1446 2181456789101112

3489

*1 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 23.014*2 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 21.013*3 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 16.045

103

Cost of reinforcement steel works

Description

Cost of formworksCost of concrete works

Table A.23 -Cost Calculations for Civil Works Non-Conformance 4 - (CNC-4)

TOTAL

Delay due to reconstruction

Page 117: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

# NosDiameter

(mm)Length

(m)Width

(m)Height

(m)Weight

(kg)Amount

154 8 12.00 0.395 255.96

1000/20 = 50 50 12 6.12 0.888 271.731000/20 = 50 50 12 5.18 0.888 229.99

757.682

Outer 130+25+25 = 180 3.14 180 10.00 56.52Minus Top Portion 180*60/360 =30 -3.14 30 10.00 -9.42Minus Bottom Portion -1 10.00 1.80 -18.00Inner 3.14 130 10.00 40.82Minus Bottom Portion 130*60/360 =22 -3.14 22 10.00 -6.91

63.013

Outer � /4 = 0,79 0.79 10.00 1.80 1.80 25.60Minus Inner -0.79 10.00 1.30 1.30 -13.35

12.25

Table A.24 - Quantity Calculations for the Civil Works Non-Conformance 5 - (CNC-5)

104 Formworks

Total Amount (m2)Concrete Works (C25)

Total Amount (m3)

Job Type

Reinforcement Steel Works

Total Amount (kg)

Page 118: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Amount of the Job

Day Loss

Unit Price of the R.C Steel

Works ($/ton) * 1

Unit Price of the Formworks

($/m2) * 2

Unit Price of the Concrete

Works ($/m3) * 3

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1234 0.76 310.00 2364 63.01 6.19 3904 12.25 33.38 4094 1 855 1446 2301456789101112

3336

*1 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 23.014*2 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 21.013*3 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 16.045

TOTAL

Delay due to reconstruction

105

Description

Table A.25 - Cost Calculations for the Civil Works Non-Conformance 5 - (CNC-5)

Cost of formworksCost of reinforcement steel works

Cost of concrete works

Page 119: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

# NosLength

(m)Width

(m)Height

(m)Amount

1Outer (75,28 - 71,88 = 3,40) 2 0.50 3.40 3.40

1 0.30 3.40 1.021 2.70 3.40 9.181 0.90 3.40 3.061 1.40 3.40 4.761 0.70 3.40 2.381 2.75 3.40 9.35

Inner 2 0.20 3.40 1.361 2.70 3.40 9.181 0.60 3.40 2.041 0.80 3.40 2.721 0.40 3.40 1.361 2.45 3.40 8.33

58.14

Table A.26 - Quantity Calculations for the Civil Works Non-Conformance 6 - (CNC-6)

Job Type

Formworks

Total Amount (m2)

106

Page 120: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Amount Of The Job

Unit Price of the Formworks ($/m2) * 1

Total Cost ($)

12 58.14 6.19 3603456789101112

360

*1 - 2002 Profitless Unit Price of the Ministry of the Public Works and Settlement by job number 21.013

107

TOTAL

Description

Table A.27 - Cost Calculations for the Civil Works Non-Conformance 6 - (CNC-6)

Cost of formworks

Page 121: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Diameter of the Butt - Welded

Pipes (mm)

Number of the Failures

Unit Price of the Butt Welding

($/no) * 1

12345 110 1 5.495 160 2 6.455 315 1 10.036 315 1 10.036 450 1 15.0278 160 2 6.458 250 1 8.528 315 1 10.03910 110 1 5.4910 160 1 6.4511 110 1 7.0811 315 1 12.9212

*1 - 2002 - 2003 Profitless Unit Prices of Turkish Bank of Provinces according to diameter by job numbers 36.021 / 06,09,13,15,18

108

Table A.28 - Cost Calculations for the Civil Works Non-Conformance 7 - (CNC-7)

" " 10

" " 6

" " 15

13

" " 713

5

" " 9

Defects in the butt welding" "

Total Cost ($)

TOTAL

" "

Description

117

" "

" "

" " 10

10

513

" "

Page 122: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day Loss Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1 0.25 637 1446 5212 0.50 755 1446 11012 0.50 755 1446 11012 0.50 755 1446 11013 0.50 735 1446 10913 1.00 735 1446 21813 0.50 735 1446 10914 0.50 855 1446 11515 0.75 832 1446 17095 1.00 832 1446 227867 0.25 889 1446 58489 Failure of the loader 3 0.25 453 1446 47510 1.00 441 1446 18871112

16267

Failure of the truck 2

Table A.29 - Cost Calculations for the Civil Works Non-Conformance 8 - (CNC-8)

Failure of the truck 1

TOTAL

Description

Failure of the loader 1

Failure of the excavator

Failure of the loader 1

109

Failure of the truck 3

Failure of the loader 1

Failure of the loader 3

Failure of the truck 2

Failure of the grayder

Failure of the loader 2Failure of the truck 2

Page 123: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

MonthsNumber of the

Replaced Canalets

Day Loss Type of the Canalet

Length of the Canalet

(m)

Installation Cost of the Canalet

($/m) *1

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

1 2 0.03 100 5 3.04 637 1446 1551 1 0.03 280 5 4.36 637 1446 841 1 0.03 400 5 5.42 637 1446 902 1 0.03 600 5 7.11 755 1446 1022 2 0.03 100 5 3.04 755 1446 1622 1 0.03 180 5 3.80 755 1446 852 2 0.03 280 5 4.36 755 1446 1763 1 0.03 180 5 3.80 735 1446 843 1 0.03 280 5 4.36 735 1446 873 1 0.03 400 5 5.42 735 1446 934 2 0.03 180 5 3.80 855 1446 1764 1 0.03 280 5 4.36 855 1446 915 1 0.03 100 5 3.04 832 1446 845 1 0.03 180 5 3.80 832 1446 875 2 0.03 280 5 4.36 832 1446 1806 1 0.03 280 5 4.36 866 1446 917 1 0.03 180 5 3.80 889 1446 897 1 0.03 400 5 5.42 889 1446 978 1 0.03 100 5 3.04 834 1446 848 1 0.03 180 5 3.80 834 1446 879 1 0.03 100 5 3.04 453 1446 72

" "

Reinstallation

" "

" "

" "

" "

" "

Table A.30 - Cost Calculations for the Civil Works Non-Conformance 9 - (CNC-9)

" "" "

" "

" "" "" "

" "

" "

Description

110

" "" "

" "

" "

" "" "

Page 124: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

MonthsNumber of the

Replaced Canalets

Day Loss Type of the Canalet

Length of the Canalet

(m)

Installation Cost of the Canalet

($/m) *1

Daily Overhead

Cost ($)

Daily Delaying Penalty

($)

Total Cost ($)

9 1 0.03 180 5 3.80 453 1446 769 2 0.03 280 5 4.36 453 1446 15810 1 0.03 180 5 3.80 441 1446 7611 1 0.03 280 5 5.19 442 1446 8311 1 0.03 400 5 6.45 442 1446 8912 2 0.03 100 5 3.63 684 1446 16412 1 0.03 280 5 5.19 684 1446 90

2991

*1 - 2002-2003 Profitless Unit Prices of the State of Hydraulic Works by job numbers 38.043, 38.047, 38.051, 38.054

" "

" "

Table A.30 - (Continued)

Description

" "" "

" "

" "

111

TOTAL" "

Page 125: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

1 2 3 4 5 6 7 8 9 10 11 12March April May June July August September October November December January February

Internal DNC-1 (Table A.3) 1344 7762 7962 1344 2016 20428DNC-2 (Table A.4) 1660 1660DNC-2 (Table A.5) 6921 6921DNC-3 (Table A.6) 675 932 225 464 187 2483DNC-5 (Table A.8) 152 114 267DNC-6 (Table A.9) 3810 3896 7706DNC-7 (Table A.10) 9 11 1 3 3 4 2 2 2 2 6 5 50

External DNC-4 (Table A.7) 4402 2181 2278 4624 2280 15765DNC-8 (Table A.11) 6746 6746

14419 17155 2407 8543 9027 6159 2 2282 2018 2 6 5 62025Internal MNC-1 (Table A.12) 2484 1656 1242 1863 828 452 226 8751

MNC-2 (Table A.13) 1091 1151 1156 3397MNC-3 (Table A.14) 341 285 626MNC-4 (Table A.15) 491 13 7 519 3 7 1040MNC-6 (Table A.17) 2278 4670 6948

External MNC-5 (Table A.16) 984 572 127 249 142 303 248 259 150 30343468 913 3364 2940 2285 3680 4976 255 828 711 376 23796

Internal CNC-1 (Table A.18) 401 50 49 187 14 2 126 88 916CNC-1 (Table A.19) 625 131 138 273 113 128 1408CNC-4 (Table A.23) 3489 3489CNC-5 (Table A.25) 3336 3336CNC-6 (Table A.27) 360 360CNC-7 (Table A.28) 28 25 31 12 20 117CNC-8 (Table A.29) 521 3302 4362 1151 3987 584 475 1887 16267CNC-9 (Table A.30) 329 525 264 267 351 91 186 171 306 76 171 254 2991

External CNC-2 (Table A.21) 1526 15261876 4186 9821 4940 4826 116 770 216 780 1977 431 469 30409

5344 5099 13185 7880 7111 3796 5746 471 1608 1977 1142 845 5420518779 17280 11759 16174 7114 5189 5445 225 3626 1979 889 700 89159984 4974 3833 249 9024 4766 303 2528 259 150 2707119763 22254 15592 16423 16138 9955 5748 2753 3626 1979 1148 850 116230

112

TOTAL EXT. FAILURE COSTS ($)TOTAL INT. FAILURE COSTS ($)

SUBTOTAL OF DNC ($)

SUBTOTAL OF MNC ($)

SUBTOTAL OF CNC ($)

Table A.31- Summary of the Failue Costs ($)

SUBTOTAL OF MNC+CNC ($)

DE

SIG

NM

ATE

RIA

LC

IVIL

WO

RK

S

TOTALType Nonconformances

TOTAL FAILURE COSTS ($)

Page 126: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Day Loss

Daily Overheads of Design Office

($)

Daily Overheads of Construction

Site ($)

Daily Delaying Penalty

($)

Charge Of the Consultant

($)

Total Cost ($)

1 1 225 2252 1 755 1446 220134 2 232 46445 2 187 345 7195 175 175556789101112

3784

113

Table A.32 - Cost Calculations for Preventive Training

Training of the design group

Description

Training of the design groupTraining of the construction groupTraining of the construction group

Training of the construction groupTraining of the design groupTraining of technicianTraining of quality control engineerTraining of storage employee

TOTAL

Page 127: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Total Cost ($)

123456 6156 2656 2906 2657 4107 2907 2657 907 290891011 64511 28011 31011 28012 43012 31012 28012 10012 310

5725

114

Table A.33 - Cost Calculations for Preventive Maintenance

Maintenance of the truck 3

Maintenance of the excavator

Maintenance of the truck 1Maintenance of the loader 2Maintenance of the grader

Maintenance of the roller

Maintenance of the truck 2Maintenance of the loader 3

Description

Maintenance of the truck 2

TOTAL

Maintenance of the excavatorMaintenance of the loader 1Maintenance of the truck 1

Maintenance of the loader 1

Maintenance of the loader 2Maintenance of the grader

Maintenance of the loader 3Maintenance of the rollerMaintenance of the truck 3

Page 128: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months

Total Cost

($)123

503

503

353

35456789

509

509

359

35101112

340

123M

eeting btw. designers and surveyors

27545

Meeting btw

. designers and construction group275

5M

eeting btw. designers and farm

ers65

6M

eeting btw. designers and em

ployer80

7M

eeting btw. designers and surveyors

2757

Meeting btw

. designers and employer

808

Meeting btw

. designers and employer

809

Meeting btw

. designers and employer

8010

Meeting btw

. designers and farmers

36010

Meeting btw

. designers and employer

8011

Meeting btw

. designers and employer

8012

Meeting btw

. designers and employer

801810

115

Calibration of the total station 2

Calibration of the total station 1

Description

Calibration of the total station 1

Calibration of the total station 2

Calibration of the distom

atC

alibration of the nivo

Table A.34 - C

ost Calculations for C

alibration

TOTA

L

Calibration of the distom

atC

alibration of the nivo

TOTA

L

Total Overheads ($)

Description

Months Table A

.35 - Cost C

alculations for Preventive C

omm

unication

Page 129: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Description

Number of Transport For HDPE

Pipes

Amount of the Purchased Wooden Elements

(m3)

Unit Price Difference in

Transport ($/Truck)

Unit Price Difference in

Wooden Materials

($/m3)

Total Cost ($)

12345678 Price difference in transport 2 30 609 Price difference in transport 4 30 12010 Price difference in transport 5 30 15011 Price difference in transport 3 30 9011 Price difference in wooden elements 30 15 45012 Price difference in transport 3 30 9012 Price difference in wooden elements 13 15 195

1155

Table A.36 - Cost Calculations for Supplier Quality Evaluation

116

TOTAL

Page 130: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

Months Description Day LossDaily Overhead

Cost of C.S. ($)

Daily Delaying Penalty

($)

Cost Of Consumables

($)

Total Cost ($)

1234 First internal audit 110 1105678 Second internal audit 0.5 834 1446 140 12809101112 Third internal audit 90 90

1480TOTAL

117

Table A.37 - Cost Calculations for Internal Quality Audits

Page 131: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

1 2 3 4 5 6 7 8 9 10 11 12

March

April

May

June

July

August

Septem

ber

October

Novem

ber

Decem

ber

January

February

Prevention CostsQuality Management System Consulting 625 625 625 625 2500Assignment of the Quality Manager 1700 1700 1700 1700 1700 1700 1850 1850 1850 1850 1850 1850 21300Assignment of the Quality Control Engineer 1200 1200 1200 1200 1200 1300 1300 1300 1300 1300 12500Assignment of the Quality Control Technician 900 900 900 900 900 900 900 6300Cost of Consumables Used in Documentations 32 118 345 325 325 200 175 138 125 138 125 88 2133Cost of Internal Quality Audits (Table 5.37) 110 1280 90 1480Cost of Supplier Quality Evaluation (Table 5.36) 60 120 150 540 285 1155Cost of Preventive Training (Table 5.32) 225 2201 464 894 3784Preventive Communication Costs (Table 5.35) 275 340 80 355 80 80 440 80 80 1810Preventive Maintenance Costs (Table 5.33) 1435 1345 1515 1430 5725Total Prevention Costs ($) 2582 4644 4145 4424 4459 5515 5825 5608 4375 4778 6310 6023 58687Appraisal CostsCost of Consumables Used in Inspections 30 30 40 50 50 60 80 90 120 110 100 100 860Calibration Costs (Table 5.34) 170 170 340Total Appraisal Costs ($) 30 30 210 50 50 60 80 90 290 110 100 100 1200Total Costs ($) 2612 4674 4355 4474 4509 5575 5905 5698 4665 4888 6410 6123 59887

Table A.38 - Summary of the Prevention and Appraisal Costs ($)

TOTA

L

118

Page 132: IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM ...M.S., Department of Civil Engineering Supervisor : Prof. Dr. A.Melih Yanmaz January 2005, 119 Pages There is a growing tendency in the

YearsInternal

Failure Costs ($)

External Failure Costs

($)

Total Failure Costs

($)

Prevention Costs

($)

Appraisal Costs

($)

Prevention & Appraisal

Costs ($)

Total Quality Costs

($)

2002 1 March 18779 984 19763 2582 30 2612 223752 April 17280 4974 22254 4644 30 4674 269283 May 11759 3833 15592 4145 210 4355 199474 June 16174 249 16423 4424 50 4474 208975 July 7114 9024 16138 4459 50 4509 206476 August 5189 4766 9955 5515 60 5575 155307 September 5445 303 5748 5825 80 5905 116538 October 225 2528 2753 5608 90 5698 84519 November 3626 3626 4375 290 4665 829110 December 1979 1979 4778 110 4888 6866

2003 11 January 889 259 1148 6310 100 6410 755812 February 700 150 850 6023 100 6123 6973

TOTAL 89159 27071 116230 58687 1200 59887 176117

Months

Table A.39 - Total Quality Costs ($)

119