identifying critical spare parts & recommending stock...

18
1 Identifying Critical Spare Parts & Recommending Stock levels JIG & DMS Plants Camrin Janse van Rensburg 2019-05-14

Upload: others

Post on 26-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

1

Identifying Critical Spare Parts amp Recommending Stock levels ndash JIG amp DMS Plants

Camrin Janse van Rensburg

2019-05-14

2

Agendabull Purpose of Project

bull Value Add of Project

bull 5 Steps Followed ndash ASampR Asset Criticality Tool utilised

1 System Criticality

2 Asset Criticality

3 Search for Spares - Sources of Information

4 Material Criticality

5 Service Levels amp Duplication

bull Example of the Tool used

bull Consequences amp Likelihood tables

bull Rates worked at

bull Final List - Stats

bull Assumption Decisions Inclusion amp Exclusions

bull Sources of Information

bull Learnings amp Recommendations

bull Special Thanks

3

Purpose of Project

Purpose of Project

bull Identify Critical Spares to part level(BOM) and specify the stock levels to be kept on-site

4Value Proposition of Project

Value Proposition of Project

NB Only if spares are listed and kept on stock will project add value1 1 Mean Time To Repair

12 Production losses

13 Failure Avoidance ndash Components about to fail replaced timeously jobs scheduled

12 Anglo Americanrsquos vision for asset-care(P101 target) achieved ie liners

13 Possible reduction in squirrel stores ndash Trust in stores could be rebuilt

14 Reduced Safety risk ndash Preventing temptation to bridge out ie probes

15 Reduced Non-compliance risk ndash ie trip-wires

16 Artisan Overtime Costs

5Criticality Process

Anglo American Criticality Analysis Tool utilized ndash FMECA process rarr

bull Arranged SAP follow

Ore Flow

bull Performed with

MS+Production

bull Signed off - Section

Engineer

bull Risk Matrix

bull Services added

additionally

bull Elevators

bull Overhead Cranes

bull Compressed Air

bull Electrical Distribution

System Criticality

bull ForemenMaster

Artisans

bull Signed off - Section

Engineers

Asset Criticality

bull Sources to be

discussed

Search for Spares

bullCategories

bullEquipment

Criticality

bullSHE

bullMHSAMine

Regs

bull Absence of

Spare impact on

Asset

bullSupply Lead

time

bullSensitivity

bull gt 30 = C1

bull16-29 = C2

bull0 ndash 15 = C3

Material Criticality

bullPurchase History

bullNo of unitsasset

bullNo of units

across all Critical

Assets

ServiceLevels

Hyperlink to Sheet

6

Example of Tool used

7

Consequence amp Likelihood tables

8

Consequence amp Likelihood tables

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 2: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

2

Agendabull Purpose of Project

bull Value Add of Project

bull 5 Steps Followed ndash ASampR Asset Criticality Tool utilised

1 System Criticality

2 Asset Criticality

3 Search for Spares - Sources of Information

4 Material Criticality

5 Service Levels amp Duplication

bull Example of the Tool used

bull Consequences amp Likelihood tables

bull Rates worked at

bull Final List - Stats

bull Assumption Decisions Inclusion amp Exclusions

bull Sources of Information

bull Learnings amp Recommendations

bull Special Thanks

3

Purpose of Project

Purpose of Project

bull Identify Critical Spares to part level(BOM) and specify the stock levels to be kept on-site

4Value Proposition of Project

Value Proposition of Project

NB Only if spares are listed and kept on stock will project add value1 1 Mean Time To Repair

12 Production losses

13 Failure Avoidance ndash Components about to fail replaced timeously jobs scheduled

12 Anglo Americanrsquos vision for asset-care(P101 target) achieved ie liners

13 Possible reduction in squirrel stores ndash Trust in stores could be rebuilt

14 Reduced Safety risk ndash Preventing temptation to bridge out ie probes

15 Reduced Non-compliance risk ndash ie trip-wires

16 Artisan Overtime Costs

5Criticality Process

Anglo American Criticality Analysis Tool utilized ndash FMECA process rarr

bull Arranged SAP follow

Ore Flow

bull Performed with

MS+Production

bull Signed off - Section

Engineer

bull Risk Matrix

bull Services added

additionally

bull Elevators

bull Overhead Cranes

bull Compressed Air

bull Electrical Distribution

System Criticality

bull ForemenMaster

Artisans

bull Signed off - Section

Engineers

Asset Criticality

bull Sources to be

discussed

Search for Spares

bullCategories

bullEquipment

Criticality

bullSHE

bullMHSAMine

Regs

bull Absence of

Spare impact on

Asset

bullSupply Lead

time

bullSensitivity

bull gt 30 = C1

bull16-29 = C2

bull0 ndash 15 = C3

Material Criticality

bullPurchase History

bullNo of unitsasset

bullNo of units

across all Critical

Assets

ServiceLevels

Hyperlink to Sheet

6

Example of Tool used

7

Consequence amp Likelihood tables

8

Consequence amp Likelihood tables

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 3: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

3

Purpose of Project

Purpose of Project

bull Identify Critical Spares to part level(BOM) and specify the stock levels to be kept on-site

4Value Proposition of Project

Value Proposition of Project

NB Only if spares are listed and kept on stock will project add value1 1 Mean Time To Repair

12 Production losses

13 Failure Avoidance ndash Components about to fail replaced timeously jobs scheduled

12 Anglo Americanrsquos vision for asset-care(P101 target) achieved ie liners

13 Possible reduction in squirrel stores ndash Trust in stores could be rebuilt

14 Reduced Safety risk ndash Preventing temptation to bridge out ie probes

15 Reduced Non-compliance risk ndash ie trip-wires

16 Artisan Overtime Costs

5Criticality Process

Anglo American Criticality Analysis Tool utilized ndash FMECA process rarr

bull Arranged SAP follow

Ore Flow

bull Performed with

MS+Production

bull Signed off - Section

Engineer

bull Risk Matrix

bull Services added

additionally

bull Elevators

bull Overhead Cranes

bull Compressed Air

bull Electrical Distribution

System Criticality

bull ForemenMaster

Artisans

bull Signed off - Section

Engineers

Asset Criticality

bull Sources to be

discussed

Search for Spares

bullCategories

bullEquipment

Criticality

bullSHE

bullMHSAMine

Regs

bull Absence of

Spare impact on

Asset

bullSupply Lead

time

bullSensitivity

bull gt 30 = C1

bull16-29 = C2

bull0 ndash 15 = C3

Material Criticality

bullPurchase History

bullNo of unitsasset

bullNo of units

across all Critical

Assets

ServiceLevels

Hyperlink to Sheet

6

Example of Tool used

7

Consequence amp Likelihood tables

8

Consequence amp Likelihood tables

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 4: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

4Value Proposition of Project

Value Proposition of Project

NB Only if spares are listed and kept on stock will project add value1 1 Mean Time To Repair

12 Production losses

13 Failure Avoidance ndash Components about to fail replaced timeously jobs scheduled

12 Anglo Americanrsquos vision for asset-care(P101 target) achieved ie liners

13 Possible reduction in squirrel stores ndash Trust in stores could be rebuilt

14 Reduced Safety risk ndash Preventing temptation to bridge out ie probes

15 Reduced Non-compliance risk ndash ie trip-wires

16 Artisan Overtime Costs

5Criticality Process

Anglo American Criticality Analysis Tool utilized ndash FMECA process rarr

bull Arranged SAP follow

Ore Flow

bull Performed with

MS+Production

bull Signed off - Section

Engineer

bull Risk Matrix

bull Services added

additionally

bull Elevators

bull Overhead Cranes

bull Compressed Air

bull Electrical Distribution

System Criticality

bull ForemenMaster

Artisans

bull Signed off - Section

Engineers

Asset Criticality

bull Sources to be

discussed

Search for Spares

bullCategories

bullEquipment

Criticality

bullSHE

bullMHSAMine

Regs

bull Absence of

Spare impact on

Asset

bullSupply Lead

time

bullSensitivity

bull gt 30 = C1

bull16-29 = C2

bull0 ndash 15 = C3

Material Criticality

bullPurchase History

bullNo of unitsasset

bullNo of units

across all Critical

Assets

ServiceLevels

Hyperlink to Sheet

6

Example of Tool used

7

Consequence amp Likelihood tables

8

Consequence amp Likelihood tables

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 5: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

5Criticality Process

Anglo American Criticality Analysis Tool utilized ndash FMECA process rarr

bull Arranged SAP follow

Ore Flow

bull Performed with

MS+Production

bull Signed off - Section

Engineer

bull Risk Matrix

bull Services added

additionally

bull Elevators

bull Overhead Cranes

bull Compressed Air

bull Electrical Distribution

System Criticality

bull ForemenMaster

Artisans

bull Signed off - Section

Engineers

Asset Criticality

bull Sources to be

discussed

Search for Spares

bullCategories

bullEquipment

Criticality

bullSHE

bullMHSAMine

Regs

bull Absence of

Spare impact on

Asset

bullSupply Lead

time

bullSensitivity

bull gt 30 = C1

bull16-29 = C2

bull0 ndash 15 = C3

Material Criticality

bullPurchase History

bullNo of unitsasset

bullNo of units

across all Critical

Assets

ServiceLevels

Hyperlink to Sheet

6

Example of Tool used

7

Consequence amp Likelihood tables

8

Consequence amp Likelihood tables

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 6: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

6

Example of Tool used

7

Consequence amp Likelihood tables

8

Consequence amp Likelihood tables

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 7: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

7

Consequence amp Likelihood tables

8

Consequence amp Likelihood tables

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 8: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

8

Consequence amp Likelihood tables

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 9: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

9

Rates worked at ndash how long will this take me

Planned Actual Reason

Identification of System level

+- 16minsystem line

15minline ndash JIG6minline ndash DMS

bull Initially failuresconsequences were discussions

bull Failure causes amp impact understood 2nd time round

Identification of Asset level

04minasset line 103minline bull More assets than estimated

Identifying Spares of Critical Assets

068minasset line 162minline bull Time taken to search for spares unknown

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 10: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

10

Final List Stats - JIG

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 11: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

11

Final List Stats - JIG

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 12: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

12

Final List Stats - DMS

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 13: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

13

Final List Stats - DMS

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 14: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

14

Assumptions amp Decisions 5 Assets Critical on Safety Low on Production not taken

forward

6 Smallest maintainable item ie Crusher up to O-ringsGearboxes up to Gearbox

7 Do you consider Fire Suppression parts Yes youshould In this case stock kept by Contractor

8 Equipment not considered critical Walkways LightsGuards Platforms Cable racks

9 JIG ndash Assume Link One Manuals are correct dataunless informed otherwise

10 DMS ndash Assume SAP orders are most recent and correct

11 P101 targets is it best practice to run the machinewithout that spare If the spare is not there impact onasset

12 Stock level recommendations consider

121 Same spare used on different places

122 Realistic number of spares replaced in one go

1 Failure scenarios -

bull Worst possible

bull Most likely

2 Systems = Dam walls bursting Conveyor structures burning down

3 Assets = Pump or Gearbox failures

4 Consequence and Likelihood if

bull No maintenance was performed

bull No spare kept on site

bull Installed redundancy considered

bull Hard Controls considered ie fire suppression temperature probes

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 15: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

15

Sources of Information

1 Equipment changed without updating Master Data at Drawing Office

2 Link One very useful tool when used correctly

3 Pulley Register Plumber-block amp adaptor sleeve registers ndash Drawing office amp reliability engineers

4 Service Equipment ie NB Overhead Cranes Electrical Distribution amp CampI obtained from Foremen Artisans

Contractors ndash Often overlooked

5 Links to existing SAP Functional Locations

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 16: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

16

Learnings amp Recommendations

1 NB NB - Update Link OneMaster Data for Sustainability ndash One source of information

2 Linking correct spares to Functional Locations on SAP

3 Specifically - Add Electrical Distribution amp Overhead Cranes Technical Information to SAP

and Link One

4 Pre-populating with possible failures amp consequences prior to confirming with client

worked better

5 Measure time worked - Actual times will assist greatly with future work

Support Equipment Critical Equipment

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 17: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

17

Special Thanks

Team members - Scheepers Schoeman amp Darius Booyens for putting in 15hr days

Gordian ndash Jelmen Grundel for Optimizing Stock levels

18

Any Questions

Thank you

Page 18: Identifying Critical Spare Parts & Recommending Stock ...saama.org.za/wp-content/uploads/simple-file-list/... · 12.1 Same spare used on different places 12.2 Realistic number of

18

Any Questions

Thank you