iegp-6351-8110-ra- 000-0001, toyo...
TRANSCRIPT
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 2 OF 106
CONTENTS 1. EXECUTIVE SUMMARY 3 1.1. Project Description 3 1.2. Conclusions and Recommendations 3 2. INTRODUCTION 5 2.1. Study Aims & Objectives 5 2.2. Scope of Work 5 3. TERMINOLOGY 5 3.1. Definitions 5 3.2. Abbreviations 6 4. PROJECT DETAIL 6 4.1. Process Overview 8 4.2. Project Site / Location 16 4.3. Meteorological Data 16 5. OVERVIEW OF RA METHODOLOGY 17 6. HAZARDS ASSOCIATED WITH THE PROJECT 17 6.1. General 17 6.2. Hazards Associated with Flammable Materials 17 6.3. Hazards Associated with Toxic Materials 18 7. HAZARD IDENTIFICATION 18 7.1. Hazardous Substances 18 7.2. Modes of Failure 24 7.3. Review of Industry Incidents 25 7.4. Unit Sectionalization & Selected Failure Cases 35 8. CONSEQUENCE ANALYSIS 45 8.1. Source Term Modelling 45 8.2. Dispersion Modelling 49 8.3. Physical Effects Modelling 49 9. RISK ANALYSIS DISCUSSION 63 9.1. Ethylene Recovery Unit (ERU) 63 9.2. Ethylene Glycol Unit (EG) 75 9.3. Offsite & Utility Facility (O&U) 87 9.4. Client Cases 87 10. CONCLUSION AND RECOMMENDATIONS 99 11. GUIDELINES FOR DISASTER MANAGEMENT PLAN 103 11.1. Introduction 103 11.2. Action Plans 104 12. REFERENCE 106
ATTACHMENT - A - RA METHODOLOGY & ASSUMPTIONS ATTACHMENT - B - CONSEQUENCE ANALYSIS RESULTS ATTACHMENT - C - CONSEQUENCE ANALYSIS HAZARD CONTOURS
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 3 OF 106
1. EXECUTIVE SUMMARY
1.1. Project Description
M/s. Indian Oil Corporation Limited (IOCL) has appointed M/s. Toyo Engineering India Pvt.
Ltd. as the Project Management Consultant (PMC) for installation of Ethylene Glycol
production facilities from Front End loading (FEL) stage up to Plant commissioning and final
contract closure.
1.2. Conclusions and Recommendations
Risk analysis identified the potential hazards that are associated with process and storage
facility in the proposed facilities coming under this Project. To assess consequences based
on the realization of the identified hazards, worst-case scenarios such as catastrophic
rupture of reflux drum, accumulator, storage sphere and storage tank on fire which have
very low likelihood (low frequency of occurrence, 5 x 10-7per year), certain scenarios like
large holes with frequency of occurrence (frequency in the range of 5 x 10-5 to 5 x 10-7 per
year depending upon nominal diameter of pipeline) and medium hole like pump seal leak
(10 mm equivalent hole having frequency 3.75 x 10-4 per year) have been considered.
The study reveals that for most of the failure cases, hazard distances are limited to
plant boundary and not directly affect outside the complex. The detailed discussion
on risk analysis of the identified failure cases has been given in Section 9.
Major recommendations arising out of the Risk analysis study for this project are
summarized below.
Ethylene Recovery Unit:
H2S Gas Detectors with audio-visual alarms (beacons) to be provided in vicinity of
equipment handling H2S gas (Case ER-2).
Sufficient number of Hydrocarbon gas detectors to be provided in the vicinity of pumps
and equipment handling light hydrocarbon (ER-8).
Requirement of inventory isolation to be reviewed during detail engineering for vessels
handling large amount of hydrocarbon (ER-8, ER-11, ER-12).
Catastrophic rupture scenario of Deethylenizer Reflux drum shall be included in
Disaster Management plan.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 4 OF 106
Ethylene Glycol Unit:
Sufficient number of Hydrocarbon gas detectors / Toxic Gas detector (EO) to be
provided in the vicinity of pumps and equipment handling light hydrocarbon e.g.
ethylene, ethylene oxide (EG-1, EG-4, EG-6, EG-7, EG-8, EG-9).
Sub-station and SRR shall be positively pressurized to avoid ingress of any HC or Toxic
gas inside these building (EG-9).
HC / Toxic Gas detector to be provided at sub-station and SRR air unit suction (EG-9).
Provide HC gas detector in vicinity of 061-V-140 for early detection of any leakage.
Vehicular movement on roads along the ethylene storage sphere should be avoided to
eliminate potential ignition source.
Offsite & Utility Facility:
Provide active / passive fire protection for Ethylene Storage Sphere as per OISD(OU-1)
Provide HC gas detector in vicinity of ethylene product transfer pump seal for early
detection of any leakage (OU-1, OU-3, OU-4).
Requirement of inventory isolation to be reviewed during detail engineering (OU-1).
Vehicular movement on South side road along the ethylene storage sphere should be
avoided to eliminate potential ignition source (OU-1, OU-3, OU-4).
Catastrophic rupture scenario of Ethylene Storage Sphere shall be included in Disaster
Management plan.
Excess flow check valve shall be provided on each loading bay (OU-8, OU-11, OU-14)
Heat detection based automatic water sprinkler system to be provided (OU12, OU-14).
Continuous presence of people E-side of property line should be discouraged (OU-5).
It is recommended to allow minimum number of vehicles at a time inside loading gantry.
This may result in longer time for gantry operations but will reduce the chances of any
possible ignition & consequent hazardous scenario and resultant risk arising, on
account of any leakage from the gantry (OU-7, OU-12, OU-15).
Creek Crossing Pipe Rack: All hydrocarbon vents and drains on headers running through the pipe rack should be
plugged-off. Regular monitoring / heath check-up of headers running through the pipe rack crossing
the creek should be carried out.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 5 OF 106
2. INTRODUCTION
2.1. Study Aims & Objectives
This Risk Analysis identifies the potential events leading to major accident hazards and the
magnitude of safety related consequences of each event. It does not establish the
probability of the event occurring.
The objectives of this study are to:
Identify possible failure / hazards associated with the coming new facility
Assess the possible consequences of these hazards should they occur.
Suggest suitable mitigation measures to minimize frequency and the consequence of
these Hazards.
2.2. Scope of Work
The intent of the RA Study is to systematically identify all potential failure / accidents /
hazards and its consequences. Subsequently analyse the extent of damage due to such
incidents and draws suitable mitigating measures.
The scope of RA Study for Project will include the following units:
Ethylene Glycol Unit (Capacity: 357 KTPA)
Ethylene Recovery Unit (Capacity: 180 KTPA)
Offsite & Utilities
The RA Study shall be performed only for the above new facilities. Detailed assessment for
the existing facilities or integration with the existing facilities or impact of existing facilities on
new facilities is not considered within the scope. However, effect of new facilities on existing
facilities have been reviewed and analysed.
3. TERMINOLOGY
3.1. Definitions
PROJECT : PMC SERVICES FOR ETHYLENE GLYCOL
PROJECT AT PARADIP REFINERY (IEGP)
COMPANY : INDIAN OIL CORPORATION LIMITED
PMC / CONSULTANT : TOYO ENGINEERING INDIA PVT. LTD.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 6 OF 106
3.2. Abbreviations
CCPS Center for Chemical Process Safety
C&E Cause and Effect
CIA Chemical Industries Association
DNV Det Norske Veritas
ESD Emergency Shutdown
ETA Event Tree Analysis
HAZOP Hazard and Operability Study
IMD Indian Meteorological Department
LFL Lower Flammability Limit
MSDS Material Safety Datasheet
PES Potential Explosion Site
PFD Process Flow Diagram
P&ID Piping and Instrumentation Diagram
PHAST Process Hazard Analysis Safety Tool
RA Risk Assessment
SIL Safety Integrity Level
UDM Unified Dispersion Modelling
VCE Vapor Cloud Explosion
4. PROJECT DETAIL
The project consists of Ethylene Glycol (EG) unit of capacity 357 KTPA licensed by
Scientific Design Company, Ethylene Recovery Unit (ERU) of capacity 180 KTPA, licensed
by Lummus Technology and Offsite and Utilities. The overall plot plan of EG & ERU is
shown in Figure 4.1
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 7 OF 106
Figure 4.1: Overall Plot Plan
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 8 OF 106
4.1. Process Overview
The following section summarizes the processes involved in the Ethylene Recovery Unit,
Ethylene Glycol and Offsite & Utility facilities.
4.1.1. Ethylene Recovery Unit
Ethylene Recovery Unit is licensed by ABB Lummus. A schematic diagram of the ERU is
provided in Figure 4.2
Figure 4.2 Ethylene Recovery Unit
Feed Treatment Section
The contaminants in the FCC offgas will be removed before the feed is processed in the
downstream distillation section. Feed is first sent to the lower bed of the Caustic/Water
Wash Tower (C-101) where the H2S in the feed is removed and the amount of CO2 is
reduced. Next the feed goes through a FCC Offgas Chloride Treater (R-105) via Chloride
Treater Feed KOD (V-107) to remove chlorides. After the Caustic Tower and Chloride
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 9 OF 106
Treater, the feed gets heated in Oxygen Converter Feed / Effluent Exchanger (E-107) and
Oxygen Converter Feed Heater (E-108) and goes to the FCC Offgas Oxygen Converter (R-
102 A/B). The ethylene losses in the converter will be less than or equal to 1% of the
ethylene in the feed stream.
The offgas from the Oxygen Converter is gets cooled in Oxygen Converter Feed / Effluent
Exchanger (E-107) and Oxygen Converter Effluent Air Cooler (AC-101) and routed to the
upper bed of the Caustic/Water Wash Tower (C-101) to remove any remaining acid gases.
The offgas is then chilled in Dryer Feed Chiller (E-106) before being sent to the Dryer /
Treater (R-103 A/B) to remove the water, mercaptans, ammonia and amines. Finally, the
feed goes through a Mercury Adsorber (R-201 A/B) where the mercury is removed.
Distillation Section
The treated feed is then sent to the FCC Offgas Chiller (E-201), located in the Cold Box,
where a binary refrigerant is used to chill the feed. After being chilled it is then sent to the
Demethanizer (C-201).
The Demethanizer is provided with an intercooler using binary refrigerant to minimize the
ethylene losses. In the Demethanizer the FCC offgas fed into the lower part of the tower is
contacted against a side draw stream from the Deethylenizer (C-301), which enters at the
top of the tower.
The overhead stream from the Demethanizer is used as regeneration gas for the
Dryer/Treaters and then sent to OSBL to be used as refinery fuel gas. The Demethanizer
bottoms stream is sent to the Deethylenizer (C-301). The Deethylenizer overhead is fully
condensed using binary refrigerant and produces 99.5 wt% ethylene. The liquid ethylene
product is then sent to the Offsite. A small ethylene product stream is sent to the PP plant.
The bottoms stream is sent to OSBL as C3+ Product, to the offspec LPG system. A side
draw from the Deethylenizer is sent back to the top of Demethanizer as a wash liquid, with a
portion of the side draw recovered as ethane product. A binary refrigerant consisting of
ethylene and propylene is utilized to provide the refrigeration at the necessary levels for the
process users.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 10 OF 106
4.1.2. Ethylene Glycol Unit
The Ethylene Glycol plant is licensed by Scientific Design Company. A schematic diagram
of the EG plant is provided in Figure 4.3
Figure 4.3 Ethylene Glycol Unit
EO REACTION, EO AND CO2 Scrubbing Section
Ethylene, oxygen, and ballast gas enter from battery limits and are mixed with lean cycle
gas before entering a preheating unit (Gas-Gas Exchanger E-111). The gas mixture flows
from E-111 to the EO Reactor/Gas Coolers (R-110) where about 9.6% of the ethylene is
converted per pass. The ethylene to ethylene oxide selectivity is 91% at start-of-run (SOR).
The reactors produce ethylene oxide. The ethylene oxide is scrubbed from the EO
Reactor/Gas Coolers exit gas using lean cycle water in Wash Tower (C-115) and the rich
cycle water is sent to the EO Stripping Section. The (scrubbed) cycle gas is sent through the
CO2 Contactor Section of the Wash Tower (C-115) to remove carbon dioxide made in the
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 11 OF 106
EO Reactor/Gas Coolers. The CO2-lean gas is then recompressed back to the EO
reactor/Gas Coolers in Recycle Compressor (K-115). Boiling water on the shell side of the
multi-tubular reactors removes the heat of reaction. Water circulation through the shell side
of the reactors is by thermo-syphon action. The steam-water mixture from the reactors shell
side is sent to steam drums (V-110) where make-up boiler feed water is preheated and
steam is separated from water and sent to the 21 kg/cm2g steam header.
CO2 Removal Section
The rich carbonate solution from the Carbonate Solution Exchanger (E-117) is regenerated
at essentially atmospheric pressure using stripping steam. The regenerated lean carbonate
solution is returned to the CO2 Contactor Section of the Wash Tower (C-115) for CO2
absorption.
EO Stripping and EO Reabsorption Section
Rich cycle water containing ethylene oxide in solution is preheated in Cycle water exchanger
(E-312) before entering the Stripping Column (C-310) where ethylene oxide is stripped out.
The lean cycle water is then pumped through a series of heat exchangers (E312 & E-
313A~F) where the water is cooled prior to being returned to the Scrubber Section of the
Wash Tower using Cycle Water Pump (P-312 A/B). A bleed stream is taken and sent to the
glycol unit to purge the glycol made in the cycle water loop. The ethylene oxide in the
overhead vapor from the Stripping Column (C310) is reabsorbed by contact with cooled
process water in the Re-absorber (C-320). The overhead from the Re-absorber is
compressed back into the cycle gas system by the Reclaim Compressor (K-320) while the
bottoms are sent to the Glycol Feed Stripper (C-510).
Glycol Reaction and Glycol Evaporation Section
Ethylene oxide solution from the Re-absorber (C-320) is sent to the Glycol Feed Stripper (C-
510) for removal of CO2 .The CO2 -free stream is then preheated in series of exchanger (E-
520~E523) and fed to the Glycol Reactor (R-520). The reactor effluent is fed into the first
stage of a Seven Effect Evaporator System. The cycle water bleed from the cycle water and
the MEG Column Condenser (E-621) blowdown are treated in a Cycle Water Treating Unit
(A-550) and then used in the evaporator system as reflux. The condensate from the
reboilers of the evaporators is used to preheat the feed to the Glycol Reactor (through pump
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 12 OF 106
P-*535A/B), and is then sent to the Recycle Water Tank (TK-540). The overhead from the
Fifth Effect Evaporator (extraction steam) is used in the Regenerator Extraction Reboiler (E-
223). The overhead vapor from the Sixth Effect Evaporator is used as stripping steam for
both the Stripping Column and Glycol Feed Stripper and also is used to re-boil the Vacuum
Effect Evaporator bottoms (E-537) and to preheat the feed to the Glycol Reactor through
First Stage Reactor Feed Heater (E-521). The overhead from the Vacuum Effect Evaporator
is condensed in Vacuum Effect Condenser (E-538) with a portion returning to the column as
reflux, another portion is used as reflux for the Drying Column (C-610) and the remainder is
sent to the Recycle Water Tank (TK-540) using Evaporator Hotwell Pump (P-537A/B) via
Recycle Water Cooler (E-540 A/B). The concentrated glycol from the Vacuum Effect
Evaporator is pumped to the Drying Column (C-610) for removal of the remaining water.
Glycol Drying and Glycol Purification Section
The crude wet glycol is dried by vacuum distillation in the Drying Column (C-610). The
Drying Column bottoms are filtered in MEG Column Feed Filter (GN-620A/B) and fed to the
MEG Column (C-620) where fiber grade monoethylene glycol product is taken as a side
stream product near the top of the column. The product is cooled in MEG Product Cooler
(E-622) and stored in the MEG Rundown Tanks (TK-640 a/B) for subsequent pumping to
OSBL storage. The MEG Column bottoms are sent to the MEG Splitter (C-630) using MEG
Column Bottoms Pump (P-620A/B) where the remaining MEG is removed from the heavier
glycols and recycled back to the Vacuum Effect Evaporator (C-537). The MEG Splitter
bottoms are filtered in DEG Column Feed Filters (GN-710 A/B) and are sent to the DEG
Column (C-710) for DEG and TEG Separation.
Glycol Drying and Glycol Purification Section
Heavy glycols from the MEG Splitter (C-630) bottoms are distilled in the DEG Column (C-
710) where the diethylene glycol (DEG) product is taken overhead. The DEG product is
cooled in DEG Product Cooler (E-712) and stored in the DEG Rundown Tanks (TK-730 A/B)
for subsequent pumping to OSBL storage. The DEG Column bottoms are then sent to the
TEG Column (C-720) for further distillation where the triethylene glycol (TEG) product is
taken overhead. The TEG product is cooled in TEG Product Cooler (E-722) and stored in
the TEG Rundown Drums (V-740 A/B) for subsequent pumping to OSBL storage. The TEG
Column bottoms, containing the polyglycols, are stored in the PEG Drum (V-750).
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 13 OF 106
4.1.3. Offsite & Utilities
Brief description of O&U systems are mentioned in the below:
Air Separation Unit (ASU)
Air separation unit is required to produce gaseous Oxygen and Nitrogen used in ER/EG
Units.
Gaseous oxygen is required as a raw material in EG process. Gaseous Nitrogen is required
as ballast gas in EG process as well as other purposes such as blanketing, purging,
regeneration, start-up operation of compressors etc.
Air is filtered to remove particulates and is then compressed in the Main Air Compressor.
After the air is compressed, it passes to the aftercooler where it is cooled with cooling water
and condensed water is removed. The saturated air then passes to the Adsorber vessels
where water vapor and carbon-dioxide are removed to prevent these components freezing
out in the cryogenic section of the plant and causing blockages. From the Adsorber, the air
then passes to the cold box. The stream leaving the Adsorber enters the main heat
exchanger, where it is cooled to around its dew point by heat exchange with the returning
product streams, and fed into the bottom of the high pressure distillation column.
To generate refrigeration for the distillation process, nitrogen from the top of the low
pressure section of the cold box is passed through an expander, where the pressure of the
gas is reduced to create refrigeration. After the cold box, the compressed, dry air is split
into oxygen and nitrogen streams by distillation at cryogenic temperatures.
Cooling Water System
The cooling water system which includes cooling towers, cooling water recirculation pump,
cooling water distribution headers and cooling water treatment facilities (viz. chemical
dosing for quality control, sulphuric acid for pH control etc.) and other auxiliary items.
Intermediate / Product Storage and Product Evacuation
Storage of Intermediate Feed/product is used to buffer production/consumption imbalance
or product off specification.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 14 OF 106
Ethylene Storage
Ethylene product is pumped by the Ethylene product Pump (060-P-302A/B) in ERU,
bypassing FCC off Gas Chiller (060-E-201) to Ethylene Storage Spheres (207-HS-002A~D).
The spheres will be used to buffer ethylene production/consumption imbalance (MEG plant
non-operational) or product out of specification. Four ethylene storage spheres are used.
Out of four spheres, three are for on-spec ethylene storage and one is common for off-spec
ethylene storage and maintenance and inspection.
Five days storage is considered for on-spec ethylene product. Ethylene product in the tanks
is stored at ~18 kg/cm2g, -31.7 °C. The constant boil-off vapors will be sent to Deethylenizer
column (060-C-301). This shall be further verified with ERU Process Licensor (Lummus
Technology Inc.).
MEG Product Storage
MEG product from Ethylene Glycol unit is transferred to offsite MEG Storage Tanks (207-
TK-003 A~E) using MEG Product pumps. One tank is considered for maintenance, since
tank maintenance and inspection time is 3 to 6 months.
DEG Product Storage
DEG product from Ethylene glycol unit is routed to DEG Storage tank (207-TK-004 A~B)
located in offsite area. One tank is considered for maintenance, since tank maintenance and
inspection time is 3 to 6 months.
TEG Product Storage
TEG product from Ethylene glycol unit is routed to DEG Storage tank (207-TK-005 A~B)
located in offsite area. One tank is considered for maintenance, since tank maintenance
and inspection time is 3 to 6 months.
Product Evacuation Tanker Loading Gantries will be used for road tanker loading of finished liquid products. Top loading of the
tanker is considered for non-pressurized filling and bottom loading is considered for
pressurized filling. Loading will be done through mass flowmeters (all 7 bays).
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 15 OF 106
Ship Loading
Ship loading is considered only for MEG Product Evacuation. New line for MEG Product
Transfer from storage to south jetty is to be considered for ship loading of MEG
product. It will be dedicated line for MEG product only. Dedicated pumps (with
standby) shall be considered for ship loading of the MEG product. New loading arm for
loading MEG Product in the ship is to be considered at south jetty. Loading arm
capacity shall match with the maximum loading rate i.e. 1000 x 1.1 m3/hr.
Barrel Filling Facility
Automated barrel filling (Barrel size: 200 let.) facility provided for TEG product in offsite
area.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 16 OF 106
4.2. Project Site / Location
The project is located in Paradip, Odisha, India as shown in Figure 4.4
4.3. Meteorological Data
Refer Assumption A5 of document “RA Study Methodology & Assumptions” (Doc. No.:
IEPG-6351-8110-PH-000-0013 Rev A2) for Meteorological data considered for the study.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 17 OF 106
5. OVERVIEW OF RA METHODOLOGY
The key elements of RA Study comprise the following steps:
System Definition
Hazard Identification
Consequence Analysis
The RA methodology & assumptions are detailed in document “RA Study Methodology &
Assumptions” (Doc. No.: IEPG-6351-8110-PH-000-0013 Rev A2) as attached in Annexure
A.
6. HAZARDS ASSOCIATED WITH THE PROJECT
6.1. General
As this is a preliminary risk assessment hence it is primarily concerned with the impact of
the project on the surrounding environment and population. Discussion of hazardous events
will focus on those materials that will be present in quantities large enough to cause
potential problems outside the site, if a release occurs.
The main hazards will arise from the loss of containment of pressurized liquids or gases. A
loss of containment of liquid hydrocarbons has the potential to cause a pool fire, a jet fire or
a vapour cloud explosion. Gaseous hydrocarbons, though, do not result in pool fires
although they too are liable to giving rise to jet fires and vapour cloud explosions.
6.2. Hazards Associated with Flammable Materials
The units under this project contain numerous flammable streams, which on release could
result in a flammable hazard. This release could result in:
Jet Fire (ignited release)
Flash Fire (unignited release)
Vapor Cloud Explosion
Boiling Liquid Expanding Vapor Explosion (BLEVE)
Pool Fire
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 18 OF 106
6.3. Hazards Associated with Toxic Materials
The unit under this project contains potentially toxic streams, which on release could result
in a toxic hazard. These releases also pose a flammable hazard. On release toxic hazards
can cause physiological effects, dependant on the concentration and duration of exposure.
7. HAZARD IDENTIFICATION
Hazard identification involves a review of the hazardous properties of the material processed
and / or stored at the plant, review of major accidents worldwide at similar facilities. Based
on this review, a comprehensive list of potential loss of containment sources was generated
as a basis for subsequent consequence analysis.
7.1. Hazardous Substances
7.1.1. Hydrogen
Hydrogen (H2) is very light and rises very rapidly in air at normal temperature and pressure.
It is highly flammable (burns with an almost invisible flame of relatively low thermal radiation)
and explosive. It has the widest range of flammable concentrations in air among all common
gaseous fuels. This flammable range of Hydrogen varies from 4% by volume (lower
flammable limit) to 75% by volume (upper flammable limit). Hydrogen flame (or fire) is nearly
invisible even though the flame temperature is higher than that of hydrocarbon fires and
hence poses greater hazards to persons in the vicinity.
Hydrogen is biologically inactive and essentially non-toxic, hydrogen is a simple asphyxiant.
Hydrogen is not listed in the IARC, NTP or OSHA as a carcinogen or potential carcinogen.
Exposure to high concentrations may exclude an adequate supply of oxygen to the lungs.
No significant effect to human through dermal absorption and ingestion is reported. Refer to
Table 7.1 for properties of hydrogen. Constant exposure of certain types of ferritic steels to
hydrogen results in the embrittlement of the metals. Leakage can be caused by such
embrittlement in pipes, welds, and metal gaskets.
Table-7.1: Hazardous Properties of Hydrogen
S. No. Properties Values 1. LFL (%v/v) 4 2. UFL (%v/v) 75 3. Auto ignition temperature (°C) 520 4. Heat of combustion (Kcal/Kg) 28700 5. Normal Boiling point (°C) -252 6. Flash point (°C) N.A.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 19 OF 106
7.1.2. Methane
Methane in form of liquid or gas is extremely flammable. The liquid will rapidly boil to the
gas at standard temperatures and pressures. The liquefied gas can cause frostbite to any
contaminated tissue. As a gas, if venting or leaks, catches fire. The gas is lighter than air
and may spread long distances from leak source, creating an explosive re-ignition hazard.
Vapours can be ignited by pilot lights, other flames, smoking, sparks, heaters, electrical
equipment, static discharge, or other ignition sources at locations distant from product
handling point. Explosive atmospheres may linger. Refer to Table 7.2 for properties of
methane.
Methane is essentially non-toxic. Methane acts as a simple asphyxiant and present
significant health hazard by displacing the oxygen in the atmosphere.
Table: 7.2: Hazardous properties of Methane S. No. Properties Values
1. LFL (%v/v) 5.0 2. UFL (%v/v) 15.0 3. Auto ignition temperature (°C) 630 4. Normal Boiling point (°C) -161.5 5. Flash Point (°C) -187.8
Potential Hazardous Effects – Flammable
7.1.3. Ethane
Ethane is extremely flammable gas. If venting or leaks, catches fire. The flammable
vapours may spread from leak source, creating an explosive re-ignition hazard. Vapours can
be ignited by pilot lights, other flames, smoking, sparks, heaters, electrical equipment, static
discharge, or other ignition sources at locations distant from product handling point.
Explosive atmospheres may linger. Refer to Table 7.3 for properties of ethane.
Table: 7.3: Hazardous properties of Ethane
S. No. Properties Values 1. LFL (%v/v) 3.0 2. UFL (%v/v) 12.5 3. Auto ignition temperature (°C) 472 4. Normal Boiling point (°C) -88 5. Flash Point (°C) -135
Potential Hazardous Effects – Flammable
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 20 OF 106
7.1.4. Propane
A spillage or loss of containment of this hydrocarbon will result in a highly flammable
Vapour. Propane forms an explosive air-vapour mixture at ambient temperature. Propane
vapour is heavier than air and may travel to remote place of ignition e.g. along drainage, into
basement etc. Propane liquid leak generates large volumes of flammable vapours (approx.
250:1).
Cold burns (frostbite) will result from skin / eye contact with liquid. Propane liquid release or
vapour pressure jets present a serious risk to eyes. Abuse involving wilful inhalation of high
concentration of vapour, even for short periods, can produce unconsciousness, or might
prove fatal. Inhalation may cause irritation to the nose and throat, headache, nausea,
vomiting, dizziness and drowsiness. These materials delivered, stored and used at
temperature above their flash point. In case of the fire, immediately fire brigade should be
called. If gas has ignited, should not try attempting to extinguish, but stop gas flow and allow
burning out. Every precaution must be taken to keep containers cool to avoid the possibility
of a boiling liquid expanding vapour explosion (BLEVE).
Table: 7.4: Hazardous properties of Propane
S. No. Properties Values 1. LFL (%v/v) 2.1 2. UFL (%v/v) 9.5 3. Auto ignition temperature (°C) 450 4. Normal Boiling point (°C) -42.1 5. Flash Point (°C) -104 (PMCC)
Potential Hazardous Effects – Flammable
7.1.5. Propylene
Propylene is highly hazardous hydrocarbon products (due to its flammable nature) handled
in the Refinery. It is primarily a mixture of C3 hydrocarbons components, which remain in
gaseous state under atmospheric pressure and temperature. Equipment’s of Ethylene
Recovery units (i.e. vessels, columns, pumps, compressors etc.) are commonly associated
with Propylene. Refer to Table 7.5 for properties of Propylene.
Table: 7.5: Hazardous properties of Propylene S. No. Properties Values
1. LFL (%v/v) 2.0 2. UFL (%v/v) 11.0 3. Auto ignition temperature (°C) 455 4. Heat of combustion (Kcal/Kg) 11000 5. Normal Boiling point (°C) -47
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 21 OF 106
7.1.6. Ethylene
Ethylene is a colourless, flammable gas with a slightly sweet odour or a colourless,
cryogenic liquid with a slightly sweet odour. This gas acts as a simple asphyxiant and
presents a significant health hazard by displacing the oxygen in the atmosphere. The gas
may spread long distances. Distant ignition and flashback are possible. The cryogenic liquid
will rapidly boil to the gas. The liquefied gas can cause frostbite to any contaminated tissue.
Both the liquid and gas pose serious fire hazards when accidentally released. Ethylene can
undergo a violent chemical reaction at elevated temperatures. Refer to Table 7.6 for
properties of ethylene.
Table: 7.6: Hazardous properties of Ethylene S. No. Properties Values
1. LFL (%v/v) 2.7 2. UFL (%v/v) 36.0 3. Auto ignition temperature (°C) 450 4. Heat of combustion (Kcal/Kg) 11000 5. Normal Boiling point (°C) -104 6. Flash Point (°C) 136 (OC)
Potential Hazardous Effects – Flammable
7.1.7. Ethylene Oxide
Ethylene Oxide is extremely flammable. It may form explosive mixtures with air and oxidizing
agents. Flammable vapours may spread from spill. Explosive atmosphere may linger.
Vapours can burn without the presence of air or oxidizing agents. ETO can decompose
violently under certain conditions. Vapour in air has very low ignition energy and is prone to
static or other low energy ignition sources.
Ethylene oxide is toxic in nature, if involved in a fire and may emit irritating and potentially
toxic fumes. Fumes and vapours may spread from leak. Vapours are heavier than air and
may collect in low spots.
Table: 7.7: Hazardous properties of Ethylene Oxide S. No. Properties Values
1. LFL (%v/v) 3 2. UFL (%v/v) 100 3. Auto ignition temperature (°C) 429 4. Normal Boiling point (°C) 10.5 5. Flash Point (°C) -20 6. IDLH (ppm) (exposure time 1800 sec) 800 (NIOSH)
Potential Hazardous Effects – Flammable, Toxic
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 22 OF 106
7.1.8. Hydrogen Sulfide (H2S)
Hydrogen sulphide release is associated mainly with Amine Regeneration section, Sour
Water Stripper and Sulphur Recovery Unit. Hydrogen sulphide is a known toxic gas and has
harmful physiological effect. Accidental release of hydrocarbons containing hydrogen
sulphide poses toxic hazards to exposed population. Prolonged exposure to hydrogen
sulphide can cause irritation in eyes, respiratory system, apnea, coma, convulsions;
conjunctivitis, eye pain, lacrimation (discharge of tears), photophobia (abnormal visual
intolerance to light), corneal vesiculation, dizziness, headache, lassitude (weakness,
exhaustion), irritability, insomnia, gastrointestinal disturbance, liquid frostbite is also
flammable and can cause substantial damages if it finds source of ignition. The hazardous
properties of H2S are listed in table below:
Table: 7.8: Hazardous properties of Hydrogen Sulfide (H2S) S. No. Properties Values
1. LFL (%v/v) 4 2. UFL (%v/v) 46 3. Auto ignition temperature (°C) 260 4. Normal Boiling point (°C) -60.4 5. Melting / Freezing Point (°C) -82.8 6. IDLH (ppm) (exposure time 1800 sec) 100 (NIOSH)
7.1.9. Carbon Dioxide
Carbon dioxide (CO2) under ambient conditions is a colourless odourless gas. At higher
concentration, it has a sharp acidic odour and can be toxic. CO2 may cause asphyxiation
when the available oxygen is displaced.
CO2 is not flammable and the major hazard associated with CO2 exposure is toxicity.
Exposure to moderate concentrations can cause headache, drowsiness, dizziness, stinging
of the nose and throat, excitation, rapid breathing and heart rate, excess salivation,
vomiting, and unconsciousness. At higher concentrations, the CO2 dissolved in the blood
lowers the pH affecting the respiratory, cardiovascular and central nervous systems.
Potential Hazardous Effects – Toxic
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 23 OF 106
7.1.10. Mono-ethylene Glycol (MEG)
MEG has a low vapour pressure and not readily evaporate from water or soil. Ethylene
glycol is a clear, colorless, odorless, involatile and hygroscopic liquid with a sweet taste. It is
somewhat viscous liquid; miscible with water.
Table: 7.9: Hazardous properties of Mon-ethylene glycol (MEG) S. No. Properties Values
1. LFL (%v/v) 3.2 2. UFL (%v/v) 15.3 3. Flash Point (°C) 111 (cc) 4. Auto ignition Temperature (°C) 398 5. Normal Boiling point (°C) 197.6 6. Melting Point (°C) -13
7.1.11. Di-ethylene Glycol (DEG)
DEG is stable at room temperature. DEG is odorless, colorless, and hygroscopic liquid with
a sweet taste and bitter aftertaste. Table: 7.10: Hazardous properties of di-ethylene glycol (DEG)
S. No. Properties Values 1. LFL (%v/v) 1.6 2. UFL (%v/v) 10.8 3. Flash Point (°C) 124 (oc) 4. Auto ignition Temperature (°C) 224 5. Normal Boiling point (°C) 244 6. Melting Point (°C) -6.5
7.1.12. Tri-ethylene Glycol (TEG)
TEG is stable at room temperature. TEG is odorless, colorless to pale yellow liquid. Very
mild, sweet odor. Mixes with alcohol. Material is hygroscopic, absorbs moisture from
surrounding air. Table: 7.11: Hazardous properties oftrii-ethylene glycol (TEG)
S. No. Properties Values 1. LFL (%v/v) 0.9 2. UFL (%v/v) 9.2 3. Flash Point (°C) 176.667 (cc) 4. Auto ignition Temperature (°C) 347 5. Normal Boiling point (°C) 285 6. Melting Point (°C) -5
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 24 OF 106
7.1.13. Ethylene dichloride (EDC)
Ethylene dichloride is a clear, colorless liquid with a sweet choloroform-like odor. The liquid
is flammable, and its vapors can form explosive mixtures with air. Table: 7.11: Hazardous properties oftrii-ethylene glycol (TEG)
S. No. Properties Values 1. LFL (%v/v) 6.2 2. UFL (%v/v) 15.9 3. Flash Point (°C) 13 (cc) 4. Auto ignition Temperature (°C) 413 5. Normal Boiling point (°C) 83.5 6. Melting Point (°C) -35.5
7.1.14. Oxygen
Oxygen is a tasteless, colorless gas, odorless. Breathing pure oxygen at high pressure
(greater than 1 atm) can sause hyperoxia. Oxygen is stable when kept isolated as a
compressed gas in cylinders.
Table: 7.11: Hazardous properties oftrii-ethylene glycol (TEG)
S. No. Properties Values 1. LFL (%v/v) None reported 2. UFL (%v/v) None reported 3. Flash Point (°C) Non flammable 4. Auto ignition Temperature (°C) - 5. Normal Boiling point (°C) -183 6. Melting Point (°C) -218.4
7.2. Modes of Failure
There are various potential sources of large leakage, which may release hazardous
chemicals and hydrocarbon materials into the atmosphere. These could be in form of gasket
failure in flanged joints, bleeder valve left open inadvertently, an instrument tubing giving
way, pump seal failure, guillotine failure of equipment / pipeline or any other source of
leakage. Operating experience can identify lots of these sources and their modes of failure.
A list of general equipment and pipeline failure mechanisms is as follows:
7.2.1. Material / Construction Defects
Incorrect selection or supply of materials of construction
Incorrect use of design codes
Weld failures
Failure of inadequate pipeline supports
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 25 OF 106
7.2.2. Pre-Operational Failures
Failure induced during delivery at site Failure induced during installation Pressure and temperature effects Overpressure Temperature expansion / contraction (improper stress analysis and support design) Low temperature brittle fracture (if metallurgy is incorrect) Fatigue loading (cycling and mechanical vibration)
7.2.3. Corrosion Failures
Internal corrosion (e.g. ingress of moisture) External corrosion Cladding / insulation failure (e.g. ingress of moisture) Cathodic protection failure, if provided
7.2.4. Failures due to Operational Errors
Human error
Failure to inspect regularly and identify any defects
7.2.5. External Impact Induced Failures
Dropped objects Impact from transport such as construction traffic Vandalism Subsidence Strong winds
7.2.6. Failure due to Fire
External fire impinging on pipeline or equipment Rapid vaporization of cold liquid in contact with hot surfaces
7.3. Review of Industry Incidents
A review of industry incidents related to Ethylene Recovery and Ethylene Glycol facilities
was carried out using well established international accident databases such as Major
Accidents Reporting System (eMARS) maintained by Major Accidents Hazards Bureau
(MAHB) and Emergency Response Notification System (ERNS) maintained by Right To
Know Network (RTK). Major accidental events with potential for personnel injury or fatality
due to fire, explosion and/or toxic release were identified and analyzed. Refer to Table 7.8
for incident reported by eMARS for various hazardous substances mentioned under Section
7.1.
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 26 OF 106
Table 7.8 Incidents reported by eMARS accident database
Date Incident Consequence Substance Involved
Fatality Injuries
23-01-2014 During the change of piping and support of a feed line of
an intermediate storage vessel for hydrochloric acid, an
explosion occurred. The flame propagated back into the
tank, causing a second explosion inside. The explosion
was caused by the unexpected presence of a
considerable amount of hydrogen in the tank which was
formed in a reaction of traces of metal powder and the
hydrochloric acid and accumulated over a period of two
months. The metal powder traces were present in the in
the feed to the storage tank due to incomplete reaction in
upstream reactor due to the lower operating temperature.
The reaction continued in the storage tank and hydrogen
thus formed accumulated at tank top.
The tank ripped open and
was catapulted into the air,
killing both workers in the
process.
Hydrogen 2 No serious injuries
were reported
01-09-2005 A fire broke out affecting the heavy fuel purification plant
of the refinery. A jet-fire was ignited, causing rupture of
the 3” hydrogen pipe and subsequently ignition of the
released hydrogen. Approximately 30 minutes later, the
fire ignited an 8" fuel pipe of the diathermic oil system
The fire was kept under
control and evolved without
noticeable changes until
consumption of the fuel once
the pipes were shut off
Hydrogen No
fatalities
were
reported
No damages to
persons have been
reported
consequent to the
accident.
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 27 OF 106
Date Incident Consequence Substance Involved
Fatality Injuries
ruptured and subsequent ignition of the product. according to the emergency
response plan which had
been activated. The fire was
extinguished in 3 hours and
40 minutes after the fire
initiated
24-06-2005 An over-dosage of natron lye in a silicon dust suspension
container raised the pH-value up to 11, producing large
amounts of hydrogen in a short time. The hydrogen
caused an extreme pressure increase in the container
which consequently burst. The expanded hydrogen ignited
immediately on contact with the atmosphere
Total destruction of plant
section, damage to adjacent
buildings and cars in
surrounding area
Hydrogen No
fatalities
were
reported
No serious injuries
were reported
12-10-2002 Leakage of about 70 m3 of distilled petroleum
intermediate and 200 Nm3 of hydrogen in
Desulphurization unit of distilled intermediate. The
initiating event was vessel rupture which led to jet flame
and pool fire. This activation of external emergency plan
controlled the events.
No further consequences
were reported.
Hydrogen No
fatalities
were
reported
No serious injuries
were reported
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 28 OF 106
Date Incident Consequence Substance Involved
Fatality Injuries
27-02-2005 Leakage in pipe of Ethylene Oxide plant. Leak at the rate
of approximately 200 kg/hr was observed resulting in loss
of 22 tons of highly flammable hydrocarbons. The leakage
took place in the curve of a METHANE pipe (situated high
above the ground) through several small holes in the pipe.
Probable cause is condensation of water in the transport
gas.
As soon as the leakage was discovered it had been
arrested by putting custom made pipeline clamp.
Afterwards extra checks were undertaken in which the
company monitors the clamp placed around the pipe.
Release of unignited
flammable hydrocarbons into
the atmosphere.
Methane
Ethane
No
fatalities
were
reported
No injuries were
reported
25-04-2015 In Steam Cracker plant, a major leak occurred as a result
of the catastrophic failure of the nuts on the studs
connecting the bonnet and the body of a 2” manual drain
valve (flange leak) in a blow-down line. The bonnet was
ejected from the valve body, creating a 2” opening in the
system to atmosphere. Approximately 45 tons highly
flammable hydrocarbons were released to atmosphere.
Release of unignited
flammable hydrocarbons into
the atmosphere.
Methane
Ethylene
No
fatalities
were
reported
No injuries were
reported
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 29 OF 106
Date Incident Consequence Substance Involved
Fatality Injuries
The system was stopped, isolated and depressurized to
flare and maintenance work was undertaken to replace
the damaged valve.
27-09-2001 Release of propane from the emergency drain valve
(globe valve not closed properly) of road tanker while
taking sample using in-house designed & constructed
adapter and house / valve assembly.
Release of 16.10 tonnes
propane to ground.
Substantial quantity of
propane went into surface
water drains and reached
the oil/water interceptors.
Propane flashed off there.
Propane No
fatalities
were
reported
No serious injuries
(minor frost burns)
were reported
16-06-2001 Saturate Gas Plant (SGP), de-ethanizer column overhead
line failure resulting in an inventory loss and release of
extremely flammable gases. A catastrophic failure
occurred on a section of pipework (ID: 6”) of SGP, at an
elbow just downstream of a water-into gas injection point.
The primary cause of the catastrophic rupture and was the
erosion / corrosion of the 6” pipe which carried the
overhead vapours from the De-ethanizer to the Heat
Released gas formed vapour
cloud which subsequently
exploded resulting in
damage to SGP structure
and damage to houses and
businesses within a 1km
radius of the site (broken
windows and cracks to
ceiling and walls).
Ethane
Propane
Butane
No
fatalities
were
reported
72 civil injuries
were reported.
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 30 OF 106
Date Incident Consequence Substance Involved
Fatality Injuries
Exchanger in the SGP. The failure occurred downstream
of, and in close proximity to, a water injection point that
was not part of the original design.
The wall thickness of overhead line had been reduced
from around 7-8mm to a minimum of 0.3mm.
01-07-2008 Flange leak of hydrocarbon pump discharge of Olefin
installation during shutdown maintenance activity resulting
in release of hydrocarbon and subsequent fire due to
nearby ignition source (dropped wrench, hammer or
others).
Burn injury to maintenance
worker.
Propane 2 No serious injuries
were reported
14-08-2003 Insufficient temperature and pressure in the de-butanizer
column which led to untreated gas accumulating in the
petrol tank forming a pocket. This gas pocket spread
outside into the recipient until it reached an ignition source
resulting in flash fire and vapour cloud explosion.
Serious damage to the
industrial plant, storage
tanks in the area, window
and roof collapse of
buildings in plant area and
affected surrounding area.
Butane and
lighters
9 10
01-01-2007 In Steam Cracker Unit, a leak on the vent hole of the cold
box housing the ethylene / ethylene heat exchanger
(insulated by pearlite). The vent hole located at a height of
Release of unignited highly
flammable gas to the
atmosphere.
Ethylene
Ethane
No
fatalities
were
No injuries were
reported
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 31 OF 106
Date Incident Consequence Substance Involved
Fatality Injuries
15 m is used to evacuate the inert nitrogen of the cold box
that functions between -40 and -50 °C under 8 to 11 bar.
72 tonnes of flammable gas were released into the air at a
rate of 60 kg/hr.
To avoid any risk of ignition or explosion, the operator has
installed 4 gas detectors, constantly measured the internal
pressure of the box, monitored the development of leaks
by video camera with a feed to the control room,
increased the vent hole from 1" to 3" after installing an
elbow on it to divert the leak from the installation, which
was then connected to a mobile flare and put into service.
Water and steam curtain systems and fire monitors were
pre-positioned in case of a major leak. Automatic shut-off
valves were installed to rapidly isolate the section
concerned and the work permits procedure was modified
to take into account the deteriorated the situation.
reported
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 32 OF 106
Date Incident Consequence Substance Involved
Fatality Injuries
17-03-2008 Release of ethylene and subsequent fire with explosion in
a tank farm causing material damage of approx. 2000000
EUR. Also engulfed adjoining acrylonitrile tank developing
to a full scale fire.
To limit the further damage, cooling of nearby equipment
over several hours by the onsite fire brigade and external
fire brigades were carried out. Evacuation of parts of the
installation and cordoning public roads were done.
Damage to equipment and
buildings of the installation
Ethylene No
fatalities
were
reported
No injuries were
reported
24-07-2013 Leakage of hydrocarbon from propylene compressor of
the Steam Cracker. A threaded connection of ¾ inches oil
pipe ¾ on an isolation valve cracked due to a progressive
fatigue caused by vibration appeared throughout the oil
circuit. Vibration and notch effect in the thread root (a 5
mm thread emerging largely beyond the useful engaged
height which is approximately 10 mm) were the main
factors behind the rupture.
Environmental pollution due
to flaring of hydrocarbons for
48 hours during the
production process.
Propylene No
fatalities
were
reported
No injuries were
reported
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 33 OF 106
Date Incident Consequence Substance Involved
Fatality Injuries
18-06-2007
Hydrogen sulfide is separated from the refinery gas in
the absorption column with diisopropanolamine (CAS
82229-41-2). The cleaned fuel gas is conveyed into the
refinery's fuel gas network.
When the event occurred the low-level shut-down
system of the column triggered. Under normal conditions
a control valve would have closed and the column level
would have risen again. The control valve however was
blocked in open position by metal parts (column
internals) and the column level dropped to zero. The
charged diisopropanolamine was diverted entirely to the
regenerator and a gas break-through of H2S occurred
over the diisopropanolamine-regenerators towards the
Claus-plants. Both the Claus-plants and the
downstream catalytic post-combustion unit were
overcharged and the gas containing H2S was discharged
over the 175m high chimney of the cracker.
Strong odour nuisance > 1h H2S
Nil
No injuries were
reported
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 34 OF 106
Date Incident Consequence Substance Involved
Fatality Injuries
05-09-2006 Release of carbon monoxide (CO) and hydrogen sulphide
(H2S) occurred in the area where a new unit of the refinery
was under construction.
During the start up phase of the catalytic cracking unit
CR4/FCC, CO is generated during approx. 30 minutes
while the charge passes at less than 700°C through the
catalyst.
Also the H2S, which is contained in the combustion gas
generated by the oven receiving the stripping water from
the unit, is directly released to atmosphere.
Release of toxic gas to
atmosphere
CO & H2S
estimated
amount
released
(225 kg)
No
fatalities
were
reported
7 injuries were
reported.
05-01-2009 In vis-breaking unit of a refinery, while performing an
intervention on equipment which could potentially inhaled
H2S.
Inhalation of hydrogen
sulphide leading to fatality.
H2S 1 No injuries were
reported.
10-09-2002 During unloading catalyst from a blinded reactor at Claus
unit. By the end of the day one of the workers violated the
end of work order and entered the restricted area (confined
vessel) without any protection. As soon as he entered the
vessel they fell unconscious. The other two workers tried to
help him, entered the vessel without protection and suffered
the same symptoms too.
Inhalation of hydrogen
sulphide leading to fatality.
H2S & CO 3 No injuries were
reported.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 35 OF 106
7.4. Unit Sectionalization & Selected Failure Cases
The Ethylene Recovery unit and Ethylene Glycol unit were divided into 08 and 13 sections,
respectively, for the analysis based on inventories, hazardous properties of process streams
and process conditions. The detailed plant sectionalization is graphically depicted in Figure
7.1, Figure 7.2 & Figure 7.3 and Table 7.9, Table 7.10 & Table 7.11 presents the description
and modelling conditions of the hazardous sections for ER, EG and O&U facilities
respectively. Even though some of the streams, such as steam system, BFW etc., were
identified as not posing any significant toxic or flammable hazards, these were also included
in the sections list for completeness.
A list of selected failure cases was prepared based on process knowledge, engineering
judgment, experience, past incidents associated with such facilities and considering the
general mechanisms for loss of containment. A list of cases has been identified for the RA
study based on the following.
Cases with high chance of occurrence but having low consequence:
Example of such failure cases includes two-bolt gasket leak for flanges, pump seal
failure, sample connection failure, instrument tapping failure etc. The consequence
results will provide enough data for planning routine safety exercises. This will emphasize
the area where operator's vigilance is essential.
Cases with low chance of occurrence but having high consequence:
Example includes catastrophic failure of lines, process pressure vessels, pressurized
storages etc.
This approach ensures at least one representative case of all possible types of accidental
failure events, is considered for the consequence analysis. Moreover, the list below includes
at least one accidental case comprising of release of different sorts of highly hazardous
materials handled in the refinery. Although the list does not give complete failure incidents
considering all equipment’s, units, but the consequence of a similar incident considered in
the list below could be used to foresee the consequence of that particular accident.
Also Client cases have been considered for the analysis based on their comment. Headers having hydrocarbon / toxic substance cross over the creek through pipe rack. It is to be noted that these headers do not have any flanges or instrument connections over the pipe rack. Hence leakage of flanges is ruled out. However, for consequence analysis (as a conservative approach), leak on these headers over pipe rack is considered as per Client’s requirement. The cases selected for analysis are mentioned in Table 7.12.
060C10106
0R
105
060
V1
02
060E101
060V101
060P106A/B 060P107A/B 060P108
060TK101
060
V1
07
060E107
060E108
060
R1
02A
060
R1
02B
060E114
060AC101
062C101 062C102
062T101
062
V1
01
062E101
062E104
062E101A/B
062
E1
03A
/B
062P901A/B
062E105
062P902A/B06
0R
103
A
060
R1
03B06
0R
104
060GN201A/B
060
V1
03
060
V1
04
060E110
060E111
060E201
060C201 060C301
060
E2
02
060P201A/B
060P202A/B
060
E3
04
060
v30
2
060
E3
02
060
E3
03
060E301
060v301
060P301A/B
060P302A/B
060
E2
03
060
V4
06
060
V4
06
060
V4
04
060E203
060
V4
07
060E401A~F060JS404
060
V4
02
060
V4
01
060
V4
03
060V408
060K401
060AC401
060E302
060E402A~D
Figure 7.1 ER Unit
21-Aug-2017
I3
PAGE 36 OF 106
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 37 OF 106
Figure 7.2 EG UNIT
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 38 OF 106
Figure 7.3 Offsite & Utilities Sectionalization
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 39 OF 106
Table 7.9 ER Plant Sectionalization & Selected Case list
Section Description Main Equipment Case
ID Selected Failure Cases
Process Conditions Static
Inventory
(kg)
Pressure
(kg/cm2a)
Temperature
(°C)
Mass Flowrate
(kg/h)
Phase
[Note 1]
Amine Treatment Section
DGA/Water wash Column (062-C-101), DGA
Regenerator (062-C-102), DGA Regenerator Reflux
Drum (062-V-101), DGA Regenerator Condenser (062-
E-101), DGA Storage Tank (062-T-101)
ER-01 DGA/Water wash tower overhead line instrument
tapping failure 14.1 40 56788 V 1932
ER-02 DGA Reflux drum overhead line pin hole leak 1.5 98 2309 V 2500
Caustic Water Wash
Section
Caustic/Water Wash Tower (060-C-101), Chloride
Treater Feed KOD (060-V-107), FCC Off gas chloride
Treater (060-R-105), Oxygen Converter Feed/Effluent
Exchanger (060-E-107)
ER-03 FCC Off gas Chloride treater outlet flange gasket
failure 12.3 54.8 57007.2 V 3496
Oxygen Converter
Section
Oxygen Converter Feed Heater (060-E-108), FCC Off
gas Oxygen Converter (060-R-102A/B) ER-04
FCC Off gas Oxygen Converter outlet line flange
gasket leak 11.4 266 57007.2 V 1144
Drying & Treating Section
Dryer Feed Chiller (060-E-106), Dryer Feed Gas KOD
(060-V-103), FCC Off gas Dryer / Treater (060-R-
103A/B), FCC Off gas Mercury Adsorber (060-R-104),
Mercury Adsorber Effluent Filters (060-GN-201A/B)
ER-05 Process off gas line from C-101 to Dryer feed KOD
flange leakage 10.9 54.9 56813.1 V 2945
ER-06 Mercury Absorber Effluent filter flange gasket leak 10 15.6 56173.7 V 2661
ER-07 Regeneration gas line instrument tapping failure 7.9 300 10700.7 V 452
Demethanizer Section
Demethanizer )060-C-201), Demethanizer Bottoms
Pumps (060-P-201 A/B), Demethanizer Intercooler
Circulating Pumps (060-C-202A/B), Demethanizer
Intercooler (060-E-202), Demethanizer Reboiler (060-E-
203)
ER-08 Demethanizer Bottoms Pumps seal failure 9.4 -42.7 57295.6 L 141749
ER-09 Demethanizer Intercooler Circulation pump seal
failure 10.5 -84.7 230000.2 L 77066
Deethylenizer Section
Deethylenizer (060-C-301), Deethylenizer Condenser
(060-E-301), Deethylenizer Reflux Drum (060-V-301),
Deethylenizer Side Reboiler (060-E-304) Deethylenizer
Reflux Pumps (060-P-301A/B), Ethylene Product Pumps
(060-P-302A/B), C3+ Product Cooler (060-E-303)
ER-10 Deethylenizer overhead line instrument tapping
failure 17.9 -33.5 128185.7 V 28073
ER-11 Ethylene Product pump seal failure 46.5 -31.7 22596.2 L 7705
ER-12 Deethylenizer bottom line flange gasket leak 18.6 51.4 4866.2 L 6624
ER-13 Catastrophic rupture of Deethylenizer Reflux Drum 17.2 -35 - L 7309
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 40 OF 106
Section Description Main Equipment Case
ID Selected Failure Cases
Process Conditions Static
Inventory
(kg)
Pressure
(kg/cm2a)
Temperature
(°C)
Mass Flowrate
(kg/h)
Phase
[Note 1]
Binary Refrigerant
Section
FCC Off gas Chiller (060-E-201), Heavy Binary
Refrigerant Accumulator (060-V-404), Medium Binary
Refrigerant Accumulator (060-V-405), Light Binary
Refrigerant Accumulator (060-V-406), Binary Refrigerant
Vent Drum (060-V-407)
ER-14 Catastrophic Rupture of Light Binary Refrigerant
Accumulator 26.1 -1 - L 813
Binary Refrigerant
Compressor Section
Binary Refrigerant Compressor (060-K-401)
ER-15
Binary Refrigerant Compressor discharge
instrument tapping failure 28.4 83.7 310000 V 5355
Table 7.10 EG Plant Sectionalization & Selected Case list
Section Description Main Equipment Case
ID Selected Failure Cases
Process Conditions Static
Inventory
(kg)
Pressure
(kg/cm2a)
Temperature
(°C)
Mass Flowrate
(kg/h)
Phase
[Note 1]
Ethylene Oxide Reaction
Section
Sulfur Guard Bed (061-R-150), Ethylene Filters (061-GN-
150A/B), Oxygen Mixing Station Sparger (061-M-110),
Gas-Gas Exchanger (061-E-111), Reactor (061-R-110)
EG-01 Ethylene Filters flange gasket leak 26 35 22500 V 1127
EG-02 Reactor Feed line instrument tapping failure 22.37 57 981000 V 49480
EG-03 Reactor Outlet line flange gasket leak 20.33 90 981000 V 40710
Ethylene Oxide & CO2
Scrubbing Section
Wash Tower (061-C-115), Wash Tower Feed / Bottom
Exchanger (061-E-115), Recycle Gas Compressor (061-
K-115)
EG-04 Recycle Compressor Instrument tapping failure 22.52 59 939865 V 23840
CO2 Removal Section Regenerator / Regenerator Feed Flash Drums (061-C-
220) EG-05 Ballast line flange gasket leak 26 45 39.9 V 1230
Ethylene Oxide Stripping
Section
Cycle Water Exchanger (061-E-312), Stripping Column /
Flash Drum (061-C-310), Stripping Column Condenser
(061-AC-311), Acid Scrubber (061-C-311)
EG-06 Acid Scrubber outlet flange gasket leakage 1.28 51 34727 V 552
EG-07 Pin hole leak at inlet of Stripping Column
Condenser (Toxic Release) 1.48 97 58550.6 V 1230
Ethylene Oxide Re-
absorber Section
Reabsorber (061-C-320), Reclaim Compressor KOD
(061-V-320), Reclaim Compressor (061-K-320) EG-08
Flange gasket leak in Reclaim Compressor
discharge 24 127 1483.6 V 630
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 41 OF 106
Section Description Main Equipment Case
ID Selected Failure Cases
Process Conditions Static
Inventory
(kg)
Pressure
(kg/cm2a)
Temperature
(°C)
Mass Flowrate
(kg/h)
Phase
[Note 1]
Glycol Reaction Section
Glycol Feed Stripper (061-C-510), Reactor Feed Pumps
(061-P-510A/B), Reactor Feed Preheater (061-E-520),
First Stage Reactor Feed Heater (061-E-521), Second
Stage Reactor Feed Heater (061-E-522), Third Stage
Reactor Feed Heater (061-E-523), Glycol Reactor (061-
R-520)
EG-09 Glycol Feed Stripper overhead line instrument
tapping failure 1.28 51 1138 V 323
Glycol Evaporation
Section
First Effect Evaporator (061-C-531), Second Effect
Evaporator (061-C-532), Third Effect Evaporator (061-C-
533), Fourth Effect Evaporator (061-C-534), Fifth Effect
Evaporator (061-C-535), Sixth Effect Evaporator (061-C-
536), Vacuum Effect Evaporator (061-C-537),
Concentrated Glycol Pumps (061-P-530A/B)
EG-10 Concentrated Glycol Pump seal failure 1.29 91 54159 L 135400
Glycol Drying Section Drying Column (061-C-610), Drying Column Bottoms
Pumps (061-P-610A/B) EG-11 Drying Column Bottoms pumps seal failure 1.17 162 48749 L 92940
MEG Purification &
Product Section
MEG Column (061-C-620), MEG Column Bottoms Pumps
(061-P-620A/B), MEG Column Product Pumps (061-P-
622A/B), MEG Post treatment Resin Bed (061-V-640),
MEG Product Transfer Pumps (061-P-640A/B), MEG
Rundown Tanks (061-TK-640A/B),
EG-12 50 mm hole on MEG Column overhead line 95 mmHg 139 68858.5 V 22.07
EG-13 MEG Column Bottoms pumps seal failure 0.5 164 4977 L 46210
EG-14 MEG Procut Transfer Pump seal failure 6.5 48 41504 L 5633
MEG Splitter Section MEG Splitter (061-C-630), MEG Splitter Bottoms Pumps
(061-P-630 A/B) EG-15
MEG Splitter Bottoms Pump discharge instrument
tapping failure 7.45 175 3163 L 16440
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 42 OF 106
Section Description Main Equipment Case
ID Selected Failure Cases
Process Conditions Static
Inventory
(kg)
Pressure
(kg/cm2a)
Temperature
(°C)
Mass Flowrate
(kg/h)
Phase
[Note 1]
DEG Purification &
Product Section
DEG Column (061-C-710), DEG Column Bottoms Pumps
(061-P-710 A/B), DEG Column Reflux Pumps (061-P-711
A/B), DEG Rundown Tanks (061-TK-730 A/B), DEG
Product Transfer Pumps (061-P-730 A/B)
EG-16 DEG Column Bottoms Pumps seal failure 6.6 178 203 L 7023
EG-17 DEG Product Transfer Pump discharge instrument
tapping failure 6.0 55 2953 L 2020
TEG Purification &
Product Section
TEG Column (061-C-720), TEG Column Bottoms Pumps
(061-P-720 A/B), TEG Column Reflux Pumps (061-P-721
A/B), TEG Rundown Drums (061-V-740 A/B), TEG
Product Transfer Pumps (061-P-740 A/B)
EG-18 TEG Product Transfer Pump discharge instrument
tapping failure 6.0 164 1342 L 822
Moderator Injection
System Moderator Feed Drum (061-V-140) EG-19 Moderator Feed Drum line rupture 24.5 40 - L 1836
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 43 OF 106
Table 7.11 Offsite & Utilities Selected Case list
Section Description Main Equipment Case
ID Selected Failure Cases
Process Conditions Static
Inventory
(kg)
Pressure
(kg/cm2a)
Temperature
(°C)
Mass Flowrate
(kg/h)
Phase
[Note 1]
Ethylene Storage
Ethylene Storage Sphere (207-HS-002A/B/C/D), Ethylene
BOG package (207-A-001), Ethylene Product Transfer
Pumps (207-P-002 A/B), Ethylene Product Vaporizer
(207-E-002 A/B),
OU-01 Flange gasket failure at the outlet of ethylene
sphere 19 -31.7 23420 L 1239695
OU-02 Flange gasket leak at BOG Package 19 -31.3 3376 V 10692
OU-03 Ethylene Product Transfer pump seal failure 30 -31.7 24750 L 1239696
OU-04 Ethylene vaporizer outlet line instrument tapping
failure 28 40 22500 V 635
OU-05 Catastrophic rupture of Ethylene Storage sphere 19 -31.7 - L 1239695
MEG Storage
MEG Storage Tanks (207-TK-003 A~E), MEG Product
Transfer Pump (207-P-003A~D), MEG Ship Loading
Pump (207-P-010 A/B), Loading Arm for MEG Tanker
Loading (207-Z-003A~E)
OU-06 MEG Product Transfer pump seal leak Atm 48 104500 L 4633
OU-07 MEG Ship loading pump discharge piping flange
gasket leak 4.25 48 546500 L 115831
OU-08 MEG Truck loading arm rupture 2.5 48 60150 L 28958
OU-09 MEG Tank on Fire Atm 48 - L 8047759
DEG Storage
DEG Storage Tanks (207-TK-004 A/B), DEG Product
Transfer Pump (207-P-004A/B), Loading Arm for DEG
Tanker Loading (207-Z-004A/B)
OU-10 DEG Product Transfer pump seal leak Atm 48 60500 L 2072
OU-11 DEG Truck loading arm rupture 2.5 48 60500 L 14572
OU-12 DEG Tank on Fire Atm 48 - L 2490400
TEG Storage
TEG Storage Tanks (207-TK-005 A/B), TEG Product
Transfer Pump (207-P-005A/B), Loading Arm for TEG
Tanker Loading (207-Z-005)
OU-13 TEG Product Transfer pump seal leak Atm 48 60500 L 2072
OU-14 TEG Truck loading arm rupture 2.5 48 60500 L 14572
OU-15 TEG Tank on Fire Atm 48 - L 349800
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 44 OF 106
Table 7.12 Client Cases
Section Description Case
ID Selected Failure Cases
Process Conditions
Static Inventory (kg) Pressure
(kg/cm2a)
Temperature
(°C) Mass Flowrate (kg/h)
Phase
[Note 1]
Pipe Rack over Creek
CC-01 C3+ Product header from ERU to PRU rupture 17.5 40 4866.2 L 3309
CC-02 50 mm hole on Refinery Off gas header from FCC to ERU 13.1 40 56788.0 V 6557
CC-03 50 mm hole on Fuel Gas header from ERU to Refinery
fuel gas system 5 40 26456.6 V 1605
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 45 OF 106
8. CONSEQUENCE ANALYSIS
Consequence analysis involves the application of the mathematical, analytical and computer
models for calculation of the effects and damages subsequent to a hydrocarbon / toxic
release accident.
Computer models are used to predict the physical behaviour of hazardous incidents (size,
shape and orientation of hazard zones). The model uses below mentioned techniques to
assess the consequences of identified scenarios:
Source Term/ Discharge Modelling
Dispersion Modelling
Physical Effects Modelling
Impact Assessment
The different consequences (Flash fire, pool fire, jet fire and Explosion effects) of loss of
containment incidents depend on the sequence of events & properties of material released
leading to the either toxic vapour dispersion, fire or explosion or both.
8.1. Source Term Modelling
Source term or discharge modelling involves determination of the discharge rate, release
duration and other physical properties of the released material, such as temperature and
pressure. These estimated parameters are then set as the initial conditions for the
subsequent dispersion or fire / explosion effects modelling.
8.1.1. Hole Size
Following hole sizes were considered in this RA study for selected failure cases:
Flammable gas release:
Flange Gasket leak: 50 mm
Instrument Tapping Failure: 50 mm
Pump Seal Failure: 10 mm
Toxic material release:
For pin hole leak: 5 mm
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 46 OF 106
8.1.2. Release Rate Calculation
In the event of a catastrophic rupture of a vessel, the Instantaneous Model was used to
model the rapid release of the entire inventory, where the material in the vessel is expanded
from initial conditions to atmospheric pressure. For releases from holes in pipes/ vessels,
release rate was calculated using standard orifice type calculations based on process
conditions and leak size.
For gas releases, the pressure in the system, and hence the release rate, slowly decrease
following isolation, resulting in a time dependent release. As a conservative approach, the
calculated initial release rate was assumed constant over the release duration for such
scenarios.
For large leaks from streams (e.g. guillotine failure of pipes) downstream of pumps/
compressors, the discharge rate will be limited by the maximum allowable flow of the pumps
/ compressors, which is generally slightly higher than the nominal capacity of the equipment.
For all release scenarios downstream of pumps / compressors, the release rate calculated
from PHAST 6.7 was compared with the pumping rate. If the calculated release rate
exceeds the normal pumping rate, the discharge rate was capped at 30% above the
maximum capacity of the pump / compressor to reflect performance curve characteristics as
a general approach in this study.
8.1.3. Release Duration
Release duration is another important output from the discharge modelling which is
determined by the upstream inventory and means of leak detection and isolation. The total
inventory available for release was calculated as the sum of equipment/ piping inventory and
the throughput before isolation is achieved.
It was assumed that isolation can be achieved within 10 minutes under normal conditions.
This value corresponds to typical time for human intervention for shutdown and isolation.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 47 OF 106
Table 8.1 Summary of Source Term Modelling for Ethylene Recovery Unit
Case ID Hole Size (mm) Release Rate (kg/s) Release Duration (min)
ER-01 50 4.7 40
ER-02 5 0.83 46
ER-03 50 3.99 54
ER-04 50 2.79 60
ER-05 50 3.54 58
ER-06 50 3.48 57
ER-07 50 1.6 23
ER-08 10 0.15 60
ER-09 10 0.23 60
ER-10 50 7..67 60
ER-11 10 1.12 60
ER-12 50 9.11 14
ER-13 - - -
ER-14 - - -
ER-15 50 11.8 60
Table 8.2 Summary of Source Term Modelling for Ethylene Glycol Unit Case ID Hole Size (mm) Release Rate (kg/s) Release Duration (min)
EG-01 50 10.67 10
EG-02 50 8.3 30
EG-03 50 7.16 30
EG-04 50 8.3 44
EG-05 50 7.46 1
EG-06 50 0.363 25
EG-07 50 0.38 29
EG-08 50 8.3 2
EG-09 50 0.37 14
EG-10 10 0.87 60
EG-11 10 0.35 60
EG-12 50 0.316 2
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 48 OF 106
Case ID Hole Size (mm) Release Rate (kg/s) Release Duration (min)
EG-13 10 0.53 60
EG-14 10 1.8 50
EG-15 50 51.1 6
EG-16 10 1.92 60
EG-17 50 44.17 1
EG-18 50 42.28 1
EG-19 50 64.7 <1
Table 8.3 Summary of Source Term Modelling for Offsite & Utilities Facility Case ID Hole Size (mm) Release Rate (kg/s) Release Duration (min)
OU-01 50 8.9 60
OU-02 50 8.89 21
OU-03 50 2.55 60
OU-04 50 11.38 6
OU-05 - - -
OU-06 50 0.2 60
OU-07 50 34.5 60
OU-08 50 23.4 28
OU-09 - - -
OU-10 50 0.1 60
OU-11 50 28.3 15
OU-12 - - -
OU-13 50 0.1 60
OU-14 50 28.4 15
OU-15 - - -
Table 8.4 Summary of Source Term Modelling for Client Cases
Case ID Hole Size (mm) Release Rate (kg/s) Release Duration (min)
CC-01 50 49.1 <2
CC-02 50 4.38 60
CC-03 50 1.46 60
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 49 OF 106
8.2. Dispersion Modelling
Dispersion modelling involves mathematical simulation of how the released materials
disperse in the ambient atmosphere. Downwind and crosswind concentrations are
determined to find the gas cloud hazard footprint. Vapour dispersion modelling was
conducted using PHAST’s Unified Dispersion Model (UDM). The model considers the
following aspects of vapour cloud behaviour in dispersion modelling:
Continuous, instantaneous or time-varying releases
Jet, heavy-gas and passive dispersion
Elevated, touchdown and ground level dispersion
Droplet dispersion, rainout and droplet vaporization
Dispersion over land or water surfaces
8.3. Physical Effects Modelling
Physical effects modelling determine the magnitude of damage caused by exposure to fire,
heat radiation, overpressure or toxics. The possible hazardous outcomes are described as
below.
8.3.1. Flash Fire
A flash fire results from delayed ignition of a flammable vapour cloud, generated either
through vaporization directly from the release, or from vaporizing pools. The main hazards
of a flash fire being direct contact with the flame.
The area of possible direct flame contact is determined through the distance which the
Lower Flammability Limit (LFL) of the vapour cloud has travelled. All persons within the flash
fire envelop were assumed to be fatally injured. Due to the extreme short duration of a flash
fire, radiation effects are negligible.
Figure 8.1 presents the flammable gas dispersion results for selected worst cases in
Ethylene Recovery Unit, Ethylene Glycol Unit and O&U facility.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 50 OF 106
Figure 8.1 Consequence Contours for Flammable Gas Dispersion
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 51 OF 106
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 52 OF 106
8.3.2. Jet Fire
A jet fire results from immediate ignition of the flammable material from a pressurized
release. The working level heat radiation impact will vary widely depending on the angle of the flame
to the horizontal plane, which in turn mainly depends on the location of the leak. In this study, jet
fires were modelled for all pressurized releases of hydrocarbons.
Upon accidental leakage, the pressurized fluid will disperse as a jet, initially moving forward in the
spatial direction of the leak until the kinetic energy is lost and gravity slumping or lifting of the cloud
occurs, dependent upon whether the fluid is heavier or lighter than air.
The primary hazard associated with jet fires is direct flame contact and thermal radiation,
both of which were modelled using default parameters in PHAST 6.7, with release
orientation set at horizontal non-impinging.
Jet Fire results for selected worst case in Ethylene Recovery Unit, Ethylene Glycol Unit and
O&U facility are presented in Figure 8.2
Figure 8.2 Jet Fire Consequence Contours
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 53 OF 106
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 54 OF 106
8.3.3. Pool Fire A liquid pool is formed during a prolonged leakage if the rate of leakage exceeds the rate of
vaporization. A pool fire results upon ignition of flammable liquid pool due to failure of
process vessel/ piping. Pool extension was modelled in PHAST as an ‘early pool fire’ which
takes into account the release rate, rainout, pool spreading and burning rates. The release
orientation was set at downward impinging for modelling of pool fires. The pool fire
dimensions were limited to the bund area or trench / ditch around each process zone if
provided.
Pool fire results for selected worst cases in Ethylene Glycol Unit and O&U facility are
presented in Figure 8.3. In Ethylene recovery unit there is no pool fire case.
Figure 8.3 Pool Fire Consequence Contours
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 55 OF 106
8.3.4. Vapor Cloud Explosion (VCE)
When a large amount of flammable vaporizing liquid or gas is rapidly released, a vapor
cloud forms and disperses in the surrounding air. If this cloud is ignited before the cloud is
diluted below its Lower Flammability Limit (LFL), a VCE or flash fire occurs. Explosion may
only occur in areas of high congestion, or confinement. Ignition in the open area may only
result in a flash fire or unconfined Vapor Cloud Explosion yielding relatively lower damaging
overpressure.
The Baker-Strehlow-Tang (BST) model in PHAST V6.7 was used in modelling the
overpressure generated from a VCE. The mass of hydrocarbon vapor within its lower and
upper flammable limits is considered to be available for explosion.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 56 OF 106
Figure 8.5 Overpressure Contour (Total Flammable Mass)
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 57 OF 106
8.3.5. Fireball
A fireball can result from an immediate ignition of sudden release of pressurized liquid / gas
due to catastrophic rupture of pressure vessels. Ignition of the rapidly released materials will
form a ball of flame rising rapidly into the air and burning out in a short time. Fireballs may
also be caused by escalation from direct flame impingement on the vessel. Flashed vapor
from the vessel inventory was considered in modelling of fireball scenarios. For this study,
fireball scenario was modelled only for equipment where significant concentrations of
hydrogen or natural gas are present.
The thermal radiation level over distance from the fireball for catastrophic rupture of Light
binary refrigerant accumulator of Ethylene recovery unit is presented in Figure 8.6.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 58 OF 106
Figure 8.6 Thermal Radiation Level Vs Distances from Fireball for Light binary
refrigerant accumulator Rupture
8.3.6. Toxic Gas Dispersion
Following a loss of containment scenario involving toxic substances such as H2S, Ethylene
Oxide (EO) the resulting toxic gas cloud may disperse long distances from the source and
cause fatalities. It may also pose significant hazard of toxic / asphyxiation to any personnel
present in close proximity to the release source. Figure 8.7 present the selected worst case
for toxic gas dispersion modelling in EG Unit
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 59 OF 106
Figure 8.7 Toxic Gas Dispersion Distance
EG-6 Acid scrubber outlet flange gasket leakage
8.3.7. Summary of Hazardous Outcomes
The hazardous outcomes considered for each scenario is presented in Table 8.5, Table 8.6,
Table 8.7 and Table 8.8 for the Ethylene Recovery Unit, Ethylene Glycol Unit, O&U facility
and Client Cases respectively. The following abbreviations are used in the tables:
JF: Jet Fire
PF: Pool Fire
FB: Fireball
FF: Flash Fire
VCE: Vapour Cloud Explosion
TX: Toxic Gas Dispersion
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 60 OF 106
Table 8.5 Physical Effects Modelling Summary for Ethylene Recovery Unit
Case ID Failure Case Description Leak Size (mm)
FF JF FB TX VCE PF
ER-01 DGA/Water wash tower overhead line instrument
tapping failure 50 Y Y - - Y -
ER-02 DGA Reflux drum overhead line pin hole leak 50 - - - Y - -
ER-03 FCC Off gas Chloride treater outlet flange gasket
failure 50 Y Y - - Y -
ER-04 FCC Off gas Oxygen Converter outlet line flange
gasket leak 50 Y Y - - Y -
ER-05 Process off gas line from C-101 to Dryer feed
KOD flange leakage 50 Y Y - - Y -
ER-06 Mercury Absorber Effluent filter flange gasket
leak 50 Y Y - - Y -
ER-07 Regeneration gas line instrument tapping failure 50 Y Y - - - -
ER-08 Demethanizer Bottoms Pumps seal failure 50 Y Y - - - -
ER-09 Demethanizer Intercooler Circulation pump seal
failure 50 Y Y - - - -
ER-10 Deethylenizer overhead line instrument tapping
failure 50 Y Y - - Y -
ER-11 Ethylene Product pump seal failure 50 Y Y - - Y -
ER-12 Deethylenizer bottom line flange gasket leak 50 Y Y - - Y -
ER-13 Catastrophic rupture of Deethylenizer Reflux
Drum 50 Y - Y - Y -
ER-14 Catastrophic Rupture of Light Binary Refrigerant
Accumulator 50 Y - Y - Y -
ER-15 Binary Refrigerant Compressor discharge
instrument tapping failure 50 Y Y - - Y -
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 61 OF 106
Table 8.6 Physical Effects Modelling Summary for Ethylene Glycol Unit
Case ID Failure Case Description Leak Size (mm)
FF JF FB TX VCE PF
EG-01 Ethylene Filters flange gasket leak 50 Y Y - - Y -
EG-02 Reactor Feed line instrument tapping failure 50 Y Y - - - -
EG-03 Reactor Outlet line flange gasket leak 50 Y Y - - - -
EG-04 Recycle Compressor Instrument tapping failure 50 Y Y - - - -
EG-05 Ballast line flange gasket leak 50 Y Y Y - Y -
EG-06 Acid Scrubber outlet flange gasket leakage 50 Y Y - Y - -
EG-07 Pin hole leak at inlet of Stripping Column
Condenser (Toxic Release) 50 Y Y - Y - -
EG-08 Flange gasket leak in Reclaim Compressor
discharge 50 Y Y - - Y -
EG-09 Glycol Feed Stripper overhead line instrument
tapping failure 50 Y Y - Y - -
EG-10 Concentrated Glycol Pump seal failure 50 Y Y - - Y Y
EG-11 Drying Column Bottoms pumps seal failure 50 Y Y - - - Y
EG-12 50 mm hole on MEG Column overhead line 50 Y Y - - - Y
EG-13 MEG Column Bottoms pumps seal failure 50 Y Y - - - Y
EG-14 MEG Procut Transfer Pump seal failure 50 Y Y - - - Y
EG-15 MEG Splitter Bottoms Pump discharge instrument
tapping failure 50 Y Y - - Y Y
EG-16 DEG Column Bottoms Pumps seal failure 50 Y Y - - Y Y
EG-17 DEG Product Transfer Pump discharge
instrument tapping failure 50 Y Y - - - Y
EG-18 TEG Product Transfer Pump discharge
instrument tapping failure 50 Y Y - - Y Y
EG-19 Moderator Feed Drum flange line rupture 50 Y Y - - Y Y
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 62 OF 106
Table 8.7 Physical Effects Modelling Summary for Offsite & Utilities Facility
Case ID Failure Case Description Leak Size (mm)
FF JF FB TX VCE PF
OU-01 Flange gasket failure at the outlet of ethylene
sphere 50 Y Y - - Y -
OU-02 Flange gasket leak at BOG Package 50 Y Y - - Y -
OU-03 Ethylene Product Transfer pump seal failure 50 Y Y - - Y -
OU-04 Ethylene vaporizer outlet line instrument tapping
failure 50 Y Y - - Y -
OU-05 Catastrophic rupture of Ethylene sphere 50 Y - Y - Y -
OU-06 MEG Product Transfer pump seal leak 50 Y - - - - Y
OU-07 MEG Ship loading pump discharge piping flange
gasket leak 50 Y - - Y Y
OU-08 MEG Truck loading arm rupture 50 Y - - - Y
OU-09 MEG Tank on Fire 50 Y - - - Y Y
OU-10 DEG Product Transfer pump seal leak 50 Y - - - - Y
OU-11 DEG Truck loading arm rupture 50 Y - - - - Y
OU-12 DEG Tank on Fire 50 Y - - - Y Y
OU-13 TEG Product Transfer pump seal leak 50 Y - - - - Y
OU-14 TEG Truck loading arm rupture 50 Y - - - - Y
OU-15 TEG Tank on Fire 50 Y - - - Y Y
Table 8.8 Physical Effects Modelling Summary for Client Cases
Case ID Failure Case Description Leak Size (mm)
FF JF FB TX VCE PF
CC-01 C3+ Product header from ERU to PRU rupture 50 Y Y - - Y -
CC-02 50 mm hole on Refinery Off gas header from
FCC to ERU 50 Y Y - - Y -
CC-03 50 mm hole on Fuel Gas header from ERU to
Refinery fuel gas system 50 Y Y - - - -
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 63 OF 106
9. RISK ANALYSIS DISCUSSION
This section discusses the consequences of selected failure scenarios / cases as listed in
Section 7.4, Table 7.9, and Table 7.10 & Table 7.11 for ER, EG and O&U facilities
respectively. The hazard distances due to the scenarios are reported for 3D and 5D
weather conditions. The consequence analysis results are reported in tabular form for all
weather conditions, the same is attached as Annexure-B. Hazard distance contour for the
worst case of the selected scenario is attached as Annexure-C.
9.1. Ethylene Recovery Unit (ERU)
Fifteen (15) cases have been identified for modelling to assess the hazards in Ethylene
Recovery Unit. The details of these cases and the hazards are discussed in this section.
ER-1 (DGA/Water wash tower overhead line instrument tapping failure)
DGA / Water wash tower overhead contains 40.1 wt% of ethylene vapor and other
hydrocarbons. The pressure and temperature of the vapor is 13.1 kg/cm2g and 40°C
respectively. Failure of instrument tapping (hole dia.: 50 mm) is considered for the
modelling. From the outcome of the modelling, it is observed that flash fire, jet fire and VCE
will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 18 36 29 24 30 19 14
5D 17 36 30 25 30 19 14
From the above table and hazard contour Annexure-C Figure C1.1 & Figure C1.2, the flash
fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene recovery unit.
Overpressure effect zones are contained within the ethylene recovery unit and do not impact
any buildings and therefore no specific recommendations are made.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 64 OF 106
ER-2 (DGA Reflux drum overhead line pin hole leak)
DGA Reflux Drum is operating at 1.5 kg/cm2g and 98°C respectively. The vapor mostly
contains CO2 (96.44 wt%), some amount of H2S (0.5 wt%) gas is also present. A pin hole
leak due to corrosion is considered having equivalent hole size of 5mm to toxic gas release
is considered for the modelling. From the outcome of the modelling, it is observed that toxic
release will be realized. The hazard distance are summarized in below table
Weather Condition Toxic Distance (m) 3D 16
5D 10
From the above table and hazard contour Annexure-C Figure C1.4, the IDLH distance would
be less and gas containing H2S would be safely dispersed within the battery limit of ethylene
recovery unit. H2S gas being heavier than air it try to settle out at ground level.
From the above observation following is recommended
Provide H2S Gas Detector with audio-visual alarms (beacons) for early detection of any
leakage so as to take necessary mitigation measures.
Ensure escape sets along the escape route are available to escape from the leak
source to a safe location.
Routine inspection and preventive maintenance of equipment (DGA Regenerator
overhead, Reflux drum) and associated piping is advised so as to avoid any untoward
occurrence.
Overpressure effect zones are contained within the ethylene recovery unit and do not impact
any buildings and therefore no specific recommendations are made.
ER-3 (Caustic/Water wash tower overhead line instrument tapping failure)
Caustic/Water wash tower overhead contains hydrocarbon ethylene vapor. The pressure
and temperature of the vapor is 11.3 kg/cm2g and 54.8°C respectively. Failure of instrument
tapping (hole dia.: 50 mm) is considered for the modelling. From the outcome of the
modelling, it is observed that flash fire, jet fire and VCE will be realized. The hazard
distance are summarized in below table
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 65 OF 106
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 16 33 27 22 29 18 14
5D 15 33 28 23 29 18 14
From the above table and hazard contour Annexure-C Figure C1.5 & Figure C1.6, the flash
fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene recovery unit.
Overpressure effect zones are contained within the ethylene recovery unit and do not impact
any buildings and therefore no specific recommendations are made.
ER-4 (FCC Off gas Oxygen Converter outlet line flange gasket failure)
FCC Off gas Oxygen Converter is normally operated at 11.3 kg/cm2g pressure and 266°C
temperature. This contains ethylene and other light hydrocarbons. Failure of its outlet
flange gasket (equivalent hole dia.: 50 mm) is considered for the modelling purpose. From
the outcome of the modelling, it is observed that flash fire, jet fire and VCE will be realized.
The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 12 28 22 18 27 17 13
5D 11 28 23 19 26 17 13
From the above table and hazard contour Annexure-C Figure C1.8 & Figure C1.9, the flash
fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene recovery unit.
Overpressure effect zones (Annexure-C Figure 1.10) are contained within the ethylene
recovery unit and do not impact any buildings and therefore no specific recommendations
are made.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 66 OF 106
ER-5 (Process Off gas line from C-101 to Dryer feed KOD flange leakage)
C-101 off gas normal operating pressure and temperature is 9.9kg/cm2g and 55°C
respectively. This stream mainly contains ethylene vapor and other light hydrocarbons.
Failure of its outlet flange gasket (equivalent hole dia.: 50 mm) is considered for the
modelling purpose. From the outcome of the modelling, it is observed that flash fire, jet fire
and VCE will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 15 31 25 20 29 18 14
5D 14 31 26 21 28 18 14
From the above table and hazard contour Annexure-C Figure C1.11 & Figure C1.12, the
flash fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene recovery unit.
Overpressure effect zones (Annexure-C Figure 1.13) are contained within the ethylene
recovery unit and do not impact any buildings and therefore no specific recommendations
are made.
ER-6 (Mercury Adsorber Effluent Filter flange gasket leak)
060-R-104 effluent gas normal operating pressure and temperature is 9kg/cm2g and 16°C
respectively. This stream mainly contains ethylene vapor and other light hydrocarbons
(methane, ethane, propylene). Failure of inlet flange of filter GN-201A (equivalent hole dia.:
50 mm) is considered for the modelling purpose. From the outcome of the modelling, it is
observed that flash fire, jet fire and VCE will be realized. The hazard distance are
summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 15 31 25 20 29 18 14
5D 14 31 26 21 28 18 14
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 67 OF 106
From the above table and hazard contour Annexure-C Figure C1.14 & Figure C1.15, the
flash fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene recovery unit.
Overpressure effect zones (Annexure-C Figure 1.16) are contained within the ethylene
recovery unit and do not impact any buildings and therefore no specific recommendations
are made.
ER-7 (Regeneration gas line instrument tapping failure)
FCC Off gas Dryer / Treater (060-R-103A/B) regeneration gas mainly contains methane &
ethane (44.84wt% & 27.34 wt% resp.). The normal pressure and temperature of
regeneration gas is 6kg/cm2g and 300°C (temperature during hot swiping is considered as a
conservative approach) respectively. Failure of instrument on regeneration line (equivalent
hole dia.: 50 mm) is considered for the modelling purpose. From the outcome of the
modelling, it is observed that flash fire and jet fire will be realized. The hazard distance are
summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2)
4 12.5 37.5 3D 7 21 17 8
5D 7 21 17 NR
From the above table and hazard contour Annexure-C Figure C1.17 & Figure C1.18, the
flash fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene recovery unit.
ER-8 (Demethanizer Bottoms pump seal failure)
Fluid from Demethanizer (060-C-201) bottom at temperature -43°C and pressure
8.2kg/cm2g is pumped by means of Demethanizer bottoms pump (060-P-201A/B) at 17.5
kg/cm2g as feed to Deethylanizer (060-C-301). Failure of demethanizer bottoms pump seal
(equivalent hole dia.: 10 mm) with an average frequency of occurrence 3.75 x 10-4 per year
is considered for the modelling purpose. From the outcome of the modelling, it is observed
that flash fire and jet fire will be realized. The hazard distance are summarized in below
table
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 68 OF 106
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2)
4 12.5 37.5 3D 3 8 7 5
5D 3 8 6 5
From the above table and hazard contour Annexure-C Figure C1.19 & Figure C1.20, the
flash fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene recovery unit. However considering the failure frequency of the pump seal,
following is recommended
Provide HC gas detectors near to Demethanizer bottoms pump (060-P-201A/B) seal.
Considering liquid hydrocarbon inventory in Demethanizer bottom, requirement of
suitable means of inventory isolation shall be reviewed during detail engineering.
ER-9 (Demethanizer Intercooler Circulation pump seal failure)
Fluid from Demethanizer (060-C-201) top section at temperature -84.8°C and pressure
8kg/cm2g is pumped by means of Demethanizer Intercooler Circulation pump (060-P-
202A/B) at 9.5 kg/cm2g and back to Demethanizer. Failure of demethanizer intercooler
circulation pump seal (equivalent hole dia.: 10 mm) with an average frequency of
occurrence 3.75 x 10-4 per year is considered for the modelling purpose. From the outcome
of the modelling, it is observed that flash fire and jet fire will be realized. The hazard
distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2)
4 12.5 37.5 3D 3 8 7 5
5D 3 8 6 5
From the above table and hazard contour Annexure-C Figure C1.21 & Figure C1.22 (only jet
fire of radiation intensity 4 kW/m2 is realized), the flash fire distance (LFL distance) and jet
fire distance would be less and restricted within the ethylene recovery unit. However
considering the failure frequency of pump seal, it is recommended to provide HC gas
detector near to Demethanizer Intercooler Circulation pump (060-P-202A/B) seal.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 69 OF 106
ER-10 (Deethylenizer overhead line instrument tapping failure)
Deethylenizer in ERU operates at a pressure of 16.9 kg/cm2g and at a temperature of -
33°C. Deethylenizer overhead stream contains ethylene as a major component. Failure of
overhead line instrument tapping (equivalent hole dia.: 50 mm) is considered for the
modelling purpose. From the outcome of the modelling, it is observed that flash fire, jet fire
and VCE will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 52 57 46 39 107 75 62
5D 52 54 42 35 105 74 62
From the above table and hazard contour Annexure-C Figure C1.23, Figure C1.24 and
Figure C1.25, the flash fire contour (LFL distance), jet fire contours (4/12.5/37.5 kW/m2) and
similarly overpressure contour of 0.1 & 0.3 bar covers the N-E side road. Overpressure
contour of 0.03 bar, engulf BOG compressor shed of Ethylene storage sphere. However
considering that the area between ERU and Ethylene storage sphere is open and there is
no congestion or confined space, there will not be sufficient mass to cause explosion.
From the above observation following is recommended
Provide Hydrocarbon Gas Detector in vicinity of Deethylenizer (060-C-301) for early
detection of any leakage so as to take necessary mitigation measures.
Vehicular movement on ERU N-E side road to be minimized to avoid any source of
ignition.
ER-11 (Ethylene Product Pump seal failure)
Fluid from Deethyleniizer Reflux Drum (060-V-301) at temperature -35°C and pressure 16.2
kg/cm2g is pumped by means of Ethylene Product pump (060-P-302A/B) at 45.5 kg/cm2g to
cold box and further to Ethylene Storage Spheres. Failure of Ethylene Product pump seal
(equivalent hole dia.: 10 mm) with an average frequency of occurrence 3.75 x 10-4 per year
is considered for the modelling purpose. From the outcome of the modelling, it is observed
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 70 OF 106
that flash fire, jet fire and VCE will be realized. The hazard distance are summarized in
below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 26 37 30 25 51 33 26
5D 24 35 28 23 49 32 26
From the above table and hazard contour Annexure-C Figure C1.26 & Figure C1.27, the
flash fire distance (LFL distance) and jet fire distance would be restricted within the ethylene
recovery unit.
Overpressure effect zones (Annexure-C Figure 1.28) 0.1 and 0.3 bar is restricted within the
ethylene recovery unit. 0.03 bar overpressure contour covers some part of ER plant road
along N and E side.
From the above observation following is recommended
Provide Hydrocarbon Gas Detectors in vicinity of Ethylene Product Transfer pump (060-
P-302A/B) for early detection of any leakage so as to take necessary mitigation
measures.
Considering liquid hydrocarbon inventory in Deethylenizer Reflux drum, requirement of
suitable means of inventory isolation shall be reviewed during detail engineering.
ER-12 (Deethylenizer bottom line flange gasket leak)
Fluid from Deethyleniizer Reflux Drum (060-V-301) at temperature -35°C and pressure 16.2
kg/cm2g is pumped by means of Ethylene Product pump (060-P-302A/B) at 45.5 kg/cm2g to
cold box and further to Ethylene Storage Spheres. Failure of Ethylene Product pump seal
(equivalent hole dia.: 10 mm) with an average frequency of occurrence 3.75 x 10-4 per year
is considered for the modelling purpose. From the outcome of the modelling, it is observed
that flash fire, jet fire and VCE will be realized. The hazard distance are summarized in
below table
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 71 OF 106
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 30 53 42 33 70 47 38
5D 29 29 14 12 55 35 27
From the above table and hazard contour Annexure-C Figure C1.29, flash fire contour (LFL
distance) would be restricted within the ethylene recovery unit. Figure C1.30, the jet fire
contours of intensity 4 & 12.5 kW/m2 would be restricted within the ERU battery limit,
however jet fire contour of 4 kW/m2 covers N-E side road of ER unit, this may cause injury
to person if they are not able to reach to safe location within 20 sec.
Overpressure effect zones (Annexure-C Figure 1.31) 0.1 and 0.3 bar is restricted within the
ethylene recovery unit. 0.03 bar overpressure contour covers some part of ER plant road
along N and E side.
From the above observation following is recommended
Considering liquid hydrocarbon inventory in Deethylenizer bottom, requirement of
suitable means of inventory isolation shall be reviewed during detail engineering.
ER-13 (Catastrophic rupture of Deethylenizer Reflux Drum)
Deethyleniizer Reflux Drum (060-V-301) operates at temperature -35°C and pressure 16.2
kg/cm2g. The case considered for modelling is catastrophic rupture of the vessel with an
average frequency of occurrence 5X10-7 per year. Although the occurrence frequency is
remote, to assess the worst possible consequence, this unlikely failure case is considered.
In the Catastrophic rupture scenario, vessel is destroyed by an impact, a crack, or some
other failure which propagates very quickly. The release is assumed to form a
homogeneous mass, expanding rapidly with no restrictions from the shattered vessel.
The instantaneous release of hydrocarbon may lead to fire ball explosion on immediate
ignition. Else the dispersing hydrocarbon vapor-air cloud may reach an ignition source and
a flash fire would occur. The hazard distance are summarized in below table
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 72 OF 106
Weather Condition
Hazard Distances (m) Flash Fire
Fire Ball (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 64 350 186 67 493 227 131
5D 100 350 186 67 497 230 142
From the above table and hazard contour Annexure-C Figure C1.32, flash fire contour (LFL
distance) would be within the property line. However it covers N & E side road of Ethylene
recovery unit. Figure C1.33, the radiation contours of intensity 12.5 & 37.5 kW/m2 remains
within the property line. However may hinder fire-fighting efforts. Radiation contour of 4
kW/m2 covers entire ER unit, major portion of EG unit, ethylene storage spheres & its
associated equipment, SRR, future sub-station, Fire water booster pump and would be
going outside the E side property line by 89-176 meters depending upon the wind direction.
Radiation intensity contour of 12.5 kW/m2 covers the entire ERU, some portion of EG unit,
ethylene storage sphere & its associated equipment, existing pump shed & scrap yard on E-
side of EG unit. Overpressure effect zones (Annexure-C Figure 1.34) 0.3 bar contour
would cover entire ER unit, however no occupied building would be coming in this contour.
0.1 bar contour would cover entire ER unit, some portion of EG unit, entire ethylene storage
sphere facility, existing petcoke rapid rail loading station, existing pump shed and also going
outside of property line on E-side of new facility by 17-51 meters. 0.03 bar contour would
cover entire ER unit, EG unit, ethylene storage sphere facility, existing petcoke rapid rail
loading station, existing pump shed, fire water booster pump shed, SRR, SS-1, part of Air
Separation unit and also going outside of property line on E-side of new facility by 242-321
meters.
From the above observations following is recommended
Efficiently monitor health of the vessel by
inspection of vessel internals, thickness measurement (involving techniques like
ultrasonic thickness measurement) & administering other techniques during shut-
down period.
This event shall be included in emergency response plan.
Ensure adequate numbers of Hydrocarbon Gas Detectors are provided in accordance
with OISD-116.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 73 OF 106
Ensure availability of water spray system for equipment handling significant amount
of hydrocarbon to protect against thermal heat radiation are provided in accordance
with OISD-116.
ER-14 (Catastrophic rupture of Light Binary Refrigerant Accumulator)
Light Binary Refrigerant Accumulator (060-V-406) operates at temperature -1°C and
pressure 25.1 kg/cm2g. The case considered for modelling is catastrophic rupture of the
vessel with an average frequency of occurrence 5X10-7 per year. Although the occurrence
frequency is remote, to assess the worst possible consequence, this unlikely failure case is
considered. In the Catastrophic rupture scenario, vessel is destroyed by an impact, a crack,
or some other failure which propagates very quickly. The release is assumed to form a
homogeneous mass, expanding rapidly with no restrictions from the shattered vessel.
The instantaneous release of hydrocarbon may lead to fire ball explosion on immediate
ignition. Else the dispersing hydrocarbon vapor-air cloud may reach an ignition source and
a flash fire would occur. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Fire Ball (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 19 178 94 34 182 83 47
5D 24 178 94 34 207 100 60 From the above table and hazard contour Annexure-C Figure C1.35, flash fire contour (LFL
distance) would be limited within the battery limit of ethylene recovery unit.
Figure C1.36, the radiation contours of intensity 37.5 kW/m2 remains within the ethylene
recovery unit. Radiation contour of intensity 12.5 kW/m2 would cover N-E side road of ER
unit which may finder the fire-fighting efforts. Radiation contour of 4 kW/m2 would cover
entire ER unit, some portion of EG unit, entire ethylene storage spheres & its associated
equipment,
Overpressure effect zones (Annexure-C Figure 1.37) 0.3 & 0.1 bar contour would remain
within the property line. 0.03 bar contour would cover entire ER unit and may slightly go
outside the property line (1~17 meters) at E-side of ER unit. However no occupied building
would be coming within these contours.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 74 OF 106
From the above observations following is recommended
Efficiently monitor health of the vessel by inspection of vessel internals, thickness
measurement (involving techniques like ultrasonic thickness measurement) &
administering other techniques during shut-down period.
Ensure availability of water spray system for equipment handling significant amount
of hydrocarbon to protect against thermal heat radiation are provided in accordance
with OISD-116.
ER-15 (Binary Refrigerant Compressor discharge instrument tapping failure)
Binary Refrigerant compressor discharges refrigerant at a pressure of 27.4 kg/cm2g and at a
temperature of 84°C. Failure of discharge line instrument tapping (equivalent hole dia.: 50
mm) is considered for the modelling purpose. From the outcome of the modelling, it is
observed that flash fire, jet fire and VCE will be realized. The hazard distance are
summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 36 58 46 36 74 49 39
5D 35 59 47 38 73 49 39
From the above table and hazard contour Annexure-C Figure C1.38, Figure C1.39 and
Figure C1.25, the flash fire contour (LFL distance), jet fire contours (4/12.5/37.5 kW/m2) and
overpressure contour (0.03/0.1/0.3 bar) would remain within the ethylene recovery unit.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 75 OF 106
9.2. Ethylene Glycol Unit (EG)
EG-1(Ethylene Filter flange gasket leak)
Ethylene from Sulfur Guard Bed (061-R-150) goes through Ethylene filter (061-GN-150A/B)
with pressure and temperature is 25 kg/cm2g and 35°C respectively. This stream mainly
contains ethylene vapor coming for Ethylene recovery unit. Failure of inlet flange of filter
GN-150A (equivalent hole dia.: 50 mm) is considered for the modelling purpose. From the
outcome of the modelling, it is observed that flash fire, jet fire and VCE will be realized. The
hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 41 55 44 35 88 61 50
5D 40 55 45 36 87 60 50
From the above table and hazard contour Annexure-C Figure C2.1, Figure C2.2, flash fire
contour (LFL distance) and jet fire contours would be limited within the battery limit of
ethylene glycol unit.
Overpressure effect zones (Annexure-C Figure C2.3) 0.3 & 0.1 bar contour would remain
within the limits of EG unit. 0.03 bar contour would cover south & east side road of EG unit.
However no occupied building would be coming within these contours.
From the above observation following is recommended:
Provide HC gas detector in vicinity of sulfur guard bed and ethylene filters.
EG-2 (Reactor Feed line instrument tapping failure)
Reactor feed line operating pressure and temperature is 21.37 kg/cm2g and 57°C
respectively. This stream contains ethylene vapor. Failure of inlet line instrument tapping
(equivalent hole dia.: 50 mm) is considered for the modelling purpose. From the outcome of
the modelling, it is observed that flash fire and jet fire will be realized. The hazard distance
are summarized in below table
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 76 OF 106
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2)
4 12.5 37.5 3D 7 38 30 NR
5D 7 39 32 NR
From the above table and hazard contour Annexure-C Figure C2.4, Figure C2.5, flash fire
contour (LFL distance) and jet fire contours (radiation intensity of 4 & 12.5 kW/m2 would be
limited within the battery limit of ethylene glycol unit.
EG-3 (Reactor outlet line flange gasket leak)
Reactor operates at 19.33 kg/cm2g pressure and 90°C temperature. Failure of outlet line
flange gasket (equivalent hole dia.: 50 mm) is considered for the modelling purpose. From
the outcome of the modelling, it is observed that flash fire and jet fire will be realized. As
The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2)
4 12.5 37.5 3D 7 38 30 NR
5D 7 39 32 NR
From the above table and hazard contour Annexure-C Figure C2.6, Figure C2.7, flash fire
contour (LFL distance) and jet fire contours (radiation intensity of 4 & 12.5 kW/m2) would be
limited within the battery limit of ethylene glycol unit.
EG-4 (Recycle Compressor instrument tapping failure)
Recycle compressor operates at 21.52 kg/cm2g pressure and 55°C temperature. Failure of
discharge line instrument tapping (equivalent hole dia.: 50 mm) is considered for the
modelling purpose. From the outcome of the modelling, it is observed that flash fire and jet
fire will be realized. As The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2)
4 12.5 37.5 3D 6.8 37.5 30 13
5D 6.5 38.5 31.5 14
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 77 OF 106
From the above table and hazard contour Annexure-C Figure C2.8, Figure C2.9, flash fire
contour (LFL distance) and jet fire contours (radiation intensity of 4/12.5/37.5 kW/m2) would
be limited within the battery limit of ethylene glycol unit.
From the above observation following is recommended:
Provide HC gas detector at suction and discharge of Recycle Gas compressor (061-K-
115).
EG-5 (Ballast line flange gasket leak)
Ballast gas (future – methane) operates at 25 kg/cm2g pressure and 45°C temperature.
Failure of flange gasket (equivalent hole dia.: 50 mm) is considered for the modelling
purpose. From the outcome of the modelling, it is observed that flash fire, jet fire and VCE
will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 27 49 39 31 54 34 27
5D 26 49 39 32 53 34 27
From the above table and hazard contour Annexure-C Figure C2.10, Figure C2.11 and
Figure C2.13 flash fire contour (LFL distance), jet fire contours (radiation intensity of 4
kW/m2) and overpressure contours (intensity 0.03/0.10/0.3 bar) would be limited within the
battery limit of ethylene glycol unit.
EG-6 (Acid Scrubber outlet flange gasket leak)
Acid Scrubber operates at 0.280 kg/cm2g pressure and 51°C temperature. Failure of outlet
line flange gasket (equivalent hole dia.: 50 mm) is considered for the modelling purpose.
From the outcome of the modelling, it is observed that flash fire and jet fire will be realized.
Also as the gas mainly contain ethylene oxide which is toxic in nature, IDLH contour is also
drawn for this scenario. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2) Toxic Dispersion
4 12.5 37.5 IDLH (EO-800 ppm) 3D 4 11 NR NR 96
5D 4 12 10 NR 67
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 78 OF 106
From the above table and hazard contour Annexure-C Figure C2.14 and Figure C2.15, flash
fire contour (LFL distance) and jet fire contours (radiation intensity of 4 kW/m2) is small and
would be limited within the battery limit of ethylene glycol unit. Figure C2.16 shows the
toxic gas dispersion contour, this covers sub-station and satellite rack room.
From the above observations following is recommended
Maintain positive pressure inside Sub-station and Satellite rack room. Flammable /
Toxic Gas (EO) detector shall be provided at the air suction duct of these building.
Ensure adequate number of HC gas detector / Toxic gas detector (EO) is provided
in vicinity of Ethylene oxide stripping Section.
Wind sock shall be installed at visible location.
Escape set to be provided along the escape route.
EG-7 (Pin-hole leak at inlet of Stripping Column condenser)
Stripping column overhead operates at 0.48 kg/cm2g pressure and 97°C temperature. Pin
hole leak (equivalent hole dia.: 5 mm) is considered for the modelling purpose. From the
outcome of the modelling, it is observed that flash fire and jet fire will be realized. Also as
the gas mainly contain ethylene oxide which is toxic in nature, IDLH contour is also drawn
for this scenario. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2) Toxic Dispersion
4 12.5 37.5 IDLH (EO-800 ppm) 3D 2 9 NR NR 71
5D 2 10 NR NR 59
From the above table and hazard contour Annexure-C Figure C2.17 and Figure C2.18, flash
fire contour (LFL distance) and jet fire contours (radiation intensity of 4 kW/m2) is small and
would be limited within the battery limit of ethylene glycol unit. Figure C2.19 shows the
toxic gas dispersion contour.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 79 OF 106
From the above observation following is recommended
Provide HC gas / Toxic gas (EO) detector in vicinity of Stripping column, Reflux
pump, Acid Scrubber. Also ensure that fire-fighting system such as water spray
system provided as per OISD-116.
Ensure escape set along the escape route is available.
EG-8 (Flange gasket leak of Reclaim Compressor discharge)
Reclaim Compressor operates at 23 kg/cm2g pressure and 127°C temperature. Failure of
discharge line flange gasket (equivalent hole dia.: 50 mm) is considered for the modelling
purpose. From the outcome of the modelling, it is observed that flash fire, jet fire and VCE
will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 12 41 33 24 26 17 13
5D 11 42 34 26 26 17 13
From the above table and hazard contour Annexure-C Figure C2.20, Figure C2.21 and
Figure C2.22 flash fire contour (LFL distance), jet fire contours (radiation intensity of
4/12.5/37.5 kW/m2) and overpressure contours (intensity 0.03/0.10/0.3 bar) would be
limited within the battery limit of ethylene glycol unit.
From the above observation following is recommended
Provide HC gas / Toxic gas (EO) detector in vicinity of Stripping column, Reflux
pump, Acid Scrubber. Also ensure that fire-fighting system such as water spray
system provided as per OISD-116.
EG-9 (Glycol Feed Stripper Overhead line instrument tapping failure)
Glycol Feed Stripper operates at 0.280 kg/cm2g pressure and 51°C temperature. Failure of
overhead line instrument tapping (equivalent hole dia.: 50 mm) is considered for the
modelling purpose. From the outcome of the modelling, it is observed that flash fire and jet
fire will be realized. Also as the gas mainly contain ethylene oxide which is toxic in nature,
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 80 OF 106
IDLH contour is also drawn for this scenario. The hazard distance are summarized in below
table
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2) Toxic Dispersion
4 12.5 37.5 IDLH (EO-800 ppm) 3D 4 11 NR NR 96
5D 3.5 12 10 NR 67
From the above table and hazard contour Annexure-C Figure C2.23 and Figure C2.24, flash
fire contour (LFL distance) and jet fire contours (radiation intensity of 4 kW/m2) is small and
would be limited within the battery limit of ethylene glycol unit. Figure C2.25 shows the
toxic gas dispersion contour, this covers sub-station and satellite rack room.
From the above observations following is recommended
Maintain positive pressure inside Sub-station and Satellite rack room. Flammable /
Toxic Gas (EO) detector shall be provided at the air suction duct of these building
and near as per OISD-116
Wind sock shall be installed at visible location.
Escape set to be provided along the escape route.
EG-10 (Concentrated Glycol pump seal failure)
Fluid from Vacuum Effect Evaporator (061-C-537) bottom section at temperature 91°C and
pressure 0.29 kg/cm2g is pumped by means of Concentrated Glycol pump (061-P-530A/B)
to Drying Column (061-C-610). Failure of Concentrated Glycol pump seal (equivalent hole
dia.: 10 mm) with an average frequency of occurrence 3.75 x 10-4 per year is considered for
the modelling purpose. From the outcome of the modelling, it is observed that the released
liquid would form a pool around the point of source. The pool may catch fire in the presence
of an ignition source nearby giving rise to pool fire. Also jet fire would be realized if release
immediately catches fire. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 4 11 9 NR 44 21 NR
5D 4 10 8 NR 46 22 NR
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 81 OF 106
From the above table and hazard contour Annexure-C Figure C1.26 & Figure C1.27 (only jet
fire of radiation intensity 4 & 12.5 kW/m2 is realized), the flash fire distance (LFL distance)
and jet fire distance would be less and restricted within the ethylene glycol unit.
Figure C2.28 shows contours for Pool Fire. Pool fire of intensity 4 & 12.5 kW/m2 would be
experienced, limited to Ethylene Glycol unit. However, thermal radiation of intensity 12.5
KW/m2 due to pool fire would engulf nearby process vessel in radius of 22 meters
depending upon the wind direction.
EG-11 (Drying Column bottoms pump seal failure)
Fluid from Drying Column (061-C-610) bottom section at temperature 162°C and pressure
0.17 kg/cm2g is pumped by means of Drying Column Bottom pump (061-P-610A/B) to MEG
Column (061-C-620). Failure of Drying Column Bottom pump seal (equivalent hole dia.: 10
mm) with an average frequency of occurrence 3.75 x 10-4 per year is considered for the
modelling purpose. From the outcome of the modelling, it is observed that the released
liquid would form a pool around the point of source. The pool may catch fire in the presence
of an ignition source nearby giving rise to pool fire. Also jet fire would be realized if release
immediately catches fire. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 2 4 NR NR 34 20 11
5D 2 4 NR NR 35 23 11
From the above table and hazard contour Annexure-C Figure C1.29 & Figure C1.30 (only jet
fire of radiation intensity 4 kW/m2 would be realized), the flash fire distance (LFL distance)
and jet fire distance would be less and restricted within the ethylene glycol unit.
Figure C2.31 shows contours for Pool Fire. Pool fire of intensity 4,12.5, 37.5 kW/m2 would
be experienced, limited to Ethylene Glycol unit. However, thermal radiation of intensity 12.5
KW/m2 due to pool fire would engulf nearby process vessel in radius of 23 meters
depending upon the wind direction.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 82 OF 106
EG-12 (50 mm hole on MEG Column overhead line)
MEG Column overhead’s operating pressure and temperature is 0.18 kg/cm2g and 139°C
respectively. 50 mm hole on MEG Column overhead line is considered for the modelling
purpose. From the outcome of the modelling, it is observed that flash fire and jet fire will be
realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire Jet Fire (kW/m2)
4 12.5 37.5 3D 3 9 NR NR
5D 2 11 NR NR From the above table and hazard contour Annexure-C Figure C2.32, Figure C2.33, flash fire
contour (LFL distance) and jet fire contours (radiation intensity of 4 kW/m2 would be less
and limited within the battery limit of ethylene glycol unit.
EG-13 (MEG Column bottoms pump seal failure)
Fluid from MEG Column (061-C-620) bottom section at temperature 162°C and pressure
0.17 kg/cm2g is pumped by means of Drying Column Bottom pump (061-P-610A/B) to MEG
Column (061-C-620). Failure of Drying Column Bottom pump seal (equivalent hole dia.: 10
mm) with an average frequency of occurrence 3.75 x 10-4 per year is considered for the
modelling purpose. From the outcome of the modelling, it is observed that the released
liquid would form a pool around the point of source. The pool may catch fire in the presence
of an ignition source nearby giving rise to pool fire. Also jet fire would be realized if release
immediately catches fire. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 3 8 7 NR 40 21 NR
5D 3 7 5 19 41 23 NR
From the above table and hazard contour Annexure-C Figure C2.34 & Figure C2.35, the
flash fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene glycol unit. Figure C2.36 shows contours for Pool Fire. Pool fire of intensity
4,12.5 kW/m2 would be experienced, limited to Ethylene Glycol unit. However, thermal
radiation of intensity 12.5 KW/m2 due to pool fire would engulf nearby process vessel in
radius of 23 meters depending upon the wind direction.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 83 OF 106
EG-14 (MEG Product Transfer pump seal failure)
Fluid from MEG Column (061-C-620) upper section at temperature 48°C and pressure 5.5
kg/cm2g is pumped by means of MEG Product Transfer Pump (061-P-640A/B) to MEG
Rundown Tank (061-TK-600A/B). Failure of MEG Product Transfer pump seal (equivalent
hole dia.: 10 mm) with an average frequency of occurrence 3.75 x 10-4 per year is
considered for the modelling purpose. From the outcome of the modelling, it is observed
that the released liquid would form a pool around the point of source. The pool may catch
fire in the presence of an ignition source nearby giving rise to pool fire. The hazard distance
are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 7 2 NR NR 58 28 NR
5D 7 2 NR NR 61 29 NR
From the above table and hazard contour Annexure-C Figure C2.37 & Figure C2.38, the
flash fire distance (LFL distance) and jet fire (only 4kW/m2) distance would be less and
restricted within the ethylene glycol unit.
Figure C2.39 shows contours for Pool Fire. Pool fire of intensity 4,12.5 kW/m2 would be
experienced, limited to Ethylene Glycol unit. However, thermal radiation of intensity 12.5
KW/m2 due to pool fire would engulf nearby process vessel in radius of 29 meters
depending upon the wind direction. Thermal radiation of intensity 4 kW/m2 would be
covering E-side road of EG unit which may hinder the fire-fighting activities.
EG-15 (MEG Splitter Bottoms Pump discharge instrument tapping failure)
Fluid from MEG Splitter (061-C-630) bottom section at temperature 175°C and pressure
7.45 kg/cm2g is pumped by means of MEG Splitter Bottoms Pump (061-P-630A/B) to DEG
Column (061-C-710). Failure of MEG Splitter bottoms pump discharge line instrument
tapping (equivalent hole dia.: 50 mm) is considered for the modelling purpose. From the
outcome of the modelling, it is observed that the released liquid would form a pool around
the point of source. The pool may catch fire in the presence of an ignition source nearby
giving rise to pool fire. Also jet fire would be experience if release immediately get ignition
source. The hazard distance are summarized in below table
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 84 OF 106
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 4 12.5 37.5 0.03 0.1 0.3
3D 22 43 35 29 97 54 NR 48 32 26
5D 22 39 31 25 103 55 NR 48 32 26
From the above table and hazard contour Annexure-C Figure C2.40 & Figure C2.41, the
flash fire distance (LFL distance) and jet fire distance would be restricted within the ethylene
glycol unit.
Annexure-C Figure C2.42 shows contours for Pool Fire. Pool fire of intensity 4,12.5 kW/m2
would be experienced, limited to Ethylene Glycol unit. However, thermal radiation of
intensity 12.5 KW/m2 due to pool fire would engulf nearby process vessel in radius of 55
meters depending upon the wind direction. Thermal radiation of intensity 4 kW/m2 would be
covering E-side road of EG unit which may hinder the fire-fighting activities.
From Annexure-C Figure C2.43 it can be seen that overpressure contours would be limited
to Ethylene Glycol unit. No building is coming under these contours.
EG-16 (DEG Column bottoms pump seal failure)
Fluid from DEG Column (061-C-710) bottom section at temperature 178°C and pressure 6.6
kg/cm2g is pumped by means of DEG Column Bottom pump (061-P-710A/B) to TEG
Column (061-C-720). Failure of DEG Column Bottom pump seal (equivalent hole dia.: 10
mm) with an average frequency of occurrence 3.75 x 10-4 per year is considered for the
modelling purpose. From the outcome of the modelling, it is observed that the released
liquid would form a pool around the point of source. The pool may catch fire in the presence
of an ignition source nearby giving rise to pool fire. Also jet fire, VCE would be realized.
The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 4 12.5 37.5 0.03 0.1 0.3
3D 10 7 6 6 64 32 NR - - -
5D 11 8 6 5 68 34 NR 18 14 12
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 85 OF 106
From the above table and hazard contour Annexure-C Figure C2.44 & Figure C2.45, the
flash fire distance (LFL distance) and jet fire distance would be less and restricted within the
ethylene glycol unit.
Annexure-C Figure C2.46 shows contours for Pool Fire. Pool fire of intensity 4,12.5kW/m2
would be experienced, limited to Ethylene Glycol unit. However, thermal radiation of
intensity 12.5 KW/m2 due to pool fire would engulf nearby process vessel in radius of 34
meters depending upon the wind direction. Thermal radiation of intensity 4 kW/m2 would be
covering N-side road of EG unit which may hinder the fire-fighting activities.
From Annexure-C Figure C2.47 it can be seen that overpressure contours would be limited
to Ethylene Glycol unit. No building is coming under these contours.
EG-17 (DEG Product Transfer Pump discharge instrument tapping failure)
Fluid from DEG Rundown Tanks (061-TK-730A/B) operating at temperature 55°C and
atmospheric pressure is pumped by means of DEG Product Transfer Pump (061-P-730A/B)
to OSBL DEG Storage Tanks (207-TK-004A/B). Failure of DEG Product Transfer pump
discharge line instrument tapping (equivalent hole dia.: 50 mm) is considered for the
modelling purpose. From the outcome of the modelling, it is observed that the released
liquid would form a pool around the point of source. The pool may catch fire in the presence
of an ignition source nearby giving rise to pool fire. The hazard distance are summarized in
below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 4 12.5 37.5 0.03 0.1 0.3
3D 13.5 3.13 NR NR 50.29 31.49 NR NR NR NR
5D 13.5 2.96 NR NR 51.38 33.14 NR NR NR NR
From the above table and hazard contour Annexure-C Figure C2.48 & Figure C2.49, the
flash fire distance (LFL distance) and pool fire (intensity 4 / 12.5kW/m2) distance would be
restricted within the ethylene glycol unit.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 86 OF 106
EG-18 (TEG Product Transfer Pump discharge instrument tapping failure)
Fluid from TEG Rundown Drum (061-V-740A/B) operating at temperature 164°C and
atmospheric pressure is pumped by means of TEG Product Transfer Pump (061-P-740A/B)
to OSBL TEG Storage Tanks (207-TK-005A/B). Failure of TEG Product Transfer pump
discharge line instrument tapping (equivalent hole dia.: 50 mm) is considered for the
modelling purpose. From the outcome of the modelling, it is observed that the released
liquid would form a pool around the point of source. The pool may catch fire in the presence
of an ignition source nearby giving rise to pool fire. Also jet fire would be experience if
release immediately get ignition source. The hazard distances are summarized in below
table. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 4 12.5 37.5 0.03 0.1 0.3
3D 15 26.6 21 17.6 42.5 32.7 22.6 17.8 13.3 11.6
5D 16 24.4 19.0 16 43.38 34.11 22.7 18.4 13.6 11.8
From the above table and hazard contour Annexure-C Figure C2.50, Figure C2.51 and
Figure C2.52, the flash fire distance (LFL distance), jet fire and pool fire (intensity
4/12.5/37.5kW/m2) distance would be restricted within the ethylene glycol unit.
From Annexure-C Figure C2.53 it can be seen that overpressure contours would be limited
to Ethylene Glycol unit. No building is coming under these contours.
EG-19 (Moderator Feed Drum line rupture)
Moderator from Moderator Feed Drum (061-V-140) operating at temperature 40°C and 23.5
kg/cm2g pressure is feed to EO reactor with nitrogen pressure. V-140 outlet line rupture is
(equivalent hole dia.: 50 mm) is considered for the modelling purpose. From the outcome of
the modelling, it is observed that the released liquid would form a pool around the point of
source. The pool may catch fire in the presence of an ignition source nearby giving rise to
pool fire. Also jet fire would be experience if release immediately get ignition source. The
hazard distances are summarized in below table. The hazard distance are summarized in
below table
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 87 OF 106
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 4 12.5 37.5 0.03 0.1 0.3
3D 11.7 79 64 52 173 87 38 15 12 11
5D 11.7 75 60 50 186 101 41 15 12 11
From the above table and hazard contour Annexure-C Figure C2.54 & Figure C2.57, the
flash fire & overpressure contours would be restricted within the EG unit. Figure C2.55 &
Figure C2.56, the jet fire & pool fire (intensity 4/12.5/37.5kW/m2) distance would be
restricted within the facility. However, the contours are covering East side of road of EG
unit.
From above observation following is recommended:
Provide HC gas detector in vicinity of 061-V-140 for early detection of any leakage.
Vehicular movement on roads along the ethylene storage sphere should be avoided to
eliminate potential ignition source.
9.3. Offsite & Utility Facility (O&U)
OU-1 (Flange gasket failure at the outlet of ethylene sphere)
Ethylene is stored in four ethylene storage sphere (207-HS-002A~D), 18 meters in diameter,
with a stored capacity of 3053m3. Ethylene is stored at pressure and temperature of sphere
is 18kg/cm2g and -38°C respectively. Failure of sphere outlet flange gasket failure
(equivalent hole dia.: 50 mm) having frequency of occurrence 5 x 10-5 to 5 x 10-7 per year is
considered for the modelling purpose. From the outcome of the modelling, it is observed
that flash fire, jet fire and VCE will be realized. The hazard distance are summarized in
below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 71 70 56 48 144 102 86
5D 72 66 52 43 143 101 85
From the above table and hazard contour Annexure-C Figure C3.1, Figure C3.2 and Figure
C3.3, the flash fire distance (LFL distance), jet fire and overpressure contours would be
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 88 OF 106
restricted within the ethylene storage sphere area. However, the radiation may have impact
on the adjacent spheres.
From above observation following is recommended:
Provide active / passive fire protection for Ethylene Storage sphere as per OISD.
Provide HC gas detector in vicinity of ethylene product transfer pump seal for early
detection of any leakage.
Requirement of suitable means of inventory isolation shall be reviewed during detail
engineering.
Vehicular movement on roads along the ethylene storage sphere should be avoided to
eliminate potential ignition source.
OU-2 (Flange gasket leak at BOG Package)
Normally BOG compressor package will be in line during holding mode of operation of
sphere. During normal operation the vapor line from sphere will be floating with ERU unit.
Failure of BOG compressor outlet flange gasket (equivalent hole dia.: 50 mm) having
frequency of occurrence 5 x 10-5 to 5 x 10-7 per year is considered for the modelling
purpose. From the outcome of the modelling, it is observed that flash fire, jet fire and VCE
will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 41 55 44 38 88 61 50
5D 40 52 41 34 87 60 50
From the above table and hazard contour Annexure-C Figure C3.4, Figure C3.5 and Figure
C3.6, the flash fire distance (LFL distance), jet fire and overpressure contours would be
restricted within the ethylene storage sphere area and no building is covered under these
contours.
OU-3 (Ethylene Product Transfer Pump seal failure)
Ethylene Product Transfer pump is used to transfer ethylene to MEG unit through Ethylene
vaporizer, with a capacity of 56 m3/hr. Failure of Ethylene Product Transfer pump seal
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 89 OF 106
(equivalent hole dia.: 10 mm) having frequency of occurrence 3.75 x 10-4 per year is
considered for the modelling purpose. From the outcome of the modelling, it is observed
that flash fire, jet fire and VCE will be realized. The hazard distance are summarized in
below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 23 34 27 23 48 32 26
5D 20 32 25 21 46 31 25
From the above table and hazard contour Annexure-C Figure C3.7, Figure C3.8 and Figure
C3.9, the flash fire distance (LFL distance), jet fire and overpressure contours would be
restricted within the ethylene storage sphere area and no building is covered under these
contours. However, radiation intensity of 12.5kW/m2 would be reaching to Ethylene
vaporizer structure.
From above observation following is recommended:
Provide active / passive fire protection as per OISD-116.
Provide HC gas detector in vicinity of ethylene product transfer pump seal for early
detection of any leakage.
Vehicular movement on roads along the ethylene storage sphere should be avoided to
eliminate potential ignition source.
OU-4 (Ethylene Vaporizer outlet line instrument tapping failure)
Ethylene vaporizer used to vaporize liquid ethylene from ethylene transfer pump. The outlet
temperature and pressure of ethylene vaporizer is 40°C and 27 kg/cm2g. Failure of ethylene
vaporizer outlet instrument tapping (equivalent hole dia.: 50 mm) is considered for the
modelling purpose. From the outcome of the modelling, it is observed that flash fire, jet fire
and VCE will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 43 58 45 36 91 62 51
5D 43 58 46 37 89 61 50
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 90 OF 106
From the above table and hazard contour Annexure-C Figure C3.7, the flash fire distance
(LFL distance), would be restricted within the ethylene storage sphere area. Figure C3.11
shows jet fire contours. Radiation intensity of 12.5kW/m2 covers ethylene storage sphere
depending upon the wind direction. Radiation intensity of 4kW/m2 convers South side road
of Ethylene storage area. Figure C3.12 shows overpressure contours. 0.1/0.3 bar
overpressure contours remains inside of sphere area. However, no building is covered
under these contours.
From above observation following is recommended:
Provide active / passive fire protection as per OISD-116.
Provide HC gas detector in vicinity of ethylene product transfer pump seal for early
detection of any leakage.
Vehicular movement on roads along the ethylene storage sphere should be avoided to
eliminate potential ignition source.
OU-5 (Catastrophic rupture of Ethylene Storage Sphere)
Ethylene is stored in four ethylene storage sphere (207-HS-002A~D), 18 meters in diameter,
with a stored capacity of 3053m3. Ethylene is stored at pressure and temperature of sphere
is 18kg/cm2g and -38°C respectively. The case considered for modelling is catastrophic
rupture of the vessel with an average frequency of occurrence 5X10-7 per year. Although
the occurrence frequency is remote, to assess the worst possible consequence, this unlikely
failure case is considered. In the Catastrophic rupture scenario, vessel is destroyed by an
impact, a crack, or some other failure which propagates very quickly. The release is
assumed to form a homogeneous mass, expanding rapidly with no restrictions from the
shattered vessel. The instantaneous release of hydrocarbon may lead to fire ball explosion
on immediate ignition. Else the dispersing hydrocarbon vapor-air cloud may reach an
ignition source and a flash fire would occur. The hazard distance are summarized in below
table
Weather Condition
Hazard Distances (m) Flash Fire
Fire Ball (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 433 1840 1007 395 2657 1133 566
5D 680 1840 1007 395 2657 1133 566
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 91 OF 106
From the above table and hazard contour Annexure-C Figure C3.13, Figure C3.14 and
Figure C3.15, LFL contour covers ER, EG, Air separation units, sub-station (SS-1), SRR.
Radiation contours of intensity 37.5 kW/m2 remains within the property line. However,
4/12.5 kW/m2 radiation can go outside the property line on E-side. Overpressure contours
would be going outside the property line.
From the above observations following is recommended
Efficiently monitor health of ethylene storage sphere by inspection of vessel
internals, thickness measurement (involving techniques like ultrasonic thickness
measurement) & administering other techniques during shut-down period.
Ensure availability of water spray system for equipment handling significant amount
of hydrocarbon to protect against thermal heat radiation.
Continuous presence of people just outside the E-side property line should be
discouraged.
Consider this failure scenario in formulating the Disaster Management plan.
OU-6 (MEG Product Transfer Pump seal leak)
MEG Product Transfer pump (207-P-003A~D) is used to transfer MEG to loading gantry.
Normal capacity of pump is 95 m3/hr. Failure of MEG Product Transfer pump seal
(equivalent hole dia.: 10 mm) having frequency of occurrence 3.75 x 10-4 per year is
considered for the modelling purpose. From the outcome of the modelling, it is observed
that flash fire and pool fire will be realized. The hazard distance are summarized in below
table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 23 NR NR NR 30 19 9
5D 20 NR NR NR 31 21 9
From the above table and hazard contour Annexure-C Figure C3.16 and Figure C3.17, LFL
contour is limited to the leak source. Radiation intensity of 12.5/37.5 kW/m2 not impacting
the storage tank.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 92 OF 106
OU-7 (Ship Loading pump discharge flange gasket leak)
MEG Ship loading pump (207-P-010A/B) is used to transfer MEG to ship loading. Normal
capacity of pump is 500 m3/hr. Failure of MEG Ship Loading pump discharge flange gasket
leak (equivalent hole dia.: 50 mm) having frequency of occurrence 5 x 10-5 to 5 x 10-7 per
year is considered for the modelling purpose. From the outcome of the modelling, it is
observed that flash fire, jet fire, pool fire and VCE will be realized. The hazard distance are
summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 4 12.5 37.5 0.03 0.1 0.3
3D 10 7 6 NR 183 96 NR 12 11 10
5D 10 6 6 NR 193 97 NR 13 11 10
From the above table and hazard contour Annexure-C Figure C3.18 through Figure C3.21,
LFL contour, Jet fire contour, Overpressure contour is limited to the leak source. Pool fire
contour of intensity 4/12.5kW/m2 would be realized. However, these are limited within the
property line.
OU-8 (MEG Truck Loading Arm leak)
MEG is loaded in truck tanker through 5 loading bays. Capacity of each loading bay is
55m3/hr. One shift of ten hours is considered for loading and unloading operation in a day.
Effective filling time of one tanker is 30 mins. Failure of Large hole at MEG loading bay
(equivalent hole dia.: 50 mm) having frequency of occurrence 5 x 10-5 to 5 x 10-7 per year is
considered for the modelling purpose. From the outcome of the modelling, it is observed
that flash fire, jet fire and pool fire will be realized. The hazard distance are summarized in
below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 7 3.6 NR NR 115 56 NR
5D 7 3.4 NR NR 121 57 NR From the above table and hazard contour Annexure-C Figure C3.22 and Figure C3.14, LFL
contour and jet fire contour (4kw/m2) is limited to the leak source. Pool fire radiation intensity
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 93 OF 106
of 12.5 kW/m2 would impact other loading bay and also this in-circles N-side of future
benzene / Styrene loading gantry.
From the above observation following is recommended:
Provide excess flow check valve in liquid line, both on loading arm side and wagon
side.
Provide heat detection based automatic water sprinkler system.
Ensure sufficient number of fire water monitors at the gantry area covering the entire
length of the gantry for firefighting. Provide water spray system at loading bay area as
per the OISD guideline.
OU-9 (MEG Tank on Fire)
MEG is stored in five storage tanks (207-TK-003A~E), 25 meters diameter & 15 meters
height , with a nominal capacity of 7363m3 each tank. These are cone roof tanks with
nitrogen blanketing. MEG is stored at atmospheric pressure and 48°C temperature. The
case considered for modelling is MEG tank on fire with an average frequency of occurrence
5X10-7 per year. Although the occurrence frequency is remote, to evaluate the impact of the
pool fire radiation on adjacent storage tanks, this unlikely failure case is considered. From
the outcome of the modelling, it is observed that flash fire, pool fire and VCE will be realized.
The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 27 40 18 NR 44 30 25
5D 28 42 19 NR 48 32 26
As apparent from the Annexure C, Figures C3.25 through C3.27, pool fire of radiation
intensity 12.5 KW/m2, would not reaching to adjacent tank in the dyke. Also overpressure
contours are limited within the storage area.
OU-10 (DEG Product Transfer Pump seal leak)
DEG Product Transfer pump (207-P-004A/B) is used to transfer DEG to loading gantry.
Normal capacity of pump is 55m3/hr. Failure of DEG Product Transfer pump seal
(equivalent hole dia.: 10 mm) having frequency of occurrence 3.75 x 10-4 per year is
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 94 OF 106
considered for the modelling purpose. From the outcome of the modelling, it is observed
that flash fire and pool fire will be realized. The hazard distance are summarized in below
table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 1 NR NR NR 23 16 7
5D 1 NR NR NR 24 17 7
From the above table and hazard contour Annexure-C Figure C3.18 Figure C3.29, LFL
contour is limited to the leak source. Also pool fire radiation intensity contour of 12.5/37.5
kW/m2 not reaching to storage tanks.
OU-11 (DEG Truck Loading Arm leak)
DEG is loaded in truck tanker through 1 loading bay. Capacity of loading bay is 55m3/hr.
One shift of ten hours is considered for loading and unloading operation in a day. Effective
filling time of one tanker is 30 mins. Failure of Large hole at DEG loading bay (equivalent
hole dia.: 50 mm) having frequency of occurrence 5 x 10-5 to 5 x 10-7 per year is considered
for the modelling purpose. From the outcome of the modelling, it is observed that flash fire
and pool fire will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 9 NR NR NR 97 47 NR
5D 9 NR NR NR 103 49 NR From the above table and hazard contour Annexure-C Figure C3.30 and Figure C3.31, LFL
contour and pool fire contour (4kw/m2) is limited to the leak source. Pool fire radiation
intensity of 4 kW/m2 would impact other persons in loading bay and also this in-circles N-
side of future benzene / Styrene loading gantry.
From the above observation following is recommended:
Provide excess flow check valve in liquid line, loading arm side
Provide heat detection based automatic water sprinkler system
Ensure sufficient number of fire water monitors at the gantry area covering the entire
length of the gantry for firefighting
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 95 OF 106
OU-12 (DEG Tank on Fire)
DEG is stored in two storage tanks (207-TK-004A/B), 15.5 meters diameter & 12 meters
height , with a nominal capacity of 2264m3 each tank. One tank will be operating. These are
cone roof tanks with nitrogen blanketing. DEG is stored at atmospheric pressure and 48°C
temperature. The case considered for modelling is DEG tank on fire with an average
frequency of occurrence 5X10-7 per year. Although the occurrence frequency is remote, to
evaluate the impact of the pool fire radiation on adjacent storage tanks, this unlikely failure
case is considered. From the outcome of the modelling, it is observed that flash fire, pool
fire and VCE will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 31 330 187 NR 38 33 32
5D 29 350 188 NR 29 24 22
As apparent from the Annexure C, Figures C3.32 through C3.34, LFL contour and
overpressure contours remains within the tank dyke area. Pool fire of radiation intensity
12.5 KW/m2, would be within the property line. However, this will cover the tanks in the dyke
area.
From the above observation following is recommended:
Provide heat detection based automatic water sprinkler system
Ensure sufficient number of fire water monitors at the tank area
OU-13 (TEG Product Transfer Pump seal leak)
TEG Product Transfer pump (207-P-005A/B) is used to transfer TEG to loading gantry.
Normal capacity of pump is 55m3/hr. Failure of TEG Product Transfer pump seal
(equivalent hole dia.: 10 mm) having frequency of occurrence 3.75 x 10-4 per year is
considered for the modelling purpose. From the outcome of the modelling, it is observed
that flash fire and pool fire will be realized. The hazard distance are summarized in below
table
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 96 OF 106
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 1 NR NR NR 23 16 7
5D 1 NR NR NR 24 17 7
From the above table and hazard contour Annexure-C Figure C3.35 Figure C3.36, LFL
contour is limited to the leak source. Also pool fire radiation intensity contour of 12.5/37.5
kW/m2 not reaching to storage tanks.
OU-14 (TEG Truck Loading Arm leak)
TEG is loaded in truck tanker through 1 loading bay. Capacity of loading bay is 55m3/hr.
Failure of Large hole at TEG loading bay (equivalent hole dia.: 50 mm) having frequency of
occurrence 5 x 10-5 to 5 x 10-7 per year is considered for the modelling purpose. From the
outcome of the modelling, it is observed that flash fire and pool fire will be realized. The
hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Jet Fire (kW/m2) Pool Fire (kW/m2) 4 12.5 37.5 4 12.5 37.5
3D 9 NR NR NR 97 47 NR
5D 9 NR NR NR 103 48 NR
From the above table and hazard contour Annexure-C Figure C3.37 and Figure C3.38, LFL
contour is limited to the leak source. Pool fire radiation intensity of 4 kW/m2 would impact
other persons in loading bay and also this in-circles N-side of future benzene / Styrene
loading gantry.
From the above observation following is recommended:
Provide excess flow check valve in liquid line, on loading arm side
Provide heat detection based automatic water sprinkler system
Ensure sufficient number of fire water monitors at the gantry area covering the entire
length of the gantry for firefighting
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 97 OF 106
OU-15 (TEG Tank on Fire)
TEG is stored in two storage tanks (207-TK-005A/B), 7.5 meters diameter & 7.2 meters
height , with a nominal capacity of 3184m3 each tank. One tank will be operating. These are
cone roof tanks with nitrogen blanketing. TEG is stored at atmospheric pressure and 48°C
temperature. The case considered for modelling is TEG tank on fire with an average
frequency of occurrence 5X10-7 per year. Although the occurrence frequency is remote, to
evaluate the impact of the pool fire radiation on adjacent storage tanks, this unlikely failure
case is considered. From the outcome of the modelling, it is observed that flash fire, pool
fire and VCE will be realized. The hazard distance are summarized in below table
Weather Condition
Hazard Distances (m) Flash Fire
Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 16 158 78 NR 12 11 10
5D 15 165 76 NR 12 11 10
As apparent from the Annexure C, Figures C3.39 through C3.41, LFL contour and
overpressure contours remains within the tank dyke area. Pool fire of radiation intensity
4/12.5 KW/m2, would be within the property line. However, this will cover the tanks in the
dyke area.
From the above observation following is recommended:
Provide heat detection based automatic water sprinkler system.
Ensure sufficient number of fire water monitors at the tank area.
9.4. Client Cases
CC-01 (C3+ Product header from ERU to PRU rupture)
C3+ Product from Deethylenizer (060-C-301) bottom is sent to Propylene Recovery Unit at a
pressure of 16.5 kg/cm2g and temperature of 40°C through 2” header on pipe rack over
creek. Rupture of C3+ Product header, having frequency of occurrence 5 x 10-7 per year is
considered for the modelling purpose as a conservative approach. From the outcome of the
modelling, it is observed that flash fire, jet fire and VCE will be realized. The hazard
distances are summarized in below table.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 98 OF 106
Weather Condition
Hazard Distances (m) Flash Fire
Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 14 28 20 NR 30 18 14
5D 13 26 18 11 28 18 14 As apparent from the Annexure C, Figures C4.1 through C4.3, LFL contour, Jet fire and
overpressure contours remains within the creek area only. Also no pool of liquid C3+
Product is possible.
CC-02 (50 mm hole on Refinery Off gas header from FCC to ERU)
Refinery Off gas from FCC is fed to Ethylene Recovery Unit at a pressure of 12.1 kg/cm2g
and temperature of 40°C through 18” header on pipe rack over creek. A 50 mm hole is
considered for the modelling purpose as a conservative approach. From the outcome of the
modelling, it is observed that flash fire, jet fire and VCE will be realized. The hazard
distances are summarized in below table.
Weather Condition
Hazard Distances (m) Flash Fire
Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 16 34 24 NR 30 18 14
5D 15 34 25 NR 29 18 14 As apparent from the Annexure C, Figures C4.4 through C4.6, LFL contour, Jet fire and
overpressure contours remains within the creek area only.
CC-03 (50 mm hole on Fuel Gas header from ERU to Refinery fuel gas system)
Fuel Gas from Demethenizer (060-C-201) via 060-E-201 sent to Refinery Fuel gas system
at a pressure of 4 kg/cm2g and temperature of 40°C through 16” header on pipe rack over
creek. A 50 mm hole is considered for the modelling purpose as a conservative approach.
From the outcome of the modelling, it is observed that flash fire, jet fire and VCE will be
realized. The hazard distances are summarized in below table.
Weather Condition
Hazard Distances (m) Flash Fire
Pool Fire (kW/m2) Overpressure (bar) 4 12.5 37.5 0.03 0.1 0.3
3D 14 28 20 NR 30 18 14
5D 13 26 18 11 28 18 14 As apparent from the Annexure C, Figures C4.4 through C4.6, LFL contour, Jet fire and
overpressure contours remains within the creek area only.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 99 OF 106
10. CONCLUSION AND RECOMMENDATIONS
A Risk Analysis has been carried out for the new facilities coming under Ethylene Glycol
(IEGP) Project. To assess consequences based on the realization of the identified hazards,
worst-case scenarios such as catastrophic rupture of reflux drum, accumulator, storage
sphere and storage tank on fire which have very low likelihood (low frequency of
occurrence, 5 x 10-7/year), certain scenarios like large holes with frequency of occurrence
(frequency in the range of 5 x 10-5 to 5 x 10-7 per year depending upon nominal diameter of
pipeline) and medium hole like pump seal leak (10 mm equivalent hole having frequency
3.75 x 10-4 per year) have been considered. The effect zone has been indicated for the
weather condition causing worst consequences for each failure scenario.
The study reveals that for most of the failure cases, hazard distances are limited to
plant boundary and not affecting outside the complex. The detailed discussion on
risk analysis of the identified failure cases has been given in Section 9.
Major recommendations arising out of the Risk analysis study for this project are
summarized below.
Ethylene Recovery Unit: H2S Gas Detectors with audio-visual alarms (beacons) to be provided in vicinity of
equipment handling H2S gas (Case ER-2).
Sufficient number of Hydrocarbon gas detectors to be provided in the vicinity of pumps
and equipment handling light hydrocarbon (ER-8).
Requirement of inventory isolation to be reviewed during detail engineering for vessels
handling large amount of hydrocarbon (ER-8, ER-11, ER-12).
Catastrophic rupture scenario of Deethylenizer Reflux drum shall be included in
Disaster Management plan.
Ethylene Glycol Unit: Sufficient number of Hydrocarbon gas detectors / Toxic Gas detector (EO) to be
provided in the vicinity of pumps and equipment handling light hydrocarbon e.g.
ethylene, ethylene oxide (EG-1, EG-4, EG-6, EG-7, EG-8, EG-9).
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 100 OF 106
Sub-station and SRR shall be positively pressurized to avoid ingress of any HC or Toxic
gas inside these building (EG-9).
HC / Toxic Gas detector to be provided at sub-station and SRR air unit suction (EG-9).
Provide HC gas detector in vicinity of 061-V-140 for early detection of any leakage.
Vehicular movement on roads along the ethylene storage sphere should be avoided to
eliminate potential ignition source.
Offsite & Utility Facility: Provide active / passive fire protection for Ethylene Storage Sphere as per OISD(OU-1)
Provide HC gas detector in vicinity of ethylene product transfer pump seal for early
detection of any leakage (OU-1, OU-3, OU-4).
Requirement of inventory isolation to be reviewed during detail engineering (OU-1).
Vehicular movement on roads along the ethylene storage sphere should be avoided to
eliminate potential ignition source (OU-1, OU-3, OU-4).
Catastrophic rupture scenario of Ethylene Storage Sphere shall be included in Disaster
Management plan.
Excess flow check valve shall be provided on each loading bay (OU-8, OU-11, OU-14)
Heat detection based automatic water sprinkler system to be provided (OU12, OU-14).
Continuous presence of people E-side of property line should be discouraged (OU-5).
It is recommended to allow minimum number of vehicles at a time inside loading gantry.
This may result in longer time for gantry operations but will reduce the chances of any
possible ignition & consequent hazardous scenario and resultant risk arising, on
account of any leakage from the gantry (OU-7, OU-12, OU-15).
Creek Crossing Pipe Rack: It is to be noted that headers crossing creek over pipe rack, do not have any flanges or
instrument connections. Hence leakage of flanges / snap-off of instrument tapping is ruled
out. However, for consequence analysis (as a conservative approach), rupture / leak on
these headers over pipe rack is considered as per Client’s requirement. From the
consequence analysis it can be seen that the hazard distances due to fire, overpressure is
restricted within the creek area only. Considering these, as a prevention measure following
actions need to be taken care:
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 101 OF 106
All hydrocarbon vents and drains on headers running through the pipe rack should be
plugged-off.
Regular monitoring / heath check-up of headers running through the pipe rack crossing
the creek should be carried out.
General Recommendations
Mitigating Measures
Mitigating measures are those measures in place to minimize the loss of containment event
and, hazards arising out of Loss of containment. These include:
Rapid detection of an uncommon event (HC leak, Toxic gas leak, Flame etc.) and
alarm arrangements and development of subsequent quick isolation mechanism for
major inventory.
Measures for controlling / minimization of Ignition sources inside the facility.
Active And Passive Fire Protection for critical equipment and major structures.
Effective Emergency Response plans to be in place.
Detection and isolation
Ignition Control
Ignition control will reduce the likelihood of fire events. This is the key for reducing the
risk within facilities that process flammable materials. As part of mitigation measure it
strongly recommended to consider removal of Smoking booths which are located inside
unit though they are not acting as direct source of ignition.
Proper checking of contract people for Smoking or Inflammable materials to be ensured
at entry gates to avoid presence of any unidentified source of ignition.
The vehicles entering the facility should be fitted with spark arrestors as a mandatory
item.
Escape Routes
Provide windsocks throughout the site to ensure visibility from all locations. This will
enable people to escape upwind or crosswind from flammable / toxic releases.
Sufficient escape routes from the site should be provided to allow redundancy in
escape from all areas.
Escape sets shall be provided along the escape route in the unit.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 102 OF 106
Provide breathing apparatus at strategic locations inside the unit.
Provide sign boards marking emergency/safe roads to be taken during any exigencies.
Emergency security / evacuation drills to be organized at organization level to ensure
preparation of the personnel’s working in the complex for handling any extreme
situation.
Active and Passive Fire Protection
In order to prevent secondary incident arising from any failure scenario, it is
recommended that automatic/manual sprinklers should be provided on the large
inventory vessels and Storage Tanks/Mounded Bullets and should be regularly checked
to for their functionality.
It is to be ensured that firefighting systems for Existing/New tanks are provided as per
latest OISD guidelines.
Fire proofing of structures and vessels supports as per latest OISD guidelines to
prevent hazard escalation in the event of fire.
Preventive Maintenance for Critical Equipment
In order to further reduce the probability of catastrophes efficient monitoring of vessel
internals during shut-down to be carried out for pressurized vessels handling significant
volume of hydrocarbons, whose rupture would lead to massive consequences based
upon the outcomes of RA study.
Others
Closed sampling system to be considered for pressurized services like Ethylene etc.
Whenever a person visits for sampling and maintenance etc. it is always recommended
to carry portable HC / Toxic Gas detector.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 103 OF 106
11. GUIDELINES FOR DISASTER MANAGEMENT PLAN
11.1. Introduction
Disasters are major accidents which cause wide spread disruption of human and
commercial activities. Normally, common accidents are absorbed by the community, but
disasters are major accidents and community cannot absorb them with their own resources.
Most of the disasters, natural or technological (man- made) have sudden onset and give
very short notice or no time to prevent the occurrence. Disasters may cause loss of human
life, injuries and long-term disablement of people working in the organization and local
community around the industrial area. Normally, loss of revenue / employment and
rebuilding cost lead to severe economic constraints.
The likelihood of disaster needs to be foreseen, as the past experiences indicate.
Therefore, if disasters are foreseeable, the mitigating efforts can be planned in advance.
Paramount importance should be given to protect human life and environment, in such
planning.
As the IOCL, Paradip facility is existing operating facility and have the disaster management
plan for the facility.
Following are the essential aspects of a conventional DMP:
Organization Structure Service coordinator
Chain of command Fire & safety coordinator
Suggested responsibilities of the members
of DMP organogram
Plant coordinator
Overall Technical coordinator Finance coordinator
Chief co-coordinator Electrical and communication coordinator
Technical coordinator Transport and Medical coordinator
Manufacturing / Production units coordinator Personnel and Welfare coordinator
Material coordinator Administration, Welfare and Security
coordinator
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 104 OF 106
11.2. Action Plans
The selected failure scenarios as analyzed in Section 9 of the report may be considered as
representative cases of failures that may lead to loss of containment.
The failures selected when realized may lead to disastrous consequences as they affect
major process units that handle large inventory of flammable or toxic material. Inability to
timely control such event may result in heavy casualty to life and property.
11.2.1. Emergency Plan for Controlling the Initial Incident
In case of release of contents to atmosphere and when there is no fire, the action plan shall
include: Report the incident to the superior officer concerned / control room.
Break the nearest fire alarm field station and / or dial the fire station giving the location
and nature of emergency.
Mobilize all firefighting resources including foam truck and DCP tender and ask them to
be ready to fight any eventuality and be near the scene.
Ambulance and medical staff to report at the scene. Remove injured personnel and
render medical treatment.
Start firewater spray to reduce vapor concentration. Care should be taken to avoid
water spray on spilled liquid.
As per wind direction, remove / isolate the ignition sources like heaters, vehicles etc.
If vapor cloud moves towards control room, air-handling (HVAC) unit is to be stopped.
In case a fire is noticed in the area, the “Fire emergency procedure” must be put into
action immediately.
Take emergency shutdown of the unit and also neighboring units.
Shut down concerned rotating equipment (e.g. pump / compressor) which is supplying
inventory to the place of incident or Isolate the nearest concerned valves to segregate
the concerned vessel.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 105 OF 106
11.2.2. Disaster Plan
Trigger off the Emergency plan by sounding the alert system and prepare for any
emergency arising in case fire is not brought under control leading to catastrophic situation.
The emergency action plan to be initiated in case of failure would be as follows: Take an emergency shutdown of nearby process units, which are still in operation.
Depending on the nature of the severity of disaster the whole complex may have to be
shut down. Decision is to be taken by Chief co-coordinator, Overall Technical co-
coordinator and Fire and Safety Co-coordinator in consultation amongst themselves.
Operate the cooling water spray on the affected vessel/nearby vessels.
Start additional firewater pumps and maintain header pressure.
Arrange for topping up diesel in firewater pumps/DG sets.
Inject foam on the vessels under fire through foam lines using the trucks or other foam
making equipment as and where accessibility permits.
Inform ambulance and medical staff to report at the scene.
Remove injured personnel and render medical treatment. Get additional medical
help if required. Hospitalize the affected people and inform their families.
Cordon off the affected area and remove all non-essential employees (e.g. Contractor’s
personnel).
Arrange for traffic control inside the refinery and outside the main gate. Ensure
that the approach road to the main gate is cleared to facilitate movement of essential
services. Arrange for refreshments for firefighting personnel.
Arrange relief crew for firefighting personnel.
Inform neighboring people about the fire (colony and outsiders) to avoid panic among
the people.
Inform local authorities/police station. Arrange for evacuation of people.
Inform the press about the nature and seriousness of the fire to avoid false
propaganda.
Intimate concerned authorities about the situation. Obtain supplementary
materials/equipment etc. for crisis control from other places if required.
The inputs given above may be suitably updated in the existing Disaster Management Plan
(DMP) of Paradip Refinery and Petrochemical Complex.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE 106 OF 106
12. REFERENCE
[1] Climatological Normals 1961-1990 by Indian Meteorological Department
[2] UK HSE, Application of RA in Operational Safety Issues, Det Norske Veritas Ltd,
2002
[3] OGP Risk Assessment Data Directory – Ignition Probabilities, Report No. 434-6,
International Association of Oil & Gas Producers, March 2010
[4] Cox A.W., Lees F.P., Ang M.L., (1990), Classification of Hazardous Locations,
IChemE, Rugby, UK
[5] Woodward, J. L., Estimating the Flammable Mass of a Vapor Cloud, CCPS Concept
Book, AIChE
[6] Lees, F.P., Loss Prevention in the Process Industries, Butterworth-Heinemann, 1996
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE A1 OF A20
ATTACHMENT - A
ASSUMPTIONS REGISTER
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-PH-
000-0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 1 OF 7
CONTENTS
1. Introduction 2
2. SCOPE OF WORK 2
3. OBJECTIVE 2
4. TERMINOLOGY 2
4.1 Definitions 2
4.2 Abbreviations 3
5. RA METHODOLOGY 3
5.1 System Description 3
5.2 Hazard Identification 3
5.3 Consequence Analysis 4
5.3.1 Source term/ Discharge modelling 4
5.3.2 Dispersion Modelling 4
5.3.3 Physical effects modelling 5
5.3.4 Impact Assessment at Consequence End-Point 6
5.4 Risk Mitigation Measures 6
5.5 Guidelines for Disaster Management Plan (DMP) 6
6. DOCUMENTS REQUIRED 6
7. RA REPORT CONTENT 7
8. SOFTWARE 7
9. REFERENCE 7
ATTACHMENT – 1 - Assumptions Register
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-PH-
000-0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 2 OF 7
1. Introduction M/s. Indian Oil Corporation Limited (IOCL) has appointed M/s. Toyo Engineering India Pvt. Ltd. as the Project Management Consultant (PMC) for installation of Ethylene Glycol production facilities from Front End loading (FEL) stage up to Plant commissioning and final contract closure.
2. SCOPE OF WORK The intent of the RA Study is to systematically identify all potential failure / accidents / hazards and its consequences. Subsequently analyse the extent of damage due to such incidents and draws suitable mitigating measures. The scope of RA Study for Project will include the following units: Ethylene Glycol Unit (Capacity: 357 KTPA)
Ethylene Recovery Unit (Capacity: 180 KTPA)
Offsite & Utilities
The RA Study shall be performed only for the above new facilities. Detailed assessment for the existing facilities or integration with the existing facilities or impact of existing facilities on new facilities or vice versa is not considered within the scope.
3. OBJECTIVE This Risk Analysis identifies the potential events leading to major accident hazards and the magnitude of safety related consequences of each event. It does not establish the probability of the event occurring. The objectives of this study are to: Identify possible failure / hazards associated with the coming new facility
Assess the possible consequences of these hazards should they occur.
Suggest suitable mitigation measures to minimize frequency and the consequence of these Hazards
4. TERMINOLOGY
4.1 Definitions
PROJECT : PMC SERVICES FOR ETHYLENE GLYCOL PROJECT AT PARADIP REFINERY (IEGP)
COMPANY : INDIAN OIL CORPORATION LIMITED
PMC / CONSULTANT : TOYO ENGINEERING INDIA PVT. LTD.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-PH-
000-0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 3 OF 7
4.2 Abbreviations CCPS Center for Chemical Process Safety C&E Cause and Effect CIA Chemical Industries Association DNV Det Norske Veritas ESD Emergency Shutdown ETA Event Tree Analysis HAZOP Hazard and Operability Study IMD Indian Meteorological Department LFL Lower Flammability Limit MSDS Material Safety Datasheet PES Potential Explosion Site PFD Process Flow Diagram P&ID Piping and Instrumentation Diagram PHAST Process Hazard Analysis Safety Tool RA Risk Assessment SIL Safety Integrity Level UDM Unified Dispersion Modelling VCE Vapour Cloud Explosion
5. RA METHODOLOGY A detailed procedure as given by the American Institute of Chemical Engineers Center for Chemical Process Safety (CCPS CPRA) will be adopted to conduct the RA. The key elements of this procedure are outlined in following sections.
5.1 System Description The study begins with the system definition. This involves a review of the process description, PFDs, P&IDs etc. to have a thorough understanding of the process. The process is then divided into subsections, considering process conditions, for further analysis.
5.2 Hazard Identification The RA begins with hazard identification which involves a review of the hazardous properties of the materials processed and stored at the plant. Following techniques may be employed for identification of hazards: 1. Collection of information on relevant operating conditions of proposed facilities. 2. Identification of hazard prone areas based on credible and worst case accidental release
scenarios. 3. Identification of worst case scenarios involving fire and explosion etc. on the basis of
safety feature / instrumentation provided at the station.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-PH-
000-0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 4 OF 7
5.3 Consequence Analysis Consequence modelling will be used to predict the size, shape, and orientation of hazard zones resulting from releases of flammable or toxic substances. Elements comprising the consequence analysis are described in the following sections.
5.3.1 Source Term/ Discharge Modelling Source term or discharge modelling involves determination of the maximum discharge rate, release duration and other physical properties of the released material, such as temperature and pressure. These estimated parameters are then set as the initial conditions for the subsequent dispersion or fire effects modelling. Refer Attachment -1 for Hole sizes considered in this RA Study.
Release Rate Calculation In the event of a catastrophic rupture of a vessel, the Instantaneous Model will be used to model the rapid release of the entire inventory, where the material in the vessel is expanded from initial conditions to atmospheric pressure. For releases from holes in pipes/ vessels, release rate will be calculated using standard orifice type calculations based on process conditions and leak size. For gas releases, the pressure in the system, and hence the release rate, slowly decrease following isolation, resulting in a time dependent release. As a conservative approach, the calculated initial release rate is assumed constant over the release duration for such scenarios. For large leaks from liquid streams, the release rate calculated from orifice type calculations will be compared with the pumping rate. If the calculated release rate exceeds the normal pumping rate, the discharge rate will be capped at 1.3 times the normal pumping rate. This will be applied to all leak locations downstream of a pump. Release Duration Release duration is determined by the upstream inventory and means of leak detection and isolation. The total release inventory will be calculated as the sum of equipment / piping inventory and the pump throughput before isolation is achieved. With the provision of gas and fire detectors and emergency shutdown system, it is assumed that isolation will be achieved within 2 mins. under normal conditions. It is possible for the isolation system to fail, in which case isolation can be achieved through manual intervention within 10 mins. Based on isolation system design and valves provided timing will be chosen accordingly.
5.3.2 Dispersion Modelling This involves mathematical simulation of how the released material disperses in the ambient atmosphere. Downwind and crosswind concentrations are determined to find the gas cloud hazard footprint.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-PH-
000-0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 5 OF 7
Vapour dispersion modelling will be conducted using PHAST’s Unified Dispersion Model (UDM).
5.3.3 Physical effects modelling Physical effects modelling determine the magnitude of damage caused by exposure to fire, heat radiation, overpressure or toxins. The following possible hazardous outcomes will be considered in the RA; Flash Fire A flash fire results from delayed ignition of a flammable vapour cloud, generated either through vaporization directly from the release, or from vaporizing pools. The main hazards of a flash fire being direct contact with the flame. The area of possible direct flame contact effects is determined through the distance which the lower flammability limit (LFL) of the vapour cloud has travelled. Due to the extreme short duration of a flash fire, radiation effects are negligible. Jet Fire A jet fire results from immediate ignition of the flammable material from a pressurized release. The main hazards from a jet fire are direct flame contact and radiation. Pool Fire A pool fire results upon ignition of a flammable liquid pool due to failure of process vessel/ piping. It is assumed that any liquid release shall form a pool around the source of the release. In the event of an ignition source a pool fire may ensue and shall result in a hazard due to thermal radiation. However, within the process units, Jet Fire effects will dominate and pool fires on process plant are not modelled. However, Storage Tank fires are modelled. Fireball A fireball would result from immediate ignition of a release resulting from cold catastrophic rupture of a pressurized vessel. Ignition of the rapidly released materials will form a ball of flame rising rapidly into the air and burning out in a short time. Vapour Cloud Explosion (VCE) When a flammable vapour cloud forms, disperses and accumulates in areas with high congestion or confinement, and is then ignited, a Vapour Cloud Explosion (VCE) may result. The plant will be divided into Potential Explosion Site (PES) based on the equipment layout and the Baker-Strehlow-Tang model will be used to model the overpressure generated at given distance from the PES.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-PH-
000-0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 6 OF 7
Toxic Gas Dispersion In case the released material is toxic and the cloud is dispersed without being ignited, it may cause toxic effects to exposed personnel. The aim of the toxic risk study is to determine whether the operators in the plant, people in occupied buildings and the public are likely to be affected by toxic substances. Toxic gas cloud e.g. EO Dispersion was undertaken to the Immediately Dangerous to Life and Health Concentration (IDLH) limit to determine the extent of the toxic hazard created as the result of loss of containment of a toxic substance.
5.3.4 Impact Assessment at Consequence End-Point Thermal Radiation The main hazard for jet fire, pool fire or fireball is personnel being exposed to the thermal radiation. While the fire scenario in this study is expected to last for some duration, the maximum exposure time to heat radiation is 20 seconds. The exception is fireballs which generally last less than 20s. In this case, the duration of the fireball is used as the exposure time. Refer Attachment -1 for damage criteria adopted for this study. Vapour Cloud Explosion (VCE) The primary cause for injuries or fatalities is damage to lung when expose to high overpressures. Refer Attachment -1 for damage criteria adopted for this study. Toxic Materials Refer Attachment -1 for damage criteria adopted for this study.
5.4 Risk Mitigation Measures Any mitigation measures will be recommended based on the result of the consequence analysis, towards minimization of risk identified in the study.
5.5 Guidelines for Disaster Management Plan (DMP) Based on the worst case identified in this study, guidelines for Disaster Management Plan (DMP) will be provided. IOCL to update the existing Disaster Management Plan (DMP) of Paradip Refinery.
6. DOCUMENTS REQUIRED The following documents will be required as input to the RA Study: Process Description
PFDs
Plot Plan, equipment and piping layout, and elevation drawings
ESD Philosophy
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-PH-
000-0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 7 OF 7
Fire Protection Philosophy
Engineering Design Datasheets for all plant items/equipment
Heat and Mass Balance
P&IDs
Material Safety Data Sheets (MSDS)
7. RA REPORT CONTENT The RA Report will contain the following sections: Executive Summary
Introduction
Project Site and Surroundings
Hazard Identification
Consequence Analysis
Conclusion and Recommendation (Risk Mitigation Measures)
Guidelines for Disaster Management Plan (DMP)
References
Annexures including RA Study Methodology & Assumptions, rule set and / or data sources, and Conclusion assessment results.
8. SOFTWARE
The RA will be conducted using the 6.7 version of DNV PHAST.
9. REFERENCE [1] Climatological Normals 1961-1990 by Indian Meteorogical Department [2] UK HSE, Application of RA in Operational Safety Issues, Det Norske Veritas Ltd,
2002 [3] OGP Risk Assessment Data Directory – Ignition Probabilities, Report No. 434-6,
International Association of Oil & Gas Producers, March 2010 [4] Cox A.W., Lees F.P., Ang M.L., (1990), Classification of Hazardous Locations,
IChemE, Rugby, UK [5] Woodward, J. L., Estimating the Flammable Mass of a Vapor Cloud, CCPS Concept
Book, AIChE [6] Lees, F.P., Loss Prevention in the Process Industries, Butterworth-Heinemann, 1996
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 1 OF 11
ATTACHMENT - 1
ASSUMPTIONS REGISTER
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 2 OF 11
Study Assumptions The table below presents the Summary of Assumptions intended to use in RA Study for the Scope as described in Section 2. Assumption Sheet Description
Study Basis
Assumption No. A1 Drawing and Documents
Software Tools
Assumption No: A2 Risk Analysis Tool
Hazard Identification
Assumption No: A3 Representative Hole Size
Assumption No: A4 Scenario Identification
Metrological Data
Assumption No: A5 Meteorological Data
Consequence Modelling
Assumption No: A6 Isolation Time & Release Direction
Assumption No: A7 Representative Process Parameters
Assumption No: A8 Physical Effect Modelling
Assumption No: A9 Impact Criteria
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 3 OF 11
STUDY BASIS
Assumption A1 Drawing and Documents
Following documents will be referred for conducting Risk Analysis
Sr. No.
Drawing / Document Title
1 Process Description
2 Process Flow Diagram
3 Heat & Mass Balance
4 Piping & instrumentation Diagrams
5 Equipment Datasheets
6 Loss Prevention Philosophy (PDRP4280-8150-PH-0004 Rev A2)
7 Risk Analysis Report (PDRP4280-8150-RP-0001 Rev A3)
8 Risk Analysis Report Addendum to Rev A3 (PDRP4280-8150-RP-0001 Rev A4 and A5)
9 Basic Engineering Design Data
10 Overall Site Plan (PDRP4200-8230-01-600-0001 Rev S1)
11 Equipment Layout
12 Material Safety Data sheet (MSDS)
Reference:
Sr. No. 6-8 Received from Owner vide mail 16.08.2016
RE 6351-IEGP Data Required for Risk Assessment & DMP .msg
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 4 OF 11
SOFTWARE
Assumption A2 Risk Analysis Tool
The PHAST Ver. 6.7 will be used for Consequence Modelling and Risk Modelling. The
Unified Dispersion Model (UDM) is respected as one of the world’s leading dispersion models
for Process Safety applications.
PHAST Ver. 6.7 models all stages of a release from outflow through a hole or from a pipe end,
through atmospheric dispersion to thermal radiation from fires and explosion overpressures.
The consequence outputs from PHAST Ver. 6.7 software are:
The dimensions of the jet fire in terms of jet length and thermal radiation effect distance;
The downwind distance to 100% Lower Flammable Limit (LFL);
Damage Contours in terms of Jet, Flash fire and Explosion; and
Explosion Overpressure
Reference:
1. PHAST Ver. 6.7 Technical Notes
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 5 OF 11
HAZARD IDENTIFICATION
Assumption A3 Representative Hole Size
Based on the OGP guidelines, the following hole sizes shall be considered for the RA study purpose.
Leak Type. Hazard Material Hole Size (mm)
Large Leak Flammable Release 50
Pin hole Leak Toxic Release 5
Reference:
1. The leak sizes considered for RA and consequence analysis are aligned with the leak sizes available in OGP Risk Assessment Data Directory - Report No. 434 (March 2010).
2. Risk Analysis Report (PDRP4280-8150-RP-0001 Rev A3)
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 6 OF 11
HAZARD IDENTIFICATION
Assumption No: A4 Scenario Identification
The definition of the isolatable sections boundaries is based on study of the PFDs and P&IDs.
The limits of the isolatable sections are defined and bounded by the location of the following:
Emergency Shutdown Valves (ESDVs);
Emergency Depressurization Valves (EDPVs);
Normally Closed valve with positive isolation;
Pressure Safety Valve (PSVs).
This identification step is based on a worst possible case or based on the maximum amount of
material within a process loop, or a worst possible (credible) case from a hazards review. The
purpose of short listing failure cases is to focus attention on those cases, which shall give a
realistic idea of worst case scenario consequences for similar incidents.
The sections containing non-hazardous material (such as water or air) are not considered in the
study.
It is essential to identify the scenario based on isolatable section approach. A worst possible
(credible) scenario will be selected based on vulnerable equipment and associated piping
system.
Reference:
1. CPR-18E-Guidelines for RA(Purple Book)
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 7 OF 11
METEOROLOGICAL DATA
Assumption No: A5 Meteorological Data
Weather Data: Following weather conditions will be considered for RA Study
Sr. No. Parameter Value
1
Ambient Temperature 22.4°C
2 Relative Humidity 80%
3 Surface Roughness Length 0.3 m
Wind Speed & Stability Class: Following wind speed & stability conditions will be considered for RA Study
Sr. No. Wind Speed (m/s) Pasquill Stability Category
4 3 D
5 5 D
Reference:
1. Sr. No. 1, 2, 4 & 5 - Risk Analysis Report (PDRP4280-8150-RP-0001 Rev A3)
2. Sr. No. 3 - Phast 6.7 Technical Notes
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 8 OF 11
CONSEQUENCE MODELLING
Assumption No: A6 Isolation Time & Release Direction
Release Duration:
The closing (isolation) time of the systems is based on the following considerations:
An automatic blocking system is a system where the detection of the leakage and closure of the blocking valves is fully automatic. There is no action of an operator required. The closing time of the blocking valve is 2 min.
A remote-controlled blocking system is a system where the detection of the leakage is fully automatic. The detection results in a signal in the control room. The operator validates the signal and closes the blocking valves using a switch in the control room. The closing time of the blocking valve is 10 min.
A hand-operated blocking system is a system where the detection of the leakage is fully automatic. The detection results in a signal in the control room. The operator validates the signal, goes to the location of the blocking valves and closes the valves by hand. The closing time of the blocking valve is 30 min.
This is the conservative approach considered for assessment rather than the actuals to study worst case effects (Purple book).
1 hour release duration will be considered for identified worst case and the same shall be used as an input for preparation of guideline for Disaster Management plan.
Release Direction:
As pipeline is aboveground, leak release orientation is considered in horizontal plane for estimating risk to personnel as conservative approach.
Release Height
The height of the outflow in relation to the surrounding area is determined by the location of the vessel or the pipeline. The height is equal to the location of the pipeline or the bottom of the vessel, given a minimum height of one meter. A height of 0 meters is only assumed for underground pipelines and vessels.
Release Inventory
Release inventory will be estimated based on the following equation: Release inventory = Initial release rate x Isolation time + Inventory of associated main equipment
(A) + Inventory of associated piping.
Reference:
1. CPR 18E, Guideline for quantitative risk assessment, Purple book
A2
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 9 OF 11
CONSEQUENCE MODELLING
Assumption No: A7 Representative Process Parameters
The material characterization such as Pressure, Temperature and Composition etc. for
each scenario shall be taken from Piping & Instrumentation Diagram, Process Flow
Diagram & Heat and mass balance.
To have more conservative approach, the condition such as maximum pressure and
minimum temperature stream in the section shall be taken into consideration.
Reference:
1. CPR 18E, Guideline for quantitative risk assessment, Purple book.
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 10 OF 11
CONSEQUENCE MODELLING Assumption No: A8 Physical Effect Modelling Depending on the type of release, the expected outcomes of consequence analysis are:
For gas & two-phase release under pressure:
Jet Fire
This outcome occurs following the immediate ignition of a flammable material, usually from a
pressurized source.
Flash Fire
Flash fires arise from delayed ignition of a well-mixed flammable gas/ vapor cloud in the
absence of significant confinement or obstruction. There are minimal overpressure effects and
primarily local impacts.
Vapor Cloud Explosion (VCE)
When a flammable vapor or gas mixes with air and its concentration lies between the lower
flammable limit (LFL) and upper flammable limit (UFL). An ignition source will ignite the mixture.
If this event takes place in a confined space then the enclosure usually suffers a significant
internal overpressure for a short duration.
Toxic Gas Dispersion
The results of toxic dispersion shall be analyzed and the distances for dispersion of toxic
components will be reported.
Boiling Liquid Expanding Vapor Explosion (BLEVE)
It results from the sudden failure of vessel containing liquid at a temperature well above its
normal (atmospheric) boiling point.
For liquid release:
Pool Fire
Pool fire will occur from an ignited liquid pool resulting from a liquid release.
Reference:
1. CPR 18E, Guideline for quantitative risk assessment, Purple book. 2. PHAST Risk v6.7 / 7.1 Release Notes
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-PH-000-
0013, Rev-A2
ISSUED : 28-Oct-2016 IEGP PAGE 11 OF 11
CONSEQUENCE MODELLING
Assumption No: A9 Impact Criteria
Thermal Radiation Following thermal radiation levels, are proposed to be set as thresholds
Radiation Level (kW/m2) Impact
4.0 Sufficient to cause pain to personnel if unable to reach cover within 20 seconds, however, blistering of skin (1st degree burn) is likely
12.5 Minimum energy required for piloted ignition of wood, melting of plastic etc.
37.5 Sufficient to cause damage to process equipment
Explosion Radiation Following explosion overpressure levels, are considered to be set as thresholds
Overpressure Level (barg) Impact
0.3 Wooden utility poles snapped; tall hydraulic pressure in building, slightly damaged
0.1 Steel frame of clad building slightly distorted
0.03 Limited minor structural damage
For the study TNT model of PHAST 6.7 will be used.
Toxic Release For toxic release, IDLH limit will be used to determine the extent of the toxic hazard created as
the result of loss of containment of a toxic substance. The IDLH values were taken from NIOSH
Chemical Listing and Documentation of Revised IDLH Values 2009.
Sr. No. Substance IDLH (ppm) Institute
1 Ethylene Oxide (EO) 800 NIOSH
Reference: 1. Tender Document - RHQCC15138 Pg. 90 / 194 & 91 / 194 2. Risk Analysis Report (Doc. No.: PDRP4280-8150-RP-0001 Rev A4) 3. OGP Risk Assessment Data Directory, Vulnerability of Humans, Report no. 434-14.1,
434-15 March 2010 4. Methods of the determination of possible damage, “Green Book”, CPR 16E, TNO 1992
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE B1 OF B5
ATTACHMENT - B
CONSEQUENCE ANALYSIS RESULTS
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE B2 OF B5
Unit Cases Failure Case
Operating Conditions
State Release
Rate kg/s
Weather Flash Fire (m)
Jet Fire (m) / Fire Ball Pool Fire (m) Blast Over Pressure (m)
IDLH Conc.
Distance (m)
NOTE Temp (OC)
Press. (kg/cm2g)
4 kW/m2
12.5 kW/m2
37.5 kW/m2
4 kW/m
2
12.5 kW/m2
37.5 kW/m2
0.03 bar
0.1 bar 0.3 bar
ER
ER1 DGA/Water wash tower overhead line instrument tapping failure 40 13.1 V 4.7
3D 18 36 29 24 - - - 30 19 14
5D 17 36 30 25 - - - 30 19 14
ER2 DGA Reflux drum overhead line pin hole leak 98 1.5 V 0.01
3D - - - - - - - - - - 16 Toxic release - H2S
5D - - - - - - - - - - 10
ER3 Caustic / Water Wash Tower overhead line instrument tapping failure 54.8 11.30 V 3.99 3D 16 33 27 22 - - - 29 18 14
5D 15 33 28 23 - - - 29 18 14
ER4 FCC Off gas Oxygen Converter outlet line flange gasket leak 266 10.40 V 2.79
3D 12 28 22 18 - - - 27 17 13
5D 11 28 23 19 - - - 26 17 13
ER5 Process off gas line from C-101 to Dryer feed KOD flange leakage 55 9.90 V 3.54
3D 15 31 25 20 - - - 29 18 14
5D 14 31 26 21 - - - 28 18 14
ER6 Mercury Absorber Effluent filter flange gasket leak 16 9.00 V 3.48
3D 15 31 25 20 - - - 29 18 14
5D 14 31 26 21 - - - 28 18 14
ER7 Regeneration gas line instrument tapping failure 300 6.90 V 1.6
3D 7 21 17 8 - - - - - -
5D 7 21 17 NR - - - - - -
ER8 Demethanizer Bottoms Pumps seal failure -43 8.4 L .15 3D 3 8 7 5 - - - - - -
5D 3 8 6 5 - - - - - -
ER9 Demethanizer Intercooler Circulation pump seal failure -84.7 9.50 L 0.23
3D 4 8 NR NR - - - - - -
5D 4 8 NR NR - - - - - -
ER10 Deethylenizer overhead line instrument tapping failure -33.5 16.90 V 7.67 3D 52 57 46 39 - - - 107 75 62 5D 52 54 42 35 - - - 105 74 62
ER11 Ethylene Product pump seal failure -31.7 45.50 L 3.13 3D 26 37 30 25 - - - 51 33 26
5D 24 35 28 23 - - - 49 32 26
ER12 Deethylenizer bottom line flange gasket leak 51.4 17.60 L 9.11
3D 30 53 42 33 - - - 70 47 38
5D 29 29 14 12 - - - 55 35 27
ER13 Catastrophic rupture of Deethylenizer Reflux Drum -35 16.20 L -
3D 64 350 186 67 - - - 493 227 131
5D 100 350 186 67 - - - 497 230 142
ER14 Catastrophic Rupture of Light Binary Refrigerant Accumulator -1 25.10 L -
3D 19 178 94 34 - - - 182 83 47
5D 24 178 94 34 - - - 207 100 60
ER15 Binary Refrigerant Compressor discharge instrument tapping failure 84 27.40 V 11.8
3D 36 58 46 36 - - - 74 49 39
5D 35 59 47 38 - - - 73 49 39
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE B3 OF B5
Unit Cases Failure Case
Operating Conditions
State Release
Rate kg/s
Weather Flash Fire (m)
Jet Fire (m) Pool Fire (m) Blast Over Pressure (m) IDLH
Conc. Distance
(m)
NOTE Temp (OC)
Press. (kg/cm2g) 4 kW/m2
12.5 kW/m2
37.5 kW/m2
4 kW/m2
12.5 kW/m2
37.5 kW/m2
0.03 bar
0.1 bar
0.3 bar
EG
EG1 Ethylene Filter flange gasket leak 35 25.00 V 10.45 3D 41 55 44 35 - - - 88 61 50 - 5D 40 55 45 36 - - - 87 60 50 -
EG2 Reactor Feed line instrument tapping failure 57 21.37 V 8.30 3D 7 38 30 NR - - - - - -
5D 7 39 32 NR - - - - - -
EG3 Reactor outlet line flange gasket leak 90 19.33 V 7.15 3D 6 35 28 10 - - - - - - - 5D 6 36 29 12 - - - - - - -
EG4 Recycle Compressor instrument tapping failure 41 21.52 V 8.59 3D 6.8 37.5 30 13 - - - - - - -
5D 6.5 38.5 31 14 - - - - - - -
EG5 Ballast line flange gasket leak 45 25 V 7.46 3D 27 49 39 31 - - - 54 34 27 - 5D 26 49 39 32 - - - 53 34 27 -
EG6 Acid Scrubber outlet flange gasket leakage 51 0.28 L 0.36
3D 4 11 NR NR - - - - - - 96 Toxic release - EO
5D 4 12 NR NR - - - - - - 67
EG7 Pin hole leak at inlet of Stripping Column condenser (Toxic Release) 97 0.48 L 0.38
3D 2 9 NR NR - - - - - - 71 Toxic release - EO
5D 2 10 NR NR - - - - - - 59
EG8 Flange gasket leak in Reclaim Compressor discharge 127 23.00 V 8.3 3D 12 41 33 24 - - - 26 17 13 -
5D 11 42 34 26 - - - 26 17 13 -
EG9 Glycol Feed Stripper Overhead line instrument tapping failure 51 0.28 L 0.36
3D 4 11 NR NR - - - - - - 96 Toxic release - EO
5D 3..5 12 10 NR - - - - - - 67
EG10 Concentrated Glycol Pump seal failure 91 0.29 L 0.87 3D 4 11 9 NR 44 21 NR - - - - 5D 4 10 8 NR 46 22 NR - - - -
EG11 Drying Column Bottoms Pump seal failure 162 0.17 L 0.35 3D 2 4 NR NR 34 20 11 - - - - 5D 2 4 NR NR 35 23 11 - - - -
EG12 50 mm hole on MEG Column overhead line
139
0.18 L 0.32 3D 3 9 NR NR - - - - - - -
5D 2 11 NR NR - - - - - - -
EG13 MEG Column Bottoms Pump seal failure 164 0.50 L 0.53 3D 3 8 7 NR 40 21 NR - - - - 5D 3 7 5 19 41 23 NR - - - -
EG14 MEG Product Transfer Pump seal failure 48 5.50 L 1.8 3D 7 2 NR NR 58 28 NR - - - 5D 7 2 NR NR 61 29 NR - - -
EG15 MEG Splitter Bottoms Pump discharge instrument tapping failure 175 7.45 L 51.1 3D 22 43 35 29 97 54 NR 48 32 26 5D 22 39 31 25 103 55 NR 48 32 26
EG16 DEG Column Bottoms Pump seal failure 178 6.60 L 1.92 3D 10 7 6 6 64 32 NR - - - -
5D 11 8 6 5 68 34 NR 18 14 12 -
EG17 DEG Product Transfer Pump discharge instrument tapping failure 55 5 L 16.21
3D 13.5 3.13 NR NR 50.29 31.49 NR NR NR NR -
5D 13.5 2.96 NR NR 51.38 33.14 NR NR NR NR -
EG18 TEG Product Transfer pump discharge instrument tapping failure 164 5 L 39.6
3D 15.4 26.6 21 17.36 42.5 32.7 22.6 17.8 13.3 11.6 - 5D 15.5 24.4 19.0 15.58 43.3 34.1 22.7 18.4 13.6 11.8 -
EG19 Moderator Feed Drum line rupture 40 23.5 L 64.7 3D 11.7 79 64 52 173 87 38 15 12 11 -
5D 11.7 75 60 50 186 101 41 15 12 11 -
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE B4 OF B5
Unit Cases Failure Case
Operating Conditions
State Release
Rate kg/s
Weather Flash Fire (m)
Jet Fire (m)/Fire Ball Pool Fire (m) Blast Over Pressure (m)
IDLH Conc.
Distance (m)
NOTE Temp (OC)
Press. (kg/cm2g)
4 kW/m2
12.5 kW/m2
37.5 kW/m2
4 kW/m2
12.5 kW/m2
37.5 kW/m2
0.03 bar
0.1 bar
0.3 bar
O&U
OU1 Flange gasket failure at the outlet of ethylene sphere -31.7 18 L 8.9
3D 41 55 44 38 - - - 88 61 50 -
5D 40 52 41 34 - - - 87 60 50 -
OU2 Flange gasket leak at BOG Package -31.3 18 V 8.89 3D 41 55 44 38 - - - 88 61 50 -
5D 40 52 41 34 - - - 87 60 50 -
OU3 Ethylene Product Transfer Pump seal failure -31.7 29 L 2.55
3D 23 34 27 23 - - - 48 32 26 - 5D 20 32 25 21 - - - 46 31 25 -
OU4 Ethylene Vaporizer outlet line instrument tapping failure 40 27 L 11.38
3D 43 58 45 36 - - - 91 62 51 - 5D 43 58 46 37 - - - 89 61 50 -
OU5 Catastrophic rupture of Ethylene Sphere -31.7 18 L - 3D 433 1840 1007 395 - - - 2657 1133 566 - 5D 680 1840 1007 395 - - - 2657 1133 566 -
OU6 MEG Product Transfer pump seal leak 48 Atm L 0.2 3D 2 NR NR NR 30 19 9 - - - - 5D 2 NR NR NR 31 21 9 - - - -
OU7 Ship Loading pump discharge flange gasket leak 48 3.25 L 34.5
3D 10 7 6 NR 183 96 NR 12 11 10 - 5D 10 6 6 NR 193 97 NR 13 11 10 -
OU8 MEG Truck loading arm leak 48 1.5 L 23.4 3D 7 3.6 NR NR 115 56 NR - - - - 5D 7 3.4 NR NR 121 57 NR - - - -
OU9 MEG Tank on Fire 48 Atm L - 3D 27 - - - 40 18 NR 44 30 25 - 5D 28 - - - 42 19 NR 48 32 26 -
OU10 DEG Product Transfer pump seal leak 48 Atm L 0.1 3D 1 NR NR NR 23 16 7 - - - - 5D 1 NR NR NR 24 17 7 - - - -
OU11 DEG Truck loading arm leak 48 1.5 L 28.3 3D 9 NR NR NR 97 47 NR - - - - 5D 9 NR NR NR 103 49 NR - - - -
OU12 DEG Tank on Fire 48 Atm L - 3D 31 - - - 330 187 NR 38 33 32 - 5D 29 - - - 350 188 NR 29 24 22 -
OU13 TEG Product Transfer pump seal leak 48 Atm L 0.1 3D 1 NR NR NR 23 16 7 - - - - 5D 1 NR NR NR 24 17 7 - - - -
OU14 TEG Truck loading arm leak 48 1.5 L 28.4 3D 9 NR NR NR 98 47 NR - - - - 5D 9 NR NR NR 103 48 NR - - - -
OU15 TEG Tank on Fire 48 Atm L - 3D 16 - - - 158 78 NR 12 11 10 - 5D 15 - - - 165 76 NR 12 11 10 -
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE B5 OF B5
Cases Failure Case
Operating Conditions
State Release
Rate kg/s
Weather Flash Fire (m)
Jet Fire (m) Pool Fire (m) Blast Over Pressure (m)
IDLH Conc.
Distance (m)
NOTE Temp (OC)
Press. (kg/cm2g)
4 kW/m2
12.5 kW/m2
37.5 kW/m2
4 kW/m2
12.5 kW/m2
37.5 kW/m2
0.03 bar
0.1 bar
0.3 bar
CC1
C3+ Product header from ERU to PRU
rupture
40 16.5 L 49.1
3D 14 28 20 NR - - - 30 18 14 -
5D 13 26 18 11 - - - 28 18 14 -
CC2
50 mm hole on Fuel Gas header from
ERU to Refinery fuel gas system
40 12.1 V 4.38
3D 16 34 24 NR - - - 30 18 14 -
5D 15 34 25 NR - - - 29 18 14 -
CC3 50 mm hole on Refinery Off gas header
from FCC to ERU 40 4 V 1.46 3D 8 16 NR NR - - - - - - -
5D 8 16 NR NR - - - - - - -
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C1 OF C148
ATTACHMENT - C
CONSEQUENCE ANALYSIS HAZARD CONTOURS
<Security Level 2>
TOYO ENGINEERING INDIA
PVT. LTD.
RA METHODOLOGY & ASSUMPTIONS
DOC NO. : IEGP-6351-8110-RA-
000-0001, Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C2 OF C148
Figures shown below are the worst case distances out of two weather condition i.e. farthest hazard
distances (for flash fire, jet fire, pool fire, overpressure, toxic dispersion) are reported out of
weather condition 3D and 5D.
The distances for hazard outcomes are shown in Annexure –B.
Ethylene Recovery Unit (ER): Figure C1.1 through C1.40
Ethylene Glycol Unit (EG): Figure C2.1 through C2.57
Offsite & Utilities Facility: Figure C3.1 through C3.41
Client Cases: Figure C4.1 through C4.8
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C3 OF C148
Figure C1.1: Case - ER1- DGA/Water Wash tower overhead line instrument tapping failure - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C4 OF C148
Figure C1.2: Case - ER1- DGA/Water Wash tower overhead line instrument tapping failure - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C5 OF C148
Figure C1.3: Case - ER1- DGA/Water Wash tower overhead line instrument tapping failure - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C6 OF C148
Figure C1.4: Case – ER2 – DGA Reflux drum overhead line pin hole leak – Toxic substance (H2S) release contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C7 OF C148
Figure C1.5: Case – ER3 –Caustic/Water Wash tower overhead line instrument tapping failure - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C8 OF C148
Figure C1.6: Case – ER3 –Caustic/Water Wash tower overhead line instrument tapping failure – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C9 OF C148
Figure C1.7: Case – ER3 –Caustic/Water Wash tower overhead line instrument tapping failure - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C10 OF C148
Figure C1.8: Case – ER4 – FCC Off-gas Oxygen Converter outlet line flange gasket leak - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C11 OF C148
Figure C1.9: Case – ER4 – FCC Off-gas Oxygen Converter outlet line flange gasket leak – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C12 OF C148
Figure C1.10: Case – ER4 – FCC Off-gas Oxygen Converter outlet line flange gasket leak – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C13 OF C148
Figure C1.11: Case – ER5 – Process off gas line from C-101 to Dryer Feed KOD flange gasket leakage - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C14 OF C148
Figure C1.12: Case – ER5 – Process off gas line from C-101 to Dryer Feed KOD flange gasket leakage – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C15 OF C148
Figure C1.13: Case – ER5 – Process off gas line from C-101 to Dryer Feed KOD flange gasket leakage – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C16 OF C148
Figure C1.14: Case – ER6 – Mercury Absorber Effluent Filter flange gasket leakage - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C17 OF C148
Figure C1.15: Case – ER6 – Mercury Absorber Effluent Filter flange gasket leakage – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C18 OF C148
Figure C1.16: Case – ER6 – Mercury Absorber Effluent Filter flange gasket leakage - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C19 OF C148
Figure C1.17: Case – ER7 – Regeneration gas line instrument tapping failure - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C20 OF C148
Figure C1.18: Case – ER7 – Regeneration gas line instrument tapping failure - Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C21 OF C148
Figure C1.19: Case – ER8 –Demethanizer Bottoms pump seal failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C22 OF C148
Figure C1.20: Case – ER8 –Demethanizer Bottoms pump seal failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C23 OF C148
Figure C1.21: Case – ER9 –Demethanizer Intercooler Circulation pump seal failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C24 OF C148
Figure C1.22: Case – ER9 –Demethanizer Intercooler Circulation pump seal failure –Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C25 OF C148
Figure C1.23: Case – ER10 –Deethylenizer Overhead line instrument tapping failure – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C26 OF C148
Figure C1.24: Case – ER10 –Deethylenizer Overhead line instrument tapping failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C27 OF C148
Figure C1.25: Case – ER10 –Deethylenizer Overhead line instrument tapping failure – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C28 OF C148
Figure C1.26: Case – ER11 – Ethylene Product Pump seal failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C29 OF C148
Figure C1.27: Case – ER11 – Ethylene Product Pump seal failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C30 OF C148
Figure C1.28: Case – ER11 – Ethylene Product Pump seal failure – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C31 OF C148
Figure C1.29: Case – ER12 – Deethylenizer Bottom line flange gasket leak – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C32 OF C148
Figure C1.30: Case – ER12 – Deethylenizer Bottom line flange gasket leak – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C33 OF C148
Figure C1.31: Case – ER12 – Deethylenizer Bottom line flange gasket leak –Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C34 OF C148
Figure C1.32: Case – ER13 – Catastrophic rupture of Deethylenizer Reflux Drum – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C35 OF C148
Figure C1.33: Case – ER13 – Catastrophic rupture of Deethylenizer Reflux Drum – Fire Ball contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C36 OF C148
Figure C1.34: Case – ER13 – Catastrophic rupture of Deethylenizer Reflux Drum – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C37 OF C148
Figure C1.35: Case – ER14 – Catastrophic rupture of Light Binary Refrigerant Accumulator – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C38 OF C148
Figure C1.36: Case – ER14 – Catastrophic rupture of Light Binary Refrigerant Accumulator –Fire Ball contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C39 OF C148
Figure C1.37: Case – ER14 – Catastrophic rupture of Light Binary Refrigerant Accumulator – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C40 OF C148
Figure C1.38: Case – ER15 – Binary Refrigerant Compressor discharge instrument tapping failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C41 OF C148
Figure C1.39: Case – ER15 – Binary Refrigerant Compressor discharge instrument tapping failure – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C42 OF C148
Figure C1.40: Case – ER15 – Binary Refrigerant Compressor discharge instrument tapping failure – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C43 OF C148
Figure C2.1: Case - EG1- Ethylene Filter flange gasket leak - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C44 OF C148
Figure C2.2: Case - EG1- Ethylene Filter flange gasket leak - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C45 OF C148
Figure C2.3: Case - EG1- Ethylene Filter flange gasket leak - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C46 OF C148
Figure C2.4: Case – EG2- Reactor Feed line instrument tapping failure - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C47 OF C148
Figure C2.5: Case – EG2- Reactor Feed line instrument tapping failure - Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C48 OF C148
Figure C2.6: Case – EG3 - Reactor outlet line flange gasket leak - Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C49 OF C148
Figure C2.7: Case – EG3 - Reactor outlet line flange gasket leak - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C50 OF C148
Figure C2.8: Case – EG4 – Recycle Compressor Instrument tapping failure - Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C51 OF C148
Figure C2.9: Case – EG4 – Recycle Compressor Instrument tapping failure - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C52 OF C148
Figure C2.10: Case – EG5 – Ballast line flange gasket leak - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C53 OF C148
Figure C2.11: Case – EG5 – Ballast line flange gasket leak - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C54 OF C148
Figure C2.12: Case – EG5 – Ballast line flange gasket leak - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C55 OF C148
Figure C2.13: Case – EG5 – Ballast line flange gasket leak - Fireball contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C56 OF C148
Figure C2.14: Case – EG6 – Acid Scrubber outlet flange gasket leak - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C57 OF C148
Figure C2.15: Case – EG6 – Acid Scrubber outlet flange gasket leak - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C58 OF C148
Figure C2.16: Case – EG6 – Acid Scrubber outlet flange gasket leak - Toxic Gas (IDLG-EO) contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C59 OF C148
Figure C2.17: Case – EG7 – Pin hole leak at inlet of Stripping Column Condenser - Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C60 OF C148
Figure C2.18: Case – EG7 – Pin hole leak at inlet of Stripping Column Condenser - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C61 OF C148
Figure C2.19: Case – EG7 – Pin hole leak at inlet of Stripping Column Condenser – Toxic Gas (O-IDLH) contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C62 OF C148
Figure C2.20: Case – EG8 – Flange gasket leak in Reclaim Compressor discharge- Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C63 OF C148
Figure C2.21: Case – EG8 – Flange gasket leak in Reclaim Compressor discharge - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C64 OF C148
Figure C2.22: Case – EG8 – Flange gasket leak in Reclaim Compressor discharge – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C65 OF C148
Figure C2.23: Case – EG9 –Glycol Feed Stripper Overhead line instrument tapping failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C66 OF C148
Figure C2.24: Case – EG9 –Glycol Feed Stripper Overhead line instrument tapping failure – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C67 OF C148
Figure C2.25: Case - EG9 - Glycol Feed Stripper Overhead line instrument tapping failure - Toxic Gas (EO-IDLH) contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C68 OF C148
Figure C2.26: Case - EG10 – Concentrated Glycol Pump seal failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C69 OF C148
Figure C2.27: Case - EG10 – Concentrated Glycol Pump seal failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C70 OF C148
Figure C2.28: Case - EG10 – Concentrated Glycol Pump seal failure – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C71 OF C148
Figure C2.29: Case - EG11 – Drying Column Bottoms Pump seal failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C72 OF C148
Figure C2.30: Case - EG11 – Drying Column Bottoms Pump seal failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C73 OF C148
Figure C2.31: Case - EG11 – Drying Column Bottoms Pump seal failure – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C74 OF C148
Figure C2.32: Case - EG12 – 50 mm hole on MEG Column overhead line – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C75 OF C148
Figure C2.33: Case - EG12 – 50 mm hole on MEG Column overhead line – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C76 OF C148
Figure C2.34: Case - EG13 – MEG Column Bottoms Pump seal failure - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C77 OF C148
Figure C2.35: Case - EG13 – MEG Column Bottoms Pump seal failure - Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C78 OF C148
Figure C2.36: Case - EG13 – MEG Column Bottoms Pump seal failure - Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C79 OF C148
Figure C2.37: Case - EG14 - MEG Product Transfer Pump seal failure - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C80 OF C148
Figure C2.38: Case - EG14 - MEG Product Transfer Pump seal failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C81 OF C148
Figure C2.39: Case - EG14 - MEG Product Transfer Pump seal failure – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C82 OF C148
Figure C2.40: Case - EG15 - MEG Splitter Bottom Pump seal failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C83 OF C148
Figure C2.41: Case - EG15 - MEG Splitter Bottom Pump seal failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C84 OF C148
Figure C2.24: Case - EG15 - MEG Splitter Bottom Pump seal failure - Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C85 OF C148
Figure C2.43: Case - EG15 - MEG Splitter Bottom Pump seal failure - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C86 OF C148
Figure C2.44: Case - EG16 - DEG Column Bottom Pump seal failure – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C87 OF C148
Figure C2.45: Case - EG16 - DEG Column Bottom Pump seal failure – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C88 OF C148
Figure C2.46: Case - EG16 - DEG Column Bottom Pump seal failure –Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C89 OF C148
Figure C2.47: Case - EG16 - DEG Column Bottom Pump seal failure – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C90 OF C148
Figure C2.48: Case - EG17 - DEG Product Transfer Pump discharge instrument tapping failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C91 OF C148
Figure C2.49: Case - EG17 - DEG Product Transfer Pump discharge instrument tapping failure – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C92 OF C148
Figure C2.50: Case - EG18 - TEG Product Transfer Pump discharge instrument tapping failure – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C93 OF C148
Figure C2.51: Case - EG18 - TEG Product Transfer Pump discharge instrument tapping failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C94 OF C148
Figure C2.52: Case - EG18 - TEG Product Transfer Pump discharge instrument tapping failure – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C95 OF C148
Figure C2.53: Case - EG18 - TEG Product Transfer Pump discharge instrument tapping failure –Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C96 OF C148
Figure C2.54: Case - EG19 – Moderator Feed Drum line rupture – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C97 OF C148
Figure C2.55: Case - EG19 – Moderator Feed Drum line rupture – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C98 OF C148
Figure C2.56: Case - EG19 – Moderator Feed Drum line rupture – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C99 OF C148
Figure C2.57: Case - EG19 – Moderator Feed Drum line rupture – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C100 OF C148
Figure C3.1: Case - OU1 - Flange gasket failure at the outlet of ethylene sphere - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C101 OF C148
Figure C3.2: Case - OU1 - Flange gasket failure at the outlet of ethylene sphere - Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C102 OF C148
Figure C3.3: Case - OU1 - Flange gasket failure at the outlet of ethylene sphere - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C103 OF C148
Figure C3.4: Case – OU2 - Flange gasket leak at BOG Package – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C104 OF C148
Figure C3.5: Case – OU2 - Flange gasket leak at BOG Package –Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C105 OF C148
Figure C3.6: Case – OU2 - Flange gasket leak at BOG Package – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C106 OF C148
Figure C3.7: Case – OU3 – Ethylene Product Transfer Pump Seal failure – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C107 OF C148
Figure C3.8: Case – OU3 - Ethylene Product Transfer Pump Seal failure – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C108 OF C148
Figure C3.9: Case – OU3 – Ethylene Product Transfer Pump Seal failure – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C109 OF C148
Figure C3.10: Case – OU4 – Ethylene Vaporizer outlet line instrument tapping failure – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C110 OF C148
Figure C3.11: Case – OU4 – Ethylene Vaporizer outlet line instrument tapping failure – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C111 OF C148
Figure C3.12: Case – OU4 – Ethylene Vaporizer outlet line instrument tapping failure – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C112 OF C148
Figure C3.13: Case – OU5 – Catastrophic rupture of Ethylene Storage Sphere – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C113 OF C148
Figure C3.14: Case – OU5 – Catastrophic rupture of Ethylene Storage Sphere – Fireball contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C114 OF C148
Figure C3.15: Case – OU5 – Catastrophic rupture of Ethylene Storage Sphere – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C115 OF C148
Figure C3.16: Case – OU6 – MEG Product Transfer Pump Seal leak – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C116 OF C148
Figure C3.17: Case – OU6 – MEG Product Transfer Pump Seal leak – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C117 OF C148
Figure C3.18: Case – OU7 – Ship loading pump discharge flange gasket leak – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C118 OF C148
Figure C3.19: Case – OU7 – Ship loading pump discharge flange gasket leak – Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C119 OF C148
Figure C3.20: Case – OU7 – Ship loading pump discharge flange gasket leak – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C120 OF C148
Figure C3.21: Case – OU7 – Ship loading pump discharge flange gasket leak – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C121 OF C148
Figure C3.22: Case – OU8 – Truck loading arm leak – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C122 OF C148
Figure C3.23: Case – OU8 – Truck loading arm leak – Jet Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C123 OF C148
Figure C3.24: Case – OU8 – Truck loading arm leak – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C124 OF C148
Figure C3.25: Case – OU9 – MEG Tank on Fire – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C125 OF C148
Figure C3.26: Case – OU9 – MEG Tank on Fire – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C126 OF C148
Figure C3.27: Case – OU9 – MEG Tank on Fire – Overpressure contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C127 OF C148
Figure C3.28: Case – OU10 – DEG Product Transfer pump seal leak – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C128 OF C148
Figure C3.29: Case – OU10 – DEG Product Transfer pump seal leak – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C129 OF C148
Figure C3.30: Case – OU11 – DEG Loading arm leak – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C130 OF C148
Figure C3.31: Case – OU11 – DEG Loading arm leak – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C131 OF C148
Figure C3.32: Case – OU12 – DEG Tank on fire – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C132 OF C148
Figure C3.33: Case – OU12 – DEG Tank on fire – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C133 OF C148
Figure C3.34: Case – OU12 – DEG Tank on fire – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C134 OF C148
Figure C3.35: Case – OU13 – TEG Product Transfer pump seal leak – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C135 OF C148
Figure C3.36: Case – OU13 – TEG Product Transfer pump seal leak – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C136 OF C148
Figure C3.37: Case – OU14 – TEG Loading arm leak – Flash Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C137 OF C148
Figure C3.38: Case – OU14 – TEG Loading arm leak – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C138 OF C148
Figure C3.39: Case – OU15 – TEG Tank on fire – Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C139 OF C148
Figure C3.40: Case – OU15 – TEG Tank on fire – Pool Fire contour (Weather Condition 5D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C140 OF C148
Figure C3.41: Case – OU15 – TEG Tank on fire – Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C141 OF C148
Figure C4.1: Case – CC1 – C3+ Product header from ERU to PRU rupture - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C142 OF C148
Figure C4.2: Case – CC1 – C3+ Product header from ERU to PRU rupture - Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C143 OF C148
Figure C4.3: Case – CC1 – C3+ Product header from ERU to PRU rupture - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C144 OF C148
Figure C4.4: Case – CC2 - 50 mm hole on Fuel Gas header from ERU to Refinery fuel gas system - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C145 OF C148
Figure C4.5: Case – CC2 - 50 mm hole on Fuel Gas header from ERU to Refinery fuel gas system - Jet Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C146 OF C148
Figure C4.6: Case – CC2 - 50 mm hole on Fuel Gas header from ERU to Refinery fuel gas system - Overpressure contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C147 OF C148
Figure C4.7: Case – CC3 - 50 mm hole on Refinery Off gas header from FCC to ERU - Flash Fire contour (Weather Condition 3D)
<Security Level 2>
TOYO ENGINEERING INDIA PVT. LTD.
RA STUDY REPORT
DOC NO. : IEGP-6351-8110-RA-000-0001,
Rev-I3
ISSUED : 21-Aug-2017 IEGP PAGE C148 OF C148
Figure C4.8: Case – CC3 - 50 mm hole on Refinery Off gas header from FCC to ERU - Jet Fire contour (Weather Condition 3D)
Report: U1804-Rev01
Revision: A
Date: 16/02/2018
Use of this document is subject to the confidentiality provisions and intellectual property rights in the terms and conditions applicable to the contract under which it was produced.
Rapid Risk Assessment Report
Rapid Risk Assessment Study for BS VI – IOCL Paradip
EPC Works for Paradip Refinery Compliant
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 2 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Project / Facility: Rapid Risk Assessment Study for BS VI – IOCL Paradip
Study: Rapid Risk Assessment Report
Doc. No: U1804-Rev01
Revision: A
Issue Date: 16.02.2018
Prepared for: IOCL Paradeep
Prepared by: Bell Engineering Software Technologist LTD, Abu Dhabi.
Rev Date Issue Prepared by Reviewed by Approved by
A 16.02.2018 Issued for Review
Kenny Loh C G Kulkarni
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 3 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Table of Contents Abbreviations ............................................................................................................................................. 6
1 Introduction........................................................................................................................................... 8
1.1 Background .................................................................................................................................. 8
1.2 Purpose of RRA ........................................................................................................................... 8
1.3 Project Description ....................................................................................................................... 8
2 Project Description ............................................................................................................................. 11
2.1 Process Description of DHDT Unit ............................................................................................. 11
2.2 Process Description of HGU Unit ............................................................................................... 12
2.3 Process Description of IGHDS Unit ........................................................................................... 12
2.3.1 Selective Hydrogenation Section (SHU): ................................................................................... 12
2.3.2 LCN and MCN Splitters Section: ................................................................................................ 13
2.3.3 Selective HCN HDS Section – 1 stage HDS scheme: ............................................................... 13
2.3.4 Selective MCN HDS Section – 1 stage HDS scheme: .............................................................. 13
2.3.5 HCN and MCN Stabilizer Sections: ........................................................................................... 13
2.4 Process Description of ISOM Unit ............................................................................................. 14
2.5 Process Description of KHDS Unit ............................................................................................. 15
3 Types of Risk ..................................................................................................................................... 16
3.1 Flammable Gas Dispersion ........................................................................................................ 16
3.2 Flash Fire ................................................................................................................................... 16
3.3 Vapor Cloud Explosion ............................................................................................................... 16
3.4 Jet Fire ....................................................................................................................................... 16
3.5 Pool Fire. .................................................................................................................................... 16
3.5.1 Surface Fire ........................................................................................................................ 16
3.5.2 Bund Fire. ........................................................................................................................... 16
4 Methodology Adapted ........................................................................................................................ 17
5 Considerations for Disaster Management Plan. ................................................................................ 18
6 Hazards Identification ......................................................................................................................... 19
7 Risk Acceptance Criteria. ................................................................................................................... 20
8 Assumptions and Study Basis ........................................................................................................... 21
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 4 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
8.1 Following assumptions and basis of study were made : ............................................................ 21
8.2 Meteorological data. ................................................................................................................... 22
Wind 22
9 Conclusions and Recommendations ................................................................................................. 24
Annexure ................................................................................................................................................... 25
ISO Risk Contour od DHDT unit. ........................................................................................................... 25
ISO Risk Contour of IGDHS unit. ........................................................................................................... 25
ISO Risk Contour of KHDS .................................................................................................................... 26
ISO Risk Contour of HGU ...................................................................................................................... 26
ISO Risk Contour of ISOM ..................................................................................................................... 27
Combined ISO Risk Contour .................................................................................................................. 27
List of Figures Figure 1-1 – Overall Plot Plan .................................................................................................................... 10
Figure 1-2 – Overall Plot Plan .................................................................................................................... 10
Figure 7-1 – Risk Acceptance Criteria ....................................................................................................... 20
Figure 9-1 - ISO Risk Contour of DHDT unit.............................................................................................. 25
Figure 9-2 - ISO Risk Contour of IGDHS unit. ........................................................................................... 25
Figure 9-3 - ISO Risk Contour of KHDS .................................................................................................... 26
Figure 9-4 - ISO Risk Contour of HGU ...................................................................................................... 26
Figure 9-5 - ISO Risk Contour of ISOM ..................................................................................................... 27
Figure 9-6 - Combined ISO Risk Contour .................................................................................................. 27
Figure 9-70 – Radiation on a Plane for Pool Fire for IGHDS tank ............................................................. 28
Figure 9-8 – Radiation on a Plane for Pool Fire for IGHDS tank ............................................................... 28
Figure 9-9 - Radiation on a Plane for Pool Fire for IGHDS tank ................................................................ 29
Figure 9-10 - Radiation on a Plane for Pool Fire for ISOM tank ................................................................ 29
Figure 9-11 - Radiation on a Plane for Pool Fire for ISOM tank ................................................................ 30
Figure 9-12 - Radiation on a Plane for Pool Fire for ISOM tank ................................................................ 30
Figure 9-13 - Radiation on a Plane for Pool Fire for ISOM tank (203-TK-046/047) .................................. 30
Figure 9-14 - Radiation on a Plane for Pool Fire for ISOM tank (203-TK-046/047) .................................. 31
Figure 9-15 - Radiation on a Plane for Pool Fire for ISOM tank (203-TK-046/047) .................................. 31
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 5 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Figure 9-16 - Radiation on a Plane for Pool Fire for ISOM tank 203-TK-018-019_BS-VI HGU FEED
TANK .......................................................................................................................................................... 31
Figure 9-17 - Radiation on a Plane for Pool Fire for ISOM tank 203-TK-018-019_BS-VI HGU FEED
TANK .......................................................................................................................................................... 32
Figure 9-18 - 700 ppm of H2S due to 250 mm leak is not reaching beyond boundary limits of IOCL. ..... 34
List of Tables Table 1-1 – Details of Units with Capacities ................................................................................................ 8
Table 2-1 - Equipment Modification Details ............................................................................................... 11
Table 4-1 - Unit wise type of Risk .............................................................................................................. 19
Table 5-1 - Wind Velocity ........................................................................................................................... 22
Table 5-2 - Wind Direction and Percentage of Time for Each Quadrant ................................................... 23
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 6 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Abbreviations IOCL Indian Oil Corporation Limited
RRA Rapid Risk Assessment
DHDT Diesel Hydrotreating Unit
DHT Diesel Hydrotreating Unit (
HGA Hydrogen Generation Unit
IGHDS Indmax Gasoline Hydrodesulphurization
HCU Hydrocracker unit
KHDS Kerosene Hydro Desul Furization Unit
ISOM Isomerization Unit
HCN Heavy Cracked Naphtha
LCN Light Cracked Naphtha
MMTPA Metric Tons Per Annum
ALARP As Low As Reasonably Practicable
PSA Pressure Swing Absorption
ROG Refinery Offgas streams
SHU Selective Hydrogenation Section
UFL Upper Flammable Limit
LFL Lower Flammable Limit
HSE Health Safety & Environment
U
Million Metric Tons Per Annum
Adsorption
Unit
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 7 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Executive Summary
1. From the Risk Contours it is observed that in most cases of process units, the e-6 contour is
contained within boundary limits of IOCL. And hence it is within acceptable limits.
2. All the tanks are atmospheric and well with in the boundary of the facility. Being liquid the
credible fire scenarios include Pool fire and Full surface fire. The 37.5 kW heat radiation from
these fire does not extend beyond facility boundary.
3. In case of KHDS unit, the H2S concentration of 700 ppm does not extend beyond boundary
limit.of the facility even with 250 mm leak. It is demonstrated in figure 9-18. 1
37.5 kW/m2 heat radiation
from these fire does not extend beyond facility boundary.
all units
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 8 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
1 Introduction 1.1 Background
Indian Oil Corporation Ltd. (herein after referred to as The Client) is planning to make their Paradip
Refinery compliant to produce 100% BS-VI MS and HSD products. Paradip Refinery is the latest refinery
of Indian Oil Corporation Limited (IOCL) and has a design crude processing capacity of 15.0 Million
Metric Tons Per Annum (MMTPA). The various units of the refinery is being commissioned stage-wise
and the refinery is presently under stabilization.
To make Paradip refinery of IOCL BS-VI compliant, there is a need for installation of new units and also
revamp of old units to produce 100% BS-VI MS and HSD complaint products.
ThyssenKrupp Industrial Solutions, India (tkIS) (hereinafter referred to as The Contractor) is appointed as
detailed engineering contractor for this project.
As part of this project, The Contractor is required to submit Rapid Risk Assessment Report (RRA). Bell
Energy, Bell Engineering Software Technologists Ltd,(hereinafter called The Consultant) an organisation
well known in the field of HSE has been assigned the work of preparation of RRA study report.
1.2 Purpose of RRA The purpose of RRA is to identify the Hazards at the early stages of development of project, analyze the
hazards and propose the preventive and mitigative measures where necessary, to bring the risk level to
As Low As Reasonably Practicable (ALARP)
1.3 Project Description The basic objective of the Project is to up-grade the Paradip Refinery for producing 100% BS-VI quality
fuels by inducting new units and/or revamp of existing units. Following units with capacities as under are
planned to be implemented:
Table 1-1 – Details of Units with Capacities
Sr. No. Unit Capacities for BS-VI (TMTPA)
1. ISOM-new 1100
2. INDMAX–GDS-new 1150
3. HGU-new 60 kTPA **
4. Kero HDS-new 300
5. DHDT-existing 20% revamp
6. VGO-HDT- existing Quality revamp - Change of catalyst.
New HGU will include 1 no. Pressure Swing Absorption (PSA). For refinery off gas treatment
another PSA is considered.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 9 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
The scope further includes Storage, dispatch facilities, Utilities & other off-site facilities. All the above
units & facilities will be integrated with Paradip Refinery.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 10 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
The Overall plot plan of the facility is presented below.
Figure 1-1 – Overall Plot Plan
Figure 1-2 – Overall Plot Plan
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 11 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
2 Project Description 2.1 Process Description of DHDT Unit
This process description section provides explanation for the changes in equipment to be able to process
additional HSD feed in the Diesel Hydrotreater (Unit 013) at Indian Oil Corporation Limited in Paradip,
India. The Unit 013 is originally designed for 15000 tpd, with the additional feed the unit throughput will
increase by 20% to 18000 tpd.
For the revamped case, the feedstock to the Diesel Hydrotreating Unit (DHT) is a mixture of kerosene,
AGO, VGO, coker gas oil and Heavy Cracked Naphtha (HCN), LCO, HCO from the FCC and HSD from
VGO HDT.
These feedstocks enter the DHT Unit through four separate lines before being mixed ISBL:
• AGO, VGO and Kerosene from the AVU
• Coker Gasoil from the DCU
• LCO, HCN and HCO from the FCC
• HSD from the VGO HDT
Due to the increase of throughput, the following equipment will need likely need to be modified. Rating of
the existing vendor data sheets is needed to confirm.
Table 2-1 - Equipment Modification Details
013-C-001 Product Stripper Tray modifications
013-C-004 LP Amine absorber Tray modifications
013-P-001A/B/C Feed Charge Pump Increased impeller size
013-P-005A/B Diesel Product Pump Increased impeller size
013-E-004A/B Diesel Product Trim Cooler Tube modifications
Due to changes in the Product Diesel Flashpoint specification to min 42°C, the wild naphtha can be kept
in the Diesel Product which maximizes the diesel yield. This additional yield recovery will require
modification of the following additional equipment — a rating of the existing vendor data sheets is
needed to confirm.
013-C-002 Vacuum Drier Tray modifications
013-P-007A/B Drier Recycle Pump Tray modifications Pump
013-E-006A/B Drier Overhead Condenser Tube modifications
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 12 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
2.2 Process Description of HGU Unit The plant design is based on Naphtha and Natural Gas as main feedstocks and an additional Refinery
Offgas streams (ROG). Naphtha and Natural Gas will be processed in Hydrogen Generation Unit (HGU),
while ROG will be processed in ROG PSA Unit.
The purge gas from the PSA purge gas from the HGU will be the primary fuel to the reformer furnace and
naphtha, natural gas or refinery fuel gas from BL will serve as the supplementary fuel.
The purge gas from the Refinery Offgas PSA will be exported to Refinery fuel gas header as per client`s
request.
The HGU consists of the following major process steps:
• Naphtha Pre-treatment
• Feed Treatment
• Steam Reforming
• CO Shift Conversion
• H2 Purification by Pressure Swing Adsorption (PSA)
• Process Steam and Condensate System
The ROG PSA consists of the following major process steps:
• ROG Compression
• H2 Purification by Pressure Swing Adsorption (PSA)
• Fuel Gas Compression
The design of the whole complex is based on modern, environmental friendly, reliable process steps for
dependable and uninterrupted operation with ease of operation and safety as key elements.
2.3 Process Description of IGHDS Unit
2.3.1 Selective Hydrogenation Section (SHU): Two FCC gasoline cuts are processed in the Prime G+TM unit. The LCN cut (C5- 70°C) which is
available at 40°C and the MCN cut (70 – 185°C) which is available at 128°C and contains impurities such
as Chlorine.
The SHU reactor R-101 operates in down-flow mode at moderate temperature, mainly under liquid phase
and achieves the following functions:
The SHU reactor R-101 operates in down-flow mode at moderate temperature, mainly under liquid phase
and achieves the following functions:
Diolefins removal from the full range FCC gasoline:
From the light fraction LCN cut it helps achieving better stability of this product sent to the
gasoline pool.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 13 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
From the heavy fraction HCN in order to prevent eventual fouling problems in the downstream
selective HDS section and achieving long catalyst cycles in line with FCC turnarounds.
Conversion of light mercaptans and light sulfides to heavier sulphur compounds, which are
recovered in the heavy cut HCN. The light cut produced by the LCN Splitter has therefore very
low sulphur content, does not require a sweetening and can be sent directly to gasoline pool,
The SHU effluent is directly sent to the LCN Splitter C-101.
2.3.2 LCN and MCN Splitters Section: The LCN splitter is reboiled by means of a heater. It produces as vapor distillate a sweet hydrogen rich
gas to be routed to fuel gas network.
The MCN splitter operates at lower pressure. It produces an intermediate cut MCN as liquid distillate -
essentially C6s rich in benzene and olefins and with moderate sulphur content- that will be routed to the
Mild MCN HDS section.
2.3.3 Selective HCN HDS Section – 1 stage HDS scheme: MCN splitter bottoms (HHCN) is mixed with hydrogen make-up and recycle gas and heated by heat
exchange against effluent before entering the Main HCN HDS reactor, R-201. The reactor
temperature is controlled by the bypass on the HDS feed/effluent E-201 heat exchanger.
Hydrodesulphurization reactions and limited olefin saturation take place in the two beds reactor operating
in down-flow mode and in vapor phase.
An injection of liquid quench is foreseen between the catalytic beds of the Main HCN HDS reactor in
order to limit the temperature rise due to the heat of reaction and control olefins saturation.
2.3.4 Selective MCN HDS Section – 1 stage HDS scheme: MCN splitter top distillate (MCN) is mixed with hydrogen make-up and recycle gas and heated by heat-
exchange against effluent in the exchanger E-301 before entering the Main MCN HDS reactor, R-301.
The reactor temperature is controlled by the duty of the MCN HDS Heater H-301.
Hydrodesulphurization reactions and limited olefin saturation take place in the two beds reactor operating
in down-flow mode and in vapor phase.
2.3.5 HCN and MCN Stabilizer Sections: H2S and light ends removal in the hydrodesulphurization heavy and medium gasolines is carried out in
the stabilizer columns C-202 and C-301 respectively.
The HCN stabilizer C-202 is reboiled by the reboiler E-203 using the HCN HDS Effluent as heating
medium and by E-204 on HP Steam for the remaining duty required. It produces a sour vapor distillate
and sweet desulphurized heavy gasoline HCN. The sour vapor distillate will have to be treated OSBL for
H2S removal to produce a sweet purge gas effluent before being routed to Fuel Gas system.
The MCN stabilizer C-301 is reboiled by the reboiler E-305, using the bottom of MCN Splitter as heating
medium. MCN Stabilizer products are a sour vapor distillate and a medium cut gasoline MCN that will
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 14 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
have to be splitted downstream to get rid of the benzene and sulphur prior to being incorporated into the
MS pool.
2.4 Process Description of ISOM Unit The Penex process is specifically designed for continuous catalytic Isomerization of light naphtha. The
reactions take place in a hydrogen atmosphere, over a fixed bed of catalyst, and at operating conditions
that promote Isomerization and minimize hydrocracking.
Moderate operating conditions are used in the Penex process. The low operating temperature (120 to
175ºC) enables the Penex process to achieve the highest normal paraffin conversion. Ideally, the
Isomerization catalyst would convert the feed paraffin’s to the highest-octane number branched
structures: C5 to iso-pentane and C6 to 2,3- dimethylbutane. However, the Isomerization reactions are
equilibrium limited with lower temperatures favoring the concentration of highly branched isomers. When
operating at typical commercial conditions the ratios of iso to normal paraffin’s in the reactor effluent will
be approximately 3 to 1 and 9 to 1, respectively, for pentane and hexane. Ring opening is partially
promoted and the reactor effluent will contain less C6 naphthene than the feed. The C5 paraffin
equilibrium mixture will consist of essentially only normal and iso pentane; there is no formation of neo-
pentane. The C6 iso-paraffin equilibrium distribution is split approximately 45/55 between the higher
octane dimethylbutanes and lower octane methyl pentanes.
The first reactor may, therefore, be operated at a higher temperature and achieve a higher reaction rate.
This reduces the inventory of catalyst and the reactor size required. Most of the Isomerization is
accomplished at a high rate in the first reactor and the final portion is performed at a lower temperature
taking advantage of the more favorable equilibrium.
The standard Penex design since 1987 has been the Hydrogen-Once-Through (H-O-T) design. In this
unit, there is no recycle compressor, product condenser nor product separator.
Organic chloride promoter is added continuously with the feed and is converted to hydrogen chloride in
the reactor. Since the catalyst functions with small amounts of promoter (measured in parts per million), it
is not necessary to provide separate equipment for recovery and reuse of hydrogen chloride. It is
permitted to leave the unit by way of the stabilizer gas. The quantity of stabilizer gas is small, due to the
selective nature of the catalyst that permits very little hydrocracking of the light naphtha charge to take
place. The stabilizer gas contains the excess hydrogen required for plant control and the C1-C3
hydrocarbons introduced by way of the make-up hydrogen. The stabilizer off gas is scrubbed for
hydrogen chloride removal before entering the refinery fuel gas system.
The catalyst itself is non-corrosive and, despite the presence of small amounts of hydrogen chloride
during operation, the dryness of the system permits construction with carbon steel. Over thirty years of
commercial service have demonstrated the adequacy of this inexpensive metallurgy.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 15 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
2.5 Process Description of KHDS Unit Hydrodesulphurization reactions occur when hydrogen reacts with the sulphur atom and forms hydrogen
sulphide. The rate of reaction depends upon the type of sulphur compound present in SR Kerosene fuel
are mercaptans, thiophene and its derivatives, benzothiophene, small amounts of benzothiophene
derivatives etc.
Below are the different sections covered in this unit:
• Feed Section
• Preheat Train and Wash water section
• Feed Heater and Reactor Section
• LT Separator and RG Amine Absorption Section
• Recycle gas compressor section
• Stripper Section
• Sour Gas Amine Absorption Section
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 16 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
3 Types of Risk 3.1 Flammable Gas Dispersion
If the Flammable gas released due to loss of containment forms a vapor cloud. If the flammable
concentration of the cloud while between upper flammable limit (UFL) and lower flammable limit (LFL)
does not get ignition source then the cloud loses its ability to catch fire and results in to harm less
dispersion (If no toxic substance is not present).
3.2 Toxic Gas Dispersion
In case of Toxic gas cloud, the fatal concentration if reaches ground level (1 m) it can affect human
beings.
3.2 Flash Fire Flammable gas released due to Loss of Containment, has the potential to form a flammable vapor cloud.
The cloud starts drifting either due to momentum or wind speed and direction. If it finds a credible ignition
source, due to delayed ignition of the flammable gas cloud, a flash fire can occur in an uncongested
area.
3.3 Vapor Cloud Explosion Upon release in the absence of immediate ignition sources, flammable gas forms a flammable vapor
cloud. Upon finding a credible ignition source, delayed ignition of the flammable gas cloud can lead to an
unconfined vapor cloud explosion if the gas is accumulated in a congested area, as no confinement is
identified for the project facilities. The degree of blast is dependent upon the congestion and the confined
volume.
3.4 Jet Fire Jet fires can occur due to immediate ignition of the released flammable gas or delayed ignition of the HC
vapor cloud flashing back leading to a jet fire scenario at the release location. This applies to the small
leak sizes (e.g. less than 100mm) of flammable material where the release from small opening causes
molecule atomization and due to friction can catch fire. If it does not catch fire, it can form liquid spray of
small droplets.
3.5 Pool Fire. Pool fire can occur due to immediate or delayed ignition as a result of liquid pool formation. The size of
the pool fire will be governed by liquid burning rate. For tank facilities, full surface fire and bund fire can
occur.
3.5.1 Surface Fire Surface fire can occur in case of tank roof failure and the substance stored in the tank catches fire.
3.5.2 Bund Fire. The liquid pool formed as a result of loss of containment from a bunded tank can vaporize and get an
ignition source and resultantly catch fire
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 17 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
4 Methodology Adapted The Methodology adapted for the purpose od this RRA is as follows;
1. Study process description of the units involved.
2. Study Lay out, Piping & Instrumentation diagrams, Process Flow diagrams and Heat and
Material balance.
3. The P & Ids were used for the purpose of sectionalisation and parts count.
4. Based on the properties of the material consequence analysis were performed.
5. Using failure frequencies, the risk analysis was carried out.
6. The results have been compared with the risk acceptance criteria.
7. The study considers all the loss of containment cases for the leak sizes as mentioned in the
Assumptions and Study basis.
For the purpose of simulation Phast for Consequence Analysis and Phast Risk software for Risk Analysis
has been used.
PFDs
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 18 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
5 Considerations for Disaster Management Plan. These units are close to the water (Lake or river) and if the same is used for transportation /
travelling, people need to be made aware the flammable and Toxic risk they are exposed to and
what emergency actions are needed.
An Escape and Evacuation plan including Muster location is needed for these people are.
Since these units contain hydrocarbon and are part of a refinery, the disaster management plan of
the existing refinery should be adequate to cater to the requirements of this section also. If not then
these actions need to be integrated in to existing DMP after checking.
Since the facility includes H2S, H2S zoning analysis and its implementation should be considered.
.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 19 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
6 Hazards Identification The units concerned here are basically Hydrocarbon processing units operating at high temperatures
and high pressures. Like any other refineries, the main risk is flammable risk. In KHDS Unit, the Toxic
material i.e. H2S. is present However it is very less than the fetal concentration of 700 ppm.In some
other streams / Unit Benzene and Toluene in small ppm is present. However, the risk from Benzene
depends upon the continuous exposure. This is termed as “Occupational health issue” and not
instantaneous health (fatality) issue.
Unit wise type of Risk
Table 6-1 - Unit wise type of Risk
Sr Unit Description. Substance Type of Risk
1 HGU Naphtha, Natural
Gas, Hydrogen
Flammable Flash Fire
Vapor Cloud
Explosion
2 KHDS H2S, HC Toxic Flammable
3 ISOM Naphtha, HC Flammable
4 IGDHS Hydrogen, HC Flammable Explosion
5 DHDT HC Flammable
The flammable consequences normally do not extend beyond boundary wall. The boundary walls
themselves offer protection from flammable consequences. These consequences of these are
considered in calculating risk.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 20 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
7 Risk Acceptance Criteria. For this study, the Risk Acceptance Criteria of UK HSE and adapted by India is considered.
Figure 7-1 – Risk Acceptance Criteria
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 21 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
8 Assumptions and Study Basis 8.1 Following assumptions and basis of study were made :
S. No. Category Sub-
Category Assumption Justification
1 Vessel Volume
Calculated based on vessel dimension, assuming 100% full. For simplification, assuming that vessel in cylindrical shape. Only vessel type either vertical and horizontal are considered with inventory, others e.g. heat exchanger, pump, ejector, etc. have no static inventory as it is similar to others, considered as piping volume
2 Parts Count PFDs are used for the parts count as P&IDs are not available at this stage. Assumptions: 1. 2 flanges per valve (manual or actuated) 2. Pipng, valve, flanges size are considered to be 10" as no P&IDs yet available 3. Each piping length inlet and outlet of vessel is assumed 20m
P&IDs are not available
3 Failure Frequency
OGP database failure frequency will be adopted
4 Release hole size
Hole sizes are based on OGP recommended range and hole size 1. 1 - 10 mm, representative as 5mm (small leak) 2. 10 - 50 mm, representative as 25 mm (medium leak) 3. 50 - 150 mm, representative as 100mm (Large leak) 4. > 150 mm, full bore rupture, piping diameter of 10"
Company criteria is not available
5 Consequence Modelling
General - Surface Roughness
1.0 as large refinery with large obstacles as per PHAST definition
General - Ambient Temp.
27 deg C
General - Operating Pressure
Based on provided H&MB, streams and PFD
IGHDS & ISOM - Operating
Consider Operating pressures as 0.9 times Design Pressures of the respective equipment. Design pressures of equipment referred to the
(Except for IGHDS and ISOM Units)
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 22 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
S. No. Category Sub-
Category Assumption Justification
Pressure Licensor in Equipment list
General - Operating Temperature
Based on provided H&MB, streams and PFD
IGHDS & ISOM - Operating Temperature
Consider Operating Temperature as 25 °C lower than the Design Temperatures of the respective equipment. Design Temperatures of equipment will refer to the Licensor in Equipment list
6 Wind speed and stability
2F for night
5D for daytime Windrose
distribution Paradip Refinery, refer to the provided PFDs
7 units IGDS and ISOM,
following operating conditions have been assumed in absence of Heat and Mass Balance:
Operating Pressure: 0.9 times operating pressure of respective equipment as given by licensor. Operating Temperature: 25 Deg C lower than the operating temperature as indicated by Licensor
For IGDS unit, equipment tag numbers and inter equipment distances have been assumed based on the process description and past experience for similar project as the same are not provided by Licensor.
8.2 Meteorological data.
Wind Table 8-1 - Wind Velocity
Average velocity
- Summer 37 – 45 km/hr
- Winter 15 – 26 km/hr
Maximum velocity 72 m/sec (259 km/hr)(During 1999 cyclone)
- cyclone 200 - 250 km/hr (S-SE)
Basic wind speed for structural design 65 m/sec (234 km/hr)
(Except for IGHDS and ISOM Units)
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 23 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Table 8-2 - Wind Direction and Percentage of Time for Each Quadrant
% of time
N
NE
E
SE
S
SW
W
NW
Calm
Morning (0830)
13.8 6.4 2.1 2.4 7.7 21.6 11.0 8.2 (∆26.8)
Evening (1730) 15.0 6.7 9.41 8.16 15.0 24.8 4.8 1.8 (∆27.8)
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 24 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
9 Conclusions and Recommendations 1. The combined Risk Contour demonstrates that the general public is exposed to ( as this is RRA
which concentrates on general public) less than e-6 which is within Broadly Acceptable region.
when compared with UK HSE Risk Acceptance Criteria as adapted by India.
2. From the Risk Contours it is observed that in most cases of process units, the e-6 contour is
contained within boundary limits of IOCL. And hence it is within acceptable limits.
3. All the tanks are atmospheric and well with in the boundary of the facility. Being liquid the
credible fire scenarios include Pool fire and Full surface fire. The 37.5 kW heat radiation from
these fire does not extend beyond facility boundary.
4. Fn Curve: Since the risk more than e-5 is not extending beyond facility boundary, the Fn curve is
not relevant
5. All the tanks are atmospheric tanks. Being liquid the credible fire scenarios include Pool fire and
Full surface fire. It is noted that heat radiation (37.5 kW and 12 kW ) from these fire does not
travel beyond facility boundary
6. Company should get H2S zoning done in areas having high H2S
37.5 kW/m2
(37.5 kW/m2 & 12 kW/m2)
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 25 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Annexure ISO Risk Contour od DHDT unit.
Figure 9-1 - ISO Risk Contour of DHDT unit. It can be seen from the above Risk Contour that the e-6 contour is well within the boundary of the facility.
ISO Risk Contour of IGDHS unit.
Figure 9-2 - ISO Risk Contour of IGDHS unit. It is evident from the risk contour that the contour of e-6 is well within the boundary of the facility.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 26 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
ISO Risk Contour of KHDS
Figure 9-3 - ISO Risk Contour of KHDS It can be seen from the LSIR contours that e -6 contour is well within the boundary limit of the facility.
ISO Risk Contour of HGU
Figure 9-4 - ISO Risk Contour of HGU It can be noted from the above LSIR contour, that e-6 contour is confined with in the boundary of the
facility.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 27 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
ISO Risk Contour of ISOM
Figure 9-5 - ISO Risk Contour of ISOM The e-6 contour is well within the boundary of the facility.
Combined ISO Risk Contour The combined LSIR also e-6 risk contour does not extend beyond boundary limit.does not
Figure 9-6 - Combined ISO Risk Contour
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 28 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
It may be noted that combined e-6 Risk Contour does not extend beyond facility boundary.
Tanks.
All the tanks are atmospheric tanks. Being liquid the credible fire scenarios include Pool fire and Full
surface fire. For the purpose of RRA, it is necessary to check heat radiation from these fire whether it
extends beyond facility boundary or not. (37.5 kW)
IGHDS tank.
Tank details: Diameter = 37.6m Height = 19m Operating Temp: 40degC Operating Press = atm pressure
Figure 9-70 – Radiation on a Plane for Pool Fire for IGHDS tank
Figure 9-8 – Radiation on a Plane for Pool Fire for IGHDS tank The thermal radiations level modelled = 4, 12.5 and 37.5 kW/m2.
(37.5 kW/m2)
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 29 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Findings = 12.5 and 37.5 do not reach 2 m height and ground level. 4 kW/m2 can reach and extend
approximately 73m away from tank.
IGHDS Tanks
Figure 9-9 - Radiation on a Plane for Pool Fire for IGHDS tank
ISOM Tanks.
Figure 9-10 - Radiation on a Plane for Pool Fire for ISOM tank
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 30 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Figure 9-11 - Radiation on a Plane for Pool Fire for ISOM tank
Figure 9-12 - Radiation on a Plane for Pool Fire for ISOM tank ISOM (203-TK-046/047)
Figure 9-13 - Radiation on a Plane for Pool Fire for ISOM tank (203-TK-046/047)
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 31 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Figure 9-14 - Radiation on a Plane for Pool Fire for ISOM tank (203-TK-046/047)
Figure 9-15 - Radiation on a Plane for Pool Fire for ISOM tank (203-TK-046/047)
203-TK-018-019_BS-VI HGU FEED TANK
Figure 9-16 - Radiation on a Plane for Pool Fire for ISOM tank 203-TK-018-019_BS-VI HGU FEED TANK
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 32 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Figure 9-17 - Radiation on a Plane for Pool Fire for ISOM tank 203-TK-018-019_BS-VI HGU FEED TANK
Similarly SKO Product storage Tank has been modelled and the Thermalradiation is found within the stipulated limit of 37.5 KW/m2 at the facilityboundary limit.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 33 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
Annexure a
PROJECT DESCRIPTION
The basic objective of the Project is to up-grade the Paradip Refinery for producing 100% BS-VI quality
fuels by inducting new units and/or revamp of existing units. Following units with capacities as under are
planned to be implemented:
Sr. No. Unit Capacities for BS-VI (TMTPA)
1. ISOM-new 1100
2. INDMAX–GDS-new 1150
3. HGU-new 60 kTPA **
4. Kero HDS-new 300
5. DHDT-existing 20% revamp
6. VGO-HDT- existing Quality revamp - Change of catalyst.
** New HGU will include 1 no. Pressure Swing Absorption (PSA). For refinery off gas treatment another
PSA is considered.
The scope further includes Storage, dispatch facilities, Utilities & other off-site facilities. All the above
units & facilities will be integrated with Paradip Refinery.
Rapid Risk Assessment Study for BS VI – IOCL Paradip
Rapid Risk Assessment Report
Report Ref: U1804-Rev01 Page 34 of 34 © Copyright Bell Energy 2018
Version: A 16.02.2018
700 ppm of H2S due to 250 mm leak is not reaching beyond boundary limits of IOCL.
Figure 9-18 - 700 ppm of H2S due to 250 mm leak is not reaching beyond boundary limits of IOCL.