i d-a277 739 final iii'l'illliiil site investigation report · the change will be to...

265
( ,• ~ INSTALLATIORET ATNPOG M I "D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report | Volume 2 Appendices A Through GVolume 1 | November 1992 0 161 St AIR REFUELING GROUP ARIZONA AIR NATIONAL GUARD SKY HARBOR INTERNATIONAL AIRPORT PHOENIX, ARIZONA *This dDoM'n a zta poved J 1•,• cp, ; cci ane++ .. d •J ita 94-09980 I 9411111111111!99O4 4 1 062 Hazardous Waste Remedial Aclions Program Oak Ridge K-25 Site * 1 O '.U T knnesscc18 1.6y ,M'Alacd d b.' MAR1 IN MARIFFIA t!NF:Rc;y S NiTl, I ~r h ' R O F I•N F :.R (; y .' "R•)• .A( " R 1; 400 *11 0 0 0• I I I II I i

Upload: others

Post on 15-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

( ,• ~ INSTALLATIORET ATNPOG M

I "D-A277 739 FINAL

IIi'l'illlIiil Site Investigation Report| Volume 2

Appendices A Through GVolume1 |

November 1992 0161 St AIR REFUELING GROUPARIZONA AIR NATIONAL GUARDSKY HARBOR INTERNATIONAL

AIRPORTPHOENIX, ARIZONA

*This dDoM'n a zta poved

J 1•,• cp, ; cci ane++ .. d •J ita

94-09980I 9411111111111!99O4

4 1 062Hazardous Waste Remedial Aclions Program

Oak Ridge K-25

Site* 1 O '.U T knnesscc18 1.6y,M'Alacd d b.' MAR1 IN MARIFFIA t!NF:Rc;y S NiTl, I

~r h ' R O F I•N F :.R (; y� �.' "R•)• .A( " R 1; 400

*11 0 0

0•

I I I II I i

Page 2: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

PI*Sc fooororn cum w0 ris 1V01ft101 is #!sOsm to wwumq Ii ho w r*%oxvw w'ioiflf -4 OWe to rI*..tw flh1t01 sedWen# awsflin a" Sources 981on1Q @Mw

W.A#Ty'atin rKn'bXStn SjC'Or 0re*nQh IN OMuto v&nafrv~oi ý1,ce1.jooLAaerS ý>m# 4rq'l1ag tIr vm~alln C.OW1=00Wl5 R.0011 1215 .iOWSM Ce0'-111W~.9 ':v .4)d V A~ ~'?32-I3V2 ana Ito It. 'A0Cq 'A M*,~W'U.Wý@" OAflW týý 0Pyr- n P t,., r? IR2~rWCP_.03

1. Agency Use Only (Leave Blanit) 2. Repor Date 3. Repon Type and Dates Covered V- .

4. Title ad Subtaite 5. Funding NurTbrs4

S 6. Authorls)

7. Perfornm" Organization Namrets) and Address(es) S. Performing Organizaion Report

9. SponsonngiMontormg Agency Nanietsl and A~ddess(tsi 10. Sponsoringillomtoring AgencyHazardous Waste Remedial Action Program Report NumberOak Ridge TN

Air Nationai Guara Reaoiness Center4 ~Andrews Air Force B~ase. Mayad 0331

11. Supplementad Notes

12. OistnibutiorvAvaiiabitity Statement '12b. Ciinbtiib~on Code

Aporcved for oublic release: distribution is unlimited

13. A~bstract Imaxiumrm 200 woras;

'14.~--~ Sujc Terms 15. Nube of P"

16. Prce Cod

17 icun Clsificaio of I.Scrt-/siia o t. 1.ScriyCasfcto f 2.Uiato dA~aRep n ncassfi d hi Pae ncassfid bsrac ' ncassfi d on

41

Page 3: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

41FINAL

SITE INVESTIGATION REPORT161ST AIR REFUELING GROUP

ARIZONA AIR NATIONAL GUARDSKY HARBOR INTERNATIONAL AIRPORTAND PAPAGO MILITARY RESERVATION

PHOENIX, ARIZONA

4 VOLUME 2 ,APPENDICES

A THROUGH G

I Submitted To:

4AIR NATIONAL GUARD READINESS CENTERI ANDREWS AIR FORCE BASE, MARYLAND

Submitted By:

HAZARDOUS WASTE REMEDIAL ACTIONS PROGRAMOak Ridge K-25 Site

Oak Ridge, Tennessee 37831-7606managed by

MARTIN MARIETTA ENERGY SYSTEMS, INC. --ce -or

for the Msicr.Fo

U.S. DEPARTMENT OF ENERGY fT7,-under contract DE-AC05-84OR21400 .

4iPrepared By:-.

I IT CORPORATION o .. .312 DIRECTORS DRIVEI KNOXVILLE, TENNESSEE 37923 -- A, -,

1 NOVEMBER 1992 J

,II

KNfWPSSI ()V/1 1-92IF1

4 I

S

m

Page 4: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

!

I List of Appendices

i Appendix Title

I VOLUME 2

A Variance and Nonconformance ReportsI B Preliminary Review of Hydrogeologic Data for Facilities Adjacent to Sky Harbor

Air National Guard Base

I C Geophysical Survey Report

D SOV Survey Report

E Soil Boring Logs

F Piezometer and Monitoring Well Completion Diagrams

G Piezometer and Monitoring Well Development RecordsI

i VOLUME 3

H Sample Collection LogsI Slug Tests and Analysis

J Potentiometric Measurements

K Results of Screening Analyses

L Tabulation of Soil Analytical Results

M Tabulation of Water Analytical Results

I

Ii

lI

h

Page 5: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

APPNDX

VAINEADNNOFRAC EOT

,, -ini nimiilI~ |Im im/

Page 6: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

jlj VARIANCE LOGI CHRONOLOGIC LIST OF PROJECT VARIANCES

PROJECT NUMBER 4__ 0__ ______ ____/ PAGE / OF I ,

PROJECT NAME •kl 1/Zroe

S RESPONSIBLEDAT VARIANCE GRANTED AND APPUCABLE DOCUMENT INDIVIDUAL

~~g- //-3 Ol C /A 'F A-fr7f-A\ &A-.ASC V/As.-ý _ _ _

ipZ ;7F l 41 F6r AAI CIA-) T3-Tn_3_4o)A6-Tc. ____

__ _ _ _ _ __ _ _ _ _ _ __ _ _ _ _ __7_ ,~A1

/ i ~/ 4 VAn A-6 6?.jA.. - 0 z-- A-- ý < AJS/_____

j -I YAL k, z- -- h/4-p omv'

/01/o 51 ,ozoc c " /X S•A /Liý

______ 2 VA. /L sj/...-

a/V I,",) SA__

Page 7: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I VARIANCE FORM VARIANCE NO._ _

j PROJECT NO. 9~- PAGE ___OF '

I PROJECT NAME ALI~ E- S-~t§ ~ DATE ='2

VARIANCE (INCLUDE JUSTIFICATION)

7Fý4 O F 5•cq~,,(' F-i kjkZ( 4 A ^A) 4AL0OCJA-rl,-O ý'C4-A( C 'CCAcA~

fO' T IL .-'z A ' ,,fAA'DZU 1`4A 6-k5 CA "-V'4Alp#Lktr Wi r fL ANI Ect 4T14,d

'ctO"C ,sP4F- IS~' Iti~J tf~Ei~~ A - A/6,550z t*_S tf -S~ 60/DkDA 7C

40 z- r" C~ -IkO&~7"J 7K O 460oc- e~ QEiTt< 5~A11&*D$t -E7ýC-

a~~o. C-7'ZT7 Fdi si--l- lv f~- /e7~i ~ - - 5 .' Pc efbr'

4 APPUCADLE DOCUMENT: 0 SI gr i-,PMft 'i Ait A// ei~ kr,,/CCQ6 Ate-

I CC: 54.k REQUESTED BY DATE L2AAPPROVED BY DATE

MM:ý/DATEk~2

I ~~DATE' ~

rxac

Page 8: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

VARIANCE FORM VRC O

I PROJECT NO. 4CT~ -PAGE ___OFJ.

PROJECT NAME Ll 4-Sc'- 1-6( !5~S~ DATE ,2kOV c

VARIANCE (INCLUDE JUSTIFICATION)

45CbV 5*fI&q$- C-&-.itCZ C, 44(,36i #6 W j:*ý ~A,6 -r& IE'JAc i4-rc7 6c~ 1,A

59Y gAAA~t woo1M ?C4.,4 ,izC fx$-A444 LX5/t"6 ~T7 dos iL9tce~ FG- A$'C

cc 75r 46 s P)C-5~ $'-oo- 15

vj44 9,cL~f E *cT-UJC Sy5rc7K~T't1if .. S4 ISZ1~, m'j McC4

* -7Z-k US4C oýPA CL E"-' 6 L*--.s f t,5w I/4/5ZG*6 d' k~O4 TL '6AIC B A6LTh WQ

4 A g*9^Kr *fgTl'* WhIU( WO01 9-ý4 -- r 0uAJc(eT1; 4 ?CA AIVUJr OF~ S--mfL 'INM 60ur~kkit-

70o coai~ *5%,,j A5 9 1 A*.3 4.~bu(&O Ap( w )r I /'

E PPUCABEDCUET 5 fcwioj~& 6 S

I C ~.REQUESTED BY DATE l-~CC -NLWmAPPROVED B DATE

DATE 1 2 q

00

Page 9: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I '

"" I =--VARIANCE FORMVARIANCE NO. -

PROJECT NO. 4•-9 2 2- PAGE / OF /

SPROJECT NAME 5-4• •DATE

VARIANCE (INCLUDE JUSTIFICATION)

~~ ,'AJý- V .4C/' J - A .' At,~ 4'-A'-- d2AA-1& AýCA-

// `4k- 5ýý A~ AL- $jct u A-AA Ar-a!

i

4 A. C S A,-Iiv--ý C-jlo A -7A -ý i,-C'a, 1

p /

II APPLICABLE DOCUMENT:

* ~ ~ / /-1, c.A, 6 --./ . - -- ~ ~ 7/ ~ )~~o A r j

S~~H#2,,vAP F',/,s -0111ý APPROVED BY DATE /?,,/•'/A

P M /rill'

0M DAT 11, I2ZC

* /• d J r& O ff ce

DAT

Page 10: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

30 00 0 0

t. ~~SBJ-02 CNRT

....... ... S

.JE .. .. .. ... .. .S1~EARA IW-0

.. .. .. ...

ASHL ARARKWJNG

APRON

UNDERGROUND-BLG5

LEASE UINE

<3 ~LEGEDJ

S -SOV ~FIGURE 4-6I SITE NO. 3S0 -SOIL B3ORING FUEL BLADDER AREA

PROPOSED SANPUNG LOCATIONS

I0 ~-MONITOR WELL 161AREFG ARYZOM ANG- I SKY M4RaOR A4PI PL7OMM AALZO"dI40 0 40 FEET IN D4EATIONALLIEUTECHNOLOGY

4-25 CORPORATION

Page 11: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

INTERNATIONAL A-77-A 6- iý I"- i-~-7H ETECKNOLQGlY___COW RATION

5 BY 61A Date 11 ~AQ... Subject 5VU 64~ bf44ý AA Sheet No .L.ofChkd BY....Date...... _11' PW FROM~ &'W~ KA. O~AProl No 40n X,

0

-7 7 -

No ~

L

Page 12: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

TECHNOOLGY VAIANCE NO. -4 XCORPRAION VAINE0......

VARIANCE LOG

4,

PROJECT NO. 409721 PAGE -" OF--.-

PROJECT NAME AIR NATIONAL GUARD SKY HARBOR DATE: 12/11 rO

VARIANCE (;NCLUDE JUSTIFICATION)

PURPOSE:

The purpose of this variance is to document a change in the

analytical procedure and equipment for on-site field screening

analysis of soil boring samples at Sky Harbor National Guard. This

change does not ^ffect the target compounds or the intended use of

the resulting data, but allows a more accurate qualification and

quantification of the target compounds.

CHANGE:

originally as stated in the SAP, a Photovac lOS50 portable gas

chromatograph (GC) using headspace technique was to be used to

determine relative concentrations of the target compounds.

The change will be to replace the 1OS50 GC with a SRI model 8610 GC

equipped with an PID and FID detector in series, purge and trap,

and Peaksimple data system. The onboard integrator of the IOS50

will be replaced with a laptop computer and printer.

APPLICABLE DOCUMENT:

I ~~~,$4,4dAW4 Al)f-

CC: $ .jjy (ntmes.) REQUESTED BD ATE:

I ,APPROVED . DATE:

00DATE: 0L00 0I

.! 000

Page 13: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

,I2WERNATIONALTECHNOLOGY VARIANCE NO.

VARIANCE LOG S

A"

2PROJECT NO. 409721 PAGE -OF-

PROJECT NAME AIR NATIONAL GUARD SKY HARBOR DATE: 12/11' 90 0

VARIANCE (INCLUDE JUSTIICATION)

JUSTIFICATION:

1. The headspace procedure is an indirect method fordetermining the concentration of compounds. The use of

the SRI with the purge and trap allows direct measurement

of the compounds. Because of the direct measurement:

* lower detection limits are obtainable

there will be less variability of measurement

therefore the data will be more accurate

* less sample prep equipment is required causing

a reduction in cost, time, and potentialbiasing and errors 0 *IA

* more accurate simulation of standard laborato-ry procedures

2. Because the SRI utilizes the FID and PID in series it is

easier to more accurately identify and quantify thetarget compounds in a complex chromatograph by comparing

* the results of the two detectors. The 1OS50 only utilizes

the PID thus relying more on the operators interpreta-

tion.iS

* APPLICABLE DOCUMENT:

0 CC: REOUESTED 8Y;,L)e IDATE:/

APPROVED BY: DATE:PftIW MeWW S

_ _ _DATE.WO -MW OMfW

_ _ _ DATE:

LA-

0

Page 14: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I"IERNATIONALTECHNOLOGY VA N

ORAONVANC NO.____U,

VARIANCE LOG4"

3 2PROJECT NO. 409721 PAGE O.0F-.

PROJECT NAME AIR NATIONAL GUARD SKY HARBOR DATE: 12/11/90

VARIANCE (INCLUDE JUSTIFICATION)

JUSTIFICATION (continued):

3. The interfacing and utilization of a laptop computer by

the SRI allows chromatographic data to be stored on

floppy disk in a format that permits the data to be

easily stored an recalled at any future time for reexami-

nation, integration and manipulation. The 10S50 does not

allow this without the addition of extra peripheral

support.

4. The higher level of technology in the SRI allows the

operator to easily and more accurately control the GC

operational parameters thus allowing for more accurate

qualification and quantification of the target compounds

APPLICABLE DOCUMENT:

CC: REQUESTED Ba DATE:LIAIIAIF

APPROVED BY: DATE:

DATE:Q~f Asfmf OMsW

DATE:

0 000000 *

,mWW=,'

Page 15: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Di VARIANCE FORM3 ~VARIANCE NO.I

PROJECT NO. 2'?-J, 6 PAGE / OF___

PROJECT NAME ixiA(Y *U~z AiJ6 - 5'!DATE // AIA,' 9/

VARIANCE (INCLUDE JUSTIFICATION) S-2- AA.J) )A-

oy a<1 - 5,V ae~ i -~.~ c~ o0 • ' Yo m a6 1Q ý ~pc ;.c .Ac-v-oi r ý 4 q A) c y-4t A

/,sS 1*4( SC A•e4 4 b, rmeadJ (o ado/o, lroý,If) I~d01 . ln pc/)o"&";

~ ~Jr~.r -4Q-6 7Th"e.. zc/ '.-~ m OiAC

s-,,.b( Jý .;y_ $o-k5r-ev_ ctmý ^g4 ckS

APPUCADLE DOCUMENT:

* CC: Wu-4)REQUESTED BY DATEJAt9

A ,APPROVED BY KIDATE

4v* 77 DATE Ilrd9

ItyI

0~(lm DATE0 00

Page 16: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

;i z -

-j I .-

it

II

30 50 psitM7 I I LIM

acaspIk SCAI MA7IJ 1.189

pe C.*I Imd5.L SIMONPe C~r tv*.01 c".

No. WlliVwf.

410 * 0 0 5 7

Page 17: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

tcA

-. ~-~- c:_ ____ __

to: : . . _ _ _ _ __ _ _ _ _ _

3-- 40- Pan . ~ - --

UT.0 1.11

TEt-, cflop__ -v w%4^!PpC~ Loýs

-lli - - - - - .

- - - - - . m

Page 18: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

NOW

VARIANCE FORMSVARIANCE NO.

PROJECT NO. " oZL,:c PAGE / OF 7.

PROJECT NAME , 6'" - DATE ,/ ,'

VARIANCE (INCLUDE JUSTIFICATION) J/, ,,--"-" §o,___ . --

4 /$,jo, Ct<.A.•fcA,, o¢•'oS -; z - 4vi<-k •'<' '• L'• '• •-_,.

2A +- ,•.-QL• C • s-•--'sxr• !-° -& •'• '•< '•:

_:", •/..• ,t, '•~• p•-v L "" .- '.-:4,<-•_-V ,..•.V-,V

c-j (F,~ -19 C L- Ar-

IPII "I

II r.• ] " " • ' L ., < .v• ¢-~ 'C 8 ./ f .'& s . - ,. l.' , .,- ; -'- 4 c . A . t , , • - - , 2. • = •'. -A ,-2 ~ A L , - • ,s & • - , • •

ý,CA

c)O/A-Ao 6 '--- - '

APPUCABLE DOCUMENT: r,, ",',f I VW, S- ".'"

CC: ,--', - REQUESTED BY DATE JJ %'APPROVED BY DATE /

4 ~ m~~2R1~)DATE qcA /

,II

. 0 0 0 0 0 0 0 0 0D

Page 19: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

:- Sky Harbor Coordinates:

U D• - "z:•zc- Des,

0

S"- * - : z L P"'•¢C ... CE -S, '2, CC• _ , * ,• " ÷" '• " -

iiJ

t2L

HI

-I KH L-

-~ I- 7

:>., . ~ __ ____ I _ ____ ___

, . :.

4+ Inm0l mm m ]mm m m m,0 ,m0 0-,,,,-,- 0. ,

Page 20: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

41 ý'. >NO WELL CONS PUCTI0N' LOG -- s-rc a r C

if-'c N o. Cl C ent/Drc le.---.~t: ~ t

Ee C:O--c..N

M~e~*/Type

ev~~~~~~~~~~D Dameter ___________________

AA At~ GUARD DSS (,N)

Ccrnpcs~t cr~ & S.Ze________ _________

_____! SEP, :,I Z S

TypeD:arneter______________________Total Ler=t, (TOC to, TOS)__ ____________

Vert!etec Cap (Y / N

C'POUTCcmccsit:cr, & Propcrt~crs _____________

Tremtec ( Y / NInterval 865

4CE?-ý17PALIZERS (YIN / NDeptr'( s)_______________________

SEALTypeSource _________________________

Setuc/!icraticrn t~me - Vo0 F~uc Acce-

______ Tremiec ( Y / N

F!LTER DACKType________________________Amt. USeCC_______________ ___

TremeC (Y/N)* ~~~~~Source_________

C-r. S;ZeDs.______________ ____

Type________________________Diameter___________________ ___

SoCt Size & Type _______________

Intervai t3 _____________________

!rer'21 E5. _ _ _ _ __ _ _ _ _ _ -

4~E (Y7 ~W

-7

Page 21: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

T>ýTO i N3 4/ELL CONISTRUCT ION LOG -- Stercarc F 'uSr tcrl,0Ir~a*22 t~cr Sky Harbor Coordinates:Se

Ictatr 7Z ] Ccrtlr-2c~cr-ztrt. I Comc. Erc. (__

XrOTEC-TI VC CSGev r-1ater~a! / Type

D' aneter ___________________

E -sDevtt BGS__________________Waterticrt O-RPr ( Y 1,4N

E, ev. SURFACE p)ADCoiccs~ticn & 5ze _____________

4Breatrhes W'tI) Va(c~se Z~re (Y /N)

RISER DIETypeDiameter____________________Total Length (TOC to TOS)____________VerntilateaCap (YIN)

Compos It ion & Prc~ort Icrs____________

Tremiea (Y /N)Interval BGaS

4 CENTPALIZERS (Y/ N)IePtth( s)__________________ ____

SEALTypeSource______________________ __

- ________ - ~Setuip/1-1yaration time - Vol.........o Fiu-c t-c:eTremied (Y /N)FILTER PACKType_____________________

- ~~~~Amt. Ljseo ___________________

Tremec (Y/N)Source________________________

Gr. Size Dist. __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

SCREEN

II ~~~~~~~~Diameter__________________4 I S~ot Size &Type ______________

BUM (Y/N)interval 85-3

4 _____ -,.ttcmnC0 (Y/N)

_____ __ I

Page 22: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

E EL ý'E N'T LO 0 r~~gd k-&-Sky Harbor Coordinates

IDev Ccr-:c-

:.v E

-- ,a~rn,7 cr!wcwr ~r'-: a

t-- -ar r-;:

_________ca''. crato'A' cu:l ='Zr-Znc ___________ fta _________

T .. e rýLev''e T~.tM t C a tV Tem coc H Crcu.c- v tv

STOS

Page 23: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

L I

11 I 1 1 I

4 -L

I I t

Page 24: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3 -r:: Sky Harbor Coordinates

X,

A: ~ '-- _________L NA:) Chrezk Y/N DI

7"... Tc 'I-eas'-re Trý:kcre~s ar: Sar-n'e Free Pro:,.:t ("lake, rý:ce e

De ":Tc: as': Bc:m of S--een 'er a____________

7-~~ ~ Sa,,> a-:

7--~

N: r k ý)6 7Gasf Ga~s/CsEc vcý _______ -,~ o.. _____~x - C ( 3 s: .: ______4

4 -a

:----'*a:. Hz~rC- Dum: U Gas Lift/ D-s~acemert :ým. ~Jcter ________

t.:.crert (M~ake, ýýcce', etc. ________________ re)etD :r

Z -,Crta rer:zef7 ( Y / N )Avc~e :),r-e Pale. _______c~m

A::aIEase cs Dent, DeotnOf Ccnc, Turtv2C te' To wtr k eprHuro te Crm"7T Tine Iintake~t) () aS.) in2 (NTa) O'r r r

4 - ___ _ - ___ __ -7KW-_ _

Page 25: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

T C- w :O-7 WL L S 'L 3 L FCyEL

i2 > Sky Harbor Cgordimatimm E

______t JO Fa' 5~___ rt Ec7:

2Cf r.:e Y/Nz-ýY 4

Deccaec5'::- mE 52Xcefir CflE Baer~ 7ef:

S *: -. c Ev:L-rnert (rl~ke, icce!, etlc.)

5 am -r :E cl :;.-et ecc 'c c Y/ N

I' .Z cr c~s--ete taiýe,, DeotU'(S) wr'ele ;urn; set.___________________ -

~; Arv~e rc'e)VCA SVA ETALS C.47:~CB O~ A~NS

~-e~a z (:!-cle) F i Iter-ed Urf 1 terec E~c t r

- Ls Y/ N Perer-- yc YN

Page 26: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Sectin No.: 6.0RwAtvton No.: 1

FIgure 6.1 oat: 2MO/b0 XsPage 4 of 6

VARIANCE FORMVARIANCE NO.- -

6PROJECT NO. 09:1 Z-. PAGEL OF __

PROJECTNAME --Li DATE I r -Q~ 9'

VARIANCE (INCLUDE JUSTIFICATION) 5 -A--qP'oý- $i

/sx on^ o" CA .Y'dfOj-- / 0 e1.j ",V se . 4 t C'05+- fC-44vc C of. -c ze

t,ý4 l 1 ''*, 144 -,;I I kL cc//er- wk S t 4~1 t tl, 44W 0& A C ..Wf•@f4~c/w* p ~ am~ &ý ;fl~iyI jp ov" wa,4 ý J *cA

4uV - , L'P. s (e 1i;ic pet (~4 <1 0- 51fte -7. 1 ,u4, dj AA -4 - tt\1 L /.. Lora,

~A)~41 ~ 3 ~ysCO.)J/ e4 IjJ A.,iE we, 4t.-Lkl#

I~~ SSky /A44e, CiA -e-ro5JC

do, vs 0 /a/ L( APRVED ,a BY:4-44 k

0 S S S0 0 05

Page 27: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Section No.: 60Revision No.: I

Figure 6-1 Date: 2/09/90

Page 4 of 6

caro"" VARIANCE FORM

PROJECT NO. qH 2.I PAGE 1 OF L

PROJECTNAME htarhor AD DATE 1/ I,/gl I

VARIANCE (INCLUDE JUSTIFICATION)3/ 4 A•vP--- /. Av.At../'/ "•..,"T&

ThK. 0trrtAA- CUP &Zm J Lkýt CoMC'% YQ

By y\1r' 6'ý C HeL) 61- r*e

0T- /S 0 0D0 6

'! APPLICABLE DOCUMENT: ý,64 PlL latt, •) - Anvvb

15. G•Jn Q•' Ull-/ur (e Officerr

•"-'•*•' •!•-,",•t •,'•J •-• DATE:•

0 0

Page 28: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

* i~i~i VARIANCE FORM VRAC O

PROJECT NO. _________________ PAGE Z. OF I.

PROJECT NAME Y4/,(oC ~~ DATE ZZ JAIV9/

VARIANCE (INCLUDE JUSTIFICATION) 5.7z -41,P j-Srior-' ei- SaIL~ ~ i

.f.C4,.//LJe 3I4f/-4 q

6- colk,,4dah 4' Svvyt /-/7ire

.4

4dk.%4 4 4 4 too lo Lcad444 moi

APPLICABLE DOCUMENT:

CC: lbon- REQUESTED BY DATE '-'I.~~4OL4~~(I 'H~ APPROVED BYDATE

DATE 94.7%W.2

4~aa fie

44AUý DTE -A4S

Page 29: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

- ESslaan No.: E0~., 'F~gw.-1cm: 2"N/o

______________pop 4 off

VAM~ANCE FORMVARIANCE NO.

PRoaaCTNo. "4,11 N PAGE L.OF I

PROJECT NAME '5' AA ~a Ar~3 i. DATE LL L

VAINMCE (INCLUDE JUSTIFICATION)

J~ ?44' gt 4 81 -J~U .4A 4n& M~, rA h.. Awl., V3Rf

C4 VO ~ tL. A 0.4. ýC -b f; (C~.*.wL4) 4. P, q-..

0AhA at Sky N&4W s:-z iL fi4 Pw.A; IracApP iA*.j M t.af-I(A f.#vRi

k+4 OR 4 %- cox-1 ew4-4c wl-;- wa. ?aa-. i&l* RGUSID Y __

d43.wAýeZý P44g.

4. "f 4 w

qeco" ,., &,a

it~~~~~~~~ ~ ~ ~ ~ 0e,0 4- t :* .A4I 91 w ,d vj , RC M 6.Cf

10 -. tt4 Atm40v a0 141 0e~ w

Page 30: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

moawwNo. I0pops 4 of a

L cii~ VARIANCE FORM 4VAMRANCS. NO,

PROJCT NO. __ _ _ _ _ _ _ _ _ _ _ _ PANI 7- O

IPROJECT NAME -•X- FO-IA Af46 51- DATE 13 F svVARLANCE (INCLWOE JUS11PICAI'ION)

& i las jsfdr.cp4c'JA.r

APPROVE BY ____ _____DATE ___

Qualy Aemnce 0m

____ ____ __-DATE

0 0

Page 31: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

.v- 3-91 FR: :0:28 HAZRP FAX NO. 6'54353269 ?.j,

RvioDocument No.: DOEiWP.100

Date: July 1990Pae 5-1 of 5-4

HAZARDOUS WASTE REMEDIAL ACrIONS PROGRAMSTANDARD OPERATING PROCEDURE 5

GROUNDWATER SAMUO WITH BAILERS

i. OBJECTIVE

The purpose of thiA procdurc is to define reqairceacou for the coletko of groundwater4 Usmples.

2. BACKGROUND

Metbods used for the collection of roundwater samples icdlde bailing and a variety ofpumping technique. Bdlem are bollow cyladen with undirectional (open up) check valves atthe bottom cud. Some bafles may also be coed or valved at the upper ed& Baile used minenviromental appaittionos are typically contructed of stainim reeL dposable nylon string,diapmable monofilentent polypropylene, Teflon-coated mtainless steel wire, or Teflon, with

4 stainless stel or Tdon being pmreerred. ThM ba is lowered into the well on an acceptableline or coated wire ine until submerged. 7w bailer i thea reuveyed to the surfae for samplecoilecion. lthis procedure de'cribe groundwater umpling with bad-er. For the best rmults,the sequence of sampling is from ilast to mot coazaminated wells. It is preferable for mostsampling events sing balml to have dedicated bailers or enough bailrs to last for I day'sw, h of samiping (normally 6 to S/ld

4

3. RESPNSYBILITIES

•,~ Th: e She Manager ir mpouible for emuring that field personnel are4 trained ian the we of thi promdum and for vezin that groundwater sampls are collected in

accordasc wth tw pF udur

x~i" - -The Project Field Osologist bs responsible for complying withti procdure., inchidig sample acllction, packaging, and dnemattiom.

4

4

4

00

4 0 0 6 0 0 0 _

Page 32: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

.Y- 3-91 FRI 10:28 .AZWRAP F• NO .4"5S269

Document No.: DOEJHWP.IOO

Revisio 0Dae. Juy 1990Pape 5-2 of 5-4

k REQrUIRD EQUIPENMENT

0 For surace sample - bailer "ap.* For specific depbt - boilcr typee Bottom-filling bottom-emptying bailer (with bottom release, if needed) of the

appropriate material.a Cean rope or wire line of suficiet lenth for conditiom.* Appropriate sample container; with labels and presrvativ, as required.a Hard plastic or steel cooler with cold packs (or ice).* Water-level meter andor other wtae-kel measuring device.e Temperature, conductivity, pH. dissolved oygn sad organic vapor meters, if

* Plastic sheeting.* Decoontamination supplies, s uquiredo Personnel proteetive clothing and equipment, if reqlred by the site-specific health

and safety pla* Latc. or poly l chloride (PVC) glovs

S. PROCEDURE

The following steps must be followed when sampfng goundwater with boflers:

1. Put on protective clothing and equipment as specifed in the site-specific health andmisety pla

2. Prepare f si for sample aequsition by covering tn pound surface around thewelhead with plasti sheeting. ArrWg doe requir samplin eqpupmet forconveciect um If o*4kae dueonuinatioe a rmqukv4 arrange the necssarysupplies in a nearby but separate location, way hom the deal d.

3. Open the w•e md noe the condition of the caing and eap keock for vaponwing vapor aaung equipmeaL Uaig a waer4ave meta, determine the staticwater level and depth to well bottom. Record th& winfomation, in the field logbookor on the water sampling, frm.

4. Purge the well aeordin to Hazardous Waste Remed Actiow Prpm(HAZWRAP) Standard Operating Procedure (SOP) 4, if noe already anpllished.Alow, ft wwr loeel to remr to a depth at lest sufcien for the completesubmergenc of the bailer vithout contacting the well bottom.

S. While the wall is recovering from purging. decositnlnase the boaie. If the bailerwas decontaminated bhore arrival at the site, t protective wrapping.Securely att•a the bailer to the m The eod of the 1ln sbould Am be secured.

i04

Page 33: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Document No.: DOEJHWP.100Revislio: 0 3Date. Jul 1900Pale 5-3 of 5-4

I-r

6. Arrange the sample container in the order of use. Volatile organic analyte (VOA)samples, if required, will be obtained fiat. followed in order by semivolatilm(SVOA) and other samples. S

7. Lowe the bailer into the well Do not allow the bailer to touch the cuing. Thebailer should enter the water slowly to prevent oratlon. particularly when VOA andSVOA samples are being collected. Do not permit the bailer to contact the wellbottom.

& Retrieve the ed bailer to the surface. Do • allow the line to contact thegroimd. Hang the bailer from a bailer stand or other auppor. if available, or have 9an amistant hold it off the ground. Te first baller of water should be used as arinse and then dkeandd. Immediately obt any required VOA and SVOAsamples by using the release valve to gently tranfer water to the sample bottle.The sample bottle should be tilted when fli to prevent aeration. Cbeck thetiffed vial for bubbles. Thie fBwt volume of sample should be used as a rinse andthen dicarded. wa tie ample baedi cota ptservatime. If simple filtration is

4 requied, it should be done as son as posible. or after ample retrieval. E aftercollecting VOA and SVOA ample, the Wto requlied simple volume is greaterthan the water remaining in the bailer, decant the water into a clean compositingcontainer. Mw compmiting container must have adequate volume to contain theentire volume necesary for collection. Apa lower the bailer to collect water foradditional sample volume, if eeded.

4 9. When the compmited sample volume is suicient, decant water into the remainingsample containers. Add prmervatic (if needed), cap, seal, and properly label allcontainers. Plaw the filled containers in the cooler(s) immiediately.

10. Record sample types and amounts cleted, and time and date of collection in thefield logbook and on the groundwater sampling form per HAZ WRAP SOP 1. PartsA and B, rswpectively. Prepare hobok-ciody and analytic request documents as 1required by the project quality murance plan.

11. Decontaminate sampling equipment acording to HAZWRA? SOP 14.12. Clean up the area and place disposable materlak (plat sbaeeting. gkows, Trek) in

the designated reoeptle. Closu and lock the wel cover.

4 6. 1RESTRICTION&UM ATIONS

Obtain cn.site data suh a temperature conductivity, pK or d•hved oxygenmeasurements after sample have been collected. This May require additional time for well

4

4 0 , 0 II [

Page 34: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~Y 1FRI. 10:29 h.AZWAIFJ FAý. NO. 4 26

Dmumet X4(.. DOEriwp.wooR~vimoa0Dama July 19904 Pap 5.4 of5.4

7. REFERENCES

4 ~~Driscot] F. 0., Grndwate and Wefts, Second Edition, SL Paul, MinnagoWa Johnson Div'isin,L -S. Enviownenwil Protection Agency, A C&Wm~ndAimm of &wpfunId Fied 0pmam,, Mfetsaa±,EPA/540/P-87/001, 1987.U.S. Eavirommcnai Protection Agency. Mwanua of Wow Well Conwuicda, Pnac*esEPA/570,9.75.o01, 1975.

Page 35: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

1 3-9' FR: .0 29 H Z rA FAX KO 6'54353269 ,

IM'

POSITION PAPER NO. 2

OEVELOPMENT AND SAMPLING OF LOW RECUARGE WELLS.

Hydrogeology Support Groupiazardous Waste Remedial Actions Program*

Martin Marietta Energy Systems. Inc.Oak Ridge, Tennessee 37831-7106

1. INTRODUCTION

A low recharge wall can be defined as a well that does not recover to90% of its static water level within 6 to 8 h after being purged. There are

4 many other definitions for low recharge formations; however, this is the onethat the Hazardous Waste Remedial Actions Program (HAZWRAP) will use in itsdiscussion of this issue. Low recharge formations can be found in most of thefollowing environmental scenarios: fine-grained, unconsolidated material suchas clay, silt, shale, or clay in the interstices of larger-grained material; 0or igneous and metamorphic rocks. Under the above conditions, four problemareas surface when it is the task of the hydrogeologist to obtain arepresentative sample of the groundwater from these types of aquifers. Theyare: how do you reduce siltation within the well, how do you develop a lowrecharge well, how do you purge a low recharge well, and when do yoL samplefor volatile organics after purging a low recharge well? *

In the following document, we will discuss these issues and present themost recent discussions with regard to these issues. It is the intent of thisposition paper to make the hydrogeologist aware of the problems associatedwith low recharge wells and to provide some guidance on the above issues. Forthe purpose of this position paper, only low recharge aquifers composed offine-grained, unconsolidated materials will be discussed.

2. SILTATION AND DEYELOPI4ENT

2.1 STATMENDT OF THE PROBLEN

Siltation and development problems are usually relegated tounconsolidated sediment aquifers. These are generally not problems associatedwith slow recharge in consolidated sedimentary, igneous, or metamorphicenvironments. Both of these issues (i.e., siltation and development) will be

*Operated by Martin Marietta Energy Systems, Inc., for the U.S. Department ofEnergy under contract OE-ACOS-840R21400.

4

I

4 0 0 •

Page 36: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

discussed concurrently since, in general, they are related issues (i.e.,siltation is largely a problem of ineffective developmnt procedures and/orwell construction techniques).

Siltation Is the process whereby, during well construction and/ordevelopment, small-sized aquifer material (generally smaller than thatretained on a #50 US standard sieve) can be found within the well casing,making the water sample turbid. It is of note that this same grain size range(i.e., less than #50 standard sieve size) makes up over 30% of the aquifersaterial, which is the principal reason why the formation is a slow recharger.This material ends up in the well casing usually by two methods. in thefirst, the fine-grained materials are introduced into the well casing directlyduring well installation. This usually occurs at the same time as the wellscreen, filter pack, and riser pipe are placed at the bottom of the borehole.From the time the borehole drilling is complete and the well Is placed,groundwater will move up into the auger flights, carrying with it anassociated amount of aquifer material due to hydrostatic pressure. Thescreen, casing, and filter pack are introduced directly into this 'soup',thereby introducing the fine-grained material directly into the casing. Alsoduring placement, the aquifer material may become integrated with the filterpack material during placement of the filter pack.

The second siltation problem area occurs during development. Inmonitoring well construction, the purpose of the design of the filter pack isto retain 95 to 100% of the aquifer material. In general, this is not alwaysaccomplished because all too often the well screen size and filter pack sizeare selected before the field investigation (i.e., during the work plandevelopment stage). During this stage, when they suspect slow rechargeaquifers, 10-slot screens with Ottowa #1, Moare 0i, or equivalent filter pickmaterial are selected in advanc, of actual field Information. The developmentprocedure, therefore, must clean out the residual materials in the well casingand must also pull the fine material out of the filter pack since it wasplaced and comingled with aquifer material during placement. Therefore, dueto poor construction design, new aquifer fine-grained material is pulled 4ntothe casing during development because the filter pack material cannot retain95 to 100% of the aquifer material.

This represents a synopsis of the siltation and development problemsassociated with monitoring well construction techniques. The followingsection will discuss some of the more recent published articles relevant tothese issues.

2.2 PALISIED APPROACMES TO SILTATION AND IVELOPMEDT

2.2.1 Well Construction Nethods

The key question to be answered in assessing well construction methodsin low-yield aquifers is, "Can well-designed construction techniques improvethe quality and quantity of groundwater samples from a low recharge aquifer?*.In review of the literature, the following information is submitted forevaluation:

S. _•- mmm m m l ill i i • iii .. .... 0

Page 37: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

--. •V- 3-9L FR: '.0 30 KUR£P FX NC, 6:54353269

C

33

o In a study conducted by Paul, Palmer, and Cherkauer (1988), a seriesof ten wells were placed in glacial tills. Of these wells some hadbeen installed wet (the well was not cleaned out of excess loosematerial before well placement) because of delays in setting thescreens, and some had been installed dry (the loose materials hadbeen removed from the borehole). Of the wells installed wet, thewet wells exhibited 50 to OO times greater turbidity than wellsinstalled dry.

o In an article in Groundwater Age (Wehrmann, 1983), a method that canbe used in clayey environments, where an open borehole can besustained, is to pump water down the inside of the monitoring wellcasing, out the screen, and up the annulus of the borehole. Thisshould be done both before and after the gravel pack is emplaced tofree fine-grained material from the surface of the borehole and thegravel pack materials. Circulation should be continued until thewater coming up the annilus looks clear (Wehrmann, 1983).

4 o According to Nielson (1988). the continuous-slot, wire- wound screenis more effective in preventing formation materials from becomingclogged in the openings. It allows particles slightly smaller thanthe openings to pass freely into the well without wedging in theopening, making these intakes nonclogging.

o In an article by Gass (1989), drilling methods and well constructiontechniques must be adapted to minimize borehole damage before theinstallation of a well screen (commonly referred to as 'skineffect") and a filter pack, or at least to correct borehole damagebefore installation of the well screen and filter pack. Inaddition, it must be understood that the effectiveness of welldevelopment is going to be extremely limited in alleviating thiseffect. To reduce this effect, he suggests several techniques: (1)boring the zone representing the screened interval with a 3- to5-in. Shelby tube, (2) scratching the sides of the borehole with anoversized brush or wire to eliminate the smear effect, and/or (3)developing the low-recharge well with a bailer or small-diametersurge block to achieve gentle agitation of the filter pack so thatany residual fine material that may have been incorporated into thefilter pack during its emplacement can be removed.

2.2.2 Well Construction Materials

In assessing well construction materials, the following information issubmitted for evaluation:

o In an article by Gass (1968). Gass states that the filter packshould be graded, fine to medium sand. Because of the adation,the effective size of the filter pack will be quite small and yetwill still be orders of magnitude more permeable than the formation Sand will not restrict well yield. In almost all cases, a 10-slotscreen will retain 80% to 90% of the filter pack.

a

S

4

Page 38: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4i

o In an article by Nielson (1988), the use of in artificial filterpack in a fine-grained material allows the screen slot size to beconsiderably larger than if the screen were placed in without thefilter pack. This is particularly true where fine slot sizes, whichare designed to hold out formation materials, are either impracticalor not commercially available. The larger screen slot size affordedby the filter pack allows for the collection of adequate volume ofsediment-free samples (Nielson, e9S8).

a Paul, et &l. (1988), states that the function of the filter pack isto stabilize the borehole and to prevent formation materials fromentering the well. They recommend that the proper size of filterpack and screen can be chosen from the grain size distribution curveof the formation by applying the method outlined by Driscoll (1986).In addition, he states that commonly available well screens and sandpacks were not capable of filtering out clay-sized particles foundin fine-grained glacial tills. The optimal well design wouldrequire a silt-sized sand pack and a very fine-meshed screen (<0.05mw). In addition, the wells within his study were constructed ofdifferent types of screens (slotted and continuous). From thiscondition he observed in his glacial till study that surging of thewells that had standard factory slot screens pulled more formationmaterial through the sand pack and into the screen than wells thathad continuous-slot screens. There were no substantial differencesin the turbidity measurements between the three types of wellscreens that had been bailed.

From the information collected, several Issues were not discussed. Oneof these issues is the use of sumps in well construction in low-yieldunconsolidated aquifers. It has been a standing practice during the past 5years that sumps be used in well construction in low-yield aquifers. A sumpis a piece of blank casing placed below the screen and is designed to retainand separate the siltation materials (accumulated fine-grained materialsettling out of suspension) from the screened interval. This device is usedprimarily to keep the entire surface area of the screened interval open toreceive groundwater.

Another issue that has become a standard practice is to ensure anappropriate filter pack thickness. All too often, particularly in shallowgroundwater wells (i.e., those less than 50 ft), a 2-in. well is placed in anominal 4-in. borehole. It is generally agreed that the filter pack thicknessshould equal the well diameter and that it should be tremied into place. Thereasoning behind this position is that an insufficiently large filter packthickness will not retain the large volum of fine- grained material trying toenter the well screen and that a sufficient volume is needed to effectivelyretain or retard this condition.

In addition to the above, Johnson Screens has developed a new screenspecifically designed for low-yield aquifers. This new well screen is calledChannel Pack and is basically two continuously wrapped screens separated by aglass bead filter pack. This screen has not been extensively field tested, soits advantages and disadvantages have not been well established.

• • • • T

..... . ,, I~lmm "0

Page 39: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I:I 0

2.2.3 Recomendations

Based on the above information, the following construction 'nethods andmaterial specifications are recoumended:

o Filter pack thickness around the well screen should be at least the

same thickness as the diameter of the casing/riser.

o Sumps should be placed below the well screens to act as a sedimenttrap for all low-yield aquifer wells.

o Well screens should be of the continuous slot variety.

o Well screens, casing, and filter pack material should be placed indry wells (i.e., the loose "soupy" material within the drill casingshould be cleaned out or removed before materials placement).

o For optimum design, the filter pack should be graded according tothe aquifer particle size distribution to ensure that the largestpercentage of the aquifer material will be retained by the filterpacK.

o Well screen slot size should be sized to the filter pack. In mostinstances, the filter pack should be sized to retain 95 to 100% ofthe aquifer material.

3. DEVELOPMENT

The main purpose for the development of a well, any well, is to producea turbid-free sample (i.e., to rid the filter pack, screen, and well casing ofthe small particles that remain that are the direct result of the installationprocedure or design). Beyond this, the goal for wells in the water wellindustry differs significantly from the hazardous waste industry. In thewater well industry, the purpose of well development is to obtain maximumyield with the least turbidity for the purpose of water consumption. In thehazardous waste industry, the purpose of development is to obtain a turbid-free sample for the purposes of chemical analysis in the parts per billionrange. Wells designed for pump testing are the exception since increasingwell efficiency may improve the quality of the pump test data. There is asignificant difference between these two goals. In the hazardous wasteindustry, constructing wells for the purpose of high yields tends to be asecondary requirement.

Couin methods of well development in fine-grained materials arepumping, surging, bailing, and the use of compressed air to "blow out" thewell. All of these, or combinations thereof, are acceptable methods withinthe water well industry; however, all do not carry the same level ofconfidence within the hazardous waste industry. The following Is a

II

S, i m II I Ii i m i l I l l l l4

Page 40: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3-9 FR. 3`. 32 43%2A

66presentation of recent information from literature addressing this issue. X'

3.2 PUBLISHED INFORMATION ON OEVELOPMENT .

o In the development of wells in glacial tills (Harman, 1988), astainless steel submersible pump was used. The pump was lowered byhand to decrease the turtidity of the water. The pumping rate wasslow and continuous, with a low volume of water being pumped. This

I Ipulled the fine-grained material from the sand pack. The siltsettled to the bottom, and water samples could be taken from the topof the water column. Bailing could be used instead of pumping todevelop the well.

o In tight formations, well development must be sufficiently vigorousto remove fine-gralned particleswithout damaging the well (Marbury and Brazie, 1988). The turbidityof the water needs to be reduced.

o According to Giddings (1985), the steep hydraulic gradient caused bydewatering the well during pumping causes turbulent flow in theaquifer and in the gravel and sand pack, and this results in a veryturbid sample. A surge and block bailer has been successfully usedin developing low recharge wells.

o According to Gass (1988), when an attempt is made to develop a siltor clay formation, the formation will not bridge, and greater b S

* amounts of the formation will be pulled into the well. The same"type of surge energy reaches the formation when a well is purged andsampled with a bailer that fits snugly within the well or when a

4 pump that just fits In a well is rapidly inserted or removed fromthe well. The key to achieving clean samples then is to reduce oreliminate surge energy from reaching the formation.

o The following study was performed by Paul, Palmer, and Cherkauer(1988). In this case, some wells installed in fine-grained glacialtills were surged for 10 imn and then bailed along with wells thatwere bailed only. Water was collected from the screened intervalsIfor turbidity analysis. The hydraulic conductivity of the formationwas sufficiently low that no significant well recovery occurredbetween the time the well was bailed and the sample was taken. Manyof the samples contained a considerable amount of sediment.Baillngs of two wells Indicated a large amount of clay sediment atthe bottom, which was easily agitated, especially when the bailertouched bottom. The wells were then pumped dry to reduce the amountof sediment and were allowed to recover. When samles were taken 4months later, the turbidity had been reduced in all but one well.

o Surging of the wells increased the turbidity. The turbidity was 50to 100 times greater than that in wells that were bailed. Sand packand screens had little effect on the amount of turbidity. In surgedwells, the average turbidity stayed the same between the twosampling periods. In the bailed wells the turbidity decreasedfourfold (Paul, Palmer, and Chorkauer, 1988).

|Eli

C 0'

Page 41: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

7

o In the restoration of clogged wells installed In glacial tills,jetting was used, and fine sand, silt, and clay are washed out oftne water-bearing formation. Theturbulence created by the jet brings these fine materials back intothe well through screen openings above and below the point ofoperation (Gass, 1985).

3.2 DEVELOPMEN(T RECOMqMENDATIONS. Based on the above Information and In consideration of the procedures S

previously recommended for well design and installation, the followingdevelooment procedures are recommnded:

o Remove any sediment that may exist within the well casing. This maybe accomplished by using a sand bailer (which most drill rigoperators are familiar with for larger diaeter wells), by usingpump and surge, or by using air lift techniques to remove thesediment in the sediment trap.

o Ideally, the first attempt should be to develop a low yield well bypumping and/or removing water at a rate equal to or less thin therecharge rate of the aquifer. This may be accomplished usingperistaltic pumps, ballers, or bladder pumps for some aquifers. The • 0

a object of this methodology Is to induce water into the well at avery low but constant rate until the water is relatively clear.(NOTE: If bladder pumps are to be used, removing the silt from thewell is critical because of the potential damage to the bladder.)

a If the above techniques cannot be accomplished and the wells arepumped to near dryness even with slow rates of water removal, thenext recommended option is to use a closed-bottom bailer in a pump-and-surge-type scenario. Under this scenario, as the bailer entersthe well, the bailer itself acts as a surge block and forces waterout through the screen, dislodging silt and clay size particles fromthe screen and the filter pack with the intentiw of the particlesreturning through the screen to be removed during the bailing Soperation. The surging activity, however, should not be so vigorousas to extend the surging action into the aquifer materAil itse1f.If during this process the well is pumped to dryness, the aboveprocedure say have to be repeated one to two additional times toobtain a smple that is relatively sediment free. A specificapplication of this approach is to develop the well in stages (2 to3 ft at a time, from the bottom up). In this the surge strokeshould not exceed the surged interval.

o At the completion of the development of a well, a well recovery testshould be performd. This test Is similar to a rising head slugtest. These data will assist the field hydrogeologist in thedevelopment of other wells and in the scheduling and planning of

A II •

0

Page 42: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

•i- •-• FE 033 •• F•, NC, •,4 2 .. 1

U purge and sample activitýes. It is not implied, however, that well ur,recovery tests should be conducted on every well. The discretior ofthe use of this test is held within the purview of the fieldhydrogeclogist and the HAZWRAP project team.

4. PURGING AND SAMPLING

4.1 PURGING

Perhaps the most critical component of collecting a representativesample of the aquifer water occurs during the purging process. The mainpurpose of purging a well is to remove the stagnant water from the well casingand borehole and to replace it with groundwater that more accurately reflectschemical conditions within the aquifer. A lot of discussion has focused onthis issue. The rationale for purging is to help remove fine-grained

p particles in the well and sand pack that may potentially enter tne well screenand the sample (Paul, Palmer, and Cherkauer, 1988). (NOTE: All operationsneed to be performed with materials and equipment that have been thoroughlycleaned to avoid introducing c€,ntaiminaton into the well. This is especially

r critical in low-yield wells because even a minute amount of contaminant may4result in relatively high concentrations in samples.)

The following is a presentation of discussions on this issue that haveoccurred in technical publications over the past several years:

o According to the Wisconsin Oepartment of Natural Resources Guidance(Llndorf, Feld, CUnnelly, 1987), the most straightforward method forvemoving all of the stagnant water from wells screened in lowpermeability formations is to pump or bail the well dry. Thisprocedure may be the best way to ensure that all of the stagnant

, water In the well has been exchanged with water from the aquifer.* After purging, the well should be allowed to fully recover and can

be purged a second time if needed.

o The Environmental Protection Agency (EPA) Technical EnforcementGuidance Document (1986) is similar to this. It states that whenlow-yield wells are being developed, they should be pimped to

* dryness once. If the recharge rate of the well causes the formationwater to vigorousl' cascade down the intake screen and accelerate

a the loss of volatii;s, the well should not be pumped dry. If thisis anticipated, three casing vblumes should be purged from the well

5 at a rate that does not cause the recharge water to be excessivelyagitated.

o If a monitoring well is drained completely during purging, the4 formation water will be exposed to the atmosphere as it enters the, well. This may cause a 10% loss of volatiles within 5 min and a 70%

loss within I h. Protocols should avoid draining the well mnd anyunnecessary exposure of the sample to the atmosphere, especiallywhen combined with turbulence (P4cAlary and Barker, 1987).

a

a

a

S , l l I m mmi~mm----mmm mm m mm mm6 m mmm6 S mm mmm . . .

Page 43: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

M-3-91 FR:' .C 34 nAZRA? rAlA NC. 6,4.-3jetAIt9 4iI ,

So If the sand pack around screens is drained during purging orflushing, the formation water will flow into the well by cascadingthrough the headspace in the dewatered sand filter pack. Somevolatilization can be expected to affect the groundwater even beforea sample can be collected (McAlary and Barker, 1987).

o The amount of recharge may limit the amount of sample that can becollected. Frequent purging will likely dewater the saturated zone,causing the well to go dry for a period of time. In wells thatrequire a very long period of time to recharge, the Interval betweensampling events may not be sufficient to allow full recovery tostatic water-level conditions. In such cases, an annual orsemiannual sampling event may be more appropriate than quarterlyevents (Narbury and Brazie, 1988).

o The results of a laboratory standing-column volatilization test byMcAlary and Barker (1987) showed that losses will reach 10% within 1h and 99% in I month. The standing water should therefore be

_ thoroughly purged before sampling. In the context of a samplingevent, It may be acceptable in moderately low permeability materialsto return for sampling of volatile organics several hours afterpurging, provided that the calm surface of the water in the casingwas the only exposure of the sample to headspace.

4.2 SAMPLING

The problems of purging and saMpling low recharge wells are mutuallyrelated events. The type of purging a field team performs may affect thesampling effort. In addition, within the literature, it is not clear as tothe best time to sample for volatile organics. The following are submittedfor evaluation and review:

o In low-yielding bedrock aquifers, wells may be pumped dry byremoving only one bore volume of water. If the water- bearingfractures are located just below the static water table level, thewell will refill by cascading water entering the bore and falling tothe bottm. This alters the dissolved gases in the water andincreases the dissolved oxygen content. Many monitoring parametersare sensitive to this alteration, and it can lead tomisrepresentative sampling (Giddings, 1985).

o A water-level monitoring period of several hours or days may berequired to determine whether the well bore is making water or todetermine If the water level will return to static water-levelconditions. In these instances, it may be possible to remove onlyone casing volume before sampling (Narbury and Brazie, 1988).

!

!

Page 44: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

10 4o Samples should be collected as soon as there is a sufficient amount

of water in the well bore in order to get a sample that Isrepresentative of the formation water (Llndorf, Fold, Connelly,1987).

o According to the EPA Guidance, as soon as the well recovers, theorder of sampling should be pH, volatiles, oxidation-reduction,semivolatiles, pestictdes/polychlorinated biphenyls (PCBs), metals,and inorganic compounds. For wells with a recovery time of greater 0than 3 h, samples should be taken in order of their volatility assoon as there is a sufficient volume of water available for a samplefor each parameter, Parameters that are not pH sensitive or subjectto volatillzation should be taken last.

o In the sampling of naturally purged wells (Robin and Gillham, 1987), 1results Indicated that a representative sample could be obtainedfrom the screened interval through the use of dedicated samplingdevice, such as a syringe sampler, The intake would need to belocated near the bottom of the screened interval. Tne voltme of thesample would have to be significantly less than the volume of thescreened interval. Some contamination could result fromdisplacement of water by the sampling device. In this study, asscreen lengths became shorter (screen lengths of 1, 2, and 5 It),the first samples were progressively more contaminated.

o In a recent article by Herzon et al. (1988) eleven 2-fn. 00stainless steel wells were developed using bailers and a diaphragmpump. Bailers were used to extract water and to act as surge blocksto draw in fine materials. This procedure was repeated four timesfor each well. The diaphragm pumps were used to pump the wells todryness so that a rising-head test could be performed on each well.Samples were retrieved at several different times after purging.The final conclusions were that wells in low- yield aquifers shouldbe purged before sampling and that concentrations of volatileorganics in the sample collected 4 h after purging contained thehighest volatile organic concentrations.

5. EQUIPI•ET FOR DEVELOPMENT, "=INI&, AND SAUPLING

To minimize the Introduction of contamination into the well, positivegas displacement Teflon bladder pumps are recommended for purging wells.Teflon or stainless steel bailers are also recommended purglni equipment.Where these devices can't be used, peristaltic pumps, gas-lift pumps,centrifugal puyps, and venturt pumps may be used. Where a suMling devicerequires an intake line, or discharge line, the composition of the line shouldbe Teflon, polyethylene lined with Teflon, or polyethylene. Where a samplingdevice requires a support line to the surface (as in bailers), the supportline should be single- strand, stainless steel wire, Teflon-coated stainless

4 steel wire (single strand or braided), or a stainless steel leader attached tomonofilament polyethylene line.

I

,|0

Page 45: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

N•Av 3-9: FR* .0 36 HAZWRAP FAX NO. :54353269

11 4Pumping rates for peristaltic pumps are typically less than ISOO mL/min.

Other types of pumps produce volatilization and high-pressure differentlals,causing variability in the analysis of pH, specific conductance, metals, andvolatile organic samples. They are, however, acceptable for purging wells(EPA Guidance, 1986). S

The equipment required for jet development includes a jetting tool withI' two or more nozzles, a high-pressure pump, a high-pressure hose, and a supply

of water. The nozzles should be evenly spaced on the jetting tool (Gass,1985).

The valve-type plunger could be used in tight formations because it hasa lighter surging action. A bailer can be used along with the plunger (Gass,t 1985).

In Paul, Palmer, and Cherkauer, the surging process (in fine-gralnedglacial tills) was performed with a length of polyvinyl chloride (PVC)electrical conduit fitted with an oversized rubber stopper. The rubberstopper was small enough to allow passage through the well but large enough toforce water before It. A peristaltic sampling pump was used to remove the

bottom sediment from the monitoring wells.

In a study by Griffin et &l. (1988) on the collection of volatileorganics from fine-grained materials, samples were collected using a double-check valve, leflon bailer with a bottom-draining device. For shallow,

j small-diameter wells with low yields, evacuation of the well by a bailer isfeasible. Syringes can also be used to sample water from low hydrostatic headaquifers because they only remove a small volume of water from the well(Nielson, 1985).

6. RECO9UIEDED PROCEDURES FOR PURGING AN SAMPLING

The following purge and sample procedures are based on a review of theinformation provided above, known characteristics of monitoring well rechargeand well dynamics, and the best available technology. The succeedinginformation is provided to act as a starting point with regard to planning andexecution of sampling activities within low recharge environments, It isunderstood that as field activities commence, minor revisions to the purge andsample activities may be required based on site- specific information;however, the following scenario should be used and planned for during theI early stages of field activity development.

The following procedures are reconmended for purging and sampling of lowrecharge aquifers:

o As a general rule, under low recharge conditions, purge and sampleactivities snould not occur for a minimum of

I 7 d after well development. This period may be extended, dependentS upon very low recharge conditions and varying site conditions.

4 '

I I I IN I0lI l

Page 46: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

12

o Purging and sampling are considered by HAZWRAP to be mutuallyinclusive activities (i.e., they are not separate events).Therefore, the comon field activity of purging all wells first thensampling is not considered to be the best available procedure.Purging and sampling should be considered, in terms of schedule, asone event.

ro Purging Degins with placing the pump or purge device at the top ufthe water column to remove the water from the well casing and

,1 borehole from the top down.

o Purge rates should be at a value less than that indicated from thewell development recharge rate recorded at the conclusion of welldevelopment. Under low recharge conditions, this rate will rarelyexceed 0.S gal/min. This low purge rate will permit the water withinthe casing and borehole to exchange without punping the well todryness or appreciably depressing the static water level.

o If the above condition cannot be met, the entire volume of waterwithin the well casing and borehole should be removed at the ratedetermined above. f it is already known that the well can bepumped down without appreciable recharge, the rate specified aboveshould not be exceeded. Excessive pumpiln will only cause turbidityproblems when eventual recharge and sampling begin. (NOTE: As areminder, under the well construction recommendations, each wellwill exhibit a 2- to 5-ft sediment trap to be located below thescreen. Therefore, the sediment trap should be removed of built-upsediment before actual purging and sampling).

o If the well does not recover to 90% of its static water level within6 to 8 h, only one borehole volume need be removed. If the wellrecovers in less time, purge activities should be repeated at leastone more time. At the conclusion of the Initial purge activities,if significant fines have accumulated In the sediment trap, thesefines should be removed before the second purge activity.

o Sampling from wells in which the static water level was notappreciably depressed is to occur immediately after purge activitiesare completed (within 3 h as a genral rule). Sampling from wells,in which the water was Lompletely remved from the well or therecovery time exceeds 3 h, will occur (for volatiles and pH and

4 m oxidation-reduction sensitive analytes) when the water level hasj reached a point above the bottom of the screen such that a

sufficient sample can be retrieved. Sampling for other nonsensitiveanalytes my occur at some point later as the well has had time tomore completely recover and provide sufficient sample. Ifsufficient ample has not become available within 24 h, the HAZWRAPProject Manager should be immediately informed so that a decisioncan be made as to the disposition of this condition.

,!

I,tI

Im l mm i ll l-mm . .

Page 47: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

•AY- 3-91 FR: :036 HAZIRAP FAX NC. 6*64353269 ?,20

* &1 4

REFERENCES

IIDriscoll, F. G., Groundwater and Wells, (second edition), JohnsonDivision, St. Paul, MN 55112, 1089 pp., 1986.

Cass, Tyler E., "Geveloping and Completing Observation Wells,"Groundwater and Unsaturated Zone Monitorino and Samling, National Water WellAssociation, pp. 94-117, October 22-24, 1985.

Gass, Tyler E., "Monitoring Well Filter Pack and Screen Slot Selection;A Reassessment of Design Parameters," Water Well Journal, pp. 30-32, June1988. Gass, Tyler E., 'Monitoring Wells in Non-AQuifer Formations,* waterWeJ.Journal, pp. 27-28, February 1989.

[ Giddings, Todd, 'Bore Volume Purging to Inmrove Monitoring Well- Performance: An Often-Mandated Myth," pp. 253-256, Conference on Groundwater

and Unsaturated Zone Monitoring and Samolina, National Water Well Association,1 October 1985.

Griffin, R. A., Herzog, B. L., Johnson, T. M., Morse, W. J., Hughes, R.E., Chou, S. F. J., and Fol lmer, L. R., "Mechanisms of Contaminant MigrationThrough a Clay Barrier - Case Study, Wilsonville, Illinois," A.I $h.or.Course- Vol. 2. Groundwater Samoling, pp. 12-110 to 12-121, 1988.

Harman, Dan, Personal Communication, September 19, 1988.

Herzog, B. L., Chou, S. J., Valkenburg, J. R., and Griffin, R. A.,"Changes in Volatile Organic Chemical Concentrations After Purging SlowlyRecovering Wells,' GrounrdWjter Monitorina Revie, pD. 9l 1988,

Lindorf, D., Fold, J., and Connelly , Groundwater Samolina Prpc@dureGi elinui,% Wisconsin Department of Natural Resources Publication PUBL-WR-153

1 87, February 1987.

Marbury, R. E., and Brazie, M. E., 'Ground Water Monitoring in TightSFormations,* Procledinas of the Second National Outdoor ActLion ýonfsrence~gAouife" Restoration, Groundwater MonItorln and Geophysical Methgds, Vo-1,pp. 483-492, Association of Groundwater Scientists and Engineers and U.S. EPAEnvironmental Monitoring and Support Laboratory-Las Vegas, May 23-26, 1968.

4 NcAlary, 1. A. and Barker, J. F., 'Volatilization Losses of OrganicsDuring Groundwater Sampling from Low Permeability Materials,' pp. 63-68,Groundwater Monitorina Review, Fall 1987.

Nielson, David M., "A Comparison of Sampling Mechanisms Available forSmall-Diameter Ground-Water Monitoring Wells,' Ground Water and UntaturatedZone Mnnitorlng and Samlilna, National Water Well Association, October 198S.

I.l

• • • •• •_ _ .O .. .. .. •

4, l m l m ml ml

Page 48: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I , 3-r FRt rG:3i kAZ•REP FAý NO. 615435"269 P. 2,

41XIS14 1•

Nielson, David M., "Design and Installation of Ground Water Monitoring41 Wells,* ASTH Short Course. Vol. 1. Monitorina Wells: LocAtioU. Design andInstal at-Xin, pp. 56-123, 1988.

i Paul, D. G., Palmer, C. D. and Cherkauer, 0. S., "The Effect ofConstruction, Installation, and Develooment on the Turbidity of Water inMonitoring Wells in Fine-Grained Glacial Till," pp. 73-82, iroundwater

* ~MonitorlinpRtview, Winter 1988.

* Robin, M. J. L. and Gillham, R. W., "Field Evaluation of Well PurgingProcedures," pp. 85-93, Gro-undwater Monitorino Review, Fall 1987.

"Standard Guide for Sampling Groundwater Monitoring Wells," op. 2-3,American Society for Testing and Materials, May 1986.

* U.S. EPA, RCRAGround Water Mongtorinq Technical Inforcement Gutdancel Documen(TLI.GD., printed by National Water Well Association, Dublin, Ohio, p.208, 1986,

Wehrmann, H. A., 'Monitoring Well Design and Construction,' Gro"ndwaterS,&Ut, p. 37, April 1983.

4

a ea

4 &

a

4,I

a

4

4 0 0

Page 49: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I UJo~o VARIANCE FORM

IVARIANCE NO. /

PROJECT NO. Yo2l, oz.oz; PAGE / OF __

PROJECT NAME Ski 6A&%ltý< DATE ~~

VARIANCE (INCLUDE JUSTIFICATION)

Y-4

op W11ssL+050 A'1T~gV7Mte-*Vi

I (e~r?vtre-4 4o re#G'IA'(. / 3cio'.I4 ,P, Ji -a-,,~t e e - J ..5i;'1J /-'scl-

JOI At ;5 /O W4.);/IId/L*Aq.re' .y

jowk~r5A r(. Y ctm 14Q.q s4kl4)'(ý dt 7

APPLICABLE DOCUMENT:

6 CC: ~ ~vC~ _________ DATEh REQUESTED BY4

APPROVED BY DT ,1

4 9 /c DATE IOAFR-9/

DATE

~zw~ProectManager

Page 50: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I 0I

I Document No.: DOE/HWP-100Revision: 0Date: July 1990Page 4-I of 4-4

I HAZARDOUS WASTE REMEDIAL ACTIONS PROGRAMSTANDARD OPERATING PROCEDURE 4WELL DEVELOPMENT AND PURGING

g 1. OBJECTIVE

The objective of this procedure is to define the procedural requirements for wellI development and purging.

S2. BACKGROUND

Monitor wells are developed to remove skin (i.e., near-well-bore formation damage) andto settle and remove fines from the filter pack. Wells should not be developed for 24 h aftercompletion when a cement bentonite grout is used to seal the annular space. However, wellsmay be developed before grouting if conditions warrant. Wells are purged immediately before 4groundwater sampling to remove stagnant water and a sample representative of groundwaterconditions. Wells should be sampled within 3 h of purging (optimum) to 24 h after purging(maximum, for low recharge conditions).

3. RESPONSIBILITIES

Sit Managtc The Site Manager is responsible for ensuring that field personnel aretrained in the use of this procedure and for verifying that development and purging are carriedout in accordance with this procedure.

I Project FReld Geolo"t: The Project Field Geologist is responsible for complying with

this procedure.

4. REQUIRED EQUIPMENTI* Pump, pump tubing, or bailer and rope or wire line.* Power source (e.g., generator), if required.I Water-level meter or weighted surveyor's tape.e Temperature, conductivity, pH. and/or dissolved oxygen meters (for Sect. 5.2 below).* Personnel protective equipment as specified in the site-specific health and safety plan.

I

0as |I| Smt 0l~ll~mI~mlI~lllidll111mm 0 u0~snl 0 - 00

Page 51: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3I Document No.: DOF/HWP-100Revision: 0Date: July 1990Page 4-2 of 4-4

9 Decontamination supplies, if required on-site.9 Disposal drums, if required.

5. PROCEDURES

5.1 WELL DEVELOPMENT

"The following steps must be followed when developing wells:4

1. Put on personnel protective clothing and equipment as specified in the site-specifichealth and safety plan.

- 2. Open and check the condition of the wellhead, including the condition of thesurveyed reference mark, if any.

3. Determine the depth to static water level and depth to bottom of the casing.4. Prepare the necessary equipment for developing the well. There are a number of

techniques that can be used to develop a welL Some of the more common methodsare bailing, overpumping, backwashing" mechanical surging, surge and pump, and

a• , high-velocity jetting. All of these procedures are acceptable; however, final approvalof the development method rests with the appropriateness of a specific method tothe site and the Hazardous Waste Remedial Actions Program (HAZWRAP) project

, manager.5. For screened intervals longer than 10 ft, develop the well in 2- to 3-ft intervals from

-, • bottom to top. This will ensure proper packaging in the filter pack. 'Note It isgood practic to decelop all samcnW and ifitm-packed well n stage.

6. Continue well development until produced water is clear and free of suspendedsolids. Record pertinent data in the field logbook and on appropriate well

4 development form per HAZWRAP SOP 1, Parts A and B, respectively.7. Remove the pump assembly or bailers from the well, decontaminate (if required), and

-1 * clean up the site. Lock the well cover before leaving. Dispose of produced water asrequired by the project work plan.

5.2 VOLUMETRIC METHOD OF WELL PURGING4

The following steps should be followed when purging a well by the volumetric method:

1. Put on personnel protective clothing and equipment as specified in the site-specifichealth and safety plan.

S2. Open the well cover and check the condition of the wellhead, including the conditionof the surveyed reference mark, if any.

3. Determine the depth to static water level and depth to bottom of well string.Calculate the well volume (volume of water within the well bore) using the followingformula (or equivalent):

t0€ *1••••

*, I 0 0 0i i0

Page 52: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

A

I Document No.: DOE/HWP-100Revision: 0Date: July 1990Page 4-3 of 4-4

1 7.4805 (4X)dH = volume (in gallons),

I where

D = casing diameter in feet. (NOTE: This equation is used for grouted wells withshort screens For wells with long screens and/or ungrouted wells, then D =borehole diameter in feet.)SdH - the distance from well bottom to static water level in feet.

Note these data and calculations in the field logbook.

4. Prepare the pump and tubing, or bailer, and lower it into the casing.5. Remove the number of well volumes specified in the project plans. Generally, three

to five well volumes will be required. In low-recharge aquifers, the well willcommonly pump or bail to dryness before three well volumes of water are removed.If this is the case, there is no need to continue with purging operations (HAZWRAPPosition Paper No. 2). Record pertinent data (e.g., water volume) in the field

i 6 logbook.6. Remove the pump assembly or bailer from the well, decontaminate it (if required),

and clean up the site. Lock the well cover before leaving. Dispose of producedI water as required by the project work plan.

4 5.3 INDICATOR PARAMETER METHOD OF WELL PURGING

1. Put on personnel protective clothing and equipment as specified in the site-specifichealth and safety plan.

2. Open the well cover and check the condition of the wellhead, including the conditionof the surveyed reference mark. if any.

3. Determine the depth to static water level and depth to bottom. Lower the probe(s)of the indicator meters (e.g., temperature, conductivity) into the water to a pointnear (but not at) the well bottom or use the flow-through system for indicatorparameter meuurement. Alternatively, set up surface probe(s) (e.g., pH, dissolvedoxygen) at the discharge orifice or dedicated probe port of the pump assembly orwithin the flow-through chamber. Allow subsurface probe(s) to equilibrate accordingto manufacturer's specifications. Record the equilibrated readings in the fieldlogbook together with the time.

4. Assemble the pump and tubing, or bailer, and lower into the casing.5. Begin pumping or bailing the well. Record indicator parameter readings at

predetermined intervals. Maintain a record of the approximate volumes of waterproduced.

& Continue pumping or bailing until indicator parameter readings remain stable withint10% for three consecutive recording intervals. Purging should continue until thedischarge stream is clear. In low-recharge aquifers the well may pump or bail to

* 0 60 S 000

Page 53: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

L S

3Document No.: DOEIWP-100Revision: 0Date: July 1990Page 4-4 of 4-4

dryness before indicator parameters stabilize. In this case, there is no need tocontinue purging. Record pertinent data (e.g., water volume) in the field logbook.

7. Remove the pump assembly or bailer from the well, decontaminate (if required), andclean up the site. Lock the well cover before leaving. Dispose of produced water asrequired by the project work plan.

6. RESTRICrIONS•LIMTATIONS S

Where flammable free or emulsified product is expected or known to est on or ingroundwater, use only intrinsically safe electrical devices and place portable power sources (e.g.,generators) 50 ft or more from the wellhead and disposal drums.

S

7. REFERENCES

Driscoll, F. G., Groundwater and Wells, Second Edition, St. Paul, Minnesota, Johnson Division,1986. 0

U.S. Environmental Protection Agency, A Compend••m of Suerfd Field Operamons Methods,EPA/540/P-87/001, 1987.

U.S. Environmental Protection Agency, Manual of Water Well Conwnuaion Practices,EPA/570/9-75-001, 1975.

S Ill l I il lll l l ll ll

Page 54: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

SE-CH~clw VARIANCE LOG

CHRONOLOGIC LIST OF PROJECT VARIANCES

PROJECT NUMBER , PAGE / OF /

PROJECT NAME -

,•oJ.,• ,..Jd/L,• C. •e.-5RESPONSIBLE

DATE 40ROOM GRANTED AND APPLICABLE DOCUMENT INDIVIDUAL

"I , " .J! '--Z AF z-..• 47• , -,Atoi"• "--,A ,,,4- , • .,. ,• ___-_..

S4

-j - . A4 I

I /•3 ,' •1-,&a• i -•,-.,r-,. • •. '.CA• --- F . 1f¢'

4 t _ _ _ II

4, I 0

4 I

41

£

4.

B

(

i

ImI*[ m m mmmm•mmm=

Page 55: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

--.- NONCONFORMANCE REPORTNRI NO. /

PROJECT A7.ANG k1, 14nrhor PAGE 1L OF

PROJECT NO 409721 OAT1: 0'18/91

1. NONCONFORMANCE DESCRIPTION

Problem: Poor recovery of some pe,1- or ,ompletel los, of peaks fur start of daystandard analysis.

Criteria: Per SOP, start of day calibration will be ran and acceptable recovery occur forall compounds.

Impact: Has no impact on previous analytical data, but will have significant impact onany future data if not corrected.

01/17/91

lOIN WD BY ATIL __ _

2. PROPOSED CORRE.CTWl ACTION INCLXOING I rTIATION AND COMPLETION DATES

Cleaning of lamp and detector head 01/17, 01/18, 01/19 and recalibrate.

* 4

TO W PWEFORMED BY: . ,

&. APPROVAL FOR PROPOSED CRETV

* ~4.CRE~V ACTION TAMU (IF OIFPERENT FROM THATPROSD

4 GC was replaced 01/19/91 with a new instrument from a different vendor.

S GRRCTlE ACTION COMPLETE I0B1/1O9,/91

PEO~d~DATE L

CC: PROGRAM MANAGEPROJKCT MANAGEOUY AS N MANAGEROUM.YfASURNC COORDINATORCEffRAL PLE

L * 01/09091

Page 56: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

.- oI% "= x o_•-" .....- r - . P- N

DJ 1 463 a Lz.E: z ClJ - IT TD4 -L PPj

FULLSCALE MILLIVOLTS 256 S

SI .833

iS

4.63

iI 6.400

II ------------ - = -11.983C

12.650

nimb- 0 SK H F=DO XII E I 4 Z* aR J C -

D~IL" I .. ..1 C .3 - F,•

A1 Sd. aTMN94FzD Z5 C 4- ( LA S -'1 C3LA.,. TE

AET.TIME PEA AREA HEIGHT AREA% NORMT EXT.STD INT.STD. FE NAML-..,,4,.40) 1401.95 64.45 8.-3007 9.61 1401.95 14(:)1.9501

8.467 2602. 07 222 35 15.4064 17.84 260)2 .07 2602.069 1.15) 212059.98 174.75 12.1968 14.12 20,59.98 2059.9827

10. 867 2580.66 b204.55 15.2796 1.89 275.12 275.1227 BENZENE W .

I 11•98 1057.73 99.75 6.2626 7.25 1057.77 1057. 7277 1 ..12.650 280.54 28.10) 6 1.611 9.7 280.54 280.544113.517 1550.76 177.85 9.1t818 10.63 1550. 76 1550.7592 7:.I 1.750 :431.59 323.75 20 3179 52,53 :431.59 43 1.5 75

14.467 1667.60 172.85 9.8736 11.43 166 7.60 1b67.b001 t4.4716.0.7 153.81 27.90 o.9107 1.05 153.81 153.8100 c:,7

I DILUTION FACTOR = 1TOTAL NUMBER OF PEAKS DETECTED 14 AREA REJECT= 75FOTAL NUMBER OF IDENTIFIED PEAK.S I USING SIYHARB.rF' .LTI TOTAL UN-CORRECTED FEAK AREA 16889.5TOTAL NORMALIZED PEAK AREA 14583.97INFERNRL STANDARD CORRECTION FACTOR IINTERNAL STANDARD PEAK NAME AT TIME I

TOTAL HYDROCARBONS(total peaý area using TPH cal.curve) 71979 NANOGRANE

|

S 0 0 0 S 0 S 6

Page 57: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

---- NONCONFORMANCE REPORTNR NO. ____

PROJECT A7ANCU St-y H arbor PAGE .- OF ._PROJECT No. 409721 DATE: 01/30/91

1. NONCONFORMANCE DESCRIPTION

Problem: Significant shifting of retention time and loss of resolution for ethylbenzeneand xylenes.

Criteria: Per SOP, calibration should show consistent retention time and separation ofpeaks.

Impact: Samples ran during time GC was out of control, some tentative identificationand quantification of compounds based upon information from retention timedata obtained from extra standard runs daily. Samples will be rerun whenback on line.

CWIDE~FUD @Y: L~a&OýA ML

2. PROPOSED CORRECT!I ACTIO INCLUON NTIAON AND COMPLETION DATES

Check temperature program, carrier gas flow rate, carrier gas pressures, connectors forleaks, cycle through program shooting standards monitoring standards data 01/29 through02/01/91.

To a PERFORMED BY: ŽC~

3.APPROVAL FOR PROPOSED CORRCIEACIt-

4. CORRCTIVE ACTION TAM (F DIqqURT PO ThAT PROPOSED)

Same as above.

L C ACT'I.ON ,'_PU.J__ 01/29/91-02/01/91SpERFORMED U: Th____

CC: PROGRAM MANAGERPROJECT MANAGEQUALITY ASRNEMANAGERalUALMV SUAC ORIAOOENTRAL FILESOThNM

• S

i

Page 58: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

S

I C3 MAOG3AM P LOT

DATA F-LrE P =STSD± I PRN1L 3 a- 19cP D-07 O1 -- 730< --1991 J

FULLSCALE MILLIVOLTS A4

q .i I

" . --. - --------- --

----- 3 10.683

12.617

|." . 13.867

-m::-__. 15. 633

16.167I.

SKY A BFnCF PU -IEN IX AZ F, PROJECT I -r e 0 7 2DATA F ILENAMiE C -- STSD±l .. PRN

13- ZS z 07 0,--7 0--1 -Z1-r F~T OF DAY 11 STANDARD - 7..00;.o

RET.TIME FEAý AREA HEIGHT AREA% NORM'%. EXT.STD INT.STD. F' o 0 E k'•,'.2:3 ''" .•85 ~3L8�. 9.e579 .7.87 1bl .5 I61.95l• ICpEV

. 37 -31.76 1.61 7.Q89-2 1.77 5.87 5. 8 71q BENZENE -.NEL.. 687. 4!2. C)7 -82.2 54.t547 1. 75 71.64 71. 4(:,3 TEE12.b1 7 142.2:7. 17.93 6.9401 2.19 9.74 ?.3440 FOLUENF .1-,867 17.06 1:3.5C6 5.7119 14.71 62.90 .b2.8?53 PCE i-.:15.633 2-'.61 Z2.74 12.7.261 5.84 24.98 24.976b O.,MXYL

18.167 ' 18.04 4.6941 2.41 11.32 -,.:24Q F.L"

DILUjTION FAC-TOR =1TOTAL NUMBER OF FEA0_5 DETECTED 8 AREA REJECT= 5('1TOTAL NUMBER OF IDENTIFIED PEAýS 7 USING Sý 0-4F,.,-P7

ONLY IDENTIFIED 'EA '% WEFRE REP0QTED-OjTHER PEA4S MAY HAVE BEEN [1 E,rt3TAL 'jN-COF:'FECTED c-EAý AREA 21"4?. 94IUTAL. NPORMALIZED) F'EA4 AREA 4 -.7 .02PINTERNAL STANDARD CORRECTION FACTOR iINTERNAL cTArNDARD F'EA NAME AT TIME 1

TQTAL H'DFO-CARb(NSttotal peak area usinq T'H c.l.c-rve, q i,-,

Page 59: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4. C O AT G A PLOTDATA F I bCE C F EDSD 1 PM F FQN

~i2. :54- : 3 O2-C)1-1I•1 4

IJLCx Ln A. Z" [LL-['Wf >-/L DUC

IA4

tI

--------- ...-------- : -- :-- - : -.= =: -_= .

Ia

-'- . . . .- -- - --7 1.7

, iI- .--

S...........- - --- ----.---- - - - - -- ==- S

-12 .96

I

v K P4OeN C X AZ , E ROnECT -£ 4P =7 Ft

DA A FI L.ENAM1E C. EDSDZ3 - PR~N

I21 X z 5,4 -- --3-:3 C-12--OX- ?1.=END OF D"Y STDv 2uL FC=O +a- 2uL-L ( ;D EI X

'El E - 4-REA4 ;4E iG.H r A PE'EA% NORM% EYT. STD INT.STE. r.EA .,,NE "-"

.2± 1l,. :: 15.5:8: 28.41 874.74 874. 'aO9 TCA'Ez -.

- "'>.. - 144.7s': 14.7-1 .46 1ik8. a 18.882 1E.E' 'E"iE E -z: .z? 11 .

7,) I S.20t 3.9(l 274. 12 274. 1 45 TrE

11 6 - q2.& 4.8E' O. 2979 4.82 148.54 149 . 5 _r68 TILt.FE ...1,, ZIl 2 1 98. 50 If'). 2c? 1 12.70 3,)' 9f) 3 1, 991'5 F-:

[ 2.@" •57. JP 94.1,h E; t)¢• • .9 159. 66 15• 6 - E 'HEt tj 9

I 1 A) 1.±55.'5 142.7(' 14.2954 f. TCh 255.57 55.o5_'> f I-S -. 967 1 •2 56) 88. 51. 1 .397 5 -7.75 27e. 5t% 2Z' 9. 5m :4 y, L •-

r.uLITf'pjDN FACTOR I

TrCIOJL • NIUMi'qF C'F PE-o F OETECTFE, 11 AF-ýEA REJEC-T 5C)

Mi~ IJMHi4E- ODF; L[EN.KT 1jE lED 'EýE S S: Fulsc-' ý

rJNLY TiINFt IFIEIP F'E( wEr-E REF'QýTEL-OTHER F'EAfS M;AY HAVE SEEN L'E L'.i

rrJTOTL PIJ-,JfPELFED FE ARFEA 11585.74

Cf L)L rIURIRMnL. I ZED E 'EE o AREA ETEI2

c. C I i l ,l lI' P. mli l IIC I Ir IIIf I 1 1

4 0 0 4

Page 60: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3 I~i~~NONCONFORMANCE REPORT 1NR NO. -3

PROJECT toR5.PAGE UOFPROJECTNO. MoflDATE: ZEL 1E3 91

1. NONCONFORMANCE DESCRIPTION

W0C5AV"i01E0 -t AIV-y.tf 8"Z-0 0"' F~lkj) SCe iA457~/V. l~wo cA4E.*S A.4C /#cAlrTriqro ,//C

AkSWl4 jAf0 kkJ., A&ZOLTtD f-J S.4vipco f4o-r IWCo.4( Sc.4ý,"-D Foot. % L .

44- r T-r VA NO-54OA v.AI "-. Nd~T CJ~ 4 iC~~y/t4C 5 IM44 -m 1 feo- -cAs.f 7s C~c-H S3'z IVY-- '.*AoV4"#y 46L.jc. A-TrA FAW4~ A'r e C-51 o4C PC&#. F41vcscp 3 .

$JA/,'- 5AV*iP(, AAJ*4,) B~~ C )3r sq /4d/cA'104SO -'- 013 ME-(JCC oot 4As;VC~ c~ P&MQSS WC4A.4l"/6,*

IDENTIFIED BY: % ~ DATE: 2. fECA F/

2. PROPOSED CORRECTIVE ACTION, INCLUDING INITATION AND COMPLETION DATES1. .5Amiu-45 F4,VI 5,9-02. 9A-JC 6 XCCIPCO &f4O~~iM -rin( hf~ VoA *0g5,0 Ao.0J ~Ac ( 4J

S.3 SAM 6 0 S St o.Au4C £C)LCCb pto.D0#4 ri.M( Fo#L to, Ar4 SiA 4wp 9AT* PA¶?tT CAJh0

4. SA04A.- 515 Z-e/-3Z-ZM - -rc FI Scogi& rv T/4 *10 IrA(. 0,0A1*10

SF.'*(MACC .,. FbA SA,~ft6 'm i( I.*QI F- C.JA77W ld C

TO BE PERFORMED BY: :L 01~i. i-'f Fc'O)-140 4I-5 '

3. APPROVAL FOR PROPOSED CORRECTIVE ACTION"

Pr* Ma er 750itW

Qualft.suiranc Manager a* 4. CORRECTIVE ACTION TAKEN (IF DIFFERENT FROM THAT PROPOSED)

5. CORRECTIVE ACTION COMPLETEPERFORMED BY: DATE: -2' -

VERIFIED BY: DATE: 3-2-

CC: PROGRAM MANAGER* PROJECT MANAGER

QUALITY ASSURANCE MANAGERQUALITY ASSURANCE COORDINATOR

uCENTRAL FILES ___________

OTHER: __ _ _ _ _ _

Page 61: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Jp~mom

Ukjrr a a

2W rý MA jCjrp fw m wu,ZVXZ.zLw. s-- J 71.M W3 Znm2U

zw" A~r-r- Jft -. 2xuwm minz *asW

29ý -Ambc2W inafwM&.W 3rC -

TRANSMIISSI ON REPORT

THIS DOCL TIENT WAS CONEF I RMED(REDUCED SAMIPLE ABOVE -SEE DETAILS BELOW)

** COUNT **TOTAL PAGES SCANNED 3TOTAL PAGES CONFIRM1ED 3kF.SI t.* 01: 1. NSi bAI CI I SIxr

x,. kI()IoI SIAVI m" Sl lk&I I IMI ~ D1 RA I I0\ N PAU~i F I0II Ki-Sl 1.lS

ELRR~lz - .2'II 11:41 A\ C U'' A3' ; C I'LL'iLO

\o''I

OPI l.I<A( IoI\ \I \1111.k< 4 t1 4tloo(Ibl S 1)- I-Cl 1:A *C [ ok 0 ikiC LO G2 'CI'L\ C4I It- I'IIU)I ' \1(oI 11: I'. lk l r&ok~tAkl) RI RFHAN I\ ITI N IL kS K'UIAN STIAI \ I

\11 SID A L O %k:))l 1, \11 FI-F I.I\J KI k~l \:T 1N R

Page 62: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I 1INTERNATIONALL iTECHNOLOGY RE OR1O1 TELECONCOPRTOIR C R F 1 MEETING

Propect Name INumber Phase ITask SUbtask

o Date r_ ime CALL FROM C NAME:___ __ __ __ __ __ __ __ __ __ __ __ CALL TO 03 $4ýeo, Sqre-S

Or~mer Participants -Name/ Location/ Representing: CALL FROM C0 NAME.CALL TO M. ýA r\czk~;'\~:Telephone Number.

4 ~ Company Name:

Address:

Topic City

•, 9AZf ANAL/sCa. state zip Coca

Summary (Decisions & Specific Actions Required by Named Persons):

/ -;0J$' t - RCVI\ 4-LA- -QM k._.b asA J .LQ: £ e

A D -Acv 4-Lw -0)c c'.-3 01

6e- acmjve-8~ 4( -re'4.-M cjosc. ko~j, b.-

C. V 41f- 61L ZS' - •Z,?O -0 1 CI-07-6W 0 2-A re-/.EAý Z/16AtL~u6t- oyyAkl jt o -rfM4.- r44t ces kolduiý Iml

~'.•iv~ ~-oI~o-S2-c'i ~ CI-of-31-4- orv rcejjcd V'/sl 5A, S)/d

.Required Action: A. /, J -Io 5cdý4,eJJAL~ acJ44.e5 lodci.. sba-,-e*10' 6 e~ 4. 42 c R~Aove recyI A4' C.-J~r,-M t ci*C ~Z 413 /2 ,~c14 &I- IEA a)7+t See W11f- /0 isl /le44 -

D., 41tr/e -4 :EfsS coe,4 4r-ý A r/eadI5AQe4 1Ceiijhuý/* Prepared~ (Signatur

I Distribution- Other Oietnibution (By PireparertOriginal to Project File

*Copy to Project Manager Tt5~A~ ( PAGE ...LOFCopy to Prepaer ________________________

4 ~0 -0 0*

Page 63: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

INTERNATIONAL O TELECONTECHNOLOGY RECORD OFCORPORATION [ ETN

C] MEETINGPrelect Name Number Phase iTask SubtasK

D Date Tme J CALL FROMP. NAME.

* zz -4,S -'t I. i- CALL TO 0 •: 5"a-re-'SOther ParticiOants - Name/ Location/Representing CALL FROM C3 NAME.

CALL TO 1E MC C \QA'CATeloollone Number

* Company Name:

I* Address:

Topic 4 City

51E644~P A4A-cY3<51 State Zip Cooe

I Summary (Decisions & Specific Actions Required by Named Personsa:

2. .. •-ca4*..& 5• .(~ ~ dA~S ~ t&Ib\fwN XP 3k a CA, 2.A 4-.' 3 we S G

4 I-c ?-A Same V 16Q, -ýV c

- P-,40 re441x f~ ~A - A.-Lv~ - ;4e cAe.~

4*

4

I Required Action:

-. (I,.,, ZFA.

Pnl~roer igna

Di~stributionl PieOtmer Distribution (By Preparer)tOriginal to PrOlwc File

CODY to P olot Manager- PAGE OF --CODbY to Prep~arer ( AE••O

_.4CA• •••

"4 lm• 0 0 m ! ! !! ! ! 00

Page 64: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I 4 I m

r C

r4

d 0.

-V N U -

Io 3

00 >

-u 0 01

z2c CDCuw >

a. f00

C) 2.0 0 cccr

9 a: ;SJI>

L C6 u

0) U) a: CC w 0 0 ~L'u *C

n a - a .C

00

o -

z ~<<z

Cu

CD m

r4 0 a ) aP

m CL IDLL 2

0 E

.-. z a:~-UL

4) 0E

S2 Ll 4)

4 .4ic zE

I 'I < Z 0. C

4) 1 C

an x -C = 0 0Eu -w cc

LL< 1 0 _j C

Z as .2a

0 0J 00c0)

m mxa :36- o CL

a.~ wL (L CL co C60- z 0 z ()

Page 65: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

CD z

z zIo 0

I u

do

0

0 -I

2

CL~~~(

-- CLc

, 4c

C) CCa U, a

0a Z E 0 P

Z 700 OI u c

E -Z --) CL z X0 C

2 g 0 i nC tEC

oU -) - -1 -) I

w C-E

o~ oL C0

0Jr

l

1

0~ E c

LLC o

4~1

;b 0 00

0m

Page 66: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

C)C

C 0

0~

ez 2 ca -m

0 0

2Uu -20C mF(U (oL o c m

0 0 x

QL Z *

0.. 0 0 CC cccOR r-- ** 0

LU0 0 ci

Co 0. 0Uw~ -JO

0 (U. (D

IN - - Nm 2Uui

. mO tC4' I

22 -i 2hit 0 E U

I .~ 0

e H c- w CL~~3

f13 CL (U

0

E 0

2w( (U.

000w E

comm I c

0 20 E

I.J -J w. f cc 0

. 4 - m a.0

0 A X 0 1-0 0 0E 0 07

Page 67: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

w

U-

ci r

z z

00 0<0E

0 00LU

z AI

- Uz<w C)

D tjZ -c

00

o 0 w cc

). <Cf< 0

w) a. Z cc ccc00 0

CL

w o0L

o -----------

00

U 4D- 0

II

2'

0a 0

0 0

u- I.- CC

00 E Q a

Page 68: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

-I.2

CQ z

a, 20 0<, C u

c0 65c -l a

.0 1.o 0 D

3CL

Ooo Z- Z, L) Eow oo 0 6<< c

0o a:'0

(0 >I- CLu Z. Z ,U

CL~~~. Z :0 )L

- -. -- CO 0-

4U ' 0 0o 0 W -)o ao m z0

4< < <<aa a:.S

> c0

a, S

E E,IjI2 2

0..

cna,

E >

0(3E

~~2ma

Z:040

000 S 4z, 0 EJ w

< < 0 0 0- 0 0

Page 69: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

C)C

~C C)I 2C\J I U

C13 'A

o o

00 o

00

* zz I

LU 0

LU d

0a

N 4

(A .Lz c0 0 ~

m~ 0- L C

-J) a:i .( <U U F

I-Z 0(aL n -

0o -1 Ul

0000

z ~ 1-0J9 o;

LU

I. y.

r 0

E - E

J <

aý, o

ý.,fi V-1 zE

Z 0

u -1 0z ~~z 1: z z 14L I '

4 W E D

z -c -J w0 0 0 c r c ( 0 cc

0a D 0 4

Page 70: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

--4 9

00 -

0 U)

VI 0

0 -

0

z C

z ~0z 0 0.

. <0 a.L <U aI- - E

-cc- - --

U) < < <Uc 0 a, 0E

w CL

W L .Z 00 -0

C) -L

-

-. m z- 0 0 D

<~~~~ <w c c

-h -7C, 000 o

0L

(A CL2E0.

E 4)

_ I 0 CL

z le

4 4 il E7

1 6~

-co z z z

Zx 'U <)

o 0

00 Q(

AA _H 1-z w z

L0 0 < o

S991 ~ -Ii<

00 0

z V) 4

Page 71: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

z IC t44

cc

0 0-

Ej 2

zw

w cc-

a. <0 0 Ca

- (.) 0000>-< Z

0Z

Lo CWcr - cr 0 0

<' < w a.

w~ ~ a. a. 0<4< < w cc cc

CiCLCD c C

wZ

00U.U

ID6:

EE2 C

0~ Eo

> E.

> r

wL 0

X 0

I0 2!

3 U.a:z CC

00i

2~. a.

a

L~~ E

Page 72: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

nrc

000

00 L0

M e S

z z - S

U. 00-~

0%3

Ha0 e:0 ) 0

LU a

> 0~ 0

4V wT-0 3-, 0

CL 0 a - 0 2Z. .4- L)) 0

CL z ~ ~ a: a:m0

0- 00)1m a. a

w 0

0 o -0~

E 0 0 U

.A :E CL f

0 E c

- C a- u 0

E -~ E

N. zo~E0

* ý E 0J a00 E S (4 6

0~ DZ

z w wOdW a:

00~~~> < 5 0

a: z 0 J z -

I-- 0- 0'." ,4. 0 0 .Ze 0

wI * ti I -i uQ, d, f

51 ~ ~ 1 ;a *~4ehU _) cc_0 0 0 r0 f 0 0 0 a 02 OC 0 I

cc cc _ VI I %A v U.

0 0 S 0 0 0 0

Page 73: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

-- 4oI C')

6. 6-- z -I

c c0 0

<0Ca:S

a 0

0zz

W 00. D0_

,) 0 0 .r < rUo - 00CC F

a- F- -4

.0 1(J)~~~U w C -C-

C. CL

LA. 4D1 U 4

UJ ~2:2 a

o '[-EOE

E 9

U) CL

EE

. 0 0

SEIA.

EEf ~ R CL -j - I.

0 zE

0U CC z -0

Z mj 0

0.0. 9? ~0.

cc S cc 01

Page 74: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

C*-, r Z

25 , 1-oN o

W CD

0 0 <

a. 0

w H C) fl Z0

L.LJ~ F-Z

-.Zo cc 000 C)

U) <c, < W JLu-.j U/) W -JI 2rc LJ

a) OoD Z 00

0 a a. C

0 0

CL .

I-c 0 ~

00

5."

0

00

2 ;' , *

25 1

00 z

) 0 A I0. 1

~~ L2L .

cct 0 z E

h- 0

FZ;Z 0 -0Unwo < 0 1ý 14tz'z I 4L

0 z 0.E

0 0 ~ 0 N 0

a: a: cc~ 0 , ''I

0. 0. 0L Z

LC

Page 75: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

C)a

COC

-0 0 IIc a

0 0

u

< UIc

z

D 0~ zZ, 0 TY c Or

LAz a- <z0a 0L0o -o F-2

<I (n U<< WO u(j C) WL -j cc - - - - - -

0 0-00- 4) N

0 - '

o U.~~-.U- ,- ~ iN.-r CDa

A~C S;i . ~4z :~j-• E

p VA ~M

AA '

L L' '4

_j 0E. *k m * 92

- IEt I)'. r.E

P E

0 a0

z 0 z

- z I~d ac w 0 -

00z z X.~ z c

9- a - - ý - ; 0,- - ;;0 1

0 <4 CL L. -1 a a)

00 nn n, j C, JC ,i 0 ~CL (L Cd) a) CL

0use&:-

Page 76: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

56

A~me

I- -s

/E~ - 4-s - .,T

IA I- (

Page 77: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I;IL

+* AAME o - s. - -fe e

___________ cLL 4 TP

kL e- ako- '_______;-_ -~.~.~ c SL -3 a. r C Lo- V')

Page 78: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

62

V,!.* ýtAA..?,,% k~f

44

4f.-

4IW 3 O- --

Ur, -(K Wek A& e -e4 4 JL+.w

Page 79: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

MCC

LA-4

- a,4cW~- L.~c~~-

4oC,~-e -- re- -jZ ý,eyje

4 ~ ~jL kw4-OZ.

* i-Acr er..iýo.4c ,o. QCo -'O

a-Cet*

Page 80: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

S~OL t'j- e-

Ct- -T*~*_ca"

C. 9k

C- Uf-.-- -6--

0 0 0 0 *

Page 81: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

S

--- NONCONFORMANCE REPORTNR NO.

PROJECT A7.AN,"ky Hari-or PAGE - OF.

POJECT NO. 409721 DATR: 03/04/91

1. NONCONFORMANCE DESCRIPTION

Problem: No sensitivity of PID detector for TCA, after finding that TCA and DCE arenot co-eluding as originally thought.

Criteria: Scope of work required analysis of samples and reporting contaminationconcentration for TCA.

S

Impact: Reported concentration for DCE will change along with detection limits; willnot be able to report confident TCA values.

02/02/91

2. IqROPOSaD COPJECTWE ACIN INCL.UOMN INITITI'ON AND COMPL.ETION DATES

Continue program on present course, at end of project re-intergrae DCE values, reviewFID response for TCA and see if its possible to determine TCA concentration from FID.

2/21/9 -03/04/91

3 APPROVAL FOR PROPOSE ,ORRECTIVE ACTION- ,,

4. CORECTIVE ACTION TAMN (IF DIFFEW NT FROM THAT P O

Same as above. UCE values were reintergrated and corrected values reported, TCA detectionlimit for FID was high and resulting curve was poor and inconsistant. Results reported withunique qualifier.

L ORETV ACTION COLEUI IAT 03/04/91

CC: PROGAMW MANAGERh ~PROJECT MANAMEA ~OUA~1ASURNC MANAGERIOU•I•I ASSUR~qANCEl COORDIATOR

CFLEEn iHiliim

Orrmb

Page 82: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

, go

I Is.94

u5

CS-

4 . I cc "

C" co co -I

CSS

0- 'a, . C -4 C

11.2-Dt 'aW-0 l

Page 83: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

% I

* 44

C-0

0 40

Page 84: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

III

Ib

APPENDIX B

PRELIMINARY REVIEW OF HYDROGEOLOGICDATA FOR FACILITIES ADJACENT TO

SKY HARBOR AIR NATIONAL GUARD BASE

Page 85: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

SMemorandum "I TECHNOLOGY

CORPORATION M emor

STo Don Willen, Project Manager Date September 18, 1990

From Steve Sares, Principal Hydrogeologist

Sub]ect Preliminary Review of Hydrogeologic Data for FacilitiesAdjacent to Sky Harbor Air National Guard Base

I. INTRODUCTION

In accordance with your request, I have prepared a brief summary of

data collection activities and analysis of hydrogeologic data for0 facilities adjacent to the Sky Harbor Air National Guard facilities

at the Phoenix, Arizona Airport (the Base). These activities andpreliminary conclusions regarding the hydrogeology of the vicinityare presented below.

aThe goal of this data collection and review effort is to aid indetermining appropriate monitoring-well placement and designspecifications for wells to be installed during the Base SiteInvestigation (SI). As you are aware, there has been muchdiscussion of appropriate depth, screen interval, and location forthe SI monitoring wells.

Data collection activities for this task were conducted betweenJuly 9 and 11, 1990 and consisted of locating and obtainingavailable potentiometric records for facilities generally within

0 one and one-half miles of the Base. Field activities such asverification of well locations or measurement of water levels werenot conducted during data collection activities. All findings

* presented below are based on the assumption that data collection,reduction, calculation, and presentation contained in the recordsare accurate and complete. Records were obtained from the

* following agencies:

City of Phoenix Environmental Services Department

* "Arizona Department of Environmental Quality (ADEQ)

Arizona Department of Water Resources (ADWR)

In addition, a Remedial Investigation report was located at apublic library which contained hydrogeologic information relevantto the Air National Guard facilities at the Papago MilizaryReservation (Papago). The sources of information and relevanthydrogeologic information are further discussed below.

LA8 85

Page 86: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I

Mr. Don WillenSeptember 18, 1990Page 2

I II. DATA SOURCE BIBLIOGRAPHY

Six primary sources of information were identified and evaluated inthis effort. Selected pages of reports and files were extractedand copied from the sources listed below:

0 A. Summary of the Phase II Site Investigation for the City* of Phoenix at the West Sky Harbor Fuel Storage Facility

and Vicinity, Phoenix Sky Harbor International Airport,* Phoenix, Arizona. (May 31, 1990), Groundwater* Technology, Inc. Received from Mr. Donn Stoltzfus, City

of Phoenix.

B. ADEQ files for Avis Sky Harbor, ADEQ File No. 4715.122.Received from Mr. Douglas Jamison, ADEQ.

C. ADEQ files for Garrett General Aviation Services* Division, ADEQ File No. 4715.355. Received from Mr.

Douglas Jamison, ADEQ.

D. Draft Remedial Action Plan for Del Rio Landfill, City ofPhoenix, Arizona (February 23, 1990), Dames and Moore.Received from Mr. Donn Stoltzfus, City of Phoenix.

E. Estes Landfill Hydrogeology. Received from Mr. DonnStoltzfus, City of Phoenix.

F. Remedial Investigation Report, 52nd Street RI/FS,Phoenix, Arizona for Motorola, Inc. (June 1987), Damesand Moore. Copy at Saguaro Library, Phoenix, Arizona.

In addition to the above referenced documents, several others werereviewed and received from the agencies listed above. Informationin the additional documents either duplicated information presentedbelow or are for facilities remote from the Base. Mr. David Annisof the ADWR also provided much valuable discussion regardingfacilities and history of hydrogeologic investigations in the areaadjacent to the Base.

II. FINDINGS

Results of the hydrogeologic investigation at the Sky Harbor fuelfacilities (Reference A) are likely to be directly applicable tothe SI as the fuel facilities are located approximately 4,300 feet(0.8 miles) from the center of the Base on a bearing of fiftydegrees west of north (N 50 W). These findings are summarizedbelow.

0

a

a ,mmm,~ • • •

Page 87: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

0

I I Mr. Don Willen

September 18, 1990Page 3

Five monitoring wells, 90 feet deep, were installed atthe site in March and April 1990. The water level ineach well is approximately 71 feet below grade or at anelevation of 1,038 to 1,036 feet above Mean Sea Level(feet MSL).

Detailed casing elevations and depth to water were notincluded in the information provided, however, a sitegradient map indicates a due westerly groundwater flowdi.Lction at a gradient of approximately 0.002 or 10.9 ftper mile.

Lithologic logs indicate mixed, unindurated alluvium atthe site consisting generally of sand to silt in the 0-5foot depth interval, sand to pebbles in the 5-15 footinterval, and sand to cobbles below 15 feet.

Avis Car Rental facility at Sky Harbor is conducting aninvestigation for a fuel release (Reference B). The Avis facilityis located approximately 7,600 feet (1.4 miles) from the center ofthe Base on a bearing of N 82 W. Findings from these files aresummarized below.

The depth to water, measured on 24 Nov 87 ranges from61.26 to 64.51 feet below the surface, this correspondsto an approximate elevation of 1,035 to 1,039 feet MSL.

The groundwater flow direction at the site is generallywest with the flow direction diverging to northwest andsouthwest west of the Avis site. Reports suggest thatthe divergence may be caused by an Arizona Department ofTransportation (ADOT) dewatering project located in linewith 21st Street between Buckeye Road and the Salt River.

The ADOT project was in operation at the time thematerial in the files was prepared (1987). At that timethe dewatering system consisted of 11 wells each pumpingat approximately 1,500 gallons per minute.

The U.S. Geological Survey (USGS) conducted a pump testduring the dewatering project and determined the aquifertransmissivity (T) to be 194,000 GPD/ft, and hydraulicconductivity (K) to be 1,200 GPD/ft, using a saturatedthickness of 150 feet.

.. • (mRmm • m mmm'•--..--•mm m m mmm mmmm, m m •

Page 88: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Mr. Don WillenSeptember 18, 1990Page 4

Garrett General Aviation Services Division operates a facilitylocated approximately 6,300 feet (1.2 miles) southwest of thecenter of the Base on a bearing of S 73 W. This facility isconducting an investigation for fuel and solvent release (ReferenceC). Findings from the Garrett files are summarized below.

The depth to groundwater was measured to be approximately •55.5 to 57.9 feet below grade or at an elevation of 1,044to 1,042 feet MSL on 5 Dec 88.

Garrett has presented the groundwater flow direction tobe northwesterly (N 36 W). The ADEQ disagrees with thisintexpretation and states that the ground water flowdirection at Garrett is North 80 East. This direction isinconsistent with the regional flow direction asindicated by all other references from the area. I havereviewed the available potentiometric data at Garrett andthe flow direction, based on three-point solutions rangesfrom N 15 W to S 36 E depending on the combination oiwells used. Thus the data from Garrett appearsinconsistent and should not be relied upon for the BaseSI.

The City of Phoenix owns a landfill located approximately 14,600 5feet (2.8 miles) southwest of the Base on a bearing of S 74 W.This landfill is called the Del Rio or 16th Street landfill and itis located on the south edge of the Salt River (Reference D).Findings from the files are presented below.

Depth to groundwater is typically 35 to 40 feet belowground level or at an elevation of 1,045 t, 1,040 feetMSL.

Water levels in wells have demonstrated fluctuation of upto 28.7 feet in a single well over a period of ten years.The peak water level (all wells) was 1,055.6 feet MSL 5(approximately 24 feet below ground level). The minimumwater level over the same period was 1,020.51 feet MSL(approximately 59.5 feet below ground level).

Hydrographs for monitoring wells over the period from1979 to 1990 indicate that water elevations in wells in 5the period 1986 to 1990 are at the lower end of the range(1,025 to 1,045) while during the period 1983 to 1986they were in peak ranges (1,055 to 1,045). In general,water levels in these wells have declined approximately20 feet from the 1983 peaks to the 1990 lows or anaverage of 2.8 feet per year. Prior to the 1983 peak 5levels, water levels were in the 1,030 foot range as late

o • • •• • •

Page 89: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

El

Mr. Don WillenSeptember 18, 1990Page 5

as 1982. Water levels in monitoring wells demonstrate a

strong correlation to flows in the Salt River, thus acontinued decline in water levels cannot be projected.

Reference D provided several potentiometric maps for theDel Rio Landfill. These maps were prepared by theauthors of the report by unknown means. Based on the

Ii maps presented, the groundwater flow direction averagesa bearing of N 60 W (300 degrees azimuth) for nine maps,•iresented in the report under dry river conditions. Onepotentiometric map representing conditions of flow in theriver was also presented, the groundwater flow directionin this case was S 57 W (213 degrees azimuth).

The City of Phoenix also owns another landfill southeast of theBase. The Estes Landfill is located approximately 6,500 feet (1.2

4 miles) from the Base on a bearing of S 82 E (Reference E).

Depth to water at the Estes Landfill is typically 40 to60 feet below ground level or at an elevation of 1,080 to1,060 feet MSL.

4 Water levels in monitoring wells also fluctuate inassociation with flow in the River at the Estes Landfill.The maximum fluctuation observed in a single well over aperiod of seven years is 43.77 feet. The peakgroundwater elevation in all wells is 1,111.5 feet MSL(approximately 20 feet below ground level). The minimum

4 I water level in all wells was 1,038.63 feet MSL (84 feetbelow ground level.

Potentiometric data from shallow and deep wells suggesta downward vertical gradient at the Estes Landfill,however, lack of well specifications in the information

4 •presented prohibits and analysis of the ver.tical gradientconditions.The groundwater flow direction from prepared maps

U reviewed averages S 83 W during dry conditions in theriver. One map presented for streamflow conditions

4 depicts a groundwater flow direction of S 51 W.

The Motorola facility is located approximately 3000 feet (0.6miles) on a bearing of S 15 W from ANG facilities at the Papago

S' Military Reservation. Findings from review of Reference F arepresented below.

I

S 5 0 S

Page 90: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4

Mr. Don WillenSeptember 18, 1990Page 6

Depth to water at the Motorola facility is approximately 22feet below the ground level or at an elevation of 1,198 feetMSL.

Hydrograph records for well DM101 (nearest to Papago) indicatea maximum fluctuation of five feet, primarily in response toprecipitation, The peak water level in this well was 17.5 feetbelow the top of casing and the minimum measured was 23 feetbelow the top of casing.

Groundwater flow direction in the shallow portions of the4 aquifer is approximately S 70 W.

Alluvium overlies volcanic bedrock to a depth of approximately26 feet. The alluvium thins to the north and west and may bethinner at ANG facilities at Papago.

4

III. DISCUSSION AND CONCLUSIONS

A. MONITORING WELL SCREEN INTERVAL

Sky Harbor

The Base is located in an area with ground elevation ofapproximately 1,110 feet MSL. The current monitoring well designcalls for 50 feet of screen to be placed 30 feet below the ambient

O water table and 20 feet above the water table.

Data from the Sky Harbor fuel facility investigation and othersites in the area suggest that the water table will be encounteredat a depth of approximately 70 feet below the surface or at anelevation or 1,040 feet MSL. This configuration will require soil

4 borings to be extended to approximately 100 feet below the groundsurface for well construction. The well bottom will be located atan elevation of approximately 1,010 feet MSL and the top of thescreen interval will be approximately 50 feet below ground or 1,060feet MSL.

* Using data from the Del Rio Landfill (Reference D) during periodsof prolonged flow in the Salt River, water levels may be expectedto rise as much as 20 to 25 feet. Assuming a 20 foot rise in thewater table due to flow in the river, the water table elevation atthe Base would be approximately 1,060 feet MSL. This is at thelevel of the top of screen in proposed monitoring wells. Based on

4 this scenario, it may be prudent to set the top of screen at anelevation of 1,C65 or 25 feet above the expected water table.

I

Page 91: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

IIMr. Don WillenSeptember 18, 1990Page 7

ka

A screen length of 50 feet would place the bottom of the well at1,015 feet or 25 feet below the expected water table. Assumingfive feet of saturated well are required for representative samplesto be collected, the water table could go as low as 1,020 feet andthe wells would remain useful. This is approximately the lowestlevel recorded at any of the surrounding areas, the 1,020 levelalso represents over seven years of useful life at an average watertable decline rate of 2.8 feet per year. The 50-foot-long screenproposed should be adequate for the objectives of the SI and futureuse.

Papago

The current proposed monitoring well design for Papago wells is thesame as the wells designed for the Base; thirty feet of screen tobe placed within the water table. Given the information presentedin Reference F, above, it is likely that upon completion ofpiezometers at Papago and measurement of water levels, it will bedesirable to modify the screened interval to allow 15 feet belowand five to ten feet above the water table. This interval shouldbe sufficient to accommodate anticipated water-level fluctuations.

B. MONITORING WELL PLACEMENTS

Sky Harbor

6 Proposed monitoring well locations for the Base SI were developedassuming a westerly (N 90 W) groundwater flow direction. Thepossibility of significant deviation from this direction motivatedthe collection of existing data to verify the assumption ofwesterly grour-;ater flow.

Because the potentiometric data obtained during this effort werenot collected from a single point in time, they cannot be used inpreparation of an area potentiometric map, therefore accurateprediction of groundwater flow direction for the base cannot bemade.

Generally, published groundwater flow directions are in a westerly(S 83 W) to northwesterly (N 60 W) direction during no-flowconditions in the Salt River. The exceptions to this condition are

p during flow in the river and one combination of water levels at theGarrett Aviation facility. Groundwater flow direction during river

* flow is discussed below. The Garrett data are inconsistent, usingthe same four data points groundwater flow direction variation of

i!

*

Page 92: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

F

Mr. Don WillenSeptember 18, 1990Page 8

140 degrees can be obtained. It is advisable not to utilize thisdata in placement of SI wells unless separate conformation ofeasterly flow directions can be made.

I

The available data indicate that during periods of river flow, thegroundwater gradient on the south side of the river is in asouthwesterly direction (S 57 W to S 51 W). It follows, assumingflow in the river creates a mound in the water table coincidentwith the axis of the river, that the groundwater flow directionnorth of the river would be in a northwest (N 57 W to N 51 W)direction during periods of river flow.

Using the above discussion it is reasonable to assume thatgroundwater flow direction around the Base is primarily westerly,with a maximum northerly component of 30 degrees north of westduring no-flow in the river and a maximum northerly component of 39degrees during periods of flow in the river. Given this analysisit is recommended that the initial plan of piezometer installationand flow direction determination prior to well placement be adheredto for the SI. It may be prudent to periodically measure waterlevels in elevation-surveyed wells from surrounding facilities todevelop an area potentiometric map during the SI. Any offsitemonitoring should be limited to facilities within a one and one-half to two mile radius of the Base.

Papago

Proposed monitoring well locations for Papago were developedassuming a westerly groundwater flow direction. Should piezometricinformation agree with the data contained in Reference F,indicating a southwesterly flow direction, it may be desirable torelocate well MW4-03 to the west side of Building 112. Howeverthis determination should be postponed until site-specificpotentiometric data are available.

0 0

Page 93: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4II

14

* APPENDIX C

GEOPHYSICAL SURVEY REPORT

4l

4

4

nni Ii i

Page 94: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

jb•

GEOPHYSICAL INVESTIGATION

161 AREFG* SKY HARBOR lAP

PHOENIX, ARIZONA

PROJECT NO. 409721

PREPARED BY:

IT CORPORATION17461 DERIAN AVENUE, SUITE 190

IRVINE, CALIFORNIA 92714

SEPTEMBER 1991 S

KN/WP45101,0%3-91ADRAFT 02

, • •• • • • • S

S . S S ,-0 0 w,,., --- m .. 5m ,m,--. m m, .-

Page 95: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

1

4 ~ Table of Contents

List of Figures ii

1.0 Introduction

2.0 Field Procedures 1

2.1 Geophysical Clearance 2

2.2 Geophysical Survey: Site 5 - Ammunition DisposalArea 2

6 3.0 Data Processing and Interpretation 3

4.0 Discussion and Results 4

* 5.0 Conclusions 5

References R-1

Appendix A - Theoretical Background

Appendix B - Electromagnetic Induction Profiles

Appendix C - Sample Ground Penetrating Radar Recordsa

4

/&

4

t

4

4

0

Page 96: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

r

List of FiguresU

4

4- Figures Title

1 Geophysical Survey Area

2 Geophysical Interpretation Map

KN/W451/0g-03-9 g /DRAF'T 02 ii

I0

4 I

Page 97: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I GEOPHYSICAL SURVEYii,

1.0 Introduction_

A geophysical survey was conducted from December 13 to 23, 1990 at Sky Harbor Interna-

4 tional Airport (lAP) in Phoenix, Arizona. The survey was conducted in two phases. The firstphase involved the geophysical clearance of all proposed soil organic vapor (SOV) sampling

points and soil boring and monitoring well locations of underground pipelines and utilities atSite 1 (JP-4 Hydrant Area), Site 2 (Hazardous Waste Storage Area), Site 3 (Fuel Bladder

4 Area), Site 4 (107TCS Hazardous Waste Collection Area), and Site 5 (Ammunition DisposalArea). Electromagnetic (EM) utility locators and ground penetrating radar (GPR) methods

were used during this phase of the investigation.

* During the second phase of the geophysical investigation, EM and GPR surveys wereconducted at Site 5 to locate buried ammunition. In 1980, live 50-caliber ammunition was

discovered in excavations during installation of a closed circuit television (CCT) system(AZANG ;990). Ammunition was found in two areas shown in Figure 1. The Preliminary

4 Assessment (PA) reported that ammunition was found at depths ranging from 6 to 8 feet at alocation approximately 50 feet south of the CCT trench locations (HMTC, 1988).

The locations of the Site 5 EM and GPR surveys are shown in Figure 1. Several modifica-

I tions ,o the original survey design were necessary based on unanticipated field conditions. Asoriginally planned, magnetic and EM surveys were to be the primary means of locating buriedammunition with the use of GPR restricted to problem areas or areas requiring additional

data. However, due to the abundance of surface structures, vehicles, and underground4 utilities, EM surveying was conducted only in areas relatively uncongested with metallic

material. The magnetic survey was not performed because of interference from unwanted

sources over much of the area of the site. As a consequence, GPR was used as the primaryexploration tool. In addition, the EM survey was extended 130 feet to the west to include a

- more open area approximating background soil conductivity conditions.

2.0 Field Procedures.lThis section describes the field procedures used for the geophysical clearance and theIKN/WP4S1)og-o-g/1DRAF'r #2

* 0 0 0 0 0 0 0 •0

Page 98: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

AIRCRAFT PARKING AREA

LAJ W w w w w w W W w w w w wz z z z z z z z z z z z z Z Z Z

UNE OS

UNE 20S

UNEOS - - - ILOI p -LINE 40S hr - .I

( N 9 .30 ISCO ED) MU MONUNE 60S 11A 2.08ý •'

UNE 80S -80 OCAON PROX

UINE SOS- - -- - -

UNE 100S BUILDING 7

•'UNE 140S .l•

UNE 120S

•.UNE1200S -

UNE 220S - - - - - - - - - -

UNE 240SUNE 260S

UNE 280S

LIGHT

LUNE 300S TEL -0 -SET NAIL

MA HOLE 0 N 9129.0650~~UN 325 - - -POW~ER E 11191.8904

LINE 340S1-$

Page 99: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

[-SET CONCRETE, w "' "a" L'JWNAIL & SHINERz z z z z z z z z z3 :3 " -1 3 3 "m "m " "n m N 9405.9349

E 11659.5025

- - -- 1 bIsco RED 6MUNTIM N

M9ON 0.

S13R E•/I FIRE STATION- i$H{I4r5-o2 LEGEND:

-• •N 9325.1079 ZUklk E 11447.2469

FIRE LI UGHT3• •, STA'nOION

\IGlHT 0 MANHOLE

"'POLJE MONITORING WELL

-.- GPR SURVEY LINE NTHl-TRAVERSE DIRECTION

GEONICS EM-31 SURVEY UNE

SCALE:

6 50 100 FEET

FIGURE 1SITE 5-AMMUNITION DISPOSAL AREAGEOPHYSICAL SURVEY AREA

161 AREFG, ARIZONA ANGSKY HARBOR lAPPHOENIX, ARIZONA

�I NTERNATIONALTECHNOLOGYCORPORATION

Page 100: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

AIRCRAFT PARKING AREA

N NN N Nw w hW w w hi LJ L iaz z z z z z z z z z z Z:: 3 : 3 :3 : 3 - 3:3 :3 ::3 ::3 :3 :3 :M :3 "

UNE OS

LINE 20S _ _ _ _ _

MI*5-01UNE 40S N 9353.3085 U//ILDING/_7,

E 11052.0835 SDISCOVERED AMMUNILINE 60S 198 (LOATON APPROX)..

LINE 100S7

L UNE 140S

LUNE 140SS -1

U LNE 150S

UNE 200S

LUNE 2205

UINE 240S 4

.8 LINE 260S

-c d LNE 280SLIGHT

a N 05- SET NAIL

.--.

AH 0 N 9129.0650LIUNE 320S POWER E 11191.6904

i POLE

UINE 340S

4N: •• • •• ••

-- ,1 nu ]m i mn u mi l! n ! S

Page 101: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Nl W1q I)-SET CONCRETE,. ,. ,. ,. . w ,, w w w w ,w wJ• AL&SIE

z z z z z z z z zNI &SIE:3 :3 ":3 =1 = :3 -1 :3 =1 :3 "1 ::3:3 N 9405.9349

\1980 (LOCATION APPROX)

MANHOL ELECTRIC ?

"3 AMMUNITION *I N-NMON APPROX. HONE

LINES FIRE STATION

\' N N9325.1079 *L LGEDE 11447.2469.

e r"77I1REH STAT.ON UGHT

LIGHT 0 MANHOLESPOLE

(I MONITORING WELL

CA•-1 CUT IN ASPHALT

rpgA/omAg,-Q_• UTIUTY DASHED WHERE APPROXIMATE.QUERIED WHERE UNCERTAIN

FT TRANSFORMER

SCALE:

50 100 FEET

FIGURE 2SITE 5-AMMUNITION DISPOSAL AREAGEOPHYSICAL INTERPRETATION MAP

151 AREFG, ARIZONA ANGSKY HARBOR lAPPHOENIX, ARIZONA

� INTERNATIONALTECHNOLOGYCORPORATION1

Page 102: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

geophysical survey at Site 5 (Ammunitions Disposal Area). A Geophysical Survey Systems,

Inc. (GSSI) Subsurface Interface Radar System 10, which was equipped with 120-, 300-, and W

500-MHz monostotic antennae, a Radio Detection Model RD-400 electromagnetic cable 0

locator, and a Metrotech Model 810 pipe and cable detector were used during the geophysical

clearance phase. The GPR unit and a Geonics EM-31DL (EM-31) with a digital data logger

were used during the geophysical surveys at Site 5. Detailed equipment descriptions and

supporting theory are included in Appendix A.

2.1 Geophysical Clearance

Geophysical field procedures used to clear drilling locations of subsurface obstructions are

described in this section. First, all utilities near the drilling point evident from utility maps

and visual observation were traced by placing the Metrotech or RD-400 transmitter on the

line, delineating the line using the receiver, and marking it on the ground surface using

orange surveyor's paint. Individual drilling locations were then cleared by holding the

transmitter on the line and circling with the receiver at a radius of approximately 40 feet.

When a line was located using the receiver, the transmitter was relocated to that point and the

line was traced and marked in the vicinity of the drill point. If a utility was found within

approximately 3 feet of the drilling location, it was moved and the entire procedure repeated.Finally, in areas where nonmetallic pipes or large numbers of utilities were present, two * S

perpendicular GPR profiles were conducted over the drilling point using the 120-, 300-,

and/or 500-MHz antennae. If additional utilities were located within 3 feet of the drilling

location, the boring was moved and the clearance procedures repeated.

2.2 Geophysical Survey: Site 5 - Ammunition Disposal Area

EM and GPR surveys were conducted at Site 5 to determine the possible location of buried

ammunition disposed of during the 1950s.

To provide spatial control, a 20- by 20-foot grid was marked with surveyors paint in the area

of interest. The location of the base grid relative to permanent site features is shown in

Figure 1.

Readings of conductivity and in-phase component field strength, as measured by the EM-31,

were collected at 5-foot intervals along both north-south and east-west lines spaced 20 feet

apart. The locations of the EM survey lines are shown in Figure 1. Data were stored in adigital data logger and downloaded to a laptop computer at the completion of the survey.

Many of the EM survey lines were conducted in segments due to buildings and other

KNVWP451/09-03-91/DRAFT #2 2

Smml 0 u m am m0...

Page 103: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

obstructions. For example, data were not collected in the Liquid Oxygen Storage Area

(Building No. 46 and its perimeter) because of the adverse effects of the oxygen tanks and 3)

surrounding fences.

The GPR survey was concentrated in the vicinity of the Ammunition Dump and in the areas

where ammunition was discovered during trench excavations in 1980. The locations of the

GPR profiles are shown in Figure 1. All GPR profiles within the Liquid Oxygen Storage S

Area (Lines GPR-1 through GPR-9) were conducted with both the 300- and 120-MHz

antennae All other GPR profiles were conducted with only the 300-MHz antenna. All GPR

data were stored on digital tape for later processing.

To allow an accurate interpretation of the geophysical data, the locations of all surface

metallic objects were accurately plotted relative to the base grid as shown in Figure 2.

3.0 Data Processing and Interpretation 5

Computer-generated plots of the EM profiles are included in Appendix B. In-phase and

conductivity anomalies were tracked from line to line when possible, or noted as single

anomalies. Some portions of the data severely affected by buildings and vehicles were

deleted before plotting.

Field mapping of surface metallic objects made it possible to distinguish anomalies caused by

known sources from those caused by buried pipelines and other conductive objects. Contour

maps of the EM data were not generated because a significant portion of the data was

affected by buried objects and surface features.

Color plots of the GPR sections were made for interpretation, with a color scale proportional

to the amplitude of the reflected signal. Two-way travel times were converted to depths

using an assumed relative dielectric constant of five. Anomalies due to known sources, such

as surface objects or buried pipes, are noted on the profiles. Examples of interpreted GPR

sections are included in Appendix C.

KN/WP451/O.03-91/DRAFT #2 3

• • •• • •• •S

4b in n0umm e• i mn 0 l i 0mn nnm0 0

Page 104: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

-,.-

* 4.0 Discussion and Results

The first phase of geophysical surveying involving geophysical clearance of subsurface

obstructions to drilling resulted in the successful installation of all SOV probes, soil borings, 4

and monitoring wells.

In the second phase of geophysical surveying, EM and GPR were used to assess the likeli-

hood of additional buried ammunition at Site 5. The results of the EM survey are presented

graphically in Appendix B and are summarized in Figure 2. After discarding in-phase and

conductivity anomalies due to known sources, significant remaining anomalies were observed

to exhibit continuity between parallel survey lines, and because of their linear character are

interpreted to be caused by underground utilities.

GPR profiles are presented in Appendix C. Assuming a relative dielectric constant of five for

geologic materials at Site 5, effective depth of penetration was approximately 5 feet for the

300 MHz antenna and approximately 12 feet for the 120 MHz antenna. Although the

penetration depth of the 120 MHz antenna was significantly greater, its resolution was

correspondingly lower then the 300 MHz model. In addition, the 120 MHz antenna was not

shielded, and therefore was subject to signal interference from aboveground sources. An

example of this can be seen in Figure C-4, in which a fence is responsible for a hyperbolic

reflection between 75 and 90 feet. Because of these shortcomings, it is not likely that the 120

MHz antenna was capable of resolving containerized ammunition.

The anomalies observed on GPR profiles north of monitoring well MW5-02 were compared

with known surface and subsurface features as shown in Figure 2. Two significant anomalies

could not be related to known features. Anomaly A, shown in Figures 2 and C-2, is located

at approximately 19 feet south on Line 440 east. This anomaly is traceable through several

parallel survey lines, and its trace intersects a manhole located at the intersection of Lines 400

east and 20 south. Further, the depth of the anomaly is less than approximately 3 feet. There

is little doubt that the source of the anomaly is an underground utility. Anomaly B (Figures 2

and C-2) is characteristic of a metal object very near the ground surface. A similar anomaly

was caused by an iron manhole at the intersection of Lines 400 east and 20 south.

KNdWP451/09-03-91/,DRAFT #2 4

0 S 0 0 0 0 0 0 0 S

Page 105: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I

GPR surveys in the area north of monitoring well MW5-02 were apparently capable of

resolving underground utilities down to several inches in diameter. Therefore, assuming that

ammunition was containerized or buried in some other bulk fashion, it is likely its presence I

would be indicated in the GPR data to a depth of roughly 5 feet. The lack of unaccounted- 4

for GPR anomalies is an indication that large concentrations of ammunition are not present in

this location.

GPR profiles in the vicinity of Building 46, labelled GPR-1 through GPR-9 in Figure 1, were

compared with known surface and subsurface features. Anomalies traceable across several

records can be explained by the presence of features shown in Figure 2. For example,

comparison of Figures 2 and C-4 demonstrates the hyperbolic signature of several under-

ground utilities and the masking effect of the concrete-slab floor of Building 46.

No anomalies were found that strongly indicated the presence of buried ammunition near

Building 46. However, as shown in Figure C-4, geologic layering below a depth of approxi-

mately 2 feet is apparently indistinct to nonexistent. This leads to two possibilities: (1)

layering does not exist; this may be a natural condition or layering may be disturbed, (2)

layering exists but was not resolved with GPR due to poor penetration or interference from

known features. In considering the latter case, Figures C-l, C-2, and C-3 should be compared 0to Figure C-4. Figures C-1, C-2, and C-3 are radar profiles obtained along survey lines

located approximately 150 feet northeast of Building 46 (Figure 1). Geologic layering in this

area appears much more distinct than in the vicinity of Building 46; thereby lending support

to the former possibility.

5.0 Conclusions

Two phases of geophysical surveying were conducted at Sky Harbor IAP using GPR and EM

methods. The first phase of surveying involved geophysical clearance of drilling and SOV

locations of subsurface obstructions. In the second phase of the survey, subsurface conditions

were assessed for the presence of buried ammunition.

The geophysical clearance phase of work resulted in the successful installation of all borings,

monitoring wells, and SOV sample points.

The results and conclusions of the second phase of the investigation are based primarily on

GPR data. The EM data were of limited use because of the adverse effects of abundant

KN/WP451/01W03-glODRAFT 02 5

• • • •• • •

0 iumummnnlmn•nlil 0~,,,mn 0 0 0n n 0

Page 106: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

surface and subsurface electrically conducting material not related to previous disposal

operations.

Radar data in the vicinity of Building 46, the Liquid Oxygen Storage Area, did not provide 4

direct evidence of buried ammunition. However, the apparent lack of layering in geologic

materials within this area may be due to excavation and disruption during disposal operations.

Geologic layering appears more distinct in the survey area northwest of Building 46. This

may be an indication that disposal has not occurred in this area. Further, no anomalous

materials were apparent in the radar data to its approximately 5-foot depth limit, although

underground utilities were clearly resolved in this same interval. This implies that buried S

ammunition, if present and of approximately the dimensions of a typical underground utility

diameter, would be detected to a depth of approximately 5 feet.

Direct confirmation of the presence or absence of buried ammunition at Site 5 is not possible

based solely on nonintrusive methods. Individual cartridges smaller than the minimum

dimensions resolved by GPR may be present at any of the locations surveyed. Ammunition

in any form may be present at depths greater than effectively sensed by radar. Finally,

ammunition disposal occurring in discrete zones of dimensions smaller than the geophysical * 0grid spacing of 20 feet may not have been crossed by a geophysical survey line and therefore

could remain undetected.

KN/WP451/0og-3-91/DRAFT #2 6

• • • •• • •S

Page 107: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

[S

ReferencesUr D I

Arizona Air National Guard, 11 July 1990, Memorandum to Martin Marietta Energy Systems

F (Map Attached).

Dobrin, M. B., 1976, Introduction to Geophysical Prospecting, McGraw-Hill, New York.

Hazardous Materials Technical Center, July 1988, Preliminary Assessment, 161st Air

Refueling Group, Arizona Air National Guard, Sky Harbor International Airport, Phoenix,

Arizona.

Keller, G. V. and F. C. Frischknecht, 1966, Electrical Methods in Geophysical Prospecting.

International Series in Electromagnetic Waves, Vol. 10. Pergamon Press, Oxford, England.

Milson, J., 1989, Field Geophysics, Geological Society of London Handbook, Open Universi-

ty Press, Milton Keynes.

Telford, W. M., L. P. Geldart, R. E. Sheriff, D. A. Keys, Applied Geophysics, Cambridge *University Press, Cambridge, England.

Ulriksen, C. P. F., 1982, "Application of Impulse Radar to Civil Engineering," Department of

Engineering Geology, Lund University of Technology, Sweden.

S

KNWP451,/0-2,-91/mAFr I R- 1

,-

Page 108: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

S

I iTHEORTICA BACKROUN

K• 4S .AP,'•-•-91,DRAT #

• • • •• • •

,m• •fnm~m

Page 109: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

APPENDIX A

THEORETICAL BACKGROUND

A. 1.0 Electromagnetic InductionElectromagnetic (EM) induction equipment used during this investigation consisted of a

Geonics EM-31DL terrain conductivity meter (EM-31) with an Omni digital data logger, a

Metrotech Model 810 pipe and cable detector (Metrotech), and a Radio Detection Model RD-

400 electromagnetic cable locator (RD-400).

The EM-31 has a transmitter and receiver coil mounted at each end of a 12-foot-long plastic

boom. An audio-frequency alternating current is applied to the transmitter coil, causing the

coil to radiate a primary EM field with a magnetic field vector parallel to the axis of the

coils. This time varying magnetic field induces eddy currents in any conducting material in

the subsurface as described by Faraday's Law on induction. These eddy currents have an

associated (secondary) magnetic field with a strength and phase shift relative to the primary

field that is dependent on the conductivity of the medium. The receiver coil measures the

resultant effect of both primary and secondary fields. By comparing the signal at the receiver

to that at the transmitter, the instrument is able to record the in-phase component (in-phase) 0

and the component 90 degrees out of phase (quadrature) with the primary field.

Most geological materials are poor conductors, and the flow of current through the material

takes place in the pore fluids (Keller and Frischknecht, 1966). Conductivity is predominantly

a function of soil type, porosity, permeability, pore fluid ion content, and degree of saturation.

The EM-31 is calibrated so that the out-of-phase component is converted to electrical

conductivity in units of millisiemens per meter (mS/m) (McNeill, 1980). The in-phase

component is read in parts per thousand (ppt) of the primary EM field and is generally

adjusted in the field to read zero response over background materials.

The depth of penetration for EM induction instruments is dependent on the transmitter-

receiver separation and coil orientation (McNeill, 1980). The EM-31 has an effective

exploration depth of about 18 feet when operating in the vertical dipole mode (horizontal

coils). In the absence of large metallic features such e, tanks, drums, pipes, and reinforced

concrete, the maximum instrument response results from materials at about 3 to 5 feet below

ground surface. A single buried drum typically can be located to depths of about 5 feet

whereas clusters of drums can be located to significantly greater depths depending on

KN/WP451 APP/08.26-91fORAFT #i A- 1A, S

0 0 0 0 0 0 0) 0 0 4

Page 110: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

background noise. The EM-31 generally must pass over or very near to a buried metallic

object to detect it. Both the out-of-phase (conductivity) and in-phase components exhibit a

characteristic anomaly over near-surface metallic conductors. This anomaly consists of anarrow zone having strong negative amplitude centered over the target and a broader lobe of

weaker, positive amplitude on either side of the target. For long, linear conductors such as

pipelines, the characteristic anomaly is as described above when the axis of the coils

(instrument boom) is at an angle to the conductor, however, when the instrument boom is

oriented parallel to the conductor, a positive amplitude anomaly is obtained.

EM-31 applications include the delineation of soil contamination, oil brine pits, buried

metallic and nonmetallic debris, landfill boundaries, buried pipes and cables, and buried

drums and tanks.

The RD-400 and Metrotech are specifically designed to accurately locate and delineate

underground pipes and utilities. A transmitter emits a radio-frequency signal that induces a

secondary EM field in nearby utilities. A receiver unit measures the signal strength of thissecondary field and emits an audible response to allow the precise location of the pipe, cable,

or other conductor in which a signal is induced. If the utility is accessible anywhere, the

source signal can be directly applied to it, making the secondary field much larger and readily 0measurable.

A.2.0 Ground Penetrating RadarGround penetrating radar (GPR) equipment used during this investigation consisted of a

Geophysical Survey Systems, Inc. (GSSI) Subsurface Interface Radar System 10 equippedwith 120-MHz, 300-MHz, and 500-MHz monostatic antennae.

In conducting a GPR survey, a transmitter antenna that emits a high frequency (center

frequencies in the range of 80 to 900 MHz) EM wave into the subsurface is pulled along the

survey line. This wave propagates at the speed of light in a vacuum scaled by the square root

of the relative dielectric constant of the medium and reflects at boundaries where the relative

dielectric constant (and therefore the propagation velocity) changes. The contrast in velocitybetween the two media can be quantified as a reflection coefficient at the boundary. The

magnitude of the reflection coefficient increases as the contrast in velocities increases, and its

sign is positive or negative depending on whether the velocity increases or decreases,

respectively, at the boundary.

KNWWP451 APP/OS-26-91/ORAFT #1 A-2S

0 0 0 0 S 0 0 0 0

Page 111: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

[A

I The reflected signal is detected at a receiver antenna, often as a characteristic triplet that is Ethe result of the receiving antenna response and multiples generated along the propagation X

I path. The signal is transmitted to a control unit, displayed on a color monitor, and saved on

digital tape (if necessary).

As predicted by Maxwell's equations for a propagating EM wave, two kinds of charge flow

J are caused by the alternating electric (E) and magnetic (H) fields associated with it (Ulriksen,

1982). These are conduction currents and displacement currents. The conduction current

term is predominant at lower frequencies and it is these that are used in the EM induction

method. At the higher frequencies used in the GPR method, the displacement current term

becomes predominant. The high frequencies will set bound charges in motion causing sj polarization.

The material physical properties that describe the movement of charges by conduction

currents and displacement currents are the conductivity and the dielectric constant of the

medium, respectively. The conductivity is a measure of the ease with which charges and

charged particles move freely through the medium when subjected to an external electric

field. The dielectric constant, or its value normalized by the dielectric constant of free space,called the relative dielectric constant, is a measure of how easily a medium polarizes to

accommodate the EM fields of propagating wave (Keller and Frischknecht, 1966).

Although conductivity has a lesser effect on the transmission of EM waves emitted from aGPR unit, it does have an important effect on the attenuation of the waves (Ulriksen, 1982).

Highly conductive media will attenuate the EM signal rapidly, restricting depth penetration of

the first several feet. Highly resistive (poorly conductive) media will allow much deeper

depth of penetration. The frequency of the transmitted waves also affects the depth of

penetration. Lower frequencies penetrate deeper, but have low resolution, whereas the higherfrequencies can resolve smaller objects and layers at the expense of decreased effective depth

penetration.

In unconsolidated materials, conduction takes place mostly through the pore fluids (Keller and

Frischknecht, 1966). Changes in pore fluid content, porosity, permeability, and degree of

saturation will therefore affect reflected and refracted EM signals. This is how trenches, in

which there may be different compaction relative to the surrounding area, can be identified.

When the target of a GPR survey is a metallic conductor such as metal pipes and cables,

drums, tanks, ammunition shells, etc., the mechanism is somewhat different. An EM wave

KN/WP451 .APP/0e-2G-91/DRAFT #1 A-3

4 0 0 0 0 0 0

Page 112: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4,l

will completely reflect when reaching a metallic conductor. This total reflection makes

metallic targets well suited for the GPR method when they are within the depth of penetration U;

range of the instrument. There will be no reflections from below the metallic conductor,

although there generally will be multiples. The edges of the metallic reflector will have .

diffraction patterns that are a result of the fact that both the transmitting and the receiving

antennae are not focused, but emit and receive from a 45 degree cone. This cone allows the

radar to see objects that are ahead of it, placing them deeper in time. As the radar

approaches the object, the reflection becomes shallower, with the shallowest reflection taking

place when the radar is right above it. The same pattern will be seen as the antenna moves

away from the object.

Applications of GPR include delineation of pits and trenches containing metallic and

nonmetallic debris; location of buried pipes, drums, and tanks; mapping of landfill boundaries;

and mapping of near-surface geology. Near-surface metallic objects such as pipes and tanks

exhibit a characteristic high-amplitude hyperbolic anomaly and generally are relatively easy to

recognize.

K 01

KWW451 APP•o-26.91/DRFT .i A-4

*• l n[ I[ lnniI II lml i II

Page 113: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

-I T

APPENDIX B

ELECTROMAGNETIC INDUCTION PROFILES

KNtWP45 .APP/09-03-91/DRAFT #2

IT -mmmm mm imm m m i m mmmm

Page 114: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

cm

C* w,U,

0 c so- LINE EM-O S

E 44 . _ _o-

!,C,

Eo 20o3o0

Sto 20 LINE EM-20 S

0 2 B

/

0z

4 -20.

O4

* LINE EM-40 S

40

2 A V V204

-

-20

-40

-6 . . * * I S i i I . . . . . .

too 30 00

Distance (feet)

4

o 1994 IT CORPORATIONALL COPYRIGHTS RESERVED

DO No SUMle The$ Otmfng

0 0 0 0 0 a

Page 115: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

8. - BUIDIN-F - BLAST FENCES1~I

I0 F - FENCEFH - FOE HYDRANTm

f LP - LIGHT POLEto €0 M - MANHOLE

* *- . 0 P - UTILJTY.......... .n n0

'O RC - REINFORCED CONCRETE8 - SEWER

-I0 ~ V - VEHICLE

.4 -- CONOUCTIVITY-MILUSIEMENSIMETER (mS/rn)

. . . IN-P4.ASE COMPONENT -.I ...... . , • PARTS PER THOUSAND OF PRIMARY

300 400 ELECTROMAGNETIC FIELD (PPT)S~ANOMALY

20

% •-=-• /• FR LOCATION OF SURVEY LINES

S/- o-10

ft30063

B -

-1t

-24f1 FIGURE B- 1

360 • "ELECTROMAGNETIC INDUCTION PROFILES

t) SITE 5 - AMMUIrTION DISPOSAL AREA161l AREFO

SKY HARBOR lAPPHOENIX. ARIZONA

0 w- 00

Page 116: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4p

i 0 T LINE EM-60 S

E 20 -

0U -40-

-60Lt0 0 3000

-0

-44

> 4LINE EM-80 S

-20

40

20100I200OR00

-40

t00 20 300

S140 IT CORORAIO

ALL COPYtRIGHTS RESERVEDDo Nol 3"1*k Thiol Granng

0 0 !!!

Page 117: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

_ _ _

E LEGEND:S- BUILDING

BF - BLAST FENCE;0 s .0 :r F -FENCE

SFH - FIRE HYDRANT

a Q LP - LIGHT POLE

0 M - MANHOLE0 P - UTILITY

G I AC - REINFORCED CONCRETE8 S-SEWER

-tV V-VEHICLE

-CONDUCTIVITY --F20 ~MLLISEI&ENS/METER (mS8m)

-. IN-PHASE COMPONENT.. ,30 , .,, •PARTS PER THOUSAND OF PRIMARY

300 400 ELECTROMAGNETIC FIELD (PPT)0S -_

20smREFER TO FIGURE 1FOR LOCATION OF SURVEY LINES

0

.-t 0-;10S

* , ft 3

300 400'S

20

to

0

-t0

-2s

. .. ... f* FIGUREB-2

ELECTROMAGNETIC IDCTION PROFILESSITE 5 - AMMUNITION DISPOSAL AREA

161 AREFO

SKY HARBOR lAPPHOENIX. ARIZONA

-mTEiAlIONAL

* 0 0 0 0 0 0

Page 118: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I

mWC4

6006 . LINE EM- 120 S

E 40%.

E-0, o B

>b

"0• • -2o

0 .4.

46 -............. . . . . . . .I . .

6C LINE EM-140 S

40

z3 20 B

4 C0

-20

4 .4

.61...........................I . I

100 aw Soo60

LINE EM-160 S

o 40.2 •

20 -

-20

-4 I~. .. .... ........, ...... ... .lee 200 300

Distance (feet)

0 1964 IT CORPORATIONALL COPYRIGHTS RESERVEO'00 Nl Scale This Oravng

4 0 0 0 0 0 0 0 0 0

Page 119: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:

B - SUILDINGBF - BLAST FENCE

E F - FENCEFH - FIRE HYDRANT

!0 S , LP LIGHT POLEM - MANHOLE

z20 0 P UTILITY

fA RC - REINFORCED CONCRETESl0o 8 -SEWER

O V VEHICLE3

0 " - CONDUCTIVITY-0 MILLUSEMENS/METER (mS/m)

-to - IN-PHASE COMPONENT -PARTS PER THOUSAND OF PRIMARYELECTROMAGNETIC FIELD (PPT)

ft NOTE.3 I -0 REFER TO FIGURE 1" 300 S00

FOR LOCATION OF SURVEY LINES40 S

20

10

I

-to

-20

400 ,0

160 5

t0

tO

a

-o FIGURE B-3

-a0 ELECTROMAGNETIC INDUCTION PROFILESft SITE 5 - AMMUWmON DISPOSAL AREA

. .-30 I 1 AREFGS400 SKY HARBOR lAP

eet) PHOENIX. ARIZONA

l i� DIT . .RNiONAL

C RP AflON

Page 120: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

E04

IM

w

020

S~r LINE EM-i180 S

ClP C/P

0C. 40.-4- 30

C P LINE EM-200 S

40. C F

zv20

40

-20

-40.

s-100 200 300LINE EM-220 S

40.R C=•rP

Do"olS" Tus-I-rn

200

-20.

-40.

Distance (feet)

w1004 IT COIRPORqATIONALL COPYRIGHTS RESERVED

"-Do Not Sem Thee ormf•o

Page 121: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:

a - BUILDINGBF - BLAST FENCE

F FENCEFM - FIRE HYDRANT

oS LP - LIGHT POLE

M - MANHOLEP - UTLITYRC - REINFORCED CONCRETE

*9 C - CURB

V V-VEHIICLE

CONDUCTIVITY -MLLISIEMENSIMETER (mSrm)

0"-10 = --- H-PHASE COMONENT -

0 PARTS PER THOUSAND OF PRWdARYELECTROMAGNETIC FIELD (PPT)

300 400 REFER TO FIGURE I

LINE ES-200 S FOR LOCATION OF SURVEY LINES

F

to

1G

-to

-10.20

toa

-itFIGURE 1-4

-24 ELECTROMAGNETIC INDUCTION PROFILESft SITE S - AWAUWN•ON DISPOSAL AREA

I -20 16 1 AREFGno 200 SKY HARBOR IAP

(feet) PHOENIX. ARIZONA

0E 0 ,,,',0,, .,

Page 122: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4N

uiw6 ~~LINE EM24S

E

0

.6 o 200 3m

LINE EM-260 S

z

-40

f LINE EM-280 S

.4C

-40

too 200 200

Distance (feet)

S0 19S4 IT C0ORPORATIONALL COPYRIGHTS RESERVED

4 00O "O Scale This Drewenq

4 000000 *

Page 123: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:8 - BUILDING

BF - BLAST FENCE

F - FENCE

OS FH - FOE HYDRANT

LP - LIGHT POLEa:r. M - MANHOLE0 P - UTILITY

CA10 W RC - REINFORCED CONCRETE

0 C - CURB0 V - VEHICLE

03

"o CONDUCTIVITY --10 MILLISIEMENSIMETER (mSrm)

1-. - IN-PHASE COMPONENT -

-as -- PARTS PER THOUSAND OF PRIMARY"0 ELECTROMAGNETIC FEW (PPT)""0

300 400 Nama SREFER TO FIGURE 1

FOR LOCATION OF SURVEY LINES20

to

0

-tO

-20

ft. . . -SO

30 400

SHca.

20

-to

FIGURE B-5

ft ELECTROMAGNETIC INDUCTION PROF1LES400 SITE 5 - AMMUNITION DISPOSAL AREA

11II AREFG

fet) SKY HARBOR IAPPHOENIX. ARIZONA

ENERATIONAL

0~&C 0 00

Page 124: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I u- . I I I. I l i .... i

0

04

'o _C_ LINE EM-320 SZ2O

a

0

IC 00 200 350

60 LINE EM-300 S

40 T

20

~~0

-20

-40

ooLINE EM-30 S

z 20

-20

-401

100 2 0

Distance (feet)

S106(4 IT CORPORATION

ALL COPYRIGHTS RESERVEO00 No0 SML TheN

EM-340 S

0 0 0 0 0 0 0 0 0

Page 125: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:E - BUILDING

OF - BLAST FENCEF - FENCEFH - FIRE HYDRANT

, LP LIGHT POLE20 M - MANHOLE

300 P - UTILITY(A RC - REINFORCED CONCRETE

to S- SEWERo0 V - VEHICLE0

"CONDUCTIVITY -0 MIUSIEMENSIMETER (mS/m)

-to =(D --.- IN-PHASE COMPONENT -

PARTS PER THOUSAND OF PRIMARY-20 ELECTROMAGNETIC FEW (PPT)"ft

• . - II1 I • • • I ' '1 •Q

320 S REFER TO FIGURE I

FOR LOCATION OF SURVEY LINES

20

I .

-10

340 S

20

0

-to,FIGURE B-6

ELECTROMAGNETIC IOUCTION PROFILES... . . . . . .,-38 SITE 5 - AMMUNITION DISPOSAL AREA

300 400 II1 AREFOSKY HARBOR lAP

e (feet) PHOENX. ARIZONA

0 0 0 0 0 0 0 0 0

Page 126: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

s0-W

m

I * Ir-P

cc Vvv

U / LN E

40

ri 0 .. .... II... .... ... . .. . . .' ..' '.. .'4 0 200 901

SLINE EM-40 E / RC

40

,B \fT

20

4 0

t00 200 301

Distance (feet)

ALL COPYRIGHTS RESERVED

4 ~~~0o NO Sc. Thee Otmngq

40 LIN EM4 E P0/•~~~~~~ T iil *I• '• mata I iI lB I illI / m I

•, nmnm m n n ~ i ~ i~iin m mi I pi

Page 127: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:

S B - BUILOINGBF - BLAST FENCE

F - FENCE

-0 FH - FIRE HYDRANT

/F 7F LP -LIGHT POLET T. M - MANHOLE

P - UTILITY

0 RC - REINFORCED CONCRETE0 0 S -SEWER

SV - VEHICLE(S)0o CONDUCTIVITY-

-ILLISIEMENISME TER (mIlSom)

. -- HN-PHASE COMPONENT -

"PARTS PER THOUSAND OF PRIMARY0 -10 ft ELECTROMAGNETIC FIELD (PPT). . . 10

-300

REFER TO FIGURE 1FOR LOCATION OF SURVEY LINES

P PT- T

ft

300

IC

p p

0

FIGURE B-7ft'

S. . . -10 ELECTROMAGNETIC INDUCTION PROFLES300

SITE 5 - AMMUNITION DISPOSAL AREA161 AREFG

SKY HARBOR lAPPHOEMX. ARIZONA

E &TERMATIONA

0uJ-"4 E .. miUi l .. 0 iiS Sl S 0 i0i0.... .. .

Page 128: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4

NN

v N

Co

"L•

VN

02z

I LINE EM-60 E

-, CDVI/

, 21 2

LINE EM-O0 E

1 "

VP

(a

1E

2 B

00

0 Q 0

too 200 301

40Pp

[

I • 904IT ORF•TRTTO

2 V'

0.................. o 200 301

I ~ ~~~ ~ T 14I OPRTO

06No ScaI TM -, n flria I I II I I

0 ~~0 0 v

Page 129: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:

S - BUILDING

S BF - BLAST FENCEF - FENCEH - FIRE HYDRANT

LP - LIGHT POLE

SM - MANHOLEp ~P - UTILTYT~ RC - REUUOKCED CONCRETE

K T S SEWER0 V-VEHICLE

"V -- CONDUCTIVITY-MILLISIEMENSIMETER (mSim)

-.- IN-PHASE COMPONENT -"PARTS PER THOUSAND OF PRIMARY

V. "ELECTROMAGNETIC FIELD (PPT),ft V

- 3001 10,oQREFER TO FIGURE 1

FOR LOCATION OF SURVEY LINES

PT

ft.............. I , , , , • . - to300

FIGURE 1-8

.ft ELECTROMAGNETIC INDUCTION PROFILES300 SITE 5 - AMMUNITION DISPOSAL AREA

161 AREFG

SKY HARBOR lAPPHOENIX. ARIZONA

0CORPORATION

ULM* •••

Page 130: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4.r.. 0

N0 z LINE EM- 120 E

E4 0E , T

" 20 ". _.__ .CO-E--

20

CI 00

G * a J * * , i i . a * ,. . . . . ..., . . .

too 200 300

40 LINE EM- 140 E

Tz

r.o

4e 20 1B0

l0to - 0 300

B LINE EM-le0 E

20

100 200 300

Distance (feet)

0 1964 IT CORPORATIONALL COPYRIGHTS RESERVED

Do NAm kal The Drawing

4 S 0 0 0 0 0 0 0 0

Page 131: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:

0 - BUILDINGBF - BLAST FENCEF - FENCEFH - FIRE HYDRANT

- LP - LIGHT POLESM - MANHOLE

(A P - UTILITY0 RC - REINFORCED CONCRETE

0 S-SEWERV - VEHICLE

CONDUCTIVlTYPM.USIEMENS/METER (mS/m)

IN-PHASE COMPONENT -

1 PARTS PER THOUSAND OF PRIMARY

L ft 13 ELECTROMAGNETIC FIELD (PPT)

300 -..

. .. 10

REFER TO FIGURE I

FOR LOCATION OF SURVEY LINES

a

fti I J * * * , * • -10

300

FIGURE B-9

ft 0 ELECTROMAGNETIC INOUCTION PROFILES300 SITE 5 - AMMUNITION DISPOSAL AREA

161 AREFOSKY HARBOR lAP

PHOENIX. ARIZONA

4 !* 000m Jl ;.m il,!l"il

Page 132: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

0

I"

N

CC

mm LINE EM-1ISO E02

S40

E BB

20

0

> . .,. .., , , , ,. . . . . . ..... . .. . . .. . . .x oo, 200 300

40 _ LINE EM .220 E20

Cm0

100 200 300

40 LINE EM-220 E

B

to200 300

Distance (feet)

0 1014 IT CORPORATIONSALL COPYRIGHTS RESERVED

+0 401 "kale) Thos COlrvwng

I II mell I I lmil I i m li LINn E E,22 ES.. .. .. mn m ,m== nnumm n n II l II I

Page 133: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

s ~LEGEND:B - UJLDINGSF - BLAST FENCEF - FENCE

- 1FH - FOE HYDRANTLP - LIGHT POLE

M- MANHOLEP - UTILITY

0 RC- REIFORCED CONCRETEa0 S-SEWER"a V - VEHICLE0* CONDUCTIVITY -

MILLISIEMENSIMETER (mSIm)

""-. WI-PHASE COONENT -

"ft PARTS PER THOUSAND OF PRIMARY..... . . ELECTROMAGNETIC FIELD (PPT)

300

REFER TO FIGURE 1FOR LOCATION OF SURVEY LINES

0

ft,. . . . . I I I I f -to0

300

0

FIGURE B- 10. , • , , , , , , * ft

.300 EL.-to ELCTROMAGNETIC ODUCTION PROFLESSITE S - AMMUNITION DISPOSAL AREA

161 AREF•

SKY HARBOR lAPPHOENIX. ARIZONA

SINTERMATIORAL

m l lWWII

4 000

Page 134: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I0

NN

r.0

04

40 LINE EM-260 E

SB k'

40

zg

to00

0oo 200 300

LINE EM-260 E

40

0 I . .. .,, , . A . . .I i i-

too 200 300

S~LINE EM-280 E

40

2(

100 200 300_

Distance (feet)

I InS4 IT CORPORATIONALL COPYRIGHTS RESERVED

"00 No Scale Thos Or#aItng

0 0 0 0 S 0 0 0 0 I

Page 135: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:S B - SUOLING

BF - BLAST FENCE 4

F - FENCEFH - FIRE HYDRANTLP - LIGHT POLE

m- M - MANHOLESP - UTILITY

0 PC - REPIFA-CED CONCRETE

O S-SEWV3 v - VEILE10O CONIUCTIVITY

(D ILLISLUENS/METER (mS8M)

- N-PHASE COMPONENT -

v RM PER THOUSAND OF PRIMARY"o" ELECTROMAGNETIC FELD (PPT)

300 ~-to -300NTE

• io F,'Jm w

PO LOCATION OF SURVEY LNES

0

ft

300

0

FIGURE B- 11

fIto ELECTROMAGNETIC INDUCTION PROFILES300 SITE 5 - AMMUNITION DISPOSAL AREA

I$1 ARElO

SKY HARBOR lAPPHOENIX. ARIZONA

D3MAW

4 0 0 0 0 S S *

iI'I l~iil II • I I I III•I III [] III i i i i i i ,

Page 136: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

0I~

NOZ LINE EM-300 E

"20

C4o0 o0

too 200 300

I l p ... ,** , , . I * I-

100 200 300

LINE EM-320 E

Tz

me 20-

o V00

40

100 200 300

LINE EM-340 E

20

0 . . . . . . .I . ............ .. .. .. ...t00 200 300

*l Distance (feet)

1 t114 IT CORPORATION4 ALL COPYRIGHTS RESERVED

Do Not Scale This OGroing

4 0 0 0 0 0 0 0 0 0 q

Page 137: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

LEGEND:

B - BULDINGBF - BLAST FENCE

_ _-_F - FENCEFH - FIRE HYDRANT

"LP - LIGHT POLEM - MANHOLE

to SP - UTLITY* RC - REINFORCED CONCRETE0 S - SEWER03 V - VEHICLE"100 CONOUCTIVITY-

to MILLISIEMENSIMETER (mSIm)

S-. IN-PHASE COMPONENT -

PARTS PER THOUSAND OF PRIMARY"ELECTROMAGNETIC FIELD (PPT)

300

REFER TO FIGURE 1FOR LOCATION OF SURVEY LINES

0

ft

300

0

FIGURE B-12

-t ELECTROMAGNETIC INDUCTION PROFILES

300 SITE S - AMMUNITON DISPOSAL AREAI I) AREFG

SKY HARBOR IAPPHOENIX. ARIZONA

L IN -a ENATIONAL0rECKNOL60a

Page 138: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

NCY. I B0 LINE EM-360 E

E 40

* Co

oE

2 200

Oz F

000

* I .* I . . . . . . . .

t00 200

40 LINE EM-380 E

0 BF

20-

0 0

z95.. .............. ........ .......

10 0oo 200

4 LINE EM-400 E

too0 200

I Distance (feet)

I

Do N.E ScaW Tft,i Drawm9q

0 0 0 0 0 0 0 0 0

Page 139: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

°5.

LEGEND:

0

0 a - BUILDING0oF - BLAST FENCE

0 F• - FENCE

0 FN - FIRE HYDRANTLP - LUGHT POLE

M - MANHOLEP - UTLITY

0 RC - REINFORCED CONCRETEf..... ... a - SEWER

300 V - VEHICLE

- CONDUCTIVITY -

MI.USIEMENSIMETER (m8Im)

IN-PHASE COMPONENT -PARTS PER THOUSAND OF PRIMARYELECTROMAGNETIC FIELD (PPT)

0NOTEREFER TO FIGURE 1

FOR LOCATION OF SURVEY LINES

4

ft0 300

FIGURE 1-13

ELECTROMAGNETIC IN)CTO PROFILES

SITE 5 - AMMUNITION DISPOSAL AREA1-1 AREF]

SKY HARBOR lAPPHOENIX. ARIZONA

4 0 0 0 0 0

Page 140: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

!N

E40 .. ,LINE EM-420 E

2C

300

too 200 3

40- LINE EM-440 E

20

0

• . . . . .. . . . . . . . . . . . . I . . . . . . .

too 200 31

40- / LINE EM-480 E

20

0

. . . . . . . .. .. . I• I . . . . .too 200 31

00 001 CSI*Thi DraingDistance (feet)

4 LINE• EM-• 60 E

4 •, I I~l i iii I l lHl

Page 141: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

0 LEGEND:o a - BUILDINGa 13OF - BLAST FENCE

"0 F - FENCE0FH- FIRE HYDRANT

LP- LIGHT POLEM - MANHOLE

",a P - UTILITY

. ,ft I ' RC - REI*NOCED CONCRETE

300 to 8 SEWERV VEHICLE

CONDUCTIVITY-MILLISIEMENSIMETER (mSlm)

-. - IN-PHASE COMPONENT -

PARTS PER THOUSAND OF PRIMARYELECTROMAGNETIC FIELD (PPT)

0 NOTE:REFER TO FIGURE 1FOR LOCATION OF SURVEY LINES

ft

300

0

300 1-10

FIGURE 8- 14

ELECTROMAGNETIC INDUCTION PROFLESSITE 5 - AMMUNITION DISPOSAL AREA

161 AREFG

SKY HARBOR lAPPHOENIX. ARIZONA

0 0 . . . .. . .ft ITRNATIONAL

4 1 0 S 0H 0

"• Ill n| HI ll niiOiPOHATION

Page 142: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

T

APPENDIX C

SELECTED GROUND PENETRATING RADAR RECORDS

4 S

kS

KWW45l.PP/-APPENDIXF C2

4. 0

Page 143: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

CC PositionW I*- Cut In Asphalt --*Pipe

10 0 10 21) 30 40 50 60 70Oz ID -i.~mJ M-..' I - . " -

WSW. gem

100

0.

0 7

0C

SC

NE

z I

40-

* 1964 IT CORPORATIONALL COPYRIGHTS RESERVEDDo Not Scott- This Drawing

Page 144: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

t) 'sition (feet) PIPE? PIPE 1- Fire Station -O

70 so 90 +100 110 120 1:10 14015

p! WO I

-2

-3 0

-4

CD

-6 D

-7

-8

-9

FIGURE C- I

GROUND PENETRATING RADAR

LINE 360 E, 300 MHz ANTENNASITE 5 AMMUNITION DISPOSAL AREA

161 AREFG

SKY HARBOR IAPPHOENIX. ARIZONA

j jINTERNAIONALTECHNOLOGYCORPORATION

4 000 0000

Page 145: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

N Position (feet)S

47P1P Anomaly A/PIPE ?

0 10 1,20 30 40 s0-1

-100

-w0-- 0

-2

UnU

oO 0

C3

401 UJ 30 I l I 'IE -

z - M

4 0-40

-6

50-50V

10 1964 IT CORPORATIONALL COPYRIGHTS RESERVEDDo Not Scale This Drawing

Page 146: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

NPosition (feet) SPIPE ?

PIPE PIPE ? Anomaly B PIPEI0 0 2 040 50 6011 70 80

,tn~i=-j -0.

0-I

-0

>~ >

do- Apt-3 'Q0

CD

30-' 41

F -7

50- : .,

LINE 460 E

FIGURE C-2GROUND PENETRATING RADAR

LINES 440 E & 460 E300 MHz ANTENNA

SITE 5 AMMUNITION DISPOSAL AREA161 AREFO

SKY HARBOR lAPPHOENIX, ARIZONA

j jINTERNATIONALTECHNOLOGYCORPORATION

Page 147: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

W 0- Cut In Asphalt - ~ Position (f

300 310 320 330 340 350 360 370 380 390

cz

10--

40 04

L)0

40

50-

0 1904 IT CORPORATION4 0 ALL COPYRIGHTS RESERVED-

00 Not scale this Drawing

4 000 0 0 0 0 00

Page 148: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

PIPE ?Position (feet) ~jElectric Manhole Anomaly A E380 390 400 410 420 430 440 1~45C 460 470 480

T -0

II owl -6 AIII

-7

FIUEj -

F61GARE C-

SKY HARBOR lAPPHOENIX, ARIZONA

j jINTERNATIONALTECHNOLOGYCORPORATION

Page 149: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

0 Position (feet)

3 iNW JPIE I*- Concrete Slab--.* PIPE<20 10 20 340 40 50 60 *70 80 90 100

0z 0 0-

10- ____________________-0

10-20-

30 -5 >

000

> 40-D C

I~ a.-

0ý 6

Z E 50-

100- 7- A 60

ILE

I 6 0120 M 00z

Page 150: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

NW Position (feet) SEPIPE PIPE I*- Concrete Slab PIPE

S,10 Jj20 30 40 so 6 0 j 7 0 80 90 100

0-

P~20-

A' 'V-1

30- CD

FIUR C-4

LIN 40-

120 ANM00Mi NENA

SITE '5 .AMMUNITION DISPOSAL AREA161 AREFG

SKY HARBOR lAPPHOENIX, ARIZONA

j JIAfrERNATIONALTECHNOLOGYCORPORATION

4 0 0 0 0 00000

Page 151: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

IL

APPENDIX D

SOV SURVEY REPORT

Page 152: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

SOIL GAS SURVEY

SKY HARBOR AIR NATIONAL BASE

& PAPAGO MILITARY RESERVATION

PHOENIX, ARIZONA

BENVIRONMENTAL SERVICES, INC.&

I S

Page 153: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I SOIL GAS SURVEY 0

SKY HARBOR AIR NATIONAL BASE

& PAPAGO MILITARY RESERVATION

PHOENIX, ARIZONA

PREPARED FOR

IT CORPORATION

312 DIRECTORS DRIVE

KNOXVILLE, TENNESSEE

PREPARED BY

TARGET ENVIRONMENTAL SERVICES, INC.

9180 RUMSEY ROAD

COLUMBIA, MARYLAND 21045

(301) 992-6622

FEBRUARY 1991

I

Page 154: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

mS

EXECUTIVE SUMMARY

From January 15-17, 1991, TARGET Environmental Services, Inc.

(TARGET) conducted a soil gas survey at the Sky Harbor Air National 0

Guard Base and at the Papago Military Reservation, Phoenix,

Arizona, as part of a site investigation. Samples were analyzed

by GC/FID for petroleum hydrocarbons and by GC/ECD for chlorinated

hydrocarbons.

Very low levels of FID Total Volatiles occurred in several

locations in the JP-4 Hydrant Area and the Hazardous Waste Storage

Area at the Sky Harbor Air National Guard Base and at the Papago

Military Reservation. None of the standardized FID analytes were

present above their 1 gg/l detection limit in any of the areas at 0

either site.

GC/ECD analysis indicated that relatively low levels of 1,1-

dichloroethene (1,l-DCE) were present in samples collected from the

JP-4 Hydrant Area and the Hazardous Waste Storage Area at the Sky

Harbor Air National Guard Base. Tetrachloroethene (PCE) was

observed in all field samples. However, since comparable levels

were also observed in all Field Control Samples (indicating

persistent carryover in the sampling equipment), it is questionable

whether the concentrations present in the field samples accurately 5

reflect conditions in the soil gas at the sampling locations. None

of the other standardized halogenated hydrocarbons were present

above their respective detection limit in any soil gas samples from

either site.

S

G • • •• • •i

•, mmmmmmmmm,, m m m mmmnnN m n

Page 155: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Introduction

IT Corporation contracted Target Environmental Services, Inc.

(TARGET) to perform a soil gas survey at three locations on the Sky

Harbor National Guard Base and at one location on the Papago

Military Reservation, both in Phoenix, Arizona, as part of a site

4 investigation. The field and analytical phases of the work were

performed from January 15-17, 1991.

Field Procedures 9

Soil gas samples were collected at a total of 32 locations at

the three sites. Fourteen (14) samples were collected at Site 1

(JP-4 Hydrant Area), 11 with the hydraulic probe and 3 with the

drive rod. Twelve (12) samples were collected in Site 2 (Hazardous

Waste Storage Area), all using the hydraulic probe. Sampling was

attempted but was unsuccessful in three locations in Site 3 (Fuel

Bladder Area). Six (6) samples were collected at the hazardous

waste collection area on the Papago Military Reservation, all with

the drive rod. Sampling order is included in Table 1 and sampling 0

depths are shown in Table 2.

To collect samples with the van-mounted hydraulic probe, the

probe was used to advance connected 3' sections of i" diameter 0

Sthreaded steel casing down to the sampling depth. Although the

j proposed sampling depth was 10', some samples were collected at

shallower depths due to probe refusal. The entire sampling system 0

was purged with ambient air drawn through an organic vapor filter

cartridge. A teflon line was inserted into tne casing to the

bottom of the hole, and the bottom-hole line perforations were

I1

4 S S 0 0 0 0 0 0 0

Page 156: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I1-

3 isolated from the up-hole annulus by an inflatable packer.

To collect samples with the drive rod, a 1/2 inch hole was

produced to the sampling depth. Where pavement was present, an

electric hammer drill was employed for penetration prior to using

the drive rod. The entire sampling system was purged with ambient

air drawn through an organic vapor filter cartridge, and a stain-

less steel probe was inserted to the full depth of the hole and

sealed off from the atmosphere.

Whether using the hydraulic probe or the drive rod, a sample

of in-situ soil gas was then withdrawn through the probe and used

to purge atmospheric air from the sampling system. A second sample

of soil gas was withdrawn through the probe and encapsulated in a

pre-evacuated glass vial at two atmospheres of pressure (15 psig).

The self-sealing vial was detached from the sampling system,

packaged, labeled, and transported to the laboratory for analysis.

Prior to the day's fielQ activities all sampling equipment,

drive rods, and probes were decontaminated by washing with soapy

water and rinsing thoroughly. Internal surfaces were flushed dry

using pre-purified nitrogen, and external surfaces were wiped clean

using clean paper towels.

* Field control samples were collected at the beginning and end

of each day's field activities and after finishing a day's sampling

in an area. These QA/QC samples were obtained by inserting the

4 probe tip into a tube flushed by a 20 psi flow of pre-purified

nitrogen and collecting in the same manner as described above.

2

4

4 0 0 0 0 0 0 0 0 0SNUNNIIi IIlI i ii

Page 157: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Laboratory Procedures

All of the samples collected during the field phase of the

survey were subjected to dual analyses in the field in TARGET's

climate-controlled mobile laboratory using a Shimadzu 14-A gas

chromatograph.

The first analysis was conducted according to EPA Method 601

(modified) on a gas chromatograph equipped with an electron capture

detector (ECD), but using direct injection instead of purge and

trap. Specific analytes standardized for this analysis were:

1,1-dichloroethene (1,1-DCE)1,1,1-trichloroethane (1,1,1-TCA)tetrachloroethene (PCE)

Ten other halogenated hydrocarbons are also included in

TARGET's standard gas mixture and are standardized in every

analytical batch. These compounds (and their respective detection

limits, in ag/l) are trichlorofluoromethane (0.05), methylene

chloride (1.0), trans-1,2-dichloroethene (1.0), 1,1-dichloroethane

(1.0), cis-l,2-dichloroethene (1.0), chloroform (0.10), carbon

tetrachloride (0.05), trichloroethene (0.10), 1,1,2-trichloroethane

(0.10), and 1,1,2,2-tetrachloroethane (0.1).

The second analysis was conducted according to EPA Method 602

(modified) on a gas chromatograph equipped with a flame ionization

detector (FID), but using direct injection instead of purge and

trap. The analytes selected for standardization in this analysis

were:

benzenetolueneethylbenzenemeta- and para- xyleneortho-xylene

3

-

II i - - . . . . . . . . . . . . . .

Page 158: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3 These compounds were chosen because of their utility in evaluating

the presence of fuel products, or petroleum based solvents.

4 The FID Total Volatiles values were generated by summing the

areas of all chromatogram peaks and calculated using the instrument

response factor for toluene. Injection peaks, which also contain

the light hydrocarbon methane, were excluded to avoid the skewing

of the Total Volatiles (Totals) values due to injection distur-

bances and biogenic methane. For samples with low hydrocarbon

concentrations, the calculated Total Volatiles concentration is S

occasionally lower than the sum of the individual analytes. This

is because the response factor used for the Total Volatiles calcu-

lation is a constant, whereas the individual analyte response fac-

tors vary with concentration. It is important to understand that

the Total Volatiles levels reported are relative, not absolute,

values.

The analytical equipment was calibrated using an instrument-

response curve and injection of known concentrations of the above

4 standards. Retention times of the standards were used to identify

the peaks in the chromatograms of the field samples and their

response factors were used to calculate the analyte concentrations.

4 The tabulated results of the laboratory analyses of the soil gas

samples are reported .4 microgrars per liter (gg/l) in Tables 3

through 5. Although "micrograms per liter" is equivalent to "parts

4 per billion (v/v)'"1 in water analyses, they are not equivalent in

gas analyses, due to the difference in the mass of equal volumes

of water and gas matrices.

4 For QA/QC purposes, a duplicate analysis was performed on

4

I

4 ! 0 i 0i

Page 159: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

lb

3 every tenth field sample. Laboratory blanks of nitrogen gas

(99.999%) were also analyzed after every tenth field sample.

quality Assurance Samples

All laboratory blanks were free of detectable levels of the

standardized analytes.

All Field Control Samples contained tetrachloroethene (PCE)

ranging from 0.08 to 4.0 gg/l, indicating persistent carryover in

the sampling equipment. The PCE observed in the field samples

(0.60 to 6.7 gg/l) may not accurately reflect conditions in the

soil gas at the sampling locations. Unsuccessful attempts were

made to remove the contamination from the sampling equipment.

Instead of immediately outflushing the nitrogen drawn into the

sampling system during the purging step, the nitrogen was allowed

to set in the sampling box for 5 minutes prior to flushing. In

addition, sampling boxes were evacuated for 1/2 hour at the end of

each day.

Analyte concentrations in duplicate sample pairs were within

acceptable limits.

5

0 0 00 050

Page 160: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

mS

TABLE 1

SAMPLING ORDER

JANUARY 15, 1991 JANUARY 16, 1991 JANUARY 17, 1991

SITE 2 SITE 1 SITE 4SAMPLE SAMPLE SAMPLE 5

1* 6* 1*

2 7 23 8 34 9 45 10 56 11 6

7 12 7

8 13"* 8**910111213**

SITE 1 SITE 2 SITE 1SAMPLE SAMPLE SAMPLE

1 14 142 15"** 153 164 175*** 18"**

* Beginning of Day, Field Control Sample** Field Control Sample***End of Day, Field Control Sample

6

Page 161: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

TABLE 2

SAMPLING DEPTH SITE 1

SAMPLE FEET

1 102 93 104 107 108 109 10

10 10 S11 712 714 1015 416 417 4

SAMPLING DEPTH SITE 2

SAMPLE FEET

2 103 104 105 106 107 98 109 10

10 911 912 1014 10

SAMPLING DEPTH SITE 4

SAMPLE FEET

2 23 24 45 3 06 27 2

7

0S

Page 162: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

0 00

S00000000000000

V4 00000000000000v v v

W4

4 .4 m

E-4 E-4. A ~ ~ 0 H0 0 0 0 Ln ooorio 0H OH *. .. ....................

v vv v vv v vv vvE-4 W H 5-0 rH~ 04 04>tqU) :04 U

U) HE4

>4 1 4 1- 14- 1 -4- - -

C" ) MM 0vv vv vv vvE-4O U PQ4

::) H ~E4640

w ~ 00000000000000 z~I

09 H 0 00P

E-4 A E-

*- 00000000000000 03 SA

W .z 44A - *4 46-4 .- r- 4

-4 e4 03o 4v vv v vv v vvv vv v vv W- J~ n

U~E E-4Ad0 P4 43~

rI 0c5. 0 E4

0 00000000000000 a. 04.jo~a-

C) . V. V VV V V .~ . .5. . -0 CO E-COv v vv v v .4J44 Cr

a) %0 41

P. E4 AU4 9-4 at6 .v4P ..-

44 9- -

0~~ % S 0 a

Page 163: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

0000 00 0

r-4 rVV4 VVE-4

4r

W 0000 00 0

v-4 ~~- v vv v

E- E4 VVV VV V 0 0 0 >

H 1. - 4i

E-4o W H 0 >4OH .4 4

U) r

CH z 0000 00 r

w 1 4r.3E-

0 0 >4vvvv000 00 0 x n

w E4 64

- w z~ VV0 E-

04z a 0000 00 0 mI

9 H 0

E- E-4u

E- 4ral 00 0000raP22z >4 00 0

u E4 rza ra 0 z~

[-4E- 0400

W 0000 U4 00 9 41H 00 E-00

0 vvvv v v v v 41Nr. Fa 0 0 '41.4 [4

0 0 r 0 ra D11

04E4> 0 05$4 E-E-

S 000 00 0 0 4S .

Page 164: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

E4000000000000H #r4H.

#4 000000000000 0'E-(

H4 VV U t4

b, T,

w 1 coo; 1;ooo 4o4 E-

E-14 vv v v0vP4 ra3

A F0

CA Ho

0 zz

9 H 0 0

E- 0 W. r4.4 rk

z 4 q . H . .0Wh VVZVVVVVVVVVVH t-4 sc

U~~ ~ ~ E444 F4 vvvv vvvvcz~E 94m a0 P4 =

*E-4 I 00 4p

W 0 r- 0 04

Page 165: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

P. 0

000 00 00

E4 000 00 00

9-4

W 000 00 00

UU

9-4 rO

r4 v vv v v v v z

E-4 E- 000 00 00>0

0>4 V V E-V E-

E-o 00 0c 0 HH > ***

9:~ 0cJ 0I vvv vv vv W

5.4~r ::)'4

W W 000 00C )00 m

m-9- 9-44 - -'4

E40U H 0 0

000 64 00ooc 00 N~

04 P4 004Nal Ou4) E-

pa W4 004 55z to v14.4 fo D,

W~ 000 H4 00 00 r.41~ Z64 N 4 - C 0 . 4 ) H

0' . v vv v vv v v '4 i4 W~m0 0 9-44.' 54D

ra~ra 03N 14 =C

5.4 >4 $4 0-

t to . . . 0 H r411w 54 v

r4C4~~ ra . )

uI E-4W

W a E-44 to~i

Page 166: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

00

E- 00

00

UU

r. .4 E4 E-(- 10.4 VV W

P3 U

Z4. 00

H) 0 0W-

co P

I W00Z

0 CJ0 C

N - 0 P4 C4H 00.

OW In4 vv UE-4 0Z W 04P

z 14 tq 0L) E-4 f4-v -

z N4 mNa

04 0 9ra 0

0 v v 41 14 g

144

z 00*

00 Of4J. E-N

E-44'.4

0. 11 1"14111Pi 4 E-4e E- QE

N1 in V4 04

Pd 0- 14E- U1

Page 167: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4E 6

4 WV

11 000000 00 0

ri4

I-4 V VVVv vV

000000OO OO 00 0 >0H HH Hr- . .

E-4 W H 0-4

44 NpqN

H z 0~00 00 O

H~a rr

,a Oc HH - HH H N4 (n

9QI P Z ~ 0

E-4 zz wH %a 6

S)I m v vv v vv v v v U o Pr4

0 z 0

.1 00 00 00

E-4 E-4HH -4 - Hg

0 FA 04

gN In 0CEAA 000000 00 0 P4

.. *4 Hq .6 . . .94 XZ r4r4- 4ý -HH Hr4 H ' O

0 VV V VV V .0.14E- P *'1

Z4 005 Z4

4000000 00 .0Ir c4> 404J p H

E-4 0*0410 z

to5 0 r-4 0 4J C4N 4 0 w

14 m 4"

Oq 0 P r111z CO I 14

m 0imix90 4 414E-H3 % %) U -

z W4E

_~~- 01 __ __ 1

Page 168: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4 S

4 APPENDIX E

SOIL BORING LOGS

*

4 Iwm m • • m mmmmmlmm • • l ~almlmilm m Im

Page 169: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

BOPI NG L or BRI NG/WELL N.: 5 i S-Pg ___oirtil~ r _jA. tj( Site:. f-T q

:rcL ect No..4ci~zI.cz.,y Client/Prole ect.w A~cHAZWPAP Contr-actor C. QppoAc, Dr-i Contr-actor"Lifos "- iller :;nzl: Star-tea. giv-Ap koo -- n Driq Ericea: t q r ( Borehole dlia(s): 9 ADr~c rlettrcc/Riq Type: Ap aa

uzcc: ~, ~E-Log ( Y / From -Lo - Protectlon Level

L!Ltholcaic Description ct"'6 6 .

IL~14 t 1J~ Af 1Ed1iv. f

-4 /2f uxq 4 ý f v o ^ f

0 jf ý4... w sv . c

70,-

*~~~( ;A .q

(CCL'

A&;.- dA'u.A A s CPQr. XT

u Thi~n wallI Tw.e R - Rock Coring %A________ Flela G/C(Make/Moa.)S* 5ollt sPoor~ti.0e) 0 - Other Pik_________ 6/C Oper.: ______________

C - CuttingS Notes: Ao le, iS~*.IA Aa %&LrL

0 0 0S 50

Page 170: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

IBORI NG LOG BO NO-:wELTNPage-*i- oflnsaflaticrL f~m&1 Site; EV AE.MY19

o- ) Drg.Encd:I fipi (o 5 A m Driler: o Ie iaOs: qI

4 Lo e-: Dv E-o: r- to Protec-tion Level:j

:~ ~ Lithologic Descrijption 09 e e ti W,

fu- SOW334"

tAF'44 IC.t Xf sr,

YA9 6*s 2i0 - d

S. CD W_ 4%.Ik-

F4 ~ ~ i ?DL~ '9 9 6

~i dW.A. C~A.'j iC-a' .S

0 SAO" 80~e

uThin wall Ti.be R - Rock Coring P., Flela G/CCMake/Mocl.)__________5 oI it spooN Ube) 0 -Other __ _ __ _ __ _ G/C Oper.:____________

C utnsNoteS: ma W4~JLtL~(rL

4 ~~~000 0

Page 171: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

X)BORING LOG FB0RING/WELLU.E. £S - MAYe '-of-Ir nstallatiofl: 5.fH - A V vaI iI :roiect NQ.:4'd bu.o4.. c~ lient/Pro ect: SfZ-p TK- &&W Ite:

HAZWRAP Contractof- I Drw~ cO Contractor. r In en-Dn~rt Started; 14 i (12.aS 55 m, Onl Ended:a 1 q79 (111 A-m) IBoremole adiavs): 3/ Q;4Dr~a !lethco/Plg Type: A x. PA&A -- a.'L4dJViJ

L.ccceO by- &AbE-Log ( Y ED From - to :protectlon Levei AC

~ ~,. ~ Lithologic Description 4 $ot

qo~~ 014O~SP

Pi 0

90 4$*u4 ~A"24 t$,~

(o0. -100L.1 \

U ~~~~~~L Z v'f ~3Ai~,I fl*4~ ~ ,ET '.&e

5I 6 CA.~ k07 .w-w

i.~ o44 I ________________ ____I - ~~-"' } _____I

7 h alTe R~c oigFedGCMk/o)__________Spltsoo~~e *Ohe ____________ 6COpr: ____-V_______)__

CutVg N tes4 ___________________________________

0) 0ý 051 310 SS S

Page 172: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

(5- cL//Z~e- S-- 3 -EV DATE MAY ~[50PING LOG BORING/WFELL N:

ir5*aiiatlcn Sky Harbor Coordinates: S~ite ,

r-.7'XýoP.-D Ccntr~ctCr-. rj2~a- Drl Cont7r-actor- %f Amw Dri I ýen ýý Loab&Dr to St2rtea s, ~ ( WO e_ Dna Encec t I-oft, -ti -L mJl orer~ole ia(s) 4Z4

4Orio rmetnoo/Ptc Type: A 4.t..uA,"a Cm Fro&Coac C'i E-Loc 7 v Fm -toroectlion Levelt

~~~ ~Litr~oloaic Desc-otion- - ' '

m,. -w.A tC

15

O0% F41A, C.yVJL A.-r

AW61> a'&A SJ~ Ls4ý4 5 JI. (LIhJ~ &0

/xy 414)4 LEL4. -1,so

F~!- - /C(rl:!%e/M~cc PAJ

E i: T::ccrt~te)0 tr CoC c-= 2..: ~~o-t t'r ___ KCcrA

Page 173: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

6m va-l!'oREV DATE. MAY I C)9(

SO~itNO LOG BORING/WELL NOf.; Page 23L or' 5r~staila~cicn:kHro Coordinates: Sit e: ac1-* -ro iec t No.: q~?4.oz.d3f C) ent/Pro ject: ilw ,j

M-7P;; Contractor OTcjAm, ria Contractor' aG Aam. Mj I eD ria Startea ijit1 (.1.o -.- m) Drna Enaea: 11 1J (1:c -wA--M) I rrer'io Ie a Ia(s)

4 ~~DrIq riemoia/Riq Type: _i_ Ap,*m. 4 .,mLooceC Cv: E-Loai ( Y NW From..._.to_.......I... Protectoeel b

CS -ihloi Description G01 ,

- - Mo kt v.4wLy- -

Lb 0 AA 12 v, A'" - so

soo* MA-, ro F*L.. Cyw

S Ar.JSf

L4-' S'4~L~ 4

as.~ .'~

o Jo rc- viy

W.C 4pn N

SS0 0J 9-4 0 041

Page 174: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

FI~//~ S-3I- AEV DATE. MAY 19C)O50PltJG LOG BORINCVWELLNO~.; MC-~ PageL.I.of 3lr.ýtailaucrl Sky Harbor Coordinates: ISite.

s 'ro lec t N. q 4L,* .njO C) ent/Pro ject: 1ýAwktr . w P C c nr ctcr2C - [ _L .m a tp , iD ia C o n tra c or- L u f " q , .& . .. l D rille r - ) g e i a ' 'b.rIa Startea, (1. - mloD~ Encae i olq (it :A. -ml Boren~ole ala(s) q-A,

Dnlq lAetrnod/pia Type: kLOOCeC CV CvtAb,.4 HtfEf-LocCC Y /1"N CFrom to Protectlon) Level.

t C! 9L~r.0 LIthologic Descricition lOt

AT-r !L( 1 q

90L6 A*5. (IX f-J/ (5i~ p -

55ft

A ~ ~~~~ __ _ __ _ __ _ ___

u - -r. wall TLC? R - Pock Ccrirg AlA Fie~c G/C(Mz!.ke/riaa MAJi:ocr.(tLt~e) 0 - Otrier CA ___ NI Cr A

Page 175: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~Ie-L/Z~.. S3~..- EV DATE. mAY vb0PI NiG LO BORING/WELLI'NO.: LASS -0O P aqe _L__of

jj.uýaII1ticn Sky Harbor Coordinates:Sie-(iC i ~f'-''Client/Pro ect: o,4 4*eV-, i 12ng.~?'~Ccntr2CtOr- Onha~j, IDl Contrac[0Lj or. DrilIler r:ýI

Cjrl() 52r~ea t10q (oitD m) I r l Encea: 2 J4 Iq j 6 0 r)8orenole aiavs) 912

-brig r1it-noo/Aia Type: fjdLc*e ry I E-Log ( Y /(I) From - to Protection Level

49 ý1 Llthologic DescriotIon *,c C00 t ~~' .4 \,c~(jI

4 04'' 0 ti 5~sk\

4 25', .-. OAV ~. z

((2~4:Z 01 Id,%rO %

U--

* ~~30 0 Aos

4 iu *7n.wall TLc? R - Rock Ccirn.9 PA_________ Fiec /rieMj AAS .' scocn.(Mie) 0 - Other CA& S G/C Open.: kiAk

- H~~otes _____ -

Page 176: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

F~e-uzg. -3.- V DATE MA/Y itqoE)) UI HG LOG BOPING/WELLNO;,: Y-~page -1.of.3 rz'.31iLaCn Sk Harbor Coordiuates: ISite: 5;,

-ro jo. fJ..I ?11.014o' Client/Pro ect: k~2,*i Z a -4 ~ Ccontractor. 1 Dr-ic Contractor- .j.,- Drifller

L~-OStarted) 11i i q If L m) Dr-Ia( Endledl 2-L JA ( .8O .*.m)IBor-enoie 012(5) IVA"C~riq r-i~tnoo/Pia Type: AILLo"'ec~v Cy 00Lo IY From....to.......... Protection Level

~tLitholoalC Descrip~tion Gj f ~ 0%1 \ atef

3 3#- 17 op-&r

4-. o ~ ~ E4 to 5A4.~r4x

* ~~A* 1 ~*LuiA 1 b~dtj

o-

77u 2r wail TLC? P *Pock Ccrirrg MAA Fie~c G/C(Make/Mooaj A)A_____.___________0Other___ G/C Ooer.. N___________A____

Page 177: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~ S-d--PEV 'DATE MAY 199,-60,4I1 HG 1-00 BORING/WELLNO.: Pae 7 oirE',30i.-icn Sky earbor Coordinates:Sie

Z~o~i~~Client/Pro ject: ALR T yAZ2CcntrCtor* 1:~ Cotaco Bori liter

4,I~ 5tj)e 1 Sc4' 0 ) u'oo )IB n I e( 25

Drc MA10/1 Tye A7t

cy 6kt-r) E-Loou y Ce' V). Frmt rtcine

00L

* 'Jr

Al

4 z UL-h3OAs- ruiWSO- A- SýAp(Jao S,NJ U/1014*4 co OA&

44 G"ý4 A6JIO Iý&ýýW

4 j 7r, wall Tt-n A 0 RoCk Ccrir~g NJA- Fie'c 6/C(Mazke,Micc A k___________* ' -zor.(ti.-e) 0 - Other CA..A -S G/C Over.: ha___________A___

4 oe:________________________

4

Page 178: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

;rý SkHfarhnr -1Coordinates:

4iJ~ .7ent,~roiec,~ Ccrt~2tcr- rc~ .- . J-Drl: Coriralcior- .i6 r e F

-n I Dr'c Ercec 1/31 3 1 20 A in.- c-ero e c~ars)~j r-rcj,'Ric Tyce 1 4

r~~~~~~p" 'e Cc j) rm t ee

4 _,t

",4^ A-- A**

Sea 16I ~;I

15 a CQ"'AOL d 2f%/

rIf CW'-4O, Sowbv m4 'YL~ \~-4 SI

5' wl- Er&-A14A~ (7-- - -L po(!f ,,ý T

-- A-6- __ _ __ _ _ __ _ _ 33 1

-- ~~~~r rrvq-6 f:AC _v ________________________________

A) A,

S 0 0 00 0L0?

Page 179: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

P 3 LO0G BO I NGiWELL NO M 2~-j

3 1-T'7 Sky Harbor Coordinates: S te ,

SoDr e *0cA (1 "W 4- 'r') D~r Encec 3h ~Ic 13j w0 zLm Bcrerole Cia(s)Dro ~ercc/PoTypes A ./~-

E-LcC i ýý Frcm to ý)rccec':Cn Leve!

90

&Jo tell/E-~ L~tIcc~ Des:7 S

Lf 0 ~ Ok,~ ~ "Ag.

'2. 5 Yo5/)0,T

fa

0 10

POR0 S.e- 4sJO%)

I-V- i A-.r-I~4 6/jftj,.

*(,7.SrYL S/A)s

j~O.AJO~a *, .

ILI so

-- 1(4~1'A

Page 180: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

2;:;j~cnr~t~ ~ t DATE MAY IC9(

@ 1 0PftIG LOG BORING/WELLNO.; Pj •e--L Pa ofo =

r.ý:ailaticn Sky Harbor Coordinates: Sit e. - ~L.

r- 7 P -cn r ct r. F D rna Contractor- . ~ ~ Drillerýýrr, L~a. h- O: .7 -- m) IDrla Ended. t1,3;2o* miw BeM orenole dalas) j,7/1

4 ~riq rle-trioa/Fzia Type: At k,~cce c ~E-LOO ( Y /, or( From -to Protection Level ~

Cý; , 1Lithologic Descriotion 6 ,0 c , to0 #3 It aO 4

(IPrO 413( i~) , A q 9 Se 10

3 '*404 )4E re "?~~ '

5r-*

w21 P PccAu,& -3rn COAOA-Otlreri V-A 0 rVOOer. AJ

~~~~'' pit~ _____________________________P

Page 181: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

,~I ~&'iZ- £-3 ~ EV DATE MAY lqc

BPNG LOG BORING/'WEPLLNO. (UWCJ-09 Dage -- f--II n-taIalfl:tI Sky Harbor Coordinates: ISite:!SDro Iec t N4o.: I CIlient /Drc 1,ct: HA--b.m9.M - S m af-A 34a .

.H.AZWPAP Contractor rr&, ý Droe Ccntractor- L~.c" j ýIDr, ller- DA...' LI, t~

*Dn~a 5tartec. 3bilg (11 '44.A-.M) I Drjc Encea: I lti (L W mil Borehole dJia(s) VDrnc Method/Riq Type-Aiw-r D,-Tut- oj-rrtcineLcaaec ov Ab.&E~cv /0)) From - to- oeto ee

Lithologic Des:oo NJ Ib G

AP Sio cal- . 13AO -4'~4 el~J..'-YA' 4 j Qw - Y 1&t-l 20%., 9-1 --a)J 4 j, soe ,-f-

o 6jo 570'-

0 NoA&4.ovw*.2 6t,, eyA- 5*

,, I

g:N~~tq, 4ý7.-O'~

40 A)r Ii~gt, t,-4-.V'4, -

C. 4%JrIA 1?-'~ e

~t. W dc i "P. y 5/'.

3or No ý 5

S ~ 3 IP A) o

Page 182: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Fu-,,6.~7 0~- PEV.'DATE.MAY I (cBORING LOG BORING/WELL NO. Pag -2.- of......3o

ii nstallation: SU Rarbor *Coordinates: Site: tDroject NO.: 407'l,( Client/Drolect-H2g4 m*^A A6LJAQ

qHAZWP.AP Contractor-.teo' Drio Contr-actor- L&a Drl ler'Orba Startea. 73kiu 4 (q %e A m)I Drbc Encea: -/il1(1 sopml Borehole dlia(s): nIV13.

Dni LlgeC Oa/Ri TypeC:h#E I. Eo t Fr om ~to Protection Level

3S A)o' i Va.-'~

aLI 0 105~ w4 ý- 7 -A 3/2) 1r,Al rO--

4 wo~~~~x4.% -/CAI( Cj"m,CA04vJO 'o ' S-3D6T oov-c 64aa'A

1* f.- pv 4J.,.tsbe 1 AUA17S VA ALb4VJL1

-5eaJ ' Dm, qC ry 24

Ua/ 6O~aA"4 I Ll071 sa,j A, p" CbgiS. A&%,

1b S , 44 l'%2Lo -1~ &A j

*S

U - 7-r ai I~ %c - Rock Cci-r-C _________ Fie!-. 3/C(M2Ke/Mrcaj.J ___________

* *~ socrtL~) - Ctb~er o____________ oer. ________________

4

0 40 e0 00

Page 183: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

*or 4U- 0 0 0 0 0 0 0 0~

IInstallatIcn: Sky marbor Coordinates: 5i te: $MBAciu&, te.. WS

Project No.: '49k- Clfent/Prolsct. HAbW p

X, ~~~HAZWPAP Contractor IT( Drna Ccntracto~r LAisj ",gdfp r e

Cr0o Statea 31411 I It$ A-m) IDrIc Enaeo: 3h* (4s 3 ?-m) Borer~ole aiaS)l '% v3/.,"

4Loa ec bv E-Lco ( Y / (qrFrom to - - Protectuon Level

Lithe gic Deccnotion

0AJ ~ Ab,

Cnqjei ~ ~ ~ S j 4 a.CP $pp

1tv re

PtAAAO rw C.4-kg it~j~i i-.

AM0 5- 51IS RA#1

Iu 7' Tr, wallI Ttt? R - Pock. Ccrirng _ _________Fte~c C/C(riaKe/Moc __________

4~~~ ~~ C 5. SCOOcntLte) 0 - Otmer _________ C~'c ~er. ________________

Noe

Page 184: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~',~ze £-~ ~-PEV :)ATE "~AY

5OR:NG LOG BOPING/,OE-L N 4LLac -- o

r'stailaticfl Sk Harbor Coordinates: Site:

)r-oiecl NO. '1 Li.-L-4-1 Clent/OrClrec` 5g, W0.4-4ZWP;A: Ccrntractcr- T Dr'a Ccrtracfcr- LwDr fler IM-

4 Dr~o 572-rcecei. 9' 2 ( a-C a. m) IDrc E'~c-: / 2jo4 I i.oi m 5orer~ole cia(SDr~o Mietn~co/Pi6 Type: A .L mmd-i ~iLCGceC- -V E-Lcc -rm..........to.... Prtcti'or) Leve'!

Lttrio~lcci Desc t f w09 4..,\~0- -- D-46 n. iw ~ r1Y.S)

tw DA~ So$T.¶-.7 G,.(W%'A) ' 4.50lb t -4Aovr

4

lu 0 f% -- a01

@ 4 I,0 0t,

A* k r"'~ (t-a- C-ff .- w.M d, 1- WLj t. So

va, MA~~________~GCMk'lcM

4

* 4 0 4

Page 185: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~I ~-L1Z~ .53 .- REV. DATE MAY 995OPI NG LOG BORI NG/WELL N.- Mw1 - 2Pae oir.staialticf Sk Harbor Coordinates: SieDro tect 'JO 'lovj!3icLoG Cflent/Proiect. ~wk w' 4

U - rA.ZWP;. Cntrac or Dr~c Contra tor- Ljv,. DleDr~c 5t~rte o. k W IS: A.-.m) Drna Er'aeq 12*h (K.W *m)1Spreroleaia(s). iDrIg rietrmoc/Ria Type: k wo *,

- Loce tVE-Loo ( Y / & ) From -_ to Protect 101 Level~b i~o

P'-s-D lo a f Dest rto _4t k 9

tjo c'. v& f iy

Xtt.iP C~ t)4 4.& 4 4 4

f*-w 0' 5 1 P'.4d.A5

* 0 ko c~ 5 /3) , so5ots ~~o M&- Yf) 3 r: 6 -Al 0.4 0' -.r, v

69w-ek K*4 gP

141l t7 ________- r y XCS12e, fWO-a _________If__V_____So

I~ 6- - .ttewt.J

* 00 6 01 50

Page 186: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

P/6- /~'Z~ .S- ~- V. DATE MAY 1990

IBOP ING LOG BORING/WELLNO, ~aqe .. LorS Insiallattcfl Sk inarbor Coordiz~atea:sie

HAZWP,;.P ContraCtor- Fr Al.. Dniq Contractor. L r.~w LaoOnirDrba Starte0. /i f -aa r .A.m) Onto~ Erioeo It f C mLM P- Bo~renole aa(s)

LoaCeC Dv E-Loo a From to) Protection Level.'(uD~

eiofC ~ ~Lithologic Desciott~io1, 4I,

A,6 At--

II

10 (:o1to ""p Z

~Lote M- V4T )

* . /0 0 0,00

Page 187: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

F, --ta!,a c Sky Harbor Coordinates: IStDrie' 'i0c Ceroa/vc 7cc: k- n% CAN

:ccc :-ý-te N--4q (M40 -- to ýte: r e

()ct i De: -Lo - ,ov+~

P44,.. prf#V #AVp is B

I I

*A~ 0

Page 188: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

50IA/&L "O S3 )

-r Sk Sbr C oriae:St

er L-3o)rc

U rcec 2~U-/-f We CeC00 C-,

,S K -

-OP P.F4 ~

SIXJC C&U(. A~-'9-, -,

6/0 1 eCoft %APjý a

*~~~ ~~ A)& '40t(o

So 0% /,ý c,"cK0 OZ0 31)S

l~~j. ~ 0 0Ae L-~ ______

0% 0

* 100 0A 0 00

Page 189: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

L/ -S-;; ýA -

F'',2 7' Sky Harbor Coordinates: $_ te L.

c~ /21/4 E'?3e- 4- M) E Crerlce c-aW S

4 Z~ *'tcc/R Tv~e: OKa. ~ P00,c r-cm t I rcteýZ.'Cr ..eveý )

II

'4~~1/ C.0(,A.A~.

tj 0 v'

A ;k S/2)

50

* ~ ~~ 300 Ro , -S

va~''. e e __ _ _ __ _ _ __ __ _ __ __

L.:e ____CIA___S

>:zzt~:e 0-ore'-___ ____ ___ _- -AJA

Page 190: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

i i -et at crSky Harbor Coordinate 8: St __

D~r-c Sta~-teC 1/21 r- Ecc . 7. mq cEzor-c'e C-aw sI~~ Dr- Z1tc'' 'rvCe //Lz/ 1-4n0.AIn.Ll

tv CAe E--cc Frm t Pr-ctec,!or, Leve~

4 ~ ~_ .%Xt tS

L;'?Cl Des e *

.0 4.1- CL. cýZ,-o

CAho i4/,-V;LY So

So Aso 6'14

ýJA4

g.,j .ý

ri 611 ST2I ~ ~ ~ ~ ~ P pJ&.VMT F&M.Cs... j$o7y/

5*AO *4 PiOr gVWM U A -)---o ~ 6 s C-'w MK _

* pJ

0 0 0 0 00

Page 191: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I r~a ~tr Sk Harbor Coordinates: Se

_.c eDr I:Z c4V~1.~ ert~ c /ec:t

[)rlc 5trec t 3o iýýcre c et a~s) I? -4r~ ýIDrcc,/Rictype)

-ccce:- E-ý.c &A," ý.... o-,Cte~r-'-r Leve £

I N

A4 IL 3T L"

&Z 51XL -Ilk3 , W 4 4

0 No

ot

MAO cbo4, (3

-: C: - C31Z*2e-C Ao ~ r~~L *I%~~ A,

Page 192: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

-s-a ;1. r Sky Harbor coordinates:Se

4);ý 5"2 -.,c *zI'-I 06 /1 Ao I vi Du,3'e t t m Bcrer e r a, s c

)r!- -eý%cc/PlcType: ~-

-ý Litrolocic on:~c~ ,C

LWV LsAl )4 4p'-'-ýr(

CIA vw. A- A4q-

* 4 50

Z -

0 5

C¶iLtt.J Fx -~I, O ~ ) 5,r~M -1

-v -; -j A A ,

N4A

Page 193: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

P U L0 5 BRINv3 E~LL NO j-I *i!-:it'cr Sk Earbor Coordinates: S te~r~ jo., nCiL. iept/Zrc'e:, HAZjY4AJ /Say * o$ A4.

-A\~~Z crr~tc ~Drc : Crtractcr- k~,.a.& E,., -,r,! er AoT . ,, rX.____

Dr: tte /,Ii * ~Ar) IDr 2 E'C~ec iIjIq, 1 06;r P-- ) Ecrerc 1e c! a(s) 4?. 1:Dr:. r.etrn.c./PiC Tv()e: Ait Pa46mec, HA%ý

I .. c~: .' ~ ... E -..cc ;rcm - to _ - rteC-LjCr Leve, D6,oA&4

0 QC~

(A 5 r ~ 4Thy ~ ,TVn-c

ZL.

15 0

j_ NoCbK

-,. ~'r.a&NO K

a A@L~ L~V~Lf9&Lii

½' ~ ~ ~ ~ L" U-eJ (PW~ '0b b.... . Lw~-

-~~~~~L 44# .'r uP?,iI

:~~~:2 o$-0'&5 A-

4 ~ ~~~~~~~~~~~ e ",c~orte '~cCr:__________ ~ ~ A

CIA r Oa

Page 194: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

-Ta 2 :.7~o Sky Harbor Coordli nates: S~te74:,rclec, NiO Alzi.C*? C' lert/Orc ec:.Wg jAv 7S,- e.

~~Aw~A~ Cortoectzr " I Drlr Ccrtractor- LOW.,& It ~ ~Drc~2:eo g(40 Li &_ m) ~rlc t-~ec: Y7/,vm~o'r'eCas fl j

Dr:, j-ýeco' C TvAe ,.. ,j". - O - ctec:or~Leve'

'%%

4J r N\c \ %~ " '. \,tLit lcc D c--ý,to

4 5f?

LiL~

0 3: sý~~t .

4 ~~ 50qT. ITY W* *

5~ orOJO~ j(4AoLVV A-)

- I ~ L4 S Ici

3, NA

Page 195: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

i rtaý a' -: Sky Harbor Coordinates: ISe.Drciect~r AOUZ..' rt~ e:S-

IAAW-AO

4:wr~r Yoe:2ccr ATtja..u cCrr2:r r ~Z.E

rmft-9 4/-IJi' 41:tj- AJ1 1

100

ppI4rL SiLD 9p rCs -f2-

0l 0*9 -591- LAWYA n

N A

-, oI~oL~~.~Pcc A2X<

A. S

Page 196: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3 rýa.:~ Sky Harbor Coordinates: __________

:7 77cg-iJo 5-5 A, c t-& m) c e~c 2/, mg S-,p-?r) ECrerCe I ,

-' , a(C )

-zt 'ýO~ C. L~trolccic DecEY z--t on O1 \ 1

0 AID&--~ 50

S~~L' u -0 '4 6-^,-k , 20% )t~~~~

ro O(; . &A-. 313, O 4w &*.A, 4o

5'.', 1-

I~~ L WIo ~P ~rYL514I ~ &/4A49~or

0tio ~CI-

__ _ __ _ __ _ _ J

Page 197: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Ic.a ar Sky Harbor Coordinates: r t

cr 737ec 2jAA 5-5s jr' lDr- :1'cec .21tl m-~ ec'ero e Ca~ý'i t iDr: ~et":/~'cTvce ,

7, *::e: -. ' aQý 4,-uz -Prm . to,... ~r~e: Leve,

5A O'?o, 13. ASLJ#,

tA7 ^4&,Au , SOP,~ ~ ~ '

174,t Dt1Jy) -vý ,S

a ~ ~$J~) 4 6AAgJ-L ;W'/-, A. w

ow -^ 60AOW- i. LLU0L'A, S%

poL r *q1-4s

NO 54 ONP 1-fA4l &vtA"( t c4,1

--- *a" 'o --.- e D-C C- N7~K : IA,

6- N A

N ~A_____________________ _

Page 198: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3OirG LO0G BORING/WELLNO. :,t DATE MAYe __o

SCcntractor- lT~Dna Contracto Ir- L LriIIe ~ttL a&X

be-ta 5tartea i $~rt (060S -6 m) IDria Enaepa lit w oeoea(s) 7N,'

LOOCeC tv.LT E-Loo ( Y /n) From - to P'roLeCt OnlLeve)l

&t.~ _ £' C ' tq .rr -/ w1 --S

Wt.

0AI,-TO -.

0 S ý

100

20 Ajo l -'- S

&.-IW4 (. r

1' -- 0" -

PAPA CA)Ja G'

u *-r wali T~tx P -Rock Cuirig . F'lc G/C( 2ke/moo' A__________

S s0or0( 0e 0 " Ote C-, S

Page 199: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

r.~td~tIfl~ Haror ~S-3~- Se. EV DATE MAY 109()

ir-5tai2LPC Sry Harborrn Crordinates:

bria Srteo j~zh of &~ m)I Drna Endlea oli 14, 1 1 o A-. r Borenoiecia~s) 43h .

LOaceC Cvý 6^ELo From... to..... Procectwnl-evet

Lihcoi Decriotion ýc0

0 fjo -t fg- f- r--A

Lf 0 -10 No R.jk.o vdDA y

15OJ P E.0 iA.)Ioit, q, 1, c, 46* - so

""Y' j~i~ 06'L, -ACO

o ~ 17 ryl 6 . 1q A'4'J) 6~~f v v.

.S5

~PAI 644..P_ qs.44. Sea~ /~ So

00 • 5, ,A,,Aw~S~.A,~j.~ /) J

kw& O -. ý

5Ao 13 A,0' .

0M.LL~~d.~P, F-C uLL fT o4 f -.

0 0f 00 So 10 0 0S

Page 200: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

-, A-: -AY ;QP IC LO0G NON~J o

rsta~iticr sk Harbor CoordinAtes: Ste 7Dro ect o'bzg ýji. bd&erlt,_c At W

4ZP~ Ccrtractcr I " Ccrtractor- kyCDr I e X

~rc St.-tec n.-L i ~ A- m' Drl c Eflcec 1 -444 a 1 P_ Lrr) FBCrer~c e C!a(S 7y 3&:Dr~c: retrco/!PicType: 4 _.-Cf~w

:c~c:~~ Fcm--to- Prtec-,=r'Leveb. A..,7:-

Litf~loaic Desc,-:Lion 0 0 . pso - _ _ _ _ _ _

0 5.~~ t3F.OJIL toA "0.-,

/0

to ~~Lt ~~ ~~

/J.

3.OW ( -- <-s~#t

- - Y~e~ A- -4

M;.o wotiiS

CSe A. 0 0 0 04 A,

Page 201: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

F /~yZ~e. S-~- 3E ýA-E -AV cýFmO BORING;YvE-L NO 5112 4Y

aZ: Sky Hfarbor Coordinates: 5:,c iec: 4c Wcjo4i CAW4 en/r VZ y

-4w~~ rtrctr-~Dr c Ccrtr-a'r-t,; x.~ r esr t3,,ec :ýh t ( & J rc cec q30A 'n) Bcretc!e c as; 0i

j r m. to..... ~rt: Leve, ZZ A

- C,; ezc.t Lithoo~ccc Desr:-;:t on '0 Aj- So

0 tk J5 r> ,j 15.0. ý. i V/ý 4 -ý R

Ao' Sr l KI,-&4 'S

5• 0A~ COdt)~j 1~% t.,(0,K'o ~ ."oJ 5&9 AAVoAb

II S /)

0 ~ ~~ ~~ IV SSS

Page 202: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

F PEv DA'_- "1AY ~1

-4c2rtractCr C Drý: Cczrtraztcr- L er e

I -c~cec::v E cc - N i rm ____to........... ~rt~ Leve, t)(A

L tr'oiccl Desc- :Zor wr~~ C

c , /. A "c4 . 4T 053AX VA'

jS~Uttvd~O ~1

/L) Iii10

i#44A',r ~J/ &mVg z,

-4P

0 A) -So KI~k

:Er:e) C-Cre-,, s ___ k AA

Page 203: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Sk Harbor Coordinates: St

ý A"4

D7.~~~~~~ c~ /%r( 0 0

~~O g e: -'ccc 1E : or-1SS~ L'

0 5AjD k"- i

t*W1, 1 4 I-

4S'~ 1 UOP "V

c..S ___________________

0S0 0 0 $ K&Oi 16 So

Page 204: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~P- :)3~.~ ATE MAY 10 :

E3PN LOG BOPI IO`ING'WL~ NO _W -1T ace --I- or2,r~tallali~rr Sky Harbor Coordinates: Si75te3

~r-~e: ~ _I'* Cflent/Or-jcl A*ý44- .41ADP CCntractcr- I '_) I ^ C r'trac tor- L~, i .- Dr~ er- x~DYb st~rtec 3JJ1(6T rn :)Qz EnrCeC 3/-,R r3 mr> l Borer~Ce 0l1) If .4

t r-q Mer~.c/RgType ~ ~From - o PrCteCtcon Level b.Ai

0'60

\1jC

Aki- a--A tr 7.-24:-

25'4 f 5

0 00 200 0 0J 0 *-r

Page 205: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

A

F~c-,/-g ..- 3oP tV :)ATE "AY l9l';O P ýG LOG' COPING/ViELL NO c c e..i..cr3I rs'aliaticfl S! Harbor Coordinates: Site-Drclect No,: 40N'o Iv Client/Droj*lectRJ A3HAZW,,P-.D Ccntr2Ct~r- 17 Gptý~~ Contractor-'mr Dri I er~ xDrIc StarteO. 312zj IL_ Drc. ýraeo: 3LN m) Boer'eF ~ I c

Dr~c rietPOO/pic Types -ivxM r B5&..OE -

clccec tv C-.,c E-Lcc F rom - to ~ r-teCuon Level i4~p*

-L;tho&ccC De-otir~ 'c 40 GI

3 S ^-. to -'-tt4 A" w, '~.W -um. *i'i - -

7 ~~ SAQ( 3g...w(7. -'rfk5# rvf4/:) 1 , e

(I.4 Id'eN $L) /7i0J(rsvL '7/7) f 5-4-T ,/ SI Sr

tt4 P-0 LOWIt gco r- S %--s- pws6.

S..4'.& 7. .~~4-". Ca- AX,

7 A.A42. Ye LjJ% l, ? `V, q~,&j

q~~o fv. 1, ; K31-1~ f~-

0 \0 CSA4C 0 000

Page 206: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~/ ~ 3-'3 ~ - EV DATE ".AY '9g0

I rsta. !at cr, Sk Harbor Coordinates: Site j

Dr-o ect Noc.. J, C!* Vent/Drc iec':.)traZtor-.CIc.Prtractcr I Dr-c Ccr'tr-actor--A Dr-iI ler-

Drnc St2":ec. ~ (& 3o A- m D r-c: Er-cec 3*41 i To Prrd ~cr-eroe cfa(s)- 0Dr-Ic Metrioc/Ric Type: D&a-L43.cccec ýýv 61ý.ý E-.CC N)~-m__ to Pr-otection LevelIC0

c ON

Ltrolocic Desc''-:t on IL,~~

.. ~AJ?~#

85 .0

t3AP1- t?.r %Vo-N/ r.u)IK , 6-w,&iu.

IAM4 w~- / &IOI I ,f-

0 0 0!ýe 0 0 cte

Page 207: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

S - .3, a Sky Harbor C:o:rdinatese:Drciec' j2 44*9W f -'~ iert/orc ect O:K7 4ý SI -

:' r"rcLr MC 'rgi.ei I '-: Ccrtr-2:t'Jr-- WA~ ~ 'r6e'A~.m.

31c (02~e 2f ,n I D~r Er~e C-? m 0I Dri DA, I

~~ E-Lcc ; rcm to ýýCteCt-r ev

~~~ ~Litrolcac Des-7-:t on .- -

rb %Fiý &., A~j.)7 T (kA A00, Sd

0 S. 4-"I)RA~Pd~ 4 (O-I 406 r 6,'.I.EI

0~~ 32

5o

-30 9- 0

Page 208: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

r5a.3 3':cr SUy Harbor Coordinates: l e3

Dr:~ ~ Cc~te ' z. - D r: t.' : c 23 'Y '. rv L: Om ~ Bc re 6;",, 3A

Dr: -ecc/P~c Type: (DUA-4.Eh3

cczeE¶..cc Frcm. .... to......... rtz~.~ e

35o 0~ ~A. 94t Fit-u. C ~ A.,' 3'4

PA.&,>- ra qP" Aou 0. '-Aa. MAO

w too/,

JUi~ 9 eSCMA*.'l 4 4 Uw'>v S.'w^.wc!t..'Yf r/f ). /01 r-

I 0 tjo Pi~covr.A-y A-(4A J90U-

I ~(3Jylk5t") p.,

e ~~0 A 00 0 f-

Page 209: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~o:& .3eOPfNG,-3 ELL N /~ ~-3B 'sa, 3: -sk S arbor Coordinates: SreDrccect lic. '4cma),, I !ier't/Orc~er-:. A-34A Ae3

- ~4ZV~P.~.ZCortr~aCtCr. IT, Dr'CC'rczr -C e .y 'A3

rcStte , (g,2 V ) Dr'c -E"ceC _TI1k q 30 mr) -RorLro'1e 1071".

O.ccec ýlv 60OV.P.... E-L-cc '() Frcm to- ne:cr' Leve 0-

0 b piu V0% ijt.%). W, 6, t

j.V7~~~ is.-. rcL -

1- 44,w#s Ow.

&,Ao42, Afw 4L - -

10

* '/6x

Page 210: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I~I6L/re.....7- - EV DATE. MAY I9 ccBORING LOG TBO07lNG/WELL~& NO.:ge.L...3 Intallti~nSk Harbor Coordinates:Sie-Dc rect wo.. Cflent Prolec Sae

HAZWPAP Contractor. - "A JDla Ccntract~r rw3~Nwww Driller4 ~~Dnia 5tarteO: 31.V44 . i ( * m) IDna Enclem m)BrhlXia,:i~~

Drig rietrnoo/Riq Type: 23-111 I.M a M -oeo..3j):isf4

Loc ec by. E-Log Y 1W/ From - to Protectlon Level- 1

o t 0s % Llthologic Des-criotioni o60% e ' 4

0-.-.-- -m~ -ou (-0.

L,/,) ~ 64ALL. /

0No P-"""C r Sc

0 A)'o X~CCZ"tT- ytV..C&W' AK AJ r~IS*~

Lr DA.. (7 rylt foc"awA S4t

2o~~ /Jo s IlziM-4n

30-~~ o .

IU 7* r, waIl TLt? R RoCk Ccrir.g __________Fie~c G/'C(Make/Moa3. ___________

4 S - Sc oora~ti.e) 0 W ter _____________ G/C acer.:________________

c :.: - ~ te ____________ ______________________________

Page 211: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

*~~~ RE-',~. V,3 DEVATE MAY I Or6oP 1 G L0 C7 ORING/WELL NO: *f503-01 Pace -A..ofiinstallaticri: Sky Darbor Coordinates: Tsite:

orciect Nio.: I~~. Client/Project: pAj " s v& IHAZWP.AP Contractor (Ta,& r IDrIaontr-actor- WWCG rilI I erD rbc Startec. 3 ve (5 (, iii~.L~m Drica Enaeo: _3ft., qf (1:00_ m) Boreriole Cia(s):~

Drlb Methoo/Rio Type:Loccec by E-Loo a /(N From -to - Protection Level

'it

£~~~~~0 C4~~.C ~~I

* ~v 3S-Lthologic Descriotion-0PJO .cA*ie-C.r4n%&~ 94 f---

4, 1-oAf:O vvAvJ % ^ . i.w

4TV S *A1 A41ý Coco,&,, 101) -V

4 \0v 0

~~~~~ p ' C~

~ ~gT x-y' 4- .69 ,e," 1 091T -

*~~O~ 6o4pia*4 it~ -~~

S 4 4LSA Isr J(-c

4 ~s ide4JM )~L40ST Vs

0 Lj~ 2

0 ic *rOA - ,

304 9i4taqýE M" 5k

70 IV r WallI TLt! P - Rock Ccring :1:jFt cGC c G/Vae/Mlocij So~tv..s* sc~~~~ocr,(Lte) 0 - Other _____________GiC Ooer..________________

Notes -

2 2- sx C^-sx Pt~c

Page 212: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~ ~ S-3 P- EV. DATE M1AY 19;

BORI NG LOG BORING/WELLNO, -S13- 03 =- ace -LorInstallaticn. sU Harbor Coordinates: Si-Mt e: 3Protect No.: L40N COL-l~l~ent/Oro ect:

$AWA otrator,5 (ri CotrcormLW Drf Her~

DrIc 5tre:3jAiQ'jA~ Drla Enaeg 3[4Lt4 3.p- mil Sorerhole (;a(S)- (O

-Drtg ietmod/Riq Type: TtL,3 PLLod ec by- E-Loo V From to Protection Level-b

10t Lithologic DesmoriponGI

10 z

0/ &CN -4 ,h S2ptl, ýJ o aw

Ole~ - N' s& e ArIZ, 7!

S

0 A)* so~~-

30- 0 tO

U - Tr, wa I Thtt R - Rock Ccrirg Fie~c G/C(Make/MOa. ____________

S -c scocnrti..e) 0 - Other __ ___________ G/C DOer.:_________________

Page 213: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

* ~~-~~F S-3d- PEV DATE MAY 19C

BORIN1 LO0G BORING/WELL NO.: S133- 03 Dage 2- orinstallation: sU Harbor Caordinnteu: -Site:iDroiect No.: "41'-lz I Client/Drolect: R tLX sL

HAZWPAP Contractor.A- am~"ý I~ Dria Contractor- 6. Lw g*&tt DrilIler- x

L n tre.324 (U (1 m)Dn Ended: Sls t f Ao m)j Boreriole dia(s): tO f

Drig method/Rig Type: 1ý T~az

Lociec tv &*4N tA E-Loo ( Y /(ý From -to Protectbon Level-~

to c L Litholoclic Descriotion - *ecqc"A

P4-0 tt V , u, 5v

oA O lcy-v'&L ;h ). FAlo".

So 0

o aw No AS'e 4-ATL - ri- X1,C"

0 1 f3 fco

0 A) o ii`) L , Crv & 41flS"1

4 65 0j So 00

Page 214: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

41 ~REV. DATE. MAY 19Cý

BORPING LOG BORING/WELLNO. C3C41PaeIo J-inStaliaticfl; Sky Harbor Coordinates: I Site. 3Droiect No.. Cllent/ProleCt: Hpt&JW f S&HAZWPAP Contra2ctor- (r4%f4*.& * DrfaCcrtractor- AVW.rVkj I rilfer D- . ~dIDr~o '*?rteC. Siatjij 4(1.2 r .. m) I Drn EnCea: 31zslqi (j,.0-0 A.m)lBorerhole dia(sY toloj',DrIg rler~hodl/Rig Type: j)-AA¶. Tisa.Loage ev 6dt ,h%% E-Log v /(N_)) From -......to_ Protecti)on LeveI

Lithologic Descriotion \ ' ,&"

itl., Ati 4

50ktw,.- -/ ~ .a~wg

6t*444a- Frw\A&d A-J aP. gtld,-1 AOu4-r

0 ae. (%, 4.~c-yj c

030SAw.O m (? r/~.f)~s

rv~4 5 ' _V3 OF"&,S4,~d~

fdWP. roS S .A4AG.J; -i A -

0 w li 3A, T

4 &t,-4 ,

lu *TnwallI TLtel R - Rock Ccring _ _________Fitk: G/C(Make/Moa ____________

~cc~t~) 0 - Ott~er __ ___________ G/C Ope. _________________

Page 215: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

v S- P EV DATE MAY 10SOP ING LOG 5TORING/WELLNO: S0-OIinstallation Sky Harbor Coordinates: Site. 3Project NO: w4:cI~ C I erit/Dro lect. H~cW4r. 4!E OzacAYHAZWPAO Contractor T ~ O DrIp Ccntractorf- Orni er x

4 Orb SLartea. Jl¶10- _(Z OOF m) IDrna Enged: k3icm) IBorehole cia(s) I C) 7/"Drig metmho/RiO Type: 7,,4 FL~.Laogec by c$*iu.. E-Log Y AM b From ...... to.......... Pr-otection Level I)

W,-4 TV~5 "wb-w ("ý /-z1hy;

,0- &Io -"CeAI I- S

P~~~4.ok .70%,-~ IAA'4s L-d~" -c"~ '

-~ LJ/ ~4.A. MO~ eC1" ' /

P'*ýkit (!.yiA4

' e

g~A, ~--r ii .ra A~.

4 KaI w-, 44. m

0 0 0 to *0& C 0 0oai

Page 216: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

- 0PIN3, No' At ___ei-

=2- Sky Harbor Coordinates: S le

C ' - '': :"CeC 2ha mt_ _trn c-er'c C2S 74

Dr~ ~t~~/PiCTvoe:I c'::IN] ýrcmrr 1t0 7r77ect:C1,Leve, Z).S4

IrI

A~~ .\ It

0 o c- 1

I L14) . c 59 v

7 0SY 41 :2-c.,yr-

W W I , I* c" v A % A & & L " -6 c

S S 0 S 05 0 0 I

Page 217: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

a:2 ' Sky Harbor Coordinates: IS:

Ic 7r:~z/vo e. At. 14-%&6.

01 No A~ 6---. 4,

A0 ý'-v K --vsr Fz#So %-* yA e

C,- $vi

ft - vs mS I-() P....f~a~~./£.~AS

- 5AW.O L -3A". Is~ f. ~f-If S/1, , 1.)-L

5--A sr]W /P &AF .to 4'.~~4j*)

__ __ __ __ _ __ __ __ _ __ __CAW$_ _

- -- _ _ __ _ _ _ _ __0_ _ _

1 6

0~ k A. 0AA000

Page 218: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

IC'Sky Harbor Coordinates: I $ e 5-

-AW: r-tr-clcr- I ~Dr~c Cct-:cr LA~ug "M .. , Or- e'- x

-Ne_ý E-L-cc Fr-cm - to - r-ctec-Tcr- Leve

0"

\~~S -' ~~ LittTolcoic Dec-:-- -*,-on ~ ' c' ~ ~ ~

IT~ IA'AýI, r.49 JSAw

£eWA44~~~P~~dA &4A*P.M J..S 1,£

f~ 0'o'.& Av V4AAf Mfo'tz*4.J,,-

roo

Z PCc AAJ

CA :Cee PA. A.HN A

Page 219: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

PEV DATE MAY '9'94[BOPING LOG BORING/WELL~ NO. Dag e....L..of -Installation: " %=3 p Site.fV pDr-o ect NO.:J ' .024.ja Client/Prolect:t:4byk % IHAZWRAP Contractor. Q&d Dr1i COntrictOr~ I DrilIler

*Driq Started: t4'vt ( - m) IOnf Enaea: 1) m Borerio Ie (Ita(s).*Drfa Methcd/fgl Type: RL.6t A"

L-ogecv by %A-# E-Log ( Y /ON )From Lo -~ Protection Level~

Litolgi Descrptio /t t ~ Y

ft i

&i4

P- Can 4- ALL4N TA rl15A 6o.~ l. =~g$g

6 0 -- P o -^ s - 9 " - f V A~

V f 0 (#~C4z .

/,S,.b4 -?_ _

U hi al TAe *RckCaig iedG/(MkSAaJ '

S'5pltsoorcti~e) u~tw (A.A &GCer:___________C C ttn s o es _ __ _ __ _ __ _ _ __ _ __ _ __ _ _ __ _ __ _ __ _ _ __ _ __ _ __ _ _

0~~~O 5 A

Page 220: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3reO JIN LOG BORING/V<LL N - Dc -ELýI Eaa:nsky Harbor Coordinates: I Site. ree 5s,sec7-)

644ZVoP-: ý.crtractcr it.Ap,.l I~I I I Drer- CP.ODre St~r~ec ftp (& niAmLrn Dr-c t--cec If.' ils f m) Bcrero Ie c;a(S *1

Dr-ic metrica/Rig Type: At Aenww1¶I~~~al

ccc~z a.... -L.CC Frcm..to....... Pr-otection Level Ttz4

Ic

T\\ 6 Net

0 ~ cr.:e LCtr'ertc _______io NC Zqer t tAoI

0 0 0 0 0A,4,0,

Page 221: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

77ZP , LOG BOPING/w-ELL N P - c 2-. :acir'5,a,;2icr Sk Harbor Coordinates: Site f"^-

:)l s2tcdift e &am) IDr! c Ercec dri, Tc )IRrenc iec -a(s) LS

.c cec C:v 4.0-ft E-ý.ccI Frcm tc - rotecticr) Leve!

0 ~ ~ ~ ~ #I tM.-I Lirlo c De-zrý:Un

55A4 Sa,4JA4g _ *ICA--% (,u a

20 w/&i$ W%,;6 -6L*gA4 ý t~ 0

Amdr 4'fJ PI

S A,

*,, X46

-- -:e)erNP ' :,:er IAA

Page 222: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

REV. DATE. MAY 19904BOPNG OGBORING/WELL NO.: ?e-3 Pa 11o

Dr I SlLartec. fi q; ( jz g J m) IDrli Eridefa: I - Si-o ja.m) Borehol e wia(s): 4-0

Drig Ilethoo/Rig Type: Pj / R..LooceC bv E-Lo ( Y _N From ___to Drotection Level:-

Off, Litriologic Description

4,p ,v- APO -POL'

/0ý 4 "W f~q. SIX r Oe A 5P.(f wt- CýUýO

Lv*1 rrve 43(/4)1 IN -W 6s

(A)

4 00

50

Rio~ $i...4 Ar

U*Thin Wail Tube R - Rock Coring,_, Fiela G/C(Make/Mod.)__________5SSP I It SPOON(Ltube) 0O-Other~ K 0 /C Oper.: .C - Cuttings Notes. NN.

4. 0

Page 223: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

Fl ~ ~ a P-/z. * EV DATE ".AY Q1

BORING LOG BORfNG/"WELL NO.- P- 03 Dage~oInstallatlcn Sk Elarbor Coordinates- LSite.Droiect NO.; t,- -Client/Pro lect: /SV4HAZWPAP Contractor. x-r C.,, IDra Contractor- E Drilien-

IDrna Startec: rn) I m DrIc Ended: kg .... m) IBoreno Ie a ia(s)DrIg letnooa/Pig Type: S~ee- .. _________

* ~~Looced ýlv E-Loo From _- to - Proteto- ee ~

O' L Litnoloaic Descr:,,tion ~ ~ ~ ~ c

470.-- -r . LL '-f- Of saJ. A6 'y- 417 ro-. ýQ

ELAE

4

4 0

No& 000

Page 224: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

ntrolor ;) I~r C or C) ri

* ~~E-Looi Y //u From .......... to D

tt LltholoroIC DocrrM-)m \3, ~ ~~

Lo 52 -1.AWuiA,-. -00-& (ZVH /1

Itto

u7-- aI I H~ okCrn i ~ 4A

0 -A~1' Ot~e 4: A %Jd)1CajhR ggaNA

Page 225: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~~~..... IIIr~ r cr ..........~ 4 i r

9 ro 'rtoc 2./li 0fl e..Am) 1 D') r v* F /~i r) -. F3ri 0t-Lo~lzo -ý (l 11(', / 14m 0-)"CIfle

4 - LJ~Ateoi ) cdo..

Il : ýf ^ 41 1 %" L Q

I KI

2-S

6 I

"1 , alTL'tO-oýCcig m kO..-I I. / Oe.

Page 226: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

It

I

4

APPENDIX F

PIEZOMETER AND MONITORING WELLCOMPLETION DIAGRAMS

m=6

I

* I

:I*

"I00000000

Page 227: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

PtEZQMETER INSTALLATION SKETCH

PROJECT NAME &us",ajaLAwt INSTAL-ED BYGA*L1I-JXL

PROj ECT NO 4c)117-1 02.0 CHE:KEZB MA. CA'E .& k

BORING NO ____________

PIEZOMETER NO 5K I (P-

9C %PIP 'N A*-- ONCRM'E#1p

4CAP

Px,: P!CE

* 2. GROUT

I Vt l3~.~~.&> ~:&.i~.~.r 1 ORING

iS0 U*~~~IG T 4/0''w ~ -.. i

SI..~41'3

4 -. " l~j-

I Z .5 -A v

4 r<--.- (w;~O OF eR'N

AATT Sj.

0.d~

L(C (.

0 0 0 5 0 0 0

Page 228: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

'1

I i

PIEZOMETER INSTALLATION SKETCH

PREjCT NAME 5H. As,.)(- INSTALLED 8yA->A D-TE SLLAPROjEC7 NO 140fo7 1. AJLd-, 1 CHECKED BY • DATE

BOPING NO SI,. '-7

P!EZOMETER N• & . (Ps-z

GROUT-.p

- :.,-.5",,.,S3 ,,

-- sz- E... baA

I 2~:NCRE'E jvc~

A, %Ws. U.

\t

A-

GROUT

"O"ONNG

3o4 / 10

aft&, 3A'CE-~w , I

* 14'f ~ ~t

4 304O OF& BORING

Page 229: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3 '-a-PIEZOMETER INSTALLATION SKETCHE

4 ~~~~Cj;ýEY^- NAME 50,,r UH4e~b'a- 1A.-j( INSTAL.EZ By,&. LLI4/f/taPRO~JEC7 NO 40741L OZLO CHiECKED BY J . :)T: __

BORING NO 3-PIE ZOMETER NC O

:3NCRETE; .

033 34rf'C&-4 Xi'3j s.cE

4 5

4 V,

N3.

so2' ~35'~R30

4 3o

50TTDM OF BORIN1 ?~uAll-~ I 's-' /A

khu... iop L4 ~ 5r~~ C6~-.~* /lj L C

'.~~ a~3~lb.± ,~4 "'-(

Page 230: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

F

REV. DATE: MAY 1990

IMONITORING WELL CONSTRUCTION LOG - Standard Flush mount

WELL NO.: .h,,% - 2 I installatlort 5L H,6 . I Site: ,

Pro oect No.: iUjjt Client/ProlecL: k j*:q' /5 ,r L 06- ,r3I* HAZWIAP Contractor. IT' &;.,, " DrIg Contractor. L,

IBultBv: W ICorn I .e COOran:, t 6t

Elev.. II 16.:•:)

Giglht E PROTECTIVE CSGGSElev. Material / Typeý -ý - d5gyw , - .,•I .GS HeIght 000' Diameter- "Depth 83P Depth BGS

$ ,- Watertight O-Ring (Y / N)

Elev1..'10 SURFACE PAD /Depth BGS. 02 ComposItIon&SIze C,,tj(Acý.q IJArlo'tA~ ,.

Breathes With Vadose Zone ( Y

RISER PI:PEType %•..•',,. •t•0 Diameter,

2.0 Total Length (TOC to TOS)2. VentllatedCap (Y

'40 GROUTComposition & Proportions -1 t3gv 1w. 7 ufl

Tremled (Y /(tp

LAI. •Interval 868CENT--C RALIZERS ( y cv

, Depth(s)

SEAL

bFI & Type _' a.j. L½I;At.lr i.T

.0 ~Sotrce 9f -b Setuv/Hylratlon time' Jd. Vol.FluidAddeJ -4,.S'' • , k-;,., ,_ Tremled (y Y j 2.0

" -'=FILTER PACKType_______________________ A6

-� Amt. Used d'0 , ,.- ~~Treniled (YtlI

Source,

Gr. Size Dist. 2,ri n&,,2.,,. bg-j

SCREENType -i It)j

S1 •'_' O~~~Dameter •.,.-,oSlot Size & Type r' 01o

__"___Interval BGS

interval 856 Length=- I •,,Bottom Cap 6) N

______ I BAM1ILL PLUG

Material __ _ __ _ __ _ __ _ __ _

Borehole dia. SSewtuo aratinJme A jA•yenole Ola.Tremled

S=• I ll I I I/ I I II I I I I I

Page 231: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

w-

4

3 REV. DATE: MAY 1990MONITORING WELL CONSTRUCTION LOG - Stanaard Flush Mount IWELL NO.: PKLS- 02. 1 installation SmLvkkae I Site-

Pro ect No.: 1OW6.1-'. Client/Prolect: A•4•- ,. A .,

A HAZWRAP Contractor. a I DrIg Contractor. I,•,,,•LA ,,fjLa-

Comp. Starti 7&/61.1 .. .c .A m) Comp. Eno. Z/ if I 10 O )

Elev t . '• WS,

Height n PROTECTIVE CSGMaterial / Type- 5a. W1 S ,,--rlwm, ;;T,,,

GS He It DiameterDepth 665 Depth BGS

Watertight 0-Ring &,Elev. , SURFACE PADDepthBGS . C• Compositionf&Size 3, •3 A.. .4 gn,

Breathes WIth Vaoose Zone (Y / N)RISER PIPE

355 / Type SCAL. L40 PVC35l Diameter. 4l j-,. 1-r,

Total Length (TOC to TOS),1G•Du' Ventllated Cap ( Y/•J)

GROUTComposition & Proportions ""1' xTremiea ( Y r • IS• A-W , 1 8SAfl.•,

Interval 65ICENTRALIZERS ( YKtI

Depth(s).AJA

SEALType t4" iia. ~ ~ ~ I3iSource _____________________

4S. S Set./Hydrat Ion time. ZQ-- vol. FluioAddedA,.QTeC •A A ~Tremnied ( Y A:

- FILTER PACK= ~Type t-e: +60 C0*...'aueAmt. Used IS s if : s 60

Tremlea ( Y

Source_________________G Gr. Size Dist. ZW,&g .i..dMx, he•1 t1Y rw

SCREEN-- _ Type- cn, . 46 e•

i~o 1 . . .Diameter 4-,' "

t'o rntervalBGS ,iIb-,-o& _ ___,'

SUMP N)In-terval BAY. Length.Z..Bottom CaP /79 N

BACKFILL RLUG? Material P CA

Borehole dla. 5etup/l rtiol timen__ _ _TremleO

0 0 0 ! ! ! ! !

Page 232: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

ElJ16REV. DATE: MAY 1990

MONITORING WELL CONSTRUCTION LOG - Standard F lush Mount IWELL NO.. Ali A-31Instal latiort #4I._ Site:Project No.. Client/Pro ect:H w9eHAZ WRAP Contractor' -T%,*Qg~_ Oni Contractor. -

Comp.Start: 3 ( .±-'Lo Comp.Eno: i~i i ~ kc _r)*BulIt By: Wei Coord.: 14 Wz t

4 Heignt.POETIECCGS Elev. ~Material / Type -uA7.

GSHeIght 001A1 DiameterDepth 805 Depth BGS

Watertight 0-Ring 6)1 N)

Elev. SURFACE PAD4Depth BGS 0 -I Comp~osition & Size )f 34-xI4 Cmjwi.&vz

Breathes With Vadose Zone (Y /N)

RISER PIPEType_.~ m" 190 FiJleDiamleter ~ *

4 Total Length (TOCto 1p~)35' Verntilated Cap (Yc

ý5 . 1-1GROUrT30 13 i'm T- k 0. CorriposItion & Portions '4ihu Tw.XlAfiaE

Lo Tremied (Yep)10 interval BGS,

?CfCENTRAL IZERS ( Y (Depth(s)_

SEAL43Type- Yyv ' 3 i.. y- Cm A

H -4U F.ýc S~~ etwP/hYvation tie22fsiVl Fluid Added_%.ftLI H'i-

FILTER PACKType 2oo~ S. - b 60 Sol PC.--%Amt. Usea 2.Tremied (Y (3iý

Gr. Size Dist. 2"ok h

SCREENType VA pqý4

Slot Size & Type 0.010

interval BSG AJ Length ABottom Cap 0 YN

TD: BACKFILL PLUMaterial pi

Boreole ia.Setup/1Hyantlof time AJ k8ore~edaTremied (YIN)

Page 233: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

i REV. DATE: MAY 1990

uMONITORING WELL CONSTRUCTION LOG -- Standard Flush MOunt M

WELL NO.: Muir.- a4I Installatiori &k,,, Site: BAum .5... t.Pro lect No.: %l,",.,, Client/Project: Wm &a A •HAZWRAP Contractor IT Ci " CgContractor:

Comr. Start: 3 '• , ( (1 r jrn) Comr. End: Tful1tt 4 TOD""u i t BY: CAcWeI I, Coorc.:Elev.•

Heighte PROTECTIVE CSC,

GS Elev.t _Material /Type -s;Tg& 7beGS Height 000 , Diameter ";

Depth BOS D mBS i Ai

Watertight O-Ring O N)

Elev._V SURFACE PADDepth BGSLJ I - ConvosUiuon&S•AzeCA

""reathes With Vadose Zone ( Y /N)

RISER PIPE20 Tx 0 Type Sc..we' .4. •

/ P' Diameter ,.- ;K s; 60 Total Length (TOC to TOS)

a11'• VentilateoCap (Y4D)

~Ii~ GROUTCoirosit on & Lip~ons 5%y Us~.jw..wc-,m1Ty I

// ~~~Trernie0 o Y_/ Interval BGS O-2~e.

CENTRALIZERS ( y/ 0Depth~s),

SEAL

39 - - Setup/HyatIon rn..-O.Vol. Fluid AadeaTrernied ( Y t:0

_-T FILTER PACKType 74'vo C-"e ' *-S.m 6o 6&Amt. Used_______________

""TremleO ( Y/WJ- ~~~Source-_______________

Gr. Size Dist. / 60 aO- 1w

SCREENType -afte!4~ 44 "vc-

Diameter 'fi.a.Slot Size & Type e.oio,Interval 5435 73-73

•I SUMP /N )Interval a•. )o . LengthBottom Cap (/N N)

BACKFILL PLUGMaterial Af A

Borehl'le dIa. Setup/ftatlon time A,.Tremled rIT7WI

00Ii .°

Page 234: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3 REV. DATE: MAY 1990

MONITORING WELL CONSTRUCTION LOG - Standard Flush 'Mount

WELL NO.: At j-z.- Installation . - . Site: ±

Pro ect No.: I' Cl ient/Pro lect: Rkw-• /f.*HAZWRAP Contractor. iT "& nr- "Onlg Contractor ( -,oj ,

I ultB;••_•.=• e'CoS •''zzcorm. start: IIh.ikl 2. f - -4- ,,*M) I COMO. Eno: I /zekQI a •'°° "•M)

Elev. Sl

, k C(6,6 3

H-Eeig h PROTECTI VE CS0 SGSElev. tu•,.• • flMaterl., / Type £•tL. Toe S ,t.a- •r - Spc,,GS HeIgt o0'. DiameterDepth BG. Depth BOS

Watertight O-Ring ('/ N)

Elev. ' , SURFACE PADDepth 565 Compostion&Size C,,.w crr./ 4. x

Breathes With Vadose Zone ( Y/N)

RISER PIPEType -. -j 9vCDiameter L.-

Total Length (TOC to TOS) 4, A-Ventilated Cap ( Y 4()) 5

GROUTComposition & Proportions Apiea L4 o4" TyroL TsD

Tremled (Y/(E)

Interval B65

CENTRALIZE.R (y Y 5

Depths)

SEAL4.SType VY L. &.' O.i~.J.g

3S Source_ ___S1 -o'Setup/Hydration ttie-jl avol Fluid AaOdd%*aL

Tremled (Y/ 4D-. FILTER PACK

Type .. • QC S#-a Op ,_. *,,,

Amt. Used _" 7/ n 2.. 1o -f VDm 46

--- Tremied (Y i(YpSource_____________Gr. Size Dist. F.01,in .IS P,. i &a CA-

Type ,, •cc.3. eo PUcDiameter . % . y.•

.. "" Slot Size & Type .0,_4 .01 -Interval BGS5 n-

SUrIP ( Y / N )

Interval BS6 Length

TBottom Cap E/ N

TD, 101BACITILL PLUG-V Material_ _ _ _ _

Boreole 01a. 5etUre/tre atlon time A)ATremled ( Y / N

• • .. . .

I4|=I l l IIl1l l 0l ll0l l0 l l l0l *

Page 235: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

REV. DATE: MAY 1990

MONITORING WELL CONSTRUCTION LOG -- 5tanaard Flush MountWE•LL NO.: At•Z.-a2-l Instalain:u Sk,, ý . I Site: 2-Pro ect tio.: klft!. I ClIent/Prolect: -7 / - &,, -A!,3L

A HA2WRAP Contractor .-. , Dri Contractor ,-SComo. Start: t/6,1W 1( YV: D m) I Comp. End: -'•/ 61!1;• '•m

--Built BY: ,Well Coord.: ,

Elev. h~l* SOhelt 0• PROTECTIVE CSG

O5 Elev...A ° •, Material / Type ',W4. "r',W.M.,w..- L.U,,

GSHeight DiameterDepth BGS Depth 85.

Watertight O-Ring ( *_.-

Elev. "'• W SURFACE PADDepth BGS 0-.3, Composition &Size xk2A A C .,,,

Breathes With Vadose Zone IYIN

G /.RISERPIPE.... Type s941 NPVc..

Diameter 4.'Mb.I Total Length (TOC to T.S) 1bo

Ventilated Cap ( Y CV)

GROUTComposition & Proportions '1 I-*Wb.•"fl'.l _-

Tremled (YInterval BGS

Dept•(s)

SEALType ~''J~I~~

2.• SourceL4~~~~~ 4f eu/dainVl Fluid AcjldeCLLkký6

-; Tremled (YFILTER PACKType 2•t•oC,.•Co,, S, .-A go" 12O0*,Amt. Used , E SA

- Tremied (Y= ~~~~Source_________________

Or.SizeDist. •6 k3/F,& *LO PAOow

SCREENType &C4 1110 ?y c..Diameter T4e" .#>.Slot Size & Type Q.,0so.L,. , Y.•,

Interval 805

Bottom Cap 6 N)•[•" L •BACWILL •UO

"Material PA_ _ _

eI '-"-"oie 01set5.on time_ A

00000 00

Page 236: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

3 REV. DATE: MAY 1990

MONITORING W? L CONSTRUCTION LOG -- StanOard Flush Mount

WELL NO.: eM,3-01 Istiort C&1aQMeIProjlect No.ý • . Clent/P'olect: H • S- Y,• A•SHAZWRA, Contractor rTC., , I urig C-ntr'a:t... L,-- A.", -,.,,.Coil .y: cpStart: o.,,.3•• ,2 :' f -•m) I Cornp, Eno: -e' C°'3 /mL/1 (IS" :e% A M•l

Elev._____

Height . PROTECTIVE CSG

GS Elev.__ Material / Type . i - A

GSHeight 000' Diameter I 'Depth BG5 Depth 585 12

Watertight O-Rring (' N)

Elev. SURFACE PAD

Depth BGS " G Composition & Size A5--c,.J , i e'.,rBreathes With Vadose Zone (Y / N)

( 3x , / RISER PIPE

i/3 s x Dianeter - 4 = C)Total Length (TOCJ.t TOS) $• t.

I , - Ventilated CaD 6 N )SKC'- GROUTsiir

Cooosl on&Proportions £% -

Tremlea (Y/'U)Interval BS f)- 4 1 '/k ,

CNTRALIZERS (Y A5)Depth(s)

SEALType Y" &it-M

3. ~~~~Source. (~"E*~~- -Setup/Hyrtlon tme-2Z4%mLVol. FluidJ AAdd dLC.%4

5, -- So FILTER PACKType U01a& =j

- Amt. Use0d -x

- ~Tremied (Y (N)Source - -Gr. Size DisL. r•~/•o 0 60 oQ -po,-

Type .. t2V&.gDianeter v. ,•d-, X. 0Slot Size & Type d.010

_______Interv~al 605- -0- 41OSsur'LP N)

inteal 4 N 10 -O( LengthBottom Cap (9N)

FTD.BACKFILL PLUG40- 14-- rMaterial AJ A

Setup/tWition fme AIBorehole d. Tremled -",0)

0 l I I I I I

Page 237: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

rS

REV. DATE: MAY 1990

MONITORING WELL CONSTRUCTION LOG -- Standard Flush Mount 4,WELL NO.: tK .o Ilnstallation C , Y .,y w 1,Aj6' Site:

4 Pro lect NO.: all I Client/Prolect: biA44)R?'• A"HAZWRAP Contractor I" C" hAfsrO Dria Contractor , ,Comp. Start: 3ý/zz•, ( r it m) Como. End: 312-l /11 )o

-- Bul It By: We,•• I Iwe orc .;a'

Elev.

Heigh PROTECTIVE CSGGS Elev.- Material / Type (ulL I/or-.- ,

GS-Height Diameter. 1 ."Depth B6S Depth BGS - 1y,

Watertight O-Ring () N)

Elev._[___ SURFACE PADDepth BGB0S/" 'V Composition & Size ?( Yx I S

q O Breathes With Vadose Zone ( Y / N)

RISER PIPE2- OW-0 PM/ Type S- %o( C/Diameter ýt Lg,.,= T.. ,

%AS Total Length (TOC) TOS)jbx ) /Ventilated Cap N)

/ GROUT

Co~qvoltion & Proportions VaAný &;-// ~~Tremted (Yd•

Interval BGS - 4pYL*•,

CENTRALIZERS (YDepth(s)

SEA.

'tO ~~~~~Ty-pe K'. Zv4 u~wSource .Setup/HWatloýn time 151., Vol. Fluid

Li4 Tremled (Y£• •FILTER PACK

- - Type Z 0,4 CA OAA CO to ~ %Amt. Used _______-___

= Tremled (Y &4Source_ i*.Ag 0Or. Size Dist. 2_.A, f, . 116• Uw•

S~~~Dlamter ••', ~.Slot Size & TypeInterval /66 - 100 A

Inteval-11 A' Length L±.ATD: " ; - Bottom Cap 4 )

I• I•~~AW<ILL .e

MiterialBorehole dia. Setwp/H(tlon time_ tVr

T4m S•fpN)

4 I iInm iii 0 0 0II 0 S 0 0•

Page 238: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

REV. DATE: MAY 1990

MONITORING WELL CONSTRUCTION LOG - Standard Flush Mount

Prolect No.: I4a0A."O. C~lent/Pro ect: ijaB- wa&At

PROTECTIVE CSGG5Ee.Materl alI/ Type Swus.ZO W i~ki4O',

GSHeIght (wDiameterDepth BGS Depth 888

Watertight Cl-RIng T~~r~

Elev. SURFACE PADDepth 885 0 ComrEosl Lion& Size 34,r7~xA ca

Breathes With Vadose Zone Y /N)VA RISER PIPE

- Type-i -'( Ak

30 iameter w- * Z)if ~~Total Length (TOC toT? S64,______

VentilatedICa (Y KILY

GROUTCo-mpasltlon &Proport Ions V iru.L..i.~a z.-f

W kjf" i o -74L MTrernledY )IntervalBS''

CENTRALIZERS C Y AGPDepth(s) A-*

SEAL2.Type %k" (fhtm=a.ne...

g ~~Source_____________4 4 so Setup/lt/draiton tI.i~ 0 Vol. Fluid Added ijb&

Tremled (YI/F

Type t;D*t.5d. gt 64AL DAmnt. Used Z 446 6Sg6Tremledsource_______________Gr. Size Dist. Zdf (Ud #t.iD.. t- Lo poumo

- SCREENType -4" V AM4

foIDiameter____________________Slot Size&~ 1.O0 -wag

11 -Interval 1 I

SUMIP ('ON)

ID.~inera 856I _____ 1otfC ED 100 Length - A

4 1~4-.BAC1(FILL MUiG AMaterial________________ ___

WOW* dl& ettpftntIlfl time .. IdABorehoe dla.rremled CT*4

Page 239: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

12 In

PIEZOMETER INSTALLATION SKETCH:~rz;\'ECT NAME SILY 144'2 &k'h INSTALLED BY.-in..... D.TEPROjECT NO If(* 4 U.0aa CHECKED BY _________ DATEBORING NO___________

PIEZOMETER NO f'P-ai

LT 20 6± scH E..4~ 90. PIP' (NZ3NCRETE,:

Av

II

PVC IPE

2" .4S6

GROUT

90RINGN

* //0

5r~jc: "-

35

"BO. 9TTOM OF BORINGS

4S

Page 240: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

J I

PIEZOMETER INSTALLATION SKETCH

l PFiC•JECT NAME 514. & INSTALLED By D.T

E tAL.a PROJECT NO 4 .CHECKED BY MA DATE

BORING NO ,

PiEZOMETER NO " L P -oL, fP'PE :PGUARO POSTS 13)

AT ,200 IS SCEES 80 :,,S PIPI? INA

CONCRETE) v-"&

Pvc PIPE

,-m 4 io0'i rz s

GROUT - -'

BORINGI Af' : .:.

I p"Iii;

20M '40 0 1 ,i

4C1 K

BORITMNGrBOIN

I IS

3.r

4 S &wa~rQ : 7' I

- - -P EI.

4s . BOTTOM OF BORING

*

o 4

Page 241: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

El PIEZOMETER INSTALLATION SKETCH

4 PROJECT NAME !ýkt W4A&.aaw "?4, INSTALLED BYfa.dlS'DA.TE aLSPROJECT NO 4 011Z1 lz2- W CHECKED BY _ _ _ DATE

BORING NO _ __

PIEZOMETER NO __" _ _-PIPE ZAP

GLARC O-STS (3)IT ,20* "6 SCH EL &-80 so % :PIpe INCONCRETE)

A4PP~OXIMA r,- EXIS 'AIGV.;A04AIC SuilR ACE • . .Y •7CL •

4PVC PIPE

BORING

vowe..4 3

g~p9II

1 30"

i BOTTOM OF BORING

-

q 0 0 0 0 000

Page 242: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I REV. DATE: MAY 1990 iMONITORING WELL CONSTRUCTION LOG -- Standard Flush Mount

WELLtO.: ,•"-o.ll installation Pm~i. 1k. I Site:•JProject No.: 1401*j'='L Client/Prolect: 4M=-JAW. -C-Y AP- l 0b

K AZWRAP Contractor. ' • •,n I Drilg Contractor. L oma~z •,=, ,,,.T

IComp. Start: 21041( IS z m JComp. End:.__ 10,01 t (IX a 4n -,--M

Eev. t . P.OTECIVE SGGS Elev. 1_,16 1 Material / Type S kmIL "iAu- gtgajm hmG~S Height

Depth kSS •Diameter

Depth 565 Depth B6SWatertight O-Ring (/ ---

Elev. .. SURFACE PAD

4Depth BGSO0- Compositionl& Size 34f. A 3,6 K #A 97,k~j

/RISER PIPE /N

_/ Type L • ?i.Diameter 4.,,.&.t*•

•4,. . Total Length (TOC to TOS) 2- 1. S. ,;•:: ..... Ventilate0 Cap ( Y4

GROUTComposition & Proportions i.~It ~L~~r

Tremled( Y/&l.)), ' -

Interval • &-..S 9" )z_ .

CENTRALIZERS al N)

Depth(s) 1 HS9•,f'SEAL

5-5 Type L"s i." " a f

Yg. ~~~~~~~Source_______________-.-- 4. ) Setup/Hydration time. ... 44Lr.Vol. Fluid AodeO..•Ji9 A

• Tremled (I Y(

=i *.L pi.Ue

Tremie (Y )1 UVL LIZ Z

Gr. Size DISt 2fY', F r. em-.SCREEN

LEE. Diameter %t". Slot Size & Type o.060Interval BGS 21______

IAerval a Length q--•rA Bottom Cap (Y)/ N)

TD. BA 1L B-.A

Bau It IIL Setuiv*vtfcn tulle UAlTriMled &,*k#4-

I

4 •I/ I I I I |11|

Page 243: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

4 &

I ~REV. DATE: MAY 1990 A

MONITORING WELL CONSTRUCTION LOG -- Stanaardc Flush Mount

WELL tNO.: 1%44-oz- Installatlon: A s.' a &,.. rt o, I Site: 4Project No.: 40TU Client/Prolect: I1,but .S ,? SL A

HAZWRAP Contractor. .r Dri Contractor.SComp. Start: 21dMN, I• "fi*=J 'L-A")J Com. Eno: Z ( /q,

. BuilIt By'. rmp,,j ;, I-L f• r WeilI Coorol... Ni•: .

Elev. %7-•.'kk A

PROTECTIVE CSG,

GS E ev.. Material / Type S.-a, i • -1 S - A IL 6

6S Heiht Diameter_"Depth6 BGS Depth BGS

Elev 4AWatertight O-Ring &@k -•"r,-.,

Eiev. \ ,.. SURFACE PAD SDepth BOS 0. Composition & Size 3 A. c TO, Ai I QP, _c•.6,jA.-

Breathes With Vadose Zone (Y / N)

RISER PI PEType sch4. 40O NVC.

fD DiameterD.....er... / Total Length (TOC to TOS) 1 •4,

VentflatedCap (Y/69)

GROUTComposition & Proportions 0 f

% aft e&Qhial d.J~4,kia3

Tremled (YInterval BGS6 - a ,,

CENTRALIZERS (01N )Depth~s) 24.%JA jAetS-

SEALType - At"LgCatz n[&- m-*aSourc_ _ __ _ _

*,2 -Setup/ydratiun time-LmeLVol" Flu, # (,op( Y

Mb ,A.. Trernied (Y )" " . ?: -•IILTERPACK

-. - ITremiled2 (Y/ )

•f Gr. SizeDIsL 2.obEO , O o,..0Tr

44.5 _Type %CJ4. '40 )-IV..

011 Sit Diamieter r-b.N.,, -. k-. Slot Size & Type J0. .A I 0.1" ,

Intetvai 8652d- qi-r -

LUM N ) w 1 Lnt i

TUBottom cap (~Y N)

-'j E l I-BACIFILL PLUGBorehole di&. Setp/Htlt ion time WA*

Tramled (-o4t"

4 0 0 6 0 0 S 0 0 0

Page 244: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

I S.

APPENDIX G

PIEZOMETER AND MONITORING WELLDEVELOPMENT RECORDS

*

iS

LS

r0

!0

bSI

, , n 5 l l l l nl i l l Ia m i l m

Page 245: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

REV. DATE: MAY 19W03 WELL DEVELOPMENT LOG -Well No.:&- Pag e....L'of.J....iInstallation: s•• ite: Gv--r_• -k_

Project No.: yo°l •Clhent/Prolect: ft .m F,7 A#YrSHAZWIRAP Contractor. I Dev. contractor e-- 4~ k.. ._

Dev. Start ( : _0ev. End: CsQ Dla.: 2- s, 0,-_Developed ty: AtA D ev. Rigj Y /N)

Dev. Method 14-rA arJt( at4A+M& - ~ ~ ~ yr

Eoutwiiet •- f-I)

Pre-Dev. SW. jMaximum oruwOown Oduing mImilng tt at " grm

Range and Average Dischage rate •. "

Total Quantlty of material bailed

Total otl ty of water dischrged by purping A,' ,

Disposition or u dischage water T4 60-

Time Volume Water Tur•idlty Clarity/ Temc pH Con~jctlvlty RemarPs

Levelc Color * C nlUtvy ReakT~~~mer S~ t TOC o" c

oat ga-ter &to-te

Ill

SV,•II

iI

0 m Imi l i l -0.0,=0 0, - 00-

Page 246: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

By. .... Date 1-0q Subject CýasC.. Wsl).1 S.I Sheet No. --.. L of..L

Chkd. By 01' .Date W ' Proj. No. 4(l-

- - 3 C l ~t 3

t= c

Page 247: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

,~/~wZ~- ~-4&REV DATE.MAwELL DEvELOPMENT LOG 1welNi~O..~ __ 1ace-L-or..In~stallation SkNarbor CrdntsISite.

D ro iect No., :& 7 1 .02 G Cl Ient/Pro iect ký-a ~ rANC ýHAZW`RAP Contractor- ITC 0~ ev Contr~ctcrDev Star*: (is ...*....rn Dev Enc I r- Oý-- so Dap.4Developec Dv I ('o Ck DevR Pc r/ N)

Dev Mie'noo ±C 5c.LA-~

Ecuipmern I 4 PIC~ '81 A11gi 4J

;Pre-Dev. SWL IT '5 3 aximum crawaown C rirg pum.,iing 't at. A_____4

Range ano Average DIscriarge rateA

Total Quantity of material bat lec 21-7 -

Total cuantity of water dtsct argea tDy piLinPing /

Disoosititon of a~sctiarge water ,IAý -f C-A L (iliV

Volume Water Ca

r___ t. BTOC Color 0C

Iste k "4,Zf7z 7 -4m5

U~o' J /~d~ 4~7.07 U7ý 5

ko /3 00 7,0 9&0~h

I(C~o

0/0 AX S0 S 0

Page 248: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

rS.- REV. DATE: MAY 1990

ifWELL DEVELOPMENT LOG P5-- WelIl No.: I Page - or.........I installation: Site: r jtt- er,S" ~Pr'ojeCt No.: q0 q 7.2_ 1 Clent/Pro lect: 5kPE " ,/ . "-,J1"/o, r£ •/

HAZWRAP Contractor. ev. Contractor. r ,41Dev. Start (,r.:,o .. m) I Dev. End: (% :S' ) I Csq Dia.: ,2 ,2 . I

Developec by: & . €)eiu I Dev. Rig ( Y / N)

Dev. Method 4k~if A',7A Aa;/j 1t)-W i--O ~ ~ M4S AjJý

* Equiment 3*etc -

Pre-Oev. SWI. 72 . " 015 . ,m1axmum drw ,own during pump.ing tt at gpm

ReW ad Average Dischairge rate r~ g p n

Total Quantity or material balled 9 , -) 5

Total auantllty of water alsclgedo by pumping A/,

Disposition of' dlschwge water .

Volume Water. Clarity/ TempTime R~a 1 t BToLevel Turbldity Clar T 01 Conductivlty Remarks

12.10 0 o N, cA s. 14' I'7 , t<.3t

i"Z"s re;-,,, P,• I 1, •7 }• •" s'.

2 2- 1 100,• '

-s --- -, -

I m

13 1 6 0 0 0 00

Page 249: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

h

W h3NATIONAL

By IZ-r Date - Subject Lo.-ca l-.t Ps-Z- Sheet No.__k of

Chkd. By__Date , . Proj. No. -

v~

. z (f+. , . 2c ý7o 4 t, X %,.g. C, *ý .s,

III )GI*I- • If O I I I••

+ II . . .

Page 250: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

1P/1-6-.4d ."-44- t FJ." REV. DATE. MAY 1;;0WELL DEVELOPMENT LOG welI No..a ,e ..L.. orf

Installation ý EKab • •, . SiteDroject No.: ,p7'1 ICj.(', I Client/Proiect 4, / C-7SHAZWIRAP Contractor .IT C,, i I Dev. Cottractor: I

Dev Start._ I Oev. Enc. (lit :_ _ __M) _ =o D . _.

D~evelooe(:: Dy: /.--C'Lw V %i. V. 4 I, C/O',"...• 6 ' t Oev RicC Y•)/ N)

Eauiprnent P~L1UC -

.re-Dev SW:.L ,aximum .raw.own Curing pumping .t.-,.IV,-,

Range ana Average Dlscharge rate L) A-Total ouantity or material bailea .. 5?Total auantity of water dlscnargeo by pumping

D~sposition of discharge water _-(ejJ V_ ý'vw5-'

VolTme Water Clarity/ Temp

R Tall, ft. Troc Color e Conductivity RemarKS

l -q 7 119 /130 •1363 to z I~ t C

~ 217 ,25 1'&0 IC5

(4 -_7l4 11 LJ

Page 251: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

- REV. DATE: MAY 1990

WELL DEVELOPMENT LOG -WeliNo.: PS-i lP=-- or--

SProject No.; LtoqT--Lk 'Chient/Prolect: AAAPs / sl H,,, A04C ,

SHAZWRAP Contractor I Dev. Contractor - ... E.W. ,0Dev. Start (M :%T=) I Dev. End: (%, :ýo.•Jn) Cso Dia.: 7- ,L,Devetolope by: .,, v, sý,w, gc,.)¢J Sww,.,,; I ev. Rigj (Y /N )

o'.6,,,& I- go- q %

Dev. Method ;ýc ., e- -, 4-L, j~am" 1 koA - ZZ e~vo.e

4E~lulrnent .• &•--ea. T--5

Pre-Dev. SWl. 2- .... Maximurn araw0own uringpunfining ft at 0-.n

Range and Aver-age Dlscharge rate C . - . ,- \ ,.. -

Total quantity of material balled ED-ink_ _ _ _

Total Jantlty of water dlscrgeO by pumping A

Disposition of discharge water - 6, A_

Volume Water Clarity/Time R Levei Tuidity Clarit TeM pH Conductivity Remarks

-" r TCcolor C Remarks

1009 IT 40 F.., "

1o03 2'4 CJty 2L0. SS 1- Moo60rý..

tlo% 10 CA~v• r zo.O 44 1"+ 0 10" .. l tr , • ••~

LO.'4•• •. • • •t

t O so 1 5 7 Z 0 .5 "I W 0 1 .

1100 r0 tO' ttI.

%I OF S's

Oto S5 lox -%&

-N-ow-

Page 252: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

r By D ate i-O2 Subject k~"~~ L4-).-- k Sheet o- f

I Chkd. By-......Date C.Proj. No.

LI.r~eT 0 -~~.\%

I L~4X~'tr j~t1WI045%

Page 253: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

7-/~4J~t-~-4& - REV. DATE. MAY 1(;;('wEL L OEVELOPMENT LOG WelIl No.: H)r- 0 PaeL or Iinstallation: skNarbar COQ W Site: K, C&,v )3PDro iect NO.:403ZZa Client/Protiect.'A

HAZWRAP Contractor. 7(,r1 Dev. Contractcr-0ev Start (CI:zl......m) 0ev. Enoa (vq 8......M) CSDi a.Develooeo by D ev. Rio rY`-N)

0ev Metriod :SLuab-sh ~rý- . b4-v' 's~j4l't2

Eouiciment y/ Hti Izcit ie& boI~' 4 1,5

Pre-Dev w. ...2... - .. jiximum, drwown during PumDIng ft at ARange and Average Discharge rate -&6 oV C

Total qawntity of material balled 1•ý-,

Total ouantl ty of water Oiscriargec tby pumnping

D:soositionorfdiscrarge water !-Qd1 4 4 v~uic~~v

Time in Water Clarity/ Temp pH ConutvtTimeLevel Turbidit Color 0 C Onutvy Remarics

Gr63 ~ tt'ddyk1ýid 20.7 4$'2 /09Qa. (~ [ 1 22,1 ~ /C

0ý1 0 15

Page 254: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

[ PVS/'/4, -- ,-•--4&• - REV. DATE. MAY 1990WELL DEVELOPMENT LOG wIelINo.. AAWS-OZ. $Page Ltof.L iinstallation: sky Esartr C._t Site %- .- I.roiect No.: 4'cj7o-_I Client/Protect. &M•-S / . 14-,Lr.,- AAý'

HAZWRAP Contractor. Z-i- D ev Contractor L-.,.. - e. ' ,Dev Start ( $' : -&S-...,, ) ' I Dev. Ena: ( tz ;:.._mf I Cso Dia.: i- -.J,,

*I' Developed by: -rI0 ,, -6-- E.fv. Dev Rio a N)

I S~~~Dev Method 'r,, .,--e.,_ r_ - u ,,. -- ,_ .. .

Ecuipment - ,-- .

Pre-Dev. SWL x-. . Maximum Crawdown during pumping tt at _____-

Range ana Average Discharge rate , - • , -

Total uaqntity ot material balled 7.0

Total auanti ty of water ctscnarged by pumping I So k S

Disposition of discnarge water ' •,. &ete-----e,

volume Water b idty Clarity/ Temp pH ConductivityTime Rei•i•yd t. TOC Color 0 C Y emars

IS - - - - - S*-, S.a

wm~-t, '.

S ( . Z3. 30

& (0• 0 0. Z3 4.23.0 \o

I II I ICX Z3,Uii il IJ -71 iik

Page 255: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

/,Z4- "- 4& ,REV. DATE. MAY 1 (;90

I-WELL DEVELOPMENT LOG IWeIINo.. li•,i iPa!-e 4 of...

installation: k ab oria~ Site L;-ra/,ISProject NO.: 4o•' 72I.(no I Client/Prolect. • / •k 4 Atx " A •'kJL I

HAZWRAP Contractor i-T C.,",(- Dev. Contractor IDev. Start (0O:S16.jn) I Dev Eric: (• :to._.._-m) CsoDia.: in a

4 DeveloDeC by: .c,4ytoý L-.•xjtvehv,ý Dev Rio_ Y//N) 7

Dev. Method u J44<A c5.tý b 9tL .lvy 1L wVS

Pre-Dev. SWL aximum drawdown during pumping ft at CC7-

Range and Average Discharge rate M m-0-

Total Q=q.•tty of material balea :!5,

Total ovantity of water discharged by pnmping

DispositLion of discharge water 4- * L

Volume Water Troiaity Clarity/ Temn•pH Cnctvy ersTime ~~Level T H CnutvtTim eWs ft. BTOC Color 0C Reak

to P4 • 21,j- , 7,K' 2--

7F Y 417

4. 1

0• 0 0 0 0 0 0 0 0

Page 256: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

,~/SL~'/~d- -4eREV DA7TE. M1AYi ~l DEVELOPMIENT LOG jwf o.M.j-1,i~oJc

installation muEarbor CodntsISite . o, .Dr etN. jUu 2 I CIin/roicH&A SYWaaif)& r.

HAZWRAD Contractor jT6U f 0ev. Contractor Ljat1~v#*&qo ~.Dev Star*, ('1 :30-A.JLm)* 4I 1ev E!7. 1~211 aQ.eJl fIz(.h4 012a.~ aaIcDeveiooec IDy ý UIDev R!c (YZ N)

Dev Methoc L 4 H .- S.,"g g. f5- 20 ja ,r, IRAK4- rtn &pLn~.&&

30-6'(o 1%.J - aAI.U Lt4&,TLL taL4'L.A. C~AEA4Ur,( *1LALCeerT p,% e.2..

Eouipment b"sA.kauaa-, Rf itML--L~'F~., &~

Pre-Dev. SWL 74 I~. -M...Jaximum crawcown curing pumping AJ A rt at-C-,

Range ano Average DIscharge rate &,p('t *~em.(l ~i~ ~M

Total otantity of material iailec 57Total cuantity orwater clscmargea by pumingla J6D~svosi tion of Oiscrarge water Cnwrrw4L Opg otp.aj~j ~u

LevT* Waer Clarit/ Tem

Time Rom Waere 7urtidflty 0C p Con~uctivty eas

~"A

It~s d16, q96I

IJ -- /V -# -A-

0 0 00 0 0 0

Page 257: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

REV. DATE: MAY 19903 WELL DEVELOPMENT LOG we I INo.: &j tA) C) 7 Page orinstal laect: I Site:

*HAZWRAP Contractor i ~ 01Dev. Contractor .,A 4ia--.- '.A

Dev. Start (to : V........n) Dev. End: 0& :"....n Cs Di.:rDeveloped by: k6L&% al Iev 'C s8"D)

0ev. Method it~aKf

Equiprnent A OO- aJ - DISFP

Total Quantity of water discharged by pumping 4Disposition of disctiarge water dr a-6~ 4 4AV ~xi( ~t

Tme f L BTOC Color C

4U 5

Z2cC3 U3_7A a

-C~ Vv-f-----

4'S Iq q co

Page 258: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

WEL DEELOMEN LO REV. DATE: MAY 1990

WELL EVELPMEN LOGWeillNo.: AA.(AI -o? Pag Lof I.L..

Instal lation: 1o*. o~ Site: Ct-,, - Z_ .Project No.: -~toci.z~i Icient/Project: Ak" E-, !>-

HAZWRAP Contractor. I-~c. Dev. Contractor. ~ ~ -.-

* ev. Start (t :is..A-J ) IDev. End (0o -& t i) ICsQ Dia.: 1-

Developed tr: ga..-z_ Dev.Rig CrN)

Dev. Method `Sr lb--&.,Q.s -e ~.-. ~f-t SAJTQ.c

EQuipment ... vL~....-C(4

Pre-Dev. SWL -+.S i...I uzn rauwaown a.ring pwvuV "% ,1 rt at (.it -

Paige aid Average DIschvge rate 44=* 4,6, w

Total Quantity of material balled ________________________________

Total Quantity of water dischargix by puf~ifg % tk

DiDsmitiorI of aisclwg water -T. ~

Volumie WaterTime RLevel TIufbidity Clarity/ Tewiv PH Conouctivity ifl~~-' SO Color CReak

091S. -ý - - - & ýZbs--

-ee - - - - - - VL.-A., au

ows Z%41 -.- %I* ZOj , , 0

- L-~~t3 t. t~ p. 24 ittso em- ~ 04

M% L. Vwr C. ZZ, r.'.10 %Ito

Oq.S0 uo, SAL CA...r Z,~ &,qT itt 0

Isooo ~ ~ ~ ZZ kw~ SLt(. tgk70 1-O

too k~s k-1z U.Cý, -jz -3 -4.( 04

wor W% s IQ-C"Y 7.Z. ' -i It tS

D09 I 00r 0e 0z 0 0 4 fC 0

Page 259: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

F/S-'44 r-4 , - REV. DATE. MAY 19;0WELL DEVELOPMENT LOG well No.. -O 7PaoeA or.Linstallation: skymarbw Aem mI SiteiProject No.: M).OZa6 Cl ient/Pro lect: 16

HAZWRAD Contractor- Dev. Contractor-L^OA 9Dev Start -- I.....ni) 3h.4 Dev.Eria: ( ... m) cso Dia.. 4IDevelopec by:- Dev. Rig /Y' N

Dev Methood -S2ý 9q 4 .. a 4a.ýi~ BAR 20 .ru& &ap p.

3 0 -~ fd s * ,. T kf4 .u PA.Latd (AAMr t 4Lii C 4-VFi sr%/ 2-4 t,3TLA

Pre-Dev. SWL :Z d' Mxiu rawdown aiuring pumping ft at__________

Rance ano Aver-age Discharge r-ate -pcAn

Total quantity of material baiele Sj6 ea-fle'v r

Total quantity of water dischnarged by pumping ICs*

Disposition of disctiarge water a h k -c Pgii woir cu-OLA.,r" ieu wsg

Time Volumre Laeve Trta-icity Clarity/ Temp pH Conductivity mrsft. BTOCCor C-a (I -ý - - -_ - -, ____ -____ __3

lda0 Is - - - le, Y','"2..ý.J9 7 )JIA5 ý - .'(4 20 -1,0 93 01

' 5-5 - -i (j Z 41 ICSO

10 23. 10"0

l2L)$L -5 3 ý "I.7 'I L S

-a 0 3 . L75 "I3L

ý3,1 L-11 I~jS

3L3, . t 'ý 100

0~I b

Page 260: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

~F/~~J4.d. ~3*4-~ . - j REV. DATE. MAY 1';90

wELDVLPETLGWel No.As-- Paqe -- cLL...

Dev Metnod Sýs.dt ",/ Ci r-~~M)FAI 2 0h&~ hA4L rwok VA..q

Ecui~ment bay L~o At g&r, d fI 4J TJO.4mT..S4 tdtI7dIA

4Pre-Dev w. SWL -1 aximurn crawoown curing Pumc)Ing ft at__________

Range anO Average Dtsctlarge rate S- t

Total Imnt ity ofmater~3~il a I5 baI e

Total ouantity at water dJlSchageC by p.un~ing J•• 6'J'43

D4 C)5CS~tion cf diSCtiarge water i3X ,.ug.,a A..s er 1 4AMS~ & i.v *Q1c.

Volve w ter~ iit Carity/ Temo pH Conductivity e aiTime~~~r Reo -ee urbd Color aCRmr,

~ q-2a,7 4 13

0`140 LI v2; 1

0- C c is 40 b c

4

Page 261: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

1-/4-u 44- ~-r+& REV. DATE. MIAY (;90wE LL D E vE L0PrIENT L Or, we) I No.. AMW S - i Place -- L-orinstallation sk urnb SiteDroiect NC.: "-+?t Clierit/Prolect &vW;-S. r. 4~.

IHAZWRA:) Contractor: --T-t... Dev. Cont-actcr L.....Dev Star-, (,'; :S-rjn) % 0ev En~c. ((, ss.rf ItCSc Dfa.DNveiooec oy 6, r Dev PIC / N

Dev rMet,-oc S ~~* L ~ 4'e-. 6.- cr-.

Pre-Dev. Swt- -y-.'O -aximum orawoown during pumping ft at - :

Range and Average DIscharge rate - --

Total ~auntity of material bailea 2.*O

Total cuantity of water dlscnargeo Dy punping IS~O

Distosition of discharge water -7- -1e & W-k P4-ý

Tie Volume~ Waterbdity Clarity/ Temp nucityemrTime rW¶ t. BTOC Color 0C-

I tkDVAT -4 G.- . ~k k-okc.

%"'W q0 2%, V* -4, z - I 0:% 41S It "A Z.'&A 4;zo to-4

Vkkto k2o CAo.A-Y 7-1k -- 3 ~S

14L48 ( .0SA" Z.3 (0 Z5, k090

%4 t S. .,-U"

0

Page 262: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

- REV. DATE: MAY 1990

WELL DEVELOPMENT LOS jWeilNo.: IF-O(- -IaeIo I

Dev. Stetho :11--& _LD Dev End ('4C I :eoJ t2,.Lee Cs! D~ia1: ",) S

* Eoulmwt S,,,eytL Pa, Uc, +~e 90 ,%D Pý;,J&--'~

II

Range and Average Dischwg rate j IA, )

Total Quantity of material balled CIA uxlM

* Total Qgti atty orwater dlschegedi by pumping _ /kA

* Dlapsltivn of also"ugwater ýp*ff 01 s PAIS &4 puLp y om~ela -o,)kf

T olme VOITW dit Claity/ TempTieR dLevel Turbldt tolo Oc p Conductivity Rfok

:?1 t*i I~qo 4U"-,0~ P~.- -

2& -4.2 Im.- n

Ise & 0 0-N 40t I0*0

Page 263: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

- EV. DATE- MAY 1990

WELL DEVELOPMENT LOG I WellNo.: pJz-oIe- Pa:: -Le ofInstallation I Site: p&,iD• AAProject No.: 4M(.-o-0(. Client/Project: M 4t - Ae,,

HAZWRAP Contractor. I Dev. Contractor- Sa.'W iT hW&" &u. 4e.-, C'o.l Dev. Start (D •..- .. I Dev. I (1 :-5---m) I Csq Die.: _, I.Developed by.V. e agJ a~ mir-/, w et- SO V t (VP , •. A •- • Dev.Z Rig (NIIN ) _

Dev. Method 70S 40 Vc, ~ 7j L~p wI i'~)

, Equipmet C.MOAL &e w , ii ,,4 i + /o /iU

Pre-Dev.~lu SKin .............drU IXM'- j ft at L .I gpm

, VNinge and Average Dlscharge rate grn

Total quantity of material belled Lj. •1i ab

* Total quantity ofwater discharged by pumping tt

$Disposition of dsctwge water LeM A) 101 5ý w ad# N 15 U g LAWZe PNOM- A iQp

Volume Water.Time Level Turbidity Clarity/ Temp H Cociuxtivity ReareksR f L BTOC Color

303 zl 00~ua

jI3 I 00I X, 00o 60~Aop0311 A 141- 7.30 /%o ,,, "0o,, "0 000!.2,,' ;14 /• s,,4 ,•. -Iq let.R. 0 Ay, 000eo

A0 241 4•2 2WD•••

Page 264: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

L* - REV. DATE- MAY 1990

WELL DEVELOPMENT LOG WeillNo.: 0P -L- or II nstallation: I Site: ~AJPKy A#)C,

*Project No.: &C 4Z% -Cllenfl/Pro eCCL: Afwa I -HAZWRAP Contractor ~ I0ev. Conltractor pe t aLI,Dev Start =( X% - ) I ev.En* 60 (10 :S ...j__) Csp Dla.: "

D&V%.r i Lt 4

jPre-Oev. SV& SI ...JMxlm aairw~own Grnvmfg ... tat.- A) 1,4

Range and Ave-age Discharge rate _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

4 ~~~Tot~al quantity or material balled (iO 5

Total quantl ty or water discharged by vpnvlng

Di~smitlonor d~scharge water J&fi~ji 55 eQA4 0* £A&V 2 PMA67W Rmdm&-

Leve Wate.rbd Clarity/ Term a.clvt eakTime Lee -ubdt Color *9C C~t~t eak

4q35 -X-1 ý 1330 f"w~p

joO~~ 3.S 5A4 23.3 1. J3.Wx Vo4G7 "fE.4p

*~I Io' "*o ".. A.za iW

to -3. - -- 3 -U -"o- -~a

20 0 0 0 0 am t

Page 265: I D-A277 739 FINAL IIi'l'illlIiil Site Investigation Report · The change will be to replace the 1OS50 GC with a SRI model 8610 GC equipped with an PID and FID detector in series,

P'~Q/Z- r 4REV. DATE: MAY I 1P[WELL DEVELOPMENT LOG JWell No.. &&Iq-.Oz-fmIod

W ~~~~Developed by: Aw4_De.Ro;q

Dev Method •-siA.4-& &Ale~Us 0 ~ v.&.fa. .. /kj.

Pre-Dev. SWt-I :4 - Maiu Crawdown curing Pumping ... iAb&Ik.I ft at__________

Range and Average Discharge rate ______________________________

Total quantity of material bailed VJ~ bm /hB~IAL .~rt

Total auanttty of water dischlarged! Cy puminTig 04Disposition of discharge water .0 r1J Q.srua~J., Z~~Vif* .

Voum Water.Time Level Turbidity Clarity/ Termp PH Conductivity Remarxs

- ft. BTOC Color 0 C1

(o0q 2j. 2 7.0 L 3C

/is o e'.Z (. -I- 04 NI30 2l1 7L U- 4.0- L44 1.i jv#%4LW

DA-fw 25A -fi o1Izz1- Lt. -4 1.3 j

4 136f Z4.5 I.31 1003I~o !¶-~*%~ 7-4 99()

1143S f - " z 7.38 110 '

1.50S T3/ -z q3 ~ ~ I

'(5 2 ~-~ OA, IL 'AVw~

(j4vA04.J 5' Vo. Yz ~ STA"&JL4 V^A,,&&.