impact of concession regime on the performance of nigerian
TRANSCRIPT
© 2021, IJSRMS All Rights Reserved 8
International Journal of Scientific Research in ___________________________ Research Paper. Multidisciplinary Studies E-ISSN: 2454-9312
Vol.7, Issue.10, pp.08-15, October (2021) P-ISSN: 2454-6143
Impact of Concession Regime on the Performance of Nigerian Seaports
I. Njoku1*
, C.C. Ibe2
1Department of Logistics and Transport Technology, Federal University of Technology Akure, Ondo State, Nigeria
2Department of Logistics and Transport Technology, Federal University of Technology Owerri, Imo State, Nigeria
*Corresponding Author: [email protected], Tel.: +2348036645117
Available online at: www.isroset.org
Received: 13/Oct/2021, Accepted: 19/Oct/2021, Online: 31/Oct/2021
Abstract— This study examines the impact of concession regime on the performance of Nigerian seaports. The essence is
to find out if the landlord port model adopted in 2006 is better than the service port model used since 1956. Data were
mainly derived from the Nigerian Port Authority abstract of ports operation statistics. The study used the t-test statistic to
analyse the general port performance using cargo throughput, turnaround time and berth occupancy ratio as variables. A
sample of six (6) major ports in Nigeria were analysed to rank and compare their pre- and post-concession efficiencies. The
study relied on input-oriented Data Envelopment Analysis (DEA) model, using Ship traffic and Cargo throughput as
inputs; and Total Number of Equipment, Berth length, Total Number of Berth and Total Number of Staff as outputs. The
study revealed a fluctuation in cargo movement during pre-concession era while the throughput continues to increase
unabated during the post concession era. The analysis also revealed that there is a significant difference between
turnaround time during pre and post concession periods and that there is no significant difference between pre and post
concession berth occupancy. The Onne port with an average of 86.80% was ranked the most efficient while Calabar was
the least with 42.27% efficiency level. This study recommends that the government should encourage public ownership
and private sector operations of the port infrastructure in Nigeria.
Keywords— Regime, concession, performance, model, throughput, infrastructure, efficiency
I. INTRODUCTION
A concession contract is, by definition, more complex than
a license, since it involves not only questions about service
provision and delivery, but also about adequate
maintenance of assets, investments to be made and risk
apportionment between the concessionaire and regulator.
Concession contracts can be regarded as an intermediate
solution between public ownership and full privatization of
a port. Private participation was introduced to achieve
efficiency gains in the industry and at the same time
political concerns are safeguarded by not making society
lose ownership of essential assets [1].
According to [2] port size and infrastructure, private sector
participation and quality of both cargo-handling and
logistics services are important determinants of efficiency.
Transport terminals’ efficiency intensely increases the
speed of transshipments and consequently, of supply
chains.
Also, time savings occasioned by requisite efficient port
infrastructure development has led to competitive
dynamism and has also offered itself as a catalyst for an
increased productivity in a given port system [3].
The competition among ports is more severe at the present
time than it used to be. Reference [4] considered that port
markets used to be described as monopolistic due to the
exclusive and immovable geographical location of the
ports and the unavoidable concentration of port traffic. The
development of international container and intermodal
transportation has changed the market structure from one
of monopoly to one where hardline competition takes place
worldwide. Many ports, no longer enjoy the monopoly of
handling the cargoes that is from their hinterland rather
they compete for cargoes from distant neighbouring ports.
Due to severe competition, many studies focus their
attention to measuring efficiency in ports. Reference [5]
are of the view that the analysis of individual ports and
terminals are essential for the health of the industry and the
survival and competitiveness of its players. In addition to
provision of valuable tool for the use of port managers and
operators, these studies also serve as input for regional port
planning and operations.
As a result of this, performance measurement has become a
fundamental issue to stakeholders in the port industry
globally. Ports in the West African sub region are not left
out of the new world order of severe competition and
technological changes in the port market.
The major problem in the Nigerian port industry is the
persistent performance gaps in sea ports and the need to
adapt the capacity of all ports to a new world order in the
maritime sector at a time when there is scarce public
Int. J. Sci. Res. in Multidisciplinary Studies Vol.7, Issue.10, Oct 2021
© 2021, IJSRMS All Rights Reserved 9
funding. Competitiveness and technological changes are
the new world order in the maritime industry. Due to the
inability of the ports to meet the growing gap between
demand and capacity, Nigerian ports have growingly been
under pressure to improve on their productivity and
efficiency by making sure that port services are provided
on an internationally competitive basis.
For ports, measuring performance is an essential tool in
order to sustain and increase competitiveness. In a nutshell,
the growth in ship size, advent of containerisation and
advances in cargo handling methods have imposed
substantial infrastructural requirement on seaports.
Besides, the rising incapability of the government to
funding state owned ports has led to deregulation and
hence removal of ports financing and management
functions from public to private sector. This shift in
responsibility placed much emphasis on productivity and
efficiency in the management of seaports. This is rational
given that privatized ports face competition and must be
productive and efficient to stay viable. This is actually the
condition and challenge facing Nigerian ports under the
concession regime. However, before the advent of port
concession (1956-2005), the Nigerian port system suffered
from numerous ills which inter alia included the
following:
i. High turnaround time for ships which lasted for
weeks, sometimes months, depending on the cargo
being loaded or discharged;
ii. Cargo-handling plants and equipment owned by the
NPA were few and mostly unserviceable leading to
shipping companies hiring these machines from
private sector sources after having paid NPA;
iii. Dwell time for goods in ports was prolonged due to
poor port management and as such overtime cargo
filled the most active seaports leading to port
congestion;
iv. Unproductive labour force; Labour for ship work was
held in the vice-grip of wharf overlords who
controlled dockworker unions and supplied less than
the manpower paid for.
v. Insecurity of cargo in the ports
vi. Multiple government agencies in the port, corrupt
practices and excessive charges, etc.
In order to tackle these problems, Nigeria undertook a
major port reform program which culminated in the
concession of all ports to the private operators. The port
concession programme in Nigeria was completed in 2006
after an international competitive bidding process. This led
to the emergence of 26 terminals which were concessioned
to private terminal operators on the Build, Operate and
Transfer (BOT) model. As a result of the reform, cargo
handling operations at the port was handed over to terminal
concessionaires, leaving NPA as the landlord. The
Nigerian ports witnessed a rapid transformation as a result
of this reform in which Nigerian ports were concessioned
to the port operators called concessionaires. This process
has singularly injected the much-needed private investment
fund into the process of port infrastructure development.
Thus, the central objective of this research is to analyse
and compare ports performance in pre and post concession
regimes. Whereas the specific objectives are to empirically
test the influence of time factor on port efficiency and to
determine port capacity utilisation with respect to berth
occupancy rate.
Hypotheses
H01: There is no significant difference between pre
and post concession ports’ performance
H02: There is no significant difference between pre
and post concession turnaround time
H03: There is no significant difference between pre
and post concession berth occupancy
II. RELATED WORK
There are divergent views among authors on the effects of
private sector participation on port efficiency. Reference
[6] investigated the impact of different types of port
ownership on technical efficiency of ports in the UK
employing the Translog production function. He did not
find any significant difference provided the policy
environment is competitive. Similarly, [7] assessed
different types of ownership and administrative systems in
the port sector by applying stochastic parametric frontier
approach and upheld that port performance is not a
function of ownership structure. In the same vein, [8]
studied the financial performance of Greek’s port new
governance model using a stochastic parametric frontier
approach; the result of the study indicated that despite
profitable results in majority of the Greek ports, the
financial statement raised doubt as to the efficiency of the
ports organisational structure.
Conversely, there are many empirical studies supporting
institutional reforms based on private sector participation
as a veritable tool to achieving higher efficiency in port
terminal operations. Particularly, [9] evaluated Mexico’s
port reform of privatisation and decentralisation using
Malmquist productive Index (MPI) the result showed
significant short-term improvements in performance. This
is collaborated by [10] on the study of Spanish port by
applying Translog and Cobb-Douglas production frontier
model which showed improved productivity due to
technological progress after the reform. Reference [11]
study of Portuguese ports using DEA - allocative and
technical efficiency, identified substantial improvements in
efficiency due to the reform. Similarly, [12] examined the
relative efficiency of major Asian container terminals
using Stochastic Frontier Analysis (SFA) using both cross-
sectional and panel data the result obtained supported view
that privatisation improves efficiency.
Besides, they argued that privatization has become a
strategy to gain competitive edge in the global market
Int. J. Sci. Res. in Multidisciplinary Studies Vol.7, Issue.10, Oct 2021
© 2021, IJSRMS All Rights Reserved 10
place. Reference [13] investigated the US public port
system and concluded that the US public port system is
dominated by inefficient operation as a result of political
interference and risk aversion. In conclusion, they argued
that the injection of private capital through privatisation
will increase efficiency. Reference [14] is of the view that
private investors and operators’ pursuit of profit
maximization objective may undermine long term
investment in facilities and services in a broader social
perspective. This is mostly true in regions with limited
competition; privatisation will then lead to private
monopolies of port facilities. The study of the efficiency of
27 Spanish 1985 to 1989 by [15] using a translog function
discovered that the most efficient Spanish ports are those
with more centralized management system than those with
autonomous management.
Reference [16] branded long pay-back period, high costs in
the port industry as factors that make outright sale and
complete transfer of operations and regulatory functions
counterproductive. He was of the view that complete
dependence on the private sector may result in delayed
investment in key operational facilities and equipment.
Reference [17] pointed out the need to critically look at the
conceptual and methodological aspects of each reform in
order to gain a global view of the influence of institutional
reforms on national ports efficiency.
The key issue is, whether the efficiency gap in a nation’s
port sector can be explained by the difference of port
ownership and institutional structure and if private sector
participation and port reforms have enabled inefficient
ports to become more efficient. Reference [18] employed
the Stochastic Frontier Analysis in benchmarking container
port technical efficiency in Latin America and the
Caribbean (LAC). The results derived from the model
reveals that, between 1999 and 2009, port technical
efficiencies in LAC ranged between 5% in Rosario to 93%
in San Juan. The overall average is 41.7% and the standard
deviation is 21.4%. This result demonstrates that even the
most technically efficient port in the region still has space
for improvement and, conversely, the least technically
efficient port has a very large gap to close regarding the
frontier.
III. METHODOLOGY
Sources of Data This research entirely relied upon secondary information
for the analysis. The data were obtained from the NPA
Annual Reports and Abstract of Port Statistics, internet,
dissertations and other relevant textbooks.
Methods of Data Analysis
This research made use of t-Test statistic and Data
Envelopment Analysis (DEA). Firstly, the study made a
holistic assessment of the performance of the 26 terminals
in Nigeria. In this case, Cargo throughput, Ship turnaround
time and Berth Occupancy were used as variables and the
two-sample t-Test was used in analyzing these data to test
the difference between the sample means for the pre and
post concession era to substantiate if there is any statistical
significance. The variables used were taken within the
range of seven years of pre concession (1999-2005) and
seven years of post-concession (2006-2012). Secondly, the
study analysed a sample of six (6) major ports in Nigeria to
confirm the difference between the pre and post concession
performance. The analysis was based on ranking and
comparing the pre- and post-concession efficiency gains of
the following ports namely: Lagos Port Complex, Tin Can
Island Port, Delta Port Complex, Rivers Port Complex,
Onne Port Complex and Calabar Port Complex.
The most efficient port was used to benchmark the others.
Parameters such as Ship traffic, Cargo throughput, Total
Number of Equipment, Berth length, Total Number of
Berth and Total Number of Staff were employed as
variables using Data Envelopment Analysis to assess the
efficiency of the ports. The variables used were equally
taken within the range of seven years of pre concession
(1999-2005) and seven years of post-concession (2006-
2012). Other analytical tools include the use of
percentages, charts and graphs, where applicable.
t-Test Statistic
To test the research hypotheses, data in tables 1, 5 and 9
were analysed using t-Test Statistic. The equation of the
t-Test Statistic is presented as follows.
√
Where:
√
Decision Rule:
Reject the H0 if the computed t is greater than the table
value and does not fall within the acceptance region.
Otherwise accept H0.
H0: refers to null hypothesis
H1: refers to alternative hypothesis
Data Envelopment Analysis (DEA)
DEA is a non-parametric efficiency evaluation model
based on mathematical programming theory [19]. It is used
in econometrics and operations research for multi-variant
frontier estimation and ranking which can be employed in
the calculation of efficiency levels within a group of
organisations. This is accomplished by calculating the
relative performance of the units being investigated to the
group’s best practice. Reference [20] assert that efficiency
is a relative term that can be measured by the process of
benchmarking. There are two types of efficiency;
Technical and Scale efficiency. Reference [5] define
technical efficiency as relative productivity over time or
Int. J. Sci. Res. in Multidisciplinary Studies Vol.7, Issue.10, Oct 2021
© 2021, IJSRMS All Rights Reserved 11
space or both and scale efficiency as possible divergence
between actual and ideal production size.
The concept of DEA is developed from the basic idea that
efficiency of a DMU is determined by its ability to convert
inputs into desired outputs. This idea of efficiency was
adopted from engineering which defines efficiency of a
machine/process as output/input ≤ 1. In this approach,
efficiency is always less than or equal to unity as some
energy loss will always occur during transformation
process. There are various models of the DEA
methodology; however, DEA Window Analysis model was
used in this research to calculate the average efficiency
using CCR and BCC model. This version of DEA was first
used by Charnes et al (1985); window analysis is a time-
dependent version of DEA which is applied with panel
data. The basic idea is to treat each port as if it was a
different port in each of the years under review. Each
port’s performance is not only compared with that of other
ports but also against its own performance at different
times. This approach is necessary since we are comparing
the performance of Nigerian ports at different times and
with different ownership structures.
From the study, four inputs and two outputs were utilized
in the derivation of the efficiency level:
a) Input 1- Berth length
b) Input 2- Total No. of Berth
c) Input 3- Total No. of Equipment
d) Input 4- Total No. of Staff
e) Output 1- Cargo Throughput
f) Output 2 - Total Ships Traffic
The Basic Mathematical Formulation of DEA is presented
as follows:
Maximize
{∑
}
{∑ }
Subject to
{∑ }
{∑ }
Where:
Eb is the efficiency of any unit b
yrj is observed quantity of output r produced by unit j = 1,
2…, N
xij is observed quantity of input I used by unit j = 1, 2…, N
urb is the weight (to be determined) given to output r by
base unit b
vib is the weight (to be determined) given to input i by base
unit b
c is a very small number
IV. RESULTS AND DISCUSSION
Test of Hypothesis 1
H01: There is no significant difference between pre and
post concession ports’ performance
Table 1. Variables for Test of Hypothesis 1
CARGO THROUGHPUT
Year X1 (pre-concession) Year X2 (post-
concession)
1999 22232936 2006 46150518
2000 28932880 2007 57473350
2001 35940692 2008 63982749
2002 36987241 2009 65775509
2003 39765945 2010 76744727
2004 40816947 2011 83450032
2005 44952078 2012 77104738
Source: Nigerian Ports Authority (1999 - 2012)
To test Hypothesis 1, the data in Table 1. were analysed
using t-Test statistic and the result is as shown in Table 2,
Table 3 and Table 4. The table value t = 0.025(12) = ±2.19
at 0.05 significance with 12.0 degrees of freedom. Since
the computed value tc = -13.21 is more than the critical
value -2.19 (i.e., in absolute terms) and falls outside the
acceptance region, thus, we reject H0 and accept H1 and
conclude that there is a significant difference between pre
and post concession ports performance. In Table 2, the
mean of X1 is 35661245.57 which is the average cargo
throughput of the pre concession period. This is lower than
67240231.85 which is the mean of X2 which is the cargo
throughput of the post concession period. This implies that
the average cargo throughput of post concession period
doubled that of pre concession period.
Table 2. Paired Samples Statistics 1
Mean N
Std.
Deviation
Std. Error
Mean
Pai
r 1
x1 35661245.5
714 7
7715526.955
73
2916195.079
81
x2 67240231.8
571 7
12931396.86
599
4887608.601
73
Table 3 shows a positive correlation of 0.9 between X1 and
X2 and Table 4 shows that the calculated t = -13.21 is more
than -2.19 table value in absolute terms.
Table 3. Paired Samples Correlations 1
N Correlation Sig.
Pair 1 x1 & x2 7 0.936 0.002
Table 4. Paired Samples Test 1 Paired Differences t d
f
Sig.
(2tail
ed) Mea
n
Std.
Deviatio
n
Std.
Erro
r
Mean
95%
confidence
interval of
the
Difference
Low
er
Upp
er
Pa
ir
x1-
x2
-
3E+0
07
6323338
.620
2389
997
-
4E+0
07
-
3E+0
07
-
13.2
13
6 .000
Int. J. Sci. Res. in Multidisciplinary Studies Vol.7, Issue.10, Oct 2021
© 2021, IJSRMS All Rights Reserved 12
Fig1. shows that trend of cargo throughput during post
concession increased sharply as against the pre concession.
It rose from 44952078mt in 2005 to 77104738mt in 2012
which translates to 72% increase.
Fig1. Pre and Post concession’s Trend of Cargo Throughput
Test of Hypothesis 2
H02: There is no significant difference between pre and
post concession turnaround time
Table 5. Variables for Test of Hypothesis 2
TURNAROUND TIME (DAYS)
Year X1 (pre-
concession)
Year X2 (post-concession)
1999 6.31 2006 5.31
2000 7.01 2007 3.75
2001 7.91 2008 4.59
2002 11.34 2009 6.55
2003 7.89 2010 5.38
2004 6.44 2011 5.48
2005 7.40 2012 5.75
Source: Nigerian Ports Authority (1999 - 2012)
To test Hypothesis 2, the data in Table 5 were analysed
using t-Test statistic and the result is as shown in Table 6,
Table 7 and Table 8. The table value t = 0.025(12) = ±2.19
at 0.05 significance with 12.0 degrees of freedom. Since
the computed value tc = 4.71 is more than the critical value
2.19 and falls outside the acceptance region, we therefore,
reject
H0 and accept H1 and draw a conclusion that there is a
significant difference between turnaround time during pre
and post concession periods. In Table 6, the mean of X1 is
7.75 which is the average turnaround days of the pre
concession period. This is higher than 5.25 which is the
mean of X2 which is the average turnaround days of the
post concession period. This implies that turnaround time
in pre concession period than that post concession period.
Table 6. Paired Samples Statistics 2
Mean N
Std.
Deviation
Std. Error
Mean
Pair 1 x1 7.7571 7 1.70258 0.64352
x2 5.2586 7 0.88492 0.33447
Table 7 shows a positive correlation of 0.56 between X1
and X2 and Table 8 shows that the calculated t is equal to
4.7.
Table 7. Paired Samples Correlations 2
N Correlation Sig.
Pair 1 x1 & x2 7 0.567 0.184
Table 8. Paired Samples Test
Paired Differences T d
f
Sig
.
2tail
ed
Me
an
Std.
Devi
ation
Std.
Erro
r
Mea
n
95%
confidence
interval of
the
Difference
Low
er
Uppe
r
Pair
x1-x2
2.49
857
1.40
465
.5309
1
3.79
766
4.7
06
6 .00
3
Fig 2 indicates that the trend of vessel turnaround time
during post concession period is decreasing as against the
trend in pre concession period. There was an average of
5.5days turnaround time at the post concession against
7.7days turnaround time at the pre concession. This means
a 32% reduction in number of days a vessel would have
waited to have its cargo discharged.
Fig. 2 Pre & Post Concession’s Trend of Vessel Turnaround
Time
Test of Hypothesis 3
H03: There is no significant difference between pre and
post concession berth occupancy
Table 9. Variables for Test of Hypothesis 3
BERTH OCCUPANCY (%)
Year X1 (pre-concession) Year X2 (post-concession)
1999 47.09 2006 48.49
2000 44.76 2007 44.95
2001 51.78 2008 36.72
2002 56.58 2009 47.46
2003 52.75 2010 51.21
2004 50.93 2011 51.45
2005 49.70 2012 45.92
Source: Nigerian Ports Authority (1999 - 2012)
To test Hypothesis 3, the data in Table 9 were analysed
using t-Test statistic and the result is as shown in Table 10,
Table 11 and Table 12. The table value t = 0.025(12) =
0
10,000,000
20,000,000
30,000,000
40,000,000
50,000,000
60,000,000
70,000,000
80,000,000
90,000,000
0
2
4
6
8
10
12
Series1, 1999, 6.31 Series1, 2000, 7.01
Series1, 2001, 7.91
Series1, 2002, 11.3
Series1, 2003, 7.89
Series1, 2004, 6.44
Series1, 2005, 7.4
Series1, 2006, 5.31
Series1, 2007, 3.75 Series1, 2008, 4.59
Series1, 2009, 6.55
Series1, 2010, 5.38 Series1, 2011, 5.48 Series1, 2012, 5.75
Int. J. Sci. Res. in Multidisciplinary Studies Vol.7, Issue.10, Oct 2021
© 2021, IJSRMS All Rights Reserved 13
±2.19 at 0.05 significance and 12.0 degrees of freedom.
Since the calculated value tc = 1. 703 is less than table
value t = 2.19 and falls within the acceptance region, thus,
we accept H0 and conclude that there is no significant
difference between pre and post concession berth
occupancy. The reason for the acceptance of H0 here is
informed by the Decision Rule of the t-Test statistic (as in
3.3.1 in Chapter Three) which states that H0 should be
accepted if tc is less than the table value. In Table 10, the
mean of X1 is 50.51 which is the average berth occupancy
rate of the pre concession period and is higher than 46.6
which is the mean of X2 which is the average berth
occupancy rate of the post concession period. This means a
7.7% reduction in pre concession berth occupancy rate.
Table 10. Paired Samples Statistics 3
Mean N
Std.
Deviation
Std.
Error
Mean
Pair 1 x1 50.5129 7 3.85285 1.45624
x2 46.6000 7 4.99809 1.88910
Table 11 shows a positive correlation of 0.075 between X1
and X2 while Table 12 shows that the calculated t is equal
to 1.703.
Table 11. Paired Samples Correlations 3
N Correlation Sig.
Pair 1 x1 & x2 7 .075 .874
Table 12. Paired Samples Test 3
Paired Differences t d
f
Sig.
2tai
led Me
an
Std.
Devia
tion
Std.
Erro
r
Mea
n
95%
confidence
interval of
the
Difference
Low
er
Uppe
r
Pair
x1-x2
3.91
268
6.079
08
2.297
68
-
1.709
35
9.535
07
1.7
03
6 .139
Fig 3 signifies that the trend of berth occupancy during
post concession period slightly declined as against the
trend in pre concession period. There was an average of
51% occupancy rate at the pre concession against 47%
occupancy rate at the post concession. This implies a 7.7%
decrease in occupancy rate at the ports.
Fig 3. Pre & Post Concession’s Trend of Berth Occupancy
4.4 DEA Based Efficiency Measurement of Nigerian
Ports
The study analysed the efficiency of six Nigerian ports
namely Lagos Port Complex, Tin Can Island Port, Delta
Port Complex, Rivers Port Complex, Onne Port Complex
and Calabar Port Complex; seven years before concession
and seven years after i.e., 1999-2012 using the DEA
Window technique to capture the trend of efficiency
changes over the period under review. The data for this
analysis are contained in Table 13 and the result is as
shown in Table 14.
Table 13. Input and Output Variables for DEA Analysis
Ports
Year
Inputs Outputs
1 2 3 4 1 2
Berth
Length
No. of
Berths
Total
No. of
Equipt.
Total
No.
of
Staff
Throughput
(Tons)
No.
of
Ship
Calls
LPC 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
15 15 15 15 15 15 15 15 15 15 15 15 15 15
98 99 98 92 85 80 81 81 81 80 80 80 89 97
3110 3027 2894 2943 2817 2731 2179 760 959 717 726 712 664 661
7890170 9164477 11461451 11754539 11875265 12294640 13432106 15112819 18547253 20809224 21566202 21239855 22808353 19957706
837 858 1022 929 882 891 955 1376 1359 1452 1545 1588 1594 1444
TCIP
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
1045 1045 1045 1045 1045 1045 1045 1045 1045 1045 1045 1045 1045 1045
5 5 5 5 5 5 5 5 5 5 5 5 5 5
79 81 85 89 96 101 101 137 145 150 168 188 188 190
1279 1276 1264 1372 1376 1362 1131 850 799 668 637 604 537 530
2921032 3138007 4133077 4105028 4583505 4075386 4743741 7399531 10003300 12807920 13541016 14461638 16230591 15281010
357 435 474 405 549 504 495 903 1185 1367 1389 1504 1628 1507
Delta Ports
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
1790 1790 1790 1790 1790 1790 1790 1790 1790 1790 1790 1790 1790 1790
11 11 11 11 11 11 11 11 11 11 11 11 11 11
123 79 55 54 56 56 56 80 88 82 60 60 62 64
1271 1216 1214 1206 1169 388 942 836 480 426 424 422 411 410
1146946 1612034 1480163 1668663 1635847 1296050 1922254 1162404 1249763 1913238 6590471 9807661 8538831 6987533
331 266 307 292 261 229 295 193 205 246 321 341 362 109
Rivers Port
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
1117 1117 1117 1117 1117 1117 1117 1117 1117 1117 1117 1117 1117 1117
8 8 8 8 8 8 8 8 8 8 8 8 8 8
77 77 64 53 40 49 56 59 58 65 60 68 71 74
1322 1252 1243 1286 1249 1096 929 868 506 424 415 407 391 390
1933830 2255178 3518229 3666413 3702553 3210907 3516188 3001019 3112518 3488791 5141451 5808533 7463620 5574653
271 265 313 329 303 261 239 270 317 378 459 482 584 461
Onne Port
Complex
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
2063 2063 2063 2063 2063 2063 2063 2063 2063 2063 2063 2063 2063 2063
8 8 8 8 8 8 8 8 8 8 8 8 8 8
1 1 2 2
13 13 13 40 45 48 48 55 58 60
383 368 375 595 392 1185 362 336 206 572 499 459 207 205
2527970 7166436 9056487 10182079 11994981 2158548 2554328 2535759 2482177 3144943 23832763 17215120 2470112 27580642
241 342 479 532 554 390 423 444 394 379 689 769 885 873
0
10
20
30
40
50
60
199
9
200
0
200
1
200
2
200
3
200
4
200
5
200
6
200
7
200
8
200
9
201
0
201
1
201
2
Berth Occupancy
Int. J. Sci. Res. in Multidisciplinary Studies Vol.7, Issue.10, Oct 2021
© 2021, IJSRMS All Rights Reserved 14
Calabar 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
1037 1037 1037 1037 1037 1037 1037 1037 1037 1037 1037 1037 1037 1037
8 8 8 8 8 8 8 8 8 8 8 8 8 8
70 69 70 46 38 34 38 32 38 44 51 56 58 61
598 583 566 393 597 264 590 459 274 254 262 265 261 261
226635 300124 324866 399595 481062 752910 857726 776787 949523
1245599 1721249 1594277 1878753 1723195
140 207 154 109 163 213 276 321 897 351 321 197 179 303
Source: NPA Annual Reports and Abstract of Port Statistics LPC ≡ Lagos Port Complex and TCIP ≡Tin Can Island Port
Result of the DEA
Table 13 gives is an overview of the input and output data
used for the analysis. The result of this analysis as
presented in table 14 shows that the efficiency of virtually
all the ports, except Onne port, fluctuated in the period
before the concession but experienced remarkable increase
in the concession regime. The Onne port recorded a
significant and stable efficiency before and during the
concession regime. The good performance of this port in
pre concession era may be attributed to a kind of partial
concession to INTELS which it enjoyed as at that time and
the outstanding performance during concession regime as a
result of full concession. The port scored 86.1% and
ranked Number One port while LPC recorded 73.6 to
emerge Number Two port. TCIP, Rivers and Warri ports
ranked Number Three, Four and Five ports respectively.
Table 14. Average Relative Efficiencies (%) of Six Sample Ports
Ports Year LPC TCIP Warri Rivers Onne Calabar
1999 54.0 58.9 48.0 55.0 90.0 26.8
2000 64.4 61.2 58.2 56.5 95.0 24.7
2001 58.5 54.0 55.1 51.1 91.0 26.8
2002 55.8 54.0 52.0 57.0 93.0 40.2
2003 57.2 54.0 43.0 53.3 67.1 68.5
2004 65.3 54.0 52.7 51.2 82.2 47.2
2005 69.3 71.4 56.6 59.8 79.0 50.0
2006 86.7 89.7 60.1 71.4 89.7 58.7
2007 97.4 85.9 64.9 59.8 79.5 53.8
2008 92.1 86.2 69.3 71.4 87.6 59.7
2009 90.1 86.2 69.4 79.9 85.3 55.4
2010 75.4 86.2 72.6 90.1 70.5 19.3
2011 91.0 83.5 72.6 95.1 95.0 24.7
2012 64.1 73.0 73.3 78.1 100 24.3
Average 73.6 73.0 56.9 66.4 86.1 41.4
Source: Result of DEA analysis 2019
Table 15 deals with result of the pre-concession
efficiencies of the ports. It is remarkable to note that Onne
port continues to lead with 85.33% this time while Calabar
maintains the last position with 40.60%.
Table 15. Pre-Concession Ports Efficiencies Ports Year LPC TCIP Warri Rivers Onne Calabar
1999 54.0 58.9 48.0 55.0 90.0 26.8
2000 64.4 61.2 58.2 56.5 95.0 24.7
2001 58.5 54.0 55.1 51.1 91.0 26.8
2002 55.8 62.8 52.0 57.0 93.0 40.2
2003 57.2 54.8 43.0 53.3 67.1 68.5
2004 65.3 60.4 52.7 51.2 82.2 47.2
2005 69.3 71.4 56.6 59.8 79.0 50.0
Average 60.64 60.50 52.23 54.84 85.33 40.60
Rank 2 5 4 1 6
Source: Result of DEA analysis 2019
Table 16 shows the result of the post-concession
efficiencies of the ports. It is also interesting to note that
Onne port maintains the lead with 86.80% where Calabar
retained the last position with 42.27%.
Table 16. Post-Concession Ports Efficiencies Ports Year LPC TCIP Warri Rivers Onne Calabar
1999 86.7 89.7 60.1 71.4 89.7 58.7
2000 97.4 85.9 64.9 59.8 79.5 53.8
2001 92.1 86.2 69.3 71.4 87.6 59.7
2002 90.1 90.6 69.4 79.9 85.3 55.4
2003 75.4 67.2 72.6 90.1 70.5 19.3
2004 91.0 83.5 91.6 95.1 95.0 24.7
2005 64.1 95.4 73.3 78.1 100.0 24.3
Average 85.26 85.50 71.60 77.97 86.80 42.27
Rank 3 2 5 4 1 6
Source: Result of DEA analysis 2019
V. CONCLUSION AND FUTURE SCOPE
The result of the analysis shows that the pre concession era
witnessed a fluctuation in cargo throughput while the post
concession era recorded spectacular increase in throughput.
The study also reveals that the average turnaround time of
7.34days at the pre concession period went down to 5.25 at
post concession period. This shows a 32.25% decrease.
The Berth Occupancy Rate declined from an average of
51% to an average of 47%. This implies a 7.7% decrease in
occupancy rate at the ports. The berth occupancy at
average of 47% in the ports is low. This implies under
capacity utilization of the ports. This is because
international standard recommends berth occupancy values
within the range of 60% and 80% as the safest to aim at.
Personnel strength of the NPA naturally, reduced from an
average of 1233 at pre-concession period to 503 at post-
concession. The analysis as well reveals that out of the six
sample ports assessed, Onne port complex with an average
of 86.80% maintained a lead in the post-concession regime
and thus ranked the most technically efficient port while
Calabar was the least with 42.27% efficiency level in same
period. These results agree with the views of authors who
believed that port reforms and private sector participation
have positive effects on port efficiency. The participation
of the private sector has proven to be a key ingredient in
improving the fortunes of Nigerian Ports. The Nigerian
environment and its port sector in particular equally proved
to be conducive for private sector participation.
The study made the following findings based on the
strength of these objectives;
a) That the concession regime has a tremendous
positive impact on the performance of Nigerian
seaports with an upsurge in cargo throughput.
b) That there is a reduction in turnaround time and
vessel/cargo dwell time in ports.
c) That there is no significant difference between pre
and post concession berth occupancy
d) That there is a significant difference in the nature
of models on the trend of cargo movement in pre
and post concession
Int. J. Sci. Res. in Multidisciplinary Studies Vol.7, Issue.10, Oct 2021
© 2021, IJSRMS All Rights Reserved 15
A lot of infrastructures have been put up in the ports during
the concession regime and thus there is need for properly
maintenance of these facilities. Beside the fact that
adequate maintenance of the infrastructure will lead to
greater productivity, Nigeria would have acquired adequate
infrastructural foundations upon which her future port
growth and development will be sustained. Given the
upsurge in cargo throughput in the post-concession regime,
government should be proactive, knowing that this
portends future port congestion problems and should use
the present data to plan for the future development of the
ports. Since the participation of the private sector has
proven to be a key ingredient in improving the fortunes of
Nigerian ports, government should support more public
ownership and private sector operations of the port system.
The average turnaround time at post concession period is
5.25. This is not yet down to 48hours international
standard for ship turnaround time. The port operators
should strive hard to improve on this. In effect,
government should also strive to reduce customs clearance
in the port to 24 hours. It will help reduce the average
turnaround time at the ports. Finally, the berth occupancy
rate at an average of 47% in the post concession regime is
poor. This means the concessionaires should beef up their
efforts to attract more vessels to the ports so as to meet up
with the international standard of 60-80% range of
occupancy rate.
ACKNOWLEDGMENT
We wish to express our profound gratitude to these two
institutions — Federal University of Technology, Akure
and Federal University of Technology Owerri, for
providing the insight, expertise and conducive environment
that are very helpful in research.
REFERENCES
[1] C. Crampes and A. Estache, ‘Regulatory Tradeoffs in Designing
Concession Contracts for Infrastructure Networks’, World Bank/Economic Development Institute, Policy Research Working
Paper, 1854, Washington DC, 1997.
[2] O. R. Nwaogbe, A. Pius., A. Abduljeli, and H. H. Alharahsheh, “An empirical study of Nigerian seaports operational performance”.
Transport & Logistics: the International Journal, Vol. 20, Issue 48,
ISSN 2406-1069, 2020, [3] O. M. Olapoju. “Assessing the Contribution of Containerization to
the Development of Western Ports, Lagos Nigeria” Journal of
International Logistics and Trade, Vol. 17, No.1, pp.12-20, 2019. [4] K. P. B Cullinane and T. F. Wang, ‘Data Envelopment Analysis
(DEA) and Improving Container Port Efficiency’ in Brooks, M. R.
and Cullinane, K. (ed.) Devolution, Port Governance and Performance, Elsevier, London. 2007.
[5] K. P. B. Cullinane, T. F. Wang and D. W. Song, “Container Port
Production and Economic Efficiency”, Basingstoke: Palgrave-Macmillan, 2005.
[6] Z. Liu, “The Comparative Performance of Public and Private
Enterprise. The Case of British Ports”, Journal of Transport Economics and Policy, Vol. 29, No.3, pp.263-274, 1995.
[7] T. Notteboom, C. Coeck and J. van den Broeck, “Measuring and
Explaining the Relative Efficiency of Container Terminals by means of Bayesian Stochastic Frontier Models”. International Journal of
Maritime Economics 2, pp.83–106, 2000.
[8] A. A. Pallis and T. Syriopoulos, “Port Governance Models: Financial Evaluation of Greek Port Restructuring”, Transport
Policy, 14, pp.232–246, 2007.
[9] A. Estache, M. Gonza´ lez and L. Trujillo, “Efficiency Gains from Port Reform and the Potential for Yardstick Competition: Lessons
from Mexico”. World Development, Vol.30, No.4, pp.545–560,
2002. [10] M. M. Gonzalez and L. Trujillo, “Reforms and Infrastructure
Efficiency in Spain’s Container Ports”, Transportation Research Part A, Policy and Practice, Vol.42, No.1, pp.243-257, 2008.
[11] C. P. Barros, “The Measurement of Efficiency of Portuguese
Seaport Authorities with DEA. International Journal of transport Economics, vol. 30, No. 3, pp.335-354, 2003.
[12] K. Cullinane, D. W. Song and R. Gray, “A Stochastic Frontier
Model of the Efficiency of Major Container Terminals in Asia: Assessing the Influence of Administrative and Ownership
Structures”. Transportation Research Part A 36, pp.743–762, 2002.
[13] D. Haarmeyer and P. Yorke, “Port Privatization: An International Perspective”. Reason Foundation, Los Angeles, 1993.
[14] G. De Monie,“Privatization of Port Structures in: Bekemans, L.,
Beckwith, S. (Eds.), Ports for Europe: Europe’s Maritime Future in a Changing Environment”.European Interuniversity Press,
Brussels, 1996.
[15] N. P. Coto-Millan, J. Banos-Pino and A. Rodrı’guez-Alvarez, “Economic Efficiency in Spanish Ports: Some Empirical Evidence”.
Maritime Policy and Management Vol.27, No.2, pp.169–174, 2000.
[16] A. Baird, “Port Privatization: Objectives, Extent, Process, and the UK Experience, International Journal of Maritime Economics Vol.2
No.3, pp.177–194, 2000.
[17] S. Cheon, D. E. Dowall and D. W. Song, “Evaluating Impacts of Institutional Reforms on Port Efficiency Changes: Ownership,
Corporate Structure and Total Factor Productivity Changes of
World Container Ports”, Transportation Research Part E, pp.546-
561, 2010.
[18] J. M. Sarriera, G. Araya, T. Serebrisky, C. Briceño-Garmendía and
J. Schwartz, “Benchmarking Container Port Technical Efficiency, in Latin America and the Caribbean: Stochastic Frontier Analysis”, the
World Bank, Sustainable Development Department, WPS6680
Publication, 2013. [19] A. Charnes, W. Cooper and E. Rhodes, “Measuring the Efficiency
of Decision Making Units, European Journal of Operational
Research 2, pp.429–444, 1978. [20] P. M. Panayides, C. N. Maxoulis, T. F. Wang and K.Y. A.Ng, “A
Critical Analysis of DEA Applications to Seaport Economic
Efficiency Measurement”, Transport Reviews, Vol.29, No.2, pp.183-206, 2009.
AUTHORS’ PROFILE
Dr. I. Njoku bagged Bachelor of Technology, Master of
Science and Doctor of Philosophy degrees in Maritime
Transport Management from the Federal University of
Technology, Owerri Nigeria (FUTO) in 2000, 2009 and
2015 respectively. He also obtained another Master’s
degree in Financial Management from FUTO in 2007. He
is a Lecturer at the Department of Logistics and Transport
Technology, Federal University of Technology, Akure
Nigeria. His area of specialization includes maritime
transport and shipping finance. He has published widely in
both national and international journals. He is a member of
CILT, Nigeria.
Prof. C. C. Ibe pursed B.Sc. from University of Benin,
M.Sc. and Ph.D. from FUTO. He is currently working as
Professor in Department of Logistics and Transport
Technology, FUTO. He is a fellow of CILT, Nigeria. He
has published more than 50 research papers in reputed
international journals. He has over 20 years of teaching
experience and 5 years of industry experience.