Stage 1 Course Works Information
Memorandum
IGC 2021-2026 Strategic Plan
IGC- Preeminent Private Members Golf
Club
Member Information Sessions
Special General Meeting - 7th December
Welcome
Lyndal Plant - Vice President /
Chair Course Master Plan Working Group
Stage 1 Course Works
Gayle Brown - Treasurer
Financial Position
Paul Laxon - Director /
Chair Clubhouse Working Group
Clubhouse Update
Steve Lamerton - CEO
Strategic Plan and
Special General Meeting
Q & A Session
Information Session Agenda
Xx
Xx
Xx
Xx
Xx
New Green 1 to Green 9 (the Green
Loop) as per the Course Architect Design
Meiers Road Dam Expansion
New toilet on the Green Loop
Expanded Member cart storage facility
Upgrade of the overflow carpark and
expansion of the main carpark
Connecting path from Somerset
Indooroopilly to the clubhouse precinct
Stage 1 Course Works 2022/23
Driven by opportunity to integrate:
• reinstatement of 5 holes around the RV,
WITH
• course water storage improvement AND
• overdue course quality & infrastructure
upgrades across the Green Loop, WITH
• permanent solution to old tip site issues,
AND
• the most cost- efficient use of on-site earth
(i.e. “cut/fill balance”)
Stage 1 Course Works 2022/23
Why do the Green Loop in one phase?
• Gets on with delivering,
o overdue improvements to part of the course not touched for 40 years, and
o water storage improvement
• Most efficient construction & earthworks movement
• Actually less disruptive to members,
o than smaller stages & temporary holes over longer time
• Raises the bar of course quality,
o across greens, fairways, tees, bunkers, habitat
• Gains benefits of completion within 12 months
Stage 1 Course Works 2022/23
Deliver a package of priority works:
• across whole Green Loop, car parks &
cart shed & RV path
• within 12 months,
o without impacting on current Driving Range,
Blue, Gold and Red Loops
• returning to 36 holes in 2023
Dependent on:
• funding, contractor engagement and
statutory approvals
Stage 1 Course Works 2022/23
$11.5M Stage 1 Course Works
Funded via Relevant Funds:
• $20.9M available @ 30 Sep, 2021
• $11.9M projected balance post
completion of course works
Operating Cash
• $6.3M cash @ 30 Sep, 2021 funding for:
o Opex & business as usual capex remaining
9 months subscription period
o $3M budget for Clubhouse renovations
Affordability – 2022/23
Relevant Funds
• $11.5M Expenditure in 2022/23
• $4M Expenditure allowed in 2026, funded by:
o $1.2M Somerset RV Income
o $3.3M Investment Returns @ 5%pa
• $10M Minimum balance
Operating Cash surpluses
Debt Free, except for $250K, 10 yr gov’t
Covid loan funding @ 2.5%pa
Standby funding available
Affordability – to 2026
2021 2022 2023 2024 2025 2026
Operating Cash a/c (Nominal$) 4.3 0.5 0.4 1.2 2.3 1.8
Relevant Funds (Nominal$) 21.2 14.3 11.9 12.8 13.6 10.3
Total Nominal $ 25.5 14.8 12.3 14.0 15.8 12.1
Total Real $ (2021) 25.5 14.5 11.8 13.2 14.6 11.0
0
5
10
15
20
25
30
$ M
illio
ns
Year ending 31 December,
Affordability – to 2026
Relevant Funds
• Somerset RV Income growth
o $3M in 1st decade, $14.5M in 2nd decade
• Investment income compounding
• $31M Development Expenditure allowed
• $10M Minimum balance
Operating Cash growth
• Growth in:
o entrance fees, from 2x multiplier to 3x;
o non-subscription revenue streams, 2% above CPI
• Whilst maintaining annual subscriptions,
operating costs and ongoing capex with CPI
Affordability – 20 years
Affordability – 20 years
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Operating Cash a/c (Nominal$) 4.3 0.5 0.4 1.2 2.3 1.8 3.0 4.3 2.8 4.0 5.6 5.1 6.9 8.9 9.4 11.6 14.0 14.6 17.3 20.1
Relevant Funds (Nominal$) 21.2 14.3 11.9 12.8 13.6 10.3 11.1 12.0 10.0 11.2 12.6 10.2 12.1 14.3 11.5 13.8 16.2 13.6 15.9 18.3
Total Nominal $ 25.5 14.8 12.3 14.0 15.8 12.1 14.1 16.2 12.8 15.2 18.2 15.3 19.0 23.2 20.9 25.5 30.3 28.2 33.2 38.4
Total Real $ (2021) 25.5 14.5 11.8 13.2 14.6 11.0 12.5 14.1 10.9 12.7 14.9 12.3 15.0 17.9 15.9 18.9 22.0 20.1 23.2 26.4
0
5
10
15
20
25
30
35
40
45
$ M
illio
ns
Year ending 31 December,
Conclusion
IGC is in a strong financial position
RV Lease provides a current base and
ongoing income stream for renewed
investment in IGC’s major assets
Clubhouse Update
Ellivo clubhouse concept / detailed
round floorplans
Quantity Surveyor review undertaken
In the process of appointing a builder
(ECI process)
Member information sessions imminent
Construction commencement first
quarter 2022
Strategic Plan 2021 - 2026
Proactive view of development
opportunities
Responds to feedback
Lifestyle factors
Traditions
Core focus on golf
Special General Meeting
Resolutions
• Amend the Constitution:
o Electronic voting
o Flexibility for membership category movement
o Credit management of unpaid house accounts
• Clarify the 2017 SGM resolution #2: reimbursement of $367k from Relevant Funds
• Use of Relevant Funds up to $5.5M to complete Stage 1 works not covered by the 2017 resolution
Healthy financial position
Tuesday 7 December 2021