iee subproject 02 bac giang - asian development bank · poverty reduction for the beneficiaries of...
TRANSCRIPT
Initial Environmental Examination May 2013
Vietnam: Sustainable Rural Infrastructure Development Project in the Northern Mountain Provinces Subproject 2: Improving Xuan Huong Pumping Station, Lang Giang District, Bac Giang Province
Prepared by the Ministry of Agriculture and Rural Development for the Asian Development
Bank
ii
CURRENCY EQUIVALENTS
Currency unit: Vietnam Dong (VND) and US dollar ($) Exchange rate on 11
th June, 2012: $1 = 20,828 VND
ABBREVIATIONS
ADB - Asian Development Bank
AH - Affected Households
AP - Affected Persons
CPC - Commune People’s Committee
CSB - Commune Supervision Board
CSC - Construction Supervision Consultant
CPMU - Central Project Management Unit
DARD - Department of Agriculture and Rural Development
DIA - Direct Impact Area
DONRE - Department of Natural Resources and Environment
DPC - District People’s Committee
EM - Ethnic Minority
EMP - Environmental Management Plan
IEE - Initial Environmental Examination
IIA - Indirect Impact Area
MONRE - Ministry of Natural Resources and Environment
PPC - Province People’s Committee
PPMU - Provincial Project Management Unit
RP - Resettlement Plan
SIA - Secondary Impact Area
SRIDP - Sustainable Rural Infrastructure Development Project in the Northern
Mountain Provinces
UXO - Unexploded Ordinance
This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
iii
TABLE OF CONTENTS
CURRENCY EQUIVALENTS ............................................................................................ II
ABBREVIATIONS ............................................................................................................. II
TABLE OF CONTENTS ..................................................................................................... III
LIST OF FIGURES ........................................................................................................... IV
LIST OF TABLES .............................................................................................................. IV
I. INTRODUCTION ........................................................................................................ 5
A. Subproject Rationale .............................................................................................. 5
B. Subproject Objectives ............................................................................................ 5
C. Project Alternatives ................................................................................................ 5
II. DESCRIPTION OF PROJECT ........................................................................................ 6
III. DESCRIPTION OF CURRENT ENVIRONMENT ........................................................ 16
IV. ENVIRONMENTAL IMPACT SCREENING ................................................................ 19
V. OUTLINE ENVIRONMENT MANAGEMENT PLAN (EMP) ............................................. 28
A. Environmental impact mitigation plan ................................................................... 28
B. Environmental impact monitoring ......................................................................... 31
C. Environmental Compliance Monitoring ................................................................. 34
D. Responsibilities in the EMP implementation ......................................................... 37
E. Monitoring and reporting system .......................................................................... 39
F. Expenditure for EMP implementation ................................................................... 40
VI. PUBLIC CONSULTATION AND SUBPROJECT INFORMATION DISCLOSURE ....... 41
A. Description of activities to date ................................................................................. 41
B. Outcomes of public consultation up to the reporting time ......................................... 41
C. Community consultancy activities in the future ......................................................... 42
VII. GRIEVANCE REDRESS MECHANISM ..................................................................... 43
VIII. CONCLUSIONS AND RECOMMENDATIONS ......................................................... 45
APPENDIXES ................................................................................................................. 47
Appendix 1: Cost for EMP implementation ................................................................... 47
Appendix 2: Photos on the existing environment ........................................................ 48
Appendix 3: Minute on dumpsite identification ............................................................. 51
Appendix 4: Document of consultation and participation .............................................. 54
Appendix 5: Details of consultation activities ................................................................ 61
Appendix 6: Documentation of Public Consultation ...................................................... 62
Appendix 7: List of data sources used in IEE Preparation ............................................ 64
Appendix 8: Sample Complaint Form ........................................................................... 65
iv
LIST OF FIGURES
Figure 1: Map of drainage basin and surrounding Area .............................................. 11 Figure 2: Map of irrigated basin and Surrounding Area ............................................... 12 Figure 3: Subproject Layout ........................................................................................ 11 Figure 4: Layout of Headworks Cluster ....................................................................... 12 Figure 5: Typical canal cross section .......................................................................... 15
Figure 6: Grievance redress mechanism .................................................................... 44
LIST OF TABLES
Table 1: Description of subproject ................................................................................. 6 Table 2: Description of ground environment ................................................................ 16 Table 3: Environmental impact screening ................................................................... 19 Table 4: Environmental impact mitigation plan ............................................................ 28 Table 5: Environmental monitoring plan ...................................................................... 31 Table 6: Environmental compliance monitoring plan ................................................... 34 Table 7: EMP Implementation ..................................................................................... 37 Table 8: Monitoring and reporting system ................................................................... 39 Table 9: Expenditure for EMP implementation ............................................................ 40 Table 10: Public consultation and information disclosure ............................................ 41 Table 11: Outcomes of public consultation.................................................................. 41 Table 12: Expected community consultation activities ................................................ 42 Table 13: Estimated for disclosure information activities ............................................. 47 Table 14: Cost estimation for implementation of capacity building .............................. 47 Table 15: Attendance in consultation meetings ........................................................... 62 Table 16: Matrix of issues and concerns ..................................................................... 63
5
I. INTRODUCTION
A. Subproject Rationale
1. Sustainable Rural Infrastructure Development Project in Northern Mountain provinces (SRIDP) is being implemented through a sector loan from Asian Development Bank (ADB). Ministry of Agriculture and Rural Development (MARD) is the executing agency for the sector loan. SRIDP coverage are 15 mountainous provinces in northern Vietnam (Bac Giang, Bac Kan, Cao Bang, Dien Bien, Ha Giang, Hoa Binh, Lai Chau, Lang Sơn, Lao Cai, Phu Tho, Son La, Thai Nguyen, Tuyen Quang, Vinh Phuc, Yen Bai).
2. While the poverty levels throughout the country had been significantly reduced as results of development efforts; the statistics in mountain provinces above had indicate rather slow improvement during the last decade (47% in 2002, 32.3% in 2006 and 27% in 2008)
1. Part of the
problem is due to the inadequate access facilities, social services, and commercial opportunities. It is for this reason that GOV and ADB had pursued the SRIDP to provide sustainable access facilities in these poverty stricken mountain provinces. These infrastructures include rural roads, public markets, irrigation and water supply facilities. As a part of the SRIDP, the Subproject “Improvement of Xuan Huong Pumping Station, Lang Giang District” will be implemented in Bac Giang province
B. Subproject Objectives
3. The Upgrading Xuan Huong pumping station in Xuan Huong commune, Lang Giang district seeks to improve the efficiency of irrigation, drainage, productivity and crop yields, increasing farmers’ income, mitigate the risks of natural disasters (droughts, floods), and contributing to poverty reduction for the beneficiaries of the subproject. The subproject contributes to the sustainable development of rural agriculture area.
C. Project Alternatives
4. Efforts to minimize the adverse social impacts of the Subproject include minimizing the land required for establishing the new pump-house, electric power substation and connecting channels to the existing drainage channel and irrigation main canal to avoid involuntary resettlement impacts to productive farms within the subproject area.
5. Initial Environmental Examination (IEE) has been prepared to meet the Social Policy Safeguards requirements of ADB
2 and GOV
3. The IEE contains the following contents:
(i) Section II: Description of the project (ii) Section III: Description of the existing environment (iii) Section IV: Environmental impact screening (iv) Section V: Outline environmental management plan (v) Section VI: Public consultation and disclosure activities (vi) Section VII: Grievance Redress Mechanism (vii) Section VIII: Conclusion and Recommendations
1 Report and Recommendation of the President to the Board of Directors, ADB, September 2010
2 ADB Social Policy Safeguard (2009)
3 Law on environmental protection approved by the National Assembly of Socialist of Vietnam on 29
November, 2005
6
II. DESCRIPTION OF PROJECT
Table 1: Description of subproject
Description Subproject data
1. General information
1.1 Subproject name Improvement of Xuan Huong Pumping Station, Lang Giang district, Bac
Giang province
1.2 Subproject type Pumping station, irrigation and drainage system upgrading
1.3 ADB Environment
Category
Category B
1.4 Project employer Bac Giang DARD
1.5 Address of project Owner No. 2 Nguyen Van Cu – Bac Giang City- Bac Giang Province
1.6 Name and title of Head of
Subproject Owner Manh Quan Phuc, Director of PPMU
1.7 Telephone, fax and email
address of Subproject Owner
Tel: 02403853665; Fax: 0240853983 Email: [email protected]
1.8 Name of Environmental
Officer of PPMU
Nguyen Van Hien
1.9 Telephone, fax and email
address of PPMU Environment
Officer
Tel: 02403853665; Fax: 0240853983 Email: [email protected]
2. Description of subproject
2A. Common Facilities
2A.1 Pump house Currently: two pump house, one for irrigation and the other for drainage
installed at the dike road. The building is already dilapidated and is in dire
need for immediate repair. Inside the two buildings are old pumps used for
the respective irrigation and drainage systems. An old electric substation is
installed near the pump stations to provide power to the facility.
After upgrading: A new single pump house is constructed in the adjacent
lot that will house both irrigation and drainage pumps and auxiliary
facilities. A new electric substation will also be installed adjacent to the
pump station. The minor movement is also in line with the construction of a
major dike road whose alignment will cross the existing pump house.
The old pump-house, old pumps, old transmission line and other old
appurtenances are to be dismantled, the lot cleaned of waste and debris.
All dismantled materials turned over to the appropriate Province office.
2A.2 Auxiliary works - Water drainage system: pumping water from the suction chamber to the
downstream by submersible pump.
- Fire protection system: CO2 gas and dry powder fire extinguishers.
- Measurement system: electronic buoy.
- Ventilation system: exhaust fans, blowers
- Mechanical equipment on the pipeline: assembly joint, steel pipes,
damper valves.
2A.3 Electrical system and
devices
- 22kV line: Repositioning electric pole 55 of Road 673 about 15m away
from the previous position.
- Electric line to the new substation will be connected directly from the
existing electric power line.
- Substation: 2 transformers with capacities of 560 KVA-6(22)/0.4kV and 1
transformer with capacities of 100KVA-6(22)/0.4kV,
- 0.4 KV line: Lower voltage lines from behind the transformers are wired in
the cable trough from the substation to the pumping control station and
then to the pump motors.
2A.4 Management house Length: 17.5m; width: 6m; concrete rooftop
Management house contains 2 office with area of 44m2, 1 warehouse with
area of 19m2, and a 19m
2 bedroom
7
Description Subproject data
2B. Drainage System
2B.1 New subproject or
upgrading rehabilitation
subproject
Upgrading subproject
2B.2 Grade of the irrigation
work
Irrigation work grade IV (TCXDVN 285:2002)
2B.3 Water source Flooded areas within the subproject catchment
2B.4 Drainage Area 1,280 ha agricultural land of Xuan Huong commune
2B.5 Specification of the
headwork cluster for drainage
system
Currently
- Xuan Huong 1 drainage pumping station has 10 horizontal axis pumps
with capacity 1200 m3/hour (one irrigation pump unit);
- Xuan Huong 2 drainage pumping station has 7 horizontal axis pumps
with capacity 1200 m3/h.
- Dyke crossing (box culvert): at km4+900 on the left bank of Thuong river.
- Stilling basin is degraded.
After improvement:
Xuan Huong pump station after being renovated and upgraded will have
the following features:
- Drainage pumping station: New 900VSP machines (vertical axis)
installed with total capacity=4*170kw= 680 KW;
- Total capacity Q-tk = 6600 m3/h*4 machines = 7.3m
3/sec;
- Drainage coefficient q= 5.7 l/s-ha;
- Dyke crossing (box culvert) replaced
- Stilling basin is desilted.
2B.6 Specifications of the canal
system and works on the canal
Currently, the drainage canal system of the two drainage pumping stations
is earth canal system, which is heavily silted, such that the water
conveyance capacity is already poor. Part of the irrigation canal is
concrete-lined but the earth section is severely silted, the aqueduct (plume)
of the drainage canal has also been degraded.
After improvement: Drainage canals desilted, aqueduct repaired (broken
pipes replaced), clogged irrigation canals desilted,
Drainage canal:
- Length of T1=2,390m:
+ Dimension of 5 canal segments of T1 canal is (1.0x1.1) m,
(1.2x1.5) m, (2.2x1.5) m, (3.2x1.5) m, (7.2x1.5) m respectively.
+ The three dimensions (n x B x H) of 5 drainage sluices on T1
canal is (1x1,0x1,2) m, (1x1,0x1,2) m, (1x1,2x1,5) m, (1x1,5x1,5)
m, (2x1,0x1,5) respectively.
- Length of T2=2,273m:
+ Dimension of T2 canal is (2.4x1.5) m;
+ The three dimensions (n x B x H) of 3 drainage sluices on T2
canal is (1x1,5x1,5) m
2C. Irrigation System
2C.1 New subproject or
upgrading rehabilitation
subproject
Upgrading subproject
2C2 Grade of the irrigation work Irrigation work grade IV (TCXDVN 285:2002)
2C.3 Water source Surface water
2C.4 Determine water source Thuong river
2C.5 Is this water for domestic
use?
No
2C.6 Irrigated and drainage
areas
Currently, irrigates a total of 170ha agricultural lands in Xuan Huong
commune, However the performance of the pumps are approximately 60%
of the original design, thus operating cost is high which includes power
consumption, and water losses due to leakage.
After upgrading: The upgraded facility will continue to irrigate the 170 ha
8
Description Subproject data
agricultural lands, however the pumps will be able to function at full
capacity at relatively lower operation cost, and low amount of water losses.
2C.7 Specification of the
headwork cluster for irrigation
system
Currently: One horizontal axis irrigation pump unit with capacity 1200
m3/hour in Xuan Huong 1 drainage pumping station.
After upgrading:
- Irrigation pumping station: 1 close coupled centrifugal pump, horizontal
axis, capacity: 33 KW, total capacity Q = 1,200 m3/h, irrigation area: 170
ha, irrigation coefficient =1.45 l/s-ha
- Dyke crossing arch culvert design = 7.3 m3/s, BxH = 1.6x2 m, L=18.3m.
- Stilling basin = 5 x 0.75m
- Pumping station (for irrigation)
+ Designed level of suction tank is +1.2m,
+ Designed level of discharge tank is +6.72m
2C.8 Specifications of the canal
system and works on the canal
Currently: 2 sets of irrigation canal systems. Part of the irrigation canal is
concrete-lined but the earth section is severely silted.
After improvement: Clogged irrigation canals desilted, and lined with bricks
held together by concrete.
Length =1534 m, in which:
- Irrigation canal KC, KT1: L= 160+678 = 838m; B x H = 0.6x0.8 m;
- Irrigation canal KT2, KT3: L= 191+505 = 696m; B x H = 0.5x0.7 m
3. Construction activities
3.1 Commencement date
(month/year)
10/2013
3.2 Completion date
(month/year)
12/2014
3.3 Number of workers About 50 workers
3.4 Construction camps
required (Yes/No)
Yes, 1 tent will be built.
3.5 Construction in rainy
season (Yes/No)
Yes, but only in favorable weather conditions.
3.6 List of volume and
construction equipment/vehicles
condition
It is estimated that the following construction equipment will be used: 3
excavators; 1 bulldozer; 2 compactors; 3 500L concrete mixers and other
minor construction equipment. Other works will be mostly constructed
manually.
3.7 Location and extent of
borrow area and description of
material source/s
- Sand and gravel are purchased in Ha Chau-Hiep Hoa sand station, the
transport distance is about 35 km.
- Stone is purchased in Dong Mo quarry – Lang Son province, transport
distance is about 60 km.
- 70% excavated soil (about 29,860 m3) meeting technical requirements
of filling soil and necessary quantity of filling soil during the
construction. This volume exceeds required volume of filling earth
expectation, hence there is no need to exploit earth from borrow pits.
- Other materials are purchased in Bac Giang city, transport distance is
about 5 km.
3.8 Method on management of
excess excavated/surplus soil
- Volume of excavated soil: 42,658.19 m3
in which mud is 1,060.34 m3,
organic soil is 3,823.1 m3.
- Volume of filling soil: 19,778.87 m3
Excavated soil with good mechanical properties is utilized for filling, the
unused and the surplus will be transported to the disposal site. The
disposal site is located in Phuc Man village, which is 2km far from the
headwork. This includes various deep brick container, the vegetation cover
in here is mostly wild plants, shrubs; and the soil volume capacity is about
30,000m3. The disposal area is not near the water source so there is no
rainy water accompanied by soil and stone flowing down to the water
source.
9
Description Subproject data
3.9 Type and approximate
quantity of raw construction
materials
- Stone of all types: 2,837.988 m3
- Sand of all types: 1,919.238 m3
- Cement: 962,517 tons
- Steel of all types: 218,148 tons
- Asphalt: 575.4 kg
3.10 Quantity of solid waste
generated from construction
(calculated monthly in unit of
m3)
- Soil, sand, debris… and other construction solid wastes (cement bags,
bottles, etc.) estimated of about 12 m3 are collected and hauled to the
disposal site in accordance with the subproject’s regulations (estimated
at 0.4 m3/day)
- Domestic waste is estimated at 450 kg (average waste amount per
capita in the rural area is 0.3 kg/day x 50 people x 30days/month).
4. Operation and maintenance activities
4.1 Party Responsible for O & M Xuan Huong pumping station’s operation is managed by Lang Giang
Irrigation Work Exploitation Enterprise, affiliated to Cau Son–Cam Son
Irrigation Exploitation Company Ltd., 3 communes benefited from the
project is Xuan Huong, My Thai and Phi Mo are responsible to contribute
labor for renovation and repair of the works.
4.2 O & M Activities Operation activities:
- Manage, monitor equipment system of pump headwork cluster monitor
drainage canal system;
- Plan detail irrigation period for specific crops and for growth periods of
crops; close/open water regulation outlet based on schedule; check and
protect canal systems, overflow, culverts; record operation of the entire
canal system, branch canals, on-farm canal;
Management activities:
- Patrol, inspect and report the condition ò canal, culverts, and related
works;
- Implement remedial measures promptly to prevent leakage and
infiltration of canals, especially by termites or burrowing;
- Remove and dredge mug, debris, and vegetation from waterways,
canals and works on canals;
- Repair rainwater ditches and other small earthworks relating to canal
slops, works on canals and management road;
- Regularly lubricate mechanical components of pumping station and the
gates on canals;
- Replace damaged components of steel doors.
4.3 Beneficiaries Direct beneficiaries include 33,032 people in 3 communes of Xuan Huong,
My Thai and Phi Mo in Lang Giang district.
4.4 Periodic timing for
maintenance of the canal
system/pipe cleaning
Maintenance work is carried out regularly every year including dredging
liquid mud suction tank, caulking and mending concrete, anti rust painting
the valve gates, machine oil and greasing, etc.
Also the canal dredging will be carried out periodically 2 times/year ( before
each production crop).
5. Resettlement and land acquisition 4
5.1 Number of Affected
Households (AHs)
179 households
5.2 AHs loosing > 10%
productive land or livelihood
source
0
5.3 Number of AHs that must
relocate
0
5.4 Total land area to be
acquired (m2)
Temporary = 0 Permanent = 13696.5
4 This data is taken from the Resettlement Plan
10
Description Subproject data
5.5 Total government land to
be acquired (irrigation and traffic
land) (m2)
Temporary = 0 Permanent = 0
5.6 Agricultural land area to be
acquired) (m2)
Temporary = 0 Permanent = 13696.5
5.7 Forest land to be acquired
(m2)
Temporary = 0 Permanent = 0
5.8 Aquaculture land to be
acquired (m2)
Temporary = 0 Permanent = 0
5.9 Residential land to be
acquired (m2)
Temporary = 0 Permanent = 0
5.10 Garden land to be
acquired (m2)
Temporary = 0 Permanent = 0
5.11 Other land to be acquired
(m2)
Temporary = 0 Permanent = 0
6. Subproject cost
Total cost of subproject 67,356,281,000 VND equivalent to 3,227,421 USD
7. Environmental
Clearance
Due to scope of the subproject, in accordance with environmental
regulations of Vietnam, an EIA was prepared and approved by Bac Giang
DONRE.
11
Figure 1: Map of drainage basin and surrounding Area
DIA
SIA
SIA
IIA
IIA
Xuan Huong pumping station
(for drainage)
DRAINAGE CANAL
12
Figure 2: Map of irrigated basin and Surrounding Area
DIA
SIA
SIA
IIA
Xuan Huong pumping station
DRAINAGE CANAL
IRRIGATION CANAL
13
Figure 3: Subproject Layout
Drainage Canal T1
Drainage Canal T2
Irrigation Canal 2
Irrigation Canal 1
Drainage Canal T1
Pump house for Irrigation and Drainage
14
Figure 4: Layout of Head works Cluster
15
Figure 5: Typical canal cross section
16
III. DESCRIPTION OF CURRENT ENVIRONMENT
6. The Direct Impact Area (DIA) is the a) 13,696.5m2 land on which the new pump-house,
auxiliary facilities will be built; b) irrigation canals that need desilting and brick-lining, and c) the drainage channel that need desilting. The Secondary Impact Area (SIA) includes the 1,280 ha periodically flooded land used for agriculture that needs to be drained, the 170 ha. Irrigation service area, and the strip of land 100 m on both sides of the construction site. The Indirect Impact Area (IIA) covers the subproject beneficiary area corresponding Xuan Huong, My Thai, Phi Mo communes.
Table 2: Description of Existing Environment
Description Subproject data
1. Subproject location
1.1 Communes: Xuan Huong
1.2 District: Lang Giang
1.3 Province: Bac Giang
1.4 Geographical
location:
Pumping station’s location: Latitude: 21º18’45”
Longitude: 106º11’43”
Subproject’s location: Latitude: from 21º18’45” to 21º22’56”
Longitude: from 106º10’43” to 106º15’03”
2. Natural environmental conditions
2.1 Air quality This subproject locates in the rural area, without much effect from industrial production
activities. It was observed that the air quality is very good, without strange odors or
dust.
2.2 Noise and
vibration
The subproject is located in the rural area without great demand of transportation and
industrial services, moreover, there is no large-scale industrial park in the area, noise
pollution is not a problem.
2.3 Climate and
natural disasters
Rainy season: from April to October, the rainfall is concentrated mostly during July,
August and September.
Dry season: from November to March, especially in the months from July to January
next year.
Flooding occurs frequently every year due to seriously degraded water drainage
system without being renovated and upgraded (flooding period can be between 1-2
days or 3-5 days). The most serious ever incident is the 2008 flood which damaged
totally the agriculture land area for a long period, causing Large losses for the
production and livelihoods.
2.4 Topography The terrain is low-lying flat land of the Lang Giang district, which is suitable for
development of agricultural crops.
2.5 Water bodies The subproject area is located next to Thuong river, which receives drainage water
from the subproject, and supplies water for Xuan Huong pumping station for irrigation.
2.6 Ground water Currently, ground water is exploited from shallow wells (dug wells and drilled well) and
used for domestic activities. It is observed that the water is in good quality, there is no
sign of foul odor and unpleasant taste.
Ground water table depth change in seasons, shallow during the rainy months and
deep during the dry season.
2.7 Water Quality According to the observations of the Bac Giang provincial DONRE in the year 2010,
one water sample from Thuong river which is near the Xuan Huong pumping station in
Xuan Huong commune showed that the water quality from the sample did not pass the
Vietnam standards as contained in QCVN 08:2008/BTNMT. Laboratory analysis of
17
Description Subproject data
the water sample showed that compared to the maximum water quality standard limits,
BOD5 was 6.26 times higher; COD was 4.7 times higher; ammonia was 1.65 times
higher; nitrite was 5.35 times higher; SS indicator was 4.27 times higher, other
indicators were among the allowable limits.
Based on visual observation of the water on the Thuong River near the subproject site,
physical characteristics of the surface water showed no sign of scum, sediment, foul
odor.
2.8 Inundation Inundation occurs frequently every year due to seriously degraded water drainage
system without being renovated and upgraded (flooding period can occur 1-2 days or
3-5 days). The most serious ever incident is the 2008 flood which damaged totally the
agriculture land area for a long period, causing Large losses for the production and
livelihoods.
2.9 Terrestrial flora
and fauna
The dominant terrestrial flora in the subproject area is paddy rice grown by the local
farmers. Other species include the scattered trees (acacia mangium, melia..) and
some fruity trees (banana, dracontomelum, litchi, longan…) along the access roads
and agricultural crops (bean, peanut, maize, etc.), shrubs, grasses, and other common
weeds. No rare and valuable plants that should be protected are found within the
study area.
Terrestrial fauna includes domestic animals (buffalo, cow, pig, chicken, etc.) and
terrestrial wild life (birds, snakes, reptiles, etc.). Likewise, there are no rare and
valuable animals that should be protected found in the study area.
There are no wildlife species of animals listed in Red Book found within the subproject
area.
2.10 Aquatic flora and
fauna
There is no endangered species in the study area recorded in the Red Book, that should be protected.
Aquatic flora: mostly algae, mosses, and water plants, other phytoplankton, and no
rare aquatic plants.
Aquatic animals: including fishes, shrimps, snails, etc., but no species identified in the
protected list.
2.11 Protected areas There is no protected area in the subproject study area
3. Environmental and social conditions
3.1 UXO There are no UXO left in the subproject area. This problem had already been solved in
the previous construction.
3.2 Land use Total land area of the three communes of Xuan Huong, My Thai, Phi Mo in the entire
area of the subproject is 2,870.19 ha, that is broken down into: agricultural land area:
1,955.19 ha, non-agricultural area: 891.39 ha, and unused land area: 23.61 ha
3.3 Residential lands
traversed
There is one low density residential site located on the other side of the headwork and
one residential site located near the first section of the irrigation canal.
3.4 Rural
infrastructure
There is a low voltage (22 kV line) electric power line near the subproject site. One of
the electric pole (Number 55 in Road 673) will need to be relocated to the new position
15m away from the current one.
There is a road built on the dike of the Thuong river on which the current pump house
is located. Similarly, an inter-village road is found within the subproject area. These
horizontal structures . will be used for transporting construction materials and
equipment.
Medical facilities, schools, office of CPC are not located in the subproject construction
site so there is no affect.
3.5 Agriculture Agriculture: mainly rice and agricultural crops
Aquaculture: subsistence fish farming at household level
18
Description Subproject data
3.6 Population (direct
and indirect
beneficiaries)
- Xuan Huong commune has 12,009 people, its density is 1,022 persons/km2
- Phi Mo commune has 8,581 people, its density is 977 persons/km2
- My Thai commune has 8,233 people, its density is 1,008 persons/km2
3.7 Ethnic Minorities In the subproject area, there are two ethnic minority groups of Tay and Muong, but with
a very small proportion, about 1%.
3.8 Livelihood and
employment
Main occupation of the local community is agriculture with livestock raising. Only a few
households are running their small business and some people are State officers.
Average income per capita of local people residing in the subproject area is more or
less 3,500,000VND/person/year
The household poverty rates in the communes of Phi Mo, Xuan Huong, My Thai in the
subproject area are 9.5%, 16.18% and 10.83% respectively.
3.9 National/ Cultural
heritage
There is no cultural and natural heritage site in the subproject area
3.10 Public health Common diseases in the summer are: diarrhea, fever virus, dengue fever, typhoid
fever.
Diseases occur in the dry season when there are high amounts of dust: sinusitis, eye
diseases, and others.
19
IV. ENVIRONMENTAL IMPACT SCREENING
7. An environmental impact assessment is an assessment of the possible positive or negative impact that a proposed project may have on the environment, together consisting of the environmental, social and economic aspects. To identify and evaluate the impacts of any one project, there are various methods commonly used for environmental impact assessment such as checklist method; matrix method; the Battelle environmental evaluation system; and cost-benefit analysis method.
8. The checklist method was utilized, which is widely used and generally sufficient for small-scope projects having Category B classification.
Table 3: Environmental impact screening
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
1. Impacts in pre-construction stage
1.1 Loss of
residential land
and/or agricultural
land
Yes Small Negative Permanent
The shifting of the pump house and electric
substation will necessitate the acquisition of the
adjacent lot onto which the new facility will be built
on. Upgrading works in the irrigation canal will be
limited to within its existing alignment, while the
drainage canal will only require desilting and
improvement of its existing earthen maintenance
road.
Location: The new pumping station site at the
adjacent lot of the current facility.
Scope: Agriculture land area on the right hand
side of the pumping station will be permanently
acquired equivalent to 1.37 hectares, which may
result in the reduction of farm income by the
affected land owners. The impact was assessed in
the RP as not severe since none of the AHs will
require relocation and none will have more than
10% of their livelihood source affected. Besides,
the land owners are entitled to receive
compensation for land and assets on land which
have been recovered reasonably based on the
approved RP.
2. Impacts in construction stage
2.1 Erosion or
sedimentation
caused by land
clearance or land
excavation or
filling
Yes Low Negative Temporary
Location: Cultivation areas and water ways along
the upgraded canals and the headwork area
Scope: During the construction, soil erosion and
soil and stone falling into farm lands may happen.
As a result, the subproject adversely impacts on
agriculture production as non-fertile soil from
excavated embankments may cover farmlands,
thus reducing the effective area suitable for crop
production, and eventually reduces agriculture
yield and farm incomes. Similarly, siltation of
20
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
canals may cause reduction of water conveyance
capacity, thus when strong rains come, much of
the surface water run-off over taps the canal banks
and cause flash floods on the adjacent lands.
However, the subproject area historically is a flood
prone area and so this subproject is being
implemented in order to drain water during the
rainy season in order that the farmers can be able
to plant. So regardless of canal silting, the
subproject area will still inundate. What is critical is
that the completed drainage canals be desilted
prior to contractor’s demobilization. In view of this,
the impact is judged to be not significant.
Duration of impact: 14 months of construction
period.
2.2 Pollution of
water source and
soil due to
construction
vehicles and
equipment
Yes Small Negative Temporary
Scope: These petroleum-based hazardous
substances can leak from construction vehicles
and equipment during their operation, and/or
during maintenance work, and the pollutant can
spread to cultivation lands around the headwork
construction site, causing negative effects to plants
or affecting crop productivity.
Contaminants during subproject construction could
be carried away by rain and surface-water to flow
into the canal and Thuong river and cause the
deterioration of its water quality and affect the
aquatic environment in it
However, the estimated number of construction
vehicles and equipment are few, and much of the
work most especially in the canal upgrading is
manual, so the probable amount of petroleum
leakage may not be significant to affect the
adjacent lands. Similarly, construction substances
in the form of paints and thinners are normally
placed in cans to avoid unnecessary spillages; and
are to be placed in sealed and roofed storage
areas. Thus, this is assessed as insignificant
impact
Location: Along the canals and the headwork
cluster area
Duration of impact: Construction period
2.3 Noise,
vibration
generated from
construction
equipment
Yes Small Negative Temporary
Scope: Large source of noise and vibration is from
the use of construction machinery for headwork
cluster, especially the work of compaction. As the
subproject locates in rural area with sparse
population density, surrounding are fields of Xuan
Huong, My Thai, Phi Mo communes, with heavy
vegetation, these factors will either absorb the
noise or easily dissipate it. Within the subproject
21
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
area, the terrain is sloping in most areas, open,
well ventilated and covered with vegetation. Noise
generated by construction vehicles and equipment
can easily be dissipated. Similarly, the few units of
construction equipment operating during daytime is
not significantly loud to cause much alarm for local
residents. Much of the work is done manually
especially in the canal upgrading which is not
expected to generate much noise.
Location: The construction site
Duration of impact: 14 months of construction
stage, especially during time when compactors and
concrete mixers are used.
2.4 Damages to
existing public
infrastructures
and disruption of
public utility
services
(electricity, roads,
schools and
health stations)
Yes Small Negative Temporary
During the course of construction, the overloaded
and over speeding trucks may damage the roads,
causing obstacles for local people’s movement
around the area.
Collision of these trucks to public facilities on the
service road, such as water pipe, ditches, canal,
etc, may cause damages that will result in the
suspension of services.
Moving one 22kV electricity pole to the new
position 15m away from the previous position. The
dismantling, transfer and restoration of the facility
may take some time. In the meantime electric
power services may be suspended. The residential
areas surrounding are affected by temporary loss
of power due to relocation of electric power lines.
Location: The residential site along the service
road; construction site
Scope: The impact is not significant since the power disruption can be minimized under the project design, in view of : a) early coordination to be held with the electric company to inform them of the relocation work; and b) local people to be informed beforehand of the impending utility line transfer and restoration schedule for them to prepare for such event. Similarly, there is a small probability of construction trucks encountering accidents most especially hitting public utilities that will result in the suspension of services. Duration of impact: 14 months of construction
stage
2.5 Impacts on
vehicular traffic
movement and
safety
Yes Small Negative Temporary
The inter-village roads and Thuong river dike are
planned to be used to transport construction
materials and waste. These activities will hamper
the movement of the local residents due to
increased traffic volume and road occupation of
large vehicles. During the construction of the box
culvert under the dike, the traffic on the dike will
also be disrupted. This box culvert is where flood
22
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
waters discharged by the pump house will flow out
to the Thuong river.
Soils and stone scattered on the road during
transport, as well as potholes caused by frequent
travels of heavy load construction trucks, make the
dike road more difficult to traverse and may be
dangerous for fast moving vehicles traveling during
rainy days.
If construction materials are not properly extracted
from borrow pits and temporarily stored in the right
places. This will affect the aesthetic of the area,
endanger the traveling people and vehicles, and
increase the risks of accidents, especially at night
when the light is not enough.
Location: The residential site along the service
road; construction site
Scope: The impact is not Large since: a) much of
the excavation materials (70%) are fit for use as
filling materials in the embankments, and its
volume (42,658.18 m3) is more than enough to
meet the backfill requirements. The distance of
construction materials (i.e. sand, gravel, concrete,
etc. at 5-35km); as well as the disposal site (2 km)
is not so far from the site, and so the frequency of
travel and volume of transport vehicles can be
regulated so as not to significantly disrupt regional
vehicular traffic will not be significant. , Generally
traffic frequency is the area is not high such that
these will not be affected by the transport of
construction materials. Cleanliness in the work
area is a manageable impact that entails the
implementation of cleanliness by the contractor in
its workplaces.
Duration of impact: These impacts will only exist
during the construction time
2.6 Affect access
to private assets Yes Small Negative Temporary
Source: Construction activities on the canal and
works on the canal
Location: The whole length of the canal alignment
Scope: The canal works may affect agricultural
production of the local residents with farms
adjacent to the canals during the course of
construction. The narrow maintenance path beside
the canal (irrigation and drainage) also serves as
an access path by the local people to their farms.
Once upgrading works on the canal are
implemented, the section where activities are
focused, may not only affect the canals but also
the pathways. In view of this, access to the farm
and other assets of local people nearby will be
affected.
However, due to the construction method, that
23
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
relies on few heavy-duty construction equipment,
that is complemented by much manual labor, this
approach will not require the occupation of a large
area, therefore, temporary detour paths can be
installed for local people’s use. Similarly, with the
phased construction stages of the canal, the
obstructed portion will be limited to the section
where works is on-going, therefore possible
impacts on the access to private assets of local
people in the area is not much.
Duration of impact: This impact is only exist at
the construction time.
2.7 Benefits of
jobs or livelihoods
by mobilizing local
workers
Yes Small Positive Temporary
Location: The residential/commercial clusters
within the subproject area
Scope: Demand for goods in the local market,
food services and construction supply stores will
develop as a result of the implementation of the
subproject. This will provide opportunities for local
people to increase incomes or get short term
employment. The hiring of local workers during the
construction will create jobs and income for them,
which will contribute to the poverty reduction of the
locality. About 50 workers are needed in the
subproject.
Duration of impact: Construction period
2.8 Social impacts
due to the
presence of
construction
workers in the
region
Yes Small Positive/
Negative Temporary
Source: Migrant construction workers
Location: subproject area, communes
Scope:
- Positive: Workers from other provinces who come to live in the project area will promote cultural exchange, provide service and trade activities in the locality. - Negative: conflicts between migrant workers and
local people may happen due to cultural
differences and a possible rise of social evils such
as theft, robbery, prostitution, etc. may occur.
However, the workers would stay only for short
period of time because of section construction
approach, and the strict employment regulations
for workers will ensure that negative impacts is
negligible.
Duration of impact: Construction period
2.9 Risks in terms
of safety with the
local people and
construction site
Yes Small Negative Temporary
Source: Construction activities which may affect
the public health and safety of the labors and the
surrounding residential community
Location: In all the subproject area
Scope: Dust, noise and vibration, and emissions
generated during the transportation of materials
and the construction activities, wastewater and
24
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
solid wastes generated from the construction
equipment and domestic wastes of workers affect
the quality of water, soil and air which directly
affect the health and safety of the workers and the
surrounding residents.
Accidents during the construction may occur for
the workers and local residents such as falling
materials, pits, etc.
These impacts are negative but preventable, with
the coordination of contractor by using safety
measures with the cooperation of the local health
authorities. These impacts will happen only in
short period.
Duration of impact: Construction period
2.10 Issues
related to
handling of
wastes, including
domestic wastes
and construction
wastes
Yes Small Negative Temporary
Waste soil and gravels in the construction site, if
not being properly collected, may be swept by
rainwater into canals to cause sedimentation.
Domestic wastes from the temporary construction
tents may cause soil, water and air pollution if not
properly collected and treated. This will affect the
residential site around the subproject area.
Location: Construction sites and tents
Scope: Much of the construction solid waste in the
form of excavation materials can be reused. It is
estimated that 70% (29,860 m3), of these spoils
are suitable for backfill; while mud (1,060.34 m3)
and organic matter (3,823 m3) can be used in the
farmlands. The rest will have to be disposed of in
the identified disposal area that has a total capacity
of 30,000m3. Other construction waste can also be
accommodated in this refuse disposal area. For
domestic waste, it is estimated that the total waste
generation for the 1 year construction period is
about 450 kg for the 50 construction workers (at
0.5kg/capita/day X 30 workers) to be hired by the
contractor. The amount is not large to be a concern
by local authorities, and these can easily be
disposed of in the commune’s landfill.
Duration of impact: Construction period
2.11 Disruption of
irrigation water
supply
Yes Signifi
cant Negative Temporary
Source: Irrigation water supply suspension during
construction time
Location: Agricultural land area in the subproject
area
Scope: The construction of the canals requires
suspension of irrigation activities to allow workers
to do construction work along the canal sections to
be upgraded. It will be difficult to excavate the
canal sections, install brick lining, and backfill the
embankments if water continues to flow in the work
area. However this will deprive downstream farms
25
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
of their irrigation water thereby depriving them of
their income. The construction methodology,
prescribed in the design, nevertheless will entail a
phased implementation of the canal lining works,
where construction will be contained in a certain
segment of the canal, and only when the works
had been completed that activities in the next
segment will commence. Also, water diversions are
also options prescribed for adoption by the
contractor. In view of these subproject design
prescribed methodologies, the impact is not
significant, while it is negative, it is temporary.
Duration of impact : construction period
3. Impacts in operation stage
3.1 Increase in
farm incomes Yes
Signifi
cant Positive Permanent
Source: Irrigation and drainage pumping station
and the upgraded canal system
Location: Entire area of the subproject
Scope: The upgrading will solve the problem of
water logging of 1,280 ha of agriculture land of
three communes of Xuan Huong, Phi Mo and My
Thai. The upgraded infrastructures will during rainy
season, be able protect crops especially those that
are susceptible to excessive moisture (i.e. cash
crops, fruit-bearing trees, etc.), and increase their
yield. With the increase in yield, the income of the
local farmers will also increase, thus providing
them with financial resources to meet their basic
needs (i.e. food, clothing, education, health, etc.)
and improve their standard of living.
Duration of impact : Operations & maintenance
period
3.2 Effects of
drainage
pumping, water
drainage
Yes Small Negative Long-term
Source: Operation of water drainage during peak
time will involve 4 pumps with total capacity of
6,600m3/h, water volume drained from the
subproject area will be discharged to Thuong river
Location: Work system, water intake and outlet
Scope: If the intake pipe of the drainage pumping
station is not provided with suitable filters, then
aquatic life such as fish, shrimp, algae may be
sucked into the system and be discharged into the
Thuong river. It is possible that these aquatic lives
may be harmed in the process. Modern pumping
systems however, are provided with filters to
prevent the entry of unwanted materials into the
equipment which may also be harmful to its
mechanism, which may cause maintenance
problems.
26
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
However, if negligence by pump operators may
cause the suction and possible loss of these
aquatic lives, the impact is negligible since the
variety of these fresh water species is common
and no endangered ones have been reported in
the area.
At the water intake and the discharge areas, the
water flow may be disturbed, the canal bottom may
be eroded due to great and concentrated water
volume. The pumping station is only active in rainy
season, the peak time is not long, moreover, the
drainage flow coming out from the subproject area
is smaller than the drainage flow at the discharge
source of Thuong river (5.7 m3/s compares to 46.5
m3/s), the impacts on the hydrological regime and
water source at the discharge position is negligible.
3.3 Increase
agricultural
productivity
Yes Signifi
cant Positive Permanent
Source: The upgraded works will increase the
water supply during dry season that is sufficient to
irrigate the 170 hectares service area; and improve
the drainage of 1,280 hectare agricultural areas
during the rainy season.
Location: Entire area of the subproject
Scope: Drainage facility enables the farming
communities to be engaged in agriculture during
the rainy season. Without the pumping station,
these areas are submerged by flood waters. The
upgraded facility ensures all of the inundation
susceptible areas to be properly drained to a level
that the farmers are able to properly use the
affected land for productivity most especially in
growing cash crops requiring well drained soils (i.e.
vegetables, fruit trees, etc.).
3.4 Deterioration
of soil and water
quality due to
increase in the
amount of farm
chemical use
Yes Moder
ate
Negative,
positive Permanent
The upgraded work will help insure favorable
conditions for farming, thus encourage agricultural
intensification within the service area. Among the
inputs this program, is the application of inorganic
fertilizers, pesticides, fungicides and other farm
chemicals. If not properly applied, these farm
chemicals are flushed into the receiving waters
thru the irrigation system. The residual farm
chemicals in the discharge water can pollute the
receiving waters, affect the health and growth of
aquatic life, and may get adsorbed into the food
chain thru the fishes and crops harvests.
Location: Subproject service area and the
receiving water bodies.
Scope:
- Positive side: Farm chemicals will help increase
significantly the income of farmers. These
chemicals such as fertilizers are intended to
27
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION AND SCOPE Ye
s/No
Small / Large
Negative / Positive
Temporary / Permanent?
increase farm yield; pesticides and fungicides on
the other hand are focused on controlling insect
pests and diseases of planted agricultural crops
and fruit-trees thereby reducing crop losses.
- Negative side: Commercial farm chemicals are
mostly inorganic that can in the long-term, have
negative effects on the soil, and pollute the
receiving environment if not properly used.
Agriculture extension service is needed to train
farmers on the proper use of these farm chemicals
else they (farmers) may contribute to the
deterioration of the environment within their area.
3.5 Improvement
in vehicular traffic
mobility within
subproject area
Yes Small Positive Permanent
Source: Renovating and upgrading the drainage
and irrigation maintenance roads.
Location: Entitled area of the subproject
Scope: The renovated and upgraded maintenance
roads of the drainage and irrigation canals works
help access the farm lands of local people, thereby
allowing the movement of vehicles and people, as
well as transportation of goods and services in the
area, most especially during the flood season.
Unobstructed mobility transfer to higher farm
income due to lower losses, and thereafter, lead to
improvement of the local people’s socio-economic
conditions.
3.6 Improvement
in public health
conditions
Yes Moder
ate
Negative,
positive Permanent
Location: Communes in the subproject area
Scope:
- Positive side: The inundated area is drained by
drainage pumping station thereby eliminate the
favorable conditions for reproduction and growth of
harmful insects and parasites, limit the spread of
diseases caused by flooding, such as cholera,
typhoid, fever, fungal diseases and others
- Negative side: Increase in farm chemical use may
have residual impact on the health of the local
people.
The positive impact is more significant, but
measures need to be put in place to advise
farmers on the use of farm chemical
3.7 Impact on
employment or
livelihood issues
Yes Signifi
cant Positive Permanent
Source: Construction and operation activities that
local residents can take part
Location: Entire area of the subproject
Scope: Once the subproject is completed, the
agricultural production condition for farmers will be
improved, therefore farm incomes is expected to
increase, leading to better socio-economic
condition of the region.
28
V. OUTLINE ENVIRONMENT MANAGEMENT PLAN (EMP)
A. Environnemental impact mitigation plan (EMP)
Table 4: Environmental impact mitigation plan
Potential
impacts
Mitigation Measures Responsi
bility
Cost
1. Pre-construction stage
1.1 Loss of
residential and
agricultural lands
Implementation of mitigation measures as presented in the RP of the subproject. Approved RP will be implemented by the District compensation, assistance and resettlement board.
PPMU 2,493mill
(see RP)
2. Construction stage
2.1 Erosion or
sedimentation
caused by land
clearance or land
excavating or
filling
1. Site clearance, filling and earthworks will be carried out in
the dry season; and during favorable dry days during the
rainy season;
2. Upgrading works in the canals are to be done by
segments, and cleaning the site promptly right after
completion of the segment, before turning to next segment.
Contractor
Included in contract with contractor
2.2 Pollution of
water source,
aquatic
environment due
to wastes, spent
oil/lubricants,
paints and
thinners
1. Storing petroleum products (i.e. gasoline/diesel, lubricants,
paints and thinners) in the safe area with concrete floor and
roof to avoid contact with rain water and floods;
2. Ensure that vehicles and construction equipment are
maintained in good conditions by following the units
manufacturer’s prescribed maintenance schedules.
3. Regularly cleaning the scattered soil and debris from the
construction site to the disposal site
4. Arranging waste collection bins at the construction site,
tents and requiring the workers’ compliance of environment
safety regulations. Wastes will be hauled to the disposal sites
according to local regulations.
5. Prohibiting disposal of wastes or hazardous materials
close to dug wells.
Contractor
Included in contract with contractor
2.3 Noise,
vibration
generated from
construction
equipment
1. Ensuring that construction equipment and vehicles are maintained in good condition by following the units manufacturer’s prescribed maintenance schedules.
2. Limiting construction activities causing loud noise during daytime most especially those that are within or near residential and/or institutional areas;.
3. Informing residents living near the work areas of construction time and schedule;
4. Provide workers with personal safety devises such as ear protection;
Contractor
CPC
Included in
the contract
with
contractor
2.4 Impacts on
the existing
infrastructure of
the locality
(electricity,
roads, schools
and health
stations)
1. Provide information to the managers of the public
infrastructures, if any relocation is needed, a plan should be
agreed beforehand;
2. Disallow overloading vehicles that will exceed the access
road capacity
3. Minimize the transport of construction materials and waste
during rainy days;
4. Comply with local traffic regulation especially when
traversing residential and institutional areas along public
road;
5. Restore the surfacing of public roads used as access after
construction stage.
Contractor
Included in
the contract
with
contractor
2.5 Impacts on 1. Contractor prepares by-pass road on Thuong river dike Contractor Included in
29
Potential
impacts
Mitigation Measures Responsi
bility
Cost
the traffic
operation and
safety
while constructing discharge sluice over the dike to ensure
the traffic during the construction time;
2. Install signage and lighting system to illuminate
construction site located along public roads
3. Avoid overloading vehicles that will exceed the road’s
capacity.
4. Observe local speed limits for construction vehicles
the contract
with
contractor
2.6 Affect access
to private assets
1. Implement upgrading works on a per canal segment, and
only upon completion will work progress to the next segment.
2. Provide detours to allow local people continued access to
their farms and other assets thereby by-passing construction
site;
3. Inform the communities who live near the subproject area,
by posting information materials on CPC bulletin board,
loudspeakers, and public meetings; on the plan and
schedule of construction works;
4. Promptly restore construction site especially access path
after completion of every segment.
Contractor
Included in the contract with contractor
2.7 Optimize the
benefits to local
labor and
enterpreneurs
1. Give hiring preference to qualified local labor.
2. Patronize as much as practicable, local suppliers of
construction materials and services. Contractor
Included in
the contract
with
contractor
2.8 Social
impacts due to
the presence of
migrant workers
in the subproject
area
1.Considering the possibility for renting local people’s
houses for workers’ accommodations rather than building
temporary construction camps;
2. Ensure that construction camps are maintained in clean
and hygienic conditions by following the units manufacturer’s
prescribed maintenance schedules.
3.Orient migrant workers to properly communicate with local
communities and implement training programs on cleanliness
and personal hygiene, awareness and prevention of highly
communicable diseases (i.e. HIV/AIDS, etc.);
4. Developing regulations for migrant workers and
establishing management boards to oversee disciplinary
action on individuals who violate the camp rules.
Contractor
Included in
the contract
with
contractor
2.9 Risks to the
health and safety
of local people or
construction
workers
1. Constructing temporary facilities to help access to the
affected assets;
2. Notify communities living near the subproject area on the
construction schedule and timing, by posting information
materials on CPC bulletin board, loudspeakers, and public
meetings;
3. Provide personal safety equipment for the workers and
training them on how to use these equipment;
4. Ensure safety of the construction sites and restrict the
local people’s access to the construction site by installing
sufficient fencing and warning signs
5. Regularly inspection and supervision by the competent
agencies of construction site to ensure the safety of the
workers as well as the nearby local community.
6. Notify community on any the potential risks, when these
arise during the construction time;
7. Truck drivers to avoid exceeding the allowed load and
speed limits while transporting the construction and waste
materials
8. Not performing construction activities during heavy rains
Contractor
Included in
the contract
with
contractor
30
Potential
impacts
Mitigation Measures Responsi
bility
Cost
9. Backfilling all pits, ensuring that all potholes in the
construction sites are properly lighted to limit risks of
accidents for the community.
10. Disclose environmental grievance redress mechanism
to people.
2.10 Issues
related to
handling of
wastes, including
domestic and
construction
wastes
1. Reuse suitable excavated materials for reinforcement of
canal embankment or filling low lying areas;
2. Arrange provision of waste bins for workers in the
construction site and camp/tent;
4. Regularly cleaning up and transport non-usable wastes
from the construction site to the disposal site;
5. Regularly collect wastes and keeping them in a temporary
safe area before transporting these refuse to the dump site
that is isolated from water source
Contractor
Included in
the contract
with
contractor
2.11 Disruption
of irrigation water
supply
1. The community should be informed about the construction
schedule most especially the irrigation system upgrading
works.
2. When possible, construct canals during non-planting
period (December-January);
3. Implement upgrading works on a per canal segment, and
only upon completion will work progress to the next segment.
4. Provide water diversion works for every canal segment
upgraded, to allow continuous flow of irrigation water to
downstream users.
Contractor
PPMU
Included in
the contract
with
contractor
3. Operation stage
3.1 Increase in
farm incomes
DARD to assign agriculture extension workers to provide
appropriate farm technology to farmers in order for them to
further increase their production; and locate new markets to
sell the products.
DARD Provincial
budget
3.2 Deterioration
of water quality
due to increase
use of farm
chemicals such
as fertilizers,
pesticides,
fungicides and
others
1. Coordinating with agriculture extension agency to ensure that farmers are trained in the proper utilization of farm chemicals such as fertilizers and pesticides; 2. Disseminate to farmers the integrated pest management
(IPM) through meetings and/or information leaflets.
3. Advocacy and raising awareness of local people in
collecting bottles, packages of pesticides after use, not
dumping in the field;
CPCs Provincial
budget
3.3 Improvement
in public health
conditions
1. Local health authorities to hold seminars intended to raise
awareness of local people in public health issues related to
water pollution and potential health risks brought by improper
use of farm chemicals, and provide alternative farming
methods such as Integrated Pest Management (IPM);
2. Advocacy and raising awareness of local people in
collecting bottles, packages of pesticides after use, not
dumping in the field;
CPCs Provincial
budget
3.4 Impacts due
to wastes
generated by
operation
workers
1. Installing signage and developing regulations on sanitation
and safety in the work operation area;
2. Arranging waste bins in the operation area;
3. Hiring a garbage collection unit to collect and transport
wastes to the designated waste disposal area every 3-5 days
CPC Provincial
budget
31
B. Environmental impact monitoring
9. Environmental impact monitoring is implemented to assess impacts of the project related to
surrounding environmental conditions.
Table 5: Environmental monitoring plan
Mitigation measures
Parameters Location Methods Frequency Responsibilit
y Cost
1. Preconstruction stage
1.1 Implement approved RP
• Number of APs paid compensation & other benefits
• Number of complaints and those resolved.
Affected areas Interview
Monthly or when there are complaints filed
PPMU Part of RP cost.
2. Construction stage
2.1 Controlling of water quality
• Turbidity, • Oil & grease and
other visible pollutants
• Discharge end of the irrigation canals (two ends)
• River segment downstream of discharge of the pumping station
Observation
Weekly and after heavy rains
Contractor
Included in the contract with the contractor
2.2 Proper maintenance of Construction equipment and vehicles
• Number of construction equipment & vehicles maintained
• Number of equipment and vehicle breakdown
• Volume of spent oil and petroleum products collected and properly disposed.
• Maintenance area for construction equipment and vehicles
Observation Interviews
Monthly
Construction supervision consultant
Included in the contract with the contractor
2.3 Minimization of excessive noise generation
Noise level
• At the construction site of the headwork cluster and canals
• Near the residential sites
Observation,
Every month and when receiving feedback from community
Contractor
Included in the contract with the contractor
2.4 Prompt restoration of damaged public infrastructure
• Number and duration of public infrastructure service disruption
• Number of complaints raised and those resolved.
Subproject area and access road used to transport materials & waste
Observation Interview
Weekly or whenever there are community complaints
Contractor
Included in the contract with the contractor
32
Mitigation measures
Parameters Location Methods Frequency Responsibilit
y Cost
2.5
Implement
traffic
management
plan
• Number of Traffic
accidents
Along public
road used as
transport route
by
construction
trucks and
vehicles
Observation
Interview
Weekly or
whenever
there are
community
complaints
Contractor
Included in the contract with the contractor
2.6.
Provide
access to
temporarily
blocked
Properties
• Number of Complaints from local residents with construction blocked assets.
Affected
properties at
construction
area
Observation Interviews
Monthly Contractor
Included in the contract with the contractor
2.7 Proper
management
of migrant
workers
Number of
complaints of local
people and those
resolved.
Construction
camp and
residential
areas near
construction
site
Observatio
n Monthly
Contractor
Included in the contract with the contractor
2.8
Implement
proper
health and
safety
measures in
the work
place
• Number of work stoppages due to occupational accident
• Number of civilian accidents related to transport of materials & waste along public road.
• On construction site; and
• transport route to quarry site
• Observation
• Interviews
Weekly or
whenever
there are
community
complaints
Contractor
Included in the contract with the contractor
2.9 Proper
Construction
Waste
disposal
• Number and capacity of waste disposal site
• Volume of solid waste generated
• Volume of spoils reused
• Volume of excess excavation materials disposed
• Construction site;
• Waste disposal site
• Observation
• Interview • Report
review
Monthly Contractor
Included in the contract with the contractor
2.10 Proper
domestic
waste
management
• Number and capacity of garbage disposal sites
• Volume of garbage generated
• Volume of garbage disposed
Construction
camp (tent)
• Observation
• Interview • Report
review
Monthly Contractor
Included in the contract with the contractor
2.11 Insure
adequate
irrigation
water supply
• Number of complaints and those resolved.
At irrigation
service area Interview
Every week
or when
there is
complaint
from
affected
farmers
Contractor
commune
irrigation
staff
Included in the contract with the contractor
3. Operation stage
33
Mitigation measures
Parameters Location Methods Frequency Responsibilit
y Cost
3.1
Agriculture
extension
workers to
provide
famers with
appropriate
farm
technology
to increase
production of
quality
produce.
• Number of adaptors of new farm technologies;
• Increase in farm yields due to new technology adaptation
Subproject
area
• Observation
• Interview;
Every 6
months for the
first 3 years.
CPC Provincial Budget
3.2
Agriculture
Extension
workers to
provide
farmers with
appropriate
alternative
technology
in lieu of
farm
chemicals
such as
Integrated
Pest
Management
• Number of adaptors of alternative technologies;
• Increase in farm yield due to alternative technology adoption
Subproject
area
• Observation
• Interview;
Every 6
months for the
first 3 years.
CPC Provincial Budget
3.3
CPC/DPC
health
workers to
provide
seminar farm
chemicals,
its ill effects,
medical
treatment
methods,
and ways to
avoid
• Seminars conducted
• Number of health cases reported with symptoms of farm chemical contamination
Subproject
area
• Observation
• Interview;
Every 6
months for the
first 3 years.
CPC Provincial Budget
3.4 Waste
management
• Volume of garbage collected, ,
• Frequency of garbage collection
• Pumping station management office and the surrounding areas
Observati
on
2 times/year in first five years of operation stage
Xuan
Huong
CPC
irrigation staff
Provincial Budget
34
C. Environmental Compliance Monitoring
10. Environmental compliance monitoring was conducted to check compliance with operating
procedures, technical standards and/ or specification requirements for contractors in the (EMP).
Table 6: Environmental compliance monitoring plan
Mitigation Measure
Parameters Location Methods Frequency Responsibi
lity Cost
1. Pre-construction stage
1.1 Implement Approved RP
• Information materials posted at CPC board (i.e. construction schedule; schedule of meetings, etc.) • Payment of compensation and
other benefits to APs • Restoration of temporary
affected lands; • Resolution of
complaints/grievances of APs.
Affected areas
Observation, interviews
Monthly, or when actual payment of compensation & other benefits occur.
PPMU Included in RP budget
(2,493mill. VND)
2. Construction stage
2.1 Erosion and sediment controls
• Stability of canal embankment and pump head-works, • Cleanliness of canal beds.
Construction site
Observation
After heavy rains
CSC
Included in the contract with PPMU
2.2 Control of water pollution
• Fuel, oil, lubricants and paints stored in appropriate containers. • Work place regularly cleaned
of excavated soil and debris; • Solid and hazardous waste
are promptly collected, stored in appropriate containers, and properly disposed of following regulations.
Construction site
Observation
Weekly CSC
Included in the contract with PPMU
2.3 Noise reduction measures put in place
• Proper maintenance of construction equipment and vehicles; • Observance of local speed
limits for construction vehicles traversing roads thru residential and institutional areas; • Speed limit signs installed at
strategic areas along road.
Dike road, Observation
Weekly CSC
Included in the contract with PPMU
2.4 Proper Maintenance and use of Construction vehicles and equipment
• Noise level of equipment and vehicles kept at regulated levels • Vehicle emissions kept at
regulated levels; • Cargos of trucks transporting
materials covered; • Absence of fuel/oil leaks from
operating construction equipment and vehicles
Dike road, Vehicle/equipment maintenance area
Observation
Weekly CSC
Included in the contract with PPMU
2.5 Prevention of damages to local utilities.
• Construction equipment and vehicles properly managed: o preventive maintenance of
construction vehicles and equipment followed;
o Prompt repair of damaged vehicles and equipment on site;
Construction area and transport route of subproject trucks carrying materials.
Observation
Weekly CSC
Included in the
contract with
the
PPMU
35
Mitigation Measure
Parameters Location Methods Frequency Responsibi
lity Cost
o Establishment and observance of speed limits for construction vehicles and equipment
• Posting of information materials on CPC board informing the people of schedule utility service disruptions • Roads damaged by
construction trucks restored or put in better condition.
2.6 Implement traffic management plan
• Detours established such as Thuong river dike while construction of box culver under the dike; • Traffic warning signs and
lighting installed at strategic areas; • Information materials posted
at CPC bulletin board to relay construction schedule; • Overloading of vehicles and
over speeding avoided;
Public road used as transit route for construction and waste materials
Observation
Weekly CSC Included in the contract with the PPMU
2.7 Proper Management of personnel most especially migrant workers
• House-rules developed for construction personnel • Orientation held for workers
on relationship with local population, health and sanitation. • Seminars held for construction
workers on prevention of on the spread of infectious and sexually transmitted diseases (HIV/AIDS); as well as orientation on avoidance/ prevention of social evils like drugs, gambling, prostitution, violence, theft, etc; • Complaints/ grievances raised
by local people and resolved
Workers camp and residential areas near construction site.
Observation, interview
Monthly CSC Included in the contract with the PPMU
2.8 Occupational health and safety of workers and local residents
• Temporary access to blocked properties installed; • Information materials posted
at CPC boards, and public address system used to relay construction schedule and important announcements to the local residents; • Provision of Personal Safety
Equipment and training on their use; • Adequate temporary fencing
installed in all construction area; • Regular safety inspection of
work areas conducted and prompt action made on issues found. • Health and Safety
Orientations held for workers; • Provision of first aid station
and arrangements with local health facility for treatment of workers and residents; • Drivers of transport trucks to
Construction Area, Workers Camp and quarry site
Observation, interview
Monthly CSC Included in the contract with the PPMU
36
Mitigation Measure
Parameters Location Methods Frequency Responsibi
lity Cost
observe speed limits and avoid overloading vehicles. • Provision of sanitary facilities
at worker’s camp and its cleanliness. • Prompt restoration of areas
used as temporary facilities after all construction work completion.
2.9 Solid Waste management
• When practicable reuse excess excavation materials meeting technical standards for construction work. • -Suitable solid waste disposal
areas identified and clearance secured from authorities of their use. • Temporary storage areas for
construction materials including oil and fuel located in stable areas that is not flood prone and isolated from work sites.
Disposal sites and construction materials storage area
Observation
Weekly CSC
Included in the
contract with
the
PPMU
2.10 Implement waste manage for domestic waste from worker’s camp
• Sanitary facilities provided for use of workers following Ministry of Health Standards; • Adequate potable water
supply provided for use of workers • Suitable disposal area for
worker’s domestic waste provided in coordination with local authorities; • Regular collection of workers
garbage.
Worker’s camp
Observation
Weekly CSC
Included in the
contract with
the
PPMU
2.11 Continue supply of irrigation water to service area
• Temporary water diversion works installed ; • Number of Complaints filed
related to disruption of irrigation water supply, and those resolved
Canal segment under upgrading; Farmlands downstream of construction site
Observation, Interview
Weekly CSC Included in the contract with PPMU
3. Operation stage
3.1 Conduct agriculture extension work to farmer beneficiaries
• Seminars conducted on appropriate farming technology; • Seminars conducted on
Integrated Pest Management (IPM) or other similar alternative technology; • Seminar conducted on
Organic farming
Subproject area
Observation, Interview
Once per 06 months during the 5 year of operation
DARD
Provincial budget
3.2 Conduct public health awareness seminars on ill effects of water pollution due to use of farm chemicals; treatment methods
• Seminars conducted; • Health cases reported with
symptoms of farm chemical poisoning •
Subproject area
Observation, Interview
Once per 06 months during the 5 year of operation
CPCs
Provincial budget
37
Mitigation Measure
Parameters Location Methods Frequency Responsibi
lity Cost
and alternatives to their use. 3.3 Implement Waste management
• Garbage promptly placed in suitable receptacles, regularly collected and disposed in landfill of local community.
Pump house and canals.
Observation
Twice per year during first five years
Irrigation management unit
Provincial budget
D. Responsibilities in the EMP implementation
Table 7: EMP Implementation
Organization Roles and Responsibilities
Subprojects preparation Subproject implementation Subprojects operation
CPMU
Guide Safeguard Consultant during the preparation of IEE report. Review and provide comments on IEE submitted by PPMU
- Guide PPMU safeguards officer on implementation of EMP during construction period.
- Monitor progress during construction period.
- Collect environmental reports from PPMU
- Prepare 6 month monitoring report and submit to ADB and DONREs/DPC for review
- Guide PPMU safeguards officers on implementation of EMP in the first operation year.
- Monitor progress in the first operation year.
- Collect environmental reports from PPMU
PPC Not applicable
The Subproject has overall responsibility for environmental activities of subproject during the construction period
The subproject employer is responsible for environmental activities in the operation stage, including implementation of EMP
PPMU
- Assist Safeguard consultant and responsible for the preparation of IEE and submit for approval.
- Ensuring PPMU staff are well trained in environmental management
- Responsible for EMP implementation during pre-construction and construction stages;
- Ensure that details of contracts and bidding invitation documents include environmental requirements.
- Implement inspection and monitoring of environmental concerns during construction stage.
- Coordinate with CPMU on environmental monitoring report preparations
- Responsible for EMP implementation during first year of operation;
- Undertake investigation and monitoring of environmental concerns during first years of operation.
- Support the subproject employer to propose the environmental requirements O&M procedures.
DPC
Integrate recommendations and contributions of DONRE in EMP
Monitor EMP implementation through their own internal monitoring system
Monitor EMP implementation through their own internal monitoring system
Commune Supervision
Board and local community
- Involve in consultations and participate in the identification and preparation of
- Participate in environmental monitoring activities as directed;
- Participation in the solution
Participate in environmental monitoring activities as directed
38
Organization Roles and Responsibilities
Subprojects preparation Subproject implementation Subprojects operation
members (CSBs
5 )
subprojects. - Contribute ideas to
environmental assessment document once they receive it.
of environmental problems if any
Contractor Not applicable
- Preparation of site EMP acceptable to Subproject owner to meet general requirements of subproject EMP
- Allocate sufficient resources to meet the requirements and obligations in site EMP
- Prepare monthly progress report in their EMP implementation and whenever directed by the PPMU.
Not applicable
CSC Not applicable
- Ensuring CSC staff are well trained in environmental monitoring
- Carry out the EMP monitoring in accordance to contract TOR
- Prepare regular Monitoring reports and submit them to the PPMU
Not applicable
5 CSBs, established under Decree 80/2005/QD-TTg Regulation for Participatory investment supervision, dated on 18/04/2005. Article 8 of Decree 80 provides the community with opportunities to inspect the compliance, monitor implementation and evaluate results of investments in commune, including environmental impacts.
39
E. Monitoring and reporting system
Table 8: Monitoring and reporting system
Project Stage Type of Report Frequency Responsibilities Submitted to Whom
Construction
Site Environmental performance Report: The report must reflect the status of the environment in accordance with the Environmental Management Plan (EMP) on the whole subproject area during construction time
Monthly CSC PPMU
EMP compliance Monitoring report: indicating compliance with subproject EMP and monitoring results
Monthly CSC
PPMU
EMP implementation Report: indicating all activities complying with EMP in field and monitoring results.
Every 6 months PPMU/CPMU ADB/DONRE DPC;
Subproject Environment Report: indicating all environmental commitments in Subproject area and compliance with EMP
When the Subproject completes
CPMU ADB/DONRE/ DPC
Operation
EMP implementation Report: indicating activities complying with EMP of the Subproject during operations and maintenance phase
Every 6 months in first 5 years of operation
PPMU ADB CPMU
40
F. Expenditure for EMP implementation
Table 9: Expenditure for EMP implementation
Item Pre-construction
stage Construction stage Operation stage Total
Implementation of approved Resettlement Plan
2,493mill VND Included in the contract with the contractor
Provincial budget
Various
Control of waste source
Not applicable Included in the contract with the contractor
Provincial budget
Included in contract between investor and stakeholders
Impact evaluation, control of environmental risks
IEE consultant and PPMU
Included in the contract with the contractor
Provincial budget Included in contract
between investor and stakeholders
Environmental monitoring
Included in project management expenditure of PPMU
Included in the contract between PPMU and CSC
Provincial budget Included in contract
between investor and stakeholders
Awareness enhancement and accessing to environmental law system
Included in project management expenditure of PPMU
Included in the contract between PPMU and CSC
Provincial budget Included in contract
between investor and stakeholders
Training for enhancing capacity of environmental monitoring
Not applicable Included in the training budget of CPMU
Total: 28,000,000 VND (detail in Appendix 1)
Not applicable
28,000,000 VND
Community monitoring
Not applicable Local budgets ( as in Decision No. 80/2005/QD-TTg)
Local budgets (as in Decision No. 80/2005/QD-TTg)
Local budget
Public consultation
As stated in the consultant contract
In the implementation cost of CSC
Not applicable Included in contract between investor and stakeholders
Public disclosure of information
Consultant of IEE preparation and PPMU
Total: 9,100,000 VND (detail in Appendix 1)
Not applicable 9,100,000 VND
41
VI. PUBLIC CONSULTATION AND SUBPROJECT INFORMATION DISCLOSURE
A. Description of activities to date
Table 10: Public consultation and information disclosure
Consultation method
Details of activities
Consultation
Meeting for
Xuan Huong
commune
Date held 21/4/2012
Location held Xuan Huong Commune People’s Committee
Invitees CPC, Youth Union, Women Union, Father Front,
Farmer Association, Veteran Association, affected
people and beneficiaries
Methods of invitation PPMU sends invitation to CPC, CPC broadcasts in
loud speakers, coordinates with Women Union to
mobilize the women’s participation
Meeting agenda attached (Yes/ No) Yes
Minutes of meeting attached (Yes/
No)
Yes
Number of participants 56 (See Annex)
B. Outcomes of public consultation up to the reporting time
Table 11: outcomes of public consultation
Description of Issue
raised By Whom? Reference in IEE Required Follow-up Actions
Transportation accidents
from over speed material
trucks and spilling of
materials from the trucks
Residents of
Xuan Huong
commune
Impacts on
transportation,
changes in the
transportation
safety
Setting up regulations and installing speed
restriction signs with the material trucks
Require covering during transportation of
construction materials
During the construction
time, local residents
cannot get water for their
production due to dryness
requirement for
construction of canal’s
bottom
Local
residents in
the three
communes
Disruption in
irrigation water
supply due to
upgrading of
canals
Inform the local people on the construction
schedule
Women are less involved
in social activities
Local
residents
Public
consultation in
Appendix 6
Women Union branches in the communes
will participate to ensure legitimate benefits
for women
Encouraging women to engage in the
construction, management and operation of
the work
42
C. Community consultancy activities in the future
Table 12: Expected community consultation activities
Activity Participants Expected outcomes Schedule Cost Estimate Organize direct consultation meetings with: (i) representatives of commune authorities; (ii) representatives of affected households; (iii) DPC if necessary.
General community
Notify the community about activities and construction schedule, environmental management methods, and how to apply information system based on community feedback
Every 3 months for large-scale consultation meeting; Every week during the construction stage for information disclosure to CPC
Estimated in the budget for EMP
Feedback mechanism/ Fixing mistakes
General community
Feedback about questions or uncomfortable issues about construction works
Every week during construction stage
In the contracts signed between stakeholders
43
VII. GRIEVANCE REDRESS MECHANISM
11. The CPMU has developed a grievance redress and resolution mechanism for environment
to address grievances and complaints related to EMP implementation in a timely and satisfactory
manner for the on-going similar projects (Figure 4).
12. Every attempt should be made to establish a rapport between the affected communities
and the implementing agencies through frequent interactions and transparency thereby maximizing
the resolution of grievances at commune level. A three-stage procedure for redress of grievances
is proposed based on practice as follows:
(i) Stage 1: Complaints from affected people on any environmental damage caused by the project implementation will be lodged verbally or in written form by the affected people (refer to Appendix 8 for sample complaint form). The staff from commune/Commune Supervision Board will assess the level of environmental damage and report to the PPMU within 15 days of the complaint is received.
(ii) Stage 2: If no resolution can be reached or if no response is received from the liaison officer within 15 days of registering the complaint, the affected people can take their complaint to the District People Committee who will conduct a site investigation to assess the damage and discuss with a contractor during the construction stage to determine and immediately take the appropriate remedial measures within 30 days of the complaint is received.
(iii) Stage 3: If the affected people are not satisfied with the decision of District People
Committee or in the absence of any response, the affected people can appeal to the DONRE or Provincial People’s Committee (PPC). The DONRE/PPC will provide a decision on the appeal within 45 days but not exceeding 60 days
6, from the day it is
received by the PPC. In this stage, DONRE/PPC will enforce PPMU to take the strong corrective action to resolve the problems either though enforcement of contractor’s duties under the signed contract or providing necessary additional actions under its overall duties of project implementation.
13. A complaint or a case to the Court of Law may be done separately or independently from
the Project level Grievance Redress mechanism filing process. Implementers of the mechanism
should be guided by appropriate government decrees related to complaints such as: Law on
Complaints No. 02/2011/QH13; Article 64 of Government Decree 84/2007/ND-CP; Clause 2, Article
40 of Decree 69/2009; and regulation on grievance at Government Decree 75/2012/ND-CP dated
20/11/2012.
6 Law on Complaints, Article 28, Law No. 02/2011/QH13 dated November 11, 2011
44
Figure 6: Grievance redress mechanism
Grievance
Commune Supervision Board/Commune People Committee (CPC)
District People Committee (DPC)
Construction Engineer/ Construction Supervision Consultant (CSC)
CORRECTIVE
ACTION
Environment Police
CPMU/MARD
PPMU
Stage 3
Stage2
Stage1
DONRE/Provincial People Committee (PPC)
45
VIII. CONCLUSIONS AND RECOMMENDATIONS
14. Subproject upgrading Xuan Huong pumping station in Xuan Huong commune, Lang Giang
district will be carried out by Bac Giang PPMU of SRIDP in Lang Giang district of Bac Giang
province.
15. Project environmental impact assessment was implemented and main potential
environmental impacts of subproject in construction stage include:
(i) Loss of agricultural land and income from these plots due to construction of
subproject facilities;
(ii) Disruption of irrigation water service due to canal upgrading activities
(iii) Erosion or sedimentation of waterway and irrigation canals caused by the
clearance of land or earthworks
(iv) Possible pollution of water sources and aquatic environment due to improper
waste disposal, leakage of hazardous materials (i.e. fuel, oil, paints & thinners)
into the waterways;
(v) Occupational health and safety risks to local people or construction workers
16. Main potential environmental impacts of subproject in the operation stage include:
(i) Increase agricultural productivity and farm incomes due to increase and reliable
irrigation water supply during the dry season, and sustainable draining of
inundated farm lands during the rainy season;
(ii) Deterioration of soil and aquatic environment due to increase in the use of farm
chemicals such fertilizers and/or pesticides and fungicides; and
(iii) Impacts due to waste generated during operation of the work
17. Mitigation measures and monitoring have been developed for subproject, including the
following activities among others:
(i) Implement the approved RP; (ii) Implement proper waste management in the workplace, including prompt
collection of waste, appropriate temporary storage, suitable handling and transport, and disposal;
(iii) Store hazardous materials (i.e. fuel, oil, lubricants, and paints) in appropriate containers, and promptly dispose of hazardous waste materials in accordance to local laws;
(iv) Implement preventive maintenance of construction equipment and vehicles; (v) Hold orientation seminars with migrant workers on house rules for their behavior
in the workplace, relationship with local population, personal health & sanitation, and prevention of sexually transmitted diseases (HIV/AIDS); and
(vi) Implementation of occupational health and safety measures in the workplace
18. Institutional arrangements for environmental planning and EMP performance monitoring
had been prepared. Included in the plan is for the winning construction contractor task to prepare
measures and commitment to implement environmental impacts mitigation. Other task include the
Construction Supervision Consultant to offer methods, and human resources to implement EMP
monitoring works base on tasks contained in the IEE. The PPMU is also mandated to monitor
compliance with environmental regulations of construction contractors .
19. Based on the findings of environmental assessment and Environmental Management Plan
(EMP) mentioned in this document, some following conclusions on the subproject are drawn out:
(i) The Improvement of Xuan Huong pumping station in Xuan Huong commune, Lang Giang district, seeks to improve the efficiency of irrigation, drainage, and farm
46
productivity, thereby increase crop yields as well as farmers’ income; manage the risks of natural disasters (droughts, floods); and contributing to poverty reduction for the beneficiaries of the subproject. The subproject seeks to contribute to the sustainable development of rural agriculture in the subproject area.
(ii) IEE results and Environmental management plan (EMP) for the subproject indicates no significant impacts to the environment, it means the subproject is a category B activity. It is therefore recommended that further assessment on the environment in the project area is not needed. Recommendation on mitigation measures in EMP will be included into the bidding documents, and contractors will estimate total expenditure for these mitigation activities and be paid when these measures are effectively implemented. Once approved, the IEE will be the basis for implementing the next steps to ensure the project progress.
Consultant of IEE
preparation:
PPMU safety policy official
reviewing IEE:
Signature:
Signature:
Date:
Date:
`
47
APPENDIXES
Appendix 1: Cost for EMP implementation
Cost for public information disclosure
The CSC will implement public information disclosure before construction stage. Information will be disseminated to the commune authorities and local people through following measures: (i) meetings at the commune headquarters; (ii) send documents on measures, detailed construction plan in each stage to the CPC. (iii) broad cast news about constructing activities during construction stage. The documents are publicly posted at the CPC so that local people can read and understand.
Table 13: Estimated for disclosure information activities
Estimated time: 14 months Activities Frequency Quantity Cost Estimated cost Source of cost
Broadcasting on the radio about the construction activities
Every 2 weeks during construction process
2 times x 60 weeks = 120 times
30.000 VND for each news
3.600.000 VND
In the contracts signed between investor and stakeholders
Organizing large-scope consultation meeting with representatives of commune, district and the family involved in construction process
Every 3 months during the construction
5 times during 14 months
500.000 VND for each meeting
2.500.000 VND
In the contracts signed between investor and stakeholders
Stick involved information to CPC and residents
Every week during construction process
60 times during construction process
50.000VND for each news
3.000.000 VND
In the contracts signed between investor and stakeholders
Total 9.100.000 VND
Table 14: Cost estimation for implementation of capacity building
Contents Trainees Number of trainees
Cost rate (VND) Source of cost
Training on food hygiene, occupational safety and environmental protection
Workers and technicians of contractors
All workers and construction staff on site
50 persons x 200,000 VND /person = 10,000,000 VND
Included in the contract between contractor and the stakeholders
Training on environmental management
Waste sources control PPMU staff
3 persons 500,000 VND/person x 3 person = 1,500,000 VND
Included in the contract between contractor and the stakeholders
Impact assessment, environmental risk control
PPMU Staff
3 persons 500,000 VND/person x 3 person = 1,500,000 VND
Included in the contract between contractor and the stakeholders
Environmental monitoring
PPMU staff CSC Staff
8 persons include 3 persons in PPMU and 5 persons in CSC
500,000 VND/person x 8 person = 4,000,000 VND
Included in the contract between contractor and the stakeholders
Enhancing awareness and access to environmental legal system
PPMU staff CSC Staff
8 persons include 3 persons in PPMU and 5 persons in CSC
500,000 VND/person x 8 person = 4,000,000 VND
Included in the contract between contractor and the stakeholders
Training for enhancing capacity of environmental monitoring
CSC Staff 5 persons 5 persons x 1,000,000 VND/person = 5,000,000 VND
Included in the contract between contractor and the stakeholders
Training for CSB CSB Staff 2 persons / 1 commune x 1 communes = 2 persons
2 persons x 1,000,000 VND/person = 2,000,000 VND
Included in the contract between contractor and the stakeholders
Total (VND) 28.000.000
Appendix 2
Status of the pumping station’s substation
Status of storage pond
2: Photos on the existing environment
Road to Xuan Huong pumping station
Status of the pumping station’s substation Discharge pond
Status of storage pond Status of machine units
48
Discharge pond
Status of machine units
Status of control system
Status of sluice under through the water drain dyke
Drain sluice goes under through
Status of control system Discharge tank of irrigation pumping station which is damaged,
water overflows, great water loss
the water drain dyke Drain sluice
under through the road Drain canal is seriously deposited
49
of irrigation pumping station which is damaged,
water overflows, great water loss
Drain sluice
is seriously deposited
Seriously degraded irrigation canal
Consolidated irrigation canal
Irrigation canal which is still an earth canal which is
seriously sediment
degraded irrigation canal Aqueduct from irrigation canal
Consolidated irrigation canal One section of the consolidated irrigation canal
Irrigation canal which is still an earth canal which is
sediment Subproject’s disposal site
50
canal over the drain canal
One section of the consolidated irrigation canal
disposal site
51
Appendix 3: Minutes of the dumpsite identification
Subproject: Construction of Xuan Huong pumping station, Bac Giang province
Today is October 12th 2011, at head quarter of Xuan Huong CPC, Lang Giang district, Bac Giang
province, we are:
1. Representative of project owner: Bac Giang PPMU of SRIDP
- Mr. Nguyen Binh Duong - Position: Deputy Director
- Mr. Hoang Van Dung - Position: Technical staff
2. Representative of local government
- Mr. Ha van Le - Position: Vice president of CPC
3. Representative of consultant agency: Infrastructure development investment consultancy corporation
- Mr. Do Thanh Kien - Position: Director
- Mr. Nguyen Quoc Huy - Position: Technical staff
After field survey, we agree with position of dumping site as follows:
- Dumping site for subproject Upgrading Xuan Huong pumping station is in Phu Man hamlet, Xuan Huong commune.
- Expected capacity is 30.000m3.
- Distance from work site to dumping site is of 2 km
Parties record the minute to identify position of dumping site and as basis to develop estimation cost, construction implementation.
52
53
54
Appendix 4: Document of consultation and participation
55
56
57
58
59
60
Appendix 5: Details of consultation activities
Consultation meeting in Xuan Huong CPC
Women participated in the meeting
61
activities
Appendix
MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT
Sustainable Rural Development Project in the Northern Mountain Provinces
DOCUMENTATION OF PUBLIC CONSULTATION
I. SUBPROJECT:
Upgrading Xuan Huong pumping station, Lang Giang district, Bac Giang
II. DATE, TIME, AND VENUE /
Date 21/4/2012 in Xuan Huong
III. ATTENDANCE:
Table 15: Attendance in consultation meetings
Communes Total Attendance
Male
Xuan Huong 34
My Thai 1
Phi Mo 1
Total 36
IV. PROGRAM:
Topic / Activity
Introduction participants of the commune, and objectives the consultation meeting
Presentation the project origin, composition of consultants
Presentation detailed specifications of the subprojects: road length, width, road grades, road types, and etc…
Presentation ADB resettlement policies, Government of Vietnam, provincial policies and the policy framework of subprojects: the conditions of eligibility for compensation and resettlement assistance if state revenues land.
Consultation on:
- the compensation and resettlement plan for the subproject, replacement cost, measures to support relocation and resettlement required by the subproject;
- the project implementation plan;
- the environmental impacts and mitigation measures.
Consultation on the grievances and grievances redress.
Consultation on issues related to gender.
Consultation on issues related to ethnic
Appendix 6: Documentation of Public Consultation
MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT
CENTRAL PROJECT MANAGEMENT UNIT
Sustainable Rural Development Project in the Northern Mountain Provinces(ADB Loans 2682/2683-VIE)
DOCUMENTATION OF PUBLIC CONSULTATION
Upgrading Xuan Huong pumping station, Lang Giang district, Bac Giang
DATE, TIME, AND VENUE / LOCATION
Xuan Huong head quarter CPC, Lang Giang district, Bac Giang
Table 15: Attendance in consultation meetings
Total Attendance Ethnic Minority
Female Male
19 3
0 0
0 0
19 3
Topic / Activity Responsible Person / Entity
Introduction participants of the commune, and objectives the A representative of the CPC
Presentation the project origin, reasons for consultation, the Representatives of the PPMU
Presentation detailed specifications of the subprojects: road length, width, road grades, road types, and etc…
Project designer
tion ADB resettlement policies, the policy framework of the Government of Vietnam, provincial policies and the policy framework of subprojects: the conditions of eligibility for compensation and resettlement assistance if state revenues land.
Safeguard consultants
compensation and resettlement plan for the subproject, replacement cost, measures to support relocation and resettlement
the project implementation plan;
the environmental impacts and mitigation measures.
Safeguard consultants
Consultation on the grievances and grievances redress. Safeguard consultants
Consultation on issues related to gender. Safeguard consultants
Consultation on issues related to ethnic minority. Safeguard consultants
62
: Documentation of Public Consultation
MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT
Sustainable Rural Development Project in the Northern Mountain Provinces
Upgrading Xuan Huong pumping station, Lang Giang district, Bac Giang province
Lang Giang district, Bac Giang Provinces.
Minority Attendance
Female
2
0
0
2
Responsible Person / Entity
A representative of the CPC
Representatives of the PPMU
designer
Safeguard consultants
Safeguard consultants
Safeguard consultants
Safeguard consultants
Safeguard consultants
63
V. ISSUES AND CONCERNS
Table 16: Matrix of issues and concerns
No.
Issue Raised Response on Issue Raised
Issue
Who Raised the Issue/ Suggestion
Response
Person / Sector Who Responded to
the Issue/ Suggestion
1
We require a supervisory board to ensure fair and clear compensation
Nguyen Van Chuyen – Vuon village
Yes, of course. A supervisory board including representative of DPC, PPMU will be establish to monitor compensation implementation.
Phan Hong Giang – safeguard consultant
2
Apply measures to reduce dust level
Duong Thi Tuyet – Phuc Man village
Contractor is responsible to apply dust mitigation measures, such as: cover material transportation trucks, watering surface transportation road, watering trucks wheels and in dry condition
Vu Quoc Chinh – safeguard consultant
3 Presence of workers in commune will affect our daily lives
Ha Van Danh – Vuon village
Construction activities will be arranged to adapt to local holiday time.
Phan Hong Giang – safeguard consultant
4
Dust, noise and vibration affecting to people
Nguyen Thi Bon – Phuc Man village
The investor perform environmental commitments. Contractor seriously implement measures to minimize environmental impacts during construction process
Vu Quoc Chinh – safeguard consultant
5
The construction materials should be neatly put in one side of the canal during the construction time, and all the holes must be filled in after the construction.
Nguyen Van Phuong – Hoa village
The contractor is required to do that. Warning signs, lighting system are installed at worksite, yards for material concentration to avoid risk of accident
Vu Quoc Chinh – safeguard consultant
6
Participation of communities in the activities of the project
Dao Thi The – Phuc man village
Local government will cooperate with construction contractors to hire local people for unskilled jobs in construction process, encouraging participation of women.
Phan Hong Giang – safeguard consultant
7
The land buying and selling prices are timely and spatially variant, to be fair and to avoid grievance, we prefer to get compensation based on the prices regulated by the province.
Ha Van Suong – Hoa village
Yes, we will consider this and will select the most suitable price for compensation
Phan Hong Giang – safeguard consultant
Other agreements
(i) Everyone in the meeting supported for and highly agreed with the project implementation of Upgrading Xuan Huong pumping station in Lang Giang district, Bac Giang Province. Existing
64
pumping station after operation period of more than 50 years has been severely degraded. Most items of the work do not meet technical requirement serving for agricultural production of locality. Current efficiency of the pumping station is only 60% compared to the initial design. The subproject contributes to the sustainable development of agriculture-rural area.
(ii) The APs were all agreed with contents and informed about subproject scope of impacts, possible land acquisition of the AHs, fully agree with the project’s policy on compensation and resettlement assistance, accept cash compensation at replacement costs.
(iii) It is thought that the environmental impacts of the project during construction are inevitable, but these effects can be overcome with the mitigation measures as proposed in the meeting.
(iv) Accept supports for vulnerable groups such as poor households, single female-headed households, and ethnic Smallity groups.
(v) Encourage the more actively and meaningfully participation of women and ethnic Smallity people into the process of REMDP implementation, management and monitoring.
(vi) When compensation payment is made, it must be presented both husband and wife for witness and receipt.People may represent in the Community Monitoring Board during subproject construction.
(vii) All agreed with the complaint mechanism and resolve procedure in accordance with current legislation.
(viii) The women and ethnic minority are also highly agreed with action plans on gender and ethnic minority of subproject.
(ix) Participants wish to receive full benefits and rights as specified Project Policy Framework and in the law and legal documents of Vietnam.
(x) Interests, demands and comments of participants will be considered and addressed in the project cycle
VI. TIME OF ADJOURNMENT: 21/4/2012;
VII. PREPARED BY: Vu Quoc Chinh
Phan Hong Giang
Appendix 7: References
1. Environmental status report of Bac Giang province, 2010. Bac Giang Provincial Department of
Natural Resources Environment December 2010
2. Periodic environment observation result report of Bac Giang province, 2010. Bac Giang
Provincial Department of Natural Resources Environment, November, 2011
3. Statistical Yearbook of Lang Giang district, Yen The Statistics Bureau, June 2011
5. Survey data in the Communal Peoples Committees of Xuan Huong, Phi Mo, My Thai
6. The documents in the basic design of the Subproject on renovating, upgrading Xuan Huong
pumping station, Xuan Huong commune, Lang Giang district, Bac Giang province
65
Appendix 8: Sample Complaint Form
Form 32 (Issued enclosed Decision 1131/2008/QD - Prime Minister June 18, 2008 of the Inspector
General)
Socialist Republic of Vietnam
Independence - Freedom – Happiness
......., Day... month... year...
The complaint
Dear: ................................................ (1)
Full name: ...................................................... (2); Profile ID: .................... (3)
Address: ............................................................................................................
Complaints: .................................................................................................. (4)
The complaint: .............................................................................................. (5)
..............................................................................................................................................................
..............................................................................................................................................................
..............................................................................................................................................................
.................................................................................................................................................(Docum
ents, accompanying evidence - if any)
The complainant
(sign and write their full name)
(1) Names of agencies, organizations and individuals competent to settle complaints
(2) The full name of the complainant,
- If a claims representative for the agency, organization, please write the title and name of the
agencies and organizations himself represent.
- If the complaint is clearly authorized under the authorization of agencies, organizations and
individuals
(3) This content agency resolved complaints recorded
(4) Complaints first time (or the second times) for the decision, administrative action by whom?
(5) The complaint
- Written summary of the situation leading to the complaint
- Demand (request ) of the complainant (if any);