iisc - 3mwpv_plant

Upload: suhasjoshi7166

Post on 05-Apr-2018

236 views

Category:

Documents


4 download

TRANSCRIPT

  • 8/2/2019 Iisc - 3mwpv_plant

    1/38

    Indian Institute of Science

    Renewable Energy SystemsReports

    A case study of

    3-MW scalegrid-connected solarphotovoltaic power plantat Kolar, Karnataka

    Performance assessment &

    recommendations

    H. Mitavachan, Anandhi Gokhale

    and J. SrinivasanREPORT IISc-DCCC 11 RE 1 AUGUST 2011

    NDIAINOT EUT FTISNI ECSCIEN

    Divecha Centre forClimate Change

  • 8/2/2019 Iisc - 3mwpv_plant

    2/38

    The Divecha Centre for Climate Change wasestablished at the Indian Institute of Science in

    January 2009 with a generous financial

    contribution from Arjun and Diana Divecha and the

    Grantham Foundation for the Protection of the

    Environment.

    The primary goal of this Centre is to understand climate

    variability and climate change and its impact on the

    environment. The Centre has undertaken outreach activities

    to create awareness among people and policy makers about

    climate change and its consequences. This has been donethrough workshops, lectures and quiz contests. An annual

    invited public lecture called the Jeremy Grantham Lecture

    on Climate Change has been organized. The Centre has

    identified technologies to mitigate climate change in

    collaboration with entrepreneurs and different engineeringdepartments in the Indian Institute of Science. The Centre is

    also working with Grantham Institute for Climate Change

    at Imperial College, London, on the impact of climate

    change on water.

  • 8/2/2019 Iisc - 3mwpv_plant

    3/38

    Indian Institute of Science

    Renewable Energy SystemsReports

    H. Mitavachan, Anandhi Gokhaleand J. Srinivasan

    REPORT IISc-DCCC 11 RE 1 AUGUST 2011

    NDIAINOEUT FTITSIN ES CCIEN

    Divecha Centre forClimate Change

    A case study of3-MW scalegrid-connected solarphotovoltaic power plant

    at Kolar, KarnatakaPerformance assessment &

    recommendations

  • 8/2/2019 Iisc - 3mwpv_plant

    4/38

  • 8/2/2019 Iisc - 3mwpv_plant

    5/38

    Karnataka Power Corporation Limited (KPCL) has established 3 MW capacitypeak

    grid-connected solar photovoltaic power plant near Yalesandra village in Kolar

    district of Karnataka, which is the first of its scale in India. After the site

    preparations were completed the first segment was installed in 4 months,

    followed by the second and third segments in the next two months. The plant

    was fully commissioned on 27 December 2009. The Yalesandra plant is one

    among 20 such Mega-watt size solar power plants in India, *as on 31st July

    2011. India has an ambitious plan to build large grid-connected solar power

    plants, with a cumulative installed capacity of 20,000 MWp by 2020, under the

    National Solar Mission. Hence, it is essential to document the performance ofthe first large-scale grid-connected solar power plant installed in Karnataka. In

    this report we discuss the performance of the photovoltaic solar power plant in

    Kolar during 2010.

    0The Yalesandra power plant is located at a latitude of 12 53' and a longitude of

    078 09'. The overall area occupied by photovoltaic modules is 10.3 acres. The

    plant has 3 segments with each segment having an installed capacity of 1 MW .p

    Each segment has 4 inverters with a capacity of 250 kW each. There are 13,368modules (557 arrays with 24 modules per array) that contain mono-crystalline

    Silicon solar cells. The solar photovoltaic modules are connected such that a

    voltage of 415 volts is generated at the output of each inverter. This is stepped up

    to 11 kV by a step-up transformer and connected to the existing 11 kV grid.

    The total electrical energy generated by the Yaleasandra plant during 2010 was

    3.34 million kWh and 3.30 million units were sold to the grid. Although the

    performance of the photovoltaic modules was good, there were teething

    troubles associated with the inverters, which was the main reason for reducedenergy generation. The impact of temperature variation of modules on their

    performance was studied both on daily and yearly basis. It is observed that the

    efficiency of the plant is more sensitive to temperature than the solar insolation.

    Daily datasets of five minute average data have been used for in-depth analysis.

    Some of the maintenance and technical related problems faced by the plant

    operators have also been discussed.

    *CheckMNREwebsite(http://www.mnre.gov.in/solar-conclave2010.htm)formoredetagrid-connectedsolarpowerplantsinIndia

    Executive Summary

  • 8/2/2019 Iisc - 3mwpv_plant

    6/38

  • 8/2/2019 Iisc - 3mwpv_plant

    7/38

    1. 1

    2. 4

    2.1 Technical details 5

    2.2 Cost details 8

    2.3 Plant Maintenance & Operation 8

    3. 9

    3.1 Segment-1 and Segment-2 10

    3.2 PV Modules Temperature 17

    3.3 Performance of Inverter-1 18

    3.3.1 Effect of temperature on the efficiency 19

    3.3.2 Performance of Inverter-1 on good days Daily plots 20

    4. 23

    5. 25

    6. 26

    7. 27

    Introduction

    Site details

    Performance Analysis

    Technical and maintenance related problems

    Conclusion

    References

    Acknowledgments

    Contents

  • 8/2/2019 Iisc - 3mwpv_plant

    8/38

  • 8/2/2019 Iisc - 3mwpv_plant

    9/38

    Karnataka's power sector has three main hydro and other renewable energy sources.ut il it ie s name ly ; Ka rn ataka Power So, to reduce the dependence on fossil fuels

    Corporation Ltd. (KPCL) - the Public Sector and increase the share of renewable energy

    generation utility, the Karnataka Power sources, KPCL has started investing in wind

    Transmission Corporation Ltd. (KPTCL) - and solar energy technologies.

    the Public Sector transmission utility, and its

    regional distribution utilities - ElectricityIn early 2009, KPCL started the ArunodayaSupply Companies (ESCOMs). KPCL is thescheme to demonstrate, popularize andmain power generator in the state with anincrease the usage of solar energy forinstalled capacity of 5975.91 MW of hydel,

    electricity generation. Under this scheme,thermal, solar and wind energy, with anKPCL came up with a proposal for installingadditional 9500 MW in the pipeline.the country's first 3MW scale photovoltaicpsolar power plant near Yalesandra village in

    Till 1985, the state's entire capacity had Kolar district of Karnataka. The intent of thebeen hydroelectric, but with 2328 MW of project was to provide power to the farmerscoal based thermal power stations (and a to enable pumping and using of thefew diesel and wind-based plants), the hydro groundwater for irrigation. There are aroundshare of capacity has dropped to about 61%. 450-500 10-HP pumps in about 14Further, only about 75% of the hydro surrounding villages and farmers were

    capacity is available for utilization; the unable to use these at full capacity becauseremaining 25% comprises (a) non-firm of inconsistent power supply. The Kolarcapacity (i.e. a part of the water stored in p l a n t w a s f u l l y c o m p l e t e d a n dsome hydro-reservoirs is also meant for commissioned on 27 December 2009 (seeirrigation), (b) unforeseen outages Figure1). Later, two more plants with the(necessitating a spinning reserve), and (c) same capacity were constructed in Belgaummaintenance protection reserve. Also, in and Raichur (see Table1 and Figure2).years of poor rainfall, the contribution of

    hydel plants to annual electricity generationIndia has an ambitious plan to build largedecreases further [1]. One of the main

    grid-connected solar power plants, with areasons for the power crisis in 2008-09 was cumulative installed capacity of 20,000 MWPthe failure of the monsoon, which reducedby 2020, under the National Solar Mission.the reservoir levels in the major hydelHence, it is essential to document thereservoirs (viz., Linganamakki, Supa andperformance of the first large-scaleMani) by 26% compared to 2007-08 and thisgrid-connected solar power plant installedled to a reduction of 29.51% (2261 MU) inin Karnataka. This report contains thehydro generation [2]. All of these are leadinganalysis of the performance of theto an increased dependence on thermalphotovoltaic solar power plant in Kolarplants, whose GHG emissions are high andduring 2010.pollute the environment more compared to

    1

    1. Introduction

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    10/38

    Figure 1 : Photovoltaic Solar Power Plant at Yalesandra, Kolar, Karnataka

    Table 1 : Mega Watt scale Solar PV Plants in Karnataka State (all are under KPCL)

    Place

    YalesandraKolar

    Itnal, ChikkodiBelgaum

    YapaldinniRaichur

    ShivanasamudraMandya

    Cost per Mega Watt(Approximate figures)

    Rs. 20 crore

    Rs. 20 crore

    Rs. 14.5 crore

    -

    Total NominalCapacity (MW)

    3

    3

    3

    5

    Contractor

    Titan Energy Systems Ltd.

    Photon Energy Systems Ltd.

    BHEL(yet to be commissioned)

    -

    2

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    11/38

    Figure 2 : Karnataka map showing the locations of all the three 3MW Solar PV Power Plants

    3

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    12/38

    2. Site details

    The Yalesandra plant installation site has a room, substation and other anci llarysteep slope with a level difference of about st ructures. The general in formation

    15 m and there are rock outcrops in the site. regarding the climatic conditions of Kolar

    The structures for the Power Plant district and description of the Plant are given

    comprises Solar Arrays, PCUs, control in the Tables 2 and 3.

    Table 2 : General Climatic conditions of Kolar dist rict [3]

    Height above sea level

    Ambient Air Temperature

    Relative Humidity

    Rainfall

    882mo

    Maximum: 40 C

    Minimum: 18oC

    Maximum: 99.1% (during monsoon)

    Minimum: 18.3%Annual average: 1549 mm

    Period: 4 months

    Table 3 : General description of Yalesandra PV Plant

    Place of Installation Near Yalesandra Village, Kolar, Karnataka,India

    Latitude & Longitude of the place 12053 & 78

    009

    Allotted Land Area 15 acres (10.3 acres effectively used)

    Nominal Capacity of the PV Plant 3 MW

    Date of Commission 27th December 2009Owner Karnataka Power Corporation Limited

    (KPCL)

    Installed by (Contractor) Titan Energy Systems Ltd., Secunderabad

    Modules Titan S6-60 series

    SCADA for diagnosing and monitoring Yes

    PCU (Inverters) 250 kW (12 Nos)

    HT Transformer and switchgear for 1.25 MVA for each MW

    evacuation

    4

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    13/38

    2.1 Technical details

    Segments

    The 3 MW Plant is divided into three single Inverter, and each array consists of 24

    independent segments of one MW each. modules connected in series. The power

    Each segment is equipped with four generated from 3 MW PV Plant at 0.415 kVpInverters of 250 kW each and grouped is stepped up to 11 kV with the help of threetogether to form one LT panel. Depending on step-up transformers and connected tothe mix of 225 & 240 Wp modules, 45 to 46 existing 11 kV lines. The simple blockPV Arrays are connected in parallel to each diagram of the Plant is shown in Figure 3.

    Figure 3 : Simple block diagram of the PV Plant

    LT PANEL 3

    z=

    z=

    z=

    z=

    z=

    z=

    z=

    z=

    z

    =

    z=

    z=

    z=

    HT METERING CUBICLE

    LT PANEL 2

    PV Arrays PCUs MCBs

    TRANSFORMER 2

    LT PANEL 1

    TO SCADA

    TO SCADA

    TO SCADA

    SPARE

    11 kV

    KPTCL lines

    11 kV HT PANELTRANSFORMER 1

    TRANSFORMER 3

    5

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    14/38

    Tables 4 and 5 give the general technical details and the module specifications of the Plant.

    Table 4 : Technical data of Solar PV

    225 W & 240 Wp pTwo type of S6- 60 series modules are used

    13,368

    [10,152 - 225 W ;p 3216 240 Wp ]

    Total number of modules

    Mono-Crystalline SiliconSolar Cell material

    24 Modules1 Array

    45-46 (Total 557 Arrays with 12 Inverters)No. of Arrays per Inverter (250 kW)

    1st MW 181

    2nd & 3rd MW 188 per MW

    Arrays per MW

    5.4 acreTotal Solar Cells area

    15 degreeInclination of Modules

    Table 5 : Module Specifications [4]

    Type S6-60 series

    Maximum Power, Pmp (W) 225 240

    Maximum Power Voltage (Vmp) 28.63 V 29.62 V

    Maximum Power Current (Imp) 7.93 A 8.12 A

    Open Circuit Voltage (Voc) 37.50 V 37.62 V

    Short Circuit Current (Isc) 8.52 A 8.55 A

    Module dimensions (mm) 1657 x 987 x 42Number, type and arrangement of cells 60, Mono-Crystalline, 6 x 10 Matrix

    Cell Size 156 x 156 (mm)

    Nominal Operating Cell Temp (C)NOCT 45

    Weight (Kg) 19

    Glass Type and Thickness 3.2mm Thick, Low iron, Tempered

    6

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    15/38

    Power Conditioning Units (PCUs) Transformers

    All the twelve PCUs are identical and are The full load rating of the Transformers is

    supplied by the single manufacturer 1.25 MVA. All the three oil - cooled

    BONFIGLIOLI (VECTRON, RPS 450 type). Transformers are supp li ed by theThe MPPT device is in-built in the control ma nu fa cturer Pan El ec tr o Technic

    system which allows operating at constant Enterprises Pvt. Ltd. The efficiency is

    voltage. The efficiency of the PCUs is 98.91% at rated voltage and 99.3% at

    around 96% at nominal load. The rated maximum flux density.

    capacity of the PCU is 250 kW.

    Mounting structure

    Type

    6 x 4 Module Array

    (24 modules per )Structure

    Material Mild Steel

    Overall dimensions (mm) 6780 x 6030

    Coating Galvanized

    Wind rating 160 km per hour

    Tilt angle 150

    Foundation PCC

    Fixing type Nut Bolts

    Timelines

    Foundation was laid on 9th January 2009 30th September 2009, 2 MW on 12th

    and the site handed over to TITAN on 28th November and 3 MW on 27th DecemberMay 2009. 1MW was completed onp 2009.

    p

    p

    7

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    16/38

    2.2 Cost details

    Table 6 : Cost breakup of 3 MWp Yalesandra PV power plant [3] [5]

    The total cost of installing the Power Plant The detailed Cost breakup of 3 MW Kolar PV

    including the maintenance charges for first plant is given in Table 6.three years is approximately Rs. 60 crores.

    Item

    SPV Arrays totaling to 3 MWp

    PCUs

    Mounting structures

    Cables & Hardware

    Junction box & distribution boxes

    Lightning Arrester, Earthing kit

    PVC pipes & accessories

    Spares for 3 years

    SCADA system

    Taxes, CST/KVAT, etc.

    Design, engineering, quality surveillance,testing, transportation, insurance coverage, etc.

    Total Supply of Equipments (for 3 MW)

    Erection & Commissioning

    10 kW additional solar PV system withBattery support

    Cost (in Rupees)

    43,50,00,000

    5,40,00,000

    3,00,00,000

    50,00,000

    9,00,000

    12,00,000

    3,00,000

    5,00,000

    20,00,000

    1,05,78,000

    1,80,99,400

    55,75,77,400

    2,98,00,000

    31,00,000

    Note: Miscellaneous expenses have not been taken into account

    2.3 Plant Maintenance & OperationIn addition to 3 MW , one more 10 kW PV regularly to meet the water requirements of

    the Plant. The other two pump sets remainplant has been installed on the rooftop ofidle most of the time.office building to take care of domestic

    lighting and cooling loads of the Plant, Cleaning of PV Modules:including the load of exhaust fans. At

    Generally, the modules are cleaned bypresent, the plant is maintained by 13

    spraying water with the help of extendableworkers which includes 2 technical persons

    hosepipes. Occasionally, wipers are used towho look after data collection and

    remove the accumulated dirt and birdmonitoring.

    droppings, say once in a month. On an

    Three bore - wells have been installed at average, each module is cleaned once in athe site with pump-set capacities of 2 HP, week on rotational basis.5 HP and 10 HP. The 2 HP pump set is used

    p

    8

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    17/38

    3. Performance analysis

    The total Energy produced by 3 MW Plant generation during 2010. Since Segment-3

    was not performing satisfactorily for a fewduring the year 2010 was 3,347,480 units.months, which is evident from the figure, weOut of this, 3,303,200 units were sold to thewill restrict our analysis to the first twogrid. Figure 4 shows the contribution of allSegments only.the three Segments in the total power

    p

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    Month

    450000

    400000

    350000

    300000

    250000

    200000

    150000

    100000

    50000

    0

    MonthlyEner

    gyGeneration(kWh)

    Energy generated by 3 MW Plant - 2010

    Segment-3

    Segment-2Segment-1

    Figure 4 : Contribution of all the three segments in the total power generation during 2010

    9

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    18/38

    The performance of the first two segments mean output of 6655.4 kWh per day. The

    and their cumulative production over the capacity factor for this 2 MW plant was

    year 2010 is shown in Figures 5 and 6 around 14.52% at the generation end

    respectively. The total cumulative Energy (impact of grid-off times and maintenance

    generated by both the Segments together down times are not included).

    for the year 2010 was 2,429,219.6 kWh with

    3.1 Segment-1 and Segment-2

    Figure 5 : Daily Performance of Segment 1 & 2 during 2010

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    0

    1000

    2000

    3000

    4000

    5000

    6000

    EnergyGe

    neratedperday[kWh/day]

    Time [Daily]

    Segment-1

    Segment-2

    10

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    19/38

  • 8/2/2019 Iisc - 3mwpv_plant

    20/38

    The decline in energy generation during number of cloudy days during that period

    August to November period in Figure 7 was (see Figures 8 and 9). The declination can

    mainly due to the improper functioning of be seen more clearly in Fig. 11 which shows

    four Inverters (two in Segment-1 and the the variation of daily efficiency for the 2 MW

    other two in Segment-2), and partially plant during the year 2010.

    because of higher plant downtime and more

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0

    2000

    4000

    6000

    8000

    10000

    12000

    En

    ergyProduced[kWh]

    Time [Daily]

    Figure 7: Daily energy production of 2MW Plant [Seg.1 & 2]

    12

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    21/38

    Figure 8: Daily performance of all the 8 inverters

    Figure 8 shows the daily performance of all 2, 3, 5 and 7 (which are shown in red) were

    the inverters, first four come under malfunctioning during the period August toSegment-1 and the next four under November, as compared with the remaining

    Segment-2. It can be seen that the Inverters four inverters.

    Inverter 6

    Inverter 3

    Jan Mar May Jul Sep Nov

    Inverter 6

    Date

    0.0

    200.0k

    400.0k

    600.0k

    800.0k

    1.0M

    1.2M1.4M

    1.6M

    Inverter 4

    EnergyGen(wh/day)

    Inverter 1

    0.0

    200.0k

    400.0k

    600.0k

    800.0k

    1.0M1.2M

    1.4M

    1.6M

    EnergyGen(wh/day)

    Jan Mar May Jul Sep Nov0.0

    200.0k

    400.0k

    600.0k

    800.0k

    1.0M

    1.2M

    1.4M

    1.6M

    Inverter 7

    EnergyGen

    (wh/day)

    Date

    Inverter 5

    Inverter 2

    Inverter 8

    Jan Mar May Jul Sep Nov

    Date

    13

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    22/38

    Figure 9: Monthly Plant down-time in hours-2010

    Grid-off times: Figure 9 shows the was observed that the grid-offs occurred

    cumulative monthly grid-off times during the mainly during the peak hours (11.30 am

    year 2010. Out of the 357 days of the Plant's 2 pm), that is, when the availability of solar

    operation, there were 75 days on which the insolation is maximal.

    grid was off for less than an hour and 57 days The Plant was shut down for 8 days duringwith grid-offs more than one hour. Totally the

    November for repairing the faulty cables andgrid was off for about 201.4 hours. Also, it

    Inverters.

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    0

    20

    40

    60

    80

    100

    Dow

    ntime(Hours)

    Month

    Plant Shut Down

    Grid-Off Times

    14

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    23/38

    The Plant is equipped with a Pyranometer mid May to mid June, due to some problemo in the Pyranometer. The highest recordedinstalled at an angle of 15 , equal to the

    daily insolation was 7199 Wh/sqm on 2ndinclination of the Modules. The Solar March 2010. The yearly average insolationInsolation recorded at the site is shown inon the panels was about 4789 Wh/sqm/day.Figure 10. The Insolation data is not

    available for about 44 days, especially from

    Solar Insolation

    o

    Figure 10: Daily Solar Insolation at the site - 2010 [@15 . inclination]

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    Time [Daily]

    15

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

    Insolation[15Wh/m2]

    o

  • 8/2/2019 Iisc - 3mwpv_plant

    24/38

    Efficiency

    The 2-MW plant efficiency is the combined insolation of 2561 Wh/sqm and an average0efficiencies of segments 1 and 2 after the module temperature of 28.63 C. The daily

    dc-ac conversion by inverters to 415 Volts efficiency of the 2MW plant ranged from 5%and just before stepping up to 11 kV ac. So, to 13.41% depending on the performance ofthis should not to be confused with the arrays, inverters, average moduleoverall plant efficiency. temperature and the solar insolation. The

    yearly average daily efficiency of the plantFigure 11 shows the efficiency of the 2 MW

    was about 10.14%, considering the daysplant, that is combined efficiency of

    which have grid-offs for less than half ansegments 1 & 2, over the study period. The

    hour or no grid-offs. The abnormal drop inhighest efficiency achieved was 13.41% on

    the efficiency during the last few months was24th July 2010. The total energy generated

    mainly due to inverter related problems.on that day was 4975.8 kWh with solar

    Figure 11: Daily Efficiency of 2 MW Plant [Seg.1&2]

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0

    2

    4

    6

    8

    10

    12

    14

    16

    PlantEfficiency(%)

    Time [Daily]

    16

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    25/38

    Figure 12: Daily average temperature of PV modules (During day time) 2010

    Figure 12 shows the daily average Although the solar insolation level is more in

    temperature of PV modules for the year March compared to January, the efficiency0 during March is low. This may be due to2010. It ranged from a minimum of 24.65 C

    0 increase in the daily average temperature of(on 6th Dec) to a maximum of 51.9 C (onPV modules during that month, as seen from23rd April).the Figure. But this is not very clear because

    Figure 13 shows the combined plots of plantof too much noise in the data. To reduce the

    efficiency, daily average modulesnoise and explore the issue further, we

    temperature and daily solar insolation withdecided to analyze a single inverter which

    reference to time scale. It appears from thehad performed well during the study period.

    figure that the efficiency is more sensitive to

    modules temperature than the insolation.

    3.2 PV Modules Temperature

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec10

    20

    30

    40

    50

    60

    Tempera

    ture[deg.

    Celsius]

    DATE

    17

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    26/38

    Figure 13: Daily variation of average modules temperature, insolation (in Wh) and efficiency of the 2MW Plant

    3.3 Performance of Inverter-1

    As the performance of Inverter-1 is good energy generation by Inverter-1 versus the

    compared to other Inverters (see Figure 8), incident solar insolation on that day for the

    we chose this Inverter for more in-depth year 2010. The energy generation increases

    study. Figure 14 shows the plot of daily linearly with the increase in solar insolation.

    18

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    27/38

    Inverter-1

    0 1000 2000 3000 4000 5000 6000 7000 8000

    0

    200

    400

    600

    800

    1000

    1200

    1400

    1600

    EnergyG

    enerated(kWh)

    Solar Insolation (Wh/m2

    /day)

    Figure 14: Annual plot of daily energy generated by Inverter-1 versus solar insolation

    3.3.1 Effect of temperature on efficiency

    Figure 15 shows the variation in energy This is mainly because of increase in the

    generation of solar modules with insolation temperature of modules, which negatively

    and the effect of module temperature on impacts the efficiency more during that time

    their efficiency. The plots are made using the [see Figure 15(B)]. Figure 16 shows the5 minutes average values from 10 am to variation in efficiency of the modules with

    3 pm on 21st January, 2010. variation in temperature of modules, along

    with color mapped values for average solarEven though the energy generation shows

    irradiance. The efficiency of the modulesdirect dependency on the incident solar o

    decreases from 14.5% at 30 C to 11.5% atinsolation [see Figure 15(A)] and reaches

    o55 C. It is also clear from the Figure that thethe maximum during peak insolation hours,temperature of modules increases with thethe efficiency of the modules decreases andincrease in solar insolation and reaches thereaches the minimum during peak hours.

    19

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    28/38

    09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00

    11.2

    12.0

    12.8

    Efficiency

    Temperature

    Time, 21-Jan

    Efficiency(%)

    42

    49

    56

    Temperature(

    oC)

    maximum during peak insolation hours, values) for the year 2010. Due to lots of

    leading to reduced conversion efficiency. noise below 20 , the temperature values0 0Thus, the Plant's capacity to produce were binned between 20 C and 55 C. Then

    maximum power is retarded during peak the efficiency values were binned betweeninsolation hours, when the availability of 10% and 15% choosing only the maximumincident solar radiation is highest, because points. The plot shows linear decrease in theof increase in modules temperature. daily efficiency of modules from 14.5% to

    11.5% with increase in the daily averagedFigure 17 shows the annual plot of dailyo o

    modules temperature from 25 C to 50 C.efficiency of modules in Inverter-1 versus

    daily averaged module temperature (binned

    0C

    3.3.2 Performance of Inverter-1 on good days Daily plots

    Figure 18 shows the daily performance plots efficiency of Inverter-1 with modules

    of Inverter-1 on 24th March, 11th May, 18th temperature. The values of solar insolation,

    June, 24th July and 20th September. The modules temperature and efficiency are

    plots on the left side show the variation of averaged for every 5 minute interval. The

    energy generation with solar insolation and energy generation values are the cumulative

    the right side plots show the variation in figures generated for the same time period.

    Figure A: Insolation and Energy Generation (of Invereter-1) Figure B: Efficiency and Temperature of Modules (of Invereter-1)

    Figure15: Plots of insolation, & temperature of

    Inverter-1 modules on January 21

    energy generation, efficiency

    09:00 10:00 11:00 12:00 13:00 14:00 15:00

    650

    700

    750

    800

    850

    900

    950

    1000

    1050

    1100

    1150

    1200

    Insolation

    Energy Generated

    Time, Jan 21

    Insolation(W)

    12000

    13000

    14000

    15000

    16000

    17000

    EnergyGenerated(Wh)

    20

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    29/38

    25 30 35 40 45 50 55 60

    11.0

    11.5

    12.0

    12.5

    13.0

    13.5

    14.0

    14.5

    15.0

    5 Min Avg. Efficiency

    Efficiency(%)

    0Temperature ( C)

    20.00

    100.0

    200.0

    300.0

    400.0

    500.0

    600.0

    700.0

    800.0

    900.0

    1000

    SCALE FOR AVG

    SOL IRR (W/m2)

    Figure 16: Efficiency v/s Temperature of modules of Inverter-1

    on January 21, 2010 (Color scale : Average Solar Irradiance)

    (5 min average values)

    Figure 17: Plot of daily maximum efficiency versus temperature of modules in Inverter-1 for 2010

    11.0

    11.5

    12.0

    12.5

    13.0

    13.5

    14.0

    14.5

    25 30 35 40 45 50 55

    Temperature ( )0C

    MaximumEffic

    iency(%)

    Maximum EfficiencyLinear Fit of Maximum Efficiency

    Plot Maximum Efficiency vs Temperature of Modules in Inverter 1

    21

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    30/38

    Figure 18: (Left) Daily plots showing variation of energy generation with insolation;(Right) Daily plots showing variation of efficiency with modules temperature

    09:36 10:48 12:00 13:12 14:24 15:36 16:48

    20

    30

    40

    50

    60

    70

    Time (July-24)

    TempMod(DegC)

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    Efficiency(%)

    09:36 10:48 12:00 13:12 14:24 15:36 16:48

    100

    200

    300400

    500

    600

    700

    800

    9001000

    1100

    1200

    Time (July-24)

    SolarInsolation(W/m2)

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000 EnergyGeneration(Wh

    )

    09:36 10:48 12:00 13:12 14:24 15:36 16:48100

    200

    300400

    500

    600

    700

    800

    9001000

    1100

    1200

    Time (March-24)SolarInsolation(W/m2

    )

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000 EnergyGeneration(Wh)

    09:36 10:48 12:00 13:12 14:24 15:36 16:4820

    30

    40

    50

    60

    70

    Time (March-24)

    TempMod(Deg.C)

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    Efficiency(%)

    09:36 10:48 12:00 13:12 14:24 15:36 16:48100

    200

    300400

    500

    600

    700

    800

    9001000

    1100

    1200

    Time (Sept-20)SolarInsolation(W/m2)

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000

    EnergyGeneration(Wh)

    09:36 10:48 12:00 13:12 14:24 15:36 16:4820

    30

    40

    50

    60

    70

    Time (Sept-20)

    TempMod(DegC)

    6

    8

    10

    12

    14 Efficiency(%)

    09:36 10:48 12:00 13:12 14:24 15:36 16:48100

    200

    300400

    500

    600

    700

    800

    9001000

    1100

    1200

    Time (June-18)

    SolarInsolation(W/m2)

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000 EnergyGeneration(Wh)

    09:36 10:48 12:00 13:12 14:24 15:36 16:4820

    30

    40

    50

    60

    70

    Time (Ju ne-18)

    TempM

    od(Deg.C)

    6

    7

    89

    10

    11

    12

    13

    14

    15

    Efficienc

    y(%)

    09:36 10:48 12:00 13:12 14:24 15:36 16:48100

    200

    300400

    500

    600

    700

    800900

    1000

    1100

    1200

    Time (May-11)

    SolarInsolation(W/m2)

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000 EnergyGeneration(Wh)

    09:36 10:48 12:00 13:12 14:24 15:36 16:4820

    30

    40

    50

    60

    70

    Time (May-11)

    TempMod(Deg.C)

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    E

    fficiency(%)

    Solar Insolation Energy Generation

    Temp Mod Efficiency

    22

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    31/38

    4. Technical and maintenance related problems

    Some of the major technical & maintenance ?Presently the modules are cleaned byrelated problems faced by the plant sp ra yi ng wa te r. Bu t th e du stoperators are as follows: accumulated on the modules turns into

    paste form once the modules are water?The power of the PV plant cannot be fed sprayed, making it difficult to remove.

    to the grid if the power supply from the Also, the height of the modulesgrid stops. Due to this, the power from mounting structures (see Figure 19)the PV Plant is not available when it is makes it impossible to remove the dirtneeded most and the capacity of the completely with wipers while standingPlant to work effectively has been on the ground. This has led inevitably, toretarded. the option of cleaning the modules by

    climbing on top of them (and then using?There is no tracking mechanism towipers!). This will weaken the strengthlocate the modules if they fail. If aof solar modules as well as mountingmodule fails, it is very tiresome tostructures in the long run and also affectidentify it because no sensors havethe power production. Hence, it is feltbeen installed for this purpose. The onlythat there is a need to address this issuesolution presently available is to wait tillby developing alternate method/the peak time to identify the Invertertechnology for cleaning the PV(from which the output is lower). Thenmodules.the Inverter has to be isolated and all

    the 45-46 arrays connected to this?Recently, some of the modules have

    inverter should be checked. Once the

    shown change in color (see Figure 20).faulty array is located, all the connected It is yet to be ascertained whether thismodules need to be checked to identify color change in the modules has anythe faulty one. negative impact on their performance.

    0Figure 19: Photo of PV Plant showing the modules mounting structures inclined at 15 .

    23

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    32/38

    Figure 20: Visual color change of the photovoltaic modules

    24

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    33/38

    5. Conclusion

    The performance of the 3 MW Yalesandra afternoon. The daily efficiency of modulespvaried from 14.5% to 11.5% with thesolar photovoltaic power plant has beenvariation in the daily averaged modulesanalyzed for the year 2010. The total

    o otemperature from 25 C to 50 C. Hence,electrical energy generated by thecooling of the solar modules may beYalesandra power plant during 2010 wasdesirable to increase the efficiency. There is3.34 million kWh and 3.30 million units werea need to evaluate if the additional energysold to the grid. Based on the performance ofrequired for cooling the solar modules will bethe first two segments we estimate the meanless than the additional energy generatedoutput to be 6655 kWh per day. This is lowerdue to higher efficiency.than expected for a solar power plant and is

    on account of teething trouble associated

    with inverters and the grid-encountered inThe daily plots showing the variation ofthe first year of the operation of the plant. Itefficiency with modules temperature and thewas found that failure in inverters were thevariation of energy generation with solarmost frequent incidents. This is mostlyinsolation have been plotted for five differentcaused by lack of experience in the initialdays of the year. Also, some of the presentproduction stage and some unexplainedmaintenance and technical problems facedinverter failures might be caused byby plant operators, including the colordisturbance from the grid and otherchange in PV modules and cleaning issues,interconnected issues [6].

    have been discussed.

    The impact of temperature variation (ofIt is also suggested that more measuringmodules) on the performance ofinstruments such as Pyrheliometer, Rainphotovoltaic mono-crystalline siliconGauge, Thermocouple (Thermometer) formodules was studied both on daily andmeasuring ambient temperature, to beyearly basis (daily average values). It isinstalled in the plant and the existingobserved that the efficiency of modules isinstruments to be calibrated for greatermore sensitive to temperature than the solaraccuracy. This will enable further technicalinsolation. The normal daily trend is that the

    analysis of Indias first 3MW scale plant andefficiency of Plant is high during morning help KPCL in their future solar power planthours but low during the middle of the dayprojects.and again starts increasing from late

    25

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    34/38

    6. References

    1. AntonetteD'SaandK.V.NarasimhaMurthy,Karnataka'sPowerSector

    Forward,InternationalEnergyInitiative,discussionpaper,2002.

    2. K.Jairaj,EnergyscenarioinKarnataka,powerpointpresentation,

    GovernmentofKarnataka.

    3. SolarPVPowerPlants,contractagreementforsupplyofequipment

    KPCLandTi tanEnergySystemsLtd.,Secunderabad.

    4. Operati onmanual ,Ti tanEnergySystemsLtd.,Secunderabad.

    5. ContractagreementforErecti on,testi ngandcommi ssi oni ngof3MKPCLandTi tanEnergySystemsLtd.,Secunderabad.

    6. MohamedA.El tawi l andZhengmi ngZhao,Gri d-connectedphotovol t

    Technicalandpotentialproblems-Areview,RenewableandSustainableEnergyReviews,

    14,2010,112129.

    26

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    35/38

    7. Acknowledgements

    WewishtothankMr.B.R.Nagaraju,Ex-ChiefEngineer,REProjects

    CorporationLtd.(KPCL)forparticipatingintheprojectbygivingauthordataforthisresearch.Wethank Mr.A.V.V.Reddy,ExecutiveEngineer,i

    Plantforgivingustheperformancedataoftheplant.Wealsoappreciateh

    timewithusandsharinghisconcernsabouttheplantduringourfieldvisi

    C.Krishnamurthy,ExecutiveEngineer,Electrical Division,KPCLforhe

    andotherinformationrelatedtotheplant.

    WealsoacknowledgeMr.M.K.Nagaraj andtheofficestaffatDivecha

    Change,fortheirkindsupportduringthecourseofthisproject.

    27

    3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka

    Report I I Sc-DCCC11RE1

  • 8/2/2019 Iisc - 3mwpv_plant

    36/38

  • 8/2/2019 Iisc - 3mwpv_plant

    37/38

    Satellite image of the 3-MW scale grid-connected solar photovoltaic power plant at Kolar, Karnataka

  • 8/2/2019 Iisc - 3mwpv_plant

    38/38

    REPORT IISc-DCCC 11 RE 1AUGUST 2011